Building the Future Current Activities this Week : Mass Excavation : Grading is ongoing in Area 3. Backfilling of on-grade is ongoing in Area 1. Site Utilities : Installation of the new electrical ductbank is ongoing. Installation of North Sanitary Manhole is complete. Storm Sewer installation (Line 6000) is ongoing on east side of France Family Drive. Foundations : Area 2 Field Level – Footing installation on North Stage Footing is complete to Column Line 15. Area 1 Mezzanine Level – Installation of Elevator Pit walls are complete. Area 4 Mezzanine Level – Installation of Drilled Piers are ongoing. Soil Nail Wall : Area 2 – Shotcrete installation is complete. To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner From: Brandon Valdez Office: Kansas City Date: 5.5.2010 Re: Wizards Stadium Project Update – Week of 5.3.2010 Concourse Level Area 1/2 – E-Line Footing Placement is ongoing. Concourse Level Area 1 – Steel Decking installation in Steel Erection Sequence 1-1 is ongoing. Field Level Area 1 – Secondary Electric Ductbank installation has started at D-Line.

Construction Update 5-5-2010

Embed Size (px)

DESCRIPTION

KC Soccer Stadium construction update from Turner Construction.

Citation preview

Page 1: Construction Update 5-5-2010

Building the Future

Current Activities this Week:

Mass Excavation:

Grading is ongoing in Area 3. Backfilling of on-grade

is ongoing in Area 1.

Site Utilities:

Installation of the new electrical ductbank is ongoing.

Installation of North Sanitary Manhole is complete.

Storm Sewer installation (Line 6000) is ongoing on

east side of France Family Drive.

Foundations:

Area 2 Field Level – Footing installation on North Stage

Footing is complete to Column Line 15.

Area 1 Mezzanine Level – Installation of Elevator Pit walls

are complete.

Area 4 Mezzanine Level – Installation of Drilled Piers

are ongoing.

Soil Nail Wall:

Area 2 – Shotcrete installation is complete.

To: David Ficklin - OnGoal

Rory O’Connor – OnGoal

Lee Turner – OnGoal

Andy Heitmann – Turner

Dave Dudzik - Turner

From: Brandon Valdez

Office: Kansas City

Date: 5.5.2010

Re: Wizards Stadium Project

Update – Week of

5.3.2010

Concourse Level Area 1/2 – E-Line Footing

Placement is ongoing.

Concourse Level Area 1 – Steel Decking

installation in Steel Erection Sequence 1-1 is

ongoing.

Field Level Area 1 – Secondary Electric

Ductbank installation has started at D-Line.

Page 2: Construction Update 5-5-2010

Building the Future

Structural Steel Erection:

Field Bowl – Structural Steel Erection is ongoing in

Sequence 1-1 (between Column Lines D-C). Installation of

steel decking has started.

Underground Electrical:

Secondary service ducts is complete from Electrical Room

01.34.04 south past Column Line 25.

Secondary service ducts at Column Line D have started.

Projected Activities occurring next Week:

Mass Excavation:

Grading at Truck Dock Area will begin.

Site Utilities:

Installation of the Storm Line 6000 on the East Side (France

Family Drive) of the site will continue.

Deep Underground Plumbing:

Sanitary in Area 3 will begin.

Foundations:

Area 2 Field Level – Placement of foundation walls at stage

area will begin.

Area 3 Field Level – Footing excavation will begin.

Structural Steel Erection:

Erection of Structural Steel in Sequence 1-2 will begin.

Area 1 – Structural Steel Erection at West

Building continues. First Level of Stadium

Suite Steel being set.

Field Level Area 1 – Shot looking north from

Concourse Level.

Field Level Area 1 – South Field Wall

Footings being placed.

Page 3: Construction Update 5-5-2010

Building the Future

Additional Photos:

Mezzanine Level Area 1 – VIP Entrance

taking shape.

Field Level Area 1 – Southeast Vomitory

Foundation Wall.

Field Level Area 2 – West Stage Foundation

Wall.

Field Level Area 1 – Southeast Vomitory

return wall formwork being installed.

Area 1 – Shot looking North West showing

West Building Structural Steel.

Field Level Area 2 – North Stage footings are

complete to Column Line 15.