4
Building the Future Current Activities this Week : Mass Excavation : Backfilling of on-grade seating is ongoing in Area 2 and Area 3. Site Utilities : Storm Sewer Installation (Line 6000) is ongoing on the east side of France Family Drive. Foundations : Area 3 Field Level – Foundation installation continues on the east side of the site. Currently to Column Line 1. Concrete Flatwork : Area 1 – Slab-on-grade is placed at field level to Column line 23. Prep for Slab-on grade is ongoing from Column lines 23-15. Structural Steel Erection : Area 1 – Main Canopy Truss Erection is ongoing (Seq 1-8). Area 3 – Steel erection is ongoing in Sequence 3-2. ongoing. Precast Concrete : Area 2 – Precast erection has started. Underground MEP : Electrical Secondary Distribution is ongoing in Areas 2. To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner From: Brandon Valdez Office: Kansas City Date: 8.4.2010 Re: Wizards Stadium Project Update – Week of 8.2.2010 Area 3 – Installation of Storm Line 6000 is ongoing on the east side of France Family Drive. Area 2 – Precast erection has started on the south elevation. Field Level Area 3 – Foundations are continuing on the East Side.

Construction Update 8-04-2010

Embed Size (px)

Citation preview

Page 1: Construction Update 8-04-2010

Building the Future

Current Activities this Week:

Mass Excavation:

Backfilling of on-grade seating is ongoing in Area 2

and Area 3.

Site Utilities:

Storm Sewer Installation (Line 6000) is ongoing

on the east side of France Family Drive.

Foundations:

Area 3 Field Level – Foundation installation continues on

the east side of the site. Currently to Column Line 1.

Concrete Flatwork:

Area 1 – Slab-on-grade is placed at field level to

Column line 23. Prep for Slab-on grade is ongoing from

Column lines 23-15.

Structural Steel Erection:

Area 1 – Main Canopy Truss Erection is ongoing (Seq 1-8).

Area 3 – Steel erection is ongoing in Sequence 3-2.

ongoing.

Precast Concrete:

Area 2 – Precast erection has started.

Underground MEP:

Electrical Secondary Distribution is ongoing in Areas 2.

To: David Ficklin - OnGoal

Rory O’Connor – OnGoal

Lee Turner – OnGoal

Andy Heitmann – Turner

Dave Dudzik - Turner

From: Brandon Valdez

Office: Kansas City

Date: 8.4.2010

Re: Wizards Stadium Project

Update – Week of

8.2.2010

Area 3 – Installation of Storm Line 6000 is

ongoing on the east side of France Family

Drive.

Area 2 – Precast erection has started on the

south elevation.

Field Level Area 3 – Foundations are

continuing on the East Side.

Page 2: Construction Update 8-04-2010

Building the Future

MEP Rough-in:

Area 2 – Shallow electrical and plumbing rough-in is

ongoing. Ductwork installation on Suite Level is ongoing.

Plumbing rough-in is ongoing on Suite Level.

Metal Stud Framing:

Area 1 – Metal stud framing for Suite and Press

Levels are ongoing. Metal stud framing is ongoing on

Main Concourse West Building.

Projected Activities occurring next Week:

Mass Excavation:

Backfilling of on-grade seating areas will continue in Area

3. Grading in Area 3 (east of A-Line) will continue.

Site Utilities:

Installation of the Storm Line 6000 on the East Side (France

Family Drive) of the site will be complete. Sanitary Sewer

installation will begin at locations where Storm Line 6000

is complete.

Deep Underground MEP:

Deep Electrical Distribution installation will continue

in Area 3.

Foundations:

Area 3 Field Level – Foundation installation will continue.

Concrete Flatwork:

Area 2 Field Level – Concrete placement for Slab-on-Grade

will be completed to Column Line 15.

Area 1 and 2 Field Level – Installation of on-grade seating

risers will continue.

Structural Steel Erection:

Erection of Structural Steel in Sequence 3-2 will

continue. Installation of columns for Canopy will begin.

Area 1 – Shot of the West Building from the

south concourse.

Field Level Area 1 – Masonry underway on

Field Level.

Field Level Area 3 – Steel Erection has

started in Sequence 3-2. Steel is currently

set to Column Line 4.

Page 3: Construction Update 8-04-2010

Building the Future

Erection of the Canopy Trusses will continue in

Sequence 1-8.

Underground MEP:

Electrical Secondary will continue in Area 3.

MEP Rough-in:

Plumbing and Electrical rough-in for Area 2 Field Level slab

on grade will continue. MEP Rough-in at Suite Level will

continue. Ductwork installation on Press Level will begin.

Metal Stud Framing:

Area 1 – Metal stud framing for Concourse, Suite and Press

Levels will continue.

Area 1 – First course of masonry going up on

southwest restrooms.

Suite Level Area 1 – 80x34 return air duct

being installed at mechanical shaft at

Column Line 27.

Page 4: Construction Update 8-04-2010

Building the Future

Additional Photos:

Concourse Level Area 1 – Installation of

metal deck on platforms is complete.

Roof Level Area 1 – Roof curbs have arrived

and are being set on roof.

Concourse Level Area 1 – Terrace area

taking shape.

Field Level Area 1 – Slab-on-Grade prep

ongoing for next pour from Column Line 23-

15.

Area 1 – Players benches concrete is nearly

complete.

Suite Level Area 1 – Installation of plumbing

carriers is ongoing on Suite Level.