Building the Future
Current Activities this Week:
Mass Excavation:
Backfilling of on-grade seating is ongoing in Area 2
and Area 3.
Site Utilities:
Storm Sewer Installation (Line 6000) is ongoing
on the east side of France Family Drive.
Foundations:
Area 3 Field Level – Foundation installation continues on
the east side of the site. Currently to Column Line 1.
Concrete Flatwork:
Area 1 – Slab-on-grade is placed at field level to
Column line 23. Prep for Slab-on grade is ongoing from
Column lines 23-15.
Structural Steel Erection:
Area 1 – Main Canopy Truss Erection is ongoing (Seq 1-8).
Area 3 – Steel erection is ongoing in Sequence 3-2.
ongoing.
Precast Concrete:
Area 2 – Precast erection has started.
Underground MEP:
Electrical Secondary Distribution is ongoing in Areas 2.
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 8.4.2010
Re: Wizards Stadium Project
Update – Week of
8.2.2010
Area 3 – Installation of Storm Line 6000 is
ongoing on the east side of France Family
Drive.
Area 2 – Precast erection has started on the
south elevation.
Field Level Area 3 – Foundations are
continuing on the East Side.
Building the Future
MEP Rough-in:
Area 2 – Shallow electrical and plumbing rough-in is
ongoing. Ductwork installation on Suite Level is ongoing.
Plumbing rough-in is ongoing on Suite Level.
Metal Stud Framing:
Area 1 – Metal stud framing for Suite and Press
Levels are ongoing. Metal stud framing is ongoing on
Main Concourse West Building.
Projected Activities occurring next Week:
Mass Excavation:
Backfilling of on-grade seating areas will continue in Area
3. Grading in Area 3 (east of A-Line) will continue.
Site Utilities:
Installation of the Storm Line 6000 on the East Side (France
Family Drive) of the site will be complete. Sanitary Sewer
installation will begin at locations where Storm Line 6000
is complete.
Deep Underground MEP:
Deep Electrical Distribution installation will continue
in Area 3.
Foundations:
Area 3 Field Level – Foundation installation will continue.
Concrete Flatwork:
Area 2 Field Level – Concrete placement for Slab-on-Grade
will be completed to Column Line 15.
Area 1 and 2 Field Level – Installation of on-grade seating
risers will continue.
Structural Steel Erection:
Erection of Structural Steel in Sequence 3-2 will
continue. Installation of columns for Canopy will begin.
Area 1 – Shot of the West Building from the
south concourse.
Field Level Area 1 – Masonry underway on
Field Level.
Field Level Area 3 – Steel Erection has
started in Sequence 3-2. Steel is currently
set to Column Line 4.
Building the Future
Erection of the Canopy Trusses will continue in
Sequence 1-8.
Underground MEP:
Electrical Secondary will continue in Area 3.
MEP Rough-in:
Plumbing and Electrical rough-in for Area 2 Field Level slab
on grade will continue. MEP Rough-in at Suite Level will
continue. Ductwork installation on Press Level will begin.
Metal Stud Framing:
Area 1 – Metal stud framing for Concourse, Suite and Press
Levels will continue.
Area 1 – First course of masonry going up on
southwest restrooms.
Suite Level Area 1 – 80x34 return air duct
being installed at mechanical shaft at
Column Line 27.
Building the Future
Additional Photos:
Concourse Level Area 1 – Installation of
metal deck on platforms is complete.
Roof Level Area 1 – Roof curbs have arrived
and are being set on roof.
Concourse Level Area 1 – Terrace area
taking shape.
Field Level Area 1 – Slab-on-Grade prep
ongoing for next pour from Column Line 23-
15.
Area 1 – Players benches concrete is nearly
complete.
Suite Level Area 1 – Installation of plumbing
carriers is ongoing on Suite Level.