AASHTO/FHWA Peer Exchange: Context Sensitive Solutions Baltimo AASHTO/FHWA Peer Exchange: Context Sensitive Solutions Baltimo re, MD Sept. 6 re, MD Sept. 6 - - 8, 2006 8, 2006 C S S e x c h a n g e U.S. 40 - Berthoud Pass East Context Sensitive Design For Rural Roads Michelle Li CDOT - Region 1 Planning & Environmental Manager

Context Sensitive Design C For Rural Roads S

  • Upload
    others

  • View
    20

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Context Sensitive Design C For Rural Roads S

AASHTO/FHWA Peer Exchange: Context Sensitive Solutions BaltimoAASHTO/FHWA Peer Exchange: Context Sensitive Solutions Baltimore, MD Sept. 6re, MD Sept. 6--8, 20068, 2006

CSSexchange

U.S. 40 - Berthoud Pass EastContext Sensitive Design

For Rural Roads

Michelle Li CDOT - Region 1 Planning & Environmental Manager

Page 2: Context Sensitive Design C For Rural Roads S

AASHTO/FHWA Peer Exchange: Context Sensitive Solutions BaltimoAASHTO/FHWA Peer Exchange: Context Sensitive Solutions Baltimore, MD Sept. 6re, MD Sept. 6--8, 20068, 2006

CSSexchange

U.S. 40 - Berthoud Pass EastProject Description

– Purpose & Need: “To construct a feasible improvement which will increase operation efficiency of US 40 on Berthoud Pass.”

– Primary Considerations: Environmental Mitigation and Recreational Area Access from the Highway

– Historic mountain pass over the Continental Divide (from Berthoud Falls to summit)

– Location: 50 miles west of Denver in Clear Creek County– Length: 5 miles - Total Cost: $70 million

– Status: Construction began in 1998. Phases 1 and 2 completed in 2002. Phase 3 to be completed in Fall 2006.

Page 3: Context Sensitive Design C For Rural Roads S

AASHTO/FHWA Peer Exchange: Context Sensitive Solutions BaltimoAASHTO/FHWA Peer Exchange: Context Sensitive Solutions Baltimore, MD Sept. 6re, MD Sept. 6--8, 20068, 2006

CSSexchange

Regional Context U.S. 40 - Berthoud Pass East

Rocky MountainNational Park

Estes Park

Boulder

Georgetown

Empire

WinterPark

Fraser

Lake Granby

ContinentalD

ivideDenver

40

34

9

25

2570

70

66

36

40

40

40

BERTHOUDPASS EAST

Page 4: Context Sensitive Design C For Rural Roads S

AASHTO/FHWA Peer Exchange: Context Sensitive Solutions BaltimoAASHTO/FHWA Peer Exchange: Context Sensitive Solutions Baltimore, MD Sept. 6re, MD Sept. 6--8, 20068, 2006

CSSexchange

Project History

– Named for Captain Edward L. Berthoud, who discovers it in 1861 while exploring a direct mail route through Colorado

– First built in 1874 as a narrow, private wagon road

– U.S. Forest Service and Colorado Highway Department agree to construct it as an improved automobile road in 1919

– Construction begins in 1920 and is completed in 1923

– Is further widened and paved in 1938, becoming an important access route for central Colorado

Page 5: Context Sensitive Design C For Rural Roads S

AASHTO/FHWA Peer Exchange: Context Sensitive Solutions BaltimoAASHTO/FHWA Peer Exchange: Context Sensitive Solutions Baltimore, MD Sept. 6re, MD Sept. 6--8, 20068, 2006

CSSexchange

CSS Approach

What makes this a CSS project as opposed to the traditional format?Project initiated with the following CSS objectives:• Iterative and comprehensive public involvement process• Roadway improvements to meet driver expectancy • Address other safety and travel efficiency needs• Protect and improve water quality and wetlands• Improve visual quality by following USFS objectives• Enhance access to recreation resources• Compatibility with wildlife and USFS scenery management• Avoidance of Arapaho National Forest impacts

Page 6: Context Sensitive Design C For Rural Roads S

AASHTO/FHWA Peer Exchange: Context Sensitive Solutions BaltimoAASHTO/FHWA Peer Exchange: Context Sensitive Solutions Baltimore, MD Sept. 6re, MD Sept. 6--8, 20068, 2006

CSSexchange

Transportation Needs

• Improve safety and traffic flow• Resolve roadway deficiencies involved

with snow storage• Vegetate eroded and unstable slopes• Minimize surface icing and water quality

problems• Prevent wildlife/vehicle collisions by

inclusion of three wildlife underpasses

28’ to 40’ Wide

Page 7: Context Sensitive Design C For Rural Roads S

AASHTO/FHWA Peer Exchange: Context Sensitive Solutions BaltimoAASHTO/FHWA Peer Exchange: Context Sensitive Solutions Baltimore, MD Sept. 6re, MD Sept. 6--8, 20068, 2006

CSSexchange

Compatibility with Natural Environment

Environmental Issues Considered• Water Quality and Erosion Control• Slope Stability and Plant

Establishment• Wetlands• Threatened and Endangered Species• Avoidance of the Alpine Forest• Visual Resources• Cultural and Historic Impacts• Social Impacts to the Local

Community and Ski Industry

Page 8: Context Sensitive Design C For Rural Roads S

AASHTO/FHWA Peer Exchange: Context Sensitive Solutions BaltimoAASHTO/FHWA Peer Exchange: Context Sensitive Solutions Baltimore, MD Sept. 6re, MD Sept. 6--8, 20068, 2006

CSSexchange

Compatibility with Human Environment

Community Needs• Increased mobility of U.S. Highway• Improved highway safety for drivers• Enhanced access to mountain resort communities• Aesthetic considerations

Major Issues• Getting public buy-in on future benefits of improving

Berthoud Pass during construction phase• Traffic management during construction phase

Page 9: Context Sensitive Design C For Rural Roads S

AASHTO/FHWA Peer Exchange: Context Sensitive Solutions BaltimoAASHTO/FHWA Peer Exchange: Context Sensitive Solutions Baltimore, MD Sept. 6re, MD Sept. 6--8, 20068, 2006

CSSexchange

Project Vision

Issues and Solutions• Safety and mobility• Water quality• Wetlands• Wildlife• Visual resources• Recreation/historic

restoration• Construction

sequencing• Financial constraints

Page 10: Context Sensitive Design C For Rural Roads S

AASHTO/FHWA Peer Exchange: Context Sensitive Solutions BaltimoAASHTO/FHWA Peer Exchange: Context Sensitive Solutions Baltimore, MD Sept. 6re, MD Sept. 6--8, 20068, 2006

CSSexchange

Seamless Stakeholder Involvement Process

Stakeholders• Iterative design/analysis process• Value Engineering process• USFS, CDOT and FHWA Interdisciplinary Team

– Environmental Assessment– Design – Construction

• Partners for Access to the Woods (PAWS): non-profit group addressing ADA compliance and accessibility issues on public lands

Page 11: Context Sensitive Design C For Rural Roads S

AASHTO/FHWA Peer Exchange: Context Sensitive Solutions BaltimoAASHTO/FHWA Peer Exchange: Context Sensitive Solutions Baltimore, MD Sept. 6re, MD Sept. 6--8, 20068, 2006

CSSexchange

Seamless Stakeholder Involvement Process

Level of Public Involvement• Communication Methodologies: open houses,

newsletters, small group meetings, agency contacts• Role of the Stakeholders: consensus of preferred

alternative, identification of mitigation measures, selection of aesthetic treatment

Page 12: Context Sensitive Design C For Rural Roads S

AASHTO/FHWA Peer Exchange: Context Sensitive Solutions BaltimoAASHTO/FHWA Peer Exchange: Context Sensitive Solutions Baltimore, MD Sept. 6re, MD Sept. 6--8, 20068, 2006

CSSexchange

Transportation Successes

• Widened the roadway from two to three lanes• Added a guardrail to reduce rate and severity of accidents• Created shoulders for turn-offs and snow storage• Increased design speed of switchbacks• Built retaining walls to reduce risk of falling rocks• Addressed a range of aesthetic and design challenges

Page 13: Context Sensitive Design C For Rural Roads S

AASHTO/FHWA Peer Exchange: Context Sensitive Solutions BaltimoAASHTO/FHWA Peer Exchange: Context Sensitive Solutions Baltimore, MD Sept. 6re, MD Sept. 6--8, 20068, 2006

CSSexchange

Facility as a Community Asset • Regional Context: Access to mountain recreation

areas (Winter Park Ski Resort and Rocky Mountain National Park)

• Local Context: Access to homes and businesses

Page 14: Context Sensitive Design C For Rural Roads S

AASHTO/FHWA Peer Exchange: Context Sensitive Solutions BaltimoAASHTO/FHWA Peer Exchange: Context Sensitive Solutions Baltimore, MD Sept. 6re, MD Sept. 6--8, 20068, 2006

CSSexchange

Challenges of Using a CSS Approach for this Project

Challenges• Getting the public involved and accepting of

“short-term pain for long-term gain”• EA scheduled for only one year, but took

three to complete• Learning to conduct business in a new way• Required an education process• Financial and budget constraints

Page 15: Context Sensitive Design C For Rural Roads S

AASHTO/FHWA Peer Exchange: Context Sensitive Solutions BaltimoAASHTO/FHWA Peer Exchange: Context Sensitive Solutions Baltimore, MD Sept. 6re, MD Sept. 6--8, 20068, 2006

CSSexchange

Challenges of Using a CSS Approach for this Project

Financial and Budget Constraints• Strategic project for CDOT• Rigid schedule and budget• Phases 1 & 2 - Approximately $45 million

total allocation• Extremely tight schedule for NEPA process

and design

Page 16: Context Sensitive Design C For Rural Roads S

AASHTO/FHWA Peer Exchange: Context Sensitive Solutions BaltimoAASHTO/FHWA Peer Exchange: Context Sensitive Solutions Baltimore, MD Sept. 6re, MD Sept. 6--8, 20068, 2006

CSSexchange

Challenges of Using a CSS Approach for this Project

Design Challenges and Solutions• Multi-disciplinary team blending CDOT,

FHWA, and consultant staff• Consideration of traffic claming built into

roadway alignment• Tremendous geological challenges

– Avalanche chutes– Landslides– Very high retaining walls

Page 17: Context Sensitive Design C For Rural Roads S

AASHTO/FHWA Peer Exchange: Context Sensitive Solutions BaltimoAASHTO/FHWA Peer Exchange: Context Sensitive Solutions Baltimore, MD Sept. 6re, MD Sept. 6--8, 20068, 2006

CSSexchange

Accomplishments from Using a CSS Approach for this Project

Accomplishments• Precedent-setting project for CDOT, resulting in

other spin-off CSS projects• Developed long-term partnership between CDOT

and USFS• Project outcome heralded as exceeding original

expectations, while continuously “raising the bar” for future CDOT projects

• Recognized as exemplary by AASHTO, International Erosion Control Association, FHWA, and American Road & Transportation Builders Association

Page 18: Context Sensitive Design C For Rural Roads S

AASHTO/FHWA Peer Exchange: Context Sensitive Solutions BaltimoAASHTO/FHWA Peer Exchange: Context Sensitive Solutions Baltimore, MD Sept. 6re, MD Sept. 6--8, 20068, 2006

CSSexchange

Significant Atypical Project-Specific Issues

• Topography: 11,000 ft. elevation at summit• Design constraints: sharp curves and tight

switchbacks, cutting through US Forest Service land • Strategic CDOT project of statewide significance• Little room for construction activity, short season

(June through October) • Traffic control in a year-round recreational area• Visual aspects of the corridor• Historical/archeological• Ecosystem/native habitat

Page 19: Context Sensitive Design C For Rural Roads S

AASHTO/FHWA Peer Exchange: Context Sensitive Solutions BaltimoAASHTO/FHWA Peer Exchange: Context Sensitive Solutions Baltimore, MD Sept. 6re, MD Sept. 6--8, 20068, 2006

CSSexchange

CSS Bottom Line

• How were our actions different?

• How was our attitude different?

• How was our decisionmaking different?

• How did our customers respond as partners?

• Was there buy-in from all?

Page 20: Context Sensitive Design C For Rural Roads S

AASHTO/FHWA Peer Exchange: Context Sensitive Solutions BaltimoAASHTO/FHWA Peer Exchange: Context Sensitive Solutions Baltimore, MD Sept. 6re, MD Sept. 6--8, 20068, 2006

CSSexchange

Contact Information

For further information please contact: Michelle Li – Colorado Dept. of Transportation Region 1 - Planning & Environmental Manager (303) 757-9112 [email protected]

Daniel A. Lovato - U.S. Forest Service Clear Creek District Ranger (303) 567-3001 [email protected]