Copy of ID progress as on 30 07 11

Embed Size (px)

Citation preview

  • 8/3/2019 Copy of ID progress as on 30 07 11

    1/6

    Sl.No Description

    Planned work

    completion

    till 30.07.11

    ( in % )

    Guest Floors

    I Fourth Floor

    1 False ceiling 100%

    2 Fixing of door frame 100%

    4 Dadoing:For toilets/ Kitchen/lift cladding 100%

    5 Fixing of Vanity counters 100%

    6 Fixing of Marbles in dado/niche above counter 100%

    7 Fixing of inbuilt furniture / wall panel / mirror panel 65%

    8 Flooring - Tiles/ Marble threshold,IPS for corridors 41%

    9 Internal Painting works excluding final coat 33%

    II Fifth Floor

    1 Marking for levels, bullmark for MEP & ID works 100%

    2 Corecutting for plumbing works 100%

    3 Chasing for electrical conduits 100%

    4 Chasing for plumbing works 100%

    5 Fixing of electrical conduits/boxes walls & above false ceiling 100%6 Fixing of sanitary lines 100%

    7 bore packing 100%

    8 Waterproofing & brick bat filling in toilet area 100%

    9 Fixing of plumbing line & sprinkler line including testing 100%

    10 Fixing of HVAC & Ducting 100%

    11 Fixing of FCUs 100%

    12 POP punning in rooms & corridors 100%

    13 False ceiling 83%

    14 Fixing of door frame 100%

    16 dadoing:For toilets/ Kitchen/lift cladding 100%

    17 Fixing of Vanity counters 100%

    18 Fixing of Marbles in dado/niche above counter 100%

    19 Fixing of inbuilt furniture / wall panel / mirror panel 16%

    20 Flooring - Tiles/ Marble threshold,IPS for corridors 41%

    III Sixth Floor

    1 Marking for levels, bullmark for MEP & ID works 100%

    Mantri Magnolia - progr

    Phase

  • 8/3/2019 Copy of ID progress as on 30 07 11

    2/6

    2 Corecutting for plumbing works 100%

    3 Chasing for electrical conduits 100%

    4 Chasing for plumbing works 100%

    5 Fixing of electrical conduits/boxes walls & above false ceiling 100%

    6 Fixing of sanitary lines 100%

    7 bore packing 100%

    8 Waterproofing &brick bat filling in toilet area 100%9 Fixing of plumbing line & sprinkler line including testing 100%

    10 Fixing of HVAC & Ducting 100%

    11 Fixing of FCUs 100%

    12 POP punning in rooms & corridors 83%

    13 False ceiling 11%

    14 Fixing of door frame 74%

    15 dadoing:For toilets/ Kitchen/lift cladding 45%

    16 Fixing of Vanity counters 16%

    IV Second Floor

    1 Marking for levels, bullmark for MEP & ID works 100%

    2 Corecutting for plumbing works 100%

    3 Chasing for electrical conduits 100%

    4 Chasing for plumbing works 100%

    5 Fixing of electrical conduits/boxes walls & above false ceiling 100%

    6 Fixing of sanitary lines 100%

    7 bore packing 100%

    8 Waterproofing &brick bat filling in toilet area 100%

    9 Fixing of plumbing line & sprinkler line including testing 100%

    10 Fixing of HVAC & Ducting 100%

    11 Fixing of FCUs 100%

    12 POP punning in rooms & corridors 100%14 Fixing of door frame 42%

    15 dadoing:For toilets/ Kitchen/lift cladding 13%

    V Third Floor

    1 Marking for levels, bullmark for MEP & ID works 100%

    2 Corecutting for plumbing works 100%

    3 Chasing for electrical conduits 100%

    4 Chasing for plumbing works 100%

    5 Fixing of electrical conduits/boxes walls & above false ceiling 100%

    6 Fixing of sanitary lines 100%

    7 bore packing 100%

    8 Waterproofing &brick bat filling in toilet area 100%

    9 Fixing of plumbing line & sprinkler line including testing 100%

    10 Fixing of HVAC & Ducting 100%

    Guest Floors

    I Seventh Floor

    1 Marking for levels, bullmark for MEP & ID works 100%

    2 Corecutting for plumbing works 100%

    Phase I

  • 8/3/2019 Copy of ID progress as on 30 07 11

    3/6

    3 Chasing for electrical conduits 100%

    4 Chasing for plumbing works 100%

    5 Fixing of electrical conduits/boxes walls & above false ceiling 100%

    6 Fixing of sanitary lines 100%

    7 bore packing 100%

    8 Waterproofing &brick bat filling in toilet area 100%

    9 Fixing of plumbing line & sprinkler line including testing 22%10 Fixing of HVAC & Ducting 22%

    12 POP punning in rooms & corridors 100%

    14 Fixing of door frame 9%

    II Eighth Floor

    1 Marking for levels, bullmark for MEP & ID works 100%

    2 Corecutting for plumbing works 100%

    3 Chasing for electrical conduits 100%

    4 Chasing for plumbing works 100%

    5 Fixing of electrical conduits/boxes walls & above false ceiling 100%

    6 Fixing of sanitary lines 100%

    7 bore packing 67%

    8 Waterproofing &brick bat filling in toilet area 30%

    11 POP punning in rooms & corridors 63%

    III Ninth Floor

    1 Marking for levels, bullmark for MEP & ID works 100%

    2 Corecutting for plumbing works 100%

    3 Chasing for electrical conduits 100%

    4 Chasing for plumbing works 100%

    5 Fixing of electrical conduits/boxes walls & above false ceiling 22%

    6 Fixing of sanitary lines 22%

    IV Tenth Floor1 Marking for levels, bullmark for MEP & ID works 33%

    VI Eleventh Floor Public Area

    1 Balance Civil works 62%

  • 8/3/2019 Copy of ID progress as on 30 07 11

    4/6

    Actual

    completed as

    on 27.07.11

    ( in % )

    Remarks

    35%Only 8 rooms framing is done, no MEP clearance for gypsum board, rooms wiring

    pending, HVAC canvas/grills/fcu drain pending), Sprinkler rework is pending.

    95%

    75% Marble is awaited, FCU drain issue.

    - Marble/wash basins awaited. Services ceiling clearances still pending.

    - Marble is awaited

    5% Shortage of manpower, Glazing side is not covered

    - No services clearance( flooring will be done after false ceiling)

    -

    90%

    75% Balcony pending for rainwater

    100%

    100%

    100%100%

    100%

    95%

    50% Testing 0%, Sprinkler 50 %

    80%

    60%

    75%

    0%No MEP clearance for gypsum board, rooms wiring pending, HVAC canvas/grills/fcu

    drain pending), Sprinkler rework is pending, Shortage of manpower

    60% Shortage of manpower

    60% Clearance only for 12 rooms given by MEP

    - Marble/wash basins awaited. Services ceiling clearances still pending.

    - Marble is awaited

    - Shortage of manpower, Glazing side is not covered

    - No services clearance( flooring will be done after false ceiling)

    70% Shortage of manpower

    ess as on 27.07.11

    FCU with heater not received, FCU drain no clearance

  • 8/3/2019 Copy of ID progress as on 30 07 11

    5/6

    75% Balcony pending for rainwater

    100%

    100%

    100%

    100%

    100%

    95%50% Testing 0%, Sprinkler 50 %

    70%

    60%

    -

    -

    -

    -

    -

    60% Shortage of manpower

    75% Balcony pending for rainwater

    100%

    100%

    100%

    100%

    100%

    70% Corner room is pending

    50% Testing 0%, Sprinkler 50 %

    35% Piping is done, duct material not available

    50% 0.5

    --

    -

    40%

    20%

    30%

    20%

    30%

    -

    -

    69%

    -

    35%

    56%

    56%

    I

    FCU with heater not received, FCU drain no clearance

    Shortage of manpower

    No MEPClearance

    Shortage of Manpower

    No MEPClearance & shortage of manpower

    Shortage of manpower, shortage of materials ( FCU's , cisterns & fire dampers0

  • 8/3/2019 Copy of ID progress as on 30 07 11

    6/6

    33%

    56%

    33%

    -

    -

    72%

    -30%

    -

    -

    30%

    22%

    33%

    22%

    33%

    -

    -

    61%

    -

    20%

    -

    11%

    -

    11%

    -

    -

    -

    Shortage of manpower & Materials

    shortage of materials & Manpower

    shortage of materials & Manpower