40
Discrete Damages/Cost Variance Analysis Method for Quantifying Damages in Construction Claims i Table of Contents 1. INTRODUCTION ............................................................................................................................... 1 2. SEVEN STEP PROCESS ................................................................................................................... 2 3. DEVELOPMENT OF COST ANALYSIS DATABASES ............................................................... 5 3.1 CONTROL BUDGET CALCULATIONS ...............................................................................................5 3.2 ACTUAL COST CALCULATIONS ........................................................................................................7 3.3 COST VARIANCE CALCULATIONS....................................................................................................8 3.4 ALLOCATION OF COST VARIANCES ..............................................................................................11 List of Figures Figure 1 Discrete Damages/Cost Variance Analysis Method ..................................................................... 1 Figure 2 Typical Cost Account Structure ................................................................................................... 3 Figure 3 Three-Dimensional Damage Matrix ............................................................................................. 4 Figure 4 Control Budget Revisions with Time ........................................................................................... 5 Figure 5 Sample Evolution of Control Budget ........................................................................................... 6 Figure 6 Discrete Damages/Cost Variance Analysis Methodology .......................................................... 11 Figure 7 Cost / Damages Matrix ............................................................................................................... 12

Cost Variance Analysis

Embed Size (px)

Citation preview

Page 1: Cost Variance Analysis

Discrete Damages/Cost Variance Analysis Method for Quantifying Damages in Construction Claims

i

Table of Contents 1. INTRODUCTION ............................................................................................................................... 1

2. SEVEN STEP PROCESS ................................................................................................................... 2

3. DEVELOPMENT OF COST ANALYSIS DATABASES ............................................................... 5

3.1 CONTROL BUDGET CALCULATIONS ...............................................................................................5

3.2 ACTUAL COST CALCULATIONS ........................................................................................................7

3.3 COST VARIANCE CALCULATIONS....................................................................................................8

3.4 ALLOCATION OF COST VARIANCES..............................................................................................11

List of Figures

Figure 1 Discrete Damages/Cost Variance Analysis Method ..................................................................... 1

Figure 2 Typical Cost Account Structure ................................................................................................... 3

Figure 3 Three-Dimensional Damage Matrix ............................................................................................. 4

Figure 4 Control Budget Revisions with Time ........................................................................................... 5

Figure 5 Sample Evolution of Control Budget ........................................................................................... 6

Figure 6 Discrete Damages/Cost Variance Analysis Methodology.......................................................... 11

Figure 7 Cost / Damages Matrix ............................................................................................................... 12

Page 2: Cost Variance Analysis

Discrete Damages/Cost Variance Analysis Method for Quantifying Damages in Construction Claims

1

1. INTRODUCTION

The “discrete damages/cost variance analysis method” for quantifying construction claim damages involves the specific distribution of all costs incurred on the project rather than quantifying only certain parts of the cost or damage analysis as may be used in the other methods. The credibility of this method is established by separating the cost growth that results from bid error, noncompensable, and compensable cost problems, as established by first using the modified total cost method, and then identifying individual compensable problems with specific costs tied to each problem. In addition, the cost growth for each claim problem is applied to each relevant cost account to demonstrate that the “sum of the parts” of each claim does not exceed the whole cost overrun for each cost account. The discrete damages/cost variance analysis method is illustrated by Figure 1.

Figure 1

Discrete Damages/Cost Variance Analysis Method

Page 3: Cost Variance Analysis

Discrete Damages/Cost Variance Analysis Method for Quantifying Damages in Construction Claims

2

The discrete damages/cost variance analysis method appropriates all costs taken from the claimant’s cost records into cost variance analysis categories, which set forth the claimed costs separate from the other noncompensable causes of cost overruns. These cost variance analysis categories include the original bid, any bid errors, approved changes, pending changes, specific compensable problems (claims), and noncompensable (or nonrequested) costs. Because the claimant is in each case associating a particular item of damage for each compensable problem, the cause/effect relationship is established as the numbers are calculated. Accordingly, the claimed amount is both easy to verify and difficult to refute. Most contractors maintain cost records that have some degree of subdivided cost account detail. Therefore, it is more credible to demonstrate variances at the greatest level of detail possible using the available cost records.

However, this method may be difficult to apply in a case where there are several interrelated cause- and-effect relationships, such as a project impacted by numerous change orders as well as contractor- caused problems. Using this method, the damages that may be caused by the discrete damages category, cumulative impact of changes, would be calculated directly using industry studies, or the measured mile method, or indirectly by claiming some portion of the remaining cost overrun in each cost account. Depending on the method used for calculating productivity loss, the claim is often calculated on a cost account basis or based on all remaining labor overruns if those overruns can be tied to the impact of the issues being claimed.

The advantages of this discrete damages/cost variance analysis method are:

1. Because all components of the cost records are evaluated and distributed

into the claim matrix, the total value of the requested funds can be fully explained and justified.

2. The link between entitlement and the amount of damages is developed at the lowest level of detail of the cost records, thus providing significant credibility to the burden of proof.

3. Isolation of the damages of cost components and individual claim problems identifies the hard areas of claim while also identifying the soft spots to be negotiated, if necessary.

2. SEVEN STEP PROCESS

The discrete damages/cost variance analysis method involves seven steps. By analysis of the detailed cost records, each project work activity is first divided into the basic cost elements (cost accounts) of direct labor, labor burdens, construction equipment ownership and operating expense, rental equipment, subcontracts, permanent materials and equipment, consumable materials and

Page 4: Cost Variance Analysis

Discrete Damages/Cost Variance Analysis Method for Quantifying Damages in Construction Claims

3

supplies, field overhead, home office overhead, and profit. A typical cost account structure is shown by

Page 5: Cost Variance Analysis

Discrete Damages/Cost Variance Analysis Method for Quantifying Damages in Construction Claims

4

Figure 2. The bid cost (budget) and the actual cost for each cost element of each project activity are identified.1

Figure 2

Typical Cost Account Structure

Secondly, the detailed project as-planned and as-built schedules are analyzed to identify the time frame of specific delays, disruptions, changes, labor strikes, suspensions, adverse weather conditions, deliveries of critical equipment and material, acceleration, etc. The time frame for each problem isolates when each problem and cost occurred, which can then be traced back to the contractor’s job cost reports and other man-hour records.

The third step involves evaluation of the contractor’s bid estimate to determine if it underestimated any cost elements of any activity. Knowledge of industry standards, efficient construction techniques, man-hour productivities, and cost estimating are essential to properly evaluate the contractor’s bid. In addition to the evaluation of bid errors, all approved and pending changes to the contract price are applied to derive an adjusted bid value for each work activity.

As a fourth step, each activity and its cost elements are evaluated for noncompensable cost items. These may include costs incurred because of labor strikes, idle time due to bad weather, equipment down-time caused by the contractor’s improper operation or maintenance, inefficient management of the contractor’s labor or of subcontractors, or other cost items that are clearly not the owner’s responsibility. The actual cost for each activity is reduced by such noncompensable costs to derive an adjusted value.

As a fifth step, each activity is assessed by time frame for the impact and cost overrun caused by each specific claim problem. Damages such as additional labor, equipment or material costs, premium time, second shift costs, reduced productivity, extended overhead, financing costs, and labor or

1 Often, the cost accounts used by the contractor during its bid preparation may be different than those that it used during the execution of the project in its job cost report. Hopefully, the contractor has reconciled the

Page 6: Cost Variance Analysis

Discrete Damages/Cost Variance Analysis Method for Quantifying Damages in Construction Claims

5

different cost accounts between the bid phase and the execution phase when it set up its job cost report. If not, the analyst will need to perform this reconciliation to prepare the cost/damages matrix.

Page 7: Cost Variance Analysis

Discrete Damages/Cost Variance Analysis Method for Quantifying Damages in Construction Claims

6

material escalation are identified and assigned to the appropriate claim problem to complete the distribution of all project costs. Cost overruns outside the time frame in which the problem or its effect occurred are excluded from the compensable cost distribution and, therefore, are noncompensable.

In the sixth step of the analysis, the cost/damage analysis matrix of the damage analysis components, project work activities, and cost accounts are totaled to determine the specific dollar amount of each requested claim (compensable problem). The actual cost for each project work activity by row is first distributed into one or more of the appropriate cost accounts. The actual cost in each cost account of each activity is then distributed into the appropriate damage analysis component category. The cost/damage analysis matrix is illustrated in three dimensions by Figure 3.2

Figure 3

Three-Dimensional Damage Matrix

As a final, seventh step, the claimant must clearly communicate the basis of the distribution of costs into the claim categories and support each element of the requested compensable damages with a cause-and-effect explanation to support the entitlement for cost recovery.

2 In practice, the spreadsheet of costs will be set up in two dimensions, with the cost accounts as sub

Page 8: Cost Variance Analysis

Discrete Damages/Cost Variance Analysis Method for Quantifying Damages in Construction Claims

7

cost elements under each work activity.

Page 9: Cost Variance Analysis

Discrete Damages/Cost Variance Analysis Method for Quantifying Damages in Construction Claims

8

3. DEVELOPMENT OF COST ANALYSIS DATABASES

The structure of the methodology first requires the establishment of two separate data bases, a control budget data base, and an actual cost data base, which are linked by work activity and cost element definition. A third data base called cost variance/allocation is developed from the first two.

3.1 CONTROL BUDGET CALCULATIONS

The control budget is a restatement of the original bid estimate in a form that facilitates comparisons between budget and actual costs. The control budget is normally prepared after bid opening and before construction starts.

The control budget is not the contractor's bid. The bid proposal is the price sheet used in the contract as the basis of payment for work performed. The contractor prepares an estimate of costs, overheads, and anticipated profit (the total of which becomes the bottom line of its bid), but the makeup of individual cost elements becomes hidden when assigning values (prices) to each bid item. Bid unbalancing is common. In addition, payment is usually based on units of work completed and not for interim steps along the way. An example of the latter is payment for concrete—paid for by the cubic yard, in place. No separate payment is usually made for forming, finishing, etc. For this reason, the control budget (which shows separate estimated costs of forming, finishing, and placement of concrete), and not the bid schedule, is to be used as the basis for comparison for calculations of damages using the discrete damages/cost variance analysis approach.

Control budgets usually vary over time, as illustrated by Figure 4.

Figure 4

Control Budget Revisions with Time

Page 10: Cost Variance Analysis

Discrete Damages/Cost Variance Analysis Method for Quantifying Damages in Construction Claims

9

Page 11: Cost Variance Analysis

Discrete Damages/Cost Variance Analysis Method for Quantifying Damages in Construction Claims

10

Various events cause this variance to happen; the most common being pay quantity variations, change orders, contractor-initiated improvements to means and methods, and subcontractor and supplier negotiations, as shown by Figure 5. In constructing a control budget data base, the time dimensions must be included. On one case, a contractor submitted a modified total cost claim of $4 million. The owner's outside auditor validated the loss at $4 million. When time-related cost reports became available through discovery, it was found that the contractor had lost $3 million prior to the first event stated to have caused the delay claim. The result was that the contractor's “window of opportunity” for recovery of its losses suddenly became only $1 million.

Figure 5

Sample Evolution of Control Budget

The contractor's management-initiated adjustments need to be well addressed and well structured in the damages presentation. Examples of management-initiated adjustments include the result of the contractor's negotiations with subcontractors and/or suppliers. A somewhat common occurrence might be a subcontractor dropping its price by $50,000 because the contractor furnished scaffolding service to the subcontractor. The contractor's additional cost of providing this service may be $15,000, which would result in an increase to the contractor's profit of $35,000 (which the contractor then owns).

Page 12: Cost Variance Analysis

Discrete Damages/Cost Variance Analysis Method for Quantifying Damages in Construction Claims

11

Other examples of management-initiated adjustments involve post-bid improvements in means and methods.

The structure of the control budget database, including original, revised, and modified contract elements, must be time-variance oriented and trackable for categories of events. Typically, a contractor estimates the cost of the project on a two-dimensional spreadsheet showing work activities on one axis and cost elements on the other. To provide for the complete comparison to actual costs, a third dimension – time – needs to be considered. Each event that changes the control budget is expressed as an additional spread sheet containing the cost revisions to the preview control budget. In addition to the above considerations, which only mention costs, it is usually advantageous to provide for quantities of work, labor hours, and equipment types and hours.

In summary, a properly constructed control budget data base for use as the basis of comparison to actual costs as part of a discrete damages/cost variance analysis calculation method must be fully integrated and time sensitive.3

3.2 ACTUAL COST CALCULATIONS

Actual costs are recorded and reported as construction progresses. Labor costs are based on periodic payrolls. Equipment use hours are developed from operators' time cards and validated from recorded readings on hour meters. Construction equipment charges are based on hours of operation. Material costs are captured from invoices and paycheck stubs as are subcontractor costs.

The key to organizing the cost data for comparison to the control budget is proper and timely coding and posting to an account structure defined by the control budget. Correlation and integration of cost accounts to an appropriate activity level definition in the project schedule also facilitates the cause- effect connection of the problem and the cost overrun. If this correlation is performed well, subsequent cost and damage analysis work becomes a simple chore. If it is not done well, the effort is large and the resulting cost becomes one that is not normally recoverable in a claim.

In well-organized cost tracking, the cost of additional work directed by the owner is easily determined. However, the discrete damages/cost variance analysis method (as well as the modified total cost method) is most applicable when many changes to the work occur simultaneously and result in changes to the unchanged work (productivity impact and resultant delay to completion).

Sometimes cost accounting adjustments are required; for example, when costs are miscoded and posted to an incorrect period of time. A case of miscoding is illustrated by a contractor's claim for $200,000 for owner-caused productivity impact on installing large bore pipe. The contractor's original bid estimate and control budget for the work was $500,000. The actual cost, as posted, was

Page 13: Cost Variance Analysis

Discrete Damages/Cost Variance Analysis Method for Quantifying Damages in Construction Claims

12

$700,000.

3 The concept of a properly constructed control budget database is also applicable to the other damages calculation methods.

Page 14: Cost Variance Analysis

Discrete Damages/Cost Variance Analysis Method for Quantifying Damages in Construction Claims

13

The contractor's bid estimate and control budget for placing the pipe hangers was $100,000. The actual cost report showed no cost for the pipe hangers. Review of the project history through document analysis and interviews revealed that the foreman responsible for the pipe installation was also responsible for the pipe hangers. All of the pipe hangers had, in fact, been placed. The foreman had not separated the pipe hangers effort but had recorded all efforts to the piping installation task. The result was the contractor's claim was reduced to $100,000 ($200,000 piping installation overrun less $100,000 adjustment for the pipe hangers).

Cost posting to an incorrect period is all too common for materials, outside equipment rental, and subcontractors. Usually what happens is that the cost is posted during the period that the invoice is paid, which is a month or more after the work was performed or the material incorporated in the work. Appropriate cost accounting adjustments must be made to the actual cost database prior to the final comparison forming the basis of damage recovery using the discrete damages/cost variance analysis method.

In addition to the above considerations, it is usually desirable to make a cost comparison on both actual quantities of work and earned value.

In summary, a properly constructed actual cost database must also be fully integrated and time sensitive.

3.3 COST VARIANCE CALCULATIONS

Cost variance calculations are simply the mathematical differences between budget elements and actual costs, preferably computed for increments of time and in total. By considering all project costs in the variance analysis, the analyst is afforded the opportunity to identify anomalies, such as the pipe hangers issue discussed earlier, and make appropriate cost accounting adjustments. Proper adjustments make the cost variance analysis more credible.

The use of a cost variance analysis is a fundamental component of the contractor’s damages calculations on a complex engineering, procurement, and construction project where the contractor is attempting to recover its increased costs for numerous problems affecting multiple disciplines of work. A contractor’s failure to utilize this approach could severely limit the credibility of its claim because:

• The absence of support for the contractor’s actual costs at the detailed cost

account level in its cost reporting system may question whether the contractor actually incurred cost overruns in the areas of work that it alleged it was damaged;

• The absence of its bid estimate details, including the assumption it made in preparing its bid, may question whether the contractor is attempting to recover

Page 15: Cost Variance Analysis

Discrete Damages/Cost Variance Analysis Method for Quantifying Damages in Construction Claims

14

for its bid error;

Page 16: Cost Variance Analysis

Discrete Damages/Cost Variance Analysis Method for Quantifying Damages in Construction Claims

15

• By addressing the cost variance at the detailed cost account level, and demonstrating that the sum of all of cost increases for each cost account, including those cost increases for which it seeks additional compensation, do not equate to more than the costs that the contractor incurred for each cost account; and

• The contractor has addressed costs that result from its performance problems in addition to costs for which it is seeking additional compensation.

A cost variance analysis must often be supplemented by a quantity4 variance analysis to ensure

that:

• Increases in man-hours and related costs are not the result of quantity growth due to the contractor’s bid error;

• The contractor can separate quantities that are included in approved and pending change orders, and not comingle the man-hours required to install those quantities with man-hours due to productivity loss;

• The unit man-hours to design or install different types of engineering or construction quantities can be separately applied during the variance analysis calculations;

• The contractor has considered quantity overages due to over-procurement and waste;

• Material and equipment costs for each quantity type can be applied during the variance analysis calculations to ensure accuracy of the results; and

• The sum of all of the quantities for each of the damages analysis categories does not exceed the total quantities installed by the contractor for each discipline of work.

A cost variance analysis must often be supplemented by a man-hour5 variance analysis to ensure

that:

• Man-hours associated with quantity growth are not included in the contractor’s other claims, such as claims for productivity loss;

4 Quantity variance analysis include but are not limited to engineering deliverables such as the number of design drawings, piping isometrics, and other documentation required by engineering to support the construction work, as well as physical quantities of materials to be installed during construction, such as concrete, soil quantities

Page 17: Cost Variance Analysis

Discrete Damages/Cost Variance Analysis Method for Quantifying Damages in Construction Claims

16

for import or export during site preparation, number and/or length of piles for foundations, structural steel, installed equipment, piping, instruments, electrical materials, etc.

5 Quantity variance analysis include but are not limited to engineering deliverables such as the number of design

drawings, piping isometrics, and other documentation required by engineering to support the construction work, as well as physical quantities of materials to be installed during construction, such as concrete, soil quantities for import or export during site preparation, number and/or length of piles for foundations, structural steel, installed equipment, piping, instruments, electrical materials, etc.

Page 18: Cost Variance Analysis

Discrete Damages/Cost Variance Analysis Method for Quantifying Damages in Construction Claims

17

• Man-hours included in pending and approved change orders are separately addressed and not included in the contractor’s other claims, such as its change order and productivity loss claims;

• Man-hour growth that resulted from the contractor’s bid error are not improperly included in the contractor’s other claims;

• Man-hours resulting from contractor-caused problems are not included in the contractor’s other claims; and

• The sum of all of the man-hours for each of the damages analysis categories does not exceed the total man-hours incurred by the contractor for each discipline of work.

A cumulative impact claim is often an attempt by the contractor to recover man-hours associated with multiple changes that occurred on the project. It is the “ripple” from an activity disrupted by several changes does not only impact nearby or follow-on work, but also can potentially impact any and all project work being performed concurrently or subsequent to that activity. In fact, one could argue that the impact to nearby or follow-on work is akin to “local” disruption, which the contractor should recognize and price in the change order. It is the effect, the unforeseeable impact, on other base scope work that seems to be at issue with cumulative impact claims.

A common problem is that the contractor uses a cumulative impact claim as a global claim in an attempt to recover all of its additional man-hours that it incurred above its bid man-hours as part of its overall damages request. Thus, all increased man-hours are the result of loss of productivity allegedly caused by the cumulative impact of changes.

Arbitration panels, courts, and boards seem to at least consider the effects of RFIs and other impacts, and not dismiss them for not being approved change orders. It may be reasonable that cumulative impacts derive from multiple change orders, RFIs, differing site conditions, suspensions of work, or other work interruptions that are widely recognized as compensable events. Therefore, not only can owner-approved changes be used as part of a cumulative impact claim, but also unapproved change orders and all other potentially disruptive events factor into the cause-effect relationship. However, the contractor should still recognize any direct disruption that is caused by these events during the project and submit the required change order documentation and costs.

The use of a man-hour variance analysis can help ensure that a cumulative impact claim is not being used to capture increased man-hours that may have resulted from other causes. While the quantification of increased man-hours can be performed using various methods, such as a measured mile analysis or from using various industry studies, the man-hour variance analysis will frame the man-hours such that over-recovery is precluded because the sum of the parts cannot exceed all of the man-hours incurred. If the man-hour variance is performed for all engineering

Page 19: Cost Variance Analysis

Discrete Damages/Cost Variance Analysis Method for Quantifying Damages in Construction Claims

18

and construction disciplines, significant credibility is built into the contractor’s claim. If the contractor fails to use a

Page 20: Cost Variance Analysis

Discrete Damages/Cost Variance Analysis Method for Quantifying Damages in Construction Claims

19

man-hour variance analysis in its claim calculations, and the owner can demonstrate that the contractor is claiming more man-hours than it incurred when all other damage analysis categories are considered. The contractor’s credibility suffers and its claim may be denied.

3.4 ALLOCATION OF COST VARIANCES

The final step in calculating damages under the discrete damages/cost variance analysis method is to allocate the variances to the responsible party. Categories for allocation usually include contractor bid error, contractor performance error, other noncompensable costs, and contractor compensable claim costs, as shown by Figure 6. Identification and utilization of other categories is commonly performed.

Figure 6

Discrete Damages/Cost Variance Analysis Methodology

Allocation is made by expert opinion utilizing the cost variance analyses and other parallel analyses that may include the following:

Analysis of bid requirements;

Analysis of contract requirements;

Analysis of construction requirements;

Schedule/delay/impact analysis; and

Analysis of project history.

Page 21: Cost Variance Analysis

Discrete Damages/Cost Variance Analysis Method for Quantifying Damages in Construction Claims

20

The mathematical structure of the allocation should demonstrate clearly that all variances have been included and totaled to an amount equal to the difference between the contract price and actual costs incurred. An example of the overall allocation of cost variances into a cost damages matrix using the discrete damages/cost variance analysis method is shown by Figure 7.

Figure 7

Cost / Damages Matrix

Page 22: Cost Variance Analysis

1

Evaluation of Changes in Process Plant Projects

Owners often issue basic design packages for process plant projects to pre-qualified engineering, procurement, and construction (EPC) contractors as part of a bid request. Owners may represent that the basic design is sufficiently defined to enable the EPC contractor to prepare a fixed-price bid for the final design, procurement, and construction of the facility. Despite these representations, and after the contract is signed, owners frequently initiate what they believe to be simple design changes to the EPC contractor’s scope of work. Under most contracts, the EPC contractor is required to submit, in advance of performing the changed work, its change order price including all associated cost and schedule impacts. Cumulatively, design changes costing five to ten percent of the original contract price of a process plant project are not unusual.1

However, the delay and disruption costs alleged to be associated with higher percentages of changes can be a significant and painful surprise to the owner should the EPC contractor submit a cumulative impact claim at the end of a project.

The price tag for such delay and disruption claims can rise to “unbelievable” magnitudes, especially when a significant number of the changes occur late in the final design work schedule or during construction and the cumulative direct cost of the approved changes is considerably greater than ten percent of the original contract price. In such cases, a comprehensive examination considering the overall cause-effect relationships of design changes, coupled with all of the other problems that occurred during the project, can be performed to determine whether the magnitude of the EPC contractor’s alleged cost increases over its current contract price are reasonable and compensable. An equitable resolution of responsibility for these increased costs must also take into account the EPC contractor’s responsibility for problems that occurred during the project. Allocation of the EPC contractor’s increased costs that directly or indirectly result from the owner’s design changes is central to the resolution of complex delay and disruption claims.

This article discusses the uniqueness of design changes on process plant projects and how such changes can have a significant ripple effect on the project’s engineering, procurement, construction, and start-up work activities. First, the potential effect of changes on various equipment operations in a process plant is presented. Second is a discussion of the need to understand, agree upon, and analyze the totality of the scope of changes. Third, the effect of changes on the various process operating conditions of a process plant is examined. Fourth is a discussion of the various cost considerations that should be contemplated in evaluating changes to the design of a process plant. Next, the potential effect of a change on environmental and safety designs and hazardous operations reviews is addressed. Finally, the need for the owner and the EPC contractor to consider the effect of changes on multi-discipline design coordination and fabrication of specialty process equipment is emphasized. Accompanying this text is a

Page 23: Cost Variance Analysis

2

1 William Schwartzkopf, Calculating Lost Labor Productivity in Construction Claims at p. 47 (1995).

Page 24: Cost Variance Analysis

3

diagram that illustrates the overall cause-effect relationships of design changes and other problems that can lead to delay, disruption, and increased costs of a highly impacted project.

Process Equipment Operations Are Connected

Process plants differ from other construction projects because they use mechanical, chemical or other process equipment to alter the state of matter or composition of the feedstock material streams (solid, liquid, or gaseous phase) to produce different products. The products are usually changed in their chemical composition through various process equipment, such as reactors, distillation columns, compressors, heat exchangers, furnaces, separation vessels, filters, kilns, pelletizers, crystallizers, and others. The products may also be different in their temperature, pressure, and state. In process plants, the chemical composition, temperature and pressure changes are usually accomplished using several process unit operations.

Process unit operations are like a manufacturing assembly line with the output of the previous process operation or equipment item becoming the input or feed to the next process operation or equipment item. Therefore, the impact of a design change to one process operation and its associated equipment can have a ripple effect2 on the design of successor process equipment. As design changes occur, the effect on the design of successor equipment must be constantly evaluated. This means that, beyond defining the design aspects of the process equipment, the process engineer also must coordinate with all other engineering disciplines to ensure that the proper design basis is considered in the civil, structural, mechanical, electrical, and instrumentation designs. Likewise, changes to the process design will often have a ripple effect on the work performed by other engineering disciplines. Such ripple effects often manifest themselves as delays, disruption, loss of productivity, and related increased man-hours and costs if the changes are numerous or significant in overall magnitude, and particularly when the changes occur late in the design process or during construction.

Scope of Changes Must Be Understood, Agreed Upon, and Analyzed

A change in the material properties from upstream process unit operations may affect and change not only the very next process unit operation in the chain, but also equipment design and unit operations several steps downstream in the overall plant operation. For example, a change in the temperature of a liquid process stream flowing out of a reactor may not only require a design change in the water-cooled heat exchanger that is used to cool the reactor product, but the design of the cooling tower may also need to be altered as a result of this change. This change might affect not only the size, civil design, and electrical requirements of the cooling tower, but also the size of the water pipelines circulating cooling water to the process equipment.

Thus, another important and unique characteristic of process plants is that the scope of the change may not be limited to the directly affected process equipment or even the

Page 25: Cost Variance Analysis

4

next downstream process equipment item. The scope of the change must be identified and analyzed

2 Ripple effects are also referred to as knock-on effects or impacts.

Page 26: Cost Variance Analysis

5

for its potential impact on each downstream process equipment operation and all utilities affected by the change, such as fuel gas and oil, cooling water, steam systems, inert nitrogen systems, plant air requirements, and electrical power requirements. Each process equipment item has different operating and design factors (temperature, pressure, composition, flow rate, etc.) that affect its metallurgy, desired operation and products, including design considerations of cost, environmental emissions, and safety.

Not all changes to a process plant are process changes. This point is made because the impact of process changes on the overall multi-discipline design integration of equipment, piping and instrument systems can be significant, whereas non-process changes may not affect more than one equipment, piping, or instrument item. Process changes include changes to the process flow diagrams (additional or deleted equipment) that change the chemistry, heat and material balance, flow rate, pressure, and temperature, and changes to the primary process control instrumentation. Changes to the P&IDs involving manually operated valves, maintenance piping, local instrument indicators, and other instrumentation that does not automatically control the process conditions, as well as changes to structures, insulation, painting, civil, and electrical systems, are not process changes. However, these non-process changes may result from process changes and, therefore, need to be considered in the overall cost and schedule impact of a process change.

For example, adding a drain valve on the low point of a piping system to drain the fluids during a maintenance shutdown would not be a process change even if it affected piping in the processing part of the plant. Adding local instruments, such as a pressure or temperature indicator, also would not be a process change. Another example of a non-process change would be adding a utility station that supplies air for pneumatic maintenance tools or water pipes for safety showers and wash down stations. Commonly, these types of non-process changes may not be changes in scope. Instead, owners may argue that the incorporation of these items into the final engineering design is design development and should have been included in the EPC contractor’s scope of work, schedule, and costs.

The time and resources required to evaluate the potential cost and schedule impact that a change may have on the engineering, procurement, and construction of a process plant may not be fully predictable. This uncertainty is caused by the equipment, material, instrument, utility, and design and operational variables that may result from a change. For example, a change in the operating temperature of a reactor may also change:

1. The steam requirements to heat the reactor, which could change the size

of the boiler, fuel gas or steam piping; 2. The cooling water requirements to cool the product stream exiting the

reactor, which in turn might change the size of the cooling tower, cooling tower circulating pumps, water pipelines, and associated electrical, structural, and civil design requirements;

3. The insulation requirements for the affected equipment and pipelines;

Page 27: Cost Variance Analysis

6

4. The reactor steel and pipe metallurgy design requirements; or 5. Potentially, other equipment, instrument, and other changes.

Page 28: Cost Variance Analysis

7

The EPC contractor’s change order proposal usually must contain the following information:

1. The initiator – owner or contractor; 2. Reason(s) for change (operability, maintenance, safety, environmental;

engineering or construction errors by others, etc.); 3. Description of the change with respect to facilities and services; 4. Impact on the contract price including all direct, indirect, delay, loss of

productivity, acceleration, and impact costs; 5. Impact on the project completion date with supporting

schedule documentation; 6. Impact on the project’s utilities or process requirements, as applicable; 7. Definition of any impact on the contractor’s guarantees; and 8. Definition of the latest date for the owner’s approval of the change

without affecting the project completion date.

When the EPC contractor submits its change order proposal to obtain the owner’s approval to proceed with the change, the EPC contractor may not be able to satisfy the contractual requirements to include all such cost and schedule impacts in its change order proposal. This problem occurs because, at the time that the change order proposal is submitted, the contractor may not be able,3 or does not apply the needed resources and take the time, to accurately estimate the materials, man-power, and schedule impact required by the engineering, procurement, and construction disciplines to accomplish all of the items of work affected by such changes.

The owner’s decisions about performing the change may be, in part, based on minimal or no effect of the change on the project schedule. When a contractor has deliberately misled an owner regarding the schedule impact of a change, the contractor may not later be able to benefit from the owner’s detrimental reliance on the contractor’s misrepresentation of schedule impact.

Process Operating Conditions

Unlike other engineered projects such as highways or buildings, process plants must be capable of being started up, shutdown, and operated safely and efficiently under a variety of temperature, pressure, and flow rate conditions. Because process plant operating conditions are dynamic, the scope of a change and the appropriate design modifications for all affected equipment and utility systems must be evaluated under start-up, normal/steady state, turndown, and upset or abnormal operating conditions. The design considerations that are used for evaluating the impacts of each particular change on a process plant are fundamentally the same as those used in the original design process to confirm that the equipment designs are still valid, safe, and optimal for the new process conditions created by the change. Whenever a change is introduced, each operating parameter of the process plant must be evaluated in order to determine not only the required

Page 29: Cost Variance Analysis

8

3 Typically, the Contract specifies the amount of time that the contractor is allowed to prepare its response to the owner’s Change Request. The amount of time allowed may not be sufficient to fully evaluate the requested change.

Page 30: Cost Variance Analysis

9

equipment and material changes, but also the engineering, procurement, and construction resources required to accomplish the change.

• Steady State Design. The initial operating parameter considered in the design of

process plants is “steady state,” or normal operating conditions. Steady state design considers the design process conditions for each process step to operate as planned, transferring usually by pipelines the output product(s) from the initial process equipment operation and feeding those products to the downstream process equipment. Equipment and instrumentation are designed such that the required process conditions (temperature, pressure, flow rate, and composition of the process solids, liquids, or gases that are created or used in each process step) will produce the intended product streams. “Steady state” implies that there is no change in the process conditions over time, and that there is balance between the sum of all material and energy entering and exiting each process equipment operation and the entire process plant as a whole. Process engineers refer to this fundamental condition of the steady state design as "the design heat and material balance." These balances often involve hundreds of process and utility streams and energy (heating and cooling) inputs and outputs.

When a process change occurs, the EPC contractor must first evaluate the effect of the change, if any, on the steady state heat and material balance. Changes could affect the size of equipment, piping, and control valves as well as civil, structural and electrical requirements.

• Maximum Product Output and Turndown. Process plant production facilities

may need to be operated at increased or reduced production flow rates compared to “steady state” flow rates. For example, market conditions may require higher or lower quantities of products to be produced during certain periods of the year, requiring an adjustment to inventory or production rates. Also, there may be a disruption in the product distribution facilities or other processes supporting the process plant operations, such as water, fuel, or power supply. Significant time is required to completely shutdown and start-up a large process plant such as an oil refinery, ethylene plant, or a fertilizer plant. Unplanned start-up and shutdowns of process plants also can result in degradation of product quality as well as an increased risk of emissions or accidents. The need to reduce production is often only temporary. For example, the economics of a complete shutdown and start-up of a large oil refinery unit may require the coker to operate safely and efficiently at reduced rates rather than to shut the unit down when full capacity operations are not required.

Therefore, all components comprising each process operation (piping, equipment, materials, utilities, instrumentation, pressure relief devices, etc.)

Page 31: Cost Variance Analysis

10

must be designed and sized to operate and control at the full production capacity and at reduced operating rates. The affect of changes on equipment and materials designs for

Page 32: Cost Variance Analysis

11

maximum and reduced product flow rates must also be considered when evaluating changes to process plants. Failure to evaluate the effect of process changes on maximum and reduced flow rate conditions could cause costly field modifications, delays in the completion of construction, and start-up and operating problems.

• Maintenance and Unusual Operations. Almost every process plant has unusual

operations designed to produce special products or operations connected with the maintenance of the facility. For example, the design of certain reactors must facilitate catalyst removal and change-out. Common design considerations for process plants also include the safe use of isolation equipment during maintenance, the design of separate utility connections such as inert gas (nitrogen), steam, and plant water to enable special operations, and additional piping and tankage used during unusual operations.

Therefore, changes to the design of process plants must be evaluated for their potential effect on unusual and maintenance operations. Failure to evaluate the effect of process changes on unique or maintenance operations can lead to any number of expensive later changes.

• Dynamic (Unsteady State) Design. Process plants must also be designed to

operate safely at dynamic (unsteady) state operations, including cold start-up, recovery from process operating problems, and planned shutdown conditions. Under unsteady state design situations, the process units are not operating in balance and the process conditions (temperature, pressure, and flow rates) within the process steps may fluctuate.

Therefore, designers of process plants must consider unsteady state operating conditions whenever a process change is made. Design considerations should be reviewed under the unsteady state design process conditions to ascertain which systems might be affected by a change. Such reviews should include considering increased utility amounts (steam, power, cooling water, inert gas such as nitrogen), changes to the operating characteristics of mechanical equipment (kilns, reactors, pumps, furnaces, compressors, etc.), diverting of off-specification products during start-up and shutdown, and evaluations of temperature increases and decreases of process material in the pipelines and equipment to reduce stress on piping, connections and vessel metallurgy.

Unsteady state operations may require additional equipment, instruments, and piping or even additional process operations. The effects of a process change on unsteady state operations must be evaluated by the process and other discipline engineers to avoid extensive delays in the commissioning and start-up

Page 33: Cost Variance Analysis

12

of the facility, production loss, unsafe operations, environmental problems, or late field modifications.

Page 34: Cost Variance Analysis

13

Effects of Design Changes on Project Cost

The owner and the EPC contractor should both be concerned about the cost impact of a change. The owner should evaluate whether the EPC contractor’s engineers have optimized the design resulting from the change, and have charged a reasonable price for the changed work. In addition to the direct cost of the changed work, the EPC contractor’s estimators and schedulers must also quantify the indirect cost and schedule impacts to the project that result from implementing the change. To ensure that a complete evaluation of a change is addressed before its implementation, three cost variables should be considered in evaluating changes to the design of a process plant:

• Capital Cost. Design requirements are the primary factor that influence the

initial capital cost of a process plant. The design phase is the optimum time to address constructability considerations that can save both time and cost during construction. Major equipment items and bulk materials comprise the largest individual cost elements of the process plant. For example, the diameter of the process pipes, the material types (stainless steel v. carbon steel), the need for insulation or heat tracing and the use of control valves in the lines must all be optimized in order to mitigate project cost. A change that increases the diameter of just one pipe run by one inch can have a cost impact of tens of thousands of dollars and cause significant delay if the change occurs during the construction phase. To further this example, a construction phase change in pipe size may cause significant delay and disruption and increased costs as a result of the need to: purchase additional pipe, flanges, gaskets, and fittings; re-engineer pipe supports; re-calculated pipe stress values; resize and repurchase control valves; and re-fabricate pipe connections to vessels or other equipment.

In addition to the cost of installed equipment and materials, the cost of spare parts and operating equipment should be factored into the on-stream reliability of the operating facility. Design changes can also affect the need for and cost of spare equipment and materials.

• Operating Cost. Operating costs are also considered in the process design. The

effect of process changes on operating costs should also be evaluated, such as the need for insulation to conserve heat, utility consumption, and added operating personnel or control instrumentation. For example, adding piping insulation or heat tracing in a late field modification, in order to reduce operating costs, is often more costly than if these costs were included during the design phase of the project or when the change order was approved.

• Maintenance Cost. The cost to maintain operating equipment and

instrumentation for the intended life of the process plant is also a major design

Page 35: Cost Variance Analysis

14

factor. Changes made to process plants must consider these design characteristics to minimize unexpected increased costs of field modifications to provide a

Page 36: Cost Variance Analysis

15

maintainable facility. For example, the direct cost of adding a control valve late in the design phase may be covered in the cost of a change order. However, the cost of the structural modification to provide for access to that control valve may not be considered when the change was approved, but will certainly be brought to the attention of the EPC contractor by the operating and maintenance personnel of the plant prior to or during start-up and commissioning. Making late field modifications to allow for such access is often more costly than the cost would have been if these access considerations were included during the design phase of the project or when the change order was approved.

Environmental and Safety Design and Hazardous Operations Reviews

Owner specifications, industry standards, and governmental regulations dictate numerous environmental and safety design requirements in process plants. For example, minimum distance requirements from a fire source affect the location of instrumentation and equipment. Safety and environmental requirements define the need for back-up emergency equipment. Requirements are often compounded such as when fire protection design requirements influence the need for alarms, analyzers, and fire protection coating on structural steel. “Hazardous Operations” reviews employ special procedures to evaluate hazards associated with operation of the process plant.

These same environmental and safety requirements may need to be considered when changes are incorporated into a process plant design. Failure to do so may result in more costly field modifications, delayed construction, and accidents and injury to personnel and/or property when these missing items are eventually discovered.

The Effect of Changes on Design Coordination, Procurement, and Fabrication of Specialty Process Equipment

A process change may also impact multiple engineering disciplines, vendors and suppliers who are performing other planned work to complete the project. This impact is in addition to the operational effect that an upstream process operational change may have on downstream process equipment and operations. The personnel performing this “other planned work” are also controlled by budgets and time constraints to complete their part of the project. The time and cost for these disruptions to the unchanged part of the project are often not fully considered in the direct cost of a change.

As the effects of change impacts are determined, multiple engineering disciplines and specialists in certain process operations may need to be called upon to identify and analyze any necessary design adjustments. These analyses include how the system will be designed and constructed as well as how the changed plant will react under different operating parameters. Such analyses can be time-consuming and, as a result, may well delay critical engineering deliverables that are needed for procurement of equipment and materials or Issued for Construction drawings.

Page 37: Cost Variance Analysis

16

Changes can also have detrimental effects on fabricators of specialty equipment used in a process plant. Production schedules require fabricators of specially designed equipment to operate their facilities in a production line mode. If a change requires a hold to be placed on equipment, that equipment may be pulled from the fabrication assembly line so that other equipment can be fabricated. Therefore, the overall delay to specialty equipment can often be more than the time required to provide the changed specification to the fabricator. These increased fabrication costs and schedule impacts need to be considered as part of the change order costs. If the change is not coordinated with the vendor, modifications must be made in the field or new equipment and materials must be purchased and delivered, adding further delay and disruption to the project.

Summary and Cause-Effect Matrix

A single change - and especially a blizzard of changes - introduced late into the design of a process plant project can extend the contractual completion date of a project, cause significant delay and disruption, and significantly increase project costs. The multiple layers of review and analysis that are required for the implementation of changes within a process plant project are common, unlike many other sectors of the construction industry. What at first might be considered a simple change may well result in numerous design, procurement, and construction modifications because of this complex cause-effect relationships so unique to process plants. Failure to fully evaluate the cause-effect relationships may have unknown or unintended results on the final cost and schedule of the project. Therefore, each change introduced into a process plant project must be carefully analyzed for all design, procurement, construction, turnover, pre- commissioning, start-up, operations, maintenance, safety, regulatory, and environmental considerations. The later in the project a change is introduced, the more disruptive the change implementation becomes to the already completed design, as well as to the already constructed components of the plant affected by the change.

If the EPC contractor is experiencing multiple changes to its scope of work emanating from process, scope, and other types of changes, as well as other delays and performance problems, sorting out the cause-effect relationships in order to allocate responsibility for delay and loss of productivity often cannot be accurately determined until after the completion of the project. As previously stated, the EPC contractor may be contractually obligated to include all schedule and cost impacts in its original change order pricing. Such contractual requirements complicate the contractor’s recovery of change order impact costs.

Design changes are usually not the only cause of delay and disruption to the engineering, procurement, and construction of a highly-impacted process plant project. Other contributors often include errors and omissions in the basic design package supplied by the owner, defective specifications, late owner responses to the EPC contractor’s requests for information, late and defective owner-furnished equipment and material, weather impacts, strikes, force majeure events, underestimated quantities, and EPC contractor performance problems during the engineering, procurement, and construction phases of the project. Sorting

Page 38: Cost Variance Analysis

17

out these variables in order to properly and equitably allocate the responsibility for delay and increased costs for all problems that have occurred during the project can be a complicated challenge.

Page 39: Cost Variance Analysis

18

When delays and disruption occur, contractors often submit requests for time extensions. If the owner refuses to grant a time extension for excusable delays, the contractor may be directed to accelerate to mitigate the excusable delays and avoid liquidated damages for delays that were caused by the contractor. Such acceleration often leads to loss of productivity, which results in increased construction man-hours and costs. Therefore, while the design changes may start out as the primary causes of delay, disruption, and increased costs on a project, the effects of these changes on the overall time and cost for completion of a process plant are typically intertwined and may be concurrent with all of the other problems that have occurred during the project. Diagrams such as in the Cause-Effect Matrix shown in Figure 1 are helpful in tracing the responsibility for the design changes and other primary and secondary causes of delay and disruption, intermediate effects and other secondary causes, and the ultimate effects and associated increased costs of all problems that occurred during the execution of the project

A thorough understanding of the engineering, procurement, and construction sequences and procedures for a process plant project is vital in order to comprehensively quantify all potential schedule and cost effects during the change order pricing, review and approval process. This understanding is also essential to avoid and/or resolve disputes over the alleged cost of such changes at the end of a highly-impacted project, one that usually involves claims and costly arbitration or litigation.

Page 40: Cost Variance Analysis

Increased Equipment & M

aterial Costs

Increased Direct Labor Costs

Increased Home Office O

verhead Costs

Increased Field Indirect Costs

Congestion

Increased Supervision

Dilution of Supervision / Coordination Problem

s Increased C

oordination Labor Rate Increase for Shift D

ifferential Night W

ork Labor Rate Increase for Premium

Time

Acceleration

Requests for Information

Requests for Scope Changes

Dela

y &

Disr

uptio

n

Rewo

rk

Typical Cause - Effect Matrix for a Delay / Disruption Construction Claim

Intermediate Effects and Secondary Causes

Owner Approves Time Extension for Excusable and Compensable Delays

No Time Extension Approved by Owner

Primary Causes Typical Owner / Engineering Problems

Late IFC Drawings Design Basis/Drawing Errors & Omissions Defective Specifications Understated / Overstated Quantities Design Changes

Productivity Loss

Resequencing & Out-of-Sequence Work Increased Number / Size of Crews Trade Stacking Overtime Work Shift Work

Productivity Loss

Late Responses to RFIs Late Responses to Change Order Requests Scope Changes

Secondary Causes Typical Owner-Caused

Administrative Problems

Late Precedence Work by Others Work Access Constraints Delayed Review and Approval of Contractor’s Submittals

Direct Man-Hour Growth Indirect Man-Hour Growth Increased Equipment & Materials Quantities

Typical Owner-Caused Procurement Problems

Improperly Tagged Equipment & Materials Late Owner-Furnished Equipment & Materials Misfabricated Owner-Furnished Equipment & Materials

Ultimate Effects

Typical Problems Beyond the Control of All Parties

Weather Impacts Labor Strikes

Allocation of Responsibility for Total Cost Overrun

Other Force Majeure Issues Owner EPC Contractor

$ 22,600,000 $ 14,400,000

Typical Contractor-Caused

Problems

Lack of Qualified Construction Labor Lack of Supervision Defective Construction Vendor / Supplier Delivery Delays Poor Planning and Scheduling Practices

Figure 1

Total Cost Overrun $ 37,000,000

000-13 C/E Matrix 1/10/08