Upload
others
View
21
Download
0
Embed Size (px)
Citation preview
2017 Construction CPM ConferenceRon Winter, PSP, FAACE
Schedule Analyzer Software
CPM CPM CPM CPM ACTIVITY ACTIVITY ACTIVITY ACTIVITY STATUSSTATUSSTATUSSTATUS
Ron Winter, PSP, FAACE
• Bachelor of Science in Engineering
• Construction Scheduler
• US Air Force Navigator
• Construction Scheduler
• Master of Science in Systems Management• Master of Science in Systems Management
• Programmer, Project Manager, Customer
Support, and Industrial Trainer
• Construction Scheduler
• Developer of Schedule Analyzer Software
2Construction CPM Conference
Introduction
• Documenting activity status really matters
• Improper or imprecise statusing often causes
problems
– Cause conflict between project stakeholders
– Affect critical path of project schedule– Affect critical path of project schedule
– Affect time and cost in delay situations
• Most CM textbooks devote very little space to
this subject
• Definitions of status needs to be standardized
• Rules for applying status needs to be developed
3Construction CPM Conference
Introduction
• Types of statusing problems
– Statused to have begun when not
– Failure to note actual start
– In-progress status incorrect
– Statused to have finished when not– Statused to have finished when not
– Failure to status as finished
– Changing or restating period status
– Disagreement on current status
4Construction CPM Conference
ACTIVITY STATUSACTIVITY STATUSACTIVITY STATUSACTIVITY STATUS5
Reasons to Update
• Reasons for Updating Status
– Reflect best estimate of project completion
– Maintain schedule’s usefulness as management tool
– Evaluate work procedures and performance– Evaluate work procedures and performance
– Contractual requirement
6Construction CPM Conference
Issues
Not Started In-Progress FinishedCompleted
Work
7Construction CPM Conference
− No Actual Start− No Actual Finish
− Actual Start− No Actual Finish
− Actual Start− Actual Finish
Projected
Work
Activity Start
• Two constraining forces to activity start
– Logical predecessors
• Hard constraint
• Soft constraint
– Administrative requirements– Administrative requirements
• Appropriate workers showing-up
• Required common materials and tools present
• Required minor tools and support equipment
• Access to the work area
• Availability of required utilities
• Useable plans
• Supervision 8Construction CPM Conference
In-Progress Activity
• Accurate knowledge of work scope is essential
to assess status
– If scope changes, then status can change non-linearly
• Work to be completed better understood
• Unexpected additional work discovered
• Damage to completed work
9Construction CPM Conference
Status In-Progress Act
• Numerically estimated using Remaining Duration
– Estimate made by working party
• Working party gets the benefit of doubt
• Can request backup verification if seriously in doubt
– Might be called Estimated Remaining Duration
• Planned productivity
• Current resource availability
– Uncouple the RD and Percent Complete to
track Cost Percent Complete
10Construction CPM Conference
Status In-Progress Act
• Using Percent Complete is problematic
– Some scheduling programs use Percent Complete
• Recommend converting RD into Percent Complete and inputting
– Can result in fractional days for RD
• Activity may start on the same day predecessor • Activity may start on the same day predecessor finishes
– Leaving PC at 99% to cover punchlist is poor
• If activity is substantially complete then 100%
• Retained logic can cause late starts for successors
• Confusing to view in Gantt Chart
• Typical retainage will cover the costs being tracked11Construction CPM Conference
Status Relationship Lag
• Activities experience non-linear progress
• Relationship lags typically based on time
• Status determination requires lag re-evaluation
• Other than remaining lag estimates,
– Activity statusing does not involve logic changes– Activity statusing does not involve logic changes
– Statusing the project involves logic changes
• Using Oracle® Primavera P6™, Start-to-Start
lags can be statused
– Based on Actual Start
– Based on Data Date
12Construction CPM Conference
Status Front-Loading
• Un-proportionally large status ‘earned’ at start
• Many do not allow this practice
– Progress payment is larger
• Reasons to front-load
– Fund small sub-contractor’s early outlays– Fund small sub-contractor’s early outlays
– Major equipment only compensated after install
• Reasons for uneven progress
– Learning curve
– Interruptible work
– Delays
13Construction CPM Conference
– Technical difficulties
– Varying manpower
Frequency of Statusing
• Open question that should be discussed
• Status at least as often as contractually required
reporting period
• More often than published involves
– Bad:– Bad:
• Wasted effort
• More chances to corrupt the schedule
– Good:
• Status is more accurate
• Status is more granular
• Allows for better productivity analysis14Construction CPM Conference
Frequency of Statusing
• Other than by contract, frequency depends on
– Occurrence of specific control events
– Degree of uncertainty
– Magnitude of the project
– Time to completion– Time to completion
– Troubles encountered
– PM’s ability to process updates
• Unplanned status updates occur when
– Unexpected revision in work sequence
– Delivery problems
– Change in activity duration estimates 15Construction CPM Conference
Status Involvement
• Absent contract language, contractor responsible
– May be just the contractor’s scheduler
– Better if both PMs, Suncontractors, and scheduler ‘walk the job’ together
• Agree on status
• Person responsible for work should estimate RD
– May involve superintendent of follow-on work
• How complete is necessary to begin next task
• Networked scheduling systems sometimes allow
for status updating by Primary Resource
– Someone responsible for allowing the update16Construction CPM Conference
Parts of Activity Status
17Construction CPM Conference
Parts of Activity Status
18Construction CPM Conference
Parts of Activity Status
19Construction CPM Conference
Parts of Activity Status
20Construction CPM Conference
Parts of Activity Status
21Construction CPM Conference
Parts of Activity Status
22Construction CPM Conference
Parts of Activity Status
23Construction CPM Conference
SCHEDULE UPDATE SCHEDULE UPDATE SCHEDULE UPDATE SCHEDULE UPDATE PROGRESSPROGRESSPROGRESSPROGRESS 24
Update Process
• Two types of schedule updates
– Status of planned work
– Revisions to schedule to indicate plan changes
• Status discrete activities from schedule
• Create Update Report from likely activities• Create Update Report from likely activities
– Sometimes called a Turnaround Document
• Status taken at the end of the workday
• Entire project statused at the same time
• Pictures of current progress very helpful
– Recommend annotating/narrating essential issues
25Construction CPM Conference
Comments IN a Picture
26Construction CPM Conference
Using Windows Explorer:
Properties / Details
Update Progress
• Design drawing status can be assessed
– Weighted drawing count
– Averaged base manhours per drawing
– Percent complete
– Status calculation– Status calculation
– Evaluation by discipline
– Evaluation of % complete of earned versus spent
• Activity pacing delays should be re-affirmed
• Verify status of deliveries with every update
– Critical deliveries may legally bind supplier
27Construction CPM Conference
Once Status is Taken
• Make a copy of current before updating
– Sometimes called Baseline Schedule
• Write a narrative or list of what was changed
• P6: Do not re-calculate until update is complete
– Early Start will change & update Planned Start– Early Start will change & update Planned Start
– Meaningless Planned Start date will be frozen
• Establish new Data Date
– First moment new/continuing work can begin
• Be careful when statusing resources
– Updating resources can change activities
28Construction CPM Conference
Update Progress
• Update and publish status as soon as possible
– Difficulty and cost of correcting increases with time
• May need to be revised and re-published after
review
• Process must be complete prior to next update• Process must be complete prior to next update
– Two sets of updates
29Construction CPM Conference
REVIEWING STATUSREVIEWING STATUSREVIEWING STATUSREVIEWING STATUS30
Reviewing Status
• Reviewer should verify status accuracy &
completeness
– Contractor’s estimate assumed accurate
– Reviewer can question individual instances
• Verify reasonability of actual dates• Verify reasonability of actual dates
– Especially out-of-sequence early starts
– Progress made without an Actual Start date
– Actual Start and Original = Remaining Duration
– 100% complete without Actual Finish date
• All suspended activities should be closely
reviewed31Construction CPM Conference
Reviewing Status
• Actual dates in the ‘future’
– Actual dates later than or equal to Data Date
– Incompatible for software using
• Oracle/Primavera P6™ Retained Logic setting
• P6 Progress Override setting• P6 Progress Override setting
– Less problematic for
• Microsoft Project™
• P6 Actual Dates software setting
• Actual Date equal to Data Date is ‘in the future’
– Should not be allowed
32Construction CPM Conference
Reviewing Status
• Be wary of negative progress
– Remaining Duration increases over last update
– Started activities become ‘unstarted’
– May legitimately be the result of
• Revised workplan or scope• Revised workplan or scope
• Better understanding the scope of work
• Delay or disruption
• Damage to existing work
– All cases should be explained in the narrative
33Construction CPM Conference
What About Delays?
• Non-scheduled status assessment upon Notice
of Potential Claim/Delay
• Status all near-critical activities, not just delayed
• Note any potential concurrent delay
• Accurate As-Built schedules essential for TIA’s• Accurate As-Built schedules essential for TIA’s
• Inaccurate As-Built dates will hamper later delay
analysis
– Actual dates verified at the time of the delay carries more weight than those researched later
34Construction CPM Conference
Confirming Status
• Jobsite photos• Meeting minutes• Inspection logs• Certified workhour
submittals• Emails
• Installed quantities reports
• Deficiency reports
• Material receiving logs
• Transmittal logs
• Drawing logs
35Construction CPM Conference
• Emails• Daily reports• Progress reports• Change Order files• Pay applications• Productivity reports
• Drawing logs
• Superintendent diaries
• Project correspondence
• Field notes & timeline data
• System turnover data
• Quantity records
PROJECT STATUSPROJECT STATUSPROJECT STATUSPROJECT STATUS36
Project Status
• Project status only available after activities are
statused
• Project status is latest computed,
– Early Finish date of all activities in the schedule
– Early Finish date Substantial Completion activity– Early Finish date Substantial Completion activity
• Compare this date with Baseline and last update
– Ahead of schedule
– On-Time
– Behind schedule
• Should maintain a Schedule Log
37Construction CPM Conference
Schedule Log Entries
• Project identification name
• Data date of the update
• Project’s planned completion date
• Current early finish date
• Project critical total float• Project critical total float
• Slippage/gain project critical TF from prior period
• Number of activities in the schedule update
• Location and name of data file or database
• Update identification number or version
• Date the schedule update submitted to owner
• Date the schedule update approved by owner38Construction CPM Conference
Conclusions
• Status adds complexity to scheduling
• Regular updates essential to keep schedule
current
• Statusing should follow rules for
– Accuracy– Accuracy
– Consistency
• Time and money saved if accuracy verified
contemporaneously
• Delay analysis depends on accurate status
• Project status only viable if statused correctly
39Construction CPM Conference
Questions?
Construction CPM Conference 40