1
document.xlsx Page 1 of 1 Contract No Title Modification of Ru158 CTR No 004 Scope demolition of the existing 3" Y-piece and installation 6" Y-piece accordingly Duration (days) 7 days MANPOWER PLANT & EQUIPMENT Item No Description Nationality Unit Rate Qty Duration Total Item No Description Unit Rate Qty Duration Total 1.1 Senior Pipeline Engineer(QAQC) $1,346.00 1 5 $ 6,730.00 Plant & Equipment 1.2 Senior Pipeline Engineer(HSE) $1,346.00 1 5 $ 6,730.00 2.1 Generator $ 796.49 2 5 $ 7,964.90 1.3 Senior Pipeline Engineer(Test E $1,346.00 1 1 $ 1,346.00 2.2 welding machine $ 289.00 4 5 $ 5,780.00 1.4 Welding Specialist Iraq $ 600.00 3 6 $ 10,800.00 2.3 Side boom $ 389.00 1 2 $ 778.00 1.5 Fabrication Engineer Iraq $ 500.00 2 5 $ 5,000.00 2.4 crane 25T $ 831.00 1 3 $ 2,493.00 1.6 Machining Foreman Iraq $ 500.00 4 4 $ 8,000.00 2.5 pipe cutter $ 255.00 1 4 $ 1,020.00 Pipeline Technical Iraq $ 340.00 2 3 $ 2,040.00 2.6 grinding machine $ 70.00 3 4 $ 840.00 2.7 Trailer $ 500.00 1 2 $ 1,000.00 2.8 Hiab crane $ 380.00 1 4 $ 1,520.00 2.9 High force torqueing system 20T $ 236.00 1 3 $ 708.00 2.10 Test Work Pack $ 4,300.00 1 1 $ 4,300.00 SUB-TOTAL $ 40,646.00 PSD SUPPORT / SECURITY Item No Description Unit Rate Qty Duration Total 4.1 - $3,600.00 1 9 $ 32,400.00 4.2 XXX - $ - $ - SUB-TOTAL $ 26,403.90 SUB-TOTAL $ 32,400.00 TRANSPORTATION AND MATERIAL STORAGE Item No Description Unit Rate Qty Duration Total Transportation and Material Storage MANPOWER TOTAL $ 40,646 3.1 XXX $ - $ - PSD SUPPORT / SECURITY $ 32,400 3.2 XXX $ - $ - PLANT & EQUIPMENT $ 26,404 TRANSPORTATION AND MATERIAL STORAGE $ - MATERIALS / CONSUMABLES / SUBCONTRACTORS $ - Total $ 99,450 SUB-TOTAL $ - MATERIALS / CONSUMABLES / SUBCONTRACTORS NOTES Item No Description Unit Rate Qty Total XXX Materials / Consumables / Sub-contractors 5.1 XXX $ - $ - 5.2 XXX $ - $ - SUB-TOTAL $ - CN101614 China China China Type 1 PSD (Security Team) - 4

CTR for Modification of RU158

Embed Size (px)

DESCRIPTION

RU158

Citation preview

Page 1: CTR for Modification of RU158

document.xlsx Page 1 of 1

Contract NoTitle Modification of Ru158CTR No 004Scope demolition of the existing 3" Y-piece and installation 6" Y-piece accordinglyDuration (days) 7 days

MANPOWER PLANT & EQUIPMENT

Item No Description Nationality Unit Rate Qty Duration Total Item No Description Unit Rate Qty Duration Total1.1 Senior Pipeline Engineer(QAQC) $ 1,346.00 1 5 $ 6,730.00 Plant & Equipment1.2 Senior Pipeline Engineer(HSE) $ 1,346.00 1 5 $ 6,730.00 2.1 Generator $ 796.49 2 5 $ 7,964.90 1.3 Senior Pipeline Engineer(Test Engineer) $ 1,346.00 1 1 $ 1,346.00 2.2 welding machine $ 289.00 4 5 $ 5,780.00 1.4 Welding Specialist Iraq $ 600.00 3 6 $ 10,800.00 2.3 Side boom $ 389.00 1 2 $ 778.00 1.5 Fabrication Engineer Iraq $ 500.00 2 5 $ 5,000.00 2.4 crane 25T $ 831.00 1 3 $ 2,493.00 1.6 Machining Foreman Iraq $ 500.00 4 4 $ 8,000.00 2.5 pipe cutter $ 255.00 1 4 $ 1,020.00

Pipeline Technical Iraq $ 340.00 2 3 $ 2,040.00 2.6 grinding machine $ 70.00 3 4 $ 840.00 2.7 Trailer $ 500.00 1 2 $ 1,000.00 2.8 Hiab crane $ 380.00 1 4 $ 1,520.00 2.9 High force torqueing system 20T $ 236.00 1 3 $ 708.00 2.10 Test Work Pack $ 4,300.00 1 1 $ 4,300.00

SUB-TOTAL $ 40,646.00

PSD SUPPORT / SECURITY

Item No Description Unit Rate Qty Duration Total4.1 - $ 3,600.00 1 9 $ 32,400.00 4.2 XXX - $ - $ -

SUB-TOTAL $ 26,403.90

SUB-TOTAL $ 32,400.00 TRANSPORTATION AND MATERIAL STORAGE

Item No Description Unit Rate Qty Duration TotalTransportation and Material Storage

MANPOWER TOTAL $ 40,646 3.1 XXX $ - $ - PSD SUPPORT / SECURITY $ 32,400 3.2 XXX $ - $ -

PLANT & EQUIPMENT $ 26,404 TRANSPORTATION AND MATERIAL STORAGE $ -

MATERIALS / CONSUMABLES / SUBCONTRACTORS $ -

Total $ 99,450 SUB-TOTAL $ -

MATERIALS / CONSUMABLES / SUBCONTRACTORS

NOTES Item No Description Unit Rate Qty TotalXXX Materials / Consumables / Sub-contractors

5.1 XXX $ - $ - 5.2 XXX $ - $ -

SUB-TOTAL $ -

CN101614

ChinaChinaChina

Type 1 PSD (Security Team) - 4 Client - refer to minimum