document.xlsx Page 1 of 1
Contract NoTitle Modification of Ru158CTR No 004Scope demolition of the existing 3" Y-piece and installation 6" Y-piece accordinglyDuration (days) 7 days
MANPOWER PLANT & EQUIPMENT
Item No Description Nationality Unit Rate Qty Duration Total Item No Description Unit Rate Qty Duration Total1.1 Senior Pipeline Engineer(QAQC) $ 1,346.00 1 5 $ 6,730.00 Plant & Equipment1.2 Senior Pipeline Engineer(HSE) $ 1,346.00 1 5 $ 6,730.00 2.1 Generator $ 796.49 2 5 $ 7,964.90 1.3 Senior Pipeline Engineer(Test Engineer) $ 1,346.00 1 1 $ 1,346.00 2.2 welding machine $ 289.00 4 5 $ 5,780.00 1.4 Welding Specialist Iraq $ 600.00 3 6 $ 10,800.00 2.3 Side boom $ 389.00 1 2 $ 778.00 1.5 Fabrication Engineer Iraq $ 500.00 2 5 $ 5,000.00 2.4 crane 25T $ 831.00 1 3 $ 2,493.00 1.6 Machining Foreman Iraq $ 500.00 4 4 $ 8,000.00 2.5 pipe cutter $ 255.00 1 4 $ 1,020.00
Pipeline Technical Iraq $ 340.00 2 3 $ 2,040.00 2.6 grinding machine $ 70.00 3 4 $ 840.00 2.7 Trailer $ 500.00 1 2 $ 1,000.00 2.8 Hiab crane $ 380.00 1 4 $ 1,520.00 2.9 High force torqueing system 20T $ 236.00 1 3 $ 708.00 2.10 Test Work Pack $ 4,300.00 1 1 $ 4,300.00
SUB-TOTAL $ 40,646.00
PSD SUPPORT / SECURITY
Item No Description Unit Rate Qty Duration Total4.1 - $ 3,600.00 1 9 $ 32,400.00 4.2 XXX - $ - $ -
SUB-TOTAL $ 26,403.90
SUB-TOTAL $ 32,400.00 TRANSPORTATION AND MATERIAL STORAGE
Item No Description Unit Rate Qty Duration TotalTransportation and Material Storage
MANPOWER TOTAL $ 40,646 3.1 XXX $ - $ - PSD SUPPORT / SECURITY $ 32,400 3.2 XXX $ - $ -
PLANT & EQUIPMENT $ 26,404 TRANSPORTATION AND MATERIAL STORAGE $ -
MATERIALS / CONSUMABLES / SUBCONTRACTORS $ -
Total $ 99,450 SUB-TOTAL $ -
MATERIALS / CONSUMABLES / SUBCONTRACTORS
NOTES Item No Description Unit Rate Qty TotalXXX Materials / Consumables / Sub-contractors
5.1 XXX $ - $ - 5.2 XXX $ - $ -
SUB-TOTAL $ -
CN101614
ChinaChinaChina
Type 1 PSD (Security Team) - 4 Client - refer to minimum