    C O U N T Y O F S A N D I E G O

    ovember 2014

    Las Colinas Detention and Reentry Facility

    Schedule : Sitework began summer 2012 forPhase 1 occupancy August 2014; Phase 2began fall 2014 for completion January 2016Scope: Construct 1,216 bed multi-custodywomen's detention campus on 45 acres,replacing the existing facility.Delivery: Design-Build: Balfour BeattyEst. Cost: $289.2 million project cost

    Capital Improvement Projects2014/15 - 2018/19

    Cedar and Kettner Development Parking Structure

    Schedule : Groundbreaking December 2013or completion summer 2015.

    Scope: Construct 10-level parking structureroviding approximately 650 spaces for County

    Administration Center staff.Delivery: Design-Build: McCarthy Building Co.Est. Cost: $36.1 million project cost

    County of San DiegoDepartment of General Services

    5560 Overland Avenue, Suite 410San Diego, CA 92123

    858.694.3610www.sdcounty.ca.gov/general_services

    Register for notication of solicitations athttp://buynet.sdcounty.ca.gov

    Alpine Branch Library

    Schedule : Contract award October 2014 forcompletion spring 2016Scope: Construct approx. 12,700 sq ft Zero NetEnergy Library to replace the 3,000 sq ft leasedfacility.Delivery: Design-Build: C.W. DriverEst. Cost: $9.2 million project cost

    County Administration Center Waterfront Park2014 Orchid Award-Urban Planning

    Boulevard Fire Station

    Schedule : Groundbreaking January 2014 forompletion spring 2015

    Scope: Construct 7,866 sq ft new re station withiving quarters and bays for 6 emergency vehicleso replace the existing shared facility.

    Delivery: Design-Build: Hunter Steel Constr. Co.Est. Cost: $3.5 million project cost

    Imperial Beach Branch Library

    Schedule : In procurement for contract awardwinter 2014/15 with completion spring 2016Scope: Demo existing facility and construct 12,000 SF building integrating with existing2,000 SF City community room.Delivery: Design-Build: In procurementEst. Cost: $9.1 million project cost

    2014 AIASD Merit Award-Interiors

    http://buynet.sdcounty.ca.gov/http://www.sdcounty.ca.gov/general_serviceshttp://buynet.sdcounty.ca.gov/http://www.sdcounty.ca.gov/general_services
  • 8/9/2019 Current Capital Project

    2/2

    C O U N T Y O F S A N D I E G O

    Department of General Services

    Planned and ProposedCapital Construction Opportunities

    FY2014/15 - 2018/19

    Additional information can be found at:City, County, Port Rotation - http://www.sandiego.gov/publicworks/about/contracting/consultant/rotationlist.shtmlCounty Operational Plan & Budget Information http://www.sdcounty.ca.gov/auditor/budinfo.html

    !"#$%& ()*+,%-"$. !*$%*+ / /01 (2*+3,$4 52*$#*6 7#-%* 891 7,$ : -*;"6 !5

    Project RFB/RFPForecast

    Scope Delivery Est ProjectCost

    County Operations Center -Crime Lab and Fleet Facility

    DDA; Fleet bldg/parking in design;select Crime LabGC, Architect

    Proposed 150,000 SF for CrimeLaboratory, Property and Evidence, andCentral Investigations staff; relocation ofFleet service facility, new parking structure

    DDA/Design-Build

    $104.8 million

    East County Regional CenterTIs and Window Replacement

    November 2014 7th floor tenant improvements, replacewindows 6th, 7th and 8th floors.

    CM at Risk $7.7 million

    North County CrisisResidential Health Facility

    Winter 2014/15 Design and construct new 6,500 SF shortterm residential building

    Design-Build Est. $4 million

    Pine Valley Fire Station Winter 2014/15 Design and construct new 4-bay building

    with sleeping quarters

    Design-Build Est. $4 million

    Assessor/Recorder/CountyClerk El Cajon Branch Office

    TBD; Currentlyin site acquisition

    Design and construct new 14-15,000 SFbuilding

    Design-Build TBD

    North Coastal Mental HealthCenter (Oceanside)

    TBD; Currentlyconfirmingprogram

    Design and construction of a peer-centered facility for recovery,rehabilitation, job screening/placement

    Design-Build TBD

    Borrego Springs Library TBD; Currentlyin site acquisition

    Acquire site, design and construct new14-15,000 SF building

    Design-Build Est. $9.9 million

    Cedar & Kettner DevelopmentProject

    RFP/RFB TBD Phase 2 private mixed use development ofthe Cedar & Kettner development site

    PrivateDevelopment

    N/A

    Regional CommunicationsSystem Replacement

    Varies by site Design, procure and install P25 NationalInteroperability Platform at various sites

    May vary by site TBD

    4S Ranch Library Expansion TBD; Currentlyin site acquisition

    Design and construct approx. 7,000 SFexpansion of existing facility

    CM at Risk TBD

    Job Order Contracting(JOC) & Consultants

    RFB/RFPForecast

    Scope Delivery Est Cost

    General, Mechanical/HVAC,various other specialty JOCs

    Periodicallythrough the year

    Provide general, engineering or specialtyconstruction services for County projects

    JOC Contract Up to$4,200,000

    Consulting Opportunities

    Board Policy F-40 allows use of the City, County and Port District Consultant Rotation List for qualified consultant services up to$1,000,000.These lists include architectural, construction and project management, various engineering and specialty professionalconsulting services.Also register on and monitor the Countys BuyNet - http://buynet.sdcounty.ca.gov - for new procurements. Such procurementsmay include architectural, engineering, construction and project management, commissioning, and other professional services.

    November 2014

    http://buynet.sdcounty.ca.gov/http://www.sdcounty.ca.gov/auditor/budinfo.htmlhttp://www.sandiego.gov/publicworks/about/contracting/consultant/rotationlist.shtml