Customer Meeting April 28, 2010 Torrington, WY

Customer Meeting April 28, 2010 Torrington, WY. Agenda Introductions Accomplishments Update on Torrington Area PVVC Overview PVVC Schedule and Cost Estimates

Embed Size (px)

Citation preview

Page 1: Customer Meeting April 28, 2010 Torrington, WY. Agenda Introductions Accomplishments Update on Torrington Area PVVC Overview PVVC Schedule and Cost Estimates

Customer MeetingApril 28, 2010

Torrington, WY

Page 2: Customer Meeting April 28, 2010 Torrington, WY. Agenda Introductions Accomplishments Update on Torrington Area PVVC Overview PVVC Schedule and Cost Estimates

AgendaIntroductionsAccomplishmentsUpdate on Torrington AreaPVVC OverviewPVVC Schedule and Cost EstimatesQuestions/CommentsWrap Up

Page 3: Customer Meeting April 28, 2010 Torrington, WY. Agenda Introductions Accomplishments Update on Torrington Area PVVC Overview PVVC Schedule and Cost Estimates

Accomplishments since 2003Whiterock Substation (2005)Lingle Tap (2003)Lyman-Yoder Tap (2005)McGrew area Caps (2005)Stored mobile transformer at Guernsey Rural

(2004)Wood Pole Testing and Treatment (2003 &

2004)Letter of Concurrence between Tri-State and

Western on Platte Valley conversion project (2005)

Glendo Substation Relay System & RTU replacement

Page 4: Customer Meeting April 28, 2010 Torrington, WY. Agenda Introductions Accomplishments Update on Torrington Area PVVC Overview PVVC Schedule and Cost Estimates

Accomplishment since 2003Gering Station Service Switchgear (2006)

Gering PCBs 162, 462, 966 replacement (2006)

Glendo PCB 524 (2006)

Limestone additions (PCB 442, new control & relay system, new RTU) (2009)

Repaired Mobile transformer and returned to Guernsey Rural (2009)

Page 5: Customer Meeting April 28, 2010 Torrington, WY. Agenda Introductions Accomplishments Update on Torrington Area PVVC Overview PVVC Schedule and Cost Estimates

Upcoming Projects (2008-2011)Torrington transformer KY2A addition (In-service

May 2010)

Gering-Gering Valley 34.5-kV rebuild (2011)

Page 6: Customer Meeting April 28, 2010 Torrington, WY. Agenda Introductions Accomplishments Update on Torrington Area PVVC Overview PVVC Schedule and Cost Estimates

Torrington KY2A additionProject to add 115/34.5-kV 50 MVA

transformerJoint project with City of TorringtonTransformer delivered - Oct 2008Construction contractor complete – Dec 2008Control Design & switchboard deliveredCommissioning ongoing

Page 7: Customer Meeting April 28, 2010 Torrington, WY. Agenda Introductions Accomplishments Update on Torrington Area PVVC Overview PVVC Schedule and Cost Estimates

Platte Valley Voltage ConversionThe objective of the Platte Valley Voltage

Conversion Project is to convert the operating voltage of the 34.5-kV transmission lines and related facilities between Lingle Substation and Sievers Rural Substation to 69-kV.

The lines were rebuilt in the early 90’s to 69-kV standard.

Page 8: Customer Meeting April 28, 2010 Torrington, WY. Agenda Introductions Accomplishments Update on Torrington Area PVVC Overview PVVC Schedule and Cost Estimates

Platte Valley Voltage ConversionThe majority of the work is converting the

numerous substations and taps along the line segments to 69-kV.

Western and Tri-State signed a Letter of Concurrence in November 2004 laying the initial scope and responsibilities for the upgrades.

Page 9: Customer Meeting April 28, 2010 Torrington, WY. Agenda Introductions Accomplishments Update on Torrington Area PVVC Overview PVVC Schedule and Cost Estimates

Platte Valley Voltage ConversionScope:Lingle Substation: Install a 115/69-kV 40 MVA

transformer and associated equipment.

Torrington Substation: Install a 69/34.5-kV 50 MVA transformer and associated equipment.

Sievers Rural Tap: Install a 69/34.5-kV 25 MVA transformer and associated equipment.

Construct eleven miles of new 69-kV line between East Morrill Tap and Sievers Rural Tap.

Page 10: Customer Meeting April 28, 2010 Torrington, WY. Agenda Introductions Accomplishments Update on Torrington Area PVVC Overview PVVC Schedule and Cost Estimates

Platte Valley Voltage ConversionScope (cont):Torrington Rural Tap: Replace transformer and

rebuild high side for 69-kV.

Henry Tap: Replace transformer and rebuild high side for 69-kV.

Village of Morrill Tap: Make necessary modifications to operate existing dual winding transformer at 69-kV.

Connect the Town of Lingle Tap to the Limestone-Lingle 34.5-kV line.

Page 11: Customer Meeting April 28, 2010 Torrington, WY. Agenda Introductions Accomplishments Update on Torrington Area PVVC Overview PVVC Schedule and Cost Estimates

Platte Valley Voltage ConversionScope (cont):

Estimated Cost: $21MPlanned ISD: FY2015Project Manager: Roy GearhartCurrent Status: Not planned to start until

FY2012. System Studies updated every two years. System Studies planned for 2010.

Page 12: Customer Meeting April 28, 2010 Torrington, WY. Agenda Introductions Accomplishments Update on Torrington Area PVVC Overview PVVC Schedule and Cost Estimates

Platte Valley Voltage ConversionMajor Milestones to date

Various System Studies: 2000-2010Meeting with Platte Valley Customers: April 2003Western and Tri-State signed Ltr of Concurrence:

November 2004Meeting with Platte Valley Customers: April 2005Meeting with Platte Valley Customers: April 2007

Published Platte Valley Voltage Conversion Project Overview: January 23, 2006

Page 13: Customer Meeting April 28, 2010 Torrington, WY. Agenda Introductions Accomplishments Update on Torrington Area PVVC Overview PVVC Schedule and Cost Estimates

Platte Valley Voltage ConversionLingle Substation

Scope:115kV/69kV 40MVA transformer with high and low side interrupters for protection.New Substation site required for 115/69kV additionsNew Control Building

Schedule: 2012-2015

Estimate: $4,730k (In 2014 $’s)

Page 14: Customer Meeting April 28, 2010 Torrington, WY. Agenda Introductions Accomplishments Update on Torrington Area PVVC Overview PVVC Schedule and Cost Estimates

Platte Valley Voltage ConversionLingle Town

Scope: Move connection to Limestone 34.5-kV line with ~0.5 mile of new 34.5-kV line.

Schedule: 2012-2015

Estimate: $100k - $200k (no detail estimate done)

Page 15: Customer Meeting April 28, 2010 Torrington, WY. Agenda Introductions Accomplishments Update on Torrington Area PVVC Overview PVVC Schedule and Cost Estimates

Platte Valley Voltage ConversionTorrington Rural

Scope:Convert to 69-kV with a 69kV/12.47kV 5MVA and a 69kV/24.9kV 7.5MVA transformers and 69kV improvements on high side.

Schedule: 2012-2015

Estimate: $1,500k (In 2014 $’s)

Page 16: Customer Meeting April 28, 2010 Torrington, WY. Agenda Introductions Accomplishments Update on Torrington Area PVVC Overview PVVC Schedule and Cost Estimates

Platte Valley Voltage ConversionTorrington Substation

Scope:New 69-kV yard with 4–69kV bays; 69kV/34.5kV 50MVA Transformer; New Control Building; more land.

Schedule: 2012-2015

Estimate: $5,400k (In 2014 $’s)

Page 17: Customer Meeting April 28, 2010 Torrington, WY. Agenda Introductions Accomplishments Update on Torrington Area PVVC Overview PVVC Schedule and Cost Estimates

Platte Valley Voltage ConversionHenry

Scope:Convert to 69-kV with a 69kV/12.47kV 7.5MVA transformer and 69kV improvements on high side.

Schedule: 2012-2015

Estimate: $900k (In 2014 $’s)

Page 18: Customer Meeting April 28, 2010 Torrington, WY. Agenda Introductions Accomplishments Update on Torrington Area PVVC Overview PVVC Schedule and Cost Estimates

Platte Valley Voltage ConversionVillage of Morrill

Scope:Convert to 69-kV high side winding on existing 34.5/69/7.2/12.47kV 2.5MVA transformer and 69kV improvements on high side.

Schedule: 2012-2015

Estimate: No estimate done

Page 19: Customer Meeting April 28, 2010 Torrington, WY. Agenda Introductions Accomplishments Update on Torrington Area PVVC Overview PVVC Schedule and Cost Estimates

Platte Valley Voltage ConversionEast Morrill Tap – Wildcat 69-kV line

Scope:Construct ~3 miles of new 69-kV line from East Morrill tap to Wildcat. Creates the Lyman-Wildcat 34.5-kV line. Allows Village of Lyman and Lyman Rural loads to remain 34.5-kV

Schedule: 2012-2015

Estimate: $1,395k (in 2012 $’s)

Page 20: Customer Meeting April 28, 2010 Torrington, WY. Agenda Introductions Accomplishments Update on Torrington Area PVVC Overview PVVC Schedule and Cost Estimates

Platte Valley Voltage ConversionWildcat Substation

Scope:No new additions initially planned at Wildcat. Should the system needs change, the new Torrington-Sievers Rural 69-kV line could be interconnected with the 34.5-kV system at Wildcat to provide system reliability improvements.

Page 21: Customer Meeting April 28, 2010 Torrington, WY. Agenda Introductions Accomplishments Update on Torrington Area PVVC Overview PVVC Schedule and Cost Estimates

Platte Valley Voltage ConversionWildcat-Sievers Rural 69-kV line

Scope:Construct a new 10 mile 69-kV line between Wildcat and Sievers Rural to bypass Mitchell area.

Bypasses City of Mitchell and Mitchell Rural loads, leaving them at 34.5-kV

Schedule: 2012-2015

Estimate: $4,045K

Page 22: Customer Meeting April 28, 2010 Torrington, WY. Agenda Introductions Accomplishments Update on Torrington Area PVVC Overview PVVC Schedule and Cost Estimates

Platte Valley Voltage ConversionSievers Rural

Scope:69/34.5kV 20 MVA transformer with high and low side protection; new control building; land.

Sievers Rural load remains served at 34.5-kV.

Schedule: 2012-2015

Estimate: $2,250k (In 2014 $’s)

Page 23: Customer Meeting April 28, 2010 Torrington, WY. Agenda Introductions Accomplishments Update on Torrington Area PVVC Overview PVVC Schedule and Cost Estimates

Wrap UpQuestions or Comments?

Page 24: Customer Meeting April 28, 2010 Torrington, WY. Agenda Introductions Accomplishments Update on Torrington Area PVVC Overview PVVC Schedule and Cost Estimates