PSDS DELIVERY & EQUIPMENT LIFTING PLAN

FOR TAMAN CUEPACS STATION

PACKAGE S6 : CONSTRUCTION AND COMPLETION OF ELEVATED STATIONS AND OTHER ASSOCIATED WORKS AT TAMAN SUNTEX, TAMAN CUEPACS AND BANDAR

TUN HUSSIEN ONN

ACCESS AND ENTRANCE

ENTRANCEACCESS TO STATION

ENTRANCE AT PIER 95 - 96

LIST OF EQUIPMENT

LIFTING PLAN

LIFT UP USING ROUGH TERRAIN 25 TONNE CRANE TADANO TR-250M

CRANE ON TOP OF VIADUCT AND PARKING ADJACENT TO EQUIPMENT ROOM

LOW LOADER WILL PARK AT GRAND SAGA SLIP ROAD BELOW STATION

THE HEAVY EQUIPMENT TO LIFT UP – BUS TIE FEEDER (2.325 TONNE)

ROUGH TERRAIN CRANE TADANO TR-250M

WORKING RADIUS

DIMENSIONS

CRANE POSITION

PLATFORM SB

PLATFORM NB

DELIVERY DATE

PACKAGE S6 : CONSTRUCTION AND COMPLETION OF ELEVATED STATIONS AND OTHER ASSOCIATED WORKS AT TAMAN SUNTEX, TAMAN CUEPACS AND BANDAR

TUN HUSSIEN ONN

ONE DAYFIRST LIFT SOUTH BOUND ROOM (PLATFORM)NEXT NORTH BOUND ROOM (PLATFORM) TENTATIVE DATE; 26/8/2015 & 27/8/2015LIFTING UP START 10.00PM