Upload
claudiotomas
View
221
Download
0
Embed Size (px)
Citation preview
8/6/2019 Description of the Proposed Wharf Facility
http://slidepdf.com/reader/full/description-of-the-proposed-wharf-facility 1/10
9. Description of the Proposed Wharf Facility
This chapter provides information about the potential impacts of the construction and operation of the
wharf facility. These potential impacts have been assessed using the impact assessment methodology
described in Volume 1. Details on the wharf facility design are derived from Maunsell (2005), which is in
Appendix 47, Volume 15.
9.1 Introduction
A key component of the proposal is to construct and operate a wharf facility. The proposed facility is
required to meet specific design criteria to facilitate the most cost effective method proposed for pulpstorage, handling and dispatch to market.
The proposed wharf will be situated on the Tamar River adjacent to the pulp mill. The facility will be
located on the east bank of the Tamar River, north of Dirty Bay and south of Big Bay in Long Reach
(Figure 9-1).
9.2 Infrastructure and Services
9.2.1 Wharf Infrastructure
The wharf facility has a service life of 50 years and will be designed, constructed and operated to
accommodate:
mooring of purpose built pulp freighters with capacity of up to 65,000 dead weight tonnage (dwt) and
a range of general cargo and container carriers with capacity of up to 50,000 dwt (Table 9.1);
dispatch and transport of pulp product from the warehouse/terminal using 64 tonne pay load flat deck
tractor trailers along side of the berthed self loading vessels;
receipt and handling of heavy plant and equipment for the pulp mill during the construction period;
and
receipt and handling of equipment by mobile cranes (one 400 tonne mobile crane and two 100 tonne
mobile cranes) required for ongoing pulp mill operations on a periodic basis. The facility will also be
able to accommodate a portainer crane as an option.
These requirements will be satisfied with the following proposed wharf specifications:
Loading quay (wharf deck) is 224m long;
Wharf deck level of RL+5m;
Depth along berthing face to allow for vessel draft of 13m;
The width of the quay allows tractor trailers to pass each other. The adopted width of the quay is 20m;
The width of the approach trestles is 10m; and
Heavy lift bay to facilitate operation of mobile cranes as required.
Volume 2: Page 9-610
32/11709/IIS_Volume 2 Draft Integrated Impact SatementBell Bay Pulp Mill
8/6/2019 Description of the Proposed Wharf Facility
http://slidepdf.com/reader/full/description-of-the-proposed-wharf-facility 2/10
The facility is required to cater for Open Hatch Bulk Carriers (OHBC), Container vessels and Gearbulk
vessels (General Cargo vessels). In addition to these, the facility is also required to accommodatebarges. Details of the vessels considered in the design are noted below:
Table 164: Size Class Vessels to Use the Proposed Wharf Facility
Max Vessel Min Vessel BargeType
OHBC
Star “O” Class
Gearbulk Vessel Heavy Plant
and Equipment
Barge
Bell Bay Port No 4
Barge
Dead Weight Tonnage
(dwt)
65,000 t 5,000 - 50,000 t - -
Length OA 230 m 105 m – 230 m 50 m 24.4 m
Beam 32.26 m 15.8 m - 32 m 15 m 7.8 m
Laden Draught 12.02 m 6.4 m -12 m 3 m 1.66 m
Laden Freeboard 4.5 m 2.7 m – 4.5 m 0.5 m 0.5 m
Source: Maunsell Aecom, 2005.
The proposed wharf (Figure 9-1) will extend into the Tamar River approximately 185 m from the high tide
mark. This is necessary to achieve the required draft of RL -13 m. Situating the wharf at this location
prevents the need for dredging that would otherwise be necessary to accommodate the required draft of
the OHBC Star “O” Class and Gearbulk vessels at berth (Figure 9-2). Photographic Sheet 9-1 shows
typical shipping configuration for loading such vessels.
It is anticipated that maintenance dredging of the deep - water berth will not be required throughout the
life of the facility.
Volume 2: Page 9-611
32/11709/IIS_Volume 2 Draft Integrated Impact SatementBell Bay Pulp Mill
8/6/2019 Description of the Proposed Wharf Facility
http://slidepdf.com/reader/full/description-of-the-proposed-wharf-facility 3/10
G
U N N S L I M I T E D
F O R
I N F
O R M A T I O N
O N L Y
F i g u r e
9 - 1
8/6/2019 Description of the Proposed Wharf Facility
http://slidepdf.com/reader/full/description-of-the-proposed-wharf-facility 4/10
G
U N N S L I M I T E D
F O R
I N F
O R M A T I O N
O N L Y
F
i g u r e
9 - 2
8/6/2019 Description of the Proposed Wharf Facility
http://slidepdf.com/reader/full/description-of-the-proposed-wharf-facility 5/10
Photographic Sheet 9-1. OHBC Star “O” Class vessel loading
8/6/2019 Description of the Proposed Wharf Facility
http://slidepdf.com/reader/full/description-of-the-proposed-wharf-facility 6/10
9.2.2 Ship Loading
The design vessel (OHBC) is self loading and will not be moved during loading. The vessel includes two
overhead gantries that may load the ship simultaneously.
Based on a laden draft of 12.02m, it is proposed that a minimum underkeel clearance of 1m be adopted.
A minimum of 13m depth for the maximum design vessel will thus be required below lowest astronomical
tide (LAT): thus the seabed level adjacent to the wharf face is to be RL-13m or lower.
9.2.3 Pulp Storage Warehouse
The primary building constructed in association with the wharf facility is the proposed pulp storagewarehouse. This facility will be 14.0 metres high, will have a floor space of 20,000 m
2, and, once
completed, up to 50,000 tonne of pulp will be stored here prior to dispatch to market. This facility will be
designed to maximise materials storage, handling and dispatch efficiency from the warehouse to the
loading gantry.
The building will be founded on reinforced cast-in-situ concrete foundations on ground. The floor slabs
will be power floated and treated with protective coating as required.
The lightweight roof structures will be constructed of galvanized anti condensate profiled steel sheets on
the galvanized roof purlins.
Storage will be ventilated by natural ventilation consisting of ridge ventilators and wall mounted grilledopenings.
The lower parts of the external walls will be constructed of block work or prefabricated concrete panels.
The upper parts of the external walls will be built using:
Galvanized structural steel z-purlins fixed to the columns; and
Vertical profiled, PVF2 finished, steel sheeting according to the detailed design.
9.2.4 Design Loads
Cargo
The OHBC and Gearbulk vessels will carry pulp stacks, organised into 32 tonne units. It is anticipated
that the units will be stacked and stored in a warehouse adjacent to the wharf. The stacking of units will
be carried out using forklifts, and transportation of pulp to the wharf/terminal will be by tractors and
trailers.
Terminal Tractor and Trailer Loads
Terminal tractors and trailers will be loaded such that the maximum total combined load of a single
tractor trailer will be 90 to 100 tonnes. The trailers will be approximately 3.6 m wide, have three axles
and be designed to support 64 tonnes (2 pulp units). The terminal tractor trailers will be similar to the
Kalmar terminal tractor trailers, used in Australian ports.
Volume 2: Page 9-615
32/11709/IIS_Volume 2 Draft Integrated Impact SatementBell Bay Pulp Mill
8/6/2019 Description of the Proposed Wharf Facility
http://slidepdf.com/reader/full/description-of-the-proposed-wharf-facility 7/10
The terminal export operations considered involve the continuous shuttling of pulp units to the wharf
where they are loaded onto the vessel by the ships gear.
Other Material Loads
Salt will be unloaded from the Gearbulk vessels and either unloaded into truck loading hoppers or placed
directly on the deck by retrieval by front end loaders into trucks.
Measures will be required to address potential structure durability issues that will arise from this
operation.
Cranes
The wharf site will be used as a staging point for the importation of select equipment during theconstruction of the new pulp mill. The size of some of this equipment impedes its transportation by road,
and the new wharf will therefore receive such items. It is expected that this gear will be brought onto site
by barge and unloaded off the barge at the wharf with the use of mobile cranes. Mobile cranes will also
be used for the occasional unloading of heavy cargo from vessels once the wharf is operational.
Allowance has been made for a heavy lift bay to facilitate the operation of these mobile cranes.
Wharf and storage warehouse construction
Construction of the proposed wharf facility will be a staged process over a 14-month period, which will
commence immediately after receipt of project approval. A preliminary design feasibility study
undertaken by Maunsell Aecom (2005) indicates that the preferred option is a piled deck with approach
bridges.
This option comprises a complete suspended structure on piles and two mooring dolphins. The
suspended structure consists of two approach trestles each approximately 10 metres wide and 95
metres long and a wharf deck, 20 metres wide and 224 metres long respectively. Generally, this
suspended structure consists of an in-situ reinforced concrete deck on prestressed concrete planks
supported by precast concrete headstocks.
The facility’s mooring dolphins (approximately 4 metres x 4 metres in dimension and supported on piles)
will be positioned upstream and downstream of the wharf deck with an offset of approximately 30 metres
from the approach trestles and a setback of 10 metres from the berthing face. Catwalks will provide
access to the dolphins.
A site specific geotechnical investigation has been undertaken for the proposed wharf facility. The
geotechnical investigation has discovered considerable depth of sediments (up to 40m) overlying dolerite
rock.
Pile size and pile bent spacings for the wharf were adopted after consideration of the geotechnical
conditions encountered on-site. Steel tubular piles 760 mm diameter with bent spacings reduced to 6 m
will be used. The total thickness of the deck will be 450 mm.
It is estimated that completion of bulk earthworks activities associated with the construction of the
storage warehouse will occur within five months of commencement. Within twelve months into the overall
project 26-month construction period, sections of the wharf will be completed to enable receipt of heavy
Volume 2: Page 9-616
32/11709/IIS_Volume 2 Draft Integrated Impact SatementBell Bay Pulp Mill
8/6/2019 Description of the Proposed Wharf Facility
http://slidepdf.com/reader/full/description-of-the-proposed-wharf-facility 8/10
lift plant and equipment required for the construction of the pulp mill. This equipment will be transported
from the wharf to the pulp mill construction site.
Plant and equipment deployed on-site during the wharf construction will include dump trucks, bulldozers,
excavators, vibrating rollers, pile drivers, drilling rigs, barges, tenders, concrete pumps, mobile cranes
and concrete trucks.
9.2.5 Services
Water Supply
Potable water will be provided on the wharf. A non-potable water main will also be installed on the wharf
for deck and hopper wash down and fire fighting. An approved (by the Fire Brigade) 150 diameter main,will need to be provided with hydrants at 60m centres for adequate coverage. Both potable and non-
potable water services on the wharf will be connected to water mains on land.
Sewerage
Domestic sewerage facilities will be required at the wharf facility. This service will be integrated into the
proposed sewer system associated with the pulp mill.
Lighting
General operational lighting on wharf for trucking operations and on mooring dolphins for line handling
will be required. For the purposes of reducing potential impact on neighbouring properties, lighting will
be baffled as required. Cope lighting will also be provided along the berthing face of the wharf.
Electricity
General power will be provided on the wharf. General Purpose Outlets (GPOs) will be positioned along
the wharf approximately every 40 metres.
Stormwater
Kerb and guttering will be provided and a stormwater system will be provided to drain the facility. The
stormwater system will comprise stormwater pits on the working platform and approach trestles whichwill drain into Gross Pollutant Traps (GPT) installed on the wharf (suspended off the deck) or installed on
land. The water is subsequently pumped to the effluent treatment plant.
Natural Gas
Natural gas will not be required at this facility.
Telecommunications
Telecommunications services will be installed in the warehouse and at other locations on the wharf
facility as required.
Volume 2: Page 9-617
32/11709/IIS_Volume 2 Draft Integrated Impact SatementBell Bay Pulp Mill
8/6/2019 Description of the Proposed Wharf Facility
http://slidepdf.com/reader/full/description-of-the-proposed-wharf-facility 9/10
9.2.6 Containment of Hazardous Materials
Hazardous materials including liquid caustic soda, sulphuric acid bullets, and salt will be handled in a
specified bunded area on the wharf. The bunded areas will drain into a GPT through valves, installed on
the deck, which will be open when chemicals and other hazardous materials are not being handled. At
times when chemicals are being handled, these valves will be locked shut to guard against the possibility
of a spill into the stormwater system and to contain the spill in the bund.
Pipework will be provided on the wharf to allow for the pumping of caustic soda from the vessel to a tank
and transfer pump on the reclaimed land. The caustic transfer pipe outside the bunded area will be
installed inside a second outer pipe for safety and for containment of any leak should this occur.
Potable water will be provided on the wharf for a safety shower and eyewash for emergency washdown.
Salt handling operations will occur on the wharf and run off from this area will be through the stormwater
system into a GPT as for normal stormwater.
9.3 Design Options
9.3.1 Portainer Crane Option
Containers may also be utilised in the future for the transportation of pulp and, as a result, a portainer
crane option has been considered. The portainer crane option is based on the preferred wharf option
(piled deck with approach bridges) with additional crane beams and intermediate piles being introducedto support crane loads and tie down. Other modifications to the preferred option include the provision of
a crane maintenance area.
For the portainer crane operation, the necessary wharf modifications are considered in two stages. Stage
1 includes works that are built into the wharf at the time of initial construction. Implementing the Stage 1
works will reduce the cost of those items that will be difficult to build into the facility at a later time. Stage
2 includes works that can be deferred until a later time without the need for significant modification of the
constructed wharf.
For the size of vessels using the facility (up to 65,000 dwt) the overall hatch coverage length is
approximately 150m. With buffers placed clear of the approach road, the coverage of the crane will be
177m (224m-20m-27m).
It is anticipated that the rail mounted ship to shore crane will be as detailed in Table 165.
Volume 2: Page 9-618
32/11709/IIS_Volume 2 Draft Integrated Impact SatementBell Bay Pulp Mill
8/6/2019 Description of the Proposed Wharf Facility
http://slidepdf.com/reader/full/description-of-the-proposed-wharf-facility 10/10
Table 165: Typical Portainer Crane Dimensions and Loading
General Dimensions
Rail Gauge 25.4m
Length of crane between buffers 27m
Reach 40m
Distance between wheel bogie centrelines 12m
Loading
Wheels per leg 8 no.
Distance between wheels 1m
Load per wheel 60 tonnes
9.3.2 Modifications due to Portainer Crane Requirements
The modifications to the wharf facility include the addition of 2 crane beams (front and rear), extra piles to
support the crane loads and a crane maintenance area as shown in Sketch 20024505 - 007 in Appendix
47, Volume 15.
The Portainer Crane could be installed some time after commissioning of the wharf and thus only the
front crane beam will be provided in the initial construction (Stage 1). The front crane beam will beconstructed along the front row of piles, the front row piles will be 914OD.
The rear crane beam could be built as Stage 2 and prior to the commissioning of the Portainer Crane
and its construction could be carried out from the existing deck.
9.3.3 Heavy Lift Area
A heavy lift area will give greater flexibility in operation of the wharf. This heavy lift area will be used
initially for the unloading of large/heavy equipment brought by ship or barge (required for the construction
of the mill) and once the wharf is operational, be used for the occasional unloading of heavy cargo from
vessels.
The heavy lift area will consist of supplementary parallel RC beams that will be installed in the mid
section of the wharf. The heavy lift area will be located as shown in the drawings in Appendix 47,
Volume 15.
Volume 2: Page 9-619
32/11709/IIS_Volume 2 Draft Integrated Impact SatementBell Bay Pulp Mill