Dr Khairuddin Abdul Rashid
1
Session 2
PWD Form DB/T (2002)
Articles of AgreementArticles of Agreement
Conditions of Contract
Clause 1 – 15
Dr Khairuddin Abdul Rashid
2
PWD Form DB/T 2002
Prepared by a Technical Committee set up in 1996
Chair – JKRChair – JKR
Members – representatives from JKR, JPS, DBKL, JPN, KKR, Treasury and MAMPU
1st – 2000
2nd Edition – 2002
Dr Khairuddin Abdul Rashid
3
PWD Form DB/T 2002
Contents
� Articles of Agreement
� First to Fourth Recital� First to Fourth Recital
� Article 1 to 4
� Conditions of Contract
� Clause 1 to 58
� Special Conditions Clause
59 to 62
� Appendices
Dr Khairuddin Abdul Rashid
4
PWD Form DB/T 2002
Subsidiary forms
� Form of Tender PWD Form
DB/T-A2002
� Addendum No 1 (Amendments
no. 1 to 10)
� Addendum No 2 (Amendments
no. 1 to 25) for Deferred
Payment only
Also a guide on the use of the form
Dr Khairuddin Abdul Rashid
5
PWD Form DB/T 2002
Salient points
� Old concepts
Turnkey – contractor design &
supervise
D & B – contractor design,
JKR supervise
� New concepts
Turnkey – contractor design,
supervise & equipt
D & B – contractor design &
supervise
Dr Khairuddin Abdul Rashid
6
PWD Form DB/T 2002
Salient points
� Design bond no longer required
� DLP 24 months
� 30% Bumi participation
� Bumi consultants only if project value <RM50 m<RM50 m
� Bumi + Non-Bumi JV of local consultants if project value >RM50 m
� Direct payment to contractor’s consultants
� Used when:
No expertise in JKR
Specialist design
Emergency
� Requires Treasury’s approval if to be called on direct negotiation or selective tender
Dr Khairuddin Abdul Rashid
7
PWD Form DB/T 2002
Articles of Agreement
� Contract No / Expenditure
� Date of signing
� Parties – Government & the � Parties – Government & the contractor
� 1st Recital – project title
� 2nd Recital – Contractor’s Proposal
� 3rd Recital – Contract Sum Analysis
� 4th Recital – meeting the Government’s requirements
Dr Khairuddin Abdul Rashid
8
PWD Form DB/T 2002
Articles of Agreement
� Article 1 – Contractor agrees to
design and construct
� Article 2 – Government agrees
to pay … Contract Sum
� Article 3 – Government’s
requirements, the Contractor’s
Proposal, the Contract Sum
Analysis, the Contract
Schedule of Rates… signed
and appended
Dr Khairuddin Abdul Rashid
9
PWD Form DB/T 2002
Articles of Agreement
� Article 4 – Contract documents
i. Articles of Agreement
ii. Conditions of Contract and ii. Conditions of Contract and
Appendices
iii. Government’s Requirements
iv. Contractor’s Proposal
v. Contract Sum Analysis
vi. Schedule of Rates
vii. Form of Tender
viii. Letter of Acceptance
Dr Khairuddin Abdul Rashid
10
PWD Form DB/T 2002
Articles of Agreement
� Signature of parties
i. Contractor and witness
ii. Government and witness
Dr Khairuddin Abdul Rashid
11
PWD Form DB/T 2002
Conditions of Contract
Clause 1
� Interpretation, definitions
� Reference to clauses of the
conditions
� Documents read as a whole
� Definitions – see Cl. 1.3 (a) to (r),
p1-3
� New sub-clauses (s) to (x) on
‘deferred payment’
Dr Khairuddin Abdul Rashid
12
PWD Form DB/T 2002
Conditions of Contract
Clause 2 Contractor’s Obligations
Key obligations
� Cl. 2.1(a) Design, construct
and complete the works
� Cl. 2.2 Fully responsible for
the design, execution and
maintenance and guarantee
the Government
� Cl. 2.3.2 Novation
� Cl. 2.4.1 QA System
Dr Khairuddin Abdul Rashid
13
PWD Form DB/T 2002
Conditions of Contract
Clause 2 Contractor’s Obligations
Key obligations
Cl. 2.7.1 Care of the works up to Practical Completion or Partial Practical Completion or Partial Occupation subject to Cl. 2.7.2 (a) to (f) ‘excepted risks’
� Cl. 2.9 Employ local, regd consultants (PD’s consent)
� Cl. 2.10 Engage Bumiputera as sub-contractors (30% [40%] of CS)
� Cl. 2.11 Submit programme
Dr Khairuddin Abdul Rashid
14
PWD Form DB/T 2002
Conditions of Contract
Clause 3 PD’s Rights to Take
Action
� Cl. 3 (i) any matter related to:� Cl. 3 (i) any matter related to:
� Cl. 40 (mutual termination)
� Cl. 45 (Delay and EoT)
� Cl. 54 (Determination)
� Cl. 55 (War or Earthquake) or
� Cl. 56 (Arbitration)
is reserved for the Officer
named in Appendix 1
Dr Khairuddin Abdul Rashid
15
PWD Form DB/T 2002
Conditions of Contract
� Clause 3 (ii) PD’s rights to
issue instructions requiring a
variation under Cl. 27.2 is
subject to the financial limits as subject to the financial limits as
set out in Appendix 1
(Treasury Instructions 202)
Dr Khairuddin Abdul Rashid
16
PWD Form DB/T 2002
Conditions of Contract
Clause 4 PD’s Instructions
� Cl 4.3 must be in writing
� Cl. 4.1 Contractor shall comply
in 7 days… see Cl 4.2 (non-
compliance), Cl. 27.1
(contractor object with reasons)
� Cl. 4.2 If within 7 days, the
contractor fails to comply, PD
may employ and pay others
(deduct monies due to the
contractor)
Dr Khairuddin Abdul Rashid
17
PWD Form DB/T 2002
Conditions of Contract
Clause 5 Notices
� Cl. 5 Written notices to be left
at the contractor’s office on at the contractor’s office on
site, to be confirmed by his PM
or send to contractor’s place of
business
Dr Khairuddin Abdul Rashid
18
PWD Form DB/T 2002
Conditions of Contract
Clause 6 Contract Documents
� Cl. 6.1 PD keeps the original copy, contractor keeps the copy, contractor keeps the duplicate copy
� Cl. 6.2 Contractor submit 8 certified copies, Cl 6.3 2 copies of drawings, etc, Cl. 6.4 one copy of contract documents keep at the site
� Cl. 6.5 On completion contractor to submit as built drawings
Dr Khairuddin Abdul Rashid
19
PWD Form DB/T 2002
Conditions of Contract
Clause 7 Sufficiency of Contract
Documents
� Cl. 7.1 Contractor to provide � Cl. 7.1 Contractor to provide
everything necessary…
� Cl. 7.2 the Articles of
Agreement, the Conditions and
the Appendices shall prevail
over other documents… any
ambiguity/discrepancy to refer
to PD, contractor to rectify at
his own cost
Dr Khairuddin Abdul Rashid
20
PWD Form DB/T 2002
Conditions of Contract
Clause 7 Sufficiency of Contract
Documents
� Cl. 7.3.1 (a) and (b) Documents � Cl. 7.3.1 (a) and (b) Documents
are mutually explanatory…
between the Government’s
Requirements and the
Contractor’s Proposal, the
former prevails
Dr Khairuddin Abdul Rashid
21
PWD Form DB/T 2002
Conditions of Contract
Clause 8 Materials, Goods and
Workmanship
� Cl. 8.1 the works shall be in � Cl. 8.1 the works shall be in
accordance to the contract
� Cl. 8.4 contractor to carry out
checks and tests
� Cl 8.5 PD may issue
instructions to remove from the
site or rectify any work,
materials… not in accordance
to the contract
Dr Khairuddin Abdul Rashid
22
PWD Form DB/T 2002
Conditions of Contract
Clause 9 Restriction and Procedure
on Use of Imported Materials
and Goods
� Cl. 9.1 Malaysian materials and
goods only
� Cl. 9.2 Imported materials, etc
can only be used if approved
by the Government
Dr Khairuddin Abdul Rashid
23
PWD Form DB/T 2002
Conditions of Contract
Clause 10 Construction Plan,
Equipment, Vehicles and
Machineries
The contractor is responsible and
shall pay all port dues, prepare
and submit all documents and
abide by the requirements of
the relevant authorities, pay all
charges and expenses and
supply a list to the PD
Dr Khairuddin Abdul Rashid
24
PWD Form DB/T 2002
Conditions of Contract
Clause 11 Non-removal of
Materials and Equipment on
Site
Equipment, temporary works,
materials… intended for the
works can only be removed
from the site with the written
consent of the PD
Dr Khairuddin Abdul Rashid
25
PWD Form DB/T 2002
Conditions of Contract
Clause 12 Statutory obligations,
notices, fees and charges
� Cl. 12.1.1 The contractor shall � Cl. 12.1.1 The contractor shall
comply with statutory
requirements
� Cl. 12.2 The Contractor shall
pay/indemnify the Government
against liability of any fees,
charges…
Dr Khairuddin Abdul Rashid
26
PWD Form DB/T 2002
Conditions of Contract
Clause 12 Statutory obligations,
notices, fees and charges
� Cl. 12.1.2 Divergence to be � Cl. 12.1.2 Divergence to be
brought to attention; the
contractor shall propose
amendments (in case of
emergency see Cl. 12.1.3) and
with the PD’s consent carry out
the works at his own cost
(subject to Cl. 12.3)
Dr Khairuddin Abdul Rashid
27
PWD Form DB/T 2002
Conditions of Contract
Clause 12 Statutory obligations,
notices, fees and charges
� Cl. 12.3.1 and 12.3.2 Variation � Cl. 12.3.1 and 12.3.2 Variation
in the statutory requirements /
conformity with terms of an
authority’s approval after date
of tender leading to amendment
to contractor’s proposal is
treated as an instruction of the
PD affecting a Variation under
Cl. 27.2
Dr Khairuddin Abdul Rashid
28
PWD Form DB/T 2002
Conditions of Contract
Clause 13 Custom Dues and
Taxation
� Cl. 13.1 – 13.3 The contractor � Cl. 13.1 – 13.3 The contractor
to pay all duties and taxes and
make arrangement for their
employees to pay income tax
Dr Khairuddin Abdul Rashid
29
PWD Form DB/T 2002
Conditions of Contract
Clause 14 Antiquities
� Cl. 14.1 found on the site
becomes the property of the becomes the property of the
Government. The contractor
shall not disturb, preserve the
findings, and inform the PD
� Cl. 14.2 PD shall issue
instruction
� Cl. 14.3 Compliance with 14.2
may lead to reimbursement for
loss and or/expense
Dr Khairuddin Abdul Rashid
30
PWD Form DB/T 2002
Conditions of Contract
Clause 15 Copyright, royalties and
patent rights
� Cl. 15.1 The contractor is � Cl. 15.1 The contractor is
responsible for payment of all
royalties or other sums … of
any patented articles, etc in
respect of the works other than
those provided by the PD
� Cl 15.2 Issue on patent that
arises due to PD’s instruction,
the sum added to the contract
Dr Khairuddin Abdul Rashid
31
End of Session 2