 Ma’aden Sulphuric Acid Plant Project 5 June 2009 Dr. Peter Weber President, Metals Pr ocessi ng Di vi si on

Design Plant

Embed Size (px)

DESCRIPTION

refer for detailed engineering

Citation preview

  • Maaden Sulphuric Acid Plant Project

    5 June 2009Dr. Peter Weber

    President, Metals Processing Division

  • Outotec Oyj CMD 20092

    1.Basics

    2.Project Overview

    3.Project Development

    4.Project Execution

    5. Services

  • Outotec Oyj CMD 20093

    1.Basics

    2.Project Overview

    3.Project Development

    4.Project Execution

    5.Services

  • Outotec Oyj CMD 20094

    Basics Sources and Use of Sulphuric Acid

    Total 200 million t H2SO4

  • Outotec Oyj CMD 20095

    DryingTower

    SulphurFurnace

    +WasteHeat

    Boilers

    ConverterBed 1-3

    +Heat-

    exchang.

    Interm.Absorber

    Converter

    Bed 4

    FinalAbsorberAmbient Air

    Dry Air

    SO2 SO3+ SO2

    SO2SO3

    Tail Gas

    Diluted Acid

    Product Acid

    Sulphur Steam

    Steam

    H2O

    BFW

    Sulphur Burning Plant Sulphur Burning Plant Block Flow SheetBlock Flow Sheet

  • Outotec Oyj CMD 20096

    Total 200 million t H2SO4

    World Sulphuric Acid Production and Consumption World Sulphuric Acid Production and Consumption -- 20072007

    Production Consumption

  • Outotec Oyj CMD 20097

    1.Basics

    2.Project Overview

    3.Project Development

    4.Project Execution

    5. Services

  • Outotec Oyj CMD 20098

    Project Overview Key Figures

    USD 5,52 billions*Total Maaden Investment for Fertilizer Complex

    USD 495 M**Total Cost Sulphuric Acid Plants

    EUR 270**Outotec Import Contract

    * Source Maaden Press Release: June 2008; ** Contracts June 2007

  • Outotec Oyj CMD 20099

    Project Overview - Geographical Location

    Riyadh

    Dammam

    Ras Az Zawr

    Az ZabirahBurayda

    Hail

    AlJalamid

    MaadenPhosphate

    Project

    R E D S E A

    Gulf

    4.5Mt/y

    3.5Mt/y

    Jawf

    Jeddah

    Qurayyat

    Eshidiya Project Location

  • Outotec Oyj CMD 200910

    Project Overview Fertilizer ComplexAmmonia (1)

    0.657 Mt/a NH3

    Sulfuric Acid (3)

    High Pressure Steam~ 4.5 Mt/a H2SO4

    Cogeneration Plant

    Phosphoric Acid (3)1.370 Mt/a P2O5Phosphogypsum

    DAP (3)2.922 Mt/a

    Port

    Dry Stack

    Electric Distribution System

    Panamax Vessels

    Natural Gas

    Molten Sulphur

    Phosphate Concentrate4.50Mt/a

  • Outotec Oyj CMD 200911

  • Outotec Oyj CMD 200912

    Converter A progress

  • Outotec Oyj CMD 200913

    View from Plant A to Plant B/C

  • Outotec Oyj CMD 200914

    1.Basics

    2.Project Overview

    3.Project Development

    4.Project Execution

    5.Services

  • Outotec Oyj CMD 200915

    Project Development Convertible EPC approach

    Lump SumLump Sum

    DESIGN BASISDESIGN BASIS

    BIDDINGBIDDING

    ANALYSE/ANALYSE/NEGOTIATE/NEGOTIATE/

    AWARDAWARD

    MAADENMAADEN

    EPC EPC CONTRACTORCONTRACTOR

    Contractor BidContractor Bid

    MANAGE AND CONTROLMANAGE AND CONTROL

    ENGINEERINGENGINEERING

    PROCUREMENTPROCUREMENT

    CONSTRUCTIONCONSTRUCTION

    ENGINEERINGENGINEERING

    PROCUREMENTPROCUREMENT

    OPEN BOOK OPEN BOOK ESTIMATEESTIMATE

    CONVERT CONVERT TO LUMP TO LUMP

    SUMSUM

    ANALYSE/ANALYSE/NEGOTIATE/NEGOTIATE/

    COMMITCOMMIT

    ReimbursableReimbursable

    - Engineering services reimbursable rates

    - Agreed profit margin- Agreement on LDs

    and major commercial terms

    Fix price

    May 2006 June 2007

  • Outotec Oyj CMD 200916

    1.Basics

    2.Project Overview

    3.Project Development

    4.Project Execution

    5.Services

  • Outotec Oyj CMD 200917

    Scope of Services and Supplies Outotecs scope:

    Design, engineering, delivery and Commissioningon a Lump-Sum-Turnkey basis

    GAMA Arabias scope:Local supplies and Construction

    Some key data:Project implementation schedule: 31 month to MCTotal tons of structural steel: 3.800 metric tonnesTotal tons of equipment: 25.000 metric tonnesTotal cubic meters concrete 23.000m3Total electrical drives installed: 200Total cables installed: 350 kmTotal construction hours: 3.750.000

  • Outotec Oyj CMD 200918

    Project Task Force

    Project execution having all project team members in the same location (separate task force office)

    Short and efficient communication ways, fast decisions

    Interacting of engineering team ensured

  • Outotec Oyj CMD 200919

    Global SourcingSupplies from and Fabrication in Europe Asia (South Korea, Taiwan, China) North America (Canada) South America (Argentina, Brazil)

  • Outotec Oyj CMD 200920

    Managing Complex Logistics Approx. 120 shipments Approx. 140.000 freight tons

    (100.000 frt break bulk40.000 frt container shipment)

    Heavy items up to 290 tons Shipments from Europe,

    Asia and America

  • Outotec Oyj CMD 200921

    Engineering Home Office Oberursel up to 40 Worldwide Expediting (Outotec) up to 5

    Construction Site Raz Az Zawr / KSA (GAMA) Technical Management Team up to 35 Suppliers supervision up to 20 Construction Indirects up to 140 Construction Direct Manpower up to 1,200

    Commissioning up to 10

    Total up to 1,450

    Manpower

  • Outotec Oyj CMD 200922

    Organization Chart Overall Project

    Outotec Project Management

    ConstructionCompany

    Clients engineerEPCM

    Employer MPC

    Construction CompanyTechnical Mgmt.

    Process Engineering

    Plant Engineering

    Civil/Structural Engineering

    Electrical/Instrumentation Engineering

    Home Office Construction Mgmt.

    QA/QC Management

    Procurement/Shipping

    Local ConstructionSubcontractors

    HSE Management

    Vendors/Suppliers

    Expediting/Inspection

    Outotecsresponsibility area

  • Outotec Oyj CMD 200923

    0,0

    5,0

    10,0

    15,0

    20,0

    25,0

    30,0

    35,0

    40,0

    45,0

    50,0

    55,0

    60,0

    65,0

    70,0

    75,0

    80,0

    85,0

    90,0

    95,0

    100,0

    %

    Early / Month 0 10, 2,3 4,1 1,3 3,7 2,4 2,4 2,4 3,3 3,2 3,1 3,3 4,3 3,5 2,9 4,5 4,8 2,9 2,5 3,5 3,4 4,6 4,3 3,6 2,6 2,1 1,8 1,3 1,1 1,0 0,8 0,4 0,3 0,4 0,3 0,3 0,3 0,3 0,1 0,1 0,0

    Target / Month 0 6,7 4,2 3,5 1,8 3,2 2,4 2,3 2,5 2,7 2,8 3,0 3,1 3,7 3,3 2,5 3,7 4,3 3,6 3,4 3,5 4,5 5,0 4,3 3,4 3,1 3,4 2,2 1,6 1,3 1,3 1,0 0,3 0,3 0,4 0,4 0,3 0,3 0,3 0,1 0,1 0,0

    Actual / Month 0 0,0 8,0 3,9 2,5 2,3 2,9 2,0 2,0 7,3 2,4 1,8 5,7 1,7 1,6 2,3 2,7 4,7 3,7 3,4 5,0 4,3 6,0 4,6

    Late / Month 0 2,9 6,0 2,9 2,2 2,6 2,3 2,2 2,6 2,2 2,5 2,9 3,0 3,0 3,1 2,2 2,8 3,7 4,3 4,4 3,5 5,5 5,3 4,4 3,1 3,5 4,8 2,6 2,0 1,5 1,5 1,3 0,3 0,3 0,4 0,4 0,4 0,3 0,3 0,1 0,1 0,1

    Early cum. 0 10, 12, 17, 18, 22, 24, 26, 29, 32, 35, 38, 41, 46, 49, 52, 57, 61, 64, 67, 70, 74, 78, 83, 86, 89, 91, 93, 94, 95, 96, 97, 97, 98, 98, 98, 99, 99, 99, 99, 10 10

    Target cum. 0 6,7 10, 14, 16, 19, 21, 24, 26, 29, 32, 35, 38, 41, 45, 47, 51, 55, 59, 62, 66, 70, 75, 80, 83, 86, 89, 92, 93, 94, 96, 97, 97, 97, 98, 98, 98, 99, 99, 99, 99, 10

    Actual cum. 0 0,0 8,0 11, 14, 16, 19, 21, 23, 31, 33, 35, 40, 42, 44, 46, 49, 53, 57, 61, 66, 70, 76, 81,

    Late cum. 0 2,9 8,9 11, 14, 16, 19, 21, 23, 26, 28, 31, 34, 37, 40, 42, 45, 49, 53, 58, 61, 67, 72, 76, 79, 83, 88, 90, 92, 94, 95, 97, 97, 97, 98, 98, 98, 99, 99, 99, 99, 10

    0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41

    early

    target

    late

    Progress Curve - Total Project

    Effective Date MC

  • Outotec Oyj CMD 200924

    Risks and Risk Mitigation Quality

    Completion Schedule

    Procurement/material cost

    Currency exchange rate

    Country specific risks

    Technological risks

    Supplier qualification procedure/ Intensive expediting/permanent fabrication supervision in suppliers workshops for critical items

    Intensive suppliers expediting and reporting, permanent analysis of actual vs. target progress by engineering discipline and for construction

    Global sourcing and strict bid comparison/analysis

    Precise cash planning and forward hedging contracts

    Political risk insurance

    Largest plant ever built, but manageable upscale factor

  • Outotec Oyj CMD 200925

    1.Basics

    2.Project Overview

    3.Project Development

    4.Project Execution

    5. Services

  • Outotec Oyj CMD 200926

    Services Important critical Spare Part Package sold

    Intelligent computerized training simulator sold for operator training before and after first commissioning

    Opportunities for long-term Service frame agreement related to:

    Spare Part Supplies Operation assistance Assistance in Maintenance and shut down planning Training frame agreement

  • Outotec Oyj CMD 200927

    Overall View Construction Site

  • Outotec Oyj CMD 200928

    Q&AMore out of ore!

    www.outotec.com