ISBT Anand Vihar Proposal finally approved in the UTTIPEC governing body meeting after many revisions/modifications by UTTIPEC on 28 Aug ‘09. NOC received from AAI. Authority approved & granted the project for Environment Clearance on 18.01.10. NOC from DPCC is received. Applied for Tree cutting permission. Modified drawings also submitted on 29.3.10. Drawings and Documents resubmitted to DDA for approval on 5 Oct ‘09 after incorporating all the observation/comments from DDA. Pre-qualification of contractors for construction- finalized. ADB requirement to Pre Q contractors as per ADB norms . ADB norms . Loan sanctioned from NCRPB. The weekly review meeting with Architect on 19.01.10, for EOT to be coordinated/obtained by TD & DIMTS to pursue DDA approval process further. Meeting with ADB consultants held on 29 Jan ‘10 and 15Feb ‘10. Draft copy of tender sent to ADB-Consultants as per ADB and got back their comments. EFC has been sent to GM-ISBT. Proposed date of NIT for construction Mar ‘10 (Dec’09). Proposed Completion Date : Aug ’11. (Mar ’11). c

DIMTS projects.compressed

Embed Size (px)

Citation preview

Page 1: DIMTS projects.compressed

ISBT Anand Vihar– Proposal finally approved in the UTTIPEC governing

body meeting after many revisions/modifications by UTTIPEC on 28 Aug ‘09.

– NOC received from AAI.– Authority approved & granted the project for

Environment Clearance on 18.01.10.– NOC from DPCC is received.– Applied for Tree cutting permission. Modified drawings

also submitted on 29.3.10.– Drawings and Documents resubmitted to DDA for

approval on 5 Oct ‘09 after incorporating all the observation/comments from DDA.

– Pre-qualification of contractors for construction-finalized. ADB requirement to Pre Q contractors as per ADB norms .ADB norms .

– Loan sanctioned from NCRPB.– The weekly review meeting with Architect on 19.01.10,

for EOT to be coordinated/obtained by TD & DIMTS to pursue DDA approval process further.

– Meeting with ADB consultants held on 29 Jan ‘10 and 15Feb ‘10.

– Draft copy of tender sent to ADB-Consultants as per ADB and got back their comments.

– EFC has been sent to GM-ISBT.– Proposed date of NIT for construction Mar ‘10 (Dec’09).– Proposed Completion Date : Aug ’11. (Mar ’11).

c

Page 2: DIMTS projects.compressed

ISBT Sarai Kale Khan– Concept Plan submitted to UTTIPEC on 24 Apr ’09.– To retain the ITDR on its existing location, the entire

proposal has been modified & resubmitted on 18 Sep ‘09 & again on 23 Sep ‘09 for consideration.

– Proposal approved by LG during the Governing body meeting on 15 Jan ‘10.

– NOC from AAI received.– Applied for DPCC & EIA. EIA presentation has been re-

submitted .– Modified Drawings submitted to MCD on 9 Jun ’09. Now

the drawings need to be resubmitted as the proposal entirely modified by UTTIPEC. Drawings are ready for resubmission inthis week.

– Loan sanctioned from NCRPB– Draft copy of tender sent to ADB-Consultants as per ADB

and got back their comments.– Required documents, drawings & reports submitted for

NCR-PB on 30 Oct ‘09.NCR-PB on 30 Oct ‘09.– Documents required by NCR-PB/ADB submitted on 18

Dec ‘09. – Meeting with ADB consultants held on 29 Jan ‘10 & 15

Feb ‘10.– Pre-Qualification of contractors finalized. ADB

requirement to Pre Q contractors as per ADB norms. – EFC has been sent to GM-ISBT.– Likely date for NIT for construction : May’10 (Jun ’10, Feb

’10)

– Likely Completion date : Oct ‘11. (Jun ’11)

ccc

Page 3: DIMTS projects.compressed

TO BE DEMOLISHED

TO BE RETAINED

ISBT KASMERE GATE

PLAN INDICATING AREAS TO BE DEMOLISHED / RETAINED

Page 4: DIMTS projects.compressed

DATA CENTRE CONTROL CENTRE

Page 5: DIMTS projects.compressed
Page 6: DIMTS projects.compressed

FOB at Mother Teresa

Page 7: DIMTS projects.compressed

FOB at Mathura Road

Page 8: DIMTS projects.compressed

FOB at Africa Avenue

Page 9: DIMTS projects.compressed

FOB at Pushp vihar

Page 10: DIMTS projects.compressed
Page 11: DIMTS projects.compressed