70
1 Directional Drilling

Directional Drilling

Embed Size (px)

DESCRIPTION

Directional drilling manualInformation and guides, Shahrood university of technology

Citation preview

  • 1

    Directional Drilling

  • 2

    Directional Drilling

  • 3

    Directional Drilling

    - Overview :

    Controlled directional drilling is the engineering process of planning and drilling a well

    It is a drilling method in a predetermined trajectory, until reaching a target or objective situated off of the

    vertical line that passes thorough the rig

    Directional drilling started as corrective operations for some problems occurring during drilling such as:

    Sidetracks due to fishing operation failures or

    Extreme borehole tortuosity

  • 4

    - Overview :

    Today, however, the applications of directional wells in the industry are manifolds

    Most recent advances include the drilling of horizontal wells and multilateral wells, have revealed extremely

    efficient in increasing the productivity of reservoirs

    with small thickness

    Directional Drilling

  • 5

    - Overview :

    Among the most important uses of directional wells is the development of offshore fields

    The cost of the development of those fields using vertical (conventional) wells would have made their

    exploitation prohibitive

    Directional Drilling

  • 6

    Directional Drilling

  • 7

  • 8

    - Application of Directional Drilling :

    Inaccessible locations:

    Natural or artificial barriers preclude the access

    from the vertical of the target

    Relief wells:

    Technique used to combat a blowing up well

    The relief well reaches an area close to where the gas is entering the well and mud with adequate

    weight is pumped to kill the well

    Directional Drilling

  • 9

    - Application of Directional Drilling :

    Natural directional wells:

    Use the natural tendency of certain formations

    to reach the target with lower cost

    (vertical too expensive)

    Horizontal wells:

    In thin formations, horizontal wells increase the

    area exposed to flow, increasing production

    Directional Drilling

  • 10

    - Application of Directional Drilling :

    Sidetrack:

    Change in the original trajectory due to pieces of metal or fishes that could not be recovered by fishing operation

    Sidetracks are not planned in advance, but the equipment and techniques are the same used

    in directional drilling

    Directional Drilling

  • 11

    Directional Drilling

  • 12

    - Application of Directional Drilling :

    Environmental pressures, as for example in Alaska and in the Amazon, have increased the use of

    onshore directional drilling

    Directional drilling is also used in the development of geothermal projects

    Geothermal reservoirs can reach temperatures of

    370oC, and are used to generate steam from water

    pumped from surface

    Directional Drilling

  • 13

    - Well Trajectory Local Coordinate System:

    The planned and drilled trajectories of a directional well are either 2D or 3D objects

    Associated to any point along the trajectory (planned or actual) there are

    three values that can be determined (planned

    trajectory) or measured (actual trajectory)

    Those values can be used to determine the coordinates of the point in the rig local coordinate

    systems

    Directional Drilling

  • 14

    - Well Trajectory Local Coordinate System:

    The values are :

    Measured Depth

    Inclination

    Azimuth

    Directional Drilling

  • 15

    - Well Trajectory Local Coordinate System:

    The measured depth at the point of the trajectory is the measured of the length along the trajectory,

    from the rotary table to the point

    Therefore, the measured depth is not, in fact, a depth in the strict sense of the word but a length

    (unless for a perfectly straight vertical trajectory)

    Directional Drilling

  • 16

    - Planning a 2D Directional Well Trajectory :

    Directional Drilling

  • 17

    - Planning a 2D Directional Well Trajectory :

    The location of the rig determines the rig local coordinate system

    The rig and the target determine a vertical plane which contains the vertical V, and the target T

    It is on this vertical plane that the directional well trajectory is planned drawn

    Directional Drilling

  • 18

    - Planning a 2D Directional Well Trajectory :

    Directional Drilling

  • 19

    - Planning a 2D Directional Well Trajectory :

    Point R corresponds to the rig location, and also the origin of the rig local coordinate system

    Point T is the target, whose coordinates (v, n, e) are respectively the TVD, relative North/South,

    and relative East/West coordinates of the target

    Directional Drilling

  • 20

    - Planning a 2D Directional Well Trajectory :

    The distance d from the target to the vertical axis V is called the horizontal departure to target and is

    calculated from the relative coordinates n and e as

    follows:

    Directional Drilling

  • 21

    - Planning a 2D Directional Well Trajectory :

    The target azimuth is the angle of the vertical plane and is given by:

    Directional Drilling

  • 22

    - Planning a 2D Directional Well Trajectory :

    The parameters v (TVD) and horizontal departure d are the basic parameters we need to plan the 2D

    trajectory of the directional well

    Directional Drilling

  • 23

    - Terms for Well Trajectory :

    When drilled from conventional rigs, a directional well trajectory starts with a vertical hole section

    drilled to a given depth where it starts to curve

    This point is called kick-off point (KOP) and its determination depends on various factors,

    in particular, the mechanical competence and

    stability of the formation where the curved section

    (and the angle) starts to build

    Directional Drilling

  • 24

    - Terms for Well Trajectory :

    A too soft formation will not support the lateral force required to drive the bit into a curved path

    A too hard formation will resist to the effects of the deviation tool

    Directional Drilling

  • 25

    - Terms for Well Trajectory :

    The position of the KOP will also affect the final and/or the maximum inclination of the trajectory

    The engineer, therefore, will have to simulate several trajectories and choose the one that best

    fits the characteristics of the region to be drilled

    Some restrictions on the trajectory will narrow the range of possibilities

    Directional Drilling

  • 26

    - Terms for Well Trajectory :

    For example, the ideal or necessary angle to reach the target :

    To drill the reservoir perpendicular to the plan of highest permeability in anisotropic rocks, or

    Perpendicular to the fractures of a naturally fractured reservoir

    Parallel to a blowing out well to more efficiently kill the well

    Directional Drilling

  • 27

    - Terms for Well Trajectory :

    The hole section that follows the KOP is called build-up section

    It is always recommended to run a casing shortly after the end of the build-up section

    A cased borehole will prevent the formation of key seats which may lead pipesticking problems

    Since casing projects should follow several design criteria, it is appropriate, and advisable, that

    engineers work as an integrated team aiming to

    end up with a small number of optimized plans

    that comply with all design criteria

    Directional Drilling

  • 28

    - Terms for Well Trajectory :

    The final choice will consider economics, logistics (availability of deflection tools at or close to the

    location, etc)

    The experience of the team will also play an important role, reducing substantially the number

    of interactions required to obtain the optimal plans

    Directional Drilling

  • 29

    - Geometric Elements of 2D Well Trajectories:

    The simplest curved segment used in trajectory planning is the sector of circle

    An advantage is that only one parameter is required to define the curve

    One such parameter is the radius of the circle R

    Instead of specifying the radius R, it is possible to specify its inverse c, or curvature

    Directional Drilling

  • 30

    - Geometric Elements of 2D Well Trajectories:

    The radius and the curvature are related by

    Directional Drilling

  • 31

    - Geometric Elements of 2D Well Trajectories:

    The curvature can be expressed as:

    Directional Drilling

    A length L of a circle of radius R subtend an angle

    such that L = R for in radians

    C: rad/min

  • 32

    - Geometric Elements of 2D Well Trajectories:

    The radius can be calculated by:

    Directional Drilling

    for c in degrees per length

    Common units of curvature are degrees per 100 ft, and

    degrees per 30 m

  • 33

    - Geometric Elements of 2D Well Trajectories:

    It is common also to refer to curvature as :

    buildup rate (BUR for building angle curves)

    dropoff rate (DOR for dropping angle curvatures

    doglegseverity (DLS for curves in general, and in particular to measure the degree of tortuosity of a trajectory)

    Directional Drilling

  • 34

    - Geometric Elements of 2D Well Trajectories:

    The TVD and the horizontal departure are the basic parameters needed to plan a 2D trajectory for a

    directional well

    All other parameters are set by the engineer, or are calculated

    The degree of freedom of a trajectory type is the number of independent parameters we need to set

    in order to calculate the remaining parameters

    Directional Drilling

  • 35

    - Geometric Elements of 2D Well Trajectories:

    Directional Drilling

  • 36

    2D Trajectory Geometries

  • 37

    - Classifying 2D Well Trajectories:

    Build and Hold

    Build, Hold, and Partial Drop (Modified S type)

    Build, Hold, and Drop ( S type)

    Continuous Build

    Directional Drilling

  • 38

  • 39

    - Classifying 2D Well Trajectories:

    Build and Hold (Profile A):

    Drilling starts vertical to the KOP

    From this point angle starts to build (build up segment) until a maximum inclination is reached

    (end of build)

    Drilling continues with a straight segment (slant) until reach the target

    Directional Drilling

  • 40

    - Classifying 2D Well Trajectories:

    Build and Hold (Profile A):

    The Build and Hold type has three parameters and two degrees of freedom:

    KOP

    BUR

    Maximum Inclination

    Directional Drilling

  • 41

    - Classifying 2D Well Trajectories:

    Build and Hold (Profile A):

    Determine KOP given BUR and max (Max.Inclination)

    Directional Drilling

  • 42

  • 43

    - Classifying 2D Well Trajectories:

    Build and Hold (Profile A):

    Determine KOP given BUR and Max. Inclination

    Directional Drilling

  • 44

    - Classifying 2D Well Trajectories:

    Build and Hold (Profile A):

    Directional Drilling

  • 45

    - Classifying 2D Well Trajectories:

    Build and Hold (Profile A):

    Determine max given KOP and BUR

    Directional Drilling

  • 46

  • 47

    - Classifying 2D Well Trajectories:

    Build and Hold (Profile A):

    Determine max given KOP BUR and

    Directional Drilling

  • 48

    - Classifying 2D Well Trajectories:

    Build and Hold (Profile A):

    Directional Drilling

  • 49

    - Classifying 2D Well Trajectories:

    Build and Hold (Profile A):

    Determine BUR given KOP and max

    Directional Drilling

  • 50

    - Classifying 2D Well Trajectories:

    Build and Hold (Profile A):

    Determine BUR given KOP and max

    Directional Drilling

  • 51

    - Classifying 2D Well Trajectories:

    Build and Hold (Profile A):

    Determine BUR given KOP and max

    Directional Drilling

  • 52

    - Classifying 2D Well Trajectories:

    Build and Hold (Profile A):

    Directional Drilling

  • 53

  • 54

    - Classifying 2D Well Trajectories:

    Build, Hold, and Drop (profile C):

    Drilling starts vertical to the KOP

    From this point angle starts to build (build up segment) until a maximum inclination is reached

    (end of build)

    Drilling continues straight (slant segment) until a point called DOP (drop-off point) is reached

    From this point, angle decreases (drop-off segment) until it becomes vertical (end of drop)

    From this point, drilling continues vertical until reach the target

    Directional Drilling

  • 55

    - Classifying 2D Well Trajectories:

    Build, Hold, and Drop (profile C):

    The Build and Hold type has five parameters and four degrees of freedom:

    KOP

    BUR

    Maximum Inclination

    DOR

    EOD (vertical depth of the endof-drop)

    Directional Drilling

  • 56

  • 57

    - Classifying 2D Well Trajectories:

    Build, Hold, and Drop (profile C):

    Determine max given KOP, BUR (c1), DOR (c2), and EOD

    Directional Drilling

  • 58

    - Classifying 2D Well Trajectories:

    Build, Hold, and Drop (profile C):

    Determine max given KOP, BUR (c1), DOR (c2), and EOD

    Directional Drilling

  • 59

    - Classifying 2D Well Trajectories:

    Build, Hold, and Drop (profile C):

    The measured depth, true vertical depth, and

    horizontal departure of the endofbuild (EOB) section is given by

    Directional Drilling

  • 60

  • 61

    - Classifying 2D Well Trajectories:

    Build, Hold, and Partial Drop (profile B):

    Drilling starts vertical to the KOP

    From this point angle starts to build (build up segment) until a maximum inclination is reached

    (end of build)

    Drilling continues straight (slant segment) until a point called DOP (drop-off point) is reached

    Directional Drilling

  • 62

    - Classifying 2D Well Trajectories:

    Build, Hold, and Partial Drop (profile B):

    From this point, angle decreases (drop-off segment) until a given inclination is obtained

    (end of drop)

    From this point, drilling continues straight until each the target

    Directional Drilling

  • 63

    - Classifying 2D Well Trajectories:

    Build, Hold, and Partial Drop (profile B):

    The Build, Hold, and Partial Drop type has six parameters and five degrees of freedom:

    KOP BUR maximum inclination DOR hang length - s (sometimes the vertical depth of the EOD)

    hang inclination (the inclination to reach the target)

    Directional Drilling

  • 64

    - Classifying 2D Well Trajectories:

    Build, Hold, and Partial Drop (profile B):

    This is very similar to the BuildHoldDrop type

    The difference is that the trajectory reaches the target with a given angle (hang inclination)

    Directional Drilling

  • 65

  • 66

    - Classifying 2D Well Trajectories:

    Continuous Build (profile D):

    Drilling starts vertical to the KOP

    From this point angle starts to build in a relative smaller rate (build up segment) until the drilling

    reaches the target

    Directional Drilling

  • 67

    - Classifying 2D Well Trajectories:

    In addition to these basic types, there exist other special profiles

    These profiles are more suitable to deep drilling projects, extended reach wells (ERW), and

    horizontal wells

    Directional Drilling

  • 68

    - Classifying 2D Well Trajectories:

    Catenary:

    The catenary type was proposed with the purpose of minimizing the torque along the drillstring

    It is a special case of the continuous build type, but with a controlled variable curvature

    It would represent the natural shape of a drillstringsuspended at the rotary table and at the

    target

    Several operational problems put a lot of difficultiesin this type of trajectory

    Directional Drilling

  • 69

    - Classifying 2D Well Trajectories:

    Double Build:

    This type is very common in horizontal drilling

    It is an analogous of the build, hold, and drop, but, instead of dropping to the vertical, the second

    curved segment is another build, ending at the

    inclination of 90o

    Directional Drilling

  • 70

    - Classifying 2D Well Trajectories:

    Reverse Double Build:

    To extend the horizontal section for pay zones not too far from the rig position, a reversed double

    build type is used

    In this kind of trajectory, the first curved segment is

    built in a direction opposite to the target, so to

    increase the departure of the target

    Then a second build segment starts, dropping back

    to vertical and continuing building angle, now in the

    direction of the target

    Directional Drilling