Upload
others
View
7
Download
0
Embed Size (px)
Citation preview
D.N.I.T. Engineering Cell
Name of work:- Prevision of New Room for Urdu Department in P.G 1 Building 2nd Floor
in LCW University, Lahore.(Based on 1st January to 30thJun 2017)
Schedule Items
S.
No.
Item No. MRS. Description of work Quantity Unit Rate in
Rs.
Amount in
Rs.
1.
22 b/ Ch 4 Dismantling 2nd class tile roofing.
1260.00 Cft 100 Sft 726.00 9148.00
2. 18 /Ch-4 Removing cement or lime plaster.
431.00 Cft 100 Sft 242.00 1043.00
3. 20 / Ch -4 Dismantling cement concrete
reinforced, separating
reinforcement from concrete,
cleaning and straightening the
same.
25.00 Cft 100 Cft 10454.40 2614.00
4. 5 / Ch-7 Pacca brick work in Second Floor:-
Ratio 1:5 brickwork
625.00 Cft 100 Cft 22735.70 142098.00
5. 3 / Ch- 10 P/L watering and ramming brick
ballast 1½"to 2"gauge mixed with
25% sand, for Floor foundation,
complete in all respects.
473.00 Cft 100 Cft 4395.85 20792.00
6. 5 f / Ch 6 Cement concrete plain i/c placing,
compacting, finishing and curing
complete (including screening and
washing of stone aggregate): Ratio
1: 2: 4
315.00 Cft 100 Cft 20849.40 65676.00
7. 6 a iii / Ch 6 Reinforced cement concrete in roof
slab, beams, columns lintels,
girders and other structural
members laid in situ or precast laid
in position, or prestressed members
cast in situ, complete in all
respects:- (nominal mix 1: 2: 4)
Add extra labour for R.C. concrete
in 2nd and subsequent storeys. ( 3rd
floor )
893.00 Cft Per Cft 382.50 341573.00
8. 9 / 6 Ch
Fabrication of mild steel
reinforcement for cement concrete,
including cutting, bending, laying
in position, making joints and
fastenings, i/c cost of binding wire
and labour charges for binding of
steel reinforcement (also includes
removal of rust from bars):-
Deformed bars (Grade-40)
3000.00 Kg 100 Kg 9980.20 299406.00
9. 9 ( c) /11 Ch Cement plaster 1:4 upto 20' 1192.00 Sft 100 Sft 2562.6 30546.00
height:- 3/4" thick (Second floor)
10. 10 b / 11 Ch Cement plaster 3/8" thick under
soffit of R.C.C. Ratio (1:3) roof
slabs only, upto 20' height.
1310.00 Sft 100 Sft 2199.44 28813.00
11. 5 / Ch 7 Pacca brick work in Third Floor
Ratio 1:5
289.00 Cft 100 Cft 23646.5 68338.00
12. 35 / Ch 9 P/L roof insulation, comprising of
single layer of tiles 9"x4½"x1½"
grouted with cement sand mortar
1:3 laid over 2" (50 mm) thick
earth(including mud plaster) over
thermopore sheet, over polythene
sheet 300 gauge over a layer of
bitumen, complete in all respects:-
Thermopore sheet 1" thick
1460.00 Sft 100 Sft 7284.40 106352.00
13.
44 / Ch 25 P/F windows consisting of M.S.
box section frame 2"x1½", leaves
frame 1½"x1"box section frame for
glazing 3/8"x3/8" using 16 SWG
sheet 'U' shaped rubber supported
with 1"x1/8" M.S. flat for fixing
3/16" thick glass panes M.S. box
section ½"x½" of 16 SWG for
fixing 24 SWG wire gauze on outer
side by means of ¾"x1/8" M.S. flat
and screws including grill of M.S.
flat ½"x1/8" or ¼"x¼" square bar
with independent frame of½"x½"
box section of 16 SWG i/c all C.P.
fitting and painting 3 coats
complete in all respect.
180.00 Sft Per Sft 469.10 84438.00
14. 31 / Ch 13 Preparing surface and painting with
emulsion paint on new surface three
Coats
3325.00 Sft 100 Sft 1122.55 37325.00
15. 5 c / Ch 13 Preparing surface and painting of
doors and windows any type i/c
edges three coat
400.00 Sft 100 Sft 1521.45 6086.00
16. 15 / Ch - 9 Khuras on roof 2'x2'x6"
2.00 Nos. Each 461.45 923.00
17. 26/ Ch- 23 P/L cutting, jointing, testing and
disinfecting P.V.C. pipe line with
`B' Class working pressure pipe, in
trenches, complete in all respects:-
4" i/d
45.00 Rft Per Rft 159.05 7157.00
18. 37 / Ch- 23 Providing and installing P.V.C.
bends, of B.S.S. Class `B' working
pressure:- 4” i/d
2.00 Nos. Each 379.15 758.00
19. 38 / Ch 23 Providing and installing P.V.C.
tees, of B.S.S. Class `B' working
4.00 Nos. Each 1101.65 4407.00
pressure:- 4" i/d
20. 39 / Ch 23 Providing and installing P.V.C.
sockets, B.S.S. :- Class `B'
working pressure:-4" i/d
2.00 Nos. Each 229.30 459.00
21. 3 / Ch 24 S/E of PVC pipe for wiring
recessed in walls, including
inspection boxes, pull boxes, hooks,
cutting jharries, and repairing
surface, etc., complete with all
specials. 20 mm i/d
150.00 Rft Per Rft 38.30 5745.00
22.
A
10i/ Ch 24
S/E of single core PVC insulated
copper conductor cables, in prelaid
PVC pipe/M.S. conduit/G.I
pipe/wooden strip batten/wooden
casing an capping/G.I.
wire/trenches (rate for cables
only):- 250/440 volts, PVC
insulated:
3/0.029"
500.00 Rft
RerRft
11.45
5725.00
B 10 iii/Ch -24 7/0.029"
450.00 Rft Per Rft 15.75 7088.00
C 10 v Ch -24 7/0.044" 300.00 Rft Per Rft 31.95 9585.00
23. 27/Ch -24 S/E of bakelite button holder shade,
large size.
12.00 Nos. Per Rft 51.25 615.00
Total Schedule Items Rs. 1286710.00
Deduction for old material Tile roofing Rs. 71052.00
Total Amount Schedule Items Rs. 1215658.00
Rate quoted percentage above or blew on Schedule Items Rs.
Total Amount Schedule Items Rs.
Add 16% PRA Tax on Schedule Items Rs.
Total Amount Schedule Items Rs.
Total Schedule Items Rs._______________
Total Non Schedule Items Rs._______________
Grand Total Rs.______________
D.N.I.T. Engineering Cell
Name of work:- Prevision of New Room for Urdu Department in P.G 1 Building 2nd Floor
in LCW University, Lahore.(Based on 1st January to 30thJun 2017)
Non- Schedule Items
S.
No.
Item No.
MRS.
Description of work Quantity Unit Rate in Rs. Amount in
Rs.
1. N.S Laying Floor of Glazed Tile
(Master) 1/4" Thick Size 16"x16"
Laid in pigment over 1:2 Cement
Sand Mortar 3/4" Thick i/c
Finishing Complete in all Respects
as directed by the engineer in
charge.
1435.00 Sft Per Sft
2. N.S Laying Dado of Glazed Tile
(Master) 1/4" Thick Size 16"x16"
Laid in pigment over 1:2 Cement
Sand Mortar 3/4" Thick i/c
Finishing Complete in all Respects
as directed by the engineer in
charge.
110.00 Sft Per Sft
3. N.S P/L Gutka of Clading on wall Size
9”x3”x2 ¼” Laid with cement
mortar 1:3 i/c Cutting of Gutka
with Grinder mortar 1:6 on back
side Gutka i/c Scaffolding etc. in
all Respect as directed by the
Engineer incharge.
993.00 Sft Per Sft
4. N.S
P/F PVC duct 33x33 mm for
wiring i/c nails/ Screws etc.
Admjee / G.M Complete in all
respect.
100.00 Rft Per Rft
5. N.S S/E light plug with box 5/Amp
Multi-Function (opal) made by
Australia complete in al respect.
06.00 Nos. Each
6. N.S S/E Power plug with 10 To 15 /
Amp (opal) made by china
complete in all respect.
02.00 Nos. Each
7. N.S S/E of Plastic Board pair(8+2=10
pair) With Bakelite Sheet (Opal)
Switches, making requisite
number of hole for switches etc.
Complete in all respect.
4.00 Nos. Each
8. N.S S/E of Plastic Board pair(2+2=4
pair) With Bakelite Sheet (Opal)
Switches, making requisite
6.00 Nos. Each
number of hole for switches etc
complete in all respect
9. N.S Supply, installation, fixing, wiring,
testing and Dimmer/ Regulator,
bracket, nuts, bolts and all
amounting arrangement, complete
in all respect . These items will be
of approved quality and make.
There will consist of as described
and equipped as above but
specified as under:- (GFC,PAK,
YOUNS) 56" Sweep
4.00 Nos. Each
10. N.S P/F 23 watts Energy Saver Philips
Company Complete in all
Respects as Director by the
Engineer incharge
12 No Each
Total Non-Schedule Rs.__________
Add 16% PRA Tax on Non-Schedule Items Rs.__________
Total Rs._____________
D.N.I.T. Engineering Cell
Name of work:- Renovation / Special Repair of Chemistry Department (Lab) in L.C.W
University, Lahore. ( Based on 1st January 2017 to 30th Jun 2017)
Schedule Items
S.
No.
Item No.
MRS.
Description of work Quantity Unit Rate in
Rs.
Amount in
Rs.
1 13/Ch 4 Dismantling brick work in lime or
cement mortar.
269.00 %cft 2468.4 6642.00
2 19 c/Ch 4 Dismantling cement concrete 1:2:4
plain.
168.00 %cft 6388.8 10721.00
3 32 b/Ch 4 Removing windows and sky lights
with chowkat.
3.00 each 179.85 540.00
4 48/Ch 4 Removing cement or lime plaster. 379.00 %sft 242 916.00
5 50/ Ch 4 Dismantling glazed or encaustic tiles,
etc.
234.00 %sft 1240.8 2900.00
6 55 i/Ch 4 Dismantling G.I./M.S. conduit/G.I.
flexible/PVC pipes or conduit wiring,
etc. of all sizes including making good
damaged surface (building portion):-on
surface
1694.00 per rft 7.35 12453.00
7 54/Ch 4 Dismantling plug point and making
good damaged surface (building
portion).
15.00 Each 34.35 515.00
8 53/Ch4 Dismantling light, fan and call bell
point including casing and
capping/strip open type, and making
good damaged surface (building
portion).
14.00 per
point
40.1 561.00
9 5 f/Ch 6 Cement concrete plain including
placing, compacting, finishing and
curing complete (including screening
and washing of stone aggregate): Ratio
1: 2: 4
69.00 %cft 20849.4 14391.00
10 4 i/ Ch7 Pacca brick work in foundation and
plinth in:- Cement, sand mortar:- Ratio
1:6
65.00 %cft 19503.4 12671.00
11 5/ Ch 7 Pacca brick work in ground floor:-
cement, sand mortar:- Ratio 1:4
148.00 %Cft 21577.6 31911.00
12 5/ Ch 7 Pacca brick work in ground floor:-
cement, sand mortar:- Ratio 1:5
207.00 %Cft 21079.1 43673.00
13 6/Ch 6 Providing and laying reinforced
cement concrete (including prestressed
concrete), using coarse sand and
screened graded and washed aggregate,
in required shape and design, including
forms, moulds, shuttering, lifting,
compacting, curing, rendering and
finishing exposed surface, complete
(but excluding the cost of steel
reinforcement, its fabrication and
placing in position, etc.):- Reinforced
cement concrete in roof slab, beams,
141.00 per cft 338.9 47695.00
columns lintels, girders and other
structural members laid in situ or
precast laid in position, or prestressed
members cast in situ, complete in all
respects:- Type C (nominal mix
1: 2: 4)
14 9 b /Ch 11 Cement plaster 1:4 upto 20' (6.00 mm)
height:- ½" (13 mm) thick
3326.00 %sft 1740.7 57895.00
15 10 b /Ch 11 Cement plaster 3/8" (10 mm) thick
under soffit of R.C.C. roof slabs only,
upto 20' height. 1:3
528.00 %sft 1975 10418.00
16 49 ii/ Ch 4 Scraping:- Ordinary distemper, oil
bound distemper, or paint of wall.
1078.00 %sft 435.6 4695.00
17 31/ Ch 13 Distempering:- old surface:- two coat 1910.00 %sft 429.5 8202.00
18 23/Ch 11 Preparing surface and painting with
emulsion paint:- two coat
2047.00 %sft 781.2 15991.00
19 4 c/Ch 13 Painting old surfaces:- Painting doors
and windows, any type: two coat
744.00 %sft 919.2 6839.00
20 9 /Ch 6 Fabrication of mild steel reinforcement
for cement concrete, i/c cutting,
bending, laying in position, making
joints and fastenings, including cost of
binding wire and labour charges for
binding of steel reinforcement (also
includes removal of rust from bars):-
Deformed bars (Grade-40)
450.00 % kg 9980.2 44911
21 9 /Ch 19 Providing and fixing glazed earthen
ware sink, including bracket set, waste
pipe and waste coupling:-60x45 cm
(24"x18")
21.00 each 1746.4 36674.00
22 26/Ch 19 Providing and fixing chromium plated
bib cock:- 1.5 cm (½")
2.00 each 333.5 667.00
23 27/Ch 19 Providing and fixing chromium plated
tee stop cock 15mm (½").
9.00 Each 453.5 4082.00
24 34/Ch 19 Providing and fitting "P" trap:- 10 cm
(4") glazed.
22.00 Each 136.6 3005.00
25 26/Ch 23 Providing, laying, cutting, jointing,
testing and disinfecting P.V.C. pipe
line with `B' Class working pressure
pipe, in trenches, complete in all
respects:- 4" i/d
245.00 Rft 159.05 38967.00
26 37 i/ Ch 23 Providing and installing P.V.C. bends,
of B.S.S. Class `B' working pressure:-
4" i/d (100 mm)
6.00 Each 379.15 2275.00
27 38 i/ Ch 23 Providing and installing P.V.C. tees, of
B.S.S.Class `B' working pressure:- 4"
i/d (100 mm)
8.00 Each 1101.65 8813.00
28. 39/Ch 23 Providing and installing P.V.C.
sockets, B.S.S. Class `B' working
pressure:- 4" i/d
18.00 Each 229.3 4127.00
29.
Providing, laying, cutting, jointing,
testing and disinfecting G.I. pipeline in
trenches, with socket joints, using G.I.
pipes of B.S.S. 1387-1967 complete in
all respects, with specials and valves.
A
22/Ch 23
Medium Quality
½" i/d thick
225.00
Rft
68.15
15334.00
B 22/Ch 23 ¾" i/d thick 200.00 Rft 85.8 17160.00
C 22/Ch 23 1¼" i/d thick 180.0 Rft 157.45 28341.00
30. 3/Ch 24 Supply and erection of PVC pipe for
wiring recessed in walls, including
inspection boxes, pull boxes, hooks,
cutting jharries, and repairing surface,
etc. complete with all specials.20 mm
i/d
700.00 Rft 38.3 26810.00
31. 4/Ch 24 Supply and erection of PVC pipe for
wiring on surface including clamps
inspection boxes, pull boxes, bends,
tees, repairing surface, etc., complete
with all specials:-
200.00 Rft 20.05 4010.00
32.
A
10/ Ch 24
Supply and erection of single core
PVC insulated copper conductor
cables, in prelaid PVC pipe/M.S.
conduit/G.I pipe/wooden strip
batten/wooden casing an capping/G.I.
wire/trenches (rate for cables only):-
250/440 volts, PVC insulated:
7/0.74 mm (7/0.029")
2370.00
p/rft
15.75
37328.00
B 10/ Ch 24 3/0.74 mm (3/0.029") 500.00 p/rft 22.7 11350.00
C 10/ Ch 24 7/1.12 mm (7/0.044") 1100.00 p/rft 31.95 35145.00
33. 43 I / Ch 24 Supply and erection of tube light, i/c
rod, choke, starter with frame, flexible
wire, i/c connection from ceiling rose,
etc., complete. double rod (80 watts)
with two chokes and 2 starters.
18.00 Each 1255.2 22594.00
Total Schedule Items Rs. 631222.00
Rate quoted percentage above or blew on Schedule Items Rs.
Add 16% PRA Tax on Schedule Items Rs.
Total Amount Schedule Items Rs.
Total Schedule Items Rs._______________
Total Non Schedule Items Rs._______________
Grand Total Rs.______________
D.N.I.T. Engineering Cell
Name of work:- Renovation / Special Repair of Chemistry Department (Lab) in L.C.W
University, Lahore. ( Based on 1st January 2017 to 30th Jun 2017)
Non-Schedule Items
S.
No.
Item No.
CMR.
Description of work Quantity Unit Rate in Rs. Amount in
Rs.
1. N.s Laying Floor of Glazed Tile
(Master) 1/4" Thick Size 16"x16"
Laid in pigment over 1:2 Cement
Sand Morter 3/4" Thick i/c
Finishing Complete in all Respects
as directed by the engineer in
charge.
1067.00 Per Sft
2. N.S Laying Dado of Glazed Tile
(Master) 1/4" Thick Size 16"x16"
Laid in pigment over 1:2 Cement
Sand Morter 3/4" Thick i/c
Finishing Complete in all Respects
as directed by the engineer in
charge.
444.00 Per Sft
3. N.S Laying Dado of Glazed Tile
(Master) 1/4" Thick Size 8"x8"
Laid in pigment over 1:2 Cement
Sand Morter 3/4" Thick i/c
Finishing Complete in all Respects
as directed by the engineer in
charge.
88.00 Per Sft
4. N.S Laying Floor of Glazed Tile
(Master) 1/4" Thick Size 8"x8"
Laid in pigment over 1:2 Cement
Sand Morter 3/4" Thick i/c
Finishing Complete in all Respects
as directed by the engineer in
charge.
436.00 Per Sft
5. N.S P/F Laminated vine board 5/8”
thick Shatters & partition for lab
counters i/c full hinges, C.P
handle, Brass Screws, China lock
and painting complete in all
respect as per directed by
Engineer-in-charge.
690.00 p sft
6. N.s P/L 3/4" thick Marble slab of Get
black Granite pre polished spotless
for Counter of required size and
design laid in white cement and
matching pigment over a bed of
3/4" thick cement sand mortar 1:2
i/c cutting hole for lab sink, cocks
etc pere chemical polishing and
making double gola on all exposed
edges complete in all respect as
approved by the Engineer Incharge
490.00 Per Sft
(counter)
7. N.s P/F floor trap grating of stainless
steel 6”x6” complete in all respect
as directed by Engineer in Charge.
21.00 Each
8. N.S Providing and fixing Main D.B
Box 24x18 Circuit Breakers Single
pole (Legrand) 20 Amp triple pole
(Hitachi) M.C.C.B T.P 50 Amp to
100 Amp D.B light and volt meter
complete in all respects as directed
by the Engineer-in-charge.
1.00 Each
9. N.S Supply of Exhust fan 12” sweep
including installation fixing,
wiring installation fixing, wiring,
testing, and commissioning, of
wall fitted of approved make
sweep including cost of blades,
plastic frame/ louver, nuts, bolt, all
necessary fixing with frame
15”x15” accessories, complete in
all respect as directed by the
Engineer in charge. ( GFC Pak).
6.00 Each
10. N.S S/E of Palstic Bord pair(8+2=10
pair) With Bakelite Sheet (Opal)
Switches, making requisite
number of hole for switches
etc.complete in all respect.
24.00 each
11. N.S Supply , Installation of Bracket fan
of 18" Sweep of GFC/PAK or
younus i/c wiring, testing,
commissioning and connecting
etc. Complet in all respects as
directed by engineer incharge.
5.00 Each
12. N.S Supply , installation, fixing,
wiring, testing and Dimmer/
Regulator, bracket,nuts,bolts and
all amounting arrangment,
complete in all respect . Tese items
will be of approved quality and
make. Thes wil consist of as
described and equipped as above
but specified as under: (GFC,PAK,
YOUNS) 56" Sweep
10.00 Each
13. N.S. P/F three way scientific type swan
neck cock ½” dia including C.P
Bend ½” dia 2 Nos, bibe cock 2
No, C.P Barrel Nipple ½” dia 1
No, and C.P Socket ½” With C.P
nozzle, and tee cross and all other
accessories complete in all respect.
37.00 Each
Total Non-Schedule Rs.__________
Add 16% PRA Tax on Non-Schedule Items Rs.__________
Total Rs._____________
D.N.I.T. Engineering Cell
Name of work:- Construction of Textile & Interior Design Department, Fine Arts PG-III
LCW University, Lahore. (Based on MRS 1st January, 2017 to 30th
June, 2017)
Schedule Items
S.
No.
Item No. MRS. Description of work Quantity Unit Rate in
Rs.
Amount in
Rs.
1. 20/Ch-4 Dismantling cement concrete
reinforced, separating reinforcement
from concrete, cleaning and
straightening the same.
400.00 Cft 100 Cft 10454.40 41818.00
2. 22(b)/Ch-4 Dismantling 2nd class tile roofing.
5500.00
Sft
100 Sft 726.00 39930.00
3 13/Ch-4 Dismantling brick work in lime or
cement mortar.
700.00 Cft 100 Sft 2468.40 17279.00
4.
A
6(a)(2)/Ch-6
Reinforced cement concrete in roof
slab, beams, columns lintels, girders
and other structural members laid in
situ or present laid in position, or
pre-stressed members cast in situ,
complete in all respects
Type B (nominal mix 1: 1½: 3)
800.00 Cft
Per Cft
368.00
294400.00
B 6(a)(3)/Ch-6 Type C (nominal mix 1:2:4).
6000.00
Cft
Per Cft 338.90 2033400.00
5. 6(d)/Ch-6 Extra labour for R.C. concrete in 2nd
and subsequent storeys.
6800.00
Cft
Per Cft 21.80 148240.00
6. 9(b)/Ch-6 Fabrication of mild steel
reinforcement for cement concrete,
including cutting, bending, laying in
position, making joints and
fastenings, including cost of binding,
wire and labour charges for binding
of steel reinforcement (also includes
removal of rust form bars) 40 grade
Deformed bars.
28000.00
Kg
100 Kg 9980.20 2794456.00
7. 5+6(ii)/Ch-7 Pacca brick work in second floor
cement sand mortar 1:5
9979.00
Cft
100 Cft 22735.70 2268795.00
8. 5+6(ii)/Ch-7 Pacca brick work in 3rd floor cement
sand mortar 1:5
1000.00
Cft
100 Cft 23646.50 236465.00
9. 10(b)/Ch-11 Cement plaster 3/8" thick under
soffit of R.C.C. roof slabs only, upto
20' height. 1:3
6000.00
Sft
100 Sft 1975.00 118500.00
10. 9(b)/Ch-11 Cement plaster 1:4 upto 20’ height
½” thick.
16750.00
Sft
100 Sft 1740.70 291567.00
11. 9(c)/Ch-11 Cement plaster 1:4 upto 20’ height
¾” thick.
16750.00
Sft
100 Sft 2338.20 391649.00
12. 7©/Ch-12 First class deodar wood wrought
joinery in doors and windows, etc.
panelled, or panelled or glazed, or
fully glazed, fixed in position, i/c
chowkat, holdfast, hinges, tower
bolts, chocks, rubber stop, cleats/G.I.
clamps, handles and chord with
hooks, etc. complete (excluding
sliding bolt or lock) 1½" thick.
350.00 Sft Per Sft 1062.80 371980.00
13. 51/Ch-25 P/F all types of partly fixed and
partly openable glazed anodised
bronze colour aluminium doors,
using delux section of M/s Al-Cop or
Pakistan Cables, having chowkat
frame of size (1½" x4") and leaf
frame of (2½"x1½") wide sections
i/c the cost of ¼" thick imported
tinted glass with aluminium
triangular gola and rubber gasket to
support the glass and leaf edging,
using approved standard fittings,
locks, 3" wide long handles etc., and
hardware any required as approved
by the engineer in-charge.
80.00 Sft Per Sft 538.25 43060.00
14. 18(iv)/Ch-12 P/F sliding bolt to doors brass
sliding bolt, 12" long.
20.00
Nos.
Each 337.75 6755.00
15. 44/Ch-25 P/F windows consisting of M.S. box
section frame 2"x1½", leaves frame
1½"x1" box section frame for
glazing 3/8"x3/8" using 16 SWG
sheet 'U' shaped rubber supported
with 1"x1/8" M.S. flat for fixing
3/16" (5 mm) thick glass panes M.S.
box section ½"x½" of 16 SWG for
fixing 24 SWG wire gauze on outer
side by means of ¾"x1/8" M.S. flat
and screws including grill of M.S.
flat ½"x1/8" or ¼"x¼" square bar
with independent frame of ½"x½"
box section of 16 SWG i/c all C.P.
fitting and painting 3 coats complete
in all respect.
600.00 Sft Per Sft 469.10 281460.00
16. 5©/Ch-13 Painting of door & windows any type
i/c edges on new surface 3 coats.
1000.00
Sft
100 Sft 1521.45 15215.00
17. 31/Ch-13 Preparing surface and painting with
emulsion paint: on new surface 3
coats.
18000.00
Sft
100 Sft 1122.55 202059.00
18. 3/Ch-10 P/L, watering and ramming brick
ballast 1½" to 2" gauge mixed with
25% sand, for floor foundation,
complete in all respects.
2500.00
Cft
100 Cft 4395.85 109896.00
19. 5(f)/Ch-6 Cement concrete plain i/c placing,
compacting, finishing and curing
complete (i/c screening and washing
of stone aggregate) 1:2:4.
1500.00
Cft
100 Cft 20849.40 312741.00
20. 35(iii)/Ch-9 P/L roof insulation, comprising of
single layer of tiles 9"x4½"x1½"
grouted with cement sand mortar 1:3
laid over 2" thick earth (i/c mud
plaster) over thermopore sheet, over
polythene sheet 300 gauge over a
layer of bitumen, complete in all
respects, Thermopore sheet 1"
7000.00
Sft
100 Sft 7284.40 509908.00
21. 15/Ch-9 Khuras on roof 2'x2'x6"
10.00
Nos.
Each 461.45 4515.00
22. 16/Ch-9 Bottom Khuras of brick masonry in
cement mortar 1:6, 4'x2'x4½" over 3"
cement concrete 1:4:8.
10.00
Nos.
Each 848.25 8483.00
23. 33/Ch-25 P/F stair railing (all types and
designs) of hard wood, i/c bends and
corners, screwed to 5/8"x5/8" M.S.
square bars 2.75 ft. high, at 5.5 inch
inch centre to centre, fixed in steps of
stairs, M.S. flat 1"x1/8" welded to
bars, painting/polishing 3 coats, etc.
complete.
100.00 Rft Per Rft 823.10 82310.00
24. 32A/Ch-13 P/A weather shield paint of approved
quality on external surface of
building including preparation of
surface, application of primer
complete in all respect on new
surface two coats.
2762.00
Sft
100 Sft 2089.50 57712.00
25. 12/Ch-6 P/F ornamental cement 15ail 2” thick
(1: 2: 4), without steel.
900.00 Sft Per Sft 55.95 50355.00
26. 14(a)/Ch-12 P/F mild steel chowkat of doors,
windows, C. window, etc. i/c
holdfast, making and threading holes
for hinges, etc. completeM.S. angle
iron 1½"x 1½"x ¼" welded with
M.S. flat 2"x ¼"
200.00 Sft Per Sft 137.50 27500.00
27.
P/L, Cutting, jointing, testing and
disinfecting pipe line trenches, with
PVC pipes of B.S.S. with ‘B’ class
working pressure complete in all
A
26(a)/Ch-23
respects.
3” dia
251.00 Rft
Per Rft
106.05
26619.00
B 26(b)/Ch-23 4” dia 350.00 Rft Per Rft 159.05 55668.00
28.
A
37(i)(a)/Ch-23
P/I PVC bends of B.S.S. ‘B’ class
working pressure
3” dia.
20.00
Nos.
Each
222.35
4447.00
B
37(i)(b)/Ch-23 4” dia. 15.00
Nos.
Each 379.15 5687.00
29.
A
38(i)(a)/Ch-23
P/I PVC tee of B.S.S. ‘B’ class
working pressure
3” dia.
8.00 Nos.
Each
624.50
4996.00
B 38(i)(b)/Ch-23 4” dia. 8.00 Nos. Each 1101.65 8813.00
30.
A
22(iib)/Ch-23
P/L cutting, jointing, testing and
disinfecting G.I. pipeline in trenches,
with socket joints, using G.I. pipes of
B.S.S. 1387-1967 complete in all
respects, with Medium Quality
¾” dia
400.00 Rft
Per Rft
78.70
31480.00
B 22(iic)/Ch-23 1” dia 300.00 Rft Per Rft 108.30 32490.00
C
22(iie)/Ch-23 1 ½” dia 300.00 Rft Per Rft 174.10 52230.00
31. 6(ii)/Ch-19 P/F glazed earthen ware wash hand
basin (22”x16”) i/c bracket set, waste
pipe and waste coupling, etc.,
Coloured , with pedestal.
3.00 Nos. Each 2679.75 8039.00
32. 7/Ch-19 P/F stainless steel sink with drain
board, size (48"x24") including
bracket set, waste pipe and waste
coupling.
1.00 No. Each 4434.15 4434.00
33. 26(ii)/Ch-19 P/F chromium plated bib cock. ½”
dia
2.00 Nos. Each 316.45 633.00
34. 39(i)/Ch-19 S/F of cast iron manhole cover with
frame, etc. complete.
1.00 No. Each 197.25 197.00
35. 23(ii)/Ch-19 P/F chromium plated pillar-cock,
heavy ½” dia
4.00 Nos. Each 699.50 2798.00
36. 29/Ch-19 P/F chromium plated mixing valve,
for wash hand basin, sink or shower.
10.00
Nos.
Each 1558.40 15584.00
37. 34(ii)/Ch-19 P/F “P” trap 4” dia glazed. 10.00
Nos.
Each 136.60 1366.00
38. 3(ii)/Ch-19 P/F glazed earthen ware water closet,
squatter type, (Orisa pattern)
combined with foot rest, Coloured
4.00 Nos. Each 1415.15 5661.00
39. 12(ii)/Ch-19 P/F plastic made low down flushing
cistern 1363 litter (3gallons) capacity
i/c bracket set copper connection,
complete Coloured.
47.00
Nos.
Each 1179.80 4719.00
40. 1(ii)/Ch-19 P/F glazed earthen ware water closet
European type, excluding seat and
cove Coloured.
1.00 No. Each 2333.05 2333.00
41. 11(ii)/Ch-19 P/F glazed earthen ware low down
flushing cistern 13,63 litres (3
gallons) capacity, i/c bracket set,
copper connection, etc. Coloured
1.00 No. Each 1419.80 1420.00
42. 2(ii)/Ch-19 P/F double seat and cover only
Plastic.
1.00 No. Each 232.30 232.00
43. 15/Ch-19 P/F chromium plated soap dish. 3.00 Nos. Each 192.70 578.00
44. 18(ii)/Ch-19 P/F chromium plated towel rail 20”
long and ½” dia.
3.00 Nos. Each 297.55 893.00
45. 19/Ch-19 P/F looking glass 22”x16” size &
5mm thick first quality.
5.00 Nos. Each 383.70 1919.00
46. 17/Ch-19 P/F, chromium plated toilet paper
holder.
5.00 Nos. Each 412.75 2064.00
47. 27/Ch-19 P/F chromium plated tee stop cock
½” dia
20.00
Nos.
Each 453.50 9070.00
48.
A
3(ii)/Ch-24
S/E of PVC pipe for wiring recessed
in walls, i/c inspection boxes, pull
boxes, hooks, cutting jharries, and
repairing surface, etc., complete with
all specials.
¾” dia
4000.00
Rft
Per Rft
38.30
153200.00
B 3(iii)/Ch-24 1” dia 1000.00
Rft
Per Rft 45.30 45300.00
C 3(vi)/Ch-24 2” dia 500.00 Rft Per Rft 76.80 38400.00
49.
A
10(a)(i)/Ch-24
S/E of single core PVC insulated
copper conductor cables, in prelaid
PVC pipe/M.S. conduit/G.I pipe/
wooden strip batten/wooden casing
an capping/G.I. wire/trenches (rate
for cables only)
3/0.029
7000.00
Rft
Per Rft
11.45
11450.00
B 10(a)(iii)/Ch-24 7/0.029 4000.00
Rft
Per Rft 15.75 63000.00
C 10(a)(iv)/Ch-24 7/0.036 2000.00
Rft
Per Rft 22.70 45400.00
D 10(a)(vi)/Ch-24 7/0.064 1000.00
Rft
Per Rft 75.35 75350.00
50. 30/Ch-24 S/E of ceiling rose bakelite.
50.00
Nos.
Each 37.25 1863.00
51. 39(i)/Ch-24 S/E of button holder bakelite large
size.
40.00
Nos.
Each 29.60 1184.00
52. 45/Ch-24 S/E of girder clamp hook, (5/8") with
M.S. plate (1"x¼"), with bolts and
nuts for hanging & ceiling fans.
30.00
Nos.
Each 154.55 4637.00
Total Schedule Items Rs. 11484602.0
Add 16% PRA Tax on Schedule Items Rs.
Total Amount Schedule Items Rs.
Rate quoted percentage above or blew on Schedule Items Rs.
Total Amount Schedule Items Rs.
Total Schedule Items Rs._______________
Total Non Schedule Items Rs._______________
Grand Total Rs.______________
D.N.I.T. Engineering Cell
Name of work:- Construction of Textile & Interior Design Department, Fine Arts PG-III
LCW University, Lahore. (Based on MRS 1st January, 2017 to 30th
June, 2017)
Non- Schedule Items
S.
No.
Item No.
MRS.
Description of work Quantity Unit Rate in Rs. Amount in
Rs.
1. N.S. Laying Floor of glazed tiles
(Master) ¼” thick size16”x16”
laid in pigment over 1:2 cement
sand mortar ¾” thick i/c finishing
complete in all respects as directed
by the Engineer in charge.
7000.00 Sft Per Sft
2. N.S. Laying Dado of glazed tiles
(Master) ¼” thick size16”x16”
laid in pigment over 1:2 cement
sand mortar ¾” thick i/c finishing
complete in all respects as directed
by the Engineer in charge.
800.00 Sft Per Sft
3. N.S. Providing and laying in position
pre-polished marble slab China
Verona laid in with ¾” thick C:S
mortar and grouted filled in with
matching colour cement. i/c the
cost of grinding, chemical
polishing complete in all respects
as par design pattern shown on the
drawing and as approved by the
Engineer-in-charge. Marble slab
China Verona ¾” thick 5’x1’
150.00 Sft Per Sft
4. N.S. Providing and laying in position
pre-polished marble slab China
Verona laid in with ¾” thick C:S
mortar and grouted filled in with
matching colour cement. i/c the
cost of grinding, chemical
polishing complete in all respects
as par design pattern shown on the
drawing and as approved by the
Engineer-in-charge. Marble slab
China Verona ¾” thick 5’x6”
190.00 Sft Per Sft
5. N.S. P/F false ceiling for gypsum board
2’x2’ with aluminium tee fixing i/c
labour etc. complete in all respects
as directed by the Engineer
incharge.
5000.00 Sft Per Sft
6. N.S. P/L gutka of cladding on wall size
9”x3”x 2 ¼” laid with cement
surkhi mortar 1:3 i/c cutting of
gutka with grinder mortar filling
1:6 on back side gutka i/c
scaffolding etc complete in all
respects as directed by the
Engineer Incharge.
5000.00 Sft Per Sft
7. N.S. P/F UPVC Grooved Door 1 ½”
thick of approved design and
colour i/c cost of fitting and
fixture, locking arrangement,
Transporation etc. complete in all
respect as directed by the Engineer
In charge.
200.00 Sft Per Sft
8. N.S. Laying Dado of glazed tiles
(Master) ¼” thick size 12”x18”
laid in pigment over 1:2 cement
sand mortar ¾” thick i/c finishing
complete in all respects as directed
by the Engineer in charge.
900.00 Sft Per Sft
9. N.S. Laying Floor of glazed tiles
(Master) ¼” thick size 12”x18”
laid in pigment over 1:2 cement
sand mortar ¾” thick i/c finishing
complete in all respects as directed
by the Engineer in charge.
300.00 Sft Per Sft
10. N.S. Providing & fixing Tower Bolt
made of Iron 10” long , complete
in all respect.
23.00 Nos. Each
11. N.S. P/F floor trap grating of stainless
steel 6”x6” complete in all
respects as directed by the
Engineer-in-Charge.
20.00 Nos. Each
12. N.S. P/F chromium plated double bib
cock ½” dia made by (Master
ECO) complete in all respects as
directed by the Engineer-in-
charge.
6.00 Nos. Each
13. N.S. P/F Muslim shower with PVC
flexible coloured pipe (Master) etc
complete in all respects.
6.00 Nos. Each
14. N.S. S/E of Plastic Board 4 pair with
Bakelite sheet (Opal), Switches,
making requisite number of holes
for switches etc. complete in all
respect.
10.00 Nos. Each
15. N.S. S/E of Plastic Board 10 pair with 20.00 Nos. Each
Bakelite sheet (Opal), Switches,
making requisite number of holes
for switches etc. complete in all
respect.
16. N.S. Supply of Exhaust Fan 12” sweep
i/c installation, fixing, wiring,
testing, and commissioning, of
wall fitted of approved make
sweep including cost of blades,
plastic frame/louvers, nuts, bolts,
all necessary fixing with frame
15”x15” accessories, complete in
all respect as directed by the
Engineer Incharge. (GFC, PAK).
15.00 Nos. Each
17. N.S. Supply, installation, fixing, wiring,
testing and commissioning of fans
with required requisite sweep i/c
cost of Blades, hanging rod,
canopy, capacitor, Dimmer
/regulator, bracket, nuts, bolts and
all amounting arrangement,
complete in all respects. These
items will be of approved quality
and make. These will consist of as
described and equipped as above
but specified as under:- (GFC,
PAK. Youns) 56” Sweep
30.00 Nos. Each
18. N.S. Supply, installation of Bracket Fan
of 18” Sweep of GFC/ PAK or
Younus i/c wiring, testing,
commissioning and connecting
etc. complete in all respects as
directed by the Engineer incharge.
24.00 Nos. Each
19. N.S. P/F 23 watts Energy Saver Philips
Company Complete in all respects
as director by the Engineer
Incharge.
40.00 Nos. Each
20. N.S. S/E of Light plug with box 5/Amp
Multi Function (Opal) made by
China complete in all respects.
48.00 Nos. Each
21. N.S. Supply and erection of Power plug
with box 10 to 15/Amp (Opal)
made by China complete in all
respects.
25.00 Nos. Each
22. N.S. P/F of D.B. Powder coated
consisting of MCCB 3 Pole
Breaker 100 to 125/Amp
(HITACHI) 1No., MCB 16 to
20/Amp single pole breake
1.00 No. Each
(Legrand) 27Nos., Indication
Lights 3Nos., Volt Meter Analog
3Nos., D.B. Box with cover
16SWG Size 24”x36” 1No., i/c
paint powder coated open able 3
coats complete in all respect as
directed by the Engineer-in-
charge.
23. N.S. P/F of LED ceiling 3” down light
7 watts Make by CREST China
Model CR -7017 CR-012-CLR
LED Type complete in all respect
as directed by the Engineer-in-
charge.
250.00 Nos. Each
Total Non-Schedule Rs.__________
Add 16% PRA Tax on Non-Schedule Items Rs.__________
Total Rs._____________
D.N.I.T. Engineering Cell
Name of work:- Additional Alteration for connecting the old I.T. Building with New I.T.
Building at LCW University, Lahore. (Based on MRS 1st January, 2017
to 30th June, 2017)
Schedule Items
S.
No.
Item No. MRS. Description of work Quantity Unit Rate in
Rs.
Amount in
Rs.
1. 13/Ch-4 Dismantling brick work in lime or
cement mortar.
480.00 Cft 100 Sft 2468.40 11848.00
2. 32(a)/Ch-4 Removing door with chowkat.
2.00 Nos. Each 232.65 465.00
3. 32(b)/Ch-4 Removing window & sky light with
chowkat.
3.00 Nos. Each 179.85 540.00
4. 21(b)/Ch-3 Excavation in foundation of building,
bridges and other structures,
including dagbelling, dressing,
refilling around structure with
excavated earth, watering and
rammiing lead upto one chain and
lift upto 5 ft. in ordinary soil.
50.00 Cft 1000
Cft
6130.10 307.00
5. 2/Ch-6 Dry rammed brick or stone ballast,
1½" to 2" gauge.
20.00 Cft 100 Cft 4092.00 818.00
6. 4(i)/Ch-7 Pacca work in foundation & plinth
cement sand mortar 1:6
60.00 Cft 100 Cft 19503.40 11702.00
7. 5(i)/Ch-7 Pacca brick work in ground floor
cement sand mortar 1:5
200.00 Cft 100 Cft 21079.10 42158.00
8. 5+6(ii)/Ch-7 Pacca brick work in first floor
cement sand mortar 1:5
1050.00
Cft
100 Cft 21824.90 229161.00
9. 6(a)(3)/Ch-6 Reinforced cement concrete in roof
slab, beams, columns lintels, girders
and other structural members laid in
situ or present laid in position, or
pre-stressed members cast in situ,
complete in all respects Type C
(nominal mix 1:2:4).
650.00 Cft Per Cft 338.90 220285.00
10. 9(b)/Ch-6 Fabrication of mild steel
reinforcement for cement concrete,
i/c cutting, bending, laying in
position, making joints and
fastenings, including cost of binding,
wire and labour charges for binding
of steel reinforcement (also includes
removal of rust form bars) 40 grade
Deformed bars.
1900.00
Kg
100 Kg 9980.20 189624.00
11. 30/Ch-7 S/F sand under floor or plugging in
wells.
145.00 Cft 100 Cft 1562.00 2265.00
12. 3/Ch-10 P/L, watering and ramming brick
ballast 1½" to 2" gauge mixed with
25% sand, for floor foundation,
complete in all respects.
170.00 Cft 100 Cft 4395.85 7473.00
13. 5(f)/Ch-6 Cement concrete plain i/c placing,
compacting, finishing and curing
complete (i/c screening and washing
of stone aggregate) 1:2:4.
110.00 Cft 100 Cft 20849.40 22934.00
14. 35(iii)/Ch-9 P/L roof insulation, comprising of
single layer of tiles 9"x4½"x1½"
grouted with cement sand mortar 1:3
laid over 2" thick earth (i/c mud
plaster) over thermopore sheet, over
polythene sheet 300 gauge over a
layer of bitumen, complete in all
respects, Thermopore sheet 1"
480.00 Sft 100 Sft 7284.40 34965.00
15. 15/Ch-9 Khuras on roof 2'x2'x6"
1.00 No. Each 461.45 461.00
16. 16/Ch-9 Bottom Khuras of brick masonry in
cement mortar 1:6, 4'x2'x4½" over 3"
cement concrete 1:4:8.
1.00 No. Each 848.25 848.00
17. 10(b)/Ch-11 Cement plaster 3/8" thick under
soffit of R.C.C. roof slabs only, upto
20' height. 1:3
750.00 Sft 100 Sft 1975.00 14812.00
18. 9(b)/Ch-11 Cement plaster 1:4 upto 20’ height
½” thick.
3700.00
Sft
100 Sft 1740.70 64406.00
19. 49(b)/Ch-4 Scraping, Ordinary distemper, oil
bound distemper, or paint of wall.
200.00 Sft 100 Sft 435.60 871.00
20. 31/Ch-13 Preparing surface and painting with
emulsion paint: on old surface 2
coats.
300.00 Sft 100 Sft 781.20 2344.00
21. 5©/Ch-13 Painting of door & windows any type
i/c edges on new surface 3 coats.
280.00 Sft 100 Sft 1521.45 4260.00
22. 31/Ch-13 Preparing surface and painting with
emulsion paint: on new surface 3
coats.
4000.00
Sft
100 Sft 1122.55 44902.00
23. 32A/Ch-13 P/A weather shield paint of approved
quality on external surface of
building i/c preparation of surface,
application of primer complete in all
respect on new surface two coats.
1500.00
Sft
100 Sft 2089.50 31343.00
24. 14(a)/Ch-12 P/F mild steel chowkat of doors,
windows, C. window, etc. i/c
46.00 Sft Per Sft 137.50 6325.00
holdfast, making and threading holes
for hinges, etc. complete, M.S. angle
iron 1½"x 1½ "x ¼" welded with
M.S. flat 2"x ¼"
25. 26(b)/Ch-23
P/L, Cutting, jointing, testing and
disinfecting pipe line trenches, with
PVC pipes of B.S.S. with ‘B’ class
working pressure complete in all
respects. 4” dia
20.00 Rft Per Rft 159.05 3181.00
26. 37(i)(b)/Ch-23
P/I PVC bends of B.S.S. ‘B’ class
working pressure 4” dia.
3.00 Nos. Each 379.15 1137.00
27.
A
22(iib)/Ch-23
P/L cutting, jointing, testing and
disinfecting G.I. pipeline in trenches,
with socket joints, using G.I. pipes of
B.S.S. 1387-1967 complete in all
respects, with Medium Quality
¾” dia
60.00 Rft
Per Rft
78.70
4722.00
B 22(iic)/Ch-23 1” dia 20.00 Rft Per Rft 108.30 2166.00
28. 39(i)/Ch-19 S/F of cast iron manhole cover with
frame, etc. complete.
1.00 No. Each 197.25 197.00
29. 9/Ch-19 P/F glazed earthen ware sink, i/c
bracket set, waste pipe and waste
coupling 24"x18"
6.00 Nos. Each 1711.40 10268.00
30. 23(ii)/Ch-19 P/F chromium plated pillar-cock,
heavy ½” dia
6.00 Nos. Each 699.50 4197.00
31. 34(ii)/Ch-19 P/F “P” trap 4” dia glazed. 2.00 Nos. Each 136.60 283.00
32. 27/Ch-19 P/F chromium plated tee stop cock
½” dia
6.00 Nos. Each 453.50 2721.00
33.
A
3(ii)/Ch-24
S/E of PVC pipe for wiring recessed
in walls, i/c inspection boxes, pull
boxes, hooks, cutting jharries, and
repairing surface, etc., complete with
all specials.
¾” dia
1000.00
Rft
Per Rft
38.30
38300.00
B 3(iii)/Ch-24 1” dia 500.00 Rft Per Rft 45.30 22650.00
34.
A
10(a)(i)/Ch-24
S/E of single core PVC insulated
copper conductor cables, in prelaid
PVC pipe/M.S. conduit/G.I pipe/
wooden strip batten/wooden casing
an capping/G.I. wire/trenches (rate
for cables only)
3/0.029
3000.00
Rft
Per Rft
11.45
34350.00
B 10(a)(iii)/Ch-24 7/0.029 1800.00
Rft
Per Rft 15.75 28350.00
C 10(a)(v)/Ch-24 7/0.044 1200.00
Rft
Per Rft 31.95 38340.00
35. 43(iv)/Ch-24 S/E of tube light, i/c rod, choke,
starter with frame, flexible wire, i/c
connection from ceiling rose, etc.,
complete. round tube, 32 watt with
one chock and one starter, with
cover.
15.00
Nos.
Each 818.75 15281.00
36. 43(ii)/Ch-24 S/E of tube light, i/c rod, choke,
starter with frame, flexible wire, i/c
connection from ceiling rose, etc.,
complete. single rod (40 watts) with
one choke and one starter
8.00 Nos. Each 676.65 5413.00
37. 30/Ch-24 S/E of ceiling rose, bakelite. 8.00 Nos. Each 37.25 298.00
Total Schedule Items Rs. 1156971.00
Add 16% PRA Tax on Schedule Items Rs.
Total Amount Schedule Items Rs.
Rate quoted percentage above or blew on Schedule Items Rs.
Total Amount Schedule Items Rs.
Total Schedule Items Rs._______________
Total Non Schedule Items Rs._______________
Grand Total Rs.______________
D.N.I.T. Engineering Cell
Name of work:- Additional Alteration for connecting the old I.T. Building with New I.T.
Building at LCW University, Lahore. (Based on MRS 1st January, 2017
to 30th June, 2017)
Non- Schedule Items
S.
No.
Item No.
MRS.
Description of work Quantity Unit Rate in Rs. Amount in
Rs.
1. N.S. Re-fixing of doors & windows
complete in all respects as directed
by the Engineer in charge.
6.00 Nos. Each
2. N.S. Dismantling of cement jali etc
complete in all respects as directed
by the Engineer in charge.
330.00 Sft Per Sft
3. N.S. Laying Floor of glazed tiles
(Master) ¼” thick size16”x16”
laid in pigment over 1:2 cement
sand mortar ¾” thick i/c finishing
complete in all respects as directed
by the Engineer in charge.
650.00 Sft Per Sft
4. N.S. Laying Floor of glazed tiles
(Master) ¼” thick size10”x8” laid
in pigment over 1:2 cement sand
mortar ¾” thick i/c finishing
complete in all respects as directed
by the Engineer in charge.
150.00 Sft Per Sft
5. N.S. P/F false ceiling for gypsum board
2’x2’ with aluminium tee fixing i/c
labour etc. complete in all respects
as directed by the Engineer
incharge.
325.00 Sft Per Sft
6. N.S. P/F of M.S. security grill door
consisting of 1 ½”x 1 ½” 18SWG
M.S. pipe frame i/c solid bar 3/8”
x 3/8” in windows as per drawings
i/c enamel painting three coats,
complete in all respects.
46.00 Sft Per Sft
7. N.S. P/F floor trap grating of stainless
steel 6”x6” complete in all
respects as directed by the
Engineer-in-Charge.
2.00 Nos. Each
8. N.S. S/E of Plastic Board 10 pair with
Bakelite sheet (Opal), Switches,
making requisite number of holes
5.00 Nos. Each
for switches etc. complete in all
respect.
9. N.S. S/E of Light plug with box 5/Amp
Multi Function (Opal) made by
China complete in all respects.
10.00 Nos. Each
10. N.S. S/E of Power plug with box 10 to
15/Amp (Opal) made by China
complete in all respects.
4.00 Nos. Each
Total Non-Schedule Rs.__________
Add 16% PRA Tax on Non-Schedule Items Rs.__________
Total Rs._____________