SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 2 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

REVISION CONTROL

Issued for Internal Review

Issued for Client Review

Issued for DFS

REVISION HISTORY

Revision Date Pages Revised Remarks 00 18/08/2017 Multiple Minor Comments incorporated from review. 01 29/03/18 1 Update of Section 1.2 to reference tank datasheet. 02 03/04/18 1 Corrected Status to Issued for DFS

Page 3: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 3 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

TABLE OF CONTENTS 1 SCOPE OF WORK 5

1.1 INTRODUCTION 5

1.2 WORK INCLUDED 5

1.3 OFFSITE FABRICATION AND DELIVERY 5 1.4 ON-SITE INSTALLATION 6

1.4.1 Site Mobilisation / Demobilisation 6

1.4.2 Installation Works 6

1.4.3 Health, Safety, Environment and Quality 7

1.5 WORK EXCLUDED 7

1.5.1 Engineering and Services 7 1.5.2 Provided by the Principal 7

1.6 BATTERY LIMITS 8 2 DESIGN REQUIREMENTS 8

2.1 STANDARDS AND SPECIFICATIONS 8

2.2 CONFORMING DESIGN 8

2.3 DESIGN LOADS 8 2.4 REQUIREMENTS FOR PLATFORM SUPPORTS AND LIFTING 8

3 TECHNICAL REQUIREMENTS 9

3.1 GENERAL 9

3.2 MATERIALS OF CONSTRUCTION 9

3.3 STRUCTURAL 9 3.4 ELECTRICAL 9

3.5 SURFACE TREATMENT 9

3.6 ENGINEERING DOCUMENTATION 9

3.7 EQUIPMENT IDENTIFICATION, MARKING AND LABELLING 10 4 WORK EXCLUDED 10

5 BATTERY LIMITS 10 6 QUALITY CERTIFICATIONS AND REQUIREMENTS 10

6.1 QA REQUIREMENTS - GENERAL 10

6.2 INSPECTION AND TESTING 10

6.2.1 Inspection of Welds 11

6.3 VISUAL DEFECTS 11

6.4 FIELD TESTING 12 6.5 PRESSURE TESTING 12

6.6 INSTALLATION OPERATION AND MAINTENANCE MANUALS 12

6.7 MANUFACTURER’S DATA REPORT 12

Page 4: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 4 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

6.8 CONTRACTOR REPRESENTATION 12 7 PACKING, TRANSPORT AND STORAGE 12

8 CONTRACTOR RESPONSIBILITY MATRIX 13 9 PROGRAMME 15

10 REPORTING REQUIREMENTS 15

11 EMPLOYEE AND INDUSTRIAL RELATIONSHIP MANAGEMENT 15

12 REFERENCE DOCUMENTS 15

13 VENDOR DATA REQUIREMENTS SCHEDULE 30

LIST OF TABLES

Table 1 Contractor Responsibility Matrix 13 Table 2 Reference Document 15 Table 3 Vendor Data Requirements 30

Page 5: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 5 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

1 SCOPE OF WORK

1.1 INTRODUCTION

This document sets out the scope of work and technical requirements for the design, manufacture, supply, erection and testing of carbon steel and stainless steel tanks for the Clean TeQ Sunrise in New South Wales, Australia.

SNC-Lavalin Australia Pty Ltd (the Client’s Representative) is managing the project on behalf of Clean TeQ (the Client).

1.2 WORK INCLUDED

The Scope includes the engineering, detailed design and fabrication of the tanks listed below. The Principal will provide Design General Arrangement drawings with specifications and set-out information.

The Contractor shall provide all labour, materials, parts and services necessary to carry out the design, workshop detailing, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification and packaging, together with the provision of all necessary services, relating to the site fabricated tanks as provided in 140316-0000-45ED-TK0003, Equipment Datasheet - Site Erected Welded Tanks.

The Contractor shall include in the scope of work items, accessories and services that are usual or necessary to complete the work, but which may not have been specifically mentioned herein.

1.3 OFFSITE FABRICATION AND DELIVERY

The scope of work for off-site fabrication shall include, but not be limited to the following:

• Tank sub-assemblies and materials with all listed appurtenances • Internal baffles (if required) • Dip pipes and Up comers • Lute pot and vent dryer for sulphuric acid tanks • Overflow Boxes • Stiffeners • Nozzles and Compensation plates • Earthing lugs • Tank hold-down brackets • Gaskets • Tank manhole covers with permanent hinges or lifting arms, blank mating flanges and bolts where

specified for spare nozzles • Flange protectors on pre-assembled nozzles to protect flanges from damage in transport • Surface protection in prefabrication and after site completion • Non Destructive Testing (NDT) of welds in accordance with the requirements listed in section 6.2.1,

including provision of records • Stand-off mesh (where specified on the datasheets) • Insulation supports (as specified) • Supports for associated stairways, walkways, inspection platforms and attached structures for tanks • All ancillary items normally supplied with the equipment • All nuts, bolts, shims, fasteners and gaskets for the complete assembly of the equipment • General arrangement and shop drawings

Page 6: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 6 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

• Design and installation of lifting lugs, lifting beams and stiffeners as may be required to facilitate lifting of the individual items, as well as to provide points of tie down during transport

• Packaging including temporary supports where necessary, props, bracing, dunnage and lashing of all supplied components suitable for transport to site

• Provide loads and details for the design of the support foundation by others • Vendor Drawing and Data Requirements (VDDR) as specified • Packing, loading and transportation of the materials and pre-fabricated sections to site.

1.4 ON-SITE INSTALLATION

The scope of work for onsite installation shall include, but not be limited to the following major sections of work as detailed further in the following sections:

• Site Mobilisation / Demobilisation • Installation Work • Health, Safety, Environment and Quality.

1.4.1 Site Mobilisation / Demobilisation

The Contractor shall be responsible for the following mobilisation and demobilisation:

• Mobilisation of labour, material, plant & equipment, tools, and consumables required to perform the site installation of the tanks

• Demobilisation of labour, material, plant & equipment, tools, required to perform the site installation of the tanks

• Mobilise and demobilise staff and management to perform the site installation of the tanks.

1.4.2 Installation Works

The Contractor shall be responsible to perform the installation of the tanks required as per the technical documents (Specification, Drawings etc) and quantity as listed within this Scope of Work and as listed below:

• Supervision for performing the works • Supply of all materials, equipment, tools, cranes, consumables, temporary construction power,

construction water, lighting, lubricants, cleaning materials, construction vehicles, site office(s), stores, accommodation, etc. required in order to carry out the on-site tanks erection

• Welding, bolting, grouting , painting • Survey and acceptance of concrete foundations (constructed by others) prior to tank installation • All scaffolding works, as required • Passivation of stainless steel welds • Testing and Quality compliance, as required • Non Destructive Testing (NDT) of welds as required in the Technical Specification and drawings,

including provision of records • Hydrostatic testing • Touch up painting after installation (as required) • Mark-up and supply of as-built drawings • Any special tools and equipment required to install, adjust or maintain the equipment • Manufactures Data Report (MDR) • Vendor Drawing and Data Requirements (VDDR) as specified

Page 7: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 7 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

1.4.3 Health, Safety, Environment and Quality

The Contractor shall be responsible for Health, Safety and Environment compliance during the entire duration of project. The Contractor shall be fully responsible for the following:

• HSEQ inspectors/representatives commensurate with the workforce manning levels and job fronts • Medicals, pre-employment testing for their employers as required including any statutory medicals • Ensuring personnel employed are fit for the work, including any training requirements • Ensuring that the plant and equipment mobilised are suitable and are maintained in good condition to

perform the work • Ensuring developing, implementing various Safety control measures / procedures (Risk Analysis /JSEA

/ Daily Pre-starts, Tool Box, alcohol and drug testing etc.) • Provision of PPE for Contractor personnel who will visit / work on site • Meeting or exceeding the industry standards and legal compliance requirements • Meeting the environmental standards as per legal and Construction standards • Develop and implement project specific HSE Plan • Provision of a full time HSE Supervisory staff as required • Provision of safety representatives as per industry standards • Provision of quality representative for quality assurance • Develop and implement project specific Quality Plan, ITPs etc. as required • Weekly HSE reporting to the Client as required • Include any site specific inductions, training as required • Traffic control on site throughout site works • Permit to Work as required.

1.5 WORK EXCLUDED

1.5.1 Engineering and Services

• The site will be cleared, back-filled, levelled and compacted to the required bearing strength in accordance with the Contractor’s requirements.

• Equipment foundations will be designed, supplied and installed by others • Equipment anchor bolts will be supplied and installed by others to the Contractor’s design • Equipment access platforms, walkways, hand railing, ladders and stairways will be designed, supplied

and installed by others • Insulation of finished tanks.

1.5.2 Provided by the Principal

The Principal will provide:

• Assigned site laydown and fabrication areas • Small power supply for distribution by the Contractor (hand tools only) • Water for hydrostatic testing at a site standpipe and a DN50 hose connection. • Accommodation and messing for the Contractor’s workforce in the project Construction Camp as per

resourcing schedule provided.

Page 8: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 8 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

1.6 BATTERY LIMITS

The Contractor’s Scope of Work is defined by the following Battery Limits:

• Top of concrete footings, including cast-in hold down bolts • Face of flange for tank nozzles • Top of support stubs for over-tank platforms • Overflow lines at termination flange 0.5 metres above top of foundation.

2 DESIGN REQUIREMENTS

2.1 STANDARDS AND SPECIFICATIONS

The tanks shall be designed and built in accordance with 140316-000-45EG-0002, Technical Specification for Shop & Site Fabricated Tanks, and the drawings and standards referenced therein.

Basic data for the required tanks is provided in Appendix A drawings and 140316-0000-45ED-TK0003, Equipment Datasheet - Site Erected Welded Tanks.

2.2 CONFORMING DESIGN

Unless approved otherwise, all tanks shall comply fully with the requirements of this Scope of Work. The dimensional size, shape and general tank configuration shall be in accordance with the specific datasheet.

The Contractor may supplement their base tender with alternatives provided that they offer significant advantages. For example, if the Contractor identifies alternate tank diameters during tank strake design that result in cost effective tank fabrication, these may be offered as an alternative provided that required tank volume is maintained as per the datasheets.

Full details of any and all areas where the tanks do not conform to any of the requirements of the Specifications shall be submitted to the Client’s Representative for approval.

2.3 DESIGN LOADS

Tanks shall be designed to withstand the most severe combination of:

• Wind loading • Mass of contents • Walkways, stairways and supported structures • Live loads • Roof Loads • Static and dynamic loads applied at nozzles by pipes, agitators and other mechanical equipment • Seismic loads applicable to the region in which the tanks are installed • Lifting and installation loads.

Specific attention shall be given to static and dynamic wind loading effects when the tanks are empty and to the dynamic agitator loads.

2.4 REQUIREMENTS FOR PLATFORM SUPPORTS AND LIFTING

All tanks shall be designed for 4-point support of a bridge structure providing access, and where required a central agitator. The vertical design loads are as per data sheets. Horizontal loads shall be allowed as 10% of vertical. Stiffeners shall be employed to ensure steel buckling does not occur at locations of vertical load into the shell and at locations where there is a risk that the shell curvature may be reduced.

Page 9: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 9 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

Components and tanks shall be provided with means for safe handling by a crane, such as lifting lugs. Lifting devices shall be designed and located so as to permit lifting without damage to the tanks. Lifting lugs shall be stamped with Working Load Limit (WLL).

Where an agitator is supported by the tank, the Contractor shall carry out the detailed design and fabrication of tank baffles based on the agitator Vendor’s recommendations. Agitator and tank baffle drawings shall be provided to the tank designer.

3 TECHNICAL REQUIREMENTS

3.1 GENERAL

The tanks shall be of robust construction, suitable for operation in a heavy industrial process plant. The site erected tanks shall be furnished as complete and operable units.

Consideration shall be given to minimizing on site construction durations and where feasible, shop off -foundation assembling components into the largest economically transportable sections.

3.2 MATERIALS OF CONSTRUCTION

Materials of construction shall be in accordance with the technical specification and the equipment datasheets.

No materials of construction shall be changed after purchase order has been issued. Substitutions require written approval by the Client’s Representative.

3.3 STRUCTURAL

The Contractor shall specify the size of all equipment anchor bolts suitable for all live and dead loads, including dynamic and seismic loading.

The Contractor shall design and specify all equipment anchor bolts and hold-down brackets / lugs to ensure the tank is adequately held down for wind loads when empty.

3.4 ELECTRICAL

Provide two grounding bosses 12mm diameter holes, located at 180° apart on each tank located at least 200mm above the bottom of tanks and suitable to accept a 120mm² grounding cable.

3.5 SURFACE TREATMENT

The surface treatment of steel tanks shall comply with the Specification for Corrosion Protection - 140316-0000-45EG-0001 and datasheet information.

Paint specification for the underside of the floor of site erected tanks shall be as for the external face of tank shells.

3.6 ENGINEERING DOCUMENTATION

The Contractor shall provide the following additional engineering data with their bid:

• GA drawings of each tank including plate work development drawings showing materials selected, thicknesses, ring beams (where applicable), floor and roof cut out profiles, strakes, weld seam locations

• A loading diagram showing operating loads on the tank base, opening dimensions for impeller removal.

Page 10: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 10 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

After placement of purchase order:

• Drawings showing any ladders, platforms, handrails, stairs attached to any tank • Shop drawings of all tanks for review and approval.

3.7 EQUIPMENT IDENTIFICATION, MARKING AND LABELLING

Where components must be separated for shipment, each separable component shall be provided with a clearly stamped stainless steel temporary name tag securely attached to each such component.

All safety and information signage shall be provided and shall be in accordance with AS 1319. These signs shall support the project HSE objectives and as a minimum generally advise workplace health and safety and other statutory requirements/obligations and site-specific requirements.

4 WORK EXCLUDED

The following works shall not be included as part of this scope of work:

(See Contractor Responsibility Matrix Section 8)

• Accommodation Camp • Tank top platform steelwork and Tank Agitators • Insulation • Interconnecting pipework • Equipment access platforms, walkways and hand railing • Concrete footing detailed design.

5 BATTERY LIMITS

The battery limits for this scope of work are as follows:

• Underside of tank • Underside of tank hold-down point • Face of all nozzle connections • Earthing Lug • Top of mounting points for tank-top steelwork.

6 QUALITY CERTIFICATIONS AND REQUIREMENTS

6.1 QA REQUIREMENTS - GENERAL

The Contractor shall provide with the supplied equipment, quality assurance (QA/QC) and quality control procedure to the Client’s Representative for approval.

The Contractor is responsible for the testing and inspection of all materials and work in accordance with this specification and all applicable codes, laws and regulations.

6.2 INSPECTION AND TESTING

The Client’s Representative shall be provided with proper access to work, equipment, tools and facilities for carrying out such inspection, test, witness inspection or test points, surveillance or audit, whether it is in preparation or progress.

Page 11: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 11 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

They shall be authorised to witness any stage of manufacture, test and inspection documentation, and shall be authorised to reject any item which does not conform to the requirements of this specification.

Any omission or failure on the part of the inspectors to disapprove or reject any work or materials shall not be construed as an acceptance of any defective work or sub-standard materials.

The Contractor shall provide a detailed manufacturing program which covers the timing and phasing of all activities relating to off-site and on-site supply and site erection, showing all hold, witness and inspection points. The following inspection milestones shall be the minimum required:

• Material chemical composition and physical properties before fabrication • At fit-up before welding • Welding procedure specifications and weld procedure and welder qualification records • Regular / progressive during fabrication • At fabrication completion • Hydrostatic testing • Protective coating and linings.

Tests shall be carried out and interpreted by suitably qualified QC inspectors.

Material which is shown to be defective during testing shall not be incorporated into any fabrication.

Test and inspect all materials and work in accordance with this specification and the appropriate API standard.

6.2.1 Inspection of Welds

The following requirements shall be adhered to as a minimum:

• All welds shall be subject to 100% visual inspection in accordance with API 650 Section 6 • Longitudinal and circumferential joints on tanks shall be inspected by ultrasonics or spot radiography in

accordance with API Section 6.1 or Section 6.3 and dye penetrant testing in accordance with the appropriate API standard

• Critical and/or complicated weldments such as ring beams and support leg attachment points shall be inspected by the wet magnetic or dye penetrant method. The extent of testing shall ensure a minimum of 5 % of attachment welds are tested.

• Inspection personnel shall be qualified as stated in API 650 • Steel plates are to be subject to ultrasonic inspection • Report any non-conformance found in any inspections or tests to the Client’s Representative within one

working day. Submit the method to correct the non-conformance as part of the report.

Factory tests do not constitute a waiver of field commissioning requirements and the requirement to pass field tests under the specified operating conditions.

Upon completion of the work, issue an MDR, which comprises the quality certificates, inspection and test records, and any other relevant documents related to manufacture and testing.

6.3 VISUAL DEFECTS

The following conditions are considered unsatisfactory from the point of view of the safety and the appearance of the tank or bin and if they exceed the tolerances given in this specification, they shall be repaired or removed.

• Plate laminations • Dents

Page 12: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 12 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

• Flat spots • Buckled or warped areas • Wavy plates or wavy plate edges.

When a plate is discovered to be defective during fabrication all work on the plate and the adjacent plate shall be stopped until the defects are corrected.

6.4 FIELD TESTING

A commissioning program for field testing shall be provided at the appropriate stage of the works.

6.5 PRESSURE TESTING

All completed tanks shall be successfully hydrostatic strength and leak tested in accordance with the appropriate API standard. Flat-bottom tank floors on grade shall be subject to vacuum box testing. Elevated tank bottoms which permit unrestricted visual examination during test, need only be subject to a hydrostatic test.

The hydrostatic test shall consist of filling the tank with water and observing for leakage. Tanks which were subject to vacuum box testing of the floor shall be filled for a minimum period of 12 hours and liquid level recorded whilst other tanks shall be filled for a minimum period of two hours.

The times given above are minimum times only. The tank must remain full for a period of time to enable all visible welds to be visually checked for leakage.

6.6 INSTALLATION OPERATION AND MAINTENANCE MANUALS

After placement of Purchase Order, the Contractor shall submit an Installation Operation and Maintenance manual (IOM); the contents of which shall be submitted for approval by the Client’s Representative

6.7 MANUFACTURER’S DATA REPORT

After placement of Purchase Order, the Supplier shall submit a Manufacturer’s Data Report (MDR); the contents of the MDR shall be submitted for approval by the Client’s Representative.

6.8 CONTRACTOR REPRESENTATION

The Contractor shall allow for the provision of qualified personnel for supervision of erection, commissioning and post commissioning servicing of the equipment and operator training upon request.

The Supplier shall provide a methodology for installation and erection of the equipment.

7 PACKING, TRANSPORT AND STORAGE

All components for site erected tanks shall be packed in accordance with the Contractor’s internal standards, suitable for the transport journey to site.

The Contractor shall provide a methodology for shipment, degree of assembly for transportation, shipping dimensions and a packing list.

The site erected tank components shall be thoroughly cleaned prior to shipment.

Shop erected tanks shall be fitted with all required braces, stays and shipping saddles to ensure that the component equipment is not damaged in transit. Braces, stays and saddles shall be of the same material as the tank, i.e. steel or of steel reinforced timber construction and contoured to suit contact surface.

Page 13: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 13 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

Nozzles and flanges shall be protected from damage during shipment with wood coverings, fixed with a minimum of three bolts of the same size as the flange bolt holes.

Bolts, nuts and other loose items shall be boxed for shipment.

Gaskets furnished by the tank Supplier shall not be used for hydrostatic pressure tests but shall be suitably boxed and marked for field installation.

Tank parts shall be clearly identified by painting or dye stencilling the tank item number and purchase order number in a conspicuous location on the component.

Fabricated materials shall not be shipped until clearance and approval has been obtained from Client’s Representative.

8 CONTRACTOR RESPONSIBILITY MATRIX

Table 1 Contractor Responsibility Matrix

Item Description Contractor Others Remarks DIRECT WORKS 1 Tank fabrication offsite / onsite X 2 Transportation from Contractors fabrication yard to site X 3 Tank installation and pre-commissioning x 4 Labour, Material and Plant & Equipment X

5 Tools, Consumables required for fabrication and construction X

6 Soil Testing X 7 Traffic Control near tank areas X 8 Access, Scaffolds, Safety Barrier X 9 Cranage X 10 Unloading ,loading, Storage on site X 11 House-Keeping X 12 HSEQ requirements including supervision X 13 Construction Water source at site X 14 Transport Construct Water from source X 15 Fuel, Lubricants required for the works X 16 Construction Survey X 17 Construction Power including materials X 18 Concrete, Rebar, Formworks etc. X 19 Steel inserts supply X 20 PPE and Safety Consumables X 21 First Aider / Safety Rep X 22 Any Lift Study as required X 23 All testing of tanks, associated structural steel X 24 Wet Weather Stand-down X 25 Confined Space training, tickets etc. X

Page 14: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 14 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

Item Description Contractor Others Remarks 26 Signage at construction site X 27 GA Drawings, Specs, Data Sheets etc. X 28 Detail design & Shop drawings X

29 Supply of Bulks (fasteners, touch up paints, gaskets, anchor bolts etc.) X

30 All construction activity and related works X 31 Construction Permits X

31 Commissioning - Supervision and Labour upon request from SNC-Lavalin ( on hourly rate basis) X

INDIRECTS

1 Mobilisation / Demobilisation of labour, plant & equipment, management including flights, travel etc. X

2 Roster – transport, flights etc. X

3 Accommodation and meals for all Contractor personnel while on site X

Contractor shall

provide direct and

indirect manpower histogram

4 Site office – for all Contractor personnel X

5 Crib huts for direct work force – for all Contractor personnel X

6 Ablution – for all Contractor personnel incl. maintenance and janitor services X

7 Site Office – for Client personnel X 8 Lunch Rooms – for Client personnel X

9 Ablution – for Client personnel incl. maintenance and janitor services X

10 Vehicles for Contractor personnel Site Management team X

11 Bus for transportation of Contractor’s personnel (Site-Camp-Site) X

12 IT requirements (3G modem, Internet) for Contractors Personnel X

13 Printing and Stationery - for Contractors Personnel X 14 Storage Containers/ Hazardous storage containers X 15 General 15a Visas & work permits X

15b All medical treatment, transport and emergency response including medicines X

15c Evacuation, repatriation, offsite treatment X 15d Transport personnel to and from Site X

Page 15: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 15 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

Item Description Contractor Others Remarks 16 Site Laydown 16a Assigning of area X

16b Free Issued material: Security, Office, Stores, Workshops, Toilets etc. X

16c Temporary power supply including generator sets, switchboards & distribution X

16d Potable water X 16e Sewage collection and disposal X 17 Tool Box Meetings / Any safety training X 18 Employee relations and Industrial relations X 19 Payroll Costs including payroll additives X 20 Survey support for as-built drawings X 21 Drafting services for as-built drawings X

9 PROGRAMME

The Contractor shall provide a Level 2 schedule as part of the Tender submission.

10 REPORTING REQUIREMENTS

The Contractor will have to provide the following reports regularly to the Client / Client’s representative:

• Daily report - Workforce & Personnel report, P&E report; Actual and Planned activities and quantities • Weekly report – progress, with quantities, man-hours actual, Schedule and forecast to complete,

material status report; HSE statistics • Monthly report – as items listed in the Weekly report (for the month), S-Curves, Cost reports, Project

Changes Notices etc.

11 EMPLOYEE AND INDUSTRIAL RELATIONSHIP MANAGEMENT

The Contractor shall be responsible for performing Employee and Industrial relationship management as per the project requirements for the site installation works. Contractors are responsible for finalising site working conditions, working hours, roster and manage their own payroll etc.

12 REFERENCE DOCUMENTS

The following reference documents form part of this Scope of Work.

Table 2 Reference Document

Document No. Description Standard Specifications 140316-0000-40EG-0001 Project Specification 140316-0000-45EG-0001 Specification for Corrosion Protection 140316-0000-45EG-0002 Specification for Shop and Site Welded Tanks Data Sheet 140316-0000-45ED-TK0003 Equipment Datasheet - Site Erected Welded Tanks

Page 16: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 16 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

Document No. Description Drawings 130000-0000-45D0-0003 Mechanical Tankage Standards – Flat Bottom open tank with Agitator

Support 130000-0000-45D0-0004 Mechanical Tankage Standards – Tankage Nameplates and Nameplate

Holder 130000-0000-45D0-00013 Mechanical Tankage Standards – Sulphuric Acid Tank Arrangement 130000-0000-45D0-00014 Mechanical Tankage Standards – Sulphuric Acid Tank Details - Sheet 1 130000-0000-45D0-00015 Mechanical Tankage Standards – Sulphuric Acid Tank Details - Sheet 2 130000-0000-45D0-00016 Mechanical Tankage Standards – Storage tank shell nozzles 130000-0000-45D0-00017 Mechanical Tankage Standards – Storage tank roof nozzles 130000-0000-45D0-00018 Mechanical Tankage Standards – Bobcat Cleanout door & Tank Seal Pot

details 130000-0000-45D0-00019 Mechanical Tankage Standards – Steel tank overflow box, overflows lined

and unlined 130000-0000-45D0-00020 Mechanical Tankage Standards – Steel tank cleanout door 1000x900 lined

and unlined 130000-0000-45D0-00021 Mechanical Tankage Standards – Tank shell manhole – lined and unlined 130000-0000-45D0-00022 Mechanical Tankage Standards – Steel tank roof manholes DN600 -

unlined 130000-0000-45D0-00024 Mechanical Tankage Standards – Tank anchors and attachments

Page 17: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 17 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

Page 18: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 18 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

Page 19: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 19 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

Page 20: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 20 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

Page 21: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 21 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

Page 22: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 22 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

Page 23: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 23 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

Page 24: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 24 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

Page 25: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 25 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

Page 26: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 26 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

Page 27: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 27 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

Page 28: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 28 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

Page 29: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 29 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

Page 30: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 30 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

13 VENDOR DATA REQUIREMENTS SCHEDULE

This section specifies information to be provided by the Tenderer as part of the tender submission and by the Vendor after acceptance of tender.

Documents shall be supplied in the quantity and type as indicated where:

O = Original

P = Print/photocopy

E = electronic media

Example: 1E = 1 electronic copy

Format for all electronic media other than drawings – Microsoft Office 2007 software

Format for electronic media drawings – Microsoft CAD file format (.dgn)

Storage – CD or flash drive

Table 3 Vendor Data Requirements

Item No. Description

Req’d per each copy of Tender

Req’d for

review

Period* (Days)

As-built req’d

Final copies req’d

Req’d after Acceptance of Tender A. DRAWINGS A1 Vendor Drawings and Document List 1E 21 1E 1E A2 General Arrangement Drawings 1E 21 1E 1E A3 Foundation Load Plan and Anchor Bolt Location 1E 21 1E 1E

A4 Assembly Drawings Installation Drawings

1E 21 1E 1E 1E 21 1E 1E

A6 Structural Steel Shop Details

A7 Detail Drawings Mechanical ⌧

Electrical ⌧ 1E 21 1E 1E

A8 Hydraulic Schematic Diagrams A9 Hydraulic Assembly Details A10 Electric Motor Details A11 Electrical Wiring Diagrams and Schematics A12 Cable Block Diagrams A13 Piping and Instrumentation Diagrams (P&IDs) A14 Electrical/Instrument Location and Layout Drawings A15 Electrical / Instrument Termination Drawings A16 Single Line Diagrams A17 Lubrication System Schematics B. DATA B1 Code and Material Specifications 1E 1E 14

B2 General Description of Equipment, Operation & Duties

Page 31: Document No 140316-0000-45EW-5114

SCOPE OF WORK SITE ERECTED CARBON STEEL AND

STAINLESS STEEL TANKS

Document No 140316-0000-45EW-5114 Revision 02 Date 03/04/2018 Page 31 of 31

SNC LAVALIN 140316-0000-45EW-5114_02 - Scope of Work - Site Erected CS and SS Tanks.docx

Item No. Description

Req’d per each copy of Tender

Req’d for

review

Period* (Days)

As-built req’d

Final copies req’d

Req’d after Acceptance of Tender B3 Catalogue and Technical Brochures of Components B4 Itemised List of all Auxiliary Equipment 1E 1E 14 B5 Approvals of Relevant Authorities B6 Design Calculations for bearing life B7 Performance Curves and Data

B8 Completed Technical Questionnaire & Equipment Data Sheets 1E 1E 14 1E

B9 Bills of Material B10 Welding Procedures and Qualification Tests Reports 1E 14 1E B11 Inspection and Test Plan (ITP) 1E 14 B12 Non Destructive Testing Procedures 1E 28 B14 Calibration Procedures 1E 28 B15 Hydrotest Procedures 1E 28 B18 Commissioning Procedures 1E 42 1E B19 Label Schedule 1E 42 B20 Nameplate Details 1E 42 B22 Instrument Index

B23 Control & Instrument Equipment Specifications Sheets (Instrument Data Sheets)

B24 I/O Schedules B25 Intrinsic Safety Dossiers B26 Software Documentation

B27 Sequence & Logic Diagrams/Flowcharts/Cause & effect matrix/Interlock schedule

B28 Test Manual

B29 Vendor/ Sub Vendor’s standard surface treatment and painting procedures 1E 28

B30 Vendor/Sub Vendor’s standard rubber lining procedures 1E 28

B31 Electric Motor Data Sheet C. MANUALS

C1 Installation and Commissioning Instructions (note 2 & 3) 1E 28 6P

C2 Operating Manual (note 2 & 3)

C3 Maintenance Manual including Lubrication Instructions and Complete Parts List (note 2&3)

C4 Manufacturer’s Data Report (note 3) 2P Notes: 1. Period = calendar days following acceptance of tender for delivery of review documents 2. Items C1, C2 and C3 may be combined into one manual 3. Refer Instruction to Tenderers for minimum requirements for Manufacturer’s Data Report (MDR) and Installation,

Operating and Maintenance (IOM) Manuals