Draft Monitoring Report LMCB May 4, 2006 2

Embed Size (px)

Citation preview

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    1/33

    MONITORING REPORT

    for

    REPLACEMENT OF FOSSIL FUEL BY PALM KERNEL SHELL BIOMASSIN THE PRODUCTION OF PORTLAND CEMENT

    Lafarge Malayan Cement Bhd,L12, Bangunan TH Uptown 3,

    No 3, Jalan SS 21/39, Petaling Jaya,Selangor, MALAYSIA

    UNFCCC REF NO 247

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    2/33

    2

    By

    Table of Contents

    Section- I: Introduction ................... ..................... .................... .................... .................... ................. 3

    Section- II: Monitoring ................. .................... .................... ................... ................... ...................... 8

    Section-III: GHG Emission Reduction ..................... ................... ................... .................... ..........143

    Appendix-I - Calculations.............................................................................................................154

    Appendix 2......................................................................................................................................17

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    3/33

    3

    I: INTRODUCTION

    I.1: Purpose

    This monitoring report has been prepared for Replacement of Fossil Fuel by Palm KernelShell Biomass in

    The Production of PortlandProject project of Lafarge Malayan Cement Bhd, (LMCB), L12, Bangunan TH

    Uptown 3, No 3, Jalan SS21/39, Petaling Jaya, Selangor. The project has been registered with UNFCCC as a

    CDM project activity under article 12 of the Kyoto protocol. Submission of monitoring report and subsequent

    verification has been required mandatory by UNFCCC for issuance of Certified Emission Reductions (CERs)

    credits. The monitoring period covered under the report extends from 01/05/2000 to 31/12/2005.

    I.2: Project Description

    Lafarge Malayan Cement Bhd (LMCB) has exclusively developed the technology and skills to

    substitute a significant percentage of the coal used at its Kanthan and Rawang plants with Palm Kernel

    Shell (PKS) Biomass from the Oil Palm Industry.

    The manufacture of cement is a highly energy intensive activity. The vast majority of this energy is

    required to heat the raw materials to a level that brings about the necessary chemical change to createcement clinker. A complete description of the cement manufacturing process is given in Annex 6. InMalaysia, the heating process is predominantly achieved through the firing of coal although some

    plants have in recent years also started consuming other fossil fuels such as e.g. pet coke.

    The substitution of biomass for fossil fuels in the cement manufacturing process in Malaysia has a

    significant contribution to make to the countrys sustainable development plans. LMCB currently

    sources all of its coal supplies from outside of Malaysia. The substitution of a locally arising biomass

    product for imported fossil fuels not only reduces Malaysias dependence on imports, but also givesrise to environmental benefits from preserving fossil fuels and utilising a waste biomass stream, which

    would otherwise be stockpiled and left to biodegrade, open to saturation by tropical rains andultimately of no current use to any industry.

    The decision to substitute fossil fuel with biomass is a positive action to reduce CO2 emissions fromthe cement manufacturing process. Its a direct result of the commitments given, originally, by Blue

    Circle Industries of the UK in its Environmental Report 1999 (relevant extracts at Annex 7) and

    more recently by Lafarge S.A. of France (parent company of LMCB following its acquisition of BlueCircle Industries in 2001) as set out in its first sustainable development report, Building a Sustainable

    World (relevant extracts also at Annex 7). This action is also consistent with Lafarges global target

    to reduce CO2 emissions by 20% over the period 1990 to 2010. As stated in its 1999 Environmental

    Report, Blue Circle committed to support the development of demonstration projects in relation toflexible mechanisms such as CDM under the Kyoto Protocol.

    The technology to process and use PKS has been developed in a partnership with Blue CircleIndustries Technical Centre in Europe based on their experiences of combustion of alternative fuels.

    Knowledge and expertise have been actively transferred in the development of the project by design

    work in Europe and European expert deployment in Malaysia during design, construction andsubsequent follow up adjustments and performance monitoring.

    Training of staff and engineers has been provided during the design and commissioning stage of the project.

    Especially the transfer of knowledge from foreign visiting experts from Blue Circle and Lafarge Europe has

    involved training of local engineers and operators.

    This project is in line with Malaysian Sustainability Policy when utilizing biomass (PKS) as a

    renewable energy source. The Eight Malaysia Plan (2001-2005) specifically promotes the use of

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    4/33

    4

    renewable energy as the fifth fuel. The projects compliance with the Malaysian National Criteria forCDM Energy Projects is attached in Annex 10.

    I.3: Project Location

    The project activity is located at the LMCB cement works in West Malaysia near the two towns,

    Rawang and Kanthan respectively are shown below:

    a) West Malaysia b) Rawang Works, Selangor c) Kanthan Works, Perak

    1.3:1. Host Party(ies):

    >>

    The host country is Malaysia

    1.3:2 Region/State/Province etc.:

    >>

    The two project activities are located in the West Malaysian states of Selangor and Perak

    1.3:3 City/Town/Community etc:

    >>The nearest towns are Rawang and Kanthan

    1.3:4 Detail of physical location, including information allowing the unique

    identification of this project activity (maximum one page):

    Rawang works is located at approximately latitude 3o and longitude 101o34.5E next to the roadleading to Kuang from the junction off the trunk road Rawang Batu Arang. It is approximately 4 km

    from the North-South Expressway Interchange and 2 km from Rawang town.

    Address: Rawang Works

    48000 Rawang

    Selangor Darul EhsanMalaysia

    Kanthan works is located at latitude 4o 46N and longitude 101o 07E next to the trunk road Ipoh-Kuala Kangsar. It is approximately 22 km north of Ipoh.

    Address: Kanthan Works

    Batu 13, Jalan Kuala Kangsar

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    5/33

    5

    31200 ChemorPeral Darul Ridzuan

    Malaysia

    Both project activities are implemented within the premises of the cement works and does not require

    additional land acquisition by the LMCB. The project activity sites are indicated on the site maps

    (b)and (c) of the two works are shown above.

    I.4: Project Status

    The project activity has been registered with UNFCCC as CDM activity1 on 7 April 2006 under

    sectoral scope 4 ACM 003: Emissions reduction through partial substitution of fossil fuels with

    alternative fuels in cement manufacture, scopes related approved methodologies and Designated

    Operational Entities (DOE) (version 02 Feb 06, 07:35 23)

    I.5: Baseline Methodology Adopted

    Title of approved consolidated baseline methodology:

    Emissions reduction through partial substitution of fossil fuels with alternative fuels in cement

    manufacture. Methodology number: ACM0003.ACM0003 is a consolidated methodology based on two methodologies (NM0040 and NM0048-rev). NM0040

    was prepared based on the project activity covered by this PDD. Therefore, the ACM0003 is suitable for thisproject activity.

    The ACM0003 is applicable under the following conditions:Fossil fuel(s) used in cement manufacture are partially replaced by alternative fuels, including renewable

    biomass, where renewable biomass residues are in surplus and leakages in other uses of the renewable biomass

    will not occur;

    The project activity is to substitute around 5% of the total energy consumed by the plant with PKS, which is a

    renewable biomass residue. PKS is a waste product from the palm oil milling process and is used as a fuel in the

    palm oil mills together mesocarp fibres, which is another biomass waste product suitable for combustion. The

    palm oil mills prefer to use the fibres over the PKS and PKS will normally not exceed about a third of the totalenergy use in the boiler plants.

    CO2 emissions reduction relates to CO2 emissions generated from fuel burning requirements only and is

    unrelated to the CO2 emissions from decarbonisation of raw materials (i.e. CaCO3 and MgCO3 bearing

    minerals);

    The project activity and its boundary is confined to the fuel preparation and feeding process of PKS into the

    combustion instead of fossil fuels to meet the fuel burning requirements for the cement manufacture process.

    The methodology is applicable only for installed capacity (expressed in tonnes clinker/year) that exists by thetime of validation of the project activity;

    The project activity is for the existing kilns installations. The project activity commenced in 2000 and therefore

    the methodology only applies to existing installations at that time. Any new kilns to increase the productioncapacity will not be included in the project activity at a later stage.

    Therefore, LMCB asserts that the PKS will only replace coal and the assertion is not affected by improvementsin output, fuel consumption, and additions of other materials or fuels to the process.

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    6/33

    6

    The amount of alternative fuels available for the project is at least 1.5 times the amount required to meet theconsumption of all users consuming the same alternative fuels, i.e. the project and other alternative fuel users.

    The estimated total of PKS available in Malaysia in year 2000 was approximately 320,000 tonnes (rf. Annex 8).

    The project activity consumes around 68,000 tonnes per year, so the supply of PKS is about five times thedemand.

    Within the 180km radius defined in Annex 8, covering the states of Perak, Kelantan, Pahang, Melaka, NegeriSembilan, Selangor and partly Johor, approximately 160,00 tonnes of PKS is available in the year 2004. This

    volume is approximately 2.3 times higher than the project requirement. Assuming the palm oil plantation in

    Peninsular Malaysia increases by 9% from the year 2000, and back calculating the figures to year 2000,

    approximately 140,00 tonnes of PKS was available and this translates to about 2 times higher than the projectdemand.

    I.6: Technical description of the project:

    1.6 Project DescriptionOVERVIEW OF CEMENT MANUFACTURING PROCESS

    Cement manufacture includes three main process steps; preparation of raw materials, producing

    clinker, an intermediate, through pyroprocessing of raw materials and grinding and blending clinkerwith other products mineral components to make cement.

    There are two main sources of direct CO2 emissions in the production process: combustion of kiln

    fuels, and the calcination of raw materials in the pyroprocessing stage. These two sources aredescribed in more detail below. Other CO2 sources include direct emissions from non-kiln fuels (e.g.

    dryers, room heating, on-site transports), and indirect emissions from e.g. external power production

    and transports. Non-CO2 greenhouse gases covered by the Kyoto Protocol are not relevant in the

    cement context, in the sense that direct emissions of these gases are negligible.

    CO2 from Raw Materials

    In the clinker burning process, CO2 is released due to the chemical decomposition of calciumcarbonates (e.g. from limestone) into Lime:

    23 COCaOheatCaCO ++

    This process is called calcining or calcination. It results in direct CO2 emissions through the kiln

    stack. When considering CO2 emissions due to calcination, two components can be distinguished:

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    7/33

    7

    This process is called calcining or calcination. It results in direct CO2 emissions through the kilnstack. When considering CO2 emissions due to calcination, two components can be distinguished:

    CO2 from actual clinker

    CO2 from raw materials discarded (land filled) as partly calcined cement kiln dust (CKD), oras fully calcined bypass dust.

    CO2 from actual clinker production is proportional to the lime content of clinker, which in turn varies little in

    time or between different cement plants. As a result, the CO2 emission factor per tonne of clinker is fairly stable

    (IPCC default: 510 kg CO2/t clinker).

    The cement industry traditionally uses various fossil fuels to operate cement kilns, including coal, petroleumcoke, fuel oil, and natural gas. In recent years, fuels derived from waste materials have become important

    substitutes. These alternative fuels and raw materials (AFR) include fossil fuel-derived fractions such as e.g.

    waste oil and tyres, as well as biomass-derived fractions such s waste wood and dried sludges from waste watertreatment.

    Both conventional and alternative fuels result in direct CO2 emissions through the stack. However biomass fuelscan be considered climate-neutral. Use of alternative (biomass or fossil derived) fuels may, in addition, lead to

    important emission reductions elsewhere, for instance from waste incineration plants or landfills.

    Kiln,

    Pre Calciner

    Other Fossil Fuel

    (Coal or Petcoke)

    Fuel

    Mixing

    Project boundary

    PKS Storage

    PKS Transportation

    PKS Feeding System

    Crusher

    Fossil Fuel Transportation(On road and sea)

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    8/33

    8

    SECTION- II: MONITORING

    Section II.1: Monitoring Methodology

    Title: Approved monitoring methodology ACM0003, Version 2 Emissions reduction throughpartial substitution of fossil fuels with alternative fuels in cement manufacture

    II.2: Monitoring Period

    The monitoring of parameters has been done for both baseline emission and project emissions calculations.

    Monitoring period chosen for baseline emissions and project emission calculations is from 01/05/2000 to

    31/12/2005. A flow chart of the monitoring system, parameters monitored during the period and their recording

    frequency is given below. Data has been archived for verification purpose.

    II.3: Monitoring System

    II.3:1 Relevant data necessary for determining the baseline of anthropogenic emissions by sources of GHGs

    within the project boundary and how such data will be collected and archived :

    ID

    number

    (Pleaseusenumber

    s toease

    cross-referencing totable

    D.3)

    Data

    variable

    Source of

    data

    Data

    unit

    Measured

    (m),

    calculated (c),

    estimated (e),

    Recording

    frequency

    Proportion

    of data to be

    monitored

    How will

    the data be

    archived?

    (electronic/

    paper)

    Comment

    1. Clinkerproduc-

    tion[C]

    LMCB Ton m, c Monthly 100% Electronic,paper

    LMCB monitors the clinkerproduction as a part of theirproduction managementactivities and data is includedin monthly productionreports. Raw material to

    produce clinker is measuredusing weighing feeders and

    clinker production iscalculated.

    2. Alternative fuel

    quantity[QAF]

    LMCB Ton m Monthly 100% Electronic,paper

    LMCB monitors the amountof PKS fuel purchase as a

    part of the procurement andpayment for the deliveriesand data is included inmonthly production reports.

    Alternative fuel quantity ismeasured using weighing

    feeders.

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    9/33

    9

    3. Alternative fuelheat

    value[HVAF]

    LMCB TJ/tonne m, c Monthly 100% Electronic,paper

    LMCB monitors the heatvalue of PKS fuel as a part ofthe procurement and payment

    for all deliveries and data isincluded in monthly

    production reports.Calorimeter is used tomeasure the heat value in

    LMCB laboratory4. Alternativ

    e fuelheat

    [HIAF]

    LMCB TJ c Monthly 100% Electronic,paper

    Calculation based on themonitored data by the

    following formula:

    AFAFAF HVQHI =

    5. Alternative fuel

    emissionfactor[EFAF]

    IPCC TCO2 /TJ e Fixed 100% Electronic,paper

    This value is fixed at zero, asthe fuel is carbon neutralbiomass.

    6. Share ofheat input

    from

    alternative fuel[SAF]

    LMCB % c Monthly 100% Electronic,paper

    Calculation based on themonitored data HIAFand HIFFby the following formula:

    FFFF

    AFAF

    HVQ

    HIS

    = )(

    7. Moisturepenalty

    [mp]

    LMCB MJ/tonne/10%

    alt. Fuelshare

    c At start ofcreditingperiod

    100% Electronic,paper

    The moisture penalty will bemeasured and calculatedduring a test of heatconsumption with and withoutapprox. 10% alternative fuelinput

    8. Fossilfuel

    quantity[QFF]

    LMCB Ton m Monthly 100% Electronic,paper

    LMCB monitors the amountof fossil fuel purchase as a

    part of the procurement andpayment for the deliveriesand data is included inmonthly production reports.Quantity of fossil fuel ismeasured using weighing

    feeders before fired into thekiln.

    9. FossilfuelHeatvalue

    [HVFF]

    LMCB TJ/tonne m, c Monthly 100% Electronic,paper

    LMCB monitors the heatvalue of fossil fuel as a partof the procurement and

    payment for all deliveries anddata is included in monthly

    production reports. The valueis measured using

    calorimeter.10. Fossil

    fuelemissionfactor[EFFF]

    IPCC TCO2 /TJ e Fixed 100% Electronic,paper

    The emission factor for fossilfuels are fixed at the defaultvalue in the Revised 1996

    IPCC Guidelines for NationalGreenhouse Gas Inventories:

    Reference Manual:coal of 94.6

    kg CO2/GJ,

    Petcoke2

    92.5kg CO2/GJ,Diesel

    374.1 kg CO2/GJ,

    Shale4

    107 kg CO2/GJ

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    10/33

    10

    II.3:2 Description of formulae used to calculate project emissions (for each gas, source, formulae/algorithm,

    emissions units of CO2 equ.):

    >>

    N/A

    II.4: Treatment of leakage in the monitoring plan

    11.4:1 . If applicable, please describe the data and information that will be collected in order tomonitor leakage effects of the project activity

    ID number

    (Please usenumbers toease cross-referencingto table

    D.3)

    Data

    variable

    Source

    of data

    Data

    unit

    Measured

    (m),

    calculated

    (c) or

    estimated

    (e)

    Recording

    frequency

    Proportion

    of data to

    be

    monitored

    How will the

    data be

    archived?

    (electronic/

    paper)

    Comment

    N/A

    II .4:2. Description of formulae used to estimate leakage (for each gas, source, formulae/algorithm,emissions units of CO2 equ.)

    >>

    No leakage is derived from the proposed project activity and therefore not monitored and calculated.

    II.5 Description of formulae used to estimate emission reductions for the project activity (for each gas,

    source, formulae/algorithm, emissions units of CO2 equ.)

    >>

    Emissions reduction for the project activity is the amount of GHG emissions that would have beenemitted in the absence of the project i.e. the GHG emissions from the fossil fuel displaced.

    AFER= FFGHG

    Where:

    FFGHG is GHG emissions from fossil fuels displaced by the alternatives (tCO2/yr) see

    formula in section D.2.1.4

    II.6: Quality control (QC) and quality assurance (QA) procedures are being undertaken for

    data monitored

    Data

    (Indicate tableand ID numbere.g. 3.-1.; 3.2.)

    Uncertainty level of data

    (High/Medium/Low)

    Explain QA/QC procedures planned for these data, or why such

    procedures are not necessary.

    1 Low The data is already a part of the QA/QC system in LMCB and the data iscompiled in monthly production reports

    2 Low The data is already a part of the QA/QC system in LMCB and the data iscompiled in monthly production reports

    3 Low The data is already a part of the QA/QC system in LMCB and the data iscompiled in monthly production reports

    4 Low N/A this data is calculated

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    11/33

    11

    5 Low N/A this data is IPCC defined6 Low N/A this data is calculated7 Low N/A this data is calculated (rf. Annex 13)8 Low The data is already a part of the QA/QC system in LMCB and the data is

    compiled in monthly production reports

    9 Low The data is already a part of the QA/QC system in LMCB and the data iscompiled in monthly production reports

    10 Low N/A this data is IPCC default values

    II. 7 Please describe the operational and management structure that the project operator will

    implement in order to monitor emission reductions and any leakage effects, generated by the

    project activity

    >>

    Fuels may be purchased from different sources during the same period. Each fuel shipment may vary

    in moisture, heat value and weight. Production in some periods may be more efficient than others.Regardless of these variables and due to accurate book-keeping, the percentage of each fuel used and

    the amount of cement clinker made in a fixed time period will be recorded. Fuel heat values will besystematically measured and applied and emission factors used are laboratory tested for each fuel type.

    Since it is a normal priority for a cement company to track the fuel split, an additional fuel, that isPKS, can be easily absorbed into an existing tracking system.

    All fuels are delivered across a weighbridge with delivery notes and in accordance with contracts

    respecting the moisture content and heat value of each delivery. Fuels are tested to internationalstandards as part of ISO9001/2 management systems to generate payment to suppliers. LMCB

    documents opening stock, closing stock and dispatch of each material to generate production figures.

    Fuel testing is on an as received basis determining the real heat value to the process. The % heatcontributed from each fuel can thus be calculated. This is an already established system and company

    books are audited as per normal business procedures. LMCB is confident of capturing the actual

    tonnages of PKS utilised and the real heat content contributed to the process.

    Major data requirements in this monitoring methodology are already covered by the LMCB monthly productionreports for the facilities and information for the monitoring of the emission reductions can be obtained in these

    reports. The monthly reports are prepared by the plants manager and reported to the LMCB management.

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    12/33

    II.4.3: Data Monitored for Leakage Calculations

    Not Applicable

    II: 5 Quality Assurance (QA)/ Quality Control (QC) Plan

    Quality assurance/quality control plan was made as per ISO-9001 guidelines. Environmental

    management cell constituting of specialists has been given the task of monitoring various

    parameters involved in the project activity. Monitoring was done with necessary equipments on

    intervals mentioned in the methodology adopted for the project activity.

    II:5.1 Quality control (QC) and quality assurance (QA) procedures are being undertaken for data

    monitored

    Data

    (Indicate tableand ID number

    e.g. 3.-1.; 3.2.)

    Uncertainty level of

    data

    (High/Medium/Low

    )

    Explain QA/QC procedures planned for these data, or why such

    procedures are not necessary.

    D.3-1 Low Sampling has been carried out adhering to internationally recognized

    procedures

    D.3-2 Low Flow meters have undergone maintenance/calibration subject to

    appropriate industry standards.

    D.3-3 Low This data Not Applicable for the Project Activity.

    D.3-4 Low Flow meters have undergone maintenance/calibration subject to

    appropriate industry standards.

    D.3-5 Low This data Not Applicable for the Project Activity

    D.3-6 Low Flow meters have undergone maintenance/calibration subject to

    appropriate industry standards.

    D.3-7 Low Sampling has been carried out adhering to internationally recognized

    procedures. This has been carried out at least quarterly.

    D.3-8 Low This data Not Applicable for the Project Activity

    D.3-9 Low This data Not Applicable for the Project Activity

    D.3-10 Low Flow meters have undergone maintenance/calibration subject to

    appropriate industry standards.

    D.5-11 Low Flow meters have undergone maintenance/calibration subject to

    appropriate industry standards.

    D.3-12 Low Sampling has been carried out adhering to internationally recognized

    procedures. This has been carried out at least quarterly.

    D.3-13 Low Electricity meters have undergone maintenance/calibration subject to

    appropriate industry standards. The accuracy of the meter readings

    have been verified.

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    13/33

    13

    D.5-1 Low Sampling has been carried out adhering to internationally recognized

    procedures.

    D.5-2 Low Flow meters have undergone maintenance/calibration subject to

    appropriate industry standards.

    D.5-3 Low This data Not Applicable for the Project Activity

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    14/33

    14

    SECTION-III: GHG EMISSION REDUCTION

    III. 0 Estimation of GHG emissions by sources

    III.1 Estimate of GHG emissions by sources:

    >>

    Combustion of biomass fuel (PKS) is considered carbon neutral and there will not be any GHGemissions.

    III.2 Estimated leakage:

    >>

    Emissions due to PKS transportation is proven to be insignificant and lower compared to the total

    project emissions (rf. Annex 9). Thus leakage from off-site transportation is negligible for this project.

    Secondly, there will be no leakage for this project as the alternative fuel source is abundantly available

    (See Annex 8) and substituting fossil fuels such as diesel or fuel oil with PKS will not be cost effective

    for the existing PKS users.

    III.3 The sum ofIII .1 andIII.2 representing the project activity emissions:

    >>

    Since there is no leakage, and insignificant GHG emissions from the combustion of PKS, the project

    activity emissions are zero.

    III.4 Estimated anthropogenic emissions by sources of greenhouse gases of the baseline:

    >>

    FFGHG= [(QAF* HVAF) - MPtotal]* EFFF

    where:FFGHG= GHG emissions from fossil fuels displaced by the alternatives (tCO2/yr)

    QAF* HVAF= total actual heat provided by all alternative fuels (TJ/yr)

    MPtotal= total moisture penalty (TJ/yr)

    EFFF= emissions factor(s) for fossil fuel(s) displaced (tCO2/TJ).

    MPtotal = (SAF/10%) * C * mp

    where:SAF = Alternative fuel heat input share of total baseline heat input

    C = total clinker production

    mp = moisture penalty (MJ/tonne-10% alternative fuel share of total heat input)

    mp = (HCAF(i) HCFF)/Si * 10

    where:HCAF(i) = specific heat consumption using i% alternative fuel (MJ/tonne clinker)

    HCFF = specific heat consumption using fossil fuel only (MJ/tonne clinker)

    Si = alternative fuel heat input share of total baseline heat input in the moisture penalty test.

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    15/33

    15

    AFFFFF

    AFAF

    HIHVQ

    HIS

    += )(

    where:

    HIAF = heat input from alternative fuels (TJ/year), calculated as QAF*HVAF

    QFF = quantity of each fossil fuel used in baseline (tonne/year)HVFF = lower heating value of the fossil fuel(s) used in baseline (TJ/tonne fuel)

    Details of the calculation based on project specific data is presented in Annex 5, Baseline Calculation.

    III.5. Difference betweenIII.4andIII.3 representing the emission reductions of the project

    activity:

    >>Since there is no project emissions and only one alternative fuel (PKS) is used instead of fossil fuel

    (Coal), the total project emission reduction can be given as;

    AFER= FFGHG

    III.6. Table providing values obtained when applying formulae above:

    >>The ex postcalculation of baseline emission rates may only be used if proper justification is

    provided. Notwithstanding, the baseline emission rates shall also be calculated ex ante andreported in the CDM-PDD. The result of the application of the formulae above shall be indicated

    using the following tabular format.

    Year Estimation ofproject

    activity

    emission

    reductions

    (tonnes of CO2 e)

    Estimation

    of baseline

    emission

    reductions

    (tonnes of

    CO2 e)

    Estimation of

    leakage

    (tonnes of CO2 e)

    Estimation of

    emission

    reductions

    (tonnes of

    CO2 e)

    2000 62,011 0 0 62,011

    2001 62,011 0 0 62,011

    2002 62,011 0 0 62,011

    2003 62,011 0 0 62,011

    2004 62,011 0 0 62,011

    2005 62,011 0 0 62,011

    2006 62,011 0 0 62,011

    2007 62,011 0 0 62,011

    2008 62,011 0 0 62,011

    2009 62,011 0 0 62,011

    Appendix-I - Calculations

    I. Baseline EmissionsBASELINE INFORMATION

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    16/33

    16

    ID

    number

    Data variable Source of

    data

    Data unit Data Value Comment

    1. Clinker

    production

    [C]

    LMCB Tonne/yr 4,746,624 Average annual clinker

    production in the period 2000-

    2004

    2. Alternative fuelquantity

    [QAF]

    LMCB tonne 68,000 Average annual consumption ofPKS in the period 2000-2004

    3. Alternative fuel

    heat value

    [HVAF]

    LMCB TJ/tonne 0.01313 Average heat value measured

    for the purchased PKS.

    Measured by LMCB laboratory

    4. Alternative fuel

    heat

    [HIAF]

    LMCB TJ 893 Calculation based on the above

    data by the following formula:

    AFAFAF HVQHI =

    5. Alternative fuel

    emission factor

    [EAF]

    IPCC TCO2/TJ 0 This value is fixed at zero, as

    the fuel is carbon neutral

    biomass

    6. Share of heat

    input fromalternative fuel

    [SAF]

    LMCB % 5 Calculation based on the above

    data HIAF and HIFF by thefollowing formula:

    AFFFFF

    AFAF

    HIHVQ

    HIS

    += )(

    7. Moisture penalty

    [mp]

    LMCB MJ/tonne/10%

    alt. Fuel share

    100 The moisture penalty has been

    assessed in Annex 13 at 10%

    for 10% PKS share of the total

    heat

    Coal 582513

    Pet coke 40322

    Diesel 12363

    8. Fossil fuel

    quantity

    [QFF]

    LMCB tonne

    Shale 18997

    Average annual consumption of

    fossil fuel in the period 2000-

    2004

    Coal 0.02575

    Pet coke 0.03100

    Diesel 0.04333

    9. Fossil fuel

    Heat value

    [HVFF]

    LMCB TJ/tonne

    Shale 0.00940

    IPCC default values are used

    only in the PDD for estimation

    of emission reductions.

    Measured local values will be

    used during Validation of

    CERs. Below is the measured

    average LHV from year 2000 to

    2005 for comparison. Coal:

    0.02404 TJ/t, Pet coke : 0.03188

    TJ/t, Diesel : 0.04260 TJ/t,

    Shale heat value is not locallyavailable and default IPCC

    value will be used.

    Coal 94.610. Fossil fuel

    emission factor

    EFFF

    IPCC TCO2/TJ

    Pet coke 100.8

    The emission factor for fossil

    fuels are default values obtained

    from the IPCC reference

    guidebook as mentioned in

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    17/33

    17

    ID

    number

    Data variable Source of

    data

    Data unit Data Value Comment

    Diesel 74.1

    Shale 107.0

    ACM0003.

    Weighted Average emission

    factor (ex-ante) using Option 1

    according to ACM0003 will

    yield 94.5 tCO2/TJ.

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    18/33

    18

    Appendix 2

    MONITORING PLAN

    All the key monitoring parameters required for this project can be obtained from individual works

    Senior Works Manager Report compiled on monthly basis. This report is prepared by the Plant

    Controller and approved by the Senior Works Manager. LMCB head quarters receive all theindividual works reports and compile them as per standard ISO requirements. Monitoring data forvalidation and registration for the project and CERs can be obtained from LCMB HQ.

    Data recording approach is as per standard business accountancy procedures (Opening Stock plusdeliveries minus closing stock = utilisation) and thus minimises the possibilities of mistakes and

    misconceptions. Simplistic in that it requires only inputs that are generated as part of the standardbusiness accountancy system and/or ISO registered and audited quality procedures. These are part

    of the normal KPIs (Key Performance Indicators) measured by the respective plant.

    Internal Key Performance Indicators in the Senior Works Manager Report will track the following

    on a monthly basis;

    Cement clinker produced per plant per annum in units of tonnes. This is a publishedbusiness accountancy figure and audited internally and externally. (Data monitored : C,

    tonnes of clinker per year)

    Net Total specific Heat Consumption of each plant to produce above clinker tonnes perannum in units of kJ/kg clinker. This is a calculated figure based on the management

    accounts using weighbridge tickets of fuel supplies to generate payments to fuelsuppliers and weigher-totalisers to record consumption of heat bearing raw materials.

    The laboratory quality procedures determine the frequency of fuel/raw material

    calorific value testing and this value is applied to the amounts of each fuel/raw materialused. Procedures, frequency and test methods are all defined within each plants quality

    management systems. (Data monitored : QAF, HVAF, QFFs, HVFFs)

    An assumption is made based on historical lab test data that heat values of PKS fuel as-receivedis approximately the same as heat values of as-fired. High moisture content during delivery will

    not be evaporated significantly even after the stock piling for a few weeks. PKS fuel on the

    surface of the stockpile will dry after a few days but the inner layer is still wet. High air humidityin Malaysia contributes partly to the moisture in the PKS fuel to remain the same.

    The table below shows monitored parameters source of reference and frequency of monitoring.

    ID

    number

    Data variable Source of data Data unit Frequency

    OfMonitoring

    Comment

    1. Clinker production

    [C]

    Senior Works

    Manager Report

    tonne Monthly 1) This value is required to calculate

    total moisture penalty, MP.

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    19/33

    19

    ID

    number

    Data variable Source of data Data unit Frequency

    Of

    Monitoring

    Comment

    2. Alternative fuel

    quantity

    [QAF]

    Senior Works

    Manager Report

    tonne Monthly 1) The value is required to calculate

    the GHG emission reductions from

    fossil fuels displaced by the

    alternative fuel, FFGHG

    2) It is also required to estimate the

    share of alternative fuel, SAF in the

    moisture penalty, MP calculation.

    3. Alternative fuelheat value

    [HVAF]

    Senior WorksManager Report TJ/tonne Monthly 1) The value is required to calculatethe GHG emission reductions from

    fossil fuels displaced by the

    alternative fuel, FFGHG

    2) It is also required to estimate the

    share of alternative fuel, SAF in the

    moisture penalty, MP calculation.

    3) Heat values are based on as-fired-

    basis.

    8. Fossil fuel quantity

    [QFF]Senior Works

    Manager Reporttonne Monthly

    1) These values are required to

    estimate share of alternative fuel, SAF,

    and to calculate emission reductions.

    2) Fossil Fuels used are coal, pet coke,

    diesel and shale oil.

    9. Fossil fuelHeat value

    [HVFF]

    Senior Works

    Manager ReportTJ/tonne Monthly

    1) These values are required toestimate share of alternative fuel, SAF,

    and to calculate emission reductions.

    2) Heat values are based on as-fired-

    basis.

    3) IPCC Lower Heat Values can be

    used if no locally lab test values are

    available.

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    20/33

    20

    Appendix 3BASELINE DATA

    A B C= A X B D E=C/(C+D) F G H=(E x F x G)/10 I*

    YearQAF HVAF HIAF HIFF SAF

    mpC

    MPtotalEFFF

    tonnes/yr TJ/tonne fuel TJ/yr TJ/yr % TJ/tonne/10%AF tonnes/yr TJ/yr tCO2/T

    2000 68000 0.01313 893 16964 5.0% 0.0001 4746624 237 94[s1].5

    2001 68000 0.01313 893 16964 5.0% 0.0001 4746624 237 94.5

    2002 68000 0.01313 893 16964 5.0% 0.0001 4746624 237 94.5

    2003 68000 0.01313 893 16964 5.0% 0.0001 4746624 237 94.5

    2004 68000 0.01313 893 16964 5.0% 0.0001 4746624 237 94.5

    2005 68000 0.01313 893 16964 5.0% 0.0001 4746624 237 94.5

    2006 68000 0.01313 893 16964 5.0% 0.0001 4746624 237 94.5

    2007 68000 0.01313 893 16964 5.0% 0.0001 4746624 237 94.5

    2008 68000 0.01313 893 16964 5.0% 0.0001 4746624 237 94.5

    200968000 0.01313 893 16964 5.0%

    0.0001

    4746624

    237

    94.5

    Total

    *Option 1 selected according to ACM0003 as it was the lowest of all 3 options described.

    Year QFF-Coal HVFF-Coal QFF-Petcokes HVFF-Petcokes QFF-Diesel Oils HVFF-Diesel Oils QFF-Shale Oil HVFF-Shale

    (tonnes/yr) (TJ/tonne fuel) (tonnes/yr)(TJ/tonnefuel) (tonnes/yr) (TJ/tonne fuel) (tonnes/yr) (TJ/tonne

    2000 582513 0.0258 40322 0.0310 12363 0.0433 18997 0.00

    2001 582513 0.0258 40322 0.0310 12363 0.0433 18997 0.00

    2002 582513 0.0258 40322 0.0310 12363 0.0433 18997 0.00

    2003 582513 0.0258 40322 0.0310 12363 0.0433 18997 0.00

    2004 582513 0.0258 40322 0.0310 12363 0.0433 18997 0.00

    2005 582513 0.0258 40322 0.0310 12363 0.0433 18997 0.00

    2006 582513 0.0258 40322 0.0310 12363 0.0433 18997 0.00

    2007 582513 0.0258 40322 0.0310 12363 0.0433 18997 0.00

    2008 582513 0.0258 40322 0.0310 12363 0.0433 18997 0.00

    2009 582513 0.0258 40322 0.0310 12363 0.0433 18997 0.00

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    21/33

    21

    Appendix 4

    OVERVIEW OF CEMENT MANUFACTURING PROCESS

    Cement manufacture includes three main process steps; preparation of raw materials, producingclinker, an intermediate, through pyroprocessing of raw materials and grinding and blending

    clinker with other products mineral components to make cement.

    There are two main sources of direct CO2 emissions in the production process: combustion of kilnfuels, and the calcination of raw materials in the pyroprocessing stage. These two sources are

    described in more detail below. Other CO2 sources include direct emissions from non-kiln fuels(e.g. dryers, room heating, on-site transports), and indirect emissions from e.g. external power

    production and transports. Non-CO2 greenhouse gases covered by the Kyoto Protocol are not

    relevant in the cement context, in the sense that direct emissions of these gases are negligible.

    CO2 from Raw Materials

    In the clinker burning process, CO2 is released due to the chemical decomposition of calcium

    carbonates (e.g. from limestone) into Lime:

    23 COCaOheatCaCO ++

    This process is called calcining or calcination. It results in direct CO2 emissions through thekiln stack. When considering CO2 emissions due to calcination, two components can be

    distinguished:

    CO2 from actual clinker

    CO2 from raw materials discarded (land filled) as partly calcined cement kiln dust(CKD), or as fully calcined bypass dust.

    CO2 from actual clinker production is proportional to the lime content of clinker, which in turn varies littlein time or between different cement plants. As a result, the CO2 emission factor per tonne of clinker is

    fairly stable (IPCC default: 510 kg CO2/t clinker).

    Landfilling of kiln dust varies greatly with kiln types and cement quality standards, ranging from

    practically zero to over one hundred kilograms per tonne of clinker. The associated emissions are likely tobe relevant in some countries.

    CO2 from Fuels for Kiln operation

    The cement industry traditionally uses various fossil fuels to operate cement kilns, including coal,

    petroleum coke, fuel oil, and natural gas. In recent years, fuels derived from waste materials have becomeimportant substitutes. These alternative fuels and raw materials (AFR) include fossil fuel-derived fractions

    such as e.g. waste oil and tyres, as well as biomass-derived fractions such s waste wood and dried sludges

    from waste water treatment.

    Both conventional and alternative fuels result in direct CO2 emissions through the stack. However biomassfuels can be considered climate-neutral. Use of alternative (biomass or fossil derived) fuels may, in

    addition, lead to important emission reductions elsewhere, for instance from waste incineration plants orlandfills.

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    22/33

    22

    CO2 Abatement Options

    CO2 emissions in the cement industry can be tackled by different measures. The main categories of CO2

    abatement potentials include

    Energy efficiency: technical and operational measures to reduce fuel and power consumption perunit clinker or cement produced;

    Fuel switching: for instance, use of natural gas or AFR instead of coal

    Reduction in the dust landfilling (cement kiln dust, bypass dust) where relevant landfilling occurs; MIC: use of mineral components to substitute clinker.

    Mineral components (MIC) are natural and artificial materials with latent hydraulic properties. Examples of

    MIC include gypsum and natural pozzolanas, blast furnace slag, and fly ash. MIC are added to the clinkerto produce blended cement. In some instances the, pure MIC are directly added to the concrete mixer. MIC

    use leads to an equivalent reduction of direct CO2 emissions associated with clinker, both from calcinationand fuel combustion. Artificial MIC is waste materials from other production processes such as, e.g. steel

    and coal fired power production. Related GHG emissions are monitored and reported by the corresponding

    industry sector. Utilisation of these MICs for clinker or cement substitution does not entail additionalGHG emissions at the production site. As a consequence, indirect emissions must not be included in the

    cement production inventory.

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    23/33

    23

    APPENDIX 6: PKS AVAILABILITY CALCULATION

    The availability of PKS for the project activity is assessed by using official data by the MalaysianPalm Oil Board, who is producing annual statistics for the palm oil sector. There is no direct

    statistics on the amount of PKS available in Malaysia and must be calculated by using some

    assumptions. However this annex provides a clear and transparent calculation of the PKS

    availability and can be applied in the future as well to assess the PKS availability in any givenyear.

    The source of the data tabulated below is obtained from the official website of Malaysian Palm

    Oil Board.

    URL of Data Source : http://econ.mpob.gov.my/economy/annual/stat2004/Stactitle_04.htm

    Table :1 Total Malaysian Land Usage for Palm Trees Plantation(Hectare)

    Year Mature Immature Total

    2000 2,941,791 434,873 3,376,664

    2001 3,005,267 493,745 3,499,0122002 3,188,307 481,936 3,670,243

    2003 3,303,133 498,907 3,802,040

    2004 3,450,960 424,367 3,875,327

    Table 2: Yield (Tonnes per hectare)

    Year Fresh Fruit

    Crude

    Palm Palm

    Bunches, FFB Oil Kernel

    2000 18.33 3.46 1.01

    2001 19.14 3.66 1.05

    2002 17.97 3.59 0.98

    2003 18.99 3.75 1.022004 18.60 3.73 0.98

    Calculation on available PKS was based on the assumption tabulated below.

    Table 3: Assumptions for PKS availability

    PKS out of FFB 6%

    Excess PKS available out of total PKS 10%

    Quantity of FFB can be calculated by multiplying total planted hectares with the yield in Table 2

    for the respective years. It is assumed that PKS is 6%-8% out of total weight of FFB yield (NoelWambeck, Oil Palm Process Synopsis ed. 2, 1999). Out of this 6% about 10% of PKS is assumed

    to be available in the palm oil mills in average based on a mass and energy balance for typicalmills (Noel Wambeck, Oil Palm Process Synopsis ed. 2, 1999).

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    24/33

    24

    It can be seen on Table 4 that the annual PKS availability is between 320,000 and 385,000

    tonne/yr and it has increased over the past five years with a growth rate of 4-5 % p.a. This amount

    is about 5 times higher than the total 68,000 tonnes per year of PKS required for this projectoperation.

    Even more PKS can be available than the figures calculated above as some of the PKS can be

    replaced by empty fruit bunches, EFBs in the palm oil mill boilers. EFB constitutes 25% of the

    FFB and is also abundantly available. When PKS have a good commercial value, more EFB is

    likely to be used instead of PKS to operate the boilers in palm oil mills. It can therefore all in allbe considered very certain that the project activity will not exhaust the PKS resources and will not

    result in any leakage in terms of increased fossil fuel consumption by any present PKS users.

    Supply and demand of PKS

    The use of PKS has increased over the recent years. Supply companies, that collect the PKS andother biomass at the mills, distribute it to the industrial buyers. The industrial use of PKS in 2000

    was very limited and hence the value of PKS was low. Since 2000 more and more buyers have

    emerged and this has led to a higher value of PKS because PKS can substitute expensive fuels.The PKS price is now following the increase in oil prices. As oil prices has tripled over the pastfive years the PKS price has gone up similar over the period. Among the PKS buyers are

    industries that previously used diesel and fuel oil to generate process steam. They have installed

    biomass boilers in order to reduce the cost of steam generation. As the diesel and oil prices arehigher than coal prices these buyers will set the price level as they will be willing to pay the

    highest price for PKS.

    PKS Source Distance in Peninsular Malaysia

    Based on the past 5 years PKS consumption record the percentage of PKS usage in Rawang and

    Kanthan is given below.Rawang Kanthan Total

    % 53 47 100%

    PKS 32860 29140 62000

    Table 4: PKS availability

    Total

    Malaysia

    FFB

    (tonne)

    PKS

    (tonne)

    PKS available

    (tonne)

    2000 53,923,029 3,235,382 323,538

    2001 57,520,810 3,451,249 345,125

    2002 57,293,883 3,437,633 343,763

    2003 62,726,499 3,763,590 376,359

    2004 64,187,856 3,851,271 385,127

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    25/33

    25

    Estimation of the average distance travelled is briefed below.The distance is weighted accordingto the amount of PKS acquired from a certain radius. The total weighted distance is calculated and

    multiplied by a road windings factor since the distance is calculated based on radius.

    Two cases are presented here;

    A) Base Case Scenario

    B) Worst Case Scenario

    The base case scenario is the most likely source of PKS supply. The total weighted distance isaround 150 km.

    A) Base Case Scenario

    WorksRadius

    (km)PKS

    (tonnes) Sourcing Weight factor Weighted Distance (km)

    Kanthan 50 14570 50% 0.235 11.75

    150 14570 50% 0.235 35.25

    Rawang 50 6572 20% 0.106 5.30

    150 9858 30% 0.159 23.85

    250 16430 50% 0.265 66.25

    Total 62000 Total 142

    Road Windings Factor : 5% Total Weighted Distance : 150 km

    Calculation of the worst case scenario is shown in the table below. To be conservative, it isassumed that 70% of the required PKS is sourced from the furthest distance from both Rawang

    and Khantan works. An average distance of 180 km radius is used in the transportation assessment

    calculation by rounding up the calculated total weighted distance of 176 km.

    B) Worst Case Scenario

    WorksRadius

    (km)PKS

    (tonnes) Sourcing Weight factor Weighted Distance (km)

    Kanthan 50 8742 30% 0.141 7.05

    150 20398 70% 0.329 49.35

    Rawang 50 3286 10% 0.053 2.65150 6572 20% 0.106 15.90

    250 23002 70% 0.371 92.75

    Total 62000 Total 168

    Road Windings Factor : 5% Total Weighted Distance : 176 km

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    26/33

    26

    PKS Source Distance and Availability By States in Peninsular Malaysia

    *Note :The PKS availability is calculated based on data from MPOB for the year 2004 and thetotal available tonnes within Peninsular Malaysia is approximately 210,000 tonnes. This is

    approximately 3 times higher than the project consumption.

    50 km

    150 km

    250 km

    Kanthan

    Rawang

    Selangor - 13,832 tonnes of PKS

    N.Sembilan- 11,723 tonnes of PKS

    Melaka- 5,600 tonnes of PKS

    Johor - 67,148 tonnes of PKS

    Perak 34855

    tonnes of PKS

    Pahang- 55,092 tonnes of PKS

    Kedah-7,274 tonnes of PKS

    Terengganu-11,041

    tonnes of PKS

    Kelantan-5,731

    tonnes of PKS

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    27/33

    27

    Increase of PKS Availability in Malaysia

    YearPeninsularMalaysia Sabah & Sarawak Total

    2000 201,524 122,014 323,538

    2001 211,416 133,709 345,125

    2002 207,720 136,043 343,763

    2003 219,082 157,277 376,359

    2004 212,715 165,930 385,127

    Difference (2000-2004), % 9% 36% 19%

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    28/33

    APPENDIX 7: TRANSPORT AND POWER COMPARISONS

    CO2 emissions from transportation of fuel

    Coal used in LMCB is imported mainly using barge vessels from Sumatra, Indonesia andship vessels from China. A calculation based on an assumption that coal will be imported

    from Indonesia. This will lead to more conservative emission estimation where CO2emissions are lesser due to shorter sea travel distance.

    It will take 3 days journey in barge vessel from Sumatra with a capacity of 4000 tonnes of

    coal per trip. Fuel consumption per trip will be 30 tonnes of HFO 380. If the project could

    displace 30,000 tonnes of coal per year, 225 tonnes of HFO 380 can be saved annually.The calculation is shown in the table below.

    A B C D =C/D x A E F =D x E

    Total Fuel per

    trip (tonnes)

    Cargo Weight

    (tonnes)

    Coal Replaced by

    PKS (tonnes)

    Total Fuel

    Consumption

    (tonnes)

    Emission Factor

    (tCO2/t Fuel)-IPCC

    Emission

    (tCO2/yr)

    30 4000 30000 225 3.21 722

    Assuming the coal mining area in Sumatra and LMCB works is located within 100 km

    radius from ports in Sumatra and Malaysia respectively, 20tonne trucks will be travelling

    a distance of 400 km back and forth on road to make the coal available in the works. Iffuel consumption of a 20tonne heavy-duty diesel truck is 2500 km/tonne, on road

    transportation will consume 240 tonnes of fuel to transport 30,000 tonnes of coal. The

    table below calculates the figures explained above.

    A B C

    D = (C/20) x 2 x

    (A+B) E F = C/D G H = F x G

    Distance

    from portto LMC

    (km)

    Distance

    from CoalMining to

    port (km)

    Coal

    Replaced byPKS

    (tonnes)

    Distance

    Traveled by 20tTrucks (km)

    Fuel

    Consumptionby trucks

    (km/t)

    Total Fuel

    Consumption(tonnes)

    Emission Factor

    (tCO2/t Fuel)-IPCC

    Emission

    (tCO2/yr)

    100 100 30000 600000 2500 240 3.21 770

    Comparatively, LMCB have to use in average 2 times more PKS than coal due to lower

    heat value and higher moisture content. Since PKS is locally available, only on road

    transportation is used. Heavy-duty 20tonnes diesel trucks will be travelling an average

    distance of 180 km radius from PKS collection point. By working out the figures above asshown in the table below, on-road transportation of PKS will consume 458 tonnes of fuel

    per year.

    A B C = (B/20) x 2 x A D E = C/D F F =E x F

    Distance

    from port

    to LMC

    (km)

    Coal

    Replaced by

    PKS

    (tonnes)

    Distance Traveled by

    20t Trucks (km)

    Fuel

    Consumption

    by trucks

    (km/t)

    Total Fuel

    Consumption

    (tonnes)

    Emission

    Factor (tCO2/t

    Fuel)-IPCC

    Emission

    (tCO2/yr)

    180 63600 1144800 2500 458 3.21 1470

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    29/33

    29

    Total emissions from sea and road transportation of coal amounts to 1493 tCO2/yr.Comparatively emissions only from PKS transportation is 1470 tCO2/yr. There is no

    significant increase in emissions from transportation by substituting coal with PKS in

    LMCB. Therefore, project emission calculations from transportation of fuel areinsignificant in the project activity.

    Power Comparisons

    The energy consumption for fuel handling and crushing of coal and PKS is estimated to

    be about the same amount. Although coal has a heat value that is twice the heat value forPKS and should require less transportation on conveyors etc. it has to be ground finer in

    the coal mill, which requires more energy than crushing the PKS. PKS is not prepared to

    be as fine as coal in particle size. The emissions difference from the power consumptionfor the fuel handling system is therefore assumed to be negligible.

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    30/33

    30

    APPENDIX 8

    MOISTURE PENALTY ASSESSMENT

    Measured PKS Penalty

    Specific heat consumption will be calculated and recorded everyday as LMCB standardoperating procedures. Since the kiln will be operating throughout the year, it is not

    possible to stop the clinker production to conduct measurement of specific heat

    consumption with and without PKS. Thus data from the days where PKS was not usedwill be compared with data with the days PKS was used to calculate specific heat

    consumption for alternative and fossil fuel.(HCAF & HCFF) according to ACM0003. Later,moisture penalty, mp can be calculated by knowing the share of PKS within the same

    period of time.

    The specific heat consumption varies significantly from day to day due to technical andnon technical reasons. The most common reasons are;

    a) Weather Condition- Rainy days, high moisture in the airb) Kiln efficiency factor due to clinker production

    c) Process variation

    Observing the two specific heat consumption graphs presented below, it can be concludedthat most of the data falls in the range of 800 to 1100 kcal/kg of clinker. To make the

    calculation more accurate, all the data values outside the range will be neglected. The data

    was extracted from clinker production reports in LMCB from the year 2004 and 2005 to

    show moisture penalty from the most recent years.

    Variation of Heat Consumption Without PKS(800-1100kcal/kg)

    500

    600

    700

    800

    900

    1000

    1100

    1200

    1300

    1400

    1500

    1600

    1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57

    Data Points

    kcal/kg

    954Average

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    31/33

    31

    Variation of Heat Consumption With PKS (800-1100kcal/kg)

    500

    600

    700

    800

    900

    1000

    1100

    1200

    1300

    1400

    1500

    1 11 22 33 45 56 67 77 87 97 107

    Data Points

    kcal/kg

    960Average

    The average specific heat consumption with and without PKS together with average

    PKS heat input share for all the relevant data points calculated from the LMCB

    production reports are given below.

    HCFF = 954 kcal/kg

    HCAF = 960 kal/kg

    Si = 11%

    Thus the moisture penalty can be calculated according to the formula given in

    Annex 3 as shown below.

    10

    =i

    FFAF

    S

    HCHCmp

    PKSkgkcalmp %10//51011

    954960=

    =

    This is equivalent to 22.8 MJ/tonne/10% PKS. Since this value is very uncertain due

    to the high variation in the actual clinker production data, theoretical value of

    moisture penalty need to be calculated from the first principle. The section below is

    based on theoretical calculation and a final conclusion is made in comparison of

    both measured and theoretical values.

    PKS Penalty Calculation

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    32/33

    32

    Precalciner Cement Plants are designed with limited retention time in the PrecalcinerVessel to allow quick combustion and heat transfer of a finely ground fossil fuel in order

    to decarbonate limestone from CaCO3 to CaO + CO2 up to a 90% completion. Thus

    effectively preparing the material to be received by the Rotary Kiln for the progress of theclinkerisation reactions.

    The burning of a coarse biomass fuel inside such a vessel has a number of disadvantageswhich require a higher overall heat input to maintain the same process efficiency and

    hence production rate from a Cement Rotary Kiln.

    These can be defined and calculated as detailed below

    1. The addition of a lower heat value fuel that encompasses higher moisture willlead to an increase in the humidity (moisture content) of the combustion gases.

    This increased humidity serves no purpose to the cement making process and

    requires heating to the process temperature before discharge from the system as itis fully integrated into the gas path from the Cement Kiln. The LHV (net specific

    heat value) of the biomass used to calculate the efficiency or overall heat

    consumption accounts for the Latent Heat of Vaporisation of moisture in all

    fuels. It does not however account for the subsequent heating of that vapour toprocess conditions and the additional heat lost from the Cement manufacturing

    process as this gas forms part of the exhaust gases. Heated to 900C in the

    Precalciner where the fuel is entered some of this heat is recovered through thepreheater tower of cyclones as it preheats the incoming Raw Meal. However this

    water vapour leaves the process at typically 430C carrying some sensible heat

    with it. The calculation of a Biomass penalty is therefore applied to heating thewater vapour from ambient temperature of 30C to preheater exit temperature of

    430C as follows

    Reference Data

    Clinker production (C = clinker) 5200 tpd Net Specific Heat Consumption 900 kcals/kg C

    Or (900 * 4.181 / 1000) = 3.7656 MJ/kg C

    % Heat attained from Biomass PKS 10 %Or (3.7656/100*10) = 0.3766 MJ/kg C

    Net Specific Heat of PKS 13.13 MJ/kg PKS

    Moisture content of PKS 22 %

    Calculation

    Heat required for 1 kg water vapour 30-430C = 0.7845 MJ/kg H2O

    22% of PKS is water vapour (0.785 * 22%) = 0.1726 MJ/kg PKS

    10% of Mjoules comes from PKS (0.173*10%)= 0.0173 MJ/kg C

    2. Cement Process operates under a negative pressure and any new material input tothe system will bring with it a quantity of air from outside the process referred to

    as inleak as it is of no useful purpose to the process. Heated to 900C in the

    Precalciner where the inleak is entered some of this heat is recovered through thepreheater tower of cyclones as it preheats the incoming Raw Meal. However this

  • 8/2/2019 Draft Monitoring Report LMCB May 4, 2006 2

    33/33

    inleak leaves the process at typically 430C carrying some sensible heat with it.The calculation of a Biomass penalty is therefore applied to heating the inleak

    from ambient temperature of 30C to preheater exit temperature of 430C as

    follows

    Reference Data

    Clinker production (C = clinker) 5200 tpd

    Or (5200 * 1000 / 24) = 216,667 kg/hr C

    Measured inleak from PKS system 62 Nm3/minWeight of air (62 * 1.2923 * 60)= 4807 kg/hr Air

    Calculation

    Heat required for 1 kg air 30-430C = 0.444 MJ/kg Air

    Heat Lost per hour by Air (0.444 * 4807) = 2134.31 MJ/hrHeat Lost per kg clinker (2134.31/ 216,667) = 0.0099

    MJ/kg C

    Total Heat Loss Penalty for additional Water Vapour and inleak

    Penalty from additional water vapour = 0.0173 MJ/kg C

    Penalty from inleaking air = 0.0099 MJ/kg C--------------------

    Total = 0.0272 MJ/kg C

    Or (0.0272 * 1000 / 4.184) = 6.5 kcals/kg C

    Additional contributions to a Penalty such as Thermal Heat Exchange efficiency betweena coarse Biomass fuel and a finely ground fossil fuel inside the Precalciner vessel,

    Increased difficulty in mixing and hence complete combustion within the residence time

    available can be considered additional to the above.

    It is also recognised within the Cement Industry that runs on a basis of having one major

    maintenance period per year that items such as inleak can increase over time due to wearand tear on equipment.

    The calculated moisture penalty is about 0.027 MJ/kg which is approximately close to thevalue calculated from the actual measurement. However, due to high variation factor in

    the actual measured data, more conservative value should be used. Considering all this

    uncertainties, a moisture penalty of 0.1 MJ/kg C per 10% biomass is to be used.