28
Good Craftsmanship Guide Drainage

Drainage

Embed Size (px)

Citation preview

Page 1: Drainage

Good Craftsmanship Guide

Drainage

Page 2: Drainage

This Good Craftsmanship Guide

highlights key problems with drainage

and gives guidance on how to avoid

them. The problems are those most

commonly identified during NHBC’s

inspection of homes under construction.

All photographs are of defects and

were taken on real building sites.

The Guide, based on the NHBC

Standards, is intended for use by

NHBC registered builders and

inspection staff.

© NHBC 2004No reproduction without NHBC prior permission in writing.

Introduction

Page 3: Drainage

Drainage

Proximity to foundations 2

Gradients 4

Bedding 6

Laying/jointing pipes 7

Access 8

Backfill 13

Support and movement 15

Protection 17

Soakaways 18

Septic tanks 20

Inspection and testing 22

Contents

1

Page 4: Drainage

Proximity to foundations

2

Problem to avoid:Undermining foundations

What to do:where possible keep foundation bottoms lower thandrainage trenches

where possible keep drainage runs outside theinfluence of the foundation loading

Page 5: Drainage

3

A

more than 1m

B is within A-150mm from bottom of foundation

B

A

less than 1m

if it is necessary for drainage to be located withinthe zone of influence of the foundation loading, laythe drainage first and surround in concrete to asuitable level, before excavating foundations

Note: If A is less than 1m, concrete drainage trench up to at least theunderside of the foundation concrete. If A is more than 1m, concrete drainagetrench up to at least B.

Page 6: Drainage

Gradients

4

Problems to avoid:Drains prone to blocking

Drains do not self-cleanse if gradients are not adequate

What to do:install drainage in accordance with the design,normally at the following minimum gradients:

The following gradients may be used where flows exceed 1.0L/second:

Pipe diameter [mm] Minimum gradient

100 1 : 80

150 1 : 150

Page 7: Drainage

5

take particular care when laying drainage close tothe minimum gradients

increase gradients where ground movement isexpected (e.g. in clay soils or in made ground)

Surface water:

– 75mm and 100mm drainage should be laid at agradient not less than 1:100

– 150mm drainage should be laid at a gradient notless than 1:150

Page 8: Drainage

Bedding

6

Problem to avoid:Drainage settling due to inadequate bedding

What to do:bed pipes:

– on granular material, minimum 100mm deep

– directly on trench bottom but only where thebottom can be accurately hand-trimmed but is firm

remove any temporary packing from under pipes to avoid hard spots

provide adequate support for manholes andinspection chambers in accordance withmanufacturers’ instructions

soft spots to be removed and replaced with suitablematerial

pipe supported on hand-trimmed trench bottom

pipe supported on bed of granular material

Page 9: Drainage

Laying/jointing pipes

7

Problem to avoid:Dislodged sealing rings

What to do:ensure pipes are cut squarely

chamfer ends of cut pipe lengths

provide lubricant to ease connection and provideseal without dislodging seal

Page 10: Drainage

Access

8

Problem to avoid:Inadequate access for clearing blocked drains

What to do:provide access in accordance with the design

ensure all pipes can be rodded

use correct sized access manholes, inspectionchambers and access chambers

Page 11: Drainage

9

continued over

Notes: 1 The clear opening may be reduced by 20mm in order to provideproper support for the cover and frame. 2 Drains up to 150mm. 3 A larger clearopening cover may be used in conjunction with a restricted access. The size isrestricted for health and safety reasons to deter entry.

Min

imum

dim

ensi

ons

for

acce

ss fi

ttin

gs a

nd c

ham

bers Inte

rnal

siz

esCo

ver

size

s

Type

Dept

h to

inve

rtLe

ngth

x W

idth

Circ

ular

Leng

th x

Wid

thCi

rcul

arfr

om c

over

leve

l (m

)(m

m x

mm

)(m

m)

(mm

x m

m)

(mm

)

Rodd

ing

eye

As d

rain

but

min

100

Sam

e si

ze a

spi

pew

ork

1

Acce

ss fi

ttin

gsm

all

150

diam

0.6

or le

ss,

150

x 10

0ex

cept

whe

re15

0 x

100

150

150

x 10

01

Sam

e si

ze a

sla

rge

22

5 x

100

situ

ated

in a

225

x 10

022

522

5 x

100

1ac

cess

fitt

ing

cham

ber

Insp

ectio

n ch

ambe

rsh

allo

w0.

6 or

less

225

x 10

019

02

—19

01

1.2 o

r le

ss45

0 x

450

450

Min

430

x 4

3043

0de

epgr

eate

r th

an 1.

245

0 x

450

450

Max

300

x 3

003

Acce

ss r

estr

icte

dto

max

350

3

Page 12: Drainage

Access

10

Minim

um dim

ensions for manholes

TypeSize of largest

Min internal

Min clear

pipe (DN) (mm

)dim

ensions1

opening size1

RectangularCircular

Rectangular lengthCircular

length and width

diameter

and width

diameter

(mm

)(m

m)

(mm

)(m

m)

Manhole

less than 1.5mequal to or

deep to soffitless than 150

750 x 6757

10007

750 x 6752

na3

2251200 x 675

12001200 x 675

2

3001200 x 750

1200greater than 300

1800 x (DN+450)The larger of 1800

or (DN+450)

greater than 1.5mequal to or

deep to soffitless than 225

1200 x 10001200

600 x 600600

3001200 x 1075

1200375 - 450

1350 x 12251200

greater than 4501800 x (DN+775)

The larger of 1800or (DN+775)

Manhole shaft

4

greater than 3.0mSteps

51050 x 800

1050600 x 600

600

deep to soffitLadder

51200 x 800

1200

Winch

6900 x 800

900600 x 600

600

Page 13: Drainage

11

Notes: 1 Larger sizes may be required for manholes on bends or where thereare junctions. 2 May be reduced to 600 by 600 where required by highwayloading considerations, subject to a safe system of work being specified. 3 Notapplicable due to working space needed. 4 Minimum height of chamber inshafted manhole 2m from benching to underside of reducing slab. 5 Min clearspace between ladder or steps and the opposite face of the shaft should beapproximately 900mm. 6 Winch only - no steps or ladders, permanent orremovable. 7 The minimum size of any manhole serving a sewer (i.e any drainserving more than one property) should be 1200mm x 675 mm rectangular or1200mm diameter.

Reproduced from Tables 11 and 12 of Approved Document H to the BuildingRegulations by permission of HMSO.

ensure that manholes, inspection chambers, accesschambers and rodding eyes will be accessible, e.g.not under fences

make sure the main channel of manholes andinspection chambers is used. This will help to avoidthe build-up of solids

make connections obliquely with the flow

continued over

proprietarymanhole

Page 14: Drainage

Access

12

finish benching neatly with a steel trowel

use the appropriate type of cover, aligned with thesurrounding ground

slow radius bends

Page 15: Drainage

13

Backfill

Problem to avoid:Damage to pipes due to unsuitable backfill

What to do:place backfill as soon as the pipes have been bedded,jointed and inspected by NHBC/local authority

carry out final visual inspection before backfilling

use granular material or selected backfill from thetrench excavation free from:

– stones larger than 40mm

– clay lumps larger than 100mm

– timber

– frozen material

– vegetable matter

compact backfill in layers not deeper than 300mm

continued over

Page 16: Drainage

Backfill

14

provide protection for pipes under roads and drives

provide protection for shallow pipes under gardenareas

protected ifcover less

than 900mm

protected ifcover lessthan 1.2m

FLEXIBLE PIPES RIGID PIPES

less than600mmcover

75mm

100mm

2 layers handcompacted beforemechanicalcompaction

150mmabove

pipe

avoid mechanical compaction until fill is at least450mm above pipework

Page 17: Drainage

15

Support and movement

Problem to avoid:Damage to pipes due to differential movement

What to do:ensure pipework can move where it passes thoughsubstructure by:

– allowing at least 50mm clearance around pipe*

– providing a sleeve, or

– building pipe into wall with flexible joints within150mm of the wall

* a greater allowance may be required, for example,where settlement or clay heave may produce upto 150mm differential movement.

the opening should be protected against vermin entry

continued over

Page 18: Drainage

16

provide concrete under rest bend at base of SVP connection

ensure pipes under suspended floors areadequately supported along their length to allow for ground movement in clay subsoils or inmade ground

ensure an adequate void is left under pipeworkbelow suspended floors to allow for clay heave

50mm spacearound pipe

openingmaskedboth sides

PIPES PASSING THROUGH LINTELLED OPENING

flexiblejoint

flexiblejoint

600mmmax

600mmmax

150mmmax

150mmmax

PIPES BEDDED IN WALLS

Support and movement

Page 19: Drainage

Protection

17

Problem to avoid:Damage to access fittings and pipes

What to do:provide temporary protection to access fittings

clearly identify access points so plant movementcan avoid damaging them

Page 20: Drainage

Soakaways

18

Problem to avoid:Ineffective storage and disposal of surface water

What to do:lower than the building

locate soakaways at least 5m away from building.

carry out a percolation test unless the ground isfree draining and granular. If in doubt carry out a test

fill with clean hardcore 10mm - 150mm in size

provide PVC sheet or concrete blinding over the fillto prevent topsoil being washed into the soakaway

Page 21: Drainage

19

PVC sheet orconcrete blinding

diameter D

effective depth D

Page 22: Drainage

Septic tanks

20

Problems to avoid:Ineffective operation

Ineffective outfall

Page 23: Drainage

21

What to do:check approval from:

– Environment Agency (England and Wales)

– Scottish Environment Protection Agency (Sc)

– Environment and Heritage Service (NI)

carry out percolation test to ensure satisfactoryoutfall disposal

site at least 7m from a dwelling. In Scotland theyshould be at least 5m from a dwelling and aboundary. The tank should be within 30m of avehicle access for emptying

ensure that effluent is drained away from the building

Page 24: Drainage

Inspection and testing

22

Problem to avoid:Ineffective operation of drainage

What to do:check that pipe runs are straight, with adequategradients

check all debris is removed from pipe runs and chambers

check drainage system is in full working order at completion

carry out air/water testing

Page 25: Drainage

23

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

Notes

Page 26: Drainage

24

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

Notes

Page 27: Drainage

25

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

______________________________________________________

Notes

Page 28: Drainage

NHBC, Buildmark House, Chiltern Avenue,Amersham, Bucks HP6 5APTel: 0870 241 4302 Fax: 01494 735201 www.nhbc.co.uk

HB1961 03/04