226
PROJECT TITLE: LOCATION: ZAMBOANGA CITY % OF TOTAL AMOUNT I-ESTIMATED COST A. DIRECT COST: 1. Mobilization/Demobilization 0.79% 189,813.85 2. Environmental Compliance and Permits 0.18% 43,600.00 2. Materials 58.29% 13,923,166.19 3. Labor (including fringe benefits) 13.47% 3,216,095.28 4. Equipment Expenses 8.00% 1,909,633.38 B. INDIRECT COST: 1. Overhead, Contingency, Miscellaneous 4.77% 1,138,883.07 2. Profit 3. Comprehensive All Risk In surance 4. Value Added Tax (12% od EDC, OCM & Profit) 5. Material Testing (7% of 1% of OCM) SUB-TOTAL (CONTRACT COST) II-ESTIMATED GOVERNMENT EXPENDITURES 1. Engineering & Administrative Overhead 2.50% 597,110.87 2. POW/Site Acquisition/Pre-Engineering 3. Materials to be Furnished by the Government 4. Materials Quality Control & Hydrology (MQCH) 5. Retention for RO & C.O. SUB-TOTAL III-CONTINGENCIES/RESERVED: 1. Physical (up tom 5% of the Estimated Contract Cost) 2. Price Escalation (up to 12% of the Estimated Contract Cost) 12.00% 2,866,132.18 3. Preliminary Engineering TOTAL ESTIMATED PROJECT COST 23,884,434.81 Prepared & Designed By: Approved By: Recommencding Project Implementation: Approved Project Implementation: Officer-In-Charge Republic of the Philippines ZAMBOANGA CITY WATER DISTRICT Pilar Street, Zamboanga City BREAKDOWN OF EXPENDITURES Checked & Reviewed By: EDITO M. BAUTISTA, JR. MARLI P. ACOSTA- DE FIESTA Officer-In-Charge CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN- MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT Planning & Dev. Section Engineering Department Planning & Design Division EFREN C. SALVACION ARNULFO A. ALFONSO Officer-In-Charge OIC - Head, Technical Services Group MARK BENEDICT C. REYES Senior Engineer A (M.E.) - J.O. FELIX FEDERICO N. MENDOZA III Senior Engineer A (E.E.) - J.O. General Manager A LEONARDO REY D. VASQUEZ

Dumalon W.S. Ground Tank_Final

  • Upload
    jungzki

  • View
    238

  • Download
    4

Embed Size (px)

Citation preview

Page 1: Dumalon W.S. Ground Tank_Final

PROJECT TITLE:

LOCATION: ZAMBOANGA CITY

% OF TOTAL AMOUNT

I-ESTIMATED COST

A. DIRECT COST:

1. Mobilization/Demobilization 0.79% 189,813.85

2. Environmental Compliance and Permits 0.18% 43,600.00

2. Materials 58.29% 13,923,166.19

3. Labor (including fringe benefits) 13.47% 3,216,095.28

4. Equipment Expenses 8.00% 1,909,633.38

B. INDIRECT COST:

1. Overhead, Contingency, Miscellaneous 4.77% 1,138,883.07

2. Profit

3. Comprehensive All Risk In surance

4. Value Added Tax (12% od EDC, OCM & Profit)

5. Material Testing (7% of 1% of OCM)

SUB-TOTAL (CONTRACT COST)

II-ESTIMATED GOVERNMENT EXPENDITURES

1. Engineering & Administrative Overhead 2.50% 597,110.87

2. POW/Site Acquisition/Pre-Engineering

3. Materials to be Furnished by the Government

4. Materials Quality Control & Hydrology (MQCH)

5. Retention for RO & C.O.

SUB-TOTAL

III-CONTINGENCIES/RESERVED:

1. Physical (up tom 5% of the Estimated Contract Cost)

2. Price Escalation (up to 12% of the Estimated Contract Cost) 12.00% 2,866,132.18

3. Preliminary Engineering

TOTAL ESTIMATED PROJECT COST 23,884,434.81

Prepared & Designed By:

Approved By: Recommencding Project Implementation: Approved Project Implementation:

Officer-In-Charge

Republic of the Philippines

ZAMBOANGA CITY WATER DISTRICT

Pilar Street, Zamboanga City

BREAKDOWN OF EXPENDITURES

Checked & Reviewed By:

EDITO M. BAUTISTA, JR.

MARLI P. ACOSTA- DE FIESTA

Officer-In-Charge

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

Planning & Dev. Section

Engineering Department

Planning & Design Division

EFREN C. SALVACION ARNULFO A. ALFONSO

Officer-In-Charge OIC - Head, Technical Services Group

MARK BENEDICT C. REYES

Senior Engineer A (M.E.) - J.O.

FELIX FEDERICO N. MENDOZA III

Senior Engineer A (E.E.) - J.O.

General Manager A

LEONARDO REY D. VASQUEZ

Page 2: Dumalon W.S. Ground Tank_Final

PROJECT/LOCATION OF PROJECT: APPROPRIATE :

SOURCE OF FUND :

ISSUED OBLIGATED :

AUTHORITY RELEASED :

CALENDAR DAYS

PROJECT CATEGORY: TO COMPLETE :

Modular Ground Tank DESIRABLE STARTING DATE :

CONTRACT / / ADMINISTRATION / X /

PROJECT DESCRIPTION:

Construction of Modular Ground Tank at Brgy. Baluno & Sitio Bandera Brgy. Dulian

No. No. No.

4 4 2

4 2

1 4

2 4

4 4

4 4

4 2

2 2

4 16

TOTAL UNIT COST

SPL - 1 0.23% lot 43,600.00 43,600.00

SPL - 2 0.16% ln.m. 30,507.34 272.39

SPL - 3 0.20% units 37,003.00 18,501.50

SPL - 4 4.69% lot 884,424.00 442,212.00

ITEM 100(2)0.15% e.a. 28,100.69 1,756.29

SPL - 5 1.22% cu.m. 230,975.00 745.08

SPL - 6 0.12% cu.m. 22,644.37 352.22

SPL - 7 1.37% kgs. 257,568.83 45.80

SPL - 8 1.77% cu.m. 333,086.91 7,252.20

SPL - 9 0.37% sq.m. 69,850.83 886.21

SPL - 10 0.29% sq.m. 54,062.83 182.29

SPL - 11 0.97% lot 182,625.00 182,625.00

SPL - 12 0.62% sq.m. 116,657.12 307.69

SPL - 13 0.14% unit 26,700.60 26,700.60

SPL - 14 0.05% cu.m. 8,689.32 352.22

SPL - 15 0.47% kgs. 88,874.78 45.81

SPL - 16 0.58% cu.m. 108,970.10 7,382.80

SPL - 17 0.38% sq.m. 72,199.12 897.33

SPL - 18 0.20% sq.m. 36,848.43 182.71

SPL - 19 0.97% lot 182,685.00 182,685.00

SPL - 20 0.48% sq.m. 90,236.79 317.46

SPL - 21 0.14% unit 26,700.60 26,700.60SUPPLY & INSTALLATION OF PANAFLEX SIGNAGE 1.00 28,302.64

193.67

STRUCTURE EXCAVATION (BALUNO FENCE) 64.29 373.36

REINFORCING STEEL BAR, GRADE 33 (BALUNO FENCE) 5,624.12 48.54

45.93 7,687.33

MASONRY WORKS (BALUNO FENCE) 78.82 939.38

STRUCTURAL CONCRETE CLASS A (BALUNO FENCE)

SUPPLY & INSTALLATION OF PANAFLEX SIGNAGE

CONTRUCTION OF PERIMETER FENCE (BANDERA)

STRUCTURE EXCAVATION (BALUNO FENCE) 24.67 373.36

REINFORCING STEEL BAR, GRADE 33 (BALUNO FENCE) 1,940.10

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF

DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-SAN

ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER

SYSTEM PROJECT

1.00 28,302.64

PAINTING WORKS (BALUNO FENCE)

PLASTERING WORKS (BALUNO FENCE) 296.57 193.23

STEEL WORKS (BALUNO FENCE) 1.00 193,582.50

379.14 326.15

One-Bagger Mixer Welding Machine Construction Foreman

Concrete Vibrator Pipefiter

Bar Bender

CONTRUCTION OF PERIMETER FENCE (BALUNO)

Republic of the Philippines

ZAMBOANGA CITY WATER DISTRICT

Pilar Street, Zamboanga City

INDIVIDUAL PROGRAM OF WORK

5/10/2014

DATE

upon Approval

MINIMUM EQUIPMENT REQUIREMENT TECHNICAL PERSONNEL REQUIRED

Description Description Description Description

23,884,434.81

Painter

Power Saw Carpenter

Tamper Rammer Mason

Bar Cutter/Cut-Off Saw

Steelman

ESTIMATED COST OF PROPOSED PROJECTS

ITEM NO. DESCRIPTION % OF

TOTAL UNIT QTY.

DIRECT COST

ADJUSTED UNIT

Hauling Truck/Cargo Truck

Water Truck

Tile Cutter/Angular Grinder

Plumber

Welder

Laborers

201.68

INDIVIDUAL REMOVAL OF TRESS (small a, 150-300mm. Ø )

(BALUNO & BANDERA) 16.00 1,861.67

EMBANKMENT (BALUNO) 310.00 789.79

CONST. OF TEMPORARY FACILITY (BALUNO & BANDERA) 2.00 19,611.59

HAULING OF MATERIALS (BALUNO & BANDERA) 2.00 468,744.72

48.56

STRUCTURAL CONCRETE CLASS A (BALUNO FENCE) 14.76

80.46

7,825.77

951.17

PLASTERING WORKS (BALUNO FENCE)

MASONRY WORKS (BALUNO FENCE)

FEES & PERMITS (BALUNO & BANDERA) 1.00 43,600.00

CONSTRUCTION SAFETY & HEALTH PROGRAM (BALUNO &

BANDERA) 112.00 288.73

STEEL WORKS (BALUNO FENCE) 1.00 193,646.10

PAINTING WORKS (BALUNO FENCE) 284.25 336.51

Dumalon Ground Tank_Final

Page 3: Dumalon W.S. Ground Tank_Final

SPL - 22 0.00% cu.m. 563.56 352.22

SPL - 23 0.16% kgs. 30,209.32 45.78

SPL - 24 0.01% lot 1,988.88 1,988.88

SPL - 25 0.12% cu.m. 23,379.28 7,905.08

SPL - 26 0.08% sq.m. 15,041.05 858.02

SPL - 27 0.05% sq.m. 9,739.50 187.30

SPL - 28 0.01% sq.m. 2,526.72 1,180.71

SPL - 29 0.14% lot 26,656.00 26,656.00

SPL - 30 0.04% lot 8,421.10 8,421.10

SPL - 31 0.01% lot 1,600.00 1,600.00

SPL - 32 0.02% sq.m. 2,900.00 1,000.00

SPL - 33 0.22% sq.m. 41,856.10 353.85

SPL - 34 0.00% cu.m. 563.56 352.22

SPL - 35 0.16% kgs. 30,209.32 45.78

SPL - 36 0.01% lot 1,988.88 1,988.88

SPL - 37 0.12% cu.m. 23,379.28 7,905.08

SPL - 38 0.08% sq.m. 15,041.05 858.02

SPL - 39 0.05% sq.m. 9,739.50 187.30

SPL - 40 0.01% sq.m. 2,526.72 1,180.71

SPL - 41 0.14% lot 26,656.00 26,656.00

SPL - 42 0.04% lot 8,421.10 8,421.10

SPL - 43 0.01% lot 1,600.00 1,600.00

SPL - 44 0.02% sq.m. 2,900.00 1,000.00

SPL - 45 0.22% sq.m. 41,856.10 353.85

SPL - 46 0.01% cu.m. 1,010.88 352.22

SPL - 47 0.36% cu.m. 67,893.28 7,987.44

SPL - 48 0.23% kgs. 42,766.70 54.41

SPL - 49 0.17% lot 32,535.00 32,535.00

SPL - 50 0.20% lot 38,341.00 38,341.00

SPL - 51 0.32% sq.m. 60,046.36 862.74

SPL -52 0.13% sq.m. 25,430.28 182.69

SPL - 53 0.11% sq.m. 19,813.58 817.39

SPL - 54 0.06% lot 11,000.00 11,000.00

SPL - 55 0.09% sq.m. 17,015.00 3,357.34

SPL - 56 0.02% lot 3,700.00 3,700.00

SPL - 57 0.20% sq.m. 37,523.12 312.69

SPL - 58 0.27% cu.m. 51,209.15 9,361.82

SPL - 59 0.01% cu.m. 1,010.88 352.22

SPL - 60 0.36% cu.m. 67,893.28 7,987.44

SPL - 61 0.23% kgs. 42,766.70 54.41

SPL - 62 0.17% lot 32,535.00 32,535.00

SPL - 63 0.20% lot 38,341.00 38,341.00

SPL - 64 0.32% sq.m. 60,046.36 862.74

SPL - 65 0.13% sq.m. 25,430.28 182.69

SPL - 66 0.11% sq.m. 19,813.58 817.39

SPL - 67 0.06% lot 11,000.00 11,000.00

SPL - 68 0.09% sq.m. 17,015.00 3,357.34

1.00 11,660.00

5.07 3,558.78

1.00 3,922.00

120.00 PAINTING WORKS (BALUNO OPERATOR'S ROOM)

CONTRUCTION OF OPERATOR'S ROOM (BANDERA)

GLASS WORKS (BANDERA GUARD HOUSE) 1.00 1,696.00

TILE WORKS (BANDERA GUARD HOUSE) 2.14 1,251.55

CARPENTRY WORKS (BANDERA GUARD HOUSE) 1.00

CONTRUCTION OF GUARD HOUSE (BANDERA)

CONTRUCTION OF GUARD HOUSE (BALUNO)

17.53 909.50

PLASTERING WORKS (BANDERA GUARD HOUSE) 52.00 198.54

STRUCTURE EXCAVATION (BALUNO GUARD HOUSE)

REINFORCING STEEL BAR, GRADE 33 (BALUNO GUARD

HOUSE)

8,926.37

1,696.00

REINFORCING STEEL BAR, GRADE 33 (BANDERA GUARD

HOUSE) 659.83

TILE WORKS (BALUNO GUARD HOUSE) 2.14 1,251.55

CARPENTRY WORKS (BALUNO GUARD HOUSE) 1.00 28,255.36

375.08

STRUCTURE EXCAVATION (BANDERA GUARD HOUSE) 1.60 373.36

WATERPROOFING WORKS (BALUNO GUARD HOUSE) 2.90 1,060.00

118.29

5.47 9,923.53

1.60 373.36

659.83 48.53

909.50

48.53

373.36

8.50 8,466.69

785.95 57.68

34,487.10

1.00 40,641.46

69.60 914.50

139.20 193.65

24.24

1.00

PAINTING WORKS (BALUNO GUARD HOUSE)

STEEL WORKS (BALUNO GUARD HOUSE) 1.00

GLASS WORKS (BALUNO GUARD HOUSE) 1.00

PLASTERING WORKS (BALUNO GUARD HOUSE) 52.00 198.54

PLUMBING WORKS (BALUNO GUARD HOUSE) 1.00 2,108.21

STRUCTURAL CONCRETE CLASS A (BALUNO GUARD HOUSE) 2.96 8,379.39

MASONRY WORKS (BALUNO GUARD HOUSE) 17.53

2.87

2,108.21

28,255.36

STEEL WORKS (BANDERA GUARD HOUSE) 1.00 8,926.37

STRUCTURAL CONCRETE CLASS A (BANDERA GUARD HOUSE) 2.96 8,379.39

MASONRY WORKS (BANDERA GUARD HOUSE)

866.44

PAINTING WORKS (BANDERA GUARD HOUSE) 118.29 375.08

785.95 57.68

1.00 11,660.00

5.07 3,558.78

STEEL WORKS (BALUNO OPERATOR'S ROOM)

GLASS WORKS (BALUNO OPERATOR'S ROOM)

1.00

40,641.46

69.60 914.50

139.20 193.65

24.24 866.44

MASONRY WORKS (BANDERA OPERATOR'S ROOM)

CARPENTRY WORKS (BANDERA OPERATOR'S ROOM)

PLASTERING WORKS (BANDERA OPERATOR'S ROOM)

TILE WORKS (BANDERA OPERATOR'S ROOM)

WATERPROOFING WORKS (BANDERA OPERATOR'S ROOM)

STEEL WORKS (BANDERA OPERATOR'S ROOM)

WATERPROOFING WORKS (BANDERA GUARD HOUSE)

STRUCTURE EXCAVATION (BALUNO OPERATOR'S ROOM)

TILE WORKS (BALUNO OPERATOR'S ROOM)

WATERPROOFING WORKS (BALUNO OPERATOR'S ROOM)

STRUCTURE EXCAVATION (BANDERA OPERATOR'S ROOM)

STRUCTURAL CONCRETE CLASS A (BANDERA OPERATOR'S

ROOM)

REINFORCING STEEL BAR, GRADE 33 (BANDERA OPERATOR'S

ROOM)

PLUMBING WORKS (BANDERA OPERATOR'S ROOM)

STRUCTURAL CONCRETE CLASS A (BALUNO OPERATOR'S

ROOM)

REINFORCING STEEL BAR, GRADE 33 (BALUNO OPERATOR'S

ROOM)

CONTRUCTION OF OPERATOR'S ROOM (BALUNO)

PLUMBING WORKS (BALUNO OPERATOR'S ROOM)

CARPENTRY WORKS (BALUNO OPERATOR'S ROOM)

MASONRY WORKS (BALUNO OPERATOR'S ROOM)

PLASTERING WORKS (BALUNO OPERATOR'S ROOM)

2.90

PLUMBING WORKS (BANDERA GUARD HOUSE) 1.00

1,060.00

CONST. OF WATERPROOF SEPTIC VAULT (BALUNO

OPERATOR'S ROOM)

331.45

2.87 373.36

8.50 8,466.69

34,487.10

1.00

Dumalon Ground Tank_Final

Page 4: Dumalon W.S. Ground Tank_Final

SPL - 69 0.02% lot 3,700.00 3,700.00

SPL - 70 0.20% sq.m. 37,523.12 312.69

SPL - 71 0.27% cu.m. 51,209.15 9,361.82

ITEM 505(5) 0.82% cu.m. 154,525.07 3,278.00

SPL - 72 1.97% lot 371,332.00 371,332.00

SPL - 73 2.16% lot 406,480.00 406,480.00

SPL - 74 58.32% lot 11,000,000.00 5,500,000.00

SPL - 75 1.31% lots 246,851.80 123,425.90

SPL - 76 1.35% units 254,995.06 254,995.06

SPL - 77 2.23% units 420,594.06 420,594.06

SPL - 78 7.25% units 1,367,972.09 341,993.02

SPL - 79 0.95% cu.m. 179,740.37 6,442.31

SPL - 80 0.77% sq.m. 144,870.00 561.51

SPL - 81 0.19% lot 36,545.00 36,545.00

SPL - 82 0.19% ln.m. 35,805.00 51.15

SPL - 83 0.17% lot 31,236.00 31,236.00

SPL - 84 0.17% lot 31,725.00 31,725.00

SPL - 85 0.19% lot 36,545.00 36,545.00

SPL - 86 0.17% lot 31,236.00 31,236.00

SPL - 87 0.17% lot 31,725.00 31,725.00

100.00%

Checked & Reviewed By:

Recommencding Project Implementation: Approved Project Implementation:

1.00

33,110.16

SUPPLY & INST. OF ELEC. FACILITIES FOR GUARD HOUSE,

SIGNAGE & PERIMETER LIGHTINGS 33,628.50

38,737.70

54.22

33,110.16

33,628.50

38,737.70

SUPPLY, STRINGING & LAY-OUTING OF APPROX. 700 L.M. 1Ø

LINE W/ 6 UNITS PEDESTAL AND ACCS:

SUPPLY & INSTALLATION OF ELECTRICAL FACILITIES FOR

OPERATOR'S ROOM

SUPPLY & INST. OF ELEC. FACILITIES FOR GUARD HOUSE,

SIGNAGE & PERIMETER LIGHTINGS

SUPPLY, TESTING & INSTALLATION OF KW-HR METER,

RACEWAY AND ACCESSORIES

CONSTRUCTION OF SEPTIC VAULT (BANDERA OPERATOR'S

ROOM)

1.00

Approved By:

LEONARDO REY D. VASQUEZ

TOTAL 18,861,519.85Php

Prepared By:

CONSTRUTION OF DRIVEWAY (BALUNO & BANDERA) 27.90 6,828.85

PIPELINE & APPURTENANCES (BALUNO) 1.00 393,611.92

362,512.60

Planning & Design Division

PIPELINE & APPURTENANCES (BANDERA) 1.00 430,868.80

1.00 3,922.00

GROUTED RIPRAP (CLASS A) (BALUNO)

120.00 331.45

47.14 3,474.68

5.47 9,923.53

GLASS WORKS (BANDERA OPERATOR'S ROOM)

PAINTING WORKS (BANDERA OPERATOR'S ROOM)

Planning & Development Section

MARK BENEDICT C. REYES

SUPPLY & INST. OF DIFFERENTIAL FLOAT CONTROL VALVE &

CONST. OF CONC. VALVE BOX (BALUNO)

SUPPLY & INST. OF DIFFERENTIAL FLOAT CONTROL VALVE &

CONST. OF CONC. VALVE BOX (BANDERA)

SUPPLY, CONST. & INST. OF 100MMØ FLOWMETER W/ CONC.

VALVE BOX (FOR BALUNO & BANDERA)

SUPPLY/CONST./TESTING/DISINFECT./COMM. OF 300 CU.M.

MODULAR TANK (FOR BALUNO & BANDERA)

SUPPLY & INST. OF 40GPD HYPOCHLORINATOR (BANDERA &

BALUNO) 2.00

1.00

4.00

258.00

MARLI P. ACOSTA- DE FIESTA

130,831.45

270,294.76

595.20

EDITO M. BAUTISTA, JR.

2.00 5,830,000.00

Officer-In-Charge

445,829.70

SUPPLY, TESTING & INST. OF KW-HR METER, RACEWAY AND

ACCS. 1.00

700.00

1.00

1.00

1.00

LANDSCAPING WORKS (BALUNO & BANDERA)

SUPPLY & INSTALLATION OF ELECTRICAL FACILITIES FOR

OPERATOR'S ROOM 1.00

Officer-In-Charge

Senior Engineer A (M.E.) - J.O.

FELIX FEDERICO N. MENDOZA III

Senior Engineer A (E.E.) - J.O.

ARNULFO A. ALFONSO

Head, Technical Services Group

EFREN C. SALVACIOIN

Officer-In-Charge

Engineering Department

General Manager A

Dumalon Ground Tank_Final

Page 5: Dumalon W.S. Ground Tank_Final

No.

28,302.64

193.67

373.36

48.54

7,687.33

939.38

CONTRUCTION OF PERIMETER FENCE (BANDERA)

373.36

28,302.64

193.23

193,582.50

326.15

CONTRUCTION OF PERIMETER FENCE (BALUNO)

Republic of the Philippines

ZAMBOANGA CITY WATER DISTRICT

Pilar Street, Zamboanga City

INDIVIDUAL PROGRAM OF WORK

TECHNICAL PERSONNEL REQUIRED

ESTIMATED COST OF PROPOSED PROJECTS

ADJUSTED UNIT

1,861.67

789.79

19,611.59

468,744.72

48.56

7,825.77

951.17

43,600.00

288.73

193,646.10

336.51

Dumalon Ground Tank_Final

Page 6: Dumalon W.S. Ground Tank_Final

11,660.00

3,558.78

3,922.00

CONTRUCTION OF OPERATOR'S ROOM (BANDERA)

1,696.00

1,251.55

CONTRUCTION OF GUARD HOUSE (BANDERA)

CONTRUCTION OF GUARD HOUSE (BALUNO)

909.50

198.54

8,926.37

1,696.00

1,251.55

28,255.36

375.08

373.36

1,060.00

9,923.53

373.36

48.53

909.50

48.53

373.36

8,466.69

57.68

34,487.10

40,641.46

914.50

193.65

198.54

2,108.21

8,379.39

2,108.21

28,255.36

8,926.37

8,379.39

866.44

375.08

57.68

11,660.00

3,558.78

40,641.46

914.50

193.65

866.44

CONTRUCTION OF OPERATOR'S ROOM (BALUNO)

1,060.00

331.45

373.36

8,466.69

34,487.10

Dumalon Ground Tank_Final

Page 7: Dumalon W.S. Ground Tank_Final

33,110.16

33,628.50

38,737.70

54.22

33,110.16

33,628.50

38,737.70

LEONARDO REY D. VASQUEZ

6,828.85

393,611.92

362,512.60

Planning & Design Division

430,868.80

3,922.00

331.45

3,474.68

9,923.53

MARLI P. ACOSTA- DE FIESTA

130,831.45

270,294.76

595.20

5,830,000.00

Officer-In-Charge

445,829.70

General Manager A

Dumalon Ground Tank_Final

Page 8: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: FEES & PERMITS (BALUNO & BANDERA)

Unit of Measurement:

Output per day:

Quantity:

A. Labor

N/A

P

B. Equipment

N/A

P

C.

D. Output per hour = lot

E. Fees

a. Building Permit

b. ECC Requirement

b.1. Processing Fee

b.2. Support Fund

c. Electrical Permit

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 0% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 1

lot

1.00 lot

Designation No. Person No. of Days Daily Rate Amount

Sub-Total for A

Name and Capacity No. of Units No. of Days Daily Rate Amount

Total (A+B)

0.00

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B

1.00 lot 20,000.00 20,000.00

1.00 lot 4,000.00 4,000.00

1.00 lot 9,600.00 9,600.00

1.00 lot 10,000.00 10,000.00

43,600.00

43,600.00

Sub-Total for E 43,600.00

43,600.00

-

-

-

Page 9: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: CONSTRUCTION SAFETY & HEALTH PROGRAM (BALUNO & BANDERA)

Unit of Measurement:

Output per day: ln.m./day

Quantity:

A. Labor

a. Construction Foreman

b. Laborer

c. Skilled Worker

P

B. Equipment

N.A.

P

C.

D. Output per hour = ln.m./day

E. Materials

a. 1.20m x 2.40m Tarpaulin (Project Signage) including Layout

& Printing

b. 8-Feet (width) Sacoline

c. 2" x 3" x 10' Coco Lumber

d. 2" x 2" x 10' Coco Lumber

e. 1-1/2"" C.W. Nail

f. 3" C.W. Nail

g. 4" C.W. Nail

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

Designation No. Person No. of Days Daily Rate Amount

DETAILED UNIT PRICE ANALYSIS

SPL - 2

ln.m.

30.00

112.00 ln.m.

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-SAN

ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

2 3.73 366.00 2,732.80

1 3.73 873.52 3,261.14

4 3.73 317.00 4,733.87

Sub-Total for A 10,727.81

Name and Capacity No. of Units No. of Days Daily Rate Amount

Sub-Total for B -

Total (A+B) 10,727.81

30.00

Name and Specifications Quantity Unit Unit Cost Amount

186.67 bd.ft. 20.00 3,733.33

2 units 1,200.00 2,400.00

117.00 ln.m. 51.00 5,967.00

2.00 kg. 55.00 110.00

3.00 kg. 53.00 159.00

367.36 bd.ft. 20.00 7,347.20

1.00 kg. 63.00 63.00

-

32,337.78

288.73

Sub-Total for E 19,779.53

30,507.34

1,830.44

-

Page 10: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: CONST. OF TEMPORARY FACILITY (BALUNO & BANDERA)

Unit of Measurement:

Output per day: unit/day

Quantity:

A. Labor

a. Skilled Worker

b. Laborer

P

B. Equipment

N.A.

P

C.

D. Output per hour = unit/day

E. Materials

a. 2" x 4" x 10' Coco Lumber

b. 2" x 3" x 10' Coco Lumber

c. 2" x 2" x 10' Coco Lumber

d. *12mm thk x 1.20m x 2.40m Ordinary Plywood

e. Gauge 26 x 1.80m Length Corrugated G.I. Roofing Sheets

f. 2" C.W. Umbrella Roofing Nails

g. 2" C.W. Nail

h. 3" C.W. Nail

i. 4" C.W. Nail

* All sizes referred herein should mean commercially available

measurements tolerance of ±1 mm

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 3

unit

0.50

2.00 units

2 4.00 317.00 2,536.00

Designation No. Person No. of Days Daily Rate Amount

2 4.00 366.00 2,928.00

Sub-Total for A 5,464.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

Sub-Total for B -

186.00 bd.ft. 20.00 3,720.00

100.00 bd.ft. 20.00 2,000.00

Total (A+B) 5,464.00

0.50

Name and Specifications Quantity Unit Unit Cost Amount

16.00 shts. 221.00 3,536.00

2.00 kgs. 65.00 130.00

134.00 bd.ft. 20.00 2,680.00

24.00 shts. 800.00 19,200.00

2.00 kgs. 53.00 106.00

1.00 kg. 57.00 57.00

2.00 kgs. 55.00 110.00

Sub-Total for E 31,539.00

37,003.00

2,220.18

-

-

39,223.18

19,611.59

Page 11: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: HAULING OF MATERIALS (BALUNO & BANDERA)

Unit of Measurement:

Output per day: lot/day

Quantity:

A. Labor

a. Laborer

P

B. Equipment

a. Dump Truck/Hauling Truck

P

C.

D. Output per hour = lot/day

E. Materials

N.A.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

937,489.44

468,744.72

Sub-Total for E -

884,424.00

53,065.44

-

-

Total (A+B) 884,424.00

0.00

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B 775,376.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

2 43.00 9,016.00 775,376.00

Sub-Total for A 109,048.00

Designation No. Person No. of Days Daily Rate Amount

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-

CAPISAN-MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER

SYSTEM PROJECTSPL - 4

lot

2.00 lots

8 43.00 317.00 109,048.00

Page 12: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Unit of Measurement:

Output per day: e.a./day

Quantity:

A. Labor

a. Construction Foreman

b. Skilled Worker

c. Laborer

P

B. Equipment

a. Backhoe (0.80 cu.m.)

b. Dump Truck (10cu.m.)

c. Chain Saw

Minor Tools (5% of Labor)

P

C.

D. Output per hour = e.a./day

E. Materials

a. Rope

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

29,786.73

1,861.67

Sub-Total for E 1,120.00

28,100.69

1,686.04

-

-

320 m. 3.50 1,120.00

Sub-Total for B 23,867.65

Total (A+B) 26,980.69

8.00

Name and Specifications Quantity Unit Unit Cost Amount

1 1.00 600.00 600.00

155.65 155.65

1 1.00 12,296.00 12,296.00

1 1.00 10,816.00 10,816.00

Sub-Total for A 3,113.04

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 2.00 317.00 634.00

1 2.00 873.52 1,747.04

1 2.00 366.00 732.00

Designation No. Person No. of Days Daily Rate Amount

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-

CAPISAN-MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM

PROJECT

ITEM 100(2)

e.a.

8.00

16.00 e.a.

INDIVIDUAL REMOVAL OF TRESS (small a, 150-300mm. Ø ) (BALUNO &

BANDERA)

Item No./Description:

Page 13: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: GROUTED RIPRAP (CLASS A) (BALUNO)

Unit of Measurement:

Output per day: cu.m./day

Quantity:

A. Labor

a. Construction Foreman

b. Skilled Worker

c. Laborer

P

B. Equipment

a. One-Bagger Mixer

b. Water Truck (1000 gal.)

Minor Tools (5% of Labor)

P

C.

D. Output per hour = cu.m./day

E. Materials

a. Portland Cement

b. Washed Sand

c. Gravel

d. Weep Holes (PVC)

e. Filter Cloth

f. Boulders (15-25 kg.)

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

163,796.58

3,474.68

Sub-Total for E 114,566.40

154,525.07

9,271.50

-

-

0.71 sq.m. 302.50 213.90

49.5 cu.m. 1,200.00 59,400.00

0.75 cu.m. 1,050.00 787.50

5.00 pcs. 477.00 2,385.00

141 bags 260.00 36,660.00

12.00 cu.m. 1,260.00 15,120.00

Sub-Total for B 20,435.55

Total (A+B) 39,958.67

10.00

Name and Specifications Quantity Unit Unit Cost Amount

976.16

1 4.71 5,883.07

1 1.89 13,576.32

1,248.00

7,200.00

976.16

Sub-Total for A 19,523.13

Name and Capacity No. of Units No. of Days Daily Rate Amount

8 4.71 317.00 11,954.70

1 4.71 873.52 4,117.77

2 4.71 366.00 3,450.65

Designation No. Person No. of Days Daily Rate Amount

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-

CAPISAN-MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM

PROJECT

ITEM 505(5)

cu.m.

10.00

47.14 cu.m.

Page 14: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: STRUCTURE EXCAVATION (BALUNO FENCE)

Unit of Measurement:

Output per day: cu.m./day

Quantity:

A. Labor

a. Laborer

P

B. Equipment

N.A.

P

C.

D. Output per hour = cu.m./day

E. Materials

N.A.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 6

cu.m.

7.20

64.29 cu.m.

Designation No. Person No. of Days Daily Rate Amount

8 8.93 317.00 22,644.37

Sub-Total for A 22,644.37

Name and Capacity No. of Units No. of Days Daily Rate Amount

Sub-Total for B -

Total (A+B) 22,644.37

7.20

Name and Specifications Quantity Unit Unit Cost Amount

24,003.03

373.36

Sub-Total for E -

22,644.37

1,358.66

-

-

Page 15: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: REINFORCING STEEL BAR, GRADE 33 (BALUNO FENCE)

Unit of Measurement:

Output per day: kg./day

Quantity:

A. Labor

a. Construction Foreman

b. Steelman

c. Laborer

P

B. Equipment

a. Bar Bender

b. Bar Cutter

c. Cargo Truck (10T, 270 Hp)

P

C.

D. Output per hour = kg./day

E. Materials

a *16mmØ x 6.00m Def. Reinforcing Steel Bars

b. *12mmØ x 6.00m Def. Reinforcing Steel Bars

c. *10mmØ x 6.00m Def. Reinforcing Steel Bars

d. #16 G.I. Tie Wire

*All sizes referred herein should mean commercially avaiable measurements with tolerance of ± 1mm.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 7

kgs.

1 3.91 873.52 3,411.66

1,440.00

5,624.12 kgs.

Designation No. Person No. of Days

2 3.91 366.00 2,858.93

8 3.91 317.00 9,904.71

Daily Rate Amount

1 1.95 300.00 585.85

1 1.95 300.00 585.85

Sub-Total for A 16,175.29

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 0.59 8816.00 5,164.82

4,038.48 kgs. 40.50 163,558.44

1,148.10 kgs. 40.50 46,498.05

Sub-Total for B 6,336.51

Total (A+B) 22,511.81

1,440.00

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for E 235,057.02

257,568.83

15,454.13

-

-

273,022.96

48.54

437.54 kgs. 40.50 17,720.53

112.00 kgs. 65.00 7,280.00

Page 16: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: STRUCTURAL CONCRETE CLASS A (BALUNO FENCE)

Unit of Measurement:

Output per day: cu.m./day

Quantity:

A. Labor

a. Construction Foreman

b. Skilled Laborer

c. Laborer

Installation of Formworks

a. Skilled Worker

b. Laborer

P

B. Equipment

a. One Bagger Mixer (w/ Fuel)

b. Concrete Vibrator (w/ Fuel)

c. Water Truck (1000 gal.)

P

C.

D. Output per hour = cu.m./day

E. Materials

a. *12mm Thk. X 1.20m x 2.40m Ordinary Plywood

b. 2" x 4" x 10' Coco Lumber

c. 2" x 3" x 10' Coco Lumber

d. 2" x 2" x 10' Coco Lumber

e. 4" C.W. Nails

f. 3" C.W. Nails

g. 1-1/2" C.W. Nails

h. Portland Cement

i. Washed Sand

j. Gravel

*All sizes referred herein should mean commercially avaiable measurements with tolerance of ± 1mm.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

11.20

45.93 cu.m.

Designation No. Person No. of Days

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 8

cu.m.

4 4.10 366.00 6,003.59

8 4.10 317.00 10,399.66

Daily Rate Amount

1 4.10 873.52 3,582.14

Sub-Total for A 52,791.90

Name and Capacity No. of Units No. of Days Daily Rate Amount

2 16.40 366.00 12,007.18

4 16.40 317.00 20,799.33

1 0.41 8,520.00 3,493.89

1 4.10 1,376.00 5,642.72

1 4.10 972.00 3,985.99

Sub-Total for B 13,122.60

Total (A+B) 65,914.51

11.20

Name and Specifications Quantity Unit Unit Cost Amount

900.00 bd.ft. 20.00 18,000.00

667.00 bd.ft. 20.00 13,340.00

55.00 shts. 800.00 44,000.00

733.00 bd.ft. 20.00 14,660.00

5.96 kgs. 65.00 387.40

414.00 bags 260.00 107,640.00

10.00 kgs. 65.00 650.00

7.00 kgs. 65.00 455.00

Sub-Total for E 267,172.40

20.25 cu.m. 1,260.00 25,515.00

40.50 cu.m. 1,050.00 42,525.00

333,086.91

19,985.21

-

-

353,072.12

7,687.33

Page 17: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: MASONRY WORKS (BALUNO FENCE)

Unit of Measurement:

Output per day: sq.m./day

Quantity:

A. Labor

a. Skilled Laborer

b. Laborer

P

B. Equipment

a. One Bagger Mixer (w/ Fuel)

b. Bar Cutter

P

C.

D. Output per hour = sq.m./day

E. Materials

a. Portland Cement

b. Washed Sand

c. 100mm thk Concrete Hollow Blocks (NLB)

d. 150mm thk Concrete Hollow Blocks (LB)

e. *10mmØ x 6.00m Def. Reinforcing Steel Bars

f. #16 G.I. Tie-wire

*All sizes referred herein should mean commercially avaiable measurements with tolerance of ± 1mm.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 9

sq.m.

8.00

78.82 sq.m.

Designation No. Person No. of Days Daily Rate Amount

2 9.85 366.00 7,212.03

Sub-Total for A 13,458.52

2 9.85 317.00 6,246.49

1 9.85 300.00 2,955.75

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 9.85 1,376.00 13,557.04

Total (A+B) 29,971.31

8.00

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B 16,512.79

892.00 pcs. 14.00 12,488.00

122.00 pcs. 19.00 2,318.00

46.00 bags 260.00 11,960.00

3.50 cu.m. 1,260.00 4,410.00

208.48 kgs. 40.50 8,443.52

4.00 kgs. 65.00 260.00

Sub-Total for E 39,879.52

69,850.83

4,191.05

-

-

74,041.88

939.38

Page 18: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: PLASTERING WORKS (BALUNO FENCE)

Unit of Measurement:

Output per day: sq.m./day

Quantity:

A. Labor

a. Skilled Laborer

b. Laborer

P

B. Equipment

N.A.

P

C.

D. Output per hour = sq.m./day

E. Materials

a. Portland Cement

b. Fine Sand

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 10

sq.m.

16.00

296.57 sq.m.

Designation No. Person No. of Days Daily Rate Amount

2 18.54 366.00 13,568.08

Sub-Total for A 25,319.66

2 18.54 317.00 11,751.59

Name and Capacity No. of Units No. of Days Daily Rate Amount

Total (A+B) 25,319.66

16.00

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B -

85.00 bags. 260.00 22,100.00

4.75 cu.m. 1,400.00 6,643.17

Sub-Total for E 28,743.17

54,062.83

3,243.77

-

-

57,306.60

193.23

Page 19: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: STEEL WORKS (BALUNO FENCE)

Unit of Measurement:

Output per day: lot/day

Quantity:

A. Labor

a. Welder

b. Laborer

P

B. Equipment

a. Welding Machine w/ Cutting Outfit

b. Cut-Off Saw

P

C.

D. Output per hour = lot/day

E. Materials

a.

b. *6mm thk x 38mm x 6.00m M.S. Flat Bar

c. *10mmØ x 6.0m M.S. Plain Round Bar

d. *12mm x 12mm x 6.00m M.S. Square Bar

e. #4 x 50mm Mesh x 1.20m x 2.40m B.I. Steel Matting

f. 6011 Welding Rod

g. Industrial Oxygen (Content)

h. Acetylene (Content)

*All sizes referred herein should mean commercially avaiable measurements with tolerance of ± 1mm.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 11

lot

0.04

1.00 lot

Designation No. Person No. of Days Daily Rate Amount

2 25.00 394.00 19,700.00

Sub-Total for A 35,550.00

2 25.00 317.00 15,850.00

1 12.50 300.00 3,750.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 12.50 2,160.00 27,000.00

Total (A+B) 66,300.00

0.04

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B 30,750.00

10.00 pc. 210.00 2,100.00

70.00 pcs. 268.00 18,760.00

16.00 pcs. 3,032.00 48,512.00

16.00 pcs. 483.00 7,728.00

2.00 cyls. 750.00 1,500.00

1.00 cyl. 1,500.00 1,500.00

27.00 pcs. 1,260.00 34,020.00

15.00 kgs. 147.00 2,205.00

193,582.50

193,582.50

Sub-Total for E 116,325.00

182,625.00

10,957.50

-

-

50mmØ x 6.0m G.I. Pipe. (ASTM A53 90A-Heavy Gauge

Standard)

Page 20: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: PAINTING WORKS (BALUNO FENCE)

Unit of Measurement:

Output per day: sq.m./day

Quantity:

A. Labor

a. Construction Foreman

b. Painter

c. Laborer

P

B. Equipment

N.A.

P

C.

D. Output per hour = sq.m./day

E. Materials

a. Concrete Neutralizer

b. Solvent Based Acrylic Paint Primer

c.

d. Solvent Based Acrylic Cast

e. Solvent Based Acrylic Reducer

f. Red Oxide Metal Primer

g. Quick Dry Enamel Blue

h. Paint Thinner

i. Red Tinting Color for Solvent Based Acrylic Paint

j. Raw Sienna Tinting Color for Solvent Based Acrylic Paint

k. Thalo Blue Tinting Color for Solvent Based Acrylic Paint

l. Lamp Black Tinting Color for Solvent Based Acrylic Paint

m.#120 Sand Paper

n. #150 Sand Paper

o. 7" Paint Roller w/ Tray

p. 1" Paint Brush

q. 2" Paint Brush

r. 4" Paint Brush

s. Steel Brush

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

2.00

6.00

1.00

1.00

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 12

sq.

20.00

379.14 sq.m.

Designation No. Person No. of Days

2.00 18.96 873.52

Sub-Total for A 60,075.12

2.00 18.96 317.00 12,018.66

Daily Rate Amount

2.00 18.96 394.00 14,938.02

33,118.43

Sub-Total for B -

Name and Capacity No. of Units No. of Days Daily Rate Amount

1.00 gals. 320.00 320.00

12.00 gals. 882.00 10,584.00

Total (A+B) 60,075.12

20.00

Name and Specifications Quantity Unit Unit Cost Amount

3.00 gals. 570.00 1,710.00

7.00 gals. 724.00 5,068.00

25.00 gals. 1,029.00 25,725.00

9.00 gals. 452.00 4,068.00

2.00 pints 105.00 210.00

2.00 pints 105.00 210.00

3.00 gals. 346.00 1,038.00

2.00 pints 105.00 210.00

115.00 115.00

pints 105.00 210.00

doz. 151.00 906.00

116,657.12

6,999.43

-

-

pc. 55.00 55.00

pc. 22.00 22.00

Sub-Total for E 56,582.00

1.00 pc. 14.00 14.00

1.00 pc. 27.00 27.00

6.00 doz. 151.00 906.00

1.00 set

123,656.55

326.15

Solvent Based Acrylic Paint Top Coat (White Gloss)

576.00 5,184.00 gals.9.00

Page 21: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: SUPPLY & INSTALLATION OF PANAFLEX SIGNAGE

Unit of Measurement:

Output per day: unit/day

Quantity:

A. Labor

a. Welder

b. Laborer

P

B. Equipment

a. Cut-Off Saw

b. Welding Machine

P

C.

D. Output per hour = unit/day

E. Materials

a. Panaflex Signage w/ Aluminum Framing, Lighting and Accs.

(See Attached Shop Drawing)

b. 6mm Thk x 50mm x 50mm x 6.00m. MS Angle Bar

c. Welding Rod (6011)

d. 50mmØ x 6.0m G.I. Pipe. (ASTM A53 90A-Heavy Gauge Standard)

e. Fabricated 6mm Thk x 150mm x 200mm MS Plate w/ 4-12mmØ

Bolt Holes (see shop drawing)

f. Fabricated 6mm Thk x 200mm x 200mm MS Plate w/ 4-12mmØ

Bolt Holes (see shop drawing)

g. 10mmØ x 25mm S.S. Bolt w/ Nut & Washer

h. 12mmØ x 150mm S.S. Bolt w/ Nut & Washer

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 13

unit

2.00

1.00 unit

1 0.50 317.00 158.50

Designation No. Person No. of Days Daily Rate Amount

1 0.50 394.00 197.00

1 0.25 1,500.00 375.00

1 0.25 1,500.00 375.00

Sub-Total for A 355.50

Name and Capacity No. of Units No. of Days Daily Rate Amount

Sub-Total for B 750.00

1.00 unit 11,400.00 11,400.00

Total (A+B) 1,105.50

2.00

Name and Specifications Quantity Unit Unit Cost Amount

0.10 kg. 151.00

Sub-Total for E 25,595.10

26,700.60

1,602.04

-

-

960.00

760.00

16.00

8.00

pcs.

pcs.

60.00

95.00

15.10

28,302.64

28,302.64

2.00 pcs. 1,500.00 3,000.00

1.00 pc. 3,032.00 3,032.00

4.00 pcs. 1,200.00 4,800.00

1.00 pc. 1,628.00 1,628.00

Page 22: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: STRUCTURE EXCAVATION (BALUNO FENCE)

Unit of Measurement:

Output per day: cu.m./day

Quantity:

A. Labor

a. Laborer

P

B. Equipment

N.A.

P

C.

D. Output per hour = cu.m./day

E. Materials

N.A.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 14

cu.m.

7.20

24.67 cu.m.

Designation No. Person No. of Days Daily Rate Amount

8 3.43 317.00 8,689.32

Sub-Total for A 8,689.32

Name and Capacity No. of Units No. of Days Daily Rate Amount

Sub-Total for B -

Total (A+B) 8,689.32

7.20

Name and Specifications Quantity Unit Unit Cost Amount

9,210.68

373.36

Sub-Total for E -

8,689.32

521.36

-

-

Page 23: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: REINFORCING STEEL BAR, GRADE 33 (BALUNO FENCE)

Unit of Measurement:

Output per day: kg./day

Quantity:

A. Labor

a. Construction Foreman

b. Steelman

c. Laborer

P

B. Equipment

a. Bar Bender

b. Bar Cutter

c. Cargo Truck (10T, 270 Hp)

P

C.

D. Output per hour = kg./day

E. Materials

a *16mmØ x 6.00m Def. Reinforcing Steel Bars

b. *12mmØ x 6.00m Def. Reinforcing Steel Bars

c. *10mmØ x 6.00m Def. Reinforcing Steel Bars

d. #16 G.I. Tie Wire

*All sizes referred herein should mean commercially avaiable measurements with tolerance of ± 1mm.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 15

kgs.

1 1.35 873.52 1,176.89

1,440.00

1,940.10 kgs.

Designation No. Person No. of Days

2 1.35 366.00 986.22

8 1.35 317.00 3,416.73

Daily Rate Amount

1 0.67 300.00 202.09

1 0.67 300.00 202.09

Sub-Total for A 5,579.84

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 0.20 8816.00 1,781.66

Sub-Total for B 2,185.85

Total (A+B) 7,765.69

1,440.00

Name and Specifications Quantity Unit Unit Cost Amount

595.86 kgs. 40.50 24,132.37

39.00 kgs. 65.00 2,535.00

1,023.84 kgs. 40.50 41,465.52

320.40 kgs. 40.50 12,976.20

Sub-Total for E 81,109.09

88,874.78

5,332.49

-

-

94,207.26

48.56

Page 24: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: STRUCTURAL CONCRETE CLASS A (BALUNO FENCE)

Unit of Measurement:

Output per day: cu.m./day

Quantity:

A. Labor

a. Construction Foreman

b. Skilled Laborer

c. Laborer

Installation of Formworks

a. Skilled Worker

b. Laborer

P

B. Equipment

a. One Bagger Mixer (w/ Fuel)

b. Concrete Vibrator (w/ Fuel)

c. Water Truck (1000 gal.)

P

C.

D. Output per hour = cu.m./day

E. Materials

a. *12mm Thk. x 1.20m x 2.40m Ordinary Plywood

b. 2" x 4" x 10' Coco Lumber

c. 2" x 3" x 10' Coco Lumber

d. 2" x 2" x 10' Coco Lumber

e. 4" C.W. Nails

f. 3" C.W. Nails

g. 1-1/2" C.W. Nails

h. Portland Cement

i. Washed Sand

j. Gravel

*All sizes referred herein should mean commercially avaiable measurements with tolerance of ± 1mm.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

11.20

14.76 cu.m.

Designation No. Person No. of Days

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 16

cu.m.

4 1.32 366.00 1,929.34

8 1.32 317.00 3,342.09

Daily Rate Amount

1 1.32 873.52 1,151.17

Sub-Total for A 16,965.46

Name and Capacity No. of Units No. of Days Daily Rate Amount

2 5.27 366.00 3,858.69

4 5.27 317.00 6,684.17

1 0.13 8,520.00 1,122.81

1 1.32 1,376.00 1,813.37

1 1.32 972.00 1,280.96

Sub-Total for B 4,217.14

Total (A+B) 21,182.60

11.20

Name and Specifications Quantity Unit Unit Cost Amount

250.00 bd.ft. 20.00 5,000.00

197.00 bd.ft. 20.00 3,940.00

18.00 shts. 800.00 14,400.00

293.00 bd.ft. 20.00 5,860.00

2.50 kg. 65.00 162.50

133.00 bags 260.00 34,580.00

3.00 kgs. 65.00 195.00

2.00 kgs. 65.00 130.00

Sub-Total for E 87,787.50

7.00 cu.m. 1,260.00 8,820.00

14.00 cu.m. 1,050.00 14,700.00

108,970.10

6,538.21

-

-

115,508.31

7,825.77

Page 25: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: MASONRY WORKS (BALUNO FENCE)

Unit of Measurement:

Output per day: sq.m./day

Quantity:

A. Labor

a. Skilled Laborer

b. Laborer

P

B. Equipment

a. One Bagger Mixer (w/ Fuel)

b. Bar Cutter

P

C.

D. Output per hour = sq.m./day

E. Materials

a. Portland Cement

b. Washed Sand

c. 100mm thk Concrete Hollow Blocks (NLB)

d. 150mm thk Concrete Hollow Blocks (LB)

e. *10mmØ x 6.00m Def. Reinforcing Steel Bars

f. #16 G.I. Tie Wire

*All sizes referred herein should mean commercially avaiable measurements with tolerance of ± 1mm.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 17

sq.m.

8.00

80.46 sq.m.

Designation No. Person No. of Days Daily Rate Amount

2 10.06 366.00 7,362.09

Sub-Total for A 13,738.55

2 10.06 317.00 6,376.46

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 10.06 1,376.00 13,839.12

Sub-Total for B 16,856.37

1 10.06 300.00 3,017.25

212.82 kgs. 40.50 8,619.21

Total (A+B) 30,594.92

8.00

Name and Specifications Quantity Unit Unit Cost Amount

892.00 pcs. 14.00 12,488.00

143.00 pcs. 19.00 2,717.00

48.00 bags 260.00 12,480.00

4.00 cu.m. 1,260.00 5,040.00

Sub-Total for E 41,604.21

4.00 kgs. 65.00 260.00

72,199.12

4,331.95

-

-

76,531.07

951.17

Page 26: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: PLASTERING WORKS (BALUNO FENCE)

Unit of Measurement:

Output per day: sq.m./day

Quantity:

A. Labor

a. Skilled Laborer

b. Laborer

P

B. Equipment

N.A.

P

C.

D. Output per hour = sq.m./day

E. Materials

a. Portland Cement

b. Fine Sand

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 18

sq.m.

16.00

201.68 sq.m.

Designation No. Person No. of Days Daily Rate Amount

2 12.61 366.00 9,226.86

Sub-Total for A 17,218.43

2 12.61 317.00 7,991.57

Name and Capacity No. of Units No. of Days Daily Rate Amount

Total (A+B) 17,218.43

16.00

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B -

58.00 bags. 260.00 15,080.00

3.25 cu.m. 1,400.00 4,550.00

Sub-Total for E 19,630.00

36,848.43

2,210.91

-

-

39,059.34

193.67

Page 27: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: STEEL WORKS (BALUNO FENCE)

Unit of Measurement:

Output per day: lot/day

Quantity:

A. Labor

a. Welder

b. Laborer

P

B. Equipment

a. Welding Machine w/ Cutting Outfit

b. Cut-Off Saw

P

C.

D. Output per hour = lot/day

E. Materials

a. 50mmØ x 6.0m G.I. Pipe. (ASTM A53 90A-Heavy Gauge Std.)

b. *6mm thk x 38mm x 6.00m M.S. Flat Bar

c. *10mmØ x 6.0m M.S. Plain Round Bar

d. *12mm x 12mm x 6.00m M.S. Square Bar

e. #4 x 50mm Mesh x 1.20m x 2.40m B.I. Steel Matting

f. 6011 Welding Rod

g. Industrial Oxygen (Content)

h. Acetylene (Content)

*All sizes referred herein should mean commercially avaiable measurements with tolerance of ± 1mm.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 19

lot

0.04

1.00 lot

Designation No. Person No. of Days Daily Rate Amount

2 25.00 394.00 19,700.00

Sub-Total for A 35,550.00

2 25.00 317.00 15,850.00

1 12.50 300.00 3,750.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 12.50 2,160.00 27,000.00

Total (A+B) 66,300.00

0.04

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B 30,750.00

10.00 pc. 210.00 2,100.00

70.00 pcs. 268.00 18,760.00

16.00 pcs. 3,032.00 48,512.00

16.00 pcs. 483.00 7,728.00

2.00 cyls. 750.00 1,500.00

1.00 cyl. 1,500.00 1,500.00

27.00 pcs. 1,260.00 34,020.00

15.00 kgs. 151.00 2,265.00

193,646.10

193,646.10

Sub-Total for E 116,385.00

182,685.00

10,961.10

-

-

Page 28: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: PAINTING WORKS (BALUNO FENCE)

Unit of Measurement:

Output per day: sq.m./day

Quantity:

A. Labor

a. Construction Foreman

b. Painter

c. Laborer

P

B. Equipment

N.A.

P

C.

D. Output per hour = sq.m./day

E. Materials

a. Concrete Neutralizer

b. Solvent Based Acrylic Paint Primer

c. Solvent Based Acrylic Paint Top Coat (White Gloss)

d. Solvent Based Acrylic Cast

e. Solvent Based Acrylic Reducer

f. Red Oxide Metal Primer

g. Quick Dry Enamel Blue

h. Paint Thinner

i. Red Tinting Color for Solvent Based Acrylic Paint

j. Raw Sienna Tinting Color for Solvent Based Acrylic Paint

k. Thalo Blue Tinting Color for Solvent Based Acrylic Paint

l. Lamp Black Tinting Color for Solvent Based Acrylic Paint

m.#120 Sand Paper

n. #150 Sand Paper

o. 7" Paint Roller w/ Tray

p. 1" Paint Brush

q. 2" Paint Brush

r. 4" Paint Brush

s. Steel Brush

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 20

sq.m.

20.00

284.25 sq.m.

Designation No. Person No. of Days

2.00 14.21 873.52

Sub-Total for A 45,039.61

2.00 14.21 317.00 9,010.65

Daily Rate Amount

2.00 14.21 394.00 11,199.36

24,829.60

Name and Capacity No. of Units No. of Days Daily Rate Amount

Total (A+B) 45,039.61

20.00

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B -

17.00 gals. 1,029.00 17,493.00

9.00 gals. 576.00 5,185.92

1.00 gals. 520.00 520.00

9.00 gals. 882.00 7,940.94

7.00 gals. 724.00 5,068.00

3.00 gals. 346.00 1,038.00

7.00 gals. 452.00 3,165.13

4.00 gals. 570.00 2,280.18

2.00 pints 105.00 210.00

2.00 pints 105.00 210.00

2.00 pints 105.00 210.00

2.00 pints 105.00 210.00

2.00 sets 115.00 230.00

2.00 pcs. 14.00 28.00

4.00 doz. 150.00 600.00

4.00 doz. 150.00 600.00

2.00 pcs. 22.00 44.00

Sub-Total for E 45,197.17

2.00 pcs. 27.00 54.00

2.00 pcs. 55.00 110.00

90,236.79

5,414.21

-

-

95,650.99

336.51

Page 29: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: SUPPLY & INSTALLATION OF PANAFLEX SIGNAGE

Unit of Measurement:

Output per day: unit/day

Quantity:

A. Labor

a. Welder

b. Laborer

P

B. Equipment

a. Cut-Off Saw

b. Welding Machine

P

C.

D. Output per hour = unit/day

E. Materials

a. Panaflex Signage w/ Aluminum Framing, Lighting and Accs.

(See Attached Shop Drawing)

b. 6mm Thk x 50mm x 50mm x 6.00m. MS Angle Bar

c. Welding Rod (6011)

d. 50mmØ x 6.0m G.I. Pipe. (ASTM A53 90A-Heavy Gauge Standard)

e. Fabricated 6mm Thk x 150mm x 200mm MS Plate w/ 4-12mmØ

Bolt Holes (see shop drawing)

f. Fabricated 6mm Thk x 200mm x 200mm MS Plate w/ 4-12mmØ

Bolt Holes (see shop drawing)

g. 10mmØ x 25mm S.S. Bolt w/ Nut & Washer

h. 12mmØ x 150mm S.S. Bolt w/ Nut & Washer

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 21

unit

2.00

1.00 unit

Designation No. Person No. of Days Daily Rate Amount

1 0.50 394.00 197.00

Sub-Total for A 355.50

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 0.50 317.00 158.50

1 0.25 1,500.00 375.00

1 0.25 1,500.00 375.00

Total (A+B) 1,105.50

2.00

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B 750.00

1.00 pc. 1,628.00 1,628.00

0.10 kg. 151.00 15.10

1.00 unit 11,400.00 11,400.00

2.00 pcs. 1,500.00 3,000.00

1.00 pc. 3,032.00 3,032.00

4.00 pcs. 1,200.00 4,800.00

28,302.64

28,302.64

Sub-Total for E 25,595.10

26,700.60

1,602.04

-

-

16.00 pcs. 60.00 960.00

8.00 pcs. 95.00 760.00

Page 30: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: SPL - 22 STRUCTURE EXCAVATION (BALUNO GUARD HOUSE)

Unit of Measurement:

Output per day: cu.m./day

Quantity:

A. Labor

a. Laborer

P

B. Equipment

N.A.

P

C.

D. Output per hour = cu.m./day

E. Materials

N.A.

P

F. Direct Cost (C+E)

G.Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

597.37

373.36

Sub-Total for E -

563.56

33.81

-

-

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

cu.m.

1.80

1.60 cu.m.

Sub-Total for A 563.56

Name and Capacity No. of Units No. of Days Daily Rate Amount

Designation No. Person No. of Days Daily Rate Amount

2 0.89 317.00 563.56

Sub-Total for B -

Total (A+B) 563.56

1.80

Name and Specifications Quantity Unit Unit Cost Amount

Page 31: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: REINFORCING STEEL BAR, GRADE 33 (BALUNO GUARD HOUSE)

Unit of Measurement:

Output per day: kg./day

Quantity:

A. Labor

a. Construction Foreman

b. Steelman

c. Laborer

P

B. Equipment

a. Bar Bender

b. Bar Cutter

c. Cargo Truck (10T, 270 Hp)

P

C.

D. Output per hour = kg./day

E. Materials

a. *16mmØ x 6.00m Deformed Reinforced Steel Bar

b. *12mmØ x 6.00m Deformed Reinforced Steel Bar

c. *10mmØ x 6.00m Deformed Reinforced Steel Bar

d. #16 G.I. Tie Wire

*All sizes referred herein should mean commercially avaiable measurements with tolerance of ± 1mm.

P

F. Direct Cost (C+E)

G.Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

32,021.88

48.53

Sub-Total for E 27,568.20

30,209.32

1,812.56

-

-

274.92 kgs. 40.50 11,134.26

240.30 kgs. 40.50 9,732.15

Sub-Total for B 743.41

Total (A+B) 2,641.12

1,440.00

Name and Specifications Quantity Unit Unit Cost Amount

1 0.07 8816.00 605.95

1 0.23 300.00 68.73

1 0.23 300.00 68.73

Sub-Total for A 1,897.71

Name and Capacity No. of Units No. of Days Daily Rate Amount

2 0.46 366.00 335.41

8 0.46 317.00 1,162.04

Daily Rate Amount

1 0.46 873.52 400.26

1,440.00

659.83 kgs.

Designation No. Person No. of Days

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 23

kgs.

144.61 kgs. 40.50 5,856.79

845.00 13.00 kgs. 65.00

Page 32: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: PLUMBING WORKS (BALUNO GUARD HOUSE)

Unit of Measurement:

Output per day: lot/day

Quantity:

A. Labor

a. Plumber

b. Laborer

P

B. Equipment

P

C.

D. Output per hour = lot/day

E. Materials

a. 50mmØ x 3.00m. PVC Sanitary Pipe Series 1000

b. 50mmØ x 900 PVC Sanitary Elbow, Series 1000

c. 50mmØ PVC Coupling, Series 1000

d. PVC Solvent Cement

e. 100mm x 100mmStainless Floor Drain

P

F. Direct Cost (C+E)

G.Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

Sub-Total for E 1,679.00

1,988.88

119.33

-

-

2,108.21

2,108.21

1.00 qrt. 460.00 460.00

1.00 pc. 110.00 110.00

pcs. 483.00 966.00

3.00 pcs. 37.00 111.00

2.00 pcs. 16.00 32.00

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 24

lot

4.00

1.00 lot

Designation No. Person No. of Days Daily Rate Amount

1 0.25 873.52 218.38

1 0.25 366.00 91.50

Sub-Total for B

Sub-Total for A 309.88

Name and Capacity No. of Units No. of Days Daily Rate Amount

-

Total (A+B) 309.88

4.00

Name and Specifications Quantity Unit Unit Cost Amount

2.00

Page 33: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: STRUCTURAL CONCRETE CLASS A (BALUNO GUARD HOUSE)

Unit of Measurement:

Output per day: cu.m./day

Quantity:

A. Labor

a. Construction Foreman

b. Skilled Laborer

c. Laborer

Installation of Formworks

a. Skilled Worker

b. Laborer

P

B. Equipment

a. One Bagger Mixer (w/ Fuel)

b. Concrete Vibrator (w/ Fuel)

c. Water Truck (1000 gal.)

P

C.

D. Output per hour = cu.m./day

E. Materials

a. *12mm Thk x 1.20m x 2.40m Ordinary Plywood

b. 2" x 2" x 10' Coco Lumber

c. 2" x 3" x 10' Coco Lumber

d. 4" C.W. Nail

e. 3" C.W. Nail

f. 1-1/2" C.W. Nail

g. Portland Cement

h. Washed Sand

i. Gravel

*All sizes referred herein should mean commercially avaiable measurements with tolerance of ± 1mm.

P

F. Direct Cost (C+E)

G.Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

23,379.28

1,402.76

-

-

24,782.04

8,379.39

Sub-Total for E 19,134.87

3.00 cu.m. 1,050.00 3,152.73

1.00 kg. 53.00 53.00

0.50 kg. 55.00 27.50

7,020.00 260.00 bags27.00

30.00 60.00 kg.0.50

1,891.64 1,260.00 cu.m.1.50

90.00 bd.ft. 20.00 1,800.00

5.00 shts. 800.00 4,000.00

58.00 bd.ft. 20.00 1,160.00

Sub-Total for B 845.00

Total (A+B) 4,244.41

11.20

Name and Specifications Quantity Unit Unit Cost Amount

1 0.03 8,520.00 224.98

1 0.26 1,376.00 363.35

1 0.26 972.00 256.67

Sub-Total for A 3,399.41

Name and Capacity No. of Units No. of Days Daily Rate Amount

2 1.06 366.00 773.18

4 1.06 317.00 1,339.33

4 0.26 366.00 386.59

8 0.26 317.00 669.66

Daily Rate Amount

1 0.26 873.52 230.66

Designation No. Person No. of Days

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 25

cu.m.

11.20

2.96 cu.m.

Page 34: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: MASONRY WORKS (BALUNO GUARD HOUSE)

Unit of Measurement:

Output per day: sq.m./day

Quantity:

A. Labor

a. Skilled Laborer

b. Laborer

P

B. Equipment

a. One Bagger Mixer (w/ Fuel)

b. Bar Cutter

P

C.

D. Output per hour = sq.m./day

E. Materials

a. 150mm x 200mm x 400mm CHB (LB)

b. 100mm x 200mm x 400mm CHB (NLB)

c. Portland Cement

d. Washed Sand

e. *10mm.Ø x 6.00m Deformed Reinf. Steel Bar

f. #16 G.I. Tie Wire

*All sizes referred herein should mean commercially avaiable measurements with tolerance of ± 1mm.

P

F. Direct Cost (C+E)

G.Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

15,041.05

902.46

-

-

15,943.51

909.50

Sub-Total for E 9,177.26

48.20 kgs. 40.50 1,952.26

1.00 kg. 65.00 65.00

11.00 bags 260.00 2,860.00

0.75 cu.m. 1,260.00 945.00

41.00 pcs. 19.00 779.00

184.00 pcs. 14.00 2,576.00

Total (A+B) 5,863.79

8.00

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B 3,672.54

1 2.19 300.00 657.38

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 2.19 1,376.00 3,015.16

Sub-Total for A 2,191.25

2 2.19 317.00 1,389.25

Designation No. Person No. of Days Daily Rate Amount

1 2.19 366.00 802.00

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 26

sq.m.

8.00

17.53 sq.m.

Page 35: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: PLASTERING WORKS (BALUNO GUARD HOUSE)

Unit of Measurement:

Output per day: sq.m./day

Quantity:

A. Labor

a. Skilled Laborer

b. Laborer

P

B. Equipment

N.A.

P

C.

D. Output per hour = sq.m./day

E. Materials

a. Portland Cement

b. Fine Sand

P

F. Direct Cost (C+E)

G.Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

9,739.50

584.37

-

-

10,323.87

198.54

Sub-Total for E 5,300.00

15.00 bags. 260.00 3,900.00

1.00 cu.m. 1,400.00 1,400.00

Total (A+B) 4,439.50

16.00

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B -

Name and Capacity No. of Units No. of Days Daily Rate Amount

Sub-Total for A 4,439.50

2 3.25 317.00 2,060.50

Designation No. Person No. of Days Daily Rate Amount

2 3.25 366.00 2,379.00

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 27

sq.m.

16.00

52.00 sq.m.

Page 36: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: TILE WORKS (BALUNO GUARD HOUSE)

Unit of Measurement:

Output per day: sq.m./day

Quantity:

A. Labor

a. Skilled Laborer

b. Laborer

P

B. Equipment

a. Tile Cutter/Angular Grinder

P

C.

D. Output per hour = sq.m./day

E. Materials

a. 400mm x 400mm Granite Tiles

b. Tile Adhesive (25Kg/Bag)

c. Tile Grout (2 Kg./Pack)

P

F. Direct Cost (C+E)

G.Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

2,526.72

151.60

-

-

2,678.33

1,251.55

Sub-Total for E 2,106.00

1.00 bag 58.00 58.00

14.00 pcs. 126.00 1,764.00

1.00 bag 284.00 284.00

Total (A+B) 420.72

5.00

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B 128.40

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 0.43 300.00 128.40

Sub-Total for A 292.32

1 0.43 317.00 135.68

Designation No. Person No. of Days Daily Rate Amount

1 0.43 366.00 156.65

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 28

sq.m.

5.00

2.14 sq.m.

Page 37: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: CARPENTRY WORKS (BALUNO GUARD HOUSE)

Unit of Measurement:

Output per day: lot/day

Quantity:

A. Labor

a. Skilled Worker

b. Laborer

P

B. Equipment

a. Bar Cutter

b. Welding Machine

P

C.

D. Output per hour = lot/day

E. Materials

a.

b.

c. Chrome Heavy Duty Door Knob w/ complete accessories

d. 4" x 3" Loose Pin Hinges w/ Screw

e. 4" C.W. Nail

Fabrication of Cabinet

a. Round Cabinet Handle (Chrome)

b. Cabinet Lock (Chrome)

c. Cabinet Concealed Hinges w/ Screw

d. 1" x 2" x 8' Laua-an Lumber

e. 2" x 2" x 8' Laua-an Lumber

f. 2" x 3" x 10' Laua-an Lumber

g. 1" x 6" x 8' Laua-an Lumber

h. 19mm Thk x 1.20m x 2.40m Marine Plyboard

i. 6mm Thk x 1.20m x 2.40m Marine Plyboard

j. 6mm Thk x 50mm x 50mm x 6.00m M.S. Angle Bar

k. Ga. 16 x 1.20m x 2.40m G.I. Sheet

l. Welding Rod (6011)

m. 3" C.W. Nail

n. 1" C.W. Finishing Nail

P

F. Direct Cost (C+E)

G.Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

26,656.00

1,599.36

-

-

28,255.36

28,255.36

1.00 kg. 75.00 75.00

Sub-Total for E 20,856.00

0.50 kg. 151.00 75.50

1.00 kg. 55.00 55.00

2.00 pcs. 1,050.00 2,100.00

1.00 sht. 2,500.00 2,500.00

4.00 shts. 1,551.00 6,204.00

1.00 sht. 684.00 684.00

10.00 bd.ft. 32.00 320.00

4.00 bd.ft. 32.00 128.00

1.33 bd.ft. 32.00 42.67

2.67 bd.ft. 32.00 85.33

2.00 pcs. 200.00 400.00

8.00 pcs. 65.00 520.00

4.00 pcs. 120.00 480.00

4.00 pcs. 140.00 560.00

0.50 kg. 53.00 26.50

2.00 units 900.00 1,800.00

1.00 unit 800.00 800.00

1.00 unit 4,000.00 4,000.00

Total (A+B) 5,800.00

0.17

Name and Specifications Quantity Unit Unit Cost Amount

Pre-Fab 0.60m x 2.10m Flash Type Door, 50mm x 100mm

Mahogany Wood Door Frame w/ 6mm Thk Marine Plywood

Sheeting & w/ 50mm x 100mm Mahogany Wood Door Jamb

Pre-Fab 0.60m x 1.165m 1-Pannel Window Jamb, 50mm x 150mm

Mahogany Wood

Sub-Total for A 4,309.09

1 6.06 317.00 1,921.21

Designation No. Person No. of Days Daily Rate Amount

1 6.06 394.00 2,387.88

Sub-Total for B 1,490.91

1 0.61 2,160.00 1,309.09

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 0.61 300.00 181.82

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 29

lot

0.17

1.00 lot

DETAILED UNIT PRICE ANALYSIS

Page 38: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: STEEL WORKS (BALUNO GUARD HOUSE)

Unit of Measurement:

Output per day: lot/day

Quantity:

A. Labor

a. Welder

b. Laborer

P

B. Equipment

a. Welding Machine

b. Cut-Off Saw/Bar Cutter

P

C.

D. Output per hour = lot/day

E. Materials

a. 10mm x 10mm x 6.00m M.S. Square Bar

b. 12mm x 12mm x 6.00m M.S. Square Bar

c. 6mm Thk x 50mm x 6.00m M.S. Flat Bar

d. Hacksaw Blade

e. 6011 Welding Rod

P

F. Direct Cost (C+E)

G.Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

8,421.10

505.27

-

-

8,926.37

8,926.37

Sub-Total for E 4,538.00

8.00 kgs 151.00 1,208.00

2.00 pcs. 894.00 1,788.00

4.00 pcs. 65.00 260.00

1.00 pc. 210.00 210.00

4.00 pcs. 268.00 1,072.00

Total (A+B) 3,883.10

0.50

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B 2,460.70

1 1.00 300.00 300.09

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 1.00 2,160.00 2,160.61

Sub-Total for A 1,422.40

1 2.00 317.00 634.18

Designation No. Person No. of Days Daily Rate Amount

1 2.00 394.00 788.22

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 30

lot

0.50

1.00 lot

Page 39: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: GLASS WORKS (BALUNO GUARD HOUSE)

Unit of Measurement:

Output per day: lot/day

Quantity:

A. Labor

N.A.

P

B. Equipment

N.A.

P

C.

D. Output per hour = lot/day

E. Materials

a. Supply & Installation of 5.5 mm Thk x 13 Blades x 0.60m

width Smoke Glass Jalousies w/ Aluminum Holder

P

F. Direct Cost (C+E)

G.Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

-

1,696.00

1,696.00

Sub-Total for E 1,600.00

1,600.00

96.00

-

Total (A+B) -

1.00

Name and Specifications Quantity Unit Unit Cost Amount

2.00 sets 800.00 1,600.00

Sub-Total for B -

Sub-Total for A -

Name and Capacity No. of Units No. of Days Daily Rate Amount

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 31

lot

1.00

1.00 lot

Designation No. Person No. of Days Daily Rate Amount

Page 40: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: WATERPROOFING WORKS (BALUNO GUARD HOUSE)

Unit of Measurement:

Output per day: sq.m.day

Quantity:

A. Labor

N.A.

P

B. Equipment

N.A.

P

C.

D. Output per hour = sq.m.day

E. Materials

a. Bituminous Membrane Polyester Reinforced Waterproofing

P

F. Direct Cost (C+E)

G.Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

-

3,074.00

1,060.00

Sub-Total for E 2,900.00

2,900.00

174.00

-

Total (A+B) -

0.00

Name and Specifications Quantity Unit Unit Cost Amount

2.90 sq.mtr. 1,000.00 2,900.00

Sub-Total for B -

Sub-Total for A -

Name and Capacity No. of Units No. of Days Daily Rate Amount

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 32

sq.m.

2.90 sq.m.

Designation No. Person No. of Days Daily Rate Amount

Page 41: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: PAINTING WORKS (BALUNO GUARD HOUSE)

Unit of Measurement:

Output per day: sq.m./day

Quantity:

A. Labor

a. Construction Foreman

b. Painter

c. Laborer

P

B. Equipment

N.A.

P

C.

D. Output per hour = sq.m./day

E. Materials

a. Concrete Neutralizer

b. Solvent Based Acrylic Paint Primer

c. Solvent Based Acrylic Cast

d. Solvent Based Acrylic Paint Top Coat White Gloss

e. Solvent Based Acrylic Reducer

f. Body Filler w/ Hardener

g. #150 Sand Paper

h. #120 Sand Paper

i. Raw Sienna Tinting Color for Solvent Based Acrylic Paint

j. Thalo Blue Tinting Color for Solvent Based Acrylic Paint

k. Lamp Black Tinting Color for Solvent Based Acrylic Paint

l. Red Oxide Metal Primer

m. Quick Dry Enamel (Royal Blue)

n. Paint Thinner

o. Baby Roller

p. 2" Steel Brush

q. 3" Paint Brush

r. 2" Paint Brush

s. Paint Tray

P

F. Direct Cost (C+E)

G.Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

44,367.46

375.08

Sub-Total for E 23,113.00

41,856.10

2,511.37

-

-

1.00 pc. 33.00 33.00

1.00 pc. 27.00 27.00

1.00 set. 58.00 58.00

1.00 pc. 22.00 22.00

1.00 pc. 30.00 30.00

1.00 gal. 724.00 724.00

1.00 gal. 346.00 346.00

1.00 pint. 105.00 105.00

1.00 gal. 570.00 570.00

3.00 pints 105.00 315.00

1.00 pint. 105.00 105.00

2.00 doz. 151.00 302.00

2.00 doz. 151.00 302.00

4.00 gals. 452.00 1,808.00

1.00 gals. 546.00 546.00

5.00 gals. 520.00 2,600.00

10.00 gals. 1,029.00 10,290.00

1.00 gals. 520.00 520.00

5.00 gals. 882.00 4,410.00

Total (A+B) 18,743.10

20.00

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B -

Name and Capacity No. of Units No. of Days Daily Rate Amount

Sub-Total for A 18,743.10

2.00 5.91 317.00 3,749.75

Designation No. Person No. of Days Daily Rate Amount

2.00 5.91 394.00 4,660.58

2.00 5.91 873.52 10,332.76

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 33

sq.

20.00

118.29 sq.m.

Page 42: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: SPL - 34 STRUCTURE EXCAVATION (BANDERA GUARD HOUSE)

Unit of Measurement:

Output per day: cu.m./day

Quantity:

A. Labor

a. Laborer

P

B. Equipment

N.A.

P

C.

D. Output per hour = cu.m./day

E. Materials

N.A.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

Sub-Total for A 563.56

Name and Capacity No. of Units No. of Days Daily Rate Amount

Designation No. Person No. of Days Daily Rate Amount

2 0.89 317.00 563.56

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

cu.m.

1.80

1.60 cu.m.

Sub-Total for B -

Total (A+B) 563.56

1.80

Name and Specifications Quantity Unit Unit Cost Amount

597.37

373.36

Sub-Total for E -

563.56

33.81

-

-

Page 43: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: REINFORCING STEEL BAR, GRADE 33 (BANDERA GUARD HOUSE)

Unit of Measurement:

Output per day: kg./day

Quantity:

A. Labor

a. Construction Foreman

b. Steelman

c. Laborer

P

B. Equipment

a. Bar Bender

b. Bar Cutter

c. Cargo Truck (10T, 270 Hp)

P

C.

D. Output per hour = kg./day

E. Materials

a. *16mmØ x 6.00m Deformed Reinforced Steel Bar

b. *12mmØ x 6.00m Deformed Reinforced Steel Bar

c. *10mmØ x 6.00m Deformed Reinforced Steel Bar

d. #16 G.I. Tie Wire

*All sizes referred herein should mean commercially avaiable measurements with tolerance of ± 1mm.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 35

2 0.46 366.00 335.41

8 0.46 317.00 1,162.04

No. of Days Daily Rate Amount

1 0.46 873.52 400.26

kgs.

1,440.00

659.83 kgs.

Designation No. Person

1 0.07 8816.00 605.95

1 0.23 300.00 68.73

1 0.23 300.00 68.73

Sub-Total for A 1,897.71

Name and Capacity No. of Units No. of Days Daily Rate Amount

Sub-Total for B 743.41

Total (A+B) 2,641.12

1,440.00

Name and Specifications Quantity Unit Unit Cost Amount

144.61 kgs. 40.50 5,856.79

13.00 kgs. 65.00 845.00

274.92 kgs. 40.50 11,134.26

240.30 kgs. 40.50 9,732.15

32,021.88

48.53

Sub-Total for E 27,568.20

30,209.32

1,812.56

-

-

Page 44: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: PLUMBING WORKS (BANDERA GUARD HOUSE)

Unit of Measurement:

Output per day: lot/day

Quantity:

A. Labor

a. Plumber

b. Laborer

P

B. Equipment

P

C.

D. Output per hour = lot/day

E. Materials

a. 50mmØ x 3.00m. PVC Sanitary Pipe Series 1000

b. 50mmØ x 900 PVC Sanitary Elbow, Series 1000

c. 50mmØ PVC Coupling, Series 1000

d. PVC Solvent Cement

e. 100mm x 100mmStainless Floor Drain

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

4.00

1.00 lot

Designation No. Person No. of Days

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 36

cu.m.

1 0.25 366.00 91.50

Daily Rate Amount

1 0.25 873.52 218.38

Sub-Total for A 309.88

Name and Capacity No. of Units No. of Days Daily Rate Amount

2.00 pcs. 16.00 32.00

1.00 qrt. 460.00 460.00

2.00 pcs. 483.00 966.00

3.00 pcs. 37.00 111.00

Sub-Total for B -

Total (A+B) 309.88

4.00

Name and Specifications Quantity Unit Unit Cost Amount

1.00 pc. 110.00 110.00

2,108.21

2,108.21

Sub-Total for E 1,679.00

1,988.88

119.33

-

-

Page 45: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: STRUCTURAL CONCRETE CLASS A (BANDERA GUARD HOUSE)

Unit of Measurement:

Output per day: cu.m./day

Quantity:

A. Labor

a. Construction Foreman

b. Skilled Laborer

c. Laborer

Installation of Formworks

a. Skilled Worker

b. Laborer

P

B. Equipment

a. One Bagger Mixer (w/ Fuel)

b. Concrete Vibrator (w/ Fuel)

c. Water Truck (1000 gal.)

P

C.

D. Output per hour = cu.m./day

E. Materials

a. 12mm Thk x 1.20m x 2.40m Ordinary Plywood

b. 2" x 2" x 10' Coco Lumber

c. 2" x 3" x 10' Coco Lumber

d. 4" C.W. Nail

e. 3" C.W. Nail

f. 1-1/2" C.W. Nail

g. Portland Cement

h. Washed Sand

i. Gravel

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

11.20

2.96 cu.m.

Designation No. Person No. of Days

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 37

cu.m.

2 1.06 366.00 773.18

4 1.06 317.00 1,339.33

4 0.26 366.00 386.59

8 0.26 317.00 669.66

Daily Rate Amount

1 0.26 873.52 230.66

1 0.03 8,520.00 224.98

1 0.26 1,376.00 363.35

1 0.26 972.00 256.67

Sub-Total for A 3,399.41

Name and Capacity No. of Units No. of Days Daily Rate Amount

90.00 bd.ft. 20.00 1,800.00

1.00 kg. 53.00 53.00

5.00 shts. 800.00 4,000.00

58.00 bd.ft. 20.00 1,160.00

Sub-Total for B 845.00

Total (A+B) 4,244.41

11.20

Name and Specifications Quantity Unit Unit Cost Amount

3.00 cu.m. 1,050.00 3,152.73

27.00 bags 260.00 7,020.00

1.50 cu.m. 1,260.00 1,891.64

0.50 kg. 55.00 27.50

0.50 kg. 60.00 30.00

24,782.04

8,379.39

Sub-Total for E 19,134.87

23,379.28

1,402.76

-

-

Page 46: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: MASONRY WORKS (BANDERA GUARD HOUSE)

Unit of Measurement:

Output per day: sq.m./day

Quantity:

A. Labor

a. Skilled Laborer

b. Laborer

P

B. Equipment

a. One Bagger Mixer (w/ Fuel)

b. Bar Cutter

P

C.

D. Output per hour = sq.m./day

E. Materials

a. 150mm x 200mm x 400mm CHB (LB)

b. 100mm x 200mm x 400mm CHB (NLB)

c. Portland Cement

d. Washed Sand

e. *10mm.Ø x 6.00m Deformed Reinf. Steel Bar

f. #16 G.I. Tie Wire

*All sizes referred herein should mean commercially avaiable measurements with tolerance of ± 1mm.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

8.00

17.53 sq.m.

Designation No. Person No. of Days

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 38

sq.m.

Sub-Total for A 2,191.25

2 2.19 317.00 1,389.25

Daily Rate Amount

1 2.19 366.00 802.00

1 2.19 300.00 657.38

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 2.19 1,376.00 3,015.16

41.00 pcs. 19.00 779.00

184.00 pcs. 14.00 2,576.00

Total (A+B) 5,863.79

8.00

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B 3,672.54

48.20 kgs. 40.50 1,952.26

1.00 kg. 65.00 65.00

11.00 bags 260.00 2,860.00

0.75 cu.m. 1,260.00 945.00

15,041.05

902.46

-

-

15,943.51

909.50

Sub-Total for E 9,177.26

Page 47: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: PLASTERING WORKS (BANDERA GUARD HOUSE)

Unit of Measurement:

Output per day: sq.m./day

Quantity:

A. Labor

a. Skilled Laborer

b. Laborer

P

B. Equipment

N.A.

P

C.

D. Output per hour = sq.m./day

E. Materials

a. Portland Cement

b. Fine Sand

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

Designation No. Person No. of Days Daily Rate Amount

2 3.25 366.00 2,379.00

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 39

sq.m.

16.00

52.00 sq.m.

Name and Capacity No. of Units No. of Days Daily Rate Amount

Sub-Total for A 4,439.50

2 3.25 317.00 2,060.50

Total (A+B) 4,439.50

16.00

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B -

15.00 bags. 260.00 3,900.00

1.00 cu.m. 1,400.00 1,400.00

9,739.50

584.37

-

-

10,323.87

198.54

Sub-Total for E 5,300.00

Page 48: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: TILE WORKS (BANDERA GUARD HOUSE)

Unit of Measurement:

Output per day: sq.m./day

Quantity:

A. Labor

a. Skilled Laborer

b. Laborer

P

B. Equipment

a. Tile Cutter/Angular Grinder

P

C.

D. Output per hour = sq.m./day

E. Materials

a. 400mm x 400mm Granite Tiles

b. Tile Adhesive (25Kg/Bag)

c. Tile Grout (2 Kg./Pack)

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 40

sq.m.

5.00

2.14 sq.m.

Sub-Total for A 292.32

1 0.43 317.00 135.68

Designation No. Person No. of Days Daily Rate Amount

1 0.43 366.00 156.65

Sub-Total for B 128.40

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 0.43 300.00 128.40

1.00 bag 58.00 58.00

14.00 pcs. 126.00 1,764.00

1.00 bag 284.00 284.00

Total (A+B) 420.72

5.00

Name and Specifications Quantity Unit Unit Cost Amount

2,526.72

151.60

-

-

2,678.33

1,251.55

Sub-Total for E 2,106.00

Page 49: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: CARPENTRY WORKS (BANDERA GUARD HOUSE)

Unit of Measurement:

Output per day: lot/day

Quantity:

A. Labor

a. Skilled Worker

b. Laborer

P

B. Equipment

a. Bar Cutter

b. Welding Machine

P

C.

D. Output per hour = lot/day

E. Materials

a.

b.

c. Chrome Heavy Duty Door Knob w/ complete accessories

d. 4" x 3" Loose Pin Hinges w/ Screw

e. 4" C.W. Nail

Fabrication of Cabinet

a. Round Cabinet Handle (Chrome)

b. Cabinet Lock (Chrome)

c. Cabinet Concealed Hinges w/ Screw

d. 1" x 2" x 8' Laua-an Lumber

e. 2" x 2" x 8' Laua-an Lumber

f. 2" x 3" x 10' Laua-an Lumber

g. 1" x 6" x 8' Laua-an Lumber

h. 19mm Thk x 1.20m x 2.40m Marine Plyboard

i. 6mm Thk x 1.20m x 2.40m Marine Plyboard

j. 6mm Thk x 50mm x 50mm x 6.00m M.S. Angle Bar

k. Ga. 16 x 1.20m x 2.40m G.I. Sheet

l. Welding Rod (6011)

m. 3" C.W. Nail

n. 1" C.W. Finishing Nail

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 41

lot

0.17

1.00 lot

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 0.61 300.00 181.82

Sub-Total for A 4,309.09

1 6.06 317.00 1,921.21

Designation No. Person No. of Days Daily Rate Amount

1 6.06 394.00 2,387.88

Total (A+B) 5,800.00

0.17

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B 1,490.91

Pre-Fab 0.60m x 2.10m Flash Type Door, 50mm x 100mm

Mahogany Wood Door Frame w/ 6mm Thk Marine Plywood

Sheeting & w/ 50mm x 100mm Mahogany Wood Door Jamb

1 0.61 2,160.00 1,309.09

4.00 pcs. 120.00 480.00

4.00 pcs. 140.00 560.00

0.50 kg. 53.00 26.50

2.00 units 900.00 1,800.00

1.00 unit 800.00 800.00

10.00 bd.ft. 32.00 320.00

4.00 bd.ft. 32.00 128.00

1.33 bd.ft. 32.00 42.67

2.67 bd.ft. 32.00 85.33

2.00 pcs. 200.00 400.00

8.00 pcs. 65.00 520.00

0.50 kg. 151.00 75.50

1.00 kg. 55.00 55.00

2.00 pcs. 1,050.00 2,100.00

1.00 sht. 2,500.00 2,500.00

4.00 shts. 1,551.00 6,204.00

1.00 sht. 684.00 684.00

26,656.00

1,599.36

-

-

28,255.36

28,255.36

1.00 kg. 75.00 75.00

Sub-Total for E 20,856.00

Pre-Fab 0.60m x 1.165m 1-Pannel Window Jamb, 40mm x

150mm Mahogany Wood

1.00 unit 4,000.00 4,000.00

Page 50: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: STEEL WORKS (BANDERA GUARD HOUSE)

Unit of Measurement:

Output per day: lot/day

Quantity:

A. Labor

a. Welder

b. Laborer

P

B. Equipment

a. Welding Machine

b. Cut-Off Saw

P

C.

D. Output per hour = lot/day

E. Materials

a. 10mm x 10mm x 6.00m M.S. Square Bar

b. 12mm x 12mm x 6.00m M.S. Square Bar

c. 6mm Thk x 50mm x 6.00m M.S. Flat Bar

d. Hacksaw Blade

e. 6011 Welding Rod

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 42

lot

0.50

1.00 lot

Sub-Total for A 1,422.40

1 2.00 317.00 634.18

Designation No. Person No. of Days Daily Rate Amount

1 2.00 394.00 788.22

Sub-Total for B 2,460.70

1 1.00 300.00 300.09

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 1.00 2,160.00 2,160.61

2.00 pcs. 894.00 1,788.00

4.00 pcs. 65.00 260.00

1.00 pc. 210.00 210.00

4.00 pcs. 268.00 1,072.00

Total (A+B) 3,883.10

0.50

Name and Specifications Quantity Unit Unit Cost Amount

8.00 kgs 151.00 1,208.00

8,421.10

505.27

-

-

8,926.37

8,926.37

Sub-Total for E 4,538.00

Page 51: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: GLASS WORKS (BANDERA GUARD HOUSE)

Unit of Measurement:

Output per day: lot/day

Quantity:

A. Labor

N.A.

P

B. Equipment

N.A.

P

C.

D. Output per hour = lot/day

E. Materials

a. Supply & Installation of 5.5 mm Thk x 13 Blades x 0.60m width Smoke

Glass Jalousies w/ Aluminum Holder

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 43

lot

1.00

1.00 lot

Sub-Total for A -

Designation No. Person No. of Days Daily Rate Amount

Sub-Total for B -

Name and Capacity No. of Units No. of Days Daily Rate Amount

2.00 sets 800.00 1,600.00

Total (A+B) -

1.00

Name and Specifications Quantity Unit Unit Cost Amount

1,600.00

96.00

-

-

1,696.00

1,696.00

Sub-Total for E 1,600.00

Page 52: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: WATERPROOFING WORKS (BANDERA GUARD HOUSE)

Unit of Measurement:

Output per day: sq.m.day

Quantity:

A. Labor

N.A.

P

B. Equipment

N.A.

P

C.

D. Output per hour = sq.m.day

E. Materials

a. Bituminous Membrane Polyester Reinforced Waterproofing

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 44

sq.m.

2.90 sq.m.

Sub-Total for A -

Designation No. Person No. of Days Daily Rate Amount

Sub-Total for B -

Name and Capacity No. of Units No. of Days Daily Rate Amount

2.90 sq.mtr. 1,000.00 2,900.00

Total (A+B) -

0.00

Name and Specifications Quantity Unit Unit Cost Amount

2,900.00

174.00

-

-

3,074.00

1,060.00

Sub-Total for E 2,900.00

Page 53: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: PAINTING WORKS (BANDERA GUARD HOUSE)

Unit of Measurement:

Output per day: sq.m./day

Quantity:

A. Labor

a. Construction Foreman

b. Painter

c. Laborer

P

B. Equipment

N.A.

P

C.

D. Output per hour = sq.m./day

E. Materials

a. Concrete Neutralizer

b. Solvent Based Acrylic Paint Primer

c. Solvent Based Acrylic Putty

d. Solvent Based Acrylic Paint Top Coat White Gloss

e. Solvent Based Acrylic Reducer

f. Body Filler w/ Hardener

g. #150 Sand Paper

h. #120 Sand Paper

i. Raw Sienna Tinting Color for Solvent Based Acrylic Paint

j. Thalo Blue Tinting Color for Solvent Based Acrylic Paint

k. Lamp Black Tinting Color for Solvent Based Acrylic Paint

l. Red Oxide Metal Primer

m. Quick Dry Enamel (Royal Blue)

n. Paint Thinner

o. Baby Roller w/ Handle & Tray

p. 2" Steel Brush

q. 3" Paint Brush

r. 2" Paint Brush

s. Paint Tray

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 45

sq.m.

20.00

118.29 sq.m.

2.00 5.91 317.00 3,749.75

Designation No. Person No. of Days Daily Rate Amount

2.00 5.91 394.00 4,660.58

2.00 5.91 873.52 10,332.76

Sub-Total for B -

Name and Capacity No. of Units No. of Days Daily Rate Amount

Sub-Total for A 18,743.10

5.00 gals. 520.00 2,600.00

10.00 gals. 1,029.00 10,290.00

1.00 gals. 520.00 520.00

5.00 gals. 882.00 4,410.00

Total (A+B) 18,743.10

20.00

Name and Specifications Quantity Unit Unit Cost Amount

3.00 pints 105.00 315.00

1.00 pint. 105.00 105.00

2.00 doz. 151.00 302.00

2.00 doz. 151.00 302.00

4.00 gals. 452.00 1,808.00

1.00 gals. 546.00 546.00

30.00

1.00 gal. 724.00 724.00

1.00 gal. 346.00 346.00

1.00 pint. 105.00 105.00

1.00 gal. 570.00 570.00

44,367.46

375.08

Sub-Total for E 23,113.00

41,856.10

2,511.37

-

-

1.00 pc. 33.00 33.00

1.00 pc. 27.00 27.00

1.00 set. 58.00 58.00

1.00 pc. 22.00 22.00

1.00 pc. 30.00

Page 54: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: SPL - 46 STRUCTURE EXCAVATION (BALUNO OPERATOR'S ROOM)

Unit of Measurement:

Output per day: cu.m./day

Quantity:

A. Labor

a. Laborer

P

B. Equipment

N.A.

P

C.

D. Output per hour = cu.m./day

E. Materials

N.A.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-

SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

Sub-Total for B -

Total (A+B) 1,010.88

1.80

Name and Specifications Quantity

1,071.53

373.36

Unit Unit Cost Amount

Sub-Total for E -

1,010.88

60.65

-

-

Sub-Total for A 1,010.88

Name and Capacity No. of Units No. of Days Daily Rate Amount

Designation No. Person No. of Days Daily Rate Amount

2 1.59 317.00 1,010.88

DETAILED UNIT PRICE ANALYSIS

cu.m.

1.80

2.87 cu.m.

Page 55: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: SPL - 47 STRUCTURAL CONCRETE CLASS A (BALUNO OPERATOR'S ROOM)

Unit of Measurement:

Output per day: cu.m./ day

Quantity:

A. Labor

a. Construction Foreman

b. Skilled Laborer

c. Laborer

Installation of Formworks

a. Skilled Laborer

b. Laborer

P

B. Equipment

a. One Bagger Mixer

b. Concrete Vibrator

P

C.

D. Output per day = cu.m./ day

E. Materials

a. *12mm Thk x 1.20m x 2.40m Ordinary Plywood

b. 2" x 2" x 10' Coco Lumber

c. 2" x 3" x 10' Coco Lumber

d. 2" x 4" x 10' Coco Lumber

e. 4" C.W. Nail

f. 3" C.W. Nail

g. 1-1/2" C.W. Nail

h. Portland Cement

i. Washed Sand

j. Gravel

*All sizes referred herein should mean commercially avaiable measurements with tolerance of ± 1mm.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

3.75 cu.m. 1,260.00 4,725.00

226.67 bd.ft. 20.00

2.00

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-

SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

3.00 kgs. 65.00 195.00

2.00 kg. 65.00

kg. 65.00 130.00

77.00 bags 260.00 20,020.00

71,966.88

8,466.69

Sub-Total for E 56,175.00

67,893.28

4,073.60

7.50 cu.m. 1,050.00 7,875.00

153.33 bd.ft. 20.00 3,066.67

215.00 bd.ft. 20.00 4,300.00

4,533.33

130.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 0.76 1,376.00 1,044.29

14.00 shts. 800.00 11,200.00

Sub-Total for B 1,948.20

Total (A+B) 11,718.28

11.20

Name and Specifications Quantity Unit Unit Cost Amount

317.00 3,849.29

8 0.76 317.00 1,924.64

1 0.76 1,191.04 903.91

1 0.76 873.52 662.94

4 0.76 366.00 1,111.07

Designation No. Person No. of Days Daily Rate Amount

DETAILED UNIT PRICE ANALYSIS

cu.m.

11.20

8.50 cu.m.

Sub-Total for A 9,770.08

2 3.04 366.00 2,222.14

4 3.04

Page 56: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: REINFORCING STEEL BAR, GRADE 33 (BALUNO OPERATOR'S ROOM)

Unit of Measurement:

Output per day: kg. /day

Quantity:

A. Labor

a. Construction Foreman

b. Skilled Laborer

c. Laborer

P

B. Equipment

a. Bar Cutter

b. Bar Bender

c. Cargo Truck

P

C.

D. Output per day = kg. /day

E. Materials

a.

b.

c.

d.

*All sizes referred herein should mean commercially avaiable measurements with tolerance of ± 1mm.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-

SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

*16mm.Ø x 6.00m. Def. Reinforcing Steel Bars 113.76 kgs. 40.5 4607.28

24.000 kgs. 65.00 1560.00

*12mm.Ø x 6.00m. Def. Reinforcing Steel Bars 360.72 kgs. 40.5 14609.16

#16 G.I. Tie-wire

311.47 kgs.

42,766.70

2,566.00

-

-

45,332.71

57.68

Sub-Total for E 33,390.98

40.5 12614.54

Total (A+B) 9,375.73

1,440.00

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B 7,306.06

*10mm.Ø x 6.00m. Def. Reinforcing Steel Bars

1 0.55 2,812.00 1,534.79

1 0.55 8,816.00 4,811.76

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 0.55 1,758.00 959.51

Sub-Total for A 2,069.67

2 0.55 366.00 399.52

8 0.55 317.00 1,384.15

Daily Rate Amount

1 0.55 524.00 286.00

1,440.00

785.95 kgs.

Designation No. Person No. of Days

DETAILED UNIT PRICE ANALYSIS

SPL - 48

kg.

Page 57: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: PLUMBING WORKS (BALUNO OPERATOR'S ROOM)

Unit of Measurement:

Output per day:

Quantity:

A. Labor

a. Construction Foreman

b. Skilled Laborer

c. Laborer

P

B. Equipment

N/A

P

C.

D. Output per day =

E. Materials

1. Storm Drainage

50mm.Ø x 3.00m. PVC Pipe, Series 1000

50mm.Ø PVC Coupling, Series 1000

PVC Solvent Cement

2. Sanitary Pipe

100mm.Ø x 3.00m. PVC Pipe, Series 1000

50mm.Ø x 3.00m. PVC Pipe, Series 1000

100mm.Ø x 50mm.Ø PVC Sanitary Tee, Series 1000 1 pc. 211.00 211.00

100mm.Ø x 100mm.Ø PVC Sanitary Tee, Series 1000 4 pcs. 171.00 684.00

100mm.Ø x 100mm.Ø PVC Sanitary Wye, Series 1000 2 pcs. 211.00 422.00

50mm.Ø PVC Sanitary Coupling, Series 1000 2 pcs. 16.00 32.00

50mm.Ø x 90o PVC Sanitary Bend, Series 1000 1 pc. 37.00 37.00

100mm.Ø PVC Sanitary Coupling, Series 1000 2 pcs. 66.00 132.00

3 pcs. 483.00 1,449.00

100mm.Ø x 90o PVC Sanitary Elbow Series 1000 4 pcs. 137.00 548.00

100mm.Ø PVC Sanitary Clean Out, Series 1000 2 pcs. 98.00 196.00

4 pcs. 966.00 3,864.00

100mm.Ø x 45o PVC Sanitary Elbow Series 1000 6 pcs. 101.00 606.00

4 pcs. 16.00 64.00

2 qrts. 460.00 920.00

6 pcs. 483.00 2,898.00

50mm.Ø x 90o PVC Sanitary Bend, Series 1000 8 pcs. 37.00 296.00

Total (A+B) 6,096.00

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B -

Name and Capacity No. of Units No. of Days Daily Rate Amount

Sub-Total for A 6,096.00

1 4 524.00 2,096.00

1 4 366.00 1,464.00

Designation No. Person No. of Days Daily Rate Amount

DETAILED UNIT PRICE ANALYSIS

SPL - 49

lot

1.00 lot

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-

SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

2 4 317.00 2,536.00

Page 58: Dumalon W.S. Ground Tank_Final

PVC Cement Solvent

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

34,487.10

34,487.10

4

Sub-Total for E 26,439.00

32,535.00

1,952.10

-

-

0.60m. x 0.60m. Beveled Frameless Mirror 1 pc. 440.00 440.00

12mm. Shower Valve 1 pc. 525.00 525.00

100mm. x 100mm. Stainless Double Strainer Floor Drain 2 pcs. 110.00 220.00

Ceramic Soap Holder 1 pc. 280.00 280.00

12mm. Shower Head 1 pc. 1,218.00 1,218.00

Wall Mounted Type Lavatory w/ Complete Fittings &

Accs.1 unit 2,415.00 2,415.00

Ceramic Tissue Holder 1 pc. 300.00 300.00

4. Sanitary Fixtures

Flush Type Water Closet w/ Complete Fittings & Accs. 1 unit 3,550.00 3,550.00

Teflon Tape 6 rolls 34.00 204.00

12mm.Ø Brass Faucet 2 pcs. 270.00 540.00

12mm.Ø G.I. Union Patent, ANSI B16.3, Class 150

Standard

1 pc. 75.00 75.00

12mm.Ø x 90o G.I. Elbow, ANSI B16.3, Class 150 Standard 7 pcs. 19.00 133.00

12mm.Ø x 12mm.Ø G.I. Tee, ANSI B16.3, Class 150

Standard

4 pcs. 28.00 112.00

qrts. 460.00 1,840.00

3. Cold Pipe

12mm.Ø x 6.00m. G.I. Pipe, ASTM A53-90A Heavy Gauge

Standard

3 pcs. 722.00 2,166.00

50mm.Ø x 50mm.Ø PVC Sanitary Tee, Series 1000 1 pc. 62.00 62.00

Page 59: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: CARPENTRY WORKS (BALUNO OPERATOR'S ROOM)

Unit of Measurement:

Output per day: lot /day

Quantity:

A. Labor

a. Construction Foreman

b. Skilled Laborer

c. Laborers

P

B. Equipment

P

C.

D. Output per day = lot /day

E. Materials

1. One Unit Cabinet

3. Hardware

4" x 3" Loose Pin Hinges (Heavy Duty) w/ Screw 4 pcs. 216.00 864.00

19mm. Thk. x 1.20m. x 2.40m. Marine Plywood 3 shts. 1,551.00 4,653.00

1" C.W. Finishing Nail 1 kg. 75.00 75.00

3pcs. - 1" x 1" x 10' Mahogany Lumber 2.5 bd.ft. 32.00 80.00

Cabinet Concealed Hinges w/ Screw 12 pcs. 60.00 720.00

Drawer Handle (Chrome) 4 pcs. 160.00 640.00

Cabinet Handle (Chrome) 4 pcs. 160.00 640.00

3" C.W. Nail 1 kg. 52.00 52.00

1" C.W. Finishing Nail 1 kg. 75.00 75.00

2. One Unit Table

Sub-Total for B -

19mm. Thk. x 1.20m. x 2.40m. Marine Plywood 3 shts. 1,551.00 4,653.00

3pcs. - 1" x 1" x 10' Mahogany Lumber 2.5 bd.ft. 32.00 80.00

Total (A+B) 7,560.00

0.00

Name and Specifications Quantity Unit Unit Cost Amount

6mm. Thk. x 1.20m. x 2.40m. Marine Plywood 1 sht. 684.00 684.00

12mm.Ø x 6.00m. G.I. Pipe, ASTM A53-90A Heavy Gauge

Standard

1 pc. 722.00 722.00

Daily Rate Amount

1 4.00 524.00 2,096.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

2

1.00 lot

Designation No. Person No. of Days

DETAILED UNIT PRICE ANALYSIS

SPL - 50

lot

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-

SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

Sub-Total for A 7,560.00

4.00 366.00 2,928.00

2 4.00 317.00 2,536.00

Page 60: Dumalon W.S. Ground Tank_Final

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

Pre-fabricated 0.80m. x 2.10m. Mahogany Wood Panel

Type Door w/ 50mm. x 100mm. Door Frame & 37.5mm

1 unit 4,800.00 4,800.00

38,341.00

2,300.46

-

-

40,641.46

40,641.46

4. Door Frame/Panel Door & Window Jamb

1" C.W. Nail 1 kg. 68.00 68.00

1" Finishing Nail 2 kgs. 75.00 150.00

Sub-Total for E 30,781.00

Pre-fabricated 0.60m. X 2.10m. PVC Door w/ Door Jamb

and Hinges w/ Screw

1 unit 1,900.00 1,900.00

Pre-fab. 1.165m. X 1.45m. X 50mm. X 150mm. 2 Panel

Mahogany Wood Window Jamb

2 units 2,300.00 4,600.00

Pre-fabricated 0.80m. x 2.10m. x 50mm. x 150mm.

Mahogany Wood Door Jamb

1 unit 2,500.00 2,500.00

2" C.W. Nail 1 kg. 57.00 57.00

Drawer Lock (Heavy Duty) 4 sets 60.00 240.00

4" C.W. Nail 1 kg. 53.00 53.00

Stainless Door Knob (Heavy Duty) 2 sets 950.00 1,900.00

2-1/2" C.W. Nail 1 kg. 55.00 55.00

2" x 2" Cabinet Hinges w/ Screw 8 pcs. 65.00 520.00

Page 61: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: MASONRY WORKS (BALUNO OPERATOR'S ROOM)

Unit of Measurement:

Output per day: sq.m. /day

Quantity:

A. Labor

a. Skilled Laborer

b. Laborer

P

B. Equipment

a. One Bagger Mixer (w/ Fuel)

b. Bar Cutter

P

C.

D. Output per day = sq.m. /day

E. Materials

a.

b.

c.

d.

e.

f.

*All sizes referred herein should mean commercially avaiable measurements with tolerance of ± 1mm.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

1 8.70 366.00 3,184.20

63,649.14

914.50

Sub-Total for E 36,765.16

60,046.36

3,602.78

-

-

#16 G.I. Tie-wire 3.68 kgs. 65.00 239.32

150mm. x 200mm. x 400mm. Hollow Block (LB) 230.00 pcs. 19.00 4,370.00

*10mm.Ø x 6.00m. Def. Reinforcing Steel Bar 184.09 kgs. 40.50 7,455.84

100mm. x 200mm. x 400mm. Hollow Block (NLB) 640.00 pcs. 14.00 8,960.00

Portland Cement 46.00 bags 260.00 11,960.00

Washed Sand 3.00 cu.m. 1,260.00 3,780.00

Sub-Total for B 14,581.20

Total (A+B) 23,281.20

8.00

Name and Specifications Quantity Unit Unit Cost Amount

1 8.70 300.00 2,610.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 8.70 1,376.00 11,971.20

Sub-Total for A 8,700.00

2 8.70 317.00 5,515.80

Designation No. Person No. of Days Daily Rate Amount

DETAILED UNIT PRICE ANALYSIS

SPL - 51

sq.m.

8.00

69.60 sq.m.

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-

SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

Page 62: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: PLASTERING WORKS (BALUNO OPERATOR'S ROOM)

Unit of Measurement:

Output per day: sq.m./day

Quantity:

A. Labor

a. Skilled Laborer

b. Laborer

P

B. Equipment

N.A.

P

C.

D. Output per hour = sq.m./day

E. Materials

a. Portland Cement

b. Fine Sand

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

25,430.28

1,525.82

-

-

26,956.10

193.65

Sub-Total for E 13,546.08

40.00 bags. 260.00 10,400.00

2.25 cu.m. 1,400.00 3,146.08

16.00

Name and Specifications Quantity Unit Unit Cost Amount

Daily Rate Amount

Sub-Total for A 11,884.20

2 8.70 317.00

Name and Capacity No. of Units No. of Days

2 8.70 366.00

DETAILED UNIT PRICE ANALYSIS

SPL -52

sq.m.

16.00

139.20

-

11,884.20

Sub-Total for B

Total (A+B)

AmountNo. Person No. of Days Daily Rate

6,368.40

5,515.80

Designation

sq.m.

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-

SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

Page 63: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: TILE WORKS (BALUNO OPERATOR'S ROOM)

Unit of Measurement:

Output per day: sq.m./day

Quantity:

A. Labor

a. Skilled Laborer

b. Laborer

P

B. Equipment

a. Tile Cutter/Angular Grinder

P

C.

D. Output per hour = sq.m./day

E. Materials

a.

b.

c.

d.

e.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost 866.44

Sub-Total for E 15,048.00

Tile Adhesive (25kgs./bag)

Tile Grout (2kgs./pack)

PVC Tile Trim (White)

200mm. x 200mm. Ceramic Tiles (White)

400mm. x 400mm. Granite Tiles (White) 54.00 pcs. 126.00 6,804.00

19,813.58

1,188.82

-

-

21,002.40

6.00 pack 58.00 348.00

7.00 pcs. 130.00 910.00

390.00 pcs. 15.00 5,850.00

4.00 bags 284.00 1,136.00

Total (A+B) 4,765.58

5.00

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B 1,454.40

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 4.85 300.00 1,454.40

Sub-Total for A 3,311.18

1 4.85 317.00 1,536.82

Designation No. Person No. of Days Daily Rate Amount

1 4.85 366.00 1,774.37

DETAILED UNIT PRICE ANALYSIS

SPL - 53

sq.m.

5.00

24.24 sq.m.

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-

SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

Page 64: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: WATERPROOFING WORKS (BALUNO OPERATOR'S ROOM)

Unit of Measurement:

Output per day:

Quantity:

A. Labor

N.A.

P

B. Equipment

N/A

P

C.

D. Output per day =

E. Materials

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

11,660.00

11,660.00

Sub-Total for E 11,000.00

11,000.00

660.00

-

-

11 sq.m. 1,000.00 11,000.00

Total (A+B) -

Name and Specifications Quantity Unit Unit Cost Amount

Bituminous Membrane Polyester Reinforced Water

Proofing

a.

Sub-Total for B -

Sub-Total for A -

Name and Capacity No. of Units No. of Days Daily Rate Amount

Daily Rate Amount

1.00 lot

Designation No. Person No. of Days

DETAILED UNIT PRICE ANALYSIS

SPL - 54

lot

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-

SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

Page 65: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: STEEL WORKS (BALUNO OPERATOR'S ROOM)

Unit of Measurement:

Output per day: sq.m. /day

Quantity:

A. Labor

a. Construction Foreman

b. Skilled Laborer

c. Laborer

P

B. Equipment

a. Welding Machine

b. Angular Grinder

c. Cut-Off Saw

P

C.

D. Output per day = sq.m. /day

E. Materials

a.

b.

c.

d.

*All sizes referred herein should mean commercially avaiable measurements with tolerance of ± 1mm.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

Sub-Total for E 4,163.00

17,015.00

1,020.90

-

-

18,035.90

3,558.78

6011 Welding Rod 1 kg. 151.00 151.00

*6mm. Thk. x 20mm. x 6.00m. Flat Bar 4 pcs. 158.00 632.00

*10mm. x 10mm. x 6.00m. Square Bar 2 pcs. 216.00 432.00

*12mm. x 12mm. x 6.00m. Square Bar 11 pcs. 268.00 2,948.00

Total (A+B) 12,852.00

1.70

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B 8,280.00

1 3 2,160.00 6,480.00

1 3 300.00 900.00

Sub-Total for A 4,572.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 3 300.00 900.00

1 3 366.00 1,098.00

2 3 317.00 1,902.00

Daily Rate Amount

1 3 524.00 1,572.00

1.70

5.068 sq.m.

Designation No. Person No. of Days

DETAILED UNIT PRICE ANALYSIS

SPL - 55

sq.m.

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-

SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

Page 66: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: GLASS WORKS (BALUNO OPERATOR'S ROOM)

Unit of Measurement:

Output per day:

Quantity:

A. Labor

P

B. Equipment

P

C.

D.

E. Materials

a.

b.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

3,922.00

3,922.00

Sub-Total for E 3,700.00

3,700.00

222.00

-

-

Width Smoke Glass Jalousies w/ Aluminum Holder

Supply and installation of 5.5mm thk. x 13 - Blades Smoke

Glass x 0.65m.

4 sets 800.00 3,200.00

Supply and installation of 5.5mm. Thk. x 6 Blades x 0.60m. 1 set 500.00 500.00

Total (A+B) -

Name and Specifications Quantity Unit Unit Cost Amount

Width Glass Jalousies w/ Aluminum Holder

Sub-Total for B -

Sub-Total for A -

Name and Capacity No. of Units No. of Days Daily Rate Amount

Amount

1.00 lot

Designation No. Person No. of Days Daily Rate

DETAILED UNIT PRICE ANALYSIS

SPL - 56

lot

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-

SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

Page 67: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: PAINTING WORKS (BALUNO OPERATOR'S ROOM)

Unit of Measurement:

Output per day: sq.m. /day

Quantity:

A. Labor

a. Construction Foreman

b. Skilled Laborer

c. Laborer

P

B. Equipment

N/A

P

C.

D. Output per day = sq.m. /day

E. Materials

a.

b.

c.

d.

e.

f.

g.

h.

i.

j.

k.

l.

m.

n.

o.

p.

q.

r. Paint Tray 1.00 pc. 30.00 30.00

Quick Dry Enamel (Royal Blue) 1.00 gal. 620.00 620.00

Paint Thinner 1.00 pc. 330.00 330.00

Baby Roller 1.00 pc. 58.00 58.00

Lamp Black Tinting Color for Solvent Based Acrylic Paint 1.00 pint 105.00 105.00

Red Oxide Metal Primer 1.00 gal. 570.00 570.00

Raw Sienna Tinting Color for Solvent Based Acrylic Paint 3.00 pints 105.00 315.00

Thalo Blue Tinting Color for Solvent Based Acrylic Paint 1.00 pint 105.00 105.00

#120 Sand Paper 2.00 doz. 151.00 302.00

Red Tinting Color for Solvent Based Acrylic Paint 1.00 pint 105.00 105.00

Body Filler w/ Hardener 1.00 gal. 546.00 546.00

#150 Sand Paper 2.00 doz. 151.00 302.00

Solvent Based Acrylic Reducer 4.00 gals. 452.00 1,808.00

Lacquer Thinner 2.00 gals. 494.00 988.00

Solvent Based Acrylic Cast 5.00 gals. 520.00 2,600.00

Solvent Based Acrylic Paint Top Coat White Gloss 10.00 gals. 1,029.00 10,290.00

Concrete Neutralizer 1.00 gals. 520.00 520.00

Solvent Based Acrylic Paint Primer 5.00 gals. 882.00 4,410.00

Sub-Total for B -

Total (A+B) 13,437.12

20.00

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for A 13,437.12

Name and Capacity No. of Units No. of Days Daily Rate Amount

2 6.00 366.00 4,392.00

2 6.00 317.00 3,804.00

Daily Rate Amount

1 6.00 873.52 5,241.12

20.00

120.00 sq.m.

Designation No. Person No. of Days

DETAILED UNIT PRICE ANALYSIS

SPL - 57

sq.m.

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-

SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

Page 68: Dumalon W.S. Ground Tank_Final

s.

t.

u.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

37,523.12

2,251.39

-

-

39,774.51

331.45

Sub-Total for E 24,086.00

3" Paint Brush 1.00 pc. 33.00 33.00

2" Paint Brush 1.00 pc. 27.00 27.00

2" Steel Brush 1.00 pc. 22.00 22.00

Page 69: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: CONST. OF WATERPROOF SEPTIC VAULT (BALUNO OPERATOR'S ROOM)

Unit of Measurement:

Output per day: cu.m. /day

Quantity:

A. Labor

a. Construction Foreman

b. Skilled Laborer

c. Laborer

P

B. Equipment

N/A

P

C.

D. Output per day = cu.m. /day

E. Materials

a.

b.

c.

d.

e.

f.

g.

h.

i.

j.

k.

l.

m.

n.

*All sizes referred herein should mean commercially avaiable measurements with tolerance of ± 1mm.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

54,281.70

9,923.53

Sub-Total for E 39,869.15

1-1/2" C.W. Nail 1 kg. 63.00 63.00

Bituminous Membrane Polyester Reinforced Water

Proofing

15.70 sq.m. 1,000.00 15,700.00

cu.m. 1,400.00 700.00

12mm. Thk. x 1.20m. x 2.40m. Ordinary Plywood 5 shts. 800.00 4,000.00

4" C.W. Nail 2 kgs. 53.00 106.00

51,209.15

3,072.55

-

-

#16 G.I. Tie-wire 5 kgs. 65.00 325.00

Gravel (G-1) 0.75 cu.m. 1,050.00 787.50

Concrete Water Proofing Compound 9 pack 38.00 342.00

3" C.W. Nail 2 kgs. 55.00 110.00

30pcs. - 2" x 2" x 10' Coco Lumber 100 bd.ft. 20.00 2,000.00

30pcs. - 2" x 3" x 10' Coco Lumber 150 bd.ft. 20.00 3,000.00

Fine Sand (for plastering) 0.50

Washed Sand 1.5 cu.m. 1,260.00 1,890.00

Sub-Total for B -

Total (A+B) 11,340.00

0.91

Name and Specifications Quantity Unit Unit Cost Amount

*10mm.Ø x 6.00m. Def. Reinforcing Steel Bars 107 kgs. 40.50 4,345.65

Sub-Total for A 11,340.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

Portland Cement 25 bags 260.00 6,500.00

2 6 317.00 3,804.00

1 6 524.00 3,144.00

2 6 366.00 4,392.00

Designation No. Person No. of Days Daily Rate Amount

DETAILED UNIT PRICE ANALYSIS

SPL - 58

cu.m.

0.91

5.47 cu.m.

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-

SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

Page 70: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: SPL - 59 STRUCTURE EXCAVATION (BANDERA OPERATOR'S ROOM)

Unit of Measurement:

Output per day: cu.m./day

Quantity:

A. Labor

a. Laborer

P

B. Equipment

N.A.

P

C.

D. Output per hour = cu.m./day

E. Materials

N.A.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

1,071.53

373.36

Sub-Total for E -

1,010.88

60.65

-

-

Sub-Total for B -

Total (A+B) 1,010.88

1.80

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for A 1,010.88

Name and Capacity No. of Units No. of Days Daily Rate Amount

Designation No. Person No. of Days Daily Rate Amount

2 1.59 317.00 1,010.88

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-

SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

cu.m.

1.80

2.87 cu.m.

Page 71: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: SPL - 60 STRUCTURAL CONCRETE CLASS A (BANDERA OPERATOR'S ROOM)

Unit of Measurement:

Output per day: cu.m./ day

Quantity:

A. Labor

a. Construction Foreman

b. Skilled Laborer

c. Laborer

Installation of Formworks

a. Skilled Laborer

b. Laborer

P

B. Equipment

a. One Bagger Mixer

b. Concrete Vibrator

P

C.

D. Output per day = cu.m./ day

E. Materials

a. *12mm Thk x 1.20m x 2.40m Ordinary Plywood

b. 2" x 2" x 10' Coco Lumber

c. 2" x 3" x 10' Coco Lumber

d. 2" x 4" x 10' Coco Lumber

e. 4" C.W. Nail

f. 3" C.W. Nail

g. 1-1/2" C.W. Nail

h. Portland Cement

i. Washed Sand

j. Gravel

*All sizes referred herein should mean commercially avaiable measurements with tolerance of ± 1mm.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

71,966.88

8,466.69

Sub-Total for E 56,175.00

67,893.28

4,073.60

3.75 cu.m. 1,260.00 4,725.00

7.50 cu.m. 1,050.00 7,875.00

77.00 bags 260.00 20,020.00

2.00 kg. 65.00 130.00

2.00 kg. 65.00 130.00

226.67 bd.ft. 20.00

3.00 kgs. 65.00 195.00

215.00 bd.ft. 20.00 4,300.00

4,533.33

153.33 bd.ft. 20.00 3,066.67

14.00 shts. 800.00 11,200.00

Name and Specifications Quantity Unit Unit Cost Amount

11.20

Total (A+B) 11,718.28

Sub-Total for B 1,948.20

1 0.76 1,191.04 903.91

1 0.76 1,376.00 1,044.29

Name and Capacity No. of Units No. of Days Daily Rate Amount

Sub-Total for A 9,770.08

4 3.04 317.00 3,849.29

2 3.04 366.00 2,222.14

8 0.76 317.00 1,924.64

4 0.76 366.00 1,111.07

1 0.76 873.52 662.94

Designation No. Person No. of Days Daily Rate Amount

8.50 cu.m.

11.20

cu.m.

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-

SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

DETAILED UNIT PRICE ANALYSIS

Page 72: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: REINFORCING STEEL BAR, GRADE 33 (BANDERA OPERATOR'S ROOM)

Unit of Measurement:

Output per day: kg. /day

Quantity:

A. Labor

a. Construction Foreman

b. Skilled Laborer

c. Laborer

P

B. Equipment

a. Bar Cutter

b. Bar Bender

c. Cargo Truck

P

C.

D. Output per day = kg. /day

E. Materials

a.

b.

c.

d.

*All sizes referred herein should mean commercially avaiable measurements with tolerance of ± 1mm.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

42,766.70

2,566.00

-

-

45,332.71

57.68

Sub-Total for E 33,390.98

#16 G.I. Tie-wire 24.000 kgs. 65.00 1560.00

*16mm.Ø x 6.00m. Def. Reinforcing Steel Bars 113.76 kgs. 40.5 4607.28

*12mm.Ø x 6.00m. Def. Reinforcing Steel Bars 360.72 kgs. 40.5 14609.16

*10mm.Ø x 6.00m. Def. Reinforcing Steel Bars 311.47 kgs. 40.5 12614.54

Name and Specifications Quantity Unit Unit Cost Amount

1,440.00

Total (A+B) 9,375.73

Sub-Total for B 7,306.06

1 0.55 8,816.00 4,811.76

1 0.55 2,812.00 1,534.79

1 0.55 1,758.00 959.51

Name and Capacity No. of Units No. of Days Daily Rate Amount

Sub-Total for A 2,069.67

8 0.55 317.00 1,384.15

2 0.55 366.00 399.52

1 0.55 524.00 286.00

Designation No. Person No. of Days Daily Rate Amount

785.95 kgs.

1,440.00

kg.

SPL - 61

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-

SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

DETAILED UNIT PRICE ANALYSIS

Page 73: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: PLUMBING WORKS (BANDERA OPERATOR'S ROOM)

Unit of Measurement:

Output per day:

Quantity:

A. Labor

a. Construction Foreman

b. Skilled Laborer

c. Laborer

P

B. Equipment

N/A

P

C.

D. Output per day =

E. Materials

1. Storm Drainage

50mm.Ø x 3.00m. PVC Pipe, Series 1000

50mm.Ø PVC Coupling, Series 1000

PVC Solvent Cement

2. Sanitary Pipe

100mm.Ø x 3.00m. PVC Pipe, Series 1000

50mm.Ø x 3.00m. PVC Pipe, Series 1000

100mm.Ø x 50mm.Ø PVC Sanitary Tee, Series 1000 1 pc. 211.00 211.00

100mm.Ø x 100mm.Ø PVC Sanitary Tee, Series 1000 4 pcs. 171.00 684.00

100mm.Ø x 100mm.Ø PVC Sanitary Wye, Series 1000 2 pcs. 211.00 422.00

50mm.Ø PVC Sanitary Coupling, Series 1000 2 pcs. 16.00 32.00

50mm.Ø x 90o PVC Sanitary Bend, Series 1000 1 pc. 37.00 37.00

100mm.Ø PVC Sanitary Coupling, Series 1000 2 pcs. 66.00 132.00

3 pcs. 483.00 1,449.00

100mm.Ø x 90o PVC Sanitary Elbow Series 1000 4 pcs. 137.00 548.00

100mm.Ø PVC Sanitary Clean Out, Series 1000 2 pcs. 98.00 196.00

4 pcs. 966.00 3,864.00

100mm.Ø x 45o PVC Sanitary Elbow Series 1000 6 pcs. 101.00 606.00

4 pcs. 16.00 64.00

2 qrts. 460.00 920.00

6 pcs. 483.00 2,898.00

50mm.Ø x 90o PVC Sanitary Bend, Series 1000 8 pcs. 37.00 296.00

Total (A+B) 6,096.00

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B -

Name and Capacity No. of Units No. of Days Daily Rate Amount

Sub-Total for A 6,096.00

2 4 317.00 2,536.00

1 4 524.00 2,096.00

1 4 366.00 1,464.00

Designation No. Person No. of Days Daily Rate Amount

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-

SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 62

lot

1.00 lot

Page 74: Dumalon W.S. Ground Tank_Final

PVC Cement Solvent

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

34,487.10

34,487.10

Sub-Total for E 26,439.00

32,535.00

1,952.10

-

-

6mm. Thk. x 0.60m. x 0.60m. Beveled Frameless Mirror 1 pc. 440.00 440.00

12mm. Shower Valve 1 pc. 525.00 525.00

100mm. x 100mm. Stainless Double Strainer Floor Drain 2 pcs. 110.00 220.00

Ceramic Soap Holder 1 pc. 280.00 280.00

12mm. Shower Head 1 pc. 1,218.00 1,218.00

Wall Mounted Type Lavatory w/ Complete Fittings & Accs. 1 unit 2,415.00 2,415.00

Ceramic Tissue Holder 1 pc. 300.00 300.00

4. Sanitary Fixtures

Flush Type Water Closet w/ Complete Fittings & Accs. 1 unit 3,550.00 3,550.00

25mm. Teflon Tape 6 rolls 34.00 204.00

12mm.Ø Brass Faucet 2 pcs. 270.00 540.00

12mm.Ø G.I. Union Patent, ANSI B16.3, Class 150 Standard 1 pc. 75.00 75.00

12mm.Ø x 90o G.I. Elbow, ANSI B16.3, Class 150 Standard 7 pcs. 19.00 133.00

12mm.Ø x 12mm.Ø G.I. Tee, ANSI B16.3, Class 150 Standard 4 pcs. 28.00 112.00

4 qrts. 460.00 1,840.00

3. Cold Pipe

12mm.Ø x 6.00m. G.I. Pipe, ASTM A53-90A Heavy Gauge Standard 3 pcs. 722.00 2,166.00

50mm.Ø x 50mm.Ø PVC Sanitary Tee, Series 1000 1 pc. 62.00 62.00

Page 75: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: CARPENTRY WORKS (BANDERA OPERATOR'S ROOM)

Unit of Measurement:

Output per day: lot /day

Quantity:

A. Labor

a. Construction Foreman

b. Skilled Laborer

c. Laborers

P

B. Equipment

P

C.

D. Output per day = lot /day

E. Materials

1. One Unit Cabinet

3. Hardware

4" x 3" Loose Pin Hinges (Heavy Duty) w/ Screw 4 pcs. 216.00 864.00

Drawer Handle (Chrome) 4 pcs. 160.00 640.00

19mm. Thk. x 1.20m. x 2.40m. Marine Plywood 3 shts. 1,551.00 4,653.00

1" C.W. Finishing Nail 1 kg. 75.00 75.00

2. One Unit Table

3pcs. - 1" x 1" x 10' Mahogany Lumber 2.5 bd.ft. 32.00 80.00

Cabinet Concealed Hinges w/ Screw 12 pcs. 60.00 720.00

12mm.Ø x 6.00m. G.I. Pipe, ASTM A53-90A Heavy Gauge

Standard

1 pc. 722.00 722.00

Cabinet Handle (Chrome) 4 pcs. 160.00 640.00

3" C.W. Nail 1 kg. 52.00 52.00

1" C.W. Finishing Nail 1 kg. 75.00 75.00

19mm. Thk. x 1.20m. x 2.40m. Marine Plywood 3 shts. 1,551.00 4,653.00

6mm. Thk. x 1.20m. x 2.40m. Marine Plywood 1 sht. 684.00 684.00

3pcs. - 1" x 1" x 10' Mahogany Lumber 2.5 bd.ft. 32.00 80.00

Total (A+B) 7,560.00

0.00

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B -

Sub-Total for A 7,560.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

2 4.00 366.00 2,928.00

2 4.00 317.00 2,536.00

Daily Rate Amount

1 4.00 524.00 2,096.00

1.00 lot

Designation No. Person No. of Days

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-

SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 63

lot

Page 76: Dumalon W.S. Ground Tank_Final

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

40,641.46

40,641.46

Sub-Total for E 30,781.00

38,341.00

2,300.46

-

-

Pre-fabricated 0.60m. X 2.10m. PVC Door w/ Door Jamb

and Hinges w/ Screw

1 unit 1,900.00 1,900.00

Pre-fab. 1.165m. X 1.45m. X 50mm. X 150mm. 2 Panel

Mahogany Wood Window Jamb

2 units 2,300.00 4,600.00

Pre-fabricated 0.80m. x 2.10m. x 50mm. x 150mm.

Mahogany Wood Door Jamb

1 unit 2,500.00 2,500.00

Pre-fabricated 0.80m. x 2.10m. Mahogany Wood Panel

Type Door w/ 50mm. x 100mm. Door Frame & 37.5mm thk.

1 unit 4,800.00 4,800.00

4. Door Frame/Panel Door & Window Jamb

1" C.W. Nail 1 kg. 68.00 68.00

1" Finishing Nail 2 kgs. 75.00 150.00

2-1/2" C.W. Nail 1 kg. 55.00 55.00

2" C.W. Nail 1 kg. 57.00 57.00

Drawer Lock (Heavy Duty) 4 sets 60.00 240.00

4" C.W. Nail 1 kg. 53.00 53.00

2" x 2" Cabinet Hinges w/ Screw 8 pcs. 65.00 520.00

Stainless Door Knob (Heavy Duty) 2 sets 950.00 1,900.00

Page 77: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: MASONRY WORKS (BANDERA OPERATOR'S ROOM)

Unit of Measurement:

Output per day: sq.m. /day

Quantity:

A. Labor

a Skilled Laborer

b. Laborer

P

B. Equipment

a. One Bagger Mixer (w/ Fuel)

b. Bar Cutter

P

C.

D. Output per day = sq.m. /day

E. Materials

a.

b.

c.

d.

e.

f.

*All sizes referred herein should mean commercially avaiable measurements with tolerance of ± 1mm.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

63,649.14

914.50

Sub-Total for E 36,765.16

60,046.36

3,602.78

-

-

*10mm.Ø x 6.00m. Def. Reinforcing Steel Bar 184.09 kgs. 40.50 7,455.84

#16 G.I. Tie-wire 3.68 kgs. 65.00 239.32

100mm. x 200mm. x 400mm. Hollow Block (NLB) 640.00 pcs. 14.00 8,960.00

150mm. x 200mm. x 400mm. Hollow Block (LB) 230.00 pcs. 19.00 4,370.00

Portland Cement 46.00 bags 260.00 11,960.00

Washed Sand 3.00 cu.m. 1,260.00 3,780.00

Sub-Total for B 14,581.20

Total (A+B) 23,281.20

8.00

Name and Specifications Quantity Unit Unit Cost Amount

1 8.70 1,376.00 11,971.20

1 8.70 300.00 2,610.00

Sub-Total for A 8,700.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 8.70 366.00 3,184.20

2 8.70 317.00 5,515.80

Daily Rate Amount

8.00

69.60 sq.m.

Designation No. Person No. of Days

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-

SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 64

sq.m.

Page 78: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: PLASTERING WORKS (BANDERA OPERATOR'S ROOM)

Unit of Measurement:

Output per day: sq.m./day

Quantity:

A. Labor

a. Skilled Laborer

b. Laborer

P

B. Equipment

N.A.

P

C.

D. Output per hour = sq.m./day

E. Materials

a. Portland Cement

b. Fine Sand

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

25,430.28

1,525.82

-

-

26,956.10

193.65

Sub-Total for E 13,546.08

40.00 bags. 260.00 10,400.00

2.25 cu.m. 1,400.00 3,146.08

Total (A+B) 11,884.20

16.00

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B -

Name and Capacity No. of Units No. of Days Daily Rate Amount

Sub-Total for A 11,884.20

2 8.70 317.00 5,515.80

Daily Rate Amount

2 8.70 366.00 6,368.40

16.00

139.20 sq.m.

Designation No. Person No. of Days

DETAILED UNIT PRICE ANALYSIS

SPL - 65

sq.m.

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

Page 79: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: TILE WORKS (BANDERA OPERATOR'S ROOM)

Unit of Measurement:

Output per day: sq.m./day

Quantity:

A. Labor

a. Skilled Laborer

b. Laborer

P

B. Equipment

a. Tile Cutter/Angular Grinder

P

C.

D. Output per hour = sq.m./day

E. Materials

a.

b.

c.

d.

e.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

19,813.58

1,188.82

-

-

21,002.40

866.44

Sub-Total for E 15,048.00

PVC Tile Trim (White) 7.00 pcs. 130.00 910.00

Tile Adhesive (25kgs./bag) 4.00 bags 284.00 1,136.00

Tile Grout (2kgs./pack) 6.00 pack 58.00 348.00

200mm. x 200mm. Ceramic Tiles (White) 390.00 pcs. 15.00 5,850.00

400mm. x 400mm. Granite Tiles (White) 54.00 pcs. 126.00 6,804.00

Total (A+B) 4,765.58

5.00

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B 1,454.40

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 4.85 300.00 1,454.40

Sub-Total for A 3,311.18

1 4.85 317.00 1,536.82

Designation No. Person No. of Days Daily Rate Amount

1 4.85 366.00 1,774.37

DETAILED UNIT PRICE ANALYSIS

SPL - 66

sq.m.

5.00

24.24 sq.m.

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

Page 80: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: WATERPROOFING WORKS (BANDERA OPERATOR'S ROOM)

Unit of Measurement:

Output per day:

Quantity:

A. Labor

N.A.

P

B. Equipment

N/A

P

C.

D. Output per day =

E. Materials

a.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

11,000.00

660.00

-

-

11,660.00

11,660.00

Sub-Total for E 11,000.00

Name and Specifications Quantity Unit Unit Cost Amount

Bituminous Membrane Polyester Reinforced Water

Proofing

11 sq.m. 1,000.00 11,000.00

Sub-Total for B -

Total (A+B) -

Name and Capacity No. of Units No. of Days Daily Rate Amount

Sub-Total for A -

Designation No. Person No. of Days Daily Rate Amount

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-

SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 67

lot

1.00 lot

Page 81: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: STEEL WORKS (BANDERA OPERATOR'S ROOM)

Unit of Measurement:

Output per day: sq.m. /day

Quantity:

A. Labor

a. Construction Foreman

b. Skilled Laborer

c. Laborer

P

B. Equipment

a. Welding Machine

b. Angular Grinder

c. Cut-Off Saw

P

C.

D. Output per day = sq.m. /day

E. Materials

a.

b.

c.

d.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

17,015.00

1,020.90

-

-

18,035.90

3,558.78

Sub-Total for E 4,163.00

6mm. Thk. x 20mm. x 6.00m. Flat Bar 4 pcs. 158.00 632.00

6011 Welding Rod 1 kg. 151.00 151.00

10mm. x 10mm. x 6.00m. Square Bar 2 pcs. 216.00 432.00

12mm. x 12mm. x 6.00m. Square Bar 11 pcs. 268.00 2,948.00

Sub-Total for B 8,280.00

Total (A+B) 12,852.00

1.70

Name and Specifications Quantity Unit Unit Cost Amount

1 3 300.00 900.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 3 2,160.00 6,480.00

1 3 300.00 900.00

Sub-Total for A 4,572.00

2 3 317.00 1,902.00

1 3 524.00 1,572.00

1 3 366.00 1,098.00

Designation No. Person No. of Days Daily Rate Amount

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-

SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 68

sq.m.

1.70

5.068 sq.m.

Page 82: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: GLASS WORKS (BANDERA OPERATOR'S ROOM)

Unit of Measurement:

Output per day:

Quantity:

A. Labor

P

B. Equipment

P

C.

D. Output per day = 0 0

E. Materials

a.

b.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

3,700.00

222.00

-

-

3,922.00

3,922.00

-

Sub-Total for E 3,700.00

Supply and installation of 5.5mm. Thk. x 6 Blades x 0.60m. 1 set 500.00 500.00

Width Smoke Glass Jalousies w/ Aluminum Holder

Supply and installation of 5.5mm thk. x 13 - Blades Smoke

Glass x 0.65m.

4 sets 800.00 3,200.00

Width Glass Jalousies w/ Aluminum Holder

Total (A+B) -

0.00

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B

Sub-Total for A -

Name and Capacity No. of Units No. of Days Daily Rate Amount

Amount

1.00 lot

Designation No. Person No. of Days Daily Rate

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-

SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 69

lot

Page 83: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: PAINTING WORKS (BANDERA OPERATOR'S ROOM)

Unit of Measurement:

Output per day: sq.m. /day

Quantity:

A. Labor

a. Construction Foreman

b. Skilled Laborer

c. Laborer

P

B. Equipment

N/A

P

C.

D. Output per day = sq.m. /day

E. Materials

a.

b.

c.

d.

e.

f.

g.

h.

i.

j.

k.

l.

m.

n.

o.

p.

q.

r. Paint Tray 1.00 pc. 30.00 30.00

Quick Dry Enamel (Royal Blue) 1.00 gal. 620.00 620.00

Baby Roller w/ Handle 1.00 pc. 58.00 58.00

1.00 pc. 330.00 330.00Paint Thinner

Lamp Black Tinting Color for Solvent Based Acrylic Paint 1.00 pint 105.00 105.00

Red Lead Paint Primer 1.00 gal. 570.00 570.00

Raw Sienna Tinting Color for Solvent Based Acrylic Paint 3.00 pints 105.00 315.00

Thalo Blue Tinting Color for Solvent Based Acrylic Paint 1.00 pint 105.00 105.00

#120 Sand Paper 2.00 doz. 151.00 302.00

Red Tinting Color for Solvent Based Acrylic Paint 1.00 pint 105.00 105.00

Body Filler w/ Hardener 1.00 gal. 546.00 546.00

#150 Sand Paper 2.00 doz. 151.00 302.00

Solvent Based Acrylic Reducer 4.00 gals. 452.00 1,808.00

Lacquer Thinner 2.00 gals. 494.00 988.00

Solvent Based Acrylic Cast 5.00 gals. 520.00 2,600.00

Solvent Based Acrylic Paint Top Coat White Gloss 10.00 gals. 1,029.00 10,290.00

Concrete Neutralizer 1.00 gals. 520.00 520.00

Solvent Based Acrylic Paint Primer 5.00 gals. 882.00 4,410.00

Total (A+B) 13,437.12

20.00

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B -

Name and Capacity No. of Units No. of Days Daily Rate Amount

Sub-Total for A 13,437.12

2 6.00 317.00 3,804.00

1 6.00 873.52 5,241.12

2 6.00 366.00 4,392.00

Designation No. Person No. of Days Daily Rate Amount

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-

SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 70

sq.m.

20.00

120.00 sq.m.

Page 84: Dumalon W.S. Ground Tank_Final

s.

t.

u.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

37,523.12

2,251.39

-

-

39,774.51

331.45

Sub-Total for E 24,086.00

3" Paint Brush 1.00 pc. 33.00 33.00

2" Paint Brush 1.00 pc. 27.00 27.00

2" Steel Brush 1.00 pc. 22.00 22.00

Page 85: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: CONSTRUCTION OF SEPTIC VAULT (BANDERA OPERATOR'S ROOM)

Unit of Measurement:

Output per day: cu.m. /day

Quantity:

A. Labor

a. Construction Foreman

b. Skilled Laborer

c. Laborer

P

B. Equipment

N/A

P

C.

D. Output per day = cu.m. /day

E. Materials

a.

b.

c.

d.

e.

f.

g.

h.

i.

j.

k.

l.

m.

n.

*All sizes referred herein should mean commercially avaiable measurements with tolerance of ± 1mm.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

4" C.W. Nail 2 kgs. 53.00

0.50 cu.m. 1,400.00 700.00

51,209.15

3,072.55

12mm. Thk. x 1.20m. x 2.40m. Ordinary Plywood 5 shts. 800.00 4,000.00

-

-

54,281.70

9,923.53

Sub-Total for E 39,869.15

1-1/2" C.W. Nail 1 kg. 63.00 63.00

Bituminous Membrane Polyester Reinforced Water Proofing 15.70 sq.m. 1,000.00 15,700.00

3" C.W. Nail 2 kgs. 55.00 110.00

*10mm.Ø x 6.00m. Def. Reinforcing Steel Bars 107 kgs. 40.50 4,345.65

#16 G.I. Tie-wire 5 kgs. 65.00 325.00

Gravel (G-1) 0.75 cu.m. 1,050.00 787.50

106.00

Concrete Water Proofing Compound 9 pack 38.00 342.00

30pcs. - 2" x 2" x 10' Coco Lumber 100 bd.ft. 20.00 2,000.00

30pcs. - 2" x 3" x 10' Coco Lumber 150 bd.ft. 20.00 3,000.00

Fine Sand (for plastering)

Amount

Portland Cement 25 bags 260.00 6,500.00

Washed Sand 1.5 cu.m. 1,260.00 1,890.00

Total (A+B) 11,340.00

0.91

Name and Specifications Quantity Unit Unit Cost Amount

2 6 317.00 3,804.00

Sub-Total for B -

1 6 524.00 3,144.00

2 6 366.00 4,392.00

Sub-Total for A 11,340.00

Name and Capacity No. of Units No. of Days Daily Rate

Designation No. Person No. of Days Daily Rate Amount

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-

SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 71

cu.m.

0.91

5.47 cu.m.

Page 86: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: EMBANKMENT (BALUNO)

Unit of Measurement:

Output per day: cu.m./day

Quantity:

A. Labor

b. Laborer

P

B. Equipment

a. Tamper Rammer

b. Water Truck (1000 gal.)

P

C.

D. Output per hour = cu.m./day

E. Materials

a. Filling Materials

(Filling Materials for Baluno Ground Tank)

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

244,833.50

789.79

Sub-Total for E 115,500.00

230,975.00

13,858.50

-

-

420.00 cu.m. 275.00 115,500.00

Sub-Total for B 90,907.50

Total (A+B) 115,475.00

16.00

Name and Specifications Quantity Unit Unit Cost Amount

1 1.94 8,520.00 16,507.50

Name and Capacity No. of Units No. of Days Daily Rate Amount

2 19.38 1,920.00 74,400.00

Sub-Total for A 24,567.50

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 5

cu.m.

16.00

310.00 cu.m.

4 19.38 317.00 24,567.50

Designation No. Person No. of Days Daily Rate Amount

Page 87: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: PIPELINE & APPURTENANCES (BALUNO)

Unit of Measurement:

Output per day: lotday

Quantity:

A. Labor

a.Skilled Worker

b.Laborer

P

B. Equipment

a.Welding Machine w/ Cutting Outfit

P

C.

D. Output per hour = lotday

E. Materials

Pipeline

100mmØ x 6.00m PVC Pipe, Class 150, B/S, w/ R.R.

D2

100mmØ x 6.00m B.I. Pipe, (ASTM A53-90A Heavy Gauge Standard)

100mmØ x 100mmØ C.I. Tee, F/F, Flange End In Accordance w/ ANSI B16.1 Class 125

100mmØ C.I. Adaptor, F/P, Flange End In Accordance w/ ANSI B16.1 Class 125

100mmØ Steel Blind Flange in accordance w/ AWWA C207 Class D Std.

100mmØ Steel Ring Flange in accordance w/ AWWA C207 Class D Std.

100mmØ C.I. Sleeve Type Flexible Coupling (PVC-CI)

5/8"Ø x 3-1/2" Stainless Bolt w/ Nut & Washer

6mm Thk Rubber Gasket

D3

100mmØ x 6.00m B.I. Pipe, (ASTM A53-90A Heavy Gauge Standard)

100mmØ x 100mmØ C.I. Tee, F/F, Flange End In Accordance w/ ANSI B16.1 Class 125

100mmØ C.I. Adaptor, F/P, Flange End In Accordance w/ ANSI B16.1 Class 125

100mmØ Steel Ring Flange in accordance w/ AWWA C207 Class D Std.

100mmØ C.I. Sleeve Type Flexible Coupling (PVC-CI)

5/8"Ø x 3-1/2" Stainless Bolt w/ Nut & Washer

6mm Thk Rubber Gasket

D4, D5 & D8

100mmØ x 45o PVC Bend, Class 150, B/S w/ R.R.

D6 (Drain & Overflow Pipe)

250mmØ x 6.00m B.I. Pipe, (ASTM A53-90A Heavy Gauge Standard)

250mmØ x 250mmØ C.I. Tee, F/F

Designation No. PersonNo. of Days Daily Rate Amount

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-

SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 72

lot

1.00 lot

Sub-Total for A 12,000.00

3 4.00 366.00 4,392.00

6 4.00 317.00 7,608.00

Name and Capacity No. of UnitsNo. of Days Daily Rate Amount

1 2.00 2,160.00 4,320.00

Sub-Total for B 4,320.00

Total (A+B) 16,320.00

0.00

Name and Specifications Quantity Unit Unit Cost Amount

1.00 pc. 7,269.00 7,269.00

1.00 pc. 3,900.00 3,900.00

7.00 pcs. 2,483.00 17,381.00

1.00 pc. 473.00 473.00

1.00 pc. 3,633.00 3,633.00

1.00 pc. 2,746.00 2,746.00

1.00 pc. 520.00 520.00

1.00 pc. 7,269.00 7,269.00

24.00 pcs. 95.00 2,280.00

3.00 kgs. 85.00 255.00

1.00 pc. 473.00 473.00

2.00 pcs. 3,633.00 7,266.00

1.00 pc. 3,900.00 3,900.00

2.00 pc. 2,746.00 5,492.00

24.00 pcs. 95.00 2,280.00

3.00 kgs. 85.00 255.00

2.00 pcs. 19,554.00 39,108.00

2.00 pcs. 19,465.00 38,930.00

8.00 pcs. 524.00 4,192.00

Page 88: Dumalon W.S. Ground Tank_Final

250mmØ C.I. Body Gate Valve, F/F, PN16, NRS

250mmØ Steel Ring Flange in accordance w/ AWWA C207 Class D Std.

250mmØ C.I. Sleeve Type Flexible Coupling (B.I.)

7/8"Ø x 3-1/2" Stainless Bolt w/ Nut & Washer

D7 (Distribution Pipe)

100mmØ x 6.00m B.I. Pipe, (ASTM A53-90A Heavy Gauge Standard)

100mmØ C.I. Body Gate Valve, F/F, PN16, NRS

100mmØ Steel Ring Flange in accordance w/ AWWA C207 Class D Std.

100mmØ C.I. Sleeve Type Flexible Coupling (PVC-B.I.)

5/8"Ø x 3-1/2" Stainless Bolt w/ Nut & Washer

Ind. Oxygen (Content)

Acetylene (Content)

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

4.00 pcs. 13,671.00 54,684.00

120.00 pcs. 137.00 16,440.00

2.00 pcs. 37,059.00 74,118.00

10.00 pc. 1,150.00 11,500.00

2.00 pcs. 8,956.00 17,912.00

4.00 pc. 473.00 1,892.00

2.00 pcs. 7,269.00 14,538.00

4.00 cyls. 750.00 3,000.00

2.00 cyls. 1,500.00 3,000.00

2.00 pcs. 3,633.00 7,266.00

32.00 pcs. 95.00 3,040.00

393,611.92

393,611.92

Sub-Total for E 355,012.00

371,332.00

22,279.92

-

-

Page 89: Dumalon W.S. Ground Tank_Final

Amount

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-

SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

12,000.00

4,392.00

7,608.00

Amount

4,320.00

4,320.00

16,320.00

Amount

7,269.00

3,900.00

17,381.00

473.00

3,633.00

2,746.00

520.00

7,269.00

2,280.00

255.00

473.00

7,266.00

3,900.00

5,492.00

2,280.00

255.00

39,108.00

38,930.00

4,192.00

Page 90: Dumalon W.S. Ground Tank_Final

54,684.00

16,440.00

74,118.00

11,500.00

17,912.00

1,892.00

14,538.00

3,000.00

3,000.00

7,266.00

3,040.00

393,611.92

393,611.92

355,012.00

371,332.00

22,279.92

-

-

Page 91: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: PIPELINE & APPURTENANCES (BANDERA)

Unit of Measurement:

Output per day: lotday

Quantity:

A. Labor

a.Skilled Worker

b.Laborer

P

B. Equipment

a.Welding Machine w/ Cutting Outfit

P

C.

D. Output per hour = lotday

E. Materials

Pipeline

150mmØ x 6.00m PVC Pipe, Class 150, B/S, w/ R.R.

100mmØ x 6.00m PVC Pipe, Class 150, B/S, w/ R.R.

D2

150mmØ x 6.00m B.I. Pipe, (ASTM A53-90A Heavy Gauge Standard)

150mmØ x 150mmØ C.I. Tee, F/F, Flange End In Accordance w/ ANSI B16.1 Class 125

150mmØ C.I. Adaptor, F/P, Flange End In Accordance w/ ANSI B16.1 Class 125

150mmØ Steel Blind Flange in accordance w/ AWWA C207 Class D Std.

150mmØ Steel Ring Flange in accordance w/ AWWA C207 Class D Std.

150mmØ C.I. Sleeve Type Flexible Coupling (PVC-CI)

3/4"Ø x 3-1/2" Stainless Bolt w/ Nut & Washer

6mm Thk Rubber Gasket

D3

150mmØ x 6.00m B.I. Pipe, (ASTM A53-90A Heavy Gauge Standard)

150mmØ x 150mmØ C.I. Tee, F/F, Flange End In Accordance w/ ANSI B16.1 Class 125

150mmØ C.I. Adaptor, F/P, Flange End In Accordance w/ ANSI B16.1 Class 125

150mmØ Steel Ring Flange in accordance w/ AWWA C207 Class D Std.

150mmØ C.I. Sleeve Type Flexible Coupling (PVC-CI)

3/4"Ø x 3-1/2" Stainless Bolt w/ Nut & Washer

6mm Thk Rubber Gasket

D4, D5 & D8

150mmØ x 45o PVC Bend, Class 150, B/S w/ R.R.

100mmØ x 45o PVC Bend, Class 150, B/S w/ R.R.

Designation No. PersonNo. of Days Daily Rate Amount

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-MALAGUTAY-

SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 73

lot

0.25

1.00 lot

Sub-Total for A 12,000.00

3 4.00 366.00 4,392.00

6 4.00 317.00 7,608.00

Name and Capacity No. of UnitsNo. of Days Daily Rate Amount

1 2.00 2,160.00 4,320.00

1.00 pc. 6,331.00 6,331.00

1.00 pc. 3,276.00 3,276.00

Sub-Total for B 4,320.00

Total (A+B) 16,320.00

0.25

Name and Specifications Quantity Unit Unit Cost Amount

1.00

pcs. 115.00 2,760.00

3.00 kgs. 85.00 255.00

1.00 pc. 780.00 780.00

1.00 pc. 568.00 568.00

1.00

4.00

4.00 pcs. 2,204.00 551.00

8,645.00

2.00

24.00 pcs. 115.00 2,760.00

3.00 kgs. 85.00 255.00

6,552.00

1.00

2.00 pcs. 5,842.00 11,684.00

1.00

6,331.00

pc. 8,645.00

6,331.00

24.00

8,645.00

1.00 pc.

5.00 pcs.

2.00 pcs.

4,610.00

2,483.00

23,050.00

4,966.00

pc. 3,276.00

pcs. 2,315.00 9,260.00

pc. 568.00 568.00

pc. 8,645.00

pc. 5,842.00 5,842.00

Page 92: Dumalon W.S. Ground Tank_Final

D6 (Drain & Overflow Pipe)

250mmØ x 6.00m B.I. Pipe, (ASTM A53-90A Heavy Gauge Standard)

250mmØ x 250mmØ C.I. Tee, F/F

250mmØ C.I. Body Gate Valve, F/F, PN16, NRS

250mmØ Steel Ring Flange in accordance w/ AWWA C207 Class D Std.

250mmØ C.I. Sleeve Type Flexible Coupling (B.I.)

7/8"Ø x 3-1/2" Stainless Bolt w/ Nut & Washer

D7 (Distribution Pipe)

100mmØ x 6.00m B.I. Pipe, (ASTM A53-90A Heavy Gauge Standard)

100mmØ C.I. Body Gate Valve, F/F, PN16, NRS

100mmØ Steel Ring Flange in accordance w/ AWWA C207 Class D Std.

100mmØ C.I. Sleeve Type Flexible Coupling (PVC-B.I.)

5/8"Ø x 3-1/2" Stainless Bolt w/ Nut & Washer

Ind. Oxygen (Content)

Acetylene (Content)

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

39,108.00

11,500.00

pcs. 13,671.00 54,684.00

pcs. 19,554.00

pc.

3,633.00

pcs.

Sub-Total for E 390,160.00

19,465.00

32.00

120.00

2.00

2.00

4.00

2.00

2.00

2.00

2.00

10.00

4.00

pcs. 95.00 3,040.00

pc.

pcs.

cyls. 1,500.00 3,000.00

750.00 3,000.00 4.00

406,480.00

24,388.80

-

-

430,868.80

430,868.80

473.00 1,892.00

7,266.00

1,150.00

2.00

cyls.

38,930.00

pcs. 37,059.00 74,118.00

14,538.00

pcs. 8,956.00 17,912.00

pcs. 137.00 16,440.00

pcs. 7,269.00

Page 93: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description:

Unit of Measurement:

Output per day: lot/day

Quantity:

A. Labor

Including in the Package

P

B. Equipment

Including in the Package

P

C.

D. Output per hour = lot/day

E. Materials

Specifications:

1. Mobilization, demobilization, Labor, Tools, Equipment, Testing of Materials

& other cost contingency shall be included in this Item of work

2. Tank Concrete Foundation shall be designed as per National Structural

Code of the Philippines (NSCP) & constructed by the winning bidder and shall

conform to proposed site development and actual site soil condition

3. Three Hundred (300) Cu. M. Usable Capacity Steel Tank for Potable Water w/ complete

accessories

4. Materials shall be high tensile steel sheets with minimum 70,000psi

yield strength

5. Pipe Stub-out Connection:

1 unit - Modular Tank for Bandera: 2 units-100mmØ, 2 units -150mmØ, 2 units - 250mmØ

1 unit - Modular Tank for Baluno: 4 units-100mmØ, 2 units - 250mmØ

6. Tank Designed as per NSCP 2010 (or Latest Edition)

Seismic Zone 4

150mph Wind Load

other parameter & factor shall refer to NSCP 2010 (or Latest Edition)

7. Reference Standard:

NSCP 2010

AS/NZS 4020:1999

EN ISO 28765:2011

ANSI/AWWA D103-09

or other equivalent standards for Modular Tank

8. During bidding, the bidder shall provide the site development showing the proposed location

of Modular Tank & required to show sample wall pannel.

Note: See Attached ZCWD Baluno & Bandera Ground Tank Site Development Plan

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 74

unit

2.00 units

SUPPLY/CONST./TESTING/DISINFECT./COMM. OF 300 CU.M. MODULAR TANK (FOR

BALUNO & BANDERA)

Sub-Total for A -

Designation No. Person No. of Days Daily Rate Amount

Amount

a. SUPPLY/CONST./LEAKAGE TESTING/DISINFECT./ COMM.

OF 300 CU.M. MODULAR TANK (1 UNIT FOR BALUNO & 1

UNIT FOR BANDERA)

Name and Capacity No. of Units No. of Days Daily Rate

Name and Specifications Quantity Unit Unit Cost

2.00 units 5,500,000.00

Amount

Sub-Total for B -

Total (A+B) -

0.00

11,000,000.00

11,660,000.00

5,830,000.00

Sub-Total for E 11,000,000.00

11,000,000.00

660,000.00

-

-

Page 94: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: SUPPLY & INST. OF 40GPD HYPOCHLORINATOR (BANDERA & BALUNO)

Unit of Measurement:

Output per day: lot/day

Quantity:

A. Labor

Including in the Package

P

B. Equipment

Including in the Package

P

C.

D. Output per hour = lot/day

E. Materials

Specs:

"CHEM-TECH" heavy Duty Hypochlorinator with 100 liters Solution Tank

with stirrer, series 200, designed to deliver 40 GPD(max) vs. 125 psig,

mechanical diaphragm type and oil bathed gear assembly, driven by

electric motor, 230V, single phase, 60 Hz. With complete standard

suction & discharge accessories:

- 4 ft. Suction Tubing, clear PVC, 7/16"OD

- 8 ft. Discharge Tubing, P.E., 1/2" OD

- 1 set Back check Valve & Injection Fittings

- 1 set Foot Valve with strainer

- 1 pc. Bleed Valve

Provision for Chlorinator Injection Fittings:

50mm.Ø G.I. Coupling, ANSI B16.3 Class 150

50mm.Ø x 150mm G.I. Nipple, ASTM A53-90A Heavy Gauge Std.

50mm.Ø G.I. Cap, ANSI B16.3 Class 150

19mm.Ø G.I. Coupling, ANSI B16.3 Class 150

19mm.Ø x 12mm.Ø G.I. Bushing, ANSI B16.3 Class 150

12mm.Ø G.I. Plug, ANSI B16.3 Class 150

Pressure Gauge Assembly:

12mm.Ø x 12mm.Ø G.I. Tee, ANSI B16.3 Class 150

12mm.Ø G.I. Coupling, ANSI B16.3 Class 150

DETAILED UNIT PRICE ANALYSIS

SPL - 75

lot

1.00

2.00 lots

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

Sub-Total for A -

Designation No. Person No. of Days Daily Rate Amount

Name and Capacity No. of Units No. of Days Daily Rate Amount

Total (A+B) -

1.00

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for B -

2.00 pc. 97.00 194.00

2.00 lots 90,000.00 180,000.00

2.00 pc. 25.00 50.00

2.00 pc. 19.00 38.00

2.00 pc. 136.00 272.00

2.00 pc. 63.00 126.00

4.00 pc. 25.00 100.00

2.00 pc. 19.00 38.00

4.00 pc. 28.00 112.00

SUPPLY & INST. OF 40GPD HYPOCHLORINATOR (BANDERA &

BALUNO)

Page 95: Dumalon W.S. Ground Tank_Final

12mm.Ø x 100mm G.I. Nipple, ASTM A53-90A Heavy Gauge Std.

12mm.Ø x 6mmØ G.I. Bushing, ANSI B16.3 Class 150

12mm.Ø G.I. Plug, ANSI B16.3 Class 150

12mm.Ø Brass Ball Valve

63mm.Ø Oil-filled Pressure Gauge (0-150 psi)

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

4.00 pc. 20.00 80.00

2,000.00 8,000.00

4.00 pc. 10.00 40.00

4.00 pc. 19.00 76.00

246,851.80

14,811.11

-

-

261,662.91

130,831.45

Sub-Total for E 246,851.80

2.00 lot 56,965.80 56,965.80 Labor: Cutting & Welding works of B.I. Discharge Pipes, installation of

Appurtenances, preparation of Pressure Gauge assy. and provision for

Chlorinator Injection Fittings.

4.00 pc. 190.00 760.00

4.00 pc.

Page 96: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Unit of Measurement:

Output per day: unit/day

Quantity:

A. Labor

a. Skilled Worker

b. Laborer

P

B. Equipment

a. One Bagger Mixer (w/ Fuel)

b. Concrete Vibrator (w/ Fuel)

c. Bar Cutter

P

C.

D. Output per hour = unit/day

E. Materials

a. Supply & Installation of 100mmØ Differential Float Controlled Valve, F/F

w/ 2-Units Steel Ring Flange & Complete Bolts, Nuts & Washers

Specifications:

The valve will be controlled by a differential float-operated, maximum differential level of

4.00 meters & a maximum flowrate equals to 40.00 LPS

The differential float controlled valve will be installed below the water level, constructed with

concrete valve box

The valve will be a hydraulically operated, diaphragm actuated,

Face to face length dimension meets ISO 57529S-10 Standard, Flanged end Connection in

accordance w/ ANSI

Maximum pressure rating of PN16 (230 psi)

b. 100mmØ C.I. Sleeve Type Flexible Coupling, (C.I.-B.I.)

c. 6mm thk Rubber Gasket

d. 16mmØ x 100mm Anchor Bolts w/ Nuts & Washer

Construction of concrete valve box 1.00 unit

e. Portland Cement

f. Washed Sand

g. Gravel (G1)

h. *16mmØ x 6.00m Deformed Reinf. Steel Bar

i. #16 GI Tie Wire

j. 16mmØ x 6.00m Stainless Steel Round Bar (Type 304)

110.00

170.00

1,760.00

Designation No. Person No. of Days Daily Rate Amount

1 4.00 972.00 3,888.00

1 0.40 8,520.00

Sub-Total for A 12,000.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 4.00 1,376.00 5,504.00

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 76

unit

0.25

1.00 units

3 4.00 366.00 4,392.00

6 4.00 317.00 7,608.00

SUPPLY & INST. OF DIFFERENTIAL FLOAT CONTROL VALVE & CONST. OF CONC.

VALVE BOX (BALUNO)

Item No./Description:

3,408.00

Sub-Total for B 12,800.00

Total (A+B) 24,800.00

0.25

Name and Specifications Quantity Unit Unit Cost Amount

1.00 unit 179,160.00 179,160.00

2.00 pcs. 3,633.00 7,266.00

2.00

16.00

kgs.

pcs.

85.00

14.00

0.75

1.50

227.52

5.00

1.00

bags

cu.m.

cu.m.

kgs.

kgs.

pc.

3,640.00

945.00

1,575.00

9,214.56 40.50

65.00 325.00

12,500.00

260.00

1,260.00

1,050.00

12,500.00

Page 97: Dumalon W.S. Ground Tank_Final

k. 8mmØ x 6.00m M.S. Plain Round Bar

l. 16mmØ x 6.00m M.S. Plain Round Bar

m. 38mmØ x 6.00m G.I. Pipe ASTM A53-90A Heavy Gauge Std.

n. 6mm Thk x 50mm x 50mm x 6.00m MS Angle Bar

o. *12mm Thk x 1.20m x 2.40m Ordinary Plywood

p. 2" x 2" x 10' Coco Lumber

q. 2" x 3" x 10' Coco Lumber

r. 2" x 4" x 10' Coco Lumber

s 4" C.W. Nail

t. 3" C.W. Nail

u. 1-1/2" C.W. Nail

v. Welding Rod (6011)

*All sizes referred herein should mean commercially avaiable measurements with tolerance of ± 1mm.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

270,294.76

270,294.76

0.50 kg. 151.00 75.50

Sub-Total for E 230,195.06

254,995.06

15,299.70

-

-

33.00

50.00

67.00

1.00

0.50

0.50

1.00

5.00

1.00

2.00

3.00

kg.

kg.

bd.ft.

bd.ft.

bd.ft.

kg.

pcs.

shts.

pc.

pcs.

pc.

20.00

63.00

495.00

2,267.00

1,575.00

800.00

20.00

20.00

31.50

2,400.00

660.00

1,000.00

1,340.00

53.00

27.50

53.00

55.00

160.00

2,475.00

2,267.00

3,150.00

160.00

Page 98: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Unit of Measurement:

Output per day: unit/day

Quantity:

A. Labor

a. Skilled Worker

b. Laborer

P

B. Equipment

a. One Bagger Mixer (w/ Fuel)

b. Concrete Vibrator (w/ Fuel)

c. Bar Cutter

P

C.

D. Output per hour = unit/day

E. Materials

a. Supply & Installation of 150mmØ Differential Float Controlled Valve, F/F

w/ 2-Units Steel Ring Flange & Complete Bolts, Nuts & Washers

Specifications:

The valve will be controlled by a differential float-operated, maximum differential level of

4.00 meters & a maximum flowrate equals to 40.00 LPS

The differential float controlled valve will be installed below the water level, constructed with

concrete valve box

The valve will be a hydraulically operated, diaphragm actuated,

Face to face length dimension meets ISO 57529S-10 Standard, Flanged end Connection in

accordance w/ ANSI

Maximum pressure rating of PN16 (230 psi)

b. 150mmØ C.I. Sleeve Type Flexible Coupling, (C.I.-B.I.)

d. 6mm thk Rubber Gasket

e. 16mmØ x 100mm Anchor Bolts w/ Nuts & Washer

Construction of concrete valve box 1 unit

f. Portland Cement

g. Washed Sand

h. Gravel (G1)

i. *16mmØ x 6.00m Deformed Reinf. Steel Bar

j. #16 GI Tie Wire

k. 16mmØ x 6.00m Stainless Steel Round Bar (Type 304)

l. 8mmØ x 6.00m M.S. Plain Round Bar

4.00 1,376.00 5,504.00

No. of Days Daily Rate Amount

4.00 317.00 7,608.00

1 4.00 972.00 3,888.00

1 0.40

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 77

unit

0.25

1.00 units

3 4.00 366.00 4,392.00

6

SUPPLY & INST. OF DIFFERENTIAL FLOAT CONTROL VALVE & CONST. OF CONC. VALVE

BOX (BANDERA)

Item No./Description:

Designation No. Person

8,520.00 3,408.00

Sub-Total for A 12,000.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

1

Sub-Total for B 12,800.00

Total (A+B) 24,800.00

0.25

Name and Specifications Quantity Unit Unit Cost Amount

1.00 unit 342,600.00 342,600.00

2.00

2.00

16.00

pcs.

kgs.

pcs.

5,500.00

85.00

110.00

11,000.00

170.00

1,760.00

1.50 cu.m. 1,050.00 1,575.00

227.52 kgs. 40.50 9,214.56

14.00 bags 260.00 3,640.00

0.75 cu.m. 1,260.00 945.00

1.00 pc. 160.00 160.00

5.00 kgs. 65.00 325.00

1.00 pc. 12,500.00 12,500.00

Page 99: Dumalon W.S. Ground Tank_Final

m. 16mmØ x 6.00m M.S. Plain Round Bar

n. 38mmØ x 6.00m G.I. Pipe ASTM A53-90A Heavy Gauge Std.

o. 6mm Thk x 50mm x 50mm x 6.00m MS Angle Bar

p. *12mm Thk x 1.20m x 2.40m Ordinary Plywood

q. 2" x 2" x 10' Coco Lumber

r. 2" x 3" x 10' Coco Lumber

s. 2" x 4" x 10' Coco Lumber

t. 4" C.W. Nail

u. 3" C.W. Nail

v. 1-1/2" C.W. Nail

w. Welding Rod (6011)

*All sizes referred herein should mean commercially avaiable measurements with tolerance of ± 1mm.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

5.00 pcs. 495.00 2,475.00

3.00 shts. 800.00 2,400.00

33.00 bd.ft. 20.00 660.00

1.00 pc. 2,267.00 2,267.00

1.00 pcs. 1,575.00 1,575.00

1.00 kg. 53.00 53.00

0.50 kg. 55.00 27.50

50.00 bd.ft. 20.00 1,000.00

67.00 bd.ft. 20.00 1,340.00

445,829.70

445,829.70

Sub-Total for E 395,794.06

420,594.06

25,235.64

-

-

0.50 kg. 63.00 31.50

0.50 kg. 151.00 75.50

Page 100: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Unit of Measurement:

Output per day: unit/day

Quantity:

A. Labor

a. Skilled Worker

b. Laborer

P

B. Equipment

a. One Bagger Mixer (w/ Fuel)

b. Concrete Vibrator (w/ Fuel)

c. Bar Cutter

P

C.

D. Output per hour = unit/day

E. Materials

a. Supply & Installation of 100mmØ Full Bore Electromagnetic Flowmeter F/F,

w/ 2-Units Steel Ring Flange & Complete Bolts, Nuts & Washers

Specifications:

100mmØ Electro-Magnetic Flowmeter, ANSI 16.5, Class-150,

Flanged-Typed, Transmitter accuracy of 0.40% of rate, with highly

accurate bi-directional measurements, battery powered, with internal

battery pack of five (05) years maintenance free battery life.

Complete with two (02) mating flanges and the desired stainless steel

bolts, nuts, washers with rubber gaskets. Unit is remote-type with

complete accessories and with integrated GSM Data Logger

(wall-mounted typed signal converter) which records/logs the flow &

pressure, and is compatible with the sensor EM Flowmeter

with a recording interval programmable between 1 second

& 1 hour. EM Flowmeter & Logger housing is fully water proofed (IP68).

Data can be accessed remotely using a standard GSM mobile phone

thru simple text message to the host computer provided with a

windows-based software which can monitor multiple data loggers.

24 months warranty, with Wet Calibration Certificate per unit upon delivery.

The unit includes the following accessories:

Fifty (50) meters flow input cable with pvc conduit up to the pump house,

communication cable, Windows-based configuration software for PC's,

Two channel flow splitter cable (50 meters), 50 meters hose for pressure

line with fittings (quick fit connection).

Note: Package includes Orientation & Training of personnel

100mmØ C.I. Sleeve Type Flexible Coupling, (G.I.-PVC)

pcs.

3,915.00

2,541.00

15,660.00

10,164.00

4.00 units 286,000.00 1,144,000.00

4.00

4.00

pcs.

Name and Specifications Quantity Unit Unit Cost Amount

1 16.00 1,376.00 22,016.00

Sub-Total for B 51,200.00

Total (A+B) 99,200.00

0.25

DETAILED UNIT PRICE ANALYSIS

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SPL - 78

unit

0.25

4.00 units

3 16.00 366.00 17,568.00

6 16.00 317.00 30,432.00

100mmØ C.I. Adaptor, F/P, Flange End In Accordance w/

ANSI B16.1 Class 125

SUPPLY, CONST. & INST. OF 100MMØ FLOWMETER W/ CONC. VALVE BOX (FOR BALUNO &

BANDERA)

Item No./Description:

Designation No. Person No. of Days Daily Rate Amount

Sub-Total for A 48,000.00

1 16.00 972.00 15,552.00

1 1.60 8,520.00 13,632.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

Page 101: Dumalon W.S. Ground Tank_Final

6mm thk Rubber Gasket

16mmØ x 100mm Anchor Bolts w/ Nuts & Washer

Construction of concrete valve box 4 units

e. Portland Cement

f. Washed Sand

g. Gravel (G1)

h. *16mmØ x 6.00m Deformed Reinf. Steel Bar

i. #16 GI Tie Wire

j. 16mmØ x 6.00m Stainless Steel Round Bar (Type 304)

k. 8mmØ x 6.00m M.S. Plain Round Bar

l. 16mmØ x 6.00m M.S. Plain Round Bar

m. 38mmØ x 6.00m G.I. Pipe ASTM A53-90A Heavy Gauge Std.

n. 6mm Thk x 50mm x 50mm x 6.00m MS Angle Bar

o. *12mm Thk x 1.20m x 2.40m Ordinary Plywood

p. 2" x 2" x 10' Coco Lumber

q. 2" x 3" x 10' Coco Lumber

r. 2" x 4" x 10' Coco Lumber

s 4" C.W. Nail

t. 3" C.W. Nail

u. 1-1/2" C.W. Nail

v. Welding Rod (6011)

*All sizes referred herein should mean commercially avaiable measurements with tolerance of ± 1mm.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

64.00 pcs. 120.00 7,680.00

kgs. 75.00 750.00

1,450,050.42

362,512.60

10.00

1.00 kg. 53.00 53.00

0.50 kg. 55.00 27.50

50.00 bd.ft. 20.00 1,000.00

67.00 bd.ft.

Sub-Total for E 1,268,772.09

1,367,972.09

82,078.33

-

-

0.50 kg. 63.00 31.50

2.00 kg. 151.00 302.00

20.00 1,340.00

9.00 shts. 800.00 7,200.00

33.00 bd.ft. 20.00 660.00

1.00 pc. 2,267.00 2,267.00

2.00 pcs. 1,575.00 3,150.00

1.00 pc. 160.00 160.00

10.00 pcs. 495.00 4,950.00

17.06 kgs. 65.00 1,109.16

1.00 pc. 12,500.00 12,500.00

4.89 cu.m. 1,050.00 5,133.33

853.20 kgs. 40.50 34,554.60

50.00 bags 260.00 13,000.00

2.44 cu.m. 1,260.00 3,080.00

Page 102: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: CONSTRUTION OF DRIVEWAY (BALUNO & BANDERA)

Unit of Measurement:

Output per day: cu.m./day

Quantity:

A. Labor

a. Construction Foreman

b. Skilled Worker

c. Laborer

P

B. Equipment

a. One Bagger Mixer (w/ Fuel)

b. Concrete Vibrator (w/ Fuel)

c. Water Truck (1000 gal.)

d. Tamper Rammer

e. Motorized Road Grader

P

C.

D. Output per hour = cu.m./day

E. Materials

a. Portland Cement (Type 1P)

b. Washed Sand

c. Gravel (311A)

d. Item 201 (Aggregates Base Course)

e. *16mmØ x 6.00m Deformed Reinforced Steel Bar

f. 2" x 6" x 10' Coco Lumber

g. 2" x 2" x 10' Coco Lumber

h. 3" C.W. Nail

*All sizes referred herein should mean commercially avaiable measurements with tolerance of ± 1mm.

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

SPL - 79

cu.m.

11.20

27.90 cu.m.

1 2.49 873.52 2,176.00

Designation No. Person No. of Days Daily Rate Amount

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

Sub-Total for A 7,158.14

2 2.49 366.00 1,823.46

4 2.49 317.00 3,158.68

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 2.49 1,376.00 3,427.71

1 2.49 1,920.00 4,782.86

1 2.49 972.00 2,421.32

1 0.25 8,520.00 2,122.39

1 2.00 17,384.00 34,768.00

Sub-Total for B 47,522.29

Total (A+B) 54,680.43

11.20

Name and Specifications Quantity Unit Unit Cost Amount

24.50 cu.m. 1,050.00 25,725.00

20.50 cu.m. 682.00 13,981.00

257.00 bags 260.00 66,820.00

12.25 cu.m. 1,260.00 15,435.00

100.00 bd.ft. 20.00 2,000.00

33.00 bd.ft. 20.00 660.00

9.48 kgs. 40.50 383.94

190,524.79

6,828.85

Sub-Total for E 125,059.94

179,740.37

10,784.42

-

-

1.00 kg. 55.00 55.00

Page 103: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: LANDSCAPING WORKS (BALUNO & BANDERA)

Unit of Measurement:

Output per day: sq.m./day

Quantity:

A. Labor

a. Skilled Worker

b. Laborer

P

B. Equipment

N.A.

P

C.

D. Output per hour = sq.m./day

E. Materials

a. Carabao Grass

b. Garden Soil

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

Designation No. Person No. of Days Daily Rate Amount

DETAILED UNIT PRICE ANALYSIS

SPL - 80

sq.m.

10.00

258.00 sq.m.

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

Sub-Total for A 25,800.00

1 25.80 366.00 9,442.80

2 25.80 317.00 16,357.20

Name and Capacity No. of Units No. of Days Daily Rate Amount

258.00 sq.m. 315.00 81,270.00

30.00 cu.m. 1,260.00 37,800.00

Sub-Total for B -

Total (A+B) 25,800.00

10.00

Name and Specifications Quantity Unit Unit Cost Amount

Sub-Total for E 119,070.00

144,870.00

8,692.20

-

-

153,562.20

595.20

Page 104: Dumalon W.S. Ground Tank_Final

PROJECT NAME :

Item No./Description: SPL - 81 SUPPLY, TESTING & INST. OF KW-HR METER, RACEWAY AND ACCS.

Unit of Measurement: lot

Output per day: 1.00 lot /day

Quantity: 1.00

A. Labor

a. Skilled Worker

b. Laborer

P

B. Equipment

a. Boom Truck w/ fuel & driver

P

C.

D. Output per day = lot

E. Materials

a. 35 Footer Round Centrifugal Prestressed Concrete

Pole or Galvanized Steel Pole

Minimum Break Load : 500 kgs.

Top Diameter : 140 mm

Butt Diameter : 368 mm

b. Kiliwatthour Meter (Digital), 250 Volts, 1 Phase, Assy,

GE Class 200, 5 jaw, complete w/ Rectangular Base

c. Testing/Calibration FEE

d. 25mmØ Entrance Cap

e. 25mmØ x 3m RSC Conduit Pipe

f. 25mmØ RSC Male Adaptor

g. 25mmØ Locknut

h. 25mmØ Conduit Pipe Clamp

i. Single Wire, Secondary Rack w/ Spool Insulator

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

lot

Designation No. Person No. of Days Daily Rate Amount

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

Sub-Total for A 683.00

1 1.00 366.00 366.00

1 1.00 317.00 317.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 1.00 8,562.00 8,562.00

Sub-Total for B 8,562.00

Total (A+B) 9,245.00

1.00

Name and Specifications Quantity Unit Unit Cost Amount

assy. 1 8,160.00 8,160.00

lot 1 300.00 300.00

unit 1 18,207.00 18,207.00

pc. 1 8.00 8.00

pc. 1 6.00 6.00

pc. 1 41.00 41.00

pc. 1 367.00 367.00

Sub-Total for E 27,300.00

pcs. 4 7.00 28.00

pc. 1 183.00 183.00

36,545.00

2,192.70

-

-

38,737.70

38,737.70

Page 105: Dumalon W.S. Ground Tank_Final

PROJECT NAME :

SPL - 82

Unit of Measurement: ln.m.

Output per day: 350.00 ln.m. /day

Quantity: 700.00

A. Labor

a. Skilled Worker

b. Laborer

P

B. Equipment

N.A.

P

C.

D. Output per day = ln.m.

E. Materials

a. 50mmØx6m ASTM A53-90A Heavy Guage G.I.Pipe

b. Service Entrance Cable (Drop Wire) #6

Single wire, Secondary Rack w/ Spool Insulator

10mmØ x 6m Deformed Steel Bar

Portland Cement

Sand

Gravel

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

ln.m.

Designation No. Person No. of Days Daily Rate Amount

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

SUPPLY, STRINGING & LAY-OUTING OF APPROX. 700 L.M. 1Ø LINE W/ 6 UNITS PEDESTAL

AND ACCS:

Item No./Description:

Sub-Total for A 4,000.00

2 2.00 366.00 1,464.00

4 2.00 317.00 2,536.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

Sub-Total for B -

Total (A+B) 4,000.00

350.00

Name and Specifications Quantity Unit Unit Cost Amount

pc. 6 183.00 1,098.00

pcs. 12 180.00 2,160.00

pcs. 3 2,829.00 8,487.00

mtrs. 700 20.00 14,000.00

m3

3 900.00 2,700.00

bags 6 260.00 1,560.00

m3

2 900.00 1,800.00

Sub-Total for E 31,805.00

35,805.00

2,148.30

-

-

37,953.30

54.22

Page 106: Dumalon W.S. Ground Tank_Final

PROJECT NAME :

Item No./Description: SPL - 83 SUPPLY & INSTALLATION OF ELECTRICAL FACILITIES FOR OPERATOR'S ROOM

Unit of Measurement: lot

Output per day: 0.14 lot /day

Quantity: 1.00

A. Labor

a. Skilled Worker

b. Laborer

P

B. Equipment

N.A.

P

C.

D. Output per day = lot

E. Materials

a. 60 Amperes Main Circuit Breaker, 1 Ø, 250 V, Panel

Board enclosed in Powder Coated Finished

Panel Box with 5 Single Phase Branches of:

1 sets - 15 Amps. Branch

4 sets - 20 Amps. Branch

b. 8.0mm2 THW Stranded Wire

c. 3.5mm2 TW Stranded Wire

d. 2.0mm2 TW Stranded Wire

e. 25mmØ Entrance Cap

f. 25mmØ x 3m PVC Conduit Pipe

g. 25mmØ x 90o PVC Long Sweep Elbow

h. 25mmØ PVC Male Adaptor

i. 25mmØ Locknut

j. 20mmØ Flexible Conduit

k. 20mmØ x 3m PVC Conduit Pipe

l. 20mmØ x 90o PVC Long Sweep Elbow

m. 20mmØ PVC Male Adaptor

n. 20mmØ PVC Coupling

o. 20mmØ Locknut

p.

q. Single Wire, Secondary Rack w/ Spool Insulator

r. Surface Type Reflectorized Fluorescent

Luminaire with 1x40W Flourescent Tube

s. 23 Watts 3U CFL with Capsule

t. 16" Ceiling Orbit Fan, Industrial Type

DETAILED UNIT PRICE ANALYSIS

lot

Designation No. Person No. of Days Daily Rate Amount

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

Sub-Total for A 4,781.00

1 7.00 366.00 2,562.00

1 7.00 317.00 2,219.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

Sub-Total for B -

Total (A+B) 4,781.00

0.14

Name and Specifications Quantity Unit Unit Cost Amount

set 1 5,766.00 5,766.00

mtrs. 60 84.00 5,040.00

pc. 1 41.00 41.00

pc. 1 131.00 131.00

mtrs. 100 32.00 3,200.00

mtrs. 75 23.00 1,725.00

pc. 1 6.00 6.00

mtrs. 48 8.00 384.00

pc. 1 26.00 26.00

pc. 1 8.00 8.00

pcs. 12 6.00 72.00

pcs. 8 5.00 40.00

pcs. 15 86.00 1,290.00

pcs. 10 17.00 170.00

pcs. 12 4.00 48.00

Welding Machine Outlet pc. 1 1,472.00 1,472.00

pcs. 2 1,132.00 2,264.00

pc. 3 148.00 444.00

pc. 1 142.00 142.00

pcs.

pc. 1 2,200.00 2,200.00

Page 107: Dumalon W.S. Ground Tank_Final

u. Switch 1-Gang w/ plate (flush type)

v. Switch 2-Gang w/ plate (flush type)

w. Ceiling Socket with screw

x. Duplex Convenience Outlet w/ plate (flush type)

y. Duplex Convenience Outlet w/ plate -

weatherproof (flush type)

z. 2" x 4" x 2" PVC Utility Box ( H.D.)

a1. 4" x 4" PVC Junction Box ( H.D.) w/ Cover

b1. #16 G.I. Tie Wire

c1. PVC Solvent Cement

d1. 1/4" Camridge / Mica Tube

e1. 0.8mm x 19mm x 8m Polytype Electrical Tape

d1. 0.8mm x 19mm x 8m Rubber Tape

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

pcs. 2 107.00 214.00

pcs. 3 31.00 93.00

pcs. 2 90.00 180.00

pcs. 1 173.00 173.00

pcs. 9 21.00 189.00

pc. 3 107.00 321.00

pcs.

qrt. 0.5 460.00 230.00

mtrs. 1 13.00 13.00

pcs. 6 24.00 144.00

kgs. 2 75.00 150.00

Sub-Total for E 26,455.00

31,236.00

1,874.16

-

-

pcs. 3 25.00 75.00

pcs. 2 102.00 204.00

33,110.16

33,110.16

Page 108: Dumalon W.S. Ground Tank_Final

PROJECT NAME :

Item No./Description: SPL - 84 SUPPLY & INST. OF ELEC. FACILITIES FOR GUARD HOUSE, SIGNAGE & PERIMETER LIGHTINGS

Unit of Measurement: lot

Output per day: 0.14 lot /day

Quantity: 1.00

A. Labor

a. Skilled Worker

b. Laborer

P

B. Equipment

N.A.

P

C.

D. Output per day = lot

E. Materials

a. 3.5mm2 TW Stranded Wire

b. 20mmØ x 3m PVC Conduit Pipe

c. 20mmØ x 90o PVC Long Sweep Elbow

d. 20mmØ PVC Male Adaptor

e. 20mmØ PVC Coupling

f. 20mmØ Locknut

g. Surface Type Reflectorized Fluorescent Luminaire with 1x20 Watts Fluorescent Tube

h. 23 Watts 3U CFL with Capsule

i. Spot Light Holder w/ 23watts Eco Par Energy Saving

j. Switch 2-Gang w/ plate (flush type), w/ Led Set, 10A, 250V

k. Switch 3-Gang w/ plate (flush type), w/ Led Set, 10A, 250V

l. Ceiling Socket with screw

m. Duplex Convenience Outlet w/ plate (flush type)

n. Perimeter post lamp with cage, globe type,

(250mmx250mm) complete assembly with

23 watts Capsulated CFL

o. 2" x 4" x 2" PVC Utility Box ( H.D.)

p. 4" x 4" PVC Junction Box ( H.D.) w/ Cover

q. #16 G.I. Tie Wire

r. PVC Solvent Cement

s. 1/4" Camridge / Mica Tube

t. 0.8mm x 19mm x 8m Polytype Electrical Tape

u. 0.8mm x 19mm x 8m Rubber Tape

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

lot

Designation No. Person No. of Days Daily Rate Amount

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

Sub-Total for A 4,781.00

1 7.00 366.00 2,562.00

1 7.00 317.00 2,219.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

Sub-Total for B -

Total (A+B) 4,781.00

0.14

Name and Specifications Quantity Unit Unit Cost Amount

pcs. 25 17.00 425.00

pcs. 12 6.00 72.00

roll 2 4,725.00 9,450.00

pcs. 35 86.00 3,010.00

pc. 1 977.00 977.00

pcs. 1 148.00 148.00

pcs. 18 5.00 90.00

pcs. 12 4.00 48.00

pc. 1 143.00 143.00

pcs. 2 31.00 62.00

pc. 1 928.00 928.00

pc. 1 107.00 107.00

sets 6 1,770.00 10,620.00

pcs. 1 107.00 107.00

kgs. 2 65.00 130.00

qrt. 0.5 460.00 230.00

pcs. 3 21.00 63.00

pcs. 2 24.00 48.00

Sub-Total for E 26,944.00

mtr. 0.5 13.00 7.00

pcs. 3 25.00 75.00

31,725.00

1,903.50

-

-

33,628.50

33,628.50

pcs. 2 102.00 204.00

Page 109: Dumalon W.S. Ground Tank_Final

PROJECT NAME :

Item No./Description: SPL - 85 SUPPLY, TESTING & INSTALLATION OF KW-HR METER, RACEWAY AND ACCESSORIES

Unit of Measurement: lot

Output per day: 1.00 lot /day

Quantity: 1.00

A. Labor

a. Skilled Worker

b. Laborer

P

B. Equipment

a. Boom Truck w/ fuel & driver

P

C.

D. Output per day = lot

E. Materials

a. 35 Footer Round Centrifugal Prestressed Concrete

Pole or Galvanized Steel Pole

Minimum Break Load : 500 kgs.

Top Diameter : 140 mm

Butt Diameter : 368 mm

b. Kiliwatthour Meter (Digital), 250 Volts, 1 Phase, Assy,

GE Class 200, 5 jaw, complete w/ Rectangular Base

c. Testing/Calibration FEE

d. 25mmØ Entrance Cap

e. 25mmØ x 3m RSC Conduit Pipe

f. 25mmØ RSC Male Adaptor

g. 25mmØ Locknut

h. 25mmØ Conduit Pipe Clamp

i. Single Wire, Secondary Rack w/ Spool Insulator

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

lot

Designation No. Person No. of Days Daily Rate Amount

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

Sub-Total for A 683.00

1 1.00 366.00 366.00

1 1.00 317.00 317.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

1 1.00 8,562.00 8,562.00

Sub-Total for B 8,562.00

Total (A+B) 9,245.00

1.00

Name and Specifications Quantity Unit Unit Cost Amount

assy. 1 8,160.00 8,160.00

lot 1 300.00 300.00

unit 1 18,207.00 18,207.00

pc. 1 8.00 8.00

pc. 1 6.00 6.00

pc. 1 41.00 41.00

pc. 1 367.00 367.00

Sub-Total for E 27,300.00

pcs. 4 7.00 28.00

pc. 1 183.00 183.00

36,545.00

2,192.70

-

-

38,737.70

38,737.70

Page 110: Dumalon W.S. Ground Tank_Final

PROJECT NAME :

Item No./Description: SPL - 86 SUPPLY & INSTALLATION OF ELECTRICAL FACILITIES FOR OPERATOR'S ROOM

Unit of Measurement: lot

Output per day: 0.14 lot /day

Quantity: 1.00

A. Labor

a. Skilled Worker

b. Laborer

P

B. Equipment

N.A.

P

C.

D. Output per day = lot

E. Materials

a. 60 Amperes Main Circuit Breaker, 1 Ø, 250 V, Panel

Board enclosed in Powder Coated Finished

Panel Box with 5 Single Phase Branches of:

1 sets - 15 Amps. Branch

4 sets - 20 Amps. Branch

b. 8.0mm2 THW Stranded Wire

c. 3.5mm2 TW Stranded Wire

d. 2.0mm2 TW Stranded Wire

e. 25mmØ Entrance Cap

f. 25mmØ x 3m PVC Conduit Pipe

g. 25mmØ x 90o PVC Long Sweep Elbow

h. 25mmØ PVC Male Adaptor

i. 25mmØ Locknut

j. 20mmØ Flexible Conduit

k. 20mmØ x 3m PVC Conduit Pipe

l. 20mmØ x 90o PVC Long Sweep Elbow

m. 20mmØ PVC Male Adaptor

n. 20mmØ PVC Coupling

o. 20mmØ Locknut

p.

q. Single Wire, Secondary Rack w/ Spool Insulator

r. Surface Type Reflectorized Fluorescent

Luminaire with 1x40W Flourescent Tube

s. 23 Watts 3U CFL with Capsule

t. 16" Ceiling Orbit Fan, Industrial Type

DETAILED UNIT PRICE ANALYSIS

lot

Designation No. Person No. of Days Daily Rate Amount

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

Sub-Total for A 4,781.00

1 7.00 366.00 2,562.00

1 7.00 317.00 2,219.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

Sub-Total for B -

Total (A+B) 4,781.00

0.14

Name and Specifications Quantity Unit Unit Cost Amount

set 1 5,766.00 5,766.00

mtrs. 60 84.00 5,040.00

pc. 1 41.00 41.00

pc. 1 131.00 131.00

mtrs. 100 32.00 3,200.00

mtrs. 75 23.00 1,725.00

pc. 1 6.00 6.00

mtrs. 48 8.00 384.00

pc. 1 26.00 26.00

pc. 1 8.00 8.00

pcs. 12 6.00 72.00

pcs. 8 5.00 40.00

pcs. 15 86.00 1,290.00

pcs. 10 17.00 170.00

pcs. 12 4.00 48.00

Welding Machine Outlet pc. 1 1,472.00 1,472.00

pcs. 2 1,132.00 2,264.00

pc. 3 148.00 444.00

pc. 1 142.00 142.00

pcs.

pc. 1 2,200.00 2,200.00

Page 111: Dumalon W.S. Ground Tank_Final

u. Switch 1-Gang w/ plate (flush type)

v. Switch 2-Gang w/ plate (flush type)

w. Ceiling Socket with screw

x. Duplex Convenience Outlet w/ plate (flush type)

y. Duplex Convenience Outlet w/ plate -

weatherproof (flush type)

z. 2" x 4" x 2" PVC Utility Box ( H.D.)

a1. 4" x 4" PVC Junction Box ( H.D.) w/ Cover

b1. #16 G.I. Tie Wire

c1. PVC Solvent Cement

d1. 1/4" Camridge / Mica Tube

e1. 0.8mm x 19mm x 8m Polytype Electrical Tape

d1. 0.8mm x 19mm x 8m Rubber Tape

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

pcs. 2 107.00 214.00

pcs. 3 31.00 93.00

pcs. 2 90.00 180.00

pcs. 1 173.00 173.00

pcs. 9 21.00 189.00

pc. 3 107.00 321.00

pcs.

qrt. 0.5 460.00 230.00

mtrs. 1 13.00 13.00

pcs. 6 24.00 144.00

kgs. 2 75.00 150.00

Sub-Total for E 26,455.00

31,236.00

1,874.16

-

-

pcs. 3 25.00 75.00

pcs. 2 102.00 204.00

33,110.16

33,110.16

Page 112: Dumalon W.S. Ground Tank_Final

PROJECT NAME :

Item No./Description: SPL - 87 SUPPLY & INST. OF ELEC. FACILITIES FOR GUARD HOUSE, SIGNAGE & PERIMETER LIGHTINGS

Unit of Measurement: lot

Output per day: 0.14 lot /day

Quantity: 1.00

A. Labor

a. Skilled Worker

b. Laborer

P

B. Equipment

N.A.

P

C.

D. Output per day = lot

E. Materials

a. 3.5mm2 TW Stranded Wire

b. 20mmØ x 3m PVC Conduit Pipe

c. 20mmØ x 90o PVC Long Sweep Elbow

d. 20mmØ PVC Male Adaptor

e. 20mmØ PVC Coupling

f. 20mmØ Locknut

g. Surface Type Reflectorized Fluorescent Luminaire with 1x20 Watts Fluorescent Tube

h. 23 Watts 3U CFL with Capsule

i. Spot Light Holder w/ 23watts Eco Par Energy Saving

j. Switch 2-Gang w/ plate (flush type), w/ Led Set, 10A, 250V

k. Switch 3-Gang w/ plate (flush type), w/ Led Set, 10A, 250V

l. Ceiling Socket with screw

m. Duplex Convenience Outlet w/ plate (flush type)

n. Perimeter post lamp with cage, globe type,

(250mmx250mm) complete assembly with

23 watts Capsulated CFL

o. 2" x 4" x 2" PVC Utility Box ( H.D.)

p. 4" x 4" PVC Junction Box ( H.D.) w/ Cover

q. #16 G.I. Tie Wire

r. PVC Solvent Cement

s. 1/4" Camridge / Mica Tube

t. 0.8mm x 19mm x 8m Polytype Electrical Tape

u. 0.8mm x 19mm x 8m Rubber Tape

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

lot

Designation No. Person No. of Days Daily Rate Amount

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF DUMALON-ZAMBALES-BALUNO-CAPISAN-

MALAGUTAY-SAN ROQUE-CALARIAN-CAWIT-SINUNUC & MAASIN WATER SYSTEM PROJECT

Sub-Total for A 4,781.00

1 7.00 366.00 2,562.00

1 7.00 317.00 2,219.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

Sub-Total for B -

Total (A+B) 4,781.00

0.14

Name and Specifications Quantity Unit Unit Cost Amount

pcs. 25 17.00 425.00

pcs. 12 6.00 72.00

roll 2 4,725.00 9,450.00

pcs. 35 86.00 3,010.00

pc. 1 977.00 977.00

pcs. 1 148.00 148.00

pcs. 18 5.00 90.00

pcs. 12 4.00 48.00

pc. 1 143.00 143.00

pcs. 2 31.00 62.00

pc. 1 928.00 928.00

pc. 1 107.00 107.00

sets 6 1,770.00 10,620.00

pcs. 1 107.00 107.00

kgs. 2 65.00 130.00

qrt. 0.5 460.00 230.00

pcs. 3 21.00 63.00

pcs. 2 24.00 48.00

Sub-Total for E 26,944.00

mtr. 0.5 13.00 7.00

pcs. 3 25.00 75.00

31,725.00

1,903.50

-

-

33,628.50

33,628.50

pcs. 2 102.00 204.00

Page 113: Dumalon W.S. Ground Tank_Final

PROJECT NAME:

Item No./Description: ELECTRICAL WORKS (BALUNO & BANDERA)

Unit of Measurement:

Output per day: lot/day

Quantity:

A. Labor

a. Skilled Worker

b. Laborer

P

B. Equipment

N.A.

P

C.

D. Output per hour = lot/day

E. Materials

SUPPLY, TESTING & INSTALLATION OF KW-HR METER, RACEWAY AND ACCESSORIES

Kiliwatthour Meter (Digital), 250 Volts, Single Phase, Assembly,

GE Class 200, 5 jaw, complete w/ Rectangular Base

Testing/Calibration FEE

25mmØ Entrance Cap

25mmØ x 3m RSC Conduit Pipe

25mmØ RSC Male Adaptor

25mmØ Locknut

25mmØ Conduit Pipe Clamp

Single Wire, Secondary Rack w/ Spool Insulator

SUPPLY & INSTALLATION OF ELECTRICAL FACILITIES FOR OPERATORS ROOM

60 Amperes Main Circuit Breaker, Single Phase, 250 Volts, Panel

Board enclosed in Powder Coated Finished Panel Box

with 5 Single Phase Branches of:

1 sets - 15 Amps. Branch

4 sets - 20 Amps. Branch

8.0mm2 THW Stranded Wire

3.5mm2 TW Stranded Wire

2.0mm2 TW Stranded Wire

25mmØ Entrance Cap

25mmØ x 3m PVC Conduit Pipe

25mmØ x 90o PVC Long Sweep Elbow

25mmØ PVC Male Adaptor

25mmØ Locknut

20mmØ Flexible Conduit

20mmØ x 3m PVC Conduit Pipe

20mmØ x 90o PVC Long Sweep Elbow

20mmØ PVC Male Adaptor

20mmØ PVC Coupling

20mmØ Locknut

Single Wire, Secondary Rack w/ Spool Insulator

23 Watts 3U CFL with Capsule

18" Ceiling Orbit Fan, Industrial Type

Switch 1-Gang w/ plate (flush type), w/ Led Set, 10A, 250V

Designation No. PersonNo. of DaysDaily Rate Amount

DETAILED UNIT PRICE ANALYSIS

PROPOSED PASOBOLONG GROUND TANK, ZAMBOANGA CITY

SPL - 82

lot

0.09

2.00 lots

Sub-Total for A 15,026.00

1 22.00 366.00 8,052.00

1 22.00 317.00 6,974.00

Name and Capacity No. of UnitsNo. of DaysDaily Rate Amount

Sub-Total for B -

Total (A+B) 15,026.00

0.09

Name and Specifications Quantity Unit Unit Cost Amount

1

1

1 assy. 8,160.00 8,160.00

1

60.00

41.00

367.00

8.00

6.00

28.00

142.00

41.00

142.00

1

1

4

1

pc.

pc.

5,766.00

92.00

75.00

1.00

1.00

12.00

8.00

12.00

1.00

2.00

3.00

1.00

1.00

1.00

48.00

15.00

10.00

pc.

mtrs.

pcs.

pc.

pc.

pc.

set

mtrs.

mtrs.

mtrs.

pc.

1.00

1.00

pcs.

pc.

pc.

5,477.00

71.00

pcs.

pcs.

pcs.

pcs.

pc.

pcs.

17.00

6.00

5.00

4.00

142.00

5,766.00

5,040.00

2,944.00

1,132.00

148.00

86.00

41.00

131.00

26.00

8.00

6.00

8.00

84.00

32.00

23.00

142.00

2,264.00

1,725.00

41.00

131.00

26.00

8.00

6.00

444.00

5,477.00

71.00

384.00

1,290.00

170.00

72.00

40.00

48.00

Surface Type Reflectorized/Mirrorized Fluorescent Luminaire with 1x40

Watts Fluorescent Tube

pc.

pc.

pc.

pc.

1 lot 100.00 100.00

367.00

8.00

6.00

7.00

Page 114: Dumalon W.S. Ground Tank_Final

Switch 2-Gang w/ plate (flush type), w/ Led Set, 10A, 250V

Ceiling Socket with screw

Duplex Convenience Outlet w/ plate (flush type)

Duplex Convenience Outlet w/ plate - weatherproof (flush type)

2" x 4" x 2" PVC Utility Box ( H.D.)

4" x 4" PVC Junction Box ( H.D.) w/ Cover

#16 G.I. Tie Wire

PVC Solvent Cement

1/4" Camridge / Mica Tube

0.8mm x 19mm x 8m Polytype Electrical Tape

0.8mm x 19mm x 8m Rubber Tape

SUPPLY & INSTALLATION OF ELECTRICAL FACILITIES FOR GUARD HOUSE & CHLORINATOR ROOM

35W E27 CFL Weather Proof Street Light

3.5mm2 TW Stranded Wire

20mmØ Flexible Conduit

20mmØ x 3m PVC Conduit Pipe

20mmØ x 90o PVC Long Sweep Elbow

20mmØ PVC Male Adaptor

20mmØ PVC Coupling

20mmØ Locknut

23 Watts 3U CFL with Capsule

23 Watts PAR 38 Floodlight CFL bulb with Par Lamp Holder

Switch 1-Gang w/ plate (flush type), w/ Led Set, 10A, 250V

Switch 2-Gang w/ plate (flush type), w/ Led Set, 10A, 250V

Switch 3-Gang w/ plate (flush type), w/ Led Set, 10A, 250V

Ceiling Socket with screw

Duplex Convenience Outlet w/ plate (flush type)

2" x 4" x 2" PVC Utility Box ( H.D.)

4" x 4" PVC Junction Box ( H.D.) w/ Cover

#16 G.I. Tie Wire

PVC Solvent Cement

1/4" Camridge / Mica Tube

0.8mm x 19mm x 8m Polytype Electrical Tape

0.8mm x 19mm x 8m Rubber Tape

SUPPLY & INSTALLATION OF ELECTRICAL FACILITIES FOR SIGNAGE AND PERIMETER LIGHTINGS

3.5mm2 TW Stranded Wire

20mmØ x 3m PVC Conduit Pipe

20mmØ x 90o PVC Long Sweep Elbow

20mmØ PVC Male Adaptor

20mmØ PVC Coupling

20mmØ Locknut

Perimeter post lamp with cage, globe type, (250mmx250mm)

complete assembly with 23 watts Capsulated CFL

4" x 4" PVC Junction Box ( H.D.) w/ Cover

#16 G.I. Tie Wire

PVC Solvent Cement

1/4" Camridge / Mica Tube

0.8mm x 19mm x 8m Polytype Electrical Tape

0.8mm x 19mm x 8m Rubber Tape

P

F. Direct Cost (C+E)

G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s 2011

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011

J. Total Cost

k. Total Unit Cost

93,795.69

46,897.85

Sub-Total for E 73,460.50

1.00 qrt. 451.00 451.00

2.00 mtrs. 13.00 26.00

5.00

2.00

pc.

pc.

125.00

204.00 102.00

88,486.50

5,309.19

-

-

3.00 kgs. 75.00 225.00

1.00

2.00

7.00

9.00

3.00

1.00

1.00

5.00

2.00

3.00

3.00

pcs.

pcs.

pcs.

107.00

31.00

214.00

4,725.00

93.00

321.00

173.00

147.00

216.00

225.00

107.00

173.00 pc.

pcs.

pcs.

kgs.

21.00

24.00

75.00

460.00

16.00

15.00

10.00

12.00

8.00

12.00

460.00

13.00

125.00

204.00

1.00

1.00

500.00

4,725.00

13.00

25.00

102.00

pcs.

pcs.

qrt.

mtrs.

500.00

13.00

2.00

1.00

1.00

3.00

1.00

1.00

1.00

1.00

6.00

pc.

roll

pcs.

pcs.

pcs.

pcs.

pcs.

pcs.

pc.

35.00

8.00

36.00

18.00

12.00

0.50

5.00

2.00

2.00

4.00

2.00

5.00

128.00

1,290.00

170.00

72.00

40.00

48.00

rolls

pcs.

pcs.

pcs.

pcs.

kgs.

qrt.

mtr.

pcs.

pc.

pc.

pc.

pc.

pcs.

24.00

75.00

460.00

8.00

86.00

17.00

6.00

5.00

4.00

977.00

148.00

928.00

86.00

977.00

444.00

928.00

71.00

107.00

143.00

71.00

107.00

143.00

10,620.00

90.00

3,010.00

136.00

25.00

102.00

13.00

124.00

214.00

105.00

107.00

21.00

312.00

150.00

460.00

31.00

6.50

125.00

204.00

9,450.00 4,725.00

384.00

4.00

1,770.00

24.00

25.00

pcs.

Surface Type Reflectorized/Mirrorized Fluorescent Luminaire with 1x20

Watts Fluorescent Tube

16.00

48.00

216.00

pcs.

pcs.

pcs.

pcs.

sets

pcs.

pcs.

17.00

6.00

5.00

Page 115: Dumalon W.S. Ground Tank_Final

Project : CONST. OF TWO UNITS - THREE HUNDRED (300.00) CUBIC RESERVOIR TANK AT SITIO BANDERA, BRGY. DULIAN & AT BRY. BALUNO

Service Area : Dumalon, Zambales, Baluno, Capisan, Malagutay, San Roque, Calarian, Cawit, Sinunuc & Maasin

Location : Sitio Bandera, Brgy. Dulian & Brgy. Baluno, Zamboanga City

Scope of Work :

A. NON ENGINEERING BASIC COST

I. MATERIAL TESTING

II. BUILDING PERMIT FEE

III. CONST. OF TWO (2.00) UNITS TEMPORARY FACILITY

IV. SUPERVISION

B. ENGINEERING BASIC COST1. CONSTRUCTION OF 300 CU.M. GROUND RESERVOIR AT SITIO BANDERA, DULIAN, Z.C.

I. MOBILIZATION/DEMOBILIZATION/HAULING OF MATERIAL

II. CONSTRUCTION OF 300.00 CU.M. GROUND TANK

1. CLEARING/ LAYOUT & EXCAVATION WORKS (262.00 Cu.M.)

2. SCAFFOLDING & FORM WORKS

3. CONCRETE WORKS (148.20 Cu.M.)

4. REINFORCED STEEL WORKS (23,329.60 KGS.)

5. MASONRY WORKS (762.00 Sq.M.)

6. STEEL WORKS

7. DISINFECTION/LEAKAGE TEST & GROUTING LEAK

8. SUPPLY & INST. OF GATE VALVES, DIFFERENTIAL FLOAT CONTROL VALVE & APPURTENANCES

9. SUPPLY & INSTALLATION OF TWO UNITS - 100MMØ FLOW METER & CONST OF CONCRETE VALVE BOX

10. PAINTING WORKS (223.00 Sq.M.)

11. WATER PROOFING WORKS FOR TOP SLAB

12. SUPPLY & INST. OF 40GPD HYPOCHLORINATOR

III. CONST. OF CONCRETE PERIMETER FENCE

1. CLEARING/LAYOUTING & EXCAVATION WORKS

2. CONCRETING WORKS (14.80 Cu.M.)

3. REINFORCED STEEL WORKS (1,940.10 KGS.)

4. MASONRY WORKS:

5. FORMS & SCAFFOLDING WORKS:

6. STEEL WORKS:

7. PAINTING WORKS

IV. CONSTRUCTION OF (12.40 SQ. MTR.) OPERATOR'S ROOM

1. EXCAVATION WORKS (3.98 Cu.M.)

2. CONCRETE WORKS (8.50 Cu M.)

3. REINFORCED STEEL WORKS (1,093.10 KGS.)

4. MASONRY WORKS

5. CARPENTRY WORKS

6. SCAFFOLDING & FORM WORKS

7. PLUMBING WORKS

8. GLASS WORKS (LUMP SUM)

9. STEEL WORKS (WINDOW GRILLES)

10. WATER PROOFING WORKS (LUMP SUM)

11. PAINTING WORKS (120.00 Sq. M.)

12. CONSTRUCTION OF SEPTIC VAULT (SEALED)

V. CONSTRUCTION OF GUARD HOUSE (2.89 SQ. M.)

1. EXCAVATION WORKS (1.60 CU.M.)

2. CONCRETE WORKS (3.00 Cu.M.)

3. REINFORCED STEEL WORKS ( 660.00 KGS.)

4. MASONRY WORKS

5. TILE WORKS (2.56 Sq. M.)

6. FORM & SCAFFOLDING WORKS

7. CARPENTRY WORKS

8. STEEL WORKS

9 GLASS WORKS (LUMP SUM)

10. PLUMBING WORKS

11. WATERPROOFING WORKS (LUMP SUM)

12. PAINTING WORKS (48.00 Sq. M.)

VI. CONSTRUCTION OF (2.73 SQ. MTR.) CHLORINE ROOM

1. CONCRETE & REINFORCED STEEL WORKS

2. MASONRY WORKS

3. CARPENTRY WORKS

4. PAINTING WORKS

5. WATER PROOFING WORKS (LUMP SUM)

VII. CONSTRUCTION OF 200MM Ø & 300MM Ø RCCP DRAINAGE SYSTEM

VIII. CONSTRUCTION OF CONCRETE CATWALK/DRIVE WAY

IX. LANDSCAPING WORKS

X. ELECTRICAL WORKS

2. CONSTRUCTION OF 300 CU.M. GROUND RESERVOIR AT BALUNO, Z.C.I. MOBILIZATION/DEMOBILIZATION/HAULING OF MATERIAL

II. CONSTRUCTION OF 300.00 CU.M. GROUND TANK

1. CLEARING & EXCAVATION WORKS (262.00 Cu.M.)

2. SCAFFOLDING & FORM WORKS

Republic of the Philippines

ZAMBOANGA CITY WATER DISTRICT

Pilar Street, Zamboanga City

Pricelist as of February 2013 115 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 116: Dumalon W.S. Ground Tank_Final

3. CONCRETE WORKS (148.20 Cu.M.)

4. REINFORCED STEEL WORKS (23,329.60 KGS.)

5. MASONRY WORKS (762.00 Sq.M.)

6. STEEL WORKS

7. DISINFECTION/LEAKAGE TEST & GROUTING LEAK

8. SUPPLY & INST. OF GATE VALVES, DIFFERENTIAL FLOAT CONTROL VALVE & APPURTENANCES

9. SUPPLY & INSTALLATION OF TWO UNITS - 100MMØ FLOW METER & CONST OF CONCRETE VALVE BOX

10. PAINTING WORKS (223.00 Sq.M.)

11. WATER PROOFING WORKS FOR TOP SLAB

12. SUPPLY & INST. OF 40GPD HYPOCHLORINATOR

III. CONST. OF CONCRETE PERIMETER FENCE

1. CLEARING/LAYOUTING & EXCAVATION WORKS

2. CONCRETING WORKS (14.80 Cu.M.)

3. REINFORCED STEEL WORKS (1,940.10 KGS.)

4. MASONRY WORKS:

5. FORMS & SCAFFOLDING WORKS:

6. STEEL WORKS:

7. PAINTING WORKS

8. SIGNAGE WITH STAND & FRAME

IV. CONSTRUCTION OF (12.40 SQ. MTR.) OPERATOR'S ROOM

1. EXCAVATION WORKS (3.98 Cu.M.)

2. CONCRETE WORKS (8.50 Cu M.)

3. REINFORCED STEEL WORKS (1,093.10 KGS.)

4. MASONRY WORKS

5. CARPENTRY WORKS

6. SCAFFOLDING & FORM WORKS

7. PLUMBING WORKS

8. GLASS WORKS (LUMP SUM)

9. STEEL WORKS (WINDOW GRILLES)

10. WATER PROOFING WORKS (LUMP SUM)

11. PAINTING WORKS (120.00 Sq. M.)

12. CONSTRUCTION OF SEPTIC VAULT (SEALED)

V. CONSTRUCTION OF GUARD HOUSE (2.89 SQ. M.)

1. EXCAVATION WORKS (1.60 CU.M.)

2. CONCRETE WORKS (3.00 Cu.M.)

3. REINFORCED STEEL WORKS ( 660.00 KGS.)

4. MASONRY WORKS

5. TILE WORKS (2.56 Sq. M.)

6. FORM & SCAFFOLDING WORKS

7. CARPENTRY WORKS

8. STEEL WORKS

9 GLASS WORKS (LUMP SUM)

10. PLUMBING WORKS

11. WATERPROOFING WORKS (LUMP SUM)

12. PAINTING WORKS (48.00 Sq. M.)

VI. CONSTRUCTION OF (2.73 SQ. MTR.) CHLORINE ROOM

1. CONCRETE & REINFORCED STEEL WORKS

2. MASONRY WORKS

3. CARPENTRY WORKS

4. PAINTING WORKS

5. WATER PROOFING WORKS (LUMP SUM)

VII. CONSTRUCTION OF 200MM Ø & 300MM Ø RCCP DRAINAGE SYSTEM

VIII. CONSTRUCTION OF CONCRETE CATWALK/DRIVE WAY

X. LANDSCAPING WORKS

XI. ELECTRICAL WORKS

TOTAL PROJECT COST: 21,413,665.80Php

A. NON ENGINEERING BASIC COST

I. MATERIAL TESTING

1. ITEM 404 REINFORCED STEEL (Quality Test for each size)

10mmØ Deformed Steel Bar Grade 33 4 tests 600.00 2,400.00

12mmØ Deformed Steel Bar Grade 33 4 tests 600.00 2,400.00

16mmØ Deformed Steel Bar Grade 33 4 tests 600.00 2,400.00

20mmØ Deformed Steel Bar Grade 40 4 tests 600.00 2,400.00

25mmØ Deformed Steel Bar Grade 40 4 tests 600.00 2,400.00

Pricelist as of February 2013 116 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 117: Dumalon W.S. Ground Tank_Final

2. ITEM 405 STRUCTURAL CONCRETEPortland Cement (Quality Test) 4 tests 1,800.00 7,200.00

Fine Aggregates (Complete Test) 4 tests 1,500.00 6,000.00

Course Aggregates (Complete Test) 4 tests 1,500.00 6,000.00

100mm Concrete Hollow Block (Compressive Strength & Moisture Content) 4 tests 400.00 1,600.00

150mm Concrete Hollow Block (Compressive Strength & Moisture Content) 4 tests 400.00 1,600.00

Compressive Strength Test:

for Foundations 10 tests 250.00 2,500.00

for Column 10 tests 250.00 2,500.00

for slab 8 tests 250.00 2,000.00

for beam 8 tests 250.00 2,000.00

TOTAL COST OF MATERIAL TESTING

II. BUILDING PERMIT FEE 2 lot 15,000.00 30,000.00

TOTAL COST OF BUILDING PERMIT FEE

III. CONST. OF TWO (2.00) UNITS TEMPORARY FACILITY

a. Materials:

30 pcs. - 2" x 4" x 10' Coco Lumber 133 bd.ft. 20.00 2,660.00

36 pcs. - 2" x 3" x 10' Coco Lumber 180 bd.ft. 20.00 3,600.00

40 pcs. - 2" x 2" x 10' Coco Lumber 133 bd.ft. 20.00 2,660.00

* 12mm thk x 1.20m x 2.40m Ordinary Plywood 20 shts. 975.00 19,500.00

Gauge 26 x 1.80m Length Corrugated G.I. Roofing Sheets 24 shts. 221.00 5,304.00

2" C.W. Umbrella Roofing Nails 1 kg. 70.00 70.00

2" C.W. Nail 1 kg. 65.00 65.00

3" C.W. Nail 1 kg. 70.00 70.00

4" C.W. Nail 1 kg. 70.00 70.00

b. Labor:

2 - Skilled Worker 2 days 366.00 1,464.00

2 - Laborer 2 days 317.00 1,268.00

TOTAL COST OF CONSTRUCTION OF TEMP. FACILITY

IV. SUPERVISION

2 - Engineering Assistant 240 days 524.00 251,520.00

TOTAL COST OF SUPERVISION

B. ENGINEERING BASIC COST

1. CONSTRUCTION OF 300 CU.M. GROUND RESERVOIR AT SITIO BANDERA, DULIAN, Z.C.

I. MOBILIZATION/DEMOBILIZATION/HAULING OF MATERIAL

1. MOBILIZATION/DEMOBILIZATION 1 lot 50,000.00 50,000.00

2. HAULING OF MATERIALS

a. Labor:

4 - Laborer 30 days 317.00 38,040.00

b. Equipment Rental/Fuel

1 - Unit Hauling Truck (w/ Operator & Fuel) 30 days 9,600.00 288,000.00

TOTAL COST OF MOBILIZATION/DEMOBILIZATION/HAULING OF MATERIAL

II. CONSTRUCTION OF 300.00 CU.M. GROUND TANK

1. CLEARING/ LAYOUT & EXCAVATION WORKS (262.00 Cu.M.)

a. Labors:

4 -Contractual Laborer 5 days 366.00 7,320.00

b. Equipment/Fuel:

1 - Unit Backhoe (w/ Fuel & Operator) 5 days 8,000.00 40,000.00

1 - Unit Water Pump (w/ Fuel) 2 days 600.00 1,200.00

1 - Unit Powersaw (w/ Operator & Fuel) 2 days 2,000.00 4,000.00

TOTAL COST OF EXCAVATION WORKS

2. SCAFFOLDING & FORM WORKS

a. Materials:

800 - pcs. 2" x 2" x 10' Coco Lumber 2667 bd.ft. 20.00 53,340.00

600 - pcs. 2" x 3" x 10' Coco Lumber 3000 bd.ft. 20.00 60,000.00

400 - pcs. 2" x 4" x 10' Coco Lumber 2667 bd.ft. 20.00 53,340.00

12mmThk. x 1.20m. x 2.40m. Ordinary Plywood 140 shts. 975.00 136,500.00

4" C.W. Nail 50 kgs. 70.00 3,500.00

3" C.W. Nail 40 kgs. 70.00 2,800.00

Pricelist as of February 2013 117 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 118: Dumalon W.S. Ground Tank_Final

1-1/2" C.W. Nail 30 kgs. 65.00 1,950.00

b. Labors:

4 - Carpenter 30 days 366.00 43,920.00

8 - Laborer 30 days 317.00 76,080.00

TOTAL COST OF SCAFFOLDING & FORM WORKS

3. CONCRETE WORKS (148.20 Cu.M.)

a. Materials:

3.1. Lean Concrete (50mm Thk x 105.00 Sq.M.)

Portland Cement 48 bags 245.00 11,760.00

Washed Sand 4.5 cu.m. 1,000.00 4,500.00

3.2. Footing (F-3) (4 Units):

Portland Cement 30 bags 245.00 7,350.00

Washed Sand 1.25 cu.m. 1,000.00 1,250.00

Gravel (G1) 2 cu.m. 1,000.00 2,000.00

150mm Boulders 1.5 cu.m. 1,000.00 1,500.00

Concrete Waterproofing Compound (900g) 30 packs 30.00 900.00

3.3. Footing (F-4) (6 Units):

Portland Cement 48 bags 245.00 11,760.00

Washed Sand 2 cu.m. 1,000.00 2,000.00

Gravel (G1) 3.25 cu.m. 1,000.00 3,250.00

150mm Boulders 2.5 cu.m. 1,000.00 2,500.00

Concrete Waterproofing Compound (900g) 48 packs 30.00 1,440.00

3.4. Footing (F-1A) (1 Unit):

Portland Cement 3 bags 245.00 735.00

Washed Sand 0.125 cu.m. 1,000.00 125.00

Gravel (G1) 0.25 cu.m. 1,000.00 250.00

150mm Boulders 0.25 cu.m. 850.00 213.00

3.5. Column (C-3) (4 Units):

Portland Cement 30 bags 245.00 7,350.00

Washed Sand 1.25 cu.m. 1,000.00 1,250.00

Gravel (G1) 2 cu.m. 1,000.00 2,000.00

Concrete Addmix (150g) 30 packs 35.00 1,050.00

Concrete Waterproofing Compound (900g) 30 packs 30.00 900.00

3.6. Column (C-4) (6 Units):

Portland Cement 50 bags 245.00 12,250.00

Washed Sand 2.25 cu.m. 1,000.00 2,250.00

Gravel (G1) 3.25 cu.m. 1,000.00 3,250.00

Concrete Addmix (150g) 50 packs 35.00 1,750.00

Concrete Waterproofing Compound (900g) 50 packs 30.00 1,500.00

3.7. Column (C-1A) (1 Unit):

Portland Cement 3 bags 245.00 735.00

Washed Sand 0.125 cu.m. 1,000.00 125.00

Gravel (G1) 0.25 cu.m. 1,000.00 250.00

3.8. Tie Beam (TB) (2 Units):

Portland Cement 19 bags 245.00 4,655.00

Washed Sand 0.75 cu.m. 1,000.00 750.00

Gravel (G1) 1.25 cu.m. 1,000.00 1,250.00

Concrete Addmix (150g) 19 packs 35.00 665.00

Concrete Waterproofing Compound (900g) 19 packs 30.00 570.00

3.9. Beam (RCB1, RCB2 & RCB3)

Portland Cement 17 bags 245.00 4,165.00

Washed Sand 0.75 cu.m. 1,000.00 750.00

Gravel (G1) 1.25 cu.m. 1,000.00 1,250.00

Concrete Addmix (150g) 17 packs 35.00 595.00

3.10. Wall Footing (L=51.06 m):

Portland Cement 163 bags 245.00 39,935.00

Washed Sand 7 cu.m. 1,000.00 7,000.00

Gravel (G1) 10.75 cu.m. 1,000.00 10,750.00

Concrete Addmix (150g) 163 packs 35.00 5,705.00

Concrete Waterproofing Compound (900g) 163 packs 30.00 4,890.00

3.11. Bottom Slab

Washed Sand (for Ground Tank Bottom Slab Envelope) 30 cu.m. 1,000.00 30,000.00

Portland Cement 131 bags 245.00 32,095.00

Washed Sand 5.75 cu.m. 1,000.00 5,750.00

Gravel (G1) 8.5 cu.m. 1,000.00 8,500.00

Concrete Addmix (150g) 131 packs 35.00 4,585.00

Concrete Waterproofing Compound (900g) 131 packs 30.00 3,930.00

Pricelist as of February 2013 118 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 119: Dumalon W.S. Ground Tank_Final

3.12. Top Slab

Portland Cement 155 bags 245.00 37,975.00

Washed Sand 7 cu.m. 1,000.00 7,000.00

Gravel (G1) 10.25 cu.m. 1,000.00 10,250.00

Concrete Addmix (150g) 155 packs 35.00 5,425.00

Concrete Waterproofing Compound (900g) 155 packs 30.00 4,650.00

3.13. Stair

Portland Cement 20 bags 245.00 4,900.00

Washed Sand 0.75 cu.m. 1,000.00 750.00

Gravel (G1) 1.25 cu.m. 1,000.00 1,250.00

Pricelist as of February 2013 119 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 120: Dumalon W.S. Ground Tank_Final

3.14. Wall (L = 51.06m)

Portland Cement 576 bags 245.00 141,120.00

Washed Sand 25.5 cu.m. 1,000.00 25,500.00

Gravel (G1) 38 cu.m. 1,000.00 38,000.00

Concrete Waterproofing Compound (900g) 576 packs 30.00 17,280.00

Concrete Addmix (150g) 576 packs 35.00 20,160.00

200mm Water Stop 200 ln.mtr. 380.00 76,000.00

3.15. Junction Box

Portland Cement 21 bags 245.00 5,145.00

Washed Sand 0.75 cu.m. 1,000.00 750.00

Gravel (G1) 1.25 cu.m. 1,000.00 1,250.00

Concrete Waterproofing Compound (900g) 18 packs 30.00 540.00

b. Labors:

4 - Mason 32 days 366.00 46,848.00

20 - Contractual Laborers 32 days 317.00 202,880.00

c. Equipment Rental:

1 - Unit Water Pump (w/ Fuel) 16 days 600.00 9,600.00

2 - Units One - Bagger Mixer (w/ Fuel) 32 days 1,500.00 96,000.00

2 - Concrete Vibrator (w/ Fuel) 32 days 1,000.00 64,000.00

TOTAL COST OF CONCRETE WORKS

4. REINFORCED STEEL WORKS (23,329.60 KGS.)

a. Materials:

4.1. Footing (F-1) (4- Units)

25mm

Ø x 6.00m. Deformed Reinf. Steel Bar 40 pcs. 1,045.00 41,800.00

#16 G.I. Tie Wire 3 kgs. 75.00 225.00

4.2. Footing (F-2) (6- Units)

25mm

Ø x 6.00m. Deformed Reinf. Steel Bar 28 pcs. 1,045.00 29,260.00

#16 G.I. Tie Wire 2 kgs. 75.00 150.00

4.3. Footing (F-3) (1- Unit)

16mm

Ø x 6.00m. Deformed Reinf. Steel Bar 2 pcs. 480.00 960.00

#16 G.I. Tie Wire 1 kg. 75.00 75.00

4.4. Tie Beam (TB) (3 - Units)

25mm

Ø x 6.00m. Deformed Reinf. Steel Bar 14 pcs. 1,045.00 14,630.00

10mm

Ø x 6.00m. Deformed Reinf. Steel Bar 24 pcs. 190.00 4,560.00

#16 G.I. Tie Wire 3 kgs. 75.00 225.00

4.5. Column (C - 1) (4 Units)

25mm

Ø x 6.00m. Deformed Reinf. Steel Bar 48 pcs. 1,045.00 50,160.00

10mm

Ø x 6.00m. Deformed Reinf. Steel Bar 75 pcs. 190.00 14,250.00

#16 G.I. Tie Wire 11 kgs. 75.00 825.00

4.6. Column (C - 2) (6 Units)

25mm

Ø x 6.00m. Deformed Reinf. Steel Bar 48 pcs. 1,045.00 50,160.00

10mm

Ø x 6.00m. Deformed Reinf. Steel Bar 56 pcs. 190.00 10,640.00

#16 G.I. Tie Wire 8 kgs. 75.00 600.00

4.7. Column(C-3) (1- Unit)

16mm

Ø x 6.00m. Deformed Reinf. Steel Bar 2 pcs. 480.00 960.00

10mm

Ø x 6.00m. Deformed Reinf. Steel Bar 2 pcs. 165.00 330.00

#16 G.I. Tie Wire 1 kg. 75.00 75.00

4.8. Wall Footing

25mm

Ø x 6.00m. Deformed Reinf. Steel Bar 44 pcs. 1,045.00 45,980.00

20mm

Ø x 6.00m. Deformed Reinf. Steel Bar 46 pcs. 682.00 31,372.00

#16 G.I. Tie Wire 8 kgs. 75.00 600.00

4.9. Bottom Slab

20mm

Ø x 6.00m. Deformed Reinf. Steel Bar 5 pcs. 682.00 3,410.00

16mm

Ø x 7.50m. Deformed Reinf. Steel Bar 156 pcs. 550.00 85,800.00

16mm

Ø x 6.00m. Deformed Reinf. Steel Bar 70 pcs. 480.00 33,600.00

#16 G.I. Tie Wire 35 kgs. 75.00 2,625.00

4.10. Top Slab

12mm

Ø x 6.00m. Deformed Reinf. Steel Bar 210 pcs. 270.00 56,700.00

#16 G.I. Tie Wire 35 kgs. 75.00 2,625.00

4.11. Stair & Stair Foundation

16mm

Ø x 6.00m. Deformed Reinf. Steel Bar 26 pcs. 480.00 12,480.00

12mm

Ø x 6.00m. Deformed Reinf. Steel Bar 9 pcs. 270.00 2,430.00

10mm

Ø x 6.00m. Deformed Reinf. Steel Bar 53 pcs. 190.00 10,070.00

#16 G.I. Tie Wire 4 kgs. 75.00 300.00

4.12. Beam (RCB 1)

Pricelist as of February 2013 120 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 121: Dumalon W.S. Ground Tank_Final

20mm

Ø x 6.00m. Deformed Reinf. Steel Bar 18 pcs. 682.00 12,276.00

10mm

Ø x 6.00m. Deformed Reinf. Steel Bar 19 pcs. 190.00 3,610.00

#16 G.I. Tie Wire 4 kgs. 75.00 300.00

4.13. Beam (RCB 2 & RCB 3) :

20mm

Ø x 6.00m. Deformed Reinf. Steel Bar 8 pcs. 682.00 5,456.00

10mm

Ø x 6.00m. Deformed Reinf. Steel Bar 10 pcs. 190.00 1,900.00

#16 G.I. Tie Wire 2 kgs. 75.00 150.00

Pricelist as of February 2013 121 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 122: Dumalon W.S. Ground Tank_Final

4.14. Wall (L=44.00m)

25mm

Ø x 6.00m. Deformed Reinf. Steel Bar 301 pcs. 1,045.00 314,545.00

20mm

Ø x 6.00m. Deformed Reinf. Steel Bar 175 pcs. 682.00 119,350.00

16mm

Ø x 6.00m. Deformed Reinf. Steel Bar 365 pcs. 480.00 175,200.00

12mm

Ø x 7.50m. Deformed Reinf. Steel Bar 26 pcs. 320.00 8,320.00

12mm

Ø x 6.00m. Deformed Reinf. Steel Bar 26 pcs. 270.00 7,020.00

#16 G.I. Tie Wire 35 kgs. 75.00 2,625.00

4.15. Junction Box

10mm

Ø x 6.00m. Plain Round Bars 1 pc. 190.00 190.00

16mm

Ø x 6.00m. Deformed Reinf. Steel Bar 3 pcs. 480.00 1,440.00

12mm

Ø x 6.00m. Deformed Reinf. Steel Bar 24 pcs. 270.00 6,480.00

#16 G.I. Tie Wire 3 kgs. 65.00 195.00

Hacksaw Blade 80 pcs. 75.00 6,000.00

b. Labors:

4 - Steel Man 38 days 366.00 55,632.00

4 - Contractual Laborers 38 days 317.00 48,184.00

c. Equipment:

Bar Bender 38 days 300.00 11,400.00

Bar Cutter 38 days 300.00 11,400.00

TOTAL COST OF REINFORCED STEEL WORKS

5. MASONRY WORKS (762.00 Sq.M.)

a. Materials:

Portland Cement 90 bags 245.00 22,050.00

Fine Sand (For Plastering) 8.75 cu.m. 1,400.00 12,250.00

b. Labors:

2 - Mason 22 days 366.00 16,104.00

2 - Contractual Laborers 22 days 317.00 13,948.00

TOTAL COST OF MASONRY WORKS

6. STEEL WORKS

a. Materials:

6.1. Manhole Cover w/ Steel Ladder (3- Units)

6mm Thk. x 50mm x 6.0m Stainless Steel Flat Bar 4 pcs. 9,000.00 36,000.00

6mm Thk. x 50mm x 50mm x 6.00m Stainless Angle Bar 2 pcs. 16,000.00 32,000.00

16mmØ x 100mm Stainless Steel L-Type Anchor Bolt w/ Nuts & Washers 18 pcs. 150.00 2,700.00

16mmØ x 6.0m Stainless Plain Round Bar 4 pcs. 12,400.00 49,600.00

1.20m x 2.40m x Ga. No. 16 Stainless Plain Sheet 2 shts. 3,800.00 7,600.00

10mmØ x 6.0m M.S. Plain Round Bar 1 pc. 190.00 190.00

Hacksaw Blade 8 pcs. 65.00 520.00

Welding Rod (6011) 10 kgs. 160.00 1,600.00

Welding Rod (Stainless) 5 kgs. 580.00 2,900.00

6.2. Hand Rail:

50mmØ x 6.0m G.I. Pipe (ASTM A-53 90A Heavy Gauge Standard) 14 pcs. 1,720.00 24,080.00

16mm x 16mm x 6.00m MS Square Bar 50 pcs. 781.00 39,050.00

Hacksaw Blade 20 pcs. 65.00 1,300.00

Welding Rod (6011) 20 kgs. 160.00 3,200.00

Hacksaw Blade 30 pcs. 65.00 1,950.00

6.3. Junction Box

6mm Thk. x 50mm x 6.0m MS Flat Bar 1 pc. 880.00 880.00

16mmØ x 6.0m MS Plain Round Bar 1 pc. 495.00 495.00

6mm Thk. x 50mm x 50mm x 6.0m MS Angle Bar 1 pc. 1,500.00 1,500.00

16mmØ x 100mm Stainless Steel (L-Type) Bolt w/ Nut & Washer 6 pcs. 150.00 900.00

Hacksaw Blade 4 pcs. 65.00 260.00

Welding Rod (6011) 2 kgs. 160.00 320.00

b. Labors:

2 - Welder 30 days 394.00 23,640.00

2 - Contractual Laborers 30 days 317.00 19,020.00

c. Equipment:

1 - Unit Welding Machine 30 days 2,200.00 66,000.00

1 - Unit Disk Grinder 30 days 400.00 12,000.00

4" Grinding Wheel 4 pcs. 180.00 720.00

TOTAL COST OF STEEL WORKS

7. DISINFECTION/LEAKAGE TEST & GROUTING LEAK

a. Materials:

Chlorine Powder 25 kgs. 280.00 7,000.00

Hydraulic Cement (4-Liter/Gal) 40 gals. 1,300.00 52,000.00

Pricelist as of February 2013 122 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 123: Dumalon W.S. Ground Tank_Final

b. Labor:

1 - Skilled Worker 6 days 366.00 2,196.00

2 - Contractual Laborer 6 days 317.00 3,804.00

TOTAL COST OF DISINFECTION & LEAKAGE TEST

8. SUPPLY & INST. OF GATE VALVES, DIFFERENTIAL FLOAT CONTROL VALVE & APPURTENANCES

a. Materials:

D1Supply & Installation of Differential Float Control Valve

Supply & Installation of 150mmØ Differential Float Controlled Valve, F/F 2 units 342,600.00 685,200.00

w/ 2-Units Steel Ring Flange

Specifications:

The valve will be controlled by a differential float-operated, maximum differential level of 4.00 meters,

maximum flowrate equals to 40.00 LPS

The differential float controlled valve will be installed below the water level, constructed with concrete valve box

The valve will be a hydraulically operated, diaphragm actuated,

Face to face length dimension meets ISO 57529S-10 Standard, Flanged end Connection in Accordance w/ ANSI

Maximum pressure rating of PN16 (230 psi)

150mmØ C.I. Sleeve Type Flexible Coupling, (G.I.-B.I.) 2 pcs. 5,500.00 11,000.00

150mmØ C.I. Sleeve Type Flexible Coupling, (G.I.-PVC) 2 pcs. 5,500.00 11,000.00

6mm thk Rubber Gasket 4 kgs. 75.00 300.00

16mmØ x 100mm Anchor Bolts w/ Nuts & Washer 32 pcs. 125.00 4,000.00

Construction of two (2.0) units concrete valve box

Portland Cement 26 bags 245.00 6,370.00

Washed Sand 1.25 cu.m. 1,000.00 1,250.00

Gravel (G1) 2.5 cu.m. 1,000.00 2,500.00

16mmØ x 6.00m Deformed Reinf. Steel Bar 46 pcs. 480.00 22,080.00

#16 GI Tie Wire 5 kgs. 75.00 375.00

16mmØ x 6.00m Stainless Steel Round Bar (Type 304) 1 pc. 12,500.00 12,500.00

8mmØ x 6.00m M.S. Plain Round Bar 1 pc. 160.00 160.00

16mmØ x 6.00m M.S. Plain Round Bar 10 pcs. 495.00 4,950.00

38mmØ x 6.00m G.I. Pipe ASTM A53-90A Heavy Gauge Standard 1 pc. 1,800.00 1,800.00

6mm Thk x 50mm x 50mm x 6.00m MS Angle Bar 2 pcs. 1,500.00 3,000.00

12mm Thk x 1.20m x 2.40m Ordinary Plywood 6 shts. 975.00 5,850.00

40 pcs - 2" x 2" x 10' Coco Lumber 133 bd.ft. 20.00 2,660.00

40 pcs - 2" x 3" x 10' Coco Lumber 200 bd.ft. 20.00 4,000.00

40 pcs - 2" x 4" x 10' Coco Lumber 267 bd.ft. 20.00 5,340.00

4" C.W. Nail 2 kgs. 70.00 140.00

3" C.W. Nail 2 kgs. 70.00 140.00

1-1/2" C.W. Nail 1 kg. 65.00 65.00

Hacksaw Blade 12 pcs. 65.00 780.00

Welding Rod (6011) 3 kgs. 160.00 480.00

b. Labor:

3 - Skilled Worker 8 days 366.00 8,784.00

1 - Pipe Fitter 8 days 341.00 2,728.00

6 - Contractual Laborers 8 days 317.00 15,216.00

Valves & Appurtenances:

D2150mmØ x 150mmØ C.I. Tee, F/F, Flange End In Accordance w/ ANSI B16.1 Class 125 1 pc. 0.00

150mmØ C.I. Adaptor, F/P, Flange End In Accordance w/ ANSI B16.1 Class 125 2 pcs. 0.00

150mmØ C.I. Sleeve Type Flexible Coupling (PVC-CI) 2 pcs. 0.00

150mmØ Steel Blind Flange in Accordance w/ AWWA C207 Class D-Std. 1 pc. 0.00

19mmØ x 88mm Stainless Steel (Type 304) Bolt w/ Nut & Washer 24 pcs. 0.00

6mm Thick Rubber Gasket 3 kgs. 0.00

D3150mmØ x 150mmØ C.I. Tee, F/F, Flange End In Accordance w/ ANSI B16.1 Class 125 1 pc. 0.00

150mmØ C.I. Adaptor, F/P, Flange End In Accordance w/ ANSI B16.1 Class 125 3 pcs. 0.00

150mmØ C.I. Sleeve Type Flexible Coupling (PVC-CI) 3 pcs. 0.00

19mmØ x 88mm Stainless Steel (Type 304) Bolt w/ Nut & Washer 24 pcs. 0.00

6mm Thick Rubber Gasket 3 kgs. 0.00

D4 & D5150mmØ x 45

0 PVC Bend, Class 150, B/S, w/ R.R. 4 pcs. 0.00

D6200mmØ C.I. Body Gate Valve, F/F, PN16, NRS, Flange End in Accordance w/ ANSI B16.1 Class 125 2 pcs. 0.00

200mmØ C.I. Adaptor, F/P, Flange End In Accordance w/ ANSI B16.1 Class 125 4 pcs. 0.00

200mmØ C.I. Sleeve Type Flexible Coupling (PVC-CI) 2 pcs. 0.00

200mmØ C.I. Sleeve Type Flexible Coupling (CI-BI) 2 pcs. 0.00

200mmØ x 6.00m B.I. Pipe, (ASTM A53-90A Heavy Gauge Standard) 1 pc. 0.00

200mmØ Fabricated Flange (see Plans for Shop Drawing) 2 pcs. 0.00

6mm Thick Rubber Gasket 4 kgs. 0.00

D7

Pricelist as of February 2013 123 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 124: Dumalon W.S. Ground Tank_Final

200mmØ x 450 PVC Bend, Class 150, B/S, w/ R.R. 4 pcs. 0.00

D8100mmØ x 45

0 PVC Bend, Class 150, B/S, w/ R.R. 4 pcs. 0.00

Under Drain Pipes & Appurtenances

100mmØ C.I. Body Gate Valve, F/F, PN16, NRS, Flange End in Accordance w/ ANSI B16.1 Class 125 1 pc. 7,940.00 7,940.00

150mmØ C.I. Valve Box Cover 1 ps. 950.00 950.00

100mmØ x 6.00m PVC Pipe Class 150, B/S, w/ R.R. 6 pcs. 1,600.00 9,600.00

100mmØ Mechanical End Cap, 4 pcs. 950.00 3,800.00

100mm x 100mmØ C.I. Tee, M/M 3 pcs. 4,300.00 12,900.00

Geotextile Filter Fabric 12 sq.m. 200.00 2,400.00

Air Vent

100mmØ x 6.00m G.I. Pipe, ASTM A53-90A Heavy Gauge Std. 1 pc. 4,800.00 4,800.00

100mmØ x 90o G.I. Elbow, ANSI B16.3 Class 150 Std. 4 pcs. 870.00 3,480.00

100mmØ G.I. End Cap, ANSI B16.3 Class 150 Std. 2 pcs. 540.00 1,080.00

b. Labor:

2 - Pipefitter 4 days 341.00 2,728.00

4 - Laborer 4 days 317.00 5,072.00

TOTAL COST OF GATE VALVES, DIFFERENTIAL FLOAT CONTROL VALVE & APPURTENANCES

9. SUPPLY & INSTALLATION OF TWO UNITS - 100MMØ FLOW METER & CONST OF CONCRETE VALVE BOX

a. Materials :

Supply & Inst. of 100mmØ Full Bore Electromagnetic Flowmeter F/F w/ 2-Units Steel Flange 2 units 286,000.00 572,000.00

Specification:

100mmØ Electro-Magnetic Flowmeter, ANSI 16.5, Class-150,

Flanged-Typed, Transmitter accuracy of 0.40% of rate, with highly

accurate bi-directional measurements, battery powered, with internal

battery pack of five (05) years maintenance free battery life.

Complete with two (02) mating flanges and the desired stainless steel

bolts, nuts, washers with rubber gaskets. Unit is remote-type with

complete accessories and with integrated GSM Data Logger

(wall-mounted typed signal converter) which records/logs the flow &

pressure, and is compatible with the sensor EM Flowmeter

with a recording interval programmable between 1 second

& 1 hour. EM Flowmeter & Logger housing is fully water proofed (IP68).

Data can be accessed remotely using a standard GSM mobile phone

thru simple text message to the host computer provided with a

windows-based software which can monitor multiple data loggers.

24 months warranty, with Wet Calibration Certificate per unit upon delivery.

The unit includes the following accessories:

Fifty (50) meters flow input cable with pvc conduit up to the pump house,

communication cable, Windows-based configuration software for PC's,

Two channel flow splitter cable (50 meters), 50 meters hose for pressure

line with fittings (quick fit connection).

Note: Package includes Orientation & Training of personnel

100mmØ C.I. Sleeve Type Flexible Coupling, (G.I.-PVC) 2 pcs. 3,915.00 7,830.00

100mmØ C.I. Adaptor, F/P, Flange End In Accordance w/ ANSI B16.1 Class 125 2 pcs. 2,541.00 5,082.00

6mm thk Rubber Gasket 5 kgs. 75.00 375.00

16mmØ x 100mm Anchor Bolts w/ Nuts & Washer 16 pcs. 95.00 1,520.00

Construction of 2 - Units Concrete Valve Box

Portland Cement 28 bags 245.00 6,860.00

Washed Sand 1.25 cu.m. 1,000.00 1,250.00

Gravel (G1) 2.5 cu.m. 1,000.00 2,500.00

16mmØ x 6.00m Deformed Reinf. Steel Bar 44 pcs. 480.00 21,120.00

#16 GI Tie Wire 5 kgs. 75.00 375.00

16mmØ x 6.00m Stainless Steel Round Bar (Type 304) 1 pc. 12,500.00 12,500.00

8mmØ x 6.00m M.S. Plain Round Bar 1 pc. 160.00 160.00

16mmØ x 6.00m M.S. Plain Round Bar 2 pcs. 495.00 990.00

38mmØ x 6.00m G.I. Pipe ASTM A53-90A Heavy Gauge Standard 1 pc. 1,800.00 1,800.00

6mm Thk x 50mm x 50mm x 6.00m MS Angle Bar 1 pc. 1,500.00 1,500.00

12mm Thk x 1.20m x 2.40m Ordinary Plywood 8 shts. 975.00 7,800.00

60 pcs - 2" x 2" x 10' Coco Lumber 200 bd.ft. 20.00 4,000.00

40 pcs - 2" x 3" x 10' Coco Lumber 200 bd.ft. 20.00 4,000.00

40 pcs - 2" x 4" x 10' Coco Lumber 267 bd.ft. 20.00 5,340.00

4" C.W. Nail 2 kgs. 70.00 140.00

3" C.W. Nail 2 kgs. 70.00 140.00

1-1/2" C.W. Nail 1 kg. 65.00 65.00

Hacksaw Blade 6 pcs. 65.00 390.00

Welding Rod (6011) 2 kgs. 160.00 320.00

b. Labor:

3 - Skilled Worker 6 days 366.00 6,588.00

1 - Pipe Fitter 6 days 341.00 2,046.00

Pricelist as of February 2013 124 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 125: Dumalon W.S. Ground Tank_Final

4 - Contractual Laborers 6 days 317.00 7,608.00

TOTAL COST OF SUPPLY & INSTALLATION OF 100MMØ FLOW METER & CONST OF CONCRETE VALVE BOX

10. PAINTING WORKS (223.00 Sq.M.)

a. Materials:

Concrete Neutralizer 6 gals. 320.00 1,920.00

Solvent Based Acrylic Paint Primer 10 gals. 1,050.00 10,500.00

Solvent Based Acrylic Cast 10 gals. 500.00 5,000.00

Solvent Based Acrylic Paint Top Coat White Gloss 20 gals. 1,050.00 21,000.00

Solvent Based Acrylic Paint Reducer 6 gals. 420.00 2,520.00

Lacquer thinner 8 gals. 250.00 2,000.00

Body Filler w/ Hardener 2 gals. 640.00 1,280.00

Sand paper #150 2 doz. 150.00 300.00

Sand paper #120 2 doz. 150.00 300.00

Red Tinting Color for Solvent Based Acrylic Paint 2 pints 105.00 210.00

Raw Sienna Tinting Color for Solvent Based Acrylic Paint 6 pints 105.00 630.00

Thalo Blue Tinting Color for Solvent Based Acrylic Paint 2 pints 105.00 210.00

Lamp Black Tinting Color for Solvent Based Acrylic Paint 2 pints 105.00 210.00

Red Lead Paint Primer 2 gals. 570.00 1,140.00

Quick Dry Enamel (Royal Blue) 2 gals. 620.00 1,240.00

Paint Thinner 1 gal. 360.00 360.00

7" Roller Brush w/ Handle 2 sets 45.00 90.00

2" Paint Brush 2 pcs. 20.00 40.00

Steel Brush 1 pc. 25.00 25.00

Pricelist as of February 2013 125 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 126: Dumalon W.S. Ground Tank_Final

b. Labors:

2 - Painter 15 days 366.00 10,980.00

2 - Contractual Laborers 15 days 317.00 9,510.00

TOTAL COST OF PAINTING WORKS

11. WATER PROOFING WORKS FOR TOP SLAB

Supply & Installation of Bituminous Membrane Polyester Reinforced Waterproofing 37.7 sq.m. 1,000.00 37,700.00

TOTAL COST OF WATER PROOFING WORKS FOR TOP SLAB

12. SUPPLY & INST. OF 40GPD HYPOCHLORINATOR

"CHEM-TECH" heavy Duty Hypochlorinator with 100 liters Solution Tank

with stirrer, series 200, designed to deliver 40 GPD(max) vs. 125 psig, 1 unit 90,000.00 90,000.00

mechanical diaphragm type and oil bathed gear assembly, driven by

electric motor, 230V, single phase, 60 Hz. With complete standard

suction & discharge accessories:

- 4 ft. Suction Tubing, clear PVC, 7/16"OD

- 8 ft. Discharge Tubing, P.E., 1/2" OD

- 1 set Back check Valve & Injection Fittings

- 1 set Foot Valve with strainer

- 1 pc. Bleed Valve

Provision for Chlorinator Injection Fittings:

50mm.Ø G.I. Coupling, ANSI B16.3 Class 150 1 pc. 52.00 52.00

50mm.Ø x 150mm G.I. Nipple, ASTM A53-90A Heavy Gauge Std. 1 pc. 91.00 91.00

50mm.Ø G.I. Cap, ANSI B16.3 Class 150 1 pc. 63.00 63.00

19mm.Ø G.I. Coupling, ANSI B16.3 Class 150 1 pc. 11.00 11.00

19mm.Ø x 12mm.Ø G.I. Bushing, ANSI B16.3 Class 150 1 pc. 11.00 11.00

12mm.Ø G.I. Plug, ANSI B16.3 Class 150 1 pc. 6.00 6.00

Pressure Gauge Assembly:

12mm.Ø G.I. Tee, ANSI B16.3 Class 150 2 pc. 11.00 22.00

12mm.Ø G.I. Coupling, ANSI B16.3 Class 150 2 pc. 9.00 18.00

12mm.Ø x 100mm G.I. Nipple, ASTM A53-90A Heavy Gauge Std. 2 pc. 15.00 30.00

12mm.Ø x 6mmØ G.I. Bushing, ANSI B16.3 Class 150 2 pc. 10.00 20.00

12mm.Ø G.I. Plug, ANSI B16.3 Class 150 2 pc. 13.00 26.00

12mm.Ø Brass Ball Valve 2 pc. 130.00 260.00

63mm.Ø Oil-filled Pressure Gauge (0-150 psi) 2 pc. 2,000.00 4,000.00

Labor: Cutting & Welding works of B.I. Discharge Pipes, installation of Appurtenances,

preparation of Pressure Gauge assy. and provision for Chlorinator Injection Fittings. 1 l.s. 18,922.00 18,922.00

TOTAL COST OF SUPPLY & INST. OF 40GPD HYPOCHLORINATOR W/ COMPLETE ACCESSORIES

TOTAL COST OF CONST. OF THREE HUNDRED 300.00 CU.M. CONCRETE GROUND TANK

III. CONST. OF CONCRETE PERIMETER FENCE

1. CLEARING/LAYOUTING & EXCAVATION WORKS

a. Materials:

Nylon Chord #100 2 rolls 300.00 600.00

12mm Clear Level Hose 40 mtrs 25.00 1,000.00

b. Labor:

1 - Skilled Worker 3 days 366.00 1,098.00

4 - Contractual Laborers 3 days 317.00 3,804.00

TOTAL COST OF EXCAVATION WORKS

2. CONCRETING WORKS (14.80 Cu.M.)

a. Materials :

F1 (7 Units)

Portland Cement 19 bags 245.00 4,655.00

Washed Sand 1 cu.m. 1,000.00 1,000.00

Gravel 2 cu.m. 1,000.00 2,000.00

150mm Boulders 1 cu.m. 1,000.00 1,000.00

F2 (14 Units)

Portland Cement 21 bags 245.00 5,145.00

Washed Sand 1 cu.m. 1,000.00 1,000.00

Gravel 2 cu.m. 1,000.00 2,000.00

150mm Boulders 2 cu.m. 1,000.00 2,000.00

C1 & C1-A (7 Units)

Portland Cement 25 bags 230.00 5,750.00

Washed Sand 1.25 cu.m. 1,000.00 1,250.00

Gravel 2.5 cu.m. 1,000.00 2,500.00

C2 & C2-A (14 Units)

Portland Cement 35 bags 230.00 8,050.00

Washed Sand 1.75 cu.m. 1,000.00 1,750.00

Gravel 3.5 cu.m. 1,000.00 3,500.00

5,074,947.00

Pricelist as of February 2013 126 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 127: Dumalon W.S. Ground Tank_Final

WF (55.70 ln.m.)

Portland Cement 23 bags 230.00 5,290.00

Washed Sand 1.125 cu.m. 1,000.00 1,125.00

Gravel 2.25 cu.m. 1,000.00 2,250.00

Lintel Beam (55.70 ln.m.)

Portland Cement 16 bags 230.00 3,680.00

Washed Sand 0.75 cu.m. 1,000.00 750.00

Gravel 1.5 cu.m. 1,000.00 1,500.00

b. Labor:

2 - Masons 6 days 366.00 4,392.00

10 - Contractual Laborer 6 days 317.00 19,020.00

c. Equipment Rental/Fuel/Oil & Lubricants:

1 - Unit - One - Bagger Mixer 6 days 1,500.00 9,000.00

1 - Unit - Concrete Vibrator 6 days 800.00 4,800.00

Premium Gasoline 120 ltrs. 60.00 7,200.00

TOTAL COST OF CONCRETE WORKS

3. REINFORCED STEEL WORKS (1,940.10 KGS.)

a. Materials :

F1 (7 Units)

16mmØ x 6.00m Def. Reinforcing Steel Bars 14 pcs. 480.00 6,720.00

#16 G.I. Tie-wire 2 kgs. 65.00 130.00

Hacksaw Blade 4 pcs. 65.00 260.00

F2 (14 Units)

16mmØ x 6.00m Def. Reinforcing Steel Bars 24 pcs. 480.00 11,520.00

#16 G.I. Tie-wire 3 kgs. 65.00 195.00

Hacksaw Blade 6 pcs. 65.00 390.00

C1 & C1-A (7 Units)

16mmØ x 6.00m Def. Reinforcing Steel Bars 28 pcs. 450.00 12,600.00

10mmØ x 6.00m Def. Reinforcing Steel Bars 40 pcs. 165.00 6,600.00

#16 G.I. Tie-wire 7 kgs. 65.00 455.00

Hacksaw Blade 6 pcs. 65.00 390.00

C2 & C2-A (14 Units)

16mmØ x 6.00m Def. Reinforcing Steel Bars 56 pcs. 480.00 26,880.00

10mmØ x 6.00m Def. Reinforcing Steel Bars 78 pcs. 190.00 14,820.00

#16 G.I. Tie-wire 18 kgs. 65.00 1,170.00

Hacksaw Blade 8 pcs. 65.00 520.00

WF (55.70 ln.m.)

12mmØ x 6.00m Def. Reinforcing Steel Bars 20 pcs. 270.00 5,400.00

10mmØ x 6.00m Def. Reinforcing Steel Bars 19 pcs. 190.00 3,610.00

#16 G.I. Tie-wire 5 kgs. 65.00 325.00

Hacksaw Blade 6 pcs. 65.00 390.00

Lintel Beam (55.70 ln.m.)

12mmØ x 6.00m Def. Reinforcing Steel Bars 40 pcs. 270.00 10,800.00

10mmØ x 6.00m Def. Reinforcing Steel Bars 24 pcs. 190.00 4,560.00

#16 G.I. Tie-wire 9 kgs. 65.00 585.00

Hacksaw Blade 12 pcs. 65.00 780.00

b. Labor:

2 -Steel Man 15 days 366.00 10,980.00

4 - Laborer 15 days 317.00 19,020.00

c. Equipment:

1 - Unit Bar Cutter 15 days 300.00 4,500.00

1 - Unit Bar Bender 15 days 300.00 4,500.00

TOTAL DIRECT COST OF REBAR WORKS

4. MASONRY WORKS:

a. Materials :

Portland Cement 110 bags 245.00 26,950.00

Washed Sand 5 cu.m. 1,000.00 5,000.00

Fine sand (for plastering) 3 cu.m. 1,400.00 4,200.00

100mm thk Concrete Hollow Blocks (NLB) 893 pcs. 17.00 15,181.00

150mm thk Concrete Hollow Blocks (LB) 143 pcs. 24.00 3,432.00

10mmØ x 6.00m Def. Reinforcing Steel Bars 25 pcs. 190.00 4,750.00

#16 G.I. Tie-wire 4 kgs. 65.00 260.00

Hacksaw Blade 6 pcs. 65.00 390.00

b. Labor:

2 - Masons 14 days 366.00 10,248.00

2 - Laborers 14 days 317.00 8,876.00

TOTAL COST OF MASONRY WORKS

Pricelist as of February 2013 127 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 128: Dumalon W.S. Ground Tank_Final

Pricelist as of February 2013 128 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 129: Dumalon W.S. Ground Tank_Final

5. FORMS & SCAFFOLDING WORKS:

a. Materials :

12mm

Thk. X 1.20m x 2.40m Ordinary Plywood 16 shts. 975.00 15,600.00

60 - pcs - 2" x 4" x 10' Coco Lumber 400 bd.ft. 20.00 8,000.00

80 - pcs - 2" x 3" x 10' Coco Lumber 400 bd.ft. 20.00 8,000.00

100 - pcs - 2" x 2" x 10' Coco Lumber 333 bd.ft. 20.00 6,660.00

4" C.W. Nails 8 kgs. 70.00 560.00

3" C.W. Nails 6 kgs. 70.00 420.00

1-1/2" C.W. Nails 5 kgs. 65.00 325.00

b. Labor:

1 - Carpenter 15 days 366.00 5,490.00

2 - Laborer 15 days 317.00 9,510.00

TOTAL COST OF FORMS & SCAFFOLDING WORKS:

6. STEEL WORKS:

a. Materials :

50mmØ x 6.0m G.I. Pipe. (ASTM A53 90A-Heavy Gauge Standard) 16 pcs. 1,720.00 27,520.00

6mm thk x 38mm x 6.00m M.S. Flat Bar 16 pcs. 880.00 14,080.00

12mm x 12mm x 6.00m M.S. Square Bar 76 pcs. 270.00 20,520.00

#4 x 50mm Mesh x 1.20m x 2.40m B.I. Steel Matting 25 pcs. 1,400.00 35,000.00

6011 Welding Rod 15 kgs. 160.00 2,400.00

Hacksaw Blade 30 pcs. 65.00 1,950.00

b. Labor:

1 -Welder 20 days 366.00 7,320.00

4 - Laborer 20 days 317.00 25,360.00

c. Equipment Rental:

1 - Unit Welding Machine 20 days 2,200.00 44,000.00

1 - Unit Disk Grinder 20 days 300.00 6,000.00

4" Grinder Wheel 4 pcs. 180.00 720.00

TOTAL COST OF STEEL WORKS:

7. PAINTING WORKS

a. Materials:

Concrete Neutralizer 4 gals. 320.00 1,280.00

Solvent Based Acrylic Paint Primer 10 gals. 1,050.00 10,500.00

Solvent Based Acrylic Paint Top Coat (White Gloss) 20 gals. 1,050.00 21,000.00

Solvent Based Acrylic Reducer 7 gals. 420.00 2,940.00

Red Lead Metal Primer 4 gals. 570.00 2,280.00

Quick Dry Enamel Blue 4 gals. 620.00 2,480.00

Paint Thinner 2 gals. 360.00 720.00

Red Tinting Color for Solvent Based Acrylic Paint 2 pints 105.00 210.00

Raw Sienna Tinting Color for Solvent Based Acrylic Paint 8 pints 105.00 840.00

Thalo Blue Tinting Color for Solvent Based Acrylic Paint 2 pints 105.00 210.00

Lamp Black Tinting Color for Solvent Based Acrylic Paint 2 pints 105.00 210.00

#120 Sand Paper 2 doz. 150.00 300.00

#150 Sand Paper 2 doz. 150.00 300.00

7" Paint Roller w/ Tray 2 sets 45.00 90.00

1" Paint Brush 2 pcs. 15.00 30.00

2" Paint Brush 2 pcs. 20.00 40.00

4" Paint Brush 3 pcs. 40.00 120.00

Steel Brush 3 pcs. 25.00 75.00

b Labor:

2 - Painter 12 days 317.00 7,608.00

2 - Laborer 12 days 317.00 7,608.00

TOTAL COST OF PAINTING WORKS

8. SIGNAGE WITH STAND & FRAME

a. Materials:

Panaflex Signage w/ Aluminum Framing, Lighting and Accessories 1 set 13,000.00 13,000.00

12mm. ∅ x 150mm. Stainless Steel Bolt (Type 304) w/ Nuts & Washers 8 pcs. 80.00 640.00

6mm Thk x 200mm x 200mm Fabricated Base Plate w/ 4-16mm ∅ Bolt Hole (Attach 2 pcs. 1,800.00 3,600.00

Shop Drawing)

100mm. ∅ x 6.00m G.I. Pipe, ASTM 53 A90 Heavy Gauge - Standard 1 pc. 3,450.00 3,450.00

10mm. ∅ x 25mm. Stainless Steel Bolt (Type 304) w/ Nuts & Washers 12 pcs. 35.00 420.00

b. Labor:

2 - Skilled Worker 2 day 366.00 1,464.00

2 - Laborer 2 day 317.00 1,268.00

TOTAL COST OF SIGNAGE

TOTAL COST OF CONCRETE PERIMETER FENCE 656,614.00

Pricelist as of February 2013 129 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 130: Dumalon W.S. Ground Tank_Final

IV. CONSTRUCTION OF (12.40 SQ. MTR.) OPERATOR'S ROOM

1. EXCAVATION WORKS (3.98 Cu.M.)

b. Labors:

4 - Laborer 1 day 317.00 1,268.00

TOTAL DIRECT COST OF EXCAVATION WORKS

2. CONCRETE WORKS (8.50 Cu M.)

Note: Other Column Footing, Column, Wall Footing & Floor Lintel Beam are already included in Perimeter Fence Estimates

a. Materials:

F2 (2 Units)

Portland Cement 6 bags 245.00 1,470.00

Washed Sand 0.25 cu.m. 1,000.00 250.00

Gravel (G1) 0.5 cu.m. 1,000.00 500.00

C2-A (2 Units)

Portland Cement 7 bags 245.00 1,715.00

Washed Sand 0.5 cu.m. 1,000.00 500.00

Gravel (G1) 0.75 cu.m. 1,000.00 750.00

WF (11.00 ln.m.)

Portland Cement 5 bags 245.00 1,225.00

Washed Sand 0.25 cu.m. 1,000.00 250.00

Gravel (G1) 0.5 cu.m. 1,000.00 500.00

Floor Lintel Beam (11.00 ln.m.)

Portland Cement 4 bags 245.00 980.00

Washed Sand 0.25 cu.m. 1,000.00 250.00

Gravel (G1) 0.5 cu.m. 1,000.00 500.00

Slab on Fill (0.10m x 12.65 Sq.m.)

Portland Cement 12 bags 245.00 2,940.00

Washed Sand 0.5 cu.m. 1,000.00 500.00

Gravel (G1) 1 cu.m. 1,000.00 1,000.00

Door/Window Lintel Beam (10.00 ln.m.)

Portland Cement 3 bags 245.00 735.00

Washed Sand 0.25 cu.m. 1,000.00 250.00

Gravel (G1) 0.25 cu.m. 1,000.00 250.00

RCB

Portland Cement 12 bags 245.00 2,940.00

Washed Sand 0.5 cu.m. 1,000.00 500.00

Gravel (G1) 1 cu.m. 1,000.00 1,000.00

Roof Slab (18.70 sq.m.)

Portland Cement 23 bags 245.00 5,635.00

Washed Sand 1 cu.m. 1,000.00 1,000.00

Gravel (G1) 2 cu.m. 1,000.00 2,000.00

False Beam (10.50 ln.m.)

Portland Cement 4 bags 245.00 980.00

Washed Sand 0.25 cu.m. 1,000.00 250.00

Gravel (G1) 0.25 cu.m. 1,000.00 250.00

b. Labors:

1 Mason 4 days 366.00 1,464.00

8 - Laborers 4 days 317.00 10,144.00

c. Equipment Rental:

1 - Unit One - Bagger Mixer 4 days 1,500.00 6,000.00

1 - Unit Concrete Vibrator 4 days 500.00 2,000.00

TOTAL DIRECT COST OF CONCRETE WORKS

3. REINFORCED STEEL WORKS (1,093.10 KGS.)

Note: Other Column Footing, Column, Wall Footing & Floor Lintel Beam are already included in Perimeter Fence Estimates

a. Materials:

F2 (2 Units)

16mmØ x 6.00m Def. Reinforcing Steel Bars 4 pcs. 480.00 1,920.00

#16 G.I. Tie-wire 1 kg. 65.00 65.00

Hacksaw Blade 2 pcs. 65.00 130.00

C2-A (2 Units)

16mmØ x 6.00m Def. Reinforcing Steel Bars 8 pcs. 480.00 3,840.00

10mmØ x 6.00m Def. Reinforcing Steel Bars 11 pcs. 190.00 2,090.00

#16 G.I. Tie-wire 1 kg. 65.00 65.00

Hacksaw Blade 2 pcs. 65.00 130.00

WF (11.00 ln.m.)

12mmØ x 6.00m Def. Reinforcing Steel Bars 3 pcs. 270.00 810.00

10mmØ x 6.00m Def. Reinforcing Steel Bars 5 pcs. 190.00 950.00

Pricelist as of February 2013 130 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 131: Dumalon W.S. Ground Tank_Final

#16 G.I. Tie-wire 2 kgs. 65.00 130.00

Hacksaw Blade 2 pcs. 65.00 130.00

Floor Lintel Beam (11.00 ln.m.)

12mmØ x 6.00m Def. Reinforcing Steel Bars 9 pcs. 270.00 2,430.00

10mmØ x 6.00m Def. Reinforcing Steel Bars 7 pcs. 190.00 1,330.00

#16 G.I. Tie-wire 2 kgs. 65.00 130.00

Hacksaw Blade 2 pcs. 65.00 130.00

Pricelist as of February 2013 131 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 132: Dumalon W.S. Ground Tank_Final

Slab on Fill (0.10m x 12.65 Sq.m.)

10mmØ x 6.00m Def. Reinforcing Steel Bars 19 pcs. 190.00 3,610.00

#16 G.I. Tie-wire 1 kg. 65.00 65.00

Hacksaw Blade 3 pcs. 65.00 195.00

Door/Window Lintel Beam (10.00 ln.m.)

12mmØ x 6.00m Def. Reinforcing Steel Bars 4 pcs. 270.00 1,080.00

10mmØ x 6.00m Def. Reinforcing Steel Bars 4 pcs. 190.00 760.00

#16 G.I. Tie-wire 1 kg. 65.00 65.00

Hacksaw Blade 1 pc. 65.00 65.00

RCB

16mmØ x 6.00m Def. Reinforcing Steel Bars 22 pcs. 480.00 10,560.00

10mmØ x 6.00m Def. Reinforcing Steel Bars 30 pcs. 190.00 5,700.00

#16 G.I. Tie-wire 7 kgs. 65.00 455.00

Hacksaw Blade 10 pc. 65.00 650.00

Roof Slab

12mmØ x 6.00m Def. Reinforcing Steel Bars 65 pcs. 270.00 17,550.00

#16 G.I. Tie-wire 6 kgs. 65.00 390.00

Hacksaw Blade 10 pcs. 65.00 650.00

False Beam (10.50 ln.m.)

12mmØ x 6.00m Def. Reinforcing Steel Bars 5 pcs. 270.00 1,350.00

10mmØ x 6.00m Def. Reinforcing Steel Bars 8 pcs. 190.00 1,520.00

#16 G.I. Tie-wire 3 kgs. 65.00 195.00

Hacksaw Blade 3 pcs. 65.00 195.00

b. Labors:

1 -Steelman 14 days 366.00 5,124.00

2 -Contractual Laborers 14 days 317.00 8,876.00

c. Equipment Rental:

1 - Unit Bar Bender 14 days 300.00 4,200.00

TOTAL DIRECT COST OF REINFORCED STEEL WORKS

4. MASONRY WORKS

4.1. Laying & Plastering of CHB

(Includes CHB Laying & Plastering Works)

a. Materials:

Portland Cement 73 bags 245.00 17,885.00

Washed Sand 3.5 cu.m. 1,000.00 3,500.00

Fined Sand (For Plastering) 2 cu.m. 1,400.00 2,800.00

100mm x 200mm x 400mm Hollow Block (NLB) 640 pcs. 17.00 10,880.00

150mm x 200mm x 400mm Hollow Block (LB) 230 pcs. 24.00 5,520.00

10mmØ x 6.00m. Def. Steel Bars 42 pcs. 190.00 7,980.00

# 16 G.I. Tie Wire 3 kgs. 75.00 225.00

Hacksaw Blade 12 pcs. 65.00 780.00

b. Labors:

2 - Mason 14 days 366.00 10,248.00

2 - Laborer 14 days 317.00 8,876.00

4.2. Tile Works (31.80 sq.m.)

a. Materials:

200mm x 200mm Ceramic Tiles (White) 390 pcs. 16.00 6,240.00

400mm x 400mm Granite Tiles (White) 54 pcs. 255.00 13,770.00

Tile Adhesive (25Kg/Bag) 5 bags 305.00 1,525.00

Tile Grout (2 Kg./Pack) 5 bags 85.00 425.00

PVC Tile Trim (White) 7 pcs. 65.00 455.00

4" Grinding Wheel 1 pc. 180.00 180.00

b. Labor:

2 - Mason 9 days 366.00 6,588.00

2 - Laborer 9 days 317.00 5,706.00

c. Equipment Rental:

1 - Unit Tile Cutter 5 days 300.00 1,500.00

1 - Unit Angular Grinder 5 days 300.00 1,500.00

TOTAL DIRECT COST OF MASONRY WORKS

5. CARPENTRY WORKS

a. Materials:

5.1. Installation of Door Frame/Pannel Door & Window Jamb

Pre-Fabricated 0.80m x 2.10m x 50mm x 150mm Mahogany Wood Door Jamb 1 unit 2,500.00 2,500.00

Pre-Fabricated 0.80m x 2.10m Mahogany Wood Panel Type Door 1 unit 4,800.00 4,800.00

w/ 50mm x 100mm Door Frame & 37.5mm Thk Door Board

Pre-Fabricated 0.60m x 2.10m PVC Door w/ Door Jamb & Hinges w/ Screw 1 unit 1,900.00 1,900.00

Pre-Fab. 1.165m x 1.45m x 50mm x 150mm 2 Panel Mahogany Wood Window Jamb 2 units 2,300.00 4,600.00

Pricelist as of February 2013 132 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 133: Dumalon W.S. Ground Tank_Final

5.2. Cabinet & Table:

1-Unit Cabinet

Cabinet Handle (Chrome) 4 pcs. 160.00 640.00

Cabinet Concealed Hinges w/ Screw 12 pcs. 60.00 720.00

12mm.Ø x 6.00m G.I. Pipe, ASTM A53-90A Heavy Gauge Standard 1 pc. 600.00 600.00

3 pcs. - 1" x 1" x 10' Mahogany Lumber 2.5 bd.ft. 34.00 85.00

19mm Thk x 1.20m x 2.40m Plyboard 3 shts. 1,100.00 3,300.00

Pricelist as of February 2013 133 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 134: Dumalon W.S. Ground Tank_Final

6mm Thk x 1.20m x 2.40m Plyboard 1 sht. 420.00 420.00

3" C.W. Nail 1 kg. 70.00 70.00

1" C.W. Finishing Nail 1 kg. 75.00 75.00

1-Unit Table

Drawer Handle (Chrome) 4 pcs. 160.00 640.00

3 pcs. - 1" x 1" x 10' Mahogany Lumber 2.5 bd.ft. 34.00 85.00

19mm Thk x 1.20m x 2.40m Plyboard 3 shts. 1,100.00 3,300.00

1" C.W. Finishing Nail 1 kg. 75.00 75.00

5.3. Hardware :

4" x 3" Loose Pin Hinges (Heavy Duty) w/ Screw 4 pcs. 140.00 560.00

2" x 2" Cabinet Hinges w/ Screw 8 pcs. 65.00 520.00

Stainless Door Knob (Heavy Duty) 2 sets 950.00 1,900.00

Drawer Lock (Heavy Duty) 4 sets 60.00 240.00

4" C. W. Nail 1 kg. 70.00 70.00

2-1/2" C. W. Nail 1 kg. 65.00 65.00

2" C. W. Nail 1 kg. 65.00 65.00

1" C. W. Nail 1 kg. 65.00 65.00

1" Finishing Nail 2 kgs. 65.00 130.00

b. Labor:

1 - Carpenter 9 days 366.00 3,294.00

1 - Laborer 9 days 317.00 2,853.00

TOTAL DIRECT COST OF CARPENTRY WORKS

6. SCAFFOLDING & FORM WORKS

a. Materials:

12mm Thk x 1.20m x 2.40m Ordinary Plywood 18 pcs. 975.00 17,550.00

100 pcs. - 2" x 2" x 10' Coco Lumber 333 bd.ft. 20.00 6,660.00

80 pcs. - 2" x 3" x 10' Coco Lumber 400 bd.ft. 20.00 8,000.00

80 pcs. - 2" x 4" x 10' Coco Lumber 400 bd.ft. 20.00 8,000.00

4" C. W. Nail 8 kgs. 70.00 560.00

3" C. W. Nail 8 kgs. 70.00 560.00

1-1/2" C. W. Nail 4 kgs. 65.00 260.00

b. Labors:

1 -Carpenter 12 days 366.00 4,392.00

1 -Contractual Laborers 12 days 317.00 3,804.00

TOTAL DIRECT COST OF SCAFFOLDING & FORM WORKS

7. PLUMBING WORKS

7.1. Storm Drainage Pipe

50mmØ x 3.00m PVC Pipe, Series 1000 6 pcs. 320.00 1,920.00

50mmØ x 900 PVC Bend, Series 1000 8 pcs. 45.00 360.00

50mmØ PVC Coupling, Series 1000 4 pcs. 90.00 360.00

PVC Solvent Cement 2 qrts. 120.00 240.00

7.2. Sanitary Pipe

100mmØ x 3.00m PVC Pipe, Series 1000 4 pcs. 820.00 3,280.00

100mmØ x 450 PVC Sanitary Elbow, Series 1000 6 pcs. 85.00 510.00

100mmØ x 900 PVC Sanitary Elbow, Series 1000 4 pcs. 90.00 360.00

100mmØ x PVC Clean Out, Series 1000 2 pcs. 75.00 150.00

100mmØ PVC Sanitary Coupling, Series 1000 2 pcs. 65.00 130.00

50mmØ x 3.00m PVC Pipe, Series 1000 3 pcs. 320.00 960.00

50mmØ PVC Sanitary Coupling, Series 1000 2 pcs. 35.00 70.00

50mmØ x 900 PVC Bend, Series 1,000 1 pc. 45.00 45.00

100mmØ x 100mmØ PVC Sanitary Tee, Series 1000 4 pcs. 170.00 680.00

100mmØ x 100mmØ PVC Sanitary Wye, Series 1000 2 pcs. 155.00 310.00

100mmØ x 50mmØ PVC Sanitary Tee, Series 1000 1 pc. 130.00 130.00

50mmØ x 50mmØ PVC Sanitary Tee, Series 1000 1 pc. 65.00 65.00

PVC Cement Solvents 8 qrts. 120.00 960.00

7.3. Cold Pipe

12mmØ x 6.00m G.I. Pipe ASTM A53-90A Heavy Gauge Standard 3 pcs. 460.00 1,380.00

12mmØ x 900 G.I. Elbow, ANSI B16.3 Class 150 Standard 7 pcs. 15.00 105.00

12mmØ x 12mmØ G.I. Tee, ANSI B16.3 Class 150 Standard 4 pcs. 20.00 80.00

12mmØ Brass Faucet 2 pcs. 260.00 520.00

12mmØ G.I. Union Patent ANSI B16.3 Class 150 Standard 1 pc. 20.00 20.00

25mm Teflon Tape 5 rolls 27.00 135.00

7.4. Sanitary Fixtures:

Flush Type Water Closet w/ Complete Fittings & Accs. 1 unit 4,000.00 4,000.00

Wall Mounted Type Lavatory w/ Complete Fittings & Accs. 1 unit 2,415.00 2,415.00

Ceramic Tissue Holder 1 pc. 270.00 270.00

Ceramic Soap Holder 1 pc. 160.00 160.00

12mm Shower Head 1 pc. 220.00 220.00

12mm Shower Valve 1 pc. 250.00 250.00

100mm x 100mm Stainless Double Strainer Floor Drain 2 pcs. 150.00 300.00

6mm Thk. x 0.6m x 0.6m Beveled Frameless Mirror 1 pc. 200.00 200.00

Pricelist as of February 2013 134 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 135: Dumalon W.S. Ground Tank_Final

b. Labors:

1 -Plumber 4 days 366.00 1,464.00

2 -Contractual Laborers 4 days 317.00 2,536.00

TOTAL DIRECT COST OF PLUMBING WORKS

Pricelist as of February 2013 135 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 136: Dumalon W.S. Ground Tank_Final

8. GLASS WORKS (LUMP SUM)

Supply & Installation of 5.5mm Thk x 13 Blades Smoke x 0.65m width Glass Jalousies

w/ Aluminum Holder 4 sets 800.00 3,200.00

Supply & Installation of 5.5mm Thk x 6 Blades x 0.60m width Smoke Glass

Jalousies w/ Aluminum Holder 1 set 500.00 500.00

TOTAL DIRECT COST OF GLASS WORK

9. STEEL WORKS (WINDOW GRILLES)

a. Materials:

W-1 (1 Unit)

10mm x 10mm x 6.00m. M.S. Square Bar 1 pc. 260.00 260.00

12mm x 12mm x 6.00m. M.S. Square Bar 1 pc. 311.00 311.00

6mm thk. x 20mm x 6.00m. M.S. Flat Bar 1 pc. 700.00 700.00

Hack Saw Blade 4 pcs. 65.00 260.00

6011 Welding Rod 5 kgs 160.00 800.00

W-2 (2 Units)

10mm x 10mm x 6.00m. Square bars 1 pc. 260.00 260.00

12mm x 12mm x 6.00m. Square bars 10 pcs. 311.00 3,110.00

6mm thk. x 20mm x 6.00m. M.S. Flat bars 3 pcs. 700.00 2,100.00

Hack Saw Blade 4 pcs. 65.00 260.00

6011 Welding Rod 8 kgs 160.00 1,280.00

b. Labors:

1 -Welder 3 days 394.00 1,182.00

2 -Contractual Laborers 3 days 317.00 1,902.00

c. Equipment:

1 - Unit Welding Machine w/ Cutting Outfit 3 days 2,200.00 6,600.00

1 Unit Disk Grinder 3 days 300.00 900.00

4" Grinding Disk 4 pcs. 180.00 720.00

TOTAL DIRECT COST OF STEEL WORKS (Window Grilles)

10. WATER PROOFING WORKS (LUMP SUM)

Bituminous Membrane Polyester Reinforced Water Proofing 11 sq.mtr. 1,000.00 11,000.00

TOTAL DIRECT COST OF WATER PROOFING WORKS (LUMP SUM)

11. PAINTING WORKS (120.00 Sq. M.)

a. Materials:

Concrete Neutralizer 3 gals. 320.00 960.00

Solvent Based Acrylic Paint Primer 5 gals. 1,050.00 5,250.00

Solvent Based Acrylic Cast 4 gals. 500.00 2,000.00

Solvent Based Acrylic Paint Top Coat White Gloss 10 gals. 1,050.00 10,500.00

Solvent Based Acrylic Reducer 4 gals. 420.00 1,680.00

Lacquer thinner 2 gals. 250.00 500.00

Body Filler w/ Hardener 1 gal 620.00 620.00

Sand paper#150 1 doz. 150.00 150.00

Sand paper#120 1 doz. 150.00 150.00

Red Tinting Color for Solvent Based Acrylic Paint 2 pints 105.00 210.00

Raw Sienna Tinting Color for Solvent Based Acrylic Paint 6 pints 105.00 630.00

Thalo Blue Tinting Color for Solvent Based Acrylic Paint 4 pints 105.00 420.00

Lamp Black Tinting Color for Solvent Based Acrylic Paint 2 pints 105.00 210.00

Red Lead Paint Primer 2 qrts. 143.00 286.00

Quick Dry Enamel (Royal Blue) 2 qrts. 155.00 310.00

7" Roller Brush w/ Handle 2 sets 68.00 136.00

7" Paint Tray 1 pc. 30.00 30.00

2" Steel Brush 1 pc. 25.00 25.00

3" Paint Brush 1 pc. 30.00 30.00

2" Paint Brush 1 pc. 20.00 20.00

b. Labors:

1 - Painter 10 days 366.00 3,660.00

1 - Contractual Laborers 10 days 317.00 3,170.00

TOTAL COST OF PAINTING WORKS

12. CONSTRUCTION OF SEPTIC VAULT (SEALED)

12.1. CONCRETE & REINFORCED STEEL WORKS

a.Materials:

1. Bottom Slab

Portland Cement 6 bags 245.00 1,470.00

Washed Sand 0.25 cu.m. 1,000.00 250.00

Gravel (G1) 0.5 cu.m. 1,000.00 500.00

Concrete Water Proofing Compound 6 packs 35.00 210.00

10mmØ x 6.00m. Def. Reinforcing Steel Bars 5 pcs. 190.00 950.00

#16 G.I. Tie Wire 1 kg. 75.00 75.00

2.1.2. Top Slab

Portland Cement 3 bags 245.00 735.00

Washed Sand 0.25 cu.m. 1,000.00 250.00

Pricelist as of February 2013 136 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 137: Dumalon W.S. Ground Tank_Final

Gravel (G1) 0.25 cu.m. 1,000.00 250.00

Concrete Water Proofing Compound 3 packs 35.00 105.00

10mmØ x 6.00m. Def. Reinforcing Steel Bars 10 pcs. 190.00 1,900.00

#16 G.I. Tie Wire 2 kgs. 75.00 150.00

b.Labors:

1 - Mason 2 days 366.00 732.00

2 - Contractual Laborer 2 days 317.00 1,268.00

12.2. MASONRY WORKS

a.Materials:

100mm x 200mm x 400mm Concrete Hollow Block (NLB) 160 pcs. 17.00 2,720.00

Portland Cement 16 bags 245.00 3,920.00

Washed Sand 1 cu.m. 1,000.00 1,000.00

Fine Sand (For Plastering) 0.5 cu.m. 1,400.00 700.00

10mmØ x 6.00m. Def. Reinforcing Steel Bars 14 pcs. 190.00 2,660.00

#16 G.I. Tie Wire 2 kgs. 75.00 150.00

b.Labors:

1 - Mason 2 days 366.00 732.00

1 - Contractual Laborer 2 days 317.00 634.00

12.3. CARPENTRY WORKS

a. Materials:

Forms & Scaffolding

12mm Thk x 1.20m x 2.4m Ordinary Plywood 5 shts. 975.00 4,875.00

30 - pcs. 2" x 2" x 10' Coco Lumber 100 bd.ft. 20.00 2,000.00

30 - pcs. 2" x 3" x 10' Coco Lumber 150 bd.ft. 20.00 3,000.00

4" C.W. Nail 2 kgs. 70.00 140.00

3" C.W. Nail 2 kgs. 70.00 140.00

1-1/2"" C.W. Nail 1 kg. 65.00 65.00

b. Labor:

1 - Carpenter 2 days 366.00 732.00

1 - Contractual Laborer 2 days 317.00 634.00

12.4. Bituminous Membrane Polyester Reinforced Water Proofing 15.7 sq.m. 1,000.00 15,700.00

TOTAL COST OF CONSTRUCTION OF SEPTIC VAULT

TOTAL COST OF OPERATOR'S ROOM

V. CONSTRUCTION OF GUARD HOUSE (2.89 SQ. M.)

1. EXCAVATION WORKS (1.60 CU.M.)

a. Laborers

2 - Laborers 1 day 317.00 634.00

TOTAL COST OF EXCAVATION WORKS

2. CONCRETE WORKS (3.00 Cu.M.)

a. Material:

F (4 Units)

Portland Cement 5 bags 245.00 1,225.00

Washed Sand 0.25 cu.m. 1,000.00 250.00

Gravel (G1) 0.5 cu.m. 1,000.00 500.00

C (4 Units)

Portland Cement 3 bags 245.00 735.00

Washed Sand 0.125 cu.m. 1,000.00 125.00

Gravel (G1) 0.25 cu.m. 1,000.00 250.00

WF (5.60 Ln.M.)

Portland Cement 3 bags 245.00 735.00

Washed Sand 0.125 cu.m. 1,000.00 125.00

Gravel (G1) 0.25 cu.m. 1,000.00 250.00

Floor Lintel Beam (6.90 Ln. M.)

Portland Cement 3 bags 245.00 735.00

Washed Sand 0.125 cu.m. 1,000.00 125.00

Gravel (G1) 0.25 cu.m. 1,000.00 250.00

Door & Window Lintel Beam (4.20 Ln.M.)

Portland Cement 2 bags 245.00 490.00

Washed Sand 0.125 cu.m. 1,000.00 125.00

Gravel (G1) 0.125 cu.m. 1,000.00 125.00

Concrete Floor Slab (2.25 Sq.M.)

Portland Cement 3 bags 245.00 735.00

Washed Sand 0.125 cu.m. 1,000.00 125.00

Gravel (G1) 0.25 cu.m. 1,000.00 250.00

Reinforced Concrete Beam

456,996.00Php

Pricelist as of February 2013 137 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 138: Dumalon W.S. Ground Tank_Final

Portland Cement 3 bags 245.00 735.00

Washed Sand 0.125 cu.m. 1,000.00 125.00

Gravel (G1) 0.25 cu.m. 1,000.00 250.00

Roof Slab & Overhang

Portland Cement 6 bags 245.00 1,470.00

Washed Sand 0.25 cu.m. 1,000.00 250.00

Gravel (G1) 0.5 cu.m. 1,000.00 500.00

Pricelist as of February 2013 138 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 139: Dumalon W.S. Ground Tank_Final

False Beam (0.10 x 0.25m x 20.50 ln.m.)

Portland Cement 5 bags 245.00 1,225.00

Washed Sand 0.25 cu.m. 1,000.00 250.00

Gravel (G1) 0.5 cu.m. 1,000.00 500.00

b. Labor:

1 -Mason 3 days 366.00 1,098.00

4 - Laborer 3 days 317.00 3,804.00

c. Equipment:

1 - Unit One - Bagger Mixer 3 days 1,500.00 4,500.00

1 - Unit Concrete Vibrator 3 days 800.00 2,400.00

TOTAL COST OF CONCRETE WORKS

3. REINFORCED STEEL WORKS ( 660.00 KGS.)

a. Materials:

F (4 Units)

16mm.Ø x 6.00m Deformed Reinf. Steel Bar 5 pcs 480.00 2,400.00

#16 G.I. Tie Wire 0.5 kg. 75.00 37.50

Hacksaw Blade 2 pcs. 65.00 130.00

C (4 Units)

16mm.Ø x 6.00m Deformed Reinf. Steel Bar 16 pcs 480.00 7,680.00

10mm.Ø x 6.00m Deformed Reinf. Steel Bar 9 pcs 190.00 1,710.00

#16 G.I. Tie Wire 3.5 kgs. 75.00 262.50

Hacksaw Blade 3 pcs. 65.00 195.00

WF (5.60 Ln.M.)

12mm.Ø x 6.00m Deformed Reinf. Steel Bar 2 pcs 270.00 540.00

10mm.Ø x 6.00m Deformed Reinf. Steel Bar 3 pcs 190.00 570.00

#16 G.I. Tie Wire 0.5 kg. 75.00 37.50

Hacksaw Blade 2 pcs. 65.00 130.00

Floor Lintel Beam (6.90 Ln. M.)

12mm.Ø x 6.00m Deformed Reinf. Steel Bar 5 pcs 270.00 1,350.00

10mm.Ø x 6.00m Deformed Reinf. Steel Bar 4 pcs 190.00 760.00

#16 G.I. Tie Wire 1.5 kgs. 75.00 112.50

Hacksaw Blade 2 pcs. 65.00 130.00

Door & Window Lintel Beam (4.20 Ln.M.)

12mm.Ø x 6.00m Deformed Reinf. Steel Bar 2 pcs. 270.00 540.00

10mm.Ø x 6.00m Deformed Reinf. Steel Bar 2 pcs. 190.00 380.00

#16 G.I. Tie Wire 0.5 kg. 75.00 38.00

Hacksaw Blade 1 pc. 65.00 65.00

Concrete Floor Slab (2.25 Sq.M.)

10mm.Ø x 6.00m Deformed Reinf. Steel Bar 4 pcs 190.00 760.00

#16 G.I. Tie Wire 1 kg. 75.00 75.00

Hacksaw Blade 1 pc. 65.00 65.00

Reinforced Concrete Beam

16mm.Ø x 6.00m Deformed Reinf. Steel Bar 8 pcs 480.00 3,840.00

10mm.Ø x 6.00m Deformed Reinf. Steel Bar 10 pcs 190.00 1,900.00

#16 G.I. Tie Wire 2 kgs. 75.00 150.00

Hacksaw Blade 4 pcs. 65.00 260.00

Roof Slab & Overhang

12mm.Ø x 6.00m Deformed Reinf. Steel Bar 24 pcs 270.00 6,480.00

#16 G.I. Tie Wire 3 kgs. 75.00 225.00

Hacksaw Blade 8 pcs. 65.00 520.00

False Beam (0.10 x 0.25m x 20.50 ln.m.)

12mm.Ø x 6.00m Deformed Reinf. Steel Bar 12 pcs 240.00 2,880.00

10mm.Ø x 6.00m Deformed Reinf. Steel Bar 11 pcs 190.00 2,090.00

#16 G.I. Tie Wire 4 kgs. 75.00 300.00

Hacksaw Blade 8 pcs. 65.00 520.00

b. Labor:

1 -Steelman 8 days 366.00 2,928.00

2 - Laborer 8 days 317.00 5,072.00

TOTAL COST OF REINFORCED STEEL WORKS

4. MASONRY WORKS

4.1. Laying of CHB (17.60 Sq. M.)

a. Material:

150mm x 200mm x 400mm CHB (LB) 42 pcs. 24.00 1,008.00

100mm x 200mm x 400mm CHB (NLB) 185 pcs. 17.00 3,145.00

Portland Cement 16 bags 245.00 3,920.00

Washed Sand 1.25 cu.m. 1,000.00 1,250.00

Pricelist as of February 2013 139 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 140: Dumalon W.S. Ground Tank_Final

10mm.Ø x 6.00m Deformed Reinf. Steel Bar 12 pcs. 190.00 2,280.00

#16 G.I. Tie Wire 5 kgs. 75.00 375.00

Hacksaw Blade 8 pcs. 65.00 520.00

b. Labor:

1 - Mason 3 days 366.00 1,098.00

1 - Laborer 3 days 317.00 951.00

4.2. Plastering Works (53.25 Sq.M.)

a. Material

Portland Cement 10 bags 245.00 2,450.00

Fine Sand (For Plastering) 0.75 cu.m. 1,400.00 1,050.00

b. Labor:

1 - Mason 4 days 366.00 1,464.00

1 - Laborer 4 days 317.00 1,268.00

TOTAL COST OF MASONRY WORKS

5. TILE WORKS (2.56 Sq. M.)

a. Material:

400mm x 400mm Granite Tiles 17 pcs. 255.00 4,335.00

Tile Adhesive (25Kg/Bag) 1 bag 305.00 305.00

Tile Grout (2 Kg./Pack) 1 bag 85.00 85.00

4" Grinding Wheel 1 pc. 180.00 180.00

b. Labor:

1 - Mason 2 days 366.00 732.00

1 - Laborer 2 days 317.00 634.00

c. Equipment Rental:

1 - Unit Tile Cutter 2 days 300.00 600.00

1 - Angular Grinder 2 days 300.00 600.00

TOTAL COST OF TILE WORKS

6. FORM & SCAFFOLDING WORKS

a. Materials:

40 pcs. - 2" x 2" x 10" Coco Lumber 133 bd.ft. 20.00 2,660.00

40 pcs. - 2" x 3" x 10" Coco Lumber 200 bd.ft. 20.00 4,000.00

20 pcs. - 2" x 4" x 10" Coco Lumber 133 bd.ft. 20.00 2,660.00

12mm Thk x 1.20 m x 2.40 m Ordinary Plywood 8 shts. 975.00 7,800.00

1-1/2" C.W. Nail 2 kgs. 65.00 130.00

3" C.W. Nail 3 kgs. 70.00 210.00

4" C.W. Nail 3 kgs. 70.00 210.00

b. Labor:

1 - Carpenter 4 days 366.00 1,464.00

1 - Laborer 4 days 317.00 1,268.00

TOTAL COST OF FORM & SCAFFOLDING WORKS

7. CARPENTRY WORKS

7.1. Intallation of Pre-Fabricated of Doors & Windows:

a. Material:

Prefabricated - 0.60m x 2.10m Pannel Type Door, 50mm x 150mm Mahogany Wood Door Frame 1 unit 4,400.00 4,400.00

& 38mm Thick Door Board w/ 50mm x 100mm Mahogany Wood Door Jamb

Prefabricated - 0.70m x 1.165m 1-Pannel Window Jamb, 50mm x 150mm Mahogany Wood 2 units 800.00 1,600.00

Chrome Heavy Duty Door Knob 1 unit 950.00 950.00

Stainless Door Stopper 1 unit 170.00 170.00

4" x 3" Loose Pin Hinges w/ Screw 4 pcs. 140.00 560.00

4" C.W. Nail 1 kg. 70.00 70.00

b. Labor:

1 - Carpenter 2 days 366.00 732.00

1 - Laborer 2 days 317.00 634.00

7.2. Fabrication of Cabinet

a. Material:

Cabinet Handle (Chrome) 5 pcs. 160.00 800.00

Cabinet Concealed Hinges w/ Screw 10 pcs. 60.00 600.00

3 pcs. - 1" x 1" x 10' Mahogany Lumber 2.5 bd.ft. 34.00 85.00

19mm Thk x 1.20m x 2.40m Plyboard 5 shts. 1,100.00 5,500.00

6mm Thk x 1.20m x 2.40m Plyboard 2 shts. 420.00 840.00

3" C.W. Nail 2 kgs. 70.00 140.00

1" C.W. Finishing Nail 2 kgs. 75.00 150.00

b. Labor:

1 - Carpenter 5 days 366.00 1,830.00

1 - Laborer 5 days 317.00 1,585.00

TOTAL COST OF CARPENTRY WORKS

Pricelist as of February 2013 140 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 141: Dumalon W.S. Ground Tank_Final

8. STEEL WORKS

a. Material:

10mm x 10mm x 6.00m M.S. Square Bar 1 pc. 260.00 260.00

12mm x 12mm x 6.00m M.S. Square Bar 4 pcs. 311.00 1,244.00

6mm Thk x 50mm x 6.00m M.S. Flat Bar 2 pcs. 880.00 1,760.00

Hacksaw Blade 4 pcs. 65.00 260.00

6011 Welding Rod 8 kgs 160.00 1,280.00

Industrial Oxygen (Content) 2 cyls. 750.00 1,500.00

Acetylene (Content) 1 cyl. 1,500.00 1,500.00

b. Labor:

1 - Welder 3 days 394.00 1,182.00

1 - Laborer 3 days 317.00 951.00

c. Equipment Rental/Fuel:

1 - Unit Welding Machine w/ Cutting Outfit 3 days 2,200.00 6,600.00

1 - Unit Disk Grinder 3 days 400.00 1,200.00

4" Grinding Wheel 1 pc. 180.00 180.00

TOTAL COST OF STEEL WORKS

9 GLASS WORKS (LUMP SUM)

Supply & Installation of 5.5 mm Thk x 13 Blades x 0.60m width Smoke Glass Jalousies

w/ Aluminum Holder 2 sets 800.00 1,600.00

TOTAL DIRECT COST OF GLASS WORK (LUMP SUM)

10. PLUMBING WORKS

a. Materials:

50mmØ x 3.00m. PVC Sanitary Pipe Series 1000 2 pcs. 306.00 612.00

50mmØ x 900 PVC Sanitary Elbow, Series 1000 3 pcs. 45.00 135.00

50mmØ PVC Coupling, Series 1000 2 pcs. 80.00 160.00

PVC Solvent Cement 1 qrt. 334.00 334.00

100mm x 100mmStainless Floor Drain 1 pc. 68.00 68.00

b. Labors:

1 - Plumber 1 day 366.00 366.00

1 - Contractual Laborers 1 day 317.00 317.00

TOTAL DIRECT COST OF PLUMBING WORKS

11. WATERPROOFING WORKS (LUMP SUM)

Bituminous Membrane Polyester Reinforced Waterproofing 2.9 sq.mtr. 1,000.00 2,900.00

TOTAL DIRECT COST OF WATERPROOFING WORKS (LUMP SUM)

12. PAINTING WORKS (48.00 Sq. M.)

a. Materials:

Concrete Neutralizer 1 gal. 320.00 320.00

Solvent Based Acrylic Paint Primer 2 gals. 1,050.00 2,100.00

Solvent Based Acrylic Cast 1 gal. 400.00 400.00

Solvent Based Acrylic Paint Top Coat White Gloss 4 gals. 1,050.00 4,200.00

Solvent Based Acrylic Paint Reducer 1 gal. 420.00 420.00

Body Filler w/ Hardener 1 gal. 520.00 520.00

#150 Sand Paper 1 doz. 150.00 150.00

#120 Sand Paper 1 doz. 150.00 150.00

Raw Sienna Tinting Color for Solvent Based Acrylic Paint 1 pint 105.00 105.00

Thalo Blue Tinting Color for Solvent Based Acrylic Paint 1 pint 105.00 105.00

Lamp Black Tinting Color for Solvent Based Acrylic Paint 1 pint 105.00 105.00

Steel Brush 1 pc. 25.00 25.00

3" Paint Brush 1 pc. 30.00 30.00

2" Paint Brush 1 pc. 20.00 20.00

b. Labors:

1 - Painter 5 days 366.00 1,830.00

1 - Laborer 5 days 317.00 1,585.00

TOTAL COST OF PAINTING WORKS

TOTAL COST OF CONSTRUCTION OF GUARD HOUSE 175,801.00

Pricelist as of February 2013 141 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 142: Dumalon W.S. Ground Tank_Final

VI. CONSTRUCTION OF (2.73 SQ. MTR.) CHLORINE ROOM

1. CONCRETE & REINFORCED STEEL WORKS

a.Materials:

1.1 Wall

Portland Cement 12 bags 245.00 2,940.00

Washed Sand 0.5 cu.m. 1,000.00 500.00

Gravel (G1) 1.25 cu.m. 1,000.00 1,250.00

10mmØ x 6.00m. Deformed Reinf. Steel Bar 18 pcs. 190.00 3,420.00

12mmØ x 6.00m. Deformed Reinf. Steel Bar 8 pcs. 270.00 2,160.00

#16 G.I. Tie Wire 3 kgs. 75.00 225.00

1.2 Roof Slab

Portland Cement 7 bags 245.00 1,715.00

Washed Sand 0.25 cu.m. 1,000.00 250.00

Gravel (G1) 0.5 cu.m. 1,000.00 500.00

Concrete Water Proofing Compound (900 g) 7 packs 35.00 245.00

12mm

Ø x 6.00m. Deformed Reinf. Steel Bar 18 pcs. 270.00 4,860.00

#16 G.I. Tie Wire 3 kgs. 75.00 225.00

1.3 Floor Slab

Portland Cement 3 bags 245.00 735.00

Washed Sand 0.25 cu.m. 1,000.00 250.00

Gravel (G1) 0.5 cu.m. 1,000.00 500.00

10mm

Ø x 6.00m. Deformed Reinf. Steel Bar 7 pcs. 190.00 1,330.00

#16 G.I. Tie Wire 1 kg. 75.00 75.00

1.4. Door Lintel Beam

Portland Cement 2 bags 245.00 490.00

Washed Sand 0.125 cu.m. 1,000.00 125.00

Gravel (G1) 0.125 cu.m. 1,000.00 125.00

12mm

Ø x 6.00m. Deformed Reinf. Steel Bar 1 pc. 270.00 270.00

10mm

Ø x 6.00m. Deformed Reinf. Steel Bar 1 pc. 190.00 190.00

#16 G.I. Tie Wire 1 kgs. 75.00 75.00

b. Labors:

1 - Mason 7 days 366.00 2,562.00

2 - Contractual Laborers 7 days 317.00 4,438.00

TOTAL COST OF CONCRETE & REINFORCED STEEL WORKS

2. MASONRY WORKS

a.Materials:

1. CHB Laying & Plastering Works

100mm x 200mm x 400mm CHB (NLB) 70 pcs. 17.00 1,190.00

Portland Cement 10 bags 245.00 2,450.00

Washed Sand 0.25 cu.m. 1,000.00 250.00

Fine Sand (For Plastering) 0.5 cu.m. 1,400.00 700.00

10mm dia x 6.00m Deformed Reinf. Steel Bar 5 pcs. 190.00 950.00

#16 G.I. Tie Wire 1 kg. 75.00 75.00

b.Labor:

1 - Mason 3 days 366.00 1,098.00

1 - Contractual Laborers 3 days 317.00 951.00

TOTAL COST OF MASONRY WORKS

3. CARPENTRY WORKS

3.1 Installation of Pre-Fabricated PVC Door

a.Materials:

Pre-fabricated 800mm x 2100mm PVC Door w/ Jamb, Door Knob, Hinges & Screw 1 unit 2,200.00 2,200.00

Stainless Door Knob (Heavy Duty) 1 unit 950.00 950.00

3.2. Forms & Scaffolding Works

a. Materials:

12mm Thk x 1.20m x 2.40m Ordinary Plywood 5 shts. 975.00 4,875.00

40 - pcs. 2" x 2" x 10' Coco Lumber 133 bd.ft. 20.00 2,660.00

40 - pcs. 2" x 3" x 10' Coco Lumber 200 bd.ft. 20.00 4,000.00

4" C.W. Nail 4 kgs. 70.00 280.00

3" C.W. Nail 4 kgs. 70.00 280.00

1-1/2" C.W. Nail 2 kgs. 65.00 130.00

b.Labor:

1 - Carpenter 4 days 366.00 1,464.00

2 - Laborer 4 days 317.00 2,536.00

TOTAL COST OF CARPENTRY WORKS

Pricelist as of February 2013 142 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 143: Dumalon W.S. Ground Tank_Final

4. PAINTING WORKS

a. Materials:

Solvent Based Acrylic Paint Primer 1 gal. 1,050.00 1,050.00

Solvent Based Acrylic Cast 1 gal. 500.00 500.00

Solvent Based Acrylic Top Coat White Gloss Paint 2 gals. 1,050.00 2,100.00

Solvent Based Acrylic Paint Reducer 1 gal. 420.00 420.00

Red Tinting Color for Solvent Based Acrylic Paint 1 pint 105.00 105.00

Raw Sienna Tinting Color for Solvent Based Acrylic Paint 1 pint 105.00 105.00

Thalo Blue Tinting Color for Solvent Based Acrylic Paint 1 pint 105.00 105.00

Lamp Black Tinting Color for Solvent Based Acrylic Paint 1 pint 105.00 105.00

3" Paint Brush 1 pc. 30.00 30.00

b. Labors:

1 - Painter 3 days 317.00 951.00

1 - Laborer 3 days 317.00 951.00

TOTAL COST OF PAINTING WORKS

5. WATER PROOFING WORKS (LUMP SUM)

6.21 sq.mtr. 1,000.00 6,210.00

TOTAL COST OF WATER PROOFING WORKS

TOTAL COST OF CHLORINE ROOM

VII. CONSTRUCTION OF 200MM Ø & 300MM Ø RCCP DRAINAGE SYSTEM

1. CATCH BASIN/MANHOLE

1.1. EXCAVATION WORKS

b. Labor:

1 - Skilled Worker 3 days 366.00 1,098.00

4 - Laborer 3 days 317.00 3,804.00

TOTAL COST OF EXCAVATION WORKS

1.2. CONCRETE & REINFORCED STEEL WORKS

Portland Cement 28 bags 245.00 6,860.00

Washed Sand 1.5 cu.m. 1,000.00 1,500.00

Gravel (G1) 3 cu.m. 1,000.00 3,000.00

10mmØ x 6.00m Deformed Reinf. Steel Bar 26 pcs. 190.00 4,940.00

#16 G.I. Tie Wire 2 kgs. 75.00 150.00

b. Labor:

1 - Mason 8 days 366.00 2,928.00

1 - Laborer 8 days 317.00 2,536.00

TOTAL COST OF CONCRETE & REINFORCED STEEL WORKS

1.3. MASONRY WORKS

100mm x 200mm x 400mm CHB (NLB) 330 pcs. 17.00 5,610.00

Portland Cement 14 bags 245.00 3,430.00

Washed Sand 2 cu.m. 1,000.00 2,000.00

Fine Sand (For Plastering) 1 cu.m. 1,400.00 1,400.00

b. Labor:

1 - Mason 7 days 366.00 2,562.00

1 - Laborer 7 days 317.00 2,219.00

TOTAL COST OF MASONRY WORKS

2. LAYING OF 200mm Ø & 300mmØ RCCP

300mmØ x 1.0m RCCP 22 pcs. 1,078.00 23,716.00

200mmØ x 1.0m RCCP 16 pcs. 748.00 11,968.00

Portland Cement 9 bags 245.00 2,205.00

Washed Sand 0.5 cu.m. 1,000.00 500.00

b. Labor:

1 - Mason 7 days 366.00 2,562.00

8 - Laborer 7 days 317.00 17,752.00

TOTAL COST OF LAYING OF 200mm Ø & 300mmØ RCCP

TOTAL COST OF CONSTRUCTION OF 300MM Ø RCCP DRAINAGE SYSTEM

69,126.00

102,740.00

Pricelist as of February 2013 143 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 144: Dumalon W.S. Ground Tank_Final

VIII. CONSTRUCTION OF CONCRETE CATWALK/DRIVE WAY

1. Concrete Walk Pad

a. Materials:

Portland Cement 21 bags 245.00 5,145.00

Washed Sand 1.25 cu.m. 1,000.00 1,250.00

Gravel (G1) 2.5 cu.m. 1,000.00 2,500.00

10mmØ x 6.00m Def. Reinf. Steel Bar 25 pcs. 190.00 4,750.00

#16 G.I. Tie-wire 3 kgs. 65.00 195.00

Hacksaw Blade 4 pcs. 65.00 260.00

2. 150mm Thk Concrete Driveway (106 Sq.M.)

a. Materials:

Portland Cement 141 bags 245.00 34,545.00

Washed Sand 7 cu.m. 1,000.00 7,000.00

Gravel (G1) 10.5 cu.m. 1,000.00 10,500.00

Item 201 (Aggregates Base Course) 25 cu.m. 800.00 20,000.00

Item 200 (Aggregates Sub-Base Course) 25 cu.m. 450.00 11,250.00

8 pcs. - 1" x 6" x 8' Coco Lumber 32 bd.ft. 20.00 640.00

40 pcs. - 2" x 2" x 8' Coco Lumber 107 bd.ft. 20.00 2,140.00

4" C.W. Nail 2 kgs. 70.00 140.00

3" C.W. Nail 2 kgs. 70.00 140.00

b. Labor:

2 - Skilled Workers 8 days 366.00 5,856.00

8 - Laborer 8 days 317.00 20,288.00

c. Equipment Rental/Fuel:

1 - Unit Concrete Vibrator 5 days 800.00 4,000.00

1 - Unit One - Bagger Mixer 5 days 1,500.00 7,500.00

TOTAL COST OF CONSTRUCTION OF CONCRETE CATWALK/DRIVE WAY

IX. LANDSCAPING WORKS

a. Materials:

Garden Soil 6 cu.m. 1,200.00 7,200.00

Carabao Grass 35 sq.m. 320.00 11,200.00

b. Labor:

2 - Skilled Workers 5 days 366.00 3,660.00

2 - Laborer 5 days 317.00 3,170.00

c. Equipment Rental:

1 - Unit Compact Hand Roller 5 days 7,200.00 36,000.00

TOTAL COST OF LANDSCAPING WORKS

X. ELECTRICAL WORKS

TOTAL NUMBER OF OUTLETS: 31

1. MOBILIZATION/DEMOBILIZATION 1 lot 2,000.00 2,000.00

2. SUPPLY, TESTING & INSTALLATION OF KW-HR METER, RACEWAY AND ACCESSORIES

a. Material

Kiliwatthour Meter (Digital), 250 Volts, Single Phase, Assembly, 1 assy. 8,160.00 8,160.00

GE Class 200, 5 jaw, complete w/ Rectangular Base

Testing/Calibration FEE 1 lot 100.00 100.00

25mmØ Entrance Cap 1 pc. 41.00 41.00

25mmØ x 3m RSC Conduit Pipe 1 pc. 367.00 367.00

25mmØ RSC Male Adaptor 1 pc. 8.00 8.00

25mmØ Locknut 1 pc. 6.00 6.00

25mmØ Conduit Pipe Clamp 4 pc. 7.00 28.00

Single Wire, Secondary Rack w/ Spool Insulator 1 pc. 142.00 142.00

b. Labor:

1 - Skilled Worker 1 day 366.00 366.00

1 - Laborer 1 day 317.00 317.00

Direct Cost

3. SUPPLY & INSTALLATION OF ELECTRICAL FACILITIES FOR OPERATORS ROOM

a. Material

60 Amperes Main Circuit Breaker, Single Phase, 250 Volts, Panel Board 1 set 5,766.00 5,766.00

enclosed in Powder Coated Finished Panel Box

with 5 Single Phase Branches of:

1 sets - 15 Amps. Branch

4 sets - 20 Amps. Branch

8.0mm2 THW Stranded Wire 60 mtrs. 84.00 5,040.00

3.5mm2 TW Stranded Wire 92 mtrs. 32.00 2,944.00

2.0mm2 TW Stranded Wire 75 mtrs. 23.00 1,725.00

25mmØ Entrance Cap 1 pc. 41.00 41.00

25mmØ x 3m PVC Conduit Pipe 1 pc. 131.00 131.00

25mmØ x 90o PVC Long Sweep Elbow 1 pc. 26.00 26.00

25mmØ PVC Male Adaptor 1 pc. 8.00 8.00

25mmØ Locknut 1 pc. 6.00 6.00

Pricelist as of February 2013 144 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 145: Dumalon W.S. Ground Tank_Final

20mmØ Flexible Conduit 48 pcs. 8.00 384.00

20mmØ x 3m PVC Conduit Pipe 15 pcs. 86.00 1,290.00

20mmØ x 90o PVC Long Sweep Elbow 10 pcs. 17.00 170.00

20mmØ PVC Male Adaptor 12 pcs. 6.00 72.00

20mmØ PVC Coupling 8 pcs. 5.00 40.00

20mmØ Locknut 12 pcs. 4.00 48.00

Single Wire, Secondary Rack w/ Spool Insulator 1 pc. 142.00 142.00

Surface Type Reflectorized/Mirrorized Fluorescent Luminaire with 1x40 Watts Fluorescent Tube 2 pcs. 1,132.00 2,264.00

23 Watts 3U CFL with Capsule 3 pcs. 148.00 444.00

18" Ceiling Orbit Fan, Industrial Type 1 pc. 5,477.00 5,477.00

Switch 1-Gang w/ plate (flush type), w/ Led Set, 10A, 250V 1 pc. 71.00 71.00

Switch 2-Gang w/ plate (flush type), w/ Led Set, 10A, 250V 2 pcs. 107.00 214.00

Ceiling Socket with screw 3 pcs. 31.00 93.00

Duplex Convenience Outlet w/ plate (flush type) 3 pcs. 107.00 321.00

Duplex Convenience Outlet w/ plate - weatherproof (flush type) 1 pc. 173.00 173.00

2" x 4" x 2" PVC Utility Box ( H.D.) 7 pcs. 21.00 147.00

4" x 4" PVC Junction Box ( H.D.) w/ Cover 9 pcs. 24.00 216.00

#16 G.I. Tie Wire 3 kgs. 75.00 225.00

PVC Solvent Cement 1 qrt. 460.00 460.00

1/4" Camridge / Mica Tube 1 mtrs. 13.00 13.00

0.8mm x 19mm x 8m Polytype Electrical Tape 5 pcs. 25.00 125.00

0.8mm x 19mm x 8m Rubber Tape 2 pcs. 102.00 204.00

b. Labor

1 - Skilled Worker 7 days 366.00 2,562.00

1 - Laborer 7 days 317.00 2,219.00

Direct Cost

4. SUPPLY & INSTALLATION OF ELECTRICAL FACILITIES FOR GUARD HOUSE & CHLORINATOR ROOM

a. Material

35W E27 CFL Weather Proof Street Light 1 pc. 500.00 500.00

3.5mm2 TW Stranded Wire 1 roll 4,725.00 4,725.00

20mmØ Flexible Conduit 16 pcs. 8.00 128.00

20mmØ x 3m PVC Conduit Pipe 15 pcs. 86.00 1,290.00

20mmØ x 90o PVC Long Sweep Elbow 10 pcs. 17.00 170.00

20mmØ PVC Male Adaptor 12 pcs. 6.00 72.00

20mmØ PVC Coupling 8 pcs. 5.00 40.00

20mmØ Locknut 12 pcs. 4.00 48.00

Surface Type Reflectorized/Mirrorized Fluorescent Luminaire with 1x20 Watts Fluorescent Tube 1 pc. 977.00 977.00

23 Watts 3U CFL with Capsule 3 pcs. 148.00 444.00

23 Watts PAR 38 Floodlight CFL bulb with Par Lamp Holder 1 pc. 928.00 928.00

Switch 1-Gang w/ plate (flush type), w/ Led Set, 10A, 250V 1 pc. 71.00 71.00

Switch 2-Gang w/ plate (flush type), w/ Led Set, 10A, 250V 1 pc. 107.00 107.00

Switch 3-Gang w/ plate (flush type), w/ Led Set, 10A, 250V 1 pc. 143.00 143.00

Ceiling Socket with screw 4 pcs. 31.00 124.00

Duplex Convenience Outlet w/ plate (flush type) 2 pcs. 107.00 214.00

2" x 4" x 2" PVC Utility Box ( H.D.) 5 pcs. 21.00 105.00

4" x 4" PVC Junction Box ( H.D.) w/ Cover 13 pcs. 24.00 312.00

#16 G.I. Tie Wire 2 kgs. 75.00 150.00

PVC Solvent Cement 1 qrt. 460.00 460.00

1/4" Camridge / Mica Tube 0.5 mtr. 13.00 7.00

0.8mm x 19mm x 8m Polytype Electrical Tape 5 pcs. 25.00 125.00

0.8mm x 19mm x 8m Rubber Tape 2 pcs. 102.00 204.00

b. Labor

1 - Skilled Worker 7 days 366.00 2,562.00

1 - Laborer 7 days 317.00 2,219.00

Direct Cost

5. SUPPLY & INSTALLATION OF ELECTRICAL FACILITIES FOR SIGNAGE AND PERIMETER LIGHTINGS

a. Material

3.5mm2 TW Stranded Wire 2 rolls 4,725.00 9,450.00

20mmØ x 3m PVC Conduit Pipe 35 pcs. 86.00 3,010.00

20mmØ x 90o PVC Long Sweep Elbow 8 pcs. 17.00 136.00

20mmØ PVC Male Adaptor 36 pcs. 6.00 216.00

20mmØ PVC Coupling 18 pcs. 5.00 90.00

20mmØ Locknut 12 pcs. 4.00 48.00

Perimeter post lamp with cage, globe type, (250mmx250mm)

complete assembly with 23 watts Capsulated CFL 6 sets 1,770.00 10,620.00

4" x 4" PVC Junction Box ( H.D.) w/ Cover 16 pcs. 24.00 384.00

#16 G.I. Tie Wire 3 kgs. 75.00 225.00

PVC Solvent Cement 1 qrt. 460.00 460.00

1/4" Camridge / Mica Tube 2 mtrs. 13.00 26.00

0.8mm x 19mm x 8m Polytype Electrical Tape 5 pc. 25.00 125.00

0.8mm x 19mm x 8m Rubber Tape 2 pc. 102.00 204.00

b. Labor

1 - Skilled Worker 7 days 366.00 2,562.00

1 - Laborer 7 days 317.00 2,219.00

Direct Cost

Pricelist as of February 2013 145 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 146: Dumalon W.S. Ground Tank_Final

TOTAL COST OF ELECTRICAL WORKS

2. CONSTRUCTION OF 300 CU.M. GROUND RESERVOIR AT BALUNO, Z.C.

I. MOBILIZATION/DEMOBILIZATION/HAULING OF MATERIAL

1. MOBILIZATION/DEMOBILIZATION 1 lot 50,000.00 50,000.00

2. HAULING OF MATERIALS

a. Labor:

4 - Laborer 30 days 317.00 38,040.00

b. Equipment Rental/Fuel

1 - Unit Hauling Truck (w/ Operator & Fuel) 30 days 9,600.00 288,000.00

TOTAL COST OF MOBILIZATION/DEMOBILIZATION/HAULING OF MATERIAL

II. CONSTRUCTION OF 300.00 CU.M. GROUND TANK

1. CLEARING & EXCAVATION WORKS (262.00 Cu.M.)

a. Labors:

4 -Contractual Laborer 5 days 366.00 7,320.00

b. Equipment/Fuel:

1 - Unit Backhoe (w/ Fuel & Operator) 5 days 8,000.00 40,000.00

1 - Unit Water Pump (w/ Fuel) 2 days 600.00 1,200.00

1 - Unit Powersaw (w/ Operator & Fuel) 2 days 2,000.00 4,000.00

TOTAL COST OF EXCAVATION WORKS

2. SCAFFOLDING & FORM WORKS

a. Materials:

800 - pcs. 2" x 2" x 10' Coco Lumber 2667 bd.ft. 20.00 53,340.00

600 - pcs. 2" x 3" x 10' Coco Lumber 3000 bd.ft. 20.00 60,000.00

400 - pcs. 2" x 4" x 10' Coco Lumber 2667 bd.ft. 20.00 53,340.00

12mmThk. x 1.20m. x 2.40m. Ordinary Plywood 140 shts. 975.00 136,500.00

4" C.W. Nail 50 kgs. 70.00 3,500.00

3" C.W. Nail 40 kgs. 70.00 2,800.00

1-1/2" C.W. Nail 30 kgs. 65.00 1,950.00

b. Labors:

4 - Carpenter 30 days 366.00 43,920.00

8 - Laborer 30 days 317.00 76,080.00

TOTAL COST OF SCAFFOLDING & FORM WORKS

3. CONCRETE WORKS (148.20 Cu.M.)

a. Materials:

3.1. Lean Concrete (50mm Thk x 105.00 Sq.M.)

Portland Cement 48 bags 245.00 11,760.00

Washed Sand 4.5 cu.m. 1,000.00 4,500.00

3.2. Footing (F-3) (4 Units):

Portland Cement 30 bags 245.00 7,350.00

Washed Sand 1.25 cu.m. 1,000.00 1,250.00

Gravel (G1) 2 cu.m. 1,000.00 2,000.00

150mm Boulders 1.5 cu.m. 1,000.00 1,500.00

Concrete Waterproofing Compound (900g) 30 packs 30.00 900.00

3.3. Footing (F-4) (6 Units):

Portland Cement 48 bags 245.00 11,760.00

Washed Sand 2 cu.m. 1,000.00 2,000.00

Gravel (G1) 3.25 cu.m. 1,000.00 3,250.00

150mm Boulders 2.5 cu.m. 1,000.00 2,500.00

Concrete Waterproofing Compound (900g) 48 packs 30.00 1,440.00

3.4. Footing (F-1A) (1 Unit):

Portland Cement 3 bags 245.00 735.00

Washed Sand 0.125 cu.m. 1,000.00 125.00

Gravel (G1) 0.25 cu.m. 1,000.00 250.00

150mm Boulders 0.25 cu.m. 850.00 213.00

3.5. Column (C-3) (4 Units):

Portland Cement 30 bags 245.00 7,350.00

Washed Sand 1.25 cu.m. 1,000.00 1,250.00

Gravel (G1) 2 cu.m. 1,000.00 2,000.00

Concrete Addmix (150g) 30 packs 35.00 1,050.00

Concrete Waterproofing Compound (900g) 30 packs 30.00 900.00

3.6. Column (C-4) (6 Units):

Portland Cement 50 bags 245.00 12,250.00

Washed Sand 2.25 cu.m. 1,000.00 2,250.00

Gravel (G1) 3.25 cu.m. 1,000.00 3,250.00

Concrete Addmix (150g) 50 packs 35.00 1,750.00

90,496.00

Pricelist as of February 2013 146 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 147: Dumalon W.S. Ground Tank_Final

Concrete Waterproofing Compound (900g) 50 packs 30.00 1,500.00

3.7. Column (C-1A) (1 Unit):

Portland Cement 3 bags 245.00 735.00

Washed Sand 0.125 cu.m. 1,000.00 125.00

Gravel (G1) 0.25 cu.m. 1,000.00 250.00

3.8. Tie Beam (TB) (2 Units):

Portland Cement 19 bags 245.00 4,655.00

Washed Sand 0.75 cu.m. 1,000.00 750.00

Gravel (G1) 1.25 cu.m. 1,000.00 1,250.00

Concrete Addmix (150g) 19 packs 35.00 665.00

Concrete Waterproofing Compound (900g) 19 packs 30.00 570.00

3.9. Beam (RCB1, RCB2 & RCB3)

Portland Cement 17 bags 245.00 4,165.00

Washed Sand 0.75 cu.m. 1,000.00 750.00

Gravel (G1) 1.25 cu.m. 1,000.00 1,250.00

Concrete Addmix (150g) 17 packs 35.00 595.00

3.10. Wall Footing (L=51.06 m):

Portland Cement 163 bags 245.00 39,935.00

Washed Sand 7 cu.m. 1,000.00 7,000.00

Gravel (G1) 10.75 cu.m. 1,000.00 10,750.00

Concrete Addmix (150g) 163 packs 35.00 5,705.00

Concrete Waterproofing Compound (900g) 163 packs 30.00 4,890.00

3.11. Bottom Slab

Washed Sand (for Ground Tank Bottom Slab Envelope) 30 cu.m. 1,000.00 30,000.00

Portland Cement 131 bags 245.00 32,095.00

Washed Sand 5.75 cu.m. 1,000.00 5,750.00

Gravel (G1) 8.5 cu.m. 1,000.00 8,500.00

Concrete Addmix (150g) 131 packs 35.00 4,585.00

Concrete Waterproofing Compound (900g) 131 packs 30.00 3,930.00

3.12. Top Slab

Portland Cement 155 bags 245.00 37,975.00

Washed Sand 7 cu.m. 1,000.00 7,000.00

Gravel (G1) 10.25 cu.m. 1,000.00 10,250.00

Concrete Addmix (150g) 155 packs 35.00 5,425.00

Concrete Waterproofing Compound (900g) 155 packs 30.00 4,650.00

3.13. Stair

Portland Cement 20 bags 245.00 4,900.00

Washed Sand 0.75 cu.m. 1,000.00 750.00

Gravel (G1) 1.25 cu.m. 1,000.00 1,250.00

3.14. Wall (L = 51.06m)

Portland Cement 576 bags 245.00 141,120.00

Washed Sand 25.5 cu.m. 1,000.00 25,500.00

Gravel (G1) 38 cu.m. 1,000.00 38,000.00

Concrete Waterproofing Compound (900g) 576 packs 30.00 17,280.00

Concrete Addmix (150g) 576 packs 35.00 20,160.00

200mm Water Stop 200 ln.mtr. 380.00 76,000.00

3.15. Junction Box

Portland Cement 21 bags 245.00 5,145.00

Washed Sand 0.75 cu.m. 1,000.00 750.00

Gravel (G1) 1.25 cu.m. 1,000.00 1,250.00

Concrete Waterproofing Compound (900g) 18 packs 30.00 540.00

b. Labors:

4 - Mason 32 days 366.00 46,848.00

20 - Contractual Laborers 32 days 317.00 202,880.00

c. Equipment Rental:

1 - Unit Water Pump (w/ Fuel) 16 days 600.00 9,600.00

2 - Units One - Bagger Mixer (w/ Fuel) 32 days 1,500.00 96,000.00

2 - Concrete Vibrator (w/ Fuel) 32 days 1,000.00 64,000.00

TOTAL COST OF CONCRETE WORKS

4. REINFORCED STEEL WORKS (23,329.60 KGS.)

a. Materials:

4.1. Footing (F-1) (4- Units)

25mm

Ø x 6.00m. Deformed Reinf. Steel Bar 40 pcs. 1,045.00 41,800.00

#16 G.I. Tie Wire 3 kgs. 75.00 225.00

4.2. Footing (F-2) (6- Units)

25mm

Ø x 6.00m. Deformed Reinf. Steel Bar 28 pcs. 1,045.00 29,260.00

#16 G.I. Tie Wire 2 kgs. 75.00 150.00

Pricelist as of February 2013 147 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 148: Dumalon W.S. Ground Tank_Final

4.3. Footing (F-3) (1- Unit)

16mm

Ø x 6.00m. Deformed Reinf. Steel Bar 2 pcs. 480.00 960.00

#16 G.I. Tie Wire 1 kg. 75.00 75.00

4.4. Tie Beam (TB) (3 - Units)

25mm

Ø x 6.00m. Deformed Reinf. Steel Bar 14 pcs. 1,045.00 14,630.00

10mm

Ø x 6.00m. Deformed Reinf. Steel Bar 24 pcs. 190.00 4,560.00

#16 G.I. Tie Wire 3 kgs. 75.00 225.00

4.5. Column (C - 1) (4 Units)

25mm

Ø x 6.00m. Deformed Reinf. Steel Bar 48 pcs. 1,045.00 50,160.00

10mm

Ø x 6.00m. Deformed Reinf. Steel Bar 75 pcs. 190.00 14,250.00

#16 G.I. Tie Wire 11 kgs. 75.00 825.00

4.6. Column (C - 2) (6 Units)

25mm

Ø x 6.00m. Deformed Reinf. Steel Bar 48 pcs. 1,045.00 50,160.00

10mm

Ø x 6.00m. Deformed Reinf. Steel Bar 56 pcs. 190.00 10,640.00

#16 G.I. Tie Wire 8 kgs. 75.00 600.00

4.7. Column(C-3) (1- Unit)

16mm

Ø x 6.00m. Deformed Reinf. Steel Bar 2 pcs. 480.00 960.00

10mm

Ø x 6.00m. Deformed Reinf. Steel Bar 2 pcs. 165.00 330.00

#16 G.I. Tie Wire 1 kg. 75.00 75.00

4.8. Wall Footing

25mm

Ø x 6.00m. Deformed Reinf. Steel Bar 44 pcs. 1,045.00 45,980.00

20mm

Ø x 6.00m. Deformed Reinf. Steel Bar 46 pcs. 682.00 31,372.00

#16 G.I. Tie Wire 8 kgs. 75.00 600.00

4.9. Bottom Slab

20mm

Ø x 6.00m. Deformed Reinf. Steel Bar 5 pcs. 682.00 3,410.00

16mm

Ø x 7.50m. Deformed Reinf. Steel Bar 156 pcs. 550.00 85,800.00

16mm

Ø x 6.00m. Deformed Reinf. Steel Bar 70 pcs. 480.00 33,600.00

#16 G.I. Tie Wire 35 kgs. 75.00 2,625.00

4.10. Top Slab

12mm

Ø x 6.00m. Deformed Reinf. Steel Bar 210 pcs. 270.00 56,700.00

#16 G.I. Tie Wire 35 kgs. 75.00 2,625.00

4.11. Stair & Stair Foundation

16mm

Ø x 6.00m. Deformed Reinf. Steel Bar 26 pcs. 480.00 12,480.00

12mm

Ø x 6.00m. Deformed Reinf. Steel Bar 9 pcs. 270.00 2,430.00

10mm

Ø x 6.00m. Deformed Reinf. Steel Bar 53 pcs. 190.00 10,070.00

#16 G.I. Tie Wire 4 kgs. 75.00 300.00

4.12. Beam (RCB 1)

20mm

Ø x 6.00m. Deformed Reinf. Steel Bar 18 pcs. 682.00 12,276.00

10mm

Ø x 6.00m. Deformed Reinf. Steel Bar 19 pcs. 190.00 3,610.00

#16 G.I. Tie Wire 4 kgs. 75.00 300.00

4.13. Beam (RCB 2 & RCB 3) :

20mm

Ø x 6.00m. Deformed Reinf. Steel Bar 8 pcs. 682.00 5,456.00

10mm

Ø x 6.00m. Deformed Reinf. Steel Bar 10 pcs. 190.00 1,900.00

#16 G.I. Tie Wire 2 kgs. 75.00 150.00

4.14. Wall (L=44.00m)

25mm

Ø x 6.00m. Deformed Reinf. Steel Bar 301 pcs. 1,045.00 314,545.00

20mm

Ø x 6.00m. Deformed Reinf. Steel Bar 175 pcs. 682.00 119,350.00

16mm

Ø x 6.00m. Deformed Reinf. Steel Bar 365 pcs. 480.00 175,200.00

12mm

Ø x 7.50m. Deformed Reinf. Steel Bar 26 pcs. 320.00 8,320.00

12mm

Ø x 6.00m. Deformed Reinf. Steel Bar 26 pcs. 270.00 7,020.00

#16 G.I. Tie Wire 35 kgs. 75.00 2,625.00

4.15. Junction Box

10mm

Ø x 6.00m. Plain Round Bars 1 pc. 190.00 190.00

16mm

Ø x 6.00m. Deformed Reinf. Steel Bar 3 pcs. 480.00 1,440.00

12mm

Ø x 6.00m. Deformed Reinf. Steel Bar 24 pcs. 270.00 6,480.00

#16 G.I. Tie Wire 3 kgs. 65.00 195.00

Hacksaw Blade 80 pcs. 75.00 6,000.00

b. Labors:

4 - Steel Man 38 days 366.00 55,632.00

4 - Contractual Laborers 38 days 317.00 48,184.00

c. Equipment:

Bar Bender 38 days 300.00 11,400.00

Bar Cutter 38 days 300.00 11,400.00

TOTAL COST OF REINFORCED STEEL WORKS

Pricelist as of February 2013 148 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 149: Dumalon W.S. Ground Tank_Final

5. MASONRY WORKS (762.00 Sq.M.)

a. Materials:

Portland Cement 90 bags 245.00 22,050.00

Fine Sand (For Plastering) 8.75 cu.m. 1,400.00 12,250.00

b. Labors:

2 - Mason 22 days 366.00 16,104.00

2 - Contractual Laborers 22 days 317.00 13,948.00

TOTAL COST OF MASONRY WORKS

6. STEEL WORKS

a. Materials:

6.1. Manhole Cover w/ Steel Ladder (3- Units)

6mm Thk. x 50mm x 6.0m Stainless Steel Flat Bar 4 pcs. 9,000.00 36,000.00

6mm Thk. x 50mm x 50mm x 6.00m Stainless Angle Bar 2 pcs. 16,000.00 32,000.00

16mmØ x 100mm Stainless Steel L-Type Anchor Bolt w/ Nuts & Washers 18 pcs. 150.00 2,700.00

16mmØ x 6.0m Stainless Plain Round Bar 4 pcs. 12,400.00 49,600.00

1.20m x 2.40m x Ga. No. 16 Stainless Plain Sheet 2 shts. 3,800.00 7,600.00

10mmØ x 6.0m M.S. Plain Round Bar 1 pc. 190.00 190.00

Hacksaw Blade 8 pcs. 65.00 520.00

Welding Rod (6011) 10 kgs. 160.00 1,600.00

Welding Rod (Stainless) 5 kgs. 580.00 2,900.00

6.2. Hand Rail:

50mmØ x 6.0m G.I. Pipe (ASTM A-53 90A Heavy Gauge Standard) 14 pcs. 1,720.00 24,080.00

16mm x 16mm x 6.00m MS Square Bar 50 pcs. 781.00 39,050.00

Hacksaw Blade 20 pcs. 65.00 1,300.00

Welding Rod (6011) 20 kgs. 160.00 3,200.00

Hacksaw Blade 30 pcs. 65.00 1,950.00

6.3. Junction Box

6mm Thk. x 50mm x 6.0m MS Flat Bar 1 pc. 880.00 880.00

16mmØ x 6.0m MS Plain Round Bar 1 pc. 495.00 495.00

6mm Thk. x 50mm x 50mm x 6.0m MS Angle Bar 1 pc. 1,500.00 1,500.00

16mmØ x 100mm Stainless Steel (L-Type) Bolt w/ Nut & Washer 6 pcs. 150.00 900.00

Hacksaw Blade 4 pcs. 65.00 260.00

Welding Rod (6011) 2 kgs. 160.00 320.00

b. Labors:

2 - Welder 30 days 394.00 23,640.00

2 - Contractual Laborers 30 days 317.00 19,020.00

c. Equipment:

1 - Unit Welding Machine 30 days 2,200.00 66,000.00

1 - Unit Disk Grinder 30 days 400.00 12,000.00

4" Grinding Wheel 4 pcs. 180.00 720.00

TOTAL COST OF STEEL WORKS

7. DISINFECTION/LEAKAGE TEST & GROUTING LEAK

a. Materials:

Chlorine Powder 25 kgs. 280.00 7,000.00

Hydraulic Cement (4-Liter/Gal) 40 gals. 1,300.00 52,000.00

b. Labor:

1 - Skilled Worker 6 days 366.00 2,196.00

2 - Contractual Laborer 6 days 317.00 3,804.00

TOTAL COST OF DISINFECTION & LEAKAGE TEST

8. SUPPLY & INST. OF GATE VALVES, DIFFERENTIAL FLOAT CONTROL VALVE & APPURTENANCES

a. Materials:

D1

Supply & Installation of Differential Float Control Valve

Supply & Installation of 100mmØ Differential Float Controlled Valve, F/F 2 units 342,600.00 685,200.00

w/ 2-Units Steel Ring Flange

Specifications:

The valve will be controlled by a differential float-operated, maximum differential level of 4.00 meters,

maximum flowrate equals to 25.00 LPS

The differential float controlled valve will be installed below the water level, constructed with concrete valve box

The valve will be a hydraulically operated, diaphragm actuated,

Face to face length dimension meets ISO 57529S-10 Standard, Flanged end Connection in Accordance w/ ANSI

Maximum pressure rating of PN16 (230 psi)

100mmØ C.I. Sleeve Type Flexible Coupling, (PVC-C.I.) 2 pcs. 3,915.00 7,830.00

100mmØ C.I. Sleeve Type Flexible Coupling, (G.I.-PVC) 2 pcs. 3,915.00 7,830.00

100mmØ C.I. Adaptor, F/P 2 pcs. 2,541.00 5,082.00

6mm thk Rubber Gasket 4 kgs. 75.00 300.00

16mmØ x 100mm Anchor Bolts w/ Nuts & Washer 32 pcs. 125.00 4,000.00

Construction of two (2.0) units concrete valve box

Portland Cement 26 bags 245.00 6,370.00

Pricelist as of February 2013 149 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 150: Dumalon W.S. Ground Tank_Final

Washed Sand 1.25 cu.m. 1,000.00 1,250.00

Gravel (G1) 2.5 cu.m. 1,000.00 2,500.00

16mmØ x 6.00m Deformed Reinf. Steel Bar 46 pcs. 480.00 22,080.00

#16 GI Tie Wire 5 kgs. 75.00 375.00

16mmØ x 6.00m Stainless Steel Round Bar (Type 304) 1 pc. 12,500.00 12,500.00

8mmØ x 6.00m M.S. Plain Round Bar 1 pc. 160.00 160.00

16mmØ x 6.00m M.S. Plain Round Bar 10 pcs. 495.00 4,950.00

38mmØ x 6.00m G.I. Pipe ASTM A53-90A Heavy Gauge Standard 1 pc. 1,800.00 1,800.00

6mm Thk x 50mm x 50mm x 6.00m MS Angle Bar 2 pcs. 1,500.00 3,000.00

12mm Thk x 1.20m x 2.40m Ordinary Plywood 6 shts. 975.00 5,850.00

40 pcs - 2" x 2" x 10' Coco Lumber 133 bd.ft. 20.00 2,660.00

40 pcs - 2" x 3" x 10' Coco Lumber 200 bd.ft. 20.00 4,000.00

40 pcs - 2" x 4" x 10' Coco Lumber 267 bd.ft. 20.00 5,340.00

4" C.W. Nail 2 kgs. 70.00 140.00

3" C.W. Nail 2 kgs. 70.00 140.00

1-1/2" C.W. Nail 1 kg. 65.00 65.00

Hacksaw Blade 12 pcs. 65.00 780.00

Welding Rod (6011) 3 kgs. 160.00 480.00

b. Labor:

3 - Skilled Worker 8 days 366.00 8,784.00

1 - Pipe Fitter 8 days 341.00 2,728.00

6 - Contractual Laborers 8 days 317.00 15,216.00

Valves & Appurtenances:

D2

150mmØ x 6.00m B.I. Pipe, (ASTM A53-90A Heavy Gauge Standard) 1 pc. 16,380.00 16,380.00

150mmØ x 150mmØ C.I. Tee, F/F, Flange End In Accordance w/ ANSI B16.1 Class 125 1 pc. 0.00

150mmØ C.I. Adaptor, F/P, Flange End In Accordance w/ ANSI B16.1 Class 125 1 pcs. 0.00

150mmØ C.I. Sleeve Type Flexible Coupling (PVC-CI) 1 pcs. 0.00

D3 & D4

100mmØ x 45o PVC Bend, Class 150, B/S w/ R.R. 8 pcs. 0.00

100mmØ x 6.00m B.I. Pipe, (ASTM A53-90A Heavy Gauge Standard) 2 pcs. 0.00

100mmØ C.I. Body Gate Valve, F/F, PN16, NRS, Flange End in Accordance w/ ANSI B16.1 Class 125 2 pcs. 0.00

100mmØ C.I. Adaptor, F/P, Flange End In Accordance w/ ANSI B16.1 Class 125 4 pcs. 0.00

100mmØ C.I. Sleeve Type Flexible Coupling (PVC-CI) 4 pcs. 0.00

D3-a & D4-a

200mmØ x 45o PVC Bend, Class 150, B/S w/ R.R. 6 pcs. 5,300.00 31,800.00

200mmØ x 6.00m B.I. Pipe, (ASTM A53-90A Heavy Gauge Standard) 2 pcs. 16,380.00 32,760.00

200mmØ C.I. Body Gate Valve, F/F, PN16, NRS, Flange End in Accordance w/ ANSI B16.1 Class 125 2 pcs. 17,700.00 35,400.00

200mmØ C.I. Adaptor, F/P, Flange End In Accordance w/ ANSI B16.1 Class 125 4 pcs. 4,956.00 19,824.00

200mmØ C.I. Sleeve Type Flexible Coupling (PVC-CI) 4 pcs. 4,170.00 16,680.00

Entrance Pipe:

200mmØ C.I. Body Gate Valve, F/F, PN16, NRS, Flange End in Accordance w/ ANSI B16.1 Class 125 0 pcs. 17,700.00 0.00

150mmØ Steel Blind Flange in Accordance w/ AWWA C207 Class D-Std. 1 pc. 2,500.00 2,500.00

150mmØ C.I. Valve Box Cover 0 pcs. 950.00 0.00

200mmØ Steel Ring Flange in Accordance w/ AWWA C207 Class D-Std. 10 pcs. 2,000.00 20,000.00

6mm Thk x 50mm x 6.00m Stainless Steel Flat Bar 1 pc. 9,000.00 9,000.00

19mmØ x 100mm Stainless Steel (Type 304) L-Type Achor Bolt w/ Nut & Washer 12 pcs. 180.00 2,160.00

19mmØ x 250mm Stainless Steel (Type 304) Bolt w/ Nut & Washer 6 pcs. 125.00 750.00

16mmØ x 88mm Stainless Steel (Type 304) Bolt w/ Nut & Washer 64 pcs. 95.00 6,080.00

6mm Thick Rubber Gasket 6 kgs. 75.00 450.00

200mmØ x 45o PVC Bend, Class 150, B/S w/ R.R. 6 pcs. 5,300.00 31,800.00

200mmØ x 6.00m B.I. Pipe, (ASTM A53-90A Heavy Gauge Standard) 2 pcs. 16,380.00 32,760.00

200mmØ C.I. Body Gate Valve, F/F, PN16, NRS, Flange End in Accordance w/ ANSI B16.1 Class 125 2 pcs. 17,700.00 35,400.00

200mmØ C.I. Adaptor, F/P, Flange End In Accordance w/ ANSI B16.1 Class 125 7 pcs. 4,956.00 34,692.00

200mmØ C.I. Sleeve Type Flexible Coupling (PVC-CI) 7 pcs. 4,170.00 29,190.00

200mmØ Steel Ring Flange (See Shop Drawing) 4 pcs. 1,800.00 7,200.00

150mmØ C.I. Valve Box Cover 2 pcs. 950.00 1,900.00

16mmØ x 88mm Stainless Steel (Type 304) Bolt w/ Nut & Washer 56 pcs. 95.00 5,320.00

6mm Thick Rubber Gasket 8 kgs. 75.00 600.00

D3 & D4

200mmØ x 45o PVC Bend, Class 150, B/S w/ R.R. 12 pcs. 5,300.00 63,600.00

200mmØ x 6.00m B.I. Pipe, (ASTM A53-90A Heavy Gauge Standard) 2 pcs. 16,380.00 32,760.00

200mmØ C.I. Body Gate Valve, F/F, PN16, NRS, Flange End in Accordance w/ ANSI B16.1 Class 125 2 pcs. 17,700.00 35,400.00

200mmØ C.I. Adaptor, F/P, Flange End In Accordance w/ ANSI B16.1 Class 125 7 pcs. 4,956.00 34,692.00

200mmØ C.I. Sleeve Type Flexible Coupling (PVC-CI) 7 pcs. 4,170.00 29,190.00

200mmØ Steel Ring Flange (See Shop Drawing) 4 pcs. 1,800.00 7,200.00

150mmØ C.I. Valve Box Cover 2 pcs. 950.00 1,900.00

16mmØ x 88mm Stainless Steel (Type 304) Bolt w/ Nut & Washer 56 pcs. 95.00 5,320.00

6mm Thick Rubber Gasket 8 kgs. 75.00 600.00

Pricelist as of February 2013 150 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 151: Dumalon W.S. Ground Tank_Final

Under Drain Pipes & Appurtenances

100mmØ C.I. Body Gate Valve, F/F, PN16, NRS, Flange End in Accordance w/ ANSI B16.1 Class 125 1 pc. 7,940.00 7,940.00

150mmØ C.I. Valve Box Cover 1 ps. 950.00 950.00

100mmØ x 6.00m PVC Pipe Class 150, B/S, w/ R.R. 6 pcs. 1,600.00 9,600.00

100mmØ Mechanical End Cap, 4 pcs. 950.00 3,800.00

100mm x 100mmØ C.I. Tee, M/M 3 pcs. 4,300.00 12,900.00

Geotextile Filter Fabric 12 sq.m. 150.00 1,800.00

Air Vent

100mmØ x 6.00m G.I. Pipe, ASTM A53-90A Heavy Gauge Std. 1 pc. 4,800.00 4,800.00

100mmØ x 90o G.I. Elbow, ANSI B16.3 Class 150 Std. 4 pcs. 870.00 3,480.00

100mmØ G.I. End Cap, ANSI B16.3 Class 150 Std. 2 pcs. 540.00 1,080.00

b. Labor:

2 - Pipefitter 4 days 341.00 2,728.00

4 - Laborer 4 days 317.00 5,072.00

TOTAL COST OF GATE VALVES, DIFFERENTIAL FLOAT CONTROL VALVE & APPURTENANCES

9. SUPPLY & INSTALLATION OF TWO UNITS - 100MMØ FLOW METER & CONST OF CONCRETE VALVE BOX

a. Materials :

Supply & Inst. of 100mmØ Full Bore Electromagnetic Flowmeter F/F w/ 2-Units Steel Flange 2 units 286,000.00 572,000.00

Specification:

100mmØ Electro-Magnetic Flowmeter, ANSI 16.5, Class-150,

Flanged-Typed, Transmitter accuracy of 0.40% of rate, with highly

accurate bi-directional measurements, battery powered, with internal

battery pack of five (05) years maintenance free battery life.

Complete with two (02) mating flanges and the desired stainless steel

bolts, nuts, washers with rubber gaskets. Unit is remote-type with

complete accessories and with integrated GSM Data Logger

(wall-mounted typed signal converter) which records/logs the flow &

pressure, and is compatible with the sensor EM Flowmeter

with a recording interval programmable between 1 second

& 1 hour. EM Flowmeter & Logger housing is fully water proofed (IP68).

Data can be accessed remotely using a standard GSM mobile phone

thru simple text message to the host computer provided with a

windows-based software which can monitor multiple data loggers.

24 months warranty, with Wet Calibration Certificate per unit upon delivery.

The unit includes the following accessories:

Fifty (50) meters flow input cable with pvc conduit up to the pump house,

communication cable, Windows-based configuration software for PC's,

Two channel flow splitter cable (50 meters), 50 meters hose for pressure

line with fittings (quick fit connection).

Note: Package includes Orientation & Training of personnel

100mmØ C.I. Sleeve Type Flexible Coupling, (G.I.-PVC) 2 pcs. 3,915.00 7,830.00

100mmØ C.I. Adaptor, F/P, Flange End In Accordance w/ ANSI B16.1 Class 125 2 pcs. 2,541.00 5,082.00

6mm thk Rubber Gasket 5 kgs. 75.00 375.00

16mmØ x 100mm Anchor Bolts w/ Nuts & Washer 16 pcs. 95.00 1,520.00

Construction of 2 - Units Concrete Valve Box

Portland Cement 28 bags 245.00 6,860.00

Washed Sand 1.25 cu.m. 1,000.00 1,250.00

Gravel (G1) 2.5 cu.m. 1,000.00 2,500.00

16mmØ x 6.00m Deformed Reinf. Steel Bar 44 pcs. 480.00 21,120.00

#16 GI Tie Wire 5 kgs. 75.00 375.00

16mmØ x 6.00m Stainless Steel Round Bar (Type 304) 1 pc. 12,500.00 12,500.00

8mmØ x 6.00m M.S. Plain Round Bar 1 pc. 160.00 160.00

16mmØ x 6.00m M.S. Plain Round Bar 2 pcs. 495.00 990.00

38mmØ x 6.00m G.I. Pipe ASTM A53-90A Heavy Gauge Standard 1 pc. 1,800.00 1,800.00

6mm Thk x 50mm x 50mm x 6.00m MS Angle Bar 1 pc. 1,500.00 1,500.00

12mm Thk x 1.20m x 2.40m Ordinary Plywood 8 shts. 975.00 7,800.00

60 pcs - 2" x 2" x 10' Coco Lumber 200 bd.ft. 20.00 4,000.00

40 pcs - 2" x 3" x 10' Coco Lumber 200 bd.ft. 20.00 4,000.00

40 pcs - 2" x 4" x 10' Coco Lumber 267 bd.ft. 20.00 5,340.00

4" C.W. Nail 2 kgs. 70.00 140.00

3" C.W. Nail 2 kgs. 70.00 140.00

1-1/2" C.W. Nail 1 kg. 65.00 65.00

Hacksaw Blade 6 pcs. 65.00 390.00

Welding Rod (6011) 2 kgs. 160.00 320.00

b. Labor:

3 - Skilled Worker 6 days 366.00 6,588.00

1 - Pipe Fitter 6 days 341.00 2,046.00

4 - Contractual Laborers 6 days 317.00 7,608.00

TOTAL COST OF SUPPLY & INSTALLATION OF 100MMØ FLOW METER & CONST OF CONCRETE VALVE BOX

10. PAINTING WORKS (223.00 Sq.M.)

a. Materials:

Concrete Neutralizer 6 gals. 320.00 1,920.00

Solvent Based Acrylic Paint Primer 10 gals. 1,050.00 10,500.00

Pricelist as of February 2013 151 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 152: Dumalon W.S. Ground Tank_Final

Solvent Based Acrylic Cast 10 gals. 500.00 5,000.00

Solvent Based Acrylic Paint Top Coat White Gloss 20 gals. 1,050.00 21,000.00

Solvent Based Acrylic Paint Reducer 6 gals. 420.00 2,520.00

Lacquer thinner 8 gals. 250.00 2,000.00

Body Filler w/ Hardener 2 gals. 640.00 1,280.00

Sand paper #150 2 doz. 150.00 300.00

Sand paper #120 2 doz. 150.00 300.00

Red Tinting Color for Solvent Based Acrylic Paint 2 pints 105.00 210.00

Raw Sienna Tinting Color for Solvent Based Acrylic Paint 6 pints 105.00 630.00

Thalo Blue Tinting Color for Solvent Based Acrylic Paint 2 pints 105.00 210.00

Lamp Black Tinting Color for Solvent Based Acrylic Paint 2 pints 105.00 210.00

Red Lead Paint Primer 2 gals. 570.00 1,140.00

Quick Dry Enamel (Royal Blue) 2 gals. 620.00 1,240.00

Paint Thinner 1 gal. 360.00 360.00

7" Roller Brush w/ Handle 2 sets 45.00 90.00

2" Paint Brush 2 pcs. 20.00 40.00

Steel Brush 1 pc. 25.00 25.00

b. Labors:

2 - Painter 15 days 366.00 10,980.00

2 - Contractual Laborers 15 days 317.00 9,510.00

TOTAL COST OF PAINTING WORKS

11. WATER PROOFING WORKS FOR TOP SLAB

Supply & Installation of Bituminous Membrane Polyester Reinforced Waterproofing 37.7 sq.m. 1,000.00 37,700.00

TOTAL COST OF WATER PROOFING WORKS FOR TOP SLAB

12. SUPPLY & INST. OF 40GPD HYPOCHLORINATOR

"CHEM-TECH" heavy Duty Hypochlorinator with 100 liters Solution Tank

with stirrer, series 200, designed to deliver 40 GPD(max) vs. 125 psig, 1 unit 90,000.00 90,000.00

mechanical diaphragm type and oil bathed gear assembly, driven by

electric motor, 230V, single phase, 60 Hz. With complete standard

suction & discharge accessories:

- 4 ft. Suction Tubing, clear PVC, 7/16"OD

- 8 ft. Discharge Tubing, P.E., 1/2" OD

- 1 set Back check Valve & Injection Fittings

- 1 set Foot Valve with strainer

- 1 pc. Bleed Valve

Provision for Chlorinator Injection Fittings:

50mm.Ø G.I. Coupling, ANSI B16.3 Class 150 1 pc. 52.00 52.00

50mm.Ø x 150mm G.I. Nipple, ASTM A53-90A Heavy Gauge Std. 1 pc. 91.00 91.00

50mm.Ø G.I. Cap, ANSI B16.3 Class 150 1 pc. 63.00 63.00

19mm.Ø G.I. Coupling, ANSI B16.3 Class 150 1 pc. 11.00 11.00

19mm.Ø x 12mm.Ø G.I. Bushing, ANSI B16.3 Class 150 1 pc. 11.00 11.00

12mm.Ø G.I. Plug, ANSI B16.3 Class 150 1 pc. 6.00 6.00

Pressure Gauge Assembly:

12mm.Ø G.I. Tee, ANSI B16.3 Class 150 2 pc. 11.00 22.00

12mm.Ø G.I. Coupling, ANSI B16.3 Class 150 2 pc. 9.00 18.00

12mm.Ø x 100mm G.I. Nipple, ASTM A53-90A Heavy Gauge Std. 2 pc. 15.00 30.00

12mm.Ø x 6mmØ G.I. Bushing, ANSI B16.3 Class 150 2 pc. 10.00 20.00

12mm.Ø G.I. Plug, ANSI B16.3 Class 150 2 pc. 13.00 26.00

12mm.Ø Brass Ball Valve 2 pc. 130.00 260.00

63mm.Ø Oil-filled Pressure Gauge (0-150 psi) 2 pc. 2,000.00 4,000.00

Labor: Cutting & Welding works of B.I. Discharge Pipes, installation of Appurtenances,

preparation of Pressure Gauge assy. and provision for Chlorinator Injection Fittings. 1 l.s. 18,922.00 18,922.00

TOTAL COST OF SUPPLY & INST. OF 40GPD HYPOCHLORINATOR W/ COMPLETE ACCESSORIES

TOTAL COST OF CONST. OF THREE HUNDRED 300.00 CU.M. CONCRETE GROUND TANK

III. CONST. OF CONCRETE PERIMETER FENCE

1. CLEARING/LAYOUTING & EXCAVATION WORKS

a. Materials:

Nylon Chord #100 2 rolls 300.00 600.00

12mm Clear Level Hose 40 mtrs 25.00 1,000.00

b. Labor:

1 - Skilled Worker 3 days 366.00 1,098.00

4 - Contractual Laborers 3 days 317.00 3,804.00

TOTAL COST OF EXCAVATION WORKS

2. CONCRETING WORKS (14.80 Cu.M.)

a. Materials :

F1 (7 Units)

Portland Cement 19 bags 245.00 4,655.00

Washed Sand 1 cu.m. 1,000.00 1,000.00

Gravel 2 cu.m. 1,000.00 2,000.00

150mm Boulders 1 cu.m. 1,000.00 1,000.00

5,656,397.00

Pricelist as of February 2013 152 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 153: Dumalon W.S. Ground Tank_Final

F2 (14 Units)

Portland Cement 21 bags 245.00 5,145.00

Washed Sand 1 cu.m. 1,000.00 1,000.00

Gravel 2 cu.m. 1,000.00 2,000.00

150mm Boulders 2 cu.m. 1,000.00 2,000.00

C1 & C1-A (7 Units)

Portland Cement 25 bags 230.00 5,750.00

Washed Sand 1.25 cu.m. 1,000.00 1,250.00

Gravel 2.5 cu.m. 1,000.00 2,500.00

C2 & C2-A (14 Units)

Portland Cement 35 bags 230.00 8,050.00

Washed Sand 1.75 cu.m. 1,000.00 1,750.00

Gravel 3.5 cu.m. 1,000.00 3,500.00

RW-1 (L = 18.00 m.)

Portland Cement 150.7 bags 230.00 34,651.80

Washed Sand 7.366 cu.m. 1,000.00 7,365.60

Gravel 14.73 cu.m. 1,000.00 14,731.20

RW-2 (L = 47.00 m.)

Portland Cement 299.2 bags 230.00 68,805.65

Washed Sand 13.86 cu.m. 1,000.00 13,855.60

Gravel 27.71 cu.m. 1,000.00 27,711.20

b. Labor:

2 - Masons 6 days 366.00 4,392.00

10 - Contractual Laborer 6 days 317.00 19,020.00

c. Equipment Rental/Fuel/Oil & Lubricants:

1 - Unit - One - Bagger Mixer 6 days 1,500.00 9,000.00

1 - Unit - Concrete Vibrator 6 days 800.00 4,800.00

Premium Gasoline 120 ltrs. 60.00 7,200.00

TOTAL COST OF CONCRETE WORKS

3. REINFORCED STEEL WORKS (1,940.10 KGS.)

a. Materials :

F1 (7 Units)

16mmØ x 6.00m Def. Reinforcing Steel Bars 14 pcs. 480.00 6,720.00

#16 G.I. Tie-wire 2 kgs. 65.00 130.00

Hacksaw Blade 4 pcs. 65.00 260.00

F2 (14 Units)

16mmØ x 6.00m Def. Reinforcing Steel Bars 24 pcs. 480.00 11,520.00

#16 G.I. Tie-wire 3 kgs. 65.00 195.00

Hacksaw Blade 6 pcs. 65.00 390.00

C1 & C1-A (7 Units)

16mmØ x 6.00m Def. Reinforcing Steel Bars 28 pcs. 450.00 12,600.00

10mmØ x 6.00m Def. Reinforcing Steel Bars 40 pcs. 165.00 6,600.00

#16 G.I. Tie-wire 7 kgs. 65.00 455.00

Hacksaw Blade 6 pcs. 65.00 390.00

C2 & C2-A (14 Units)

16mmØ x 6.00m Def. Reinforcing Steel Bars 56 pcs. 480.00 26,880.00

10mmØ x 6.00m Def. Reinforcing Steel Bars 78 pcs. 190.00 14,820.00

#16 G.I. Tie-wire 18 kgs. 65.00 1,170.00

Hacksaw Blade 8 pcs. 65.00 520.00

RW-1 (L = 18.00 m.)

16mmØ x 6.00m Def. Reinforcing Steel Bars 94 pcs. 480.00 45,120.00

12mmØ x 6.00m Def. Reinforcing Steel Bars 64 pcs. 270.00 17,280.00

#16 G.I. Tie-wire 6.25 kgs. 65.00 406.19

RW-2 (L = 47.00 m.)

16mmØ x 6.00m Def. Reinforcing Steel Bars 210 pcs. 480.00 100,800.00

12mmØ x 6.00m Def. Reinforcing Steel Bars 151 pcs. 270.00 40,770.00

#16 G.I. Tie-wire 27.67 kgs. 65.00 1,798.42

b. Labor:

2 -Steel Man 15 days 366.00 10,980.00

4 - Laborer 15 days 317.00 19,020.00

c. Equipment:

1 - Unit Bar Cutter 15 days 300.00 4,500.00

1 - Unit Bar Bender 15 days 300.00 4,500.00

Pricelist as of February 2013 153 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 154: Dumalon W.S. Ground Tank_Final

TOTAL DIRECT COST OF REBAR WORKS

4. MASONRY WORKS:

a. Materials :

Portland Cement 110 bags 245.00 26,950.00

Washed Sand 5 cu.m. 1,000.00 5,000.00

Fine sand (for plastering) 3 cu.m. 1,400.00 4,200.00

100mm thk Concrete Hollow Blocks (NLB) 893 pcs. 17.00 15,181.00

150mm thk Concrete Hollow Blocks (LB) 143 pcs. 24.00 3,432.00

10mmØ x 6.00m Def. Reinforcing Steel Bars 25 pcs. 190.00 4,750.00

#16 G.I. Tie-wire 4 kgs. 65.00 260.00

Hacksaw Blade 6 pcs. 65.00 390.00

b. Labor:

2 - Masons 14 days 366.00 10,248.00

2 - Laborers 14 days 317.00 8,876.00

TOTAL COST OF MASONRY WORKS

5. FORMS & SCAFFOLDING WORKS:

a. Materials :

12mm Thk. X 1.20m x 2.40m Ordinary Plywood 16 shts. 975.00 15,600.00

60 - pcs - 2" x 4" x 10' Coco Lumber 400 bd.ft. 20.00 8,000.00

80 - pcs - 2" x 3" x 10' Coco Lumber 400 bd.ft. 20.00 8,000.00

100 - pcs - 2" x 2" x 10' Coco Lumber 333 bd.ft. 20.00 6,660.00

4" C.W. Nails 8 kgs. 70.00 560.00

3" C.W. Nails 6 kgs. 70.00 420.00

1-1/2" C.W. Nails 5 kgs. 65.00 325.00

b. Labor:

1 - Carpenter 15 days 366.00 5,490.00

2 - Laborer 15 days 317.00 9,510.00

TOTAL COST OF FORMS & SCAFFOLDING WORKS:

6. STEEL WORKS:

a. Materials :

50mmØ x 6.0m G.I. Pipe. (ASTM A53 90A-Heavy Gauge Standard) 16 pcs. 1,720.00 27,520.00

6mm thk x 38mm x 6.00m M.S. Flat Bar 16 pcs. 880.00 14,080.00

12mm x 12mm x 6.00m M.S. Square Bar 76 pcs. 270.00 20,520.00

#4 x 50mm Mesh x 1.20m x 2.40m B.I. Steel Matting 25 pcs. 1,400.00 35,000.00

6011 Welding Rod 15 kgs. 160.00 2,400.00

Hacksaw Blade 30 pcs. 65.00 1,950.00

b. Labor:

1 -Welder 20 days 366.00 7,320.00

4 - Laborer 20 days 317.00 25,360.00

c. Equipment Rental:

1 - Unit Welding Machine 20 days 2,200.00 44,000.00

1 - Unit Disk Grinder 20 days 300.00 6,000.00

4" Grinder Wheel 4 pcs. 180.00 720.00

TOTAL COST OF STEEL WORKS:

7. PAINTING WORKS

a. Materials:

Concrete Neutralizer 4 gals. 320.00 1,280.00

Solvent Based Acrylic Paint Primer 10 gals. 1,050.00 10,500.00

Solvent Based Acrylic Paint Top Coat (White Gloss) 20 gals. 1,050.00 21,000.00

Solvent Based Acrylic Reducer 7 gals. 420.00 2,940.00

Red Lead Metal Primer 4 gals. 570.00 2,280.00

Quick Dry Enamel Blue 4 gals. 620.00 2,480.00

Paint Thinner 2 gals. 360.00 720.00

Red Tinting Color for Solvent Based Acrylic Paint 2 pints 105.00 210.00

Raw Sienna Tinting Color for Solvent Based Acrylic Paint 8 pints 105.00 840.00

Thalo Blue Tinting Color for Solvent Based Acrylic Paint 2 pints 105.00 210.00

Lamp Black Tinting Color for Solvent Based Acrylic Paint 2 pints 105.00 210.00

#120 Sand Paper 2 doz. 150.00 300.00

#150 Sand Paper 2 doz. 150.00 300.00

7" Paint Roller w/ Tray 2 sets 45.00 90.00

1" Paint Brush 2 pcs. 15.00 30.00

2" Paint Brush 2 pcs. 20.00 40.00

4" Paint Brush 3 pcs. 40.00 120.00

Steel Brush 3 pcs. 25.00 75.00

b Labor:

2 - Painter 12 days 317.00 7,608.00

2 - Laborer 12 days 317.00 7,608.00

TOTAL COST OF PAINTING WORKS

8. SIGNAGE WITH STAND & FRAME

a. Materials:

Pricelist as of February 2013 154 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 155: Dumalon W.S. Ground Tank_Final

Panaflex Signage w/ Aluminum Framing, Lighting and Accessories 1 set 13,000.00 13,000.00

12mm. ∅ x 150mm. Stainless Steel Bolt (Type 304) w/ Nuts & Washers 8 pcs. 80.00 640.00

6mm Thk x 200mm x 200mm Fabricated Base Plate w/ 4-16mm ∅ Bolt Hole (Attach 2 pcs. 1,800.00 3,600.00

Shop Drawing)

100mm. ∅ x 6.00m G.I. Pipe, ASTM 53 A90 Heavy Gauge - Standard 1 pc. 3,450.00 3,450.00

10mm. ∅ x 25mm. Stainless Steel Bolt (Type 304) w/ Nuts & Washers 12 pcs. 35.00 420.00

b. Labor:

2 - Skilled Worker 2 day 366.00 1,464.00

2 - Laborer 2 day 317.00 1,268.00

TOTAL COST OF SIGNAGE

TOTAL COST OF CONCRETE PERIMETER FENCE

IV. CONSTRUCTION OF (12.40 SQ. MTR.) OPERATOR'S ROOM

1. EXCAVATION WORKS (3.98 Cu.M.)

b. Labors:

4 - Laborer 1 day 317.00 1,268.00

TOTAL DIRECT COST OF EXCAVATION WORKS

2. CONCRETE WORKS (8.50 Cu M.)

a. Materials:

F2 (2 Units)

Portland Cement 6 bags 245.00 1,470.00

Washed Sand 0.25 cu.m. 1,000.00 250.00

Gravel (G1) 0.5 cu.m. 1,000.00 500.00

C2-A (2 Units)

Portland Cement 7 bags 245.00 1,715.00

Washed Sand 0.5 cu.m. 1,000.00 500.00

Gravel (G1) 0.75 cu.m. 1,000.00 750.00

WF (11.00 ln.m.)

Portland Cement 5 bags 245.00 1,225.00

Washed Sand 0.25 cu.m. 1,000.00 250.00

Gravel (G1) 0.5 cu.m. 1,000.00 500.00

Floor Lintel Beam (11.00 ln.m.)

Portland Cement 4 bags 245.00 980.00

Washed Sand 0.25 cu.m. 1,000.00 250.00

Gravel (G1) 0.5 cu.m. 1,000.00 500.00

Slab on Fill (0.10m x 12.65 Sq.m.)

Portland Cement 12 bags 245.00 2,940.00

Washed Sand 0.5 cu.m. 1,000.00 500.00

Gravel (G1) 1 cu.m. 1,000.00 1,000.00

Door/Window Lintel Beam (10.00 ln.m.)

Portland Cement 3 bags 245.00 735.00

Washed Sand 0.25 cu.m. 1,000.00 250.00

Gravel (G1) 0.25 cu.m. 1,000.00 250.00

RCB

Portland Cement 12 bags 245.00 2,940.00

Washed Sand 0.5 cu.m. 1,000.00 500.00

Gravel (G1) 1 cu.m. 1,000.00 1,000.00

Roof Slab (18.70 sq.m.)

Portland Cement 23 bags 245.00 5,635.00

Washed Sand 1 cu.m. 1,000.00 1,000.00

Gravel (G1) 2 cu.m. 1,000.00 2,000.00

False Beam (10.50 ln.m.)

Portland Cement 4 bags 245.00 980.00

Washed Sand 0.25 cu.m. 1,000.00 250.00

Gravel (G1) 0.25 cu.m. 1,000.00 250.00

b. Labors:

1 Mason 4 days 366.00 1,464.00

8 - Laborers 4 days 317.00 10,144.00

c. Equipment Rental:

1 - Unit One - Bagger Mixer 4 days 1,500.00 6,000.00

1 - Unit Concrete Vibrator 4 days 500.00 2,000.00

TOTAL DIRECT COST OF CONCRETE WORKS

3. REINFORCED STEEL WORKS (1,093.10 KGS.)

Note: Other Column Footing, Column, Wall Footing & Floor Lintel Beam are already included in Perimeter Fence Estimates

a. Materials:

F2 (2 Units)

16mmØ x 6.00m Def. Reinforcing Steel Bars 4 pcs. 480.00 1,920.00

782,690.05

Pricelist as of February 2013 155 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 156: Dumalon W.S. Ground Tank_Final

#16 G.I. Tie-wire 1 kg. 65.00 65.00

Hacksaw Blade 2 pcs. 65.00 130.00

C2-A (2 Units)

16mmØ x 6.00m Def. Reinforcing Steel Bars 8 pcs. 480.00 3,840.00

10mmØ x 6.00m Def. Reinforcing Steel Bars 11 pcs. 190.00 2,090.00

#16 G.I. Tie-wire 1 kg. 65.00 65.00

Hacksaw Blade 2 pcs. 65.00 130.00

WF (11.00 ln.m.)

12mmØ x 6.00m Def. Reinforcing Steel Bars 3 pcs. 270.00 810.00

10mmØ x 6.00m Def. Reinforcing Steel Bars 5 pcs. 190.00 950.00

#16 G.I. Tie-wire 2 kgs. 65.00 130.00

Hacksaw Blade 2 pcs. 65.00 130.00

Floor Lintel Beam (11.00 ln.m.)

12mmØ x 6.00m Def. Reinforcing Steel Bars 9 pcs. 270.00 2,430.00

10mmØ x 6.00m Def. Reinforcing Steel Bars 7 pcs. 190.00 1,330.00

#16 G.I. Tie-wire 2 kgs. 65.00 130.00

Hacksaw Blade 2 pcs. 65.00 130.00

Slab on Fill (0.10m x 12.65 Sq.m.)

10mmØ x 6.00m Def. Reinforcing Steel Bars 19 pcs. 190.00 3,610.00

#16 G.I. Tie-wire 1 kg. 65.00 65.00

Hacksaw Blade 3 pcs. 65.00 195.00

Door/Window Lintel Beam (10.00 ln.m.)

12mmØ x 6.00m Def. Reinforcing Steel Bars 4 pcs. 270.00 1,080.00

10mmØ x 6.00m Def. Reinforcing Steel Bars 4 pcs. 190.00 760.00

#16 G.I. Tie-wire 1 kg. 65.00 65.00

Hacksaw Blade 1 pc. 65.00 65.00

RCB

16mmØ x 6.00m Def. Reinforcing Steel Bars 22 pcs. 480.00 10,560.00

10mmØ x 6.00m Def. Reinforcing Steel Bars 30 pcs. 190.00 5,700.00

#16 G.I. Tie-wire 7 kgs. 65.00 455.00

Hacksaw Blade 10 pc. 65.00 650.00

Roof Slab

12mmØ x 6.00m Def. Reinforcing Steel Bars 65 pcs. 270.00 17,550.00

#16 G.I. Tie-wire 6 kgs. 65.00 390.00

Hacksaw Blade 10 pcs. 65.00 650.00

False Beam (10.50 ln.m.)

12mmØ x 6.00m Def. Reinforcing Steel Bars 5 pcs. 270.00 1,350.00

10mmØ x 6.00m Def. Reinforcing Steel Bars 8 pcs. 190.00 1,520.00

#16 G.I. Tie-wire 3 kgs. 65.00 195.00

Hacksaw Blade 3 pcs. 65.00 195.00

b. Labors:

1 -Steelman 14 days 366.00 5,124.00

2 -Contractual Laborers 14 days 317.00 8,876.00

c. Equipment Rental:

1 - Unit Bar Bender 14 days 300.00 4,200.00

TOTAL DIRECT COST OF REINFORCED STEEL WORKS

4. MASONRY WORKS

4.1. Laying & Plastering of CHB

(Includes CHB Laying & Plastering Works)

a. Materials:

Portland Cement 73 bags 245.00 17,885.00

Washed Sand 3.5 cu.m. 1,000.00 3,500.00

Fined Sand (For Plastering) 2 cu.m. 1,400.00 2,800.00

100mm x 200mm x 400mm Hollow Block (NLB) 640 pcs. 17.00 10,880.00

150mm x 200mm x 400mm Hollow Block (LB) 230 pcs. 24.00 5,520.00

10mmØ x 6.00m. Def. Steel Bars 42 pcs. 190.00 7,980.00

# 16 G.I. Tie Wire 3 kgs. 75.00 225.00

Hacksaw Blade 12 pcs. 65.00 780.00

b. Labors:

2 - Mason 14 days 366.00 10,248.00

2 - Laborer 14 days 317.00 8,876.00

4.2. Tile Works (31.80 sq.m.)

a. Materials:

200mm x 200mm Ceramic Tiles (White) 390 pcs. 16.00 6,240.00

400mm x 400mm Granite Tiles (White) 54 pcs. 255.00 13,770.00

Tile Adhesive (25Kg/Bag) 5 bags 305.00 1,525.00

Tile Grout (2 Kg./Pack) 5 bags 85.00 425.00

Pricelist as of February 2013 156 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 157: Dumalon W.S. Ground Tank_Final

PVC Tile Trim (White) 7 pcs. 65.00 455.00

4" Grinding Wheel 1 pc. 180.00 180.00

b. Labor:

2 - Mason 9 days 366.00 6,588.00

2 - Laborer 9 days 317.00 5,706.00

c. Equipment Rental:

1 - Unit Tile Cutter 5 days 300.00 1,500.00

1 - Unit Angular Grinder 5 days 300.00 1,500.00

TOTAL DIRECT COST OF MASONRY WORKS

5. CARPENTRY WORKS

a. Materials:

5.1. Installation of Door Frame/Pannel Door & Window Jamb

Pre-Fabricated 0.80m x 2.10m x 50mm x 150mm Mahogany Wood Door Jamb 1 unit 2,500.00 2,500.00

Pre-Fabricated 0.80m x 2.10m Mahogany Wood Panel Type Door 1 unit 4,800.00 4,800.00

w/ 50mm x 100mm Door Frame & 37.5mm Thk Door Board

Pre-Fabricated 0.60m x 2.10m PVC Door w/ Door Jamb & Hinges w/ Screw 1 unit 1,900.00 1,900.00

Pre-Fab. 1.165m x 1.45m x 50mm x 150mm 2 Panel Mahogany Wood Window Jamb 2 units 2,300.00 4,600.00

5.2. Cabinet & Table:

1-Unit Cabinet

Cabinet Handle (Chrome) 4 pcs. 160.00 640.00

Cabinet Concealed Hinges w/ Screw 12 pcs. 60.00 720.00

12mm.Ø x 6.00m G.I. Pipe, ASTM A53-90A Heavy Gauge Standard 1 pc. 600.00 600.00

3 pcs. - 1" x 1" x 10' Mahogany Lumber 2.5 bd.ft. 34.00 85.00

19mm Thk x 1.20m x 2.40m Plyboard 3 shts. 1,100.00 3,300.00

6mm Thk x 1.20m x 2.40m Plyboard 1 sht. 420.00 420.00

3" C.W. Nail 1 kg. 70.00 70.00

1" C.W. Finishing Nail 1 kg. 75.00 75.00

1-Unit Table

Drawer Handle (Chrome) 4 pcs. 160.00 640.00

3 pcs. - 1" x 1" x 10' Mahogany Lumber 2.5 bd.ft. 34.00 85.00

19mm Thk x 1.20m x 2.40m Plyboard 3 shts. 1,100.00 3,300.00

1" C.W. Finishing Nail 1 kg. 75.00 75.00

5.3. Hardware :

4" x 3" Loose Pin Hinges (Heavy Duty) w/ Screw 4 pcs. 140.00 560.00

2" x 2" Cabinet Hinges w/ Screw 8 pcs. 65.00 520.00

Stainless Door Knob (Heavy Duty) 2 sets 950.00 1,900.00

Drawer Lock (Heavy Duty) 4 sets 60.00 240.00

4" C. W. Nail 1 kg. 70.00 70.00

2-1/2" C. W. Nail 1 kg. 65.00 65.00

2" C. W. Nail 1 kg. 65.00 65.00

1" C. W. Nail 1 kg. 65.00 65.00

1" Finishing Nail 2 kgs. 65.00 130.00

b. Labor:

1 - Carpenter 9 days 366.00 3,294.00

1 - Laborer 9 days 317.00 2,853.00

TOTAL DIRECT COST OF CARPENTRY WORKS

6. SCAFFOLDING & FORM WORKS

a. Materials:

12mm Thk x 1.20m x 2.40m Ordinary Plywood 18 pcs. 975.00 17,550.00

100 pcs. - 2" x 2" x 10' Coco Lumber 333 bd.ft. 20.00 6,660.00

80 pcs. - 2" x 3" x 10' Coco Lumber 400 bd.ft. 20.00 8,000.00

80 pcs. - 2" x 4" x 10' Coco Lumber 400 bd.ft. 20.00 8,000.00

4" C. W. Nail 8 kgs. 70.00 560.00

3" C. W. Nail 8 kgs. 70.00 560.00

1-1/2" C. W. Nail 4 kgs. 65.00 260.00

b. Labors:

1 -Carpenter 12 days 366.00 4,392.00

1 -Contractual Laborers 12 days 317.00 3,804.00

TOTAL DIRECT COST OF SCAFFOLDING & FORM WORKS

7. PLUMBING WORKS

7.1. Storm Drainage Pipe

50mmØ x 3.00m PVC Pipe, Series 1000 6 pcs. 320.00 1,920.00

50mmØ x 900 PVC Bend, Series 1000 8 pcs. 45.00 360.00

50mmØ PVC Coupling, Series 1000 4 pcs. 90.00 360.00

PVC Solvent Cement 2 qrts. 120.00 240.00

7.2. Sanitary Pipe

100mmØ x 3.00m PVC Pipe, Series 1000 4 pcs. 820.00 3,280.00

100mmØ x 450 PVC Sanitary Elbow, Series 1000 6 pcs. 85.00 510.00

100mmØ x 900 PVC Sanitary Elbow, Series 1000 4 pcs. 90.00 360.00

Pricelist as of February 2013 157 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 158: Dumalon W.S. Ground Tank_Final

100mmØ x PVC Clean Out, Series 1000 2 pcs. 75.00 150.00

100mmØ PVC Sanitary Coupling, Series 1000 2 pcs. 65.00 130.00

50mmØ x 3.00m PVC Pipe, Series 1000 3 pcs. 320.00 960.00

50mmØ PVC Sanitary Coupling, Series 1000 2 pcs. 35.00 70.00

50mmØ x 900 PVC Bend, Series 1,000 1 pc. 45.00 45.00

100mmØ x 100mmØ PVC Sanitary Tee, Series 1000 4 pcs. 170.00 680.00

100mmØ x 100mmØ PVC Sanitary Wye, Series 1000 2 pcs. 155.00 310.00

100mmØ x 50mmØ PVC Sanitary Tee, Series 1000 1 pc. 130.00 130.00

50mmØ x 50mmØ PVC Sanitary Tee, Series 1000 1 pc. 65.00 65.00

PVC Cement Solvents 8 qrts. 120.00 960.00

7.3. Cold Pipe

12mmØ x 6.00m G.I. Pipe ASTM A53-90A Heavy Gauge Standard 3 pcs. 460.00 1,380.00

12mmØ x 900 G.I. Elbow, ANSI B16.3 Class 150 Standard 7 pcs. 15.00 105.00

12mmØ x 12mmØ G.I. Tee, ANSI B16.3 Class 150 Standard 4 pcs. 20.00 80.00

12mmØ Brass Faucet 2 pcs. 260.00 520.00

12mmØ G.I. Union Patent ANSI B16.3 Class 150 Standard 1 pc. 20.00 20.00

25mm Teflon Tape 5 rolls 27.00 135.00

7.4. Sanitary Fixtures:

Flush Type Water Closet w/ Complete Fittings & Accs. 1 unit 4,000.00 4,000.00

Wall Mounted Type Lavatory w/ Complete Fittings & Accs. 1 unit 2,415.00 2,415.00

Ceramic Tissue Holder 1 pc. 270.00 270.00

Ceramic Soap Holder 1 pc. 160.00 160.00

12mm Shower Head 1 pc. 220.00 220.00

12mm Shower Valve 1 pc. 250.00 250.00

100mm x 100mm Stainless Double Strainer Floor Drain 2 pcs. 150.00 300.00

6mm Thk. x 0.6m x 0.6m Beveled Frameless Mirror 1 pc. 200.00 200.00

b. Labors:

1 -Plumber 4 days 366.00 1,464.00

2 -Contractual Laborers 4 days 317.00 2,536.00

TOTAL DIRECT COST OF PLUMBING WORKS

8. GLASS WORKS (LUMP SUM)

Supply & Installation of 5.5mm Thk x 13 Blades Smoke x 0.65m width Glass Jalousies

w/ Aluminum Holder 4 sets 800.00 3,200.00

Supply & Installation of 5.5mm Thk x 6 Blades x 0.60m width Smoke Glass

Jalousies w/ Aluminum Holder 1 set 500.00 500.00

TOTAL DIRECT COST OF GLASS WORK

9. STEEL WORKS (WINDOW GRILLES)

a. Materials:

W-1 (1 Unit)

10mm x 10mm x 6.00m. M.S. Square Bar 1 pc. 260.00 260.00

12mm x 12mm x 6.00m. M.S. Square Bar 1 pc. 311.00 311.00

6mm thk. x 20mm x 6.00m. M.S. Flat Bar 1 pc. 700.00 700.00

Hack Saw Blade 4 pcs. 65.00 260.00

6011 Welding Rod 5 kgs 160.00 800.00

W-2 (2 Units)

10mm x 10mm x 6.00m. Square bars 1 pc. 260.00 260.00

12mm x 12mm x 6.00m. Square bars 10 pcs. 311.00 3,110.00

6mm thk. x 20mm x 6.00m. M.S. Flat bars 3 pcs. 700.00 2,100.00

Hack Saw Blade 4 pcs. 65.00 260.00

6011 Welding Rod 8 kgs 160.00 1,280.00

b. Labors:

1 -Welder 3 days 394.00 1,182.00

2 -Contractual Laborers 3 days 317.00 1,902.00

c. Equipment:

1 - Unit Welding Machine w/ Cutting Outfit 3 days 2,200.00 6,600.00

1 Unit Disk Grinder 3 days 300.00 900.00

4" Grinding Disk 4 pcs. 180.00 720.00

TOTAL DIRECT COST OF STEEL WORKS (Window Grilles)

10. WATER PROOFING WORKS (LUMP SUM)

Bituminous Membrane Polyester Reinforced Water Proofing 11 sq.mtr. 1,000.00 11,000.00

TOTAL DIRECT COST OF WATER PROOFING WORKS (LUMP SUM)

11. PAINTING WORKS (120.00 Sq. M.)

a. Materials:

Concrete Neutralizer 3 gals. 320.00 960.00

Solvent Based Acrylic Paint Primer 5 gals. 1,050.00 5,250.00

Solvent Based Acrylic Cast 4 gals. 500.00 2,000.00

Solvent Based Acrylic Paint Top Coat White Gloss 10 gals. 1,050.00 10,500.00

Solvent Based Acrylic Reducer 4 gals. 420.00 1,680.00

Lacquer thinner 2 gals. 250.00 500.00

Body Filler w/ Hardener 1 gal 620.00 620.00

Pricelist as of February 2013 158 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 159: Dumalon W.S. Ground Tank_Final

Sand paper#150 1 doz. 150.00 150.00

Sand paper#120 1 doz. 150.00 150.00

Red Tinting Color for Solvent Based Acrylic Paint 2 pints 105.00 210.00

Raw Sienna Tinting Color for Solvent Based Acrylic Paint 6 pints 105.00 630.00

Thalo Blue Tinting Color for Solvent Based Acrylic Paint 4 pints 105.00 420.00

Lamp Black Tinting Color for Solvent Based Acrylic Paint 2 pints 105.00 210.00

Red Lead Paint Primer 2 qrts. 143.00 286.00

Quick Dry Enamel (Royal Blue) 2 qrts. 155.00 310.00

7" Roller Brush w/ Handle 2 sets 68.00 136.00

7" Paint Tray 1 pc. 30.00 30.00

2" Steel Brush 1 pc. 25.00 25.00

3" Paint Brush 1 pc. 30.00 30.00

2" Paint Brush 1 pc. 20.00 20.00

b. Labors:

1 - Painter 10 days 366.00 3,660.00

1 - Contractual Laborers 10 days 317.00 3,170.00

TOTAL COST OF PAINTING WORKS

12. CONSTRUCTION OF SEPTIC VAULT (SEALED)

12.1. CONCRETE & REINFORCED STEEL WORKS

a.Materials:

1. Bottom Slab

Portland Cement 6 bags 245.00 1,470.00

Washed Sand 0.25 cu.m. 1,000.00 250.00

Gravel (G1) 0.5 cu.m. 1,000.00 500.00

Concrete Water Proofing Compound 6 packs 35.00 210.00

10mmØ x 6.00m. Def. Reinforcing Steel Bars 5 pcs. 190.00 950.00

#16 G.I. Tie Wire 1 kg. 75.00 75.00

2.1.2. Top Slab

Portland Cement 3 bags 245.00 735.00

Washed Sand 0.25 cu.m. 1,000.00 250.00

Gravel (G1) 0.25 cu.m. 1,000.00 250.00

Concrete Water Proofing Compound 3 packs 35.00 105.00

10mmØ x 6.00m. Def. Reinforcing Steel Bars 10 pcs. 190.00 1,900.00

#16 G.I. Tie Wire 2 kgs. 75.00 150.00

b.Labors:

1 - Mason 2 days 366.00 732.00

2 - Contractual Laborer 2 days 317.00 1,268.00

12.2. MASONRY WORKS

a.Materials:

100mm x 200mm x 400mm Concrete Hollow Block (NLB) 160 pcs. 17.00 2,720.00

Portland Cement 16 bags 245.00 3,920.00

Washed Sand 1 cu.m. 1,000.00 1,000.00

Fine Sand (For Plastering) 0.5 cu.m. 1,400.00 700.00

10mmØ x 6.00m. Def. Reinforcing Steel Bars 14 pcs. 190.00 2,660.00

#16 G.I. Tie Wire 2 kgs. 75.00 150.00

b.Labors:

1 - Mason 2 days 366.00 732.00

1 - Contractual Laborer 2 days 317.00 634.00

12.3. CARPENTRY WORKS

a. Materials:

Forms & Scaffolding

12mm Thk x 1.20m x 2.4m Ordinary Plywood 5 shts. 975.00 4,875.00

30 - pcs. 2" x 2" x 10' Coco Lumber 100 bd.ft. 20.00 2,000.00

30 - pcs. 2" x 3" x 10' Coco Lumber 150 bd.ft. 20.00 3,000.00

4" C.W. Nail 2 kgs. 70.00 140.00

3" C.W. Nail 2 kgs. 70.00 140.00

1-1/2"" C.W. Nail 1 kg. 65.00 65.00

b. Labor:

1 - Carpenter 2 days 366.00 732.00

1 - Contractual Laborer 2 days 317.00 634.00

12.4. Bituminous Membrane Polyester Reinforced Water Proofing 15.7 sq.m. 1,000.00 15,700.00

TOTAL COST OF CONSTRUCTION OF SEPTIC VAULT

TOTAL COST OF OPERATOR'S ROOM

V. CONSTRUCTION OF GUARD HOUSE (2.89 SQ. M.)

1. EXCAVATION WORKS (1.60 CU.M.)

a. Laborers

2 - Laborers 1 day 317.00 634.00

TOTAL COST OF EXCAVATION WORKS

456,996.00Php

Pricelist as of February 2013 159 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 160: Dumalon W.S. Ground Tank_Final

2. CONCRETE WORKS (3.00 Cu.M.)

a. Material:

F (4 Units)

Portland Cement 5 bags 245.00 1,225.00

Washed Sand 0.25 cu.m. 1,000.00 250.00

Gravel (G1) 0.5 cu.m. 1,000.00 500.00

C (4 Units)

Portland Cement 3 bags 245.00 735.00

Washed Sand 0.125 cu.m. 1,000.00 125.00

Gravel (G1) 0.25 cu.m. 1,000.00 250.00

WF (5.60 Ln.M.)

Portland Cement 3 bags 245.00 735.00

Washed Sand 0.125 cu.m. 1,000.00 125.00

Gravel (G1) 0.25 cu.m. 1,000.00 250.00

Floor Lintel Beam (6.90 Ln. M.)

Portland Cement 3 bags 245.00 735.00

Washed Sand 0.125 cu.m. 1,000.00 125.00

Gravel (G1) 0.25 cu.m. 1,000.00 250.00

Door & Window Lintel Beam (4.20 Ln.M.)

Portland Cement 2 bags 245.00 490.00

Washed Sand 0.125 cu.m. 1,000.00 125.00

Gravel (G1) 0.125 cu.m. 1,000.00 125.00

Concrete Floor Slab (2.25 Sq.M.)

Portland Cement 3 bags 245.00 735.00

Washed Sand 0.125 cu.m. 1,000.00 125.00

Gravel (G1) 0.25 cu.m. 1,000.00 250.00

Reinforced Concrete Beam

Portland Cement 3 bags 245.00 735.00

Washed Sand 0.125 cu.m. 1,000.00 125.00

Gravel (G1) 0.25 cu.m. 1,000.00 250.00

Roof Slab & Overhang

Portland Cement 6 bags 245.00 1,470.00

Washed Sand 0.25 cu.m. 1,000.00 250.00

Gravel (G1) 0.5 cu.m. 1,000.00 500.00

False Beam (0.10 x 0.25m x 20.50 ln.m.)

Portland Cement 5 bags 245.00 1,225.00

Washed Sand 0.25 cu.m. 1,000.00 250.00

Gravel (G1) 0.5 cu.m. 1,000.00 500.00

b. Labor:

1 -Mason 3 days 366.00 1,098.00

4 - Laborer 3 days 317.00 3,804.00

c. Equipment:

1 - Unit One - Bagger Mixer 3 days 1,500.00 4,500.00

1 - Unit Concrete Vibrator 3 days 800.00 2,400.00

TOTAL COST OF CONCRETE WORKS

3. REINFORCED STEEL WORKS ( 660.00 KGS.)

a. Materials:

F (4 Units)

16mm.Ø x 6.00m Deformed Reinf. Steel Bar 5 pcs 480.00 2,400.00

#16 G.I. Tie Wire 0.5 kg. 75.00 37.50

Hacksaw Blade 2 pcs. 65.00 130.00

C (4 Units)

16mm.Ø x 6.00m Deformed Reinf. Steel Bar 16 pcs 480.00 7,680.00

10mm.Ø x 6.00m Deformed Reinf. Steel Bar 9 pcs 190.00 1,710.00

#16 G.I. Tie Wire 3.5 kgs. 75.00 262.50

Hacksaw Blade 3 pcs. 65.00 195.00

WF (5.60 Ln.M.)

12mm.Ø x 6.00m Deformed Reinf. Steel Bar 2 pcs 270.00 540.00

10mm.Ø x 6.00m Deformed Reinf. Steel Bar 3 pcs 190.00 570.00

#16 G.I. Tie Wire 0.5 kg. 75.00 37.50

Hacksaw Blade 2 pcs. 65.00 130.00

Floor Lintel Beam (6.90 Ln. M.)

12mm.Ø x 6.00m Deformed Reinf. Steel Bar 5 pcs 270.00 1,350.00

10mm.Ø x 6.00m Deformed Reinf. Steel Bar 4 pcs 190.00 760.00

#16 G.I. Tie Wire 1.5 kgs. 75.00 112.50

Hacksaw Blade 2 pcs. 65.00 130.00

Pricelist as of February 2013 160 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 161: Dumalon W.S. Ground Tank_Final

Door & Window Lintel Beam (4.20 Ln.M.)

12mm.Ø x 6.00m Deformed Reinf. Steel Bar 2 pcs. 270.00 540.00

10mm.Ø x 6.00m Deformed Reinf. Steel Bar 2 pcs. 190.00 380.00

#16 G.I. Tie Wire 0.5 kg. 75.00 38.00

Hacksaw Blade 1 pc. 65.00 65.00

Concrete Floor Slab (2.25 Sq.M.)

10mm.Ø x 6.00m Deformed Reinf. Steel Bar 4 pcs 190.00 760.00

#16 G.I. Tie Wire 1 kg. 75.00 75.00

Hacksaw Blade 1 pc. 65.00 65.00

Reinforced Concrete Beam

16mm.Ø x 6.00m Deformed Reinf. Steel Bar 8 pcs 480.00 3,840.00

10mm.Ø x 6.00m Deformed Reinf. Steel Bar 10 pcs 190.00 1,900.00

#16 G.I. Tie Wire 2 kgs. 75.00 150.00

Hacksaw Blade 4 pcs. 65.00 260.00

Roof Slab & Overhang

12mm.Ø x 6.00m Deformed Reinf. Steel Bar 24 pcs 270.00 6,480.00

#16 G.I. Tie Wire 3 kgs. 75.00 225.00

Hacksaw Blade 8 pcs. 65.00 520.00

False Beam (0.10 x 0.25m x 20.50 ln.m.)

12mm.Ø x 6.00m Deformed Reinf. Steel Bar 12 pcs 240.00 2,880.00

10mm.Ø x 6.00m Deformed Reinf. Steel Bar 11 pcs 190.00 2,090.00

#16 G.I. Tie Wire 4 kgs. 75.00 300.00

Hacksaw Blade 8 pcs. 65.00 520.00

b. Labor:

1 -Steelman 8 days 366.00 2,928.00

2 - Laborer 8 days 317.00 5,072.00

TOTAL COST OF REINFORCED STEEL WORKS

4. MASONRY WORKS

4.1. Laying of CHB (17.60 Sq. M.)

a. Material:

150mm x 200mm x 400mm CHB (LB) 42 pcs. 24.00 1,008.00

100mm x 200mm x 400mm CHB (NLB) 185 pcs. 17.00 3,145.00

Portland Cement 16 bags 245.00 3,920.00

Washed Sand 1.25 cu.m. 1,000.00 1,250.00

10mm.Ø x 6.00m Deformed Reinf. Steel Bar 12 pcs. 190.00 2,280.00

#16 G.I. Tie Wire 5 kgs. 75.00 375.00

Hacksaw Blade 8 pcs. 65.00 520.00

b. Labor:

1 - Mason 3 days 366.00 1,098.00

1 - Laborer 3 days 317.00 951.00

4.2. Plastering Works (53.25 Sq.M.)

a. Material

Portland Cement 10 bags 245.00 2,450.00

Fine Sand (For Plastering) 0.75 cu.m. 1,400.00 1,050.00

b. Labor:

1 - Mason 4 days 366.00 1,464.00

1 - Laborer 4 days 317.00 1,268.00

TOTAL COST OF MASONRY WORKS

5. TILE WORKS (2.56 Sq. M.)

a. Material:

400mm x 400mm Granite Tiles 17 pcs. 255.00 4,335.00

Tile Adhesive (25Kg/Bag) 1 bag 305.00 305.00

Tile Grout (2 Kg./Pack) 1 bag 85.00 85.00

4" Grinding Wheel 1 pc. 180.00 180.00

b. Labor:

1 - Mason 2 days 366.00 732.00

1 - Laborer 2 days 317.00 634.00

c. Equipment Rental:

1 - Unit Tile Cutter 2 days 300.00 600.00

1 - Angular Grinder 2 days 300.00 600.00

TOTAL COST OF TILE WORKS

6. FORM & SCAFFOLDING WORKS

a. Materials:

40 pcs. - 2" x 2" x 10" Coco Lumber 133 bd.ft. 20.00 2,660.00

40 pcs. - 2" x 3" x 10" Coco Lumber 200 bd.ft. 20.00 4,000.00

20 pcs. - 2" x 4" x 10" Coco Lumber 133 bd.ft. 20.00 2,660.00

Pricelist as of February 2013 161 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 162: Dumalon W.S. Ground Tank_Final

12mm Thk x 1.20 m x 2.40 m Ordinary Plywood 8 shts. 975.00 7,800.00

1-1/2" C.W. Nail 2 kgs. 65.00 130.00

3" C.W. Nail 3 kgs. 70.00 210.00

4" C.W. Nail 3 kgs. 70.00 210.00

b. Labor:

1 - Carpenter 4 days 366.00 1,464.00

1 - Laborer 4 days 317.00 1,268.00

TOTAL COST OF FORM & SCAFFOLDING WORKS

7. CARPENTRY WORKS

7.1. Intallation of Pre-Fabricated of Doors & Windows:

a. Material:

Prefabricated - 0.60m x 2.10m Pannel Type Door, 50mm x 150mm Mahogany Wood Door Frame 1 unit 4,400.00 4,400.00

& 38mm Thick Door Board w/ 50mm x 100mm Mahogany Wood Door Jamb

Prefabricated - 0.70m x 1.165m 1-Pannel Window Jamb, 50mm x 150mm Mahogany Wood 2 units 800.00 1,600.00

Chrome Heavy Duty Door Knob 1 unit 950.00 950.00

Stainless Door Stopper 1 unit 170.00 170.00

4" x 3" Loose Pin Hinges w/ Screw 4 pcs. 140.00 560.00

4" C.W. Nail 1 kg. 70.00 70.00

b. Labor:

1 - Carpenter 2 days 366.00 732.00

1 - Laborer 2 days 317.00 634.00

7.2. Fabrication of Cabinet

a. Material:

Cabinet Handle (Chrome) 5 pcs. 160.00 800.00

Cabinet Concealed Hinges w/ Screw 10 pcs. 60.00 600.00

3 pcs. - 1" x 1" x 10' Mahogany Lumber 2.5 bd.ft. 34.00 85.00

19mm Thk x 1.20m x 2.40m Plyboard 5 shts. 1,100.00 5,500.00

6mm Thk x 1.20m x 2.40m Plyboard 2 shts. 420.00 840.00

3" C.W. Nail 2 kgs. 70.00 140.00

1" C.W. Finishing Nail 2 kgs. 75.00 150.00

b. Labor:

1 - Carpenter 5 days 366.00 1,830.00

1 - Laborer 5 days 317.00 1,585.00

TOTAL COST OF CARPENTRY WORKS

8. STEEL WORKS

a. Material:

10mm x 10mm x 6.00m M.S. Square Bar 1 pc. 260.00 260.00

12mm x 12mm x 6.00m M.S. Square Bar 4 pcs. 311.00 1,244.00

6mm Thk x 50mm x 6.00m M.S. Flat Bar 2 pcs. 880.00 1,760.00

Hacksaw Blade 4 pcs. 65.00 260.00

6011 Welding Rod 8 kgs 160.00 1,280.00

Industrial Oxygen (Content) 2 cyls. 750.00 1,500.00

Acetylene (Content) 1 cyl. 1,500.00 1,500.00

b. Labor:

1 - Welder 3 days 394.00 1,182.00

1 - Laborer 3 days 317.00 951.00

c. Equipment Rental/Fuel:

1 - Unit Welding Machine w/ Cutting Outfit 3 days 2,200.00 6,600.00

1 - Unit Disk Grinder 3 days 400.00 1,200.00

4" Grinding Wheel 1 pc. 180.00 180.00

TOTAL COST OF STEEL WORKS

9 GLASS WORKS (LUMP SUM)

Supply & Installation of 5.5 mm Thk x 13 Blades x 0.60m width Smoke Glass Jalousies

w/ Aluminum Holder 2 sets 800.00 1,600.00

TOTAL DIRECT COST OF GLASS WORK (LUMP SUM)

10. PLUMBING WORKS

a. Materials:

50mmØ x 3.00m. PVC Sanitary Pipe Series 1000 2 pcs. 306.00 612.00

50mmØ x 900 PVC Sanitary Elbow, Series 1000 3 pcs. 45.00 135.00

50mmØ PVC Coupling, Series 1000 2 pcs. 80.00 160.00

PVC Solvent Cement 1 qrt. 334.00 334.00

100mm x 100mmStainless Floor Drain 1 pc. 68.00 68.00

b. Labors:

1 - Plumber 1 day 366.00 366.00

1 - Contractual Laborers 1 day 317.00 317.00

TOTAL DIRECT COST OF PLUMBING WORKS

11. WATERPROOFING WORKS (LUMP SUM)

Pricelist as of February 2013 162 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 163: Dumalon W.S. Ground Tank_Final

Bituminous Membrane Polyester Reinforced Waterproofing 2.9 sq.mtr. 1,000.00 2,900.00

TOTAL DIRECT COST OF WATERPROOFING WORKS (LUMP SUM)

12. PAINTING WORKS (48.00 Sq. M.)

a. Materials:

Concrete Neutralizer 1 gal. 320.00 320.00

Solvent Based Acrylic Paint Primer 2 gals. 1,050.00 2,100.00

Solvent Based Acrylic Cast 1 gal. 400.00 400.00

Solvent Based Acrylic Paint Top Coat White Gloss 4 gals. 1,050.00 4,200.00

Solvent Based Acrylic Paint Reducer 1 gal. 420.00 420.00

Body Filler w/ Hardener 1 gal. 520.00 520.00

#150 Sand Paper 1 doz. 150.00 150.00

#120 Sand Paper 1 doz. 150.00 150.00

Raw Sienna Tinting Color for Solvent Based Acrylic Paint 1 pint 105.00 105.00

Thalo Blue Tinting Color for Solvent Based Acrylic Paint 1 pint 105.00 105.00

Lamp Black Tinting Color for Solvent Based Acrylic Paint 1 pint 105.00 105.00

Steel Brush 1 pc. 25.00 25.00

3" Paint Brush 1 pc. 30.00 30.00

2" Paint Brush 1 pc. 20.00 20.00

b. Labors:

1 - Painter 5 days 366.00 1,830.00

1 - Laborer 5 days 317.00 1,585.00

TOTAL COST OF PAINTING WORKS

TOTAL COST OF CONSTRUCTION OF GUARD HOUSE

VI. CONSTRUCTION OF (2.73 SQ. MTR.) CHLORINE ROOM

1. CONCRETE & REINFORCED STEEL WORKS

a.Materials:

1.1 Wall

Portland Cement 12 bags 245.00 2,940.00

Washed Sand 0.5 cu.m. 1,000.00 500.00

Gravel (G1) 1.25 cu.m. 1,000.00 1,250.00

10mmØ x 6.00m. Deformed Reinf. Steel Bar 18 pcs. 190.00 3,420.00

12mmØ x 6.00m. Deformed Reinf. Steel Bar 8 pcs. 270.00 2,160.00

#16 G.I. Tie Wire 3 kgs. 75.00 225.00

1.2 Roof Slab

Portland Cement 7 bags 245.00 1,715.00

Washed Sand 0.25 cu.m. 1,000.00 250.00

Gravel (G1) 0.5 cu.m. 1,000.00 500.00

Concrete Water Proofing Compound (900 g) 7 packs 35.00 245.00

12mm

Ø x 6.00m. Deformed Reinf. Steel Bar 18 pcs. 270.00 4,860.00

#16 G.I. Tie Wire 3 kgs. 75.00 225.00

1.3 Floor Slab

Portland Cement 3 bags 245.00 735.00

Washed Sand 0.25 cu.m. 1,000.00 250.00

Gravel (G1) 0.5 cu.m. 1,000.00 500.00

10mm

Ø x 6.00m. Deformed Reinf. Steel Bar 7 pcs. 190.00 1,330.00

#16 G.I. Tie Wire 1 kg. 75.00 75.00

1.4. Door Lintel Beam

Portland Cement 2 bags 245.00 490.00

Washed Sand 0.125 cu.m. 1,000.00 125.00

Gravel (G1) 0.125 cu.m. 1,000.00 125.00

12mm

Ø x 6.00m. Deformed Reinf. Steel Bar 1 pc. 270.00 270.00

10mm

Ø x 6.00m. Deformed Reinf. Steel Bar 1 pc. 190.00 190.00

#16 G.I. Tie Wire 1 kgs. 75.00 75.00

b. Labors:

1 - Mason 7 days 366.00 2,562.00

2 - Contractual Laborers 7 days 317.00 4,438.00

TOTAL COST OF CONCRETE & REINFORCED STEEL WORKS

2. MASONRY WORKS

a.Materials:

1. CHB Laying & Plastering Works

100mm x 200mm x 400mm CHB (NLB) 70 pcs. 17.00 1,190.00

Portland Cement 10 bags 245.00 2,450.00

Washed Sand 0.25 cu.m. 1,000.00 250.00

Fine Sand (For Plastering) 0.5 cu.m. 1,400.00 700.00

10mm dia x 6.00m Deformed Reinf. Steel Bar 5 pcs. 190.00 950.00

#16 G.I. Tie Wire 1 kg. 75.00 75.00

b.Labor:

1 - Mason 3 days 366.00 1,098.00

1 - Contractual Laborers 3 days 317.00 951.00

175,801.00

Pricelist as of February 2013 163 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 164: Dumalon W.S. Ground Tank_Final

TOTAL COST OF MASONRY WORKS

3. CARPENTRY WORKS

3.1 Installation of Pre-Fabricated PVC Door

a.Materials:

Pre-fabricated 800mm x 2100mm PVC Door w/ Jamb, Door Knob, Hinges & Screw 1 unit 2,200.00 2,200.00

Stainless Door Knob (Heavy Duty) 1 unit 950.00 950.00

3.2. Forms & Scaffolding Works

a. Materials:

12mm Thk x 1.20m x 2.40m Ordinary Plywood 5 shts. 975.00 4,875.00

40 - pcs. 2" x 2" x 10' Coco Lumber 133 bd.ft. 20.00 2,660.00

40 - pcs. 2" x 3" x 10' Coco Lumber 200 bd.ft. 20.00 4,000.00

4" C.W. Nail 4 kgs. 70.00 280.00

3" C.W. Nail 4 kgs. 70.00 280.00

1-1/2" C.W. Nail 2 kgs. 65.00 130.00

b.Labor:

1 - Carpenter 4 days 366.00 1,464.00

2 - Laborer 4 days 317.00 2,536.00

TOTAL COST OF CARPENTRY WORKS

4. PAINTING WORKS

a. Materials:

Solvent Based Acrylic Paint Primer 1 gal. 1,050.00 1,050.00

Solvent Based Acrylic Cast 1 gal. 500.00 500.00

Solvent Based Acrylic Top Coat White Gloss Paint 2 gals. 1,050.00 2,100.00

Solvent Based Acrylic Paint Reducer 1 gal. 420.00 420.00

Red Tinting Color for Solvent Based Acrylic Paint 1 pint 105.00 105.00

Raw Sienna Tinting Color for Solvent Based Acrylic Paint 1 pint 105.00 105.00

Thalo Blue Tinting Color for Solvent Based Acrylic Paint 1 pint 105.00 105.00

Lamp Black Tinting Color for Solvent Based Acrylic Paint 1 pint 105.00 105.00

3" Paint Brush 1 pc. 30.00 30.00

b. Labors:

1 - Painter 3 days 317.00 951.00

1 - Laborer 3 days 317.00 951.00

TOTAL COST OF PAINTING WORKS

5. WATER PROOFING WORKS (LUMP SUM)

6.21 sq.mtr. 1,000.00 6,210.00

TOTAL COST OF WATER PROOFING WORKS

TOTAL COST OF CHLORINE ROOM

VII. CONSTRUCTION OF 200MM Ø & 300MM Ø RCCP DRAINAGE SYSTEM

1. CATCH BASIN/MANHOLE

1.1. EXCAVATION WORKS

b. Labor:

1 - Skilled Worker 3 days 366.00 1,098.00

4 - Laborer 3 days 317.00 3,804.00

TOTAL COST OF EXCAVATION WORKS

1.2. CONCRETE & REINFORCED STEEL WORKS

a. Materials:

Portland Cement 28 bags 245.00 6,860.00

Washed Sand 1.5 cu.m. 1,000.00 1,500.00

Gravel (G1) 3 cu.m. 1,000.00 3,000.00

10mmØ x 6.00m Deformed Reinf. Steel Bar 26 pcs. 190.00 4,940.00

#16 G.I. Tie Wire 2 kgs. 75.00 150.00

b. Labor:

1 - Mason 8 days 366.00 2,928.00

1 - Laborer 8 days 317.00 2,536.00

TOTAL COST OF CONCRETE & REINFORCED STEEL WORKS

1.3. MASONRY WORKS

a. Materials:

100mm x 200mm x 400mm CHB (NLB) 330 pcs. 17.00 5,610.00

Portland Cement 14 bags 245.00 3,430.00

Washed Sand 2 cu.m. 1,000.00 2,000.00

Fine Sand (For Plastering) 1 cu.m. 1,400.00 1,400.00

b. Labor:

1 - Mason 7 days 366.00 2,562.00

1 - Laborer 7 days 317.00 2,219.00

TOTAL COST OF MASONRY WORKS

2. LAYING OF 200mm Ø & 300mmØ RCCP

a. Materials:

69,126.00

Pricelist as of February 2013 164 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 165: Dumalon W.S. Ground Tank_Final

300mmØ x 1.0m RCCP 22 pcs. 1,078.00 23,716.00

200mmØ x 1.0m RCCP 16 pcs. 748.00 11,968.00

Portland Cement 9 bags 245.00 2,205.00

Washed Sand 0.5 cu.m. 1,000.00 500.00

b. Labor:

1 - Mason 7 days 366.00 2,562.00

8 - Laborer 7 days 317.00 17,752.00

TOTAL COST OF LAYING OF 200mm Ø & 300mmØ RCCP

TOTAL COST OF CONSTRUCTION OF 300MM Ø RCCP DRAINAGE SYSTEM

VIII. CONSTRUCTION OF CONCRETE CATWALK/DRIVE WAY

1. Concrete Walk Pad

a. Materials:

Portland Cement 21 bags 245.00 5,145.00

Washed Sand 1.25 cu.m. 1,000.00 1,250.00

Gravel (G1) 2.5 cu.m. 1,000.00 2,500.00

10mmØ x 6.00m Def. Reinf. Steel Bar 25 pcs. 190.00 4,750.00

#16 G.I. Tie-wire 3 kgs. 65.00 195.00

Hacksaw Blade 4 pcs. 65.00 260.00

2. 150mm Thk Concrete Driveway (106 Sq.M.)

a. Materials:

Portland Cement 141 bags 245.00 34,545.00

Washed Sand 7 cu.m. 1,000.00 7,000.00

Gravel (G1) 10.5 cu.m. 1,000.00 10,500.00

Item 201 (Aggregates Base Course) 25 cu.m. 800.00 20,000.00

Item 200 (Aggregates Sub-Base Course) 25 cu.m. 450.00 11,250.00

8 pcs. - 1" x 6" x 8' Coco Lumber 32 bd.ft. 20.00 640.00

40 pcs. - 2" x 2" x 8' Coco Lumber 107 bd.ft. 20.00 2,140.00

4" C.W. Nail 2 kgs. 70.00 140.00

3" C.W. Nail 2 kgs. 70.00 140.00

b. Labor:

2 - Skilled Workers 8 days 366.00 5,856.00

8 - Laborer 8 days 317.00 20,288.00

c. Equipment Rental/Fuel:

1 - Unit Concrete Vibrator 5 days 800.00 4,000.00

1 - Unit One - Bagger Mixer 5 days 1,500.00 7,500.00

TOTAL COST OF CONSTRUCTION OF CONCRETE CATWALK/DRIVE WAY

IX. CONSTRUCTION OF 59.00 LN.M. RIPRAP

1. Layout & Excavation Works:

a. Labor:

2 - Skilled Workers 5 days 366.00 3,660.00

8 - Laborer 5 days 317.00 12,680.00

2. Masonry Works:

a. Materials:

150mmØ Boulder 179 cu.m. 900.00 161,100.00

Portland Cement 230 bags 245.00 56,350.00

Washed Sand 25.5 cu.m. 1,000.00 25,500.00

12mmØ x 6.00m Def. Reinf. Steel Bar 140 pcs. 270.00 37,800.00

#16 G.I. Tie-wire 3 kgs. 65.00 195.00

Hacksaw Blade 6 pcs. 65.00 390.00

75mmØ x 3.00m Sanitary Pipe Series-1000 9 pcs. 473.00 4,257.00

b. Labor:

4 - Skilled Workers 25 days 366.00 36,600.00

8 - Laborer 25 days 317.00 63,400.00

c. Equipment Rental/Fuel:

1 - Unit Concrete Vibrator 25 days 800.00 20,000.00

1 - Unit One - Bagger Mixer 25 days 1,500.00 37,500.00

TOTAL COST OF CONSTRUCTION OF 59.00 LN.M. RIPRAP

X. LANDSCAPING WORKS

a. Materials:

Garden Soil 6 cu.m. 1,200.00 7,200.00

Carabao Grass 35 sq.m. 320.00 11,200.00

b. Labor:

2 - Skilled Workers 5 days 366.00 3,660.00

2 - Laborer 5 days 317.00 3,170.00

c. Equipment Rental:

1 - Unit Compact Hand Roller 5 days 7,200.00 36,000.00

TOTAL COST OF LANDSCAPING WORKS

102,740.00

Pricelist as of February 2013 165 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 166: Dumalon W.S. Ground Tank_Final

XI. ELECTRICAL WORKS

TOTAL NUMBER OF OUTLETS: 31

1. MOBILIZATION/DEMOBILIZATION 1 lot 2,000.00 2,000.00

2. SUPPLY, TESTING & INSTALLATION OF KW-HR METER, RACEWAY AND ACCESSORIES

a. Material

Kiliwatthour Meter (Digital), 250 Volts, Single Phase, Assembly, 1 assy. 8,160.00 8,160.00

GE Class 200, 5 jaw, complete w/ Rectangular Base

Testing/Calibration FEE 1 lot 100.00 100.00

25mmØ Entrance Cap 1 pc. 41.00 41.00

25mmØ x 3m RSC Conduit Pipe 1 pc. 367.00 367.00

25mmØ RSC Male Adaptor 1 pc. 8.00 8.00

25mmØ Locknut 1 pc. 6.00 6.00

25mmØ Conduit Pipe Clamp 4 pc. 7.00 28.00

Single Wire, Secondary Rack w/ Spool Insulator 1 pc. 142.00 142.00

b. Labor:

1 - Skilled Worker 1 day 366.00 366.00

1 - Laborer 1 day 317.00 317.00

Direct Cost

3. SUPPLY & INSTALLATION OF ELECTRICAL FACILITIES FOR OPERATORS ROOM

a. Material

60 Amperes Main Circuit Breaker, Single Phase, 250 Volts, Panel Board 1 set 5,766.00 5,766.00

enclosed in Powder Coated Finished Panel Box

with 5 Single Phase Branches of:

1 sets - 15 Amps. Branch

4 sets - 20 Amps. Branch

8.0mm2 THW Stranded Wire 60 mtrs. 84.00 5,040.00

3.5mm2 TW Stranded Wire 92 mtrs. 32.00 2,944.00

2.0mm2 TW Stranded Wire 75 mtrs. 23.00 1,725.00

25mmØ Entrance Cap 1 pc. 41.00 41.00

25mmØ x 3m PVC Conduit Pipe 1 pc. 131.00 131.00

25mmØ x 90o PVC Long Sweep Elbow 1 pc. 26.00 26.00

25mmØ PVC Male Adaptor 1 pc. 8.00 8.00

25mmØ Locknut 1 pc. 6.00 6.00

20mmØ Flexible Conduit 48 mtrs. 8.00 384.00

20mmØ x 3m PVC Conduit Pipe 15 pcs. 86.00 1,290.00

20mmØ x 90o PVC Long Sweep Elbow 10 pcs. 17.00 170.00

20mmØ PVC Male Adaptor 12 pcs. 6.00 72.00

20mmØ PVC Coupling 8 pcs. 5.00 40.00

20mmØ Locknut 12 pcs. 4.00 48.00

Single Wire, Secondary Rack w/ Spool Insulator 1 pc. 142.00 142.00

Surface Type Reflectorized/Mirrorized Fluorescent Luminaire with 1x40 Watts Fluorescent Tube 2 pcs. 1,132.00 2,264.00

23 Watts 3U CFL with Capsule 3 pcs. 148.00 444.00

18" Ceiling Orbit Fan, Industrial Type 1 pc. 5,477.00 5,477.00

Switch 1-Gang w/ plate (flush type), w/ Led Set, 10A, 250V 1 pc. 71.00 71.00

Switch 2-Gang w/ plate (flush type), w/ Led Set, 10A, 250V 2 pcs. 107.00 214.00

Ceiling Socket with screw 3 pcs. 31.00 93.00

Duplex Convenience Outlet w/ plate (flush type) 3 pcs. 107.00 321.00

Duplex Convenience Outlet w/ plate - weatherproof (flush type) 1 pc. 173.00 173.00

2" x 4" x 2" PVC Utility Box ( H.D.) 7 pcs. 21.00 147.00

4" x 4" PVC Junction Box ( H.D.) w/ Cover 9 pcs. 24.00 216.00

#16 G.I. Tie Wire 3 kgs. 75.00 225.00

PVC Solvent Cement 1 qrt. 460.00 460.00

1/4" Camridge / Mica Tube 1 mtrs. 13.00 13.00

0.8mm x 19mm x 8m Polytype Electrical Tape 5 pcs. 25.00 125.00

0.8mm x 19mm x 8m Rubber Tape 2 pcs. 102.00 204.00

b. Labor

1 - Skilled Worker 7 days 366.00 2,562.00

1 - Laborer 7 days 317.00 2,219.00

Direct Cost

4. SUPPLY & INSTALLATION OF ELECTRICAL FACILITIES FOR GUARD HOUSE & CHLORINATOR ROOM

a. Material

35W E27 CFL Weather Proof Street Light 1 pc. 500.00 500.00

3.5mm2 TW Stranded Wire 1 roll 4,725.00 4,725.00

20mmØ Flexible Conduit 16 pcs. 8.00 128.00

20mmØ x 3m PVC Conduit Pipe 15 pcs. 86.00 1,290.00

20mmØ x 90o PVC Long Sweep Elbow 10 pcs. 17.00 170.00

20mmØ PVC Male Adaptor 12 pcs. 6.00 72.00

20mmØ PVC Coupling 8 pcs. 5.00 40.00

20mmØ Locknut 12 pcs. 4.00 48.00

Surface Type Reflectorized/Mirrorized Fluorescent Luminaire with 1x20 Watts Fluorescent Tube 1 pc. 977.00 977.00

23 Watts 3U CFL with Capsule 3 pcs. 148.00 444.00

23 Watts PAR 38 Floodlight CFL bulb with Par Lamp Holder 1 pc. 928.00 928.00

Switch 1-Gang w/ plate (flush type), w/ Led Set, 10A, 250V 1 pc. 71.00 71.00

Switch 2-Gang w/ plate (flush type), w/ Led Set, 10A, 250V 1 pc. 107.00 107.00

Pricelist as of February 2013 166 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 167: Dumalon W.S. Ground Tank_Final

Switch 3-Gang w/ plate (flush type), w/ Led Set, 10A, 250V 1 pc. 143.00 143.00

Ceiling Socket with screw 4 pcs. 31.00 124.00

Duplex Convenience Outlet w/ plate (flush type) 2 pcs. 107.00 214.00

2" x 4" x 2" PVC Utility Box ( H.D.) 5 pcs. 21.00 105.00

4" x 4" PVC Junction Box ( H.D.) w/ Cover 13 pcs. 24.00 312.00

#16 G.I. Tie Wire 2 kgs. 75.00 150.00

PVC Solvent Cement 1 qrt. 460.00 460.00

1/4" Camridge / Mica Tube 0.5 mtr. 13.00 7.00

0.8mm x 19mm x 8m Polytype Electrical Tape 5 pcs. 25.00 125.00

0.8mm x 19mm x 8m Rubber Tape 2 pcs. 102.00 204.00

b. Labor

1 - Skilled Worker 7 days 366.00 2,562.00

1 - Laborer 7 days 317.00 2,219.00

Direct Cost

5. SUPPLY & INSTALLATION OF ELECTRICAL FACILITIES FOR SIGNAGE AND PERIMETER LIGHTINGS

a. Material

3.5mm2 TW Stranded Wire 2 rolls 4,725.00 9,450.00

20mmØ x 3m PVC Conduit Pipe 35 pcs. 86.00 3,010.00

20mmØ x 90o PVC Long Sweep Elbow 8 pcs. 17.00 136.00

20mmØ PVC Male Adaptor 36 pcs. 6.00 216.00

20mmØ PVC Coupling 18 pcs. 5.00 90.00

20mmØ Locknut 12 pcs. 4.00 48.00

Perimeter post lamp with cage, globe type, (250mmx250mm)

complete assembly with 23 watts Capsulated CFL 6 sets 1,770.00 10,620.00

4" x 4" PVC Junction Box ( H.D.) w/ Cover 16 pcs. 24.00 384.00

#16 G.I. Tie Wire 3 kgs. 75.00 225.00

PVC Solvent Cement 1 qrt. 460.00 460.00

1/4" Camridge / Mica Tube 2 mtrs. 13.00 26.00

0.8mm x 19mm x 8m Polytype Electrical Tape 5 pc. 25.00 125.00

0.8mm x 19mm x 8m Rubber Tape 2 pc. 102.00 204.00

b. Labor

1 - Skilled Worker 7 days 366.00 2,562.00

1 - Laborer 7 days 317.00 2,219.00

Direct Cost

TOTAL COST OF ELECTRICAL WORKS

Sizing Requirements:

*All sizes referred herein for ordinary plywood should mean commercially avaiable measurements with tolerance of ± 1mm.

90,496.00

Pricelist as of February 2013 167 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 168: Dumalon W.S. Ground Tank_Final

A. NON ENGINEERING BASIC COST

I. MATERIAL TESTING 43,400.00

II. BUILDING PERMIT FEE 30,000.00

III. CONST. OF TWO (2.00) UNITS TEMPORARY FACILITY 36,731.00

IV. SUPERVISION 251,520.00

1. CONSTRUCTION OF 300 CU.M. GROUND RESERVOIR AT SITIO BANDERA, DULIAN, Z.C.

I. MOBILIZATION/DEMOBILIZATION/HAULING OF MATERIAL 376,040.00

II. CONSTRUCTION OF 300.00 CU.M. GROUND TANK

1. CLEARING/ LAYOUT & EXCAVATION WORKS (262.00 Cu.M.) 52,520.00

2. SCAFFOLDING & FORM WORKS 431,430.00

3. CONCRETE WORKS (148.20 Cu.M.) 1,071,256.00

4. REINFORCED STEEL WORKS (23,329.60 KGS.) 1,299,550.00

5. MASONRY WORKS (762.00 Sq.M.) 64,352.00

6. STEEL WORKS 328,425.00

7. DISINFECTION/LEAKAGE TEST & GROUTING LEAK 65,000.00

8. SUPPLY & INST. OF GATE VALVES, DIFFERENTIAL FLOAT CONTROL VALVE & APPURTENANCES 867,418.00

9. SUPPLY & INSTALLATION OF TWO UNITS - 100MMØ FLOW METER & CONST OF CONCRETE VALVE BOX 674,299.00

10. PAINTING WORKS (223.00 Sq.M.) 69,465.00

11. WATER PROOFING WORKS FOR TOP SLAB 37,700.00

12. SUPPLY & INST. OF 40GPD HYPOCHLORINATOR 113,532.00

III. CONST. OF CONCRETE PERIMETER FENCE

1. CLEARING/LAYOUTING & EXCAVATION WORKS 6,502.00

2. CONCRETING WORKS (14.80 Cu.M.) 100,607.00

3. REINFORCED STEEL WORKS (1,940.10 KGS.) 148,100.00

4. MASONRY WORKS: 79,287.00

5. FORMS & SCAFFOLDING WORKS: 54,565.00

6. STEEL WORKS: 184,870.00

7. PAINTING WORKS 58,841.00

8. SIGNAGE WITH STAND & FRAME 23,842.00

IV. CONSTRUCTION OF (12.40 SQ. MTR.) OPERATOR'S ROOM

1. EXCAVATION WORKS (3.98 Cu.M.) 1,268.00

2. CONCRETE WORKS (8.50 Cu M.) 48,728.00

3. REINFORCED STEEL WORKS (1,093.10 KGS.) 77,535.00

4. MASONRY WORKS 106,583.00

5. CARPENTRY WORKS 33,572.00

6. SCAFFOLDING & FORM WORKS 49,786.00

7. PLUMBING WORKS 24,585.00

8. GLASS WORKS (LUMP SUM) 3,700.00

9. STEEL WORKS (WINDOW GRILLES) 20,645.00

10. WATER PROOFING WORKS (LUMP SUM) 11,000.00

11. PAINTING WORKS (120.00 Sq. M.) 30,947.00

12. CONSTRUCTION OF SEPTIC VAULT (SEALED) 48,647.00

V. CONSTRUCTION OF GUARD HOUSE (2.89 SQ. M.)

1. EXCAVATION WORKS (1.60 CU.M.) 634.00

2. CONCRETE WORKS (3.00 Cu.M.) 24,262.00

3. REINFORCED STEEL WORKS ( 660.00 KGS.) 45,133.00

4. MASONRY WORKS 20,779.00

5. TILE WORKS (2.56 Sq. M.) 7,471.00

6. FORM & SCAFFOLDING WORKS 20,402.00

7. CARPENTRY WORKS 20,646.00

8. STEEL WORKS 17,917.00

9 GLASS WORKS (LUMP SUM) 1,600.00

10. PLUMBING WORKS 1,992.00

11. WATERPROOFING WORKS (LUMP SUM) 2,900.00

12. PAINTING WORKS (48.00 Sq. M.) 12,065.00

VI. CONSTRUCTION OF (2.73 SQ. MTR.) CHLORINE ROOM

1. CONCRETE & REINFORCED STEEL WORKS 29,455.00

2. MASONRY WORKS 7,664.00

3. CARPENTRY WORKS 19,375.00

4. PAINTING WORKS 6,422.00

S U M M A R Y

Pricelist as of February 2013 168 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 169: Dumalon W.S. Ground Tank_Final

5. WATER PROOFING WORKS (LUMP SUM) 6,210.00

VII. CONSTRUCTION OF 200MM Ø & 300MM Ø RCCP DRAINAGE SYSTEM 102,740.00

VIII. CONSTRUCTION OF CONCRETE CATWALK/DRIVE WAY 138,099.00

IX. LANDSCAPING WORKS 61,230.00

X. ELECTRICAL WORKS 90,496.00

2. CONSTRUCTION OF 300 CU.M. GROUND RESERVOIR AT BALUNO, Z.C.

I. MOBILIZATION/DEMOBILIZATION/HAULING OF MATERIAL 376,040.00

II. CONSTRUCTION OF 300.00 CU.M. GROUND TANK

1. CLEARING & EXCAVATION WORKS (262.00 Cu.M.) 52,520.00

2. SCAFFOLDING & FORM WORKS 431,430.00

3. CONCRETE WORKS (148.20 Cu.M.) 1,071,256.00

4. REINFORCED STEEL WORKS (23,329.60 KGS.) 1,299,550.00

5. MASONRY WORKS (762.00 Sq.M.) 64,352.00

6. STEEL WORKS 328,425.00

7. DISINFECTION/LEAKAGE TEST & GROUTING LEAK 65,000.00

8. SUPPLY & INST. OF GATE VALVES, DIFFERENTIAL FLOAT CONTROL VALVE & APPURTENANCES 1,448,868.00

9. SUPPLY & INSTALLATION OF TWO UNITS - 100MMØ FLOW METER & CONST OF CONCRETE VALVE BOX 674,299.00

10. PAINTING WORKS (223.00 Sq.M.) 69,465.00

11. WATER PROOFING WORKS FOR TOP SLAB 37,700.00

12. SUPPLY & INST. OF 40GPD HYPOCHLORINATOR 113,532.00

III. CONST. OF CONCRETE PERIMETER FENCE

1. CLEARING/LAYOUTING & EXCAVATION WORKS 6,502.00

2. CONCRETING WORKS (14.80 Cu.M.) 253,133.05

3. REINFORCED STEEL WORKS (1,940.10 KGS.) 121,650.00

4. MASONRY WORKS: 79,287.00

5. FORMS & SCAFFOLDING WORKS: 54,565.00

6. STEEL WORKS: 184,870.00

7. PAINTING WORKS 58,841.00

8. SIGNAGE WITH STAND & FRAME 23,842.00

IV. CONSTRUCTION OF (12.40 SQ. MTR.) OPERATOR'S ROOM

1. EXCAVATION WORKS (3.98 Cu.M.) 1,268.00

2. CONCRETE WORKS (8.50 Cu M.) 48,728.00

3. REINFORCED STEEL WORKS (1,093.10 KGS.) 77,535.00

4. MASONRY WORKS 106,583.00

5. CARPENTRY WORKS 33,572.00

6. SCAFFOLDING & FORM WORKS 49,786.00

7. PLUMBING WORKS 24,585.00

8. GLASS WORKS (LUMP SUM) 3,700.00

9. STEEL WORKS (WINDOW GRILLES) 20,645.00

10. WATER PROOFING WORKS (LUMP SUM) 11,000.00

11. PAINTING WORKS (120.00 Sq. M.) 30,947.00

12. CONSTRUCTION OF SEPTIC VAULT (SEALED) 48,647.00

V. CONSTRUCTION OF GUARD HOUSE (2.89 SQ. M.)

1. EXCAVATION WORKS (1.60 CU.M.) 634.00

2. CONCRETE WORKS (3.00 Cu.M.) 24,262.00

3. REINFORCED STEEL WORKS ( 660.00 KGS.) 45,133.00

4. MASONRY WORKS 20,779.00

5. TILE WORKS (2.56 Sq. M.) 7,471.00

6. FORM & SCAFFOLDING WORKS 20,402.00

7. CARPENTRY WORKS 20,646.00

8. STEEL WORKS 17,917.00

9 GLASS WORKS (LUMP SUM) 1,600.00

10. PLUMBING WORKS 1,992.00

11. WATERPROOFING WORKS (LUMP SUM) 2,900.00

12. PAINTING WORKS (48.00 Sq. M.) 12,065.00

VI. CONSTRUCTION OF (2.73 SQ. MTR.) CHLORINE ROOM

1. CONCRETE & REINFORCED STEEL WORKS 29,455.00

2. MASONRY WORKS 7,664.00

3. CARPENTRY WORKS 19,375.00

4. PAINTING WORKS 6,422.00

5. WATER PROOFING WORKS (LUMP SUM) 6,210.00

VII. CONSTRUCTION OF 200MM Ø & 300MM Ø RCCP DRAINAGE SYSTEM 102,740.00

VIII. CONSTRUCTION OF CONCRETE CATWALK/DRIVE WAY 138,099.00

IX. CONSTRUCTION OF 59.00 LN.M. RIPRAP 459,432.00

X. LANDSCAPING WORKS 61,230.00

XI. ELECTRICAL WORKS 90,496.00

DIRECT COST

Pricelist as of February 2013 169 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 170: Dumalon W.S. Ground Tank_Final

OCM

CONTRACTOR'S PROFIT (10%)VAT (12%)

TOTAL PROJECT COST

Prepared by: Reviewed & Checked by: Submitted by:

EDITO M. BAUTISTA, JR. MARIE CLAIRE C. BONGO

Senior Engineer A (C.E.) Principal Engineer C

Planning & Design Division

ARIANN D. GODINEZ

J.O. - Senior Engineer A (E.E.)

MARK BENEDICT C. REYES

J.O. - Senior Engineer A (M.E.)

Approved by: Recommending Project Implementation: Approved for project Implementation:

ARNULFO A. ALFONSO

Department Manager C

Maintenance Department

21,413,665.80Php

EFREN C. SALVACION

Division Manager C

Planning & Design Section

MARLI P. ACOSTA - DE FIESTA

Division Manager C

Planning & Design Section

LEONARDO REY D. VASQUEZ

General Manager A

Pricelist as of February 2013 170 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 171: Dumalon W.S. Ground Tank_Final

CONST. OF TWO UNITS - THREE HUNDRED (300.00) CUBIC RESERVOIR TANK AT SITIO BANDERA, BRGY. DULIAN & AT BRY. BALUNO

Republic of the Philippines

ZAMBOANGA CITY WATER DISTRICT

Pilar Street, Zamboanga City

Pricelist as of February 2013 171 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 172: Dumalon W.S. Ground Tank_Final

12,000.00

Pricelist as of February 2013 172 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 173: Dumalon W.S. Ground Tank_Final

22,400.00

9,000.00

43,400.00

30,000.00

30,000.00

33,999.00

2,732.00

36,731.00

251,520.00

251,520.00

50,000.00

38,040.00

288,000.00

376,040.00

7,320.00

45,200.00

52,520.00

Pricelist as of February 2013 173 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 174: Dumalon W.S. Ground Tank_Final

311,430.00

120,000.00

431,430.00

16,260.00

13,000.00

20,950.00

1,323.00

12,550.00

21,000.00

1,110.00

7,890.00

6,760.00

68,280.00

84,860.00

Pricelist as of February 2013 174 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 175: Dumalon W.S. Ground Tank_Final

65,300.00

6,900.00

Pricelist as of February 2013 175 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 176: Dumalon W.S. Ground Tank_Final

318,060.00

7,685.00

249,728.00

169,600.00

1,071,256.00

42,025.00

29,410.00

1,035.00

19,415.00

65,235.00

61,400.00

1,365.00

77,952.00

125,435.00

59,325.00

25,280.00

Pricelist as of February 2013 176 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 177: Dumalon W.S. Ground Tank_Final

16,186.00

7,506.00

Pricelist as of February 2013 177 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 178: Dumalon W.S. Ground Tank_Final

627,060.00

14,305.00

103,816.00

22,800.00

1,299,550.00

34,300.00

30,052.00

64,352.00

133,110.00

69,580.00

4,355.00

42,660.00

78,720.00

328,425.00

59,000.00

Pricelist as of February 2013 178 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 179: Dumalon W.S. Ground Tank_Final

6,000.00

65,000.00

711,500.00

74,440.00

26,728.00

-

-

-

-

Pricelist as of February 2013 179 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 180: Dumalon W.S. Ground Tank_Final

-

37,590.00

9,360.00

7,800.00

867,418.00

586,807.00

71,250.00

Pricelist as of February 2013 180 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 181: Dumalon W.S. Ground Tank_Final

16,242.00

674,299.00

48,975.00

Pricelist as of February 2013 181 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 182: Dumalon W.S. Ground Tank_Final

20,490.00

69,465.00

37,700.00

37,700.00

94,610.00

18,922.00

113,532.00

1,600.00

4,902.00

6,502.00

8,655.00

10,145.00

9,500.00

13,300.00

Pricelist as of February 2013 182 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 183: Dumalon W.S. Ground Tank_Final

8,665.00

5,930.00

23,412.00

21,000.00

100,607.00

7,110.00

12,105.00

20,045.00

43,390.00

9,725.00

16,725.00

30,000.00

9,000.00

148,100.00

60,163.00

19,124.00

79,287.00

Pricelist as of February 2013 183 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 184: Dumalon W.S. Ground Tank_Final

Pricelist as of February 2013 184 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 185: Dumalon W.S. Ground Tank_Final

39,565.00

15,000.00

54,565.00

101,470.00

32,680.00

50,720.00

184,870.00

43,625.00

15,216.00

58,841.00

21,110.00

2,732.00

23,842.00

Pricelist as of February 2013 185 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 186: Dumalon W.S. Ground Tank_Final

1,268.00

1,268.00

2,220.00

2,965.00

1,975.00

1,730.00

4,440.00

1,235.00

4,440.00

8,635.00

1,480.00

11,608.00

8,000.00

48,728.00

2,115.00

6,125.00

Pricelist as of February 2013 186 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 187: Dumalon W.S. Ground Tank_Final

2,020.00

4,020.00

Pricelist as of February 2013 187 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 188: Dumalon W.S. Ground Tank_Final

3,870.00

1,970.00

17,365.00

18,590.00

3,260.00

14,000.00

4,200.00

77,535.00

49,570.00

19,124.00

22,595.00

12,294.00

3,000.00

106,583.00

13,800.00

Pricelist as of February 2013 188 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 189: Dumalon W.S. Ground Tank_Final

Pricelist as of February 2013 189 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 190: Dumalon W.S. Ground Tank_Final

10,010.00

3,615.00

6,147.00

33,572.00

41,590.00

8,196.00

49,786.00

2,880.00

7,650.00

2,240.00

7,815.00

Pricelist as of February 2013 190 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 191: Dumalon W.S. Ground Tank_Final

4,000.00

24,585.00

Pricelist as of February 2013 191 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 192: Dumalon W.S. Ground Tank_Final

3,700.00

3,700.00

2,331.00

7,010.00

3,084.00

8,220.00

20,645.00

11,000.00

11,000.00

24,117.00

6,830.00

30,947.00

3,455.00

Pricelist as of February 2013 192 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 193: Dumalon W.S. Ground Tank_Final

3,390.00

2,000.00

11,150.00

1,366.00

10,220.00

1,366.00

15,700.00

48,647.00

634.00

634.00

1,975.00

1,110.00

1,110.00

1,110.00

740.00

1,110.00

456,996.00Php

Pricelist as of February 2013 193 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 194: Dumalon W.S. Ground Tank_Final

1,110.00

2,220.00

Pricelist as of February 2013 194 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 195: Dumalon W.S. Ground Tank_Final

1,975.00

4,902.00

6,900.00

24,262.00

2,567.50

9,847.50

1,277.50

2,352.50

1,023.00

900.00

6,150.00

7,225.00

5,790.00

8,000.00

45,133.00

Pricelist as of February 2013 195 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 196: Dumalon W.S. Ground Tank_Final

12,498.00

2,049.00

3,500.00

2,732.00

20,779.00

4,905.00

1,366.00

1,200.00

7,471.00

17,670.00

2,732.00

20,402.00

7,750.00

1,366.00

8,115.00

3,415.00

20,646.00

Pricelist as of February 2013 196 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 197: Dumalon W.S. Ground Tank_Final

7,804.00

2,133.00

7,980.00

17,917.00

1,600.00

1,600.00

1,309.00

683.00

1,992.00

2,900.00

2,900.00

8,650.00

3,415.00

12,065.00

175,801.00

Pricelist as of February 2013 197 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 198: Dumalon W.S. Ground Tank_Final

10,495.00

7,795.00

2,890.00

1,275.00

7,000.00

29,455.00

5,615.00

2,049.00

7,664.00

3,150.00

12,225.00

4,000.00

19,375.00

Pricelist as of February 2013 198 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 199: Dumalon W.S. Ground Tank_Final

4,520.00

1,902.00

6,422.00

6,210.00

6,210.00

4,902.00

4,902.00

16,450.00

5,464.00

21,914.00

12,440.00

4,781.00

17,221.00

38,389.00

20,314.00

58,703.00

Pricelist as of February 2013 199 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 200: Dumalon W.S. Ground Tank_Final

14,100.00

86,355.00

26,144.00

11,500.00

138,099.00

18,400.00

6,830.00

36,000.00

61,230.00

2,000.00

8,852.00

683.00

9,535.00

Pricelist as of February 2013 200 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 201: Dumalon W.S. Ground Tank_Final

28,280.00

4,781.00

33,061.00

11,344.00

4,781.00

16,125.00

24,994.00

4,781.00

29,775.00

Pricelist as of February 2013 201 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 202: Dumalon W.S. Ground Tank_Final

50,000.00

38,040.00

288,000.00

376,040.00

7,320.00

45,200.00

52,520.00

311,430.00

120,000.00

431,430.00

16,260.00

13,000.00

20,950.00

1,323.00

12,550.00

90,496.00

Pricelist as of February 2013 202 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 203: Dumalon W.S. Ground Tank_Final

21,000.00

1,110.00

7,890.00

6,760.00

68,280.00

84,860.00

65,300.00

6,900.00

318,060.00

7,685.00

249,728.00

169,600.00

1,071,256.00

42,025.00

29,410.00

Pricelist as of February 2013 203 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 204: Dumalon W.S. Ground Tank_Final

1,035.00

19,415.00

65,235.00

61,400.00

1,365.00

77,952.00

125,435.00

59,325.00

25,280.00

16,186.00

7,506.00

627,060.00

14,305.00

103,816.00

22,800.00

1,299,550.00

Pricelist as of February 2013 204 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 205: Dumalon W.S. Ground Tank_Final

34,300.00

30,052.00

64,352.00

133,110.00

69,580.00

4,355.00

42,660.00

78,720.00

328,425.00

59,000.00

6,000.00

65,000.00

710,242.00

Pricelist as of February 2013 205 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 206: Dumalon W.S. Ground Tank_Final

74,440.00

26,728.00

193,784.00

178,862.00

210,662.00

Pricelist as of February 2013 206 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 207: Dumalon W.S. Ground Tank_Final

36,990.00

9,360.00

7,800.00

1,448,868.00

586,807.00

71,250.00

16,242.00

674,299.00

Pricelist as of February 2013 207 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 208: Dumalon W.S. Ground Tank_Final

48,975.00

20,490.00

69,465.00

37,700.00

37,700.00

94,610.00

18,922.00

113,532.00

1,600.00

4,902.00

6,502.00

8,655.00

Pricelist as of February 2013 208 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 209: Dumalon W.S. Ground Tank_Final

10,145.00

9,500.00

13,300.00

56,748.60

110,372.45

23,412.00

21,000.00

253,133.05

7,110.00

12,105.00

20,045.00

43,390.00

30,000.00

9,000.00

Pricelist as of February 2013 209 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 210: Dumalon W.S. Ground Tank_Final

121,650.00

60,163.00

19,124.00

79,287.00

39,565.00

15,000.00

54,565.00

101,470.00

32,680.00

50,720.00

184,870.00

43,625.00

15,216.00

58,841.00

Pricelist as of February 2013 210 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 211: Dumalon W.S. Ground Tank_Final

21,110.00

2,732.00

23,842.00

1,268.00

1,268.00

2,220.00

2,965.00

1,975.00

1,730.00

4,440.00

1,235.00

4,440.00

8,635.00

1,480.00

11,608.00

8,000.00

48,728.00

Pricelist as of February 2013 211 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 212: Dumalon W.S. Ground Tank_Final

2,115.00

6,125.00

2,020.00

4,020.00

3,870.00

1,970.00

17,365.00

18,590.00

3,260.00

14,000.00

4,200.00

77,535.00

49,570.00

19,124.00

Pricelist as of February 2013 212 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 213: Dumalon W.S. Ground Tank_Final

22,595.00

12,294.00

3,000.00

106,583.00

13,800.00

10,010.00

3,615.00

6,147.00

33,572.00

41,590.00

8,196.00

49,786.00

2,880.00

Pricelist as of February 2013 213 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 214: Dumalon W.S. Ground Tank_Final

7,650.00

2,240.00

7,815.00

4,000.00

24,585.00

3,700.00

3,700.00

2,331.00

7,010.00

3,084.00

8,220.00

20,645.00

11,000.00

11,000.00

Pricelist as of February 2013 214 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 215: Dumalon W.S. Ground Tank_Final

24,117.00

6,830.00

30,947.00

3,455.00

3,390.00

2,000.00

11,150.00

1,366.00

10,220.00

1,366.00

15,700.00

48,647.00

634.00

634.00

456,996.00Php

Pricelist as of February 2013 215 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 216: Dumalon W.S. Ground Tank_Final

1,975.00

1,110.00

1,110.00

1,110.00

740.00

1,110.00

1,110.00

2,220.00

1,975.00

4,902.00

6,900.00

24,262.00

2,567.50

9,847.50

1,277.50

2,352.50

Pricelist as of February 2013 216 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 217: Dumalon W.S. Ground Tank_Final

1,023.00

900.00

6,150.00

7,225.00

5,790.00

8,000.00

45,133.00

12,498.00

2,049.00

3,500.00

2,732.00

20,779.00

4,905.00

1,366.00

1,200.00

7,471.00

Pricelist as of February 2013 217 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 218: Dumalon W.S. Ground Tank_Final

17,670.00

2,732.00

20,402.00

7,750.00

1,366.00

8,115.00

3,415.00

20,646.00

7,804.00

2,133.00

7,980.00

17,917.00

1,600.00

1,600.00

1,309.00

683.00

1,992.00

Pricelist as of February 2013 218 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 219: Dumalon W.S. Ground Tank_Final

2,900.00

2,900.00

8,650.00

3,415.00

12,065.00

10,495.00

7,795.00

2,890.00

1,275.00

7,000.00

29,455.00

5,615.00

2,049.00

175,801.00

Pricelist as of February 2013 219 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 220: Dumalon W.S. Ground Tank_Final

7,664.00

3,150.00

12,225.00

4,000.00

19,375.00

4,520.00

1,902.00

6,422.00

6,210.00

6,210.00

4,902.00

4,902.00

16,450.00

5,464.00

21,914.00

12,440.00

4,781.00

17,221.00

Pricelist as of February 2013 220 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 221: Dumalon W.S. Ground Tank_Final

38,389.00

20,314.00

58,703.00

14,100.00

86,355.00

26,144.00

11,500.00

138,099.00

16,340.00

285,592.00

100,000.00

57,500.00

459,432.00

18,400.00

6,830.00

36,000.00

61,230.00

Pricelist as of February 2013 221 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 222: Dumalon W.S. Ground Tank_Final

2,000.00

8,852.00

683.00

9,535.00

28,280.00

4,781.00

33,061.00

Pricelist as of February 2013 222 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 223: Dumalon W.S. Ground Tank_Final

11,344.00

4,781.00

16,125.00

24,994.00

4,781.00

29,775.00

90,496.00

Pricelist as of February 2013 223 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 224: Dumalon W.S. Ground Tank_Final

361,651.00

376,040.00

5,074,947.00

656,614.00

456,996.00

175,801.00

S U M M A R Y

Pricelist as of February 2013 224 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 225: Dumalon W.S. Ground Tank_Final

69,126.00

102,740.00

138,099.00

61,230.00

90,496.00

376,040.00

5,656,397.00

782,690.05

456,996.00

175,801.00

69,126.00

102,740.00

138,099.00

459,432.00

61,230.00

90,496.00

15,932,787.05

Pricelist as of February 2013 225 of 226 Dumalon W.S. Reservoir Tank_Fin

Page 226: Dumalon W.S. Ground Tank_Final

1,593,278.71

1,593,278.71 2,294,321.34

21,413,665.80Php

MARLI P. ACOSTA - DE FIESTA

Division Manager C

Planning & Design Section

Pricelist as of February 2013 226 of 226 Dumalon W.S. Reservoir Tank_Fin