E-science grid facility for Europe and Latin America
www.eu-eela.eu
SA1 - Status ReportGrid Infrastructure Activity
Diego Carvalho (SA1 Activity Manager)CEFET-RJ (Brazil)
First Project ReviewBrussels, 28.04.2009
www.eu-eela.eu Brussels, First Project Review, 28.04.09
E-science grid facility for Europe and Latin America
2
Outline
• Activity Objectives and Results
• Activity in numbers
• Future Plans and Conclusions
E-science grid facility for Europe and Latin America
www.eu-eela.eu Brussels, First Project Review, 28.04.09 3
Activity Objectives and Results
www.eu-eela.eu Brussels, First Project Review, 28.04.09
E-science grid facility for Europe and Latin America
4
Objectives and Results
• “Expanding the current e-Infrastructure to consist of 41 Resource Centres (13 in Europe and 28 in Latin America) mobilising about 3000 computing cores and more than 700 Terabytes of storage space, at start of the project and to further grow by 20 % in computing and 15 % in storage over the duration of the project.”
• “Providing the full set of Infrastructure and Application-oriented Grid Services needed by all types of applications in their scientific environment.”
The current infrastructure has 22 The current infrastructure has 22 Resource Centres (11 in Europe and 11 in Resource Centres (11 in Europe and 11 in Latin America) mobilising about 5800 Latin America) mobilising about 5800 computing cores and more than 192 computing cores and more than 192 Terabytes of storage.Terabytes of storage.
The current infrastructure has 22 The current infrastructure has 22 Resource Centres (11 in Europe and 11 in Resource Centres (11 in Europe and 11 in Latin America) mobilising about 5800 Latin America) mobilising about 5800 computing cores and more than 192 computing cores and more than 192 Terabytes of storage.Terabytes of storage.
Two Core Service Centres deployed (EU and LA), Two Core Service Centres deployed (EU and LA), providing a full set of Grid Services (information providing a full set of Grid Services (information systems, data and metadata catalogues, etc.) and systems, data and metadata catalogues, etc.) and the services developed by JRA1.the services developed by JRA1.
Two Core Service Centres deployed (EU and LA), Two Core Service Centres deployed (EU and LA), providing a full set of Grid Services (information providing a full set of Grid Services (information systems, data and metadata catalogues, etc.) and systems, data and metadata catalogues, etc.) and the services developed by JRA1.the services developed by JRA1.
www.eu-eela.eu Brussels, First Project Review, 28.04.09
E-science grid facility for Europe and Latin America
5
Objectives and Results
• “Building the support of the e-Infrastructure to provide high reliability services to partnerships spanning the Atlantic Ocean by:”
• “Providing a complete set of Global Services from central EELA-2 Operation and Networking Support Centres (EOC/ENSC).”
• “Targeting the creation of Regional Operation Centres (ROC) in Latin America, covering one or more countries.”
• “Pursuing the aggressive EELA Training and Dissemination programme.”
• “Creating a comprehensive knowledge repository on Grid operation federated with the EGEE ones.”
A full set of ancillary tools was deployed on the EOC, which A full set of ancillary tools was deployed on the EOC, which acts as a central co-ordination point for the infrastructure.acts as a central co-ordination point for the infrastructure.
http://eoc.eu-eela.euhttp://eoc.eu-eela.eu
A full set of ancillary tools was deployed on the EOC, which A full set of ancillary tools was deployed on the EOC, which acts as a central co-ordination point for the infrastructure.acts as a central co-ordination point for the infrastructure.
http://eoc.eu-eela.euhttp://eoc.eu-eela.eu
Four OOD teams were engaged in Operations; they Four OOD teams were engaged in Operations; they prefigure the support teams of future Latin American ROCs.prefigure the support teams of future Latin American ROCs.Four OOD teams were engaged in Operations; they Four OOD teams were engaged in Operations; they prefigure the support teams of future Latin American ROCs.prefigure the support teams of future Latin American ROCs.
SA1 contributed trainers and infrastructure support to NA2 SA1 contributed trainers and infrastructure support to NA2 and NA3.and NA3.SA1 contributed trainers and infrastructure support to NA2 SA1 contributed trainers and infrastructure support to NA2 and NA3.and NA3.
As first step, SA1 and EGEE-SA1 agreed on common As first step, SA1 and EGEE-SA1 agreed on common protocols and procedures.protocols and procedures.As first step, SA1 and EGEE-SA1 agreed on common As first step, SA1 and EGEE-SA1 agreed on common protocols and procedures.protocols and procedures.
OOD Teams
www.eu-eela.eu Brussels, First Project Review, 28.04.09
E-science grid facility for Europe and Latin America
6
Objectives and Results
• “Contributing to the implementation, operation and support of new Certification Authorities required in Latin America and to their coordination within the framework of TAGPMA.”
The mobility of all LA CA managers is supported by the The mobility of all LA CA managers is supported by the project.project.The Peruvian CA has been submitted for accreditation.The Peruvian CA has been submitted for accreditation.The Leader of TSA1.3 is chairing TAGPMA.The Leader of TSA1.3 is chairing TAGPMA.
The mobility of all LA CA managers is supported by the The mobility of all LA CA managers is supported by the project.project.The Peruvian CA has been submitted for accreditation.The Peruvian CA has been submitted for accreditation.The Leader of TSA1.3 is chairing TAGPMA.The Leader of TSA1.3 is chairing TAGPMA.
E-science grid facility for Europe and Latin America
www.eu-eela.eu Brussels, First Project Review, 28.04.09 7
SA1 in numbers
E-science grid facility for Europe and Latin America
www.eu-eela.eu Brussels, First Project Review, 28.04.09 8
LA Public Key Infrastructure Status
Certification Authority
Registration Authority
CA Applicant
Catch All Certification Authority
Every EELA-2 country has access to the LA
Every EELA-2 country has access to the LA
PKI PKI
Every EELA-2 country has access to the LA
Every EELA-2 country has access to the LA
PKI PKI
E-science grid facility for Europe and Latin America
www.eu-eela.eu Brussels, First Project Review, 28.04.09 9
Resource Centre Map
Legacy Sitesprod.vo SitesOurGrid Sites
E-science grid facility for Europe and Latin America
www.eu-eela.eu Brussels, First Project Review, 28.04.09 10
Computing Resources
0
5
10
15
20
25
M01 M02 M03 M04 M05 M06 M07 M08 M09 M10 M11 M12
Re
sou
rce
Ce
ntr
es
0
1000
2000
3000
4000
5000
6000
7000
Co
res
Legacy Cores prod.vo Cores Legacy RCs prod.vo RCs
22 sites on the Production Infrastructure
22 sites on the Production Infrastructure
for a total of 5800 cores
for a total of 5800 cores
22 sites on the Production Infrastructure
22 sites on the Production Infrastructure
for a total of 5800 cores
for a total of 5800 cores
crash programme
E-science grid facility for Europe and Latin America
www.eu-eela.eu Brussels, First Project Review, 28.04.09 11
Infrastructure Usage - all VOs
About 1 million jobs executed
About 1 million jobs executed
About 1 million jobs executed
About 1 million jobs executed
ResourceCentres
E-science grid facility for Europe and Latin America
www.eu-eela.eu Brussels, First Project Review, 28.04.09 12
Infrastructure Usage - Only EELA-2 VO
More than 50k jobs executed
More than 50k jobs executed
More than 50k jobs executed
More than 50k jobs executed
ResourceCentres
E-science grid facility for Europe and Latin America
www.eu-eela.eu Brussels, First Project Review, 28.04.09 13
Proxy Creations
53 Registered “accounts”
One can clearly see an increase on the
One can clearly see an increase on the
infrastructure use
infrastructure use
One can clearly see an increase on the
One can clearly see an increase on the
infrastructure use
infrastructure use
E-science grid facility for Europe and Latin America
www.eu-eela.eu Brussels, First Project Review, 28.04.09 14
Metrics on M12 - DoW Table
Metric Pledged Current
Percentage of Vacant positions < 10% 8%
Percentage of deployed tools specified in AEP > 80% 98%
Percentage of consolidated documents n.a (M14) 80%
Number of meetings per month >1 >2
Number of middleware releases >1 2
Number of CA candidates ≥1 2
Number of new accredited CAs n.a (M22) 0
Percentage of committed CPU slots integrated > 50% 190%
Percentage of committed TB of storage integ. > 40% > 27%
E-science grid facility for Europe and Latin America
www.eu-eela.eu Brussels, First Project Review, 28.04.09 15
Future plans and conclusion
www.eu-eela.eu Brussels, First Project Review, 28.04.09
E-science grid facility for Europe and Latin America
16
Future Plans
• From the DoW point of view: 2nd year is devoted to operations• Keep
• the momentum - integration of new sites (short-term)• the interoperation with EGEE (long-term)
• Increase• the OOD Teams know-how (short-term)• the usage of the support system (short-term)• the deployment of OurGrid on small/shared RCs (mid-term)
• Finish• the accounting system (short-term)• the Service Level Agreement (medium-term)
• Understand• technical issues like MPI heterogeneity (short-term)
www.eu-eela.eu Brussels, First Project Review, 28.04.09
E-science grid facility for Europe and Latin America
17
Conclusions
• The infrastructure is composed by 22 Resource Centres and provides almost twice the amount of pledged job slots.
• About 1,000,000 user jobs were already executed on the infrastructure.
• Four OOD teams were trained and engaged into operations. ROC seeds.
• The use of the infrastructure increases every day.
• 2nd year is devoted to operations, fine-tuning.