Edna Maguire School Modernization - Phase 1 Summer 2012
Interim school Administrative office in leased portable
Before AfterOld Administrative office
New parking lot, Interim Administrative Office in leased portable, construction fencing around active construction site of new campus
Before AfterOld Administrative office, driveway, and leased pre-school
Interim school with leased portables, construction fencing around active construction site of new campus, warehouse demolished
Before AfterOld parking lot, portable classroom, and warehouse
Construction continues on new campus
Before AfterOld Campus
Removed warehouse to build interim school
Before AfterOld parking lot and warehouse
New electrical transformer, gas service, driveway and interim Administrative offices, teacher’s workroom and restrooms
Before AfterOld electrical transformer, portable classrooms, driveway, and leased pre-school
Leased classroom, new walkway, temporary railing, and new entry driveway
Before AfterLeased classroom, and pedestrian entrance
Maintenance shop, interim school, and new school under construction in the background
Before AfterMaintenance Shop, parking lot, and old school in the background
Tenant rental space, and warehouse removed
Before AfterTenant rental space, warehouse
Interim Classrooms with Emergency Vehicle Access
Before AfterAlto Field