Upload
graham-wood
View
216
Download
1
Embed Size (px)
Citation preview
Environmental Impact Assessment Review 26 (2006) 221–241
www.elsevier.com/locate/eiar
EIA scoping in England and Wales:
Practitioner approaches, perspectives and constraints
Graham WoodT, John Glasson, Julia Becker
Impacts Assessment Unit, Department of Planning, School of the Built Environment,
Oxford Brookes University, Gipsy Lane, Oxford OX3 0BP, UK
Received 1 September 2004; received in revised form 1 January 2005; accepted 1 February 2005
Available online 22 April 2005
Abstract
Scoping plays a critical role in shaping the nature and extent of the environmental information
subsequently contained in an Environmental Impact Statement (EIS), yet it has been identified as an
area of weakness in practice (Sadler, B., 1996) and remains a poorly understood and under-
researched component of EIA. This paper provides a detailed empirical investigation and
assessment of recent scoping activity in England and Wales, in the context of evolving European
Union (EU) regulations. Conceptual and contextual issues associated with scoping are outlined
prior to the presentation of key findings, including: approaches to scoping; the assessment of
significance; characteristics and influence of consultation; and perceived constraints to scoping. The
paper concludes with an overview of findings, possible explanatory factors, and recommendations for
future practice.
D 2005 Elsevier Inc. All rights reserved.
Keywords: Scoping; Impact significance; Stakeholder involvement
1. Introduction
The scope of an Environmental Impact Assessment (EIA) is the impacts and issues it
addresses. The scoping process involves deciding upon the significant issues that should
0195-9255/$ -
doi:10.1016/j.
T Correspon
E-mail add
see front matter D 2005 Elsevier Inc. All rights reserved.
eiar.2005.02.001
ding author. Tel.: +44 1865 483942; fax: +44 1865 483559.
ress: [email protected] (G. Wood).
G. Wood et al. / Environmental Impact Assessment Review 26 (2006) 221–241222
be covered in the assessment, and consequently it plays a critical role in shaping the nature
and extent of the environmental information subsequently contained in an Environmental
Impact Statement (EIS). For Weston (2000a), scoping can be regarded as the most
important stage in the EIA, whilst the UK Department of the Environment indicates that
bscoping is the key to a good quality environmental statementQ (DoE, 1995, p.13).Failure to adequately scope an EIA can lead to a situation where excessive resources are
expended on minor impacts, leading to voluminous EISs that cover an unnecessarily wide
range of impacts in far too much depth. EIA is not intended to produce an exhaustive,
encyclopaedic assessment of each and every potential impact, and the problem of bdeletinginconsequential or peripheral mattersQ has been identified as an issue internationally
(Sadler, 1996, p.113). In contrast, if too little attention is given to a potentially significant
impact then the perceived objectivity and legitimacy of the assessment may be reduced
and delays can ensue while the issue is subsequently addressed.
The interpretation and evaluation of the concept of dsignificant environmental effectsTexerts a major influence upon decision-making during scoping. In contrast to the idealised
notion of EIA as a rational, objective, systematic and value-free process, in practice the
interpretation of the significance of environmental effects is a highly contentious process
that occupies a bfluid boundary between science and politicsQ (Pritchard, 1993, p.11). Thepolitical dimension of decision-making during scoping introduces elements of dpowerT,dinfluenceT and dinterestsT into the equation. Scoping is thus to be considered an activity in
which there are underlying conflicting interests at stake, as well as varying perceptions of
the significance of environmental effects amongst a range of stakeholders potentially
involved in the process. Scoping therefore cannot be conceived as a rational and objective
dscientificT activity that can be replicated or verified, since the outcome of a scoping
exercise will vary according to how it is undertaken and by whom.
Ultimately the significance of environmental effects represents a subjective anthro-
pocentric judgement about the relative importance of a potential environmental impact,
contingent upon socially created environmental values that in turn will depend upon the
specific environmental and community context. However, the extent to which these values
are countenanced will depend upon the degree to which scoping is carried out as an dopenTprocess involving dialogue and exchange of ideas between stakeholders, or whether it is a
dclosedT exercise whereby the development proponents dominate the framing of the
subsequent assessment.
Sadler (1996) identified scoping as an area of weakness in EIA practice, and despite
widespread recognition of its importance, it remains a poorly understood and under-
researched aspect of EIA (Mulvihill, 2003). This paper provides a detailed empirical
investigation and assessment of recent scoping activity in England and Wales, in the
context of evolving European Union (EU) regulations. The principal aim of the paper is to
identify and explore the nature and characteristics of scoping practice carried out under the
Town and Country Planning (Environmental Impact Assessment) (England and Wales)
Regulations 1999. In particular, the paper will focus on how EIA practitioners (namely
Local Planning Authorities (LPAs), environmental consultants, and statutory consultees)
identify impacts and determine the significance of those impacts.
The paper starts by expanding upon some of the conceptual and contextual issues
associated with scoping, including the changing regulatory framework in the UK and the
G. Wood et al. / Environmental Impact Assessment Review 26 (2006) 221–241 223
EU. The research methodology is outlined and the paper then focuses on an analysis of
some key findings, including: practitioner engagement in scoping activity and the
ranking of important issues; approaches to impact identification; project-specific scoping
and methods used for the determination of significant impacts; characteristics of
consultation; and perceptions on the constraints to scoping. Some of the differences and
similarities between key practitioners are highlighted and current scoping practice is also
compared with the requirements of the 1999 EIA Regulations. The paper concludes with
an overview of findings, possible explanatory factors, and recommendations for future
practice.
The paper draws on the findings of a broader programme of research into significant
environmental effects in EIA decision-making, funded principally by the UK Economic
and Social Research Council (ESRC), with additional support from the EIA Unit at the
Office of the Deputy Prime Minister (ODPM).
2. Scoping in context
2.1. Conceptual foundations
Researchers on scoping (Mulvihill, 2003; Wood, 2003; Weston, 2000a; Jones, 1999;
DoE, 1996; Sadler, 1996; Kennedy and Ross, 1992 and others) have identified an array
of features that could be seen to constitute the ideal nature and principles of scoping in
EIA:
! early application, but part of a cyclical process that continues throughout the EIA;
! engagement of key actors, and openness to public input;
! adequate treatment of alternative options for project siting and design;
! establishment of clear boundaries (spatial, temporal, biophysical, socio-economic etc.);
! focus upon key issues and on valued environmental components that are relevant to
decision-making; and
! identification of impacts to be monitored throughout the life of the project.
An efficient and effective approach to scoping, incorporating the principles identified
above, is seen to bring several benefits. It will concentrate the assessment on the
significant impacts thus avoiding wasted time and resources, and by engaging with a wide
range of stakeholders it will help the EIA to capture knowledge and values in order to
generate better environmental information for decision-making. The US Council on
Environmental Quality (CEQ, 1997) stresses the advantages of building cooperative
working relationships with decision-making and environmental authorities, with interest
groups such as local voluntary conservation groups, and with the local community
(communities). An open and cooperative approach can exert a strong influence on the
shape of the impact assessment, increasing the likelihood of realising a process that
satisfies stakeholders. This may be particularly appropriate for controversial projects with
a diverse range of stakeholders (Mulvihill and Jacobs, 1998) and where the legitimacy of
the EIA may be of particular concern.
G. Wood et al. / Environmental Impact Assessment Review 26 (2006) 221–241224
However, as well as potential benefits, the ideal process brings problems and
challenges. A rigorous and open dialogue runs the risk of becoming lengthy, expensive
and getting dbogged downT in detail. Scoping also brings to the fore the values and
perspectives of stakeholders whose objectives and expectations regarding the EIA process
may conflict. For example, Jones (1999) notes the potential conflict between the client
(who wishes to minimise time and costs), consultant (who wishes to maximise work) and
the competent authority, consultees and the public (who wish to gain as much information
as possible).
The control of information for decision-making may influence the nature and
outcome of the process, and some stakeholders are likely to have more power and
influence in the process than others. Thus, the institutional context of EIA defines the
formal and informal rules or procedures within which scoping decision-making occurs
and this serves to determine the rights and responsibilities of stakeholders, which in turn
shapes the degree of influence that different parties can exert. Environmental
professionals may have the benefit of technical knowledge and understanding of the
relevant formal, or informal, processes, although as Sadler notes (Sadler, 1996) scoping
is often an undisciplined activity. Underpinning such problems is of course the highly
subjective nature of judgements regarding the significance of impacts in EIA (Weston,
2000b).
As such, the scoping process highlights a number of crucial issues. It raises for example
issues about the degree of openness or closure of the process; about its formal or informal
nature; about power, control and access to information; about different values and
perspectives of the participants; and about the resources implicit and available. One
approach is to see scoping in any one country/region as a point on a continuum between a
technical / rational, professional-dominated model and, at the other extreme, a participative
social model involving the collaboration and cooperation of a diverse range of
stakeholders.
In the following section the institutional context and regulatory frameworks that seek to
manage the scoping process are considered. The focus is on the Town and Country
Planning System in England and Wales, within an EU context, with reference to other
countries as appropriate.
2.2. Regulatory frameworks and institutional context
EIA regulations in the UK were formally introduced as a consequence of Directive 85/
337/EEC as amended by Directive 97/11/EC on the bassessment of the effects of certain
public and private projects on the environmentQ (EC, 1997). Article 5 (para 2) of the
Directive (as amended) provides for a formalised scoping procedure. The original EIA
Directive did not have such a requirement although most Member States applied forms of
scoping in their national systems. An important aim of introducing a scoping requirement
into the Directive was to initiate early contact between the developer and the competent
authority and to promote a certain amount of cooperation with regard to the information to
be provided on key issues.
The Directive provides for two cases. The first requires the competent authorities to
provide, if the developer so requests, an opinion on a list of information to be submitted in
G. Wood et al. / Environmental Impact Assessment Review 26 (2006) 221–241 225
an EIS. The second allows Member States to make this a mandatory procedure, i.e. the
competent authorities must provide a scoping opinion regardless of whether or not it is
requested by the developer. The Five-Year Report to the European Council and
Parliament on the application and effectiveness of the amended Directive (EC, 2003)
showed that seven of the then fifteen Member States had a mandatory scoping
procedure in place. In some countries the nature of mandatory scoping varied
according to type of project (e.g. industry, quarrying and certain agricultural projects),
and/or according to region within a country (as in Italy). Within the Member States,
guidance on the nature, content and process of scoping varies in rigour between countries
(Wood, 2003), although the EC has also provided an updated guidance document (EC,
2000).
The Five-Year review revealed mixed opinions between Member States as to whether
the introduction of the revised scoping procedures had brought improvements. For some
there was a perception that it had improved the quality of information provided to the
competent authority; for others there was a perceived potential for increasing the length of
time taken up by the EIA process (EC, 2003). Importantly, the review also showed barecognition in some Member States that public involvement at the scoping stage identifies
the issues that are dsignificantT to the people who will have to live with the project and not
just the dexpertsT who will notQ (EC, 2003, p.4). In Belgium (Brussels and Walloon
regions), Denmark, Finland, Netherlands, Spain and Sweden, consultation with the public
is a legally required part of the process. In comparison, in Austria, Germany, Ireland and
the UK, when forming a scoping opinion it is up to the competent authority to decide
whether or not the public should be consulted on the scope, but the relevant environmental
authorities or agencies are consulted.
This article focuses upon an examination of scoping decision-making for develop-
ment projects in England and Wales that fall under the Town and Country Planning
(Environmental Impact Assessment) Regulations 1999 SI No. 293. These Regulations
serve to implement the amended EIA Directive for development that occurs under the
Town and Country Planning Act 1990, which accounts for approximately 70% of all
EISs submitted in England and Wales. The Regulations came into effect on 14 March
1999 and are supported by government guidance in the form of Circular 02/99 (DETR,
1999). Under the 1999 Regulations, scoping has not been incorporated as a mandatory
activity in the UK, although in compliance with the Directive, developers have been
given the right to formally request a scoping opinion from the relevant Local Planning
Authority (LPA).
In the UK the responsibility for preparation of the EIS rests with the applicant, and
whilst the form of the EIS is not prescribed, the Regulations do introduce legally binding
minimum requirements with respect to the contents, which must now include: a
description of the development; a description of mitigation measures; the data required
to identify and assess the main effects of the project; an outline of the main alternatives
studied and the reasons why they were rejected; and a non-technical summary. Circular 02/
99 (DETR, 1999, p. 24) stresses that the emphasis in an EIS should be b. . .on the dmainT ordsignificantT environmental effects to which the development is likely to give rise. In many
cases, only a few of the effects will be significant and will need to be discussed in the EIS
in any great depthQ. The guidance also encourages a pragmatic approach to the production
G. Wood et al. / Environmental Impact Assessment Review 26 (2006) 221–241226
of EISs, highlighting that bthey should be prepared on a realistic basis and without
unnecessary elaborationQ (DETR, 1999, p. 24).In seeking to understand the process by which significant effects are determined during
scoping, it is important to have an appreciation of the role of the key stakeholders and
hence the way in which power and influence can be exerted within the requirements
(confines) of the Regulations, thereby determining the nature and content of information
put forward in an EIS.
The project proponent is under no formal obligation to consult with either the
competent authority or the public in defining the scope of the EIA. Regardless of
whether such consultation occurs, the requirement that ultimately the applicant supply
environmental information for project authorisation decision-making imparts consid-
erable power to the developer and their appointed consultants. Nonetheless, under the
Regulations a developer does have the right to obtain a formal scoping opinion from the
LPA. The scoping opinion must then be given within a 5-week period and the LPA
bmust consult the consultation bodies and the developer before adopting its scoping
opinionQ (DETR, 1999, p. 25). The LPA is under no obligation to involve the public,
although once it has formulated the scoping opinion it must be placed on the planning
register and kept available to the public for a period of 2 years. Thus, in developing a
scoping opinion the LPA does have the potential opportunity to exert a degree of
influence over the shape of the EIA and the information that must be included in the
EIS. Importantly, the Regulations also give LPAs the right to request further information
from the developer after completion of the EIS (even in situations where it has complied
with the original scoping opinion), and so in this way the competent authority ultimately
retains de facto authority for determining the scope of the EIA. The Regulations make
no provisions for disagreement between LPA and applicant with regards to the scope of
the EIA.
3. Scoping in practice: research approach
In order to investigate the nature of scoping practice under the 1999 EIA Regulations, a
questionnaire survey was distributed to LPAs in England and Wales, to statutory
consultees, and to environmental consultancies. Statutory consultees include for example
the Environment Agency, which has developed its own very useful guidance on scoping in
EIA (Environment Agency, 2002), the Countryside Agency and English Nature (where the
development is in England), the Countryside Council for Wales (where the development is
in Wales), plus a wide array of other bodies dependent on the nature and/or siting of the
development proposal.
The questionnaire included a variety of yes/no, multiple response (including likert
scale-type questions), and free response questions designed to establish:
! basic facts (e.g. involvement in scoping);
! procedures and approaches used for scoping (e.g. approaches to identifying impacts and
determining significant effects; consultation); and
! perceived constraints to scoping.
G. Wood et al. / Environmental Impact Assessment Review 26 (2006) 221–241 227
To encourage questionnaire responses that provide a realistic characterisation of the true
nature of scoping decision-making, respondents were asked to consider the questions in
relation to the most recent project for which they were actively involved in scoping.
A total of 408 LPAs, 510 environmental consultancies with an EIA capacity, and 171
statutory consultee offices were sent questionnaires relevant to their organisation. The
overall response rate for the survey was 27%. The response rate for LPAs was 26%,
environmental consultancies 30%, and 23% for statutory consultees, and served to capture
a cross-section of practitioners in terms of location, size of organisation, and EIA
experience. With respect to the statutory consultees that reported experience of
involvement in scoping, the proportion of responses to the survey according to
organisation was as follows: Environment Agency 39%; English Nature 29%; Countryside
Agency/Countryside Council for Wales 14%; English Heritage and British Waterways 7%;
and the Health and Safety Executive 4%.
The questionnaire responses correspond to a diverse range of projects, both in terms of
the scale and type of development, including scoping activity relating to proposals for the
following general sectors: agriculture, energy, extraction, industrial development, leisure,
transport (including roads), urban development (including retail), waste management, and
flood relief schemes. The data analysis focuses on identifying the general pattern of
responses from the three practitioner groupings, and explores differences and similarities
in their approach in order to provide a detailed dsnapshotT of scoping activity and decision-
making processes in England and Wales.
4. Analysis of research findings
4.1. Practitioner engagement in scoping and the ranking of important issues
Approximately 70% of LPAs and statutory consultees stated that they had been involved
in preparing a scoping opinion since the implementation of the 1999 Regulations, while just
over 60% of consultants had been involved with the production of a scoping report. The
consultancies that indicated no experience in EIA scoping can in almost all cases be
characterised as smaller dnicheT companies, whose involvement in EIA is principally
limited to acting as subcontractors offering specialist expertise, e.g. in noise assessment.
In terms of the time spent on scoping, the consultants averaged approximately 31–40 h,
compared with the much shorter 6–10 h for the LPAs and the statutory consultees. Over
one third of LPAs, and approximately 25% of statutory consultees spent less than 5 h on
the task. The projects that took the longest time included extraction and urban
development (for LPAs); transport and urban development (for consultants); and transport,
urban development and wind farms (for statutory consultees).
Survey respondents were provided with a list of 21 general issues1 relevant to scoping
and were asked to identify the importance they placed upon each of them using a five-
1 Covering spatial and temporal aspects, other impact dimensions (e.g. magnitude, cumulative, reversibility,
etc.), assessment methods, consideration of significance, alternatives uncertainty, risk, mitigation, consultation,
post-development environmental management.
G. Wood et al. / Environmental Impact Assessment Review 26 (2006) 221–241228
point scale from dnot importantT through to dvery importantT. Responses were then collated
and Table 1 provides a summary of (a) the top five issues considered to be most important
and (b) the five issues considered least important for the three respondent groups. In
general there is considerable similarity in the ranking of the most important issues, with all
three practitioner groups showing a strong interest in context-specific issues. Consid-
eration of site characteristics was rated highly by all three groups with 90% of consultants,
83% of LPAs and 93% of statutory consultees rating the issue as dimportantT or dveryimportantT in decision-making. Similarly, all three organisations rated geographical issues
as dvery importantT or dimportantT. These findings are perhaps not surprising given that it isa requirement under the 1999 Regulations to include information about the characteristics
and location of the development in an environmental statement. The majority of
respondents within all three groups also rated impact magnitude highly and placed it in
the top three issues.
Table 1
Relative importance of issues in formulating the scoping opinion/report
Rank LPAs Consultants Statutory Consultees
(a) Top five (most important) issues
1 Preliminary assessment of
characteristics of the site
Preliminary assessment
of characteristics of the site
Geographical issues
(the area of distribution
of impacts)
2 Technical issues
(dmeasurableT impacts,
e.g. noise or groundwater
conditions)
Impact magnitude Preliminary assessment
of characteristics of the site
3 Impact magnitude Consideration of mitigation Impact magnitude
4 Consideration of mitigation Determining the significance
of different impacts
Technical issues
(dmeasurableT impacts,
e.g. noise or groundwater
conditions)
5 Geographical issues
(the area of distribution of
impacts)
Geographical issues
(the area of distribution
of impacts)
Consideration of mitigation
(b) Bottom five (least important) issues
17 Accounting for uncertainty Risk of accidents Qualitative issues (impacts
based on ideas, thoughts,
feelings, etc)
18 Risk of accidents Consulting past case
studies
Consulting past case studies
19 Identification of possible
predictive techniques
Accounting for uncertainty Risk of accidents
20 Consideration of project
alternatives
Provisions for post-
development environmental
management (e.g. EMS)
Reversibility of impacts
21 Consideration of methods that
will be used for specific
impacts in the EIS itself
Identification of possible
predictive techniques
Identification of possible
predictive techniques
G. Wood et al. / Environmental Impact Assessment Review 26 (2006) 221–241 229
In formulating scoping decisions LPAs, consultants and statutory consultees all
expressed a general preference for quantitative analysis over qualitative. Over three-
quarters of respondents from all three organisations rated technical, quantitative impacts as
being dimportantT or dvery importantT issues during scoping. In contrast, less than 45% of
LPAs, statutory consultees and consultants thought that qualitative issues were dimportantTor dvery importantT.
Whilst not appearing in the top five issues, cumulative impacts were identified as
relatively important across all three groups. This is surprising, as recent research has
established that there is a lack of early identification of potential cumulative problems in
EIA, and that scoping exercises often do not specifically address cumulative impacts or
only do so in a limited way (Baxter et al., 2001; Piper, 2001). It is therefore a positive sign
that cumulative effects now appear to be recognised by practitioners, particularly as the
1999 EIA Regulations indicate that they are an issue for consideration.
The survey findings indicate that consultants and statutory consultees are more likely to
recognise the importance of what may be considered more complex scoping issues (e.g.
temporary impacts, uncertainty, impact inter-relationships and EIA methods) than is the
case for LPAs. Similarly the consideration of alternatives is given less attention by LPAs
than might have been anticipated, particularly given that the 1999 Regulations require a
developer to address alternatives in an EIA. In fact, 44% of LPAs regarded the
consideration of alternatives as dof littleT or dno importanceT in formulating the scoping
opinion. Mitigation measures are given serious consideration by all three organisations,
but again a higher proportion of consultants and statutory consultees (50%) consider them
dvery importantT than is the case for LPAs (37%).
It is possible that consultants and statutory consultees show a higher concern for these
more complex issues because of the nature of their involvement in scoping. In drafting a
scoping report, consultants will typically consider the specific details of impacts (including
following any requirements of the 1999 Regulations) and will dmap-outT the structure of
the EIA and the assessment approach in some detail. Statutory consultees are more likely
to be concerned with specific aspects of the environment that are relevant to their
organisation and the work they do (for example, English Nature will be particularly
concerned with the more detailed impacts on ecology). In contrast, it appears that LPAs are
potentially more concerned with the identification of impacts, rather than prescribing
specific fine details of the EIA content or methodology.
Risk of accidents does not appear to be a major issue for any of the three practitioner
groups at the scoping stage with 59% of LPAs, 43% of consultants and 32% of statutory
consultees rating it dof littleT or dno importanceT. However, some caution must be exercised
when looking at these figures, as the type of project will influence the degree of
importance that is placed on risk of accidents. Further research is required before
conclusions can be drawn on the degree of attention that practitioners give to risk of
accidents.
4.2. Approaches to impact identification
The next phase of the research focused on the actual approaches and tools used by
practitioners during scoping. In the first instance, the survey asked participants to specify
G. Wood et al. / Environmental Impact Assessment Review 26 (2006) 221–241230
what methods they used to identify impacts in the last project they were involved in
scoping (Table 2).
Professional judgement is by far the most commonly used approach with over 90% of
respondents from each group specifying that they use this method. There are similar high
proportions for each group with regard to consultation within their own organisation, and
for LPA and consultant consultation with statutory and non-statutory consultees. In stark
contrast to this high uptake of internal and external professional consultation, community
consultation appears to have very limited use as an approach to impact identification in
scoping, particularly in the case of statutory consultees (4%). Only 15% of LPAs and
approximately a third of consultancies report using community consultation at this stage,
thus limiting community involvement in the EIA process at the impact identification stage
of scoping.
Only a quarter of LPAs and statutory consultees were likely to consult other examples
of similar projects, while nearly 60% of consultants acknowledged that this was a method
used. Weston (2000b) recommends reviewing similar existing environmental statements or
cases to assist in scoping and as an aid in determining significant impacts. Similarly, for
Mulvihill and Baker (2001) process development (i.e. continual improvement in EA
practice) is important. They acknowledge, however, that there is relatively little sharing of
lessons from one case to another, that there are few mechanisms available to promote the
exchange of experience, and that the black of lesson transfer amongst EA processes can
erode public and stakeholder trust in institutionsQ (Mulvihill and Baker, 2001, p. 383).
Over 70% of consultancies identified that they used existing plans and policy guidance
as a tool for identifying impacts, in comparison to 43% for statutory consultees and only
18% for LPAs. Overall there appeared to be a very limited uptake of actual formal impact
identification techniques. Checklists are recommended as a tool to assist scoping by a
number of authors (e.g. Glasson et al., 1999; Environment Agency, 2002; Weston 2000b),
Table 2
Methods used by different practitioner groups to identify impactsa
Approach LPA %
(N=78)
Consultant %
(N=98)
Statutory
consultees %
(N=28)
Consultation within own organisation 80 83 86
Consultation between different statutory
and non-statutory consultees
80 91 61
Community consultation 15 34 4
Followed guidance from plans or policies 18 70 43
Legal regulations and thresholds 63 76 39
Consulted other examples of similar projects 26 57 25
Used professional judgement and experience 91 96 93
Used a checklist to identify possible impacts 30 50 32
Used other formal technique (please specify) 1 15 4
Based decision on an appraisal of the likely
controversy of the proposal
19 15 4
Other 5 8 4
a This question was multi-response therefore the % figure for each approach is a proportion of the total number
of respondents from each organisation. Figures are rounded to nearest whole number.
G. Wood et al. / Environmental Impact Assessment Review 26 (2006) 221–241 231
and they were the most popular formal technique used as an aid to impact identification,
with 30% of LPAs, 50% of consultancies, and 32% of statutory consultees.
4.3. Relative concern of specific impacts
For the last project that they were involved in scoping, respondents were asked about
their relative concern with respect to different impact themes. The survey responses relate
to a diverse range of development types and receiving environments that precludes any
detailed disaggregation (e.g. by project sector), and so the responses were collated and
examined across the practitioner groups. Whilst recognising that this approach loses the
context specific detail of scoping considerations, it is felt to be useful in providing a
dsnapshotT of the emphasis attributed to different impacts when current EIA practice in
England and Wales is considered as a whole.
Landscape and visual impacts were found to be by far the most important impact for
LPAs, with 60% identifying these impacts as being of dhigh concernT (Fig. 1). Other
impacts of high concern are: traffic/transport, flora/fauna, noise/vibration, water resources
and air quality. Like LPAs, consultancies also consider landscape and visual impacts to be
most important (57%), followed by traffic and transportation, noise and vibration, flora/
fauna, water resources and other emissions (Fig. 2).
The diverse range of statutory consultee organisations combined with the limited
number of total responses, prevents generalization with respect to the relative concern of
impacts. Nevertheless it is of note that all English Nature respondents identified impacts
upon flora and fauna as being of dhigh concernT (reflecting the ecological remit of the
organisation), whilst waste disposal and impacts upon water resources were identified as
being of dhigh concernT by the great majority of Environment Agency responses.
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Soc
ial I
ssue
s
Cul
ture
/ Her
itage
Eco
nom
ic Is
sues
Flo
ra /
Fau
na Soi
l
Air
Qua
lity
Noi
se &
Vib
ratio
n
Oth
er E
mis
sion
s
Clim
atic
Fac
tors
Was
te D
ispo
sal
Wat
er R
esou
rces
Geo
-tec
hnic
al Is
sues
Land
scap
e / V
isua
l
Tra
ffic
/ Tra
nspo
rt
Ris
k of
Acc
iden
ts
Inte
r-re
latio
nshi
ps
High Moderate Minor No Concern
Fig. 1. LPAs: relative concern of impact.
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%S
ocia
l Iss
ues
Cul
ture
/ Her
itage
Eco
nom
ic Is
sues
Flo
ra /
Fau
na Soi
l
Air
Qua
lity
Noi
se &
Vib
ratio
n
Oth
er E
mis
sion
s
Clim
atic
Fac
tors
Was
te D
ispo
sal
Wat
er R
esou
rces
Geo
-tec
hnic
al Is
sues
Land
scap
e / V
isua
l
Tra
ffic
/ Tra
nspo
rt
Ris
k of
Acc
iden
ts
Inte
r-re
latio
nshi
ps
High Moderate Minor No Concern
Fig. 2. Consultancies: relative concern of impacts.
G. Wood et al. / Environmental Impact Assessment Review 26 (2006) 221–241232
The impact types that in aggregate appear to be of least concern amongst practitioners
were risk of accidents and climatic factors. Risk of accidents was generally considered of
dno concernT or only a dminorT concern for all three groups. The majority of LPAs consider
climatic factors to be of dminorT or dno concernT (82%) while a similar (but slightly less)
percentage of consultants and statutory consultees think the same. This limited concern
may change over the next few years—for risk, partly reflecting its more explicit inclusion
in the amended EIA Directive, and for climate change reflecting the rising profile of the
issue nationally and internationally, and increasing government and non-government
guidance on the implications for development planning.
The figures also show a low level of concern for social issues, especially from the LPAs
and statutory consultees. Chadwick (2002) suggests that the ambiguity as to whether such
issues should be in EIA combined with the difficulty of their quantification may partly
explain their dpoor relationT status. With the exception of landscape and visual impacts, the
impacts of most concern are characterised by a strong quantitative component, and are
supported by standards and guidelines.
Overall, the survey findings suggest that, although scoping often results in a catch-all,
play-safe approach with a wide array of impacts identified (Weston, 2000a), practitioners
are in fact able to discriminate and identify which impacts they consider to be of most
concern.
4.4. Methods employed for the determination of significant impacts
The significance of impacts will differ depending on the context and the individuals
involved in decision-making, and because of this there is no general definition of what
constitutes significance (DETR, 2000). The assessment of significance is both an objective
G. Wood et al. / Environmental Impact Assessment Review 26 (2006) 221–241 233
exercise, with quantifiable tests, but is also a subjective exercise involving value
judgement. The questionnaire asked participants to indicate which particular methods they
used for determining the significance of the impacts identified during scoping the last
project they were involved in. Table 3 shows the findings for the three groups across a
range of methods.
The higher proportion of consultants using quantitative, and/or semi-quantitative
techniques is noticeable. Just over 50% of consultants indicated that they measure data
against pre-determined standards or guidelines when putting together their scoping reports.
The use of a dsliding scaleT to give each impact a rating (e.g. major–minor, high
significance–low significance) is also a popular approach for consultants. In addition,
matrices, overlay maps, computer modelling, attaching numerical scores to dweightT thesignificance of impacts, and field experiments are all methods used more often by
consultants than by the other two practitioner groups. Again this may be indicative of
different scoping styles in that when producing scoping reports (both for the client and for
broader circulation) consultancies undertake preliminary assessment work that feeds into
structuring the subsequent approach and detail of the EIA, in contrast to LPAs and
statutory consultees, where impact identification takes primacy.
While there are many recommended tools for determining significance, past research
has found that even amongst consultants the uptake of such tools is fairly limited. Weston
Table 3
Methods used to determine significant impactsa
Method LPA %
(N=78)
Consultants %
(N=98)
Statutory
consultees %
(N=28)
Did not use any particular method 30 9 29
Created a simple checklist of impacts 36 36 29
Attached numerical scores to dweightT the significance 1 14 0
Examined each issue on case by case basis 33 67 21
Measured data against pre-determined standards or guidelines 14 51 11
Created own standards/guidelines to determine impact significance 12 20 36
Created criteria to define what impacts would be significant 4 18 7
Using a sliding scale to give each impact a rating
(e.g. high significance–low significance)
3 48 7
Used matrices 0 15 4
Used overlay maps 3 16 14
Used computer modelling 1 18 4
Used GIS systems 9 7 36
Consultation 55 55 29
Flow charts, value trees/decision trees 0 3 0
Cost–benefit analysis 0 8 0
Messages from community dstoriesT used as criteria or guidelines 3 6 0
Field experiments 1 15 4
Preliminary impacts prediction and extrapolation 9 20 7
Professional judgement and experience 74 78 79
Other 4 9 7
a This question was multi-response therefore the % figure for each approach is a proportion of the total number
of respondents from each practitioner group.
G. Wood et al. / Environmental Impact Assessment Review 26 (2006) 221–241234
(2000b) found that only 12% of environmental consultants used any form of drationalTtechniques for scoping EIAs. This is mostly supported by the results here, which indicate
that in general only between 15% and 20% of consultants would use drationalT techniquesfor scoping. The only exception is checklists, which are used by over a third of consultants
to assist in the determination of significant impacts, in contrast to a figure of 50% during
impact identification phase.
Geographic Information Systems (GIS) analysis is one approach used to a reasonably
high degree by county LPAs with over 44% indicating that they used this technique, along
with 36% of statutory consultees. In contrast less than 6% of district and unitary authorities
and only 7% of consultants do the same. In the case of consultancies this may reflect the
data acquisition and staffing costs involved in setting up a dedicated project specific GIS
that could become redundant on completion of the EIA. For district and unitary LPAs, it is
possible that corporate GIS with relevant spatial data exists, but there may be a lack of
awareness or resources and expertise may be in short supply.
For all three practitioner groups, consultation appears to have been important in
assisting decisions on impact significance during scoping, and it is considered in more
detail in the following section.
4.5. Characteristics of consultation
In best-practice scoping all stakeholders (including the public) should be identified and
consultation with these groups should take place in order to identify the key issues early in
the process, as well as the opportunities, constraints and information needs for an effective
EIA. The advantages of stakeholder consultation in scoping are neatly summarised in the
good practice guidance from the Environment Agency (2002, p. 16) which states that:
bThe early involvement of stakeholders in the EIA has benefits for the developer in
terms of good public relations and obtaining the information about the local area.
Moreover by addressing concerns at the outset there is less likelihood of the project
being delayed, for example by the decision stage because important information has
been overlooked. By seeking to accommodate the concerns of the stakeholders, the
developer is more likely to gain the confidence of the local people, rather than
risking suspicion and mistrust that may be generated by new developments Q.
During scoping, LPAs and statutory consultees generally consulted between one and
five other parties when constructing a scoping opinion. Consultants tended to consult
slightly more widely, most typically consulting between six and ten parties. Table 4 sets
out responses on the form of consultation used by the three groups during scoping. For
LPAs, official written communications are the most popular form of consultation, followed
by informal conversations both internally and externally. Consultants use a mix of
approaches including official letters, informal conversations, formal requests for scoping
opinions from the LPA, and public meetings. Statutory consultees appear to rely most on
informal conversations with other organisations. A small proportion of LPAs indicated
that, contrary to the requirements of the 1999 Regulations, they did not consult at all with
the Environment Agency and other statutory consultees.
Table 4
Nature and mode of consultation during scopinga
No
answer
Did not
consult with
Informal
conversation
Advertisement Public
meeting
Official
letters/emails
Scoping opinion
requested
Workshop Public
display
Other
(please specify)
Mix of
approaches
LPAs % (N=78)
LPA/County Council 33 13 13 0 3 24 8 1 0 0 5
Developer 33 13 14 1 3 15 10 1 0 1 8
Environmental Consultancy 55 33 4 0 0 4 3 1 0 0 0
Environment Agency 22 8 5 1 6 40 8 1 0 0 9
Other statutory consultees 22 10 4 0 5 4 8 1 0 0 8
Community 47 35 1 5 3 4 0 0 1 0 4
Interest groups/representatives 40 27 9 3 3 12 1 0 0 0 6
Secretary of State 51 37 1 0 0 6 1 0 0 0 3
Other (please specify) 85 6 0 0 0 6 1 0 0 0 1
Consultants % (N=98)
LPA/County Council 2 1 12 0 5 9 36 0 0 3 32
Developer 21 3 2 0 9 13 0 3 0 5 17
Environmental consultancy 39 26 8 0 4 8 2 0 0 4 9
Environment agency 6 6 11 0 6 37 12 0 0 0 21
Other statutory consultees 7 6 11 0 4 39 14 0 0 0 18
Community 17 26 5 3 13 6 0 1 11 2 15
Interest groups/representatives 14 17 11 2 10 21 5 1 4 0 13
Secretary of state 27 57 0 0 1 8 4 0 0 0 3
Other (please specify) 83 15 0 1 0 0 0 0 0 0 1
Statutory consultees % (N=28)
LPA/County council 43 0 25 0 4 7 4 0 0 4 14
Developer 50 14 4 0 7 11 7 0 0 4 4
Environmental consultancy 61 11 11 0 0 4 4 0 0 4 7
Environment agencyb 53 23 12 0 0 0 12 0 0 0 0
Other statutory consultees 50 14 21 0 0 4 7 0 0 4 0
Community 71 18 0 4 4 0 0 0 0 4 0
Interest groups/representatives 61 14 14 0 7 0 0 0 0 4 0
Secretary of State 71 21 0 0 0 7 0 0 0 0 0
Other (please specify) 86 7 4 0 0 0 0 0 0 4 0
aThis question was multi-response, therefore the % figure for each group/method is a proportion of the total number of respondents from each organisation.
bFigures for this row exclude Environment Agency responses.
G.Woodet
al./Enviro
nmentalIm
pact
Assessm
entReview
26(2006)221–241
235
G. Wood et al. / Environmental Impact Assessment Review 26 (2006) 221–241236
It is clear from the findings that there is very limited active community consultation in
scoping, reflecting the lack of any regulatory requirement. Yet public participation and
consultation are important in scoping and can allow those with local knowledge to provide
inputs that will aid the identification of dsignificantT impacts. A lack of such inputs means
that community members will have little say about what the key impacts are at an early
stage and have less opportunity to shape the EIA so that it addresses their concerns. Several
authors (Glasson et al., 1999; Palerm, 2000; Weston, 2000b; Mulvihill, 2003) stress the
importance of public involvement, but identify reasons for its limited use in practice,
including: consultation fatigue; community scepticism; developer reluctance; resource
constraints and inappropriate methods.
The survey revealed largely dtraditionalT methods of public engagement where they
were used at all e.g. public meetings, displays and sometimes advertisements. Many of
these methods have their place, and indeed advertisements are a statutory requirement in
EIA, although Mulvihill (2003) suggests a twin-track approach including such conven-
tional methods, plus more open and speculative public consultation. As noted by McNab
(in Weston, 1997), opening up the process may be regarded as unnecessarily risky by
developers. Furthermore, whatever the consultation process, it is important to consider
local socio-economic characteristics; communities with limited skills for participation plus
limited resources will need different styles and approaches.
The questionnaire asked participants to report the degree to which consultation
changed their opinion on scoping issues for the last project they were involved in. For
LPAs the views of statutory consultees appeared to have the greatest influence, changing
LPA scoping opinions significantly in approximately 40% of cases. For consultancies, it
was the LPAs which had a similar degree of influence. In contrast, statutory consultees
did not seem to be influenced in a major way by any one organisation, reflecting their
independent nature and their advisory role in the process. For both LPAs and
consultancies, where community consultation has occurred, it does not appear to have
resulted in any notable change in the scoping decisions. Indeed, nearly 25% of LPAs
and 20% of consultancies indicated that consultation with the community did not change
their scoping opinion in any way at all. Further research is required to understand why
this is the case, but possible explanatory factors may be: perceived limited value of
community inputs; inappropriate, superficial and cosmetic consultation practice; and
LPA and consultant effectiveness in identifying impacts and issues that will be of
concern to the community.
4.6. Resources and constraints in the scoping process
Partly reflecting the different roles in the scoping process, LPAs and statutory
consultees tend to use one person or a number of dindividualsT to make decisions on the
significance of impacts. In contrast consultancies prefer a team-based approach.
Interactions between the three groups may involve a number of steps to assemble the
necessary information. Our findings show that the LPA officers request additional
information from the applicant in approximately 40% of cases; for statutory consultees
46% acknowledge the need to request further information. It is interesting to note that a
high proportion (77%) of those LPAs that seek additional information are actually asking
G. Wood et al. / Environmental Impact Assessment Review 26 (2006) 221–241 237
the applicant for further inputs regarding what the potential impacts may be. Their
second most common request is for information on the characteristics of the
development (53%). For statutory consultees the most common requests are for more
information on the nature of the environment and more information on potential impacts
(both 69%).
The resource implications and constraints that arise due to the various demands
of the scoping process constituted the final question in the survey. Table 5 clearly
illustrates LPA concerns about the lack of resources to undertake the tasks
involved. This is symptomatic of the increasing pressure on the limited resources of
the UK planning system, as revealed in many other contemporary studies (see for
example, ODPM/LGA, 2004). Lack of resources was also a concern for statutory
consultees.
Time-frame constraints are seen as a serious issue by all three groups, and this may
explain why LPAs seem to spend only a relatively short period of time preparing scoping
opinions. Jennings and Wattam (1998) suggest that a reduced time-span for making a
decision will decrease the consideration given to that decision. This in turn increases the
risk of making an inappropriate decision about significant impacts. Weston (2000b)
suggests coming to an agreement with the developer about extending the five weeks in
which the scoping opinion is required if LPAs feel that the time frame for making an initial
decision is too short.
Uncertainty and lack of clarity over aspects of scoping also contributed to a number of
comments about constraints. Lack of understanding of the process is seen as a fairly
significant constraint by LPAs (22%), consultants (37%) and statutory consultees (50%).
Lack of clarity regarding government guidelines is considered a constraint for over one
quarter of LPAs. Statutory consultees and consultants felt that uncertainty over baseline
data and other elements (46%) were additional significant constraints.
Table 5
Constraints on scopinga
Constraint LPA %
(N=78)
Consultants %
(N=98)
Statutory consultees
% (N=28)
No Answer 6 2 4
There are no constraints 5 5 7
Lack of resources to do scoping study 68 13 43
Lack of commitment by different parties 18 19 11
Lack of understanding of the process 22 37 50
Time-frame constraints 44 49 46
Policy and development plan constraints 0 4 4
Lack of clarity re: regulations/gov. guidance 27 13 7
Consultation requirements with other groups 23 24 4
Uncertainty over baseline data, project
description/specification etc.
17 46 46
Other 10 9 14
a For this question respondents could choose up to three constraints therefore the % figure for each constraint is
a proportion of the total number of respondents from each organisation.
G. Wood et al. / Environmental Impact Assessment Review 26 (2006) 221–241238
5. Conclusions and recommendations
From the analysis of the questionnaire data, a number of conclusions can be drawn about
the nature of current scoping practice as performed by different organisations under the
1999 EIA Regulations. The LPAs, consultants and statutory consultees have different, but
interacting, roles in the process. They also have different perspectives and types of
influence. The LPAs are the competent authorities with the power of regulation, but they are
often under-resourced and lacking in experience of EIA activity. This is particularly the case
for non-metropolitan district councils which may receive very few requests for scoping
opinions each year. In general, LPAs appear to focus on impact identification rather than the
prescription of the specific fine details of EIA content and approach. They also rely largely
on professional judgement and consultation with other professionals to identify impacts and
to determine their significance.
In contrast, consultants show a greater concern for more complex issues than LPAs
(e.g. uncertainty and impact inter-relationships) and use more quantitative techniques—
although professional judgement is still the predominant scoping method. Consultants
typically bring more technical knowledge and expertise to the process and spend a
longer period of time on scoping than the LPAs. This probably reflects the nature of
their involvement in the scoping process, with consultants taking a lead role in terms of
drafting out the more detailed boundaries of the EIA, including issues such as the extent
of baseline survey work, predictive techniques, and the overall assessment approach to
be employed. Statutory consultees also bring considerable expertise, but this is most
likely to be for specific aspects of the environment that are relevant to the remit of their
organisation.
Although the three groups have different roles, powers and expertise, there is also
considerable interdependence between them. A high degree of consultation exists
between the three types of organisation, although a small proportion of LPAs are failing
to consult with statutory consultees. This is of some concern given that it appears that
such consultees can exert considerable influence on the LPA scoping opinion and in turn
LPAs influence consultants. In contrast to the high degree of consultation between the
parties, community consultation by all three parties appears to be limited. As such, the
scoping exercise may lack the benefit of local knowledge about the receiving
environment, and also community members will have less opportunity to shape the
EIA so that it addresses their concerns. Scoping practice in England and Wales can
therefore be characterised as being a professionally inclusive, technically oriented activity,
far removed from the notions of a participative social model. Indeed, even where
community consultation has occurred it does not appear to have had much of an impact
upon the scoping outcome. Possible explanatory factors may be, as discussed: perceived
limited value of community inputs; cosmetic consultation practice; or alternatively the
LPA/consultant may in fact be acting effectively in identifying impacts of concern to the
community. The research method employed in this study has enabled a macro analysis of
overall patterns of scoping practice, but detailed case study research is required to explore
these hypotheses further.
The findings are to some extent reassuring with regard to some aspects of scoping
previously perceived as problematic. For example there is concern in the literature that
G. Wood et al. / Environmental Impact Assessment Review 26 (2006) 221–241 239
scoping can become a broadbrush exercise whereby all impacts are identified rather than
focusing upon significant impacts (Weston, 2000b). The research results suggest that even
if the emphasis in scoping opinions/reports is not restricted simply to the most significant
impacts, practitioners are certainly able to prioritise and identify those impacts they
consider to be of most concern (and thus potentially more significant) for the projects they
are involved in. However, the extent to which this is made transparent in documented
scoping opinions and reports requires further investigation. Impact inter-relationships were
also considered to be of high concern during scoping, yet such impacts are generally given
little attention in EISs. This may reflect the difficulty of assessing and communicating
inter-relationships adequately in EISs.
Professional judgement clearly plays a key role in scoping. In general, consultants make
good use of prior experience and consult on other examples of similar projects. This is less
common amongst statutory consultees and LPAs, and further work is needed to establish
appropriate mechanisms for sharing experience amongst these bodies, while avoiding the
evolution of a dcut and pasteT culture of scoping opinion formation. Of course, resource
constraints and uncertainty/lack of clarity can hinder effective scoping. This is particularly
apparent for LPAs who spend the least amount of time on preparing scoping opinions.
Promoting the use of checklists, perhaps involving a small team of LPA officers, would be
one way of assisting scoping in a way that is not prohibitively time-consuming, and the use
of the Environment Agency guidelines (even at o95!) could be encouraged.
Other recommendations include LPAs giving more emphasis to the role of alternatives
in scoping and to specifying parameters for the consideration of mitigation, although again
a lack of knowledge/capacity and resources is likely to limit this. The UK could perhaps
also improve the process by having a mandatory scoping procedure in place—as with
several other EU Member States. As highlighted earlier, some Member States also legally
require consultation with the public as a part of the scoping process. Such changes could
improve the quality of, and access to, information, but will undoubtedly have time/
resource implications. They could also shift the nature of relationships between the
stakeholders, and strengthen the role of the currently weak fourth party—the public. Issues
such as this may need to be addressed over the next few years by the UK Government with
the next stage in the adaptive evolution of EU and UK EIA regulations and procedures.
Acknowledgements
The support of the Economic and Social Research Council (Award R000239676) and
the EIA unit at the Office of the Deputy Prime Minister is gratefully acknowledged.
Thanks are also due to all the busy LPA officers, consultants and statutory consultees
around England and Wales who took part in the research, and to the peer reviewers for
their helpful comments.
References
Baxter W, Ross WA, Spaling H. Improving the practice of cumulative effects assessment in Canada. Impact
Assess Proj Apprais 2001;19(4):253–62.
G. Wood et al. / Environmental Impact Assessment Review 26 (2006) 221–241240
Chadwick A. Socio-economic impacts: are they still the poor relations in UK EISs? J Environ Plan Manag
2002;45(1):3–24.
Council on Environmental Quality (CEQ). Environmental Justice: Guidance Under the National Environmental
Policy Act. Washington DC, USA7 CEQ; 1997.
Department of the Environment (DoE). Preparation of Environmental Statements for Planning Projects that
Require Environmental Assessment—A Good Practice Guide. London, UK7 HMSO; 1995.
Department of the Environment (DoE). Changes in the Quality of Environmental Statements for Planning
Projects: Research Report. London, UK7 HMSO; 1996.
Department of the Environment Transport and the Regions (DETR). Circular 02/99: Environmental Impact
Assessment. London, UK7 HMSO; 1999.
Department of the Environment Transport and the Regions (DETR). Environmental Impact Assessment:
Guide to Procedures; 2000. http://www.odpm.gov.uk/stellent/groups/odpm_planning/documents/page/
odpm_plan_026667.hcsp (last accessed January 14th, 2005).
Environment Agency. A Handbook for Scoping Projects. Bristol, UK7 Environment Agency; 2002.
European Commission (EC). Council directive 97/11/EC of 3 March 1997 amending directive 85/337/EEC on the
assessment of the effects of certain public and private projects on the environment. Off J Eur Communities, L
1997;73:5–15.
European Commission (EC). Guidance on EIA Scoping. Luxembourg7 Office for Official Publications of the
European Commission; 2000.
European Commission (EC). Report From the Commission to the European Parliament and the Council on the
Application and Effectiveness of the EIA Directive; 2003. http://europa.eu.int/comm/environment/eia/
report_en.pdf (last accessed January 14th, 2005).
Glasson J, Therivel R, Chadwick A. Introduction to Environmental Impact Assessment. Second ed. London, UK7
UCL Press; 1999.
Jennings D, Wattam S. Decision Making: An Integrated Approach. Second ed. Harlow, UK7 Pearson Education
Limited; 1998.
Jones C. Screening, scoping and consideration of alternatives. In: Petts J, editor. Handbook of Environmental
Impact Aassessment. Oxford, UK7 Blackwell Scientific; 1999. p. 201–24.
Kennedy AJ, Ross WA. An approach to integrate impact scoping with environmental impact assessment. Environ
Manage 1992;16(4):475–84.
McNab A. Scoping and public participation. In: Weston J, editor. Planning and Environmental Impact Assessment
in Practice. Harlow, UK7 Longman; 1997. p. 60–77.
Mulvihill PR. Expanding the scoping community. Environ Impact Asses Rev 2003;23:39–49.
Mulvihill PR, Baker CB. Ambitious and restrictive scoping: case studies from Northern Canada. Environ Impact
Asses Rev 2001;21:363–84.
Mulvihill PR, Jacobs P. Using scoping as a design process. Environ Impact Asses Rev 1998;18(4):
351–69.
Office of Deputy Prime Minister (ODPM)/Local Government Association (LGA). The Skills Base in the UK
Planning System, vol. 1, 2. London, UK7 LGA; 2004.
Palerm JR. An empirical–theoretical analysis framework for public participation in environmental impact
assessment. J Environ Plan Manag 2000;43(5):581–600.
Piper JM. Assessing the cumulative effects of project clusters: a comparison of process and methods in four UK
cases. J Environ Plan Manag 2001;44(3):357–75.
Pritchard D. Towards sustainability in the planning process: the role of EIA. ECOS (Br Assoc Nat Conserv)
1993;14(3,4):10–5.
Sadler B. Environmental assessment in a changing world: evaluating practice to improve performance. Final
Report of the International Study of the Effectiveness of Environmental Assessment. Canadian Environmental
Assessment Agency/IAIA. Canada7 Ministry of Supply and Services; 1996.
Weston J. EIA, decision-making theory and screening and scoping in UK practice. J Environ Plan Manag
2000a;43(2):185–203.
Weston J. Screening, Scoping and ES Review Under the 1999 EIA Regulations. Working Paper No. 184. Oxford
Brookes University, Oxford, UK; 2000b.
Wood C. Environmental Impact Assessment: A Comparative Review. Second ed. London, UK7 Prentice Hall; 2003.
G. Wood et al. / Environmental Impact Assessment Review 26 (2006) 221–241 241
Graham Wood is a Senior Lecturer in Environmental Assessment and Management, based in the Impacts
Assessment Unit at the School of the Built Environment, Oxford Brookes University.
John Glasson is Professor in the Impacts Assessment Unit and Associate Dean (Research and Consultancy) at the
School of the Built Environment, Oxford Brookes University.
Julia Becker is a Social Scientist at the Institute of Geological and Nuclear Sciences in New Zealand, and was
formerly a Research Associate in the Impacts Assessment Unit, Oxford Brookes University.