Upload
others
View
15
Download
0
Embed Size (px)
Citation preview
- 1 -
Electricity Markets:
Balancing Mechanisms and Congestion Management
Master Thesis Report
Mathilde Dupuy
- 2 -
ABSTRACT
During the last few years, several European countries have opened their electricity
markets. Power exchanges have been created, and market based rules have been settled to
handle most of the existing mechanisms. The main goal is to improve the competition by
increasing the number of actors. More and more coordination between the different European
markets is now needed, and the trend is to go from juxtaposed regional markets to a unique
European market. Indeed, in February 2006 was launched the Electricity Regional Initiative,
where directives were given in order to foster market integration within several European
countries. In this context, two main points have to be focused on: the settlement of market
based rules for each mechanism and the integration of the different existing markets.
This master thesis is a part of a Research and Development project, and has been done
at EDF Research & Development, in the department “Economie, Fonctionnement et Etudes
des Systèmes Electriques”. It is divided in two parts.
The first part explains the main principles of the balancing mechanisms in Great-
Britain and Germany, in order to see to which extend these mechanisms are “markets”. The
study is a part of a larger project at EDF, resulting in a benchmark of the different European
Balancing Markets.
The second part deals with a key to the integration of electricity markets: the
congestion management methods. Indeed, cross border congestions are a main hindrance to
the elaboration of a European market, and new mechanisms are developed to allocate the
cross border capacities. One of them is the Market Coupling, which is a way to maximize the
market value. This thesis aims at giving a basic understanding of the method as it is carried
out today between France, Belgium and the Netherlands through the Trilateral Market
Coupling. In the frame of an Open Market Coupling including more countries, this thesis
gives an introduction to two different approaches: the “commercial” approach and the “flow-
based” approach. Simulations aim at stressing the main differences between the two methods.
- 3 -
ACKNOWLEDGMENTS
Firstly, I would like to thank Jeremy Louyrette, who has accepted to be my supervisor
at EDF. I would like to thank all the people with whom I had the occasion to work at EDF for
their cooperation and for the great working environment they have provided to me.
This master thesis has allowed me to learn a lot on very interesting and challenging topics,
and I am very grateful for that.
Besides, I would like to thank Lennart Söder and Mikael Amelin for reviewing my
thesis and being my examiners.
- 4 -
CONTENTS
Chapter I. Introduction ................................................................................................................................. 10
I.A. Background................................................................................................................................................ 10
I.B. Thesis work: Scope and Contents .............................................................................................................. 11
Chapter II. Balancing Markets: The examples of Great Britain and Germany ................................... 12
II.A. Background .............................................................................................................................................. 12 II.A.1 The different actors ........................................................................................................................... 12 II.A.2 The main principles........................................................................................................................... 13 II.A.3 Aim of the study................................................................................................................................ 13
II.B. Balancing mechanism in Great-Britain.................................................................................................... 15 I.A.1 Description of balancing services....................................................................................................... 15
II.B.1.1. Frequency response .................................................................................................................. 15 II.B.1.2. Reserve services ....................................................................................................................... 16
II.B.2 The Balancing Mechanism and the “market” aspect ......................................................................... 17 II.B.2.1. How the market works.............................................................................................................. 18 II.B.2.2. Imbalance Settlement ............................................................................................................... 21
II.C. Balancing mechanism in Germany .......................................................................................................... 23 II.C.1 Description of the services ................................................................................................................ 23
II.C.1.1. Primary control ......................................................................................................................... 23 II.C.1.2. Secondary control ..................................................................................................................... 23 II.C.1.3. Tertiary control: Minutenreserve .............................................................................................. 23 II.C.1.4. Time frame of control energy ................................................................................................... 24
II.C.2 The Balancing mechanism and the “market” aspect ......................................................................... 25 II.C.2.1. How the market works.............................................................................................................. 25 II.C.2.2. Imbalance settlement ................................................................................................................ 28 II.C.2.3. The particular case of wind power............................................................................................ 29
II.D. Conclusions.............................................................................................................................................. 30
Chapter III. Congestion Management: The Market Coupling Mechanism............................................ 32
III.A. Background............................................................................................................................................. 32
III.B. Market Coupling: Analysis of the mechanism principles........................................................................ 33 III.B.1 Some basic principles....................................................................................................................... 34
III.B.1.1. Aggregated supply and demand curves ................................................................................... 34 III.B.1.2. Net exportation curves ............................................................................................................ 35 III.B.1.3. Block offers............................................................................................................................. 37
III.B.2 Trilateral Market Coupling: how does it work? ............................................................................... 37 III.B.2.1. Overview of the mechanism as it is carried out today............................................................. 37 III.B.2.2. Algorithm of the coordination module: Coupling three markets............................................. 39
III.C. Simulation of Market Coupling............................................................................................................... 43 III.C.1 Simulation on three markets using a sequential algorithm............................................................... 43
III.C.1.1. Inputs and Outputs of the simulation....................................................................................... 43 III.C.1.2. Prices calculation..................................................................................................................... 44 III.C.1.3. Algorithm principles ............................................................................................................... 44 III.C.1.4. Steps of the algorithm ............................................................................................................. 45 III.C.1.5. Particularities of the model...................................................................................................... 51 III.C.1.6. Conclusion regarding the sequential model ............................................................................ 51
- 5 -
III.C.2 Market Coupling as a system-wide optimisation problem............................................................... 52 III.C.2.1. Definition of the parameters and variables.............................................................................. 52 III.C.2.2. Definition of the objective function ........................................................................................ 53 III.C.2.3. Formulation of the constraints................................................................................................. 55 III.C.2.4. Particularities of the simulation............................................................................................... 56 III.C.2.5. Calculation of the market prices and surplus........................................................................... 57
III.C.3 Results of the simulation: Sequential model versus optimisation .................................................... 58 III.C.4 Conclusions regarding the results .................................................................................................... 64 III.C.5 Perspectives ..................................................................................................................................... 64
III.D. Towards an Open Market Coupling ....................................................................................................... 66 III.D.1 Elaboration of the scenarios............................................................................................................. 66 III.D.2 Result of the simulations.................................................................................................................. 67
III.E. Towards a flow-based market coupling .................................................................................................. 75 III.E.1 Formulation of the problem with the Power Transfer Distribution Factors ..................................... 75 III.E.2 Data used in the model ..................................................................................................................... 76 III.E.3 Simulation on the scenarios.............................................................................................................. 79
III.F. The commercial approach versus the flow based approach ................................................................... 85
Chapter IV. Conclusions ............................................................................................................................. 86
IV.A. Main aspects of the study ........................................................................................................................ 86
IV.B. Perspectives ............................................................................................................................................ 87
- 6 -
FIGURES
Figure 1: Timescales of electricity markets ............................................................................. 10
Figure 2: Timescales of the balancing services ....................................................................... 17
Figure 3: Timescales of the British electricity market ............................................................. 18
Figure 4: Bid/Offer Data [5] ................................................................................................... 19
Figure 5: Representations of the bid/offer data ....................................................................... 19
Figure 6:Bid/offer acceptance (BOA) [6] ................................................................................ 20
Figure 7: Main Price calculation in case of a short system .................................................... 22
Figure 8: Timescales of the different kinds of reserve [2] ....................................................... 24
Figure 9: The different timescales of the German market ....................................................... 25
Figure 10: Example of bid data [3] ......................................................................................... 26
Figure 11:Extract of tender results for downwards regulation for tertiary reserves
(10.07.2007, 12:00-16:00) [16] ............................................................................................... 27
Figure 12:Extract of tender results for upwards regulation for tertiary reserves
(10.07.2007, 00:00-4:00) [16] ................................................................................................. 28
Figure 13 : The different congestion management methods in Europe [26] ........................... 32
Figure 14: Coupling of two markets when there is no congestion........................................... 35
Figure 15: Coupling of two markets when there is a congestion............................................. 35
Figure 16: Construction of the Net Exportation Curve ........................................................... 36
Figure 17: Bilateral Coupling using the NECs........................................................................ 36
Figure 18: Overview of different steps in the Market Coupling process [25] ......................... 38
Figure 19: First step of the TLC .............................................................................................. 39
Figure 20: Second step of the TLC, non-congested case ......................................................... 40
Figure 21: Second step of the TLC, non-congested case ......................................................... 40
Figure 22: TLC results, congested case................................................................................... 41
Figure 23: TLC results, congested case................................................................................... 41
Figure 24: TLC results, congested case................................................................................... 42
Figure 25: System studied ........................................................................................................ 43
Figure 26: Effect of an import or an export on the NEC ......................................................... 44
Figure 27: Coupling three markets with no constraints – incremental process ...................... 47
Figure 28: Coupling three markets with constraints – incremental process ........................... 49
Figure 29: Calculation of the consumers’ and producers’ surplus, ........................................ 50
Figure 30: Effect of an import/export on the supply an demand curves.................................. 50
Figure 31: Definition of the parameters .................................................................................. 52
Figure 32: Global surplus of the three markets aggregated, in case of no congestion ........... 54
Figure 33: Definition of the variables...................................................................................... 56
Figure 34: Particularities with linear curves .......................................................................... 56
Figure 35: Price and Volume indeterminations....................................................................... 57
Figure 36: Results of the simulation, scenario 1 ..................................................................... 59
Figure 37: Results of the simulation, scenario 2 ..................................................................... 60
Figure 38: Results of the simulation, scenario 3 ..................................................................... 61
Figure 39: Results of the simulation, scenario 4 .................................................................... 62
Figure 40: Results of the simulation, scenario 5 ..................................................................... 63
Figure 41: Calculation of the surplus using the NECs ............................................................ 65
Figure 42: Increase of the surplus resulting from the coupling............................................... 65
Figure 43: Results from the base scenario using the ATC model ............................................ 67
Figure 44: Results from the scenario 1 using the ATC model ................................................. 68
Figure 45: Results from the scenario 2 using the ATC model ................................................. 69
- 7 -
Figure 46: Results from the scenario 3 using the ATC model ................................................. 70
Figure 47: Results from the scenario 4 using the ATC model ................................................. 71
Figure 48: Results from the scenario 5 using the ATC model ................................................. 72
Figure 49: Results from the scenario 6 using the ATC model ................................................. 73
Figure 50 : Power flow distribution of a 1000 MW trnasport from Northern France to Italy 75
Figure 51:Results from the base scenario using the PTDF model .......................................... 79
Figure 52: Comparison of the results from the base scenario................................................. 80
Figure 53: Comparison of the results from the scenario 1 ...................................................... 81
Figure 54: Comparison of the results from the scenario 2 ...................................................... 81
Figure 55: Comparison of the results from the scenario 3 ...................................................... 82
Figure 56: Comparison of the results from the scenario 4 ...................................................... 82
Figure 57: Comparison of the results from the scenario 5 ...................................................... 83
Figure 58: Comparison of the results from the scenario 6 ...................................................... 84
Figure 59: Metered Imbalance ................................................................................................ 88
- 8 -
TABLES
Table 1: The different actors .................................................................................................... 17
Table 2: Imbalance settlement prices....................................................................................... 22
Table 3: The different kinds of reserve in Germany................................................................. 24
Table 4: Main aspects of the British and German Balancing Markets.................................... 31
Table 5: Results of the simulation, scenario 1 ......................................................................... 59
Table 6: Results of the simulation, scenario 2 ......................................................................... 60
Table 7: Results of the simulation, scenario 3 ......................................................................... 61
Table 8: : Results of the simulation, scenario 4....................................................................... 62
Table 9: Results of the simulation, scenario 5 ........................................................................ 63
Table 10: Prices of the futures for the second semester 2008 ................................................. 66
Table 11: Volumes on the spot market in 2006........................................................................ 66
Table 12: Day-ahead market volumes ..................................................................................... 66
Table 13: ATC matrix (in MW) ................................................................................................ 67
Table 14: Average balances in MW ......................................................................................... 76
Table 15: Initial Balances in MW ............................................................................................ 77
Table 16: Data used for PTDF and T0 .................................................................................... 77
Table 17 : Prices in €/MWh ..................................................................................................... 79
Table 18: Physical power flows, Base scenario....................................................................... 80
Table 19: Constraints on the pysical power flows ................................................................... 80
Table 20: Physical power flows and their limitations.............................................................. 83
Table 21: Physical power flows and their limitations.............................................................. 84
Table 22: Activation of minute reserve .................................................................................... 88
- 9 -
LIST OF ABREVIATIONS
• EDF: Electricité de France (main company of electricity production and distribution in
France)
• RTE: Réseau de Transport d’Electricité (French TSO)
• TSO: Transmission System Operator
• UCTE: Union for the Coordination of Transmission of Electricity
• ETSO: Association of the European Transmission Operators
• CWE: Central Western Europe
• E&W: England and Wales
• TLC: Trilateral Market Coupling
• OMC: Open Market Coupling
• NEC: Net Exportation Curve
• NIC: Net Importation Curve
• ATC: Available Transfer Capacity
• NTC: Net Transfer Capacity
• PTDF: Power Transfer Distribution Factor
- 10 -
Chapter I. Introduction
I.A. Background
In 1989, England opened its market, and Sweden followed in 1995. The first
international power pool, NordPool, was founded in the Scandinavian countries.
In the current context of opening energy markets, new objectives have become a priority.
The main goal is to allow a better competition, by increasing the number of actors. The trend
is nowadays to abolish the situations of monopoly, and base the new mechanisms on a
reduction of the overall costs. Market-based rules are laid down, in order to create a fair and
non-discriminatory market for every mechanism.
Therefore, each country in Europe has developed their own energy market, and by a better
coordination of these markets, the final goal is to integrate all of them in a unique European
market. Hereby, it would not only ensure a better economical stability, but a better physical
stability as well through a wider power system.
New methods are created for trading energy, planning production, keeping the balance
between production and consumption and managing the energy transactions on cross border
transmission lines. All of these activities are done on different timescales, corresponding to
the general description below:
Time
Years, Months, Weeks
Futures & Forward
Markets
Bilateral Market
D-1
Spot
Market
D
Intraday
Market
Real Time
Balancing
Market
Program
redeclarations
• Bids & Offers
Submission
• Initial Planning
• After the Gate closure:
Bids & Offers selection,
Pricing
Real time energy
balancing
operated by the
TSO
D+1
Imbalance
SettlementLong term contracts
D+n
Figure 1: Timescales of electricity markets
On the Futures and Forwards market, long term contracts are decided: a certain amount of
energy for a defined period of time and on an agreed price is contracted. A forward is a
bilateral contract, whereas the future is contracted on an organized market and is a
standardized product.
On the day-ahead spot market, the actors submit their bids and offers, and units submit
their production planning before the gate closure. The time of the gate closure depends on the
country. After closure of the bilateral market and the spot market, bids and offers are selected,
and the spot price is set up, through a price clearing.
Then during the day, in the so-called intra-day market, generation programs can be re-
declared and market players can modify existing bilateral contracts or create new ones.
Besides, in real time, the Transmission System Operator must keep the balance between
production and consumption, through the balancing market. Finally, the imbalance metered
between contractual and physical positions of actors is financially settled after the day of
delivery.
- 11 -
I.B. Thesis work: Scope and Contents
The thesis is divided in two parts: the first one focuses on the balancing mechanism,
corresponding to the real time in the different timescales of the market. The second one
presents a study of a congestion management method, the market coupling, which takes place
in the day-ahead market, and will probably be adopted in the intra-day market as well.
The first part of the project consists of studying the balancing mechanisms in Germany
and Great-Britain, based on literature. This was in fact a participation to a larger project,
aiming at describing and analysing the different balancing mechanisms in Europe. This
project has been carried out by EDF in order to have a benchmark of the different European
balancing markets, focusing on the format of the bids and offers. Indeed, the orders submitted
on the French balancing market are implicit, but they are to become explicit orders.
In this frame, two countries have been studied. Even if it does not give a general view
upon the existing mechanisms in Europe, it was interesting to study in detail two countries, so
that differences and likenesses could be pointed out. In this report, a summary of the study is
given, in order to give concise information regarding the two mechanisms.
If the trend is to integrate the different markets in a unique one, an increasing part of
energy transaction between the different European markets will be necessary and especially
balancing energy. To fulfil these objectives, new congestion management methods are
adopted, in order to make an optimal use of the cross border transmission lines.
Among them, the Market Coupling mechanism has been implemented in Central Western
Europe. Trilateral Market Coupling was launched between France, Belgium and the
Netherlands in November 2006. The mechanism is about to be extended to other border
countries like Germany.
In this report, we will first study the theoretical approach of market coupling and how it is
handled between France, Belgium and the Netherlands. Then, we will try to formulate the
problem in different ways and simulate the mechanism using theoretical data.
Finally, a small study will explain the differences between a commercial approach and a
flow-based approach.
In this frame, two models have been developed:
� The first one simulates the mechanism for three countries, and has been implemented
using Excel and its programming language Visual Basic for Application. It calculates
the final prices and energy transactions between the markets, starting with the net
exportation curves of the isolated markets, and the cross-border transmission
capacities.
� The second one is an optimisation under constraints using GAMS, and can be used
with N markets. Two approaches have been implemented:
• The commercial approach, where transmission constraints take into account
commercial limitations of the energy transactions.
• The flow-based approach, where transmission constraint takes into account
physical limitations of the power flows.
- 12 -
Chapter II.
Balancing Markets: the examples of Great Britain and
Germany
II.A. Background
The main specificity of electric energy is that it cannot be stored. Moreover, in order to
ensure the security of the electricity network, the balance between production and
consumption must be kept all the time.
In the day-ahead market, supply and demand curves are submitted for each settlement
period of the following day. According to these data, the balance between production and
consumption is respected, since the energy price and the traded volume are defined by the
intersection of the two curves. Nevertheless, these data are only forecasts, and the real time
situation might be different. Indeed, the demand can vary compared to the forecast, and the
production planning can fluctuate, in case of a problem in a power plant for example.
To handle those variations, a mechanism is needed to balance in real time the
consumption and the production; it is the so-called balancing mechanism.
From a country to another, the balancing mechanisms may be different, depending on the
timescales of the market, the technical differences, the means of generation or the national
rules. Nevertheless, the common trend in deregulated market is to build a market with the
balancing mechanism, based on market rules.
Though differences between countries, some common principles define the general scope
of the balancing mechanism, when it is based on market rules:
� Production plan and load forecast, which takes into account bilateral contracts, and
bidding on the day-ahead spot market.
� Balancing generation and consumption in real-time by the means of re-declarations of
generation planning and bidding on the short term balancing market, which is an intra-
day market where bids are selected and activated in real time.
� Financial imbalance settlement between physical and contractual positions. It
generally takes place the following day and spreads fairly the incomes and costs
among the actors.
II.A.1 The different actors
� The balancing mechanism is carried out in real time by the Transmission System
Operator, who is required to maintain the permanent balance between generation and
demand.
� The units which are qualified can participate to the balancing market by submitting
bids1 and offers
2.
1 Downwards regulation order
2 Upwards regulation order
- 13 -
� The Balance Responsible Entity, who is in charge of a balancing perimeter, is
responsible for the financial settlement of imbalances within its perimeter. Every
market player has to belong to a balancing perimeter and choose a balancing
responsible.
II.A.2 The main principles
To handle real time deviations between injection and withdrawals in the electrical grid,
the TSO dispose of three different kinds of reserve power, which can be used for upwards or
downwards regulations:
� Primary Reserve
This kind of reserve is automatically activated. It is usually compulsory and never
constitutes the object of a market. The cost of this control are recovered through the
networks tariffs, based on the metered quantities of generators and consumers.
� Secondary Reserve (only for the UCTE network)
This kind of reserve is automatically activated in most cases. Depending on the country, it
can be part of a balancing market. The aim of the reserve is to reconstitute the primary
reserve when it has been used.
� Tertiary Reserve
This reserve is a complementary reserve, and is often the core of the balancing market. It
is usually manually activated, and split into rapid reserve (available in less than 10-15
minutes) and cold reserve (available after a longer time). However, in some countries, the
boundaries between secondary and tertiary reserve and between the two types of tertiary
reserve are blurred.
According to the ETSO [9], three groups are identified having different services for
frequency control:
� UCTE (Union for the Coordination of Transmission of Electricity), where the three
kinds if services described above are available
� E&W (England and Wales), where the secondary control does not exist and is in
fact a part of the primary control
� The Nordel (common power system of the Nordic countries), where the so-called
“Secondary Regulation” is referred to as tertiary control, since it is manually
activated.
The object of balancing mechanism is mainly tertiary reserves, and sometimes secondary
reserves as well. This can vary from a country to another.
II.A.3 Aim of the study
The aim of the first study is to analyse the balancing mechanisms in two countries, Great-
Britain and Germany. This will allow us to see to which extent the mechanism can differ
between two countries. In order to stress the important differences and define the changes to
set up to reach a better harmonisation in Europe, it would be necessary to study the
mechanisms in all the European countries. However, it is not the aim of this master thesis.
- 14 -
This study has been carried out in a frame of a project, which aims at focusing on the
format of the orders and the type of services they are related to.
Indeed, on balancing markets, there are two types of orders: offers for upwards regulation
and bids for downwards regulation. The format of an order might be different from a country
to another. In France, the current orders are implicit, which means that a producer must offer
on the balancing market the available capacity remaining after the submission of its planning.
However, this situation might change, and let the actors submit explicit offers, with a chosen
quantity and price.
Studying two countries will not give a general European scope of the situation, but it will
nevertheless show important aspects of the balancing mechanisms, and point out some aspects
that should be harmonised.
- 15 -
II.B. Balancing mechanism in Great-Britain
National Grid Company (NGC) owns and manages the electricity transmission system in
England and Wales (E&W). By supplying Balancing Services, it maintains the balance
between injections and withdrawals on the grid. Therefore, it uses available reserves in order
to keep the system frequent at 50 ± 0.5 Hz. The allowed deviation from the nominal
frequency 50 Hz is higher than the one allowed by the UCTE, which is 50 ± 0.2 Hz. The
British synchronous network has a lower inertia than the UCTE network, due to the nature of
its generation power plant. Therefore, its network is more often prone to frequency deviation,
and needs balancing power.
Since the Great Britain is not connected to the rest of Europe, the system services are
carried out in a different way [1]. Secondary control does not exist in Great Britain.
We can distinguish three different types of balancing services [8]:
� Ancillary services, which are the system services procured by electricity producers.
There can be either mandatory or commercialised, and are detailed in the first
section
� Offers and Bids, submitted to the Balancing Mechanism. These are commercial
services offered by suppliers willing to increase or decrease the production in a
Balancing Mechanism Unit (BMU). These services are detailed in the second
section
� Other services, which are commercialised services. They are classified neither as
ancillary services nor as balancing market offers and bids.
The actors of the British balancing mechanism are:
� The TSO National Grid Company
� The BMU, which are units signatories of the Balancing and Settlement Code
� Actors not registered as BMU in some cases
II.A.1 Description of balancing services
II.B.1.1. Frequency response
Frequency response services are equivalent to the primary and secondary control in the
UCTE zone. They are part of system services, but can be remunerated.[1,2]. Dynamic
providers are in charge of handling changes second by second, whereas the non dynamic
providers change their production only from a certain level of frequency deviation.
NGC maintains the system frequency through three separate balancing services:
� Mandatory Frequency Response
The service is compulsory and automatic, guaranteed by BMUs. The bids contain an
availability fee (in £/h) and an energy fee (£/MWh). The aspect “market” is introduced
thanks to a system which allows the participant to modify the prices on a monthly basis, in
order to set a greater competition.
� Firm Frequency Response (FFR)
This service is commercialised by BMU or non-BMU actors, and act as a complement
of the other sources of Frequency Response, through dynamic and non-dynamic reserves.
FFR is procured through a monthly tender; the submitted orders can be valid for a single
month or several months. A provider submits several prices in its bid: an availability fee
- 16 -
(in £/h), an energy fee (£/h) and fees related the nomination or the revision of the offer on
a particular settlement period3 of the day.
� Frequency Control Demand Management (FCDM)
This service provides frequency response through interruption of the demand
customers; it is a way for demand-side provider to access to the market. However, the
service is conclude on a bilateral basis, and the remuneration is based on an availability
fee (£/MWh).
II.B.1.2. Reserve services
The remaining services correspond more to the tertiary reserves of the UCTE. It
contains the additional power sources which are available to NGC, and comprised
synchronised and non-synchronised sources, with different response times. [3]
� Fast start
It is a non compulsory system ancillary service, commercialised by BMU units. It is
provided by power plants which can start in a very short time (5-7 minutes), and is
concluded through bilateral contracts.
The bids contain an availability fee (£/h), an energy fee (£/MWh) and a start-up payment
(£/start).
� Fast reserve
The service is provided by BMU and non BMU, both from the production and demand
sides. The aim is to rapidly handle the frequency deviations, in less than 2 minutes. The
service is procured through a monthly tender. A provider submit several prices in its bid:
an availability fee (in £/h), an energy fee (£/MWh) and fees related the nomination or the
revision of the offer on a particular settlement period of the day.
� Short Term Operating Reserve (STOR)
The service is provided by BUM and non BMU, both from the production and demand
sides, with longer response time (240minutes).
The utilisation of this service is done through the balancing mechanism only for the BMU.
The bids contains an availability fee (£/h) and an energy fee (£/MWh).
� Demand management
The service provides reserve via a reduction of the demand. It is concluded through
bilateral agreements; there is only an energy fee (£/MWh).
� BM start-up
The service is provided by BMU only, and allows NGC to use in the balancing
mechanism additional units that would not otherwise have ran. The remuneration is based
on a start-up payment and a hot standby payment (£/h) to cover the cost of sustaining a
BMU in a state of readiness.
3 In the British system, the day is divided into 48 “windows”, or settlement period, of ½ hour each.
- 17 -
Finally, this summary of the balancing services offers in Great Britain show the
complexity of the system. The pictures below show the different timescales and actors
involved in each type of service.
Demand
Management
STOR
BM Start-up
Fast Start
Fast reserve Frequency
Response
< 240 min
< 85 min
< 5 min
< 2 min
< 1 sec
T-24 h T
FCDM
< 2 sec
Time
Figure 2: Timescales of the balancing services
Services BMU participation Non-BMU Participation
Mandatory Frequency
response
Suppliers
Firm Frequency response Suppliers & Consumers Suppliers & Consumers
FCDM Consumers
Fast Reserve Suppliers & Consumers Suppliers & Consumers
Fast Start Suppliers
STOR Suppliers & Consumers Suppliers & Consumers
Demand Management Consumers
BM Start-up Suppliers
Table 1: The different actors
II.B.2 The Balancing Mechanism and the “market” aspect
In 2001, The New Electricity Trading Arrangement (NETA) is introduced and then
extended to Scotland. The aim of this system is to allow a greater competition in the
wholesale market, while ensuring the security of the system.[6]
The new arrangements include:
• Forwards and Futures markets
• A Balancing mechanism, by which the TSO can accept offers and bids to
maintain the balance between production and consumption
• An imbalance settlement process, a financial settlement of the observed
imbalances
Through the Balancing Mechanism, NGC can buy and sell energy close to real time,
using the offers4 and bids
5 submitted by the actors. The acceptance of a bid or an offer is
managed by the Balancing and Settlement Company Elexon .
4 Upwards regulation
5 Downwards regulation
- 18 -
NGC provides the balancing services through the balancing mechanisms or other means
(bilateral contracts, specific tender for certain system services)[7].
The volumes and costs of balancing services concluded outside of the Balancing Mechanism
are integrated afterwards in the calculation of the prices for the imbalance settlement.
II.B.2.1. How the market works
Only the bids and offers belong to the balancing mechanism, which will work on
market based rules.
II.B.2.1.a. The different timescales
One of a feature of the British market is that there is a gate closure every half hour
during the whole day. Indeed, for each settlement period, the gate closure is one hour before
the beginning of this period. By this time, producers should have submitted their final
production plan, called the Final Physical Notification, and the BMUs should have submitted
their offers and bids as well.
Forward/Futures Markets
Bilateral Market
Balancing Mechanism
(on behalf of NGC)
Imbalance Settlement
(on behalf of Elexon)
T –1h
Gate Closure
T T+1/2h
-Bilateral & Forward contracts
-NGC contracts primary reserve and
other reserve contracts
NGC accepts offers & bids
for system energy
balancing
Settlement of cash flows
arising from the balancing
process
-FPN Submission
-Bids & Offers Submission
Figure 3: Timescales of the British electricity market
II.B.2.1.b. Format of the Bids & Offers
Each order are under the form of a “Bid-Offer pair”, which means that the provider
offers an interval of available capacity (a deviation from the FPN level) which can be used for
upwards or downwards regulation, depending on the level of production. Therefore, for each
submitted pair Bid/Offer, the unit defines a power level (number of MW, positive or
negative); which represents a variation from the planned level of production.
Each pair has a number, positive if the level is higher than the FPN, negative if it is
lower. The minimum order is 1 MW, and each one contain an energy price for the offer and
an energy price for the bid (£/MWh).
- 19 -
An example is given below:
Figure 4: Bid/Offer Data [5]
Each BMU can submit 10 pairs; the level of MW must be constant on each settlement period
[6]. The number of the pair increases with the proposed price.
To put it in a nutshell, the BMU offers an capacity interval, in which it can vary its
production depending on the need. It cannot offer only an upwards regulation; or only a
downwards regulation. The energy price depends on the level of the production compared to
the FPN level.
For example, considering the former bid/offer data and a FPN at 200 MW, then:
- If NGC wants to increase the production with 50 MW, starting from the FPN at 200 MW,
the energy price will be 30£/MWh
- If NGC needs afterwards a downward regulation of 80 MW, the BMU will pay 25£/MW
between 250 MW and 200 MW (pair 1), and then 20£/MW (pair –1)
The process is shown in the picture below:
Price
(€/MWh)
Puissance (MW)FPN(200 MW)
10
20
30
40
Offer Price
Bid Price
250 290 310 340160130
(-2)(-1)
(1)(2)
(3)(4)
Figure 5: Representations of the bid/offer data
- 20 -
If three positive pairs have been used for upwards regulation, the TSO must use the bid part of
those pairs before using a negative pair.
Furthermore, each BMU must submit a list of technical parameters with the order, to
allow NGC to compare it with the available system services and make the best choice. [5]
Those information concern especially the dynamic parameters, the generator specificities, the
limitation of injection and withdrawal at the network connection point…
Those parameters and the proposed prices are essential in the decision of using a bid/offer
pair instead of another reserve service.
II.B.2.1.c. Bids and Offers selection
The selection takes place right after the gate closure, based upon technical and economical
criteria.
Though the ancillary services are mainly considered as outside the Balancing Mechanism [8],
there can be used in the following case:
- NGC considers there will not be sufficient bids and offers to ensure the
security of the system
- NGC considers that they are an economical alternative to bids and offers
- The technical parameters of the offers and bids do not fit the requirements
The offers and bids, though explicit when they are submitted, are more implicit when they
are selected. Indeed, NGC can choose the quantity, and can thus accept an pair bid/offer
partly, as shown in the following example:
Figure 6: Bid/offer acceptance (BOA) [6]
The points A, B, C and D represent the accepted level, function of the time. The blue area
represents the acceptance energy volume. The picture above is called a Bid offer Acceptance.
A BMU can reject it only for security or technical reasons.
II.B.2.1.d. Remuneration
The services are paid at the bid or offer price, and not the marginal price: it is a pay-as-bid
system [6, 9]. It is important to notice that the capacity of the bids and offers are not paid for.
- 21 -
II.B.2.2. Imbalance Settlement
II.B.2.2.a. Imbalance definition
After each settlement period, the volume of the overall system energy imbalance is
calculated, in order to see if the system is globally long or short. It is the net of all systems
and energy balancing actions (including the ancillary services used outside of the balancing
mechanism) taken by the TSO for the considered period. [6]
It is called the Net Imbalance Volume (NIV):
- If NIV<0, the system is long (NGC must sell energy)
- If NIV>0, the system is short (NGC must buy energy)
Each BMU belongs to a Trading Unit, which is balance responsible. Therefore, a
Trading Unit contains several BMUs, regrouping the production on one side and the
consumption on the other. When the imbalance is calculated, only the imbalance of the whole
Trading Unit is considered, and not each BMU separately. This allows a compensation effect
between the different physical imbalances among the BMU.
Concerning the financial imbalance settlement, it is important to notice that the
imbalance is separated in two parts. Indeed, each balance responsible has two energy
accounts: one generation energy account and one production energy account.[10, 12]
Therefore, financially speaking, and there is no compensation between deviation registered on
the production side and deviation registered on the consumption side.
For example, let us consider a system where the deviations metered (compare to the
forecasts) are the following:
- An excess of 50 MWh in the production
- An excess of 50 MWh in the consumption
The overall imbalance is equal to zero, but the balance responsible must pay for a deviation of
100 MWh.
II.B.2.2.b. Financial Settlement
For each settlement period of a day, two prices are calculated:
- SSP, the System Sell Price, paid to the Trading Units, in case of a long
position
- SBP, the System Buy Price, paid by the Trading Units, in case of a
short position
These prices take into account the volume and prices of the accepted bids and offers.
The costs from the use of other system services contracted outside the balancing mechanism
appear also in the calculation, in the Balancing Services Adjustment Data (BSAD).
Indeed, for economical or technical reasons, NGC can use a balancing service outside the BM
instead of an offer or bid, and then its cost appears in the imbalance settlement prices, through
the BSAD. [6,14]
If the balancing service is provided by a BMU, the payment of the energy used is done
via the BM, and the availability fee (payment for the capacity) is integrated to the BSAD.
The services included in the BSAD are a priori the following: STOR, fast reserve, BM Start-
up. [13] NGC submits these data for each hour, the day before at 17:00 PM.
- 22 -
The imbalance settlement is based on two prices:
� The main price, paid for the imbalance which are in the same direction as the
Transmission Operator (ie the overall system): the referred balance responsible
contributes to the system deviation
� The reverse price, paid for the imbalance which are in the opposite direction to
the Transmission Operator : the referred balance responsible counters to the
system deviation
Before 2006, the SBP and the SSP were respectively equal to the average price of the
accepted offers and bids.
Since 2006, the calculation depends on the position of the system, and is more
penalizing. Indeed, the main price is calculated based on the marginal 500 MWh of accepted
offers and bids. For example, if the system is short, SBP is calculated as the volume weighted
average of 500 MWh of the most expensive offers which have been used.
The defined volume (500 MWh here) is called the Price Average Reference Volume.
Price
(€/MWh)
Price
(€/MWh)
Volume of
accepted
Offers
Volume of
accepted
Offers
marginal
500 MWhVolume
weighted
average
price
Volume
weighted
average
price
Figure 7: Main Price calculation in case of a short system
The reverse price is based on the volume weighted average of the purchase and sale
done before the Gate Closure. It is the Market Index Data (MID), which is the price of the
wholesale electricity in the short term market, related to the referred half hour. [6]
Finally, this system with two energy imbalance prices is an incentive for a better
forecast of the production and demand. Indeed, a producer with a deviation from its planning
can cannot make a benefit, but, on the contrary, often looses money.
Balance Resp.
ImbalanceSystem
positionlong
long
short
short
MID (SBP)
(main price)
MID (SSP)
(main price)
SSP
(reverse price)
SBP
(reverse price)
Table 2: Imbalance settlement prices
- 23 -
II.C. Balancing mechanism in Germany
Germany is divided four zones, each one controlled by a different TSO: RWE, EnBW,
E-ON and Vattenfall Europe Transmission6.
The TSOs are required to maintain the permanent balance between production and demand,
and provide balancing energy to the balancing groups.
Verband der Netzbetreiber (VDN) is an independent association, founded in 2001, which
represents the four TSOs. The Bundesnetzegentur (Federal Network Agency) is the common
regulator for the German networks, and in particular the electricity network. [18]
Concerning the frequency regulation, the three main kinds of services are conformed
to the definition of the UCTE:
- Primärregelung, which corresponds to the primary control
- Sekundärregelung, which corresponds to the secondary control
- Minutenreserve, which corresponds to a fast tertiary reserve
As a part of the UCTE Network, Germany must keep the frequency level at 50 ± 0.2 Hz.
Since 2001, the three kinds of services are procured through a competitive bidding,
each service having its own market. All the balancing services are therefore commercialised
and remunerated.[9] These markets appeared gradually: in February 2001 for RWE, in August
2001 for E-ON, in August 2002 for EnBW and in September 2002 for Vattenfall Europe
Transmission.
On these markets, about 7 000 MW are contracted every day for upwards regulation,
of which 3 000 MW of minute reserve, and about 5 500 MW for downwards regulation, of
which 2 000 MW of minute reserve.
II.C.1 Description of the services
II.C.1.1. Primary control
This service in provided by all synchronously connected power system inside the
UCTE area. It is automatic, must be delivered within 30 seconds, and for an incident of less
than 15 minutes.
II.C.1.2. Secondary control
This service is provided by the concerned TSO. It is semi-automatic, and must be
delivered within 5 minutes, and for an incident which lasts between 30 seconds and 15
minutes.
II.C.1.3. Tertiary control: Minutenreserve
This service reconstitutes the secondary reserves and acts as a complement to the
secondary control. The TSO uses this kind of reserve in case of a large imbalance between
production and demand. The service is manually activated by the affected TSO; it must be
provided within 15 minutes, and for an incident which lasts up to an hour. The duration of the
settlement period in Germany, which is fifteen minutes, gives a special role to this kind of
6 RWE Transportnetz Strom GmbHNET, EnBW Transportnetze AG, EON Netz GmtH, Vattenfall Europe
Transmission GmbH
- 24 -
reserve. In case the TSO is not able to meet its needs in minute reserve, it must set up
transactions with other TSOs to face the problem.
II.C.1.4. Time frame of control energy
According to the German market rules, the TSOs are responsible for supplying reserve
energy during the first hour of the incident. Then it becomes the affected balance responsible
who is in charge of the compensation via bilateral contracts.[15,21]
Figure 8: Timescales of the different kinds of reserve [2]
This last information might refer to another kind of reserve, the Stundenreserve, which
is provided within an hour. This slower reserve depends upon the balance responsible, and is a
way for the TSO to constitute a operating margin.[1]
In case of a major problem, the Stundenreserve is completed by the Notereserve, which is a
special reserve contracted by the TSO on the market. If there is an emergency, the balance
responsible can ask the TSO for this reserve.
Finally, the Kurtzeitreserve (primary, secondary and minute reserve) are the
responsibility of the TSOs, whereas the Stundenreserve and the Noterserve depends upon the
balance responsible.
The different reserves are summarized in the table hereafter:
Type of reserve Response time Who is responsible for the
reserve ?
Primary control ≤ 30 secondes All the TSO (in the UCTE)
Secondary control ≤ 5 minutes The TSO of the affected zone
Minutenreserve ≤ 15 minutes The TSO of the affected zone
Stundenreserve ≤ 1 heure The balance responsible of the
affected balancing group
Tertiary control
Notreserve variable The balance responsible of the
affected balancing group
Table 3: The different kinds of reserve in Germany
- 25 -
II.C.2 The Balancing mechanism and the “market” aspect
Procurement of primary, secondary and minute reserve is done through a tendering
process. Therefore, we can speak of a balancing “market”. Each TSOs has its owns “reserve
markets”. Primary and secondary reserves are based on a semi-annual tender, whereas minute
reserve is based on a daily tender. Recently, a common platform has been set up for the
minute reserve, so that the four TSOs can organise a common tender [16].
Many actors participate to the tender, even small ones via pooling systems. Due to an
important cooperation between the TSOs, a supplier can provide control power to any zone;
since 2004, even the suppliers from the Austrian control zones TWAG and VKW can
participate in the minute reserve market.
A pre-qualification process is performed by the TSOs, based on technical and dynamical
criteria.
Since 2005, several changes occurred in order to improve the cooperation among the
TSOs and decrease the need of balancing energy. Among them, the most important are the
creation of a common regulator and a common tender for minute reserve. A common tender
for primary and secondary reserve should be organized soon.
II.C.2.1. How the market works
II.C.2.1.a. The different timescales
The time frame of the market, available for all the zones, is described in the following picture:
Time
Primary reserve market
Secondary reserve market
Minute reserve
market
Spot market Programs submission
Programs
rectifications
Wind reserve market
D-1 D
Forward market Intra-day market
Every
6 months
Every
month
10:00
12:00 14:30
15:30
Figure 9: The different timescales of the German market
The offered minute reserve should be submitted by 10:00 AM the day before, Two
hours before the gate closure of the spot market. At 11:00 the selection of the reserve minute
offers is published. The balancing group managers submit their programs to the TSO at 2:30
PM the day before. Concerning the intra-day modifications of the generation program, they
can happen for each settlement period (15 minutes), with an advance warning 45 minutes
before.
- 26 -
II.C.2.1.b. Format of the bids and offers
� Primary and Secondary reserves
All the plants with a capacity of 100 MW or more must participate to the primary control,
but they are paid for that.
The offers are available for six months and the providers give the following information:
- Offered capacity (MW), which can be used for upwards or downwards regulation
- Price for the capacity (€/MW)
- The energy is not paid
Concerning the secondary control, the offers for upwards regulations and the bids for
downwards regulations are separated. The participation is not compulsory. The following
information is given:
- Upwards or downwards regulation
- Offered capacity (MW)
- Price for the capacity (€/MW)
- Price for the energy actually used (€/MWh)
� Minute reserve
The tender is common to the four TSOs, which is a progress towards the integration of the
four zones. However, the qualification process is done with the TSO of the zone where the
offer is submitted.
The format of the offers and bids is the following:
- Upwards or downwards regulation
- Duration of the offer: the day is divided into six periods of four consecutive hours
(starting from midnight). Therefore, an offer must be available for at least one block of
four hours.
- Offered capacity (MW), it should be at least 15 MW
- Price for the capacity (€/MW)
- Price for the energy actually used (€/MWh)
- The zone where the unit is located (Anschlussregelzone)
Example:
Product Name
Capacity
Price [€/MW]
Energy
Price [€/MWh]
Offered
Capacity [MW] Zone
NEG_00_04 55,400 0,000 50 EON
Figure 10: Example of bid data [3]
The offers seem to be explicit regarding the amount of MW given; it is interesting to
notice that the capacity is remunerated, for all services.
Before the changes occurred in 2006 , the minimal quantity to offer was 30 MW; the
decreasing of this amount allows a better competition, since more offers are now submitted.
- 27 -
II.C.2.1.c. Bids and offers selection
Once the technical and dynamical criteria respected, the selection is done based on
economical criteria.
Regarding the primary control, the offers are ordered by ascending capacity price, and
a forecast of the need defines the last accepted offer.
Regarding the secondary control, the merit order is done with the same method, but
when two capacity prices are equal, the energy price is considered. The orders are then sorted
out by ascending energy prices for upwards regulation, and descending energy prices for
downwards regulation. [19, 22]
Regarding the minute reserve, the TSOs select a certain quantity of offers and bids
after their submission, the day before. In order to guarantee the system security, a minimal
amount is required in each zone. This amount is called Kernanteile (core portion); it
represents between 1 and 15% of the total contracted amount, and is not constant. It does not
seem to affect the competition between the offers from different zones.
The merit order is done the same way as for secondary reserve.
This merit order for tertiary reserves, listing the offers and bids, and the result of the selection
is published on Internet:
Product Name Capacity
Price[€/MW]
Energy
Price [€/MWh]
Offered
Capacity [MW] Zone
Acceptance
[ja/nein]
NEG_12_16 0,670 5,000 20 RWE ja
NEG_12_16 0,672 5,000 15 RWE ja
NEG_12_16 0,674 5,000 15 RWE ja
… … … … … …
NEG_12_16 0,770 2,000 15 EON ja
NEG_12_16 0,780 0,000 15 Vattenfall ja
NEG_12_16 0,780 0,000 50 ENBW ja
NEG_12_16 0,780 0,000 46 RWE ja
NEG_12_16 0,790 0,000 15 Vattenfall ja
NEG_12_16 0,790 0,000 15 Vattenfall ja
NEG_12_16 0,790 0,000 50 ENBW ja
NEG_12_16 0,800 0,000 100 ENBW ja
NEG_12_16 0,800 0,000 15 Vattenfall ja
NEG_12_16 0,800 2,000 15 EON ja
NEG_12_16 0,810 0,000 15 Vattenfall ja
NEG_12_16 0,810 0,000 50 ENBW ja
NEG_12_16 0,810 0,000 15 Vattenfall ja
NEG_12_16 0,820 0,000 50 ENBW ja
NEG_12_16 0,820 0,000 15 Vattenfall nein
NEG_12_16 0,820 0,000 15 Vattenfall nein
Figure 11: Extract of tender results for downwards regulation for tertiary reserves
(10.07.2007, 12:00-16:00) [16]
- 28 -
Product Name
Capacity
Price [€/MW]
Energy
Price [€/MWh]
Offered
Energy [MW] Zone
Acceptance
[ja/nein]
POS_00_04 1,136 200,000 15 RWE ja
POS_00_04 1,137 200,000 15 RWE ja
POS_00_04 1,137 493,201 24 EON ja
POS_00_04 1,138 200,000 15 RWE nein
POS_00_04 1,139 200,000 15 RWE nein
Figure 12:Extract of tender results for upwards regulation for tertiary reserves
(10.07.2007, 00:00-4:00) [16]
Concerning the utilisation of the orders, once the selection done, it is based on the
energy prices and dynamic parameters. It is important to notice that the selected orders are
paid for the capacity, even if they are not activated afterwards.
The quantities of energy from the minute reserve orders which have been activated and
the imbalances for each settlement period are published on each TSO’s website. As described
in the Appendix 1, it is surprising to see that very few minute reserve orders are actually
activated, even if the imbalance is important. In fact, it seems to be the secondary reserve that
is used instead, and very rarely some minute reserve.
Nevertheless, the amount of contracted minute reserve each day (which is remunerated
by the TSO) is quite important (about 3000 MW of offers, 2000 MW of bids). The reason for
the choice of this quantity remains a bit blurry, but it might be due to some imposed rules (in
the UCTE maybe).
II.C.2.1.d. Remuneration
The system is a pay-as-bid system for the three kinds of reserve. [19] We can notice
than before 2005, E-ON was the only TSO who paid the orders at the marginal price.
Specificity here is that the capacity is always paid for by the TSO. These costs are then
integrated to the network tariff [16]. However, the energy costs are integrated in the
imbalance settlement.
II.C.2.2. Imbalance settlement
A balancing perimeter (Bilanzkreis) contains several points of injection and
withdrawal of energy, and is under the responsibility of a manager who is balance responsible
(Bilanzkreisverantwortlichen, BkV). Inside a perimeter, the different deviations can
compensate each other; during each settlement period, the balancing perimeter manager is
responsible for the balance between production and demand. The balancing perimeters are
confined in a single zone, in order to be able to settle the imbalance TSO by TSO. If a
balancing group is present on several zones, it must be divided. In its zone, the TSO
compensate the deviation from the forecast by activating the reserves; afterwards, the balance
responsible must pay for the regulation of energy done by the TSO.
For each balancing perimeter and each ¼ hour, the imbalance is calculated. Here, there
is one single imbalance, regrouping producers and consumers [20]:
∑∑ ∑∑ −+−= ExportsImportDemandSupplyImbalance
- 29 -
The imbalance settlement is based on a single price system: the imbalance price is the
same, regardless the position of the balance responsible compared to the system position
[15,16].
The prices are calculated for each settlement period of ¼ hour. The price is the volume
weighted average cost of the secondary and minute reserve which has been actually used
(only the energy, since the cost due to the capacity payment are integrated to the network
tariffs). The price is the same for positive and negative imbalances.
The balance responsibles who are in a long position get paid by the TSO (they sell the
surplus of energy); on the contrary, the ones who are in a short position pay the TSO (they
buy energy to cover their deficit).
II.C.2.3. The particular case of wind power
Regarding the fluctuating nature of this production, the balancing costs are quite high.
The additional costs due to balancing is estimated at 7 €/MWh. In 2006, the total production
of energy from the wind was around 30 millions of MWh, which amounts to a balancing cost
of 210 millions euros (while the overall cost of the balancing mechanism is about 800
millions euros) [23,24].
Since the new regulation of 2004 concerning renewable energy, wind power is
grouped in the same balancing perimeter, called EEG-Bilanzkreis, and the four TSOs are
balance responsible for this special perimeter. Therefore, a compensation effect is allowed
between the productions of the different zones, and the balancing costs are spread among the
four TSOs. There is a specific reserve for wind power, called Windreserve, which is provided
through a monthly tendering process. [21]
Concerning the imbalance settlement, the balancing costs of wind power are
incorporated to the network tariffs of the four TSOs, on a pro-rata basis of the wind power
capacity installed in their zone. Therefore, there is no incentive to reduce the imbalance
caused by wind power, since the costs are comprised in the network tariffs.
If a wider balancing perimeter regrouping all the wind power of the UCTE was
created, this could reduce the costs, thanks to the variation of winds depending on the location
and the compensation effect between different deviations.
- 30 -
II.D. Conclusions
In this part, we will try to point out the main likenesses and differences of the two
markets. We can see that, just from the study of two countries, a lot of changes are necessary
in order to improve the harmonisation and coordination between different balancing
mechanisms. The table hereafter summarizes the main points of the study:
Great-Britain Germany One TSO: National Grid Company Four TSOs: EnBW, RWE, E-ON, Vattenfall.
Each one is responsible for its own zone
- Many balancing services
- The limit between system services and
balancing market is blurred
- Three types of reserve services,
according to the definition of the
UCTE
- Secondary and tertiary power in the
balancing market
- Settlement period of ½ hour
- Gate closure for the submission of
bids and offers one hour before every
settlement period
- Settlement period of ¼ hour
- Gate closure at 10:00 on the day-ahead
spot market
Format of the Offers & Bids inside the
Balancing Market:
- Pairs
- Energy Price only (£/MWh)
- Chosen duration
Format of the Offers & Bids (for secondary
and minute reserve):
- Separation Upwards/Downwards
- Capacity Price (€/MW)
- Energy Price (€/MWh)
- Standard duration (6 months for
secondary reserve, 4 hours for minute
reserve)
Offers & Bids Acceptance:
- Selection upon economical (energy
price) and technical criteria
- The TSO chooses the quantity
- Remuneration of the used energy
only7
- Pay-as-Bid system
Offers & Bids Acceptance:
- Selection upon economical (capacity
price) and technical criteria
- The TSO must accept the whole offer
in capacity, and choose the quantity in
energy
- Remuneration of the capacity and the
used energy
- Pay-as-Bid system
For each balancing perimeter, two energy
accounts:
- One for the consumption
- One for the generation
For each balancing perimeter, one global
imbalance is calculated.
For each settlement period, two prices are
calculated:
- The main price
- The reverse price
- Income for the TSO
For each settlement period, one price is
calculated:
- Volume weighted average cost of the
secondary and minute reserve actually
used
- No income for the TSO
7 Except for specific reserve services which could be contracted inside the Balancing Market
- 31 -
Table 4: Main aspects of the British and German Balancing Markets
In conclusion, the orders inside the Balancing Market seem to be explicit in their
submission; however in Great-Britain, the orders are more implicit in their acceptance when
there is no remuneration of the capacity.
The imbalance settlement system is less penalizing in Germany, since the actors
cannot make a loss with their imbalances. Therefore, compare to Great-Britain, there are less
incentives to minimize the deviations from the contractual position and to make better
forecasts. Besides, the German market has a special system for wind power.
From this study, we could roughly stress some important points which would need to be more
harmonised:
- The type of services included in the balancing mechanism, and the limit between
system services and the balancing mechanism:
- The format of the submitted offers and bids, regarding the prices given (for capacity,
energy…) and of course regarding the quantity given (explicit/implicit offer)
- The criteria on which the TSO accepts the offers and bids, and the format of the
acceptance (whether the TSO must accept the whole offer, or if it can accept it
partially)
- The remuneration: it can be at the bid price or at the marginal clearing price, it can pay
the capacity and/or the energy
- The timescales of the market, particularly the gate closure time and the settlement
period duration
- The imbalance settlement: it can be based on a dual price or a single price system
- The definition of the imbalance for a balance responsible (potential separation
between consumers and suppliers, in order to be more penalizing)
- The specific case of wind power generation or other fluctuating production
Furthermore, if the trend is to harmonise the balancing markets and allow a better
competition between actors, there would be more exchange of balancing energy on the cross-
border transmission lines between the European countries.
Therefore, congestion management methods should improve the integration of the
different markets and allow an optimal use of the cross-border transmission capacities.
Several important changes concerning congestion management occurred lately, but mainly
concerning the day-ahead cross border capacity allocation mechanisms. But the new
mechanisms settled will probably be developed and applied in the intra-day market as well.
- 32 -
Chapter III.
Congestion Management: The Market Coupling
Mechanism
III.A. Background
At the present time, the European Commission supports every market mechanism
which increases the level of integration of the existing electricity markets in Europe.
Bottlenecks on the interconnections are the main hindrance to the integration of the different
markets. Therefore, the allocation of cross border capacity must be done in a fair and non-
discriminatory manner, using market-based mechanisms which will improve the global
economical efficiency.
Currently, there are two main kinds of market-based mechanisms:
• Explicit auctions: the product is a right to use a certain amount of capacity on a
transmission line. A tendering process is organized by the two concerned
TSOs, in order to allocate the commercial capacity. Therefore, the capacities
are allocated using market based mechanism, but their use is not optimized.
• Implicit auctions: actors submit offers and bids for electrical energy on the
power exchanges, and a special market mechanism determines the allocation
which will lead to the most efficient situation of power exchanges between the
market zones. Nowadays, the two existing implicit auctioning mechanisms are
the market splitting and the market coupling; we will explain them further on.
In the picture below, the different existing mechanisms in Europe are represented:
Explicit Auctions
Market Splitting
Market Coupling
Other Mechanisms
Outside the EUFr
UKIE
ESPT IT
CH
Be
NL
DK
(W)
De
AT
Cz
PL
SK
HR
SL
Gr
No
SeFi
DK(E)
Figure 13 : The different congestion management methods in Europe [26]
- 33 -
In 2003, the European Commission laid down preliminary principles for the
implementation of cross border congestion management methods. Through the given
guidelines, a regional approach has been taken in order to allow faster progress, but the final
goal still remains the realisation of an Internal Electricity Market in Europe. Therefore,
Electricity Regional Initiatives (ERI) has been launched in 2006 but the European regulators
Group for Electricity and Gas.
The aim of the project is to focus on the Central West Region8, consisting of the
Netherlands, Belgium, France, Luxembourg and Germany. On November 21st 2006, an
implicit auctioning process to handle day-ahead cross border capacity allocation was
implemented between the Netherlands, Belgium and France, which is the so-called “Trilateral
Market Coupling9”. It complements the existing process of explicit auctioning to handle year-
ahead and month ahead cross border capacity allocation.
Market Coupling aims at optimising the use of the D-1 available transmission capacity
on cross-border lines, by a coupling between the three Power Exchanges (APX10
, Belpex11
and Powernext12
), in cooperation with the relevant TSOs TenneT, Elia and RTE.
The TLC enables different power exchanges to be coupled in the day-ahead market, without
any change to their market structure and rules. The three power exchanges are still legally
separated markets, the coupling is done without a common order book nor a common clearing
for example.
Therefore, the Market Coupling mechanism is to be extended in order to integrate more
markets. The next step is the extension of Market Coupling to Germany and Luxembourg in
an Open Market Coupling, and then to Scandinavian countries.
III.B. Market Coupling: Analysis of the mechanism principles
Market coupling is both an implicit cross-border capacity allocation mechanism and a
mechanism for matching orders. The aim is to improve the economic surplus by a better use
of the interconnections: cheaper generation in a country may be used to cover more valuable
demand in another country. Indeed, by coupling the power exchanges, the highest bids and the
lowest offers of the coupled markets are matched, without considering the area it belongs to.
Nevertheless, the matching depends on the transmission capacity between the coupled hubs.
The daily cross-border transmission capacity
The mechanism involves handling simultaneously their supply and demand curves, but
there is no common order book. Therefore, it does not require any significant change in the
structure of the power exchanges, except the harmonisation of the day-ahead gate closure
time. The three power exchanges still exist as legally separate markets. [25]
Market Coupling allows a wider market to be created, and a more efficient use of the daily
capacity of the interconnections between the different networks, compared to explicit auctions
mechanisms.
This method for integrating electricity markets in several areas can be considered as an
alternative to another method already established in the Nordic area, the Market Splitting.
8 Also Called CWE
9 Also called TLC
10 Dutch energy exchange
11 Belgian energy exchange
12 French energy exchange
- 34 -
Market splitting is carried out by the market place operator, the NordPool, based on an
agreement between the different TSOs. As market coupling, market splitting is a system wide
optimisation, in order to make a better use of the cross-border transmission lines. The actors
notify their bids and offers in the same market place, specifying the concerned area. The
exchange capacity is integrated as a part of the day-ahead spot price calculation. The main
principle is the following: there is one single market which can be split into separated virtual
markets (with different prices) when a congestion occurs on a cross-border transmission line.
Using the same hypothesis, market coupling and market splitting should lead to the
same results. However, it is interesting to see the differences between the algorithm used and
the reason why market splitting is not used in Central Western Europe.
Indeed, the market coupling consist of coupling N markets, which results in a unique
virtual market in case of no congestions, while market splitting starts with one single market,
which is split in several different markets in case of congestions. Market coupling allows an
integration of several markets, even if they have different designs.
The main difference is that market coupling is organized with two or more power
exchanges. Therefore, according to the decentralized approach in Central Western Europe,
market coupling is more suitable since each area has its own market operator. Moreover,
market splitting remains hard to carry out in Europe, since there are too many
interconnections between the different TSOs, which means that congestions observed on a
line might not come from bilateral exchanges
Market coupling let the national markets stay independent, without sharing their bids and
offers, so it might be easier to extend to other countries.
III.B.1 Some basic principles
We will first explain the basic principles of coupling markets and how it is applied to the
Netherlands, France and Belgium.
Coupling markets involves handling simultaneously their supply and demand curves, in
order to make the highest bid (purchase) match with the lowest offer (sale).
The market coupling mechanism relies on the principles that the market with the lowest price
exports to the market with the highest price.
Let us consider two markets A and B, linked with a cross-border transmission line. If the
isolated market price in A is lower than the one in B, the market A exports to the market B.
We can reach two situations:
- The two prices become equal, if the capacity of the line is large enough
- A congestion occurs on the line, and the two prices remains different.
III.B.1.1. Aggregated supply and demand curves
On the day-ahead spot market, aggregated supply and demand curves are submitted at
the power exchange for each hour of the following day. The price of an isolated market is
given by the intersection of these two curves.
The energy transaction due to the coupling between two markets has the following
impact on the supply and demand curves:
- 35 -
Price
(€/MWh)
Price
(€/MWh)
Volume (MWh) Volume (MWh)
Market A Market B
isolated
AP
isolated
BP
*
AP*
BP
Purchase
Sale
Purchase
Sale
Figure 14: Coupling of two markets when there is no congestion
As it is shown in the picture above, when a market exports a certain quantity of
energy, it is equivalent to translate its demand curve to the right (add the value of the export).
Similarly, If a market imports a certain quantity of energy, it is equivalent to translate its
supply curve to the right (add the value of the import). The new market price is given by the
intersection of the aggregated curves, shifted with respect to the export and import. In the case
represented in the picture, there is no congestion on the line between A and B, so the two
markets have the same final price ( **
BA PP = ).
When the transmission capacity is not sufficient to reach two equal prices, the exchange
between the two markets will be equal to this transmission capacity:
Price
(€/MWh)
Price
(€/MWh)
Volume (MWh) Volume (MWh)
Market A Market B
isolated
AP
isolated
BP
*
AP *
BP
Purchase
Sale
Purchase
Sale
P∆
Figure 15: Coupling of two markets when there is a congestion
Transmission constraints limit the necessary cross-border flow. There is no complete price
convergence, but the differential between the two prices decreases.
III.B.1.2. Net exportation curves
Another concept which will be used in the algorithm to describe a market is the Net
Exportation Curve (NEC), which is also submitted on the day-ahead spot market, for each
hour of the following day.
The NEC represent the price at which the market is ready to export or to import: it represents
the net position of the market as a function of the marginal cost price. The NEC is calculated
- 36 -
by determining the volume differences between the hourly offers (supply curve) and the
hourly bids (demand curve). Therefore, it contains less information than the supply and
demand curves.
Price
(€/MWh)
Volume (MWh)
AP
Purchase
Sale
Import (MWh) Export (MWh)
Price
(€/MWh)
NEC
Figure 16: Construction of the Net Exportation Curve
If the considered market exports, the NEC will be shifted to the left; if the market imports, the
NEC will be shifted to the right. The marginal price of the isolated market is given by the
intersection of the NEC and the price axis (it is the price when the net position is equal to
zero).
Depending on the market, two types of NEC are possible: either a stepwise curve or a
linear curve. In the first type of market, the offers and bids are defined with price-quantity
range pairs (for each price, a range of quantity is defined); in the second type of market, offers
and bids are defined with price-quantity couples, and the NEC is obtained by joining the
segments.
In the TLC algorithm, there is one linear NEC, to represent the French market Powernext,
and two stepwise NECs, to represent the Dutch market APX and the Belgian market Belpex.
[28]
Coupling two markets is done easily using the NECs. The market with the lowest isolated
marginal price exports to the market with the market with the highest isolated marginal price
The export of one market is equal to the import of the other, thus the equilibrium is found at
the intersection of the net exporting curve of a market, and the net importing curve of the
other (the inverted NEC). [27]
Price
(€/MWh)
Import (MWh) Export (MWh)
Market A
Market B
Price
(€/MWh)
Import (MWh) Export (MWh)
Market A
Market B
**
BA PP = *
AP
*
BP
BAATCQ→
=*
Uncongested Case Congested Case
*Q
Figure 17: Bilateral Coupling using the NECs
- 37 -
As we can see on the example above, the representations with the NEC make the
coupling quite easy to realize. If the ATC is large enough, the equilibrium and net position is
given by the intersection of the two curves. However, if congestion occurs, the energy
transaction is equal to the ATC; the net positions are equal to the ATC and the price of a
market is given by the point on its NEC corresponding to the ATC.
III.B.1.3. Block offers
The NEC obtained when considering only simple orders is called a simple NEC. It is a
particular case; the real NEC will also consider the selected block orders. The selected block
orders are represented by price-inelastic hourly divisible orders.
When considering block orders, the supply demand and supply curves shift to the
right. The difference between the shift of the supply curve and the shift of the demand curve
(the net colume) is called the Net Block Volume (NBV). For each hour, the NEC is a
horizontal translation of the block-free NEC by the NBV[25]. We will see afterwards how
these NEC are constructed.
III.B.2 Trilateral Market Coupling: how does it work?
III.B.2.1. Overview of the mechanism as it is carried out today
III.B.2.1.a. Data used as inputs
� In the trilateral market coupling, the cross-border transmission capacity is represented
by the Available Transmission Capacity. The ATC represent the commercial capacity
for energy transactions between two markets, taking into account the yearly and
monthly explicit auctions and their nominations. The definition and calculation of the
ATC is detailed in the Appendix 2. The ATCs are submitted by the TSOs, in each
market.
� For each market and each hour of the following day, the hourly orders are collected in
a simple NEC.
� The block orders are submitted for each market. Several NECs may be constructed for
a settlement period, considering all the possible set of accepted block offers.
III.B.2.1.b. The overall process
The Trilateral market coupling process adopts a decentralised technical approach. The
three power exchanges and the three TSOs act separately, and the data submitted are not put
in common.
Using the NECs and the ATC, the algorithm determines the price of each market, and
its net position (which corresponds to a point on the NEC). The net position of a market
represents commercial transactions, and not physical power flows. We will see further on how
to make the link between those transactions and the real flows on the line.
In each power exchange, block orders are submitted to a block selector, and divisible
orders to a NEC creator. A NEC is build on the basis of n hypothetical set of accepted block
orders (which is called Winning Subset).
- 38 -
Then the resulting set of NEC is used to determine the price and the net position of
each market. The set of prices obtained might not be compatible with the assumed Winning
Subset, thus the winning subset is updated and the prices calculated again. These calculations
are iterated until the looping process reaches a stable solution.
Consequently, because of the block offers, the algorithm involves iterations between
two modules [25]:
- The block selector of each power exchange, in charge of the decentralized
selection of block offers (returns the NBV)
- The coordination module, in charge of the centralized calculation of the prices and
net positions, using the NECs and the ATCs
The following picture summarizes the different actors and modules of the algorithm.
Figure 18: Overview of different steps in the Market Coupling process [25]
Once a convergence of the solutions is observed, the coordination module returns a
price and a net position to each power exchange, which then uses these data to determine the
schedule of its participant and the portfolio allocations according to its own rules.
- 39 -
III.B.2.2. Algorithm of the coordination module: Coupling three markets
The general idea of the algorithm is to realize successively two bilateral coupling.
The first step is order the three markets regarding to their isolated marginal cost price.
Let us assume that the market A has the lowest isolated price, the market C the highest. Thus,
the market A is going to export to the market C (potentially via the market B if market B is
Belgium), which will raise the price in market A and reduce the price in market C. Two
situations can then occur:
- If a market uses all its ATC, it becomes isolated and cannot export or import
anymore. Then a bilateral coupling takes place between the two other markets
- The price of market A or C reaches the price of market B, and we aggregate the
two markets together (the two NECs are added together). Then a bilateral market
coupling takes place between the market resulting from the merging and the other
one.
We consider the following example, where we can observe an aggregation of France
and Belgium. Here, we do not consider any transmission limitation.
Regarding the price of the isolated markets, the two markets which get the closest price will
merge together. France and Belgium are aggregated, and a common NEC is constructed (by
adding the two NECs of the separated markets).
Price
(€/MWh)
Net Export (MWh)Net Export (MWh)Net Export (MWh)
Price
(€/MWh)
Price
(€/MWh)
10
20
30
40
10
20
30
40
Belgium
Netherlands
10
20
30
40
Price
(€/MWh)
Net Export (MWh)
France + Belgium
BeP
NLP
10
20
30
40
EquP
Figure 19: First step of the TLC
Then a coupling takes place between the exporting market { }BelgiumFrance + and the
importing Dutch market.
- 40 -
10
20
30
40
Net Export (MWh)
Price
(€/MWh)
FrBeNL PPP ==
Import NL
Fr+BeNL
Figure 20: Second step of the TLC, non-congested case
Without limitation on ATC, the three markets get the same price, which is given by
the intersection of the two curves.
The import made by the Netherlands and the common price can be read on the
intersection of its inverted NEC and the aggregated NEC of France and Belgium.
Since we have the market price, we can then read on the individual NEC of France and
Belgium their net positions.
Price
(€/MWh)
Net Export (MWh)Net Export (MWh)
Price
(€/MWh)
10
20
30
40
10
20
30
40
France Belgium
Export Fr Export Be
FrBeNL PPP ==
Figure 21: Second step of the TLC, non-congested case
The situation may be more complicated when there are transmission limitations. We
will now consider the three possible scenarios concerning ATC limitations, using the same
example as before.
- 41 -
� Scenario 1: Constraint on NlBeATC →
In case the ATC between Belgium and the Netherlands limit the importation, the Dutch
market becomes isolated, with a higher price. Since there is no congestion between France
and Belgium, both markets are merged and get the same price.
The import made by the Dutch market is equal to the NlBeATC → ; the net position of the French
and Belgian market can be read on their respective NECs.
10
20
30
40
Net Export (MWh)
Price
(€/MWh)Fr+BeNL
NlBeATC→
FrBe PP =
NLP
Figure 22: TLC results, congested case
Here it is interesting to notice the fact that the three considered countries are ligned up,
which will sometimes simplify the problems due to ATC limitations. Indeed, once there is a
congestion, one market gets isolated and a bilateral coupling takes place between the two
other one.
For example, in this scenario, if the ATC between Belgium and the Netherlands is not
sufficient, the Netherlands will be isolated. This is due to the absence of interconnection
between the Netherlands and France; otherwise we would have to consider an import from
France as well.
� Scenario 2: Constraint on BeFrATC →
The ATC between France and Belgium limits the export, and make its price remains at a
lower level. Belgium continues to export, and without other restriction the Belgian and Dutch
prices become equal.
10
20
30
40
Net Export (MWh)
Price
(€/MWh)
NEC Fr+Be
NL
BeFrATC →
FrP
BeNL PP =
NEC Be
Figure 23: TLC results, congested case
- 42 -
� Scenario 3: Constraint on NlBeATC → and BeFrATC →
When all ATCs are limited, we get three different prices.
10
20
30
40
Net Export (MWh)
Price
(€/MWh)
NEC Fr+Be
NL
BeFrATC→
FrPBeP
NEC Be
NlBeATC→
NLP
Figure 24: TLC results, congested case
Finally, the algorithm applied in the coordination module of the TLC appeared quite
clearly through the example above. Using the NECs of the three isolated markets and the
ATCs between them, one can calculate the final prices and the net position of the countries.
One important aspect in the TLC algorithm is that the input data are NECs and not supply and
demand curve. This is more a strategic way for the local power exchanges of giving less
information to the coordination module.
The first aim of this study is to establish a model of the mechanism (except the block
selector module).
- 43 -
III.C. Simulation of Market Coupling
III.C.1 Simulation on three markets using a sequential algorithm
The aim here is to simulate the coupling of three markets, all interconnected. It is important to
notice that the transmission capacity and the transaction are commercial; there is no
calculation of physical power flows here.
The first simulation has been implemented with Excel and its language Visual Basic
for Application. The aim of this small simulation is to develop a simple market coupling
sequential algorithm, working on three countries (M1, M2, M3), all interconnected with one
another. The simulation is done with theoretical data.
M1
M2M3
Figure 25: System studied
This model can be used to simulate the functioning of the actual “Trilateral Market
Coupling”, which is a particular case of a coupling of three markets. Indeed, we shall assume
that M1 stands for France, M2 for Belgium and M3 for the Netherlands. The Available
Transfer Capacity of the commercial line between M1 and M3 is then set to zero.
As we have already noticed before, the algorithm is slightly different in case of three
countries all interconnected and not ordered on a line. Thereby, the method would have to be
changed compared to the mechanism explained before.
III.C.1.1. Inputs and Outputs of the simulation
Inputs (available for the considered hour):
- Available Transfer Capacity (ATC) for each line, in each direction
- Net Exportation Curves for each market, without considering any block offer. Indeed,
we work here with single offers only.
Outputs (available for the considered hour):
- Accepted offers and bids in each market
- Use of the commercial power capacity on each line
- Market price for each market
Optionally, the economic surplus is computed, also called overall Social, provided we have
the global supply and demand curves on each market. In that case, it is not necessary to have
both NECs and supply and demand curves as the NECs can be deduced from the curves.
- 44 -
III.C.1.2. Prices calculation
The marginal price of each market is calculated as the intersection of the Net Export curve of
the considered market with the price axis (price of the market when the net position is equal to
zero)13
.
In the program, the prices are calculated at each step of the algorithm on every market, using
the NEC and taking into account the exchanges that take place with the neighbouring markets:
- When the market M exports 1 MWh, the NEC is translated to the left (1 MWh is
subtracted from the values of the NEC), and therefore the market price increases
- When the market M imports 1 MWh, the NEC is translated to the right (1 MWh is
added to the values of the NEC), and therefore the market price decreases.
Price
(€/MWh)
Price
(€/MWh)
Net Export (MWh)Net Export (MWh)
Effect of an import Effect of an export
Figure 26: Effect of an import or an export on the NEC
III.C.1.3. Algorithm principles
The Market Coupling mechanism relies on the following principle between two markets:
the market with the lowest price shall export to the market with the highest price. This is
equivalent to make the highest bid match with the lowest offer, regardless the market where
the order is submitted.
This is done using loops. Indeed, when a market A exports to a market B, the condition that
must be observed to increment the amount of exported power from A to B with 1 more MW is
the following:
While Price(A)<Price(B) and QAB<QAB_Max
(Where QAB is the transaction on the line between A and B).
We implement this principle in an algorithm, which treats the problem by differentiating all
the possible cases. Therefore, the method is sequential.
13
This equilibrium can also be deduced as the intersection of supply and demand curves when the whole
supply/demande curves are given as an input data
- 45 -
III.C.1.4. Steps of the algorithm
III.C.1.4.a. Calculation of the isolated market prices: Identification of the
export zone and the import zone
The three markets M1, M2 and M3 are sorted out by price, from the lowest (market A) to the
highest price (market C).
Then we distinguish two base cases:
� Base case 1:
BCAB PPPP −≤− , which means that the markets A and B export to the market C
� Base case 2:
ABBC PPPP −<− , which means that the markets B and C import from the market A.
The two markets with the closest prices will be treated together. In the base case 1,
markets A and B are the exporting area, and market C the importing one. In case 2, market A
is the exporting area, and markets B and C the importing area.
Here it is interesting to notice that the two markets with the closest prices are not merged
as they were in the TLC algorithm described before, which means that we do not exactly
aggregate their NECs. Indeed, the transmission limitations are a bit more complicated to
handle, since the three countries are not necessarily aligned.
Therefore, we choose to handle the NECs separately, using a loop that select the cheapest
offer of both NEC in the first case, or the highest offer in the second case, as explained below.
This is equivalent to an aggregation, but the result is not calculated by intersecting two curves.
III.C.1.4.b. Modification of the NECs, according to the accepted
transactions
In a two zones model, the lowest offer of the exporting area will be matched with the highest
bid of the importing area, using the commercial capacity between these two areas. By this
way, the price of the exporting area will increase, while the price of the importing area will
decrease. Then either a congestion occurs between the two zones or the prices of both markets
become equal.
As already explained above, with a three zones model, we come down to a two zones model
by handling together the two markets which prices are the closest.
� Case 1: BCAB PPPP −≤−
The markets A and B export towards the market C, so we will skim through the NECs
of A and B (at each price, in increasing order, we consider the offers made by both markets),
taking the less expensive offer, until a congestion appears or the price of the market A or B
reaches the price of the market C. At each accepted MWh, we report the modification on the
NECs of both importing and exporting countries (by shifting them to the right or the left), and
calculate the new marginal prices of the relevant markets. We also increment the resulting
amount of energy transacted on the concerned transmission line (if the offer is in A, the
transmission CAP → is incremented; if the offer is in B, the transmission CBP → is incremented).
- 46 -
� Case 2: ABBC PPPP −<−
The markets B and C import from the market A. Therefore, we will skim through the
inverted NEC (the net importation curves) of B and C, taking the most expensive importation
offer from B or C, until a congestion appears or the price of market B or C reaches the price
of the market A. At each MWh accepted, we report the modification on the NECs of both
importing and exporting countries and calculate the new marginal prices of the relevant
markets. The transaction on the concerned line is incremented (if the bid is in C, the
transmission CAP → is incremented; if the bid is in B, the transmission BAP → is incremented).
An example of the functioning of the algorithm in the case 1 is illustrated,step by step, in the
following table. A large amount of ATCs is assumed.
NEC A
NEC B
NEC C
Net Export (MWh)
Price
(€/MWh)
Net Export (MWh)
Price
(€/MWh)
C
ATC (MWh)
A�C
B�C
A�B
Net Export (MWh)
Price
(€/MWh)
Net Export (MWh)
Price
(€/MWh)
ATC (MWh)
A�C
B�C
A�B
Price
(€/MWh)
Net Export (MWh) Net Export (MWh)
Price
(€/MWh)
ATC (MWh)
B�C
A�C
A�B
- 47 -
Price
(€/MWh
)
Net Export (MWh) Net Export (MWh)
Price
(€/MWh)
ATC (MWh)
B�C
A�C
A�B
Net Export (MWh)
Price
(€/MWh)
Net Export (MWh)
Price
(€/MWh)
ATC (MWh)
B�C
A�C
A�B
Price
(€/MWh)
Net Export (MWh) Net Export (MWh)
Price
(€/MWh)
ATC (MWh)
B�C
A�C
A�B
Figure 27: Coupling three markets with no constraints – incremental process
Without any congestion, we reach the same final price in the three markets. The process
described in the picture is explained in detail in appendix 4.
In the case 2, the process is the same, excepting that the Net Importation Curves are used by
the program, instead of the Net Exportation Curve.
III.C.1.4.c. Congestions
Once a transmission capacity is reached, the algorithm is still the same, except the fact
that the congested line cannot be used anymore. The transaction underway is done via other
lines if it is possible; if there is no other available path, the transaction is stopped and the
concerned market is isolated. For example, if A exports to C and the line A-C becomes
congested, the market A keeps on exporting to C, but using the line A-B and B-C.
When the two lines connected to a market are congested, the market is isolated from
the others, and the price is then determined by its NEC when the congestion occurred.
The detail of the different steps of the algorithm is described in an algorithm tree in appendix
3.
An example of the functioning of the algorithm in the case 1 with congestions is illustrated,
step by step, in the following table.
- 48 -
NEC A
NEC B
NEC C
Net Export (MWh)
Price
(€/MWh)
Net Export (MWh)
Price
(€/MWh)
ATC (MWh)
B�C
A�B
A�C
Net Export (MWh)
Price
(€/MWh)
Net Export (MWh)
Price
(€/MWh)
ATC (MWh)
B�C
A�B
A�C
Net Export (MWh)
Price
(€/MWh)
Net Export (MWh)
Price
(€/MWh)
ATC (MWh)
B�C
A�B
A�C
- 49 -
Net Export (MWh)
Price
(€/MWh)
Net Export (MWh)
Price
(€/MWh)
ATC (MWh)
B�C
A�B
A�C
Net Export (MWh)
Price
(€/MWh)
Net Export (MWh)
Price
(€/MWh)
ATC (MWh)
A�B
A�C
B�C
Net Export (MWh)
Price
(€/MWh)
Net Export (MWh)
Price
(€/MWh)
ATC (MWh)
A�B
A�C
B�C
Figure 28: Coupling three markets with constraints – incremental process
In this example, the capacity available from A towards C is firstly fully used. Then the energy
transaction from A to C is done via the ATC from A towards B and from B towards C.
However, the line from A to B gets congested, which isolates the market A at a lower
marginal price. Both markets B and C get the same final price. The process described in the
picture above is detailed in appendix 5.
All the possible cases of congestions and prices configurations are handled by the sequential
algorithm, as it is shown in the algorithm tree.
III.C.1.4.d. Calculation of the consumers and producers surplus for each
market, before and after the coupling
The global surplus (called Social Welfare) is a way to measure the effect of market
coupling. The term “consumers’ surplus” describes the difference between the price a
consumer is willing to pay to get a certain quantity of energy and the price the consumer
actually pays for it (the marginal price). On the other hand, the term “producers surplus”
describes the difference between the price a producer get paid for a certain quantity of energy
and the price the producer was first ready to get for it (which is equal to the marginal
production cost).
- 50 -
The global surplus is the sum of these two quantities, and is represented by the coloured
area below:
Figure 29: Calculation of the consumers’ and producers’ surplus,
In order to compute those values, we need the supply and demand curves, as well as
the importation and exportation of the considered market.
If a market exports a certain quantity of energy, it is equivalent to shift its demand curve
to the right (add the value of the export):
- the price of this market increases
- the consumers’ surplus decreases
- the producers’ surplus increases
If a market imports a certain quantity of energy, it is equivalent to shift its supply curve to
the right (add the value of the import) :
- the price of this market decreases
- the consumers’ surplus increases
- the producers’ surplus decreases
Import
Export
Price
(€/MWh)
Volume (MWh)
Price
(€/MWh)
Volume (MWh)
Figure 30: Effect of an import/export on the supply and demand curves
Therefore, knowing the import and export for each market, we can calculate the global
surplus resulting from the coupling.
- 51 -
III.C.1.5. Particularities of the model
� When A exports to B, the condition that must be observed to increment the export
with 1 more MWh is the following:
While Price (A) <Price (B) and BAP → < MAX
BAP →
Where BAP → is the energy transaction on the line BA → .
Therefore, the last accepted MWh might sometimes make the price of market A higher
than the price of the market B, if we are at the edge of a step on a stepwise NEC.
� The model is defined for three markets: one with a linear NEC (France) and two with
a stepwise NECs (Netherlands and Belgium)
� The NECs of the three markets must have the same number of points
III.C.1.6. Conclusion regarding the sequential model
Constructing this model allows a better understanding of how the mechanism works,
and of all the conceivable cases with three interconnected markets. In particular, the
sequential model allows modeling the actual Open Market Coupling that came into force
between France, Belgium and the Netherlands in November 2006. The main particularity here
is that only the NECs are used as input data, the full supply and demand curves are not
required.
Nevertheless, the more countries the more possible cases to handle. Besides, there
would be a problem of capacity definition if an aggregation of markets occurs: how would we
define the capacity on the hub between an aggregation of several markets and the rest of the
system?
For those two reasons, the algorithm becomes really complicated to implement in this way
when there are more than three countries, all interconnected together.
In order to study the extension of Market Coupling, we will try to formulate the problem
in a different way. This will also give a way to validate the first model, by checking if the
global surplus is indeed maximized.
- 52 -
III.C.2 Market Coupling as a system-wide optimisation problem
The aim of the market coupling mechanism is to maximize the global surplus (or
“social welfare”). Therefore, the mechanism will be studied as an optimisation problem,
which maximizes a function under constraints. This is a way to integrate the transmission
limits easily in our problem.
The relevant components of an open market coupling will be mathematically
modelled. Firstly, the solver Excel was used, in order to validate the results obtained with the
sequential algorithm on small example. However, the solver Excel is limited to two hundreds
variables, and is not competitive enough. Thus, the problem has been implemented with the
optimisation software GAMS. Obviously, we get the same results for the small example
treated by the solver Excel or GAMS.
III.C.2.1. Definition of the parameters and variables
The different component of the mechanism must be modelled. Each market involved
has a power exchange, where offers and bids are submitted, and a transmission system
connect these markets. The model consists of nodes and lines. The nodes represent the
markets (each country has one market) and transmission lines with limited commercial
capacity connect them together. [29]
As a consequence of the formulation, we consider there is no congestion within a
market zone, each injection or withdrawal refers to a market, and each market forms a
homogeneous price zone. We do not take into account the block orders. We consider a market
with stepwise supply and demand curves, and the following denominations:
- A “step” of the supply curve is defined by a quantity jSQ , of energy and a price jSP , to
be received for this amount of energy
- A “step” of the demand curve is defined by a quantity iDQ , of energy and a price iDP ,
to be paid for this amount of energy
- nP , the price of the isolated market n, defined by the intersection of its demand and
supply curves
The parameters are described in the picture below: Price
Volume
iDP ,
jSP ,
iDQ ,
jSQ ,
nP
Figure 31: Definition of the parameters
- 53 -
The variables named jSX , and iDX , represent the accepted volume of a bid i or an
offer j. For the orders fully accepted, jSX , and iDX , are respectively equal to jSQ , and iDQ , . For
the marginal offers and bids, jSX , and iDX , might be lower than jSQ , and iDQ , .
We add variables to represent the exports. It is redundant to introduce variables for the
imports as well, since an energy transaction from A to B is an export from A to B, which is
equal to an import towards B from A. Therefore, we introduce the following variables:
mnExp → , where mn ≠ , which represents the energy transfer from the markets n to m.
Finally, the inputs of our model are:
Ps (j,n) Price of the offer j on the market n Pd (i,n) Price of the bid j on the market n
Qs (j,n) Offered volume in the corresponding offer
Qd (i,n) Offered volume in the corresponding bid
ATC (n,m) Available Transmission Capacity n->m
The variables are defined by:
Xs (j,n) Accepted Volume of the offer j on market n
Xd (i,n) Accepted Volume of the bid i on market n Exp (n,m) Transaction from n to m
III.C.2.2. Definition of the objective function
In a market n, with nI bids in the demand curve, the consumers’ surplus can be
formulated as below:
In a market n, with nJ offers in the supply curve, the producers’ surplus can be
formulated as below:
The global surplus for this market is equal to the sum of these two functions:
−+⋅−⋅=
⋅−+⋅−=+
∑∑∑∑
∑∑
====
==
nnnn
nn
I
i
iD
J
j
jSn
J
j
jSjS
I
i
iDiD
J
j
jSjSn
I
i
iDniD
XXPXPXP
XPPXPPPSCS
1
,
1
,
1
,,
1
,,
1
,,
1
,, )()(
Since ∑ ∑= =
=−n nJ
j
I
i
iDjS XX1 1
,, 0 in a market at the equilibrium, the global surplus is independent
of the market price nP .
∑=
⋅−=nI
i
iDniD XPPCS1
,, )(
∑=
⋅−=nJ
j
jSjSn XPPPS1
,, )(
- 54 -
Finally, when considering N markets, the objective function is the following:
Where the jSP , , iDP , are parameters of the problem, and the jSX , and iDX , are variables which
must be optimised. The optimisation problem is linear.
Using GAMS, we need to add a term to avoid loop flows. Indeed, when running the
program, we notice that the transmission capacities are used at their maximum. This is due to
the fact that it does not represent physical flows but commercial transactions, so the
constraints allows GAMS to make the transactions as large as possible.
To avoid these loop transactions, it is necessary to add to the objective function a term
proportional to the sum of the transactions. Thus, the objective function becomes:
In fact, this formulation of the problem is the equivalent to aggregate the demand and
supply curves of all the considered markets, and then find the optimum.
Prix (€/MWh)
Volume (MWh)
Supply Curve A+B+C
Demand Curve A+B+C
Figure 32: Global surplus of the three markets aggregated, in case of no congestion
∑ ∑∑= ==
⋅−⋅
N J
j
jSjS
I
i
iDiD
nn
XPXPM1n 1
,,
1
,, AX
∑∑ ∑∑ ⋅−
⋅−⋅
= == mn
N
n
J
j
jSjS
I
i
iDiD mnFluxXPXPnn
,1 1
,,
1
,, ),(00001.0
- 55 -
III.C.2.3. Formulation of the constraints
� Equilibrium condition
In an isolated market, the sum of the demand must be equal to the sum of the supply, as
we saw before:
However, this formulation does not take into account any coupling of the markets.
Indeed, we have to add the energy transactions between the different markets. For a market n,
the sum of the supply plus the importations must be equal to the sum of the demand plus the
exportations. The equilibrium condition becomes:
∑ ∑= =
=+−n nJ
j
I
i
iDjS XX1 1
,, 0n fromExport -n Import to
which is equivalent to: ∑ ∑ ∑∑= = ≠
→
≠
→ =+−n nJ
j
I
i nmnm
iDjS XX1 1
mnnm,, 0 Exp - Exp
Furthermore, we add a global equilibrium condition, which states that the total quantity
consumed in all the zones is equal to the total quantity produced:
0 1 1 1
,, =
−∑ ∑ ∑
= = =
N
n
J
j
I
i
iDjS
n n
XX
� Transmission constraints
The commercial energy transactions on the lines are limited by the ATC of each line.
Moreover, the variables mnExp → are all positive, since it is defined for each way on a line.
� Constraints on the volume of each offer
Considering an offer, the volume X accepted on this offer is limited by the volume effectively
offered:
≤≤
≤≤
≠∀
→→
→→
AB
BA
ATC
ATC
AB
BA
Exp0
Exp0
BA zones,market B andA
≤≤
≤≤
∀
iDiD
jSjS
QX
QX
,,
,,
0
0
i, j
∑ ∑= =
=−n nJ
j
I
i
iDjS XX1 1
,, 0
- 56 -
III.C.2.4. Particularities of the simulation
The expression of the surplus is slightly different when dealing with linear demand and
supply curves, and not stepwise curves as above.
iDX ,
jSX ,
iDP ,
jSP ,
nP
1, −jSP
1, −iDP
Price
Volume
Figure 33: Definition of the variables
The formulation of the consumers’ and producers’ surplus is the following:
∑∑=
−
=
−
⋅−⋅+⋅−
⋅−⋅−⋅
nn I
i
iDiDiDiDiD
J
j
jSjSjSjSjS XPPXPXPPXP1
,1,,,,
1
,1,,,, )(2
1)(
2
1
It is important to notice that this formula is not accurate. The problem comes from the
marginal offer, which is an offer partially accepted in most of the cases. Therefore, the price
for this offer is the marginal price, and not the price given in the offer. If we go back to the
previous example, we can see on the picture below that the calculation of the consumers’ and
producers’ surplus will not be accurate because of this last term Indeed, the formulation used
add a small term to the calculated area.
Marginale
Offre D X
Bid
Marginal D P
Offer
Marginal S P
n P
Price
Volume
Marginale
Offre S X
Figure 34: Particularities with linear curves
However, if we want to compute the accurate formula, the last term of the sum, the
one concerning the marginal accepted offer, will introduce a term in XPn ⋅ , which is a
quadratic term. In order to keep a linear optimisation problem, we will keep the previous
formula.
Using the Excel solver, we will formulate the surplus for one linear curve, and two
stepwise curves, in order to be as close as possible to the sequential model. However, since
- 57 -
the GAMS model will be used to simulate an open market coupling, we will only consider
stepwise curves in this model (when the scales are small, there is no significant differences).
III.C.2.5. Calculation of the market prices and surplus
Once we get the result of the optimisation, we obtain the energy transactions between
areas. The data are exported to an Excel File, and computations are then done using VBA.
The supply and demand curves of the markets are shifted in respect to the energy transactions
made, and we can then calculate the new market prices and the consumers’ and producers’
surplus for each market.
As a remark, in the calculation of the surplus with supply and demand curves of each
market, we use the following convention in case of price or volume indetermination:
nP
The equilibrium price is the
marginal price
1V 2V
2
21 VVVn
+=
Figure 35: Price and Volume indeterminations
This will explain slight differences between the objective function value (the global surplus)
and the global surplus calculated with the final supply and demand curves.
We will do the simulation on a small theoretical example, close to the example used to
describe the TLC in section III.B.2, and compare the result from the sequential model and the
optimisation problem solved with Excel. The example has been tested with GAMS as well,
and the results are almost the same (the differences are due to the hypothesis of the stepwise
curves).
- 58 -
III.C.3 Results of the simulation: Sequential model versus optimisation
As input to our simulation, we have the following supply and demand curves for each isolated
market:
Volume (MWh)
Pri
ce(€
/MW
h)
Supply curve
Demand curve
Volume (MWh)
Pri
ce(€
/MW
h)
Supply curve
Demand curve
Volume (MWh)
Pri
ce(€
/MW
h)
Supply curve
Demand curve
Calculation of the consumers’ and producers’ surplus (€)
Consumers’ Producers’
M1 3 090,9 2 137,2
M2 1 735 720
M3 945 2 960
Global Surplus : 11 588,125
M1: Market B
Price of the isolated market:
11,75 €/MWh
Volume of exchanged MWh :
347,5 MWh
M2: Market A
Price of the isolated market:
9 €/MWh
Volume of exchanged MWh :
202,5 MWh
M3: Market C
Price of the isolated market:
23 €/MWh
Volume of exchanged MWh :
235 MWh
- 59 -
� Scenario1: All ATCs are equal to 1000 MW
Table 5: Results of the simulation, scenario 1
Considering those results, we can deduce that the algorithm leads to the optimal
solution of the problem, since we obtain the same total surplus. Thanks to the large ATC,
there is no congestion.
Compared to the case of isolated markets, the surplus has increased by 13, 1%.
0
5
10
15
20
25
30
35
0 100 200 300 400 500
Volume (MWh)
Pri
x (
€/M
Wh
)
0
5
10
15
20
25
30
35
0 200 400 600 800 1000
Volume(MWh)
Pri
x (
€/M
Wh
)
Vente + Import
Achat + Export
Vente
Achat
0
5
10
15
20
25
30
35
0 200 400 600 800
Volume (MWh)
Pri
x (
€/M
Wh
)
M1:Market B
M2:Market A M3:Market C
0 MWh 120 MWh
130 MWh
15 €/MWh
15 €/MWh 15 €/MWh
Figure 36: Results of the simulation, scenario 1
Solver
Price of the coupled markets (€/MWh)
P1 15
P2 15
P3 15
Transmissions (MWh)
To M1 To M2 To M3
From M1 0 120,5
From M2 0 129,5
From M3 0 0
Surplus (€)
Consumers’ Producers’
M1 2 054,9 3 372,5
M2 855 2 045
M3 3 515 1 265
Global Surplus : 13 107,5 €
Algorithm
Price of the coupled markets (€/MWh)
P1 15
P2 15
P3 15
Transmissions (MWh)
To M1 To M2 To M3
From M1 0 120
From M2 0 130
From M3 0 0
Surplus (€)
Consumers’ Producers’
M1 2 055 3 372,5
M2 855 2 045
M3 3 515 1 265
Global Surplus : 13 107,5 €
- 60 -
� Scenario 2: Transmissions limitation:
=
=
→
→
0
0
13
31
ATC
ATC
This is equivalent to the real case France/Belgium/Netherlands, with no transmission
limitations (Figure 20).
Table 6: Results of the simulation, scenario 2
The results are the same than in the previous case, the transaction is done through the market
A.
0
5
10
15
20
25
30
35
0 200 400 600 800 1000
Volume(MWh)
Pri
x (
€/M
Wh
)
Vente + Import
Achat + Export
Vente
Achat
0
5
10
15
20
25
30
35
0 200 400 600 800
Volume (MWh)
Pri
x (
€/M
Wh
)
0
5
10
15
20
25
30
35
0 200 400 600 800
Volume (MWh)
Pri
x (
€/M
Wh
)
M1:Market B
M2:Market A M3:Market C
250 MWh
120 MWh
15 €/MWh
15 €/MWh 15 €/MWh
Figure 37: Results of the simulation, scenario 2
Algorithm
Price of the coupled markets (€/MWh)
P1 15
P2 15
P3 15
Transmissions (MWh)
To M1 To M2 To M3
From M1 120 0
From M2 0 250
From M3 0 0
Surplus (€)
Consumers’ Producers’
M1 2 055 3 372,5
M2 855 2 045
M3 3 515 1 265
Global Surplus : 13 107,5 €
Solver
Price of the coupled markets (€/MWh)
P1 15
P2 15
P3 15
Transmissions (MWh)
To M1 To M2 To M3
From M1 120 0
From M2 0 250
From M3 0 0
Surplus (€)
Consumers’ Producers’
M1 2 054,9 3 372,5
M2 855 2 045
M3 3 515 1 265
Global Surplus : 13 107,5 €
- 61 -
� Scenario 3: Transmission limitations:
=
=
→
→
80
80
23
32
ATC
ATC and
=
=
→
→
0
0
13
31
ATC
ATC
Table 7: Results of the simulation, scenario 3
This is equivalent to the real case France/Belgium/Netherlands, with a congestion
between Belgium and Netherlands (Figure 22). We obtain the same price in France and
Belgium, but the Dutch market is isolated and gets a higher price.
Compared to the case of isolated markets, the surplus has increased by 2,3% (the
increase of the surplus is smaller when a line is congested).
The results are illustrated in the picture below:
0
5
10
15
20
25
30
35
0 200 400 600 800
Volume(MWh)
Pri
x (
€/M
Wh
)
Vente + Import
Achat + Export
Vente
Achat
0
5
10
15
20
25
30
35
0 100 200 300 400 500
Volume (MWh)
Pri
x (
€/M
Wh
)
0
5
10
15
20
25
30
35
0 200 400 600 800
Volume (MWh)
Pri
x (
€/M
Wh
)
M1:Market B
M2:Market A M3:Market C
80 MWh
15 MWh
Congestion
12 €/MWh
12 €/MWh
19 €/MWh
Figure 38: Results of the simulation, scenario 3
Algorithm
Price of the coupled markets (€/MWh)
P1 12
P2 12
P3 19
Transmissions (MWh)
To M1 To M2 To M3
From M1 15 0
From M2 0 80
From M3 0 0
Surplus (€)
Consumers’ Producers’
M1 3 005 2 225
M2 1 215 1 340
M3 2 030 2 040
Global Surplus : 11 855 €
Solver
Price of the coupled markets (€/MWh)
P1 12
P2 12
P3 19
Transmissions (MWh)
To M1 To M2 To M3
From M1 15 0
From M2 0 80
From M3 0 0
Surplus (€)
Consumers’ Producers’
M1 3 004,9 2 225
M2 1 215 1 340
M3 2 030 2 040
Global Surplus : 11 855 €
- 62 -
� Scenario 4: Transmission limitations:
=
=
→
→
100
100
12
21
ATC
ATC and
=
=
→
→
0
0
13
31
ATC
ATC
Table 8: : Results of the simulation, scenario 4
This is equivalent to the real case France/Belgium/Netherlands, with a congestion
between France and Belgium (Figure 23). We obtain the same price in Belgium and
Netherlands, but the French market is isolated and gets a lower price.
Compared to the case of isolated markets, the surplus has increased by 11.8 %.
0
5
10
15
20
25
30
35
0 200 400 600 800 1000
Volume(MWh)
Pri
x (
€/M
Wh
)
Vente + Import
Achat + Export
Vente
Achat
0
5
10
15
20
25
30
35
0 200 400 600 800
Volume (MWh)
Pri
x (
€/M
Wh
)
0
5
10
15
20
25
30
35
0 200 400 600 800
Volume (MWh)
Pri
x (
€/M
Wh
)
M1:Market B
M2:Market A M3:Market C
240 MWh
100 MWh
Congestion
16 €/MWh 16 €/MWh
14,56 €/MWh
Figure 39: Results of the simulation, scenario 4
Algorithm
Price of the coupled markets (€/MWh)
P1 14,56
P2 16
P3 16
Transmissions (MWh)
To M1 To M2 To M3
From M1 100 0
From M2 0 240
From M3 0 0
Surplus (€)
Consumers’ Producers’
M1 2 189,8 3 188,8
M2 750 2 290
M3 3 095 1 445
Global Surplus : 12 958,6 €
Solver
Price of the coupled markets (€/MWh)
P1 14,56
P2 16
P3 16
Transmissions (MWh)
To M1 To M2 To M3
From M1 100 0
From M2 0 240
From M3 0 0
Surplus (€)
Consumers’ Producers’
M1 2 189,8 3 188,8
M2 750 2 290
M3 3 095 1 445
Global Surplus : 12 958,6 €
- 63 -
� Scenario 5: Transmission limitations:
=
=
→
→
50
50
12
21
ATC
ATC and
=
=
→
→
170
170
23
32
ATC
ATCand
=
=
→
→
0
0
13
31
ATC
ATC
Table 9: Results of the simulation, scenario 5
Compared to the case of isolated markets, the surplus has increased by 6,6%.
This is equivalent to the real case France/Belgium/Netherlands, with a first congestion
between France and Belgium, which isolates the French market, and then a second congestion
between Belgium and Netherlands (Figure 24). We finally obtain three different prices.
0
5
10
15
20
25
30
35
0 200 400 600 800 1000
Volume(MWh)
Pri
x (
€/M
Wh)
Vente + Import
Achat + Export
Vente
Achat
0
5
10
15
20
25
30
35
0 200 400 600
Volume (MWh)
Pri
x (
€/M
Wh
)
0
5
10
15
20
25
30
35
0 200 400 600 800
Volume (MWh)
Pri
x (
€/M
Wh
)
M1:Market B
M2:Market A M3:Market C
170 MWh
50 MWh
Congestion
Congestion
12,87 €/MWh
14 €/MWh17 €/MWh
Figure 40: Results of the simulation, scenario 5
Algorithm
Price of the coupled markets (€/MWh)
P1 12,87
P2 14
P3 17
Transmissions (MWh)
To M1 To M2 To M3
From M1 50 0
From M2 0 170
From M3 0 0
Surplus (€)
Consumers’ Producers’
M1 2 717,1 2 541,4
M2 960 1 810
M3 2 705 1 625
Global Surplus : 12 358,4 €
Solver
Price of the coupled markets (€/MWh)
P1 12,87
P2 14
P3 17
Transmissions (MWh)
To M1 To M2 To M3
From M1 50 0
From M2 0 170
From M3 0 0
Surplus (€)
Consumers’ Producers’
M1 2 717,1 2 541,4
M2 960 1 810
M3 2 705 1 625
Global Surplus : 12 358,4 €
- 64 -
III.C.4 Conclusions regarding the results
The solver is a way to validate the sequential model. Indeed, since the prices,
transactions and surplus calculated are the same, we can deduce that the sequential model is
optimal, and maximizes the global surplus.
Moreover, the example above shows the impact of a congestion on the global welfare.
However, the data used here are theoretical, and it would be more interesting to run the model
with realistic data.
The sequential model is based on the same principles that the TLC algorithm, besides a slight
difference due to the fact that the three countries are not necessarily aligned in the simulation.
But it is exactly the same mechanism for matching orders, and logically leads to the same
results14
.
The main difference between the sequential model and the optimisation is that the
complete supply and demand curves are not necessary in the sequential model, as it is the case
today in the TLC. This is mainly a strategic point, but it could stress the interest of a
sequential model compared to an optimisation formulation.
However, when dealing with more than three countries, an optimisation formulation is
necessary. Besides, it is a way to confirm that the market coupling mechanism actually
optimises the global economic surplus.
III.C.5 Perspectives
As a future work, it would be interesting to perform the optimisation using only the NECs.
Indeed, in a two markets situation, it is possible to compute the increase or decrease of the
economic surplus with the NECs, as shown in the picture below where the market A export
towards the market B.
14
When dealing with theoretical data, without block offers.
- 65 -
Figure 41: Calculation of the surplus using the NECs
In a bilateral coupling, it is possible to get the increase of the global surplus, using the
NEC of the exporting market and the NIC of the importing market.
Net Export (MWh)
Price
(€/MWh)
NEC A
NEC B
Net Export (MWh)
Price
(€/MWh)
NEC A
NIC B
AP0
BP0
finalP
B)(A Surplus +∆
Figure 42: Increase of the surplus resulting from the coupling
The aim of the optimisation would be to maximise the area representing the increase of
the global surplus. However, the difficulty would be in getting only two curves when dealing
with more than two markets. Therefore, it would be necessary to assume aggregations of
different markets to come down to two areas and a bilateral coupling. An iteration process
would be needed to test all the possible situations, and keep the most optimal.
- 66 -
III.D. Towards an Open Market Coupling
III.D.1 Elaboration of the scenarios
In this part, the aim is to focus on the potential extending of the market coupling
mechanism, especially to Germany, and run the GAMS simulation with realistic data. For this
purpose, we choose to build several scenarios for the second term of 2008.
The constructed supply and demand curves are based on historical data, and price
quotations. Regarding the prices, the scenarios will be based on futures’ prices for the second
term of 200815
; the following prices are used as a basis
France 53 €/MWh
Germany 55 €/MWh
Belgium 55,5 €/MWh
Netherlands 59 €/MWh
Table 10: Prices of the futures for the second semester 2008
Regarding the quantities traded in each market, we will base our argument upon
historical data from the day-ahead markets16
. As an indication, average data from 2006
concerning the different power exchanges are summarized in the table below:
Volume on the spot
market in 2006 (TWh)
Volume on the spot
market as a percentage of
the overall consumption
France 29 6 %
Germany 89 16 %
Belgium 0.5 (only since 22.11.2006) 6 %
Netherlands 19 16 %
Table 11: Volumes on the spot market in 2006
In the scenario, we will take the following volumes as an order of magnitude (it
represents the volume of energy traded during one hour on the day-ahead spot market):
France 3500 MWh
Germany 10 000 MWh
Belgium 1000 MWh
Netherlands 1 800 MWh
Table 12: Day-ahead market volumes
These data have been used as a start, but then they have been modified in order to
improve the scenarios.
The slope of the supply curve’ order of magnitude will be based on historical
aggregated curves, on the different kinds of production capacity of each country and
sometimes on resilience analysis.
15
The prices are based on Platts data. The prices for France, Belgium and the Netherlands take into account the
coupling (since it already existed when the quotation has been done) 16
The data are extracted from the power exchanges’websites: Belpex, ApX, EEX, Powernext.
- 67 -
We will assume that the demand curve is the symmetric of the supply curve (ie with
the opposite slope). Indeed, on the day-ahead market, only the marginal part of the production
and consumption is represented. This part is managed by traders, and we could say that the
demand curve is in fact a “non-production” curve: it represents the energy a trader prefers to
buy instead of produce.
The ATC between countries are based on the Etsovista data for the winter 2007. We assume
that the ATC is equal to one third on the Net Transfer Capacity.
France Germany Belgium Netherlands
France 0 900 1000 0
Germany 900 0 0 1200
Belgium 700 0 0 750
Netherlands 0 950 750 0
Table 13: ATC matrix (in MW)17
III.D.2 Result of the simulations18
The results of the base scenario are given below19
:
644.25 MW
673,75 MW 431 MW
55.262.4Netherlands
55.258.2Belgium
55.255.5Germany
55.249.9France
Coupled
Markets
Isolated
Markets
Prices (€/MWh)
Figure 43: Results from the base scenario using the ATC model
17
The countries on the vertical column export to the countries on the horizontal line. 18
In dot lines are represented the supply and demand curve before the coupling, in full lines after the coupling. 19
Since the data are available for one hour, a MW is equivalent to a MWh.
- 68 -
In the base scenario, the final prices are close to the German price. In France, the
isolated price is lower, but prices increase faster (the slope is larger) than in Germany.
The resulting energy transaction concerns the day-ahead implicit auction only, and must be
added to the transaction outside the day-ahead market.
The idea is
to simulate several situations, based on this base scenario in extreme situations.
• Scenario 1: A peak of wind is observed in Germany.
We assume an increase of 6 000 MW of production, due to the surplus of wind power.
However, all this quantity is not contracted on the day-ahead market. We assume that
wind forecast allow half of the quantity to be contracted outside the day-ahead market.
Therefore, we subtract 3 000 MW from the demand curve, and we add 3 000 MW to the
supply curve.
900MW
765.75 MW 1200 MW
415 MW
49.462.4Netherlands
49.458.2Belgium
46.737.5Germany
49.449.9France
Coupled
Markets
Isolated
Markets
Prices (€/MWh)
Figure 44: Results from the scenario 1 using the ATC model
Here we observe two congested lines, and the German market is isolated with the lowest
price. The three other markets get the same price.
- 69 -
• Scenario 2: A decrease of the temperature is observed, especially in France.
Indeed, France is very sensible to the coldness, because electric heating is very popular. In
the winter, the consumption increase by approximately 1500 MWh/° during the winter.
Here we consider an increase of 4 000 MW of demand, but only half of it is traded on the
day ahead market, assuming that the other part is contracted bilaterally. Therefore, we
subtract 2 000 MW from the demand curve, and we add 2 000 MW to the supply curve.
900MW
700 MW 811 MW
584 MW
58.762.4Netherlands
58.758.2Belgium
58.755.5Germany
6195.9France
Coupled
Markets
Isolated
Markets
Prices (€/MWh)
Figure 45: Results from the scenario 2 using the ATC model
The lines towards France are both congested, which isolates the French market with a higher
price. The three other markets get equal prices.
- 70 -
• Scenario 3: A lack of wind is observed in Germany.
It leads to a decrease of production up to 4 000 MWh and increase the German price. Half
of this amount has been contracted outside the day-ahead market. Therefore, we subtract
2000 MW from the demand curve, and we add 2 000 MW to the supply curve.
900MW
782 MW 649 MW
750 MW
60.862.4Netherlands
5858.2Belgium
60.866.2Germany
5849.9France
Coupled
Markets
Isolated
Markets
Prices (€/MWh)
Figure 46: Results from the scenario 3 using the ATC model
In this scenario we reach two groups of countries: Belgium and France on one hand, which
exports towards Germany and the Netherlands on the other hands, until the two concerned
lines get congested.
- 71 -
• Scenario 4: An increase of the price of gas is observed.
The French price is not changed, since the marginal production is more made of coal plant
in France. However, the German, Belgian, and Dutch prices are affected. In Germany, the
marginal production consist in coal or gas, so we assume an increase of the prices of 15
€/MWh (the supply curve is vertically shifted). In Belgium and the Netherlands, the part
of gas in the marginal production is more important, especially in the Netherlands: the
price is increased by 25 €/MWh on the Belgian market and by 30 €/MWh on the Dutch
market.
900MW
1000 MW 191.25 MW
562.25 MW
61.477.4Netherlands
61.469.1Belgium
61.463.4Germany
59.649.9France
Coupled
Markets
Isolated
Markets
Prices (€/MWh)
Figure 47: Results from the scenario 4 using the ATC model
In this scenario, the French market is isolated with a lower price: it exports until both
outwards lines get congested. The three other markets get equal prices.
- 72 -
• Scenario 5: We assume an unavailability of 1 800 MW of production capacity on the
Dutch market.
Moreover, an unavailability of half the transmission capacity (ATC) on the line from
Belgium to the Netherlands is observed, because of network maintenance for example.
The aim of this scenario is to isolate the Dutch market. Contrary to the TLC, it is more
“difficult” to isolate the Netherlands, because the transaction can be done through
Germany.
640 MW
834.75 MW 1200 MW
375 MW
62.2114.6Netherlands
56.558.2Belgium
56.555.5Germany
56.549.9France
Coupled
Markets
Isolated
Markets
Prices (€/MWh)
Figure 48: Results from the scenario 5 using the ATC model
The Dutch market gets isolated with a higher price, whereas the three other markets get the
same price.
- 73 -
• Scenario 6: We consider the same situation as in scenario 1, and we add a network
constraint: only half of the ATC is available on the line from Germany to the
Netherlands.
900 MW
1000 MW 600 MW
52.462.4Netherlands
52.458.2Belgium
44.437.5Germany
50.249.9France
Coupled
Markets
Isolated
Markets
Prices (€/MWh)
Figure 49: Results from the scenario 6 using the ATC model
Due to the stronger constraint on the line from Germany tote Netherlands, the German market
gets isolated first. The line between France and Belgium becomes congested two. Only
Belgium and the Netherlands get the same price.
The aim of running the scenarios above was to get a better understanding of the
situation of an Open Market Coupling including Germany, and to reach different
configurations of prices and congestions.
It is interesting to point out that in this simulation, which only deals with commercial
capacities and transactions, one congestion does not lead to four different prices. Indeed, once
a line is congested, the transaction underway is done through the other possible “lines” (ATC
in fact). In the studied area, the four countries are on a circle. To get an isolated price, a
market must have both outwards and inwards line congested.
Moreover, building scenarios and working on the slope of the curves was interesting,
because the price sensitivity is specific to each countries and its means of production, and
influence the final result of the coupling. The data used are not accurate, but they give a
general idea of the kinds of situations which can occur.
- 74 -
Besides, in the studied cases, prices spreads due to congestions are quite numerous.
Another alternative to the method implemented with the ATC is the flow-based approach,
which takes into account the real power flows on the grid, and might allow an even better use
of the cross border transmission lines. We will try to implement this approach and compare
the results using the same scenarios.
- 75 -
III.E. Towards a flow-based market coupling
III.E.1 Formulation of the problem with the Power Transfer Distribution Factors
Another method to describe the cross-border transmission limit capacity is to establish a
flow-based model. It means that, instead of considering commercial transactions and
commercial capacities (ATC), we will consider the physical power flows on the line and the
physical cross-border transmission limitations.
When we consider the real meshed networks and its physical laws, an energy transfer
on an interconnection has an effect on the power flows on all the other lines. Indeed, a
commercial transaction between two countries leads to physical power flow on every line of
the meshed network, considering the Kirchoff’s law. In the following picture, the power flow
distribution of a 1000 MW transaction from France to Italy is represented.
Figure 50 : Power flow distribution of a 1000 MW trnasport from Northern France to Italy
The model of the power flows on the line is done by the means of the so-called Power
Transfer Distribution Factor (PTDF), which represent the percentage shared in transit on each
line, depending of the balance20
of the considered countries. Here we will work with zonal
PTDF factors (we consider a country as one node); they describe the influence a commercial
exchange between two countries has on the physical flows on a given interconnection [28].
In fact, the PTDF factors translate a commercial transaction between two countries to the
expected physical flow over the transmission network.
The overall formulation of the market coupling as an optimisation problem is the same
as before, except that we add a variable for the physical power flows, and the constraints are a
bit changed. This simulation is implemented with GAMS as well.
With a flow-based approach of Market Coupling, the commercial exchange between
two markets is no longer limited by the commercial capacity on the interconnection where the
transaction is done, but it is translated to physical flows through the entire transmission
network, and thus limited by physical capacity of the lines. Therefore, other countries besides
the considered markets are taken into account.
20
The balance of a country is equal to its production minus its consumption.
- 76 -
The European interconnected power system is divided into main regional areas. In this
study, we have considered the countries of the Central Southern Europe and Central Western
Europe (as represented on the picture above). The PTDF factors are the result of a multi-linear
regression between the flows on given interconnections and the net production of the
countries involved in the PTDF calculation (by net production, it is meant supply minus
demand). The data are observed data21
, averaged on the year 2006.
The lines are represented by a maximum allowable flow maxFlow and an estimated
flow 0T which is present prior to the additional transaction. Moreover, the transactions (still
represented by the variable mnExp → , results from the market coupling optimisation problem)
are considered as variation from an initial balance lB of the concerned country l.
The resulting flow on a cross border transmission line is represented by a variable mnFlow → .
The opposite flow nmFlow → is equal to mnFlow →− .
The new transmission constraints in our optimisation problem are the following:
where the set l describe the country, ie the countries taken into account in the PTDF
calculation, including the observed markets.
III.E.2 Data used in the model
We work with the eight countries of Central Southern Europe and Central Western
Europe, including the four markets of France, Germany, Belgium and the Netherlands. We
consider the four lines betweens those markets: Fr-De, De-Nl, Nl-Be, Be-Fr.
� How we calculate the initial balance
We have the average balance for each country (in MW), which include every type of
transaction and auctions:
Sl 45 MW
It -6099 MW
At 905 MW
CH 96 MW
Fr 7700 MW
De -238 MW
Be -616 MW
Nl -2048 MW
Table 14: Average balances in MW
21
www.etsovista.org
( )
≤
−+⋅→+=
→→
=
→→→→ ∑ ∑
MAXnmnm
L
l markets
mmarketmarketmlnmnm
FlowFlow
ExpExpBnmPTDFTFlow
,
1
made ons transacticommercial the todue Balance theofVariation
,0 )()(
44444 344444 21
- 77 -
We need to compute initial balance for each market, to which we will add the
additional balance due to energy transactions resulting of the simulation. We will consider
that the initial balance for each country is equal to two third of the average balance: one third
of the balance is represented by the market coupling. This is quite consistent with the
assumption made in the simulation using the ATC, where the ATC were assumed to be equal
to one third of the NTC. Indeed, we still consider that two third of the quantity available on
the market correspond to explicit auctions. We keep the average balance to the countries
which are not studied as market in the simulation:
Sl 45 MW
It -6099 MW
At 905 MW
CH 96 MW
Fr 5133,33 MW
De -158,67 MW
Be -410,67 MW
Nl -1365,33 MW
Table 15: Initial Balances in MW
� How we calculate the maximal flows
We are given the maximal flows observed on each line. However, the actual flows are
most of the time smaller. Since we do not have here a real model of the network to define
those maximal flows, we will take the strongest constraint between the observed flows and the
NTC.
� How we understand the given PTDF
The data used for the simulation are the following:
Fr →De De →Nl Nl →Be Be →Fr
T0 (MW) 560 437 437 437
PTDF (%)
Sl -0,7 22 22 22
It -8,6 -14,2 -14,2 -14,2
At -19,2 -1,3 -1,3 -1,3
CH -9,9 -9,6 -9,6 -9,6
Fr 15,8 -14,9 -14,9 -14,9
De -21,3 14,8 14,8 14,8
Be 2,2 -63,3 -63,3 36,7
Nl 6,8 -69,6 30,4 30,4
Table 16: Data used for PTDF and T0
- 78 -
In the studied network, France and Germany are linked to other countries than
Belgium and the Netherlands. Indeed, we do not consider in the calculation only the four
studied markets, but the eight countries of the CWE22
and CSE23
area. This explains why the
net flow coming out or in (using the studied lines) is not equal to zero for France and
Germany.
Indeed, if we take Germany:
- Concerning the transit prior to any additional transaction, we observe a net flow
outwards Germany equal to 560-437=123 MW: this flow is distributed towards the
others countries
- Concerning the PTDF, the sum of the factors on the line coming out from Germany is
not equal to 100% (PTDF (De,De →Nl)-PTDF(De, Fr →De)<100%), which means
that a part of the flow is distributed on the other lines connected to Germany. Here, the
sum of the factor on the line De →Nl (14.8%) minus the factor on the line Fr →De (-
21.3%) is equal to 36.1% : this means that 63.9 % of the flow is distributed on lines
towards the other countries (Sl, It, At, CH)
Concerning France and Germany, this let us understand why the net position (resulting from
the energy transaction calculated by the model) is not equal to the net power flow coming out
or in the market. Indeed, a part of the energy transaction is distributed towards the other
connected countries.
However, concerning Belgium and Netherlands, the net position due to commercial
transaction is equal to the net physical power flow coming in or out the country.
Indeed, if we take Belgium:
- Concerning the transit prior to any additional transaction, the net balance due to this
flow is equal to 437-437=0 MW
- Concerning the PTDF, the sum of the factors on the line coming out from Belgium is
equal to 100%: (PTDF (Country,Be →Fr)-PTDF(Country, Nl →Be)=100%).
Indeed, it is equal to 36.7-(-63.3) =100%: All the flow is distributed towards France
and the Netherlands, because there is no other line connected to Belgium in the studied
system.
22
Central West Europe 23
Central South Europe
- 79 -
III.E.3 Simulation on the scenarios
The aim here is to compare the result of the flow based model with the ATC model, by
running them on the scenarios. Since the data are not accurate, the aim here is just to point out
the main aspects of both methods, not to make a quantitative analysis.
Below are given the commercial transactions resulting from the base scenario.
213.25 MW
673,75 MW431 MW
Figure 51: Results from the base scenario using the PTDF model
Isolated Market (€/MWh) Coupled Market (€/MWh)
France 49.9 55.2
Germany 55.5 55.2
Belgium 58.2 55.2
Netherlands 62.4 55.2
Table 17 : Prices in €/MWh
Firstly, it is important to notice that, contrary to the ATC model, all the possible
commercial transactions are allowed. Indeed, in this simulation, the commercial transactions
are not limited by the ATC, but are used to calculate the physical power flows and then the
real power flow is limited by a maximum. Therefore, every way of transaction is allowed, like
between France and the Netherlands in this example.
We reach the same final price than in the ATC model, and the net position of each
market is the same. We get the same global economic surplus
- 80 -
Concerning the physical power flows, they are given below, in MW:
Fr →De De →Nl Nl →Be Be →Fr
1853,45608 2212,36842 416,035083 -668,381583
Table 18: Physical power flows, Base scenario
Flow Max Flow Min
Fr →De 2850 Fr →De -740
De →Nl 3850 De →Nl -158
Nl →Be 2400 Nl →Be -2400
Be →Fr 1793 Be →Fr -2997
Table 19: Constraints on the pysical power flows
As we can see here, the remaining margins between the power flows and the
constraints are quite large, so it will certainly be difficult to reach congestion, starting from
the base scenario. The flow-based method is supposed to result in a better use of the
transmission capacities, and therefore lead to fewer price spreads and a better economic
surplus.
The picture below summarizes the base scenarios using both commercial and flow-based
approach:
PTDF ModelATC Model
55.2
55.2
55.2
55.2
55.262.4Netherlands
55.258.2Belgium
55.255.5Germany
55.249.9France
Price of the Coupled Market
(€/MWh)
Price of the
Isolated
Market
(€/MWh)
Be NL
DeFr
Be NL
DeFr
Simulation using ATCs Simulation using PTDFs
673.25 MW
644.25 MW
431 MW 673.25 MW
213.25 MW
431 MW
7424115,457424115,45Global Surplus of
the coupled market
(€)
PTDF
Model
ATC
Model
Figure 52: Comparison of the results from the base scenario
We will compare the results from the optimisation using ATC and the flow based method,
based on the scenario.
- 81 -
� Scenario 1
PTDF ModelATC Model
49.4
49.4
46.7
49.4
48.262.4Netherlands
48.258.2Belgium
48.237.5Germany
48.249.9France
Price of the Coupled Market
(€/MWh)
Price of the
Isolated
Market
(€/MWh)
Be NL
DeFr
Be NL
DeFr
Simulation using ATCs Simulation using PTDFs
765.75 MW
900 MW
1200 MW 1264.75 MW
2 574.75 MW
857 MW
415 MW
4735227,6254728941,175Global Surplus of
the coupled market
(€)
PTDF
Model
ATC
Model
Figure 53: Comparison of the results from the scenario 1
We observe no congestion with the flow-based model, and therefore a better global surplus of
the coupled markets. In this scenario, the flow –based approach allow a better use of the
transmission line capacities.
� Scenario 2
PTDF ModelATC Model
58.7
58.7
58.7
61
59.162.4Netherlands
59.158.2Belgium
59.155.5Germany
59.195.9France
Price of the Coupled Market
(€/MWh)
Price of the
Isolated
Market
(€/MWh)
Be NL
DeFr
Be NL
DeFr
Simulation using ATCs Simulation using PTDFs
700 MW
900 MW
811 MW 198.255 MW
1847 MW
203 MW
584 MW
9214394,7259210417,525Global Surplus of
the coupled market
(€)
PTDF
Model
ATC
Model
Figure 54: Comparison of the results from the scenario 2
- 82 -
Here as well the flow-based method leads to a single price and a better global surplus.
� Scenario 3
PTDF ModelATC Model
60.8
58
60.8
58
59.562.4Netherlands
59.558.2Belgium
59.566.2Germany
59.549.9France
Price of the Coupled Market
(€/MWh)
Price of the
Isolated
Market
(€/MWh)
Be NL
DeFr
Be NL
DeFr
Simulation using ATCs Simulation using PTDFs
782 MW
900 MW
649 MW 292.25 MW
2009.25 MW
173 MW
750 MW
9195628,9259190092,65Global Surplus of
the coupled market
(€)
PTDF
Model
ATC
Model
Figure 55: Comparison of the results from the scenario 3
We observe again that no congestion appears in the simulation using the PTDF.
� Scenario 4
PTDF ModelATC Model
61.4
61.4
61.4
59.6
6177.4Netherlands
6169.1Belgium
6163.4Germany
6149.9France
Price of the Coupled Market
(€/MWh)
Price of the
Isolated
Market
(€/MWh)
Be NL
DeFr
Be NL
DeFr
Simulation using ATCs Simulation using PTDFs
1000 MW
900 MW
191.25 MW 476.75 MW
823.75 MW
771.5 MW
562.25 MW
7244429,957240933,2Global Surplus of
the coupled market
(€)
PTDF
Model
ATC
Model
Figure 56: Comparison of the results from the scenario 4
- 83 -
Contrary to the ATC model, we observe no congestion in this scenario either.
� Scenario 5
In this scenario, the ATC from Belgium to Netherlands was reducd by half. This could be
transposed in the flow-based method by reducing the maximal flow on the line from Belgium
to Netherlands.
Since the physical flows are global, there are equivalent to NTC in the commercial
approach. Besides, ATC were equal to one third of NTC. Therefore dividing the ATC by two
in the commercial approach is equivalent to divide the NTC by 6, and by this way to reduce
the physical flow by one sixth in the flow-based approach.
PTDF ModelATC Model
62.2
56.5
56.5
56.5
56.6114.6Netherlands
56.658.2Belgium
56.655.5Germany
56.649.9France
Price of the Coupled Market
(€/MWh)
Price of the
Isolated
Market
(€/MWh)
Be NL
DeFr
Be NL
DeFr
Simulation using ATCs Simulation using PTDFs
834.75 MW
640 MW
1200 MW 437.75 MW
678 MW
1740.25 MW
375 MW
7377916,5257368490,225Global Surplus of
the coupled market
(€)
PTDF
Model
ATC
Model
Figure 57: Comparison of the results from the scenario 5
In this scenario again, we observe no congestion and a better global surplus.
The physical power flows and their limitations are given below:
Fr_De De_Nl Nl_Be Be_Fr
1608,53883 3079,00542 -26,5779167 -874,994583
Flow Max Flow Min
Fr_De 2850 Fr_De -740
De_Nl 3850 De_Nl -158
Nl_Be 2400 Nl_Be -2000
Be_Fr 1793 Be_Fr -2997
Table 20: Physical power flows and their limitations
- 84 -
� Scenario 6
In this scenario, we reduce the maximal power flow from Germany to the Netherlands by one
sixth.
PTDF ModelATC Model
52.4
52.4
44.4
50.2
51.762.4Netherlands
51.358.2Belgium
46.737.5Germany
48.549.9France
Price of the Coupled Market
(€/MWh)
Price of the
Isolated
Market
(€/MWh)
Be NL
DeFr
Be NL
DeFr
Simulation using ATCs Simulation using PTDFs
1000 MW
900 MW
600 MW 1071.75 MW
2093.75 MW
647 MW
4725499,0254719613,3Global Surplus of
the coupled market
(€)
PTDF
Model
ATC
Model
Figure 58: Comparison of the results from the scenario 6
The physical power flows and their limitations are given below:
Fr_De De_Nl Nl_Be Be_Fr
1071,12651 3208,33333 1196 -286,419121
Flow Max Flow Min
Fr_De 2850 Fr_De -740
De_Nl 3208,33333 De_Nl -158
Nl_Be 2400 Nl_Be -2400
Be_Fr 1793 Be_Fr -2997
Table 21: Physical power flows and their limitations
This scenario is interesting, since we observe a congestion in both simulations.
However, we can clearly see here, in the flow-based approach, that once only one line is
congested, the four market zones get different prices. This is not the case with the simulation
using commercial capacities, because once an ATC is fully used, the commercial transactions
underway can continue using other ATCs.
In the flow-based approach, once a line is physically congested, no other additional
transaction can be done. Indeed, an additional congestion would lead to a distribution of the
flow on every line of the meshed network, which is not possible since one of them is
unavailable.
- 85 -
In this example, even with congestion, the global economic surplus is larger using the
flow-based method. We can not deduce general conclusions from one scenario, but the result
is interesting anyway.
III.F. The commercial approach versus the flow based approach
It is important to see that the data used in the simulation are not accurate, and come
from several hypotheses. The simulation gives only an illustration of the flow-based
approach. Afterwards, like the approach using the ATC, the model will lay down the problem
of the calculation of the needed data and their gathering.
In the studied cases, the flow-based approach allows a better use of the cross-border
transmission capacities, and therefore results in a better global economic surplus. It leads to
fewer situations of price spreads. Nevertheless, because of the calculation of the physical
power flows behind, it could appear as less transparent for traders.
Besides, the main aspect to see in this approach is that once a line gets congested, each
zone gets a different price, which induces more price volatility. Firstly, this can be seen as an
increase of the prices volatility and therefore an argument to reject the flow-based approach.
Secondly, it compromises the current method of distributing the income from a congestion to
the TSOs. Indeed, with the methods applied today, when a line gets congested (in the sense
of ATC), the income from the congestion is shared by the two TSOs concerned by the energy
transaction. With a flow-based approach, this is not possible anymore: a transaction between
two zones can create a congestion on a line between other zones, and all the prices are then
different. It will not be fair then to share the income between the two TSOs concerned by the
initial transaction.
Moreover, the Power Transfer Distribution Factors influence a lot the results, and their
calculation must be done fairly and accurately. An important coordination between TSOs is
needed to compute the data needed in this model (initial balances, T0, PTDF…).
- 86 -
Chapter IV. Conclusions
IV.A. Main aspects of the study
The first part of this master thesis aims at giving an overview of the balancing
mechanisms in Great-Britain and Germany, pointing out the likenesses and differences. As it
is a part of a larger project resulting in a benchmark of the different balancing mechanisms in
Europe, it is does not give a general overview of the situation in Europe, and what is to be
done in order to integrate these balancing markets. However, it can be a support to understand
the basics of balancing mechanism, and how they can be applied viewed from two different
countries.
The second part of the study is supposed to allow a better understanding of the principles
of the market coupling, and the different methods which can be carried out. The main interest
was to build a model of the mechanism, and to see the most important challenges of the
mechanisms.
Firstly, the sequential algorithm simulates the Trilateral Market Coupling24
as it is done
today. The main point is that it requires the Net Exportation Curves as input data, and not the
full supply and demand curves. This is strategic, but can be an important argument in support
of this model. However, when dealing with more than three countries, the model becomes too
complicated to implement. Indeed, a formulation as an optimisation problem is more suitable
for a simulation of an Open Market Coupling including Germany. The major drawback is that
the full supply and demand curves are then needed to calculate the prices and net position of
each market.
Finally, the optimisation formulation is done using two approaches: the “commercial”
approach and the flow-based approach. By “commercial” approach, we mean that the
transmission lines are characterised by their ATCs, and no real power flow appears in this
model (it is intrinsic to the calculation of the ATCs). This kind of approach is easier to
understand, because all the physic of the grid is not clearly visible. Indeed, a transaction can
be done using all the possible ways (which are the cross border lines), without considering the
actual physical state of this line. On the other hand, in the flow-based approach, the
consideration of the real physical power flow is inherent to the model. The physical power
flows are computed using the PTDFs, data given by the TSOs.
If the flow-based approach is a bit more complicated, it is nevertheless supposed to lead to
a better use of the cross border transmission lines. Indeed, the results from the scenarios show
that the flow based approach results in better economic surplus, and fewer price spreads.
Since a congestion leads to a different price in each zone, the flow-based approach can induce
more price volatility, which could be a drawback for power exchanges.
However, we cannot deduce any general conclusion from the simulations done. Indeed,
the PTDF used are zonal, and the model is rough, due to the data used and the hypotheses
made. Anyway, the study is interesting because it gives an overview of the two methods, and
the kind of situations which can occur when Germany will be integrated in the process.
24
Only the algorithm of the coordination module
- 87 -
IV.B. Perspectives
One of the main points arising from the market coupling mechanism is the question of the
centralisation of the needed information. Indeed, as said in III.B, Market Coupling can be
seen as a different mechanism from Market Splitting because it adopts a decentralised
approach: the coupling is done between independent markets, with their own design.
Nevertheless, in the TLC algorithm, it appears that a common organisation is needed, to
carry out the mechanism. Currently, the Dutch power exchange ApX is in charge of the
functioning of the coordination module, and therefore gather the information (NECs and
ATCs). It is therefore not accurate to say that the approach is decentralised, since a common
entity is needed. This existence of a common entity raises several strategic questions: Who
should gather the information and carry out the algorithm and which degree of information
should be shared?
That is why a model using only the NECs is tempting, because it allows less information
to be given. As a future work, it would be interesting to perform the optimisation using only
the NECs.
Besides, in the flow-based approach, the calculation of the PTDFs and the data needed
will be a main issue. The flow-based approach as it is done in this master thesis is quite rough,
but it can be seen as an introduction and a support to understand the basics of the method and
its differences compared to the method using the ATCs.
- 88 -
Appendix 1
Some Data from the German Balancing Mechanism
Each German TSO publishes the volume of activated minute reserve. These data are
interesting, because they show that in fact, the minute reserve is rarely used.
Let us observe one day25
, January the 9th
2007.
The table hereafter shows the periods of the day which have seen a use of some minute
reserve:
Period Utilised minute reserve
energy (MWh)
Affected TSO
Downwards Bids
00 :30-00 :45 -122.5 RWE
23 :30-23 :45 -51.250 Vattenfall
23 :45-00 :00 -51.250 Vattenfall
Upwards Offers
10 :15-10 :30 25 EnBW
10 :30-10 :45 50 EnBW
10 :45-11 :00 50 EnBW
Table 22: Activation of minute reserve
Indeed, the activation of a reserve minute order is quite rare, whereas the published
imbalance in each zone for each period of this day are not equal to zero:
Imbalances
-350
-300
-250
-200
-150
-100
-50
0
50
100
150
0 20 40 60 80 100 120
Settlement Period
Imb
ala
nce
Vo
lum
e (M
Wh
)
RWE
EnBW
EON
Vattenfall
Figure 59: Metered Imbalance
25
Here we take arbitrarily one day to give a concrete example, but similar situations occur each day
- 89 -
Appendix 2
ATC definition
A transmission line is characterised by its transmission capacity, which is the maximum
quantity of MW allowed on this line. The following definitions are used to describe a
transmission line:
Ther
mal
Cap
acit
y Security margin
TRM
TTCATC
AACNTC
Figure 60: Description of a line
• TTC: Total Transfer Capacity (Maximal capacity available, while ensuring the
network security)
• TRM: Transmission Regulation Margin (minimal reserve to ensure reliability)
• NTC: Net Transfer Capacity (capacity used by the actors)
• AAC: Already Allocated capacity (via explicit auctioning)
• ATC: Available Transmission Capacity (available for market coupling)
When a commercial exchange of energy happens between two countries, it has an impact on
all the lines of the meshed network. NTCs and ATCs are commercial capacities, the load flow
calculations are included in these values. Therefore, once they are calculated, ATCs are
simple to use. Indeed, when a transaction of energy is settled between a market A and a
market B, it “consumes” a part of the ATC between A and B, and there is no additional power
flow calculation to make (they are contained in the ATC value).
The NTC and ATC values are published by the TSO. The main point here is how they are
calculated, and if the given value allows an optimal use of the transmission lines.
- 90 -
Appendix 3
Sequential Algorithm for Market Coupling
The algorithm tree given below summarizes all the possible paths in the first case:
A B CA B C
B A C
Selection of the exportation offers by
price on the NECs of A and B
Transmissions on the lines A-C and B-C
Saturation of A-C Saturation of B-C
Selection of the exportation offers by
price on the NECs of A and B
Transmissions on the lines A-B + B-C
if the offer is in A or only B-C if the
offer is in B
Case 1
BCAB PPPP −≤−
A and B export to C
Saturation of
A-B
Saturation
of B-C
A isolated
B exports
to C
PB=PC
Saturation
of B-C
C isolated
The less expensive
of A or B exports
towards the other
PA=PB
Saturation
of A-B
Selection of the exportation offers by
price on the NECs of A and B
Transmission on the lines B-A + A-C
if the offer is in B or only C-A if the
offer is in A
Saturation of
B-A
Saturation
of A-C
B isolated
A exports
to C
PA=PC
Saturation
of A-C
C isolated
The less expensive
of A or B exports
towards the other
PA=PB
Saturation
of A-B
- 91 -
The algorithm tree given below summarizes all the possible paths in the second case:
A C B
A B CA B C
It is important to notice that in every case, if the three prices become equal, the algorithm
stops.
Selection of the importation bids by price on
the Net Importation Curves of B and C
Transmissions on the lines A-B and A-C
Saturation of A-B Saturation of A-C
Selection of the importation bids by price on
the Net Importation Curves of B and C
Transmissions on the lines A-C + C-B if the
offer is in B or only A-C if the offer is in C
Case 2
ABBC PPPP −<−
B and C import from A
Saturation of
C-B Saturation
of A-C
B isolated
A exports
to C
PA = PC
Saturation
of A-C
A isolated
The less expensive
of B or C exports
towards the other
PB = PC
Saturation
of B-C
Selection of the importation bids by price on
the Net Importation Curves of B and C
Transmission on the lines A-B + B-C if the
offer is in C or only A-C if the offer is in B
Saturation of
B-C
Saturation
of A-B
C isolated
A exports
to B
PA = PB
Saturation
of A-B
A isolated
The less expensive
of B or C exports
towards the other
PB = PC
Saturation
of B-C
- 92 -
Appendix 4
Incremental process: non-congested case
Step 0
The marginal price of markets A, B and C are respectively 10€/MWh, 20€/MWh and
60€/MWh. Market C is prone to import using cheap offers from markets A and B.
Commercial capacities on lines A�C , A�B and B�C are respectively Q°A�
C =1400MW,
Q°A�
B =510MW and Q°B�
C =1000MW.
Step 1
340MW of offers from market A are accepted to match bids from market C. PA=20€/MWh,
PB=20€/MWh and PC=60€/MWh. The remaining commercial capacity on line QA�
C is then
equal to 1060MW.
Step 2
170MW of offers from market B are accepted to match bids from market C. PA=20€/MWh,
PB=30€/MWh and PC=50€/MWh. The remaining commercial capacity on line QB�
C is then
equal to 830MW.
Step 3
170MW of offers from market A are accepted to match bids from market C. PA=30€/MWh,
PB=30€/MWh and PC=50€/MWh. The remaining commercial capacity on line QA�
C is then
equal to 890MW.
Step 4
170MW of offers from market B are accepted to match bids from market C. PA=30€/MWh,
PB=40€/MWh and PC=50€/MWh. The remaining commercial capacity on line QB�
C is then
equal to 660MW.
Step 5
170MW of offers from market A are accepted to match bids from market C. PA=40€/MWh,
PB=40€/MWh and PC=40€/MWh. The remaining commercial capacity on line QA�
C is then
equal to 720MW. The price of the three markets is the same, and no transmission constraint
has been reached. The markets are “coupled”. The algorithm stops.
- 93 -
Appendix 5
Incremental process: congested case
Step 0
The marginal price of markets A, B and C are respectively 10€/MWh, 20€/MWh and
60€/MWh. Market C is prone to import using cheap offers from markets A and B.
Commercial capacities on lines A�C , A�B and B�C are respectively :
Q°A�
C =400MW, Q°A�
B =110MW and Q°B�
C =1000MW.
Step 1
340MW of offers from market A are accepted to match bids from market C. PA=20€/MWh,
PB=20€/MWh and PC=60€/MWh.
Q1
A�
C =60MW, Q1
A�
B =110MW and Q1
B�
C =1000MW.
Step 2
170MW of offers from market B are accepted to match bids from market C. PA=20€/MWh,
PB=30€/MWh and PC=50€/MWh.
Q2
A�
C =60MW, Q2
A�
B =110MW and Q2
B�
C =830MW.
Step 3
170MW of offers from market A are accepted to match bids from market C. PA=30€/MWh,
PB=30€/MWh and PC=50€/MWh. The remaining capacity between A and C is not large
enough to support the market needs. Thus, a part of the transaction between A and C is
transiting through zone B. 60MW of this transaction uses the available capacity on the line
A�C, whereas uses 110MW of capacity on the lines A�B and B�C.
Q3
A�
C =0MW, Q3
A�
B =0MW and Q3
B�
C =720MW.
Step 4
170MW of offers from market B are accepted to match bids from market C. PA=30€/MWh,
PB=40€/MWh and PC=50€/MWh.
Q4
A�
C =0MW, Q4
A�
B =0MW and Q4
B�
C =550MW.
Step 5
170MW of offers from market A should be accepted to match bids from market C, but there is
no transmission capacity left between A and C, even through B. 45MW of offers from market
A should be accepted to match bids from market C. PA=30€/MWh, PB=40€/MWh and
PC=40€/MWh.
Q5
A�
C =0MW, Q5
A�
B =0MW and Q5
B�
C =505MW.
The prices of the three markets are different, and transmission limits have been reached on
lines A�C and A�B. The markets are not “coupled”. The algorithm stops.
- 94 -
REFERENCES
[1] Yann Rebours, Description technique des services système en Europe et aux Etats-Unis -
Réglage de la fréquence et de la tension, September 2005
[2] Yann Rebours, Survey of Remuneration of system service, October 2005
[3] National Grid, Electricity Balancing Services Contracts Information Pack, June 2007
http://www.nationalgrid.com/uk/Electricity/Balancing/services/
[4] Elexon, Balancing and Settlement Code, 2007
http://www.elexon.co.uk/bscrelateddocs/BSC/default.aspx
[5] National Grid, Grid Code, 2007
http://www.nationalgrid.com/uk/Electricity/Codes/
[6] NETA: www.bmreports.com
[7] National Grid, Balancing Services Adjustment Data Principles, 2007
http://www.nationalgrid.com/uk/Electricity/Balancing/services/
[8] National Grid, Procurement Guidelines, 2007
http://www.nationalgrid.com/uk/Electricity/Balancing/transmissionlicensestatements/
[9] ETSO, Balance Management in Europe, 2003
http://www.etso-net.org/activities/BalanceManagement/e_default.asp
[10] ETSO, Balance Management Harmonisation, 4th
Report, January 2007
http://www.etso-net.org/activities/BalanceManagement/e_default.asp
[11] Elexon, Overview of Trading Units, 2006
http://www.elexon.co.uk/Publications/InformationSheets/default.aspx
[12] Elexon, Parties and Participation, 2006
http://www.elexon.co.uk/participating/MarketEntryExit/default.aspx
[13] National Grid, Balancing services adjustment data methodology statement, 2007
http://www.nationalgrid.com/uk/Electricity/Balancing/transmissionlicensestatements/
[14] Elexon, Overview of System Sell and System Buy Prices, 2006
http://www.elexon.co.uk/Publications/InformationSheets/default.aspx
[15] VDN (Verband der Netzbtreiber), Procurement of control power in Germany, june 2005
http://www.vdn-berlin.de/
[16]www.regelleistung.net
- 95 -
[17] www.rwetransportnetzstrom.com
[18] www.bundesnetzagentur.de
[19] Holger Berndt, Grid economist ,[email protected] ,E.ON Netz GmbH
[20] VDN , Transmission Code 2003
http://www.vdn-berlin.de/
[21] VDN ,Vertrag über die Vorhaltung und Erbringung von Windreserve für den Zeitraum
http://www.vdn-berlin.de/
[22] Stefan Kräupl , Grid economist, [email protected], E.ON Netz GmbH
[23] www.wind-energie.de
[24] Dr. Hans Auer , Modeling system operation cost and grid extension cost for different
wind penetrations based on GreenNet, 2004
[25] Belpex, ApX, Powernext, Trilateral coupling of the Belgian, Dutch and French
electricity markets, 14 th February 2007
[26] ETSO, Current Congestion Management Methods, Update 2006
http://www.etso-net.org/activities/congestion_management/e_default.asp
[27] Belpex, Powernext, ApX, Trilateral Coupling Algorithm Appendix , September 2006
[28] Marc Andreewsky, Jeremy Louyrette, EDF R&D, Premier Retour d'Expérience sur le
Couplage des Marchés France - Belgique -Pays-Bas, April 2007
[29] Hans-Jürgen Haubrich, Technical issues regarding Open Market Coupling, April 2006