MONTHLY
COMPLIANCE TOPICS
DECEMBER 2015
12. Scaffolding, including portable scaffolding
CC Forum No 38
17th December 2015
400 kV DC OHL New RUWAIS G/S - New MIRFA G/S
Contract No. N 12305/ A
Schedule for Conductor and OPGW stringing in Section 157-159
for 400 kV OHL New Ruwais G/S – New Mirfa G/S
crossing
220 kV OHL Ruwais-Elixir 1&2 ; 220 kV OHL Mirfa-Medinat Zayed
and 220 kV OHL Mirfa –Baab2
CC Forum No 38
17th December 2015
CC Forum No 38
17th December 2015
AD EHSMS RF – CoP 26.0 - ScaffoldingRoles and responsibilities
ETS specializes in Scaffolding for Overhead Transmission Lines and
Scaffolding material used by ETS is the heavy duty tubular scaffold
popularly known in the market as the Cup Lock System.
CC Forum No 38
17th December 2015
AD EHSMS RF – CoP 26.0 - Scaffolding
- Design drawings
- Site Survey
- Plans of Services (existing OHL)
- All relevant authorities and utility
services (TRANSCO, Gasco) were
informed and approvals (NOCs,
LAP/PtW) were obtained before
every work stage started.
CC Forum No 38
17th December 2015
AD EHSMS RF – CoP 26.0 - ScaffoldingScaffolding general requirements
Scaffolding material properly unloaded
Scaffolding material
properly stocked
Scaffolding material
properly prepared for assembly
CC Forum No 38
17th December 2015
AD EHSMS RF – CoP 26.0 - ScaffoldingScaffolding general requirements
Even ground and wood platforms for
each base of the scaffolding towers
All scaffolding towers were
provided with grounding rods
CC Forum No 38
17th December 2015
AD EHSMS RF – CoP 26.0 - ScaffoldingScaffolding general requirements
Ensure that all bracings and ties properly installed
CC Forum No 38
17th December 2015
AD EHSMS RF – CoP 26.0 - ScaffoldingScaffolding general requirements
Anchorage of the scaffolding – concrete block and steel wire ropes
CC Forum No 38
17th December 2015
AD EHSMS RF – CoP 26.0 - ScaffoldingScaffolding general requirements
Ladders, resting platforms and top-working platforms
CC Forum No 38
17th December 2015
AD EHSMS RF – CoP 26.0 - ScaffoldingScaffolding general requirements
Guardrails and working at height PPE
CC Forum No 38
17th December 2015
AD EHSMS RF – CoP 26.0 - ScaffoldingScaffolding general requirements
Scafftags and regular inspection of the scaffolding towers
CC Forum No 38
17th December 2015
AD EHSMS RF – CoP 26.0 - ScaffoldingSafety documents
Application for work Limit Access Permits
CC Forum No 38
17th December 2015
AD EHSMS RF – CoP 26.0 - ScaffoldingSite trainings
Toolbox Talk Safety Induction
Working at Height Traning
CC Forum No 38
17th December 2015
AD EHSMS RF – CoP 26.0 - ScaffoldingSite inspections
Conductor Stringing
Coordinator
Site Manager
Transco and Lahmeyer