Emergency Power Systems 101 An Overview of Emergency Power Systems Craig Ayers, MHA, CHFM, CHSP, CPO

Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

  • Upload
    others

  • View
    8

  • Download
    1

Embed Size (px)

Citation preview

Page 1: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

Emergency Power Systems 101An Overview of Emergency Power SystemsCraig Ayers, MHA, CHFM, CHSP, CPO

Page 2: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

Emergency Power Systems

• Purpose

• Generators

• Distribution

• Transfer switches

• Maintenance and testing

• Contingency planning

Page 3: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

GeneratorIndoor

• Indoor units

• Parallel Units

Page 4: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

GeneratorsOutdoor

• Day tank

• No day tank

Page 5: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

GeneratorsStarters

• Battery start type starters

Page 6: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

GeneratorsBatteries

• Batteries (maintenance free and conventional).

• Test batteries by using specific gravity or load testing.

• Usually the weakest link with generator failure.

• Keep clean and frequently check for corrosion.

• Replace every couple of years.

Page 7: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

GeneratorsBattery Chargers

• Float chargers

• Make sure operates properly

• Should be on life safety branch

Page 8: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

GeneratorsStarters

• Air start generators uses air pressure to turn starter.

Page 9: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

GeneratorsStarters

• Air compressor setup for air start generator

• Compressed air storage tank (enough for two starting cycles)

• Electric motor on emergency power.

• Gasoline power motor for backup.

Page 10: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

GeneratorsJacket Heaters

• Jacket heaters keep the generator warm for quick starts.

• Heaters can sometimes have a high failure rate as elements tend to burn our over time.

• Can be easily checked by touching the engine (90 -110 degrees)

• Multimeter can be used to troubleshoot.

Page 11: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

GeneratorsJacket Heaters

• Diesel engines were originally designed for vehicles. In this application, they are equipped

with a starting aid (glow plugs or ether). Operating manuals for diesel vehicles recommend

the engines be allowed to idle until warm. This warm-up period is needed to allow dissimilar

metals in the engine to expand to proper operating tolerances.

• Unlike a vehicle, when there is a power failure, there is no opportunity to warm-up: it needs to

carry a load immediately. Thus almost all emergency diesel generators are installed with

inexpensive resistance heaters to maintain the generator at a consistently warm temperature.

This is needed to insure a safe and reliable split-second start-up, and to prevent 'cold start

wear.'

• Depending on the size and environment of the emergency diesel generator, more than one

resistance heater may be needed. In engines with two resistance heaters, one heater usually

carries more of the load, running longer than the second heater.

• Factory specifications typically recommend that heaters engage at 90°F and turn off at 110°F.

Installation specifics such as engine location, make, and model effect starting characteristics,

so the optimal temperature range may vary, however there is no redundancy built in these

systems (GTS, 2007)

Page 12: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

GeneratorsFuel Storage and Distribution

• Above ground.

• Below ground.

• Can serve single or multiple generators.

• Size and location are considerations when designing fuel storage systems.

• Must meet EPA standards.

Page 13: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

GeneratorsFuel Transfer Pumps

• Pumps should be on the life safety branch.

• Should be checked for operation on a routine basis.

• Location of pumps should be considered when designing systems.

• Redundant pumps for backup operation.

Flow indicator

Page 14: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

• Pump controls can be stand alone with on/off status and controls.

Page 15: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

GeneratorsDistribution Systems

• Pump controls can be a combination of controls and alarms for pumps and fuel tank management.

Main tank fuel supply

Pump status

Page 16: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

GeneratorsParallel Setup

• What is it?

– Connecting two or more generator sets together on a single distribution circuit.

– Generators voltage and frequency must be synced together using paralleling gear.

– Similar to utility company generator arrangements.

– Newer technologies using data connections make paralleling generators.

Page 17: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

GeneratorsParallel Setup

ASCO,

Page 18: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

GeneratorsParalleling Gear

• Medium voltage paralleling gear.

Page 19: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

GeneratorsParallel Setup

• The easiest way to setup a parallel system is to use generators that are exactly alike, or at least have the same output rating and alternator pitch. Another flexible approach to backing up your power requirements is to have two or more generators of variable output. In either scenario, these can be connected in parallel with paralleling switchgear to achieve maximum output during peak requirement or the desired minimal output during other times (Diesel Service, 2013)

Page 20: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

GeneratorsParallel Setup

• Benefits of parallel generators

– Reliability

– Expandability

– Flexibility

– Ease of Maintenance

– Cost effectiveness and Quality Performance

Page 21: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

DistributionTypical

Transfer Switches

Utility

Power Generator

Page 22: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

Transfer Switches

• Transfer switches are used to switch electrical loads from utility power sources to generator power sources.

• Transfer switches may be isolation bypass type, open transition, or closed transition type.

• Three or four pole

• Manual or automatic

• Phase monitoring

• May have built in exercise timers or battery chargers built in the switch.

Page 23: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

Transfer SwitchesBasic

• Basic transfer switch with no isolation bypass.

• Test switch and switch position indicators.

• Some may have retransfer switch.

Page 24: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

Transfer SwitchesIsolation Bypass

Page 25: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

Transfer SwitchesIsolation Bypass

• Isolation bypass switches provide a means to isolate the switch in order to provide maintenance while maintaining power to the load.

• Higher cost

• Larger design

• Bypass still requires periodic servicing.

Page 26: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

Transfer Switches

• Open Transition

– Most basic for small load profiles (most common)

– Short interruption when transferring.

• Delayed Transition

– For medium and large load profiles

– Longer interruption to let magnetic fields collapse on motors before transferring load.

• Closed Transition (make before break)

– Generator and utility power are connected when synchronized, then load shifts to generator.

– Can be used to avoid power disruptions during transfer.

– Used in life safety and critical processing loads.

Page 27: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

Transfer SwitchesOpen Transition

• Open transition transfer switches are designed to switch between the normally present power supply; which is being supplied to our homes by the power stations, and the backup arrangement in the form of some generator or anything.

• They operate between these two supplies depending upon the conditions, if the primary power supply is available or not.

• They have a switch which monitors the power sources and keeps a check so that whenever the primary source fails to deliver the power, it immediately switches to the backup set of generators.

• But the major difference that it has from the closed transition transfer switch is that, this switching is not performed immediately, instead there is a short break between the opening of one contact and the closing of the other (EEC, 2013)

Page 28: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

Transfer SwitchesClosed Transition

• A closed transition transfer switch also operates on the same principle as that of an open transition switch, except the fact that the delay which is incorporated in the open transition switch has been eliminated and hence the contacts occur without any delay in the time (EEC, 2013)

Page 29: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

Transfer SwitchesTiming

• General Time Setting (basic)

– When to start generator after power is off.

– After generator start and comes up to speed, when to transfer.

– When utility power restores, how long to retransfer back to utility power.

– How long to keep generator running (cool down time). Generator starting circuit will usually daisy chain to several transfer switches.

Page 30: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

Transfer SwitchesTesting and Servicing

• Must be operation once a month (12 times per year).

• Test switch is an acceptable method of simulating a power failure. It interrupts power to the power sensing board.

• Consider opening breaker occasionally.

• Should be inspected and services at regular intervals.

• Rotate the transfer switch use for starting each month.

• Have someone at the generator when testing switches to verify a good generator start.

Page 31: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

DistributionTypical

Electrical Branches

Utility

Power Generator

Page 32: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

DistributionLife Safety Branch

• Means of egress lighting

• Exit signs

• Fire alarms

• Medical gas alarms

• Mechanical, control, or other accessories required for effective life safety

• Communication systems (such as paging)

• Battery charger for task lighting at generator set

• Generator accessories – battery charger/fuel systems

• Elevator lighting, controls, communication, and signals

• Automatic doors used for egress (NFPA 70)

Page 33: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

DistributionCritical Branch

• Power for task illumination, selected receptacles, and fixed equipment in following areas:

– Infant nurseries

– Medication preparation areas

– Pharmacy dispensing areas

– Selected acute areas

– Psychiatric bed areas (omit receptacles)

– Ward treatment rooms

– Nurses’ stations

– Other patient care areas where needed (NFPA 70)

Page 34: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

DistributionCritical Branch

– General care patient beds (at least one receptacle)

– Angiographic labs

– Cardiac catheterization labs

– Coronary care units

– Hemodialysis rooms or areas

– Emergency room treatment areas (selected)

– Human physiology labs

– Intensive care units

– Postoperative recovery rooms (selected) (NFPA 70)

Page 35: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

Distribution Critical Branch

• Other areas and systems

– Nurse call systems

– Blood, bone, and tissue banks

– Telephone and data equipment

Page 36: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

DistributionEquipment Branch (Delayed Connection)

• Vacuum systems

• Sump pumps

• Compressed air systems (medical and control)

• Smoke control and pressurization systems

• Kitchen hood systems

• HVAC/exhaust for isolation rooms, protective environment rooms laboratory, pharmacy, nuclear medicine, ETO, operating and delivery rooms, and telephone and data rooms

• Heating equipment (NFPA 70)

Page 37: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

Testing and MaintenanceLoad Testing

• The monthly tests for diesel-powered emergency generators are conducted with a dynamic load that is at least 30% of the nameplate rating of the generator or meets the manufacturer’s recommended prime movers’ exhaust gas temperature. If the hospital does not meet either the 30% of nameplate rating or the recommended exhaust gas temperature during any test in EC.02.05.07, EP 4, then it must test the emergency generator once every 12 months using supplemental (dynamic or static) loads of 25% of nameplate rating for 30 minutes, followed by 50% of nameplate rating for 30 minutes, followed by 75% of nameplate rating for 60 minutes, for a total of 2 continuous hours. Note: Tests for non–diesel-powered generators need only be conducted with available load. (EC 02.05.07 EP5)

Page 38: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

Testing and MaintenanceLoad Testing

• At least once every 36 months, hospitals with a generator providing emergency power for the services listed in EC.02.05.03, EPs 5 and 6, test each emergency generator for a minimum of 4 continuous hours. The completion date of the tests is documented (EC 02.05.07 EP7)

Page 39: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

Testing and MaintenanceLoad Testing

• Annual

– 25% load for 30 minutes, then

– 50% load for 30 minutes, then

– 75% load for 60 minutes

• 36 Month

– 30% for 4 continuous hours

• You can combine the two tests but you must meet the 30% minimal load.

Page 40: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

Testing and MaintenanceFuel

• Checking a generator’s fuel delivery system periodically is an important aspect of generator maintenance. Common problems with generators are:

– Stored diesel fuel will deteriorate over time

– Sludge and water will accumulate on the bottom of the tank, and rust can form on the sides

– Bacteria and fungus can grow in the fuel itself (ESP, 2015)

• Beware of biofuels, they deteriorate quickly

• Consider annual fuel cleaning service

Page 41: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

Testing and MaintenanceEngine Oil

• Engine oil testing can determine the health of your engine and can predict failure in engine components.

• Antifreeze testing can determine the condition of the coolant and helps in preventing corrosion. Important to maintain coolant integrity.

Page 42: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

Testing and Maintenance

• Annual maintenance and load testing takes your generator out of service for possible power outages.

• Consider doing annual maintenance and load testing at the same time while utilizing a portable standby generator for emergencies.

Page 43: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

Contingency Planning

• Quick connect hook ups for portable generators make it easy for testing and provides a quick method for connection of portable generators.

• Quick connect box

• Transfer switch

Page 44: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

Contingency Planning

• Quick connect used with hypalon generator cables

Page 45: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

Contingency Planning

• Portable generators can supply power in the event of generator failure.

• Providing electrical connections for scheduled maintenance and unscheduled outages makes the use of portable standby generators more proficient.

Page 46: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

Questions

Page 47: Emergency Power Systems 101 An Overview of Emergency …...connected in parallel with paralleling switchgear to ... switching is not performed immediately, instead ... •At least

References

Diesel Service (2013). Parallel Operation of Generator Sets: Diesel Service and Supply. Retrieved March 2, 2016 from:

http://www.dieselserviceandsupply.com/Parallel_Gensets.aspx

EEC (2013). Electrical Installation and Energy Efficiency: Electrical Engineering Community. Retrieved March 1, 2016 from;

http://engineering.electrical-equipment.org/panel-building/closed-transition-transfer-switch.html

EEC (2013). Electrical Installation and Energy Efficiency: Electrical Engineering Community. Retrieved March 1, 2016 from;

http://engineering.electrical-equipment.org/panel-building/open-transition-transfer-switch.html

ESP (2015). Fuel Testing: ESP Generators. Retrieved March 3, from http://espgenerators.com/fuel-testing/

GTS (2007). Heating Emergency Diesel Generators: Geothermal Systems. Retrieved March 21, 2016 from: http://gts-

heaters.com/GTS_White-Paper_v3-3.pdf

NFPA 70 (2014) National Electric Code