Emily M. Underhill2/11/2013 RSW Airport Traffic Control Tower (ATCT) 7/31/2021 (Construction) The tower precast shaft installation has progressed to the third ring, including interior

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

  • As news of COVID-19 continues to evolve, we want you to know the health of our passengers, airport business partners and visitors is a top priority. The Lee County Port Authority has increased the frequency of cleaning in high-traffic, high-touch areas. We encourage all of you traveling, working or visiting RSW to take the following personal precautions: Stay home if you are sick. Avoid touching your eyes, nose and mouth. Cover your cough or sneeze. Wash hands often and for at least 20 seconds. The Lee County Port Authority is monitoring the situation with information from the Center for Disease Control, World Health Organization and Florida Department of Health. For more information, please visit the Florida Department of Health or Centers for Disease Control & Prevention.

    Because We Care

    Image(s) Creative Commons, Wikimedia : Public Domain

  • April 21, 2020 Mr. Robbie Roepstorff Airports Special Management Committee Lee County Port Authority 11000 Terminal Access Road, Suite 8671 Fort Myers, Florida 33913 Dear Mr. Roepstorff: Attached is the Southwest Florida International Airport and Page Field Airport Monthly Project Summary for the month of April 2020. This report is prepared by the Lee County Port Authority Development Division each month and reflects the current status of work efforts, schedules and budgets for ongoing projects. If you have any questions regarding any of the attached information, please do not hesitate to contact me.

    Respectfully, LEE COUNTY PORT AUTHORITY

    Emily M. Underhill, P.E., A.A.E. Division Director, Development

    EMU/rrt cc: Airports Special Management Committee Benjamin R. Siegel, CPA, CM, Acting Executive Director Mark R. Fisher, A.A.E., Deputy Executive Director - Development

    Emily M. Underhill

  • • Airport Traffic Control Tower (ATCT)………………………...……………………………… 1• Rehabilitation of Airside Pavements………………...……………...……..………………… 2• Rehabilitation of Roads……………………………………………………………………… 3• Replacement of Passenger Boarding Bridges……………………………………………… 4• Skyplex Boulevard………………...……………...……..……………………….…………... 5• Terminal Building Expansion………………...……………...……..……………………….… 6

    • Page Field Airline Transport Professionals (ATP) Hangar…… 7• Page Field Peitz Hangar………………………………………… 8

    RSW Projects

    RSW Tenant Improvement Projects FMY Tenant Improvement Projects

    FMY Projects

    Sheet1

    RSW ProjectsFMY Projects

    • Baggage Handling System (BHS) Recapitalization And Optimization………………………...……………………………..…………………………121

    • Airport Traffic Control Tower (ATCT)………………………...…………………………………...…………………..…………………………1

    • Interim Security Checkpoint Imrpovements………………………...…………………………………...…………………..…………………………2

    • Maintenance Building Expansion………………………...…………………………………...…………………..…………………………3

    • Rehabilitation of Airside Pavements………………...……………...……..……………………….…………...…….…………………2

    • Rehabilitation of Roads……………………………………………………………………………………………………………………………3

    • RSW Rental Car Areas Relocation/Expansion and Associated Airport Improvements………………………………………………………………………4

    • Replacement of Passenger Boarding Bridges……………………………………………………………………………4

    • Skyplex Boulevard………………...……………...……..……………………….…………...…….………………………………….5

    • Terminal Building Charging Stations………………………………………………………………………………………….54

    • Terminal Building Expansion………………...……………...……..……………………….…………...…….………………………………….6

    • Ticket Counter and Gate Podium Modernization……………………….…...……………...……..……………10

    • Terminal Access Road (TAR) Six-Lane Expansion ………………………..……………………………………10

    • Static Signage Updates…………………………………..…………….……………………………...……………………………….13

    RSW Tenant Improvement ProjectsFMY Tenant Improvement Projects

    13

    • Airport Plaza Gas Station………………………………………………………...…………………………………………………..13

    • Florida Power & Light Co. Upgrades…………………………………………………………………………………………..14

    • Southwest/AirTran Airlines Merge…………………………………………………………………………………………..17

    • Tile Remediation………………………………………………………...……………………..…………………………19

    • FDOT Interstate 75 Connector Roadway ……………………………..………………………………………………11

    • Hertz Car Rental Area Upgrades ………………………………………..……………….……………………………………15

    • Tile Remediation …………………………………………..……………………..……………………….……………………………………15

    • Skyplex LLC - Gartner..……………………………………………………………..……..……………………….…………...…….…………………11

    • Skywalk Shopping Center..……………………………………………………………..……..……………………….…………...…….…………………10

    • Page Field Airline Transport Professionals (ATP) Hangar…………………………………………………………..7

    • Page Field Peitz Hangar…………………………………………………………..8

  • Project Description:

    Project Status:

    Consultant:

    Start Date: Completion Date:

    2/11/2013

    RSW Airport Traffic Control Tower (ATCT)

    7/31/2021 (Construction)

    The tower precast shaft installation has progressed to the third ring, including interior walls and stairs. The TRACON underground utilities have been installed and the building slab pour is near completion. TRACON precast walls and structural steel erection has begun. Miscellaneous site work also continues. The work has continued at the anticipated pace. There have been no delivery delays or manpower shortage to date. Virtual weekly project meetings have been implemented. Last updated by Joe Glowacki via email on Mar 24, 2020, 9:19 AM

    Total Estimated Cost: Total Authorized To Date:

    Remaining Balance to Finish:

    AECOM Technical Services, Inc.

    This project provides for design services, environmental permitting, mitigation, and construction of a new Airport Traffic Control Tower (ATCT) and Terminal Radar Approach Control Facility (TRACON) located midfield between existing runway and the future parallel runway.

    COSTS / BUDGET

    FAA Grants: FDOT Grants: LCPA Funds: Other Funds:

    $0.00 $32,702,813.00 $41,975,767.00

    $0.00

    $75,152,983.00 $5,010,711.00

    $80,163,694.00

    CM/GC: DeAngelis Diamond

    Development Division - April 2020 1 RSW Airport Traffic Control Tower (ATCT)

  • Project Description:

    Project Status:

    Consultant:

    Start Date: Completion Date:

    4/5/2017

    RSW Rehabilitation of Airside Pavements

    3/31/2020 (Design Only)

    Final bidding documents have been received for both the Rehabilitation of Taxiways A, F and G2 project, and the New Airfield Lighting Vault project. Both projects have been publicly advertised starting on March 19, 2020. A pre-bid meeting for the Rehabilitation of Taxiways A, F and G2 will be held on April 2 with bids due on April 30, 2020. A pre-bid meeting for the New Airfield Lighting Vault will be held on April 9 with bids due April 23, 2020. The goal is to take both construction projects to the August ASMC and September Board meetings for their approval. The construction Notice to Proceed (NTP) is anticipated to be issued in October 2020 for both projects.

    Total Estimated Cost: Total Authorized To Date:

    Remaining Balance to Finish:

    Kimley-Horn & Associates

    RSW has a network of airside pavement infrastructure (taxiways and aircraft parking aprons) that has been constructed at various times from as early as 1979 (during the original RSW construction) through 2005 (as part of the Midfield Terminal construction). Maintaining these pavement areas is critical to the safe continued operation of aircraft at RSW. This project will evaluate all pavement and recommend rehabilitation measures to correct existing pavement distresses and extend the useful life of airport infrastructure.

    COSTS / BUDGET

    FAA Grants: FDOT Grants: LCPA Funds: Other Funds:

    $2,700,387.00 $1,534,922.00 $1,533,922.00

    $0.00

    $5,708,995.00 $28,238,892.00

    $33,947,887.00

    CM/GC: Owen-Ames-Kimball Co.

    Development Division - April 2020 2 RSW Rehabilitation of Airside Pavements

  • Project Description:

    Project Status:

    Consultant:

    Start Date: Completion Date:

    10/27/2016

    RSW Rehabilitation of Roads

    4/30/2020 (Design Only)

    LCPA staff reviewed the administrative amendment draft package submitted by the consultant. It was then submitted to Lee County staff for comments. A determination from Lee County is expected by May 2020. The fountain design progress set was received on March 23, 2020. The 100% plans are anticipated to be complete by the end of April 2020. Last updated by George Gorayeb via spreadsheet on 3/23/2020.

    Total Estimated Cost: Total Authorized To Date:

    Remaining Balance to Finish:

    Johnson Engineering, Inc.

    The Southwest Florida International Airport has a network of public, non-public, landside and airside roadways that serve the vehicular transportation needs of its patrons, employees, and other customers. The landside roadway infrastructure has been constructed at various times from 1979 through 2005. This project will plan for the necessary rehabilitative measures to correct existing pavement distresses in order to maintain the level of service needed.

    COSTS / BUDGET

    FAA Grants: FDOT Grants: LCPA Funds: Other Funds:

    $0.00 $998,234.00

    $1,173,792.00 $0.00

    $2,172,026.00 $25,911,022.00

    $28,083,048.00

    CM/GC: Owen-Ames-Kimball Co.

    Development Division - April 2020 3 RSW Rehabilitation of Roads

  • Project Description:

    Project Status:

    Consultant:

    Start Date: Completion Date:

    3/21/2019

    RSW Replacement of Passenger Boarding Bridges

    12/31/2019 (Design Only)

    The project scope and fees have been negotiated. The legal advertisement was published on March 17, 2020. A pre-bid meeting is scheduled for April 8. 2020. The bid opening is anticipated for April 30, 2020. Last updated by George Ghorayeb via spreadsheet on 3/23/2020.

    Total Project Budget: Total Authorized To Date:

    Remaining Balance to Finish:

    Aero Systems Engineering, Inc.

    The original boarding bridges procured during the Midfield Terminal project needed to be replaced, as recommended by a Kimley-Horn assessment of the 27 bridges. Aero Systems was selected to prepare design documents to replace all of the boarding bridges along with the auxiliary equipment, such as ground power units (GPU) and preconditioned air units (PCA). In the process, Aero will also review the current fleet mix for each gate and determine if any changes can be made to maximize gate usage.

    COSTS / BUDGET

    FAA Grants: FDOT Grants: LCPA Funds: Other Funds:

    $0.00 $0.00

    $1,430,106.00 $0.00

    $1,430,106.00 $43,921,079.00

    $45,351,185.00

    CM/GC: Manhattan Construction (Florida), Inc.

    Development Division - April 2020 4 RSW Replacement of Passenger Boarding Bridges

    Teresa JimenezDrawing of PBB is example- do we have something like this of the actual proposed PBB?

  • Project Description:

    Project Status:

    Consultant:

    Start Date: Completion Date:

    4/11/2012

    RSW Skyplex Boulevard

    4/30/2020

    The fabrication of the aluminum architectural "blades" on the bridge pillars was held up due to complications with the aluminum acquisition. Two of the four "blades" have been installed. Substantial completion will be held upon completion of all four pillar blades, which the CM/GC is anticipating by mid April 2020. Last updated by George Ghorayeb via spreadsheet on 3/23/2020.

    Total Project Budget: Total Authorized To Date:

    Remaining Balance to Finish:

    David Douglas Associates, Inc.

    This project will include permitting and environmental approval, roadway, drainage, utility, landscaping, signage, marking and lighting design for Skyplex Boulevard between Daniels Parkway and Chamberlin Parkway.

    COSTS / BUDGET

    FAA Grants: FDOT Grants: LCPA Funds: Other Funds:

    $0.00 $6,807,492.00 $6,808,443.00

    $0.00

    $13,615,936.00 $610,610.00

    $14,226,546.00

    CM/GC: Wright Construction

    Development Division - April 2020 5 RSW Skyplex Boulevard

  • Project Description:

    Project Status:

    Consultant:

    Start Date: Completion Date:

    3/9/2017

    RSW Terminal Building Expansion

    6/30/2020 (Design Only)

    Ongoing negotiations of the scope and fees for the Contruction adminstration (CA) and Construction Management (CM) are in progress. The construction drawings and specifications have been resubmitted to Lee County Development staff for review and comments. The bid packages are currently being finalized. On April 7, 2020, based on the decrease of RSW passengers due to the world health crisis, the Board approved to delay the bidding of the construction for one year or until such time when passenger volumes, and corresponding revenues, return.

    Total Estimated Cost: Total Authorized To Date:

    Remaining Balance to Finish:

    Atkins North America, Inc.

    The increase in passenger volume within limited corridor spaces during peak hour operations has negatively impacted the terminal’s functionality. There are conflicting passenger flow patterns, insufficient space to provide additional screening for passengers within the limits of the security screening checkpoint areas, insufficient length of queuing, and the building systems are challenged to support peak hour passenger volume. The Lee County Port Authority is also seeking to increase concession amenities for the general pubic.

    COSTS / BUDGET

    FAA Grants: FDOT Grants: LCPA Funds: Other Funds:

    $0.00 $0.00

    $14,888,582.00 $0.00

    $14,888,582.00 $222,227,627.00

    $237,116,209.00

    CM/GC: Manhattan Construction (Florida), Inc.

    Development Division - April 2020 6 RSW Terminal Building Expansion

  • Consultant: Structures International, Inc.

    Airline Transport Professional Holdings (ATP), Inc. will build a 20,792 square foot flight school facility and associated hangar. The new flight school will be located on the north ramp at Page Field airport.

    Project Description:12/31/2020Completion Date:

    12/26/2019Start Date:

    Page Field AirlineTransport Professionals (ATP) Hangar

    Project Status:

    ATP has put out a Request for Proposals (RFP) for contractors to bid on the new facility. Bids have been received and will take 60-90 days before issuing a contract..pdated By Tracy James: 3/24/2020 11:29:21 AM

    Contractor: TBA

    Development Division - April 2020 7 Page Field AirlineTransport Professionals (ATP) Hangar

  • Consultant: Barbot, Steuart & Associates

    This project consists of the construction of a 8,800 SF corporate hangar on the North side of Page Field.

    Project Description: 5/1/2020 Completion Date:

    11/4/2019 Start Date:

    Page Field Peitz Hangar

    Project Status:

    Work in the office part of the hangar continues with drywall, ceiling grids, and overhead lighting. The hangar has been insulated and the doors have been installed. The next step will be to start working on the underground utilities bringing power and water to the building. Work on the apron will continue to provide access to the taxiway. Last Updated By Tracy James: 3/24/2020

    Contractor: Better Buildings, Inc.

    Development Division - April 2020 8 Page Field Peitz Hangar