Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
energizeEASTSIDEproject newsletter
Summer 2017pse.com/energizeeastside
Summer 2017 project update
About Energize Eastside
The Eastside is outgrowing the backbone of the area’s electric grid. Energize Eastside will build a new substation, upgrade existing transmission lines, and continue aggressive conservation efforts to keep Eastside lights on and foster economic development for years to come.
We’ve selected the existing corridor as our final route
After nearly four years of study and extensive dialogue with Eastside communities, PSE has selected the existing corridor “Willow 1” route as the final route to permit for Energize Eastside.
Multiple independent studies have made it clear that we need to upgrade the Eastside’s electric infrastructure now to accommodate local population and economic growth and avoid planning for power outages in the very near future.
The existing corridor is the least impactful route to Eastside communities
PSE evaluated multiple route options and selected the existing corridor because it is the least impactful route to Eastside communities. Our decision was guided by two key factors:
1. Our commitment to safety. The project will be built and operated to the highest safety and engineering standards. Using the existing corridor, along with optimized designs and operations, the project can safely co-exist with the Olympic Pipeline.
2. Our commitment to limit impacts to the environment. This route affects the fewest trees and avoids the construction of new corridors. We know our customers value trees. Our goal is for there to be more trees when the project is complete, not fewer.
PSE will replace the poles in the existing corridor
Our plan is to upgrade the existing four wooden poles to one or two steel poles, which allows us to have fewer poles within the existing corridor. PSE is committed to keeping pole heights as low as possible. New poles will typically be in the same or similar locations as the existing poles.
##
#!(!(
!(
!(
!(
#*
VU520
SammamishSubstation(existing)
LakesideRichards Creek
§̈¦405
124t
hA v
eN
E
1 02n
dAv
eN
E
132n
d Av
e N
E
N E 8th St
106t
hAv
eN
E
Bellevue
Way SE
166t
hAv
eN
E
S E 24th St
2ndAve S
N E 51st St
Northup Way
N E 83rd St
Slat
erAv
eN
E
NE 109th St
Lake
Hills
Bl
vd
EM
erce
rW
ay
N E 60th St
156t
h Av
e S
E
NE 12thSt
Ric
h ar d
s R
d
N E 80th St
Avon
dal
Wa
S E 8th St
104 t
hAv
eSE
132n
d Av
e N
E
166 t
h Av
e N
ESE 37th St
173r
dAv
eN
E
116t
h Av
e N
E
15thAve
NE 68th St
Sta t
eSt
SE 35thPl
160th
AveN
E
S E 22nd St
148 t
h Av
e N
E
1 08t
h Av
e N
E
140 t
h Av
e N
E
S E Eastgate Way
128t
h Av
e N
E
BellevueW
aySE
108 t
hAv
eSE
S E 16th St
SE 34th St
148 t
h Av
e N
E
N E Redmond Way
NE 1stSt
140t
hA v
eSE
S E 24th St
172n
dA v
eN
E
NE 53rd St
NE 104th St
3rd
St
171s
t Ave
NE
108t
hAv
eN
E
SR 202
139t
h Av
e S
E
NE38th Pl
106th
AveSE
132 n
d A v
e N
E1 3
4th
Ave
NE
116t
h Av
e N
E
124t
h Av
e N
E
145th Pl SE
156 t
h A v
S e
E
SE 38thSt
108t
hAv
eN
E
N E 87th St
148t
h Av
e S
E
NE 4thSt
Central Way
140t
h Av
e N
E
156t
h Av
EN
eN
EO
ld
Red
mon
d R
d
N E 80th St
S E 17th St
N E 8th St
158th
Ave NE
161s
t Av
e N
E
N E 40th St
124t
h Av
e N
E
N E 51st St
130t
h A v
e N
E
120t
h Av
e N
E
1 52 n
d A v
e N
E
128 t
h A v
e S
E
NE 52nd St
Main St
126t
h Av
e SE
NE 40 ht St
126t
h Av
e N
E
168 t
h A v
e S E
NE
Bellevue
Redm
ondR
d
EN 24th StN E 24th St
164 t
h A v
e N
E
112t
h Av
e SE
156t
h Av
e N
E
N E 70 htPl
116t
h Av
e N
E
N E 90th St
N E 100thSt
Lake
vie w
DrN
E
148t
h Av
e N
E
S E 14th St
NE 10 htSt
N E 60th St
18th Ave N E 100th St
Leary
Way NE
N E 70th St
vA ht651
e N
E
124t
h Av
e N
E
Willows Rd NE
Northup Way
N E 8th St
NE 95th
112t
h Av
e N
E
Railroa
d Ave
120t
h Av
e N
E
N E 95th St
156t
h Av
e N
E
S E 34th St
8th
St S
N E 30th St
122 n
d Av
e N
E
Kam
be r R
d
N E 2nd St
Be
ellvu
eW
ayN
E
Killarney
Way
SE 25th St
164t
h Av
e N
E
NE 104th St
140t
h Av
e SE
LakeW
ashin gton
BlvdN
E
SE 38th St
N E 60th St
142n
dP l
S E
N E 70th Pl
166t
h Av
e N
E
148t
h A v
e SE
Forbes Creek Dr
Bell e
v ue
Wa y
NE
N E 97th St
108t
h Av
e N
E
N E 85th St
104t
hAv
eS
E
140t
h Av
e N
ES E 12th St
Lake Hills Blvd
120t
h Av
e N
E
N E 100th St
Main St
170t
hAv
eN
E
N E 90th St
N E 4th StFa
ctor
iaBl
vdSE
7th Ave
148t
h A v
e N
E
N E 79th St
118t
h A v
e S
E
164t
h A v
e S
E
9 htAve S
Bea r Creek Pkwy
N E 24th St
148 t
h Av
e N
E
108t
hAv
eN
E
Wes
tLak
eS
amm
amis
hP
kwy
SE
N E 80th St
N E 1st St
5th Pl
Bellev
ue
Redmon
d Rd
ES1s
t St
N E 20th St
SE 8th St
12th Ave
154th Ave NE
N E 85th St
SE 36th St
Main St
N E 12th St
Lake Hills
Connector
150t
hAv
eSE
Bellevue
Redmond Rd
112t
h Av
e N
E
BeauxArts
Bellevue
Kirkland
Redmond
SwanLake
LarsenLake
MercerSlough
PhantomLake
ForbesLake
LakeBellevue
SammamishRiver
Lake HillsGreenbelt
Park
BannerwoodBallfield
Park
KelseyCreekPark
Mercer SloughNature Park
Robinswood Park
North RoseHill Park
EverestPark
Grass LawnCommunity
Park
Bridle CrestTrail Site -Redmond
RedmondCentral
Connector
MarymoorPark
BellevueMunicipal
Golf Course
BridleTrails
State ParkWatershed
Park
ArdmorePark
CrossroadsPark
ViewpointPark -
Bellevue
EastsideRail
Corridor
HiddenValleyPark
WilburtonHill Park
WestSammamish
Trail Site
Redmond PSETrail Site
¯
July 2017
LegendC-1 structures, one double circuit
C-1B structures, one double circuit
C-2 structures, two single circutis
C-16 structures, two single circuits
C-18 structures, two single circuits
!( C-2 structure
!( C-17 structure
!( C-18 structure
# Existing substation
#* Richards Creek substation (new)
SEGMENT 1: WILLOW 1 ROUTEThe Energize Eastside project will upgrade existing transmission lines from the Sammamishsubstation in Redmond to the Talbot Hill substation in Renton and connect in the middle withthe Richards Creek substation.
NOTE: These maps are for illustrative purposes only. Preliminary route, pole types, andpole heights are subject to change pending design, engineering, and environmental review.For highway crossings, pole type and heights vary.
# RichardsCreek
§̈¦405
VU520
§̈¦405
§̈¦90
SR 900
SR 169
BeauxArts
Bellevue
ClydeHill
HuntsPoint
Medina
MercerIsland
Newcastle
Redmond
Redmond
Rent
Renton
YarrowPoint
Lakeside
Sammamish
TalbotHill
LakeSammamish
LakeWashington
Soos CreekPark and
Trail
CougarMountain Regional
Wildland Park
MarymoorPark
BridleTrails
State Park
Focus area: Segment 1
LEGEND
Transmission linechanges from twosingle-circuittransmission linesto one double-circuittransmission line.
C-16 structures,two single-circuittransmission lines.
C-1 and C-1B structures,double-circuittransmission line
C-1 structures,double-circuittransmission line.
Transmission linechanges from onedouble-circuittransmission line totwo single-circuittransmission lines.
Energize Eastside project route
PSE selected the existing corridor, known as the “Willow 1” route, as the final route to permit for Energize Eastside.
Existing substation
New substation
Final route
Legend
pse.com/energizeeastside
Photo simulations are for discussion purposes only and may change pending public, regulatory and utility review
Existing Conditions
7/7/2017
Conceptual Project – Weathering Steel
Photo simulations are for discussion purposes only and may change pending public, regulatory and utility review 7/7/2017
Conceptual Project – Galvanized Steel
Time
Viewing Direction
Date
Address
3:07 PM
North
4/1/2014
1026 Monroe Ave NE, Renton
Existing Pole Heights ~55 feet
Proposed Pole Heights ~90 feet
3KOP
SEGMENTSOUTH 12
Pole Heights: Existing Conditions ~55 feet
Pole Heights: Conceptual Project ~85 feet 3
Photo simulations are for discussion purposes only and may change pending public, regulatory and utility review
Existing Conditions
7/7/2017
Conceptual Project
KOP SOUTH 19Time
Viewing Direction
Date
Address
10:28 AM
South
3/8/2016
SE 84th St, Newcastle
Existing Pole Heights ~55 feet
Proposed Pole Heights ~75 feet
SEGMENT 3
Photo simulation in Newcastle
Existing Conditions Conceptual Project
Photo simulations are for discussion purposes only and may change pending public, regulatory and utility review
Existing Conditions
2
7/6/2017
Conceptual Project
KOPSEGMENTCENTRAL 15Time
Viewing Direction
Date
Address
9:32 AM
North
4/10/2014
4489 137th Ave SE, Bellevue
Existing Pole Heights ~55 feet
Proposed Pole Heights ~75 feet
Photo simulations are for discussion purposes only and may change pending public, regulatory and utility review
Existing Conditions
2
7/6/2017
Conceptual Project
KOPSEGMENTCENTRAL 15Time
Viewing Direction
Date
Address
9:32 AM
North
4/10/2014
4489 137th Ave SE, Bellevue
Existing Pole Heights ~55 feet
Proposed Pole Heights ~75 feet
Photo simulation in Bellevue
Existing Conditions Conceptual Project
The photo simulations above show what the new transmission lines might look like, along with an image of existing conditions for comparison. Visit pse.com/energizeeastside to view additional photo simulations.
Photo simulations are for discussion purposes only and may change pending public, regulatory and utility review
Existing Conditions
7/7/2017
Conceptual Project – Weathering Steel
Photo simulations are for discussion purposes only and may change pending public, regulatory and utility review 7/7/2017
Conceptual Project – Galvanized Steel
Time
Viewing Direction
Date
Address
3:07 PM
North
4/1/2014
1026 Monroe Ave NE, Renton
Existing Pole Heights ~55 feet
Proposed Pole Heights ~90 feet
3KOP
SEGMENTSOUTH 12
Photo simulation in Renton
Existing Conditions Conceptual Project
Photo simulations are for discussion purposes onlyand may change pending public, regulatory and utility review
Existing Conditions
Photo simulations are for discussion purposes only and may change pending public, regulatory and utility review 7/7/2017
Conceptual Project
Time
Viewing Direction
Date
Address
10:49 AM
North
3/31/2014
13540 NE 54th Pl, Bellevue
Existing Pole Heights ~55 feet
Proposed Pole Heights ~90 feet
1KOP
SEGMENTNORTH 3
Photo simulations are for discussion purposes onlyand may change pending public, regulatory and utility review
Existing Conditions
Photo simulations are for discussion purposes only and may change pending public, regulatory and utility review 7/7/2017
Conceptual Project
Time
Viewing Direction
Date
Address
10:49 AM
North
3/31/2014
13540 NE 54th Pl, Bellevue
Existing Pole Heights ~55 feet
Proposed Pole Heights ~90 feet
1KOP
SEGMENTNORTH 3
Photo simulation in north Bellevue
Existing Conditions Conceptual Project
Summer 2017
Pole types and heights details
Redmond, south to SE Newport Way in Bellevue
• At each location, we’ll replace the existing four poles with one pole. Poles will typically be 90 feet to 100 feet in height.
Somerset
• At each location, we’ll replace the existing four poles with two poles. Poles will typically be 70 feet to 80 feet in height.
South Bellevue
Between Coal Creek Parkway and SE 60th Street:
• At each location, we’ll replace the existing four poles with one pole. Poles will typically be 90 feet to 100 feet in height.
South of SE 60th Street:
• At each location, we’ll replace the existing four poles with two poles. Poles will typically be 75 feet to 85 feet in height.
Newcastle, south to SE 100th Street in Renton
• At each location, we’ll replace the existing four poles with two poles. Poles will typically be 75 feet to 85 feet in height.
Renton
• At each location, we’ll replace the existing four poles with one pole. Poles will typically be 80 feet to 90 feet in height.
Through the years, we’ve heard residents express concerns about pipeline safety, tree impacts, views and pole heights. We’ve continued to evaluate engineering options and we were recently able to make changes to lower pole heights within the existing corridor. This route also removes the fewest trees. The combination of safety and fewer tree impacts make the existing corridor the reasonable choice.
Growth is straining the backbone of the Eastside’s electric grid. Energize Eastside will power the Eastside’s growth into the future.
We’re moving forward with permitting to keep the lights on
Reliable power is critical to Eastside communities’ health, safety and economic vitality. Now is the time to upgrade.
PSE’s last major upgrade to the backbone of the Eastside’s electric grid was in the 1960s. Since then, the Eastside’s population has grown eight-fold and our economy relies on power in ways it did not 50 years ago. Our customers have also learned to conserve energy and be increasingly more energy efficient. But it’s not enough.
PSE will soon submit permit applications for the southern portion of the project. PSE's plan is to build and energize the new Richards Creek substation and the southern portion of the transmission lines by summer 2018. We anticipate submitting permits for the northern portion later this year.
We need to build Energize Eastside in two construction phases to keep the backbone of the existing transmission system online and serving customers. By having the southern portion in service by next summer, we can avoid the need for rolling blackout plans. Once we’ve energized the southern portion of the project, we will begin work on the northern portion.
Questions for the project team
How is PSE working with property owners?
PSE continues to reach out to property owners along the existing corridor. We’re currently meeting with property owners to talk about landscaping and tree replacement planning for the project. As a responsible and respectful neighbor, we are reaching out to affected property owners to discuss their preferences and identify compatible vegetation to incorporate into these plans.
How will Energize Eastside affect rates?
Customers will not see an increase in their monthly bill as a direct result of Energize Eastside. That’s because PSE’s annual capital budget, which funds infrastructure upgrades, is already included in customer rates.
PSE is a heavily regulated investor-owned utility whose actions are carefully monitored and reviewed by the Washington Utilities and Transportation Commission (UTC). PSE’s rates are reviewed and approved by the UTC.
Summer 2017pse.com/energizeeastside
We’ll keep property owners and the community up to date on project progress
We appreciate the community's input and ongoing interest in Energize Eastside.
During permitting and as we prepare for construction, we’ll continue reaching out to property owners and keep the community up to date on our progress.
Puget Sound Energy, P.O. Box 97034, Bellevue, WA 98009-9734
pse.com/energizeeastside
1-800-548-2614
Thank you for your interest in Energize Eastside.
What's inside• PSE selects existing transmission line corridor, referred to as Willow 1, as final route
• PSE will soon begin the permitting process
• PSE will replace the poles in the existing corridor; view updated photo simulations
For more information• For more information about PSE’s final route,
including maps, photo simulations and a video, visit pse.com/energizeeastside
• To learn more about the Bellevue, Kirkland, Newcastle, Redmond and Renton Environmental Impact Statement (EIS) process, visit EnergizeEastsideEIS.org
To date, our outreach has included:
Outreach to 500+ property owners
Nearly 550 briefings with individuals, neighborhoods, cities and other stakeholder groups
More than 2,900 comments and questions received
9 project newsletters to 55,000+ households
22 Community Advisory Group meetings, including 6 public open houses, 2 question and answer sessions, and 3 online open houses at key project milestones
Participation in 16 EIS meetings and hearings
6888 07/17