Entergy Gulf States, Inc.(Texas)
Approved & Proposed Transmission Reliability
Projects
Entergy/ETEC Subcommittee Meeting
The Woodlands, TX
November 28, 2006
2
Recap of 2004-06 EGSI-TX TransmissionWestern Region Reliability Improvement Plan:
Phase IIScenario:• In 2003, several planning studies indicated the Western Region has the
potential to encounter voltage stability problems and thermal overloading under the double contingencies listed below.
o Loss of Lewis Creek Unit & 345 kV Line 119 (Crockett-Grimes)o Loss of Lewis Creek Unit & 230 kV Line 568 (China-Jacinto)o Loss of both Lewis Creek Units
Recommended Solution:• Phase II of the Western Region Reliability Improvement Plan addresses the
projected load growth with the following projects:o 500/230 kV Auto (Cypress) COMPLETEDo Construct Line 822 (China-Porter) 230 kV COMPLETEDo Construct 230/138 kV Porter Substation COMPLETEDo Upgrade Line 599 (Amelia-China) 230 kV COMPLETEDo Install 300 MVAr SVC at Porter Substation COMPLETEDo Install series compensation on Line 822 (China-Porter) COMPLETED
Estimated Cost: $115 MM
3
2006 EGSI-TX Approved Transmission Reliability Projects
Western Region Phase II
INSTALLED 300 MVAr
SVC
INSTALLED 300 MVAr
SVC
INSTALLED SERIES
CAPACITOR ON LINE 822
INSTALLED SERIES
CAPACITOR ON LINE 822
4
Approved 2007 EGSI-TXTransmission Reliability Projects in
Entergy’s Construction Plan
Project Name
In Service
Year
Estimated Cost
($MM) Comments
Grimes: Reconfigure Substation 2007 $0.5 Approved
Kolbs & Hanks: 230 kV Bus Upgrades 2007 $0.2 Approved
Splendora Switch Clearance/Replacement (Mandatory – Safety) 2007 $0.08 Approved
EGSI-TX Underrated Breaker Upgrades (12- 69 kV breakers, Mandatory – Safety) 2007 - 2008 $1.3 Approved
Calvert: Expand cap bank to 12 MVAr 2008 $0.6 Approved
Sandy Shores: Install 11 MVAr cap bank 2008 $0.5 Scoping Only
Porter-Tamina-Conroe Upgrade 138 kV lines 2008 $5.5 Approved
Beaumont 69 kV Improvement Plan 2009 $8 Approved
Western Region Reliability Improvement Plan: Phase 3 2010 $2
Scoping & Engineering Only
5
Approved EGSI-TX Transmission Reliability Projects in Entergy’s Construction Plan
Sandy Shores:Add 69 kV Cap Bank
Calvert: Expand 69 kV Cap Bank
Helbig
Calvert
Sandy Shores
Grimes: Reconfigure 345/138 kV Substation
Grimes
South Beaumont
Amelia
Beaumont 69 kV System Improvement Plan
Conroe
Tamina
Porter-Tamina-Conroe:Upgrade 138kV Lines
Porter
Others:• WRRIP- Phase 3
Scoping & Engineering
• Upgrades of underrated breakers (various locations, mandatory-safety)
• Splendora: Replace switch (mandatory-safety)
Kolbs
HanksKolbs & Hanks:
Upgrade 230 kV Bus
6
Grimes 345/138 kV Substation Reconfiguration
Scenario:
• 345/138 kV autotransformers tied to same node of 345 kV and 138 kV ring busses.
• Single contingency loss of either 345/138 kV autotransformer causes the loss of the parallel autotransformer.
Recommended Solution:
• Install a 345 kV circuit breaker to separate autotransformers on 345kV ring and reconfigure station to alternate lines and loads.
• Install 138 kV breaker to separate autotransformers on 138 kV ring.
Estimated Cost: $0.5 MM (2007 cost only)
7
Grimes 345/138 kV Substation Reconfiguration
AUTO #1
AUTO #2 FRO
NTIE
RC
RO
CK
ETT
RECONFIGURE 345 kV BUS
RECONFIGURE 345 kV BUS
INSTALL 138 kV BREAKER
INSTALL 138 kV BREAKER
INSTALL 345 kV BREAKER
INSTALL 345 kV BREAKER
2007
345kV
138kV
8
Hanks & Kolbs: Upgrade Substation Bus
Scenario:
• Firm load within the Port Arthur area has grown such that the Hanks and Kolbs substation through bus overloads under the loss of the Sabine to Mid County 230 kV line.
Recommended Solution:
• Upgrade limiting elements of substation bus at Hanks & Kolbs.
Estimated Cost: $0.2 MM
9
HanksKolbs
Hanks & Kolbs: Upgrade Substation Bus
10
EGSI-TX Circuit Breaker UpgradesScenario:• Based on asymmetrical fault current analysis, various circuit breakers have
been identified as underrated.
Recommended Solution:• Replace the identified underrated circuit breakers with appropriately sized
breakers.– 2006
o Cow 69kV #5515, #5510o Orange 69kV #3165, 3145
– 2007o Orange 69kV #3365o South Beaumont 69kV #3700o Port Neches 138kV #3345o West End 69kV #22135
– 2008o Orange 69kV #3370o Dupont Bulk 69kV #3255, #3260o Helbig 69kV #5585
11
EGSI-TX 69 kV System Voltage Support
Calvert 69 kV Substation • Loss of 69 kV Line 159 (Bryan – APL Hearne) causes under-voltages
at Calvert 69 kV Substation. • Expand existing capacitor bank to 12 MVAr• Approximate Cost: $0.6 MM
Sandy Shores 69kV Substation• Multiple contingencies cause under-voltages on 69 kV Line 175
“Beach Line.”• Install 11 MVAr capacitor bank
Estimated Cost: $0.5 MM
12
EGSI-TX 69 kV Voltage Support
INSTALL 11MVAR
CAP BANK
INSTALL 11MVAR
CAP BANK
EXPAND EXISTING CAP BANK
EXPAND EXISTING CAP BANK
2007
13
Porter-Tamina-Conroe:Upgrade 138 kV Lines 823 & 886
Scenario:• Lines 823 & 886 are 138 kV tie lines to the Western Region and the
Conroe area specifically.• The loss of 138 kV Line 886 (Oak Ridge – Porter) overloads Lines
823 & 886 above their thermal limits.
Recommended Solution:• Upgrade Line 886 (Tamina – Conroe) to 531 MVA capacity; replace
switches and breaker at Tamina Substation to increase rating on the Porter-Tamina line segment.
Estimated Cost: $5.5 MM
14
2007
UPGRADE TO 531MVA CAPACITY
UPGRADE TO 531MVA CAPACITY
Porter-Tamina-Conroe:Upgrade 138 kV Lines 823 & 886
15
69 kV Beaumont Network Upgrades
Scenario:• In the 69 kV Beaumont area there exists several single contingency
thermal overloads including:o 69 kV Line 581 (Helbig – Rosedale)o 69 kV Line 468 (Elizabeth – Gallier)o 230/69 kV Helbig Autotransformerso 69 kV Bus Tie Breakers (Helbig & Amelia)
Recommended Solution:• Add line breakers at Yankee Doodle 69 kV Substation.• Close normally open points at Lincoln and Crockett 69 kV
Substations.• Rebuild 69 kV Line 576 (Lincoln – South Beaumont) & 69 kV Line
98/190 (Dupont Beaumont – South Beaumont) to 106 MVA capacity.o Approximately 5.5 miles of 69 kV transmission lines
Estimated Cost: $8 MM
16
69 kV Beaumont Network Upgrades
CARDINAL
LAMAR
SOUTH BEAUMONTBULK
VIRGINIALINCOLN
YANKEEDOODLE
CROCKETT
DUPONT BEAUMONT
NITROCDT
L-458
L-458
L-1
55
UPGRADE LINE 576
UPGRADE LINE 576
UPGRADE LINE 190
UPGRADE LINE 190
UPGRADE LINE 98
UPGRADE LINE 98
CLOSE N.O.
SWITCH
CLOSE N.O.
SWITCH
CLOSE N.O.
BREAKER
CLOSE N.O.
BREAKER
ADD LINE BREAKERS
ADD LINE BREAKERS
2007
17
Western Region Reliability Improvement Plan:Phase III and IV
Western Region Reliability Improvement Plan (Phases 3 & 4)*• Potentially convert 138 kV Lines 524/824 (Jacinto-Lewis Creek) to
230 kV operation.• Construct a 230 kV transmission line from Cypress to Jacinto.• Construct a 230 kV transmission line from Porter to Lewis Creek.• Install static and dynamic VAR support in the Western Region.
* Note: This set of projects may be modified based on further activities and developments occurring at the Louisiana and Texas Commissions.
2010+
18
Alternatives to the Western Region Reliability Improvement Plan
• Projects identified in Phases 3 and 4 of the WRRIP results in greater reliance on and strengthening of the transmission corridor between the Western Region and the Beaumont area.
• Because of recent events such as the isolation of the Western Region from the rest of the Entergy System, the Company has developed several alternatives to the projects described above. These alternatives would strengthen the Western Region’s ties to the west.
19
WRRIP Alternative 1
• Enhancement of the reliability at Grimes Substation in order to reduce the reliance from the Beaumont area
• Upgrades of 138 kV Lines 112 and 485 to sufficient capacity
• Installation of a 345 kV bulk tie between Grimes and Lewis Creek
• This option also requires additional firm local generation.
20
WRRIP Alternative 2
• Enhancement of the reliability of the 345 kV tie to AEP-West in order to reduce reliance from the Beaumont area.
• Upgrade of 138 kV Line 485 to sufficient capacity
• Installation of a 345 kV switchyard on Line 119 including a 345 kV tie line to Rivtrin Substation
• This option also requires additional firm local generation.
21
Current Plan: Phases 3 & 4
ALT #2
ALT # 1
Construct/ Enhance 230 kV Network Into Lewis
Creek
Construct/ Enhance 230 kV Network Into Lewis
Creek
Construct 345 kV Network Into Rivtrin
Construct 345 kV Network Into Rivtrin
Enhance 138kV and
345kV Network at Grimes and Lewis Creek
Enhance 138kV and
345kV Network at Grimes and Lewis Creek
22
Project NameIn Service
Year
Estimated Cost ($MM)
Comments
JNEC Deweyville - Add breakers & cut-in Line 2007 $0.4 Approved
SHECO - Menard Substation Upgrades 2007 $0.1 Approved
SHECO - Turkey Creek Substation Upgrades 2007 $0.1 Approved
Approved 2007 ETEC-RelatedTransmission Reliability Projects in
Entergy’s Construction Plan
23
Longer-Term Reliability Target Areas (2011+)
• 230 kV Line 496 (China – Sabine)– For the loss of Line 599 (China – Amelia)
• 230 kV Line 194 (Hartburg-Helbig)– For the loss of the Hartburg-Cypress 500
kV line• 138 kV Line 88 (Dayton – Cheek)
– For the loss of Line 496 (China – Sabine)• 138 kV Line 571 (Jacinto – Porter)
– For the loss of Line 822 (China – Porter)• 138 kV Line 150 (Dayton – Long John)
– For the loss of Line 579 (Jacinto – Cleveland)
• 138 kV Line 561 (Gulfrich – Crown Orange)
– For the loss of Line 590 (Gulfrich – Ausimont)
• 138 kV Line 582 (Oak Ridge – Porter)– For the loss of Line 886 (Tamina – Porter)
• 138 kV Line 86 (Dayton – Eastgate)– For the loss of Line 882 (China – Porter)
• 138 kV Line 515 (Sabine – Port Neches)– For the loss of Line 516 (Sabine – Port
Neches)
• 138 kV Line 516 (Sabine – Port Neches)
– For the loss of Line 515 (Sabine – Port Neches)
• 138 kV overloads in the Jasper-Newton area
– For the loss of the Hartburg-Cypress 500 kV line
• 138 kV Lines from between Lewis Creek and Dobbin
– For the loss of 138kV sources from either the Lewis Creek or Grimes end
– [Could be addressed by the Longmire reconfiguration project]
Potential thermal overloads under single contingency conditions:
• Other target areas/ projects:– Depressed voltages in the
Lacon Substation area– WRRIP Phase 4