17
1 Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

  • Upload
    jaimin

  • View
    39

  • Download
    0

Embed Size (px)

DESCRIPTION

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects. Entergy Transmission Planning Summit New Orleans, LA July 8, 2004. Texas. 2005-06 EGSI-TX Proposed Transmission Reliability Projects. EGSI-TX Capacitor Bank Reliability Improvements (Multi-year). 69 kV Beaumont - PowerPoint PPT Presentation

Citation preview

Page 1: Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

1

Entergy Gulf States, Inc.(Texas)

Proposed Transmission Reliability Projects

Entergy Transmission Planning Summit

New Orleans, LA

July 8, 2004

Page 2: Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

2

Texas

Page 3: Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

3

2005-06 EGSI-TX Proposed Transmission Reliability Projects

69 kV Line 6(Amelia-Raywood)

Reliability Improvements(Multi-year)

230 kV Line 822

(China-Porter) New Construction

(2005 ISD)

EGSI-TX Capacitor BankReliability Improvements

(Multi-year)

230 kV Line 599 (Amelia-

China) Line Upgrade

(2005 ISD)

Porter 230/138 kV Substation (2005 ISD)

69 kV BeaumontReliability Improvements

(Multi-year)

Page 4: Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

4

69 kV Line 6 (Amelia-Raywood):Reliability Improvement Plan

Goals• Increase sectionalizing capability to reduce restoration time • Enhance voltage support• Increase line capacity

Completed Projects• Install 69 kV circuit breakers at Batson, Sour Lake, & Daisetta substations• Install additional sectionalizing equipment (i.e., motor-operated switches, motor

mechanisms, RTUs)• Upgrade line capacity from Raywood Substation to Hull Tap• Estimated Cost: $3.7 MM

In Progress Projects• Install 14 MVAR capacitor bank at Batson 69 kV substation• Upgrade line capacity from Amelia to Sour Lake• Estimated Cost: $2 MM

Projects scheduled for 2005 and beyond• Upgrade capacity from Sour Lake Substation to Hull Tap• Estimated Total Cost: $11.3 MM

2004-08

Page 5: Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

5

2004-08

Page 6: Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

6

2005 Western Region Reliability Improvement Plan (WRRIP):Phase II

3

1

254

Phase II of the Western Region Improvement Plan addresses the projected load growth in 2005.

Planning studies have indicated the Western Region has the potential to encounter voltage stability and thermal overloading problems under the following double contingencies:

• Loss of Lewis Creek Unit & 345 kV Line 119 (Crockett-Grimes)• Loss of Lewis Creek Unit & 230 kV Line 568 (China-Jacinto)• Loss of both Lewis Creek Units

500/230kV Auto (Cypress) COMPLETED

Construct Line 822 (China-Porter) 230 kV

Construct 230/138kV Porter Substation

1

3

2

5 Install 300 MVAR Static VAr Compensator At Porter 138 kV Substation

Upgrade Line 599 (Amelia-China) 230 kV4

Phase II Projects

Estimated Cost: $92 MM

Page 7: Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

7

EGSI-TX Capacitor Bank Reliability Improvement Plan

Longmire 138 kV Substation(2005 ISD)

Rivtrin 138 kV Substation (2005 ISD)

Page 8: Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

8

EGSI-TX Capacitor BankReliability Improvement Plan

Scenario:• The EGSI-TX service territory has a limited supply of reactive power from

generation sources. Steady state capacitor banks provide critical reactive power support.

• In recent years, several different factors have contributed to failures of EGSI-TX capacitor banks:– Size of pre-insertion devices– Relaying on capacitor banks

Recommended Solution: • Capacitor banks are being targeted for reliability improvements in 2005 and

beyond that may include:– Installation of new pre-insertion devices– Installation of new switches equipped with pre-insertion devices– Installation of new relaying equipment– Relocation of some capacitor banks to electrically distance the banks– Replace obsolescent equipment associated with capacitor banks

Estimated Costs: • To be determined per capacitor bank

2003+

Page 9: Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

9

Page 10: Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

10

Beaumont 69 kV Reliability Improvements

Helbig 230/69 kV Substation: ReconfigureAmelia 230/69 kV Substation: Reconfigure

Scenario:

• Loss of the Helbig 69 kV bus or loss of the Amelia 69 kV bus due to a bus-tie breaker failure has the potential to cause outages on the 69 kV subsystem that serves the Beaumont commercial and residential area.

Recommended Solution:

• Reconfigure the 69 kV side of Helbig and Amelia substations with an additional bus-tie breaker.

• Reconfigure the 230 kV side of Helbig and Amelia substations to a ring bus configuration.

• Close the normally-open breaker at Crockett 69 kV substation.

Estimated Cost: $ 4.5 MM

2005+

Page 11: Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

11

2007-08 EGSI-TX Transmission Expansion Projects

69 kV Line 6(Amelia-Raywood)

Reliability Improvements(Multi-year)

230 kV Line 524/824

(Jacinto-Lewis Creek) Convert existing 138 kV line

(2007 ISD)

230 kV Line XXX (Cypress-

Jacinto) (2007 ISD)

Lewis Creek 230/138 kV Substation

(2007 ISD)

69 kV NechesReliability Improvements

(Multi-year)

Page 12: Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

12

2007 Western Region Reliability Improvement Proposal (WRRIP): Phase III

1

Phase III of the Western Region Improvement Plan addresses the projected load growth in 2007.

Planning studies have indicated the Western Region has the potential to encounter voltage stability and thermal overloading problems under the following double contingencies:

• Loss of Lewis Creek Unit & 345 kV Line 119 (Crockett-Grimes)• Loss of Lewis Creek Unit & 230 kV Line 568 (China-Jacinto)• Loss of both Lewis Creek Units

Construct 230/138kV Lewis Creek Substation

Construct Line XXX (Cypress-Jacinto) 230 kV1

2

4Install 200 MVAR Static VAr Compensator At Jacinto 138 kV Substation

Convert Line 524 (Jacinto-Lewis Creek) to 230 kV3

Phase III Projects

Estimated Cost: $60 MM

234

5 Install 200 MVAR steady state capacitor banks at various substations

5

Page 13: Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

13

Neches Station Reliability Improvement Plan

Scenario:

• Neches substation was constructed in conjunction with Neches Power Plant in 1926-27. Most of the station’s existing equipment operating today pre-dates the 1960's.

Recommended solution:

• Construct new consolidated substation adjacent to the existing Neches Substation

Estimated costs: $8.5 MM

Vidor

Carroll St

Neches

ViwayExxon-Mobil

GlycolMobil#2

Houston ChemicalPennwalt

Mayhaw

2008

Page 14: Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

14

138 kV Line 449(Toledo-Newton)

Line Overload

69 kV Line 461(Dupont Beaumont-Kolbs)

Line Overload

EGSI-TX Transmission System Target Areas 2009 and Beyond

(Beaumont and Port Arthur Areas)138 kV Line 97

(Rayburn-Doucette)Line Overload

69 kV Line 427(Port Neches-Goodrich)

Line Overload

Stowell 138/69 kVAuto Overload

69 kV Line 581(Helbig-West End)

Line Overload

138 kV Line 455(Jasper-Rayburn)

Line Overload

Page 15: Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

15

EGSI-TX Transmission System Target Areas 2009 and Beyond(Western Region)

138 kV Line 93(Doucette-Corrigan Bulk)

Line Overload

138 kV Line 596(Lewis Creek-Longmire)

Line Overload

138 kVPanorama/Longmire/

Dobbin/NavasotaLow Voltages Cypress

500/230kV &230/138 kV

Auto Overload

230 kV Line 599(Amelia-China) Line Overload

138 kV Line 430(Cypress-Menard)

Line Overload

138 kV Line 187(Cypress-Rye) Line Overload

138 kV Line 86(Dayton-New Caney)

Line Overload

138 kV Line 50(Dayton-New Long John)

Line Overload

138 kV Line 571(Jacinto-Tamina)

Line Overload

Page 16: Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

16

2011 Western Region Reliability Improvement Proposal (WRRIP): Phase IV

1

Construct Line XXX (Porter-Lewis Creek) 230 kV1

2 Install 70 MVAR of steady state capacitor banks at various locations

Phase IV Projects

Estimated Cost: $22 MM

2

Phase IV of the Western Region Improvement Plan addresses the projected load growth in 2011.

Planning studies have indicated the Western Region has the potential to encounter voltage stability and thermal overloading problems under the following double contingencies:

• Loss of Lewis Creek Unit & 345 kV Line 119 (Crockett-Grimes)• Loss of Lewis Creek Unit & 230 kV Line 568 (China-Jacinto)• Loss of both Lewis Creek Units

Page 17: Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

17

Questions