ENVIRONMENTAL ASSESSMENT CERTIFICATE APPLICATION
WesPac Tilbury Marine Jetty Project
SECT
ION
15.0:
CON
CLUS
IONS
WesPac Tilbury Marine Jetty Project Environmental Assessment Certificate Application
Part E – Management Plans and Follow-Up Programs Section 15.0 Conclusions
1
15.0 CONCLUSIONS 15.1 Summary of Residual Effects Table 15-1 summarizes all potential residual effects, including cumulative residual effects. The potential effects are depicted for each project phase or activity and proposed mitigation are identified along with the significance determination for each effect.
WesPac Tilbury Marine Jetty Project Environmental Assessment Certificate Application
Part E – Management Plans and Follow-Up Programs Section 15.0 Conclusions
2
Table 15-1: Summary of Residual Effects Potential Adverse Residual
Effect Project Phase Contributing Project Activity or Physical Works
Mitigation Number Proposed Mitigation Significance Analysis of Residual Effect (Summary Statement)
4.0 Environmental 4.1 River Processes Release of Fine Sediments from the site from dredging and propeller wash associated with the berthing/departure of vessels
Construction Operation
Dredging of dredge area Maintenance Dredging Berthing/Departure of Vessels
Not included N/A As River Process is a Pathway Component no analysis of Significance was conducted. Significance analysis of residual effects was conducted for related VCs Changes in River currents resulting
from dredging and in-river structures
Construction Operation
Removal of existing marine infrastructure Dredging of dredge area In-river ground stabilization and piling works Construction of associated Offshore Facilities
Not included N/A
Changes in local morphology resulting from dredging and in-river structures
Construction Operation
Removal of existing marine infrastructure Dredging of dredge area In-river ground stabilization and piling works Construction of associated Offshore Facilities
Not included N/A
Changes in regional geomorphology resulting in a removal of sediment from the Fraser River system via dredging
Construction Operation
Dredging of dredge area Maintenance dredging
Not included N/A
4.2 Fish and Fish Habitat
Direct mortality or behavioural changes or changes to habitat quality and function due increased suspended sediments
Construction Operation Decommissioning
- Site preparation and removal of existing marine infrastructure
- In-river ground stabilization and piling works - Dredging - Construction of Offshore Facilities - In-river ground stabilization and pile works - Maintenance Dredging - Berthing and departure of vessels - Removal of associated Offshore Facilities
M4.2-1 Limit disturbance footprint After the implementation of mitigation measures, the Project is not predicted to result in residual effects to Fish and Fish Habitat and has therefore not been carried forward to the determination of significance.
M4.2-2 Site management
M4.2-3 Erosion and Sediment Control Plan
M4.2-4 Design for stormwater management
M4.2-5 In-Water Works Management Plan
M4.2-6 Fish Habitat Offset Plan
M4.2-7 Dredging Management Plan
Direct mortality or behavioural changes or changes to habitat quality due to removal of existing creosote piles
Construction Decommissioning
- Site preparation and removal of existing marine infrastructure
- Removal of associated Offshore Facilities
M4.2-1 Limit disturbance footprint M4.2-2 Site management M4.2-3 Erosion and Sediment Control Plan M4.2-4 Design for stormwater management M4.2-5 In-Water Works Management Plan M4.2-6 Fish Habitat Offset Plan M4.2-8 Concrete Works Management Plan M4.2-9 Minimize the effects of creosote pile removal
Direct mortality or behavioural changes or changes to habitat quality and function due to localized shading effects on aquatic habitat
Construction Operation
- Construction of associated Offshore Facilities - Berthing and departure of vessels - LNG carrier and/or barge loading
M4.2-1 Limit disturbance footprint M4.2-2 Site management M4.2-5 In-Water Works Management Plan M4.2-6 Fish Habitat Offset Plan M4.2-11 Minimize shading M4.2-12 Wetland enhancement and creation
WesPac Tilbury Marine Jetty Project Environmental Assessment Certificate Application
Part E – Management Plans and Follow-Up Programs Section 15.0 Conclusions
3
Potential Adverse Residual Effect Project Phase Contributing Project Activity or Physical
Works Mitigation Number Proposed Mitigation Significance Analysis of Residual Effect
(Summary Statement)
Changes to habitat quality and function due to wake and prop-wash impacts to foreshore habitat
Construction Operation Decommissioning
- Site preparation and removal of abandoned marine infrastructure
- Dredging activities - In-river ground stabilization and pile works - Construction of associated Offshore Facilities - Removal of associated Offshore Facilities - Berthing and departure of vessels - LNG carrier and/or barge loading
M4.2-2 Site management
M4.2-5 In-Water Works Management Plan
M4.2-6 Fish Habitat Offset Plan
M4.2-7 Dredging Management Plan
M4.2-12 Wetland enhancement and creation
Direct mortality or behavioural changes due to underwater noise and vibration
Construction Operation Decommissioning
- Site preparation and removal of abandoned marine infrastructure
- Dredging activities - In-river ground stabilization and pile works - Construction of associated Offshore Facilities - Maintenance Dredging - Removal of associated Offshore Facilities
M4.2-1 Limit disturbance Footprint
M4.2-2 Site management
M4.2-5 In-Water Works Management Plan
M4.2-7 Dredging Management Plan
M4.2-14 Underwater Noise Management Plan
Changes to habitat quality and function due to potential introduction of invasive species from ballast water exchange
Operation
- Berthing and departure of vessels - LNG carrier and/or barge loading
M4.2-13 Ballast Waste Management Plan
4.3 Marine Mammals
Injury from underwater noise Construction
- Construction of Offshore Facilities M4.3-1 Prioritization of Vibratory Pile Driving Methods Project effects on marine mammals are assessed to be not significant. If residual effects occur, these are likely to be limited to localized, temporary (short-term) disturbance effects from Project-generated underwater noise. The residual cumulative effect on marine mammals is identified as not significant. Proposed mitigation is expected to be effective at avoiding/and or minimizing potential adverse residual effect
M4.3-2 Installation of Bubble Curtain
M4.3-3 Ramp-Up/Soft-Start Procedure
M4.3-4 Sequencing of In-Water Works
M4.3-5 Adherence to Timing Window
M4.3-6 Marine Mammal Management Plan
Behavioural disturbance from underwater noise
Construction, Operations, Decommissioning
- Site preparation and removal of existing marine infrastructure
- In-river ground stabilization and piling works - Dredging - Construction of Offshore Facilities - Marine transportation of construction materials
and equipment - Dredging - Marine transportation - Removal of associated Offshore Facilities - Marine transportation of decommissioning
materials and equipment
M4.3-1 Prioritization of Vibratory Pile Driving Methods
M4.3-2 Installation of Bubble Curtain
M4.3-3 Ramp-Up/Soft-Start Procedure
M4.3-4 Sequencing of In-Water Works
M4.3-5 Adherence to Timing Window
M4.3-6 Marine Mammal Management Plan
WesPac Tilbury Marine Jetty Project Environmental Assessment Certificate Application
Part E – Management Plans and Follow-Up Programs Section 15.0 Conclusions
4
Potential Adverse Residual Effect Project Phase Contributing Project Activity or Physical
Works Mitigation Number Proposed Mitigation Significance Analysis of Residual Effect
(Summary Statement)
M4.3-7 Shut-Down of Vessel during LNG Transfer
M4.3-8 Vessel Traffic Management
M4.3-9 Do Not Disturb Marine Mammals
Injury or mortality from vessel strikes
Construction, Operations, Decommissioning
- Site preparation and removal of existing marine infrastructure
- Dredging - Construction of Offshore Facilities - Marine transportation of construction materials
and equipment - Dredging - Marine transportation - Removal of associated Offshore Facilities - Marine transportation of decommissioning
materials and equipment
M4.3-8 Vessel Traffic Management
M4.3-9 Do Not Disturb Marine Mammals
M4.3-10 Accidental Contact with Marine Mammals
4.4 Air Quality
Project emissions of measurable parameters
Construction Operation Decommissioning
-site preparation and removal of existing abandoned marine infrastructure -dredging -ground stabilization and pile installation -construction of onshore and offshore facilities -marine transportation of construction materials and equipment -road transportation
DM4.4-1 -in-design mitigation to reduce contribution of Project air emission
Residual effects of increases in 1-hour NO2 concentrations under normal operation after the implementation of mitigations are predicted to be not significant Residual effects of increases in annual NO2 concentrations under normal operation after the implementation of mitigation are predicted to be not significant Residual effects of increases in 1-hour NO2 concentrations from dredge operation after the implementation of mitigation measures are predicted to be not significant Residual effects of increases in CO concentrations for normal operation and dredger operation is predicted to be not significant given the implementation of mitigation measures Residual effects of increases in PM2, 5 under the normal operation scenario and dredge operation scenario is predicted to be not significant given the implementation of mitigation measures Residual effects of increases in PM10 under normal operation scenario and dredger operation is predicted to be not significant given the implementation of mitigation measures.
Construction Operation Decommissioning
-site preparation and removal of existing abandoned marine infrastructure -dredging -ground stabilization and pile installation -construction of onshore and offshore facilities -marine transportation of construction materials and equipment -road transportation -LNG carrier/ bunker vessel loading -berthing/ departure of vessels -marine shipping -maintenance dredging -maintaining marine security area Accident and malfunctions -removal of onshore and offshore facilities -marine transportation
M4.4-1 Ongoing routine maintenance of vehicles and implement engine idling time restrictions where practical on construction vehicles/vessels
WesPac Tilbury Marine Jetty Project Environmental Assessment Certificate Application
Part E – Management Plans and Follow-Up Programs Section 15.0 Conclusions
5
Potential Adverse Residual Effect Project Phase Contributing Project Activity or Physical
Works Mitigation Number Proposed Mitigation Significance Analysis of Residual Effect
(Summary Statement)
Operation
-LNG carrier/ bunker vessel loading -berthing/ departure of vessels -marine shipping -maintenance dredging -maintaining marine security area Accident and malfunctions
M4.4-1 In-design mitigation to reduce contribution of Project air emissions (e.g. selection of Project components)
Operation
-LNG carrier/ bunker vessel loading -berthing/ departure of vessels -marine shipping -maintenance dredging -maintaining marine security area Accident and malfunctions
M4.4-1 Implement engine idling time restrictions on marine vessels to the extent practical
Operation
-LNG carrier/ bunker vessel loading -berthing/ departure of vessels -marine shipping -maintenance dredging -maintaining marine security area Accident and malfunctions
M4.4-1 Implement a leak detection and repair program
Project GHG Emissions
Construction Operation Decommissioning
-Site preparation -dredging of dredge area -ground stabilization and pile work -construction of onshore and offshore facilities -marine transportation of construction materials -road transportation of construction materials Accident and malfunctions -LNG carrier/ bunker vessel loading -berthing/ deberthing of vessels -Marine shipping -maintenance dredging -Maintaining marine security area -marine transportation of decommissioning material and equipment
DM4.4.2-1 DM4.4.2-2 DM4.4.2-3
In-design mitigation to reduce contribution of Project GHG emissions (e.g., selection of construction, operation, and decommissioning equipment)
After the implementation of proposed mitigation measures it is predicted that the Project may contribute to GHG emissions during all phases; however, all residual project effects are assessed to be negligible.
Construction, decommissioning
Site preparation -dredging of dredge area -ground stabilization and pile work -construction of onshore and offshore facilities -marine transportation of construction materials -road transportation of construction materials Accident and malfunctions -marine transportation of decommissioning material and equipment
M4.4.2-1 M4.4.2-4
Ongoing routine maintenance of vehicles and implement engine idling time restrictions where practical on construction vehicles/vessels
Operation Decommissioning
-LNG carrier/ bunker vessel loading -berthing/ deberthing of vessels -Marine shipping -maintenance dredging -Maintaining marine security area -marine transportation of decommissioning material and equipment
M4.4.2-2 Implement engine idling time restrictions on marine vessels to the extent practical.
Operation -LNG carrier/ bunker vessel loading M4.4.2-3 Implement a leak detection and repair program
WesPac Tilbury Marine Jetty Project Environmental Assessment Certificate Application
Part E – Management Plans and Follow-Up Programs Section 15.0 Conclusions
6
Potential Adverse Residual Effect Project Phase Contributing Project Activity or Physical
Works Mitigation Number Proposed Mitigation Significance Analysis of Residual Effect
(Summary Statement)
Potential for the Project to affect climate
Construction Operation Decommissioning
-Site preparation -dredging of dredge area -ground stabilization and pile work -construction of onshore and offshore facilities -marine transportation of construction materials -road transportation of construction materials Accident and malfunctions -LNG carrier/ bunker vessel loading -berthing/ deberthing of vessels -Marine shipping -maintenance dredging -Maintaining marine security area -marine transportation of decommissioning material and equipment
DM4.4.2-1 DM4.4.2-2 DM4.4.2-3
In-design mitigation to reduce contribution of Project GHG emissions (e.g., selection of construction, operation, and decommissioning equipment)
Construction, decommissioning
Site preparation -dredging of dredge area -ground stabilization and pile work -construction of onshore and offshore facilities -marine transportation of construction materials -road transportation of construction materials Accident and malfunctions -marine transportation of decommissioning material and equipment
M4.4.2-1 M4.4.2-4
Ongoing routine maintenance of vehicles and implement engine idling time restrictions where practical on construction vehicles/vessels
Operation Decommissioning
-LNG carrier/ bunker vessel loading -berthing/ deberthing of vessels -Marine shipping -maintenance dredging -Maintaining marine security area -marine transportation of decommissioning material and equipment
M4.4.2-2 Implement engine idling time restrictions on marine vessels to the extent practical.
Operation -LNG carrier/ bunker vessel loading M4.4.2-3 Implement a leak detection and repair program 4.5 Noise
Increase in noise levels during construction
Construction
- Dredging of the dredge area - Offshore and onshore pile driving, construction
of onshore facilities, and marine transportation of construction materials and equipment
- Offshore and onshore pile driving, construction of onshore facilities, and marine transportation of construction materials and equipment
M4.5-1 Advise nearby residents of particularly noisy activities and schedule these events to reduce disruption to them whenever possible.
For Project construction, the noise assessment resulted in the conclusion that the overall residual effect of Project construction to noise is not-significant at one receptor, and negligible at all remaining assessment receptors, with an overall conclusion that there are not-significant residual effects of Project construction on noise.
M4.5-2 Establish heavy equipment muster points at least 500m from any residential dwelling, if possible.
M4.5-3 Fit equipment with standard mufflers or silencers and keep these mufflers/silencers in good working order.
M4.5-4 Take advantage of acoustical screening from existing on-site barriers to shield dwellings from construction equipment noise.
Increase in noise levels during operation
Operation
-LNG carrier/ barge loading -berthing/ deberthing -shipping -maintenance dredging -maintaining marine security zone -Accidents and malfunctions
M4.5-5 Scheduling noise emitting maintenance activities during the day where possible.
For Project operation, the noise assessment resulted in the conclusion that, given the application of mitigation the overall residual effect of Project operation to noise is negligible at all receptors, with an overall conclusion that there are negligible effects of the Project operation on noise.
M4.5-6 Notifying residents prior to high noise emitting maintenance activities (if appropriate).
M4.5-7 Set-up and implement a call in number that people can call when experience a high noise activity.
WesPac Tilbury Marine Jetty Project Environmental Assessment Certificate Application
Part E – Management Plans and Follow-Up Programs Section 15.0 Conclusions
7
Potential Adverse Residual Effect Project Phase Contributing Project Activity or Physical
Works Mitigation Number Proposed Mitigation Significance Analysis of Residual Effect
(Summary Statement)
Increase in noise levels during decommissioning Decommissioning
-Removal of offshore and onshore facilities -marine transportation of decommissioning materials and equipment
Same as Construction
4.6 Water Quality
Increase in suspended sediment due to sediment disturbance
Construction
-Site preparation -removal of existing abandoned marine infrastructure -in-river ground stabilization and pile works -shoreline enhancements, -construction of Offshore Facilities
M4.6-1 Site Management After implementation of the proposed mitigation measures, effects on the Water Quality VC and its subcomponents associated with the Project (i.e., surface water quality, sediment quality, and aquatic health) are predicted to be negligible.
M4.6-2 Stormwater Management Plan M4.6-3 In-Water Works Management Plan M4.6-5 Erosion and Sediment Control Plan (ESCP) and
Spill Prevention and Emergency Response Plan (SPERP)
M4.6-6 Scour Protection Plan -Dredging the dredge Area M4.6-8 Dredging Management Plan
Operation -Berthing and departure of vessels M4.6-6 Scour Protection Plan -Maintenance dredging M4.6-8 Dredging Management Plan
Decommissioning -Removal of Offshore Facilities Same as Construction
Contaminant release due to project activities Construction
-Removal of creosote-treated piles M4.6-3 In-Water Works Management Plan M4.6-4 Creosote Pile Removal Management Plan
-Shoreline enhancement M4.6-5 Erosion and Sediment Control Plan (ESCP) and Spill Preventions and Emergency Response Plan (SPERP)
-Construction of Offshore Facilities M4.6-7 Concrete Works Management Plan Dredging M4.6-8 Dredging Management Plan
Accidental release of deleterious substances
Construction
Accident and malfunctions M4.6-5 Erosion and Sediment Control Plan (ESCP) and Spill Preventions and Emergency Response Plan (SPERP)
M4.6-9 Waste Management Plan Operation Same as Construction Decommissioning Same as Construction
4.7 Vegetation
Direct loss of wetland and riparian ecosystems
Construction
- Site preparation and removal of existing marine infrastructure
- In-river ground stabilization and pile works - Land based ground stabilization and pile works - Construction of associated Offshore Facilities
M4.7-1 Limit disturbance footprints After the implementation of the proposed mitigation measures, residual effects on the Vegetation VC and its subcomponents associated with the Project are predicted to be negligible.
M4.7-2 Preserve native trees and vegetation M4.7-3 Soil management M4.7-5 Salvaging soils and other materials M4.7-6 Implementation monitoring during construction M4.7-10 Wetland restoration – enhancement and creation
Decommissioning - Removal of associated Offshore Facilities - Removal of associated Onshore Facilities
M4.7-1 Limit disturbance footprint M4.7-11 Decommissioning and Final Rehabilitation Plan
Direct loss of plant species of management concern (plant species at risk and traditional use plants)
Construction
- Site preparation and removal of existing marine infrastructure
- In-river ground stabilization and pile works - Land based ground stabilization and pile works - Construction of associated Offshore Facilities - Enhancement of the previously disturbed
foreshore
M4.7-1 Limit disturbance footprint M4.7-2 Preserve native trees and vegetation M4.7-4 Conduct pre-construction surveys for plant species
at risk M4.7-5 Salvaging soils and other material M4.7-6 Implementation monitoring during construction
Construction M4.7-6 Implementation monitoring during construction
WesPac Tilbury Marine Jetty Project Environmental Assessment Certificate Application
Part E – Management Plans and Follow-Up Programs Section 15.0 Conclusions
8
Potential Adverse Residual Effect Project Phase Contributing Project Activity or Physical
Works Mitigation Number Proposed Mitigation Significance Analysis of Residual Effect
(Summary Statement)
Indirect loss of wetland and riparian ecosystems
- Site preparation and removal of existing marine infrastructure
- Land based ground stabilization and pile works - Construction of associated Onshore Facilities - Enhancement of the previously disturbed
foreshore
M4.7-7 Erosion and Sediment Control Plan
Introduction/proliferation of invasive plant species
Construction - Land based ground stabilization and pile works - Construction of associated Onshore Facilities
M4.7-6 Implementation monitoring during construction M4.7-8 Invasive Plant Species Management Plan M4.7-9 Revegetate disturbed soils
Decommissioning - Removal of Onshore Facilities M4.7-8 Invasive Plant Species Management Plan
M4.7-11 Decommissioning and Final Rehabilitation Plan 4.8 Wildlife and Wildlife Habitat
Habitat loss
Construction
- Site preparation and removal of existing abandoned marine infrastructure
- In-river ground stabilization and pile works - Land-based ground stabilization and pile
works - Construction of associated Offshore Facilities - Construction of associated Offshore Facilities - Construction of associated Onshore Facilities
M4.8-1 Limit disturbance footprint After the implementation of the proposed mitigation measures, the residual effects on the Wildlife VC and its subcomponents from the Project are predicted to be negligible.
M4.8-2 Replant temporarily disturbed habitat M4.8-3 Fell trees away from sensitive habitat M4.8-4 Salvage and replace coarse woody debris within
temporarily disturbed habitat or habitat enhancement areas
M4.8-5 Identify and delineate sensitive habitat M4.8-6 Maintain project activities away from the Fraser
River M4.8-7 Develop an Erosion and Sediment Control Plan and
a Spill Prevention and Emergency Response Plan M4.8-15 Wetland enhancement and creation
Decommissioning
- Removal of associated Offshore Facilities M4.8-2 Replant temporarily disturbed habitat M4.8-4 Salvage and replace coarse woody debris within
temporarily disturbed habitat or habitat enhancement areas
M4.8-6 Maintain project activities away from the Fraser River
M4.8-7 Develop an Erosion and Sediment Control Plan and a Spill Prevention and Emergency Response Plan
M4.8-8 Develop and implement a Wildlife Management Plan M4.9-10 Develop and implement an Invasive Plant
Management Plan M4.8-15 Wetland enhancement and creation
Disturbance Construction
- Site preparation and removal of existing abandoned marine infrastructure - Dredging of dredge area - In-river ground stabilization and pile works - Land-based ground stabilization and pile works - Construction of associated Offshore Facilities - Construction of associated Offshore Facilities - Marine transportation of construction materials
and equipment - Enhancement of the previously disturbed
foreshore
M4.8-1 Limit disturbance footprint M4.8-5 Identify and delineate sensitive habitat M4.8-6 Maintain project activities away from the Fraser
River M4.8-7 Develop an Erosion and Sediment Control Plan and
a Spill Prevention and Emergency Response Plan M4.8-8 Develop and implement a Wildlife Management Plan M4.8-9 Develop and implement wildlife-specific light
management as part of Light Management Plans M4.8-10 Develop and implement an Invasive Plant
Management Plan
WesPac Tilbury Marine Jetty Project Environmental Assessment Certificate Application
Part E – Management Plans and Follow-Up Programs Section 15.0 Conclusions
9
Potential Adverse Residual Effect Project Phase Contributing Project Activity or Physical
Works Mitigation Number Proposed Mitigation Significance Analysis of Residual Effect
(Summary Statement)
M4.8-11 Develop and implement wildlife-specific noise control as part of Noise Management Plans
M4.8-15 Wetland enhancement and creation
Operation
- LNG carrier/barge loading - Berthing/departure of vessels - Marine shipping from the Project site to Sand
Heads - Accidents and malfunctions during Operation
M4.8-6 Maintain project activities away from the Fraser River
M4.8-7 Develop an Erosion and Sediment Control Plan and a Spill Prevention and Emergency Response Plan
M4.8-8 Develop and implement a Wildlife Management Plan M4.8-9 Develop and implement wildlife-specific light
management as part of Light Management Plans M4.8-10 Develop and implement an Invasive Plant
Management Plan M4.8-11 Develop and implement wildlife-specific noise
control as part of Noise Management Plans
Decommissioning
- Removal of associated Onshore Facilities - Marine transportation of decommissioning
materials and equipment
M4.8-2 Replant temporarily disturbed habitat M4.8-6 Maintain project activities away from the Fraser
River M4.8-7 Develop an Erosion and Sediment Control Plan and
a Spill Prevention and Emergency Response Plan M4.8-8 Develop and implement a Wildlife Management Plan M4.8-9 Develop and implement wildlife-specific light
management as part of Light Management Plans M4.8-10 Develop and implement an Invasive Plant
Management Plan M4.8-11 Develop and implement wildlife-specific noise
control as part of Noise Management Plans M4.8-15 Wetland enhancement and creation
Wildlife Mortality
Construction
- Site preparation and removal of existing abandoned marine infrastructure
- Construction of associated Offshore Facilities - Construction of associated Offshore Facilities - Construction of associated Onshore Facilities - Marine transportation of construction materials
and equipment - Road transportation of construction materials
and equipment
M4.8-8 Develop and implement a Wildlife Management Plan M4.8-9 Develop and implement wildlife-specific light
management as part of Light Management Plans M4.8-12 Limit and control speed on Project roadways M4.8-13 Survey for and salvage amphibians M4.8-14 Avoid vegetation clearing during the nesting season
and survey for and avoid disturbance of active nests
Operation
- Berthing/departure of vessels - Marine shipping from the Project site to Sand
Heads - Accidents and malfunctions during Operation
M4.8-8 Develop and implement a Wildlife Management Plan M4.8-9 Develop and implement wildlife-specific light
management as part of Light Management Plans M4.8-12 Limit and control speed on Project roadways
Decommissioning
- Removal of associated Offshore Facilities - Removal of associated Onshore Facilities - Marine transportation of decommissioning
materials and equipment
Same as Operation
WesPac Tilbury Marine Jetty Project Environmental Assessment Certificate Application
Part E – Management Plans and Follow-Up Programs Section 15.0 Conclusions
10
Potential Adverse Residual Effect Project Phase Contributing Project Activity or Physical
Works Mitigation Number Proposed Mitigation Significance Analysis of Residual Effect
(Summary Statement)
5.0 Economic 5.1 Economy Change in employment due to Project labour demand Construction Employment of personnel and procurement of
goods and services M5.1-1 Local and Aboriginal Hiring and Procurement
Policies Potential effect is considered beneficial.
Change in employment income due to Project-associated hiring Construction Employment of personnel and procurement of
goods and services M5.1-1 Local and Aboriginal Hiring and Procurement
Policies Potential effect is considered beneficial.
Change in business opportunities due to Project spending on materials, goods, and services
Construction Operation
Procurement of materials, goods, and services M5.1-1 Local and Aboriginal Hiring and Procurement Policies
Potential effect is considered beneficial.
Change in business opportunities due to household spending of Project-associated income
Construction Operation
Employment of personnel and procurement of goods and services
M5.1-1 Local and Aboriginal Hiring and Procurement Policies
Potential effect is considered beneficial.
Change in local government taxation revenue due to Project direct payment of property taxes
Construction Operation
Payment of local and provincial taxes n/a n/a Potential effect is considered beneficial.
Change in taxation revenue due to Project-associated direct, indirect, and induced employment and procurement of goods and services
Construction Operation
Employment of personnel and procurement of goods and services
n/a n/a Potential effect is considered beneficial.
6.0 Social 6.1 Socio-community Change in demand for health and emergency services due to direct project use of services
Construction All construction activities M6.1-1 Emergency Management Planning with local first responders
After the implementation of the proposed mitigation measures, the residual effects on the Socio-community VC and its subcomponents from the Project are predicted to be negligible. Change in demand for marine
emergency services due to accidents on site
Construction Operations Decommissioning
All marine based construction, operations, and decommissioning activities CEMP
Emergency Response and Spill Prevention Plan
Change in employment income could affect individual well-being Construction Employment of personnel and procurement of
goods and services M5.1-1 Local and Aboriginal Hiring and Procurement Policies
Nuisance due to construction noise Construction All construction activities CEMP Noise Management Plan 6.2 Land and Marine Resource Use
Change in commercial and non-commercial marine access and area use
Construction Operation
- Transportation of materials and equipment during construction
- Marine shipping during operation - Marine construction and operational activities
at site - Operation of marine safety zone
M6.2-1 Implementation of TERMPOL Recommendations Residual Project effects on commercial and non-commercial marine area use and access are assessed to be not significant. The South Arm of the Fraser and specifically the LAA is a highly industrialized area, whereby commercial and non-commercial users are familiar with in-river construction and operational activities and associated marine transportation vessel transiting. If residual effects occur, commercial and non-commercial marine use activities would continue to have access to use areas within the LAA, and would experience temporary effects to access and use from the Project. Supporting management plans along with marine systems (e.g., communication and navigational aids), will further assist support users’ capacity to respond to effects as reflected by the low magnitude of the predicted residual effects.
M6.2-2 Compliance with Maritime Regulations and Legislation
M6.2-3 Marine Access and Transportation Management
Plan
M6.2-4 Marine Communication Management Plan
M6.2-5 Timing of Construction Activities to Avoid Commercial Salmon Fishery Openings
M6.2-6 Aboriginal Communications Plan
WesPac Tilbury Marine Jetty Project Environmental Assessment Certificate Application
Part E – Management Plans and Follow-Up Programs Section 15.0 Conclusions
11
Potential Adverse Residual Effect Project Phase Contributing Project Activity or Physical
Works Mitigation Number Proposed Mitigation Significance Analysis of Residual Effect
(Summary Statement)
6.3 Current Use of Lands and Resources for Traditional Purposes
Accessing instream locations for Food, Social, and ceremonial purposes or Domestic Harvesting
Construction Operation
-Site preparation and removal of existing marine infrastructure - Dredging -In-river ground stabilization and piling works -Construction of associated Offshore Facilities -Marine transportation of construction materials and equipment -LNG carrier/barge loading -Berthing/Departure of vessels -Marine shipping from the Project site to Sand Heads -Maintenance dredging -Maintaining marine security area -Removal of associated Offshore Facilities -Marine transportation of decommissioning materials and equipment
M6.3-1 Marine Access and Transportation Management Plan
Given mitigation, Project-related effects on the Musqueam Indian Band and Tsawwassen First Nation are considered negligible and are therefore not carried forward to determination of significance or cumulative effects assessment.
M6.3-2 Marine Communication Management Plan M6.3-3 Aboriginal Group Communication Plan
6.4 Visual Quality
Temporary visibility of equipment, vessels and activities
Construction, Decommissioning
- Site preparation and removal of existing marine infrastructure
- Dredging of dredge area - Land based ground stabilization and piling
works - In river ground stabilization and piling works - Construction of associated Offshore Facilities - Construction of associated Onshore Facilities - Marine transportation of construction materials
and equipment
Project Design Conclusion of construction/ decommission activity and the removal of construction/ decommission equipment after phase completion
Project-related residual effects remaining after the application of mitigation are considered negligible and are therefore not carried forward to determination of significance or cumulative effects assessment.
Temporary visibility of lighting related to equipment, vessels and activities
Construction, Operation, Decommissioning
M6.4-2 Construction / Operation Lighting Management Practices
Project Design
Conclusion of construction/ decommission activity and the removal of construction/ decommission equipment after phase completion
Presence of visible Project components and temporary visibility of marine vessel movements
Operation
- LNG carrier/barge bunker vessel loading - Berthing/Departure of vessels - Marine shipping from the Project site to Sand
Heads
M6.4-1 External Surface Treatment The residual Project effects on visual quality from the presence of visible Project components and temporary visibility of marine vessel movements during operation is characterized as a noticeable to prominent but generally small level of visual change over the long term, that is reversible and occurs within a resilient context that would not result in a change to the existing visual character of the landscape from most viewing locations. Based on the determination of significance, this assessment concludes that there is no significant residual effect on visual quality of daytime viewing during operation.
Visibility of lighting related to site safety and navigation
M6.4-2 Construction / Operation Lighting Management Practices
The residual Project effects on visual quality from the visibility of lighting related to site safety and navigation during operation is characterized as a small change to existing lighting conditions over the long term, that is reversible and occurs within a resilient context that would not result in a change to the existing visual character of nighttime viewing. Based on the determination of significance, this assessment concludes that there is no significant residual effect on visual quality of nighttime viewing during operation.
WesPac Tilbury Marine Jetty Project Environmental Assessment Certificate Application
Part E – Management Plans and Follow-Up Programs Section 15.0 Conclusions
12
Potential Adverse Residual Effect Project Phase Contributing Project Activity or Physical
Works Mitigation Number Proposed Mitigation Significance Analysis of Residual Effect
(Summary Statement)
7.0 Heritage 7.1 Archaeological and Historical Resources
Damage or destruction of sites, features, or objects
Construction
- Ground disturbance
M7.1-1 Avoidance After implementation of the proposed mitigation measures, residual effects on the Heritage VC and its subcomponents associated with the Project are predicted to be negligible.
M7.1-2 Minimize or Reduce M7.1-3 Offset M7.1-4 Chance Find Management Procedure
Operation - Accidents and malfunctions (e.g., spills) Same as Construction
Decommissioning - Ground disturbance
Same as Construction
Changes in the level of accessibility
Construction - Site burial, fencing, or other barriers to access M7.1-2 Minimize or Reduce
Operation Same as Construction
Decommissioning - Site burial, fencing, or other barriers to access Same as Construction
8.0 Health 8.1 Human Health Acute 1-hour exposure to nitrogen dioxide – Normal Operation scenario
Operations Discussed in Sections 4.4 and 4.6 Mitigation measures captured under Air Quality and Water Quality Chapters The residual effects to human health associated with the Project are
predicted to be not significant
Acute 1-hour exposure to benzo(a)pyrene Operations
Acute 1-hour exposure to cyclopenta(c,d)pyrene Operations
Acute 1-hour exposure to 2,5-dimethylbenzaldehyde Operations
9.0 Accidents and Malfunctions
9.3.1 Hazardous Material Spill
Construction Operation Decommissioning
- Hazardous material spills on land - Hazardous material spills affecting the
estuarine environment
NA - Compliance with applicable codes and regulations on hazardous material storage and handling for the facility and marine vessels
- Procedures for the safe handling and storage of hazardous materials during construction and operations
- Maintenance of machinery and heavy equipment - Training in the proper handling, identification,
documentation, and storage hazardous materials - Containment for hazardous materials storage in
accordance with applicable regulations - Drainage system to collect stormwater runoff - Spill response equipment - Spill contingency plan
The residual consequence severity for an onshore spill that is contained on land can range from negligible to low with potential local short-term reversible effects on vegetation and wildlife.
WesPac Tilbury Marine Jetty Project Environmental Assessment Certificate Application
Part E – Management Plans and Follow-Up Programs Section 15.0 Conclusions
13
Potential Adverse Residual Effect Project Phase Contributing Project Activity or Physical
Works Mitigation Number Proposed Mitigation Significance Analysis of Residual Effect
(Summary Statement)
9.3.2 Loss of Containment of LNG
Construction Operation
- Onshore LNG release - Offshore LNG release affecting the estuarine
environment
NA - LNG transfer system and spill prevention system to be designed according to CSA Z276 Canadian Standard, and will include emergency shutdown (ESD) system and a fire and gas detection system.
- Drainage and spill containment systems that would limit the spread of potential LNG pool.
- Operating range for the flexible cryogenic line and loading arms established based on the required ship movement envelopes
- Drybreak couplings and powered emergency release couplings (PERC) that would shut off LNG flow in case of a failure
- Emergency release system (ERS) that would disconnect LNG transfer system from the vessel’s manifold in case of a failure
- Facility to be designed to meet applicable seismic design standards and potential for extreme weather and river conditions
- Berthing dolphins to be designed to withstand impact loads and loads applied under wind, wake waves and current forces
- Emergency response plan
The residual consequence severity of an offshore LNG release affecting the estuarine environment is also estimated to be low, with potential local, short-term reversible effects on the Air Quality, Vegetation, Wildlife and Wildlife Habitat, Fish and Fish Habitat, and Marine Mammals VCs.
9.3.3 Fire or Explosion
Construction Operation
- Ignition of an LNG spill at the Project facilities - Fire originating from the Tilbury LNG Plant
NA - Siting study to determine hazard distances, hazardous area classification, and ignition source policy
- Facility design and construction according to CSA Z276 Canadian Standard and other applicable codes and standards
- LNG transfer under closed loading condition, no flammable vapours emitted
- Firefighting equipment at the Project facilities, LNG vessels, and assist tugs
- Training on operational procedures and emergency response procedures
- LNG spill mitigations listed for Section 9.3.2
Preliminary results of the quantitative risk assessment undertaken for the Project indicates that the risk for an individual fatality in the immediate vicinity of the Offshore Facilities is once in 10,000 to 100,000 years, with lower likelihood in and around the Onshore Facilities.
WesPac Tilbury Marine Jetty Project Environmental Assessment Certificate Application
Part E – Management Plans and Follow-Up Programs Section 15.0 Conclusions
14
Potential Adverse Residual Effect Project Phase Contributing Project Activity or Physical
Works Mitigation Number Proposed Mitigation Significance Analysis of Residual Effect
(Summary Statement)
9.3.4 Unplanned Shutdown
Construction Operation
Unplanned shutdown NA - ESD system - Insulation of the LNG transfer system, allowing
LNG to remain in the system during prolonged shutdown
- Ability to direct boil-off gas to the LNG storage tank or vessel’s cargo system
No risk scenario is identified for unplanned facility shutdown.
9.3.5 Unplanned Disturbance of an Ecologically Sensitive Area by Equipment Operations
Construction Decommissioning
Unplanned disturbance of the riparian habitat by equipment operations
NA - Environmental training for all contractors and equipment operators
- High-visibility identification of the ecologically sensitive area
Residual risk consequence to the environment of an unplanned disturbance of an ecologically sensitive area by equipment operations is considered to be low with potential for local and short-term reversible effects.
9.3.6 Failure of Sediment Containment
Construction Operation Decommissioning
Failure of construction stormwater drainage system
NA - Drainage system to be designed by qualified professional
- Construction quality control
The residual risk consequence to the environment of a failure of the stormwater drainage system is estimated to be low with local and short-term reversible effects.
9.3.7 Marine Vessel Allision, Grounding or Collision
Construction Operation
- Allision at the Project facilities - Grounding or collision resulting in bunker fuel
release - Grounding or collision resulting in LNG release
and fire
NA - Marine vessel designed according to all applicable codes and standards, including hull construction standards
- Collision-prevention devices (e.g., lights, sound signaling devices, radar reflectors) and navigational safety aids (e.g., compasses, radar, emergency steering)
- Double-hulled LNG vessels and specialized LNG cargo tanks
- Navigation in the Fraser River by experienced master mariner (captain) and a Fraser River pilot
- Three tug escorts for Fraser River transit and berthing operations; tethered escort tugs required for LNG export vessels
- Communication equipment and established communication procedures in the Fraser River
- Safety exclusion zone enforced during berthing and LNG loading operations
- Berthing aid system - Environmental monitoring system; berthing and
unberthing not permitted under extreme weather conditions
- Emergency response plans and coordination with Canadian Coast Guard and Transport Canada for emergency response
Residual risk estimates was considered for:
• Allision at the Project Facility; • Grounding or Collision Resulting in Bunker Fuel Release; • Grounding or collision resulting in LNG release and fire
Residual risk estimates concluded low risk for Allision at the Project facilities, and moderate risk for ground or collision resulting in bunker fuel release and ground or collision resulting in LNG release and fire.
WesPac Tilbury Marine Jetty Project Environmental Assessment Certificate Application
Part E – Management Plans and Follow-Up Programs Section 15.0 Conclusions
15
15.2 Summary of Mitigation Measures The mitigation measures presented in the WesPac Tilbury Marine Jetty Project (Project) Application for an Environmental Assessment Certificate (Application) are summarized below in Table 15-2. These measures were developed to avoid, minimize, restore onsite, or offset the potential adverse effects of the Project on environmental, economic, social, heritage and health pillars as discussed in Part B of the Application.
The mitigation measures are organized in the table by Pillars and Valued Component (VC). Each mitigation measure was given a unique identification number corresponding with the first section of the Application in which it appeared. As the same mitigation measure may apply to more than one VC or Pathway Component (PC), the measure is fully described in the first section in which it appears, and thereafter referenced by number and name. Project design measures or other measures that mitigate the potential effects, in addition to the mitigation measures in the table, are summarized in each VC and PC assessment. Project phase refers to the phase during which Project-related effects will be mitigated by the measure (i.e., Construction, Operation, and Decommissioning). Timing refers to when the mitigation measure will be developed or implemented.
WesPac Midstream —Vancouver LLC (Proponent or WesPac) will also develop the plans required for permitting by the Oil and Gas Commission (OGC), including an Emergency Response Plan. WesPac will implement the Project design, management and contingency measures noted in Section 9.0 Accidents and Malfunctions. In addition, the Proponent will prepare and implement the plans presented in Section 14.0 Management Plans, which will incorporate the mitigation measures in Table 15-2 and monitoring and follow-up programs into Construction, Operation and Decommissioning Environmental Management Plans.
WesPac Tilbury Marine Jetty Project Environmental Assessment Certificate Application
Part E – Management Plans and Follow-Up Programs Section 15.0 Conclusions
16
Table 15-2: Summary of Proposed Mitigation Measures
No. PC/VC Effect Proposed Mitigation Measure Project Phase Timing Legal Requirement? Responsible Agency
Environmental 4.1 River Processes
M4.1-1
Sediment Processes, River Currents, Geomorphology
Release of fine sediments; Changes in river currents; Changes in patterns of local erosion and sedimentation
No specific mitigation is proposed for River Processes. Mitigation is capture under Fish and Fish Habitat and Water Quality VC’s
Construction Operation
n/a n/a n/a
4.2 Fish and Fish Habitat
M4.2-1 Fish and Fish Habitat
Change in habitat quality and function;
Direct loss of habitat;
Direct mortality or behavioural changes;
Riparian habitat loss or degradation
Limit Disturbance Footprint Construction n/a n/a DFO FLNR
M4.2-2 Fish and Fish Habitat
Change in habitat quality and function;
Direct loss of habitat;
Direct mortality or behavioural changes;
Riparian habitat loss or degradation
Site Management Construction Operation Decommissioning
n/a n/a DFO FLNR
M4.2-3 Fish and Fish Habitat
Change in habitat quality and function;
Direct mortality or behavioural changes;
Riparian habitat loss or degradation
Erosion and Sediment Control Plan Construction Operation Decommissioning
n/a Possible DFO FLNR
M4.2-4 Fish and Fish Habitat
Change in habitat quality and function
Design for Stormwater Management Construction Operation Decommissioning
n/a Possible DFO FLNR
M4.2-5 Fish and Fish Habitat
Change in habitat quality and function;
Direct loss of habitat;
Direct mortality or behavioural changes
In-Water Works Management Plan Construction Operation Decommissioning
n/a Possible DFO FLNR
WesPac Tilbury Marine Jetty Project Environmental Assessment Certificate Application
Part E – Management Plans and Follow-Up Programs Section 15.0 Conclusions
17
No. PC/VC Effect Proposed Mitigation Measure Project Phase Timing Legal Requirement? Responsible Agency
M4.2-6 Fish and Fish Habitat
Change in habitat quality and function;
Direct loss of habitat
Develop a Fish Habitat Offset Plan Construction Operation
Decommissioning
n/a Possible DFO FLNR
M4.2-7 Fish and Fish Habitat
Change in habitat quality and function;
Direct loss of habitat;
Direct mortality or behavioural changes
Dredging Management Plan Construction Operation
n/a Possible DFO FLNR
M4.2-8 Fish and Fish Habitat
Change in habitat quality and function;
Direct mortality or behavioural changes
Concrete Works Management Plan Construction n/a Possible DFO FLNR
M4.2-9 Fish and Fish Habitat
Change in habitat quality and function;
Direct mortality or behavioural changes
Minimize the Effects of Creosote Pile Removal Construction n/a n/a n/a
M4.2-10 Fish and Fish Habitat
Change in habitat quality and function;
Direct mortality or behavioural changes
Waste Management Plan Construction Operation Decommissioning
n/a n/a n/a
M4.2-11 Fish and Fish Habitat
Direct loss of habitat;
Direct mortality or behavioural changes;
Riparian habitat loss or degradation
Minimize Shading Construction Operation
n/a n/a n/a
M4.2-12 Fish and Fish Habitat
Riparian habitat loss or degradation Wetland Enhancement and Creation Construction Operation Decommissioning
n/a n/a n/a
M4.2-13 Fish and Fish Habitat
Change to habitat quality and function Ballast Waste Management Plan Operation n/a n/a n/a
M4.2-14 Fish and Fish Habitat
Direct mortality or behavioural changes Underwater Noise Management Plan Construction Operation Decommissioning
n/a n/a n/a
WesPac Tilbury Marine Jetty Project Environmental Assessment Certificate Application
Part E – Management Plans and Follow-Up Programs Section 15.0 Conclusions
18
No. PC/VC Effect Proposed Mitigation Measure Project Phase Timing Legal Requirement? Responsible Agency
4.3 Marine Mammals
M4.3-1 Marine Mammals Change in abundance and distribution Prioritization of Vibratory Pile Driving Methods Construction
Operation Decommissioning
n/a n/a n/a
M4.3-2 Marine Mammals Change in abundance and distribution Installation of Bubble Curtain Construction
Operation Decommissioning
n/a n/a n/a
M4.3-3 Marine Mammals Change in abundance and distribution Ramp-Up/Soft-Start Procedure Construction
Operation Decommissioning
n/a n/a n/a
M4.3-4 Marine Mammals Change in abundance and distribution Sequencing of In-Water Works Construction
Operation Decommissioning
n/a n/a n/a
M4.3-5 Marine Mammals Change in habitat quality and quantity; Change in abundance and distribution
Adherence to Timing Window Construction Operation Decommissioning
n/a n/a n/a
M4.3-6 Marine Mammals Change in abundance and distribution Marine Mammal Management Plan Construction
Operation Decommissioning
n/a n/a n/a
M4.3-7 Marine Mammals Change in abundance and distribution Shut-Down of Vessel during LNG Transfer Construction
Operation Decommissioning
n/a n/a n/a
M4.3-8 Marine Mammals Change in abundance and distribution Vessel Traffic Management Construction
Operation Decommissioning
n/a n/a n/a
M4.3-9 Marine Mammals Change in abundance and distribution Do Not Disturb Marine Mammals Construction
Operation Decommissioning
n/a n/a n/a
M4.3-10 Marine Mammals Change in abundance and distribution Accidental Contact with Marine Mammals Construction
Operation Decommissioning
n/a n/a n/a
4.4 Air Quality
DM4.4-1 Air Quality Project Emissions of Measurable Parameters In-design mitigation to reduce contribution of Project air
emissions Construction Operation Decommissioning
n/a n/a n/a
M4.4-1 Air Quality Project Emissions of Measurable Parameters Ongoing routine maintenance of vehicles and implement
engine idling time restrictions where practical on construction vehicles/vessels
Construction Operation Decommissioning
n/a n/a n/a
M4.4-1 Air Quality Project Emissions of Measurable Parameters Implement engine idling time restrictions on marine vessels to the extent practical
Operation n/a n/a n/a
DM4.4.2-1 Air Quality Project GHG Emissions; Potential for the Project to affect climate
In-design mitigation to reduce contribution of Project GHG emissions
Construction n/a n/a n/a
WesPac Tilbury Marine Jetty Project Environmental Assessment Certificate Application
Part E – Management Plans and Follow-Up Programs Section 15.0 Conclusions
19
No. PC/VC Effect Proposed Mitigation Measure Project Phase Timing Legal Requirement? Responsible Agency
M4.4.2-1 Air Quality Project GHG Emissions; Potential for the Project to affect climate
Ongoing routine maintenance of vehicles and implement engine idling time restrictions where practical on construction vehicles/vessels.
Construction n/a n/a n/a
DM4.4.2-2 Air Quality Project GHG Emissions; Potential for the Project to affect climate
In-design mitigation to reduce contribution of Project GHG emissions
Operation n/a n/a n/a
M4.4.2-2 Air Quality Project GHG Emissions; Potential for the Project to affect climate
Implement engine idling time restrictions on marine vessels to the extent practical
Operation n/a n/a n/a
M4.4.2-3 Air Quality Project GHG Emissions; Potential for the Project to affect climate
Implement a leak detection and repair program Operation n/a n/a n/a
DM4.4.2-3 Air Quality Project GHG Emissions; Potential for the Project to affect climate
In-design mitigation to reduce contribution of Project GHG emissions
Decommissioning n/a n/a n/a
M4.4.2-4 Air Quality Project GHG Emissions; Potential for the Project to affect climate
Ongoing routine maintenance of vehicles and implement engine idling time restrictions where possible on decommissioning vehicles/vessels
Decommissioning n/a n/a n/a
4.5 Noise
M4.5-1 Noise Increase in noise Advise nearby residents of particularly noisy activities and schedule these events to reduce disruption to them.
Construction Decommissioning
n/a n/a n/a
M4.5-2 Noise Increase in noise Establish heavy equipment muster points at least 500 m from any residential dwelling, if possible.
Construction Decommissioning
n/a n/a n/a
M4.5-3 Noise Increase in noise Fit equipment with standard mufflers or silencers and keep these mufflers/silencers in good working order.
Construction Decommissioning
n/a n/a n/a
M4.5-4 Noise Increase in noise Take advantage of acoustical screening from existing on-
site barriers to shield dwellings from construction equipment noise.
Construction Decommissioning
n/a n/a n/a
M4.5-5 Noise Increase in noise Schedule noise emitting maintenance activities during the day whenever possible.
Operation n/a n/a n/a
M4.5-6 Noise Increase in noise Notify residents prior to high noise emitting maintenance activities (if appropriate).
Operation n/a n/a n/a
M4.5-7 Noise Increase in noise Set-up and implement a call in number that people can call when experience a high noise activity.
Operation n/a n/a n/a
4.6 Water Quality
M4.6-1
Surface Water Quality, Sediment Quality, Aquatic Health
Increased suspended sediment due to sediment disturbance
Site Management Construction Decommissioning
n/a n/a n/a
M4.6-2
Surface Water Quality, Sediment Quality, Aquatic Health
Increased suspended sediment due to sediment disturbance
Stormwater Management Plan Construction Decommissioning
n/a n/a n/a
WesPac Tilbury Marine Jetty Project Environmental Assessment Certificate Application
Part E – Management Plans and Follow-Up Programs Section 15.0 Conclusions
20
No. PC/VC Effect Proposed Mitigation Measure Project Phase Timing Legal Requirement? Responsible Agency
M4.6-3
Surface Water Quality, Sediment Quality, Aquatic Health
Increased suspended sediment due to sediment disturbance; Contaminant release due to project activities
In-Water Works Management Plan Construction Decommissioning
n/a n/a n/a
M4.6-4
Surface Water Quality, Sediment Quality, Aquatic Health
Contaminant release due to project activities Creosote Pile Removal Management Plan Construction n/a n/a n/a
M4.6-5
Surface Water Quality, Sediment Quality, Aquatic Health
Increased suspended sediment due to sediment disturbance; Contaminant release due to project activities; Accidental release of deleterious substances
Erosion and Sediment Control Plan Construction Operation Decommissioning
n/a n/a n/a
M4.6-6
Surface Water Quality, Sediment Quality, Aquatic Health
Increased suspended sediment due to sediment disturbance
Scour Protection Plan Construction Operation Decommissioning
n/a n/a n/a
M4.6-7
Surface Water Quality, Sediment Quality, Aquatic Health
Contaminant release due to project activities Concrete Works Management Plan Construction n/a n/a n/a
M4.6-8
Surface Water Quality, Sediment Quality, Aquatic Health
Increased suspended sediment due to sediment disturbance; Contaminant release due to project activities
Dredging Management Plan Construction Operation Decommissioning
n/a n/a n/a
M4.6-9
Surface Water Quality, Sediment Quality, Aquatic Health
Accidental release of deleterious substances Waste Management Plan Construction Operation Decommissioning
n/a n/a n/a
4.7 Vegetation
M4.7-1 Vegetation
Direct loss of wetland and riparian ecosystems; Direct loss of plant species of management concern (plant species at risk and traditional use plants)
Limit Disturbance Footprint (Avoidance) Construction Decommissioning
n/a n/a n/a
M4.7-2 Vegetation
Direct loss of wetland and riparian ecosystems; Direct loss of plant species of management concern (plant species at risk and traditional use plants)
Preserve Native Trees and Vegetation (Minimize) Construction n/a n/a n/a
M4.7-3 Vegetation Direct loss of wetland and riparian ecosystems
Soil Management (Minimize) Construction n/a n/a n/a
WesPac Tilbury Marine Jetty Project Environmental Assessment Certificate Application
Part E – Management Plans and Follow-Up Programs Section 15.0 Conclusions
21
No. PC/VC Effect Proposed Mitigation Measure Project Phase Timing Legal Requirement? Responsible Agency
M4.7-4 Vegetation Direct loss of plant species of management concern (plant species at risk and traditional use plants)
Conduct Pre-construction Surveys for Plant Species at Risk (Minimize)
Construction n/a n/a n/a
M4.7-5 Vegetation
Direct loss of wetland and riparian ecosystems; Direct loss of plant species of management concern (plant species at risk and traditional use plants)
Salvaging Soils and Other Material (Minimize) Construction n/a n/a n/a
M4.7-6 Vegetation
Direct loss of wetland and riparian ecosystems; Direct loss of plant species of management concern (plant species at risk and traditional use plants); Indirect loss of wetland and riparian ecosystems; Introduction/proliferation of invasive plant species
Implementation Monitoring during Construction (Minimize)
Construction n/a n/a n/a
M4.7-7 Vegetation Indirect loss of wetland and riparian ecosystems
Erosion and Sediment Control Plan (Minimize) Construction n/a n/a n/a
M4.7-8 Vegetation Introduction/proliferation of invasive plant species
Invasive Plant Species Management Plan (Minimize) Construction Decommissioning
n/a n/a n/a
M4.7-9 Vegetation Introduction/proliferation of invasive plant species
Revegetate Disturbed Soils (Minimize) Construction n/a n/a n/a
M4.7-10 Vegetation Direct loss of wetland and riparian ecosystems
Wetland Restoration – Enhancement and Creation (Offsetting)
Construction n/a n/a n/a
M4.7-11 Vegetation
Direct loss of wetland and riparian ecosystems; Introduction/proliferation of invasive plant species
Decommissioning and Final Rehabilitation Plan Decommissioning n/a n/a n/a
4.8 Wildlife and Wildlife Habitat
M4.8-1 Wildlife and Wildlife Habitat
Habitat Loss; Disturbance
Limit Disturbance Footprint Construction n/a n/a n/a
M4.8-2 Wildlife and Wildlife Habitat
Habitat Loss; Disturbance
Replant Temporarily Disturbed Habitat Construction Decommissioning
n/a n/a n/a
M4.8-3 Wildlife and Wildlife Habitat
Habitat Loss Fell Trees Away from Sensitive Features Construction n/a n/a n/a
M4.8-4 Wildlife and Wildlife Habitat
Habitat Loss Salvage and Replace Coarse Woody Debris within Temporarily Disturbed Habitat or Habitat Enhancement Areas
Construction Decommissioning
n/a n/a n/a
WesPac Tilbury Marine Jetty Project Environmental Assessment Certificate Application
Part E – Management Plans and Follow-Up Programs Section 15.0 Conclusions
22
No. PC/VC Effect Proposed Mitigation Measure Project Phase Timing Legal Requirement? Responsible Agency
M4.8-5 Wildlife and Wildlife Habitat
Habitat Loss; Disturbance
Identify and Delineate Sensitive Habitat Construction n/a n/a n/a
M4.8-6 Wildlife and Wildlife Habitat
Habitat Loss Maintain Project Activities Away from the Fraser River Construction Operation Decommissioning
n/a n/a n/a
M4.8-7 Wildlife and Wildlife Habitat
Disturbance Develop an Erosion and Sediment Control Plan and a Spill Prevention and Emergency Response Plan
Construction Operation Decommissioning
n/a n/a n/a
M4.8-8 Wildlife and Wildlife Habitat
Habitat Loss; Disturbance; Wildlife Mortality
Develop and Implement a Wildlife Management Plan Construction Operation Decommissioning
n/a n/a n/a
M4.8-9 Wildlife and Wildlife Habitat
Disturbance; Wildlife Mortality
Develop and Implement Wildlife-Specific Light Management as part of Light Management Plan
Construction Operation Decommissioning
n/a n/a n/a
M4.8-10 Wildlife and Wildlife Habitat
Habitat Loss; Disturbance
Develop and Implement an Invasive Plant Management Plan
Construction Operation Decommissioning
n/a n/a n/a
M4.8-11 Wildlife and Wildlife Habitat
Disturbance Develop and Implement Wildlife-Specific Noise Control as part of Noise Management Plan
Construction Operation Decommissioning
n/a n/a n/a
M4.8-12 Wildlife and Wildlife Habitat
Wildlife Mortality Limit and Control Speed on Project Roadways Construction Operation Decommissioning
n/a n/a n/a
M4.8-13 Wildlife and Wildlife Habitat
Wildlife Mortality Survey for and Salvage Amphibians Construction n/a n/a n/a
M4.8-14 Wildlife and Wildlife Habitat
Wildlife Mortality Avoid Vegetation Clearing during the Nesting Season, and Survey for and Avoid Disturbance of Active Nests
Construction n/a n/a n/a
M4.8-15 Wildlife and Wildlife Habitat
Habitat Loss; Disturbance
Wetland Enhancement and Creation Construction Decommissioning
n/a n/a n/a
Economic 5.1 Economy
M5.1-1 Labour Market, Economic Development
Change in employment due to Project labour demand; Change in employment income due to project associated hiring; Change in business opportunities due to Project spending on materials, goods, and services
Local and Aboriginal Hiring and Procurement Policies
Construction Operation
n/a n/a n/a
WesPac Tilbury Marine Jetty Project Environmental Assessment Certificate Application
Part E – Management Plans and Follow-Up Programs Section 15.0 Conclusions
23
No. PC/VC Effect Proposed Mitigation Measure Project Phase Timing Legal Requirement? Responsible Agency
Social Effects Assessment 6.1 Socio-community
M6.1-1 Health and Emergency Services
Change in demand for health and emergency services due to accidents on site
Emergency Management Planning with local first responders
Construction Operation Decommissioning
n/a n/a n/a
6.2 Land and Marine Resource Use M6.2-1
Land and Marine Resource Use
Effect on navigation; Effect on commercial and non-commercial area use and access
Implementation of TERMPOL Recommendations Construction Operation Decommissioning
n/a No n/a
M6.2-2 Land and Marine Resource Use
Effect on navigation;
Effect on commercial and non-commercial area use and access
Compliance with Maritime Regulations and Legislation Construction Operation Decommissioning
n/a Yes n/a
M6.2-3 Land and Marine Resource Use
Effect on navigation; Effect on commercial and non-commercial area use and access
Marine Access and Transportation Management Plan Construction Operation Decommissioning
n/a No n/a
M6.2-4 Land and Marine Resource Use
Effect on navigation; Effect on commercial and non-commercial area use and access
Marine Communication Management Plan Construction Operation Decommissioning
n/a No n/a
M6.2-5 Land and Marine Resource Use
Effect on commercial and non-commercial area use and access
Timing of Construction Activities to Avoid Commercial Salmon Fishery Openings
Construction Operation Decommissioning
n/a No n/a
M6.2-6 Land and Marine Resource Use
Effect on commercial and non-commercial area use and access
Aboriginal Communications Plan Construction Operation Decommissioning
n/a No
n/a
6.3 Current Use of Lands and Resources for Traditional Purposes M6.3-1 Current Use of
lands and resources for Traditional Purposes
Accessing instream locations for FSC harvesting
Marine Access and Transportation Management Plan Construction Operation
Decommissioning
n/a No n/a
M6.3-2 Current Use of lands and resources for Traditional Purposes
Accessing instream locations for FSC harvesting
Marine Communication Management Plan Construction Operation Decommissioning
n/a No n/a
M6.3-3 Current Use of lands and resources for Traditional Purposes
Accessing instream locations for FSC harvesting
Aboriginal Communications Plan Construction Operation Decommissioning
n/a No
n/a
WesPac Tilbury Marine Jetty Project Environmental Assessment Certificate Application
Part E – Management Plans and Follow-Up Programs Section 15.0 Conclusions
24
No. PC/VC Effect Proposed Mitigation Measure Project Phase Timing Legal Requirement? Responsible Agency
6.4 Visual Quality M6.4-1 Visual Quality Presence of visible Project components External Surface Treatment Operation n/a No n/a M6.4-2
Visual Quality Visibility of lighting Construction / Operation Lighting Management Practices Construction
Operation Decommissioning
n/a No n/a
Heritage 7.0 Heritage Resources (Archaeological and Historical Resources)
M7.1-1 Archaeological Resources
Alteration Avoid heritage resources through re-alignment or re-design of components.
Construction Operation Decommissioning
n/a Yes CEA Agency Archaeology Branch
M7.1-2 Archaeological Resources
Alteration; Changes in the level of accessibility
Minimize or reduce effects to heritage resources through alternative protection measures that might include protective covering, stabilization, and physical barriers; Alternative measures to reduce Project effects to archaeological and historical sites
Construction Operation Decommissioning
n/a Yes CEA Agency Archaeology Branch
M7.1-3 Archaeological Resources
Alteration ‘Heritage offset’ to achieve ‘no net loss’ of heritage. Construction Operation Decommissioning
n/a Yes CEA Agency Archaeology Branch
M7.1-4 Archaeological Resources
Alteration Prepare Heritage Resource Chance Find Management Procedure to preserve and properly manage heritage resources that are unexpectedly encountered during Project activities.
Construction Operation Decommissioning
n/a Yes CEA Agency Archaeology Branch
M7.1-1 Heritage Resources
Alteration Avoid heritage resources through re-alignment or re-design of components.
Construction Operation Decommissioning
n/a Yes CEA Agency Archaeology Branch
M7.1-2 Heritage Resources
Alteration; Changes in the level of accessibility
Minimize or reduce effects to heritage resources through alternative protection measures that might include protective covering, stabilization, and physical barriers; Alternative measures to reduce Project effects to archaeological and historical sites
Construction Operation Decommissioning
n/a Yes CEA Agency Archaeology Branch
M7.1-3 Heritage Resources
Alteration ‘Heritage offset’ to achieve ‘no net loss’ of heritage. Construction Operation Decommissioning
n/a Yes CEA Agency Archaeology Branch
M7.1-4 Heritage Resources
Alteration Prepare Heritage Resource Chance Find Management Procedure to preserve and properly manage heritage resources that are unexpectedly encountered during Project activities.
Construction Operation Decommissioning
n/a Yes CEA Agency Archaeology Branch
WesPac Tilbury Marine Jetty Project Environmental Assessment Certificate Application
Part E – Management Plans and Follow-Up Programs Section 15.0 Conclusions
25
No. PC/VC Effect Proposed Mitigation Measure Project Phase Timing Legal Requirement? Responsible Agency
9.0 Accidents and Malfunctions
Section 9.3.1
Air Quality, Fish and Fish Habitat, Marine Mammals, Water Quality, Vegetation, Wildlife and Wildlife Habitat, Human Health
Hazardous material spills on land or affecting estuarine environment
• Compliance with applicable codes and regulations on hazardous material storage and handling for the facility and marine vessels
• Procedures for the safe handling and storage of hazardous materials during construction and operations
• Maintenance of machinery and heavy equipment • Training in the proper handling, identification,
documentation, and storage hazardous materials • Containment for hazardous materials storage in
accordance with applicable regulations • Drainage system to collect stormwater runoff • Spill response equipment • Spill contingency plan
Construction Operation Decommissioning
n/a n/a n/a
Section 9.3.2
Air Quality, Vegetation, Wildlife and Wildlife Habitat, Fish and Fish Habitat, Marine Mammals, Human Health
Onshore and Offshore Loss of Containment of LNG
• LNG transfer system and spill prevention system to be designed according to CSA Z276 Canadian Standard, and will include emergency shutdown (ESD) system and a fire and gas detection system.
• Drainage and spill containment systems that would limit the spread of potential LNG pool.
• Operating range for the flexible cryogenic line and loading arms established based on the required ship movement envelopes
• Drybreak couplings and powered emergency release couplings (PERC) that would shut off LNG flow in case of a failure
• Emergency release system (ERS) that would disconnect LNG transfer system from the vessel’s manifold in case of a failure
• Facility to be designed to meet applicable seismic design standards and potential for extreme weather and river conditions
• Berthing dolphins to be designed to withstand impact loads and loads applied under wind, wake waves and current forces
• Emergency response plan
Construction Operation
n/a n/a n/a
WesPac Tilbury Marine Jetty Project Environmental Assessment Certificate Application
Part E – Management Plans and Follow-Up Programs Section 15.0 Conclusions
26
No. PC/VC Effect Proposed Mitigation Measure Project Phase Timing Legal Requirement? Responsible Agency
Section 9.3.3
Air Quality, Vegetation, Wildlife and Wildlife Habitat, Fish and Fish Habitat, Marine Mammals, Economy, Socio-community, Land and Marine Resource Use, Visual Quality, Human Health
Fire or Explosion
• Siting study to determine hazard distances, hazardous area classification, and ignition source policy
• Facility design and construction according to CSA Z276 Canadian Standard and other applicable codes and standards
• LNG transfer under closed loading condition, no flammable vapours emitted
• Firefighting equipment at the Project facilities, LNG vessels, and assist tugs
• Training on operational procedures and emergency response procedures
• LNG spill mitigations listed for Section 9.3.2 (above)
Construction Operation
n/a n/a n/a
Section 9.3.4 Air Quality Unplanned Shutdown
• ESD system • Insulation of the LNG transfer system, allowing LNG
to remain in the system during prolonged shutdown • Ability to direct boil-off gas to the LNG storage tank
or vessel’s cargo system
Construction Operation n/a n/a n/a
Section 9.3.5
Water Quality, Vegetation, Wildlife and Wildlife Habitat, Fish and Fish Habitat
Unplanned Disturbance of an Ecologically Sensitive Area by Equipment Operations
• Environmental training for all contractors and equipment operators
• High-visibility identification of the ecologically sensitive area
Construction Decommissioning
n/a n/a n/a
Section 9.3.6
Water Quality, Vegetation, Wildlife and Wildlife Habitat, Fish and Fish Habitat
Failure of Sediment Containment
• Drainage system to be designed by qualified professional
• Construction quality control
Construction Operation Decommissioning
n/a n/a n/a
WesPac Tilbury Marine Jetty Project Environmental Assessment Certificate Application
Part E – Management Plans and Follow-Up Programs Section 15.0 Conclusions
27
No. PC/VC Effect Proposed Mitigation Measure Project Phase Timing Legal Requirement? Responsible Agency
Section 9.3.7
Air Quality, Water Quality, Vegetation, Wildlife and Wildlife Habitat, Fish and Fish Habitat, Marine Mammals, Economy, Socio-community, Land and Marine Resource Use, Current Use of Lands and Resources for Traditional Purposes, Visual Quality, Heritage Resources, Human Health
Marine Vessel Allision, Grounding, or Collision
• Marine vessel designed according to all applicable codes and standards, including hull construction standards
• Collision-prevention devices (e.g., lights, sound signaling devices, radar reflectors) and navigational safety aids (e.g., compasses, radar, emergency steering)
• Double-hulled LNG vessels and specialized LNG cargo tanks
• Navigation in the Fraser River by experienced master mariner (captain) and a Fraser River pilot
• Three tug escorts for Fraser River transit and berthing operations; tethered escort tugs required for LNG export vessels
• Communication equipment and established communication procedures in the Fraser River
• Safety exclusion zone enforced during berthing and LNG loading operations
• Berthing aid system • Environmental monitoring system; berthing and
unberthing not permitted under extreme weather conditions
• Emergency response plans and coordination with Canadian Coast Guard and Transport Canada for emergency response
Construction Operation
n/a n/a n/a