97
Environmental Impact Assessment Final Report FOR Proposed construction of Resort on plot bearing gut No. 31/1, 30/2/3(C+E), Mauje Chandranagar, Dapoli, Ratnagiri Submitted to MCZMA Environmental Consultant Building Environment (India) Pvt. Ltd Dakshina Building, Office No-401,4th Floor, Beside Raigard Bhavan, Sakal Bhavan Rd, Sector 11, CBD Belapur, Navi Mumbai, Maharashtra 400614 Telefax: 022 4123 7073/2757 8554 Web: www.beipl.co.in March 2017

Environmental Impact Assessment Final Reportenvironmentclearance.nic.in/writereaddata/EIA/10042018BK7OI2KM... · Environmental Impact Assessment Final Report FOR Proposed construction

Embed Size (px)

Citation preview

Environmental Impact Assessment Final Report

FOR

Proposed construction of Resort on plot bearing gut No. 31/1, 30/2/3(C+E),

Mauje Chandranagar, Dapoli, Ratnagiri

Submitted to

MCZMA

Environmental Consultant

Building Environment (India) Pvt. Ltd

Dakshina Building, Office No-401,4th Floor,

Beside Raigard Bhavan, Sakal Bhavan Rd,

Sector 11, CBD Belapur,

Navi Mumbai, Maharashtra 400614

Telefax: 022 4123 7073/2757 8554

Web: www.beipl.co.in

March 2017

2

1. Introduction ...................................................................................................................... 7

1.1 Introduction ........................................................................................................................... 7

1.2 Need of the Project ................................................................................................................ 8

1.3 Brief Description ................................................................................................................... 9

1.4 Scope of the EIA study.......................................................................................................... 9

1.5 Legal Framework ................................................................................................................ 10

1.6 Organisation of Report ....................................................................................................... 13

2. Project Description ........................................................................................................ 15

2.1 Location of the Project ....................................................................................................... 15

2.2 Connectivity ......................................................................................................................... 16

2.3 Project details ...................................................................................................................... 17

2.4 Land Use .............................................................................................................................. 20

2.5 Construction Details ........................................................................................................... 20

3. Description of the Environment ................................................................................... 23

3.1 Introduction ......................................................................................................................... 23

3.1.1 Environmental Baseline .............................................................................................. 23

3.1.2 Baseline Environmental Quality Data ....................................................................... 24

3.1.3 Methodology ................................................................................................................ 26

3.1.4 Present Environment Scenario: ................................................................................. 26

3.2 Project site and surrounding area ..................................................................................... 27

3.3 Topography and Land Use ................................................................................................. 27

3.3.1 Topography of the area .............................................................................................. 28

3.3.2 Land use cover under the proposed resort ............................................................... 30

3.3.3 Land Use and Land Cover ......................................................................................... 30

3.3.4 Drainage ....................................................................................................................... 31

3.3.5 Climatic conditions ..................................................................................................... 31

3.3.6 Soil ................................................................................................................................ 31

3.3.7 Wind ............................................................................................................................. 32

3.4 Air Environment ................................................................................................................. 32

3.4.1 Observations ................................................................................................................ 34

3.4.2 Wind Speed and Wind Direction ............................................................................... 34

3.4.3 Results .......................................................................................................................... 35

3.4.4 Visibility: ...................................................................................................................... 35

3.4.5 Rainfall ......................................................................................................................... 35

3.5 Baseline Ambient Air Quality Status ................................................................................ 35

3.5.1 Summary of the result of air quality ......................................................................... 36

3.5.2 Summary of the Ambient Quality report is as below .............................................. 37

3

3.6 Ground Water and Surface Water Monitoring ............................................................... 38

3.6.1 Sampling Procedure for Primary Data Collection ................................................... 38

3.6.2 Methodology for Sampling ......................................................................................... 39

3.6.3 Discussion on Result: .................................................................................................. 41

3.7 Geology of The Area ........................................................................................................... 42

3.7.1 Hard Rock Areas ......................................................................................................... 43

3.7.2 Soil Quality Monitoring .............................................................................................. 44

3.8 Noise Environment .............................................................................................................. 47

3.8.1 Ambient Noise Level Standards ................................................................................. 47

3.8.2 Locations of Noise Level Monitoring......................................................................... 47

3.8.3 Findings ........................................................................................................................ 48

3.9 Flora and Fauna .................................................................................................................. 49

3.9.1 Baseline Status ............................................................................................................. 49

3.9.2 Location of Biological Study ...................................................................................... 49

3.9.3 Methodology of Biological Study ............................................................................... 49

3.9.4 Flora and fauna in and around the project site ........................................................ 50

3.10 Socio–Economic Information ............................................................................................. 57

3.11 Seismology ........................................................................................................................... 59

4. Anticipated Impacts and its Mitigations ...................................................................... 61

4.1 Sources of Pollution: ................................................................................................................. 61

4.1 Impact on Land Environment ........................................................................................... 61

4.2 Impact on Soil and Geology ............................................................................................... 62

4.3 Potential Impact on Water Quality ................................................................................... 62

4.4 Impact on Noise Environment ........................................................................................... 63

4.4.1 During construction phase ......................................................................................... 63

4.4.2 During operation phase .............................................................................................. 63

4.5 Impact on Ecology ............................................................................................................... 64

4.5.1 Construction Phase ..................................................................................................... 64

4.5.2 Functional Phase ......................................................................................................... 64

5. Environmental Monitoring Program ........................................................................... 66

5.1 Monitoring Plan during Construction Phase .................................................................... 66

5.2 Environment monitoring plan during construction and operation phase ..................... 67

5.2.1 During Construction phase ........................................................................................ 67

5.2.2 During Operational phase: ......................................................................................... 68

5.3 Environment Cost ............................................................................................................... 69

6. Project Benefit ................................................................................................................ 70

7. Environment Management Plan ................................................................................... 71

4

7.1 Land Environment .............................................................................................................. 71

7.2 Management of Solid Waste............................................................................................... 71

7.2.1 During Construction Phase ........................................................................................ 72

7.2.2 During Operation Phase ............................................................................................. 72

7.2.3 Storage of Waste.......................................................................................................... 73

7.3 Air Environment ................................................................................................................. 75

7.4 Noise Pollution ..................................................................................................................... 76

7.5 Water Environment ............................................................................................................ 76

7.5.1 Proposed location of STP ........................................................................................... 79

7.6 Green Belt Development ..................................................................................................... 81

Disclosure of Consultants Engaged .............................................................................. 82

8.1 Project Details ............................................................................... Error! Bookmark not defined.

8.2 Project Team ................................................................................. Error! Bookmark not defined.

8.3 EIA Coordinator ........................................................................... Error! Bookmark not defined.

8.4 Functional Area Expert ................................................................ Error! Bookmark not defined.

8.5 Functional Area Code Details .................................................................................................. 86

9. Annexures ....................................................................................................................... 88

9.1 Result of Ambient Air Quality Monitoring ................................................................... 88

9.2 Noise Monitoring Results ......................................................................................................... 95

LIST OF TABLES

Table 1-1: Key Applicable Acts &Regulations for the project .......................................... 10

Table 2-1: Connectivity to the project site ........................................................................... 16

Table 2-2: Details of the project ........................................................................................... 19

Table 2-3: The details of the work involved in development of the resort along with

material of construction and quantity.................................................................................. 20

Table 3-1: Environmental attributes .................................................................................... 23

Table 3-2: Environmental Attributes: Frequency and Monitoring Method .................... 24

Table 3-3: Important features observed in 5 km buffer zone ............................................ 25

Table 3-4: Climatic condition details ................................................................................... 31

Table 3-5: Mean Wind speed in Ratnagiri district ............................................................. 32

Table 3-6: National Ambient Air Quality Standards ......................................................... 32

Table 3-7: Accuracy of Meteorological Equipment ............................................................ 33

Table 3-8: Monthly Normal Rainfall.................................................................................... 35

Table 3-9: Ambient air monitoring report .......................................................................... 37

Table 3-10: Result of Ground water and surface water quality monitoring .................... 40

5

Table 3-11: Details of Soil Quality Monitoring Locations ................................................. 44

Table 3-12: Soil quality results ............................................................................................. 46

Table 3-13: National Ambient Noise Level .......................................................................... 47

Table 3-14: Existing trees at site ........................................................................................... 50

Table 3-15: Available plants in and around Chandranagar, Ratnagiri ........................... 50

Table 3-16: Availability of animals in and around Chandranagar, Ratnagiri ................ 53

Table 3-17: List of Butterfly Species Reported During the Study..................................... 55

Table 4-1: Pollutants generated in construction phase ...................................................... 61

Table 4-2: Total nos. of trees proposed to be planted ......................................................... 64

Table 5-1: Project Startup checklist ..................................................................................... 66

Table 5-2 67

Table 5-3: Environment Monitoring plan during Operational Phase .............................. 68

Table 5-4: Estimated environment cost ............................................................................... 69

Table 7-1: Solid Waste Generation during Operation Phase ............................................ 73

Table 7-2: Waste disposal ...................................................................................................... 74

Table 7-3: Water Budget for the Resort 2 ........................................................................... 77

LIST OF FIGURES

Figure 1-1: District map of Maharashtra .............................................................................. 7

Figure 1-2: Ratnagiri district map ......................................................................................... 8

Figure 2-1: Project location................................................................................................... 15

Figure 2-2: Connectivity map at the project site ................................................................. 17

Figure 2-3: Layout of the project superimposed on Google image ................................... 19

Figure 3-1: Google image of site with 5 km radius ............................................................. 27

Figure 3-2: Topography 5 km around the project site ....................................................... 29

Figure 3-3: 5 km and 10 km radius drawn on topography sheet ...................................... 30

Figure 3-4: Layout of the proposed resort superimposed on the Google image .............. 30

Figure 3-5: Wind rose pattern .............................................................................................. 34

Figure 3-6: Air monitoring locations.................................................................................... 36

Figure 3-7: Location of water sampling ............................................................................... 39

Figure 3-8: Geomorphology of Ratnagiri district ............................................................... 44

Figure 3-9: Soil monitoring locations ................................................................................... 45

Figure 3-10: Location of the Noise monitoring ................................................................... 48

Figure 3-11: Literacy deatils ................................................................................................. 58

Figure 3-12: Vocational study Pattern ................................................................................. 59

6

Figure 3-13: Seismic Zone of India....................................................................................... 60

Figure 7-1: Bin system ........................................................................................................... 73

Figure 7-2: OWC location at the project site ...................................................................... 75

Figure 7-3: Water Balance (dry season) .............................................................................. 78

Figure 7-4: Water Balance (wet season) .............................................................................. 79

Figure 7-5: Phytorid technology ........................................................................................... 80

7

9. Introduction

1.1 Introduction

The Ratnagiri district lie at the heart of Konkan, a charming stretch of land on the west cost of

India, endowed with a beautiful seashore, picturesque mountains and scenic natural beauty,

and known for tropical fruit like the delicious golden Alphonso mango, cashew, jackfruit, spice

crops, coconut, areca nut and Kokam. The region is bordered by Sahyadri hills on the east and

Arabian Sea on the west. It is a tract of high rainfall ranging between 3000 to 5000 mm a year.

Indeed, the Maharashtra Sahyadris, a part of the mountain chain of Western Ghats, are one of

the country’s water towers, source of Krishna and Godavari, two major east-flowing rivers of

Peninsular India, and a large number of west flowing rivers. The latter flow into the sea through

highly productive estuaries fringed by mangroves. These abut upon long stretches of beaches,

where, on a clear day, you can see the sea-bed through a depth of 20 ft. The natural vegetation

cover of the region is mangrove forest on the coast and tropical evergreen forest inland, with

stunted tree growth and a rich herbaceous flora on the wind-swept plateaus. Today, the fertile

alluvial valleys produce rice and coconut as the main crops; the hill slopes harbour mango and

cashew nut orchards. The estuaries and the coast support rich fisheries.

Figure 9-1: District map of Maharashtra

Dapoli is one of the most sought after destination in Konkan. It is also called the "Mini

Mahabaleshwar" because of its cool climate throughout the year. It was habituated as a military

base by British army and later grown as an educational hub of the district. Situated at around

800 feet from sea level, it's a unique location and offers a hill-station experience surrounded

by attractive beaches. Dapoli is blessed with untouched beaches, historic monuments, beautiful

temples and holistic places as well as archeologically important sites along with its rich

biodiversity.

8

Figure 9-2: Ratnagiri district map

The proposed project is a construction of Resort on plot bearing gut No. 31/1, 30/2/3(C+E),

Mauje Chandranagar, taluka Dapoli, district Ratnagiri. This site falls under CRZ III category

as per the land use map and situated within 200-500m from HTL of Arabian Sea.

Keeping in view the principal of sustainable development in Coastal area as pronounced in

Coastal Regulation Zone Notification, 2011 and taking into account the tourism potential of

the Ratnagiri District, a resort is proposed at village Chandranagar, taluka Dapoli, and district

Ratnagiri. The land is a private ownership land and developable as per the local town and

country planning regulations.

1.2 Need of the Project

Tourism sector is transforming into mainstream sector of the economy of the India.

Government of India is taking up various initiatives to push the tourism sector into orbit

towards achieving economic prosperity for the county. Until, the tourism in India was largely

dependent on rich class of the country and travelers from the foreign lands. Now, since, the

economy of the India is gearing up which has created the substantial middle class, which is

turning out to be major game changer for the tourism sector. Now, middle class of the country

sees tourism as requirement to explore the life and enjoys the pleasures of the life. Hence, a

gap of demand and supply has emerged towards catering the tourism destinations,

infrastructure and tourism services. This is an opportunity to develop world class tourist

destinations, which will be in sync with the nature.

The target area of the project is village Chandranagar, Taluka Daploli of Ratnagiri District,

Maharashtra. Ratnagiri is part of the Coast of the Maharashtra which is famously known as

‘Konkan Coast’. Konkan is also a land of culture and human heritage, with many famous hill

and sea forts and pilgrimage centers. Agriculture, horticulture, fisheries and tourism have

9

therefore been the traditional pillars of economy of these districts. More recent times have

witnessed industrial development, with a chemical industry hub springing up at Lote, coal and

natural gas based power production and mining, and a proposed nuclear power facility.

Village Chandranagar is a coastal village in Dapoli taluka of Ratnagiri. Dapoli and its

surrounding area of Ratnagiri District has rich rich tourism potential, which is unexplored upto

the mark. Coastal area, flat & hilly terrain, vegetation make up pleasant climate. Tourist places

nearby are Ganapati pule, Guhagha, Veleneshar, Velas, Jaigad etc. are major tourist attractions.

The eco-friendly resort destination with all necessary facilities & services at the site would be

perfect setting to boost the tourism potential of the area.

1.3 Brief Description

The proposed project is a construction of Resort on plot bearing gut No. 31/1, 30/2/3(C+E),

Mauje Chandranagar, taluka Dapoli, district Ratnagiri. This site falls under CRZ III category

as per the land use map and situated within 200-500m from HTL of Arabian Sea. The proposed

development of resort 2 is as follows:

Reception, restaurant and kitchen

Cottages 10 Nos

1.4 Scope of the EIA study

The purpose of EIA process is to identify and assess the potential benefits or adverse impacts

of development projects on the surrounding environment consisting of land, air, water and

biological factors, taking in to account environmental, economic, social, cultural and aesthetic

considerations.

The specific objectives of EIA are:

To identify and describe the elements of the community and environment

likely to be affected by the proposed development.

To review the current environmental status of the area within 5Km radius of

the project site - collection of baseline data on the environmental attributes

including air, noise, water, land, ecological, hydro-geological climate and

socio-economic environments.

To assess likely or potential environmental impacts of the proposed activity on

air, water, soil, noise, waste generation land, ecological, hydro-geological

climate and socio-economic aspects during the construction and operation

phases of the project.

To provide necessary mitigation measures to prevent or minimize any adverse

impacts cost-effectively.

To prepare a comprehensive Environmental Management Plan to ensure that

the environmental quality of the area would be preserved.

To formulate a strategy for effective monitoring and identify any deviations in

the environmental quality after the project is operational, which would help in

evolving measures to counter these.

10

1.5 Legal Framework

Table 9-1: Key Applicable Acts &Regulations for the project

Issues Applicable

Legislation

Agency

Responsible

Applicable Permits and

Requirement

Status

Environmental

Protection

The

Environment

(Protection) Act

1986, as

amended in

April 2003;

MPCB Compliance under the rules

to maintain stipulated

standards and

environmental management

through various supporting

rules promulgated under the

Act.

CTE and

CTO shall be

obtained

under Air and

Water Acts

Protection and

improvement

of Natural

Environmental

Resource

Article 51-A

Clause (g) of

the& Directive

Principles of

State Policy

(Article 47)

Every

Citizen of

India

India states that it shall be

the duty of every citizen of

India to protect and improve

the natural environment

including forests, lakes,

rivers and wildlife and to

have compassion for all

living creatures.

Consent for

Establishment

Consent to Operate

Compliance under the

Act

Followed

Protection of

the coastal

environment

Coastal Zone

Regulation Act

1991 under

Environment

Protection Act,

1986

The proposed

activity is

permissible

under the

CRZ

Regulations,

1991. Due

clearance is

being sought

before any

development.

The

ecologically

sensitive area

shall not be

developed

within the

NDZ.

11

Issues Applicable

Legislation

Agency

Responsible

Applicable Permits and

Requirement

Status

Prevention

and Control of

Water

Pollution

The Water

(Prevention and

Control of

Pollution) Act,

1974, amended

in 1988

MPCB Consent for

Establishment

Consent to Operate

Compliance under the

Act

As the

project

progresses,

the client will

apply for

CTE from the

appropriate

regulatory

agencies

followed by

CTO &

compliance

Prevention

and Control of

Air Pollution

The Air

(Prevention and

Control of

Pollution) Act,

1981, amended

in 1987 and the

Air (Prevention

and Control of

Pollution) Rules

1982, as

amended up to

18thFeb 1992.

MPCB Consent for

Establishment

Consent to Operate

Compliance under the

Act

As the

project

progresses,

the client will

apply for

additional

CTE from the

appropriate

regulatory

agencies

followed by

CTO &

compliance

Water Cess

Collection (a

tax on water

use and water

pollution

caused)

The Water

(Prevention

&Control of

Pollution) Cess

Act 1977, been

implemented in

the state of

Maharashtra

with effect from

1st April 1983

MPCB Filing of monthly returns as

per prescribed format (Form

I under

the Act- Form I duly

completed before 5th of

next month showing

water consumed in the

previous month)

As the

project

progresses,

the client will

apply for

Water Cess

from the

appropriate

regulatory

agencies

Environmental

Protection –

EIA related

Environmental

Impact

Assessment

Notification,

September 2006

MoEFCC

through

MCZMA

Requirement of CRZ

Clearance Environmental

Impact Assessment for

environmental appraisal of

the project by MCZMA

The client

has applied

for CRZ

clearance

12

Issues Applicable

Legislation

Agency

Responsible

Applicable Permits and

Requirement

Status

Noise

Emissions

The Noise

(Regulation &

Control) Rules,

2000 as

amended in

January 2010

MPCB Compliance under the rules

to maintain stipulated

standards

Baseline

studies

completed

Monitoring

will be

undertaken

once the

project is

initiated

Effective

conservation

and

management

of natural

ecosystems

(including the

mangroves)

Forest

Conservation

Act, 1980

The National

Forest Policy,

1988

State

Department

of Forest

Compliance of the acts &

policy to conserve & mange

the mangroves in the

vicinity

Baseline

studies

completed

Monitoring

will be

undertaken

once the

project is

initiated

Protection &

conservation

of Marine

flora & fauna,

birds and other

wild life

The Coastal

Regulation Zone

Notification,

1991 amended

in 2011,

National

Biodiversity Act

2002and the

Environment

(Protection) Act

,1986

Compliance of the acts &

policy to conserve &

manage the wildlife in the

vicinity

Baseline

studies

completed

Monitoring

will be

undertaken

once the

project is

initiated

Hazardous

material

Storage

Handling

&Transport

Manufacture

Storage and

Import of

Hazardous

Chemicals 1989

and amendment

Rules 2000

under the

Environment

(Protection) Act,

1986, and Rules

framed there

under

MPCB Identification of Major

Accident Hazard under

Rule 4

Filing of Safety Report

under Rule10

Preparation of Onsite

and Offsite Emergency

Control Plan under

Rules 13 & 14

Collection,

Development and

Dissemination of

Construction

Chemical

usage like

solvents,

paints, oil,

etc should be

recorded and

the MSDS

need to be

maintained.

13

Issues Applicable

Legislation

Agency

Responsible

Applicable Permits and

Requirement

Status

information including

Do’s and Don’ts and

labelling for hazardous

substances handled

onsite under Rule 17

1.6 Organisation of Report

The report has been divided into following chapters:

Chapter 1. Introduction:

This chapter provides the purpose of the report, background information of the proposed

project, brief description of nature, size and location of project, objectives of the project,

estimated project cost, scope and organization of the study. The key environmental legislation

and the standards relevant to the project and the methodology adopted in preparation of this

report have also been described in this chapter.

Chapter 2. Project Description:

This chapter deals with the need of the project, location, environmental setting of the project,

details of project, other technical and design details and sources of pollution from the proposed

activity and measures proposed to control pollution.

Chapter 3. Description of the Environment:

The chapter presents the methodology and findings of field studies undertaken to establish the

environmental baseline conditions, which is also supplemented by secondary published data.

Chapter 4. Anticipated Environmental Impacts & Mitigation Measures:

This chapter details the inferences drawn from the environmental impact assessment of the

proposed project during various phases of project advancement, such as design, location of

project, construction and regular operations. It also describes the overall impacts of the

proposed project activities and underscores the areas of concern, which need mitigation

measures.

14

Chapter 5. Environmental Monitoring Program:

Environmental monitoring requirements for effective implementation of mitigation measures

during operational phase have been delineated in this chapter.

Chapter 6. Project Benefits:

In this chapter describes various benefits of the project to the community in the vicinity and as

well as to the region on the whole.

Chapter 7. Environmental Management Plan (EMP):

It also provides recommendations/ Environment Management Plan (EMP) including mitigation

measures for minimizing the negative environmental impacts of the project.

Chapter 8. Summary & Conclusion:

This Chapter highlights the expected benefits of the proposed plan to the socio-economic

scenario in the study area and to the country as a whole.

Chapter 9. Disclosure of Consultants Engaged:

The list of various experts involved in preparation of the present EIA/EMP report is given along

with brief introduction of the consultancy organization involved in EIA report.

15

10. Project Description

2.1 Location of the Project

The project is located in village Chandranagar, taluka Dapoli, district Ratnagiri. Proposed

resort is situated on Plot bearing gut No. 31/1, 30/2/3(C+E), Mauje Chandranagar, taluka

Dapoli, district Ratnagiri. Village Chandrangar is a coastal village in Dapoli taluka of Ratnagiri

district which lies between Latitude 17° 44' 55.94"N & Longitude 73° 07' 37.51"E.

Ratnagiri district stands along the western coast of India. It is situated at south side of the

coastline of the Maharashtra state, known as ‘south konkan’. Ratnagiri district lies between

Latitude: 16.990215 and Longitude: 73.3120233. It has north-south length of about 180 km

and average east-west extension of about 64 km. Sahyadri hills surround it in the east beyond

which there are Satara, Sangli and Kolhapur districts, Raigad district in the north, the Arabian

Sea in the west and Sindhudurg district in the south.

Figure 10-1: Project location

16

2.2 Connectivity

Village Chardranagar is situated in Dapoli taluka of Ratnagiri district of the Konkan Coast of

Maharashtra. The village has Gram panchayat and has local geographical area around 742 ha.

Table 10-1: Connectivity to the project site

From Distance

From Head Quarter

Ratnagiri

99 km

From Dapoli Camp 4 km

From Mumbai 169 km

Nearby villages Karde (3 km ) , Gavhe ( 3 km) , Asud ( 3 km ) , Pangar Wadi ( 4

km) , Dapoli Camp ( 5 km)

Nearby Talukas Mandangad Taluka towards North, Khed Taluka towards East,

Guhagar Taluka towards South, Mhasala Taluka towards North.

Nearby Tourist

places

Murud Karde, Harnai, Anjanvel, Guhaghar, Harihareshwar,

Dapoli

By Air: Nearby Airport is Lohegoan Airport which is around 138 km from the

village Chandranagar. The Ratnagiri Airport is about 100 kms but not under

use for commercial transport at this moment and the facility is being upgraded

By Rail: Chandranagar has no Railway Station. Nearby Railway Station to

reach Chandranagar is Khed Rail Way Station which is 31 km from the project

site. Ratnagiri Rail Way Station is major railway station 95 km near to

Chandranagar.

By Road: The project site at Chandranagar is accessible from State Highway-

4 and Murud ladghar Major District Road 08. There is an internal road

network developed and maintained by the Grampanchayat Chandranagar.

Road widths are of about 16 m and well maintained.

17

Figure 10-2: Connectivity map at the project site

2.3 Project details

The central ideal behind the development of the resort is to build with nature. Keeping in mind

the unique coastal ecology of the project site which is having hill sloppy and flat terrain,

overseeing the majestic view of the Arabian Sea. The resort is planned to be built with wooden

structures supported by the RCC piles, so that it will have lesser footprint on the ground.

Wooden frame structure for the resort, instead of Solid concrete construction, will be

environmentally sustainable and will add to aesthetics of the environment of the project site.

The purpose behind the project are:

To build the eco-friendly resort which is environmentally sustainable. It would be one

of its kind in Konkan Coast.

To meet the growing demands of tourism in Konkan Coast

To create an environment that could support the good standard of living environment;

To enhance the surroundings with greenery, landscaping and pleasing aesthetics; and

To implement the policy of water conservation (STP and Rain Water Harvesting),

renewable energy (Use of Solar Energy), recycling of waste (Use of Organic

Converter).

The design of the layout has taken into consideration the state of art design features for

residential space, living atmosphere and arrangements of open space so as to create a pleasant

living and working environment. Adhering to provisions of the CRZ Notification, 2011, the

development of the resort is proposed beyond the 200 m to 500 m from the HTL of the Arabian

sea, as per the guidelines stipulated in CRZ Notification, 2011.

18

The proposed development of resort will involve site formation works and construction of

wooden resort villas, access wooden roads, drains and sewer connections. The villas are

proposed to locate on a sloppy terrain.

Details of the proposed structure in Resort 1 are as follows:

Reception restaurant and kitchen

Cottages 10 Nos

The FSI and Height of the resort is well within the permissible limit i.e 0.33.and 9m

respectively, as stipulated in CR Notification, 2011.

Total Plot Area: 15950 m2

Deduction: 2640 m2

Plot area after deduction: 13310 m2

Net plot area (90) %: 11979 m2

Total built up area: 1315.68 m2

FSI consumed: 0.109

Road area: 881.81 m2

Paved area/ pathway: 881.81 m2

Green Area: 6289.75 m2

All the development is proposed between 200 m to 500 m from the HTL of the Arabian sea, as

per the guidelines stipulated in CRZ Notification, 2011.

The project site at Chandranagar village is fronting to Arabian Sea, hence, the CRZ setback

area is 500 m from the High Tide Line from the Arabian Sea, hence, attracts the provisions of

the CRZ Notification, 2011 and guidelines of Annexure III of the CRZ Notification, 2011

pertaining to development of beach resorts/ Hotels for tourists in CRZ areas.

The project site at Chandranagar was surveyed on by the Institute of Remote Sensing (IRS),

Chennai, which is one of the authorized agency of the Ministry of Environment and Forest,

New Delhi. As per the survey, the project site is situated is near to shore area and covered with

normal upland vegetation. There is no mangrove seen in the vicinity of the project site.

19

Figure 10-3: Layout of the project superimposed on Google image

Table 10-2: Details of the project

Sr

No.

Particulars Details

1 Type of project Resort project

2 Total Project area 15950 Sqm

3 Total Built up Area 1315.68Sqm

4 Fresh Water Requirement KLD

5 Total Water Demand 11 KLD

Rainwater Harvesting by way of installing Storage

Tanks of capacity 10,000 litre at each villa is

proposed.

6 Waste Water Generation 8.5 KLD

7 Sewage Treatment Plant

Capacity

9 KLD

8 Solid Waste Generation Bio-degradable- 22.2 kg/day

Recyclable- 14.8 kg/day

Provision of Organic Waste Convertor is made.

20

9 Power Requirement 225 KWH

10 Energy efficient system Energy Efficient Lighting using LEDs in Common

Areas of villas and toilet.

Solar Street Lights along pathways and open spaces

11 DG set Requirement 250 KVA – 1 set

12 Green Land Development 6289.75 Sqm

13 Paved area 881.81 Sqm

14 Parking As per requirement, parking provision is proposed:

Car- 47

Scooter-84

Cycle-84

2.4 Land Use

The proposed project site of irregular shape and the land is agricultural land, however, since

long time, the land is not under cultivation.

Attachment 1: The project layout with FSI details and parking plan is attached.

2.5 Construction Details

Table 10-3: The details of the work involved in development of the resort along with material of

construction and quantity

Sr

No.

Work details Quantity

1 Excavation for foundation in Earth Soil of all type of

sand, Gravel, Soft Murum including removing

the excavated materials upto a distance of 50 metres

beyound the building area and lift as specified, stacking

and spreading as directed including dewatering unless

provided elsewhere, preparing the bed for the foundation

and necessary backfilling, ramming, watering complete

including shoring and struting.

526.40 Cum

2 Providing soling using 80mm size trap metal in layers of

15cm each including filling voids with sand, ramming,

watering etc. complete.

20.25 Cum

3 Providing and laying in situ cement concrete in

proporation M-15 of trap metal dor foundation and

13.50 Cum

21

bedding, including bailing out water manually plywood/

steel formwork, compacting and curing complete

4 Providing M-25 R.C.C. cast in situ board piles using

minimum cement quantity at the rate of 300 Kg. per cum.,

Each of load- capacity as per design and of specified

diameter or as directed, placed through steel shell sunk to

the required depth through all strata except hard rock,

excluding provision of reinforcement, including placing

concrete by tremie arrangement, compaction of concrete

and withdrawl of shell including chippings, dressing of

R.C.C. piles cleaning the reinforcement etc. complete.

38.40 Cum

5 Providing and casting in situ cement concrete M-20 of

trap metal for R.C.C. Slabs and landings of all thickness

as per detailed drawings and designs, including centering,

plywood/steel formwork compacting, roughening the

surface if special finish is to be provided and curing

complete. including providing and placing C.C. cover

block of required size at rate of 27 Nos. per 10

square metre to reinforcement to give a clear cover as

per I.S. 456-2000 (Excluding steel reinforcement

Including admixtures/plasticizers/water proofing agents

etc complete)

137.55 Cum

6 Filling in plinth and floors with contractor's murum in

15 cm to 20 cm layers including watering compaction

complete. (Initial 5 Km lead)

661.38 Cum

7 Providing 15cm thick Laterite Stone Masonry in cement

mortar 1:4 including scaffolding, racking out joints and

watering complete. (Size of laterite stone 350mm x

275mm x 150mm) ( 6 sides cut ) ( Mortar joint

thickness not more than 12mm )

881.31 Sqm

8 Providing and fixing in position TMT Bar FE 500 HCRM

from

SAIL CRS FE 500D from TATA Tiscon Steel bar

reinforcement of various diametres in all positions for

R.C.C. pile caps, footings, foundations, slabs, beams,

columns, canopies, staircases, newels, chhajjas, lintels,

pardies, coping, fins, arches, etc. as per detailed

designs, drawings and schedules, including cutting,

bending, hooking the bars, binding with wires or tack

welding and supporting as required complete. (5

Kms.Leaiv)

14.8 MT

9 Providing and applying water proofing treatment to

vertical surface of brick and R.C.C. wall, elevated and

overhead R.C.C./Brick water tanks and sumpwell etc.

in all directions by using standard acrylic copolymer

15000 litre

22

coating of Roff Hyguard, Monopol 456, Dr. Fixit 2k

pidifin

2k or cleaseal of apparna or acqua sheild of sk

formulation or quivalent in two coats including cleaning

the surface by wire brush, washing and drying including

covering guarantee of 10 years on court stamp paper

of Rs.100 and as directed by Engineer in Charge etc.

complete.

(Prior permission of S.E. in writing is necesssary before

inclusion of item in estimate)

10 Providing and applying water proofing treatment to

vertical surface of brick and R.C.C. wall, elevated and

overhead R.C.C./Brick water tanks and sumpwell etc.

in all directions by using standard acrylic copolymer

coating of Roff Hyguard, Monopol 456, Dr. Fixit 2k

pidifin

2k or cleaseal of apparna or acqua sheild of sk

formulation or quivalent in two coats including cleaning

the surface by wire brush, washing and drying including

covering guarantee of 10 years on court stamp paper

of Rs.100 and as directed by Engineer in Charge etc.

complete.

(Prior permission of S.E. in writing is necesssary before

inclusion of item in estimate)

249.50 Sqm

11 Cottage Built up area 69.34, Volume of prefabricated

material

WOOD IN TON: - 23.40, Volume of prefabricated

material

VOLUME IN M3 :- 58.50 , Total Volume of Material

in Cubic

Mtr :- 585.00 .

10 no.

12 Reception & Restaurant Built up area 212.18, Volume of

prefabricated material WOOD IN TON:- 135.00,

Volume of prefabricated material VOLUME IN M3 :-

337.50 , Total Volume

of Material in Cubic Mtr :- 337.50 .

1 Nos.

13 Plumbing and wiring

23

11. Description of the Environment

3.1 Introduction

As a first step in the Impact assessment, it is necessary to know the existing environmental

conditions to establish the baseline. These baseline conditions when compared with the

prevailing natural ambient environmental conditions, one can assess whether the area under

surveillance is polluted, degraded or not. It is also possible to quantify the degree of existing

pollution & degradation. This baseline data always serves as a point of reference to know the

impact of development. Depending on the nature & extent of effect of proposed activity,

corrective or mitigative measures are considered accordingly & formulated. The baseline

information is also useful to delineate the merits as well as pros & cons of the proposed

development. This is one of the quintessential aspects for the decision makers while

considering environmental clearance. This chapter presents the existing baseline environmental

status of the project influenced area (within 5km radius) of the project site.

3.1.1 Environmental Baseline

The database for all environmental components is collected from primary site investigations as

well as secondary database. Furthermore, the primary data has been obtained from

Environmental Monitoring surveys viz. air, water, noise & meteorology using standard

published / reference protocols. Table 3-1 gives various environmental attributes considered

for formulating environmental baseline and Table 3-2 gives frequency and monitoring

methodology for various environmental parameters.

Table 11-1: Environmental attributes

S.

No.

Attribute Parameter Source of Data

1 Land Use Trend of land use for different

categories

Land Use Map

2 Water Quality Physical, Chemical and

Biological parameters

Grab samples are collected at three

surface water (Creek Water)

locations

3 Ambient Air

Quality

PM10, PM2.5, SOx, CO and NO2 Ambient air quality monitoring at

three locations

4 Ecology Existing marine ecology and

biodiversity terrestrial flora and

fauna within 5 km radius of

project influence area

Primary survey and Secondary

data

5 Soil Soil types and samples analyzed

for physical and chemical

parameters.

Data collected from soil sample

analysis at one onsite location

24

6 Ambient

Noise

Noise levels Ambient noise quality monitoring

at three locations

Table 11-2: Environmental Attributes: Frequency and Monitoring Method

Attributes Sampling Method Remarks

Network Frequency

Air Environment

Respirable Suspended

Particulate Matter

(RSPM)

Requisite

locations in the

project influence

area

24 hourly Gravimetric (High-

Volume with

Cyclone)

As per

CPCB

standards

for

NAAQM,

2009

Oxides of Sulphur

(SO2)

24 hourly EPA Modified West

& Gaeke method

Oxides of Nitrogen

(NOx)

24 hourly Arsenite modified

Jacob & Hochheiser

Carbon Monoxide (CO) 8 hourly OSHA ID 210 l,

Shimadzu.

Water

Parameters for water

quality:

pH, temp, turbidity,

total potassium,

salinity, Total nitrogen,

total phosphorus, DO,

BOD, Heavy metals,

faecal coliforms,

Chlorophyll a

Set of grab

samples at

requisite

locations for

surface water

(Creek water)

1 time APHA methodology Samples

for water

quality

collected

and

analysed as

per CPCB

water

quality

standards

for coastal

waters

Land Environment

pH, texture, electrical

conductivity, organic

matter, nitrogen,

phosphate, sodium,

calcium, potassium and

magnesium

Requisite soil

samples be

collected as per

BIS specifications

within project

influence area

Once Collected and

analyzed as per soil

analysis reference

book, Jackson M.L.

3.1.2 Baseline Environmental Quality Data

25

Baseline environmental condition constitute the basis for evaluation of impact of the proposed

development on the existing Environmental parameters. Baseline Environmental Conditions

can be broadly grouped into following categories:

Physical Environment which includes air, water, land, terrestrial flora & fauna, civic

infrastructure, public services, etc.

Social Environment includes demography, community facilities and services,

community characteristics, local economy, employment centre, commercial facilities

servicing the area, etc.,

Aesthetic Environment includes historical monuments, archaeological or architectural

sites at and in the vicinity of the proposed project activity. Economic environment

covers employment levels, sources and levels of income, economic base of the area,

land values, land ownership etc.

For the present EIA study, the following environmental attributes within 5 km and 10 Km

radius are considered for Baseline data:

Land environment (Topography, land use, solid waste disposal etc.);

Air environment (Meteorology, ambient air quality, noise levels)

Water environment (Ground, Surface and Drinking Water);

Biological environment (Flora, fauna, ecosystem); and

Socio-economic environment (Demography, occupational structure, educational,

medical facilities, literacy etc.)

The baseline environmental quality data for various components of environment, viz. Air,

Noise, Water, Land, flora and Socio-economic were generated during November 2016 to

February 2017 in the study area covering 5 km around the project at village Chandranar resort

site. Other environmental data on flora and fauna, land-use pattern, forest etc were also

generated through field surveys and also collected from different State Govt. Departments. The

Map of study area covering resort site at Chandranagar as core zone and 5 km radius around

core zone as Buffer Zone is depicted at Figure 3-2. Important features observed in 5 km buffer

zone are given at Table 3-3.

Table 11-3: Important features observed in 5 km buffer zone

Name of application Development of resort

Location Chandranagar Village

Taluka Dapoli

District Ratnagiri

Topo Sheet No. E43N1

Mean sea level Around 27 m above mean sea level.

Latitude and longitude 17° 44' 55.94"N & 73° 07' 37.51"E

Present land use pattern Coastal strip waste land having

vegetation, shrub and open land.

26

3.1.3 Methodology

Appropriate methodologies have been followed in developing the EIA/ EMP report. The

methodology adopted for the study is outlined below:

Conducting reconnaissance surveys for knowledge of the study area;

Selecting sampling locations for conducting various environmental baseline studies;

The sampling locations have been selected on the basis of the following:

Predominant wind directions recorded by IMD

Existing topography;

Drainage pattern and location of existing surface water bodies like lakes/ponds, rivers

and streams;

Location of villages/towns/ sensitive areas, and;

Areas, which represent baseline conditions;

The field observations have been used to:

Assess the positive and negative impacts due to the proposed resort project;

Suggest appropriate mitigation measures for negating the adverse environmental impacts,

if any, and;

Suggest post-project monitoring;

3.1.4 Present Environment Scenario:

The site under consideration at village chandranagar is private nonforest land. The present

environment scenario is described below:

Population –The population density and traffic movement in the chandranagar area is

low.

Industrial activities -The area is underdeveloped and have no major, medium industries,

industrial and associated activities.

Topography and Drainage – The investigated area is made up of coastal plain land by

sparsely vegetated gently sloping hills.

Climate – The climate of this district is typical of that on the west coast of India, with

plentiful and regular seasonal rainfall, oppressive weather in the hot months and high

humidity throughout the year. The summer season from March to May is followed by the

southwest monsoon season from June to September. October and November form the

post monsoon, December to February winter season.

Agriculture – No agriculture activities are being carried out in the project area.

Specific data in respect of Ambient Air Quality (AAQ), Water Quality (WQ), Noise

Levels (NL), Soil Quality (SQ), Socio-Economic Status (SES), Flora and Fauna were

established in study area for Environmental Impact Assessment (EIA) and preparation of

Environmental Management Plan (EMP).

27

3.2 Project site and surrounding area

The area proposed for resort at village Chandranagar is a coastal track and having hilly and flat

terrain. The vegetation is sparse. Here and there few thorny bushes only. The land is at present

not being used for any specific purpose.

Figure 11-1: Google image of site with 5 km radius

From the google image, it is observed that the site of the resort at village chandranagar is having

sloppy and flat terrain.

3.3 Topography and Land Use

The project site at village Chandranagar is situated in under Dapoli taluka of the district

Ratnagiri, which is situated on the edge of the Deccan plateau. Most of the landscape of the

Ratangiri district has been influenced by the deccan lava. The district Ratnagiri has five

characteristic landforms, namely:

Coastline

Estuarine plains and river basins

Lateritic plateaus

Residual hills and

Scarp faces of the Sahyadri

The district forms a part of the deccan trap region, which is primarily a plateau, extending from

the sea coast to continental divide, where peaks rise to 1000 meters at places. It has around 167

28

km sea long sea coast and 180 km long Sahyadri hill range. Over 85% of the land surface in

Ratnagiri district is hilly. All rivers in the district originate in the Sahyadri ranges and flow

from east to west and merge in Arabian sea. The lateritic plateau that occupies most of the

district are either formed in-situ from the lateralisation of Deccan Trap Basalt or are of

secondary nature, formed due to the lateritic material brought down from the Sahyadri hill

ranges.

The region has a highly-dissected terrain with flat topped hills. The Western Ghats, running

parallel to and at a distance of 50-60 km from the coast rise to greater heights. The drainage

along the coast is almost westerly and considered as a submerged coast, characterized by the

presence of numerous creeks and estuaries, which severely restrict the continuity of coast and

consequently the extent of deposits. Closer to the coast, deep weathering of Deccan basalt gives

rise to thick pile of laterites.

The geomorphology of the study area is its highly uneven nature with very narrow reverie

plains that fringe the coastline. Small hills, which project from the main ranges, are separated

from each other by undulating plateaus having area gradually increasing westward towards the

coast.

3.3.1 Topography of the area

The toposheet in 1:50000 scale from the survey of india is obtained to determine the topography

of the site at village chandranagar, District Ratnagiri. The topography is indicating the surface

shapes and features. The map also showing the contour, significant stream or other water

bodies, forest covert, built up area and other surface features of the area.

29

Figure 11-2: Topography 5 km around the project site

The topography of the site under reference at village Chandranagar shows hilly and flat terrain

and vegetation and shrubs. The land is sloppy in nature.

The 5 km and 10 km radius is drawn on the topography sheet, which is attached as Figure 3-3.

30

Figure 11-3: 5 km and 10 km radius drawn on topography sheet

3.3.2 Land use cover under the proposed resort

Figure 11-4: Layout of the proposed resort superimposed on the Google image

The said superimposition clearly indicates that the land is a mix of vegetation, shrubs and open

sloppy land.

3.3.3 Land Use and Land Cover

31

The remote sensing studies in EIA are of great importance due to their capabilities in analyzing

the environmental problems which arise from number of developmental activities. This

technology has emerged as a powerful tool in providing reliable multispectral, multi-temporal

information on various natural resources in spatial format. It has an important role in effective

mapping and periodic monitoring of natural resources and environmental processes.

With the rapid improvement in spatial and spectral resolution of data obtained in visible and

near infrared regions the need for assessment of land environment in different perspective is

addressed effectively. Modifications of the land surface during urbanization can produce

tremendous changes in the pattern of vegetative cover, agriculture and water course. Changes

in land cover and vegetation can be indication of environmental degradations/ alterations. Land

use pattern from the satellite image surrounding the project area is given below.

Land use and land cover of the Ratnagiri district of the year 2011-2012 obtained from the

National Remote Sensing Centre, Hyderabad is given in Figure 3-3.

3.3.4 Drainage

The project area is sloppy terrain and has natural gradient towards Western side i.e. towards

Arabian side.

3.3.5 Climatic conditions

Konkan belt experiences tropical warm, humid or maritime climate throughout the year with

regular rainfall of an average 2286-2540 mm during monsoon and the temperature difference

(between minimum and maximum) hardly exceed 10°C. Atmospheric temperature varies from

25-35°C with the average humidity ranging between 60-90%.

Table 11-4: Climatic condition details

The region can broadly be classified in two types - Very High Rainfall Non-lateritic (VRN)

soil zone of north Konkan and Very high Rainfall Lateritic (VRL) soil zone in the southern

coastal parts. The soils from the VRN zone shows varying content and pattern of distribution

of organic carbon throughout the soil depth while in the VRL zone it is in the range of low to

very low in the profile. The available phosphorus is more in the soils from VRN zone than

VRL zone, while the soils from both the zones are well supplied with available K. Both VRN

and VRL soils contain adequate available Mn and Cu but are deficient in the micronutrients

like B, Fe and Zn, which is a major problem in rice cultivation in these soils. The variation in

the soil salinity according to the season is a common feature of coastal saline soils.

3.3.6 Soil

The soils of Konkan are mainly of alluvial and residual types. The residual soil occurs on the

hilltops or slopes while alluvial is seen along the river valleys. Lateritic soil is formed in the

hilly upland where the rainfall is more than 200 cm, which is rich in Fe, Al, Ti. Nevertheless,

it is devoid of lime and poor in organic matter. Soil is lateritic in the south (Sindhudurg and

Ratnagiri districts) while it is read and loamy and alluvial towards the north Thane district).

Temperature Rainfall (mm) Humidity Wind speed km/h

15.9-35.4 937.6 58-90 9.8

32

There is wide variation in the physico-chemical properties of coastal salt affected soils in the

Konkan. The region can broadly be classified in two types - Very High Rainfall Non-lateritic

(VRN) soil zone of north Konkan and Very high Rainfall Lateritic (VRL) soil zone in the

southern coastal parts. The soils from the VRN zone shows varying content and pattern of

distribution of organic carbon throughout the soil depth while in the VRL zone it is in the range

of low to very low in the profile. The available phosphorus is more in the soils from VRN zone

than VRL zone, while the soils from both the zones are well supplied with available K. Both

VRN and VRL soils contain adequate available Mn and Cu but are deficient in the

micronutrients like B, Fe and Zn, which is a major problem in rice cultivation in these soils.

The variation in the soil salinity according to the season is a common feature of coastal saline

soils. In addition, anthropogenic interruptions like construction of embankment,

3.3.7 Wind

Winds are very strong and are mainly westerly or south westerly during the monsoon. In the

rest of the year winds blow from directions between north and east in the mornings and between

west and north-west in the afternoons.

Table 11-5: Mean Wind speed in Ratnagiri district

Jan. Feb. Mar. Apr. May. Jun. Jul. Aug. Sept. Oct. Nov. Dec. Annual.

9.3 10.5 10.8 11.1 11.9 12.2 14.5 12.2 8.5 8.2 8.9 8.7 10.7

3.4 Air Environment

Ambient air is basically natural state of the air in the outdoor environment. Composition of the

air depend upon may factors, such as climatic parameters, land elevation, pollutants etc.

Ambient air quality monitoring is required to determine the existing quality of the air.

Background information of the village Chandranagar such as topography, land use, wind speed/

directions, rainfall, source of pollution etc. has been considered, in order to understand air

quality around the project area.

Since, development of the resort is mainly with wooden structure and minimum solid concrete

construction is involved for the RCC, Rainwater Harvesting and Bio-digester, the project is not

a major contributor to the air pollution except for particulate matter emission during

construction phase due to excavation and machinery and vehicular pollution during use phase.

Ministry of Environment and Forest have defined the National Ambient Air Quality standards.

Accordingly, air quality parameters such as PM10, PM2.5, Oxides of Nitrogen (NOx), Sulphur

dioxide (SO2) and Carbon monoxide (CO) were monitored. This assessment was done by

examining sources of air emissions within a 10 Km radius of the proposed project site and

through site specific background sampling program. In this manner, background data collected

was expected to be representative of all meteorological condition.

Table 11-6: National Ambient Air Quality Standards

Sr

No.

Pollutant Time

Weighted

Avg

Concentration in Ambient Air in

ug/Cum

33

Industrial,

Residential, Rural

and other areas

Sensitive Areas

1 Sulpher Dioxide Annual Avg 50 20

24 Hours 80 80

2 Nitrogen Dioxide Annual Avg 40 30

24 Hours 80 80

3 Particulate Matter

(PM10)

Annual Avg 60 60

24 hours 100 100

4 Particulate Matter

(Pm2.5)

Annual Avg 40 40

24 hours 60 60

5 Carbon Monoxide 8 Hours avg 2 mg/Cum 2 mg/Cum

1 Hour avg 4 mg/Cum 4 mg/ Cum

6 Lead Annual Avg 0.5 0.5

24 Hours 1 1

7 Ozone 8 hours Avg 100 100

1 Hour Avg 180 180

The Central Monitoring Station (CMS) equipped with continuous monitoring equipment was

installed at site Chandranagar village at a height of about 10 m above ground level to record

wind speed, wind direction, temperature, relative humidity & rain fall. The meteorological

monitoring station was located in such a way that it is free from any obstructions and as per the

guidelines specified under IS - 8829. The accuracy of the equipment is as given below in Table

3-7.

Table 11-7: Accuracy of Meteorological Equipment

Sr. No. Sensor Accuracy

1. Wind speed Sensor ± 1 m/s

2. Wind direction Sensor ± 3 degrees

3. Temperature Sensor ± 0.5 0C

Ten minutes values of wind speed, wind direction, temperature, relative humidity and rainfall

were recorded continuously with monitoring equipment. All the sensors were connected to the

filter and then logged on to data logger. The readings were recorded in a memory module,

34

which was attached to data logger. The memory module was down loaded in computer through

Weather Link software.

3.4.1 Observations

The observations for Wind speed, Wind direction, Temperature, Relative Humidity and Rain

fall were collected during period i.e. November 2016 to February 2017. The observations are

elaborated under following four headings i.e. wind speed & wind direction, temperature &

relative humidity and cloud cover-rain fall.

3.4.2 Wind Speed and Wind Direction

During the sampling period, hourly wind speed and wind directions were recorded. The results

of wind speed and 16 wind directions are depicted in the Figure 3-5 as wind rose.

Figure 11-5: Wind rose pattern

35

3.4.3 Results

The predominant wind direction was from NW (27%), N (15.5%).Wind blows from directions

between north and north east in the morning, which changes to west and northwest in the

afternoon. During monsoon, wind flows from west and south west direction. Avg wind speed

is 8 km/h.

3.4.4 Visibility:

Visibility is generally good for most part of the year. There is possibility of lesser visibility

during monsoon. On an average the visibility is expected to be over 4.0 Km for about 300 days

in a year.

3.4.5 Rainfall

The average annual rainfall for the district as a whole is 3461.3 mm. The rainfall increases

rapidly from the coast towards the Western Ghats on the eastern border of the district. In and

near the Ghats, rainfall is very heavy. Practically the entire annual rainfall occurs during the

months June to October. The rainiest month is July when one third of the annual rainfall is

received. The normal monthly rainfall for Dapoli station is 3741.9 mm which is given in the

Table---

Table 11-8: Monthly Normal Rainfall

Month Rainfall mm Month Rainfall mm

Jan 0.5 : Jul 1301.6

Feb 0.0 : Aug 950.2

Mar 0.0 : Sep 409.6

Apr 5.0 : Oct 101.8

May 38.4 : Nov 27.5

Jun 904.4 : Dec 2.9

: Total 3741.9

Heaviest Rainfall In 24 Hrs 535.4 mm, 03rd Jun 1982

Source: Climate of Maharashtra

3.5 Baseline Ambient Air Quality Status

Sampling locations are selected considering predominant prevailing wind direction and on the

basis of sensitive receptors within 10 km of radius. Five of the sampling points were considered

within the project site itself and rest of the two locations were decided considering the

sensitivity of receptors.

36

Figure 11-6: Air monitoring locations

3.5.1 Summary of the result of air quality

3.5.1.1 PM10 Particulate Matter

Particle pollutants include dust, ash, soot, lint, smoke, pollen, spores, algal cells and other

suspended materials. Particulates are often the most visible form of air pollution since they

reduce visibility and leave dirty deposits on windows, painted surfaces and textiles. PM10 is a

measure of particles in the atmosphere with a diameter of less than 10 or equal to a nominal 10

mm. PM10 is particulate matter with an aerodynamic diameter of up to 10 µm, i.e. the fine and

coarse particle fractions combined.

The Maximum PM10 concentration at all air quality monitoring stations A-1, A-2, A-3, A-4,

A-5 are 39.1, 41.6, 47.0, 46.2 and 39.6 µg/m3 respectively. All monitored stations have PM10

concentrations less than half of 24 hours’ average limit, 100 µg/m3 as prescribed for industrial,

residential, rural and other areas as in revised NAAQ Standards from MoEF. These values

represent quite satisfactory condition regarding PM10 concentration in ambient air.

3.5.1.2 PM2.5 Particulate Matter

Particulate Matter-2.5 particles are air pollutants with a diameter of 2.5 mm or less, small

enough to invade even the smallest airways. These particles generally come from activities that

37

burn fossil fuels, such as traffic, smelting, and metal processing. PM2.5 particles are known to

produce respiratory and cardiovascular illness.

The Maximum PM2.5 concentration at all air quality monitoring stations A-1, A-2, A-3, A-4

and A-5 are 19.9, 20.4, 22.8, 26.1, and 25.3 µg/m3 respectively. All monitored stations have

PM2.5 concentrations less than half of annual 24 hours’ limit, 60 µg/m3 as prescribed for

industrial, residential, rural and other areas as in revised NAAQ Standards from MoEF. These

values represent quite satisfactory condition regarding PM2.5 concentration in ambient air.

3.5.1.3 Sulphur Dioxide (SO2):

Sulphur dioxide produces drying of the mouth, scratchy throat and smarting eyes. It also causes

chest constriction, headache, vomiting and death from respiratory diseases. This gas originates

from combustion of fossil fuels. SO2, SO3, H2SO4vapour and sulphur contribute to SO2 values

and can cause health problems, corrosion and injury to vegetation.

The Maximum SO2 concentrations at all sampling stations A-1, A-2, A-3, A-4, and A-5 are

9.3, 10.6, 17.3, 10.5 and 8.7 µg/m3 respectively. All monitored stations have SO2

concentrations well within stipulated annual 24 hours’ limit, 80 µg/m3 as prescribed for

industrial, residential, rural and other areas as in revised NAAQ Standards from MoEF.

3.5.1.4 Oxides of Nitrogen (NOX)

High temperature combustion as well as use of explosives produces oxides of nitrogen which

in turn result in photo-chemicals smog and can contribute to vegetation damage and acid rain.

Diesel also produces NOx that is easily absorbed in the blood and then reduces the oxygen-

carrying capacity of the blood. It makes the lung tissues brittle and leathery and can cause lung

cancer and emphysema (severe breathing problems).

The Maximum NOx concentrations at all sampling stations A-1, A-2, A-3, A-4, A-5, andA-6

are 10.5, 13.5, 19.4, 13.1 and 10.4 µg/m3 respectively. All monitored stations have NOX

concentrations well within stipulated annual 24 hours’ limit, 80 µg/m3 as prescribed for

industrial, residential, rural and other areas as in revised NAAQ Standards from MoEF.

3.5.1.5 Carbon Monoxide (CO):

Samples of air were collected and analyzed for CO content but CO concentration could not be

detected. Hence, the concentration of Carbon mono oxide was found below detectable limit at

all sampling stations.

Overall Ambient Air Quality of Chandranagar project area and its buffer zone is good during

monitoring period and there are no any abnormal values recorded. Concentrations of all

monitored parameters are within stipulated standards from MoEF AAQ Standards.

3.5.2 Summary of the Ambient Quality report is as below

The ambient air monitoring report is given below in Table 3-9.

Table 11-9: Ambient air monitoring report

Sr No. Location Pm10 Pm2.5 SOx NOx

38

1. A1 Max- 39.1

Min- 29.9

Avg- 34.5

Max- 19.9

Min-16.2

Avg- 18.5

Max-9.3

Min-6.3

Avg-7.8

Max-10.5

Min-7.4

Avg-8.95

2. A2 Max-41.06

Min-37.00

Avg-39.03

Max-20.4

Min-16.7

Avg-18.2

Max-10.6

Min-7.1

Avg-8.9

Max-13.5

Min-10.7

Avg-24.2

3. A3 Max- 47.00

Min- 36.7

Avg-41.85

Max-22.8

Min-18.4

Avg-18.55

Max-17.3

Min-9.9

Avg-8.85

Max-19.4

Min-11.6

Avg-15.6

4. A4 Max- 46.2

Min-38.8

Avg-42.5

Max-26.1

Min-16.8

Avg-21.45

Max-10.5

Min-7.7

Avg-9.1

Max-13.1

Min-8.7

Avg-10.9

5. A5 Max-39.6

Min-31.2

Avg- 35.4

Max-25.3

Min-16.8

Avg-21.05

Max-8.7

Min-6.2

Avg-7.45

Max-10.4

Min-7.4

Avg-8.9

Standard 100 60 80 80

Ambient Air monitoring value observed at all the monitoring stations are depicted in the above

table. It has been observed that the parameters such as PM10, Pm 2.5, SOx, Nox and Co are

well within the permissible limit of the CPCB standards. It is further stated that the proposed

activities involve minimum excavation and construction (as most of the construction is above

the

3.6 Ground Water and Surface Water Monitoring

3.6.1 Sampling Procedure for Primary Data Collection

Ground and surface water sources covering 5 km radial distance were examined for physico-

chemical, trace metals and microbiological parameters in order to assess the effect of industrial

and other activities on surface and ground water. Uniform protocol on water quality monitoring

as specified by the Ministry of Environment and Forests (2005) was followed for selection of

parameters.

The samples were collected and analyzed as per the procedures specified in “Standards

Methods for the Examination of Water and Waste Water‟ published by American Public Health

Association (APHA) 21st edition (2005). Selected physico-chemical and bacteriological

39

parameters have been analyzed for evaluating the existing base line water quality status in the

study area.

3.6.2 Methodology for Sampling

The buffer zone monitoring locations were finalized based on the drainage of the area.

Following features were also given due consideration:

Toposheet maps and google image to identify major water bodies;

Water sources both ground and surface water bodies like rivers

3.6.2.1 Ground Water Monitoring

The groundwater contamination occurring due to either natural causes or anthropogenic

activities needs regular monitoring of water quality to device ways and means to protect it.

Samples were collected in last week of January, 2017 from available water sources in the study

area. Grab samples of surface and ground water were collected. On spot analysis was carried

out for the parameters like pH, Temperature, Odour, Taste, DO etc.

3.6.2.2 Location of Sampling Stations

2 ground water and 2 surface water samples were collected during January, 2017. There are 2

borewells into the project site. The location of water sampling stations selected in 5 km buffer

zone of Chandranagar Project area is depicted in the figure 3-7

Figure 11-7: Location of water sampling

40

Water Quality has been analysed with respect to following parameters:

Physical parameters such as Ambient temperature, colour, odour, Turbidity, Total

Dissolved Solids, Total Suspended Solids

Chemical parameters such as PH, Nitrate as No3, Total Hardness as CaCO3, Total

Alkalinity as CaCO3, Chloride as CL, Sulphate as SO4, Floride as F, Dissolved Oxygen,

E Conductivity

Elemental parameters such as calcium, copper, iron, Mercury, Magnesium, Mangenese

Microbiological parameters such as total coliform and E Coli.

Result of Ground water and surface water quality monitoring report is tabulated as below:

Table 11-10: Result of Ground water and surface water quality monitoring

Sr. No. Parameters Units SW-1 SW-2 GW-1 GW-2

Limit as

per

IS:1050

0

Physical Parameters

1

Ambient

Temperature 0C 26.4 26.8 26.8 26.5

2 Colour Hazen CL CL Turbid CL <5

3 Odour - AG AG AG AG

4 Turbidity NTU <5 <5 7.93 0.98 <1.0

5 TDS Mg/lit 370 260 430.2 212.5 <500

6 TSS Mg/lit <10 <10 <10 <10 NS

Chemical Parameters

1 PH - 7.9 8.2 7.1 8.4 6.5-8.5

2 Nitrate as NO3 Mg/lit 0.4 0.5 1.48 0.17 <45.0

3

Total Hardness as

CaCO3 Mg/lit 149 136

150.0 42.0

<200.0

4

Total Alkalinity

as CaCO3 Mg/lit 35 32

68.3 96

<200.0

5 Chloride as CL Mg/lit 40.3 39.5 177.3 38.43 <250.0

41

Sr. No. Parameters Units SW-1 SW-2 GW-1 GW-2

Limit as

per

IS:1050

0

6 Sulphate as SO4 Mg/lit 21.1 21.2 67.4 57.2 <200.0

7 Fluoride as F Mg/lit 0.12 0.1 0.16 0.11 <1.0

8

Dissolved

Oxygen Mg/lit 5.6 5.4

1.7 1.9

NS

9 E Conductivity Us/cm 351 300 1048 903 NS

Elemental parameters

1 Calcium (Ca) Mg/lit 41.7 43.2 58.25 55.78 <75.0

2 Copper (Cu) Mg/lit BDL BDL BDL BDL <0.05

3 Iron (fe) Mg/lit 0.78 0.84 0.4 0.03 <0.3

4 Mercury (Hg) Mg/lit BDL BDL BDL BDL <0.001

5 Magnesium (mg) Mg/lit 8.1 7.8 30.83 30.01 <30.1

6 Mangenese (Mn) Mg/lit 0.13 0.15 <0.1 <0.1 <0.1

Microbiological parameters

1 Total Coliform

MPN/100

ml 900 500

6/7 6/7

Absent

2 E coli

MPN/100

ml <2 <2

9 6

Absent

BDL: Below Detection Limit NS: Not specified Note: For E Coli and coliform, limit of <2 can be considered as Absent

3.6.3 Discussion on Result:

The ambient temperature of ground water samples varied from 26.5 to 26.8 ºC: while for

surface water sample 26.4-26.8 ºC all values of ambient temperature for all surface and

ground water samples are representing a scenario, free of any thermal discharge.

42

With respect to Colour and odour, Surface water sample and ground water samples are

Clear in appearance, except GW 1 which is turbid. All surface water samples and

ground water samples collected for Odour test did not have any objectionable odour.

Turbidity occurs due to presence of suspended matter or colour pigment in water sample.

High values of turbidity indicate abnormal activity in related area. Turbidity of all

surface and ground water samples has less than 5 NTU, except GW 1 which has turbidity

7.93. Except GW 1, Turbidity values for all of samples are less than permissible limit (5

NTU) as prescribed in IS: 10500 of 2012.

PH values of SW1 and SW2 are 7.9 and 8.2PH values of GW 1 and GW 2 are 7.1 and

8.4. These values are within Acceptable range of 6.5 to 8.5 as per IS 10500:2012

Surface water sample have Dissolved Oxygen levels ranging from 5.4 to 5.6 mg/l which

indicates the good water quality.

Total dissolved solid of GW1 and GW2 are 430.2 and 22.5 respectively. TDS of SW1

and SW2 are 370 and 260 respectively, which are less than permissible limit of 500 mg/l

as per standards

Chloride in surface water samples ranging from 39.5 to 40.3 mg/l and ground water

ranges from 38.43 to 177.3 mg/l these values are below permissible limit of 250 mg/l as

prescribed in IS 10500:2012.

All ground water and surface water samples have fluoride value is around 0.1 mg/l which

are much lower than acceptable limit of 1.0 mg/l as per in IS 10500:2012.

Ground water samples have Coli forms and surface water samples have Coliforms 1100

MPN/100 ml Thus; the surface water samples are contaminated. This is due to surface

runoff entering these sources.

GW 1- Turbidity more than permissible limit and Iron more than desirable limit. E

coli and Coliform limits are exceeding the permissible limit. Not fit for drinking purpose.

With treatment, the water can be used for potable use.

GW 1- Chemically fit for drinking purpose, however, E coli and Coliform limits are

exceeding the permissible limit. With treatment, water can be used for potable use.

3.7 Geology of The Area

Ratnagiri because of its location i.e. the coastline and proximity to the Sahyadri ranges,

following soil types can be observed. (GSDA, 2009). Ratnagiri because of its location i.e. the

coastline and proximity to the Sahyadri ranges, following soil types can be observed. (GSDA,

2009)

Coarse Shallow Soil: They are reddish brown in colour and occur on the slopes of the

hills and are partly eroded, poor in fertility, shallow in depth and course in texture. These

soils are ideal for Cashew and Mango plantations.

Medium Deep Soil: These are reddish yellow in colour and have various names

depending upon the place of occurrence. Those situated at higher elevations are known

as Mal, while at slightly lower levels are known as Kuyat. Near water courses, which

have a fair supply of water during Rabi creekson are known as Panthal or Vaigan. Paddy

43

is grown on these soils during Kharif. On Panthal soils pulses and summer paddy can

also been grown.

Deep Soil: They occur along river banks or valleys and are usually of mixed origin and

are yellowish red to brown in colour. They are light, easily workable, well drained and

fairly fertile. Areca nut and coconut gardens are grown well on these soils.

Coastal Alluvial Soil: They are found along the coastal strip and consist of deep sandy

loams suitable for Coconut and Areca nut.

Coastal Saline Soil: They are formed due to the inundation of the creek, whereby part of

coastal soils becomes salty. They are locally known as Khar, Khajan and Kharvat etc.

They are found along coastal strip of Dapoli, Guhagar and Ratnagiri tehsils.

Geotechnical Hazards are many & diverse. The most common hazards are due to: Ground

water, Slope instability, Subsidence, compressible soil, swelling soil, weak soil, weathering of

soil & rock. Nearly all geotechnical hazards are associated in some way with water.

Water in soil & rocks can, through reducing effective stress, bring about a reduction in strength

which may lead to slope becoming unstable. Changes in ground water conditions can cause the

collapse of surface voids that can result in subsidence. Changes in moisture content in certain

clay-rich soils can result in swelling & shrinkage leading to structural damage of building

founded in them. The movement of water through certain rocks & soil can result in weathering

at rate that may result in changes in the mechanical properties during the life of a structure

placed on or in them. Slope Instability is a generic term that refers to the movement of soil &

rocks under the influence of gravity. Terms such as landslides, slips, slumps, mudflows & rock-

falls are commonly used to describe different type of slope instability.

3.7.1 Hard Rock Areas

Deccan Trap Basalt

Major part of the district is covered by basaltic lava flows of Upper Cretaceous to Lower

Eocene age. The lava flows are predominantly of ‘aa’ type with ‘pahoehoe’ type flows

occurring at few places. Deccan Trap Basalt forms an important water bearing formation in the

district. The primary porosity in the vesicular units is negligible due to lack of interconnection

and secondary filling. The secondary porosity due to cooling joints, partition planes, cracks

and fissures play an important role in ground water circulation especially in the highly porous

‘pahoehoe’ flows.

Degree of weathering and topographic setting also plays a major role in respect of productivity.

In Basalt, ground water occurs in Vesicular and Massive Basalt as well as inter-flow zones in

weathered mantle and fractured zones. In general, ground water occurs under water table

conditions in shallow aquifer and semi-confined to confined conditions in deeper aquifer. The

unconfined aquifer is developed due to the weathering and jointing of upper flow in Basalt

down to depth of 15-20 m bgl and the yield of the wells tapping such aquifer varies from 15 to

145 m3/day. Bore wells are not common in the district due to poor ground water potential of

deeper aquifers of Deccan Traps and their yield varies between 2 and 20 m3/hr.

Laterite

Laterite has better porosity due to intricate network of sinuous conduits making it porous

formation. The ground water circulates through a network of voids and conduits, joints and

fractures. The lithomarge clay occurring at base act as aquiclude preventing further percolation

of ground water and springs emerge at this contact due to lateral movement of ground water.

44

Only dug-wells are found in this formation tapping aquifer down to about 15 m and their

yield varies from about 4 to 22 m3/day.

Figure 11-8: Geomorphology of Ratnagiri district

3.7.2 Soil Quality Monitoring

The physico-chemical and fertility characteristics of the soils around the project area were

examined by obtaining soil sample from selected points and subsequent analysis of the same.

Table 11-11: Details of Soil Quality Monitoring Locations

Sr no. Location

1 S 1 at Chandranagar

2 S 2 ( Ladghar )

45

Figure 11-9: Soil monitoring locations

46

3.7.2.1 Soil Characteristics around project area

The soil samples were collected from locations. Table 3-12 summarizes the soil quality is as

below:

Table 11-12: Soil quality results

Sr

No.

Parameter S1 S2 Unit

Physical parameter

1 Moisture

content

4 3 Percent

2 Porosity 38.9 43.8 Percent

3 Water Holding

capacity

28.9 26.8 Percent

4 Soil Texture Red (Loamy) Red (Loamy) -

Chemical parameters

1 PH 5.20 5.10

2 E Conductivity 0.159 0.223 Us/cm

3 Total organic

matter

1.22 2.1 Percent

4 Total carbon 0.9 0.10 Percent

5 Nitrate 0.08 0.09 Mg/kg

6 Sulphate 125.6 122.6 Mg/kg

8 Cation

Exchange

18 25 Meq/100g

9 Calcium

Carbonate

7.8 6.7 Mg/kg

10 Total Nitrogen 360.3 250.8 Mg/kg

11 Total

Phosphorus

351.8 278.9 Mg/kg

12 Total Potasium 250 245.8 Mg/kg

47

3.8 Noise Environment

Unwanted sound which is disturbance is called Noise. Noise pollution indicates the presence

of excessive and disturbing noise from machines, vehicles, instruments, transpirations etc. It is

harmful for physical and mental health of the living beings. It interferes with the work zone

activities of the people if the noise levels are more than the permissible levels.

3.8.1 Ambient Noise Level Standards

Ministry of Environment & Forests vide SO 123(E) dated 11.2.2000 notified the Noise

Pollution (Regulation and Control) Rules, 2000. It is based on a weighted equivalent noise

level (Leq). National Ambient Noise Level Standards are given below in Table 3-13.

Table 11-13: National Ambient Noise Level

Area

Code Category of Area

Limits in dB(A) Leq

Day time Night time

A Industrial Area 75 70

B Commercial Area 65 55

C Residential Area 55 45

D Silence Zone** 50 40

** Silence zone is defined as area up to 100 meters around premises of hospitals, educational

institutions and courts. Use of vehicle horns, loud speakers and bursting of crackers are banned

in these zones.

Ambient noise level or sound pressure levels (SPL) were measured by a Portable sound level

meter. A-weighted equivalent continuous sound pressure level (Leq) value was computed from

the values of A-weighted SPL.

3.8.2 Locations of Noise Level Monitoring

To establish the ambient noise in the study area, monitoring of ambient noise level was carried

out at Four (04) representative locations in the study area using a suitable portable sound level

meter. The sampling locations varied in nature from Silence zone to residential areas. The

details of the noise monitoring locations are given below.

48

Location

Day Time Night Time

Leq dB(A) Limit dB(A) Leq dB(A) Limit dB(A)

N1 at Chadranagar 41.7 55 38.8 45

N2 at saldure Village 41.7 55 36.4 45

N3 near Dapoli 45.2 55 39.3 45

N4 at Ladghar 48.4 55 40.3 45

Figure 11-10: Location of the Noise monitoring

Reports of the Noise monitoring is listed at Annexure 9.1.

3.8.3 Findings

Recorded Noise Levels in and around Chandranagar area is in the range of 36.4 to 48.4dB (A)

at all 4 monitoring stations. Maximum levels of noise have recorded in day hours which are

natural as our most of activities have done in day hours.

49

3.9 Flora and Fauna

As defined by the Convention on Biological Diversity (CBD), biological diversity is “the

variability among living organisms from all sources including, inter alia, terrestrial, marine and

other aquatic ecosystems and the ecological complexes of which they are part, diversity within

species, between species, and of ecosystems”

Biodiversity is the variety of living organisms considered at all levels of organisation, from

genetics through species, to higher taxonomic levels, and including the variety of habitats and

ecosystems, as well as the processes occurring therein Biodiversity is not the same as the

number of different kinds of species in a place : Biodiversity is in fact more complex than

species richness, although species richness is certainly one component of

biodiversity.Biodiversity assessment is means of collecting information on the flora and fauna

present in the area. It involves conducting survey or inventory of the species of the area.

Assessment could focus on one taxanomic group or multi taxanomic such as plants, birds,

mammals, reptiles, amphibians and selected invertebrate group such as ants, butterflies.

Biodiversity assessment can only report what species have been detected and recorded as

present in the area. It is done to protect the morphologic and genetic diversity of the area.

3.9.1 Baseline Status

In the site at village biodiversity has been reported in the study area. Few of flora and fauna

have been cited over the period of time. Various types of birds, reptiles, mammals etc. are seen

in the area.

3.9.2 Location of Biological Study

The study area of this project comprises of an area falling within a radius of 5 km from the

project location. The area is thinly vegetated and there is no thick vegetation on the plateau top.

On the slopes however, some mango, cashew nuts and coconut plantations etc. are noticed.

Paddy is mainly cultivated on the slopes of the plateau and at the sea-shore.

Natural fauna in the area are wild bores, field mice, rabbits, foxes which have been reported.

The reptiles and scorpions are common in the area. Domesticated cattles are oxes, buffaloes,

cows and goat in all the villages in the area.

3.9.3 Methodology of Biological Study

Flora:

List of all plants from the study area was prepared and their habits recorded. The associations

of plants in communities were noted. To study herbaceous and woody vegetation

systematically, standard methods of analyzing vegetation i.e. quadrate of different dimensions

and line transector of appropriate lengths were employed. Their numbers (quadrate) depend

upon the requirement in specific cases. Identification of plants was done by referring to

standard florist and consulting the experts when needed. The samples (specimen) were

individually stored in separate blotting papers and put in the polythene bags. Each specimen

carried the name of the species, time and date of collection and locations.

Fauna:

50

Animals were studied by following means 1) Actual sighting 2) Calls 3) Droppings, burrows

etc and 4) By inquiring local people.

Larger animals and common birds in and around the study area were visually observed and

recorded. List of Flora & Fauna occurring in study area is enclosed at Table 3-14, 3-15, 3-16,

3-17.

3.9.4 Flora and fauna in and around the project site

Fauna:

The project site at Chandranagar has small and medium size trees along with shrubs. List of

trees present at the site area listed in the following table.

Table 11-14: Existing trees at site

Table 11-15: Available plants in and around Chandranagar, Ratnagiri

Sr.

No.

Vernacular name Scientific name Family

Trees

1 Amba Mangifera indica Anacardiaceae

2 Ashok Polyalthia longifolia Annonaceae

3 Chinch Tamarindus indica Caesalpiniaceae

4 Chipi Sonneratia apetala Lythraceae

5 Chuva Oxytenathera monostigma Gramineae

6 Gulmohar Delonix regia Caesalpiniaceae

7 Jam Syzygium samarangense Myrtaceae

8 Kadambo Acacia auriculiformis Mimosaceae

9 Kadulimb Azadirachta indica Meliaceae

10 Kajri Strychnos nux-vomica Loganiaceae

11 Kaju Anacardium occidentale Anacardiaceae

12 Kandel Rhizophora mucronata Rhizophoraceae

13 Keli Musa paradisiacal Musaceae

14 Kumbhi Careya arborea Lecithidaceae

15 Lal champa Plumeria rubra Apocynaceae

51

16 Moha Madhuca longifolia var. latifolia Sapotaceae

Sr.

No.

Vernacular name Scientific name Family

17 Monkey puzzle Araucaria araucana Araucaraceae

18 Naral Cocos nucifera Palmae

19 Nilgiri Eucalyptus citriodora Myrtaceae

20 Nir phanas Artocarpus altilis Moraceae

21 Pandhara champa Plumeria alba Apocynaceae

22 Papai Carica papaya Caracaceae

23 Pat phanas Artocarpus heterophyllus Moraceae

24 Phanas Artocarpus hirsutus Moraceae

25 Pimpal Ficus religiosa Moraceae

26 Ramphal Annona reticulate Annonaceae

27 Ratamba Garcinia indica Clusiaceae

28 Ratshirish Samanea saman Fabaceae

29 Sagwan Tectona grandis Verbenaceae

30 Sawar Bombax ceiba Bombacaceae

31 Shevaga Moringa oleifera Morangaceae

32 Shivan Gmelina arborea Verbenaceae

33 Sonmohar Peltophorum pterocarpum Carsalpiniaceae

34 Supari Areca catechu Palmae

35 Surmad Caryota urens Palmae

36 Suru Casuarinas equisetifolia Casuarinaceae

38 Umbar Ficus glomerata Moraceae

39 Vad Ficus bengalensis Moraceae

Shrubs

52

40 Bherenda Jatropha gossypifolia Euphorbiaceae

41 Chandivad Macaranga peltata Euphorbiaceae

42 Chandni Ervatamia divaricata Apocynaceae

43 Croton Croton spp. Euphorbiaceae

44 Jaswand Hibiscus rosa-sinensis Malvaceae

45 Jaswand Hibiscus schizopetalus Malvaceae

46 Erand Ricinus communis Euphorbiaceae

47 Harkusa Acanthus ilicifolius Acanthaceae

48 Kanher Narium indicum Apocynaceae

49 Karvand Carissa congesta Apocynaceae

50 Kurat Ixora parviflora Rubiaceae

51 Mogli erand Jatropha curcas Euphorbiaceae

52 Nagphani Opuntia dillenii Cactaceae

53 Nirgudi Vitex nenundo Verbenaceae

54 Nirgunda Vitex trifolia Verbenaceae

55 Nivdung Euphorbia neriifolia Euphorbiaceae

56 Pendgul Ixora coccinia Rubiaceae

57 Pivla kanher Thevetia peruviana Apocynaceae

58 Rui Calotropis gigantean Asclepiadaceae

59 Sagargota Caesalpinia bonducella Caesalpiniaceae

60 Vilayati sedge Pedilanthus tithymaloidis Euphorbiaceae

Sr.

No.

Vernacular name Scientific name Family

61 Waras Heterophragma roxburghii Bignoniaceae

Herbs

62 Alu Colocasia esculenta Araceae

53

63 Borati Ziziphus oenoplia Rhamnaceae

64 Toran Ziziphus rugosa Rhamnaceae

Climbers

65 Bandgul Vanda tesseiiata Orchidaceae

66 Bogainvel Bagainvillea spectabilis Nyctaganaceae

67 Maryadavel Ipomoea pes-caprae Convolvulaceae

68 Ukshi Calycopteris floribunda Combretaceae

Fauna:

The faunal study was conducted simultaneously along with the flora, during the month of

February 2017. Some birds and animals were observed during the study. Based on secondary

data collected from the relevant government departments, the information gathered from the

villagers and personal observations; a list of wildlife fauna is prepared as shown in the Table

2. The list presents 57 species of wildlife including 19 mammals, 19 birds and 19 reptiles.

Among them, 5 mammals and 2 reptiles are included in the Schedule I of Wildlife (Protection)

Act 1972, considered as the endangered species. However, these animals were not encountered

during the survey period. Moreover, no any wildlife or national park is located in or near to the

study area.

Table 11-16: Availability of animals in and around Chandranagar, Ratnagiri

Sr. no. Vernacular name Common name Scientific name

Mammals

1 Bhekar Barking deer Muntiacus muntjak

2 Bibalya * Leopard Panther pardus

3 Javadi manjar Small Indian civet Viverricula indica

4 Kandechor Common palm civet Paradoxurus

hermaphrodites

5 Khadi khar# Fivestriped palm squirrel Funambulus palmarum

6 Makad Bonnet macaque Macaca radiate

7 Mungoos Common mongoose Herpestes edwardsi

8 Ran dukkar Indian wild boar Sus scrofa cristatus

9 Sasa Indian hare Lepus nigricollis

54

10 Sayal Indian porcupine Hystrix indica

11 Ud manjar Smoothcoated Indian otter Lutra perspicillata

12 Wanar Common langur Semnopithecus entellus

Birds

13 Bramhani ghar# Brahminy kite Haliastur Indus

14 Chimni # House sparrow Passer domesticus

15 Chirak # Indian robin Saxicoloides fulicata

16 Dayal # Magpie robin Copsychus saularis

17 Dhanesh# Malabar pied hornbill Anthracoceros coronatus

18 Dom kavla# Jungle crow Corvus macrorhynchos

19 Gai bagla# Cattle egret Bubulcus ibis

20 Ghar# Black kite Milvus migrans govinda

21 Kavla# House crow Corvus splendens

22 Kawada Spotted dove Streptopelia chinensis

23 Kokil Asian koel Eudynamys scolopacea

24 Kukutkumba# Greater coucal Centropus sinensis

25 Kurav Herring gull Larus argentatus

26 Lahan bagla# Little egret Egretta garzetta

27 Lalbudya bulbul# Redvented bulbul Pycnonotus cafer

28 Munia# Whitebacked munia Lonchura striata

29 Parva# Rock pigeon Columba livia

30 Salunki# Indian myna Acridotheres tristis

31 Titavi# Redwattled lapwing Vanellus indicus

Reptiles

32 Azgar * Indian rock python Python molurus molurus

33 Dhaman Indian ratsnake Ptyas mucosa

55

34 Dutondya John’s earth boa Eryx johni

35 Gargar Banded kukri snake Oligodon arnensis

36 Ghonas Russell’s viper Daboia russelii

37 Kandya Common wolf snake Lycodon aulicus

38 Manjrya Forsten’s cat snake Boiga forsteni

39 Manyar Common Indian krait Bungarus caeruleus

40 Nag Indian cobra Naja naja

41 Naneti Buffstriped keekback Amphiesma stolatum

42 Pan diwad Checkered keelback water

snake

Xenochrophis piscator

43 Pan ghonas Dog-faced water snake Cerberus rhynchops

44 Phoorse Saw-scaled viper Echis carinatus

45 Samudri kasav * Olive Ridley sea turtle Lepidochelys olivacea

46 Samudri sarp Hook-nosed sea snake Enhydrina schistosa

47 Sarda# Garden lizard Calotes versicolor

48 Sarpatoli Common vine snake Ahaetulla nasuta

49 Taskar Common Indian trinket snake Coelognathus helena

Helena

50 - File snake Acrochordus granulatus

*Included in the Schedule I of Wild Life (Protection) Act 1972 # The animals encountered during the survey period

Table 11-17: List of Butterfly Species Reported During the Study

Sr. No Common Name Common Name

Family Papilionidae Baronet Or Red Baron

1 Common Rose Common Castor

2 Crimson Rose Yellow Pansy

3 Tailed Jay Blue Pansy

56

4 Lime Lemon Pansy

5 Common Mormon Peacock Pansy

6 Blue Mormon Chocolate Pansy

7 Common Emigrant Danaid Eggfly

8 Mottled Emigrant Glassy Blue Tiger

9 Small Grass Yellow Blue Tiger

10 Common Grass Yellow Plain Tiger

11 Common Jezebel Striped Or Common Tiger

12 Psyche Common Crow

13 Small Orange Tip Family Lycaenidae

14 White Orange Tip Common Pierrot

15 Yellow Orange Tip Zebra Blue

16 Common Wanderer Indian Cupid

17 Family Nymphalidae Grass Jewel

18 Common Evening Brown Common Cerulean

19 Common Treebrown Red Pierrot

20 Common Bushbrown Common Silverline

21 Common Leopard Family Hesperidae

22 Common Sailor Common Banded Awl

57

3.10 Socio–Economic Information

3.10.1.1 Methodology

The socio-economic status of the area around project site situated at village chandranagar and

karde has been examined and analyzed considering the secondary information available with

various Govt. Departments, District Collector office, census data, PHC records, literatures, and

published information. The area has also been visited in order to understand the socio-

economic profile of the area. Village Gram Panchayat has also been visited to obtain the

information.

3.10.1.2 Demographic Structure

Village Chandranagar is an interior rural region which can be considered as backward area in

terms of the urban and industrial development point of view. People by large subsist on

agricultural activities and tourism dependent small scale lodging and boarding services to

tourists.

3.10.1.3 Human settlement and demography

As per census 2011 demographic characteristics of the study area are represented by a number

of criteria, namely population composition, sex ratio, family structure, and age distribution

pattern. Attempt has been made to compare the demographic features between the census data

whenever corresponding data are available. The area selected for the study constitutes 12

inhabited villages. As per census 2011 village Dumdeowith population of 164 is the least

populated while Burondi with population 3966 is the most populated within study area.

3.10.1.4 Socio Economic Characteristics of the Area

Community Profile: The population is distributed among 2565 households in the study area.

The 12 inhabited villages have a population of 10197 comprising of 4454males and 5743

females. As may be observed from the graph below the composition of the society as far as

males and their counterparts female are concerned indicates healthy distribution.

The number of females per 1000 males is 1289 when compared with the figures of the

Maharashtra State 922 and for the nation 933 the study area found to be greater than State as

well as National figures.

The scheduled caste population of the study area on percentage basis is 1.83 % of the total

population and scheduled tribe population is 2.33%. Comparison with the State level figures

indicates percentage of SC as well as ST population in study area is much less than that of State

as well as national level. The distribution as depicted in the graph;

Literacy: The overall literacy in the 12 villages of the study area was 73.0%The male literacy

in the study area was 81.76% as compared with State was 88.38% in this period, and the female

literacy was 66.89% while it was 67.03% for the State.

58

Figure 11-11: Literacy deatils

Vocation-wise distribution of the population based on 2011 census data of the study area is

graphically represented below.

Profession Percentage

1. Total Main Workers 29.90

* Cultivators 12.23

* Agricultural Labour 3.50

* House Hold industry 0.52

* Other Workers 13.65

2. Marginal Workers 10.2

3. Non-Workers 60.01

As may be seen from these data, the percentage of main workers in the study area was29.90%,

in 2011. The percentage of cultivators was 12.23% in area. On the other hand, percentage of

agricultural laborers was 3.50% The percentage of household industries was lowest 0.52% in

the study area. The marginal workers in the study area were 10.20%. The non-workers were

60.01% in study area; it shows that dependency of non-working population on the working

population in the area is much more that of corresponding working population. Since

agriculture is the main activity in the project area, a large number of poor and land less people

work as agricultural laborers and live on subsistence level. The marginal and small farmers

are likely to get non-farm employment, which provide low income. Village wise Demographic

data within study area and village wise vocational data within study area as per census 2011

are attached as Annexure-6 and Annexure-7 respectively.

59

Figure 11-12: Vocational study Pattern

Energy Consumption Pattern: The quantity of the fuel requirement for cooking depends on

various factors such as no. of persons in the family, food habits, income of the family & Cost

of fuel. The fuel that is being used by villagers is fire wood, cow dung cakes (Goari), Kerosene,

LPG gas. The supply of kerosene is controlled by government and supplied through fair price

shops approved by government. As a result most of the villages used more than one type of

cooking fuel.

Health Status: The morbidity pattern in the study area collected from Primary Health Centre

(PHC) of the area indicates Fever, diarrhoea, gastritis, malaria and skin diseases are common

diseases and few cases of T.B, Leprosy, Respiratory Tract Infection( RTI), have been reported

in this PHC. During discussions with Medical officer of PHC he pointed out that common

fever, diarrhoea and respiratory disorders are due to seasonal changes. Ring worm infestations

are mostly reported among the patients. The main cause of infestation is the contaminated use

of water and lack of cleanliness.

Economic Resource Base: Agriculture is the basic profession in the study area and plays an

important role in economy. Agriculture production has been lowered down due to insufficient

facility and poor resources of irrigation. The impact of poor resources and land is generally on

the food production and it leads to insufficient income generation, migration, indebtness, and

people work as a labour in nearby industry. To develop their economic strength villagers prefer

construction related work, fishery, dairy and other livestock related activity. The agricultural

land is not that much productive hence the yield is not satisfactory therefore local people have

developed and adopted other skills to earn money for their daily requirement. Youth of the

project area are literate and have the capacity to grasp any occupation, hence project area has

a potential to develop their economy.

3.11 Seismology

Project site is located in Ratnagiri district and is classified under the Zone IV of the Bureau of

Indian Standards (BIS) 2000 seismic zone map for India as seen in the picture below. Zone IV

is defined as having a major damage corresponding to intensity VII and higher on MM scale.

Structurally, proposed layout has been designed to meet seismic requirements of Zone IV.

60

Figure 11-13: Seismic Zone of India

61

12. Anticipated Impacts and its Mitigations

Environmental impact assessment (EIA) reveals the potential impact on the baseline

environmental parameters in and around the project site due to project activity. The EIA

involves identification, prediction and evaluation of potential impacts of the proposed activities

within the study area. These activities include all the actions that are required for successful

construction of project and its use. The impact identification and prediction process aims to:

Identify potential source of the pollution throughout the life of project

Characterize the potential impacts affecting a target or receptor

Assess the potential of changing likely-hood of impact through Environmental

Management Plan (EMP).

4.1 Sources of Pollution:

Pollutants in the solid, liquid and gases form would be generated during the construction and

operation phase of the project.

Table 12-1: Pollutants generated in construction phase

Construction phase

Sr

No.

Activity Pollutant Frequency

1

Site Preparation,

Excavations,

Construction

activities

Air emissions – SPM, PM10,

CO, NOX, SO2.

Temporary during construction phase

only bulk of the emissions are expected

from ground working and leveling

activities.

Earth/Solid waste Periodic.

Noise Temporary during initial construction

phase.

2

Labor Camps

Sewage Temporary-during the initial

construction phase

Solid waste Temporary-during the initial

construction phase

4.1 Impact on Land Environment

The project site is flat and sloppy terrain. The development of resort on the land has been

conceptualized considering the slope & contour of the land. No flattening of the slope of the

land for development of resort villas is proposed. Development of resort villas are proposed on

wooden frame fitted on RCC piles. Rainwater Harvesting tank and bio-digester tank would be

fitted under each villa units, for which, minimum alteration of slope of the land is proposed.

During the construction period, if the construction is debris is left on site, it will lead to

degradation of the land temporarily.

62

Mitigation Measures:

Altogether flattening of the hill slops shall be strictly avoided. Construction on steep

slope shall be avoided.

All the care shall be taken where adequate alteration of the slope is proposed for

development of resort units, in order to avoid the instability of the slope.

Construction material for the resort shall not procure from excavation of the hill and

sloppy terrain of the land area.

Tree plantation shall be carried out in the project area.

Proper drain will be provided to collect the rainwater during the monsoon to prevent the

soil erosion.

All the borrow pits would be properly levelled, so that no isolated pools and puddles

are left over once water dries up.

Waste management plans as per the MPCB norms will be strictly followed to prevent

spills and leakage into the soil.

All the construction materials will be disposed as per MPCB norms.

4.2 Impact on Soil and Geology

Contamination of soils is anticipated due to poor storage and management of solid and liquid

wastes. All these impacts might be permanent if not remediated. Furthermore, contamination

of soils may occur as a result of spillage of fuels, lubricant chemicals, sanitary wastewater, etc.,

as well as from leakage from inadequately protected solid waste storage facilities and sites.

Mitigation Measures :

Proper planning of works and work design (avoid some works in rainy seasons), to avoid

or minimize erosion.

Planting of vegetation on barren and/or sloping surfaces.

Channel runoff from hardened surfaces to well designed and properly maintained drains.

Special care should be taken not to cause spreading of erosion material over the non-

project areas.

Collection of sewage/solid waste/construction waste

4.3 Potential Impact on Water Quality

The resort at the Chandranagar village is proposed at much higher elevation than the water

table. Thus, there will not be any contamination of the ground water. The impacts envisaged

on the surface and ground water quality of the area, during construction phase is the accidental

spillage of oil or fuel from construction machinery that may run off into near-by surface and

groundwater water bodies and/or uncontrolled liquid effluents from construction site or the

labour composites.

63

Further, the construction of the resort is wooden, except for concrete construction of piles,

Rainwater harvesting and Biodigester tank. Hence, there will be minimum requirement of

water during construction phase of the project, for which existing bore wells would be used.

Mitigation Measures:

Dumping of the construction debris, loose soil and other construction in sea water shall

be prohibited.

No existing resources/water sources (surface/groundwater), which are currently being

used by the villagers for the purpose of obtaining drinking water and/or water for

irrigation or other purposes.

Every effort shall be made to treat and reuse the wastewater from the washing and other

construction activity shall be treated.

During operation phase of the project adequate capacity of the sewage treatment facility

shall be installed. Exploration for nature friendly design& technology of the STP shall be

done considering the unique flat and sloppy nature of the project site. Since, the resort is

conceptualized as eco-friendly resort, it will be appropriate to explore the nature friendly

STP such as Phytorid based STP, rather than conventional STP.

Drinking water requirements during the construction phase shall be met through tankers

to the construction sites.

Local people will be employed; there will be no labour camps on the site. Drinking water

requirements during the construction phase shall be met through tankers to the

construction sites.

4.4 Impact on Noise Environment

4.4.1 During construction phase

During construction phase, there will be likely rise in ambient noise level due to sound of

machinery, equipments and plying of vehicles for transportation of material. It will affect the

personnel operating the machines. However this will be short term impacts and will be

restricted to construction phase only.

4.4.2 During operation phase

Vehicular traffic and use of DG sets in case of power failure will be main cause behind the

impact on noise during the operation phase of the project. Proper traffic management systems

will help in minimizing the noise impacts and DG sets with acoustic enclosures will be

procured for operational phase. Also plantation of trees in the project area and along the roads

will help to act as a buffer zone attenuating the noise.

Mitigation measures:

Noise should be best abated at source by choosing machinery and equipment suitably, by

proper mounting of equipment & ventilation systems and by providing noise insulating

enclosures or padding where practicable. The equipments to be procured should be new and as

such the noise emission will be optimal for their design/operation. Proper

maintenance/working should be done which keeps the noise levels within limits. There shall

be sound parking plan for the tourists vehicles, during operation phase of the project.

64

4.5 Impact on Ecology

4.5.1 Construction Phase

Disturbances to physical environment may occur either directly by occupancy of land or

indirectly by changes in water levels and flow, soil structure, land form etc. This can have

adverse impacts such as loss of habitats for flora and fauna, disturbing feeding, breeding,

nesting and migration requirements. Damages to the habitats can be caused by various

construction activities. Exposure to pollutants via mechanisms such as ingestion, inhalation,

skin contact, and sorption, direct uptake through roots foliar deposition etc. may have lethal

and sub lethal effects on the health of flora and fauna. However, in the present case there is no

generation/release of any gases that could lead to such impacts.

The project site has around 500 small and medium trees and shrubs. Clearing the around 250

trees are proposed. However, it is advised that the villas should be adjusted in such a way that

minimum trees should be disturbed. Wherever possible, the grown up trees shall be

transplanted and only the trees that cannot be saved by any means may be [proposed for cutting

under the Tree Act.

5 times the nos. of trees to be cleared, shall be planted in the project area so that loss of

vegetation in the project site could be compensated

4.5.2 Functional Phase

The impact on ecological environment during the operational phase of the project will be

positive as green belts and plantation will be developed along the roads and within the resort

area. These trees will act as nesting and breeding sites for the birds in the area. This will help

in maintaining the ecological balance of the environment.

Total nos. of trees proposed to be planted. These are total nos. of trees proposed in total land

under resort 1, 2 and 3.

Table 12-2: Total nos. of trees proposed to be planted

Sr

No.

Local name of

tree

Botanical name Nos. of tree

1 Satwin Aistorvia Scholaris 10

2 Anjani Memacylon umbellatum 35

3 Hedu Haldina Cordufolia 10

4 Kunku Mellitus phillipensis 10

5 Surangi Mammea Suriga 10

6 Nagchafa Mesus ferria 10

7 Hoom Milluse tomentose 10

8 Bakul Mimuspops elengi 35

65

9 Beheda Terminate bellirice 35

10 Dhoop Vateria indica 10

11 Jambhool Syzygium Cuminil 35

12 Trifala Zanthoxylum rhetsa 10

13 Moha Medhuce Longifolia 35

14 Kusum Scheichera oleosa 35

15 Khuri Ixors brachiats 10

Total 300

In 1st phase, 300 nos. of trees are proposed to be planted and another 300 trees will be added in

second phase.

Road plantation along the Main road avenue:

Sr No. Local name of tree Botanical name Nos. of tree

1 Aamba Mangifera indica 350

2 Naral Casoos Nucifera 39

3 Supari Areca calechu 121

Total 510

Further, total 214 trees namely Kadamb, Bakul, Kusum, Muchukund, Satwin are proposed to

be planted along the internal road avenue. Hence, total plantation proposed is 1324

66

13. Environmental Monitoring Program

Environment Monitoring is as important as that of control of pollution since the efficacy of

control measures can only be determined by monitoring. An environmental monitoring

programme is required to check whether the levels of critical pollutants are within the

environmentally acceptable limits. The monitoring of various environmental parameters is

necessary which is a part and parcel of the environment protection measures. This will help to

obtain an early warning of unacceptable environmental conditions so that control measures can

be taken immediately. It also helps to determine in a timely fashion, changes in the local

environmental quality.

5.1 Monitoring Plan during Construction Phase

Environmental monitoring during construction phase shall comprise Compliance with EMP

and governmental regulations , Necessary govt clearances and licenses etc. This can be ensured

through use of checklists for:

Site establishment and Site closure

Environmental Management Plan implementation monitoring during construction phase

Monitoring checklists are presented below.

Table 13-1: Project Startup checklist

Sr No. Environment Aspect Yes/ No Remarks

1 Personnel on site are environmental aware of

the various issues of interest

Y

2 Telephone numbers of emergency services are

available on site.

Y

3

Solid waste management system has been

established at both construction site and labor

camp.

N To be established

during the

construction Phase.

4

Wastewater management system has been

established at both construction site and labor

camp.

N To be established

during the

construction Phase.

5 Necessary fire-fighting

equipment is available and in working

condition

N To be established

during the

construction Phase. 6 Construction camp is neat and tidy and the

laborers facilities are of an acceptable standard.

N Not initiated yet

7 Waste collection and removal system is being

maintained. Sufficient fire-fighting equipment

is available at construction site and is in good

working order.

N Not established yet

67

8 All construction vehicles are in good working

order and have valid PUC certificates.

N To be ensured at later

stage

9 Dust control measures (wherever necessary) are

in place and are effectively controlling dust.

N To be implemented in

Construction Phase

10 Noise-control measures (wherever necessary)

are in place and are working effectively.

N Not required.

11 Erosion control measures (wherever necessary)

are in place and are effective in controlling

erosion.

N To be implemented in

Construction Phase

Table 13-2

5.2 Environment monitoring plan during construction and operation phase

5.2.1 During Construction phase

Sr No. Attribute Parameters Frequency of Monitoring

1 Ambient Air Quality PM10, PM2.5, SO2, NOX

and CO

Ambient Air Quality for 24hrs, once a

month

2 Water Quality Physical, Chemical and

Bacteriological

parameters.

Primary data – Groundwater samples

from One

bore well, One Surface water sample

once a month

4 Noise Levels Noise levels in dB(A) Continuous 24-hourly monitoring-

once a month during the use of

machineries.

68

5.2.2 During Operational phase:

Table 13-3: Environment Monitoring plan during Operational Phase

Provision of rest shelters for construction workers with amenities like drinking water, fans,

toilets etc.;

Provision of personnel protection devices for the workers;

Rotation of workers exposed to high noise areas if any;

First-aid facilities.

Occupational Health Survey of the employees will be carried out at regular intervals.

Sr

No.

Attribute Parameters Frequency of Monitoring

1 Ambient Air

Quality PM10, PM2.5, SO2, NOx

and CO

Ambient Air Quality for 24hrs, once in

a 6 months during operation phase

3 Sewage Water

Quality

Physical, Chemical and

Bacteriological parameters.

Inlet and Outlet of STP once in six

months during the operational phase.

4 Drinking Water

Quality

Physical, Chemical and

Bacteriological parameters.

Primary data –

Groundwater samples

from One bore well and One Drinking

water sample

This shall be done once in a six months

in operational phase 5 Noise Levels Noise levels in dB(A) Continuous 24-hourly monitoring- once

in six months during operational phase.

6 Soil characteristics Parameters related to

agricultural & afforestation

potential.

Once in six months during operational

phase

69

5.3 Environment Cost

Table 13-4: Estimated environment cost

Sr. No. Environment provision Cost (Rs.)

1 Phytorid based Sewage

treatment

5 lac

2 Organic Waste Convertor 4 lac

3 Rainwater harvesting 50 lac

4 Tree Plantation 1 lac

5 Environment Monitoring 5 lac

Total 65 lac

70

14. Project Benefit

We envisage some of the benefit of the project:

Development of Eco-friendly resort will attract domestic and foreign tourists, which in turn

will generate the employment for the local people residing in the area.

The project will be boost to tourism sector of the State of Maharashtra.

With direct employment and of indirect employment opportunities it is expected that the

monthly expenditure for daily activities like purchase of milk, vegetables, grocery,

consumables and other domestic requirement will be met from the local area. Thus there will

be rotation of funds in the local area on monthly basis which will also help in improving the

economy of local area.

With improvement in local economy and with increase in employment opportunities there

will be overall improvement in standard of living of the local people.

As a part of local area development and creating employment potential new employment

opportunities will be created through imparting vocational training to unemployed youth and

eligible people.

There will be significant change in the socio-economic scenario of the area. It will upgrade

the local economy of the area and purchasing power of local people

Increased revenue to the State Government.

71

15. Environment Management Plan

In order to avoid and minimize adverse impacts of the development and maximize the positive,

the EMP should be incorporated into overall planning and implementation phase. The EMP

integrates the baseline conditions, impacts likely to occur, and the supportive and assimilative

capacity of the system. The Environmental Management Plan (EMP) for the proposed

Chandranagar resort are classified into following categories:

Land environment

Water environment

Air Environment

Noise Environment

General precautionary measures shall be adopted at all time, which includes:

Persons working near the noise generation equipments shall use Personal Protective

Equipment such as earplugs muffs

All workers should be made aware of adverse effect high noise levels through training

program; this will ensure proper implementation of mitigation measures

All sanitary facilities shall be properly maintained all the wastes generated shall be

treated and disposed as per norms.

7.1 Land Environment

The project envisages no acquisition of land. Following measures are recommended to minimize

adverse impacts on Environment:

It must be ensured that no hill cutting is proposed outright. Development of resort

structures should be in syn with the hill slopes, for that bare minimum flattening of the

hill surface is required.

The topography of the land should be maintained.

Tree cutting is involved in the project. Hence, Tree plantation shall be done in substantial

number

Eco-friendly material should be used for the steps to resort.

7.2 Management of Solid Waste

Project proponent will explore opportunity to recycle the waste generated at the project site, in this

context project will identify authorized vendors and send used batteries, used oil, and used oil

filters for recycling. Adequate facilities for collection, conveyance and disposal of solid waste will

be developed.

72

An inventory will identify the consumption of products/material, ensuring waste’s traceability, and

identifying potential wastage and overconsumption. An inventory of all waste generated and

disposed of will be retained (type and volume) and MSPL will develop goals for reducing the

quantities of waste generated, based on periodic review inventory. The list of identified

homogeneous zones/sectors is given in Table 10-3. These zones acts individually and hence the

waste should be collected to a common collection area and then it should be segregated as

mentioned.

The proposed Solid Waste Management Plan for port complex is based on the concept of 3-R i.e.

Reduce, Reuse and Recycle. This plan shall be developed to manage solid wastes and to avoid any

discharges into the soil/land or water. It shall establish procedures for the storage, collection and

disposal of waste, hazardous and non- hazardous solid waste. The overall objective of solid waste

management plan is to minimize impact of waste generated through the following:

Minimize the amount of waste that is generated;

Maximize the amount of waste that is recovered for recycling – including segregation of

recyclable wastes at source;

Minimize the amount of waste that is deposited at landfill;

Ensure any hazardous wastes (e.g. used oils, lead-acid batteries) are securely stored and

transferred to appropriate facilities;

Ensure all wastes are properly contained, labelled and disposed of in accordance with

National/local regulations; and

Ensure waste is disposed of in accordance with the waste management hierarchy.

7.2.1 During Construction Phase

Total solid waste generated during construction phase includes pre-construction debris, demolition

debris and excavated materials. The provision will be made for segregation and sorting of waste

at the source so that negative impact will be minimized.

There are no labour camps on the site. The only solid waste expected to be generated during the

construction phase is the packaging waste, wooden and paper cartoons etc.

Various aspects of solid waste management include:

Reuse/Recycling

Collection and Transportation

Disposal

7.2.2 During Operation Phase

Total solid generated during operation phase will be purely domestic and it can be classified as

Bio-degradable and Non-Biodegradable.

73

Generally, Bio-degradable waste includes kitchen leftover. Recyclables waste include paper,

bottles, glass, safety pins etc. Other waste includes, PET bottles, thermocol, plastic coated visiting

cards, sachets, etc.

Table 15-1: Solid Waste Generation during Operation Phase

Units Occupant

load

Expected generation Quantity

generated

Quantity

generated

Bio-

degradable

Non-

Biodegradable

Bio-

Degradable

Non-

Biodegradable

Total

cottages

unit- 10

40 0.3 0.2 12 8

Resort

staff

15 0.3 0.2 4.2 2.8

Floating

population

20 0.3 0.2 6 4

Total 75 0.3 0.2 22.2 14.8

7.2.3 Storage of Waste

At selective location, the solid waste collection container shall be kept. It shall be the responsibility

of the household to empty their waste container in the collection bins. Bins for storage of bio-

degradable wastes shall be painted green, those for storage of recyclable wastes shall be painted

blue and those for storage of street sweepings shall be painted black. Facilities shall be made to

cover bins or containers of appropriate design including flaps and shall have ‘easy to operate’

design for handling, transfer and transportation of waste. Representation of the collection bins is

shown below:

Figure 15-1: Bin system

74

7.2.3.1 Disposal of waste

Waste Disposal details are tabulated as below:

Table 15-2: Waste disposal

The STP sludge shall be used as manure for gardening to possible extent.

Waste oil from DG set shall be given to vendors approved by CPCB/MPCB for the disposal.

7.2.3.2 Organic Waste Convertor

OWC is a fully automatic Bio-Mechanical Composter. It converts organic waste added to the

machine into nitrogen rich compost by reducing its volume by almost 70-80% of the original.

OWC such as Kwik Composter 800 (KC 800) is a continuous Composting System with adequate

capacity. The process of composting with KWIK COMPOSTER is very simple:

Deposit organic waste at inlet of the machine along with 10% carbonaceous material and

0.1 % composting culture.

Mixing, Curing and Composting automatically done no double shredder and external curing

system required. Thorough segregation not required.

Compost keeps collecting in a bag at the rear of the machine.

Remove the compost bag when it is full and attach another bag.

Ambience: Very Pleasant. Food Waste deposited once appears as sweet smelling compost at

rear end.

7.2.3.3 Location of proposed OWC

Adjacent to the project site under consideration, there are 2 more resorts are proposed, one at

village Chandranagar and second at village karde. Total 3 project sites are not single continuous

land; however, these project sites are close to each other.12.5 kg/day biodegradable waste.

Resort 2 at village chandranagar and Resort 3 at village Karde will generate around 22.2 kg/day

and 45.6 kg/day biodegradable waste. Therefore, total biodegradable waste would be around

180.3 kg/day.

Sr No. Waste category Collection method Disposal

1 Organic Waste Manual collection and

storage

Treatment in Mechanical

composting unit inside the

premises. The compost

generated will be used for

gardening. 2 Inorganic Waste Manual Collection and

Storage

Disposed to authorized waste

collection system and

recyclable waste to be taken

away by private vendor

75

It is proposed to treat total biodegradable waste of all 3 resorts at place of resort 2 at village

chandranagar. Waste collection bins will be at each villa of the 3 resorts, however, there would

one (1) single Organic waste convertor of adequate capacity to treat around 200 kg/day at Resort

2.

Figure 15-2: OWC location at the project site

7.3 Air Environment

For mobile source emissions:

Idling of delivery trucks or other equipment should not be permitted during periods when

they are being unloaded or are not in active use.

Dust covers should be provided on trucks that would be used for transportation of materials

prone to fugitive dust emissions.

For stationary source emissions:

Areas prone to fugitive dust emissions due to activities such as excavation, and routes of

delivery vehicles across patches of exposed earth, should be frequently watered to suppress

re-entrained dust.

76

Apart from these, the equipment/machines and vehicles should be always kept in good state

of repair to minimize emissions. Low emission vehicles / equipment should be used

wherever feasible.

7.4 Noise Pollution

During construction phase, the use of construction equipment is the major source of noise. Efforts

will be required to maintain properly functioning equipment and comply with occupational safety

and health standards. The recommended measures are as follows:

Construction equipments shall be properly maintained. Contract should specify use of

equipment generating noise of not greater than 90 dB (A).

Construction Contract Specifications should stipulate levels of maximum noise generation in

various zones (residential, commercial and sensitive) based on CPCB Noise Standards.

During the operational phase noise generation is envisaged due to vehicular movements and DG

sets. Following precautions shall be adopted to maintain the noise levels within the prescribed

limits:

A noise barrier in the form of trees/ green belt shall be developed to attenuate the noise

level.

Proper parking plan for vehicles shall be in place.

Noise from the DG set shall be controlled by providing an acoustic enclosure

7.5 Water Environment

The water supply for the project will be from following source:

Gram Panchayat ( Maharashra Jeevan Pradhikaran Water Scheme)

Existing Bore wells at project site

Rainwater harvesting tanks of capacity 10,000 litre at each villa unit

The Grampanchyat has give the No Objection Certificate for water supply for domestic purpose

as per availability.

During operation phase, the sewage generated from the resort shall be treated in Sewage

treatment plan and treated water shall be used for flushing and gardening.

Drinking water facilities and waste disposal facilities if any will be located away from

each other.

Rainwater Harvesting System

77

The water scarcity scenario in and around the project site can be solved by rainwater harvesting

(RWH). Therefore, rainwater harvesting units are suggested to construct at strategic locations.

There is provision of Rainwater harvesting storage tanks of capacity 10,000 Litre for each villas.

Table 15-3: Water Budget for the Resort 2

Component Total

population

Water Requirement % flow

to sewer

Total

sewer

Flushing Domestic Total

Cottages- 10 Nos.

( 4 persons/ Cottage)

40 3240 2160 5400 80 4320

Approx. Resort staff 15 1215 810 2025 80 1620

Floating population 20 1620 1080 2700 80 2160

Total 75 6075 4050 10,125 8100

in KLD 11 8.5

Total water requirement: 11 KLD

Expected sewage: 8.5 KLD

STP capacity: 9 KLD

78

Figure 15-3: Water Balance (dry season)

79

Figure 15-4: Water Balance (wet season)

The treated waste water will be used for green belt development and flushing within the premises.

7.5.1 Proposed location of STP

7.5.1.1 Phytorid technology

This is natural water purification process developed by the NEERI, which does not use electricity

/ power, chemical dosing, heavy maintenance to purify water. It uses natural resources like plants,

stones, pebbles etc. for purification of water. The system is based on the specific plants, such as

Elephant grass (Pennisetumpurpurem), Cattails (Typha sp.), Reeds (Phragmitessp.), Cannas pp.

and Yellow flag iris (Iris pseudocorus), normally found in natural wetlands with filtration and

treatment capability. Some ornamental as well as flowering plants species such as Golden

80

Dhuranda, Bamboo, Nerium, Colosia, etc. can also be used for treatment as well as landscaping

purposes.

The system consists of the following three zones: (i) inlet zone comprising of crushed bricks and

different sizes of stones, (ii) treatment zone consisting of the same media as in inlet zone with plant

species, and (iii) outlet zone. The phytorid technology treatment is a subsurface flow type in which

wastewater is applied to cell / system filled with porous media such as crushed bricks, gravel and

stones. The hydraulics is maintained in such a manner that wastewater does not rise to the surface

retaining a free board at the top of the filled media. The reduction in the treated effluent for the

total suspended solids (TSS) varied from 70% to 80, BOD from 78% to 84%, nitrogen from 70%

to 75%, phosphorus from 52% to 64% and fecal coliform from 90 % to 97%. The total area

required for the system is approximately 35 sq. m. for 20 m3/day.

Figure 15-5: Phytorid technology

Salient features of the technology:

Works on gravity, no moving part so maintenance is low

No electric power requirement, cost effective

Adds to aesthetics

Treatment efficiencies for the removal of faecal coliforms, BOD, COD, nutrients are up to

95%, which is greater than the traditional chemical methods.

Since it utilizes natural vegetation and rhizosphere microorganisms, it is eco-friendly

method of treating sewage.

An important factor to be considered is the aesthetic improvement that is provided by this

methodology.

No mosquitoes and odour nuisance

The treated water can be used for enhancement of environmental architecture such as

roadside fountains.

The quality of treated water is comparable to irrigation standards

81

7.6 Green Belt Development

Green belt development in the project area is proposed, this will go a long way to protect

environment and mitigate pollution levels in the area.

Depending upon the topo-climatological conditions and regional ecological status, selection of the

appropriate plant species has been made. The various criteria adopted for selecting the species for

greenbelt development are:

Plants should be fast growing;

Preferably perennial and evergreen;

Indigenous;

Should maintain the ecological and hydrological balance of the region. The general

considerations involved while developing the greenbelt are:

Trees should also be planted along the roadside.

Generally fast growing trees should be planted.

82

Declaration by Experts

Sr.

No. Functional Areas Name of the experts

Involvement (Period

& Task**)

1 Land Use Mr. Hrushikesh Kolatkar April 2016 to till date

2 Air

AP Mr. Ashwin Badge

April 2016 to till date

AQ Mr. Rishabh Sharma April 2016 to till date

3 Noise Mr. Rishabh Sharma April 2016 to till date

4 Water Mr Sanjay Shevkar April 2016 to till date

5 Geology Mr. Shrivallabh Kothe April 2016 to till date

6 Hydrogeology Mr. Shrivallabh Kothe April 2016 to till date

7 Soil Conservation Ms. Shraddha Gathe April 2016 to till date

8 Ecology & Biodiversity Mr Vivek Kulkarni April 2016 to till date

9 Risk & Hazard Assessment Mr. S.L. Bonde April 2016 to till date

10 Solid & Hazardous Waste Ms. Amrita Kulabhi April 2016 to till date

11 Socioeconomic Mr. Hrushikesh Kolatkar April 2016 to till date

83

Declaration by Experts

Contributing to the EIA of Coastal Regulation Zone for proposed construction of Resort on plot

bearing gut No. 31/1, 30/2/3(C+E), Mauje Chandranagar, Dapoli, Ratnagiri

I, hereby, certify that I was a part of the EIA team in the following capacity that developed the

above EIA.

EIA coordinator : Mr Vivek Kulkarni

Functional Area Experts:

-

84

Environmental Impact Assessment Report October 2017

**Involvement and task of the Functional Area Experts

S.

No.

Functional

Areas Name of the experts Task

1 Land Use Mr. Hrushikesh Kolatkar Secondary data collection from Organization (Govt &

Private).

Preparation of topographical maps

Analysis of Data related to Land use pattern and

Preparation of Land use map using GIS tools and its

classifications.

Verification of present status by visiting the site and

surrounding area.

2 Air AP Mr. Ashwin

Badge

Air pollution monitoring.

Meteorological parameter measurement.

Identification & assessment of quantum of emission

and its Mitigation measures.

AQ Mr. Rishabh Sharma Ambient Air Quality monitoring network

designing.

Processing of micrometeorological data for using in model.

Air quality modelling through Aermod for proposed

prediction of impact due to proposed installation of

D.G. Sets.

3 Noise Mr. Rishabh Sharma Monitoring of noise levels of the project site and

surrounding area.

Assessment of noise level and vibration potential due to

proposed project and its mitigation measures.

-

85

4 Water Dr. Prajakta

Kulkarni

Water Quality monitoring network designing Sampling

of water samples (surface and ground water).

Monitoring of water quality.

Water Balance, budgeting and water

conservation.

Identification & assessment of quantum of water pollution and its Mitigation measures.

STP - ETP Suggestion.

5 Geology Mr. Shrivallabh Kothe Geology & Geomorphologic analysis and preparation of

maps

86

8.5 Functional Area Code Details

Sr. No. Functional Area

Code

Complete Name of Functional Area

1 LU Land Use

2 AP Air Pollution Prevention, Monitoring & Control

3 AQ Meteorology, Air Quality Modeling & Prediction

4 WP Water Pollution Prevention, Control & Prediction of Impacts

5 EB Ecology & Biodiversity

6 NV Noise &Vibration

7 SE Socio- Economic Aspects

8 HG Hydrology, Ground Water & Water Conservation

9 GEO Geology

10 SC Soil Conservation

11 RH Risk & Hazards Management

12 SHW

(HW/SW/MSW)

Solid & Hazardous Waste Management (including Municipal

solid wastes)

87

Declaration by the Head of the Accredited Consultant Organization:

I, Hrushikesh Kolatkar, hereby confirm that the above mentioned experts prepared the EIA report

for proposed construction of Resort on plot bearing gut No. 31/1, 30/2/3(C+E), Mauje

Chandranagar, Dapoli, Ratnagiri.

I also confirm that I shall be fully accountable for any misleading information mentioned in this

statement.

Signature

Name: Hrushikesh Kolatkar

Designation: Managing Director

Name of EIA Consultant Organization: Building Environment India Pvt Ltd.

NABET Certificate Number & Issue Date: Rev. 57 September 05, 2017_Rev 01

88

9. Annexures

9.1 Result of Ambient Air Quality Monitoring

A-1

Project location- Chandranagar

Lat - 17.752172° and Long- 73.134115°

Week Date PM10 PM2.5 SO2 NOx

μg/m3 μg/m3 μg/m3 μg/m3

W-1 15/11//2016 31.9 17.2 8.0 8.4

16/01/2016 37.2 18.5 7.8 8.6

W-2 22/11/2016 36.3 17.6 6.4 8.2

23/03/2016 31.0 19.7 6.7 7.9

W-3 28/11/2016 37.7 18.6 6.4 7.4

29/11/2016 36.7 17.8 7.2 7.6

W-4 5/12/2016 30.1 17.2 7.0 8.1

6/12/2016 32.8 16.6 7.4 8.3

W-5 12/12/2016 33.1 18.0 6.3 8.2

13/12/2016 33.2 16.9 7.3 8.9

W-6 19/12/2016 32.8 17.0 8.2 9.1

20/12/2016 34.8 17.3 8.4 9.3

W-7 26/12/2016 36.4 18.7 7.3 8.1

27/12/2016 29.9 17.7 6.9 8.09

W-8 2/01/2017 31.4 16.4 7.4 7.09

3/01/2017 32.8 16.3 8.1 9.6

89

W-9 9/01/2017 34.0 17.9 8.0 9.4

10/01/2017 36.1 19.7 7.9 10.1

W-10 16/01/2017 39.1 19.9 8.7 9.09

17/01/2017 38.7 17.1 8.4 10.1

W-11 23/01/2017 30.1 16.02 7.3 9.4

24/01/2016 31.6 17.7 7.6 9.8

W-12 30/01/2017 33.2 16.07 8.4 10.1

31/01/2017 36.6 16.9 9.3 10.4

W-13 6/02/2017 37.2 17.0 8.7 10.5

7/02/2017 36.1 16.7 7.8 9.4

Minimum 29.9 16.2 6.3 7.4

Maximum 39.1 19.9 9.3 10.5

Average 34.4 18.5 7.8 8.95

A-2

Village- Ladghar

Lat- 17.721153° and Long- 73.143345°

Week Date PM10 PM2.5 SO2 NOx

μg/m3 μg/m3 μg/m3 μg/m3

W-1 15/11//2016 40.1 20.4 9.4 13.1

16/01/2016 41.1 19.5 8.9 10.7

W-2 22/11/2016 39.6 17.9 7.1 12.6

23/03/2016 38.1 19.1 8.6 11.2

W-3 28/11/2016 37.2 18.2 9.2 11.4

90

29/11/2016 40.2 17.7 8.9 12.6

W-4 5/12/2016 39.2 16.9 8.3 10.9

6/12/2016 38.4 19.7 8.7 10.4

W-5 12/12/2016 39.6 18.8 8.9 11.3

13/12/2016 36.7 16.7 10.6 11.4

W-6 19/12/2016 37.8 17.7 8.9 9.09

20/12/2016 39.3 17.8 9.6 10.4

W-7 26/12/2016 38.5 18.4 8.7 10.1

27/12/2016 37.0 17.3 9.09 10.5

W-8 2/01/2017 39.3 18.2 10.6 11.7

3/01/2017 38.0 19.3 9.8 11.3

W-9 9/01/2017 39.2 17.8 10.4 11.8

10/01/2017 40.7 19.3 8.9 11.3

W-10 16/01/2017 41.6 19.2 8.8 10.7

17/01/2017 38.2 18.6 9.8 11.4

W-11 23/01/2017 37.0 18.9 8.7 10.8

24/01/2016 38.3 19.8 10.1 13.5

W-12 30/01/2017 39.8 18.7 8.7 12.0

31/01/2017 39.5 18.2 8.9 11.2

W-13 6/02/2017 39.0 16.6 9.6 11.2

7/02/2017 37.9 17.2 9.0 10.1

Minimum 37.0 16.7 7.1 10.7

Maximum 41.6 20.4 10.6 13.5

Average 39.03 18.55 8.85 12.1

91

A-3

Dapoli

Lat- 17.763357° and Long- 73.182565°

Week Date PM10 PM2.5 SO2 NOx

μg/m3 μg/m3 μg/m3 μg/m3

W-1 03/03/2016 45.7 19.0 16.2 18.9

04/03/2016 47.0 18.8 13.0 15.6

W-2 10/03/2016 46.4 20.4 15.9 18.0

11/03/2016 44.0 19.1 13.3 19.0

W-3 17/03/2016 42.1 18.7 11.8 13.0

18/03/2016 40.9 19.3 16.3 19.2

W-4 24/03/2016 39.9 20.2 10.7 11.6

25/03/2016 39.6 19.3 10.1 12.3

W-5 31/03/2016 41.9 18.4 9.09 11.4

01/04/2016 40.7 20.5 12.09 14.6

W-6 07/04/2016 43.6 21.7 14.8 16.8

08/04/2016 40.5 21.8 15.6 18.3

W-7 14/04/2016 39.9 19.3 15.9 18.9

15/04/2016 38.9 18.0 17.3 19.7

W-8 21/04/2016 36.7 21.1 16.09 19.4

22/04/2016 37.0 22.6 14.9 16.9

W-9 28/04/2016 42.5 19.8 15.09 17.8

29/04/2016 41.5 20.0 13.5 18.5

92

A-5

Lat- 17.670519° and Long- 73.149017°

Week Date

PM10 PM2.5 SO2 NOx

μg/m3 μg/m3 μg/m3 μg/m3

W-1

03/03/2016 30.9 16.8 8.0 9.9

04/03/2016 32.3 19.1 8.1 10.0

W-2

10/03/2016 31.7 20.7 6.9 7.8

11/03/2016 30.3 17.0 6.7 7.4

W-3

17/03/2016 31.2 19.5 6.8 8.3

18/03/2016 32.1 21.7 8.0. 8.5

W-4

24/03/2016 31.4 20.7 6.5 7.7

25/03/2016 35.3 20.5 7.8 8.8

W-5 31/03/2016 36.0 23.9 8.0 9.3

W-10 05/05/2016 43.2 21.7 11.9 12.4

06/05/2016 40.0 21.4 12.9 14.7

W-11 12/05/2016 38.9 20.9 13.3 17.7

13/05/2016 40.7 20.5 11.9 18.1

W-12 19/05/2016 41.0 21.4 12..9 16.2

20/05/2016 39.9 21.2 11.5 14.3

W-13 26/05/2016 40.0 21.8 12.5 17.1

27/05/2016 39.3 19.2 14..9 16.3

Minimum 36.7 18.4 9.9 11.6

Maximum 47.0 22.8 17.3 19.4

Average 41.85 18.55 8.85 15.6

93

01/04/2016 38.2 22.8 8.7 8.5

W-6

07/04/2016 37.6 20.1 7.0 8.0

08/04/2016 36.4 24.9 8.3 10.4

W-7

14/04/2016 37.2 20.4 6.2 7.7

15/04/2016 38.7 22.9 6.3 8.4

W-8

21/04/2016 39.0 23.6 7.4 8.5

22/04/2016 36.4 22.5 7.8 9.9

W-9

28/04/2016 37.2 24.9 8.3 10.3

29/04/2016 37.4 23.8 6.4 9.3

W-10

05/05/2016 38.3 25.3 8.0 9.4

06/05/2016 37.7 23.5 7.9 9.8

W-11

12/05/2016 39.6 22.9 7.3 10.4

13/05/2016 35.7 20.7 6.4 9.5

W-12

19/05/2016 37.3 22.2 8.2 9.5

20/05/2016 38.7 19.2 6.3 9.6

W-13

26/05/2016 33.3 20.3 6.8 9.7

27/05/2016 36.1 18.9 6.2 7.8

Minimum 31.2 16.8 6.2 7.4

Maximum 39.6 25.3 8.7 10.4

Average 35.4 21.05 7.45 8.9

A-4

Lat- 17.804845° and Long- 73.113272°

Near Harne Village

Week Date PM10 PM2.5 SO2 NOx

μg/m3 μg/m3 μg/m3 μg/m3

94

W-1 05/03/2016 45.5 21.8 9.3 11.1

06/03/2016 43.8 19.1 8.5 9.8

W-2 12/03/2016 41.5 20.7 10.2 12.3

13/03/2016 46.8 18.2 9.3 10.7

W-3 19/03/2016 43.7 17.6 9.2 11.3

20/03/2016 39.6 20.8 8.6 10.9

W-4 26/03/2016 46.2 19.7 8.3 9.6

27/03/2016 46.0 16.8 8.0 8.7

W-5 02/04/2016 46.4 23.2 7.9 11.2

03/04/2016 44.8 23.1 7.7 9.7

W-6 09/04/2016 45.5 24.3 8.5 10.8

10/04/2016 44.6 25.4 8.1 10.3

W-7 16/04/2016 36.7 23.8 7.7 9.6

17/04/2016 38.8 22.2 7.9 8.5

W-8 23/04/2016 44.7 23.1 9.6 11.2

24/04/2016 44.4 25.8 8.4 11.9

W-9 30/04/2016 40.5 26.1 8.1 10.2

01/05/2016 38.8 24.3 9.5 12.7

W-10 07/05/2016 43.4 23.7 10.5 13.1

08/05/2016 40.4 21.6 9.8 12.2

W-11 14/05/2016 44.2 24.3 8.2 10.5

15/05/2016 42.4 22.6 9.1 11.7

W-12 21/05/2016 42.7 21.8 7.9 10.2

22/05/2016 43.9 24.1 8.6 11.4

W-13 28/05/2016 45.2 23.8 9.3 12.8

29/05/2016 40.4 20.2 7.8 8.7

Minimum 38.8 16.8 7.7 8.7

Maximum 46.2 26.1 10.5 13.1

Average 42.5 21.45 7.45 8.9

95

9.2 Noise Monitoring Results

Time Hrs N1 N2 N3 N4

6 33.4 33.8 38.2 39.5

7 34.1 35.1 39.6 39.7

Day 8 36.6 37.6 40.7 40.3

9 37.0 36.0 40.1 42.5

10 39.4 37.4 41.0 43.1

11 37.4 38.4 42.2 43.6

12 40.9 39.9 44.0 42.5

13 41.9 41.9 43.7 48.4

14 40.4 40.4 44.2 45.9

15 41.7 41.7 42.5 44.2

16 38.7 38.7 45.2 43.0

17 34.1 34.1 44.0 42.6

18 34.9 33.9 42.3 42.4

19 34.1 34.1 44.6 41.3

20 37.0 35.0 40.2 40.5

21 38.1 34.1 39.7 40.1

22 34.6 34.6 44.9 39.7

23 37.0 35.0 40.1 39.2

24 36.1 34.1 37.2 38.8

1 35.4 36.4 37.5 38.3

96

Night 2 36.4 36.4 36.6 38.9

3 38.8 34.8 39.3 40.3

4 36.8 34.3 37.2 40.9

5 37.9 34.9 36.1 39.7

Range 33.4 - 41.9 33.8-41.7 36.1-45.2 39.9-48.4

Time (Hrs) Stations

N – 1 N – 2 N – 3 N – 4 N – 5 N – 6 N – 7

Day

Time

6 35.4 41.4 41.2 40.5 40.4 41.4 42.0

7 37.1 40.4 41.6 43.6 41.1 41.9 42.5

8 34.6 42.2 45.7 44.2 41.5 42.1 42.7

9 39.0 43.8 45.1 43.3 41.7 42.7 43.3

10 44.4 45.5 46.0 45.1 43.1 43.9 44.5

11 37.4 44.7 45.2 44.0 42.5 43.5 44.1

12 41.9 45.4 44.0 39.6 41.3 43.0 43.6

13 38.9 43.7 42.7 42.9 38.8 40.9 41.5

14 41.4 41.5 42.2 40.7 38.4 41.8 42.4

15 43.7 43.0 42.5 40.3 38.5 39.9 40.5

16 38.7 40.1 45.2 42.9 41.2 40.6 41.2

17 36.1 44.1 45.0 43.7 42.9 42.4 43.0

18 37.9 43.8 42.3 44.4 41.4 42.0 42.6

19 37.1 41.2 41.6 42.6 42.1 41.8 42.4

97

20 41.0 42.7 40.2 39.1 40.2 40.7 41.3

21 38.1 45.2 40.7 41.7 38.8 39.9 40.5

22 40.6 40.1 42.9 42.3 37.0 39.5 40.1

Night

Time

23 37.0 39.8 40.1 40.6 37.8 39.1 39.7

24 40.1 39.0 37.2 35.3 37.4 38.6 39.2

1 37.4 38.8 37.5 37.2 36.5 38.2 38.8

2 36.4 40.1 35.6 35.2 38.4 37.7 38.3

3 38.8 38.8 37.3 35.6 38.7 38.3 38.9

4 38.8 39.4 38.2 38.5 39.4 39.7 40.3

5 37.9 40.5 40.1 39.0 39.7 40.3 40.9

Range 34.6 -

44.4

38.8 -

45.5

35.6 -

46.0

35.2 -

45.1

36.5 -

43.1

37.7 -

43.9

38.3 -

44.5