Upload
voquynh
View
216
Download
1
Embed Size (px)
Citation preview
Eskom Coal Supply and the Role of Emerging Miners
May 2015
2
Eskom historically utilised 2 coal contract types, with an increase in shorter-term contracts in the last 10 years
Fixed-price Long Term Contracts Fixed-price Short-Medium Term ContractsCost Plus Long Term Contracts
Description
Advantages
Disadvantages
• In place for mines that are situated close to Eskom’s power stations with all coal production dedicated to Eskom
• The coal price is based on mining costs plus an agreedprofit consisting of management fees and a return on capitaloriginally invested
• These contracts deliver coal to Eskom at a fixed price that is annually escalated according to an agreed composite escalation index
• Supply to Eskom, export marketand other local markets
• Utilised to fill the remaining coal requirement that cannot be supplied by the cost-plus and fixed price contracts
• The short-medium term mines tend to have inherently higher cost structures which relates to higher coal costs
• Historically lowest R/t cost• Transparency into mine
operations and ability to influence• Easiest long term negotiations,
simplified and expedited financing
• Predictable prices• Less price and quality variation
risk exposure than Cost Plus
• Fast and easy to negotiate• Predictable prices• Flexibility through short contract
durations and road and rail deliveries
• Eskom carries almost all risk• Mine has limited incentive to
optimise operations• Eskom provides initial and
sustaining capital expenditure
• Prices can be high if Eskom has limited alternative options
• Dependent on global market demand, price and export volumes
• Substantial price premium for mining marginal deposits and for the miner’s higher risk exposure
• Considerable contract management resources required
62 59 60 68 71 65 67 63 65 60 60 53 52 50 48
262016117211 46444540373831
31282931303030
124
F2014 F2015
122 124
F2013
126
F2011
126
F2010 F2012
122
31
F2009
133
F2008
120
31
F2007
117
31
F2006
112
31
F2004
113
F2003
105
30
F2002
93
30
F2001
89
29
F2000
92
28
Volume Trend
(2000-2015)
Fixed-price Short/ Medium TermFixed-price Long TermCost Plus
Source: PED Internal analysis
Coal Purchases (Mt)
3
Eskom’s life of station coal supply plan contains over two billion tons of un-contracted coal from 2020 onwards
-
20
40
60
80
100
120
140
160
180
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
2036
2037
2038
2039
2040
Un-contracted
Contracted
Based on a 50 year operational lifespan Only 5 stations still in operation after 2040:
Contracted
Unidentified
Coal demand, MtpaIncludes only Eskom requirements
Total uncommitted requirement of ~40Mtpa as early as 2018
Key Message• Coal supply to 2018 is contracted to an acceptable degree (with exception of Kusile),
thereafter a significant proportion of coal is not contracted. Also planned operationallifespan increases to between 50 and 60 years will compound the problem.
Source: 2012 McCloskey Coal Conference
4
Export Price and Coal Grades
5
Coal Export price trend at Richards Bay Coal Terminal in US dollars
Source: Argus Media, Macquarie Research
Shortage of coal supply to
Eskom
6
14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
124
122
120
74
8
6
4
2
0
Kelvin PS
Calorific value GJ/ton
Eskom
Export
Industrial boilers
Municipalities e.g., hospitals CementBrick and tile
MiningAgriculture
VolumeMt, 2009/2010
Eskom controlled
Competitive
Export
India
Eskom
India
• RB3, the lower quality coal grade (~5,500kcal/kg, ~23MJ/kg) has been legitimised in recent months signifying that RB3 is a tradable commodity. RB3 competes directly with Eskom’s coal requirements
• Coal Brokerage global COAL updated its Standard Coal Trading Agreement (SCoTA) in March 2012 to a new trading contract for Richards Bay (5,500 kcal/kg NAR; total moisture 14%; maximum ash 23% and 1% sulphur on as-received basis)
Sasol
Segmentation of the SA coal market, with Eskom needing higher quality and India prepared to take lower quality
Source: McKinsey Analysis
77
Eskom’s Current Coal Requirements
8
Eskom Long Term Coal Supply (Projected)Mtpa
Source: Internal analysis
Eskom has to secure 2.17 billion tonnes of coal up to 2051, ~1.05 billion is still to be contracted
▪ ~1.05 billion tonnes (average 11Mtpafrom FY2018 onwards), will be sourcedfrom new coal supply agreements andprovides an opportunity for emergingminers
▪ Potential for Waterberg supply in thefuture in addition to the Mpumalangaregion.
Medium Term Supply
▪ Long Term supply includes the lifeextensions of all our existing long termcontracts and the New Largo agreementfor Kusile
▪ The estimated saleable coal from thesesources is ~1.12 billion tonnes
Long Term Supply
▪ For the next 5-years Eskom is 80% contracted and the remaining FY16 and FY17 shortfall will be securedsoon.
▪ For the foreseeable future Eskom is fully contracted at Lethabo, Matimba, Medupi, Kendal, Duvha, Matlaand Tutuka.
Contracted/Recently Secured
Source: Internal analysis
9
Eskom Coal Requirements: Qualities
9
• Indicative Coal Quality requirement ranges (MJ/kg, Air Dried)
Note: Based on 240 specifications
1010
Market Factors
11
Export capacity of existing coal mines
§ Lack of investment will result in a decline from 2018 onwards
§ Export coal prices were around US$95 per tonne 24 months ago, but dropped below US$75 per tonne by July
2013 and to US$62 per tonne in recent weeks, recovering only to US$65 on the second week of May 2015.
Export capacity of existing South African mines(Million tonnes)
§ No new export mines have been announced
since 2012 and the only ‘sustaining’ project was
at Glencore’s Tweefontein Colliery
§ The global coal industry is reducing its focus on
thermal coal, driven by thermal coal assets have
delivered anemic returns in recent years and a
material recovery in prices over forthcoming
periods is not anticipated.
§ In the medium term companies will continue to
constrain capital expenditure
§ Eskom believes that the lack of investment in
new mining capacity over the last few of years
and the time it takes to establish a new coal mine
will force Eskom to start purchasing a proportion
of its coal requirement at prices that competes
with export opportunities, i.e. at export parity
prices.
Comments
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
2015 20352020 2025 2030
Source: Wood Mackenzie
Seaborne Thermal Growth (2015-2035)(Million tonnes)
12
Imports into India will increasing rapidly
Thank you
14
Eskom coal quality requirements
Source: PED
Parameter Typical Eskom Ranges Impact of out of spec coal Actions to improve/ manage qualities
Calorific Value (CV)
16 – 23.5 MJ/kg - Low CV coal means that more coal must be burned to produce the same electricity
- In extreme cases, the power station will not be able to burn low CV coal
- Coal can be ‘washed’ to float off lower CV coal, the miner can try to mine only the higher CV coal seams, or low CV coal can be blended with high CV coal
- The power station furnace can be designed to use low CV coal; however, once built, the required CV cannot be changed
Volatiles 20 – 26% - Coal will not ignite in the furnace if the volatiles are too low
- Excessive volatile are a safety hazard
- Limited actions possible – must source the correct coal
Ash 22 – 41% - High ash coal has less energy, increases the ash disposal requirements and can ‘clog up’ and erode key power station equipment
- Ash can be removed by washing of the coal- Equipping the station to handle higher ash coal is
possible, but generally expensive
Abrasive Index (AI)
219 – 609 mg/Fe - High AI coal will cause wear and erosion of power station equipment
- AI can be reduced by selective mining and/or washing
- To handle high AI coal, the power station must increase its frequency of maintenance, which reduces the time available for producing electricity
Sulphur <1% - Sulphur results in air pollution, which can exceed permissible levels
- Washing can reduce sulphur levels- The power station can install expensive filtering
equipment to remove the sulphur dioxide
Moisture 5.9 -11% - Higher coal moisture affects efficiency of the boiler
- Compact stockpiles to remove water and allow drying time