7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13
1/27
SEN & LALL CONSULTANTS PVT. LTD.
Architects Consultants
Patna-800 0011
Sl.
No.Item No. L B H/D Qty. Unit
1.0 Earth Work
1.1 Earth Work in excavation in foundation
PC1 15 2.40 2.40 1.15 99.36 cum
PC2 29 2.40 0.645 1.15 51.63 cum
29 1.535 1.575 1.15 80.63 cum
PC3 4.00 3.40 2.40 1.15 37.54 cum
PC4 1.00 2.40 1.995 1.15 5.51 cum
1.00 1.535 1.575 1.15 2.78 cum
PC5 1.00 3.75 2.40 1.15 10.35 cum
PC6 2.00 3.75 3.10 1.15 26.74 cum
PC7 1.00 2.40 3.345 1.15 9.23 cum
1.00 1.535 1.575 1.15 2.78 cum
Basement 1.00 34.00 11.5 3.125 1221.88 cum
1548.41 cum= 1549.00 cum
1.2 Extra for every additional lift 1549.00 cum
1.2 Filling available excavated earth
Pile 197 0.785 0.2025 15.90 497.92 cum
Pile cap & Basement (1548.4337.4637.4628.4021.57221.37517.65) 684.52 cum
1182.44 cum
= 1183.00 cum
1.3 Supplying and filling in plinth with local
sand
Pile cap Foundation 326.55 0.10 28.40
Plinth 1.15
Below basement 1 29.75 7.25 0.10 21.57 cum
Below floor
1.500.075x20.100.04=1.21
Grid 710 (D to I) 1 23.725 12.64 1.21 362.86 cum
Grid 14 (D to I) 1 22.50 9.55 1.21 260.00 cum
Lounge & stair 1 10.90 7.50 1.21 98.92 cum
Atrium 1 10.90 7.50 1.21 98.92 cum
820.69 cum
= 821.00 cum
Project : Vidhayak Awasan at Patna
MLC Hostel Block
Sheet No.
Estimate of Quantities
7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13
2/27
SEN & LALL CONSULTANTS PVT. LTD.
Architects Consultants
Patna-800 001
2
Sl.
No.Item No. L B H/D Qty. Unit
3.0 Concrete Work
3.2 Extra for providing and mixing water
proofing material 79.56 0.61 1000 970.63 No.
50 = 979.00 No..
3.1 P/L PCC (1:3:6) in foundation & plinthBelow pile cap 326.55 0.075 21.29 cum
1.15
In basement 29.75 7.25 0.075 16.18 cum
37.47 cum
+ 101.00 cum
138.47 cum
= 139.00 cum
2 Pile works
2.1 Boring providing and installation cast in
situ single under reamed pile
450 mm dia piles 197 15.90 3132.30 mtr.
= 3133.00 mtr.3x29 = 87
4x15 = 60
5x5 = 25
6x3 = 18
7x1 = 7
197 Nos.
2.2 Vertical load testing of pile upto 50 tonne 1 1 Nos.
initial test
2.3 Vertical load testing of piles
Routine test 4 4 Nos.
Providing PCC 1:3:6 under floor in G.F. 571.04 0.10 57.10 cum
Ref soling
Seenkn Area upper floor 16.00 31.19 0.45
32.00 3.50 1.50
32.00 2.55 2.40
582.29 0.075 43.67 cum
100.78
Say 101.00 cum
11.76 Providing and filling brick bat khoa 30.0 2.55 2.40 0.385 70.69 cum
= 71.00 cumPCC (1:2:4) 1.0 7.5 7.50 0.1 5.625 cum
Under portico = 6.00 cum
Sheet No.
7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13
3/27
SEN & LALL CONSULTANTS PVT. LTD.
Architects Consultants
Patna-800 001
Sheet No. 3
Sl.
No.Item No. L B H/D Qty. Unit
4.3 P/L RCC M20
4.3.1 All work upto PL
Pile cap 222 cum
Column up to PL 31 cum
Tie Beam 23 cum
for Basement Basement slab 65 cum 341 cum
Superstructure
4.3.2 wall , Column
Column 220+3.51 cum 224.0
wall 46+12.43 59.0 283 cum
4.3.3 Plinth Beam 69.00 cum
Foor Beam 490.00 cum
Roof slab 624.00 cum
Stair 77.00 cum
Chajja 14.00 cumLintel 12.00 cum
Band 20.00 cum
cooking slab 7.00 cum 1313 cum
1937 cum
Add RCC M25 instead of M20 1937 cum
4.0 Reinforced Cement Concrete works
Shuttering
4.1.1 Foundations & footings
Pile cap
PC1 15 4 2.25 0.90 121.50 sqm
PC2 29 7.38 - 0.90 192.62 sqm
PC3 8 5.495 - 0.90 39.56 sqm
PC4 1 10.08 - 0.90 9.07 sqm
PC5 2 5.85 - 0.90 10.53 sqm
PC6 4 6.55 - 0.90 23.58 sqm
PC7 1 12.78 - 0.90 11.50 sqm
408.37 sqm
= 408.0 sqm
Col. Upto P.L 76 1 1.50 114.0 sqm
40 0.90 3.60 129.60 sqm
Tie Beam 1 530.04 1.450 768.56 sqm
1420.16 sqm
7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13
4/27
SEN & LALL CONSULTANTS PVT. LTD.
Architects Consultants
Patna-800 001
Sheet No. 4
Sl.
No.Item No. L B H/D Qty. Unit
4.3 Providing & Laying ---------- RCC M20
4.3.1 All work upto PL
Pile Cap
Pc1 15 2.25 2.25 0.90 68.34 cum
Pc2 29 2.25 0.57 0.90 33.47 cum
29 1.385 1.5 0.90 54.22 cumPc3 4 3.245 2.25 0.90 26.28 cum
Pc4 1 2.25 1.92 0.90 3.89 cum
1 1.385 1.50 0.90 1.87 cum
Pc5 1 2.25 3.60 0.90 7.29 cum
Pc6 2 2.95 3.30 0.90 17.52 cum
Pc7 1 2.25 3.27 0.90 6.62 cum
1 1.385 1.50 0.90 1.87 cum
221.39 cum
= 222.00 cum
50 0.30 0.60 1.50 13.50 cum
Col. Upto Pl. 8 0.40 0.60 1.50 2.88 cumBasement 20 0.30 0.60 4.00 14.40 cum
30.78 cum
= 31.00 cum
Basement Floor slab 1 29.75 7.25 0.30 64.71 cum
Tie Beam for Basement 1 74.00 0.25 0.60 11.10 cum
A to I (8x30.30) + (5x29.75) +
4x7.25+7x7.25+2x29.75 1 456.04 0.25 0.60 68.41 cum
Outer beam at E.G.L 1 75.00 0.25 0.60 11.25 cum
RCC Alll work upto PL 90.76 cum
Pile Cap 222.0
Col. Up to Pl. 31.0
Tie Beam 87.00
Basement floor slab 65.00
405.0
4 Reinforcement cement concrete work
4.3 Providing and laying in position machine
batched mixed & machine vibrated mixed
& Machine
M-20 Concrete
4.3.15.42.1 All work upto plinth in upto + 1200 mm Lv. Ref. Page
4.3.2 All work from plinth upto floor V level
5.42.2.1 walls columns pillar poof and struls
columns G.F. 8 0.40 0.60 3.50 6.72 cum
50 0.30 0.60 3.50 31.50 cum
Ist floor 58 0.30 0.60 3.075 32.10 cum
2nd & 3rd floor 116 0.30 0.60 3.075 64.21 cum
4th floor 51 0.30 0.60 3.075 28.23 cum
Terrace floor 5 0.30 0.60 3.80 3.42 cum
1 0.30 0.30 3.80 0.34 cum
7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13
5/27
7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13
6/27
SEN & LALL CONSULTANTS PVT. LTD.
Architects Consultants
Patna-800 001
Sheet No. 6
Sl.
No.Item No. L B H/D Qty. Unit
Quantity excluding 1.0 447.19 0.25 0.75 83.85 cum
slab thickness
1.0 13.20 0.25 0.60 1.98 cum
1.0 20.60 0.25 0.60 3.09 cum
1.0 43.50 0.45 0.60 11.75 cum
100.66 cumat 2nd flloor lv.
Add Length of 0.45 x 0.65 beam 1.0 447.19 0.25 0.75 83.85 cum
1.0 43.50 0.25 0.60 6.53 cum
Add 2.0 13.20 0.25 0.60 3.96 cum
1.0 20.60 0.25 0.60 3.09 cum
97.42 cum
3rd floor similar 97.43 cum
4th floor similar 97.43 cum
5th Terrace floor ducting similar 97.43 cum
less quantity over area of Terrace of 4th fl.
Gird E & G 2 6.775Gird F 1 3.95
Gird H 1 6.90
Gird I 1 15.075
Gird I 1 13.20
Gird II
1 x 3.50
Gird 2 1 6.45
Gird 3 & 4 2 6.90
72.975 3.50 Mtrs.
Quanty 1.0 72.975 0.25 0.60 10.95 cum
1.0 3.50 0.25 0.60 0.53 cum
76.43 mtrs 85.96 cum
Machine Room etc. 3 12.30
3 6.30
55.80 0.25 0.60 8.37 cum
OHWT Beams 2.90 cum
478.91 cum
RCC column 6.0 0.30 0.60 3.25 3.51 cum
RCC Wall 19.90 0.25 2.50 12.44 cum
Top slab 1.0 7.15 2.80 0.15 3.00 cum
Bottom 1.0 7.15 2.80 0.20 4.00 cum
RCC Beam 2.0 7.15 0.25 0.60 2.15 cum2.0 2.55 0.25 0.60 0.77 cum
R.C.C. Columns & Wall (0.81+12.43) 13.24 cum
RCC. Slab (3.00+4.00) 7.00 cum
RCC Beam (2.14+0.76) 2.90 cum
Shuttering
Column 6 x 2 (0.30+0.60) 3.25 35.10 sqm
Wall 2.0 7.15 2.50 35.75 sqm
2.0 2.80 2.50 14.00 sqm
7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13
7/27
SEN & LALL CONSULTANTS PVT. LTD.
Architects Consultants
Patna-800 001
Sheet No. 7
Sl.
No.Item No. L B H/D Qty. Unit
Slab 2.0 7.15 2.80 40.04 sqm
Beam 2.0 7.15 1.45 20.74 sqm
2.0 2.55 1.45 7.40 sqm
i) Column shuttering 35.10 sqm 36.00 sqmii) wall shuttering 49.75 sqm 50.00 sqm
iii) slab shuttering 40.04 sqm 40.00 sqm
iv) Beam shuttering 28.13 sqm 29.00 sqm
R / F Column 3.51 cum @ 260.00 kg/ cum 912.60 kg
wall 12.43 cum @ 80.00 kg/ cum 994.40 kg
slab 7.0 cum @ 80.00 kg/ cum 560.00 kg
Beam 2.90 cum @ 160.00 kg/ cum 464.00 kg
Extra projected Area (15.0+10.75) 1.20 0.15 4.64 sqm
slab of 1st floor Lv. 1 31.45 31.45 0.15 148.365 sqm
Less cut outStair at G.I. () 1 3.50 4.075 0.15 2.14 cum
Single flight() 1 10.05 1.75 0.15 2.64 cum
cut out () 1 10.05 1.325 0.15 2.00 cum
cut out D & F () 4 2.45 1.85 0.15 2.72 cum
Lifts () 2 1.80 1.80 0.15 0.97 cum
stair at 4/5() 1 5.10 2.80 0.15 2.14 cum
140.40
Atrium () 1 10.05 7.575 0.15 11.42 cum
128.98 cum
2nd, 3rd & 4th floor similar excluding extra prop. 3 x 124.33 cum 372.99 cum
Terrace floor Area similar to 1st floor
1 135.00 31.45 989.10
Less Area of terrace at 4th floor
Grid E/I & 1/3 1 15.60 8.10 128.36
Grid F/I & 3/6 1 7.925 8.95 70.93
Add 1 2.825 1.85 5.23
Less Atrium 1 10.05 10.35 104.02
693.02 sqm
Quantity 1 693.02 0.15 103.953 cum
Add Manualy Machine room lift etc. 2.0 2.60 2.60 0.20 2.70 cum
1.0 11.15 4.825 0.15 8.07 cumTotal slab 616.68 cum
= 617.0 cum
Lintel D1 11.0 1.40 0.25 0.65
at G.F. Only D2 1.0 1.50 0.25 0.15
D3 7.0 1.30 0.25 0.15
D4 5.0 2.30 0.25 0.15
D5 2.0 1.70 0.25 0.15
W1 5.0 2.00
W2 6.0 1.50
5.0 59.90 0.25 0.15 11.23 cum
7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13
8/27
SEN & LALL CONSULTANTS PVT. LTD.
Architects Consultants
Patna-800 001
Sheet No. 8
Sl.
No.Item No. L B H/D Qty. Unit
Stair single flight 1 11.0
1st , 2nd & 3rd 3 10.85
43.55 1.75 0.175 13.34 cum
Steps 23 1.75 0.15 0.152 0.92 cum
60 1.75 0.15 0.152 2.39 cum
front stair 8 4.33 1.00 0.150 5.20 cum8 1.09 1.00 0.150 1.31 cum
Steps 23 1.00 0.30 0.152 1.05 cum
60 1.00 0.30 0.152 2.74 cum
Rear Stair 2 3.12 1.15 0.15 1.08 cum
G.F. 2 2.80 1.20 0.15 1.01 cum
Steps 22 1.15 0.30 0.159 1.21 cum
1st , 2nd & 3rd floor 6 3.12 1.15 0.15 3.23 cum
6 2.80 1.20 0.15 3.02 cum
57 1.15 0.15 0.153 1.50 cum
37.99 cum
For 2 Nos. 2 x 38.03 76.16 cum
= 77.00 cumRCC slab in cooking platform 1 103.20 0.60 0.10 6.19 cum
= 7.00 cum
Chajja wather shell at G.F. D1 2 0.90 + 0.50
D5 2 1.20 + 0.50
W1 5 1.20 + 0.50
W2 6 1.00 + 0.50
25.20 0.85 0.10 2.14 cum
window sill
G.F. W 1 & W2 19.00 0.85 0.10 1.62 cum
1st , 2nd & 3rd floor
W3 12x3x2.10+0.50
W4 4x3x0.90+0.50
4th floor w3 9x1x2.10+0.50
W4 4x1x0.90+0.50
139.00 0.85 0.10 11.82 cum
15.57 cum
= 15.00 cum
Add Railing for Balcony front 4 rear 24 2.10 0.125 0.30 1.89 cum
6 2.10 0.125 0.30 0.47 cum
6 8.725 0.125 0.30 1.96 cum
1 8.725 0.125 0.30 0.33 cum
Atrium & concrete 8 17.625 0.125 0.30 5.29 cum
8 11.375 0.125 0.30 3.41 cumAtrium at Terrace 2 20.14 0.125 0.30 1.51 cum
14.86 cum
Parapet Band 4 x 31.45 x 0.25 x 0.10 3.14
Surrounded Atr. (11.25+10.90) X 0.25 X 0.10 1.11 cum
19.11 cum
= 20.00 cum
4.1 Centering and shutering including etc. for OHWT 50.00
5.14
7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13
9/27
SEN & LALL CONSULTANTS PVT. LTD.
Architects Consultants
Patna-800 001
Sheet No. 9
Sl.
No.Item No. L B H/D Qty. Unit
4.1.2 walls of any thickness 5 x 2 (2.60 + 0.25) 16.35 465.97 sqm
5 x 2 (2.60 + 0.25) 4.20 119.70 sqm
Basement 4.0 30.275 2.40 290.64 sqm
4.0 7.75 2.40 74.40 sqm
1000.71 sqm
4.1.3 suspended floor, Roofs Landingbalconies etc. at 1st floor Lv.
() 1.0 30.35 30.35 - 921.123 sqm
(stair ) Less cut outs
() 1.0 3.5 4.075 - 14.26 sqm
Stair single flight outs () 1.0 10.05 1.75 - 17.59 sqm
cut outs () 1.0 10.05 1.325 - 13.32 sqm
cut outs at D & F () 4.0 2.45 1.85 - 18.13 sqm
Lift () 2.0 1.80 1.8 - 6.48 sqm
Stair at 4/5 () 1.0 5.10 2.80 - 14.28 sqm
Atrium () 1.0 10.05 7.575 - 76.13 sqm
760.94 sqm
at 2nd , 3rd & 4th floor similar 3.0 756.83 2269.89 sqm
at Terrace floor 756.83 sqm
similar
Less Terrace Below () 1.0 15.00 7.38 - 110.70 sqm
() 1.0 7.40 7.50 - 55.50 sqm
590.63 sqm
Machine Room 2.0 2.10 2.10 - 8.82 sqm
1.0 11.15 4.83 - 53.80 sqm
62.62 sqm
Less area of beam bottom 3684.08 sqm
Less area of beam bottom () (447.10 +13.20+10.30) 0.25 117.67 sqm
() 1 43.50 0.45 19.58 sqm
2nd , 3rd & 4th floor () 3 514.19 0.25 385.64 sqm
Terrace floor 1 (514.19 76.43) 0.25 109.44 sqm
Machine Room etc. 1 55.80 0.25 13.95 sqm
3037.80 sqm
Basement roof slab at Gr. Floor 1 29.75 7.25 215.69 sqm
3253.49 sqm
For OHWT 40.00 sqm3293.49 sqm
5.14.5 Shuttering for Beams & Lintels
Beams 1st floor 1 447.19 1.75 - 782.58 sqm
1 13.20 1.45 - 19.14 sqm
1 20.60 1.45 - 29.87 sqm
1 43.50 1.45 - 63.08 sqm
894.67 sqm
Total all floors
7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13
10/27
SEN & LALL CONSULTANTS PVT. LTD.
Architects Consultants
Patna-800 001
Sheet No. 10
Sl.
No.Item No. L B H/D Qty. Unit
447.19 + (43.5013.20) 1 447.19 1.75 - 782.58 sqm
1 43.50 1.45 - 63.08 sqm
2 13.20 1.45 - 38.28 sqm
1 20.60 1.45 - 29.87 sqm
913.81 sqm
3rd & 4th floor similar 2 x 913.81 1827.62 sqm
Terrace floor similar 913.81 sqm
Less
Less () 1 72.925 1.45 - 105.74 sqm
() 1 3.50 1.45 - 5.08 sqm
802.99 sqm
Add for OHWT 29.00 sqm
3 18.60 1.45 - 80.91 sqm
4549.00 sqm
Add lintels 1 40.90 0.55 - 22.50 sqm
Add tie Beam for up to Pl 768.56 sqm
5340.05 sqm
5.14.6 Shuttering for column for O.H.W.T 36.00 sqm
Pilled etc
G.F 8 x 2 (0.40+0.60) 3.50 56.00 sqm
50 x 2 (0.30+0.60) 3.50 315.00 sqm
1st , 2nd & 3rd floor 3x58x2 (0.30+0.60) 3.075 963.09 sqm
4th floor 51x2 (0.30+0.60) 3.075 282.290 sqm
Terrace floor 5 x 2 (0.30+0.60) 380.0 34.204 sqm
1 x 2 (0.30+0.30) 380.0 4.56 sqm
Add upto Pl. 250.08 sqm
1941.22 sqm
= 1942.00 sqm
5.14.7 Suttering for stair with sides
(for all floor) single flight 1 43.55 (0.175+0.75+0.175) 91.46 sqm
corners 0.5x2x (23+(3x20) 0.30 0.152 3.78 sqm
Steps 83.0 1.75 0.152 22.08 sqm
front stair 8.0 4.33 1.30 45.03 sqm
8.0 1.09 1.30 11.34 sqm
coners 2x83 .30 x .50 0.152 3.78 sqm
Steps 83 1.00 0.152 12.62 sqm
Rear stair 8.0 3.12 1.45 36.19 sqm8.0 2.80 1.50 33.60 sqm
corners 2x82 0.30x.50 0.152 3.74 sqm
Steps 82 1.15 0.152 14.33 sqm
277.95 sqm
= 278.00 sqm
5.14.20 wheather shade chajja, etc prop. From
beam bolter 1 (15.0+10.75) (1.20+0.15 34.76 sqm
Extra proj 1st floor only
Proj at 1st, 2nd , 3rd & 4th flloor 4x2 (31.45+0.15+0.15) (0.725+0.15) 222.25 sqm
4x2 (30.00 x 0.725+0.15) (0.725+0.15) 210.0 sqm
7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13
11/27
SEN & LALL CONSULTANTS PVT. LTD.
Architects Consultants
Patna-800 001
Sheet No. 11
Sl.
No.Item No. L B H/D Qty. Unit
Chajja at G.F.
D3 2.0 (0.90+0.20) (0.70+0.10) 1.760 sqm
D5 2.0 (1.20+0.20) (0.70+0.10) 2.240 sqm
W1 5.0 (1.50+0.20) (0.70+0.10) 6.80 sqm
W2 6.0 (1.0 + 0.20) (0.70+0.10) 5.76 sqm
Add sill 1.0 139.4 1.05 146.37 sqm629.94 sqm
= 630.00 sqm
5.14.11 Edges of slab and breaks at first floor
stair cut out /Atrium
6.0 10.05 60.30 mtrs.
2.0 (7.575+1.325) 17.80 mtrs.
Lift 8.0 1.80 14.40 mtrs.
Tlt Duct 4 x 2 (2.45 + 1.85) 34.40 mtrs.
Fire Duct 2.0 (1.80 + 0.80) 5.20 mtrs.
Fire Duct 2.0 (2.175 + 0.80) 2.98 mtrs.
Elect duct 2.0 (2.20+ 0.80) 6.00 mtrs.
2.0 (1.45+ 0.80) 4.50 mtrs.145.58 mtrs.
B.F. 145.58 mtrs.
2nd and 3rd & 4th floor similar 3x 145.58 436.74 mtrs.
Terrace floor similar 145.58
Add 1.0 7.5 7.50
1.0 9.2 9.20
162.28 mtrs.
Add machine
Lift 2 x 4 2.60 20.80 mtrs.
2.0 (11.15 + 4.828) 31.96 mtrs.
Total 797.36
= 800.0 mtrs.
Facia , fins 1 396.40 (0.30+0.125+0.30) 287.31 sqm
= 287.00 sqm
Shelves 1.0 103.20 0.60 61.92 sqm
= 62.00 sqm
R/F Steel in foundation & Plinth
In Pile 499.0 cum @ 100.00 kg / cum 49.90 MT
Pile Cap 222.0 cum @ 120.00 kg / cum 26.64 MT
Column up to pl 31.0 cum @ 260.00 kg / cum 8.06 MT
Tie beam 23.0 cum @ 180.00 kg / cum 4.14 MT
floor slab 65.0 cum @ 80.00 kg / cum 5.20 MT93.94 Mt
7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13
12/27
SEN & LALL CONSULTANTS PVT. LTD.
Architects Consultants
Patna-800 001
Sheet No. 12
Sl.
No.Item No. L B H/D Qty. Unit
B. F 93.94 M.T.
Providing Re imforcement to RCC works Fnd
columns & walls super struct 283.00 cum @ 260.0 kg / cum 73.58 M.T.
beams P.B Roof beams 559.00 cum @ 200.0 kg / cum 111.80 M.T.
slab for basement slab for roofs 624.00 cum @ 80.0 kg / cum 49.92 M.T.
Lintels cooking slab 12.00 cum @ 140.0 kg / cum 1.68 M.T.
stair in beam from G.F. Above 7.00 cum @ 80.0 kg / cum 0.56 M.T.
77.00 cum @ 200.0 kg / cum 15.40 M.T.
Chajja & Sill 14.00 cum @ 80.0 kg / cum 1.12 M.T.
facia railing & Beam 20.00 cum @ 140.0 kg / cum 2.80 M.T.
350.80
= 317.50
= 351 M.T.
8 mm dia 55
10 mm dia 65
12 mm dia 60
16 mm dia 65
20 mm dia 50
25 mm dia 50
32 mm dia 6
5.1 Brick work in C.M (1:6) in foundation & Plinth
Basement
above RCC Outer wall 2 (7.50 + 29.975) x 0.25 x .60 11.24 cum
Ht : (1.20 0.60) = 0.60
Internal portion 1.00 7.50 0.25 3.40 6.38 cum
1.00 5.35 0.25 3.40 4.55 cum
Lift 3.00 2.10 0.25 3.40 5.36 cum
1.00 3.05 0.25 3.40 2.59 cum
gr. Floor F. gl to pl
Ht. : 1.20-0.60-0.10 = 0.50 1.00 453.95 0.25 0.50 56.74 cum
86.85 cum
= 87.0 cum
Total Brick work in foundation & plinth (87 + 627) 714.0 cum
9.1 Providing 100 A Brick flat soling .. all comp
Below foundation 326.55 283.95 sqm
1.15
Below in Basement floor 1.00 29.75 7.25 215.69 sqm
499.638 sqm
= 500.00 sqm
from item no. 8.1 flooring 671.00 sqm
Total 1171.00 sqm
7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13
13/27
SEN & LALL CONSULTANTS PVT. LTD.
Architects Consultants
Patna-800 001
Sheet No. 13
Sl.
No.Item No. L B H/D Qty. Unit
Brick masonry in super structural
G.F. Gr. 1 1.00 24.18 0.25 3.65 22.06 cum
1.00 21.38 0.25 3.20 17.10 cum
Gr. 3 1.00 6.75 0.25 3.20 5.40 cum
Gr. 4 1.00 3.15 0.25 3.20 2.52 cum
Lift 2.00 2.10 0.25 3.50 3.68 cumGr. 5 1.00 2.15 0.25 3.20 1.72 cum
stair Gr. 6 1.00 5.95 0.25 3.20 4.76 cum
stair Gr. 7 1.00 10.16 0.25 3.20 8.13 cum
stair Gr. 8 1.00 12.03 0.25 3.20 9.62 cum
stair Gr. 10 1.00 13.15 0.25 3.20 10.52 cum
1.00 15.60 0.25 3.65 14.24 cum
Grid J 1.00 3.50 0.25 3.20 2.80 cum
1.00 3.75 0.25 3.65 3.42 cum
Grid G 1.00 3.50 0.25 3.20 2.80 cum
Grid F 1.00 1.80 0.25 3.20 1.44 cum
Grid E 1.00 6.75 0.25 3.20 5.40 cum
1.00 8.48 0.25 3.20 6.78 cumGrid D 1.00 10.25 0.25 3.20 8.20 cum
Lift 1.00 2.10 0.25 3.20 1.68 cum
Grid C 1.00 10.55 0.25 3.20 8.44 cum
Grid A 1.00 26.95 0.25 3.20 21.56 cum
1.00 26.15 0.25 3.65 23.86 cum
186.14 cum
side walls Add of Door & windows 28.00 0.35 0.25 3.65 8.94 cum
195.08 cum
Less openings D5 () 6.00 1.20 0.25 2.40 4.32 cum
W1 () 12.00 1.50 0.25 1.50 6.75 cum
W2 () 12.00 1.00 0.25 1.00 3.00 cum
Net 181.01 cum
1st floor
Grid 1 off Grid 1 & 10 2.0 31.20
on Grid 1 & 10 2.0 26.100
Grid 11
91
4 x 2 3.75
Ducts 2 x 2 1.65
Grid 3 & 8 2.0 26.10
Grid 4 1 12.125
Lift line 1 4.325
Libe 1.0 2.10
Grid 5 1 1.975
Grid 6 1 6.48
On Grid Grid A 1 19.98
Off Grid Grid A 1.0 31.10
7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13
14/27
SEN & LALL CONSULTANTS PVT. LTD.
Architects Consultants
Patna-800 001
Sheet No. 14
Sl.
No.Item No. L B H/D Qty. Unit
Grid B 1 3.90
grid C 1 5.10 + 1.20
Lift / Duct 1 (2.10 + 1.05)
Grid D 1 14.05
Grid E 2 6.73
Grid F (2x3.90) + 1.20
Grid G 1 3.50
Grid H 1 6.30
On End - Grid I 1 18.30
Off Grid end I 1 31.10
Prog 58 0.35
Total length 265.96 145.10 m
Quantity 1.00 265.96 0.25 2.475 164.56 cum
1.00 145.10 0.25 2.975 107.92 cum
272.48 cum
Less Openings B.F 272.48 cum
D1() 8 0.9 0.25 2.40 4.32 cum
D5() 4 1.20 0.25 2.40 2.88 cum
D4() 2 1.80 0.25 2.40 2.16 cum
W3() 24 2.10 0.25 2.10 26.46 cum
W4() 8 0.90 0.25 0.90 1.62 cum
Balcony() 1+1 (7.82+6.60) 0.25 2.10 7.57 cum
Net 227.47 cum
2nd and 3rd floor similar 2 227.96 455.92 cum
4th floor
similar Less (Terrace area) 227.47 cum
Grid -1 .1/2 31.22
.1/2 26.10
Grid -11 2 3.75Grid 4 .1/2 12.10
Grid F 1.0 3.90
Grid H 1.0 6.30
on Grid I .1/2 18.30
of Grid I 1.0 17.30
45.95 32.31
() 1 45.95 0.25 2.48 28.43 cum
() 1 31.31 0.25 (2.9751.40) 12.33 cum
186.71 cum
7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13
15/27
SEN & LALL CONSULTANTS PVT. LTD.
Architects Consultants
Patna-800 001
Sheet No. 15
Sl.
No.Item No. L B H/D Qty. Unit
B.F 52.20 cum
Add D 2 0.90 0.25 2.40 1.08 cum
W3 6 2.10 0.25 2.10 6.62 cum
W4 2 0.90 0.25 0.90 0.41 cum
Bal 1 2.20 0.25 2.10 1.16 cum
61.46 cumAdd for high
per carpet Ref elevation 1.0 (15.61+7.30) 0.25x3.075 25.30 cum
86.76 cum
Parapet at Terrace for and of maching Rcc 2x(31.20+31.10) x 0.25 x 1.65 51.40 cum
Machine Room 2x (9.60+5.80) 0.25 x 3.80 28.50 cum
Add duct 4x2 (2.70+2.10) 0.25 x 1.20 11.52 cum
91.42 cum
Total All Floor 170.12 + (3x92.96) + 86.94 + 91.42 627.36 cum
say 627.00 cum
6.18A Half brick masonary with brick of class
designation class 100 in foundation and
plinth Refer foundationwork page
6.19 A Extra for Half brick masonry in super
structure above plinth upto floor V level
G.F Grid 1.0 10.71
Tlt 1.0 2.40
Grid 3 1.0 6.55
Stair V 41 1.0 1.00 4.13
Stair lobby on supplying / stair 2.0 2.925
Duct 2.0 1.60
Kit 1.0 1.50
Grid B Plth 1.0 1.80
sloves etc 1.0 9.30
Store / Manage 1.0 6.97
Corridor 1.0 1.80
Duct 2x4 2.45
Gents plth 1.0 7.25
Dvos 2.0 1.00
small walls
in stair lobby 1.0 (2.50+1.90)2586 63.61
Quantity 1.0 23.86 2.90 60.19 sqm
1.0 63.61 3.35 213.09 sqm
Low hight walls for GL 1.0 (17.0+15.525) 0.30 9.76 sqm
292.14 sqm
Less opening D1 () 4.0 0.90 2.40 8.64 sqm
D() 2.0 1.00 2.40 4.80 sqm
D3() 8.0 0.80 2.40 15.36 sqm
263.34 sqm
7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13
16/27
SEN & LALL CONSULTANTS PVT. LTD.
Architects Consultants
Patna-800 001
Sheet No. 16
Sl.
No.Item No. L B H/D Qty. Unit
Gr. Floor
Grid 21
Grid 81
Plth 8.0 2.825 2.625 59.325 sqm
Kit 8.0 2.825 2.925 66.105 sqm
Security Toilet 1.0 3.175 2.925 9.287 sqm
Security 1.0 5.625 2.475 13.922 sqmDucts in Lobby 2.0 2.80 2.925 16.380 sqm
Atrium , stair, Duct 5.0 10.175 0.30 15.26 sqm
2.0 8.90 0.30 5.34 sqm
Bed rooms Horiz 8.0 6.85 2.475 135.63 sqm
Duct 8.0 2.575 2.475 50.99 sqm
Tlt Proj 8.0 1.00 2.475 19.80 sqm
Dss effors Lobby 2.0 2.975 2.475 14.73 sqm
406.76 sqm
Less Doors etc.
D1() 9.0 0.90 2.40 19.44 sqm
D3() 9.0 0.80 2.40 17.28 sqm
D4() 8.0 1.80 2.40 34.56 sqmW4() 16.0 0.90 0.90 12.96 sqm
322.52 sqm
Net 2 x 328.76 sqm
2nd & 3rd floor similar
4th floor similar 328.76 sqm
Less () 2.0 2.825 2.625 14.83 sqm
2.0 2.825 2.925 16.53 sqm
2.0 6.85 2.475 33.91 sqm
2.0 1.00 2.475 4.95 sqm
258.55 sqm
B.F. 258.54 cum
Add 2.0 0.90 2.40 4.32 sqm
2.0 0.80 2.40 3.84 sqm
2.0 1.80 2.40 8.64 sqm
4.0 0.90 0.90 3.24 sqm
278.58 sqm
Tolet for all floor 263.14 +( 3x328.76) + 278.58 1528.00 sqm
7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13
17/27
SEN & LALL CONSULTANTS PVT. LTD.
Architects Consultants
Patna-800 001
Sheet No. 17
Sl.
No.Item No. L B H/D Qty. Unit
Doors & Window Basement G.F.
type floor
Ist, 2nd,
3rd
4th floor
& Terrace Total
9.24.2 D1 4.00 3x17 1x13 68.00 Nos.
9.25.2 D18 1.0 8.00 9.00 Nos.D1b 2.00 2.00 Nos.
9.25.2 D2 2.00 2.00 Nos.
9.25.2 D3 3x10 1x8 34.00 Nos.
D3a 1.0 3.00 4.00 Nos.
D4a 1.00 1.00 Nos.
D4b 3x2 2 8.00 Nos.
D5 1.0 4.00 3x2 2 13.00 cess
D6 3x8 1x6 30.00 Nos.
D7 3x11 1x7 40.00 Nos.
D8 3x2 1x2 8.00 Nos.
Dw1 1.00 3x1 4.00 Nos.
W1a 3.00 3.00
W1b 2.00 5.00
W2 6.00 6.00
W3a 3x4 1x3 15.00
W3b 3x4 1x3 15.00
w4 3x4 1x4 16.00
W5 a 3x2 1x1 7.00
W5b 3x2 1x1 7.00
Wb 3x17 1x13 64.00
9.24 Flush doors shutter decorative type
9.24.2 35 mm thick
D1 68 0.83 2.065 116.549 sqm
D8 8 1.465 2.065 24.20 sqm140.75 sqm
= 141.00 sqm
9.25 25 mm thick flush door D1a 9 0.83 2.065 15.43 sqm
9.25.2 non decorative
D2 2 0.83 2.065 3.43 sqm
D3 4 0.73 2.065 6.03 sqm
D3a 38 0.73 2.065 57.28 sqm
82.17 sqm
Say 82.00 sqm
5.26 Extra for providing and fixing flush door
with teak veneerin one sliding5.26.1
D3 4 0.73 2.065 6.03 sqm
Say 6.00 sqm
DSR Extra for Lamination
D1a 18 0.83 2.065 30.85 sqm
D2 4 0.83 2.065 6.86 sqm
D3 4 1.465 2.065 12.10 sqm
D3a 76 0.73 2.065 114.57 sqm
164.37 sqm
say 164.00 sqm
7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13
18/27
SEN & LALL CONSULTANTS PVT. LTD.
Architects Consultants
Patna-800 001
Sheet No. 18
Sl.
No.Item No. L B H/D Qty. Unit
DSR Fire retarduct door
D5 13 1.135 2.295 33.86 sqm
say 34.00 sqm
9.1 Providing wood work intrens of door wind
2nd class teak wood
9.1.3for DW1
Ver 4x4 2.40
Hor 4x2 6.65
Ver 4x2 2.10
bolt Hor 4x2 2.625
129.40
Quantity 1.0 129.40 0.15 0.075 1.46 cum
9.6 Providing and fixing glazed shutter for
door
9.6.3.4 35 mm thick 2nd class teak wood D4 1.0 1.73 2.065 3.57 sqm
for DW1 4.0 1.73 2.065 14.29 sqm
17.86
say 19.00 sqm
9.35 Extra for providing vision panel
9.35.1 Rectangular providing vision panel 2.0 0.80 2.065 3.30 sqm
In D2
9.61 Providing and fixing wooden moulded
beading
9.61.1.1 Teak wood 50x12 mm
D1 D1a 77.0 (2x2.40)+ 0.90 438.90 Mtrs.
D2 4.0 (2x2.40)+ 0.90 22.80 Mtrs.
D3 + D3a 38 (2x2.40)+ 0.80 212.80 Mtrs.
674.50 Mtrs.
B.F 674.50 Mtrs.
D4a 1.0 (2x2.40)+ 1.80 6.60 Mtrs.
D5 13.0 (2x2.40)+ 1.20 78.10 Mtrs.
D8 8.0 (3x2.40)+ 1.50 50.40 Mtrs.
Dw1 4.0 (2x2.40)+ 6.65 45.80 Mtrs.
for Glazing (2x6.65)+ (8x0.23)+ (8x2.10) 51.38 Mtrs.
.+(8x2.43)
906.78 Mtrs.Say 907.0 mtrs.
9.34 Extra for providing lipping with 2nd edges
of shutters
140.75 + 82.17 222.92 sqm
Say 223.00 sqm
7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13
19/27
SEN & LALL CONSULTANTS PVT. LTD.
Architects Consultants
Patna-800 001
Sheet No. 19
Sl.
No.Item No. L B H/D Qty. Unit
9.218 Providing and fixing Al sliding door bolts
300x16 mm
D1a 9
D2 2
D3a 4
D1 68
D4a 1D5 13
D8 8
105 Nos.
250 x 16 m
D3 34 Nos.
9.219 Providing and fixing Alm Tower bolts
300x10mm 151 Nos. 151 Nos.
150x 10mm 2x151 Nos. 302 Nos.
9.22 Providing and fixing Alm Handle
9.222.1 125mm 151x2 302 sqm
9.139 Providing and fixing bright finished brass
mostice lock
in D why 68 Nos.
9.73 A Providing and fixing 18 mm thick 150 mm
wood
D1 68 1.50
D7 40 2.70
W1a 3 2.10
W1b 2 2.10
W2 6 2.70
W3a 15 2.70
W3b 15 1.50
W4 16 2.70
W5 0/b 14 7.25
Glazing GL2 7 10.68
GL3 1 16.80
GL4 1 16.80
451.13 0.15 67.67 sqm
say 68.00 sqm
9.74 B Providing and fixing teak wood leping for
palmet
25x3m 451.00 451
DSR Providing and fixing Alm / UPVC Doors
window/ glazingD1b 2.0 1.50 2.40 7.20 sqm
D4b 8.0 1.80 2.40 34.56 sqm
Db 30.0 1.50 2.40 108.00 sqm
D7 40.0 2.10 2.40 201.60 sqm
W1a/b 5.0 1.50 1.50 11.25 sqm
W2 6.0 1.00 1.00 6.00 sqm
w3 a/b 30.0 2.10 2.10 132.30 sqm
W4 16.0 0.90 0.90 12.96 sqm
W5 a/b 14.0 2.10 2.10 61.74 sqm
wb 64.0 0.60 1.20 46.08 sqm
621.69 sqm
say 618.00 sqm
7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13
20/27
SEN & LALL CONSULTANTS PVT. LTD.
Architects Consultants
Patna-800 001
Sheet No. 20
Sl.
No.Item No. L B H/D Qty. Unit
24.3 Providing and fixing glazing
24.3.2 with glass pan of 5.50 mm Doors & window 618.00 sqm
Fixed glazing 124.95 sqm
Doors high 30.00 sqm
Glazing in DW 49.00 sqm821.95 sqm
say 822.00 sqm
UPVC / Alm
Providing and fixing fixed glazing
Gl - 2 1.0 6.65 2.825 18.79 sqm
Gl - 3 1.0 10.75 2.825 30.37 sqm
Gl -4 1.0 16.20 2.825 45.77 sqm
Gl - 5a 1.0 3.47 2.40 8.33 sqm
Gl-b 1.0 4.375 2.10 9.19 sqm
Gl-7 1.0 5.95 2.10 12.50 sqm
124.93 sqm
Steel works
9.4 Steel work in built up tubular truken
M.S stair at terrace Approx wt 900.00 kg
10.15 Providing and fixing press steel door fram
D1 68.0 (2x2.40)+ (3x0.90) 510.00 Mtr.
D1a 9.0 (2x2.40)+ (3x0.90) 67.50 Mtr.
D2 2.0 (2x2.40)+ (3x0.90) 15.00 Mtr.
D3 34.0 (2x2.40)+ (3x0.80) 244.80 Mtr.
D3a 4.0 (2x2.40)+ (3x0.80) 28.80 Mtr.
D4a 1.0 (2x2.40)+ (3x1.80) 10.20 Mtr.
D8 8.0 (2x2.40)+ (3x1.50) 74.40 Mtr.
691.20 950.70 Mtr.
Say 951.00 Mtr.
10.21 Providing and fixing circular CI ceiling fan
box
G.F 24 Nos.
Basement 10 Nos.
Ver, 2nd , brd floor 3x38 Nos.
4th floor 1x 30 Nos.Machine 2.0 Nos.
180 Nos.
10.32 Steel work welded in built up see in railing
balcony Atrium (Length similar to cond railing )
1.0 396.40 0.900 356.76 sqm
= 356.00 sqm
7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13
21/27
SEN & LALL CONSULTANTS PVT. LTD.
Architects Consultants
Patna-800 001
Sheet No. 21
Sl.
No.Item No. L B H/D Qty. Unit
B.F. 356.76 sqm
B.F. 396.40
for stair railing
Rear stair 5 8.16 1.20 48.96 sqm
froml stair 4 8.16 1.20 39.17 sqm
singh flight 8 8.68 1.20 83.33 sqm
839.28 mtrs. 528.216 sqm
. @27 kg/sqm 14261.94 kg
Add for M.S. stair at terrace roof Approx 200.00
14461.94
= 14500.00
Grill for window
w1a 3.0 1.50 1.50 6.75 sqm
w1b 2.0 1.50 1.50 4.50 sqm
w2 6.0 1.00 1.00 6.00 sqm
w3a 15.0 2.10 2.10 66.15 sqm
w3b 15.0 2.10 2.10 66.15 sqm
w4 16.0 0.90 0.90 12.96 sqmw5a 7.0 2.10 2.10 30.87 sqm
w5b 7.0 2.10 2.10 30.87 sqm
wb 54.0 0.60 1.20 38.88 sqm
263.13 sqm
. @15 kg/sqm 3841.95 sqm
= 3842.00 sqm
Structural steel 1.0 23.18 . @10.8 kg/sqm 250.34
2.0 3.0 . @4.5 kg/sqm 27.00
277.34x3 832kg
2x4 12.40 . @91.2 kg/sqm 675.00
1507
10.33 Providing and fixing hand rail
M.S. tube 40 mm per length ref
10.32 . @3.61 kg/sqm 1946.80
Say 1947.0 kg
Flooring Below Pile cap 326.95 283.95 sqm
1.15
In Beams 29.75 7.25 215.688 sqm
11.72 Providing dea main 100A flat bridge
solings of E/I and direction 1.0 29.75 22.25 661.94 sqm
1.0 3.50 2.60 9.10 sqm
1170.68 sqm
11.29
Pre cast terrazo tiles 22 mm thick with
marble chips = 1171.0 Nos.
11.29.1
bed of cement mortar 1:4 light shade
noing white wash
G.F. Administ 1.0 8.075 4.625 37.35 sqm
Ist floor, seing 1.0 5.62 4.30 24.17 sqm
Bal 1.0 7.60 2.35 17.86 sqm
2nd , 3rd & 4th floor
similar as marked 3.0 (24.21+17.86) sqm 126.21 sqm
205.58 sqm
say 206 sqm
7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13
22/27
SEN & LALL CONSULTANTS PVT. LTD.
Architects Consultants
Patna-800 001
Sheet No. 22
Sl.
No.Item No. L B H/D Qty. Unit
11.31 Precast terrazo tiles 22mm thick with
marble chips hubbing and polishing
complete
11.31.1 Light shade and white
G.F. 2 (8.075+4.625) 0.125 3.18 sqmIst floor 2 (5.63+4.30) 0.125 2.48 sqm
2 (7.60+2.35) 0.125 2.49 sqm
2nd , 3rd & 4th floor
similar as marked 3 (2.48+2.49) 14.91 sqm
23.06 sqm
say 23.00 sqm
P/L Granite in wall Lift Lobby 10 2.50 3.0 75.00 sqm
2 2.50 4.0 20.00 sqm
95.00 sqm
P/L Granite in Kitchen slab 1 19.20 0.75 14.40 sqm
8 2.80 0.75 16.80 sqm8 2.80 0.75 16.80 sqm
8 2.80 0.75 16.80 sqm
6 2.80 0.75 12.60 sqm
77.40 sqm
= 78.00 sqm
Extra for edge moulding 1 103.20 103.20 m
= 104.00 m
8.12.1 Providing and laying vitrified floor tiles
figment etc. complete (8x3)+6 5.50 3.50 577.50 sqm
All floor living in flooring & bed (8x3)+6 4.50 3.62 488.70 sqm
1066.20 sqm
in skirting (8x3) + 6) x2 (5.50+3.50) 0.125 67.50 sqm
(8x3) + 6) x2 (4.50+3.62) 0.125 60.90 sqm
128.40 sqm
= 129.00 sqm
11.40 Providing and laying ceramic glazed floor
tiles 400x 400 maching pigment etc.
complete
was skid type
G.F Main Tlt 1.0 7.25 3.50 25.38 sqm
1.0 7.25 2.675 19.39 sqm
shift toilet 1.0 2.925 2.575 7.53 sqm
1.0 1.90 1.80 3.42 sqm
Ist , 2nd & 3rd floor 24.0 2.80 1.00 67.20 sqm
24.0 2.10 0.50 25.20 sqm
Security 3.0 2.30 1.35 9.32 sqm
4th floor 6.0 2.80 1.00 16.80 sqm
6.0 2.10 0.50 6.30 sqm
1.0 2.30 1.35 3.11 sqm
183.64 sqm
= 184.00 sqm
7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13
23/27
SEN & LALL CONSULTANTS PVT. LTD.
Architects Consultants
Patna-800 001
Sheet No. 23
Sl.
No.Item No. L B H/D Qty. Unit
8.6 Ceramic glazed tiles in walls
GF Kitchen
2(11.7+7.5) =38.40 1.0 38.40 1.50 57.60 sqm
above coking platform 1.0 19.20 0.75 14.40 sqm
Ist floor
2(1.5+2.80)=8.6 8.0 8.6 1.50 103.20 sqm
8.0 2.8 0.75 16.80 sqm
2nd floor
8.0 8.6 1.50 103.20 sqm
8.0 2.8 0.75 16.80 sqm
3rd floor
8.0 8.6 1.50 103.20 sqm
8.0 2.8 0.75 16.80 sqm
4th floor
6.0 8.6 1.50 77.40 sqm
6.0 2.8 0.75 12.60 sqm
522.00 sqm
11.36 Providing and fixing Ist quality ceramic
glazed wall tiles in skirting
G.F 2 (7.25+3.50) 2.10 45.15 sqm
WC 4x2 (1.50+1.12) 2.10 44.02 sqm
2 (7.25+2.675) 2.10 41.69 sqm
2x2 (1.12+1.28) 2.10 20.16 sqm
2 (2.925+2.575) 2.10 23.10 sqm
2 (1.12+1.28) 2.10 10.08 sqm
2 (1.90+1.80) 2.10 15.54 sqm
2 (1.80+0.90) 2.10 11.34 sqm
Ist, 2nd, 3rd & 4th floor 30x2 (2.80+1.50) 2.10 541.80 sqm
Security 4x2 (2.30+1.35) 2.10 57.96 sqm
810.84 sqm
1332.84 sqm
= 1334.00 sqm
11.42 Marble stone flooring with 18 mm thick
marble stone Ent reception Launge corridor &
11.42.7.2 Rajnagar plain white marble 18 mm 1.0 17.15 7.50 128.63 sqm
0.20 to 0.50 sqm 1.0 4.50 2.50 11.25 sqm
1.0 7.50 2.75 20.63 sqm
1.0 15.00 15.00 225.00 sqm
385.50
Ist floor corridor 2.0 30.75 1.925 118.39 sqm
1.0 12.95 4.455 57.69 sqm
1.0 6.90 5.75 39.68 sqm
1.0 7.15 2.35 16.80 sqm
232.56
7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13
24/27
SEN & LALL CONSULTANTS PVT. LTD.
Architects Consultants
Patna-800 001
Sheet No. 24
Sl.
No.Item No. L B H/D Qty. Unit
2nd and 3rd floor similar
2 232.95 465.90
4th floor similar to Ist floor 216.15 sqm
Lessmarked () 56.48 sqmLess 1.0 7.50 1.925 14.44 sqm
145.23 sqm
Total 485.51 + 232.95+465.90+145.23 1329.59 sqm
Say co. 1330 sqm
Also see on page
G.F
11.41 A Pile work in skirting risers of step shade
comp. 1 17.15 + (4x7.50)
2 (15.0+15.0+2.75)
11.41A.1 Marble tiles polished regular 8 mm thick 112.65 x 0.125 14.08 sqm
B.F. 14.08 sqm
Ist floor
coridor 2x2 30.75
2x2 12.95
Launge 2 (6.90+5.75)
coridor / Ver 2 7.15
214.40 0.125 26.80 sqm
2nd and 3rd floor similar
4th floor 2x26.80 56.60 sqm
2 30.75
2 23.25
2 12.95
133.90 0.125 16.74 sqm
Total 111.22 sqm
Add skirting in dining Hall
Black marble (Border) marble 2 (16.0+10.65+2.70) 0.30 17.61 sqm
Total 128.83 sqm
G.F. Dining hall flooring with udaipur green 1 8.70 7.25 63.08 sqm
1 10.75 8.70 93.53 sqm
156.60 sqm= 157.00 sqm
7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13
25/27
SEN & LALL CONSULTANTS PVT. LTD.
Architects Consultants
Patna-800 001
Sheet No. 25
Sl.
No.Item No. L B H/D Qty. Unit
11.48 Kota stone flooring svs 20 mm ( average)
thick base of
25 mm thick
Basement 1 9.30 7.25 67.43 sqm
1 20.20 7.25 146.45 sqm
for stair treads & lendy 1 5.10 2.85 14.54 sqmTotal basement 228.41 sqm
G.F. kitchen / slaft 1 14.75 7.25 106.94 sqm
Ent. Stores , stair , passage 1 15.00 7.25 108.75 sqm
Less lift () 2 2.30 2.05 9.43 sqm
cut off () 1 3.50 2.80 9.80 sqm
Add staff Dining 1 8.20 7.575 62.12 sqm
Less plt () 1 2.925 2.70 7.90 sqm
Front stair Hall / Lobby 1 7.375 3.50 25.81 sqm
stair treads / 1 4.20 3.50 14.70 sqm
Less cut off () 1 1.80 1.10 1.98 sqm
Single flght treads & longs 1 10.75 1.75 18.81 sqmTotal G.F. 308.02 sqm
Ist floor
stair treads & 1 5.10 2.30 11.73 sqm
Less () 1 2.70 0.30 0.81 sqm
Staft Lobby / linem 1 5.10 4.45 22.70 sqm
Less lift () 1 2.30 2.05 4.72 sqm
28.90 sqm
B.F. 28.90 sqm
Front stair / Lobby Treads 1 7.00 3.50 24.50 sqm
Less () 1 1.80 1.00 1.80 sqm
Treads / long single flight 1 10.75 1.75 18.81 sqm
Kitchen 8 2.80 1.50 33.60 sqm
Bal / Verandah 8 3.625 2.35 68.15 sqm
172.16 sqm
2nd , 3rd floor similar 2 x 172.16 344.32 sqm
4th floor similar as marked in Ist floor 17.98 sqm
Add kitchen 6 2.80 1.50 25.20 sqm
bed / Verandah 6 3.625 2.35 51.11 sqm
Terrace at 4th floor 1 17.05 7.725 131.71 sqm
1 7.625 7.98 60.85 sqm
286.85 sqmTerrace floor 1 30.76 30.760 946.18 sqm
Less Terrace at 4th floor as marked () 192.56 sqm
Less Atrium () 1 11.15 11.150 124.32 sqm
Less machine room etc. () 4.55 4.732 21.53 sqm
() 1 4.75 3.10 14.73 sqm
593.04 sqm
Total kota 308+172+343+287+600 1710.00 sqm
7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13
26/27
SEN & LALL CONSULTANTS PVT. LTD.
Architects Consultants
Patna-800 001
Sheet No. 26
Sl.
No.Item No. L B H/D Qty. Unit
sheet 47
7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13
27/27