Estimate of Qnty - Mlc Hostel 13.2.13

Embed Size (px)

Citation preview

  • 7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13

    1/27

    SEN & LALL CONSULTANTS PVT. LTD.

    Architects Consultants

    Patna-800 0011

    Sl.

    No.Item No. L B H/D Qty. Unit

    1.0 Earth Work

    1.1 Earth Work in excavation in foundation

    PC1 15 2.40 2.40 1.15 99.36 cum

    PC2 29 2.40 0.645 1.15 51.63 cum

    29 1.535 1.575 1.15 80.63 cum

    PC3 4.00 3.40 2.40 1.15 37.54 cum

    PC4 1.00 2.40 1.995 1.15 5.51 cum

    1.00 1.535 1.575 1.15 2.78 cum

    PC5 1.00 3.75 2.40 1.15 10.35 cum

    PC6 2.00 3.75 3.10 1.15 26.74 cum

    PC7 1.00 2.40 3.345 1.15 9.23 cum

    1.00 1.535 1.575 1.15 2.78 cum

    Basement 1.00 34.00 11.5 3.125 1221.88 cum

    1548.41 cum= 1549.00 cum

    1.2 Extra for every additional lift 1549.00 cum

    1.2 Filling available excavated earth

    Pile 197 0.785 0.2025 15.90 497.92 cum

    Pile cap & Basement (1548.4337.4637.4628.4021.57221.37517.65) 684.52 cum

    1182.44 cum

    = 1183.00 cum

    1.3 Supplying and filling in plinth with local

    sand

    Pile cap Foundation 326.55 0.10 28.40

    Plinth 1.15

    Below basement 1 29.75 7.25 0.10 21.57 cum

    Below floor

    1.500.075x20.100.04=1.21

    Grid 710 (D to I) 1 23.725 12.64 1.21 362.86 cum

    Grid 14 (D to I) 1 22.50 9.55 1.21 260.00 cum

    Lounge & stair 1 10.90 7.50 1.21 98.92 cum

    Atrium 1 10.90 7.50 1.21 98.92 cum

    820.69 cum

    = 821.00 cum

    Project : Vidhayak Awasan at Patna

    MLC Hostel Block

    Sheet No.

    Estimate of Quantities

  • 7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13

    2/27

    SEN & LALL CONSULTANTS PVT. LTD.

    Architects Consultants

    Patna-800 001

    2

    Sl.

    No.Item No. L B H/D Qty. Unit

    3.0 Concrete Work

    3.2 Extra for providing and mixing water

    proofing material 79.56 0.61 1000 970.63 No.

    50 = 979.00 No..

    3.1 P/L PCC (1:3:6) in foundation & plinthBelow pile cap 326.55 0.075 21.29 cum

    1.15

    In basement 29.75 7.25 0.075 16.18 cum

    37.47 cum

    + 101.00 cum

    138.47 cum

    = 139.00 cum

    2 Pile works

    2.1 Boring providing and installation cast in

    situ single under reamed pile

    450 mm dia piles 197 15.90 3132.30 mtr.

    = 3133.00 mtr.3x29 = 87

    4x15 = 60

    5x5 = 25

    6x3 = 18

    7x1 = 7

    197 Nos.

    2.2 Vertical load testing of pile upto 50 tonne 1 1 Nos.

    initial test

    2.3 Vertical load testing of piles

    Routine test 4 4 Nos.

    Providing PCC 1:3:6 under floor in G.F. 571.04 0.10 57.10 cum

    Ref soling

    Seenkn Area upper floor 16.00 31.19 0.45

    32.00 3.50 1.50

    32.00 2.55 2.40

    582.29 0.075 43.67 cum

    100.78

    Say 101.00 cum

    11.76 Providing and filling brick bat khoa 30.0 2.55 2.40 0.385 70.69 cum

    = 71.00 cumPCC (1:2:4) 1.0 7.5 7.50 0.1 5.625 cum

    Under portico = 6.00 cum

    Sheet No.

  • 7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13

    3/27

    SEN & LALL CONSULTANTS PVT. LTD.

    Architects Consultants

    Patna-800 001

    Sheet No. 3

    Sl.

    No.Item No. L B H/D Qty. Unit

    4.3 P/L RCC M20

    4.3.1 All work upto PL

    Pile cap 222 cum

    Column up to PL 31 cum

    Tie Beam 23 cum

    for Basement Basement slab 65 cum 341 cum

    Superstructure

    4.3.2 wall , Column

    Column 220+3.51 cum 224.0

    wall 46+12.43 59.0 283 cum

    4.3.3 Plinth Beam 69.00 cum

    Foor Beam 490.00 cum

    Roof slab 624.00 cum

    Stair 77.00 cum

    Chajja 14.00 cumLintel 12.00 cum

    Band 20.00 cum

    cooking slab 7.00 cum 1313 cum

    1937 cum

    Add RCC M25 instead of M20 1937 cum

    4.0 Reinforced Cement Concrete works

    Shuttering

    4.1.1 Foundations & footings

    Pile cap

    PC1 15 4 2.25 0.90 121.50 sqm

    PC2 29 7.38 - 0.90 192.62 sqm

    PC3 8 5.495 - 0.90 39.56 sqm

    PC4 1 10.08 - 0.90 9.07 sqm

    PC5 2 5.85 - 0.90 10.53 sqm

    PC6 4 6.55 - 0.90 23.58 sqm

    PC7 1 12.78 - 0.90 11.50 sqm

    408.37 sqm

    = 408.0 sqm

    Col. Upto P.L 76 1 1.50 114.0 sqm

    40 0.90 3.60 129.60 sqm

    Tie Beam 1 530.04 1.450 768.56 sqm

    1420.16 sqm

  • 7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13

    4/27

    SEN & LALL CONSULTANTS PVT. LTD.

    Architects Consultants

    Patna-800 001

    Sheet No. 4

    Sl.

    No.Item No. L B H/D Qty. Unit

    4.3 Providing & Laying ---------- RCC M20

    4.3.1 All work upto PL

    Pile Cap

    Pc1 15 2.25 2.25 0.90 68.34 cum

    Pc2 29 2.25 0.57 0.90 33.47 cum

    29 1.385 1.5 0.90 54.22 cumPc3 4 3.245 2.25 0.90 26.28 cum

    Pc4 1 2.25 1.92 0.90 3.89 cum

    1 1.385 1.50 0.90 1.87 cum

    Pc5 1 2.25 3.60 0.90 7.29 cum

    Pc6 2 2.95 3.30 0.90 17.52 cum

    Pc7 1 2.25 3.27 0.90 6.62 cum

    1 1.385 1.50 0.90 1.87 cum

    221.39 cum

    = 222.00 cum

    50 0.30 0.60 1.50 13.50 cum

    Col. Upto Pl. 8 0.40 0.60 1.50 2.88 cumBasement 20 0.30 0.60 4.00 14.40 cum

    30.78 cum

    = 31.00 cum

    Basement Floor slab 1 29.75 7.25 0.30 64.71 cum

    Tie Beam for Basement 1 74.00 0.25 0.60 11.10 cum

    A to I (8x30.30) + (5x29.75) +

    4x7.25+7x7.25+2x29.75 1 456.04 0.25 0.60 68.41 cum

    Outer beam at E.G.L 1 75.00 0.25 0.60 11.25 cum

    RCC Alll work upto PL 90.76 cum

    Pile Cap 222.0

    Col. Up to Pl. 31.0

    Tie Beam 87.00

    Basement floor slab 65.00

    405.0

    4 Reinforcement cement concrete work

    4.3 Providing and laying in position machine

    batched mixed & machine vibrated mixed

    & Machine

    M-20 Concrete

    4.3.15.42.1 All work upto plinth in upto + 1200 mm Lv. Ref. Page

    4.3.2 All work from plinth upto floor V level

    5.42.2.1 walls columns pillar poof and struls

    columns G.F. 8 0.40 0.60 3.50 6.72 cum

    50 0.30 0.60 3.50 31.50 cum

    Ist floor 58 0.30 0.60 3.075 32.10 cum

    2nd & 3rd floor 116 0.30 0.60 3.075 64.21 cum

    4th floor 51 0.30 0.60 3.075 28.23 cum

    Terrace floor 5 0.30 0.60 3.80 3.42 cum

    1 0.30 0.30 3.80 0.34 cum

  • 7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13

    5/27

  • 7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13

    6/27

    SEN & LALL CONSULTANTS PVT. LTD.

    Architects Consultants

    Patna-800 001

    Sheet No. 6

    Sl.

    No.Item No. L B H/D Qty. Unit

    Quantity excluding 1.0 447.19 0.25 0.75 83.85 cum

    slab thickness

    1.0 13.20 0.25 0.60 1.98 cum

    1.0 20.60 0.25 0.60 3.09 cum

    1.0 43.50 0.45 0.60 11.75 cum

    100.66 cumat 2nd flloor lv.

    Add Length of 0.45 x 0.65 beam 1.0 447.19 0.25 0.75 83.85 cum

    1.0 43.50 0.25 0.60 6.53 cum

    Add 2.0 13.20 0.25 0.60 3.96 cum

    1.0 20.60 0.25 0.60 3.09 cum

    97.42 cum

    3rd floor similar 97.43 cum

    4th floor similar 97.43 cum

    5th Terrace floor ducting similar 97.43 cum

    less quantity over area of Terrace of 4th fl.

    Gird E & G 2 6.775Gird F 1 3.95

    Gird H 1 6.90

    Gird I 1 15.075

    Gird I 1 13.20

    Gird II

    1 x 3.50

    Gird 2 1 6.45

    Gird 3 & 4 2 6.90

    72.975 3.50 Mtrs.

    Quanty 1.0 72.975 0.25 0.60 10.95 cum

    1.0 3.50 0.25 0.60 0.53 cum

    76.43 mtrs 85.96 cum

    Machine Room etc. 3 12.30

    3 6.30

    55.80 0.25 0.60 8.37 cum

    OHWT Beams 2.90 cum

    478.91 cum

    RCC column 6.0 0.30 0.60 3.25 3.51 cum

    RCC Wall 19.90 0.25 2.50 12.44 cum

    Top slab 1.0 7.15 2.80 0.15 3.00 cum

    Bottom 1.0 7.15 2.80 0.20 4.00 cum

    RCC Beam 2.0 7.15 0.25 0.60 2.15 cum2.0 2.55 0.25 0.60 0.77 cum

    R.C.C. Columns & Wall (0.81+12.43) 13.24 cum

    RCC. Slab (3.00+4.00) 7.00 cum

    RCC Beam (2.14+0.76) 2.90 cum

    Shuttering

    Column 6 x 2 (0.30+0.60) 3.25 35.10 sqm

    Wall 2.0 7.15 2.50 35.75 sqm

    2.0 2.80 2.50 14.00 sqm

  • 7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13

    7/27

    SEN & LALL CONSULTANTS PVT. LTD.

    Architects Consultants

    Patna-800 001

    Sheet No. 7

    Sl.

    No.Item No. L B H/D Qty. Unit

    Slab 2.0 7.15 2.80 40.04 sqm

    Beam 2.0 7.15 1.45 20.74 sqm

    2.0 2.55 1.45 7.40 sqm

    i) Column shuttering 35.10 sqm 36.00 sqmii) wall shuttering 49.75 sqm 50.00 sqm

    iii) slab shuttering 40.04 sqm 40.00 sqm

    iv) Beam shuttering 28.13 sqm 29.00 sqm

    R / F Column 3.51 cum @ 260.00 kg/ cum 912.60 kg

    wall 12.43 cum @ 80.00 kg/ cum 994.40 kg

    slab 7.0 cum @ 80.00 kg/ cum 560.00 kg

    Beam 2.90 cum @ 160.00 kg/ cum 464.00 kg

    Extra projected Area (15.0+10.75) 1.20 0.15 4.64 sqm

    slab of 1st floor Lv. 1 31.45 31.45 0.15 148.365 sqm

    Less cut outStair at G.I. () 1 3.50 4.075 0.15 2.14 cum

    Single flight() 1 10.05 1.75 0.15 2.64 cum

    cut out () 1 10.05 1.325 0.15 2.00 cum

    cut out D & F () 4 2.45 1.85 0.15 2.72 cum

    Lifts () 2 1.80 1.80 0.15 0.97 cum

    stair at 4/5() 1 5.10 2.80 0.15 2.14 cum

    140.40

    Atrium () 1 10.05 7.575 0.15 11.42 cum

    128.98 cum

    2nd, 3rd & 4th floor similar excluding extra prop. 3 x 124.33 cum 372.99 cum

    Terrace floor Area similar to 1st floor

    1 135.00 31.45 989.10

    Less Area of terrace at 4th floor

    Grid E/I & 1/3 1 15.60 8.10 128.36

    Grid F/I & 3/6 1 7.925 8.95 70.93

    Add 1 2.825 1.85 5.23

    Less Atrium 1 10.05 10.35 104.02

    693.02 sqm

    Quantity 1 693.02 0.15 103.953 cum

    Add Manualy Machine room lift etc. 2.0 2.60 2.60 0.20 2.70 cum

    1.0 11.15 4.825 0.15 8.07 cumTotal slab 616.68 cum

    = 617.0 cum

    Lintel D1 11.0 1.40 0.25 0.65

    at G.F. Only D2 1.0 1.50 0.25 0.15

    D3 7.0 1.30 0.25 0.15

    D4 5.0 2.30 0.25 0.15

    D5 2.0 1.70 0.25 0.15

    W1 5.0 2.00

    W2 6.0 1.50

    5.0 59.90 0.25 0.15 11.23 cum

  • 7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13

    8/27

    SEN & LALL CONSULTANTS PVT. LTD.

    Architects Consultants

    Patna-800 001

    Sheet No. 8

    Sl.

    No.Item No. L B H/D Qty. Unit

    Stair single flight 1 11.0

    1st , 2nd & 3rd 3 10.85

    43.55 1.75 0.175 13.34 cum

    Steps 23 1.75 0.15 0.152 0.92 cum

    60 1.75 0.15 0.152 2.39 cum

    front stair 8 4.33 1.00 0.150 5.20 cum8 1.09 1.00 0.150 1.31 cum

    Steps 23 1.00 0.30 0.152 1.05 cum

    60 1.00 0.30 0.152 2.74 cum

    Rear Stair 2 3.12 1.15 0.15 1.08 cum

    G.F. 2 2.80 1.20 0.15 1.01 cum

    Steps 22 1.15 0.30 0.159 1.21 cum

    1st , 2nd & 3rd floor 6 3.12 1.15 0.15 3.23 cum

    6 2.80 1.20 0.15 3.02 cum

    57 1.15 0.15 0.153 1.50 cum

    37.99 cum

    For 2 Nos. 2 x 38.03 76.16 cum

    = 77.00 cumRCC slab in cooking platform 1 103.20 0.60 0.10 6.19 cum

    = 7.00 cum

    Chajja wather shell at G.F. D1 2 0.90 + 0.50

    D5 2 1.20 + 0.50

    W1 5 1.20 + 0.50

    W2 6 1.00 + 0.50

    25.20 0.85 0.10 2.14 cum

    window sill

    G.F. W 1 & W2 19.00 0.85 0.10 1.62 cum

    1st , 2nd & 3rd floor

    W3 12x3x2.10+0.50

    W4 4x3x0.90+0.50

    4th floor w3 9x1x2.10+0.50

    W4 4x1x0.90+0.50

    139.00 0.85 0.10 11.82 cum

    15.57 cum

    = 15.00 cum

    Add Railing for Balcony front 4 rear 24 2.10 0.125 0.30 1.89 cum

    6 2.10 0.125 0.30 0.47 cum

    6 8.725 0.125 0.30 1.96 cum

    1 8.725 0.125 0.30 0.33 cum

    Atrium & concrete 8 17.625 0.125 0.30 5.29 cum

    8 11.375 0.125 0.30 3.41 cumAtrium at Terrace 2 20.14 0.125 0.30 1.51 cum

    14.86 cum

    Parapet Band 4 x 31.45 x 0.25 x 0.10 3.14

    Surrounded Atr. (11.25+10.90) X 0.25 X 0.10 1.11 cum

    19.11 cum

    = 20.00 cum

    4.1 Centering and shutering including etc. for OHWT 50.00

    5.14

  • 7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13

    9/27

    SEN & LALL CONSULTANTS PVT. LTD.

    Architects Consultants

    Patna-800 001

    Sheet No. 9

    Sl.

    No.Item No. L B H/D Qty. Unit

    4.1.2 walls of any thickness 5 x 2 (2.60 + 0.25) 16.35 465.97 sqm

    5 x 2 (2.60 + 0.25) 4.20 119.70 sqm

    Basement 4.0 30.275 2.40 290.64 sqm

    4.0 7.75 2.40 74.40 sqm

    1000.71 sqm

    4.1.3 suspended floor, Roofs Landingbalconies etc. at 1st floor Lv.

    () 1.0 30.35 30.35 - 921.123 sqm

    (stair ) Less cut outs

    () 1.0 3.5 4.075 - 14.26 sqm

    Stair single flight outs () 1.0 10.05 1.75 - 17.59 sqm

    cut outs () 1.0 10.05 1.325 - 13.32 sqm

    cut outs at D & F () 4.0 2.45 1.85 - 18.13 sqm

    Lift () 2.0 1.80 1.8 - 6.48 sqm

    Stair at 4/5 () 1.0 5.10 2.80 - 14.28 sqm

    Atrium () 1.0 10.05 7.575 - 76.13 sqm

    760.94 sqm

    at 2nd , 3rd & 4th floor similar 3.0 756.83 2269.89 sqm

    at Terrace floor 756.83 sqm

    similar

    Less Terrace Below () 1.0 15.00 7.38 - 110.70 sqm

    () 1.0 7.40 7.50 - 55.50 sqm

    590.63 sqm

    Machine Room 2.0 2.10 2.10 - 8.82 sqm

    1.0 11.15 4.83 - 53.80 sqm

    62.62 sqm

    Less area of beam bottom 3684.08 sqm

    Less area of beam bottom () (447.10 +13.20+10.30) 0.25 117.67 sqm

    () 1 43.50 0.45 19.58 sqm

    2nd , 3rd & 4th floor () 3 514.19 0.25 385.64 sqm

    Terrace floor 1 (514.19 76.43) 0.25 109.44 sqm

    Machine Room etc. 1 55.80 0.25 13.95 sqm

    3037.80 sqm

    Basement roof slab at Gr. Floor 1 29.75 7.25 215.69 sqm

    3253.49 sqm

    For OHWT 40.00 sqm3293.49 sqm

    5.14.5 Shuttering for Beams & Lintels

    Beams 1st floor 1 447.19 1.75 - 782.58 sqm

    1 13.20 1.45 - 19.14 sqm

    1 20.60 1.45 - 29.87 sqm

    1 43.50 1.45 - 63.08 sqm

    894.67 sqm

    Total all floors

  • 7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13

    10/27

    SEN & LALL CONSULTANTS PVT. LTD.

    Architects Consultants

    Patna-800 001

    Sheet No. 10

    Sl.

    No.Item No. L B H/D Qty. Unit

    447.19 + (43.5013.20) 1 447.19 1.75 - 782.58 sqm

    1 43.50 1.45 - 63.08 sqm

    2 13.20 1.45 - 38.28 sqm

    1 20.60 1.45 - 29.87 sqm

    913.81 sqm

    3rd & 4th floor similar 2 x 913.81 1827.62 sqm

    Terrace floor similar 913.81 sqm

    Less

    Less () 1 72.925 1.45 - 105.74 sqm

    () 1 3.50 1.45 - 5.08 sqm

    802.99 sqm

    Add for OHWT 29.00 sqm

    3 18.60 1.45 - 80.91 sqm

    4549.00 sqm

    Add lintels 1 40.90 0.55 - 22.50 sqm

    Add tie Beam for up to Pl 768.56 sqm

    5340.05 sqm

    5.14.6 Shuttering for column for O.H.W.T 36.00 sqm

    Pilled etc

    G.F 8 x 2 (0.40+0.60) 3.50 56.00 sqm

    50 x 2 (0.30+0.60) 3.50 315.00 sqm

    1st , 2nd & 3rd floor 3x58x2 (0.30+0.60) 3.075 963.09 sqm

    4th floor 51x2 (0.30+0.60) 3.075 282.290 sqm

    Terrace floor 5 x 2 (0.30+0.60) 380.0 34.204 sqm

    1 x 2 (0.30+0.30) 380.0 4.56 sqm

    Add upto Pl. 250.08 sqm

    1941.22 sqm

    = 1942.00 sqm

    5.14.7 Suttering for stair with sides

    (for all floor) single flight 1 43.55 (0.175+0.75+0.175) 91.46 sqm

    corners 0.5x2x (23+(3x20) 0.30 0.152 3.78 sqm

    Steps 83.0 1.75 0.152 22.08 sqm

    front stair 8.0 4.33 1.30 45.03 sqm

    8.0 1.09 1.30 11.34 sqm

    coners 2x83 .30 x .50 0.152 3.78 sqm

    Steps 83 1.00 0.152 12.62 sqm

    Rear stair 8.0 3.12 1.45 36.19 sqm8.0 2.80 1.50 33.60 sqm

    corners 2x82 0.30x.50 0.152 3.74 sqm

    Steps 82 1.15 0.152 14.33 sqm

    277.95 sqm

    = 278.00 sqm

    5.14.20 wheather shade chajja, etc prop. From

    beam bolter 1 (15.0+10.75) (1.20+0.15 34.76 sqm

    Extra proj 1st floor only

    Proj at 1st, 2nd , 3rd & 4th flloor 4x2 (31.45+0.15+0.15) (0.725+0.15) 222.25 sqm

    4x2 (30.00 x 0.725+0.15) (0.725+0.15) 210.0 sqm

  • 7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13

    11/27

    SEN & LALL CONSULTANTS PVT. LTD.

    Architects Consultants

    Patna-800 001

    Sheet No. 11

    Sl.

    No.Item No. L B H/D Qty. Unit

    Chajja at G.F.

    D3 2.0 (0.90+0.20) (0.70+0.10) 1.760 sqm

    D5 2.0 (1.20+0.20) (0.70+0.10) 2.240 sqm

    W1 5.0 (1.50+0.20) (0.70+0.10) 6.80 sqm

    W2 6.0 (1.0 + 0.20) (0.70+0.10) 5.76 sqm

    Add sill 1.0 139.4 1.05 146.37 sqm629.94 sqm

    = 630.00 sqm

    5.14.11 Edges of slab and breaks at first floor

    stair cut out /Atrium

    6.0 10.05 60.30 mtrs.

    2.0 (7.575+1.325) 17.80 mtrs.

    Lift 8.0 1.80 14.40 mtrs.

    Tlt Duct 4 x 2 (2.45 + 1.85) 34.40 mtrs.

    Fire Duct 2.0 (1.80 + 0.80) 5.20 mtrs.

    Fire Duct 2.0 (2.175 + 0.80) 2.98 mtrs.

    Elect duct 2.0 (2.20+ 0.80) 6.00 mtrs.

    2.0 (1.45+ 0.80) 4.50 mtrs.145.58 mtrs.

    B.F. 145.58 mtrs.

    2nd and 3rd & 4th floor similar 3x 145.58 436.74 mtrs.

    Terrace floor similar 145.58

    Add 1.0 7.5 7.50

    1.0 9.2 9.20

    162.28 mtrs.

    Add machine

    Lift 2 x 4 2.60 20.80 mtrs.

    2.0 (11.15 + 4.828) 31.96 mtrs.

    Total 797.36

    = 800.0 mtrs.

    Facia , fins 1 396.40 (0.30+0.125+0.30) 287.31 sqm

    = 287.00 sqm

    Shelves 1.0 103.20 0.60 61.92 sqm

    = 62.00 sqm

    R/F Steel in foundation & Plinth

    In Pile 499.0 cum @ 100.00 kg / cum 49.90 MT

    Pile Cap 222.0 cum @ 120.00 kg / cum 26.64 MT

    Column up to pl 31.0 cum @ 260.00 kg / cum 8.06 MT

    Tie beam 23.0 cum @ 180.00 kg / cum 4.14 MT

    floor slab 65.0 cum @ 80.00 kg / cum 5.20 MT93.94 Mt

  • 7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13

    12/27

    SEN & LALL CONSULTANTS PVT. LTD.

    Architects Consultants

    Patna-800 001

    Sheet No. 12

    Sl.

    No.Item No. L B H/D Qty. Unit

    B. F 93.94 M.T.

    Providing Re imforcement to RCC works Fnd

    columns & walls super struct 283.00 cum @ 260.0 kg / cum 73.58 M.T.

    beams P.B Roof beams 559.00 cum @ 200.0 kg / cum 111.80 M.T.

    slab for basement slab for roofs 624.00 cum @ 80.0 kg / cum 49.92 M.T.

    Lintels cooking slab 12.00 cum @ 140.0 kg / cum 1.68 M.T.

    stair in beam from G.F. Above 7.00 cum @ 80.0 kg / cum 0.56 M.T.

    77.00 cum @ 200.0 kg / cum 15.40 M.T.

    Chajja & Sill 14.00 cum @ 80.0 kg / cum 1.12 M.T.

    facia railing & Beam 20.00 cum @ 140.0 kg / cum 2.80 M.T.

    350.80

    = 317.50

    = 351 M.T.

    8 mm dia 55

    10 mm dia 65

    12 mm dia 60

    16 mm dia 65

    20 mm dia 50

    25 mm dia 50

    32 mm dia 6

    5.1 Brick work in C.M (1:6) in foundation & Plinth

    Basement

    above RCC Outer wall 2 (7.50 + 29.975) x 0.25 x .60 11.24 cum

    Ht : (1.20 0.60) = 0.60

    Internal portion 1.00 7.50 0.25 3.40 6.38 cum

    1.00 5.35 0.25 3.40 4.55 cum

    Lift 3.00 2.10 0.25 3.40 5.36 cum

    1.00 3.05 0.25 3.40 2.59 cum

    gr. Floor F. gl to pl

    Ht. : 1.20-0.60-0.10 = 0.50 1.00 453.95 0.25 0.50 56.74 cum

    86.85 cum

    = 87.0 cum

    Total Brick work in foundation & plinth (87 + 627) 714.0 cum

    9.1 Providing 100 A Brick flat soling .. all comp

    Below foundation 326.55 283.95 sqm

    1.15

    Below in Basement floor 1.00 29.75 7.25 215.69 sqm

    499.638 sqm

    = 500.00 sqm

    from item no. 8.1 flooring 671.00 sqm

    Total 1171.00 sqm

  • 7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13

    13/27

    SEN & LALL CONSULTANTS PVT. LTD.

    Architects Consultants

    Patna-800 001

    Sheet No. 13

    Sl.

    No.Item No. L B H/D Qty. Unit

    Brick masonry in super structural

    G.F. Gr. 1 1.00 24.18 0.25 3.65 22.06 cum

    1.00 21.38 0.25 3.20 17.10 cum

    Gr. 3 1.00 6.75 0.25 3.20 5.40 cum

    Gr. 4 1.00 3.15 0.25 3.20 2.52 cum

    Lift 2.00 2.10 0.25 3.50 3.68 cumGr. 5 1.00 2.15 0.25 3.20 1.72 cum

    stair Gr. 6 1.00 5.95 0.25 3.20 4.76 cum

    stair Gr. 7 1.00 10.16 0.25 3.20 8.13 cum

    stair Gr. 8 1.00 12.03 0.25 3.20 9.62 cum

    stair Gr. 10 1.00 13.15 0.25 3.20 10.52 cum

    1.00 15.60 0.25 3.65 14.24 cum

    Grid J 1.00 3.50 0.25 3.20 2.80 cum

    1.00 3.75 0.25 3.65 3.42 cum

    Grid G 1.00 3.50 0.25 3.20 2.80 cum

    Grid F 1.00 1.80 0.25 3.20 1.44 cum

    Grid E 1.00 6.75 0.25 3.20 5.40 cum

    1.00 8.48 0.25 3.20 6.78 cumGrid D 1.00 10.25 0.25 3.20 8.20 cum

    Lift 1.00 2.10 0.25 3.20 1.68 cum

    Grid C 1.00 10.55 0.25 3.20 8.44 cum

    Grid A 1.00 26.95 0.25 3.20 21.56 cum

    1.00 26.15 0.25 3.65 23.86 cum

    186.14 cum

    side walls Add of Door & windows 28.00 0.35 0.25 3.65 8.94 cum

    195.08 cum

    Less openings D5 () 6.00 1.20 0.25 2.40 4.32 cum

    W1 () 12.00 1.50 0.25 1.50 6.75 cum

    W2 () 12.00 1.00 0.25 1.00 3.00 cum

    Net 181.01 cum

    1st floor

    Grid 1 off Grid 1 & 10 2.0 31.20

    on Grid 1 & 10 2.0 26.100

    Grid 11

    91

    4 x 2 3.75

    Ducts 2 x 2 1.65

    Grid 3 & 8 2.0 26.10

    Grid 4 1 12.125

    Lift line 1 4.325

    Libe 1.0 2.10

    Grid 5 1 1.975

    Grid 6 1 6.48

    On Grid Grid A 1 19.98

    Off Grid Grid A 1.0 31.10

  • 7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13

    14/27

    SEN & LALL CONSULTANTS PVT. LTD.

    Architects Consultants

    Patna-800 001

    Sheet No. 14

    Sl.

    No.Item No. L B H/D Qty. Unit

    Grid B 1 3.90

    grid C 1 5.10 + 1.20

    Lift / Duct 1 (2.10 + 1.05)

    Grid D 1 14.05

    Grid E 2 6.73

    Grid F (2x3.90) + 1.20

    Grid G 1 3.50

    Grid H 1 6.30

    On End - Grid I 1 18.30

    Off Grid end I 1 31.10

    Prog 58 0.35

    Total length 265.96 145.10 m

    Quantity 1.00 265.96 0.25 2.475 164.56 cum

    1.00 145.10 0.25 2.975 107.92 cum

    272.48 cum

    Less Openings B.F 272.48 cum

    D1() 8 0.9 0.25 2.40 4.32 cum

    D5() 4 1.20 0.25 2.40 2.88 cum

    D4() 2 1.80 0.25 2.40 2.16 cum

    W3() 24 2.10 0.25 2.10 26.46 cum

    W4() 8 0.90 0.25 0.90 1.62 cum

    Balcony() 1+1 (7.82+6.60) 0.25 2.10 7.57 cum

    Net 227.47 cum

    2nd and 3rd floor similar 2 227.96 455.92 cum

    4th floor

    similar Less (Terrace area) 227.47 cum

    Grid -1 .1/2 31.22

    .1/2 26.10

    Grid -11 2 3.75Grid 4 .1/2 12.10

    Grid F 1.0 3.90

    Grid H 1.0 6.30

    on Grid I .1/2 18.30

    of Grid I 1.0 17.30

    45.95 32.31

    () 1 45.95 0.25 2.48 28.43 cum

    () 1 31.31 0.25 (2.9751.40) 12.33 cum

    186.71 cum

  • 7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13

    15/27

    SEN & LALL CONSULTANTS PVT. LTD.

    Architects Consultants

    Patna-800 001

    Sheet No. 15

    Sl.

    No.Item No. L B H/D Qty. Unit

    B.F 52.20 cum

    Add D 2 0.90 0.25 2.40 1.08 cum

    W3 6 2.10 0.25 2.10 6.62 cum

    W4 2 0.90 0.25 0.90 0.41 cum

    Bal 1 2.20 0.25 2.10 1.16 cum

    61.46 cumAdd for high

    per carpet Ref elevation 1.0 (15.61+7.30) 0.25x3.075 25.30 cum

    86.76 cum

    Parapet at Terrace for and of maching Rcc 2x(31.20+31.10) x 0.25 x 1.65 51.40 cum

    Machine Room 2x (9.60+5.80) 0.25 x 3.80 28.50 cum

    Add duct 4x2 (2.70+2.10) 0.25 x 1.20 11.52 cum

    91.42 cum

    Total All Floor 170.12 + (3x92.96) + 86.94 + 91.42 627.36 cum

    say 627.00 cum

    6.18A Half brick masonary with brick of class

    designation class 100 in foundation and

    plinth Refer foundationwork page

    6.19 A Extra for Half brick masonry in super

    structure above plinth upto floor V level

    G.F Grid 1.0 10.71

    Tlt 1.0 2.40

    Grid 3 1.0 6.55

    Stair V 41 1.0 1.00 4.13

    Stair lobby on supplying / stair 2.0 2.925

    Duct 2.0 1.60

    Kit 1.0 1.50

    Grid B Plth 1.0 1.80

    sloves etc 1.0 9.30

    Store / Manage 1.0 6.97

    Corridor 1.0 1.80

    Duct 2x4 2.45

    Gents plth 1.0 7.25

    Dvos 2.0 1.00

    small walls

    in stair lobby 1.0 (2.50+1.90)2586 63.61

    Quantity 1.0 23.86 2.90 60.19 sqm

    1.0 63.61 3.35 213.09 sqm

    Low hight walls for GL 1.0 (17.0+15.525) 0.30 9.76 sqm

    292.14 sqm

    Less opening D1 () 4.0 0.90 2.40 8.64 sqm

    D() 2.0 1.00 2.40 4.80 sqm

    D3() 8.0 0.80 2.40 15.36 sqm

    263.34 sqm

  • 7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13

    16/27

    SEN & LALL CONSULTANTS PVT. LTD.

    Architects Consultants

    Patna-800 001

    Sheet No. 16

    Sl.

    No.Item No. L B H/D Qty. Unit

    Gr. Floor

    Grid 21

    Grid 81

    Plth 8.0 2.825 2.625 59.325 sqm

    Kit 8.0 2.825 2.925 66.105 sqm

    Security Toilet 1.0 3.175 2.925 9.287 sqm

    Security 1.0 5.625 2.475 13.922 sqmDucts in Lobby 2.0 2.80 2.925 16.380 sqm

    Atrium , stair, Duct 5.0 10.175 0.30 15.26 sqm

    2.0 8.90 0.30 5.34 sqm

    Bed rooms Horiz 8.0 6.85 2.475 135.63 sqm

    Duct 8.0 2.575 2.475 50.99 sqm

    Tlt Proj 8.0 1.00 2.475 19.80 sqm

    Dss effors Lobby 2.0 2.975 2.475 14.73 sqm

    406.76 sqm

    Less Doors etc.

    D1() 9.0 0.90 2.40 19.44 sqm

    D3() 9.0 0.80 2.40 17.28 sqm

    D4() 8.0 1.80 2.40 34.56 sqmW4() 16.0 0.90 0.90 12.96 sqm

    322.52 sqm

    Net 2 x 328.76 sqm

    2nd & 3rd floor similar

    4th floor similar 328.76 sqm

    Less () 2.0 2.825 2.625 14.83 sqm

    2.0 2.825 2.925 16.53 sqm

    2.0 6.85 2.475 33.91 sqm

    2.0 1.00 2.475 4.95 sqm

    258.55 sqm

    B.F. 258.54 cum

    Add 2.0 0.90 2.40 4.32 sqm

    2.0 0.80 2.40 3.84 sqm

    2.0 1.80 2.40 8.64 sqm

    4.0 0.90 0.90 3.24 sqm

    278.58 sqm

    Tolet for all floor 263.14 +( 3x328.76) + 278.58 1528.00 sqm

  • 7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13

    17/27

    SEN & LALL CONSULTANTS PVT. LTD.

    Architects Consultants

    Patna-800 001

    Sheet No. 17

    Sl.

    No.Item No. L B H/D Qty. Unit

    Doors & Window Basement G.F.

    type floor

    Ist, 2nd,

    3rd

    4th floor

    & Terrace Total

    9.24.2 D1 4.00 3x17 1x13 68.00 Nos.

    9.25.2 D18 1.0 8.00 9.00 Nos.D1b 2.00 2.00 Nos.

    9.25.2 D2 2.00 2.00 Nos.

    9.25.2 D3 3x10 1x8 34.00 Nos.

    D3a 1.0 3.00 4.00 Nos.

    D4a 1.00 1.00 Nos.

    D4b 3x2 2 8.00 Nos.

    D5 1.0 4.00 3x2 2 13.00 cess

    D6 3x8 1x6 30.00 Nos.

    D7 3x11 1x7 40.00 Nos.

    D8 3x2 1x2 8.00 Nos.

    Dw1 1.00 3x1 4.00 Nos.

    W1a 3.00 3.00

    W1b 2.00 5.00

    W2 6.00 6.00

    W3a 3x4 1x3 15.00

    W3b 3x4 1x3 15.00

    w4 3x4 1x4 16.00

    W5 a 3x2 1x1 7.00

    W5b 3x2 1x1 7.00

    Wb 3x17 1x13 64.00

    9.24 Flush doors shutter decorative type

    9.24.2 35 mm thick

    D1 68 0.83 2.065 116.549 sqm

    D8 8 1.465 2.065 24.20 sqm140.75 sqm

    = 141.00 sqm

    9.25 25 mm thick flush door D1a 9 0.83 2.065 15.43 sqm

    9.25.2 non decorative

    D2 2 0.83 2.065 3.43 sqm

    D3 4 0.73 2.065 6.03 sqm

    D3a 38 0.73 2.065 57.28 sqm

    82.17 sqm

    Say 82.00 sqm

    5.26 Extra for providing and fixing flush door

    with teak veneerin one sliding5.26.1

    D3 4 0.73 2.065 6.03 sqm

    Say 6.00 sqm

    DSR Extra for Lamination

    D1a 18 0.83 2.065 30.85 sqm

    D2 4 0.83 2.065 6.86 sqm

    D3 4 1.465 2.065 12.10 sqm

    D3a 76 0.73 2.065 114.57 sqm

    164.37 sqm

    say 164.00 sqm

  • 7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13

    18/27

    SEN & LALL CONSULTANTS PVT. LTD.

    Architects Consultants

    Patna-800 001

    Sheet No. 18

    Sl.

    No.Item No. L B H/D Qty. Unit

    DSR Fire retarduct door

    D5 13 1.135 2.295 33.86 sqm

    say 34.00 sqm

    9.1 Providing wood work intrens of door wind

    2nd class teak wood

    9.1.3for DW1

    Ver 4x4 2.40

    Hor 4x2 6.65

    Ver 4x2 2.10

    bolt Hor 4x2 2.625

    129.40

    Quantity 1.0 129.40 0.15 0.075 1.46 cum

    9.6 Providing and fixing glazed shutter for

    door

    9.6.3.4 35 mm thick 2nd class teak wood D4 1.0 1.73 2.065 3.57 sqm

    for DW1 4.0 1.73 2.065 14.29 sqm

    17.86

    say 19.00 sqm

    9.35 Extra for providing vision panel

    9.35.1 Rectangular providing vision panel 2.0 0.80 2.065 3.30 sqm

    In D2

    9.61 Providing and fixing wooden moulded

    beading

    9.61.1.1 Teak wood 50x12 mm

    D1 D1a 77.0 (2x2.40)+ 0.90 438.90 Mtrs.

    D2 4.0 (2x2.40)+ 0.90 22.80 Mtrs.

    D3 + D3a 38 (2x2.40)+ 0.80 212.80 Mtrs.

    674.50 Mtrs.

    B.F 674.50 Mtrs.

    D4a 1.0 (2x2.40)+ 1.80 6.60 Mtrs.

    D5 13.0 (2x2.40)+ 1.20 78.10 Mtrs.

    D8 8.0 (3x2.40)+ 1.50 50.40 Mtrs.

    Dw1 4.0 (2x2.40)+ 6.65 45.80 Mtrs.

    for Glazing (2x6.65)+ (8x0.23)+ (8x2.10) 51.38 Mtrs.

    .+(8x2.43)

    906.78 Mtrs.Say 907.0 mtrs.

    9.34 Extra for providing lipping with 2nd edges

    of shutters

    140.75 + 82.17 222.92 sqm

    Say 223.00 sqm

  • 7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13

    19/27

    SEN & LALL CONSULTANTS PVT. LTD.

    Architects Consultants

    Patna-800 001

    Sheet No. 19

    Sl.

    No.Item No. L B H/D Qty. Unit

    9.218 Providing and fixing Al sliding door bolts

    300x16 mm

    D1a 9

    D2 2

    D3a 4

    D1 68

    D4a 1D5 13

    D8 8

    105 Nos.

    250 x 16 m

    D3 34 Nos.

    9.219 Providing and fixing Alm Tower bolts

    300x10mm 151 Nos. 151 Nos.

    150x 10mm 2x151 Nos. 302 Nos.

    9.22 Providing and fixing Alm Handle

    9.222.1 125mm 151x2 302 sqm

    9.139 Providing and fixing bright finished brass

    mostice lock

    in D why 68 Nos.

    9.73 A Providing and fixing 18 mm thick 150 mm

    wood

    D1 68 1.50

    D7 40 2.70

    W1a 3 2.10

    W1b 2 2.10

    W2 6 2.70

    W3a 15 2.70

    W3b 15 1.50

    W4 16 2.70

    W5 0/b 14 7.25

    Glazing GL2 7 10.68

    GL3 1 16.80

    GL4 1 16.80

    451.13 0.15 67.67 sqm

    say 68.00 sqm

    9.74 B Providing and fixing teak wood leping for

    palmet

    25x3m 451.00 451

    DSR Providing and fixing Alm / UPVC Doors

    window/ glazingD1b 2.0 1.50 2.40 7.20 sqm

    D4b 8.0 1.80 2.40 34.56 sqm

    Db 30.0 1.50 2.40 108.00 sqm

    D7 40.0 2.10 2.40 201.60 sqm

    W1a/b 5.0 1.50 1.50 11.25 sqm

    W2 6.0 1.00 1.00 6.00 sqm

    w3 a/b 30.0 2.10 2.10 132.30 sqm

    W4 16.0 0.90 0.90 12.96 sqm

    W5 a/b 14.0 2.10 2.10 61.74 sqm

    wb 64.0 0.60 1.20 46.08 sqm

    621.69 sqm

    say 618.00 sqm

  • 7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13

    20/27

    SEN & LALL CONSULTANTS PVT. LTD.

    Architects Consultants

    Patna-800 001

    Sheet No. 20

    Sl.

    No.Item No. L B H/D Qty. Unit

    24.3 Providing and fixing glazing

    24.3.2 with glass pan of 5.50 mm Doors & window 618.00 sqm

    Fixed glazing 124.95 sqm

    Doors high 30.00 sqm

    Glazing in DW 49.00 sqm821.95 sqm

    say 822.00 sqm

    UPVC / Alm

    Providing and fixing fixed glazing

    Gl - 2 1.0 6.65 2.825 18.79 sqm

    Gl - 3 1.0 10.75 2.825 30.37 sqm

    Gl -4 1.0 16.20 2.825 45.77 sqm

    Gl - 5a 1.0 3.47 2.40 8.33 sqm

    Gl-b 1.0 4.375 2.10 9.19 sqm

    Gl-7 1.0 5.95 2.10 12.50 sqm

    124.93 sqm

    Steel works

    9.4 Steel work in built up tubular truken

    M.S stair at terrace Approx wt 900.00 kg

    10.15 Providing and fixing press steel door fram

    D1 68.0 (2x2.40)+ (3x0.90) 510.00 Mtr.

    D1a 9.0 (2x2.40)+ (3x0.90) 67.50 Mtr.

    D2 2.0 (2x2.40)+ (3x0.90) 15.00 Mtr.

    D3 34.0 (2x2.40)+ (3x0.80) 244.80 Mtr.

    D3a 4.0 (2x2.40)+ (3x0.80) 28.80 Mtr.

    D4a 1.0 (2x2.40)+ (3x1.80) 10.20 Mtr.

    D8 8.0 (2x2.40)+ (3x1.50) 74.40 Mtr.

    691.20 950.70 Mtr.

    Say 951.00 Mtr.

    10.21 Providing and fixing circular CI ceiling fan

    box

    G.F 24 Nos.

    Basement 10 Nos.

    Ver, 2nd , brd floor 3x38 Nos.

    4th floor 1x 30 Nos.Machine 2.0 Nos.

    180 Nos.

    10.32 Steel work welded in built up see in railing

    balcony Atrium (Length similar to cond railing )

    1.0 396.40 0.900 356.76 sqm

    = 356.00 sqm

  • 7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13

    21/27

    SEN & LALL CONSULTANTS PVT. LTD.

    Architects Consultants

    Patna-800 001

    Sheet No. 21

    Sl.

    No.Item No. L B H/D Qty. Unit

    B.F. 356.76 sqm

    B.F. 396.40

    for stair railing

    Rear stair 5 8.16 1.20 48.96 sqm

    froml stair 4 8.16 1.20 39.17 sqm

    singh flight 8 8.68 1.20 83.33 sqm

    839.28 mtrs. 528.216 sqm

    . @27 kg/sqm 14261.94 kg

    Add for M.S. stair at terrace roof Approx 200.00

    14461.94

    = 14500.00

    Grill for window

    w1a 3.0 1.50 1.50 6.75 sqm

    w1b 2.0 1.50 1.50 4.50 sqm

    w2 6.0 1.00 1.00 6.00 sqm

    w3a 15.0 2.10 2.10 66.15 sqm

    w3b 15.0 2.10 2.10 66.15 sqm

    w4 16.0 0.90 0.90 12.96 sqmw5a 7.0 2.10 2.10 30.87 sqm

    w5b 7.0 2.10 2.10 30.87 sqm

    wb 54.0 0.60 1.20 38.88 sqm

    263.13 sqm

    . @15 kg/sqm 3841.95 sqm

    = 3842.00 sqm

    Structural steel 1.0 23.18 . @10.8 kg/sqm 250.34

    2.0 3.0 . @4.5 kg/sqm 27.00

    277.34x3 832kg

    2x4 12.40 . @91.2 kg/sqm 675.00

    1507

    10.33 Providing and fixing hand rail

    M.S. tube 40 mm per length ref

    10.32 . @3.61 kg/sqm 1946.80

    Say 1947.0 kg

    Flooring Below Pile cap 326.95 283.95 sqm

    1.15

    In Beams 29.75 7.25 215.688 sqm

    11.72 Providing dea main 100A flat bridge

    solings of E/I and direction 1.0 29.75 22.25 661.94 sqm

    1.0 3.50 2.60 9.10 sqm

    1170.68 sqm

    11.29

    Pre cast terrazo tiles 22 mm thick with

    marble chips = 1171.0 Nos.

    11.29.1

    bed of cement mortar 1:4 light shade

    noing white wash

    G.F. Administ 1.0 8.075 4.625 37.35 sqm

    Ist floor, seing 1.0 5.62 4.30 24.17 sqm

    Bal 1.0 7.60 2.35 17.86 sqm

    2nd , 3rd & 4th floor

    similar as marked 3.0 (24.21+17.86) sqm 126.21 sqm

    205.58 sqm

    say 206 sqm

  • 7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13

    22/27

    SEN & LALL CONSULTANTS PVT. LTD.

    Architects Consultants

    Patna-800 001

    Sheet No. 22

    Sl.

    No.Item No. L B H/D Qty. Unit

    11.31 Precast terrazo tiles 22mm thick with

    marble chips hubbing and polishing

    complete

    11.31.1 Light shade and white

    G.F. 2 (8.075+4.625) 0.125 3.18 sqmIst floor 2 (5.63+4.30) 0.125 2.48 sqm

    2 (7.60+2.35) 0.125 2.49 sqm

    2nd , 3rd & 4th floor

    similar as marked 3 (2.48+2.49) 14.91 sqm

    23.06 sqm

    say 23.00 sqm

    P/L Granite in wall Lift Lobby 10 2.50 3.0 75.00 sqm

    2 2.50 4.0 20.00 sqm

    95.00 sqm

    P/L Granite in Kitchen slab 1 19.20 0.75 14.40 sqm

    8 2.80 0.75 16.80 sqm8 2.80 0.75 16.80 sqm

    8 2.80 0.75 16.80 sqm

    6 2.80 0.75 12.60 sqm

    77.40 sqm

    = 78.00 sqm

    Extra for edge moulding 1 103.20 103.20 m

    = 104.00 m

    8.12.1 Providing and laying vitrified floor tiles

    figment etc. complete (8x3)+6 5.50 3.50 577.50 sqm

    All floor living in flooring & bed (8x3)+6 4.50 3.62 488.70 sqm

    1066.20 sqm

    in skirting (8x3) + 6) x2 (5.50+3.50) 0.125 67.50 sqm

    (8x3) + 6) x2 (4.50+3.62) 0.125 60.90 sqm

    128.40 sqm

    = 129.00 sqm

    11.40 Providing and laying ceramic glazed floor

    tiles 400x 400 maching pigment etc.

    complete

    was skid type

    G.F Main Tlt 1.0 7.25 3.50 25.38 sqm

    1.0 7.25 2.675 19.39 sqm

    shift toilet 1.0 2.925 2.575 7.53 sqm

    1.0 1.90 1.80 3.42 sqm

    Ist , 2nd & 3rd floor 24.0 2.80 1.00 67.20 sqm

    24.0 2.10 0.50 25.20 sqm

    Security 3.0 2.30 1.35 9.32 sqm

    4th floor 6.0 2.80 1.00 16.80 sqm

    6.0 2.10 0.50 6.30 sqm

    1.0 2.30 1.35 3.11 sqm

    183.64 sqm

    = 184.00 sqm

  • 7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13

    23/27

    SEN & LALL CONSULTANTS PVT. LTD.

    Architects Consultants

    Patna-800 001

    Sheet No. 23

    Sl.

    No.Item No. L B H/D Qty. Unit

    8.6 Ceramic glazed tiles in walls

    GF Kitchen

    2(11.7+7.5) =38.40 1.0 38.40 1.50 57.60 sqm

    above coking platform 1.0 19.20 0.75 14.40 sqm

    Ist floor

    2(1.5+2.80)=8.6 8.0 8.6 1.50 103.20 sqm

    8.0 2.8 0.75 16.80 sqm

    2nd floor

    8.0 8.6 1.50 103.20 sqm

    8.0 2.8 0.75 16.80 sqm

    3rd floor

    8.0 8.6 1.50 103.20 sqm

    8.0 2.8 0.75 16.80 sqm

    4th floor

    6.0 8.6 1.50 77.40 sqm

    6.0 2.8 0.75 12.60 sqm

    522.00 sqm

    11.36 Providing and fixing Ist quality ceramic

    glazed wall tiles in skirting

    G.F 2 (7.25+3.50) 2.10 45.15 sqm

    WC 4x2 (1.50+1.12) 2.10 44.02 sqm

    2 (7.25+2.675) 2.10 41.69 sqm

    2x2 (1.12+1.28) 2.10 20.16 sqm

    2 (2.925+2.575) 2.10 23.10 sqm

    2 (1.12+1.28) 2.10 10.08 sqm

    2 (1.90+1.80) 2.10 15.54 sqm

    2 (1.80+0.90) 2.10 11.34 sqm

    Ist, 2nd, 3rd & 4th floor 30x2 (2.80+1.50) 2.10 541.80 sqm

    Security 4x2 (2.30+1.35) 2.10 57.96 sqm

    810.84 sqm

    1332.84 sqm

    = 1334.00 sqm

    11.42 Marble stone flooring with 18 mm thick

    marble stone Ent reception Launge corridor &

    11.42.7.2 Rajnagar plain white marble 18 mm 1.0 17.15 7.50 128.63 sqm

    0.20 to 0.50 sqm 1.0 4.50 2.50 11.25 sqm

    1.0 7.50 2.75 20.63 sqm

    1.0 15.00 15.00 225.00 sqm

    385.50

    Ist floor corridor 2.0 30.75 1.925 118.39 sqm

    1.0 12.95 4.455 57.69 sqm

    1.0 6.90 5.75 39.68 sqm

    1.0 7.15 2.35 16.80 sqm

    232.56

  • 7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13

    24/27

    SEN & LALL CONSULTANTS PVT. LTD.

    Architects Consultants

    Patna-800 001

    Sheet No. 24

    Sl.

    No.Item No. L B H/D Qty. Unit

    2nd and 3rd floor similar

    2 232.95 465.90

    4th floor similar to Ist floor 216.15 sqm

    Lessmarked () 56.48 sqmLess 1.0 7.50 1.925 14.44 sqm

    145.23 sqm

    Total 485.51 + 232.95+465.90+145.23 1329.59 sqm

    Say co. 1330 sqm

    Also see on page

    G.F

    11.41 A Pile work in skirting risers of step shade

    comp. 1 17.15 + (4x7.50)

    2 (15.0+15.0+2.75)

    11.41A.1 Marble tiles polished regular 8 mm thick 112.65 x 0.125 14.08 sqm

    B.F. 14.08 sqm

    Ist floor

    coridor 2x2 30.75

    2x2 12.95

    Launge 2 (6.90+5.75)

    coridor / Ver 2 7.15

    214.40 0.125 26.80 sqm

    2nd and 3rd floor similar

    4th floor 2x26.80 56.60 sqm

    2 30.75

    2 23.25

    2 12.95

    133.90 0.125 16.74 sqm

    Total 111.22 sqm

    Add skirting in dining Hall

    Black marble (Border) marble 2 (16.0+10.65+2.70) 0.30 17.61 sqm

    Total 128.83 sqm

    G.F. Dining hall flooring with udaipur green 1 8.70 7.25 63.08 sqm

    1 10.75 8.70 93.53 sqm

    156.60 sqm= 157.00 sqm

  • 7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13

    25/27

    SEN & LALL CONSULTANTS PVT. LTD.

    Architects Consultants

    Patna-800 001

    Sheet No. 25

    Sl.

    No.Item No. L B H/D Qty. Unit

    11.48 Kota stone flooring svs 20 mm ( average)

    thick base of

    25 mm thick

    Basement 1 9.30 7.25 67.43 sqm

    1 20.20 7.25 146.45 sqm

    for stair treads & lendy 1 5.10 2.85 14.54 sqmTotal basement 228.41 sqm

    G.F. kitchen / slaft 1 14.75 7.25 106.94 sqm

    Ent. Stores , stair , passage 1 15.00 7.25 108.75 sqm

    Less lift () 2 2.30 2.05 9.43 sqm

    cut off () 1 3.50 2.80 9.80 sqm

    Add staff Dining 1 8.20 7.575 62.12 sqm

    Less plt () 1 2.925 2.70 7.90 sqm

    Front stair Hall / Lobby 1 7.375 3.50 25.81 sqm

    stair treads / 1 4.20 3.50 14.70 sqm

    Less cut off () 1 1.80 1.10 1.98 sqm

    Single flght treads & longs 1 10.75 1.75 18.81 sqmTotal G.F. 308.02 sqm

    Ist floor

    stair treads & 1 5.10 2.30 11.73 sqm

    Less () 1 2.70 0.30 0.81 sqm

    Staft Lobby / linem 1 5.10 4.45 22.70 sqm

    Less lift () 1 2.30 2.05 4.72 sqm

    28.90 sqm

    B.F. 28.90 sqm

    Front stair / Lobby Treads 1 7.00 3.50 24.50 sqm

    Less () 1 1.80 1.00 1.80 sqm

    Treads / long single flight 1 10.75 1.75 18.81 sqm

    Kitchen 8 2.80 1.50 33.60 sqm

    Bal / Verandah 8 3.625 2.35 68.15 sqm

    172.16 sqm

    2nd , 3rd floor similar 2 x 172.16 344.32 sqm

    4th floor similar as marked in Ist floor 17.98 sqm

    Add kitchen 6 2.80 1.50 25.20 sqm

    bed / Verandah 6 3.625 2.35 51.11 sqm

    Terrace at 4th floor 1 17.05 7.725 131.71 sqm

    1 7.625 7.98 60.85 sqm

    286.85 sqmTerrace floor 1 30.76 30.760 946.18 sqm

    Less Terrace at 4th floor as marked () 192.56 sqm

    Less Atrium () 1 11.15 11.150 124.32 sqm

    Less machine room etc. () 4.55 4.732 21.53 sqm

    () 1 4.75 3.10 14.73 sqm

    593.04 sqm

    Total kota 308+172+343+287+600 1710.00 sqm

  • 7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13

    26/27

    SEN & LALL CONSULTANTS PVT. LTD.

    Architects Consultants

    Patna-800 001

    Sheet No. 26

    Sl.

    No.Item No. L B H/D Qty. Unit

    sheet 47

  • 7/29/2019 Estimate of Qnty - Mlc Hostel 13.2.13

    27/27

    SEN & LALL CONSULTANTS PVT. LTD.

    Architects Consultants

    Patna-800 001