Estimating Project Times and Resource Costs. Learning Objectives. Describe various Methods of estimating times and costs Calculate and interpret Learning curves Recall different Types of costs Describe resource allocation Describe leveling resources. Estimating Projects. Estimating - PowerPoint PPT Presentation

Citation preview

Page 1: Estimating Project Times and Resource Costs

Estimating Project Times and Resource Costs

Page 2: Estimating Project Times and Resource Costs

Learning Objectives

Describe various Methods of estimating times and costs

Calculate and interpret Learning curves

Recall different Types of costs

Describe resource allocation

Describe leveling resources

Page 3: Estimating Project Times and Resource Costs

Estimating Projects

Estimating

The process of forecasting or approximating the time and cost of completing project deliverables.

The task of balancing expectations of stakeholders and need for control while the project is implemented.

Page 4: Estimating Project Times and Resource Costs

Types of Costs

Direct Costs Costs that are clearly

chargeable to a specific work package.

Indirect Costs Costs incurred that are not

directly tied to an identifiable project deliverable or work package.

Special Case Costs “estimated costs” usually

assigned to task that has been done over and over.

Sunk Costs Those costs that are

unrecoverable.

Capital Costs Assets that have a useful life,

year or more.

Page 5: Estimating Project Times and Resource Costs

Why Estimating Time and Cost Are Important

• To support good decisions.

• To schedule work.

• To determine how long the project should take and its cost.

• To determine whether the project is worth doing.

• To develop cash flow needs.

• To determine how well the project is progressing.

• To develop time-phased budgets and establish the project baseline.

Page 6: Estimating Project Times and Resource Costs

Factors Influencing the Quality of Estimates

5–6

Quality of Estimates

Quality of Estimates

ProjectDuration

ProjectDuration

PeoplePeople

Project Structure and Organization

Project Structure and Organization

PaddingEstimates

PaddingEstimates

OrganizationCulture

OrganizationCulture

Other (Nonproject)Factors

Other (Nonproject)Factors

Planning HorizonPlanning Horizon

Page 7: Estimating Project Times and Resource Costs

Estimating Guidelines for Times, Costs, and Resources

1. Have people familiar with the tasks make the estimate.

2. Use several people to make estimates.

3. Base estimates on normal conditions, efficient methods, and a normal level of resources.

4. Use consistent time units in estimating task times.

5. Treat each task as independent, don’t aggregate.

6. Don’t make allowances for contingencies.

7. Adding a risk assessment helps avoid surprises to stakeholders.

5–7

Page 8: Estimating Project Times and Resource Costs

Types of Estimates

Order of Magnitude

“seat of your pants” estimate with very little thought or preparation

Before it is stated, stress it is very rough and limited in accuracy

Budget Estimate

More accurate and requires some research

Can use historical data

Page 9: Estimating Project Times and Resource Costs

Cont.

Definitive Estimate

Most accurate

Use the WBS completed and tested for accuracy

Include contingency allowances – lump sum amt.

Includes: training, testing, travel, monitoring, etc.

Pro Forma Assessments

Initial profile of project costs

Can be order of magnitude, budget, or definitive estimates

Are refined until there is a particular level of comfort

Page 10: Estimating Project Times and Resource Costs

Cost Estimating Approaches

Bottom- up

Most time consuming and most expensive

Uses WBS where each task is estimated and then added together as reverse upward.

Tendency to “pad” as one goes

Parametric Procedures Applied to Specific Tasks

Using Industrial Engineering standards and analysis

Involves cost per sq. ft., linear foot, etc.

Page 11: Estimating Project Times and Resource Costs

Cost Estimating Approaches

Macro (Top-down) Approaches

Consensus methods

Expert judgment

Apportion method

Learning curves

Project EstimateTimesCosts

Page 12: Estimating Project Times and Resource Costs

Refining Estimates Reasons for Adjusting Estimates

Interaction costs are hidden in estimates. Normal conditions do not apply. Things go wrong on projects. Changes in project scope and plans.

Adjusting Estimates Time and cost estimates of specific

activities are adjusted as the risks, resources, and situation particulars become more clearly defined.

5–12

Page 13: Estimating Project Times and Resource Costs

Estimate duration times

Fairly certain if done before in other projects

derive average duration from historical data

Some projects books available containing mean tables for typical activities

Ask around

When considering the time commitment to a particular project, realistically, personnel (a resource) has 80% of their personnel time available, which is 4-6 hours of actual labor time (sometimes one can only get 4-5 hrs per day) while the rest of their time is involved with non-project related issues.

Page 14: Estimating Project Times and Resource Costs

Resources

Page 15: Estimating Project Times and Resource Costs

Estimate Resources

Four categories of resources

Money

Materials

Machines

People

Questions to ask?

Who and what are needed?

Who and what can do the work?

Who and what are available?

What level and competence is required?

Page 16: Estimating Project Times and Resource Costs

Resource Planning Resource planning is the process by which the project

manager decides which resources to obtain, from what source, when to obtain them, and how to use them.

Resource planning is mainly concerned with the trade-off analysis between: 1. cost of alternative schedules designed to accommodate

resources shortages, and

2. cost of using alternative resources; for example, overtime to meet a schedule or subcontracting to accommodate a schedule change.

Resource planning is a continuous process that takes place throughout the life cycle of the project. In a multi project environment the specific resource alternative selected also affects other ongoing projects. It is common wisdom to start the planning process by assuming that each activity is performed by the minimum cost resource alternative.

Page 17: Estimating Project Times and Resource Costs

Project Resource Tools

WBS

Resource Matrix

Gantt chart

Page 18: Estimating Project Times and Resource Costs

Resource Availability

Renewable resources are resources that are available at the same level every time period. (e.g., a fixed workforce)

Depletable resources are resources that come in a lump sum at the beginning of the project and are used up over time, such as materials or computer time on a super computer.

Doubly constrained resources are resources available in limited quantities each period. However, their total availability throughout the project is also circumscribed. The cash available for a project is a typical example of a doubly constrained resource.

Nonconstrained resources are resources available in unlimited quantities for a cost. A typical example is untrained labor or general-purpose equipment.

Page 19: Estimating Project Times and Resource Costs

Schedule Load – tasks and resources

HEURISTICS (rule of thumb)

As soon as possible As late as possible Shortest task time first -

what takes the least amount of time to do

Most resources first - which needs the most people, equipment, material to get done

Minimum Slack first Most critical followers-the

tasks that follow are critical and must start on time or the project will be delayed.

Most successors

Factors to Consider in Assigning Work (Loading Resources):

Don't always pick the same people for the toughest assignments.

Choose people with an eye to fostering their development through participation on the project.

Pick people with compatible work habits and personalities but who complement each other.

Team-up veterans with new hires to share experience and socialize newcomers into the organization.

Select people who may need to learn work together on later stages of the project or other projects.

Page 20: Estimating Project Times and Resource Costs

Resource Leveling

Leveling within slack

The Level Only Within Available Slack option looks at the Slack value of a task and delays tasks only within that amount of slack. For example, if a task is five days long and has 15 days of slack, leveling with this option turned on will delay this task only 10 days, even if this means leaving some overallocations unresolved. But does not extend the project.

Leveling outside slack

Using Leveling outside slack, we can delay or extend a tasks for when we have resources available. Unfortunately, this extends the project total time.

Do note that leveling either way does not always solved the resource overallocations. So one may have to: Hire more help

Reevaluate the task time

Look at secondary skills of existing resources.

You might decide to use resource leveling when you look at your schedule and see that you have one or more resources that are allocated at more than their Max Units values for a given time period (or periods).

Page 21: Estimating Project Times and Resource Costs

Learning Curves

Page 22: Estimating Project Times and Resource Costs

Learning Curve

Past experience indicates that individuals learn by experience (i.e., get better and better at the job by carrying out the tasks more and more).

Page 23: Estimating Project Times and Resource Costs

Learning curve

This phenomenon was first reported by T. P. Wright in 1936. But, the learning curve theory is based on assumptions such as those listed next Chase, R B., 1981

Page 24: Estimating Project Times and Resource Costs

Underlying Principles of Learning Curves

1. Each time you perform a task it takes less time than the last time you performed the same task

2. The extent of task time decreases over time

3. The reduction in time will follow a predictable pattern

Page 25: Estimating Project Times and Resource Costs

The Experience Curve As plants produce more products, they

gain experience in the best production methods and reduce their costs per unit

As plants produce more products, they gain experience in the best production methods and reduce their costs per unit

Total accumulated production of units

Cost orpriceper unit

Yesterday

Today

Tomorrow

Page 26: Estimating Project Times and Resource Costs

Learning Curve assumptions

The learning curve may vary one product to another and from one organization to another. The rate of learning depends on factors such as the quality of management and the potential of the process and products

Page 27: Estimating Project Times and Resource Costs

Moreover, it may be said that any change in personnel, process, or product disrupts the learning curve. Consequently, there is a need for the utmost care in assuming that a learning curve is continual and permanent.

Page 28: Estimating Project Times and Resource Costs

The learning curves are found to be quite useful in a variety of applications, including strategic evaluation of company and industry performance, internal labor forecasting, establishing costs and budgets, production planning, external purchasing, and subcontracting of items

Page 29: Estimating Project Times and Resource Costs

Formulas

To determine Learning Curve rate:

T2/T1 = T4/T2=T6/T3=T8/T4

To determine time to produce nth or n units:

Page 30: Estimating Project Times and Resource Costs

Learn

ing C

urv

es

5–30

Page 31: Estimating Project Times and Resource Costs

Examples

Page 32: Estimating Project Times and Resource Costs

Example Problems: 1. Beth Zion hospital has received initial certification from the state of California to become a center for liver transplants. The hospital, however, must complete its first 18 transplants under great scrutiny and at no cost to the patients. The very first transplant, just completed, required 30 hours. On the basis of research at the hospital, Beth Zion estimates that it will have an 80% learning curve.

a. How long will it take to complete the 5th transplant?

b. How long will it take for all of the first 5 transplants?

c. How long will it take to do the last 13 transplants?

2. A student at Winona State University bought six (6) bookcases for her dorm room. Each required unpacking of parts and assembly, which included some nailing and bolting. She completed the first bookcase in five (5) hours and the second in four (4) hours.

a. What is the learning rate?

b. Assuming the same rate continues, how long will the 3rd bookcase take?

c. How long will it take to do all 6 bookcases?

Page 33: Estimating Project Times and Resource Costs