12
LECTURE 9 Pricing and Estimating

Lecture 9 - Estimating Project Times and Costs

Embed Size (px)

DESCRIPTION

Lecture 9 - Estimating Project Times and Costs

Citation preview

  • LECTURE 9

    Pricing and Estimating

  • Introduction

    Estimating: The process of forecasting or approximating the time and cost of completing project deliverables.

    Good estimation is critical for successful completion of a project on time, on budget and on the mark.

    Use the WBS as the basis for creating activity estimations.

    Estimating is not an exact science.

    Projects often involve a greater degree of uncertainty. 2

  • Introduction

    Many managers regard this as an art !

    Information available to one bidder is generally available to others.

    This is an essential part of the planning process.

    Forms the basis for establishing standards for budgets, man-hours, material costs, contingencies, etc.

    Specific pricing strategies must be developed for each situation.

    3

  • Four common Estimating Methods

    Order of magnitude estimates- Made without any detailed engineering data

    - May use past experience

    - Accuracy +- 35% within the scope of the project

    Approximate (rule of thumb) estimates- Made without any detailed engineering data

    - May use previous similar projects --

    - Accuracy +- 15%

    Definitive (or detailed) estimates- Prepared from well-defined engineering data, vendor

    quotes, unit prices, etc. Accuracy +- 5%

    Estimating manual- Developed over time

    - Use to price out effort. Accuracy +-10%4

  • Additional Estimating Methods

    Direct Estimate

    - Estimate/experienced person

    - Requires judgement

    Estimate by analogy

    - Compare with similar activities

    - Requires judgement

    Factored method

    - Based on historical data

    - Requires equipment lists, sizes

    - Starts with equipment quotes

    Gross proration method

    - Based on historical data

    - Near duplicate information5

  • Detailed estimate

    - Uses the WBS

    - Takes the WBS down several levels

    Quotation method

    - Compare three quotations

    - Select the best quotation

    Handbook manuals

    Learning curves

    Additional Estimating Methods

    (continued)

    6

  • Estimation Pitfalls

    Underestimating main causes are: overly optimistic team members,

    underestimation of the amount of non-productive time,

    incomplete recall of previous experience (pain goes away and only glory remains), or

    team mates have no experience with the activity to draw upon.

    Inflating estimates sometimes novice project managers may want to inflate estimates in order to come in under budget, or time.

    7

  • Cost/Hour Estimates

    EstimatingMethod

    Generic Type

    WBSRelationship Accuracy Time to

    Prepare

    Parametric ROM* Top Down -25% to +75% Days

    Analogy Budget Top Down -25% to +75% Weeks

    Engineering(Grass Roots)

    Definitive Bottom Up -5% to +10% Months

    * Rough Order of Magnitude

    8

  • Construction Cost Estimates

    Fixed-Price or Lump Sum - i.e. $4,000 for the entire project

    Unit-Price - i.e. $90/hour for professional services

    Cost-Plus or Time and Materials or Cost-Reimbursable Contracts - i.e. cost of actual materials plus 20% profit.

    Project EstimateTimesCosts

    9

  • Explanation of Project Costs

    Project Indirect Costs

    Costs that cannot be associated with any particular work package or project activity.

    Supervision, administration, consultants, and interest

    Costs that vary (increase) with time.

    Reducing project time directly reduces indirect costs.

    Direct Costs

    Normal costs that can be assigned directly to a specific work package or project activity.

    Labor, materials, equipment, and subcontractors

    Crashing activities increases direct costs.10

  • Classroom Activity 9a

    Why is estimating not an exact science?

    Why do people tend to underestimateactivities?

    11

  • 12

    Questions?