Upload
tushar-bhutia
View
219
Download
1
Embed Size (px)
Citation preview
8/3/2019 Estimation & Budgeting-10
http://slidepdf.com/reader/full/estimation-budgeting-10 1/29
Project Cost Estimation & Budgeting
Module X
8/3/2019 Estimation & Budgeting-10
http://slidepdf.com/reader/full/estimation-budgeting-10 2/29
COST ESTIMATION Decision To Take up a Project Depends on
Real Need for the Outcome Time Required to Complete Project
Estimated Cost Involved in Completing the Project Estimation Involved in All Elements of Project Times/ Resources/ Costs
Project Cost Estimates/ Budgets/ WBS/ Project Schedules Interrelated& Any Change in One Will Affect Others & The Total Project
Project Cost Estimates Based Upon Elements of WBS & Prepared at Work
Package Level & Even Lower at Activity/ Operational Levels If Necessary
Estimates Initially Based On Opinion/ Judgement of Experts To Be RefinedLater As More Information Becomes Available
Estimating Events Further in Future More Difficult Due To Higher Degreeof Uncertainties
For Medium/ High Complex Activities Planning is An Ongoing ProcessThroughout Project Life-Cycle As Changes Inevitable in Large Projects
Project Activities Get Greatly Affected By Changes in Inputs: Project Brief Changes By Customer Can be Significant in Long Duration Projects Constraints: Degree of Uncertainty Increases in Long Duration Planning As Financial &
Other Conditions Change - Different Interest Rates/ Cash Availability/ Investor Confidence Mechanisms – Availability of People/ State of Technology Difficult To Predict Over Long Time
Feedback From Previous Projects Used as Guide for Time/ Cost Estimation
8/3/2019 Estimation & Budgeting-10
http://slidepdf.com/reader/full/estimation-budgeting-10 3/29
TYPES OF ESTIMATION
For Preparing Proposals Project Manager’s Role in the Estimating Process
Varies Between
Collecting Estimations From Other People/ Functional Experts Developing Detailed Financial Cost-Benefit Analysis Themselves
As Projects Near Completion the Estimates for Final Times/ Resources/Costs Become More Accurate
Estimation Activity Continues Throughout Life-Cycle of Projects
Five Types of Estimates Used in Project Management Client: Indicative Cost Estimate Client: Preliminary Cost Estimate Client: Approximate Cost Estimate for Project Budgeting Client: Definitive Cost Estimate Client: Historical Actual Cost
Nature & Accuracy of Estimation Types Differ & Their Use/ ApplicationDepends on the Stage in the Project Life-Cycle When Estimates Being Made
Cost Estimates Used to Develop Budgets That Become Baseline AgainstWhich Project Performance Get Evaluated
Rate of Actual Cost Expenditure Compared To Budgeted Rate of
Estimated Expenditure Measures Project Work Performance ThroughoutProject Life-Cycle
8/3/2019 Estimation & Budgeting-10
http://slidepdf.com/reader/full/estimation-budgeting-10 4/29
PROJECT PHASE & ESTIMATION TYPE
Project Phase Estimate Type Purpose Inaccuracy
Initiation Phase Client: Indicative Cost Estimate Assess Project Viability ± 20%
• To Sanction ‘Go-Ahead’ with Planning/ Designing/Tendering
Planning/ Design Client: Preliminary Cost Estimate Budget Project Completion ± 15%Phase Cost & To Give ‘Go-Ahead’
for Execution
Initial Stages of Client: Approximate Cost Estimate Provides Base-Line for ± 10%Execution Phase for Project Budgeting Controlling Cost Objectives
(70- 80)% Project Client: Definitive Cost Estimate To Determine Cost At ± 5%Execution Phase Completion
Project Cost at Client: Historical Actual Cost To Account ActualProject Completion Completion Excluding
Unresolved Disputes & Claims
Client Cost Estimation Refers to Estimation Prepared By Client Organization Starts with Indicative Cost & Continues Till Actual Cost Determined at Completion
Cost Estimating Method Varies with
Nature of Project
Life-Cycle Phase of Project
Purpose of the Cost Estimation Degree of Accuracy Required Estimating Effort Employed
8/3/2019 Estimation & Budgeting-10
http://slidepdf.com/reader/full/estimation-budgeting-10 6/29
COST ESTIMATION METHODS
Types of Estimates Estimation Methodology Inaccuracy Effort (% of Project Cost)
Client: Indicative Cost Unit Service Method/ Cost ±20% 0.01 to 0.1Estimate Indices/Capacity Curves
Capacity Ratios
Client: Preliminary Cost Parametric Cost Estimate ±15% 0.05 to 0.2Estimate Supported By Prevailing Cost
Indices/ Capacity CurvesCapacity Ratios
Client: Approx. For Budgeting Pricing Based on Quantity Take- ±10% 0.1 to 0.5Estimate Project Cost off from Designs/Drawings/
Supported with SupplierQuotation/ Tendered Amount/ Overhead Estimates
Client: Definitive Cost Detailed Pricing Supported with ±5% 1.0 to 3.0Estimate Actual Cost Data During
Execution
Contractors’ Tender Detailed Pricing at Market Rate ±2% to 5% 0.1 to 1.0Estimate Supported with Quotations from
Potential Contractors/ Suppliers
Note: Percentages Indicative Only: Depends on Type/ Size of Project
8/3/2019 Estimation & Budgeting-10
http://slidepdf.com/reader/full/estimation-budgeting-10 7/29
COSTING PROPOSAL – BASIC APPROACH
Bottom-Up Costing Method Estimates of Each Level in WBS (Work Breakdown Structure) Compiled
& Added Together By Each Level of Supervision in Project Hierarchy Estimates Prepared By Handling Personnel/ Supervisors Hence Owned
by the Team Members More Committed to Achieving If Figures Remain Unmodified
by Project Manager
Process Looses Credibility If PM Expected to Cut Costing Proposals &Consequently Staff Pad Up the Cost Estimates To Counter Effect ofSuch Cuts
Method Not Very Good for Generating Accurate Estimates
Top-Down Costing Method
Top Management Allocates Certain Amount of Money To Completethe Project Activities
The Amount Is Split Among Various Sub-Projects Based on Senior Management Estimates
Using the Target Costing Concept Creates a Degree of Competition Between Supervisors of the Activities
This Competition Often Beneficial for the Project
8/3/2019 Estimation & Budgeting-10
http://slidepdf.com/reader/full/estimation-budgeting-10 8/29
APPROACHES TO COSTING
Senior Management/Project Sponsor
Project Owner
Project Manager
Top Down Bottom Up
Costs
FixedExternally
ToProject
Project
ManagerAllocatesBudgets
ToSub-Projects
Costs
SetBy TheProject
Members
ProjectManagerCollates
Estimates
Sub-Projects
Activities
8/3/2019 Estimation & Budgeting-10
http://slidepdf.com/reader/full/estimation-budgeting-10 9/29
ELEMENTS OF ACTIVITY LEVEL COSTS
Time – Direct Labour Inputs Into Activities
Overheads – Provision for Running of Headquarters/ ProvidingCentral Support Services Office Financial & Legal Support
Salaries & Perks for Managers & Other Non-Direct Staff
Indirect Expenses – Not Directly Related To Value-Adding Activity ButConsidered Necessary To Support Project (Project Overhead) Transportation/ Training/ Project Administration
Capital Equipment – Means of Providing Conversion Process Purchase Cost – Full/ Part Depending On Use in the Project
• For Equipment with Potential for Further Use after Project CompletionResidual Value Estimated and Reduced from the Cost
Maintenance/ Running Costs
Depreciation Offset Against Activities
Materials – Consumables & Other Items Used in the Process Material Costs
• Cost Incurred By Company To Acquire Material
• Cost of Material + Margin Added
8/3/2019 Estimation & Budgeting-10
http://slidepdf.com/reader/full/estimation-budgeting-10 10/29
ELEMENTS OF COSTS
Project
Overheads
GeneralOverheads
Profit
PrimeCost
Direct Materials
Direct Labour
=Price
+
+
+
Elements of Costs Added with Desired Profit To Arrive At Price of Project
General Overheads Calculated as a Percentage of Total Cost
TotalCost
Project Overheads Include Indirect Expenses for the Project
8/3/2019 Estimation & Budgeting-10
http://slidepdf.com/reader/full/estimation-budgeting-10 11/29
COST BUILD-UP - EXAMPLE
Estimate the cost of running a commercial training course required by the coursecoordinator to work out how much to charge each participant for making a desiredprofit. Assume the programme will be fully booked.
Cost related details are as follows:• Programme requires a consultant to do the 3 days’ training at Rs. 30K/ day • Services of administrator will be required @ Rs. 1K/ day for all the 3 days• Maximum 15 participants will be able to take part in the training• Cost of printed material and stationery estimated at Rs. 800/ participant• Administrative time required to arrange the programme was 10 days• Assume overhead cost (hall rent + electricity + procurement + cost of funds) at 60% of
total cost.
Direct Labour Cost = (30K х 3) + (1K х 3) = Rs. 93, 000
Direct Material Cost = 15 х 800 = Rs. 12, 000
Prime Cost = 93000 + 12000 = Rs. 105, 000
(Fixed)
(Variable cost - Depends onNo. of Participants)
Indirect Labour - administrative Time of 10 days = 1K х 10 = Rs. 10, 000
Cost = 105000 + 10000 = Rs. 115, 000
Overhead Cost = 115000 х 0.60 = Rs. 69, 000
Total Project Cost = 115000 + 69, 000 = Rs. 184, 000
Participant Fee =184000 ‚ 15= Rs. 12, 267
8/3/2019 Estimation & Budgeting-10
http://slidepdf.com/reader/full/estimation-budgeting-10 12/29
COST ESCALATION
Accurate Cost Estimation Difficult As It Starts at Conception Stage LongBefore All Necessary/ Final Information About Project Becomes Available
Estimated Costs Differ Substantially from Actual Final Figures By Way ofCost Overruns
Actual Amount of Increase Creating Cost Overrun of Initial EstimatedCosts Called ‘Cost Escalation’
Larger & More Complex the Project Greater the Potential for Cost Escalation Concord Supersonic Airliner Cost More Than 5 Times Original Estimates Nuclear Power Plants Frequently Cost 2 to 3 Times the Estimate Cutting-Edge/High Technology/R&D Projects - Frequently Above Several Hundred %
20% Cost Escalation Common in Projects
Major Reasons for Cost Escalation in Projects Uncertainty & Lack of Accurate Information – Define Clear Objectives/ Scope Changes in Design Or Requirements – Use ‘Change Control Systems’
Economic & Social Variables in Environment - Inflation/ Strikes/ Material Shortages Work Inefficiency/ Poor Communication/ Lack of Control – Poor P Management
Involvement of Estimator Ego – Honest Prediction Difficult By Non Professionals
Type of Contract – Fixed Price: Contractor Has Incentive To Control CostsCost-Plus: Contractor Has Little Incentive to Control Cost
8/3/2019 Estimation & Budgeting-10
http://slidepdf.com/reader/full/estimation-budgeting-10 13/29
COST ESTIMATION PROCESS
Cost Estimating Process Starts By Breaking the Project Down IntoWork Phases – Design/ Engineering/ Development/ FabricationWork Packages from WBS
Project Team Including Functional Area Representatives & ContractorsDiscuss Work Phases/ Work Packages & To Receive Work Assignments
Project Team Try To Classify Tasks in the Project as Developmental: Requires Considerable Effort in Design/ Testing/ Fabrication -
Comparatively Difficult To Estimate Costs Due to Greater Uncertainty in
Requirement of Labour Hours
Off-the-Shelf: Adapting Existing Design/ Techniques/ Procedures – Simpler To
Estimate Costs as Material/ Labour Hours Required in Similar Projects Available
Estimated Costs Classified as Recurring Costs: Occur Many Times
• Associated with Periodically Repeated Tasks• Include Costs Related to Labour/ Material/ Quality Assurance/ Testing Non-recurring: Happens Only Once
• Associated with Unique Tasks/ Procurement of Special Items• Include Costs Related to Development/Fabrication/Testing of One-of-a-kind Items
Estimated Cost Figures Determined Using Four Basic Techniques
Expert Opinion Analogy Estimate Parametric Estimate Cost Engineering
8/3/2019 Estimation & Budgeting-10
http://slidepdf.com/reader/full/estimation-budgeting-10 14/29
COST ESTIMATION TECHNIQUES
Expert Opinion: Cost Estimate Provided By an Expert Provides a Reasonable/ Ball-Park Estimate Using Experience & ExpertiseWhen In-sufficient Information Available & Carried Out at the Conception Stage
To be Followed Later By More Detailed and in-Depth Cost AnalysisWhen Project is Unique/ First Time Project – Euro Tunnel Project
Analogy Estimate: Cost Estimate Developed By Reviewing Costs from aPrevious Similar Project Can be Used at Any Level of the Project: Overall/ Work Package/ Tasks
Cost of a Similar Project/ Work Package Analyzed & Adjusted for Difference inCurrent and Earlier Projects Adjustments Made to Account for Dates/ Project Scale/ Location/ Complexity/
Exchange Rates Extensive Database of Past Projects Archived for Reference During New Projects
Parametric Estimate: Cost Estimate Derived from an Empirical/
Mathematical Relationship Can be Used with Analogy Project to Scale Costs Up/ Down Can be Used Directly When Costs are Function of Project ‘Parameters’ Such as
- Physical Features: Area/ Volume/ Weight/ Capacity
- Performance Features: Speed/ Output Rate/ Power/ Strength
Parametric Estimation Most Suitable Technique When Cost Estimates
Needed Quickly To Fix Preliminary Design Characteristics
8/3/2019 Estimation & Budgeting-10
http://slidepdf.com/reader/full/estimation-budgeting-10 15/29
PARAMETRIC COST ESTIMATE - EXAMPLE
Warren Eisenberg, President of Wonder Works, Inc. a Warehouse facilities contractor,wants a quick way to estimate the material cost of a facility. The company’s engineers investigate the relationship between several building parameters and the materials for
eight recent projects comparable in terms of general architecture, layout andconstruction material. Using the method of least squares, they develop the followingformula , a multiple regression model that relates material costs (y) in US Dollars tofloor space (x₁) in terms of 10, 000 sq ft and the number of shipping/ receiving docks (x₂) In a building:
y (US $) = 201, 978 + (41, 490) x₁+ (17, 230) x
₂
The least square method also indicates that the standard error of the estimate is small,which suggests the model provides fairly close to actual costs for the eight projects.
Estimate the material cost required to construct a 300, 000 sq ft facility with two docksUsing the model.
Estimated Material Cost, y = 201, 978 + (41, 490 х 30) + (17, 230 х 2)
Facility Floor Space, x₁= 300,000 ‚ 10,000 = 30 No. of Docks, x₂ = 2
Substituting values of x₁ & x₂ in the formula
= $ 1, 481, 138
8/3/2019 Estimation & Budgeting-10
http://slidepdf.com/reader/full/estimation-budgeting-10 16/29
COST ENGINEERING ESTIMATE
Estimating Cost Using Cost Engineering Involves Detailed Cost Analysisof Individual Cost Categories at the Work Package/ Task Levels
Cost Engineering Provides Most Accurate Estimate of Cost But ConsumesConsiderable Time & Requires Detailed Work Definition & DesignInformation – May Not Be Available at Initiation Phase
The Method Starts with Breaking Down Project Into Activities/ ProjectPackages Which Get Further Broken Down into Basic Areas of Work
Engineering Fabrication
Engineering/ Fabrication Packages Further Divided Similarly Till WorkContent of Each Element Can be Used to Estimate Time Required & Costs
Each Element of Work Packages Absorbing the Cost Categories
Labour Cost: Estimated Labour Effort in Man-Hours х Basic Labour Hourly Rate Materials Cost: Estimated Material Consumption Quantity х Materials Unit Price Equipment Utilization Cost: Estimated Equipment Utilization Hour х Basic
Equipment Hiring Hourly Rate
At Task Level Detailed Estimates Derived from Standard Manuals thatContain Time & Cost Information about Labor and Materials to Perform
Particular Tasks
8/3/2019 Estimation & Budgeting-10
http://slidepdf.com/reader/full/estimation-budgeting-10 17/29
COST ESTIMATE FOR TOTAL PROJECT
Estimates of Time & Material Arrived at By Each Work Team Checked BySupervisors Referring to
Previous Similar Work Standards Manuals Reference Documents
Rules of Thumb
Supervisors Submit Their Estimates to Work Package Managers WhoCheck/ Revise/ Aggregate & Pass Work Package Level Estimates to PM
Project Manager & Independent Estimators Review the Time & MaterialsEstimate To Ensure No Cost Overlooked/ Duplicated Estimators Understood What They Were Estimating Correct Estimating Procedures Used
Allowances Made for Risks/ Uncertainties
Estimates Then Aggregated & Converted into Dollars By Multiplying ByStandard Wage Rates & Material Costs - Current/ Projected
Cost Estimate for Total Project Arrived at By Project Manager Adding In Project-Wide Overhead Rates - Cover Project Management + Administrative Costs
Company-Wide Overhead Rates - Cover General Company Expenses
8/3/2019 Estimation & Budgeting-10
http://slidepdf.com/reader/full/estimation-budgeting-10 19/29
RECONCILING ESTIMATES
Project Manager Submits To Top Management Final Cost Estimates/ ProjectSchedules & Forecasts Showing Time/ Cost Effects of Potential Escalation
Factors – Inflation/ Exchange Rates/ Project Risks
If Gross Estimate Much Smaller Project Manager Reviews Work PackageEstimates To Examine incorrect Assumptions/ Padding
If Gross Estimate Substantially Larger Project Manager Reviews EachWork Package Estimate To Identify Oversight/ Over Optimism (Estimator Ego)
Management Decide To Accept it/ Send it for Revision To Project ManagerBased On Reconciliation of Two Cost Estimates Final Cost Estimates Prepared By Project Team Using Upward Accumulation of
Work Package Estimates Known as ‘Bottom Up’ Approach Gross Estimates Prepared Based On Expert Opinion/ Analogy to Other Similar
Projects Known as ‘Top Down’ Approach
To Reconcile Differences Pushing Across-the-Board Cut Across AllEstimates Not Recommended As It Will Affect Morale of the Project Team
To Identify Mistakes in Estimation that Can Happen in Both Directions Project Manager Approves Bottom-Up Estimates of Work Packages Functional Units Approve Top-Down Estimates for Work Expected From Them
Final Estimates Mutually Agreed Upon By Project & Functional Managers
8/3/2019 Estimation & Budgeting-10
http://slidepdf.com/reader/full/estimation-budgeting-10 20/29
BUDGETING
Written Statement of Money Showing Where it is Drawn From/ The Amount/How it is to be Spent Defined as a Budget
Most Operations Need Managers to Perform Budgetary Analysis Annually
Managing Within Budget is Key Cost Control Tool of Project ManagersWorking in Perpetual Cycle of Seeking Approval & Allocation of Funds
In Public Sectors Environments Budgets/ Grants Often Allocated Using
‘Zero- Base’ Budgeting Approach
Budget Applications/ Grants Generally Contain Following Categories Labour Materials Consumables Capital Expenditure (Cap-ex) Travel Subsistence
These are Basic Elements Used in Developing Bottom-Up Costs Providing Headings Within Project Codes to Relate Activities/ Resources for Cost
Allocation
8/3/2019 Estimation & Budgeting-10
http://slidepdf.com/reader/full/estimation-budgeting-10 21/29
PROJECT BUDGET
Estimates Prepared First & Approved Estimates Become Basis for Budgets
Organizations Committed To Perform Work According to the Budget
Budgets Contain the Agreed-Upon Contracted Amount of What WorkShould Cost Which Becomes Baseline for Tracking & Controlling the Work
Project Budgets Similar to Fiscal Operating Budgets With Only Differencein Duration Covered By Each
Project Budget Covers Full Life of the Project Fiscal Budget Covers One Year at a Time
Project Budget Essentially A Planning Document Outlining the FinancialPlan of the Project
Project Budget Quantifies in Monetary Terms the Project Cost Objective
Project Budget Allocates Responsibility for Attaining The Objectives Reflects Resources Earmarked Pin-Points Results to be Achieved By the Responsible Person
Provides a Standard for Measuring Effectiveness/ Efficiency of Performing
Activities
8/3/2019 Estimation & Budgeting-10
http://slidepdf.com/reader/full/estimation-budgeting-10 22/29
ZERO-BASE BUDGETING
Where Project Activities Ongoing But Reviewed Periodically Zero-BaseApproach Takes into Account Previous Performance As Well
Further Funding Made Available to Projects Only When Progress isDemonstrated
Where Progress Found Unsatisfactory Funding for Remaining ActivitiesDenied/ Cut
For This Reason Stipulation for Attracting Private Funding to SupplementGovernment Grants Often Added in Such a Project
For Tracking Costs as Project Progresses Direct Labour & Material CostsAllocated & Costs Tracked Through Job Costing Systems
For Accounting Purposes Separate Codes issued To Different Jobs & AllRelated Costs Recorded Against These Codes
Project Manager/ Budget Holder Periodically Checks For Accuracy of the
Cost Records
Drawing a Budget Without Reference to Last Budget Requiring ManagersTo Justify All Expenditures Afresh/ Not Just the Increases Over Last Year
8/3/2019 Estimation & Budgeting-10
http://slidepdf.com/reader/full/estimation-budgeting-10 23/29
LIMITATIONS IN BUDGETING SYSTEM
Funds Left in a Budget at End of Project/ Accounting Period Often
Spent Just To Avoid Showing Unused Funds in the Accounts By Making Unnecessary Purchases
Rushing Acquisitions To Beat Deadlines
This Practice Does Not Encourage Good Use of Resources
Project Management is Not Rewarded for Managing Cost MoreEfficiently Resulting in Any Unspent Funds
Limitation of Conventional Budgeting System Avoided If RewardGranted for Cost Efficiency Through Greater Allocation of Fundsin the Future
Budgeting System Imposes Constraints in Movement of FundsBetween Different Categories Often Creating Anomalies/ Waste
Exhausted One Category of Expenditure Though Project ActivitiesRemain Unfinished May Force a Manager to Pursue Even Cost
Inefficient Activities If Budget Allows Funds from Another Category
8/3/2019 Estimation & Budgeting-10
http://slidepdf.com/reader/full/estimation-budgeting-10 24/29
PROJECT COST ACCOUNTING
Project Management Needs to Estimate/ Budget/ Control Complex Systemof Manpower/ Materials/ Facilities
To Reduce Confusion/ Improve Accuracy/ Expedite Procedures ProjectManagement Needs A System to Compute Estimates/ Store & ProcessBudgets & Track Costs
Project Cost Accounting System (PCAS) Refers to Structure & MethodologyThat Enables Systematic Planning/ Tracking & Control of Project Costs
PCAS Set Up & Used By Project Manager/ Project Accountant/ RelatedFunctional Managers
PCAS Enable Total Project & Sub-Activity Cost To Be Accumulated/ Credited& Reported Once Project Execution Phase Gets Started
PCAS Tracks Project Costs By Relating to Schedules & Work Performance& Also Permits Tracking/ Control of Schedules & Work Progresses
PCAS Enhanced To PMIS To Handle Project Planning/ Control/ Reporting
PMIS Accumulate Work Package Cost Estimates To Total Project EstimatesThat Becomes Basis For Creating Total Project & Work Packet (WP) Budgets
Time-Phased Budgets Used To Monitor/ Allocate Costs To Appropriate WP
8/3/2019 Estimation & Budgeting-10
http://slidepdf.com/reader/full/estimation-budgeting-10 25/29
PCAS - ELEMENTS
Work Package
Cost Information
Actual PerformanceInformation(Work Completed& ExpenditureIncurred)
Total Project Cost Estimates
Time-Phased BudgetFor Cost Accounts
Variance
Analysis
RevisedBudgets
PCAS OutputsPCAS Inputs
Project CostAccounting
System(PCAS)
Estimating&Budgeting
Tracking&
Control
PCAS Supports Project Managers By Providing Information Related To
How Project Progressing When Expenses IncurredWhere Problems Developing
PCAS Uses Time-Phased Budget To Create Output Reports That Help Project
Managers To Control Project Costs
8/3/2019 Estimation & Budgeting-10
http://slidepdf.com/reader/full/estimation-budgeting-10 26/29
TIME-PHASED BUDGET
Time-Phased Budget Shows How Budgeted Costs Distributed OverTime In Accordance With the Project Schedule
Throughout Duration of the Project PCAS Generates Time PhasedReports (TPR) For Every Work Package
TPR Allows Managers To Review & Compare Actual ExpenditureWith Planned Expenditure Every Month
Time-Phased Reports Used To Perform Cost Variance Analysis To Ensure Work Actually Completed & Charged Accurately
To Revise Estimates & Budgets As Needed
In Most Projects Simultaneous Control of Work Schedules & Cost
Expenditures Extremely Difficult Time-Phased Budgets Created By Consolidating Two Primary Tools
For Project Control Project Schedules Project Budgets
8/3/2019 Estimation & Budgeting-10
http://slidepdf.com/reader/full/estimation-budgeting-10 27/29
Charge RateMonths Totals
1 2 3 4 5 6 Hrs Cost
Direct Labour
(Professions)
35/ Hr
20/ Hr
50
100 100 100
50
100
100
400
3, 500
8, 000
Direct Labour CostLabour Overhead
Other Direct Costs
75%1, 7501,312
2,0001,500
100
2,0001,500
2,0001,500
3,7502,813
11,5008,625
100
Total Direct Cost
General /Admin 10%
3,062
306
3,600
360
3,500
350
3,500
350
6,563
657
20,225
2,023
Total Costs
Profits 15%
3,368 3,960 3,850 3,850 7,220 22,248
Billing Total
Project:Department:
Date:
Work Package Description:
Number/ Code:
TIME-PHASED BUDGET
8/3/2019 Estimation & Budgeting-10
http://slidepdf.com/reader/full/estimation-budgeting-10 28/29
BUDGETING USING COST ACCOUNTS
In Small Projects Planning & Performance Monitoring Done Using SimpleBudget for the Whole Project
For Larger Projects Project-Wide Budgets Broken Down Into SmallerBudgets Known As Cost Accounts For Better Control
Cost Account Used as Basic Project Tracking & Control Unit of PCAS
System of Cost Accounts Set Up In a Hierarchy Identical To the WBS
Similar To Work Packages Each Cost Account Includes Description of Work Time Schedule Responsible Person Material/ Labor/ Equipment Required
Time-Phased Budget
Cost Performance of a Package/ Group of Packages/ Whole Project Can beMonitored Using PCAS & the Cost Account Structure
Cost Accounts Also Established for Non-Direct Project Cost Where CostsCan Not Be Readily Attributed To Any Work Package/ Specific Task