8/13/2019 Example Reports for Campaign 23rd May 13
1/7
Date:- 5/23/2013
Management Inspection Supervision C/Hands Utility Men
Area/Fire Zone. Job Card No.
Job Location Operatives Names Expected Daily Task
Area/Fire Zone. Job Card No.
Job Location Operatives Names Expected Daily Task
Area/Fire Zone. Job Card No.
Job Location Operatives Names Expected Daily Task
Area/Fire Zone. Job Card No.
Job Location Operatives Names Expected daily task
Area/Fire Zone. Job Card No.
Job Location Operatives Names Expected Daily Task
Daily Work Sheet (Painting)
Comments
Operatives
8/13/2019 Example Reports for Campaign 23rd May 13
2/7
Date Time Air Temp.C
RH%
Dew PointC
Date Time Air Temp.C
RH%
Dew PointC
12/5 0745
12/5 1100
12/5 1405
Date Date
5/12/2013
5/13/2013
5/15/2013
DateBlast
Profile (m)
Surface
Dust Level
Mill Scale
Clear Y/NDate
Blast
Profile (m)
Surface
Dust Level
Mill Scale
Clear Y/N
5/12/2013 Max 85m Max 2 Yes
Date TimeArea/Item
Coated
System
Code
Coat
Number
Batch No.
Base
Batch No.
HardnerColour
DFT
(Average)
12/5 1015 Structure P01 1 Grey 150m
13/5 0850 Structure P01 2 Grey 300m
15/5 0830 Structure P01 3 Yellow 400m
Comments:-
Company:
N
CAPE CAPE Total
Total Ave. DFT 400m
Protection Fitted to Supports: IF APPLICABLE
PUT ANY APPLICABLE COMMENTS IF REQUIRED
2000 TC 5 Mpa
CoatingAdh
(Pull o
18FC
18FC
Coating Manufacturer: Carboline Coating Used: Carbomastic 18FC & Carboxane 2000TC
Stripe Coating Performed:Yes Paint Application Method:Either Airless Spray or Brush
MAX 30mg/m
Pre-wash Complete:Yes Surface Degreased: IF APPLICABLE
Surface Preparation Method:Dry Grit Blast Abrasive Used:Garnet or Aquagrit Cleaning Grade:SA 2
Soluble Salt
LevelSoluble
PUT IN DRAWING NUMBER & LINE NUMBER IF
APPLICABLE
Drawing Number Line Number Drawing Number Line Numbe
CREATE NEW WORKSHEET IF YOU RUN OUT OF
SPACE BY RIGHT CLICK ON WORKSHEET TAB
SELECT MOVE/COPY, SELECT CREATE A COPY
BOX, SELECT OK. RENAME I.E. DAILY REPORT
1, 2, 3 ETC BY RIGHT CLICK ON WORKSHEET &
SELECT RENAME
RECORD 3 TIMES DAILY (INCLUDE DAY &
NIGHTSHIFT ON SAME REPORT. ENSURE
UPDATED BEFORE END OF YOUR SHIFT
Specification:GEN-W-SP-83202 Rev A01 Line Number: IF APPLICABLE Workpack No: 8LW3
Inspector: J.Warren/P.Durin Area/Fire Zone: 8LW3 Date Work Started: 24th May 2013
PROTECTIVE COATINGS INSPECTION REPORT
DAILY INSPECTION REPORT
Client: Total Installation: Elgin 2013 Painting Campaign Contract Ref: 4300002629
Contractor: CAPE Drawing Number: IF APPLICABLE Job Card No: 8LW3-061
Steel Temp.C
Steel Temp
Report Number: EL-13-?
8/13/2019 Example Reports for Campaign 23rd May 13
3/7
5/12/2013
PUT READING IN HERE IN MPA
ATTACH TESTEX TAPE HERE ATTACH TESTEX TAPE HERE
ATTACH TESTEX TAPE HERE ATTACH TESTEX TAPE HERE
Calibration Date: Put Calibration Due Date
Inspection Equipment Used: Testex Tape and Micrometer Serial Number: Put Serial Number
ATTACH SURFACE DUST TEST RESULTS:
Inspection Equipment Used: Elcometer 108 Digital Adhesion Gauge Serial Number: Put Serial Number
ATTACH SOLUBLE SALT TESTS: (DESCRIBE TEST CARRIED OUT)
DESCRIPTION OF ADHESION TEST RESULTS:
Inspection Equipment Used: Brestle Patch & Conductivity Meter
Calibration Date: Put Calibration Due Date &(141 Solution)
Location: Put JC Number Date: Put Date Location: Put JC Number Date: Put Date
Location: Put JC Number Date: Put Date Location: Put JC Number Date: Put Date
PUT DETAILS OF TEST AS ABOVE & READING IN
HERE IN MG/M2
Serial Number: Put Serial Number
ATTACH SURFACE DUST TAPE HERE
ATTACH SURFACE DUST TAPE HERE
ATTACH SURFACE DUST TAPE HERE
Salt test detection kit used was the conductivity meter and brestle patch
PROTECTIVE COATINGS INSPECTION REPORT
TEST RECORD
ATTACH SURFACE PROFILE TEST RESULTS:
Location: Put JC Number Date: Put Date Location: Put JC Number Date: Put Date
ATTACH TESTEX TAPE HERE ATTACH TESTEX TAPE HERE
Report Number: EL-13-???
8/13/2019 Example Reports for Campaign 23rd May 13
4/7
Testex tapes attached
PROTECTIVE COATINGS INSPECTION REPORT
PHOTOGRAPHIC RECORD
Photo of Initial condition Photo of Pre-washing of vessel
Photo of blasted area Photo of blasted area
Test panel done in-situ
Test panel done in-situ
EXAMPLE
8/13/2019 Example Reports for Campaign 23rd May 13
5/7
Spray applied 18FC
Test panel done in-situ
Stripe coating C750V2Stripe coating C750V2
PROTECTIVE COATINGS INSPECTION REPORT
PHOTOGRAPHIC RECORD
Salt test result (Final Result after blasting) Stripecoating performed for 1st coat of 18FC
Stripecoating performed for 1st coat of 18FC
EXAMPLE
8/13/2019 Example Reports for Campaign 23rd May 13
6/7
PROTECTIVE COATINGS INSPECTION REPORT
PHOTOGRAPHIC RECORD
Adhesion Test - Photo value recorded on adhesion test
beside test plate
Spray applied C750V2
Test panel done in-situ
Photo of completed job as per JC
EXAMPLE
8/13/2019 Example Reports for Campaign 23rd May 13
7/7
Statement:
Deviations To Specifications:- Y/N
Documentation Package Complete:- Y/N
Company:
Name:
Position:
Signature:
Date:
CAPE Total
Site Manager Company Representative
FINAL ACCEPTANCE
FABRIC COMPLETION CERTIFICATE
Work Order Number: 8260534 Contractor: CAPE
Notification Number: 18187659 Date:
Scope of Work:
All work has been completed to the current Total approved specifications.
Work orders have been updated and closed out in SAP
Inspection records have recorded the environmental conditions, surface preparation, coating application, trace heating,
Insulation and cladding (where applicable), all of which have been measured with inspection equipment traceable to
national standards.
Specification Used For Coatings:- GEN-W-SP-83202 Rev 1
Specification Used For Insulation:- GEN-W-SP-83200 Rev A02