Expanded Public Works Program – Overview
Mr. Gilberto MartinsB Arch [ Wits] MI Arch Arch SA
Deputy Director General: Public WorksGauteng Department of Public Transport, Roads and Works
6 May 2008
GAUTENG EXPECTATIONS
Innovation = Business Unusual
4
Origin• Origin in Growth and Development Summit
[GDS] of 2003
• Four themes adopted one of which was ‘More jobs, better jobs, decent work for all’
5
• The GDS agreed that the EPWP ‘can provide poverty and income relief through temporary work for the unemployed to carry out socially useful activities. The EPWP will be designed to equip participants with a modicum of training and work experience, which should enhance their ability to earn a living in the future.’ The GDS specified that the EPWP must be “large enough to have a substantial impact on employment and social cohesion, especially for young people, women and the rural poor” .
Roads Pavement Forum (RPF)
• “Serves as a forum for the exchange of information and technologies, promoting best practice and to facilitate the discussion of issues of strategic importance to the road construction industry”
SocialConsideration
s
Economic
Consideration
• EPWP is integrated methodology where by :– Creation of assets (infrastructure provision
and maintenance)– Training and skills development (all levels)– Job creation (all levels)– Contractor development (CIDB level 1-4)– Sustainability, increase industry skills base
0
25
50
75
100
125
150
175
200
No
Dat
a19
4819
5019
5219
5419
5619
5819
6019
6219
6419
6619
6819
7019
7219
7419
7619
7819
8019
8219
8419
8619
8819
9019
9219
9419
9619
9820
0020
0220
0420
06
Year
Len
gth
(km
)
• Length of road constructed per year• 82% of roads are older than design life of 20 years, 24% of roads have
reached more than twice design life – Are we in a crisis ?
691 km, 17%
745 km, 18%
240 km, 6%
928 km, 23%
1,435 km, 36%
AADT <= 500 500 < AADT <= 2,0002,000 < AADT <= 5,000 5,000 < AADT <= 10,000AADT > 10,000
• More than 36% of road network is heavily congested
• A further 17% should be considered for capacity upgrading, and are congested during peak hours
• Congested roads contributing to maintenance problems (e.g. use of gravel road shoulders) and road safety problems
• Heavily congested roads are generally the older roads which needs rehabilitation
*AADT= Annual averagedaily traffic volume
• Additional R5.4bn to Provinces for up-scaling of EPWP from 2007/08 (PIG).
• Gauteng decision to increase amounts even further from Provincial funding:– 2006/2007 amount from R52m to R170m– 2007/08 amount from R82m to R262m– 2008/09 amount from R103m to R320m– Total R 752m– Further funding bid 09/10 MTEF allocation
[ R 1 Bil ?]
Up-scaling of EPWP in Roads
THE CHALLENGETHE CHALLENGE
• Challenges • Backlog on provincial road network – 82% of
network older than design• App 3000km Gravel road – townships • Agreements on appropriate norms, standards,
designs • Resistance to change- innovative contracting
models, materials, construction methods required
• SOSHANGUVE • ATTERIDGEVILLE • MAMELODI • MUNSIEVILLE • SOWETO • SEBOKENG • RATANDA • BOIPATONG • BOPHELONG • SHARPVILLE
• DAVEYTON • DUDUZA • THEMBISA • KAGISO • THOKOZA • KATLEHONG • MOHLAKENG • WATTVILLE • KWA-THEMA • TSAKANE
20 I
den
tifi
ed t
ow
nsh
ips
• Challenges • Cost for township road less 500 car per day
currently ranging R6m to R10m per kilometre ?• Inexperienced contractors – tender process
and documentation not fully understood• Contractor access to finance, materials,
equipment problematic• Professional site management?• Skills development basket roads industry
RE-DRESSRE-DRESS
Innovation required• Reduce construction costs• New construction methods• Alternative construction materials• Innovative and appropriate pavement design• Research and testing• New contracting models• Appropriate norms and standards for all roads• Consistently applied across all metros/
municipalities
Service Delivery Model ObjectiveService Delivery Model Objective
Effective, Efficient, Value For Money, Service Delivery
Economicconsideration
Socialconsideration
Thank You
“In order to achieve real action you must yourself be a living part of Africa and of her thought; you must be an element of that popular energy which is entirely called forth for the freeing, the progress and the happiness of Africa.”Frank Talk , Steve Biko , I write what I like