EDMS NO. REV. VALIDITY
2038214 0.2 DRAFT
REFERENCE
PS-LJ-EC-0009
Date: 2018-10-29
Note: When approved, an Engineering Change Request becomes an Engineering Change Order.
This document is uncontrolled when printed. Check the EDMS to verify that this is the correct version before use.
CERN CH-1211 Geneva 23 Switzerland
ENGINEERING CHANGE REQUEST
F61 Transfer Line Modifications
BRIEF DESCRIPTION OF THE PROPOSED CHANGE(S):
As part of the East Area renovation project during the Long Shutdown 2 (LS2), the F61
line will be completely renovated. An overhaul of the associated infrastructure will also
be performed.
DOCUMENT PREPARED BY: DOCUMENT TO BE CHECKED BY: DOCUMENT TO BE APPROVED BY:
Bard Carlsen (EN-EA)
Erwan Harrouch (EN-EA)
C. Bertone, S. Burger, D. Bodart,
J. Borburgh, E. Grenier-Boley,
M. Brugger, M. Calviani,
J. P. Corso, J. Coupard,
J. M. Cravero, H. Damerau,
S. Deleval, I. Efthymiopoulos,
S. Evrard, R. Folch, C. Gaignant,
L. Gatignon, G. Georgiev,
K. Hanke, M. Hourican,
M. Lazzaroni, P. Lelong,
R. Mompo, F. Pedrosa, S. Pittet,
R. Steerenberg, J. Somoza,
M. Tavlet, R. Veness
+
ECR-PS egroup,
LIU-PS WP Holders
(included due to potential impacts only – this
change is not part of the LIU-Project)
EATM
Roberto Losito
(on behalf of the IEFC)
DOCUMENT SENT FOR INFORMATION TO:
SUMMARY OF THE ACTIONS TO BE UNDERTAKEN:
- Replace: All magnets, beam stoppers, mechanical supports
- Renovate: Beam instrumentation, vacuum system, magnet interlock system (switch to
WIC system)
- Modify the b.352 / b.157 interface from concrete partition to an airtight wall
- New cooling circuit for magnets
- Remove obsolete cables and pull new cables (signals and DC)
- Reorganize the F61 beam dump
- Reorganize the shielding along the beam line
REFERENCE EDMS NO. REV. VALIDITY
PS-LJ-EC-0009 2038214 0.2 DRAFT
Page 2 of 11
1. EXISTING SITUATION AND INTRODUCTION
Figure 1 illustrates the existing layout in the area that is to be renovated. The area is highlighted
in Figure 2.
Figure 1: Existing layout of equipment it the area
2. REASON FOR THE CHANGE
The East Area renovation will cover the refurbishment of the East Hall with its beam lines and
infrastructure. A re-design of the beam lines is included to improve the magnet situation, the
radiation situation and maintainability in general. The performance of the new beam lines will
be improved in terms of maximum momentum and in choice of particle type. Considerable
energy savings will be possible due to a cycled powering mode of the magnets instead of a
steady state one. Therefore, several magnet families have to be re-designed to be in accordance
with the purposes of the project.
3. DETAILED DESCRIPTION
As part of the renovation of the East Zone, the F61 line will be completely renovated, this
includes the following activities:
1. Replacement of all magnets
2. Renovation of magnet interlock system (Switch to WIC system)
3. Renovation of the beam instrumentation
4. Replacement of beam stoppers
5. Renovation of the vacuum system
6. Replacement of mechanical supports
REFERENCE EDMS NO. REV. VALIDITY
PS-LJ-EC-0009 2038214 0.2 DRAFT
Page 3 of 11
The associated infrastructure will also be renovated:
7. Reorganization of the Dump F61
8. Reorganization of the shielding along the beam line
8. Modification of the interface b.352 / b.157 (Passage from a concrete partition to a
watertight wall)
9. New cooling circuit for magnets
10. Removal of obsolete cables and drawing of new cables (Signals and DC)
11. Surveyors will make a new survey network in b. 352 for F61 alignment
3.1 Removal
Listed is the equipment that is going to be removed:
- Magnets: Element Reference, Element Type
QFO 01 Q 74.03 DHZ 01 MNPA 25.05 QDE 02 Q 12.03
DVT 01 MEA 19.09 DVT 02 MEA 19.04 QFO 03 QFL 08 BHZ 01 M 101*
BHZ 02 M 226 QDE 04 Q 604 SMH 01 MEP 35.03 BHZ 01 MCB 04
QDE 01 Q 120.04B QFO 02 Q 120.01 DVT 01 MNPA 25.09 DHZ 01 M 105.02
- Instrumentation: F61.SEC01, LSD, TFA, MTV01, MTV02, MTV03
- Beam stoppers: F61.STP01, STP02
- Vacuum tubes, gauges, pumps
- Mechanical support of the equipment mentioned above
- Obsolete cables
- Flexible cooling magnet
Figure 2: Area after renovation. Shielding wall along beamline is missing from figure as at this
moment we await the RP simulation.
REFERENCE EDMS NO. REV. VALIDITY
PS-LJ-EC-0009 2038214 0.2 DRAFT
Page 4 of 11
3.2 Equipment to Install
Listed in Table 1, and illustrated in Figure 3, 4 & 5, is the equipment that is to be installed in
the area. It is listed adhering to the naming convention, ref. https://edms.cern.ch/document/1723747/.
Table 1: New equipment
Positional information relative to optics
Layout Component Name
Equipment Code Description
Start Point (m)
End Point (m)
Middle Point (m)
Length (m)
F61.000 Origin 0 0 0 0
F61.MQNCL007 MQNCL Q74L QFO 6.447 7.187 6.817 0.74
F61.BTV012 BTVMC BTV 12.3 0
F61.MCXCE013 MCXCE CR200 DHZ 12.72 12.92 12.82 0.2
F61.MQNEL014 MQNEL Q120 QDE 13.348 14.548 13.948 1.2
F61.MCXCE015 MCXCE CR200 DVT 15.012 15.212 15.112 0.2
F61.TBS016 TBS Beam Stopper #1 16
F61.TBS017 TBS Beam Stopper #2 17
F61.TBS018 TBS Beam Stopper #3 18
F61.TBS019 TBS Beam Stopper #4 19
F61.TBS020 TBS Beam Stopper #5 20
F61.MQNEF021 MQNEF QFL QFO 20.297 21.497 20.897 1.2
F61.BCGAA022 BCGAA LSD 22
F61.XSEC022 XSEC Secondary Emission Chamber 22
F61.BCTF023 BCTF Beam Current Transformer 23
F61.MBXHD025 MBXHD MCB BHZ 23.272 25.772 24.522 2.5
F61.MQNEG030 MQNEG QFS QDE 29.422 30.242 29.832 0.82
F61.MBXHD033 MBXHD MCB BHZ 31.262 33.762 32.512 2.5
F6D.BTV010 BTVMC BTV 10
F62.BTV002 BTVMC BTV 2.357 2.357 2.357 0
F62.MQNEL010 MQNEL Q120 QDE 9.1 10.3 9.7 1.2
F62.MCXCE011 MCXCE CR200 DHZ 10.7 10.9 10.8 0.2
F62.MQNEL012 MQNEL Q120 QFO 11.3 12.5 11.9 1.2
F62.MCXCE013 MCXCE CR200 DVT 12.9 13.1 13 0.2
T08.MBXHD005 MBXHD MCB BHZ 4.075 6.575 5.325 2.5
REFERENCE EDMS NO. REV. VALIDITY
PS-LJ-EC-0009 2038214 0.2 DRAFT
Page 5 of 11
Figure 3: Layout after renovation. Shielding wall along beamline not included, ref. Figure 2.
SmarTeam Item Number: ST0780788
Figure 4: First half the F61 beamline (opposite view from Figure 3)
Figure 5: Second half the F61 beamline (opposite view from Figure 3)
REFERENCE EDMS NO. REV. VALIDITY
PS-LJ-EC-0009 2038214 0.2 DRAFT
Page 6 of 11
Vent PS
To dismantle the Q74 magnet (F61.QFO01), it is necessary to vent the corresponding PS
vacuum sector.
Figure 6: Location of vacuum separation
Change in separation between b.352 and b.157
It is planned to change the separation between b.352 and b.157. An airtight wall will replace
the concrete block wall. As long as the wall is not installed, a concrete block will always be
kept in place to ensure that no access is possible through this passage.
Figure 7: Current (left) and future (right) separation of b.352 and b.157
Radioactive waste
All radioactive waste produced during the East Zone renovation project is listed in this
document: https://edms.cern.ch/document/1968497
REFERENCE EDMS NO. REV. VALIDITY
PS-LJ-EC-0009 2038214 0.2 DRAFT
Page 7 of 11
4. IMPACT ON OTHER ITEMS
4.1 IMPACT ON ITEMS/SYSTEMS
Dedicated cooling circuit The magnet cooling water is in a new closed circuit to contain activated water.
Building interface An airtight wall will replace the concrete block wall as the interface between b.157 and b.352
WIC-system Replaces the obsolete magnet interlock system
4.2 IMPACT ON UTILITIES AND SERVICES
Raw water: No
Demineralized water: Yes, dedicated circuit. https://edms.cern.ch/document/1991994/
Compressed air: Yes
Electricity, cable pulling (power, signal, optical fibres…):
Yes. Intend to re-use the DC cables and the terminal boxes on the walls of b.352.
DEC/DIC: Yes, DEC https://edms.cern.ch/document/1962098/ DIC: submitted by all the groups on SNOW
Racks (name and location):
No
Vacuum (bake outs, sectorisation…):
Yes. Description of the vacuum system after renovation:
https://edms.cern.ch/document/1737544
Special transport/ handling:
No. Notice: No overhead crane is available over the beamline.
Temporary storage of conventional/radioactive components:
Yes
Alignment and positioning:
Yes. Needs described in https://edms.cern.ch/document/1866785/
Scaffolding: No
Controls: Yes
GSM/WIFI networks: No
Cryogenics: No
Contractor(s): Yes
Surface building(s): No
Others: -
REFERENCE EDMS NO. REV. VALIDITY
PS-LJ-EC-0009 2038214 0.2 DRAFT
Page 8 of 11
5. IMPACT ON COST, SCHEDULE AND PERFORMANCE
5.1 IMPACT ON COST
Detailed breakdown of the change cost:
https://edms.cern.ch/document/1961307
Budget code: Detailed in document above
5.2 IMPACT ON SCHEDULE
Proposed installation schedule:
Schedule can be seen (MS Project file): https://espace.cern.ch/en-ea-planning/Shared%20Documents/LS2%20Plannings/LS2_East_Area.mpp
Proposed test schedule (if applicable):
See above
Estimated duration: From the 01/2019 to 08/2020
Urgency: Before closure of the PS (August 2020)
Flexibility of scheduling: Almost none
5.3 IMPACT ON PERFORMANCE
Mechanical aperture: Checked by EN-EA beamline physicist
Impedance: Checked by EN-EA beamline physicist
Optics/MADX File will be provided by EN-EA beamline physicist
Electron cloud (NEG coating, solenoid…)
Non-applicable
Insulation (enamelled flange, grounding…)
Non-applicable
Vacuum performance: 10-3 mbar on the east area side / <2e-8 mbar* after 24h of pumping on the PS side (No change to the PS side). *ref. EDMS 1752123
Others: -
REFERENCE EDMS NO. REV. VALIDITY
PS-LJ-EC-0009 2038214 0.2 DRAFT
Page 9 of 11
6. IMPACT ON OPERATIONAL SAFETY
6.1 ÉLÉMENT(S) IMPORTANT(S) DE SECURITÉ
[Indicate if the change will have an impact on an Elément Important de Sécurité (EIS).
The list of EIS components is available in EDMS document: 1182293 – “Définition et
Inventaire des EIS-Faisceau et EIS-Machine en Opération”.]
Requirement Yes No Comments
EIS-Access x No change to the access system in the PS
EIS-Beam X Beam stoppers: F61.STP01, F61.STP02 will be replaced by 5 new beam stoppers. These beam stoppers are part of the safety chain of EAST AREA EA1 (Described in https://edms.cern.ch/document/1946347/)
EIS-Machine x
6.2 OTHER OPERATIONAL SAFETY ASPECTS
Have new hazards been created or changed?
No
Could the change affect existing risk control measures?
Shielding in b.352 is still being studied (RP monitoring will have to be adapted)
What risk controls have to be put in place?
Standard safety measures. Coordination meetings between ACE and EA teams. Ref. https://indico.cern.ch/event/732724/
Safety documentation to update after the modification
Safety documentation are to be updated and can be found at https://edms.cern.ch/project/CERN-0000094170
Define the need for training or information after the change
N/A
7. WORKSITE SAFETY
[Refer to EDMS document: 1155899 – “Working on the CERN Site”.]
[Following the implementation of the change, the Safety File of the facility shall be
updated. In the temporary absence of the Safety File, the hazards inventory and risk
analysis of the concerned installation shall be established.]
The Launch Safety Agreement (https://edms.cern.ch/document/1731887) describes how
safety is managed in the project. (Provides the safety organization, regulatory tests to
be performed, and particular risks generated by the project).
REFERENCE EDMS NO. REV. VALIDITY
PS-LJ-EC-0009 2038214 0.2 DRAFT
Page 10 of 11
7.1 ORGANISATION
Requirement Yes No Comments
IMPACT – VIC: X Will be done in due time before intervention for each work-package
Operational radiation protection (surveys, DIMR…):
X The whole East Area Renovation project will be treated as ALARA lvl 3
Radioactive storage of material:
X Yes (Stored in b.157)
Radioactive waste: X Ref. https://edms.cern.ch/document/1968497
Non-radioactive waste: X Due to it being a Controlled Radiation Area, all waste is classified as radioactive.
Fire risk/permit (IS41) (welding, grinding…):
X Needed for piping works
Alarms deactivation/activation (IS37):
X Needed for piping works
Others: X
7.2 REGULATORY TESTS
Requirement Yes No Responsible Group
Comments
Pressure/leak tests: X New piping will be tested. Leak tests on vacuum system will be performed
Electrical tests: X All the new cables will be tested
Others: X
7.3 PARTICULAR RISKS
Requirement Yes No Comments
Hazardous substances (chemicals, gas, asbestos…):
X Asbestos might be found during work.
Work at height: X
Confined space working: X
Noise: X
Cryogenic risks: X
Industrial X-ray (tirs radio):
X X-ray tests to check the piping works is foreseen.
REFERENCE EDMS NO. REV. VALIDITY
PS-LJ-EC-0009 2038214 0.2 DRAFT
Page 11 of 11
Ionizing radiation risks (radioactive components):
X [Traceability by TREC.]
Others: X
8. FOLLOW-UP OF ACTIONS BY THE TECHNICAL COORDINATION
Action Done Date Comments
Carry out site activities:
Carry out tests:
Update layout drawings:
Update equipment drawings: PS_LM___0136 to be updated
Update layout database: Existing F61 line in layout database to be removed. Future configuration of F61 will be fully integrated to the layout database: Ref.
https://edms.cern.ch/document/1855540
Update naming database: New naming convention for the East Area (Applicable for F61): Ref.
https://edms.cern.ch/document/1723747
Update optics (MADX)
Update procedures for maintenance and operations
Update Safety File according to
EDMS document 1177755:
Others:
9. REFERENCES
[1] E. Harrouch et al., WPA PS - F61 line modification pendant le long shutdown 2,
EDMS2007648