18
Facilities Budget and Project Update January 26, 2021

Facilities Budget and Project Update

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Facilities Budget and Project Update

January 26, 2021

Agenda

1. Bond Financials

2. Demographic Updates

3. Project Updates

Bo

nd

Fin

anc

ials

Bo

nd

Fin

anc

ials

Demographic Update

Construction Project Updates

Internal and External Factors

● Scope creep.● COVID-19 related supply chain disruptions.● Escalation: as much as three quarters of a percent per month.● Incremental and phased construction.● Facility staff salaries. ● DSA approval delays and building code changes.● Improved bidding environment.

DHS Science and Engineering Building

Status:• Project is trending on budget with about 4 weeks to completion.• $24.M spent through 12/31/20.

Budget: $31.5M was approved. No additional $ needed.

DHS Parking Lot

Status:• Under Construction.• This project will exceed the availability of funds from Measure C. • The project completion was delayed until April 2021.

Budget:• $2.5M budget is adequate.

Frederiksen Elementary School

Status:• Phase 1 complete in June 2021. • Phase 2 bidding March 2021.• Estimated completion fall 2022.

Budget:• $50M on target.• $23.5M spent through December 2020.

Murray Elementary School

Status:• Phase 1 is under construction. • Phase 2 is in design.

Budget:• $69.7M current estimated budget. • $55M was approved.• $14.7M additional needed.• Phase 1 construction cost is over $30M.• Construction cost for Phase 2 is estimated to be

$26.9M.

Dublin Elementary School

Status:• Educational specifications are under development. • The $43M budget can be designed with a combination of renovation to

existing buildings and new construction.

Budget:• $43M current budget $33M was approved.

*This will require the use of $10M of Measure J funds.• $10M additional needed.

Emerald High School

Status:• The project is behind schedule. • Increment 1 is under construction.• Increments 2 and 3 of Phase 1 should be back from DSA in late spring of

2021.• Phase 1 is projected to be completed in the Fall of 2023.• Phase 2 has not yet started design.

Emerald High School

Budget: ● $270M needed to complete Phase 1.● $167M budgeted.● $103M shortfall.● $117.5M needed to complete Phase 2.● $92M budgeted.● $25.5M shortfall.

Additional Budget:● $128.5M budget needed.

District Office

Status:• Renovation has been designed and bid.• Project on hold.

Budget:• $5M was approved. • $3M additional needed to renovate.• $4M additional to provide new construction to replace buildings A and B.

Dublin Crossing Middle School

Status:• Project development stage in progress.• 1,100 student preliminary design target.• Project completion target August 2025.

Budget:• $130.9M current estimated budget.• $85M was approved.• $45.9M additional needed.

Next Steps

At the 2/9 meeting

○ Staff will present a recommendation for immediate / high needs projects.○ Recommend hire a consultant to update Facilities Master Plan.○ Recommend we hire a construction management firm to complete constructability

review and value engineering.

Fall 2021

○ Facilities Master Plan will be complete and presented to Board.○ Facilities workshop will be scheduled to review options based on findings of FMP.○ Board will be asked to update priorities and allocations based on this information to

guide future construction.

Facilities Questions and Discussion