Facilities Project Management Monthly Report
Wednesday, August 15, 2018 230Approved Projects
20BOIE, GREGG J
Kingsbury Hall ‐ North Corridor Tile Floor Repairs1.1‐ PLAN/EST RR
08/14/18, Spaulding floor to give me start schedule 8/14/18. waitng for Granite Glassʹ quote for replacement of
Sturdy threshold ramps.
Design Firm: Contractor: Name:
2014‐2127
Year Approved2019
Funding: DMA
Spaulding Hall ‐ Reverse Fire Doors in G26 for panic hardware1.1‐ PLAN/EST FCR
0814/18, I will discuss with SFMOon 8/16.
Design Firm: Contractor: External Name: Careno Construction
2018‐0212
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Kingsbury Hall ‐ Rm S315 INSTALL EYE WASH AND EMERGENCY SHOWER1.1‐ PLAN/EST FCR
08/14/18,Granite State sent proposal 8/14/18.
Design Firm: Contractor: Name:
2018‐0344
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Elliott Alumni Center ‐ Chiller Replacement Design1.1‐ PLAN/EST RR
08/14/18, Harriman Has PO.
Design Firm: Contractor: Name:
2019‐0003
Year Approved2019
Funding: DMA
Stoke Hall ‐ Rm G50 install and move cubicles in office space1.1‐ PLAN/EST FCR
08/14/18, Chris they will take care of.
Design Firm: Contractor: Name:
2019‐0006
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Tree Removal ‐ Oyster River Blow Down Removal1.1‐ PLAN/EST RR
08/14/18 T&S Construction presented their proposal and I m waiting for tighe and Bond to get back to us.
Design Firm: Contractor: External Name:
2019‐0008
Year Approved2019
Funding: DMA
Spaulding Hall ‐ Greenhouse Room 234 Floor Abatement1.1‐ PLAN/EST RR
08/14/18, EnviroVantage will supply start date on 8/15
Design Firm: Contractor: Name:
2019‐0034
Year Approved2019
Funding: DMA
Leavitt Cntr Transportation Center ‐ Fire Protection Work1.1‐ PLAN/EST FCR
Design Firm: Contractor: Name:
2019‐0042
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Wednesday, August 15, 2018 Page 1 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
James Hall ‐ Rm 348 Eyewash/Shower Installation2‐ IN DESIGN FCR
07/30/18, Should use Granite States proposal.
Design Firm: Contractor: External Name: Granite State /Milestone
2018‐0261
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Demeritt Hall ‐ Quote/Study on Additional Exit Door at 362A to Main Stairway2‐ IN DESIGN FCR
08/14/18,.Sent FCR to Michael Briggs on 6/20.
He is waiting for approval.
Design Firm: Contractor: External Name: Careno Construction
2018‐0330
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Morse Hall ‐ Rm 329 Lab Renovation2‐ IN DESIGN FCR
08/14/2018,Location was changed from 3rd floor to 1st floor. PO sent to SMRT. Tried to set up meeting for
Monday 08/20/18, But Mark McConnell said to hold off funding not identified .
Design Firm: SMRT Contractor: Name:
2018‐0338
Year Approved2019
Funding: COLLEGE / DEPT
ALLOC
Morse Hall ‐ HVAC Unit Replacement and Building Envelope Repairs2‐ IN DESIGN RR
Emergency Repair 08/14/18, Called Legacy chiller and received quote on new split system chiller. I asked Careno to bid on Job.
Design Firm: Contractor: Name:
2019‐0046
Year Approved2019
Funding: INST RR
MacFarlane Greenhouse ‐ Evaluate HVAC Alternatives2.5‐ IN PROCUREMENT FCR
08/14/18, Met with APH and David Goudreault 8/14 to discuss project that will commence on 8/20/18.
Design Firm: Contractor: External Name: APH
2018‐0243
Year Approved2019
Funding: COLLEGE / DEPT
ALLOC
Paul Creative Arts Center ‐ Door Deficiencies Bratton/Johnson Theatre2.5‐ IN PROCUREMENT RR
08/18/18, Careno is ordering the doors.There was no mention of moving a grand piano through these doors
until 8/8/18.
Design Firm: Contractor: External Name: Careno Construction
2018‐0346
Year Approved2019
Funding: DMA
Spaulding Hall ‐ Rm 140 Replacement of Bench/Cabinet2.5‐ IN PROCUREMENT FCR
08/14/18, 14 week delivery on casework . Scheduled to be installed during Christmas break.
Design Firm: Contractor: External Name: Careno Construction
2018‐0349
Year Approved2019
Funding: COLLEGE / DEPT
ALLOC
Rudman Hall ‐ Rm 381 Upgrade Teleconference System2.5‐ IN PROCUREMENT FCR
08/14/18,Meeting @2PM on 8/15/ to discuss to discuss installation.
Design Firm: Contractor: External Name: Yates Electrical
2018‐0366
Year Approved2019
Funding: COLLEGE / DEPT
ALLOC
Wednesday, August 15, 2018 Page 2 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Dimond Library ‐ Interior Painting of Main Lobby3‐ IN CONSTRUCTION RR
08/14/18, Walk through with Tracey, Kevin & APC on 8/15/18 @ 1PM to make sure customer is satified with
results.
Design Firm: Contractor: External Name: APC Services of New
England
2018‐0307
Year Approved2019
Funding: INST RR
Parsons Hall ‐ SmartStack Pilot3.1‐ SUBSTANTIAL COMPLETION FCR
08/14/2018, They will analyze data and setup meeting with Andy and Adam on June 1st. And would like to
keep the beta system in place.
Design Firm: Contractor: External Name: Measured Air Performance
2018‐0245
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Murkland Hall ‐ Exterior Painting3.1‐ SUBSTANTIAL COMPLETION RR
08/14/18, Painting of Entrances complete. (1) Door requires work by FCT.
Design Firm: Contractor: External Name: APC Services of New
England
2018‐0305
Year Approved2019
Funding: INST RR
Rudman Hall ‐ Rm 148 Replacement Environmental Room Humidifier3.1‐ SUBSTANTIAL COMPLETION RR
08/14/18,Technician installed Humidifier . Check out and Calibration completed 7/16/18. Waiting for Invoice
Design Firm: Contractor: External Name: Harris Environmental
Systems Inc.
2018‐0354
Year Approved2019
Funding: DMA
25BRICKETT, ALEXANDER J
Holloway Commons ‐ Retro‐Commissioning Repairs1.1‐ PLAN/EST FCR
7/27/2018_ ‐ RFS has been contacted to establish scope of repairs needed.
Design Firm: RFS Contractor: External Name:
2016‐0500
Year Approved2017
Funding: COLLEGE / DEPT
ALLOC
Whittemore Center ‐ Arena ‐ Ice System Engineering Evaluation1.1‐ PLAN/EST RR
7/27/2018_Meeting on 3/2 indicated that ice system needs replacement. Initial design phase in progress.
Design Firm: Stevens Engineering Contractor: Name:
2018‐0235
Year Approved2018
Funding: INST RR
Whittemore Center Arena ‐ Ice System ‐ Emergency Service Plan1.1‐ PLAN/EST FCR
7/27/2018_Initial meeting date to be determined.
Design Firm: Contractor: Name:
2019‐0020
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Field House ‐ New Ski Locker Room/Team Area2‐ IN DESIGN FCR
7/27/2018_Working with design team for final space renderings.
Design Firm: Harriman Contractor: Name:
2017‐0251
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
Wednesday, August 15, 2018 Page 3 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Parsons Hall ‐ Processed Chilled Water System Replacement2‐ IN DESIGN RR
7/31/2018_ Design work in final stages. Obtaining quotes for work from contractors.
Design Firm: Contractor: Name:
2018‐0048
Year Approved2018
Funding: INST RR
Parsons Hall ‐ Rms N104, N108 Classroom Renovation Iddles Lecture Halls Design
Only2‐ IN DESIGN RR
7/31/2018_ Design in progress.
Design Firm: Harriman Contractor: External Name:
2018‐0145
Year Approved2019
Funding: DMA
Rudman Hall ‐ ARO Autoclave Replacement2.5‐ IN PROCUREMENT RR
7/31/2018__Design documentation received.Obtaining quotes for work from contractors.
Design Firm: Contractor: Name:
2016‐0148
Year Approved2018
Funding: DMA
Utility Distribution ‐ Edgewood Water Tank ‐ Decomissioning3‐ IN CONSTRUCTION FCR
7/31/2018_PO for demolition issued to Charter Bros. Work to occur during winter 2018. Removal of Durham
antennae and reinstallation at Stoke in progress.
Design Firm: Contractor: External Name: Charter Brothers
2010‐0729
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
Presidentʹs House ‐ Building Exterior and Interior Painting and Repairs3‐ IN CONSTRUCTION RR
7/31/2018_Interior and exterior work in progress.
Design Firm: Contractor: Name:
2013‐1032
Year Approved2018
Funding: DMA
Nesmith Hall ‐ Bathroom Renovations3‐ IN CONSTRUCTION RR
7/31/2018_Construction in progress. Anticipated finish date 8/17.
Design Firm: Cowan & Goudreau Contractor: External Name: Greenleaf Construction
2015‐2341
Year Approved2019
Funding: DMA
121 Technology Drive ‐ Advanced Manufacturing Center3‐ IN CONSTRUCTION FCR
7/31/2018_Punchlist items in progress.
Design Firm: JSA, Inc. Contractor: External Name: Careno Construction
2016‐0301
Year Approved2016
Funding: COLLEGE / DEPT
ALLOC
Nesmith Hall ‐ Bathroom Renovations DESIGN ONLY3‐ IN CONSTRUCTION RR
7/31/2018_See project 2015‐2341
Design Firm: Cowan & Goudreau Contractor: Name:
2018‐0096
Year Approved2018
Funding: INST RR
Gregg Hall ‐ Basement Flood Restoration3‐ IN CONSTRUCTION RR
Emergency Repair 7/31/2018_Drywall work to be competed when pump station upgrades are installed. Work to be coordinated
with John OʹRourke.
Design Firm: Contractor: External Name:
2018‐0132
Year Approved2018
Funding: INST RR
Wednesday, August 15, 2018 Page 4 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Whittemore Center ‐ Arena ‐ Concessions Stand Electrical Work3‐ IN CONSTRUCTION FCR
7/31/2018_Yates has finished electrical work. Telecom work in progress.
Design Firm: Contractor: External Name: Yates
2018‐0157
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
Nesmith Hall ‐ Phone‐a‐thon Fit Out3‐ IN CONSTRUCTION SI
7/31/2018_Construction in progress. Work to be completed 9/7.
Design Firm: Harriman Contractor: External Name:
2018‐0166
Year Approved2018
Funding: SARRC ALLOC
Philbrook Hall ‐ Add Fryers to Philbrook Café, Reorganize Existing Equipment and
Access3‐ IN CONSTRUCTION FCR
7/27/2018_PO Issued to Milestone. Working beginning 7/30/2018
Design Firm: Contractor: External Name: Milestone
2018‐0324
Year Approved2019
Funding: COLLEGE / DEPT
ALLOC
Nesmith Hall ‐ Bathroom Improvements and ADA Accessibility Modifications3‐ IN CONSTRUCTION SI
7/31/2018_See project 2015‐2341 for updates.
Design Firm: Cowan & Goudreau Contractor: External Name: Greenleaf Construction
2018‐0339
Year Approved2018
Funding: SARRC ALLOC
121 Technology Drive ‐ Interior Lease Space Renovations3.1‐ SUBSTANTIAL COMPLETION FCR
7/31/2018_Project is substantially complete. Punchlist and completion items ongoing.
Design Firm: Cowan‐Goudreau Contractor: External Name: Careno Construction
2016‐0186
Year Approved2016
Funding: COLLEGE / DEPT
ALLOC
Morse Hall ‐ Third Floor Tempid Water Loop3.1‐ SUBSTANTIAL COMPLETION RR
7/31/2018_Final inspection to be completed.
Design Firm: Contractor: External Name: GSPH
2017‐0004
Year Approved2017
Funding: DMA
Rudman Hall ‐ Rm G51 Flood Restoration3.1‐ SUBSTANTIAL COMPLETION RR
Emergency Repair 7/31/2018_ Ceiling tiles completed. Old refrigerator to be removed when contents are moved.
Design Firm: Contractor: FCT Name: Sprague
2017‐0293
Year Approved2017
Funding: INST RR
Parsons Hall ‐ Rm S222 Minor Renovations3.1‐ SUBSTANTIAL COMPLETION FCR
7/31/2018_Work completed. Punchlist items in progress.
Design Firm: Harriman Contractor: External Name: Yates & GSPH
2018‐0058
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
Wednesday, August 15, 2018 Page 5 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
121 Technology Drive ‐ Fit Up of Unassigned Suite3.1‐ SUBSTANTIAL COMPLETION FCR
7/31/2018_Update ‐ Please refer to ID 2016‐0186 for updates.
Design Firm: Contractor: External Name: Careno Construction
2018‐0062
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
Stoke Hall ‐ Business Service Center Exterior Wall Repairs3.1‐ SUBSTANTIAL COMPLETION RR
7/31/2018_Interior work completed. Drip edge to be installed above exterior door.
Design Firm: Contractor: Name:
2018‐0213
Year Approved2018
Funding: DMA
Rudman Hall ‐ G Level Flood Restoration and Repair3.1‐ SUBSTANTIAL COMPLETION RR
Emergency Repair 7/31/2018_All affected areas have been repaired. Equipment replacement in progress.
Design Firm: Contractor: Name:
2018‐0230
Year Approved2018
Funding: INST RR
James Hall ‐ AHU‐3 Failure Investigation and Repair3.1‐ SUBSTANTIAL COMPLETION RR
Emergency Repair 7/31/2018_Repairs and room reconditioning finished. Final commisioning and setpoints being work on.
Design Firm: Contractor: Name:
2018‐0309
Year Approved2018
Funding: INST RR
8GEUTHER, MARK E
Taylor Hall ‐ Flood Repairs and Abatement1.1‐ PLAN/EST RR
Emergency Repair
Design Firm: Contractor: Name:
2019‐0043
Year Approved2019
Funding: INST RR
Campus ‐ Huddleston Fairchild Hetzel Site Stairs Design2‐ IN DESIGN RR
07‐25‐2018: Engineer has several egress questions for the SFMO. Time will be scheduled on the SFMO Agenda
for September.
Design Firm: Hoyle‐Tanner Contractor: External Name: TBD
2018‐0294
Year Approved2018
Funding: INST RR
Water Treatment Plant ‐ New Construction3‐ IN CONSTRUCTION SI
07‐25‐2018: Concrete tank work ongoing. Site work on going. Foundations started.
Design Firm: Woodard & Curran Contractor: External Name: Waterline Industries
2008‐0038
Year Approved2014
Funding: SARRC ALLOC
Utility Distribution ‐ HHW and Sewer Line Replacement College Road to Kendall and
Nesmith3‐ IN CONSTRUCTION RR
07‐25‐2018: Water and sewer lines scheduled to be completed 8‐3. Heating line work in on going and
scheduled to be completed no later than 8‐17‐2018.
Design Firm: Harriman/Tighe & Bond Contractor: External Name: Waterline Industries
2017‐0093
Year Approved2019
Funding: DMA
Wednesday, August 15, 2018 Page 6 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Outdoor Facility ‐ New Soccer/Lacrosse Field3‐ IN CONSTRUCTION FCR
07‐25‐2018: Contractor scheduled to mobilize 8‐6‐18.
Design Firm: Tighe & Bond Contractor: External Name: R.A.D. Sports
2017‐0285
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
Utility Distribution ‐ Reconfigure and Relocation of Colovos SSL0109 and SSL04863‐ IN CONSTRUCTION RR
07‐25‐2018: Sewer manhole in McDaniel Dr. scheduled to be completed 07‐27‐2018. Work on the sewer line
from Ritzman to Gregg scheduled to start the week of 7‐30‐18.
Design Firm: Tighe & Bond Contractor: External Name: T&S Construction
2018‐0183
Year Approved2018
Funding: INST RR
Chase Ocean Engineering Lab ‐ Expansion3.1‐ SUBSTANTIAL COMPLETION FCR
07‐25‐2018: Transformer swap out complete. Waiting on delivery of equipment being coordinated by PI.
Design Firm: HL Turner Contractor: External Name: Milestone Engineer &
Construction
2015‐2755
Year Approved2016
Funding: COLLEGE / DEPT
ALLOC
Chase Ocean Engineering Lab ‐ Tank Room Ceiling Restoration and Replacement of
HV‐33.1‐ SUBSTANTIAL COMPLETION RR
07‐25‐2018: HV‐3 installation complete.
Design Firm: HL Turner Contractor: External Name: Milestone
2017‐0153
Year Approved2018
Funding: DMA
18HECKLER, BARBARA K
Parsons Hall ‐ Installation of Exterior Window Film1.1‐ PLAN/EST FCR
7/27/2018: Will approach Milestone in early September.
Design Firm: Contractor: Name:
2016‐0425
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Thompson Hall ‐ Replace Furniture1.1‐ PLAN/EST FCR
7/27/2018: Origianal posters failed. Goal is to reproduce and reinstall by late August.
Design Firm: Contractor: FCT Name:
2017‐0087
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
1 Leavitt Lane ‐ 1st and 2nd Floor Paint and Carpet Estimate1.1‐ PLAN/EST FCR
7/27/2018:Estimate for full scope far exceeded available budget. Estimate(s) being sought for much reduced
scope. Goal is to have new estimates by Labor Day.
Design Firm: Contractor: Name:
2018‐0311
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Elliott Alumni Renovations2‐ IN DESIGN FCR
7/27/2018: Phase 1‐RM 102 on hold. Planning for RMS B03, B03C to begin in September.
Design Firm: Contractor: External Name: Milestone
2018‐0021
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Wednesday, August 15, 2018 Page 7 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Dimond Library ‐ Room 402 Flooring Replacement2‐ IN DESIGN RR
Design Firm: Contractor: Name:
2018‐0135
Year Approved
Funding: DMA
Stoke Hall ‐ Registrarʹs Office Minor Renovation2‐ IN DESIGN SI
7/27/2018: Will meet with RO in September.
Design Firm: Contractor: Name:
2018‐0175
Year Approved2018
Funding: SARRC ALLOC
Field House ‐ Womens Team Locker Room Upgrades ‐ Planning Only2‐ IN DESIGN SI
7/27/2018: Meeting to review Harrimanʹs concept drawings scheduled for 7/27.
Design Firm: Contractor: Name:
2018‐0198
Year Approved2018
Funding: SARRC ALLOC
Stoke Hall ‐ First Floor Renovation/Paul College Program2‐ IN DESIGN FCR
7/27/2018: Goal is to have concept design complete by mid‐September..
Design Firm: Contractor: Name:
2018‐0225
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Thompson Hall ‐ Graduate Student Center2.5‐ IN PROCUREMENT SI
7/27/2018: Goal is to complete by late‐August/early September completion. Furniture installation information
expected 7/27.
Design Firm: Contractor: External Name:
2017‐0212
Year Approved2017
Funding: SARRC ALLOC
Zais Hall ‐ Rm 205 Carpet/Flooring Replacement2.5‐ IN PROCUREMENT RR
7/27/2018: On track for completion by late August.
Design Firm: Contractor: Name:
2018‐0359
Year Approved2019
Funding: DMA
Health & Wellness Building ‐ Physical Reorganization of Services3‐ IN CONSTRUCTION FCR
7/27/2018: Project in track to be complete by late August.
Design Firm: Harriman A/E Contractor: Name:
2017‐0340
Year Approved2017
Funding: COLLEGE / DEPT
ALLOC
Dimond Library ‐ Minor Renovation for Customer Service and Addison Areas3‐ IN CONSTRUCTION FCR
7/27/2018: Goal is to complete by 7/20.
Design Firm: Contractor: External Name:
2017‐0423
Year Approved2019
Funding: COLLEGE / DEPT
ALLOC
Taylor Hall ‐ Rm 102 Create Wall and Door Accesss3‐ IN CONSTRUCTION FCR
7/27/2018: Project expected complete by early August.
Design Firm: Contractor: External Name: Milestone
2018‐0148
Year Approved2019
Funding: COLLEGE / DEPT
ALLOC
Wednesday, August 15, 2018 Page 8 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Nesmith Hall ‐ Room Improvements G17 ‐ G253‐ IN CONSTRUCTION SI
7/27/2018: Project expected complete by 9/13.
Design Firm: Contractor: External Name: milestone
2018‐0173
Year Approved2018
Funding: SARRC ALLOC
Dimond Library – Room 221 Renovation3‐ IN CONSTRUCTION SI
7/27/2018: Project on track to be complete by 8/20.
Design Firm: Contractor: Name:
2018‐0179
Year Approved2018
Funding: SARRC ALLOC
Nesmith Hall ‐ Upward Bound / Talent Search Relocation3‐ IN CONSTRUCTION SI
7/27/2018: Project expected complete by 8/23.
Design Firm: Contractor: External Name: Careno
2018‐0202
Year Approved2018
Funding: SARRC ALLOC
Pettee Hall ‐ Rm G18 Mold Remediation and Investigation3‐ IN CONSTRUCTION RR
Emergency Repair 7/27/2018: Project on track to be complete by 7/27.
Design Firm: Contractor: Name:
2018‐0251
Year Approved2018
Funding: INST RR
Nesmith Hall – Rm G00CRA Modifications3‐ IN CONSTRUCTION SI
7/27/2018: Project expected complete by 9/13.
Design Firm: Contractor: Name:
2019‐0002
Year Approved2018
Funding: SARRC ALLOC
30HENRY, PAUL A
Huddleston Hall ‐ Fire Code Assessment and Life Safety Plan1.1‐ PLAN/EST RR
Design Firm: SFC Engineering Partnership Contractor: Name:
2012‐0841
Year Approved2019
Funding: DMA
Huddleston Hall ‐ Ballroom AC Installation and Electrical Service1.1‐ PLAN/EST FCR
Design Firm: Harriman Associates Contractor: External Name: External
2016‐0010
Year Approved
Funding: COLLEGE / DEPT
ALLOC
FY19 Road Repairs and Crack Sealing1.1‐ PLAN/EST RR
6‐26‐18 No scope this summer
Design Firm: Contractor: External Name: TBD
2017‐0024
Year Approved2019
Funding: INST RR
Huddleston Hall ‐ Creation of Offices within Carsey School1.1‐ PLAN/EST FCR
6‐26‐18 met with team, waiting on final musical chairs with the Egress project Summer 2019
Design Firm: Harriman Contractor: External Name:
2017‐0402
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Wednesday, August 15, 2018 Page 9 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Parking & Transit Center ‐ Seal cracks in parking lot1.1‐ PLAN/EST FCR
8‐15‐18 Transportation decided to defer to summer of 2019
ʹ
6‐26‐18 have list of lots have asked 3 contactors for proposals, gave 6‐29‐18 as deadline
Design Firm: Contractor: External Name: TBD
2018‐0317
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Field House ‐ Walk of Memories Campus Tribute Gifts1.1‐ PLAN/EST FCR
6‐26‐18 meeting with Steve Pesci to discuss
Design Firm: Contractor: Name:
2018‐0367
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Mills Hall ‐ Cooling Towers Replacement1.1‐ PLAN/EST FCR
8‐15‐18 Getting Design Proposal from Harriman
Design Firm: Contractor: Name:
2018‐0370
Year Approved
Funding: COLLEGE / DEPT
ALLOC
South Drive ‐ Design Advancement2‐ IN DESIGN SI
6‐26‐18 T&B recently estimated project at DD, up dated estimate
Design Firm: Tighe & Bond Contractor: External Name:
2013‐1115
Year Approved2013
Funding: SARRC ALLOC
Huddleston Hall ‐ Design of Egress Modifications2‐ IN DESIGN RR
6‐26‐18 MEP Study ready for review next week, DD for building mid July.
Design Firm: Harriman Contractor: External Name: Harriman
2013‐1155
Year Approved2017
Funding: DMA
Huddleston Hall ‐ Roof Replacement Design Only2‐ IN DESIGN RR
6‐26‐18 Harriman working with ARM to include the design. Starting roof investigation 2013‐1155
Huddleston Egress project.
Design Firm: ARM Contractor: External Name: Harriman
2016‐0165
Year Approved2017
Funding: DMA
New England Center ‐ Adams Tower ‐ Separation of HHW and DHW Design Only2‐ IN DESIGN RR
6‐26‐18 Design is in final review, project split between Energy and Hosing construction summer 2019
Design Firm: Harriman Contractor: External Name: TBD
2016‐0402
Year Approved2017
Funding: INST RR
Philbrook Hall ‐ Kitchen Modifications2‐ IN DESIGN FCR
6‐26‐18 Selected Charter Brothers as CMAR, will start Pre‐Construction Services to explor the site this summer
Design Firm: Harriman Contractor: External Name: Charters Brothers
2017‐0399
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
Wednesday, August 15, 2018 Page 10 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Campus ‐ Main Street West Bus Pads, Shelters, AVL2‐ IN DESIGN SI
6‐26‐18 Working on details for Summer Installation Have design proposal from Tighe & Bond, Steve is
requesting an exception for design to proceed.
Design Firm: Tighe & Bond Contractor: External Name: Tighe & Bond
2017‐0438
Year Approved
Funding: GRANT
Utility Distribution ‐ College Brook Culvert Repair2‐ IN DESIGN RR
6‐26‐18 Exposted site, have to remove electrical duct bank to do work, working with Energy to incluce some
High Voltage work to take atvanatve of moving the switches above ground, meeting next week.
Design Firm: Tighe & Bond Contractor: External Name: TBD
2018‐0100
Year Approved2019
Funding: DMA
Campus ‐ Lee Circle Water Extension2‐ IN DESIGN FCR
6‐26‐18 Meet with team, consultant working on Design
Design Firm: Underwood Eng Contractor: External Name: TBD
2018‐0256
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Horton Social Science Center ‐ 3rd Floor Daiken Unit Recommissioning2.5‐ IN PROCUREMENT FCR
6‐26‐18 Operations locked out the Heat, checking to see if we still want to Retro‐Commission the system.
Design Firm: Harriman / RFS Contractor: External Name: RFS / Harriman
2018‐0295
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
Morse Hall ‐ Fire Damper Repairs2.5‐ IN PROCUREMENT FCR
6‐26‐18 Issued PPʹs to Milestone, they are gearing up to start first building.
Design Firm: Contractor: External Name: Milestone
2018‐0326
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
Gregg Hall ‐ Fire Damper Repairs2.5‐ IN PROCUREMENT FCR
6‐26‐18 Issued PPʹs to Milestone, they are gearing up to start first building.
Design Firm: Harriman Contractor: External Name: Milestione
2018‐0327
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
Horton Social Science Center ‐ 1st Floor Renovation ‐ Phase 23‐ IN CONSTRUCTION SI
6‐26‐18 Abatement and Demo complete, working on framing and rough in of electrical and HVAC.
Design Firm: Harriman Contractor: External Name: Milestone
2008‐0203
Year Approved2018
Funding: SARRC ALLOC
Philbrook Hall ‐ Refrigeration Rack System3‐ IN CONSTRUCTION FCR
6‐26‐18 in construction, CB making great progress
Design Firm: Harriman Assoc. Contractor: External Name: Charter Brothers
2015‐2492
Year Approved2015
Funding: COLLEGE / DEPT
ALLOC
Wednesday, August 15, 2018 Page 11 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
FY19 Site Stair Repairs3‐ IN CONSTRUCTION RR
6‐26‐18 Ed Kimball working on repairs
Design Firm: Contractor: External Name: TBD
2017‐0026
Year Approved2019
Funding: INST RR
FY19 Sidewalk and Walkway Repairs3‐ IN CONSTRUCTION RR
6‐26‐18 work under way with T&S and JTI
Design Firm: Contractor: External Name: T&S / JTI
2017‐0027
Year Approved2019
Funding: INST RR
Hewitt Hall ‐ Fire Damper Repairs3‐ IN CONSTRUCTION FCR
8‐1‐18 Milestone, Started work 7‐30‐18
Design Firm: Harriman Contractor: External Name: Milestione
2018‐0325
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
DPW Grounds & Roads ‐ Garage3.1‐ SUBSTANTIAL COMPLETION FCR
6‐26‐18 workign out fire calking details with Careno and some minor plumbing deficiencies witht the existing
power washer. Will re‐schedule C of O inspection after reviewing contractor SFMO binder
Design Firm: Careno Contractor: External Name: Careno
2013‐1610
Year Approved2014
Funding: COLLEGE / DEPT
ALLOC
Morse Hall ‐ Rm 345 Renovations3.1‐ SUBSTANTIAL COMPLETION FCR
6‐26‐18 Contacted stakeholder, he would like to wait and expand the system. Working with EHS on details
of new control panel to be located in the corridor.
Design Firm: Harriman Contractor: External Name: TBD
2015‐2384
Year Approved2015
Funding: COLLEGE / DEPT
ALLOC
Hood House ‐ Minor Renovation for Career and Professional Success Center3.1‐ SUBSTANTIAL COMPLETION SI
6‐26‐18 Project in punch list, occupants in the building.
Design Firm: Mannypenny Murphy Contractor: External Name: Trumbell Nelson
2016‐0409
Year Approved2016
Funding: SARRC ALLOC
Conant Hall ‐ Minor Interior Renovations3.1‐ SUBSTANTIAL COMPLETION SI
6‐26‐18 Building occupied Working on punch List, and finishing MEP improvements
Design Firm: Mannypenny Murphy Contractor: External Name: Trumbell Nelson
2016‐0410
Year Approved2017
Funding: SARRC ALLOC
Campus ‐ UNH Fire Damper Study3.1‐ SUBSTANTIAL COMPLETION FCR
6‐26‐18 buildings Survey complete, for first 4 buildings.
Design Firm: Harriman Contractor: Name:
2017‐0205
Year Approved2017
Funding: COLLEGE / DEPT
ALLOC
Conant Hall ‐ DDC Controls Installation3.1‐ SUBSTANTIAL COMPLETION RR
6‐26‐18 fiinish commissioning
Design Firm: Harriman Contractor: Name:
2018‐0192
Year Approved2018
Funding: DMA
Wednesday, August 15, 2018 Page 12 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
New England Center ‐ Flood Damage Restoration and Repairs3.1‐ SUBSTANTIAL COMPLETION RR
Emergency Repair 6‐26‐18 waiting for fin tube covers
Design Firm: Contractor: External Name: Milestione
2018‐0228
Year Approved2018
Funding: INST RR
30HOUDE, DONALD A
Utility Distribution ‐ Eversource Transmission Line1.1‐ PLAN/EST SI
8‐23‐18 New site review of locations with stone walls. 4‐19‐18 (no change) Have met several time we are
moving forward, UNH and EverSource are working on our MOU for this project. Expect notification first of
Jan for 2018 or 2019 start. We are still discusing the new requirements in the MOU. I expect a 2019 start.
Design Firm: Contractor: Name:
2016‐0277
Year Approved
Funding: SARRC ALLOC
1 Leavitt Lane ‐ Card Access Expansion1.1‐ PLAN/EST FCR
08‐10‐‐18 Customer showing new interest. We have a meeting on 8‐22‐18
Design Firm: Bruce Chaimbelan Contractor: External Name: Yates
2017‐0451
Year Approved2019
Funding: COLLEGE / DEPT
ALLOC
Gables Building B ‐ Install card access key lock box Main Office1.1‐ PLAN/EST FCR
8‐14‐18 Re‐newed interest/ I have showed a contractor, waiting for an estimate.
Design Firm: Contractor: FCT Name:
2018‐0171
Year Approved2019
Funding: COLLEGE / DEPT
ALLOC
West Edge AVL Transit Signs Install1.1‐ PLAN/EST FCR
7‐23‐18 Waiting for the client to let us know the new Bus stops have been installed.
Design Firm: Contractor: Name:
2018‐0190
Year Approved
Funding: GRANT
Campus ‐ Installation of new EMS Scheduling Software1.1‐ PLAN/EST FCR
7‐23‐18 New project, Met with Marshall and Nora Molloy. Also spoke to Gail about ADA req. Met with
Telecom for a quote. This requires a contractot to mount the unit asking Yates.
Design Firm: Contractor: Name:
2018‐0365
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Combined Heat & Power Plant ‐ Management for Installation of Transformer1.1‐ PLAN/EST FCR
8‐14‐18 Put out second notice last week. Ready to do on Saturday am.
Design Firm: Contractor: Name:
2019‐0018
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Williamson Hall ‐ Management of Stepdown Transformer for Williamson &
Christensen1.1‐ PLAN/EST FCR
7‐24‐18 New project meeting with customer.
Design Firm: Contractor: Name:
2019‐0019
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Wednesday, August 15, 2018 Page 13 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Parking & Transit Center ‐ Replace line conditioner1.1‐ PLAN/EST FCR
7‐30‐18 New getting estimate.
Design Firm: Contractor: Name:
2019‐0023
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Campus ‐ District System Heat Exchanger Cleaning1.1‐ PLAN/EST FCR
8‐14‐18 New will check into details. Working with Matt and Purchasing.
Design Firm: Contractor: Name:
2019‐0024
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Rudman Hall ‐ Automated Doors1.1‐ PLAN/EST FCR
8‐08‐18 I have shown a contractor. Waiting for cost to come in.
Design Firm: Contractor: Name:
2019‐0026
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Aquaculture Lab ‐ Building System Repairs1.1‐ PLAN/EST FCR
8‐14‐18 New project , getting information.
Design Firm: Contractor: Name:
2019‐0045
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Stoke Hall ‐ High Voltage Replacement ‐ Design Only2‐ IN DESIGN FCR
7‐23‐18 Harriman is working on this design.
Design Firm: Harriman Contractor: External Name: Yates support only.
2018‐0312
Year Approved
Funding: COLLEGE / DEPT
ALLOC
MacFarlane Greenhouse ‐ Renovation/Improvements2‐ IN DESIGN FCR
7‐23‐18 The engineerinf firm SMRT has a PO for this work. The design is in progress.
Design Firm: SMRT Contractor: Name:
2019‐0001
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
Kingsbury Hall ‐ Installation/Services for Card Access to Engineering Library S2362‐ IN DESIGN FCR
7‐23‐18 Re‐pricing , removing camera and relocation of door.
Design Firm: Contractor: External Name: Yates, Burns.
2018‐0351
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Leavitt Cntr Transportation Center ‐ Bus Maintenance Lift Replacements2.5‐ IN PROCUREMENT FCR
7‐23‐18 Working with UNH Purchasing. Questions due to answers today.
Design Firm: Contractor: External Name: Design build
2017‐0447
Year Approved2018
Funding: GRANT
Wednesday, August 15, 2018 Page 14 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
McConnell Hall ‐ Room 458 Renovation2.5‐ IN PROCUREMENT FCR
7‐23‐18 I am waiting for an valid funding source.
Design Firm: Contractor: External Name: Milestone E & C
2018‐0206
Year Approved2019
Funding: COLLEGE / DEPT
ALLOC
Cole Hall ‐ HVAC HU‐3 EQ5389 Cat Walks and Accessibility Modifications3‐ IN CONSTRUCTION RR
7‐23‐18 This project is in progress.
Design Firm: Oak Point Contractor: External Name: Milestone E & C
2018‐0086
Year Approved2019
Funding: DMA
Kingman Main Lab ‐ Greenhouse Electrical Circuit Installations3‐ IN CONSTRUCTION FCR
7‐23‐‐18 This project is in progress.
Design Firm: Contractor: External Name: Yates
2018‐0209
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Campus ‐ FY18 Electric Meter Repairs3‐ IN CONSTRUCTION FCR
7‐23‐18 Meters have been replaced in Dimond and Congreve. James hall will receive a new meter on the
transformer once we get set up . This will require a shutdown. IC Reed will do this portion.
Design Firm: Contractor: External Name: Yates
2018‐0214
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Dimond Library ‐ Rm G01 Display Install3‐ IN CONSTRUCTION FCR
7‐23‐18 This project is in construction this week.
Design Firm: Contractor: External Name: Milestone
2018‐0231
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Observatory ‐ Replace Existing Shed3‐ IN CONSTRUCTION FCR
7‐23‐18 (dept self help project) The new shed is in place. Concrete ramps were poured, we will install
electricity next.
Design Firm: Contractor: External Name: Milestone
2018‐0234
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Morse Hall ‐ Security Upgrades Including Card Readers and Video Cameras3‐ IN CONSTRUCTION FCR
7‐23‐18 Work is in Progress. About 60% complete.
Design Firm: Contractor: External Name: Yates, Burns
2018‐0322
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
Dining Buildings ‐ Add Digital Menu Boards To Dining and Retail Outlets3‐ IN CONSTRUCTION FCR
7‐23‐18 Circuits for power have been installed in Philbrook, Stillings will be next.
Design Firm: Contractor: External Name: Yates
2018‐0333
Year Approved2019
Funding: COLLEGE / DEPT
ALLOC
Wednesday, August 15, 2018 Page 15 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Telecommunications Center ‐ Generator3‐ IN CONSTRUCTION FCR
7‐23‐18 The customer has the FCR and other information. I am waiting for Funding to proceed.
Design Firm: Contractor: External Name: Yates
2018‐0352
Year Approved2019
Funding: COLLEGE / DEPT
ALLOC
1 Leavitt Lane ‐ New Circuits For Data Center3‐ IN CONSTRUCTION FCR
7‐23‐18 New Project the customer is has hired the contractor directly I will oversee the work and assist with
permits. Work is in progress.
Design Firm: Contractor: External Name:
2019‐0005
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Jackson Lab ‐ Autoclave Replacement3.1‐ SUBSTANTIAL COMPLETION RR
7‐23‐18 This new AutoClave has been connected and gone through a factory start up. Ready to turn over to
dept. Contractor has to address floor issues.
Design Firm: Contractor: FCT Name:
2017‐0377
Year Approved2019
Funding: DMA
Utility Distribution ‐ HV ‐ Circuit 11 Hamilton Smith to Memorial Union Phase II3.1‐ SUBSTANTIAL COMPLETION SI
7‐23‐18 We only have paving to complete. .
Design Firm: Contractor: External Name:
2018‐0067
Year Approved2018
Funding: SARRC ALLOC
Wildcat Stadium Parking Lot ‐Pay & Display Meter Installation & Pad3.1‐ SUBSTANTIAL COMPLETION FCR
7‐23‐18 The project is 90% complete waiting for Bollard covers. Contractor says they are going in this week.
Design Firm: Contractor: External Name: T&S const
2018‐0150
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
Thompson Hall ‐ Card Access and Security Camera Cable Pathways3.1‐ SUBSTANTIAL COMPLETION FCR
7‐23‐18 This project construction part is complete. I am working with the department and Housing to get the
testing and programming completed.
Design Firm: Contractor: External Name: Yates
2018‐0246
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe3.1‐ SUBSTANTIAL COMPLETION FCR
7‐23‐18 This project, the construction side is complete, Programming and testing still needs to be done.
Design Firm: Contractor: External Name: Yates Electric
2018‐0314
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
33PARSONS, STEPHANIE E
Campus ‐ Housing Fire Alarm/CO Detection1.1‐ PLAN/EST FCR
8/17/18: Received information from Housing on 6/20. Plan to review current and future efforts with SFMO
during September / October meetings.
Design Firm: SFC Engineering Contractor: External Name: TBD
2018‐0191
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Wednesday, August 15, 2018 Page 16 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Holloway Commons ‐ Bi‐Directional Amplifier Installation1.1‐ PLAN/EST FCR
8/17/18: This design will follow completion of Hamilton Smith installation.
Design Firm: Norris Inc. Contractor: External Name: TBD
2018‐0224
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Rudman Hall ‐ Retrofit Rm B52 for ABSL‐2 Containment1.1‐ PLAN/EST FCR
8/17/18: This project will involve extensive relocation effort for BAS cyberstation currently located in B52.
Design work for this renovation will include need for sink / eyewash, drainage is not readily availabe in the
basement level.
Design Firm: TBD Contractor: External Name: TBD
2019‐0012
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Rudman Hall ‐ Fire Alarm Replacement DESIGN2‐ IN DESIGN RR
6/21/18 ‐ Design review ongoing, installation of fire alarm is scheduled for Summer 2019.
Design Firm: SFC Engineering Contractor: External Name: TBD
2013‐1149
Year Approved2015
Funding: DMA
Hewitt Hall ‐ Fire Alarm Replacement2‐ IN DESIGN RR
8/17/18: Design ongoing, anticipate drawings for review by 8/31/18. Anticipate construction to begin
December 2018.
Design Firm: SFC Engineering Contractor: External Name: TBD
2015‐2306
Year Approved2019
Funding: DMA
Rudman Hall ‐ Conversion to DDC Controls2‐ IN DESIGN RR
8/17/18 ‐see ID 2010‐0479 for updates.
Design Firm: Contractor: External Name: TBD
2015‐2336
Year Approved2018
Funding: DMA
Rudman Hall ‐ Fire Alarm Replacement2‐ IN DESIGN RR
8/17/18 ‐ Please see ID 2010‐0479 for updates.
Design Firm: SFC Contractor: External Name: TBD
2015‐2352
Year Approved2016
Funding: DMA
Hamilton Smith Hall ‐ Bi‐Directional Amplifier Installation2‐ IN DESIGN RR
8/17/18: Working with Notifier / Norris for BDA design and quotes. Funding is in place, intend to have this
work in place by December 2018.
Design Firm: Norris Inc. Contractor: External Name: TBD
2016‐0116
Year Approved2019
Funding: DMA
Rudman Hall ‐ DDC Controls Backstop2‐ IN DESIGN RR
8/17/18 ‐ see ID 2010‐0479 for updates
Design Firm: Contractor: Name:
2017‐0288
Year Approved2019
Funding: DMA
Wednesday, August 15, 2018 Page 17 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Whittemore Center ‐ Arena ‐ Dehumidification System Design Only2‐ IN DESIGN FCR
8/17/18 Design development drawings submitted to UNH 8/3 for review. Meeting will be scheduled week of
9/3 to review DD drawings and make any additonal edits. This project is scheduled for construction
completion by May 2019.
Design Firm: Harriman Contractor: External Name: TBD
2017‐0308
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Rudman Hall ‐ Level G Instruction Lab Support Expansion2‐ IN DESIGN SI
8/17/18: SMRT is working on design development drawings for this project. Anticipate design draft drawings
for UNH review week of 8/27.
Design Firm: SMRT Contractor: External Name: TBD
2017‐0418
Year Approved2017
Funding: SARRC ALLOC
Hewitt Hall ‐ Rm G02 renovations2‐ IN DESIGN FCR
8/17/18: Nursing considering use of furniture for this project in lieu of full renovation of space. Meeting with
users 8/30 to discuss technology.
Design Firm: Lavallee Brensinger Contractor: External Name: TBD
2018‐0110
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Philbrook Hall ‐ Boiler Replacement2‐ IN DESIGN BAR
8/17/18: Boiler is not being installed until 2018‐0162 forensic review is complete.
Design Firm: Harriman Contractor: External Name: Eckhardt Johnson
2018‐0149
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
Philbrook Hall ‐ Boiler Forensic Investigation2‐ IN DESIGN RR
8/17/18: RFX for forensic study did not provide any interest. Currently exploring opportunity with term
engineering firms to provide alternate heating source in event of steam outage.
Design Firm: RFS Contractor: External Name: TBD
2018‐0162
Year Approved2018
Funding: DMA
Whittemore Center ‐ Arena ‐ Bi‐Directional‐Amplifier Installation2‐ IN DESIGN FCR
8/17/18 This design will be completed after Hamilton Smith and Holloway Commons.
Design Firm: SFC Engineering Contractor: External Name: TBD
2018‐0222
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Rudman Hall ‐ Laboratory Fume Hood Control System Replacement2.5‐ IN PROCUREMENT RR
8/17/18 SMRT to prepare plans for make ready work for AHU isolation is being scheduled for December 2018
with new HVAC control improvements to begin summer 2019. RFX for CMAR issued to UNH procurement.
Design Firm: SMRT, Inc. Contractor: External Name: TBD
2010‐0479
Year Approved2017
Funding: DMA
McLaughlin Hall ‐ Fire Alarm System Replacement2.5‐ IN PROCUREMENT FCR
8/17/18: Design is 90% complete. Will discuss the installation of systsem CO detection with SFMO during
September monthly meeting prior to finalizing design. Intent to have bid and contractor awarded by
December. Construction to begin May 2019.
Design Firm: SFC Contractor: External Name: TBD
2018‐0340
Year Approved2019
Funding: COLLEGE / DEPT
ALLOC
Wednesday, August 15, 2018 Page 18 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Service Building ‐ Fire Alarm Replacement and Building System Upgrades3‐ IN CONSTRUCTION RR
8/17/18: Minor heating and domestic hot water line repairs are ongoing with anticipated completion by 8/17.
AHU serving floor1 will be relocated October 2018.
Design Firm: Harriman Contractor: External Name: Charters Brothers
2009‐0064
Year Approved2018
Funding: DMA
Hamel Recreation Center ‐ Expansion & Renovations3‐ IN CONSTRUCTION CP
6/29/18: AWF on floor 3 is complete. Floor 3 has been turned over to Campus Recreation.
Design Firm: HGA Contractor: FCT Name: Shawmut
2013‐1176
Year Approved2013
Funding: COLLEGE / DEPT
ALLOC
Service Building ‐ Replacement and Installation of Isolation valves3‐ IN CONSTRUCTION RR
6/21/18 ‐ Please see project ID 2009‐0064 for updates and budget.
Design Firm: N/A Contractor: External Name: TBD
2013‐1465
Year Approved2016
Funding: DMA
Service Building ‐ Dispatch Center Keltron System3‐ IN CONSTRUCTION FCR
8/17/18: Keltron coordination meeting being scheduled to review system operation before proceeding to next
location for infrastructure.
Design Firm: Contractor: External Name: Norris / UNH Telecom
2016‐0123
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
Paul College ‐ HVAC and Control Modifications from Original Construction3‐ IN CONSTRUCTION FCR
8/17/18: Chilled beam solution has not been performing as desired, however at time of inquiry there were
noted problems with the chiller. Additional balancing will be scheduled for further troubleshoot.
Design Firm: RFS Contractor: External Name: TBD
2016‐0295
Year Approved2016
Funding: SARRC ALLOC
Gregg Hall ‐ Chiller Replacement ‐ Funding for Construction3‐ IN CONSTRUCTION RR
8/17/18: Please refer to project 2017‐0281 for updates on construction.
Design Firm: Harriman Contractor: External Name: TBD
2017‐0250
Year Approved2019
Funding: DMA
Gregg Hall ‐ Chiller Replacement3‐ IN CONSTRUCTION RR
8/17/18: This project was awarded to Charters Brothers. Currently waiting for executed contracts. Will begin
scheduling efforts early September.
Design Firm: Harriman Contractor: External Name: Charters Brothers
Construction
2017‐0281
Year Approved2017
Funding: DMA
Field House ‐ Steam to Domestic Hot Water System Replacement3‐ IN CONSTRUCTION RR
8/17/18: Will begin working with NPI / athletics / Operations end of August to discuss schedule and phasing
to install new units with minimum to no impact within the building.
Design Firm: Harriman Contractor: External Name: Northern Peabody
2017‐0325
Year Approved2018
Funding: DMA
Wednesday, August 15, 2018 Page 19 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
James Hall ‐ Heat Exchanger and Potable ‐ Non Potable Water Heater Replacements3‐ IN CONSTRUCTION RR
8/17/18: Unforeseen work identified when scheduling replacement. Waiting for electric water heater design
for back up prior to proceeding with steam shutdown.
Design Firm: Harriman Associates Contractor: External Name: NPI
2017‐0393
Year Approved2018
Funding: DMA
Northwest Heat Plant ‐ New Construction3‐ IN CONSTRUCTION FCR
8/17/18: Site work near complete, interior piping and boiler work ongoing. Heat scheduled to be available
10/8/18.
Design Firm: Wilson Engineering Contractor: External Name: Froling Energy
2018‐0002
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
Field House ‐ Rms 222 & 224 Minor Room Renovation3‐ IN CONSTRUCTION FCR
8/17/18: Work is ongoing; awaiting carpet tiles, UNH provided.
Design Firm: Contractor: External Name: Careno Construction
2018‐0070
Year Approved2019
Funding: COLLEGE / DEPT
ALLOC
NHVDL ‐ Relocation3.1‐ SUBSTANTIAL COMPLETION SI
8/17/18: Norris is currently installing fire alarm devices in additional areas as requested by building occupant
for added protection of building. Work scheduled to be complete 8/16/18.
Design Firm: Contractor: External Name: Norris
2013‐1537
Year Approved2014
Funding: SARRC ALLOC
Outdoor Pool ‐ Reconstruction of Outdoor Pool Facility3.1‐ SUBSTANTIAL COMPLETION CP
8/17/18: Preparing for project closeout. Final items required for the project will be purchased and this project
closed out by 12/1/18
Design Firm: water technologies Contractor: External Name: Shawmut
2014‐2059
Year Approved2014
Funding: SARRC ALLOC
Whittemore Center ‐ Arena ‐ Fire Alarm System Replacement3.1‐ SUBSTANTIAL COMPLETION FCR
8/17/18: Final modifications to glass tower with DFD coordination nearing completion. Modifications
include, removing speaker / strobe (nusence) remove manual smoke evacuation interface, provide permanent
source of heat to the room, provide 6ʹ x 2ʹ table for material storage and site command use.
Design Firm: SFC Engineering Contractor: External Name: Careno Construction
2015‐2400
Year Approved2017
Funding: COLLEGE / DEPT
ALLOC
Kendall Hall ‐ Upgrade the Nutrition Assessment & Teaching Labs3.1‐ SUBSTANTIAL COMPLETION FCR
8/17/18: Partial furniture delivery received 8/9; balance scheduled for delivery early September.
Design Firm: A Contractor: FCT Name:
2017‐0235
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
Parsons Hall ‐ Rm S128 Ammonia Gas Control System3.1‐ SUBSTANTIAL COMPLETION FCR
8/17/18: Norris has installed trouble monitor module for ammonia control system. This trouble is a latching
supervisory ‐ requiring DFD to respond and reset FA panel. Final testing will be scheduled week of 8/27.
Design Firm: Norris Contractor: External Name: Norris
2017‐0431
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
27POLITANO, FRANK
Wednesday, August 15, 2018 Page 20 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Beech Hill Radio Tower ‐ Sprint Cellular Modifications1‐ ASSIGNED FCR
Design Firm: Contractor: Name:
2019‐0025
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Kendall Hall ‐ Levels 3‐ 5 Repurposing CE and COLSA ‐ Design Only1.1‐ PLAN/EST SI
7/27/18/‐ Update ‐ MPM has been awarded the building study for this project.
Design Firm: Contractor: External Name: MPM
2017‐0186
Year Approved2018
Funding: SARRC ALLOC
Morse Hall ‐ HVAC Evaluation and Feasibility Study1.1‐ PLAN/EST RR
7/27/18/‐ RFS is working on a proposal. I have also reached out to Jacobs to help with the lab space portion of
the study.
Design Firm: Contractor: Name:
2017‐0317
Year Approved2019
Funding: DMA
Adams Tower ‐ Verizon Wireless Antenna Upgrade1.1‐ PLAN/EST FCR
7/27/18/‐We are coordinating work with Verizon for summer execution. I have not heard back from Verizon in
an month. I have not been able to get in touch with our contacts.
Design Firm: Contractor: External Name: Verizon
2018‐0310
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
Christensen Hall‐ Roof Replacement1.1‐ PLAN/EST FCR
7/27/18/‐FCR sent for design ‐ will be funded in 19. Looking for multiple proposal, we only have one at the
moment.
Design Firm: ARM Contractor: External Name:
2018‐0341
Year Approved2019
Funding: COLLEGE / DEPT
ALLOC
Childhood Study & Development Center ‐ Bathroom Partition and Privacy Wall1.1‐ PLAN/EST FCR
7/27/18/‐I have sent an FCR to the customer for review
Design Firm: Contractor: External Name: Careno
2018‐0360
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Memorial Union Building ‐ Rm 202 Barber Shop1.1‐ PLAN/EST BAR
7/27/18/‐ Concept Sketch has been distributed for review.
Design Firm: Contractor: Name:
2019‐0011
Year Approved2019
Funding: COLLEGE / DEPT
ALLOC
Adams Tower ‐ T‐Mobile Relocation of Cellular Array1.1‐ PLAN/EST FCR
7/27/18/‐ Waiting on T‐Mobile Coordination
Design Firm: Contractor: Name:
2019‐0021
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Wednesday, August 15, 2018 Page 21 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Rudman Hall ‐ Vivarium Upgrades Phase 2 DESIGN ONLY2‐ IN DESIGN SI
7/27/18/‐ Design in process final drawings due by 7/15
Design Firm: Harriman Contractor: Name:
2017‐0214
Year Approved2017
Funding: SARRC ALLOC
Coastal Marine Lab ‐ Roof Replacement2‐ IN DESIGN FCR
7/27/18/‐ I sent an FCR to the customer they have stated they have no funds for this project. However I urged
them to find something at least for design so we can get all approvals in place since it is a process because of
the lease.
Design Firm: ARM Contractor: Name:
2018‐0111
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Nesmith Hall ‐ Exterior Brick Wall and Parapet Repointing2.5‐ IN PROCUREMENT RR
7/27/18/‐ P/O is all set work scheduled for 1st week in August
Design Firm: TBD Contractor: External Name: Meditation Gardens
2014‐1972
Year Approved2016
Funding: DMA
Childhood Study & Development Center ‐ Cement Pad for Bus Shelter2.5‐ IN PROCUREMENT FCR
7/27/18/‐CDSC would like to proceed with project ‐ pending funding identification.
Design Firm: Contractor: External Name:
2018‐0055
Year Approved2019
Funding: COLLEGE / DEPT
ALLOC
Childhood Study & Development Center ‐ Roof Repair and Misc Repairs2.5‐ IN PROCUREMENT RR
7/27/18/‐ I have sent this out to various term contractors and should have pricing by 7/18
Design Firm: SMRT Contractor: External Name:
2018‐0159
Year Approved2018
Funding: DMA
Nesmith Hall ‐ South Roof Replacement3‐ IN CONSTRUCTION RR
7/27/18/‐ Viking is set to begin 3rd week of July.
This is for valley repair.
Design Firm: ARM Contractor: External Name: Viking
2010‐0433
Year Approved2018
Funding: DMA
McConnell Hall ‐ Water Intrusion Investigation3‐ IN CONSTRUCTION FCR
7/27/18/‐ Careno has sealed the window wall where the leaks were occuring. I am waiting for report , we
believe there is a bigger issue , we should have a final report by 6/29.
Design Firm: Contractor: External Name: Careno
2016‐0297
Year Approved2016
Funding: SARRC ALLOC
Rudman Hall ‐ Steam Domestic Hot Water Exchanger3‐ IN CONSTRUCTION RR
7/27/18/‐ New unit is installed, start‐up expected on 7/18
Design Firm: Contractor: External Name: GSP
2017‐0366
Year Approved2019
Funding: DMA
Rudman Hall ‐ Water Booster Pump Replacement3‐ IN CONSTRUCTION RR
7/27/18/‐ GSP has installed and we are waiting on an official factory start‐up.
Design Firm: Contractor: External Name: GSP
2017‐0367
Year Approved2019
Funding: DMA
Wednesday, August 15, 2018 Page 22 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Woodsides Complex ‐ Boiler Replacements and Modifications3‐ IN CONSTRUCTION FCR
7/27/18/‐Units PQR and MNO have completed the rough inspection all other units have begun.
Design Firm: SMRT Contractor: External Name: Careno
2017‐0408
Year Approved2017
Funding: COLLEGE / DEPT
ALLOC
Elliott Alumni Center ‐ HHW Conversion to Natural Gas Boiler3‐ IN CONSTRUCTION FCR
7/27/18/‐ Boilers are in place final connections are underway.
Design Firm: SMRT Contractor: External Name: Granite State Plumbing
2017‐0443
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
Gables A,B,C ‐ Boiler Plant Replacement3‐ IN CONSTRUCTION FCR
7/27/18/‐ Work is progressing.boilers and tanks are in place, Charters is working on tieing them in..
Design Firm: SMRT Contractor: External Name: Charters Brothers
2018‐0076
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
Gables Buildings A, B & C ‐ Replace the EPDM roof tops3‐ IN CONSTRUCTION FCR
7/27/18/‐ Gables B and C upper portions are complete, Viking will move to Gables A today, after upper roof is
complete, lower portions of all roofs will be completed.
Design Firm: ARM Contractor: External Name: Viking
2018‐0118
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
Memorial Union Building ‐ Strafford Room Chillers and AHUʹs3‐ IN CONSTRUCTION BAR
7/27/18/‐ New unit is in the building and almost piped in, ductwork is set to begin 7/17. Condensor is
scheduled for 7/24
Design Firm: SMRT Contractor: External Name: Careno
2018‐0143
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
Childhood Study & Development Center ‐ Building Improvements3‐ IN CONSTRUCTION SI
7/27/18/‐Isite work out front has begun and is set to be completed by 7/20
Design Firm: Contractor: External Name: Careno
2018‐0201
Year Approved2018
Funding: SARRC ALLOC
James Hall ‐ HVAC Modifications Investigation and Design3‐ IN CONSTRUCTION RR
7/16/18_ We have replaced the missing gasket to the AHU, however we are still investigating the fans as a
potential cause as well.
Design Firm: Contractor: Name:
2018‐0270
Year Approved2018
Funding: DMA
Memorial Union Building ‐ Strafford Room Wood Flooring Repair3‐ IN CONSTRUCTION BAR
7/27/18/‐ Sprague has completed the sub‐floor. Rubber flooring is at the factory being cut and is set for
delivery mid July.
Design Firm: Contractor: External Name: Sprague
2018‐0299
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
Wednesday, August 15, 2018 Page 23 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Christensen Hall ‐ A‐Tower ATT work3.1‐ SUBSTANTIAL COMPLETION FCR
7/27/18/‐ Work is completed just loose ends to tie up, final inspection from Durham.
Design Firm: Contractor: Name:
2017‐0083
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Paul Creative Arts Center ‐ Stair Egress Modifications3.1‐ SUBSTANTIAL COMPLETION RR
7/27/18/‐ 1st phase is complete, except for 1 door which has been delivered wrong, we are waiting on a new
ship date from factory.
Design Firm: Harriman Contractor: Name:
2017‐0232
Year Approved2017
Funding: DMA
21RINES, DANIEL M
Utility Distribution ‐ Library Way Dual Temp Lines and Tunnel Replacement Design1.1‐ PLAN/EST RR
7‐25‐18: PM to begin design work with Term consultants
Design Firm: Contractor: Name:
2017‐0005
Year Approved2017
Funding: DMA
Train Station & Dairy Bar ‐ Transit Facility Improvements ‐ UNH ‐ Durham Rail Station1.1‐ PLAN/EST SI
7/25/18: no action on project, waiting on approval of notice to proceed on funding, anticipated October.
Design Firm: Contractor: Name:
2018‐0031
Year Approved
Funding: GRANT
Utility Distribution‐ Water Main Replacements Main Street NH Hall to Congreve
DESIGN ONLY1.1‐ PLAN/EST RR
7‐25‐18: PM to begin deisgn with term consultant.
Design Firm: Contractor: Name:
2018‐0347
Year Approved2019
Funding: COLLEGE / DEPT
ALLOC
Memorial Union Building ‐ Driveway and Sidewalk ‐ Design Only2‐ IN DESIGN SI
7‐25‐18: Hoyle Tanner working to complete 90% drawings. Schedule was set by PM and agreed to by HT. 90%
will be submitted to UNH the end of August for review, Final Plans by the end of September, so project can be
put out to bid this fall/winter.
Design Firm: Hoyle Tanner Contractor: Name:
2009‐0078
Year Approved2018
Funding: SARRC ALLOC
Campus ‐ Main Street South Sidewalk2‐ IN DESIGN SI
7‐25‐18: CMA Engineers have begun preliminary deisgn work.
First invoice recieved to submit to the NH DOT.
Design Firm: CMA Engineering Contractor: Name:
2017‐0384
Year Approved2018
Funding: GRANT
Field House ‐ West Parking Lot Repaving2‐ IN DESIGN FCR
7‐25‐18: PM Met with customer, this project has been deferred until next year to coincide with the South Side
walk project. PM will revisit in the spring.
Design Firm: Contractor: Name:
2018‐0297
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Wednesday, August 15, 2018 Page 24 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
5 Leavitt Lane ‐ Library Storage Building Structure Investigation2‐ IN DESIGN RR
7‐25‐18: Waiting on engineers to preform analysis of bar joist.
Design Firm: Contractor: Name:
2018‐0363
Year Approved2019
Funding: DMA
Campus ‐ Parking Lot E1 ‐ Repaving2‐ IN DESIGN BAR
7‐25‐18: PM to meet with Customer and asset management to review scope.
Design Firm: Contractor: Name:
2019‐0015
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Paul Creative Arts Center ‐ Bratton Recital Hall Improved Access2.5‐ IN PROCUREMENT FCR
7‐25‐18: Updated drainage plans sent out to contractors for pricing. Customer still wants to complete this work
this year.
Design Firm: Tighe & Bond Contractor: External Name:
2017‐0318
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
Utility Distribution ‐ HHW Line Replacement Service Building to Zais Hall2.5‐ IN PROCUREMENT RR
7‐25‐18: Project out to Bid.
Design Firm: Contractor: Name:
2017‐0354
Year Approved2019
Funding: DMA
Presidentʹs House ‐ Major Site Repairs President Transition3‐ IN CONSTRUCTION RR
7‐25‐18:
PM coordinated with the Deans, Top coat to wait until after final furniture delivery.
Design Firm: Contractor: External Name: Bell and Flynn/ Chapman
2013‐1274
Year Approved2018
Funding: DMA
Campus Wayfinding ‐ Phase 23‐ IN CONSTRUCTION SI
7‐25‐18: Phase one punchlist complete, Field staking and dig safes to occur on 7‐26‐18. Signage installed in
August.
Design Firm: Contractor: External Name: Barlo Signs
2016‐0157
Year Approved2018
Funding: SARRC ALLOC
Whittemore Center ‐ Arena ‐ Engineering Evaluation for Exterior Concrete and Interior
Mechanical Room Slab3‐ IN CONSTRUCTION RR
7‐25‐18: SGH set crack monitors in NW Wall, and preformed survey and analysis of interior mechanical slab
on 6‐25‐18. Data will be analyzed, and futher monitoring visits will be planned.
Design Firm: SGH Contractor: Name:
2017‐0394
Year Approved2018
Funding: DMA
Combined Heat & Power Plant ‐ Water leak at exterior brick wall3‐ IN CONSTRUCTION FCR
7‐23‐18: FCR approved, PM to schedule work.
Design Firm: Contractor: External Name: T&S
2018‐0315
Year Approved2019
Funding: COLLEGE / DEPT
ALLOC
Wednesday, August 15, 2018 Page 25 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Memorial Union Building ‐ West Entry Foot Bridge and Stair Replacement3‐ IN CONSTRUCTION FCR
7‐25‐18: Work is underway.
Design Firm: included in project Contractor: External Name: Charters Brothers
2018‐0343
Year Approved2019
Funding: COLLEGE / DEPT
ALLOC
Nesmith Hall ‐ Flood Restoration and Investigation3‐ IN CONSTRUCTION RR
Emergency Repair
Design Firm: Contractor: Name:
2019‐0044
Year Approved2019
Funding: DMA
11 Brook Way ‐ Building Demolition3.1‐ SUBSTANTIAL COMPLETION RR
7‐25‐18: Building has been taken down, site clean up and hauling off debris underway.
Design Firm: Contractor: External Name: Air Quality Experts
2016‐0437
Year Approved2019
Funding: DMA
UNH Utility Master Plan3.1‐ SUBSTANTIAL COMPLETION SI
7‐25‐18: Waiting on Final Invoicing.
Design Firm: RMF Contractor: Name:
2017‐0169
Year Approved2016
Funding: SARRC ALLOC
Utility Distribution ‐ Main Street Tunnel Corrective Repair and Design3.1‐ SUBSTANTIAL COMPLETION RR
7‐25‐18: Rh White to fix/finish the installation of the SS Brackets on 8‐13‐18, during steam shutdown. This is
the last item to complete.
Design Firm: Simpson Gumpertz & Heger Contractor: External Name: R.H. White Construction
2018‐0155
Year Approved2018
Funding: DMA
Rudman Hall ‐ Dishwasher Fire/ Sprinkler Flood Restoration3.1‐ SUBSTANTIAL COMPLETION RR
Emergency Repair 7‐25‐18: Project is complete. Project will be closed out.
Design Firm: Contractor: Name:
2018‐0252
Year Approved2018
Funding: INST RR
Kingman Equipment Barn ‐ Make alterations to recreational access at Kingman Farm
off Route 1553.1‐ SUBSTANTIAL COMPLETION FCR
7‐25‐18: Pricing provided to customer. Customer to apply for Grant in the future to complete this work.
Design Firm: Contractor: External Name: T&S Construction
2018‐0323
Year Approved
Funding: COLLEGE / DEPT
ALLOC
18ROULEAU, RICHARD A
Wednesday, August 15, 2018 Page 26 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Marine Research Facility ‐ Restoration and Repairs1.1‐ PLAN/EST FCR
7/30/2018 Update:
Repair scope consists of:
1. window repair/replacement,
2. roofing and roof deck replacement where New Castle Fire Department opened roof while fighting the fire,
3. reinsulating floor,
4. reinstalling plywood floor sheathing removed as needed to remove wet insulation,
5. repairing damaged door,
6. replacing fire alarm devices and lighting consistent with 2009 work,
7. possibly reconstructing shelving for storage, and
8. possibly reconstructing an insulated head tank room.
It is intended that the customer will complete any repairs and/or changes to the damaged seawater system.
With customerʹs concurrence, the intent is to complete as many repairs under the 2018‐0336 Fire Clean‐up
project as can be done with remaining clean‐up funds. An FCR for the balance of repairs will then be
prepared and submitted for funding.
Design Firm: Contractor: External Name:
2018‐0337
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Campus ‐ Dual Temp Interconnection Plan1.1‐ PLAN/EST FCR
7/30/2018 ‐ Outline scope received from Matt OʹKeefe. Need to determine whether this will be designed as
part of make‐ready for Spaulding project or as standalone project.
Design Firm: Contractor: Name:
2019‐0022
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Spaulding Hall ‐ Expansion & Renovations ‐ Biological Science Initiative2‐ IN DESIGN CP
7/3/2018 Update: Summer 2019 make‐ready projects scoped out. Need to put together formal list and solicit
design proposal from project architect. Schematic design estimate received from construction manager. It is
much higher than previous estimates and will need to be reconciled with Vermeulensʹ SD estimate. Once
reconciled, decision will be made to move forward with design development or go back to schematic design.
Design Firm: Ellenzweig Contractor: External Name: Skanska USA Building
2016‐0278
Year Approved2016
Funding: SARRC ALLOC
UNH Manchester ‐ 88 Commercial Street ‐ Bio‐Manufacturing Innovation Center
Tenant fit‐out2‐ IN DESIGN FCR
7/30/2018 Update: Design develop documents under review. Milestone is preparing an estimate on behalf of
the landlord.
Design Firm: John Jordan Contractor: External Name: by landlord (Milestone)
2018‐0210
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Utility Distribution ‐ Horton to PCAC HHW Line Replacements and Pit Repairs3‐ IN CONSTRUCTION RR
7/31/2018 Update: Construction is ongoing. Only remaining piping is in the PCAC pit. Trench covers have
been reinstalled throughout and waterproofing of the trench covers west of the PCAC pit is underway.
Paving of area west of PCAC pit is expected to be complete within a week. Re‐establishment of landscaping
and hardscaping is underway. Project is on schedule.
Design Firm: Harriman Associates Contractor: External Name: Charters Bros.
2017‐0094
Year Approved2019
Funding: DMA
Memorial Union Building ‐ Ramp Structural Steel and Concrete Repairs3‐ IN CONSTRUCTION BAR
7/31/2018 Update: Components of this project to be performed as ancillary work associated with 2017‐0352
Granite State Room Balcony Repairs.
Design Firm: Hoyle Tanner Contractor: Name:
2017‐0138
Year Approved2017
Funding: COLLEGE / DEPT
ALLOC
Wednesday, August 15, 2018 Page 27 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Memorial Union Building ‐ Exterior Deck Recoating3‐ IN CONSTRUCTION BAR
7/31/2018 Update: Recoating effort is complete. Replacement of composite decking over recessed area has
been delayed due to unforeseen conditions of the waterproofing material, drains and concrete condition.
Correction of the unforeseen conditions is being added to scope of project via change order.
Design Firm: Contractor: External Name: Charters Bros.
2017‐0139
Year Approved2017
Funding: COLLEGE / DEPT
ALLOC
Memorial Union Building ‐ Granite State Room Exterior Deck3‐ IN CONSTRUCTION BAR
7/31/2018 Update: Base scope is essentially complete. Ancillary work related to MUB bridge below to be
rolled into project.
Design Firm: Hoyle Tanner Contractor: Name: Charters Bros.
2017‐0352
Year Approved2017
Funding: COLLEGE / DEPT
ALLOC
10 Pettee Brook Lane ‐ Renovations to Space3‐ IN CONSTRUCTION FCR
7/30/2018 Update: Construction is nearing completion. Certificate of Occupancy inspection scheduled for
8/17. Furniture delivery scheduled for 8/23 and 8/24. Some of the lounge furniture may lag behind.
Design Firm: Manypenny Murphy
Architecture
Contractor: External Name: Landlord
2017‐0472
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
Stoke Hall ‐ Elevator upgrade3‐ IN CONSTRUCTION FCR
7/31/2018: Work is in progress, going well and to be complete prior to the fall semester. We are coordinating
with Housing regarding early move‐ins using the elevator.
Design Firm: Elevator Consulting Assoc. Contractor: External Name: Careno Construction
2018‐0117
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
88 Commercial Street ‐ Mechanical Tech Lab3.1‐ SUBSTANTIAL COMPLETION FCR
7/31/2018 Update: Ordering new CNC milling machine and CNC lathe. Official opening is scheduled for
October 1.
Design Firm: John Jordan Contractor: External Name: 1850 PDRA Associates
2016‐0428
Year Approved2018
Funding: COLLEGE / DEPT
ALLOC
9 Madbury Road ‐ Lease Space Office Fit Up3.1‐ SUBSTANTIAL COMPLETION SI
7/31/2018 Update: Construction is complete with exception of punchlist items. Furniture has been installed
with some punchlist and additional ordered items remaining. Occupants have moved in and are thrilled with
their new space.
Design Firm: Harriman Contractor: External Name: Milestone, Denron,
Martineau, Sprague,
Envirovantage
2018‐0092
Year Approved2018
Funding: SARRC ALLOC
Pettee Hall ‐ Slate Roof Repairs3.1‐ SUBSTANTIAL COMPLETION RR
Emergency Repair 7/31/2018 Update: Repairs completed pending review of drone verification photos.
Design Firm: Contractor: External Name: Skyline Roofing
2018‐0098
Year Approved2018
Funding: INST RR
Wednesday, August 15, 2018 Page 28 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
James Hall ‐ Slate Roof Repairs3.1‐ SUBSTANTIAL COMPLETION RR
Emergency Repair 7/31/2018 Update ‐ Repairs completed pending review of drone verification photos.
Design Firm: Contractor: External Name: Skyline Roofing
2018‐0099
Year Approved2018
Funding: INST RR
Marine Research Facility ‐ Fire Clean‐Up and Make Safe3.1‐ SUBSTANTIAL COMPLETION FCR
7/31/2018 Update: Clean‐up and make‐safe is complete. With customer approval, intent is to use remaining
clean‐up funds toward repair and restoration to the extent possible.
Design Firm: Contractor: External Name: Careno Construction
2018‐0336
Year Approved
Funding: COLLEGE / DEPT
ALLOC
Holloway Commons ‐ Expansion Project3.5‐ WARRANTY REPAIRS CP
7/31/2018 Update: There remain just a few project items that need to be resolved.
Design Firm: Miller Dyer Spears Contractor: External Name: North Branch Construction
2014‐1657
Year Approved2014
Funding: HEFA / COLLEGE /
DEPT ALLOC
Hamilton Smith Hall ‐ Major Renovation Project3.5‐ WARRANTY REPAIRS SI
7/31/2018 Update: One year warranty period has ended. Skanska and subcontractors to complete warranty
work this summer. Also working with Milestone to do some small follow‐up work. Bi‐directional amplifier
per Town ordinance split off as separate project (2018‐0223).
Design Firm: DiMella Shaffer Associates Contractor: External Name: Skanska USA, Inc.
2012‐1851
Year Approved2013
Funding: SARRC ALLOC
Paul Creative Arts Center ‐ New Main Domestic Hot Water System Installation3.5‐ WARRANTY REPAIRS RR
7/31/2018 Update: Water heater installation completed. Domestic water booster pump design received and
may be implemented as part of this project or possibly as a separate follow‐on project.
Design Firm: Harriman Associates Contractor: External Name: Charters Bros.
2018‐0249
Year Approved2019
Funding: DMA
Wednesday, August 15, 2018 Page 29 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management