Facilities Project Management Monthly Report by Building Monday, July 02, 2018 156 Approved Project PROJECT TITLE PM Accountable Project Code Project Number: 10 Pettee Brook Lane Projects in Building 1 10 Pettee Brook Lane Renovations to Space 3IN CONSTRUCTION FCR ROULEAU, RICHARD A 7/1/2018 Update: Construction is underway. Addressing submittals and RFIs. Substantial completion anticipated for mid to lateAugust. Furniture has been ordered. Design Firm: Manypenny Murphy Archite Contractor: External Contractor Name: Landlord 20170472 11 Brook Way Projects in Building 1 11 Brook Way Building Demolition 3IN CONSTRUCTION RR RINES, DANIEL M 62618: Contract fully exectuted, abatement under way. Followed by Utilities cut/cap, and demo permit/ Demo. Design Firm: Contractor: External Contractor Name: Air Quality Experts 20160437 121 Technology Drive Projects in Building 3 121 Technology Drive Advanced Manufacturing Center 3IN CONSTRUCTION FCR BRICKETT, ALEXANDER J 6/27/2018_Punchlist items in progress. Design Firm: JSA, Inc. Contractor: External Contractor Name: Careno Construction 20160301 121 Technology Drive Fit Up of Unassigned Suite 3.1SUBSTANTIAL COMPLETION FCR BRICKETT, ALEXANDER J 6/27/2018_Update Please refer to ID 20160186 for updates. Design Firm: Contractor: External Contractor Name: Careno Construction 20180062 121 Technology Drive Interior Lease Space Renovations 3.1SUBSTANTIAL COMPLETION FCR BRICKETT, ALEXANDER J 6/27/2018_Project is substantially complete. Punchlist and completion items ongoing. Design Firm: CowanGoudreau Contractor: External Contractor Name: Careno Construction 20160186 5 Leavitt Lane Projects in Building 1 Monday, July 02, 2018 Page 1 of 29 University of New Hampshire Brenda Whitmore, Director Facilities Project Management

Facilities Project Management Monthly Report Building

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Facilities Project Management Monthly Report by Building

Monday, July 02, 2018 156Approved Project

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

10 Pettee Brook Lane Projects in Building 1

10 Pettee Brook Lane ‐ Renovations to Space

3‐ IN CONSTRUCTION

FCRROULEAU, RICHARD A

7/1/2018 Update: Construction is underway.  Addressing submittals and RFIs.  Substantial 

completion anticipated for mid to late‐August.  Furniture has been ordered.

Design Firm: Manypenny Murphy Archite Contractor: External Contractor Name: Landlord

2017‐0472

11 Brook Way Projects in Building 1

11 Brook Way ‐ Building Demolition

3‐ IN CONSTRUCTION

RRRINES, DANIEL M

6‐26‐18: Contract fully exectuted, abatement under way. Followed by Utilities cut/cap, and demo 

permit/ Demo.

Design Firm: Contractor: External Contractor Name: Air Quality Experts

2016‐0437

121 Technology Drive Projects in Building 3

121 Technology Drive ‐ Advanced Manufacturing Center

3‐ IN CONSTRUCTION

FCRBRICKETT, ALEXANDER J

6/27/2018_Punchlist items in progress.

Design Firm: JSA, Inc. Contractor: External Contractor Name: Careno Construction

2016‐0301

121 Technology Drive ‐ Fit Up of Unassigned Suite

3.1‐ SUBSTANTIAL COMPLETION

FCRBRICKETT, ALEXANDER J

6/27/2018_Update ‐ Please refer to ID 2016‐0186 for updates.

Design Firm: Contractor: External Contractor Name: Careno Construction

2018‐0062

121 Technology Drive ‐ Interior Lease Space Renovations

3.1‐ SUBSTANTIAL COMPLETION

FCRBRICKETT, ALEXANDER J

6/27/2018_Project is substantially complete. Punchlist and completion items ongoing.

Design Firm: Cowan‐Goudreau Contractor: External Contractor Name: Careno Construction

2016‐0186

5 Leavitt Lane Projects in Building 1

Monday, July 02, 2018 Page 1 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

5 Leavitt Lane ‐ Library Storage Building Structure Investigation

2‐ IN DESIGN

RRRINES, DANIEL M

6‐26‐18: Engineer was given photos of bar joist, will work up a structural analysis, and 

recommendation.

Design Firm: Contractor: Contractor Name:

2018‐0363

88 Commercial Street Projects in Building 1

88 Commercial Street ‐ Mechanical Tech Lab

3.1‐ SUBSTANTIAL COMPLETION

FCRROULEAU, RICHARD A

7/1/2018 Update:  Many tools and some larger pieces of equipment purchased and in place.  

Need to close out 1850 Associates purchase order to determine how much funding is available 

for additional tools and equipment.

Design Firm: John Jordan Contractor: External Contractor Name: 1850 PDRA Associates

2016‐0428

9 Madbury Road Projects in Building 1

9 Madbury Road ‐ Lease Space Office Fit Up

3‐ IN CONSTRUCTION

SIROULEAU, RICHARD A

7/1/2018 Update:  Construction is nearly complete.  Furniture has been ordered and will be 

installed the last weke of July.  Move‐in is scheduled for 8/1.

Design Firm: Harriman Contractor: External Contractor Name: Milestone, Denron, Martineau, Sprague, Envirovan

2018‐0092

Adams Tower Projects in Building 1

Adams Tower ‐ Verizon Wireless Antenna Upgrade

1.1‐ PLAN/EST

FCRPOLITANO, FRANK

6/26/18__   We are coordinating work with Verizon for summer execution. I have not heard back 

from Verizon in an month. I have not been able to get in touch with our contacts.

Design Firm: Contractor: External Contractor Name: Verizon

2018‐0310

Barton Hall & Cole Hall Projects in Building 1

Cole Hall ‐ HVAC HU‐3 EQ5389 Cat Walks and Accessibility Modifications

2.5‐ IN PROCUREMENT

RRHOUDE, DONALD A

6‐25‐18 We are firming up the AIA document at this time. .

Design Firm: Oak Point Contractor: External Contractor Name: Milestone  E & C

2018‐0086

Building Interior Projects in Building 2

Monday, July 02, 2018 Page 2 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Thompson Hall ‐ Graduate Student Center

2.5‐ IN PROCUREMENT

SIHECKLER, BARBARA K

6/29/2018: Project on track for late‐August/early September completion.

Design Firm: Contractor: External  Contractor Name:

2017‐0212

Campus ‐ UNH Fire Damper Study

3.1‐ SUBSTANTIAL COMPLETION

FCRHENRY, PAUL A

6‐26‐18   buildings Survey complete, for first 4 buildings.

Design Firm: Harriman Contractor: Contractor Name:

2017‐0205

Chase Ocean Engineering Lab Projects in Building 3

Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe

3‐ IN CONSTRUCTION

FCRHOUDE, DONALD A

6‐25‐18 This project is in progress. It should be complete by the end of the week.

Design Firm: Contractor: External Contractor Name: Yates Electric

2018‐0314

Chase Ocean Engineering Lab ‐ Tank Room Ceiling Restoration and Replacement of 

HV‐3

3‐ IN CONSTRUCTION

RRGEUTHER, MARK E

06‐25‐2018: HV‐3 installation complete. Controls installation scheduled for this week, start up the 

week of July 2.

Design Firm: HL Turner Contractor: External Contractor Name: Milestone

2017‐0153

Chase Ocean Engineering Lab ‐ Expansion

3.1‐ SUBSTANTIAL COMPLETION

FCRGEUTHER, MARK E

06‐25‐2018: Transformer swap out for new research equipment, scheduled for June 30.

Design Firm: HL Turner Contractor: External Contractor Name: Milestone Engineer & Construction

2015‐2755

Childhood Study & Development Center Projects in Building 1

Childhood Study & Development Center ‐ Roof Repair and Misc Repairs

2.5‐ IN PROCUREMENT

RRPOLITANO, FRANK

6/26/18_  I have sent this out to various term contractors and should have pricing by 7/6

Design Firm: SMRT Contractor: External Contractor Name:

2018‐0159

Monday, July 02, 2018 Page 3 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Conant Hall Projects in Building 2

Conant Hall ‐ DDC Controls Installation

3.1‐ SUBSTANTIAL COMPLETION

RRHENRY, PAUL A

6‐26‐18  fiinish commissioning

Design Firm: Harriman Contractor: Contractor Name:

2018‐0192

Conant Hall ‐ Minor Interior Renovations

3.1‐ SUBSTANTIAL COMPLETION

SIHENRY, PAUL A

6‐26‐18 Building occupied  Working on punch List, and finishing MEP improvements

Design Firm: Mannypenny Murphy Contractor: External Contractor Name: Trumbell Nelson

2016‐0410

Dimond Library Projects in Building 3

Dimond Library ‐ Minor Renovation for Customer Service and Addison Areas

1.1‐ PLAN/EST

FCRHECKLER, BARBARA K

6/29/2018: Careno estimate received. Awaiting revised sketch fro Salmon Falls Woodworks.

Design Firm: Contractor: External Contractor Name:

2017‐0423

Dimond Library ‐ Interior Painting of Main Lobby

3‐ IN CONSTRUCTION

RRBOIE, GREGG J

06/25/18,  Work in Progress

Design Firm: Contractor: External Contractor Name: APC Services of New England

2018‐0307

Dimond Library – Room 221 Renovation

3‐ IN CONSTRUCTION

SIHECKLER, BARBARA K

6/29/2018:  Project on track to be complete by 8/1.

Design Firm: Contractor: Contractor Name:

2018‐0179

DPW Grounds & Roads Projects in Building 1

Monday, July 02, 2018 Page 4 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

DPW Grounds & Roads ‐ Garage

3.1‐ SUBSTANTIAL COMPLETION

FCRHENRY, PAUL A

6‐26‐18 workign out fire calking details with Careno and some minor plumbing deficiencies 

witht the existing power washer. Will re‐schedule C of O inspection after reviewing contractor 

SFMO binder

Design Firm: Careno Contractor: External Contractor Name: Careno

2013‐1610

Elliott Alumni Center Projects in Building 1

Elliott Alumni Center ‐ HHW Conversion to Natural Gas Boiler

3‐ IN CONSTRUCTION

FCRPOLITANO, FRANK

6/26/18_     Work has begun, old piping has been removed. New pad is expected to be poured on 

6/26. GSP has equipment in their warehouse.

Design Firm: SMRT Contractor: External Contractor Name: Granite State Plumbing

2017‐0443

Field House Projects in Building 3

Field House ‐ Womens Team Locker Room Upgrades ‐ Planning Only

2‐ IN DESIGN

SIHECKLER, BARBARA K

6/29/2018: Harriman working on concept drawings; expect drafts for review by early August.

Design Firm: Contractor: Contractor Name:

2018‐0198

Field House ‐ New Ski Locker Room/Team Area

2‐ IN DESIGN

FCRBRICKETT, ALEXANDER J

6/27/2018__Working with design team for final space renderings.

Design Firm: Harriman Contractor: Contractor Name:

2017‐0251

Field House ‐ Steam to Domestic Hot Water System Replacement

3‐ IN CONSTRUCTION

RRPARSONS, STEPHANIE E

6/29/19: Contract has been executed.  Awaiting shipping details to coordinate work within field 

house.

Design Firm: Harriman Contractor: External Contractor Name: Northern Peabody

2017‐0325

Gables Building A Projects in Building 1

Monday, July 02, 2018 Page 5 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Gables Buildings A, B & C ‐ Replace the EPDM roof tops

3‐ IN CONSTRUCTION

FCRPOLITANO, FRANK

6/26/18_   Viking has begun with Gables C it is 60% complete. Each roof is expected to take 2 

weeks.

Design Firm: ARM Contractor: External Contractor Name: Viking

2018‐0118

Gables Building B Projects in Building 1

Gables A,B,C ‐ Boiler Plant Replacement

3‐ IN CONSTRUCTION

FCRPOLITANO, FRANK

6/26/18_  Most Demo is complete, new boilers ship on 6/27. Some pre fab is complete waiting on 

delivery of equipment.

Design Firm: SMRT Contractor: External Contractor Name: Charters Brothers

2018‐0076

Gregg Hall Projects in Building 4

Gregg Hall ‐ Chiller Replacement

2.5‐ IN PROCUREMENT

RRPARSONS, STEPHANIE E

6/29/18: RFB has been posted.  Chiller replacement to occur October / November after primary 

cooling season.

Design Firm: Harriman Contractor: External Contractor Name: TBD

2017‐0281

Gregg Hall ‐ Fire Damper Repairs

2.5‐ IN PROCUREMENT

FCRHENRY, PAUL A

6‐26‐18 Issued PPʹs to Milestone, they are gearing up to start first building.

Design Firm: Harriman Contractor: External Contractor Name: Milestione

2018‐0327

Gregg Hall ‐ Chiller Replacement ‐ Funding for Construction

2.5‐ IN PROCUREMENT

RRPARSONS, STEPHANIE E

6/29/18: Please refer to project 2017‐0281 for updates on construction.

Design Firm: Harriman Contractor: External Contractor Name: TBD

2017‐0250

Gregg Hall ‐ Basement Flood Restoration

3‐ IN CONSTRUCTION

RR

Emergency Repair

BRICKETT, ALEXANDER J

6/27/2018_Drywall work to be competed when pump station upgrades are installed. Work to be 

coordinated with John OʹRourke.

Design Firm: Contractor: External Contractor Name:

2018‐0132

Monday, July 02, 2018 Page 6 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Hamel Recreation Center Projects in Building 2

Hamel Recreation Center ‐Motorized Shades

3‐ IN CONSTRUCTION

FCRPARSONS, STEPHANIE E

6/29/18: This work has been approved.  Scheduled completion on or before 8/3/18.

Design Firm: Contractor: External Contractor Name: Portsmouth Blind Shade / Yates

2018‐0259

Hamel Recreation Center ‐ Expansion & Renovations

3‐ IN CONSTRUCTION

CPPARSONS, STEPHANIE E

6/29/18: AWF on floor 3 is complete.  Floor 3 has been turned over to Campus Recreation.

Design Firm: HGA Contractor: FCT Contractor Name: Shawmut

2013‐1176

Hamilton Smith Hall Projects in Building 2

Hamilton Smith Hall ‐ Bi‐Directional Amplifier Installation

2‐ IN DESIGN

RRPARSONS, STEPHANIE E

6/29/18: Working with Notifier / Norris for BDA design and quotes.

Design Firm: Norris Inc. Contractor: External Contractor Name: TBD

2016‐0116

Hamilton Smith Hall ‐ Major Renovation Project

3.5‐ WARRANTY REPAIRS

SIROULEAU, RICHARD A

7/1/2018 Update:  One year warranty period has ended.  Skanska and subcontractors to complete 

warranty work this summer.  Also working with Milestone to do some small follow‐up work.  Bi‐

directional amplifier per Town ordinance split off as separate project (2018‐0223).

Design Firm: DiMella Shaffer Associates Contractor: External Contractor Name: Skanska USA, Inc.

2012‐1851

Health & Wellness Building Projects in Building 2

Health & Wellness Building ‐ Physical Reorganization of Services

3‐ IN CONSTRUCTION

FCRHECKLER, BARBARA K

6/29/2018: Previously approved carpet and millwork expected complete by 8/3. Unexpected 

lobby scope in planning and estimating; completion date TBD.

Design Firm: Harriman A/E Contractor: Contractor Name:

2017‐0340

Monday, July 02, 2018 Page 7 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Health & Wellness Building ‐  Fire Alarm System Upgrade

3.1‐ SUBSTANTIAL COMPLETION

FCRPARSONS, STEPHANIE E

6/29/18: Testing / walk through with DFD / SFMO scheduled 7/19 for final acceptance.  This was 

a panel only replacement, not a full system replacement.

Design Firm: Contractor: External Contractor Name: Norris

2018‐0182

Hewitt Hall Projects in Building 1

Hewitt Hall ‐ Fire Damper Repairs

2.5‐ IN PROCUREMENT

FCRHENRY, PAUL A

6‐26‐18 Issued PPʹs to Milestone, they are gearing up to start first building.

Design Firm: Harriman Contractor: External Contractor Name: Milestione

2018‐0325

Holloway Commons Projects in Building 2

Holloway Commons ‐ Retro‐Commissioning Repairs

1.1‐ PLAN/EST

FCRBRICKETT, ALEXANDER J

6/27/2018 ‐ RFS has been contacted to establish scope of repairs needed.

Design Firm: Contractor: External Contractor Name:

2016‐0500

Holloway Commons ‐ Expansion Project

3.5‐ WARRANTY REPAIRS

CPROULEAU, RICHARD A

7/1/2018 Update: There remain just a few project items that need to be resolved.

Design Firm: Miller Dyer Spears Contractor: External Contractor Name: North Branch Construction

2014‐1657

Hood House Projects in Building 1

Hood House ‐ Minor Renovation for Career and Professional Success Center

3.1‐ SUBSTANTIAL COMPLETION

SIHENRY, PAUL A

6‐26‐18  Project in punch list,  occupants in the building.

Design Firm: Mannypenny Murphy Contractor: External Contractor Name: Trumbell Nelson

2016‐0409

Horton Social Science Center Projects in Building 2

Monday, July 02, 2018 Page 8 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Horton Social Science Center ‐ 3rd Floor Daiken Unit Recommissioning

2.5‐ IN PROCUREMENT

FCRHENRY, PAUL A

6‐26‐18  Operations locked out the Heat, checking to see if we still want to Retro‐Commission the 

system.

Design Firm: Harriman / RFS Contractor: External Contractor Name: RFS / Harriman

2018‐0295

Horton Social Science Center ‐ 1st Floor Renovation ‐ Phase 2

3‐ IN CONSTRUCTION

SIHENRY, PAUL A

6‐26‐18  Abatement and Demo complete, working on framing and rough in of electrical and 

HVAC.

Design Firm: Harriman Contractor: External  Contractor Name: Milestone

2008‐0203

Huddleston Hall Projects in Building 3

Huddleston Hall ‐ Fire Code Assessment and Life Safety Plan

1‐ ASSIGNED

RRHENRY, PAUL A

Design Firm: SFC Engineering Partnership Contractor: Contractor Name:

2012‐0841

Huddleston Hall ‐ Roof Replacement Design Only

2‐ IN DESIGN

RRHENRY, PAUL A

6‐26‐18  Harriman working with ARM to include the design. Starting roof investigation   2013‐

1155 Huddleston Egress project.

Design Firm: ARM Contractor: External Contractor Name: Harriman

2016‐0165

Huddleston Hall ‐ Design of Egress Modifications

2‐ IN DESIGN

RRHENRY, PAUL A

6‐26‐18  MEP Study ready for review next week, DD for building mid July.

Design Firm: Harriman Contractor: External Contractor Name: Harriman

2013‐1155

Jackson Lab Projects in Building 1

Jackson Lab ‐ Autoclave Replacement

2.5‐ IN PROCUREMENT

RRHOUDE, DONALD A

6‐25‐18  A PO has been provided to the contractor  for this work. Equipment has been ordered. I 

am waiting for an ETA on equipment to schedule a const start. Expected in June.

Design Firm: Contractor: FCT Contractor Name:

2017‐0377

Monday, July 02, 2018 Page 9 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

James Hall Projects in Building 4

James Hall ‐ Heat Exchanger Replacement

2.5‐ IN PROCUREMENT

RR

Emergency Repair

PARSONS, STEPHANIE E

6/29/18:  Submittals have been reviewed.  NPI provided tenative ship date of 8/17 for equipment.

Design Firm: Harriman Associates Contractor: External Contractor Name: NPI

2017‐0393

James Hall ‐ HVAC Modifications Investigation and Design

3‐ IN CONSTRUCTION

RRPOLITANO, FRANK

6/26/18_  We have replaced the missing gasket to the AHU, however we are still investigating 

the fans as a potential cause as well.

Design Firm: Contractor: Contractor Name:

2018‐0270

James Hall ‐ AHU‐3 Failure Investigation and Repair

3.1‐ SUBSTANTIAL COMPLETION

RR

Emergency Repair

BRICKETT, ALEXANDER J

6/27/2018_ Repairs and room reconditioning finished. Final commisioning and setpoints being 

work on.

Design Firm: Contractor: Contractor Name:

2018‐0309

James Hall ‐ Slate Roof Repairs

3.1‐ SUBSTANTIAL COMPLETION

RR

Emergency Repair

ROULEAU, RICHARD A

2/26/2018 ‐ Repairs have been completed.

Design Firm: Contractor: External Contractor Name: Skyline Roofing

2018‐0099

Kendall Hall Projects in Building 2

Kendall Hall ‐ Levels 3‐ 5 Repurposing CE and COLSA ‐ Design Only

1.1‐ PLAN/EST

SIPOLITANO, FRANK

6/26/18_   Update ‐ MPM has been awarded the building study for this project.

Design Firm: Contractor: External Contractor Name: MPM

2017‐0186

Kendall Hall ‐ Upgrade the Nutrition Assessment & Teaching Labs

3.1‐ SUBSTANTIAL COMPLETION

FCRPARSONS, STEPHANIE E

6/29/18:  Awaiting furniture delivery.

Design Firm: A Contractor: FCT Contractor Name:

2017‐0235

Monday, July 02, 2018 Page 10 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Leavitt Cntr Transportation Center Projects in Building 1

Leavitt Cntr Transportation Center ‐ Bus Maintenance Lift Replacements

2.5‐ IN PROCUREMENT

FCRHOUDE, DONALD A

5‐22‐18  I am working with Purchasing to put this out to bid. We tried but only received 1 SOQ, 

we are adjusting our dates and putting it back out for more request.

Design Firm: Contractor: External Contractor Name: Design build

2017‐0447

MacFarlane Greenhouse Projects in Building 1

MacFarlane Greenhouse ‐ Renovation/Improvements

2‐ IN DESIGN

FCRHOUDE, DONALD A

6‐25‐18 I have received a completed FCR from the customer, I am waiting for my BSC to inform 

me they have set up an account to write the Engineering firm a PO.

Design Firm: SMRT Contractor: Contractor Name:

2019‐0001

McConnell Hall Projects in Building 1

McConnell Hall ‐ Water Intrusion Investigation

3‐ IN CONSTRUCTION

FCRPOLITANO, FRANK

6/26/18_    Careno has sealed the window wall where the leaks were occuring. I am waiting for 

report , we believe there is a bigger issue , we should have a final report by 6/29.

Design Firm: Contractor: External Contractor Name: Careno

2016‐0297

Memorial Union Building Projects in Building 7

Memorial Union Building ‐ Granite State Room Exterior Deck

3‐ IN CONSTRUCTION

BARROULEAU, RICHARD A

7/1/2018 Update:  Removals of distressed concrete nearing completion.  Surface prep and 

patching to commence soon..

Design Firm: Hoyle Tanner Contractor: Contractor Name: Charters Bros.

2017‐0352

Memorial Union Building ‐ Ramp Structural Steel and Concrete Repairs

3‐ IN CONSTRUCTION

BARROULEAU, RICHARD A

7/1/2018 Update: Due to funding and term contract limitations, this project has been deferred, 

although components of it may be performed as ancilary work associated with 2017‐0352 Granite 

State Room Balcony Repairs.

Design Firm: Hoyle Tanner Contractor: Contractor Name:

2017‐0138

Monday, July 02, 2018 Page 11 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Memorial Union Building ‐ Strafford Room Wood Flooring Repair

3‐ IN CONSTRUCTION

BARPOLITANO, FRANK

6/26/18_    Sprague has completed the sub‐floor. Rubber flooring is at the factory being cut and is 

set for delivery  beginning of July.

Design Firm: Contractor: External Contractor Name: Sprague

2018‐0299

Memorial Union Building ‐ Exterior Deck Recoating

3‐ IN CONSTRUCTION

BARROULEAU, RICHARD A

7/1/2018 Update:  Prep work for new coating has commenced.  Recoating effort to start soon.

Design Firm: Contractor: External Contractor Name: Charters Bros.

2017‐0139

Memorial Union Building ‐ Strafford Room Chillers and AHUʹs

3‐ IN CONSTRUCTION

BARPOLITANO, FRANK

6/26/18_   Demo is complete, new unit is scheduled to arrive 7/15. Site work to begin on 6/26

Design Firm: SMRT Contractor: External Contractor Name: Careno

2018‐0143

Memorial Union Building ‐ Bookstore Flood Restoration and Repairs

3‐ IN CONSTRUCTION

BAR

Emergency Repair

POLITANO, FRANK

6/26/18_    Project is 90% complete, we are waiting on matching carpet for floor repairs. The 

carpet is expected the first week of July.

Design Firm: Contractor: External Contractor Name: Charters

2018‐0229

Memorial Union Building ‐ Granite Square Station Mail Boxes

3.5‐ WARRANTY REPAIRS

FCRPOLITANO, FRANK

6/26/18_  Warranty issues, repairs scheduled to begin 6/26

Design Firm: Contractor: FCT Contractor Name:

2015‐2517

Morse Hall Projects in Building 5

Morse Hall ‐ HVAC Evaluation and Feasibility Study

1.1‐ PLAN/EST

RRPOLITANO, FRANK

6/26/18_    RFS is working on a proposal. I have also reached out to Jacobs to help with the lab 

space portion of the study.

Design Firm: Contractor: Contractor Name:

2017‐0317

Monday, July 02, 2018 Page 12 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Morse Hall ‐ Fire Damper Repairs

2.5‐ IN PROCUREMENT

FCRHENRY, PAUL A

6‐26‐18 Issued PPʹs to Milestone, they are gearing up to start first building.

Design Firm: Contractor: External Contractor Name: Milestone

2018‐0326

Morse Hall ‐ Security Upgrades Including Card Readers and Video Cameras

3‐ IN CONSTRUCTION

FCRHOUDE, DONALD A

6‐25‐18 The contractor has a PO. Work has started.

Design Firm: Contractor: External Contractor Name: Yates, Burns

2018‐0322

Morse Hall ‐ Third Floor Tempid Water Loop

3.1‐ SUBSTANTIAL COMPLETION

RRBRICKETT, ALEXANDER J

6/27/2018_Final inspection scheduled for 6/28

Design Firm: Contractor: External Contractor Name: GSPH

2017‐0004

Morse Hall ‐ Rm 345 Renovations

3.1‐ SUBSTANTIAL COMPLETION

FCRHENRY, PAUL A

6‐26‐18    Contacted stakeholder, he would like to wait and expand the system. Working with 

EHS on details of new control panel to be located in the corridor.

Design Firm: Harriman Contractor: External Contractor Name: TBD

2015‐2384

Murkland Hall Projects in Building 1

Murkland Hall ‐ Exterior Painting

3‐ IN CONSTRUCTION

RRBOIE, GREGG J

06/25/18,  Work in Progress

Design Firm: Contractor: External Contractor Name: APC Services of New England

2018‐0305

Nesmith Hall Projects in Building 8

Nesmith Hall ‐ Exterior Brick Wall and Parapet Repointing

2.5‐ IN PROCUREMENT

RRPOLITANO, FRANK

12/28/17__    P/O is all set waiting on weather and schedule to be able to complete work

Design Firm: TBD Contractor: External Contractor Name: Meditation Gardens

2014‐1972

Monday, July 02, 2018 Page 13 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Nesmith Hall ‐ Upward Bound / Talent Search Relocation

2.5‐ IN PROCUREMENT

SIHECKLER, BARBARA K

6/29/2018: Project expected complete by late August.

Design Firm: Contractor: External Contractor Name: Careno

2018‐0202

Nesmith Hall ‐ Phone‐a‐thon Fit Out

2.5‐ IN PROCUREMENT

SIBRICKETT, ALEXANDER J

6/27/2018_Design completed. Work began 6/26

Design Firm: Harriman Contractor: External Contractor Name:

2018‐0166

Nesmith Hall ‐ Bathroom Improvements and ADA Accessibility Modifications

3‐ IN CONSTRUCTION

SIBRICKETT, ALEXANDER J

6/27/2018_See project 2015‐2341 for updates.

Design Firm: Cowan & Goudreau Contractor: External Contractor Name: Greenleaf Construction

2018‐0339

Nesmith Hall ‐ Room Improvements G00CRA, G17‐G22, G24‐G26 (including G25B)

3‐ IN CONSTRUCTION

SIHECKLER, BARBARA K

6/29/2018: Project expected complete by 9/13.

Design Firm: Contractor: External Contractor Name: milestone

2018‐0173

Nesmith Hall ‐ South Roof Replacement

3‐ IN CONSTRUCTION

RRPOLITANO, FRANK

6/26/18_   Viking is set to begin 2nd week of July.

This is for valley repair.

Design Firm: ARM Contractor: External Contractor Name: Viking

2010‐0433

Nesmith Hall ‐ Bathroom Renovations

3‐ IN CONSTRUCTION

RRBRICKETT, ALEXANDER J

6/27/2018_Construction in progress. Anticipated finish date 8/17.

Design Firm: Cowan & Goudreau Contractor: External Contractor Name: Greenleaf Construction

2015‐2341

Monday, July 02, 2018 Page 14 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Nesmith Hall ‐ Bathroom Renovations DESIGN ONLY

3‐ IN CONSTRUCTION

RRBRICKETT, ALEXANDER J

6/27/2018__See project 2015‐2341

Design Firm: Cowan & Goudreau Contractor: Contractor Name:

2018‐0096

New England Center Projects in Building 2

New England Center ‐ Adams Tower ‐ Separation of HHW and DHW Design Only

2‐ IN DESIGN

RRHENRY, PAUL A

6‐26‐18   Design is in final review, project split between Energy and Hosing construction summer 

2019

Design Firm: Harriman Contractor: External Contractor Name: TBD

2016‐0402

New England Center ‐ Flood Damage Restoration and Repairs

3.1‐ SUBSTANTIAL COMPLETION

RR

Emergency Repair

HENRY, PAUL A

6‐26‐18  waiting for fin tube covers

Design Firm: Contractor: External Contractor Name: Milestione

2018‐0228

Northwest Heat Plant Projects in Building 1

Northwest Heat Plant ‐ New Construction

3‐ IN CONSTRUCTION

FCRPARSONS, STEPHANIE E

6/29/18: Construction ongoing, utlitiy piping being installed around the building locations.

Design Firm: Wilson Engineering Contractor: External Contractor Name: Froling Energy

2018‐0002

Old Dairy Barn Projects in Building 1

Old Dairy Barn ‐ Demolition

3.1‐ SUBSTANTIAL COMPLETION

RRRINES, DANIEL M

6‐26‐18: Loam and Seed complete, lawn growing. One small patch area at wall/ foundation 

transition needs to be fixed. Milestone will adress.

Design Firm: Contractor: External Contractor Name: Milestone

2012‐1085

Outdoor Facility Projects in Building 2

Monday, July 02, 2018 Page 15 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Outdoor Facility ‐ New Soccer/Lacrosse Field

2.5‐ IN PROCUREMENT

FCRGEUTHER, MARK E

06‐25‐2018: Construction scheduled to start on or about August 1, 2018.

Design Firm: Tighe & Bond Contractor: External Contractor Name: R.A.D. Sports

2017‐0285

Mooradian Field ‐ Subsurface Improvements and Turf Replacement

3.1‐ SUBSTANTIAL COMPLETION

RRGEUTHER, MARK E

06‐25‐2018: Substantially complete. Waiting on As‐Builts

Design Firm: Tighe & Bond Contractor: FCT Contractor Name: RAD Sports

2017‐0149

Outdoor Pool Projects in Building 1

Outdoor Pool ‐ Reconstruction of Outdoor Pool Facility

3.1‐ SUBSTANTIAL COMPLETION

CPPARSONS, STEPHANIE E

6/21/18  Preparing for project closeout.  Final items required for the project will be purchased 

and this project closed out by August 2018.

Design Firm: water technologies Contractor: External Contractor Name: Shawmut

2014‐2059

Parsons Hall Projects in Building 4

Parsons Hall ‐ Rms N104, N108 Classroom Renovation Iddles Lecture Halls Design 

Only

2‐ IN DESIGN

RRBRICKETT, ALEXANDER J

6/27/2018_ Harriman has begun design work on new lecture halls.

Design Firm: Harriman Contractor: External Contractor Name:

2018‐0145

Parsons Hall ‐ Processed Chilled Water System Replacement

2‐ IN DESIGN

RRBRICKETT, ALEXANDER J

6/27/2018_ Design work in progress.

Design Firm: Contractor: Contractor Name:

2018‐0048

Parsons Hall ‐ Rm S128 Ammonia Gas Control System

3.1‐ SUBSTANTIAL COMPLETION

FCRPARSONS, STEPHANIE E

6/21/18: Norris started installation for FA interface.  Prior to testing with EHS / DFD will need to 

review the limits and setpoint for alarm notification.

Design Firm: Norris Contractor: External Contractor Name: Norris

2017‐0431

Monday, July 02, 2018 Page 16 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Parsons Hall ‐ Rm S222 Minor Renovations

3.1‐ SUBSTANTIAL COMPLETION

FCRBRICKETT, ALEXANDER J

6/27/2018_Work completed. Punchlist items in progress.

Design Firm: Harriman Contractor: External Contractor Name: Yates & GSPH

2018‐0058

Paul College Projects in Building 1

Paul College ‐ HVAC and Control Modifications from Original Construction

3.1‐ SUBSTANTIAL COMPLETION

FCRPARSONS, STEPHANIE E

6/21/18. Further work may be required.  No issues have been reported as of this update.

Design Firm: RFS Contractor: External Contractor Name: TBD

2016‐0295

Paul Creative Arts Center Projects in Building 3

Paul Creative Arts Center ‐ Bratton Recital Hall Improved Access

2‐ IN DESIGN

FCRRINES, DANIEL M

6‐26‐18: Received plans from T&B, reviewed by ADA and PM, notes sent back to Tighe and Bond 

for final. Term contractor will be contacted to resubmitt pricing. Working in conjuncture with 

the music dept to attempt completion this summer.

Design Firm: Tighe & Bond Contractor: External Contractor Name:

2017‐0318

Paul Creative Arts Center ‐ Stair Egress Modifications

3.1‐ SUBSTANTIAL COMPLETION

RRPOLITANO, FRANK

6/26/18    1st phase is complete, except for 1 door which has been delivered wrong, we are 

waiting on a new ship date from factory.

Design Firm: Harriman Contractor: Contractor Name:

2017‐0232

Paul Creative Arts Center ‐ New Main Domestic Hot Water System Installation

3.5‐ WARRANTY REPAIRS

RRROULEAU, RICHARD A

7/1/2018 Update:  Water heater installation completed.  Domestic water booster pump design 

received and may be implemented as part of this project or possibly as a separate follow‐on 

project.

Design Firm: Harriman Associates Contractor: External Contractor Name: Charters Bros.

2018‐0249

Pettee Hall Projects in Building 2

Monday, July 02, 2018 Page 17 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Pettee Hall ‐ Rm G18 Mold Remediation and Investigation

3‐ IN CONSTRUCTION

RR

Emergency Repair

HECKLER, BARBARA K

6/29/2018: Project on track to be complete by 7/20.

Design Firm: Contractor: Contractor Name:

2018‐0251

Pettee Hall ‐ Slate Roof Repairs

3.1‐ SUBSTANTIAL COMPLETION

RR

Emergency Repair

ROULEAU, RICHARD A

7/1/2018 Update: Repairs completed pending review of drone verification photos.

Design Firm: Contractor: External Contractor Name: Skyline Roofing

2018‐0098

Philbrook Hall Projects in Building 4

Philbrook Hall ‐ Kitchen Modifications

2‐ IN DESIGN

FCRHENRY, PAUL A

6‐26‐18  Selected Charter Brothers as CMAR, will start Pre‐Construction Services to explor the 

site this summer

Design Firm: Harriman Contractor: External Contractor Name: Charters Brothers

2017‐0399

Philbrook Hall ‐ Boiler Forensic Investigation

2.5‐ IN PROCUREMENT

RRPARSONS, STEPHANIE E

6/29/18: RFX for engineering / forensic analysis submitted to procurement for posting.  Dye 

testing complete, no issues identified in condensate tank / pit.  Floor drain identified tie into 

storm drain.  Blake Engineering scheduling boiler  tube test and analysis week of 7/2.

Design Firm: TBD Contractor: External Contractor Name: TBD

2018‐0162

Philbrook Hall ‐ Boiler Replacement

3‐ IN CONSTRUCTION

BARPARSONS, STEPHANIE E

6/21/18: Boiler is not being installed until 2018‐0162 forensic review is complete.

Design Firm: Harriman Contractor: External Contractor Name: Eckhardt Johnson

2018‐0149

Philbrook Hall ‐ Refrigeration Rack System

3‐ IN CONSTRUCTION

FCRHENRY, PAUL A

6‐26‐18  in construction, CB making great progress

Design Firm: Harriman Assoc. Contractor: External Contractor Name: Charter Brothers

2015‐2492

Presidents House Projects in Building 1

Monday, July 02, 2018 Page 18 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Presidents House ‐ Major Site Repairs President Transition

3‐ IN CONSTRUCTION

RRRINES, DANIEL M

6‐26‐18: Driveway Binder course installed, replaced clay subbase with suitbale material and Geo 

fabric. Exterior work is substantially complete, awaiting punch list for mason. 

Wearing course will be installed after move in.

Design Firm: Contractor: External Contractor Name:  Bell and Flynn/ Chapman

2013‐1274

Presidentʹs House Projects in Building 1

Presidentʹs House ‐ Building Exterior and Interior Painting and Repairs

3‐ IN CONSTRUCTION

RRBRICKETT, ALEXANDER J

6/27/18_Interior and exterior work in progress.

Design Firm: Contractor: Contractor Name:

2013‐1032

Roads/Grounds Projects in Building 11

FY19 Road Repairs and Crack Sealing

1.1‐ PLAN/EST

RRHENRY, PAUL A

6‐26‐18  No scope this summer

Design Firm: Contractor: External Contractor Name: TBD

2017‐0024

Memorial Union Building ‐ Driveway and Sidewalk ‐ Design Only

2‐ IN DESIGN

SIRINES, DANIEL M

6‐26‐18: Hoyle Tanner working to complete 90% drawings. Schedule was set by PM and agreed 

to by HT. 90% will be submitted to UNH the end of August for review, Final Plans by the end of 

September, so project can be put out to bid this fall/winter.

Design Firm: Hoyle Tanner Contractor: Contractor Name:

2009‐0078

Campus ‐ Huddleston Fairchild Hetzel Site Stairs Design

2‐ IN DESIGN

RRGEUTHER, MARK E

06‐25‐2018: Several field visits have been made by the engineer collecting existing conditions 

data.

Design Firm: Hoyle‐Tanner Contractor: External Contractor Name: TBD

2018‐0294

Monday, July 02, 2018 Page 19 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

South Drive ‐ Design Advancement

2‐ IN DESIGN

SIHENRY, PAUL A

6‐26‐18   T&B recently estimated project at DD,  up dated estimate

Design Firm: Tighe & Bond Contractor: External Contractor Name:

2013‐1115

Campus ‐ Main Street South Sidewalk

2‐ IN DESIGN

SIRINES, DANIEL M

6‐26‐18: Contract with CMA finalized, Project kickoff meeting was held 6‐25‐18. Local concerns 

meeting 7‐11‐18, survey work almost complete.

Design Firm: CMA Engineering Contractor: Contractor Name:

2017‐0384

Campus ‐ South Drive ‐ Temporary Connection to Colovos Road

2.5‐ IN PROCUREMENT

SIGEUTHER, MARK E

06‐25‐2018‐On hold pending funding

Design Firm: Tighe & Bond Contractor: External Contractor Name: R.A.D. Sports

2018‐0267

FY19 Sidewalk and Walkway Repairs

3‐ IN CONSTRUCTION

RRHENRY, PAUL A

6‐26‐18  work under way with T&S and JTI

Design Firm: Contractor: External Contractor Name: T&S /  JTI

2017‐0027

FY19 Site Stair Repairs

3‐ IN CONSTRUCTION

RRHENRY, PAUL A

6‐26‐18  Ed Kimball working on repairs

Design Firm: Contractor: External Contractor Name: TBD

2017‐0026

Campus Wayfinding ‐ Phase 2

3‐ IN CONSTRUCTION

SIRINES, DANIEL M

6‐26‐18: Final walkthrough with barlo completed. 

Signs in production. 

Phase one punch list complete, pending SP and DR walk through this week.

Design Firm: Contractor: External Contractor Name: Barlo Signs

2016‐0157

Monday, July 02, 2018 Page 20 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Wildcat Stadium Parking Lot ‐Pay & Display Meter Installation & Pad

3.1‐ SUBSTANTIAL COMPLETION

FCRHOUDE, DONALD A

6‐25‐18  The project is 90% complete waiting for Bollard covers. Contractor says they are going in 

this week.

Design Firm: Contractor: External Contractor Name: T&S const

2018‐0150

Campus ‐ Wayfinding ‐ Phase 1

3.1‐ SUBSTANTIAL COMPLETION

SIKING, KATHLEEN M

4/27/18: Change order issued for punch list completion, to be completed in early summer.

Design Firm: Roll Barresi & Associates Contractor: FCT Contractor Name: Barlo Signs International

2017‐0211

Rudman Hall Projects in Building 15

Rudman Hall ‐ Conversion to DDC Controls

1.1‐ PLAN/EST

RRPARSONS, STEPHANIE E

6/21/18 ‐see ID 2010‐0479 for updates.

Design Firm: Contractor: External Contractor Name: TBD

2015‐2336

Rudman Hall ‐ Level G Instruction Lab Support Expansion

1.1‐ PLAN/EST

SIPARSONS, STEPHANIE E

6/29/18: Meeting scheduled 7/2 with stakeholders and campus planning to assist in  space 

reallocation for Instructional support to occupy loading dock.

Design Firm: TBD Contractor: External Contractor Name: TBD

2017‐0418

Rudman Hall ‐ Laboratory Fume Hood Control System Replacement

1.1‐ PLAN/EST

RRPARSONS, STEPHANIE E

6/21/18 ‐ Meeting with SMRT scheduled 7/2/18 to prepare for make ready work for AHU 

isolation is being scheduled for December 2018 with new HVAC control improvements to begin 

summer 2019.

Design Firm: SMRT, Inc. Contractor: External Contractor Name: TBD

2010‐0479

Rudman Hall ‐ Fire Alarm Replacement DESIGN

1.1‐ PLAN/EST

RRPARSONS, STEPHANIE E

6/21/18 ‐ Design review ongoing, installation of fire alarm is scheduled for Summer 2019.

Design Firm: SFC Engineering Contractor: External Contractor Name: TBD

2013‐1149

Monday, July 02, 2018 Page 21 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Rudman Hall ‐ Fire Alarm Replacement

1.1‐ PLAN/EST

RRPARSONS, STEPHANIE E

6/21/18 ‐ Please see  ID 2010‐0479 for updates.

Design Firm: SFC Contractor: External Contractor Name: TBD

2015‐2352

Rudman Hall ‐ DDC Controls Backstop

1.1‐ PLAN/EST

RRPARSONS, STEPHANIE E

6/21/18 ‐ see ID 2010‐0479 for updates

Design Firm: Contractor: Contractor Name:

2017‐0288

Rudman Hall ‐ Vivarium Upgrades Phase 2 DESIGN ONLY

2‐ IN DESIGN

SIPOLITANO, FRANK

6/26/18_   Design in process final drawings due by 7/15

Design Firm: Harriman Contractor: Contractor Name:

2017‐0214

Rudman Hall ‐ ARO Autoclave Replacement

2.5‐ IN PROCUREMENT

RRBRICKETT, ALEXANDER J

6/27/2018_Design documentation received.Obtaining quotes for work from contractors.

Design Firm: Contractor: Contractor Name:

2016‐0148

Rudman Hall ‐ Rm 148 Replacement Environmental Room Humidifier

2.5‐ IN PROCUREMENT

RRBOIE, GREGG J

06/25/18, Contacted Chet Holt . Humidifier is on order and will call me when it arrives.

Design Firm: Contractor: External Contractor Name: Harris Environmental Systems Inc.

2018‐0354

Rudman Hall ‐ Steam Domestic Hot Water Exchanger

3‐ IN CONSTRUCTION

RRPOLITANO, FRANK

6/26/18_   New unit is installed, start‐up expected on 6/27

Design Firm: Contractor: External Contractor Name: GSP

2017‐0366

Monday, July 02, 2018 Page 22 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Rudman Hall ‐ Water Booster Pump  Replacement

3‐ IN CONSTRUCTION

RRPOLITANO, FRANK

6/26/18_   GSP will do this work, we are looking for a Saturday for install.

Design Firm: Contractor: External Contractor Name: GSP

2017‐0367

Rudman Hall ‐ G Level Flood Restoration and Repair

3.1‐ SUBSTANTIAL COMPLETION

RR

Emergency Repair

BRICKETT, ALEXANDER J

6/27/2018_All affected areas have been repaired. Equipment replacement in progress.

Design Firm: Contractor: Contractor Name:

2018‐0230

Rudman Hall ‐ Dishwasher Fire/ Sprinkler Flood Restoration

3.1‐ SUBSTANTIAL COMPLETION

RR

Emergency Repair

KING, KATHLEEN M

4/27/18: Restoration is complete, project is also labeling fire sprinkler valves and considering 

modifying ventilation of space behind washer.

Design Firm: Contractor: Contractor Name:

2018‐0252

Rudman Hall ‐ Steam Back Pressure Turbine

3.1‐ SUBSTANTIAL COMPLETION

FCRPARSONS, STEPHANIE E

6/29/18: Controls integration with Cogen Plant complete.  Still working with UNH IT / 

networking for troubleshooting access to the web interface.

Design Firm: Waldron Engineering Contractor: External Contractor Name: Ewing Controls / TVC

2016‐0162

Rudman Hall ‐ Rm G51 Flood Restoration

3.1‐ SUBSTANTIAL COMPLETION

RR

Emergency Repair

BRICKETT, ALEXANDER J

6/27/2018_ Ceiling tiles completed. Old refrigerator to be removed when contents are moved.

Design Firm: Contractor: FCT Contractor Name: Sprague

2017‐0293

Service Building Projects in Building 3

Service Building ‐ Dispatch Center Keltron System

3‐ IN CONSTRUCTION

FCRPARSONS, STEPHANIE E

6/29/18:  Gregg Hall ʹnodeʹ is complete.  Team will begin working on Stoke ʹnodeʹ with 

anticipation of completion August 2018.

Design Firm: Contractor: External Contractor Name: Norris / UNH Telecom

2016‐0123

Monday, July 02, 2018 Page 23 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Service Building ‐ Replacement and Installation of Isolation valves

3‐ IN CONSTRUCTION

RRPARSONS, STEPHANIE E

6/21/18 ‐ Please see project ID 2009‐0064 for updates and budget.

Design Firm: N/A Contractor: External Contractor Name: TBD

2013‐1465

Service Building ‐ Fire Alarm Replacement and Building System Upgrades

3‐ IN CONSTRUCTION

RRPARSONS, STEPHANIE E

6/29/18 Heating line replacement and isolation valve installation is ongoing.  Fire alarm is 

substantially complete, working with Norris / Scarponi on minor punchlist items prior to 

scheduling SFMO walk.  Scheduling for 7/19/18 agenda walk through.

Design Firm: Harriman Contractor: External Contractor Name: Charters Brothers

2009‐0064

Spaulding Hall Projects in Building 1

Spaulding Hall ‐ Expansion & Renovations ‐ Biological Science Initiative

2‐ IN DESIGN

CPROULEAU, RICHARD A

7/1/2018 Update: CM has been selected.  Contract to be circulated soon for signatures.  

Preconstruction services to commence thereafter.

Design Firm: Ellenzweig Contractor: External Contractor Name: Skanska USA Building

2016‐0278

Stillings Hall Projects in Building 1

Dining Buildings ‐ Add Digital Menu Boards To Dining and Retail Outlets

3‐ IN CONSTRUCTION

FCRHOUDE, DONALD A

6‐25‐18 The contractor has the PO. We are schedueling a start date and a plan.

Design Firm: Contractor: External Contractor Name: Yates

2018‐0333

Stoke Hall Projects in Building 3

Stoke Hall ‐ Registrarʹs Office Minor Renovation

2‐ IN DESIGN

SIHECKLER, BARBARA K

6/29/2018: Will meet with RO in July.

Design Firm: Contractor: Contractor Name:

2018‐0175

Monday, July 02, 2018 Page 24 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Stoke Hall ‐ Business Service Center Exterior Wall Repairs

3‐ IN CONSTRUCTION

RRBRICKETT, ALEXANDER J

6/27/2018_ Construction in progress.

Design Firm: Contractor: Contractor Name:

2018‐0213

Stoke Hall ‐ Elevator upgrade

3‐ IN CONSTRUCTION

FCRROULEAU, RICHARD A

7/1/2018: Work is in progress, going well and to be complete prior to the fall semester.

Design Firm: Elevator Consulting Assoc. Contractor: External Contractor Name: Careno Construction

2018‐0117

Taylor Hall Projects in Building 1

Taylor Hall ‐ Rm 102 Create Wall and Door Accesss

2.5‐ IN PROCUREMENT

FCRHECKLER, BARBARA K

6/29/2018: Funding available 7/1.  Start date dependent on Milestoneʹs summer schedule; work 

may need to wait until September.

Design Firm: Contractor: External Contractor Name: Milestone

2018‐0148

Thompson Hall Projects in Building 1

Thompson Hall ‐ Card Access and Security Camera Cable Pathways

3.1‐ SUBSTANTIAL COMPLETION

FCRHOUDE, DONALD A

6‐25‐18  This project is for the most part complete. The dept has some issues to work oout with 

providing an administrator. We are doing punch list.

Design Firm: Contractor: External Contractor Name: Yates

2018‐0246

Utility Distribution Projects in Building 11

Utility Distribution ‐ Library Way Tunnel Design

1.1‐ PLAN/EST

RRKING, KATHLEEN M

4/27/18: PM is waiting on final direction from asset management and utilities

Design Firm: Contractor: Contractor Name:

2017‐0005

Monday, July 02, 2018 Page 25 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Utility Distribution ‐ College Brook Culvert Repair

2‐ IN DESIGN

RRHENRY, PAUL A

6‐26‐18   Exposted site, have to remove electrical duct bank to do work, working with Energy to 

incluce some High Voltage work to take atvanatve of moving the switches above ground, 

meeting next week.

Design Firm: Tighe & Bond Contractor: External Contractor Name: TBD

2018‐0100

UNH Utility Master Plan

2‐ IN DESIGN

SIKING, KATHLEEN M

4/27/18: Final comments returned to consultants and final report due May 11, followed by 

presentations by consultants.

Design Firm: RMF Contractor: Contractor Name:

2017‐0169

Utility Distribution ‐ HHW Line Replacement Service Building to Zais Hall

2‐ IN DESIGN

RRRINES, DANIEL M

6‐26‐28: Met with DFD and EMS: will need to maintain one way access utilizing keyed in steel 

plates. 

RH White and Charter Bros pricing job.

Design Firm: Contractor: Contractor Name:

2017‐0354

Utility Distribution ‐ Edgewood Water Tank ‐ Decomissio

2.5‐ IN PROCUREMENT

FCRBRICKETT, ALEXANDER J

6/27/2018_PO for demolition issued to Charter Bros. Work to occur 8/1/18.

Design Firm: Contractor: External Contractor Name: Charter Brothers

2010‐0729

Utility Distribution ‐ Reconfigure and Relocation of Colovos SSL0109 and SSL0486

2.5‐ IN PROCUREMENT

RRGEUTHER, MARK E

06‐25‐2018: Temporary road approved by DFD and UNHPD. Temp road scheduled for 

construction the end of the week of July 9. Manhole replacement the week of July 16.

Design Firm: Tighe & Bond Contractor: External Contractor Name: T&S Construction

2018‐0183

Utility Distribution ‐ Main Street Tunnel Corrective Repair and Design

3‐ IN CONSTRUCTION

RRRINES, DANIEL M

6‐26‐18: RH White is substantially complete. Waiting on punchlist items to be completed, 

including RH White approval of  plan for steam shut down to fix the SS Brackets inside the 

tunnel.

Design Firm: Simpson Gumpertz & Heger Contractor: External Contractor Name: R.H. White Construction

2018‐0155

Monday, July 02, 2018 Page 26 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Utility Distribution ‐ HV ‐ Circuit 11 Hamilton Smith to Memorial Union Phase II

3‐ IN CONSTRUCTION

SIHOUDE, DONALD A

6‐25‐18  The contractor has a PO. Work is in Progress, I have extended the scope of work to also 

install the HV cable between the new HV switch and the H/S Sector cabinet.

Design Firm: Contractor: External Contractor Name:

2018‐0067

Utility Distribution ‐ Horton to PCAC HHW Line Replacements and Pit Repairs

3‐ IN CONSTRUCTION

RRROULEAU, RICHARD A

7/1/2018 Update: Construction is ongoing.  All piping between Horton and PCAC pits and all 

service piping into Horton and PCAC has been installed, xrayed and hydrostatically and tested.  

Trench covers have been reinstalled between Horton and PCAC pits and backfilling is in 

progress at the Horton and PCAC service entrance piping.  Re‐establishment of landscaping and 

hardscaping between Horton and PCAC pits underway.  Intent is to have Ramoneʹs open for 

business on or before July 8.  Piping inside pits has commenced.  Phase 2 trench work from 

PCAC toward Spaulding has commenced.  Unforeseen/hidden conditions are being addressed as 

they come to light.

Design Firm: Harriman Associates Contractor: External Contractor Name: Charters Bros.

2017‐0094

Utility Distribution ‐ HHW and Sewer Line Replacement College Road to Kendall and 

Nesmith

3‐ IN CONSTRUCTION

RRGEUTHER, MARK E

06‐25‐2018: Work continues. Progress is slow due to numerous unforeseen conditions. 

Contractor has hired additional resources.

Design Firm: Harriman/Tighe & Bond Contractor: External Contractor Name: Waterline Industries

2017‐0093

Utility Distribution ‐ Gables Distribution Line Replacements

3.1‐ SUBSTANTIAL COMPLETION

RRKING, KATHLEEN M

4/27/18: Project is substantially complete, waiting on final invoicing.

Design Firm: Harriman Contractor: External Contractor Name: RH White

2017‐0348

Veterinary Diagnostic Lab Projects in Building 1

NHVDL ‐ Relocation

3‐ IN CONSTRUCTION

SIPARSONS, STEPHANIE E

6/21/18:  Final details being completed; whiteboard in necropsy, hose reel in necropsy, outlet on 

standby power vs normal power.  Additional smoke detection will be installed in lab area at 

customer request.

Design Firm: Contractor: External Contractor Name: Careno Construction / Norris

2013‐1537

Water Treatment Plant Projects in Building 1

Monday, July 02, 2018 Page 27 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Water Treatment Plant ‐ New Construction

3‐ IN CONSTRUCTION

SIGEUTHER, MARK E

06‐25‐2018: Concrete tank work ongoing. Site work on going. Mock up wall approved

Design Firm: Woodard & Curran Contractor: External Contractor Name: Waterline Industries

2008‐0038

Whittemore Center ‐ Arena Projects in Building 4

Whittemore Center ‐ Arena ‐ Ice System Engineering Evaluation

1.1‐ PLAN/EST

RRBRICKETT, ALEXANDER J

6/27/2018_Meeting on 3/2 indicated that ice system needs replacement. Initial design phase in 

progress.

Design Firm: Stevens Engineering Contractor: Contractor Name:

2018‐0235

Whittemore Center ‐ Arena ‐ Engineering Evaluation for Exterior Concrete and Interior 

Mechanical Room Slab

3‐ IN CONSTRUCTION

RRRINES, DANIEL M

6‐26‐18: SGH set crack monitors in NW Wall, and preformed survey and analysis of interior 

mechanical slab on 6‐25‐18. Data will be analyzed, and futher monitoring visits will be planned.

Design Firm: SGH Contractor: Contractor Name:

2017‐0394

Whittemore Center ‐ Arena ‐ Fire Alarm System Replacement

3‐ IN CONSTRUCTION

FCRPARSONS, STEPHANIE E

6/29/18:  Final modifications to glass tower with DFD coordination nearing completion.  

Modifications include, removing speaker / strobe (nusence) remove manual smoke evacuation 

interface, provide permanent source of heat to the room, provide 6ʹ x 2ʹ table for material storage 

and site command use.

Design Firm: SFC Engineering Contractor: External Contractor Name: Careno Construction

2015‐2400

Whittemore Center ‐ Arena ‐ Concessions Stand Electrical Work

3‐ IN CONSTRUCTION

FCRBRICKETT, ALEXANDER J

6/27/2018_Yates has finished electrical work. Telecom work in progress.

Design Firm: Contractor: External Contractor Name: Yates

2018‐0157

Woodside ABC Projects in Building 1

Monday, July 02, 2018 Page 28 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Woodsides Complex ‐ Boiler Replacements and Modifications

3‐ IN CONSTRUCTION

FCRPOLITANO, FRANK

6/26/18_    New boilers are in place, piping has begun in PQR, this unit is 90% complete. 2 other 

buildings are expected to be ready for electrical by 6/29.

Design Firm: SMRT Contractor: External Contractor Name: Careno

2017‐0408

Zais Hall Projects in Building 1

Zais Hall ‐ Room 205 Carpet/Flooring Replacement

1.1‐ PLAN/EST

RRHECKLER, BARBARA K

6/29/2018: Will address week of 7/3.

Design Firm: Contractor: Contractor Name:

2018‐0359

Monday, July 02, 2018 Page 29 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management