Facilities Project Management Monthly Report by Building
Monday, July 02, 2018 156Approved Project
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
10 Pettee Brook Lane Projects in Building 1
10 Pettee Brook Lane ‐ Renovations to Space
3‐ IN CONSTRUCTION
FCRROULEAU, RICHARD A
7/1/2018 Update: Construction is underway. Addressing submittals and RFIs. Substantial
completion anticipated for mid to late‐August. Furniture has been ordered.
Design Firm: Manypenny Murphy Archite Contractor: External Contractor Name: Landlord
2017‐0472
11 Brook Way Projects in Building 1
11 Brook Way ‐ Building Demolition
3‐ IN CONSTRUCTION
RRRINES, DANIEL M
6‐26‐18: Contract fully exectuted, abatement under way. Followed by Utilities cut/cap, and demo
permit/ Demo.
Design Firm: Contractor: External Contractor Name: Air Quality Experts
2016‐0437
121 Technology Drive Projects in Building 3
121 Technology Drive ‐ Advanced Manufacturing Center
3‐ IN CONSTRUCTION
FCRBRICKETT, ALEXANDER J
6/27/2018_Punchlist items in progress.
Design Firm: JSA, Inc. Contractor: External Contractor Name: Careno Construction
2016‐0301
121 Technology Drive ‐ Fit Up of Unassigned Suite
3.1‐ SUBSTANTIAL COMPLETION
FCRBRICKETT, ALEXANDER J
6/27/2018_Update ‐ Please refer to ID 2016‐0186 for updates.
Design Firm: Contractor: External Contractor Name: Careno Construction
2018‐0062
121 Technology Drive ‐ Interior Lease Space Renovations
3.1‐ SUBSTANTIAL COMPLETION
FCRBRICKETT, ALEXANDER J
6/27/2018_Project is substantially complete. Punchlist and completion items ongoing.
Design Firm: Cowan‐Goudreau Contractor: External Contractor Name: Careno Construction
2016‐0186
5 Leavitt Lane Projects in Building 1
Monday, July 02, 2018 Page 1 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
5 Leavitt Lane ‐ Library Storage Building Structure Investigation
2‐ IN DESIGN
RRRINES, DANIEL M
6‐26‐18: Engineer was given photos of bar joist, will work up a structural analysis, and
recommendation.
Design Firm: Contractor: Contractor Name:
2018‐0363
88 Commercial Street Projects in Building 1
88 Commercial Street ‐ Mechanical Tech Lab
3.1‐ SUBSTANTIAL COMPLETION
FCRROULEAU, RICHARD A
7/1/2018 Update: Many tools and some larger pieces of equipment purchased and in place.
Need to close out 1850 Associates purchase order to determine how much funding is available
for additional tools and equipment.
Design Firm: John Jordan Contractor: External Contractor Name: 1850 PDRA Associates
2016‐0428
9 Madbury Road Projects in Building 1
9 Madbury Road ‐ Lease Space Office Fit Up
3‐ IN CONSTRUCTION
SIROULEAU, RICHARD A
7/1/2018 Update: Construction is nearly complete. Furniture has been ordered and will be
installed the last weke of July. Move‐in is scheduled for 8/1.
Design Firm: Harriman Contractor: External Contractor Name: Milestone, Denron, Martineau, Sprague, Envirovan
2018‐0092
Adams Tower Projects in Building 1
Adams Tower ‐ Verizon Wireless Antenna Upgrade
1.1‐ PLAN/EST
FCRPOLITANO, FRANK
6/26/18__ We are coordinating work with Verizon for summer execution. I have not heard back
from Verizon in an month. I have not been able to get in touch with our contacts.
Design Firm: Contractor: External Contractor Name: Verizon
2018‐0310
Barton Hall & Cole Hall Projects in Building 1
Cole Hall ‐ HVAC HU‐3 EQ5389 Cat Walks and Accessibility Modifications
2.5‐ IN PROCUREMENT
RRHOUDE, DONALD A
6‐25‐18 We are firming up the AIA document at this time. .
Design Firm: Oak Point Contractor: External Contractor Name: Milestone E & C
2018‐0086
Building Interior Projects in Building 2
Monday, July 02, 2018 Page 2 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Thompson Hall ‐ Graduate Student Center
2.5‐ IN PROCUREMENT
SIHECKLER, BARBARA K
6/29/2018: Project on track for late‐August/early September completion.
Design Firm: Contractor: External Contractor Name:
2017‐0212
Campus ‐ UNH Fire Damper Study
3.1‐ SUBSTANTIAL COMPLETION
FCRHENRY, PAUL A
6‐26‐18 buildings Survey complete, for first 4 buildings.
Design Firm: Harriman Contractor: Contractor Name:
2017‐0205
Chase Ocean Engineering Lab Projects in Building 3
Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe
3‐ IN CONSTRUCTION
FCRHOUDE, DONALD A
6‐25‐18 This project is in progress. It should be complete by the end of the week.
Design Firm: Contractor: External Contractor Name: Yates Electric
2018‐0314
Chase Ocean Engineering Lab ‐ Tank Room Ceiling Restoration and Replacement of
HV‐3
3‐ IN CONSTRUCTION
RRGEUTHER, MARK E
06‐25‐2018: HV‐3 installation complete. Controls installation scheduled for this week, start up the
week of July 2.
Design Firm: HL Turner Contractor: External Contractor Name: Milestone
2017‐0153
Chase Ocean Engineering Lab ‐ Expansion
3.1‐ SUBSTANTIAL COMPLETION
FCRGEUTHER, MARK E
06‐25‐2018: Transformer swap out for new research equipment, scheduled for June 30.
Design Firm: HL Turner Contractor: External Contractor Name: Milestone Engineer & Construction
2015‐2755
Childhood Study & Development Center Projects in Building 1
Childhood Study & Development Center ‐ Roof Repair and Misc Repairs
2.5‐ IN PROCUREMENT
RRPOLITANO, FRANK
6/26/18_ I have sent this out to various term contractors and should have pricing by 7/6
Design Firm: SMRT Contractor: External Contractor Name:
2018‐0159
Monday, July 02, 2018 Page 3 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Conant Hall Projects in Building 2
Conant Hall ‐ DDC Controls Installation
3.1‐ SUBSTANTIAL COMPLETION
RRHENRY, PAUL A
6‐26‐18 fiinish commissioning
Design Firm: Harriman Contractor: Contractor Name:
2018‐0192
Conant Hall ‐ Minor Interior Renovations
3.1‐ SUBSTANTIAL COMPLETION
SIHENRY, PAUL A
6‐26‐18 Building occupied Working on punch List, and finishing MEP improvements
Design Firm: Mannypenny Murphy Contractor: External Contractor Name: Trumbell Nelson
2016‐0410
Dimond Library Projects in Building 3
Dimond Library ‐ Minor Renovation for Customer Service and Addison Areas
1.1‐ PLAN/EST
FCRHECKLER, BARBARA K
6/29/2018: Careno estimate received. Awaiting revised sketch fro Salmon Falls Woodworks.
Design Firm: Contractor: External Contractor Name:
2017‐0423
Dimond Library ‐ Interior Painting of Main Lobby
3‐ IN CONSTRUCTION
RRBOIE, GREGG J
06/25/18, Work in Progress
Design Firm: Contractor: External Contractor Name: APC Services of New England
2018‐0307
Dimond Library – Room 221 Renovation
3‐ IN CONSTRUCTION
SIHECKLER, BARBARA K
6/29/2018: Project on track to be complete by 8/1.
Design Firm: Contractor: Contractor Name:
2018‐0179
DPW Grounds & Roads Projects in Building 1
Monday, July 02, 2018 Page 4 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
DPW Grounds & Roads ‐ Garage
3.1‐ SUBSTANTIAL COMPLETION
FCRHENRY, PAUL A
6‐26‐18 workign out fire calking details with Careno and some minor plumbing deficiencies
witht the existing power washer. Will re‐schedule C of O inspection after reviewing contractor
SFMO binder
Design Firm: Careno Contractor: External Contractor Name: Careno
2013‐1610
Elliott Alumni Center Projects in Building 1
Elliott Alumni Center ‐ HHW Conversion to Natural Gas Boiler
3‐ IN CONSTRUCTION
FCRPOLITANO, FRANK
6/26/18_ Work has begun, old piping has been removed. New pad is expected to be poured on
6/26. GSP has equipment in their warehouse.
Design Firm: SMRT Contractor: External Contractor Name: Granite State Plumbing
2017‐0443
Field House Projects in Building 3
Field House ‐ Womens Team Locker Room Upgrades ‐ Planning Only
2‐ IN DESIGN
SIHECKLER, BARBARA K
6/29/2018: Harriman working on concept drawings; expect drafts for review by early August.
Design Firm: Contractor: Contractor Name:
2018‐0198
Field House ‐ New Ski Locker Room/Team Area
2‐ IN DESIGN
FCRBRICKETT, ALEXANDER J
6/27/2018__Working with design team for final space renderings.
Design Firm: Harriman Contractor: Contractor Name:
2017‐0251
Field House ‐ Steam to Domestic Hot Water System Replacement
3‐ IN CONSTRUCTION
RRPARSONS, STEPHANIE E
6/29/19: Contract has been executed. Awaiting shipping details to coordinate work within field
house.
Design Firm: Harriman Contractor: External Contractor Name: Northern Peabody
2017‐0325
Gables Building A Projects in Building 1
Monday, July 02, 2018 Page 5 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Gables Buildings A, B & C ‐ Replace the EPDM roof tops
3‐ IN CONSTRUCTION
FCRPOLITANO, FRANK
6/26/18_ Viking has begun with Gables C it is 60% complete. Each roof is expected to take 2
weeks.
Design Firm: ARM Contractor: External Contractor Name: Viking
2018‐0118
Gables Building B Projects in Building 1
Gables A,B,C ‐ Boiler Plant Replacement
3‐ IN CONSTRUCTION
FCRPOLITANO, FRANK
6/26/18_ Most Demo is complete, new boilers ship on 6/27. Some pre fab is complete waiting on
delivery of equipment.
Design Firm: SMRT Contractor: External Contractor Name: Charters Brothers
2018‐0076
Gregg Hall Projects in Building 4
Gregg Hall ‐ Chiller Replacement
2.5‐ IN PROCUREMENT
RRPARSONS, STEPHANIE E
6/29/18: RFB has been posted. Chiller replacement to occur October / November after primary
cooling season.
Design Firm: Harriman Contractor: External Contractor Name: TBD
2017‐0281
Gregg Hall ‐ Fire Damper Repairs
2.5‐ IN PROCUREMENT
FCRHENRY, PAUL A
6‐26‐18 Issued PPʹs to Milestone, they are gearing up to start first building.
Design Firm: Harriman Contractor: External Contractor Name: Milestione
2018‐0327
Gregg Hall ‐ Chiller Replacement ‐ Funding for Construction
2.5‐ IN PROCUREMENT
RRPARSONS, STEPHANIE E
6/29/18: Please refer to project 2017‐0281 for updates on construction.
Design Firm: Harriman Contractor: External Contractor Name: TBD
2017‐0250
Gregg Hall ‐ Basement Flood Restoration
3‐ IN CONSTRUCTION
RR
Emergency Repair
BRICKETT, ALEXANDER J
6/27/2018_Drywall work to be competed when pump station upgrades are installed. Work to be
coordinated with John OʹRourke.
Design Firm: Contractor: External Contractor Name:
2018‐0132
Monday, July 02, 2018 Page 6 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Hamel Recreation Center Projects in Building 2
Hamel Recreation Center ‐Motorized Shades
3‐ IN CONSTRUCTION
FCRPARSONS, STEPHANIE E
6/29/18: This work has been approved. Scheduled completion on or before 8/3/18.
Design Firm: Contractor: External Contractor Name: Portsmouth Blind Shade / Yates
2018‐0259
Hamel Recreation Center ‐ Expansion & Renovations
3‐ IN CONSTRUCTION
CPPARSONS, STEPHANIE E
6/29/18: AWF on floor 3 is complete. Floor 3 has been turned over to Campus Recreation.
Design Firm: HGA Contractor: FCT Contractor Name: Shawmut
2013‐1176
Hamilton Smith Hall Projects in Building 2
Hamilton Smith Hall ‐ Bi‐Directional Amplifier Installation
2‐ IN DESIGN
RRPARSONS, STEPHANIE E
6/29/18: Working with Notifier / Norris for BDA design and quotes.
Design Firm: Norris Inc. Contractor: External Contractor Name: TBD
2016‐0116
Hamilton Smith Hall ‐ Major Renovation Project
3.5‐ WARRANTY REPAIRS
SIROULEAU, RICHARD A
7/1/2018 Update: One year warranty period has ended. Skanska and subcontractors to complete
warranty work this summer. Also working with Milestone to do some small follow‐up work. Bi‐
directional amplifier per Town ordinance split off as separate project (2018‐0223).
Design Firm: DiMella Shaffer Associates Contractor: External Contractor Name: Skanska USA, Inc.
2012‐1851
Health & Wellness Building Projects in Building 2
Health & Wellness Building ‐ Physical Reorganization of Services
3‐ IN CONSTRUCTION
FCRHECKLER, BARBARA K
6/29/2018: Previously approved carpet and millwork expected complete by 8/3. Unexpected
lobby scope in planning and estimating; completion date TBD.
Design Firm: Harriman A/E Contractor: Contractor Name:
2017‐0340
Monday, July 02, 2018 Page 7 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Health & Wellness Building ‐ Fire Alarm System Upgrade
3.1‐ SUBSTANTIAL COMPLETION
FCRPARSONS, STEPHANIE E
6/29/18: Testing / walk through with DFD / SFMO scheduled 7/19 for final acceptance. This was
a panel only replacement, not a full system replacement.
Design Firm: Contractor: External Contractor Name: Norris
2018‐0182
Hewitt Hall Projects in Building 1
Hewitt Hall ‐ Fire Damper Repairs
2.5‐ IN PROCUREMENT
FCRHENRY, PAUL A
6‐26‐18 Issued PPʹs to Milestone, they are gearing up to start first building.
Design Firm: Harriman Contractor: External Contractor Name: Milestione
2018‐0325
Holloway Commons Projects in Building 2
Holloway Commons ‐ Retro‐Commissioning Repairs
1.1‐ PLAN/EST
FCRBRICKETT, ALEXANDER J
6/27/2018 ‐ RFS has been contacted to establish scope of repairs needed.
Design Firm: Contractor: External Contractor Name:
2016‐0500
Holloway Commons ‐ Expansion Project
3.5‐ WARRANTY REPAIRS
CPROULEAU, RICHARD A
7/1/2018 Update: There remain just a few project items that need to be resolved.
Design Firm: Miller Dyer Spears Contractor: External Contractor Name: North Branch Construction
2014‐1657
Hood House Projects in Building 1
Hood House ‐ Minor Renovation for Career and Professional Success Center
3.1‐ SUBSTANTIAL COMPLETION
SIHENRY, PAUL A
6‐26‐18 Project in punch list, occupants in the building.
Design Firm: Mannypenny Murphy Contractor: External Contractor Name: Trumbell Nelson
2016‐0409
Horton Social Science Center Projects in Building 2
Monday, July 02, 2018 Page 8 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Horton Social Science Center ‐ 3rd Floor Daiken Unit Recommissioning
2.5‐ IN PROCUREMENT
FCRHENRY, PAUL A
6‐26‐18 Operations locked out the Heat, checking to see if we still want to Retro‐Commission the
system.
Design Firm: Harriman / RFS Contractor: External Contractor Name: RFS / Harriman
2018‐0295
Horton Social Science Center ‐ 1st Floor Renovation ‐ Phase 2
3‐ IN CONSTRUCTION
SIHENRY, PAUL A
6‐26‐18 Abatement and Demo complete, working on framing and rough in of electrical and
HVAC.
Design Firm: Harriman Contractor: External Contractor Name: Milestone
2008‐0203
Huddleston Hall Projects in Building 3
Huddleston Hall ‐ Fire Code Assessment and Life Safety Plan
1‐ ASSIGNED
RRHENRY, PAUL A
Design Firm: SFC Engineering Partnership Contractor: Contractor Name:
2012‐0841
Huddleston Hall ‐ Roof Replacement Design Only
2‐ IN DESIGN
RRHENRY, PAUL A
6‐26‐18 Harriman working with ARM to include the design. Starting roof investigation 2013‐
1155 Huddleston Egress project.
Design Firm: ARM Contractor: External Contractor Name: Harriman
2016‐0165
Huddleston Hall ‐ Design of Egress Modifications
2‐ IN DESIGN
RRHENRY, PAUL A
6‐26‐18 MEP Study ready for review next week, DD for building mid July.
Design Firm: Harriman Contractor: External Contractor Name: Harriman
2013‐1155
Jackson Lab Projects in Building 1
Jackson Lab ‐ Autoclave Replacement
2.5‐ IN PROCUREMENT
RRHOUDE, DONALD A
6‐25‐18 A PO has been provided to the contractor for this work. Equipment has been ordered. I
am waiting for an ETA on equipment to schedule a const start. Expected in June.
Design Firm: Contractor: FCT Contractor Name:
2017‐0377
Monday, July 02, 2018 Page 9 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
James Hall Projects in Building 4
James Hall ‐ Heat Exchanger Replacement
2.5‐ IN PROCUREMENT
RR
Emergency Repair
PARSONS, STEPHANIE E
6/29/18: Submittals have been reviewed. NPI provided tenative ship date of 8/17 for equipment.
Design Firm: Harriman Associates Contractor: External Contractor Name: NPI
2017‐0393
James Hall ‐ HVAC Modifications Investigation and Design
3‐ IN CONSTRUCTION
RRPOLITANO, FRANK
6/26/18_ We have replaced the missing gasket to the AHU, however we are still investigating
the fans as a potential cause as well.
Design Firm: Contractor: Contractor Name:
2018‐0270
James Hall ‐ AHU‐3 Failure Investigation and Repair
3.1‐ SUBSTANTIAL COMPLETION
RR
Emergency Repair
BRICKETT, ALEXANDER J
6/27/2018_ Repairs and room reconditioning finished. Final commisioning and setpoints being
work on.
Design Firm: Contractor: Contractor Name:
2018‐0309
James Hall ‐ Slate Roof Repairs
3.1‐ SUBSTANTIAL COMPLETION
RR
Emergency Repair
ROULEAU, RICHARD A
2/26/2018 ‐ Repairs have been completed.
Design Firm: Contractor: External Contractor Name: Skyline Roofing
2018‐0099
Kendall Hall Projects in Building 2
Kendall Hall ‐ Levels 3‐ 5 Repurposing CE and COLSA ‐ Design Only
1.1‐ PLAN/EST
SIPOLITANO, FRANK
6/26/18_ Update ‐ MPM has been awarded the building study for this project.
Design Firm: Contractor: External Contractor Name: MPM
2017‐0186
Kendall Hall ‐ Upgrade the Nutrition Assessment & Teaching Labs
3.1‐ SUBSTANTIAL COMPLETION
FCRPARSONS, STEPHANIE E
6/29/18: Awaiting furniture delivery.
Design Firm: A Contractor: FCT Contractor Name:
2017‐0235
Monday, July 02, 2018 Page 10 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Leavitt Cntr Transportation Center Projects in Building 1
Leavitt Cntr Transportation Center ‐ Bus Maintenance Lift Replacements
2.5‐ IN PROCUREMENT
FCRHOUDE, DONALD A
5‐22‐18 I am working with Purchasing to put this out to bid. We tried but only received 1 SOQ,
we are adjusting our dates and putting it back out for more request.
Design Firm: Contractor: External Contractor Name: Design build
2017‐0447
MacFarlane Greenhouse Projects in Building 1
MacFarlane Greenhouse ‐ Renovation/Improvements
2‐ IN DESIGN
FCRHOUDE, DONALD A
6‐25‐18 I have received a completed FCR from the customer, I am waiting for my BSC to inform
me they have set up an account to write the Engineering firm a PO.
Design Firm: SMRT Contractor: Contractor Name:
2019‐0001
McConnell Hall Projects in Building 1
McConnell Hall ‐ Water Intrusion Investigation
3‐ IN CONSTRUCTION
FCRPOLITANO, FRANK
6/26/18_ Careno has sealed the window wall where the leaks were occuring. I am waiting for
report , we believe there is a bigger issue , we should have a final report by 6/29.
Design Firm: Contractor: External Contractor Name: Careno
2016‐0297
Memorial Union Building Projects in Building 7
Memorial Union Building ‐ Granite State Room Exterior Deck
3‐ IN CONSTRUCTION
BARROULEAU, RICHARD A
7/1/2018 Update: Removals of distressed concrete nearing completion. Surface prep and
patching to commence soon..
Design Firm: Hoyle Tanner Contractor: Contractor Name: Charters Bros.
2017‐0352
Memorial Union Building ‐ Ramp Structural Steel and Concrete Repairs
3‐ IN CONSTRUCTION
BARROULEAU, RICHARD A
7/1/2018 Update: Due to funding and term contract limitations, this project has been deferred,
although components of it may be performed as ancilary work associated with 2017‐0352 Granite
State Room Balcony Repairs.
Design Firm: Hoyle Tanner Contractor: Contractor Name:
2017‐0138
Monday, July 02, 2018 Page 11 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Memorial Union Building ‐ Strafford Room Wood Flooring Repair
3‐ IN CONSTRUCTION
BARPOLITANO, FRANK
6/26/18_ Sprague has completed the sub‐floor. Rubber flooring is at the factory being cut and is
set for delivery beginning of July.
Design Firm: Contractor: External Contractor Name: Sprague
2018‐0299
Memorial Union Building ‐ Exterior Deck Recoating
3‐ IN CONSTRUCTION
BARROULEAU, RICHARD A
7/1/2018 Update: Prep work for new coating has commenced. Recoating effort to start soon.
Design Firm: Contractor: External Contractor Name: Charters Bros.
2017‐0139
Memorial Union Building ‐ Strafford Room Chillers and AHUʹs
3‐ IN CONSTRUCTION
BARPOLITANO, FRANK
6/26/18_ Demo is complete, new unit is scheduled to arrive 7/15. Site work to begin on 6/26
Design Firm: SMRT Contractor: External Contractor Name: Careno
2018‐0143
Memorial Union Building ‐ Bookstore Flood Restoration and Repairs
3‐ IN CONSTRUCTION
BAR
Emergency Repair
POLITANO, FRANK
6/26/18_ Project is 90% complete, we are waiting on matching carpet for floor repairs. The
carpet is expected the first week of July.
Design Firm: Contractor: External Contractor Name: Charters
2018‐0229
Memorial Union Building ‐ Granite Square Station Mail Boxes
3.5‐ WARRANTY REPAIRS
FCRPOLITANO, FRANK
6/26/18_ Warranty issues, repairs scheduled to begin 6/26
Design Firm: Contractor: FCT Contractor Name:
2015‐2517
Morse Hall Projects in Building 5
Morse Hall ‐ HVAC Evaluation and Feasibility Study
1.1‐ PLAN/EST
RRPOLITANO, FRANK
6/26/18_ RFS is working on a proposal. I have also reached out to Jacobs to help with the lab
space portion of the study.
Design Firm: Contractor: Contractor Name:
2017‐0317
Monday, July 02, 2018 Page 12 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Morse Hall ‐ Fire Damper Repairs
2.5‐ IN PROCUREMENT
FCRHENRY, PAUL A
6‐26‐18 Issued PPʹs to Milestone, they are gearing up to start first building.
Design Firm: Contractor: External Contractor Name: Milestone
2018‐0326
Morse Hall ‐ Security Upgrades Including Card Readers and Video Cameras
3‐ IN CONSTRUCTION
FCRHOUDE, DONALD A
6‐25‐18 The contractor has a PO. Work has started.
Design Firm: Contractor: External Contractor Name: Yates, Burns
2018‐0322
Morse Hall ‐ Third Floor Tempid Water Loop
3.1‐ SUBSTANTIAL COMPLETION
RRBRICKETT, ALEXANDER J
6/27/2018_Final inspection scheduled for 6/28
Design Firm: Contractor: External Contractor Name: GSPH
2017‐0004
Morse Hall ‐ Rm 345 Renovations
3.1‐ SUBSTANTIAL COMPLETION
FCRHENRY, PAUL A
6‐26‐18 Contacted stakeholder, he would like to wait and expand the system. Working with
EHS on details of new control panel to be located in the corridor.
Design Firm: Harriman Contractor: External Contractor Name: TBD
2015‐2384
Murkland Hall Projects in Building 1
Murkland Hall ‐ Exterior Painting
3‐ IN CONSTRUCTION
RRBOIE, GREGG J
06/25/18, Work in Progress
Design Firm: Contractor: External Contractor Name: APC Services of New England
2018‐0305
Nesmith Hall Projects in Building 8
Nesmith Hall ‐ Exterior Brick Wall and Parapet Repointing
2.5‐ IN PROCUREMENT
RRPOLITANO, FRANK
12/28/17__ P/O is all set waiting on weather and schedule to be able to complete work
Design Firm: TBD Contractor: External Contractor Name: Meditation Gardens
2014‐1972
Monday, July 02, 2018 Page 13 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Nesmith Hall ‐ Upward Bound / Talent Search Relocation
2.5‐ IN PROCUREMENT
SIHECKLER, BARBARA K
6/29/2018: Project expected complete by late August.
Design Firm: Contractor: External Contractor Name: Careno
2018‐0202
Nesmith Hall ‐ Phone‐a‐thon Fit Out
2.5‐ IN PROCUREMENT
SIBRICKETT, ALEXANDER J
6/27/2018_Design completed. Work began 6/26
Design Firm: Harriman Contractor: External Contractor Name:
2018‐0166
Nesmith Hall ‐ Bathroom Improvements and ADA Accessibility Modifications
3‐ IN CONSTRUCTION
SIBRICKETT, ALEXANDER J
6/27/2018_See project 2015‐2341 for updates.
Design Firm: Cowan & Goudreau Contractor: External Contractor Name: Greenleaf Construction
2018‐0339
Nesmith Hall ‐ Room Improvements G00CRA, G17‐G22, G24‐G26 (including G25B)
3‐ IN CONSTRUCTION
SIHECKLER, BARBARA K
6/29/2018: Project expected complete by 9/13.
Design Firm: Contractor: External Contractor Name: milestone
2018‐0173
Nesmith Hall ‐ South Roof Replacement
3‐ IN CONSTRUCTION
RRPOLITANO, FRANK
6/26/18_ Viking is set to begin 2nd week of July.
This is for valley repair.
Design Firm: ARM Contractor: External Contractor Name: Viking
2010‐0433
Nesmith Hall ‐ Bathroom Renovations
3‐ IN CONSTRUCTION
RRBRICKETT, ALEXANDER J
6/27/2018_Construction in progress. Anticipated finish date 8/17.
Design Firm: Cowan & Goudreau Contractor: External Contractor Name: Greenleaf Construction
2015‐2341
Monday, July 02, 2018 Page 14 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Nesmith Hall ‐ Bathroom Renovations DESIGN ONLY
3‐ IN CONSTRUCTION
RRBRICKETT, ALEXANDER J
6/27/2018__See project 2015‐2341
Design Firm: Cowan & Goudreau Contractor: Contractor Name:
2018‐0096
New England Center Projects in Building 2
New England Center ‐ Adams Tower ‐ Separation of HHW and DHW Design Only
2‐ IN DESIGN
RRHENRY, PAUL A
6‐26‐18 Design is in final review, project split between Energy and Hosing construction summer
2019
Design Firm: Harriman Contractor: External Contractor Name: TBD
2016‐0402
New England Center ‐ Flood Damage Restoration and Repairs
3.1‐ SUBSTANTIAL COMPLETION
RR
Emergency Repair
HENRY, PAUL A
6‐26‐18 waiting for fin tube covers
Design Firm: Contractor: External Contractor Name: Milestione
2018‐0228
Northwest Heat Plant Projects in Building 1
Northwest Heat Plant ‐ New Construction
3‐ IN CONSTRUCTION
FCRPARSONS, STEPHANIE E
6/29/18: Construction ongoing, utlitiy piping being installed around the building locations.
Design Firm: Wilson Engineering Contractor: External Contractor Name: Froling Energy
2018‐0002
Old Dairy Barn Projects in Building 1
Old Dairy Barn ‐ Demolition
3.1‐ SUBSTANTIAL COMPLETION
RRRINES, DANIEL M
6‐26‐18: Loam and Seed complete, lawn growing. One small patch area at wall/ foundation
transition needs to be fixed. Milestone will adress.
Design Firm: Contractor: External Contractor Name: Milestone
2012‐1085
Outdoor Facility Projects in Building 2
Monday, July 02, 2018 Page 15 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Outdoor Facility ‐ New Soccer/Lacrosse Field
2.5‐ IN PROCUREMENT
FCRGEUTHER, MARK E
06‐25‐2018: Construction scheduled to start on or about August 1, 2018.
Design Firm: Tighe & Bond Contractor: External Contractor Name: R.A.D. Sports
2017‐0285
Mooradian Field ‐ Subsurface Improvements and Turf Replacement
3.1‐ SUBSTANTIAL COMPLETION
RRGEUTHER, MARK E
06‐25‐2018: Substantially complete. Waiting on As‐Builts
Design Firm: Tighe & Bond Contractor: FCT Contractor Name: RAD Sports
2017‐0149
Outdoor Pool Projects in Building 1
Outdoor Pool ‐ Reconstruction of Outdoor Pool Facility
3.1‐ SUBSTANTIAL COMPLETION
CPPARSONS, STEPHANIE E
6/21/18 Preparing for project closeout. Final items required for the project will be purchased
and this project closed out by August 2018.
Design Firm: water technologies Contractor: External Contractor Name: Shawmut
2014‐2059
Parsons Hall Projects in Building 4
Parsons Hall ‐ Rms N104, N108 Classroom Renovation Iddles Lecture Halls Design
Only
2‐ IN DESIGN
RRBRICKETT, ALEXANDER J
6/27/2018_ Harriman has begun design work on new lecture halls.
Design Firm: Harriman Contractor: External Contractor Name:
2018‐0145
Parsons Hall ‐ Processed Chilled Water System Replacement
2‐ IN DESIGN
RRBRICKETT, ALEXANDER J
6/27/2018_ Design work in progress.
Design Firm: Contractor: Contractor Name:
2018‐0048
Parsons Hall ‐ Rm S128 Ammonia Gas Control System
3.1‐ SUBSTANTIAL COMPLETION
FCRPARSONS, STEPHANIE E
6/21/18: Norris started installation for FA interface. Prior to testing with EHS / DFD will need to
review the limits and setpoint for alarm notification.
Design Firm: Norris Contractor: External Contractor Name: Norris
2017‐0431
Monday, July 02, 2018 Page 16 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Parsons Hall ‐ Rm S222 Minor Renovations
3.1‐ SUBSTANTIAL COMPLETION
FCRBRICKETT, ALEXANDER J
6/27/2018_Work completed. Punchlist items in progress.
Design Firm: Harriman Contractor: External Contractor Name: Yates & GSPH
2018‐0058
Paul College Projects in Building 1
Paul College ‐ HVAC and Control Modifications from Original Construction
3.1‐ SUBSTANTIAL COMPLETION
FCRPARSONS, STEPHANIE E
6/21/18. Further work may be required. No issues have been reported as of this update.
Design Firm: RFS Contractor: External Contractor Name: TBD
2016‐0295
Paul Creative Arts Center Projects in Building 3
Paul Creative Arts Center ‐ Bratton Recital Hall Improved Access
2‐ IN DESIGN
FCRRINES, DANIEL M
6‐26‐18: Received plans from T&B, reviewed by ADA and PM, notes sent back to Tighe and Bond
for final. Term contractor will be contacted to resubmitt pricing. Working in conjuncture with
the music dept to attempt completion this summer.
Design Firm: Tighe & Bond Contractor: External Contractor Name:
2017‐0318
Paul Creative Arts Center ‐ Stair Egress Modifications
3.1‐ SUBSTANTIAL COMPLETION
RRPOLITANO, FRANK
6/26/18 1st phase is complete, except for 1 door which has been delivered wrong, we are
waiting on a new ship date from factory.
Design Firm: Harriman Contractor: Contractor Name:
2017‐0232
Paul Creative Arts Center ‐ New Main Domestic Hot Water System Installation
3.5‐ WARRANTY REPAIRS
RRROULEAU, RICHARD A
7/1/2018 Update: Water heater installation completed. Domestic water booster pump design
received and may be implemented as part of this project or possibly as a separate follow‐on
project.
Design Firm: Harriman Associates Contractor: External Contractor Name: Charters Bros.
2018‐0249
Pettee Hall Projects in Building 2
Monday, July 02, 2018 Page 17 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Pettee Hall ‐ Rm G18 Mold Remediation and Investigation
3‐ IN CONSTRUCTION
RR
Emergency Repair
HECKLER, BARBARA K
6/29/2018: Project on track to be complete by 7/20.
Design Firm: Contractor: Contractor Name:
2018‐0251
Pettee Hall ‐ Slate Roof Repairs
3.1‐ SUBSTANTIAL COMPLETION
RR
Emergency Repair
ROULEAU, RICHARD A
7/1/2018 Update: Repairs completed pending review of drone verification photos.
Design Firm: Contractor: External Contractor Name: Skyline Roofing
2018‐0098
Philbrook Hall Projects in Building 4
Philbrook Hall ‐ Kitchen Modifications
2‐ IN DESIGN
FCRHENRY, PAUL A
6‐26‐18 Selected Charter Brothers as CMAR, will start Pre‐Construction Services to explor the
site this summer
Design Firm: Harriman Contractor: External Contractor Name: Charters Brothers
2017‐0399
Philbrook Hall ‐ Boiler Forensic Investigation
2.5‐ IN PROCUREMENT
RRPARSONS, STEPHANIE E
6/29/18: RFX for engineering / forensic analysis submitted to procurement for posting. Dye
testing complete, no issues identified in condensate tank / pit. Floor drain identified tie into
storm drain. Blake Engineering scheduling boiler tube test and analysis week of 7/2.
Design Firm: TBD Contractor: External Contractor Name: TBD
2018‐0162
Philbrook Hall ‐ Boiler Replacement
3‐ IN CONSTRUCTION
BARPARSONS, STEPHANIE E
6/21/18: Boiler is not being installed until 2018‐0162 forensic review is complete.
Design Firm: Harriman Contractor: External Contractor Name: Eckhardt Johnson
2018‐0149
Philbrook Hall ‐ Refrigeration Rack System
3‐ IN CONSTRUCTION
FCRHENRY, PAUL A
6‐26‐18 in construction, CB making great progress
Design Firm: Harriman Assoc. Contractor: External Contractor Name: Charter Brothers
2015‐2492
Presidents House Projects in Building 1
Monday, July 02, 2018 Page 18 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Presidents House ‐ Major Site Repairs President Transition
3‐ IN CONSTRUCTION
RRRINES, DANIEL M
6‐26‐18: Driveway Binder course installed, replaced clay subbase with suitbale material and Geo
fabric. Exterior work is substantially complete, awaiting punch list for mason.
Wearing course will be installed after move in.
Design Firm: Contractor: External Contractor Name: Bell and Flynn/ Chapman
2013‐1274
Presidentʹs House Projects in Building 1
Presidentʹs House ‐ Building Exterior and Interior Painting and Repairs
3‐ IN CONSTRUCTION
RRBRICKETT, ALEXANDER J
6/27/18_Interior and exterior work in progress.
Design Firm: Contractor: Contractor Name:
2013‐1032
Roads/Grounds Projects in Building 11
FY19 Road Repairs and Crack Sealing
1.1‐ PLAN/EST
RRHENRY, PAUL A
6‐26‐18 No scope this summer
Design Firm: Contractor: External Contractor Name: TBD
2017‐0024
Memorial Union Building ‐ Driveway and Sidewalk ‐ Design Only
2‐ IN DESIGN
SIRINES, DANIEL M
6‐26‐18: Hoyle Tanner working to complete 90% drawings. Schedule was set by PM and agreed
to by HT. 90% will be submitted to UNH the end of August for review, Final Plans by the end of
September, so project can be put out to bid this fall/winter.
Design Firm: Hoyle Tanner Contractor: Contractor Name:
2009‐0078
Campus ‐ Huddleston Fairchild Hetzel Site Stairs Design
2‐ IN DESIGN
RRGEUTHER, MARK E
06‐25‐2018: Several field visits have been made by the engineer collecting existing conditions
data.
Design Firm: Hoyle‐Tanner Contractor: External Contractor Name: TBD
2018‐0294
Monday, July 02, 2018 Page 19 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
South Drive ‐ Design Advancement
2‐ IN DESIGN
SIHENRY, PAUL A
6‐26‐18 T&B recently estimated project at DD, up dated estimate
Design Firm: Tighe & Bond Contractor: External Contractor Name:
2013‐1115
Campus ‐ Main Street South Sidewalk
2‐ IN DESIGN
SIRINES, DANIEL M
6‐26‐18: Contract with CMA finalized, Project kickoff meeting was held 6‐25‐18. Local concerns
meeting 7‐11‐18, survey work almost complete.
Design Firm: CMA Engineering Contractor: Contractor Name:
2017‐0384
Campus ‐ South Drive ‐ Temporary Connection to Colovos Road
2.5‐ IN PROCUREMENT
SIGEUTHER, MARK E
06‐25‐2018‐On hold pending funding
Design Firm: Tighe & Bond Contractor: External Contractor Name: R.A.D. Sports
2018‐0267
FY19 Sidewalk and Walkway Repairs
3‐ IN CONSTRUCTION
RRHENRY, PAUL A
6‐26‐18 work under way with T&S and JTI
Design Firm: Contractor: External Contractor Name: T&S / JTI
2017‐0027
FY19 Site Stair Repairs
3‐ IN CONSTRUCTION
RRHENRY, PAUL A
6‐26‐18 Ed Kimball working on repairs
Design Firm: Contractor: External Contractor Name: TBD
2017‐0026
Campus Wayfinding ‐ Phase 2
3‐ IN CONSTRUCTION
SIRINES, DANIEL M
6‐26‐18: Final walkthrough with barlo completed.
Signs in production.
Phase one punch list complete, pending SP and DR walk through this week.
Design Firm: Contractor: External Contractor Name: Barlo Signs
2016‐0157
Monday, July 02, 2018 Page 20 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Wildcat Stadium Parking Lot ‐Pay & Display Meter Installation & Pad
3.1‐ SUBSTANTIAL COMPLETION
FCRHOUDE, DONALD A
6‐25‐18 The project is 90% complete waiting for Bollard covers. Contractor says they are going in
this week.
Design Firm: Contractor: External Contractor Name: T&S const
2018‐0150
Campus ‐ Wayfinding ‐ Phase 1
3.1‐ SUBSTANTIAL COMPLETION
SIKING, KATHLEEN M
4/27/18: Change order issued for punch list completion, to be completed in early summer.
Design Firm: Roll Barresi & Associates Contractor: FCT Contractor Name: Barlo Signs International
2017‐0211
Rudman Hall Projects in Building 15
Rudman Hall ‐ Conversion to DDC Controls
1.1‐ PLAN/EST
RRPARSONS, STEPHANIE E
6/21/18 ‐see ID 2010‐0479 for updates.
Design Firm: Contractor: External Contractor Name: TBD
2015‐2336
Rudman Hall ‐ Level G Instruction Lab Support Expansion
1.1‐ PLAN/EST
SIPARSONS, STEPHANIE E
6/29/18: Meeting scheduled 7/2 with stakeholders and campus planning to assist in space
reallocation for Instructional support to occupy loading dock.
Design Firm: TBD Contractor: External Contractor Name: TBD
2017‐0418
Rudman Hall ‐ Laboratory Fume Hood Control System Replacement
1.1‐ PLAN/EST
RRPARSONS, STEPHANIE E
6/21/18 ‐ Meeting with SMRT scheduled 7/2/18 to prepare for make ready work for AHU
isolation is being scheduled for December 2018 with new HVAC control improvements to begin
summer 2019.
Design Firm: SMRT, Inc. Contractor: External Contractor Name: TBD
2010‐0479
Rudman Hall ‐ Fire Alarm Replacement DESIGN
1.1‐ PLAN/EST
RRPARSONS, STEPHANIE E
6/21/18 ‐ Design review ongoing, installation of fire alarm is scheduled for Summer 2019.
Design Firm: SFC Engineering Contractor: External Contractor Name: TBD
2013‐1149
Monday, July 02, 2018 Page 21 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Rudman Hall ‐ Fire Alarm Replacement
1.1‐ PLAN/EST
RRPARSONS, STEPHANIE E
6/21/18 ‐ Please see ID 2010‐0479 for updates.
Design Firm: SFC Contractor: External Contractor Name: TBD
2015‐2352
Rudman Hall ‐ DDC Controls Backstop
1.1‐ PLAN/EST
RRPARSONS, STEPHANIE E
6/21/18 ‐ see ID 2010‐0479 for updates
Design Firm: Contractor: Contractor Name:
2017‐0288
Rudman Hall ‐ Vivarium Upgrades Phase 2 DESIGN ONLY
2‐ IN DESIGN
SIPOLITANO, FRANK
6/26/18_ Design in process final drawings due by 7/15
Design Firm: Harriman Contractor: Contractor Name:
2017‐0214
Rudman Hall ‐ ARO Autoclave Replacement
2.5‐ IN PROCUREMENT
RRBRICKETT, ALEXANDER J
6/27/2018_Design documentation received.Obtaining quotes for work from contractors.
Design Firm: Contractor: Contractor Name:
2016‐0148
Rudman Hall ‐ Rm 148 Replacement Environmental Room Humidifier
2.5‐ IN PROCUREMENT
RRBOIE, GREGG J
06/25/18, Contacted Chet Holt . Humidifier is on order and will call me when it arrives.
Design Firm: Contractor: External Contractor Name: Harris Environmental Systems Inc.
2018‐0354
Rudman Hall ‐ Steam Domestic Hot Water Exchanger
3‐ IN CONSTRUCTION
RRPOLITANO, FRANK
6/26/18_ New unit is installed, start‐up expected on 6/27
Design Firm: Contractor: External Contractor Name: GSP
2017‐0366
Monday, July 02, 2018 Page 22 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Rudman Hall ‐ Water Booster Pump Replacement
3‐ IN CONSTRUCTION
RRPOLITANO, FRANK
6/26/18_ GSP will do this work, we are looking for a Saturday for install.
Design Firm: Contractor: External Contractor Name: GSP
2017‐0367
Rudman Hall ‐ G Level Flood Restoration and Repair
3.1‐ SUBSTANTIAL COMPLETION
RR
Emergency Repair
BRICKETT, ALEXANDER J
6/27/2018_All affected areas have been repaired. Equipment replacement in progress.
Design Firm: Contractor: Contractor Name:
2018‐0230
Rudman Hall ‐ Dishwasher Fire/ Sprinkler Flood Restoration
3.1‐ SUBSTANTIAL COMPLETION
RR
Emergency Repair
KING, KATHLEEN M
4/27/18: Restoration is complete, project is also labeling fire sprinkler valves and considering
modifying ventilation of space behind washer.
Design Firm: Contractor: Contractor Name:
2018‐0252
Rudman Hall ‐ Steam Back Pressure Turbine
3.1‐ SUBSTANTIAL COMPLETION
FCRPARSONS, STEPHANIE E
6/29/18: Controls integration with Cogen Plant complete. Still working with UNH IT /
networking for troubleshooting access to the web interface.
Design Firm: Waldron Engineering Contractor: External Contractor Name: Ewing Controls / TVC
2016‐0162
Rudman Hall ‐ Rm G51 Flood Restoration
3.1‐ SUBSTANTIAL COMPLETION
RR
Emergency Repair
BRICKETT, ALEXANDER J
6/27/2018_ Ceiling tiles completed. Old refrigerator to be removed when contents are moved.
Design Firm: Contractor: FCT Contractor Name: Sprague
2017‐0293
Service Building Projects in Building 3
Service Building ‐ Dispatch Center Keltron System
3‐ IN CONSTRUCTION
FCRPARSONS, STEPHANIE E
6/29/18: Gregg Hall ʹnodeʹ is complete. Team will begin working on Stoke ʹnodeʹ with
anticipation of completion August 2018.
Design Firm: Contractor: External Contractor Name: Norris / UNH Telecom
2016‐0123
Monday, July 02, 2018 Page 23 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Service Building ‐ Replacement and Installation of Isolation valves
3‐ IN CONSTRUCTION
RRPARSONS, STEPHANIE E
6/21/18 ‐ Please see project ID 2009‐0064 for updates and budget.
Design Firm: N/A Contractor: External Contractor Name: TBD
2013‐1465
Service Building ‐ Fire Alarm Replacement and Building System Upgrades
3‐ IN CONSTRUCTION
RRPARSONS, STEPHANIE E
6/29/18 Heating line replacement and isolation valve installation is ongoing. Fire alarm is
substantially complete, working with Norris / Scarponi on minor punchlist items prior to
scheduling SFMO walk. Scheduling for 7/19/18 agenda walk through.
Design Firm: Harriman Contractor: External Contractor Name: Charters Brothers
2009‐0064
Spaulding Hall Projects in Building 1
Spaulding Hall ‐ Expansion & Renovations ‐ Biological Science Initiative
2‐ IN DESIGN
CPROULEAU, RICHARD A
7/1/2018 Update: CM has been selected. Contract to be circulated soon for signatures.
Preconstruction services to commence thereafter.
Design Firm: Ellenzweig Contractor: External Contractor Name: Skanska USA Building
2016‐0278
Stillings Hall Projects in Building 1
Dining Buildings ‐ Add Digital Menu Boards To Dining and Retail Outlets
3‐ IN CONSTRUCTION
FCRHOUDE, DONALD A
6‐25‐18 The contractor has the PO. We are schedueling a start date and a plan.
Design Firm: Contractor: External Contractor Name: Yates
2018‐0333
Stoke Hall Projects in Building 3
Stoke Hall ‐ Registrarʹs Office Minor Renovation
2‐ IN DESIGN
SIHECKLER, BARBARA K
6/29/2018: Will meet with RO in July.
Design Firm: Contractor: Contractor Name:
2018‐0175
Monday, July 02, 2018 Page 24 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Stoke Hall ‐ Business Service Center Exterior Wall Repairs
3‐ IN CONSTRUCTION
RRBRICKETT, ALEXANDER J
6/27/2018_ Construction in progress.
Design Firm: Contractor: Contractor Name:
2018‐0213
Stoke Hall ‐ Elevator upgrade
3‐ IN CONSTRUCTION
FCRROULEAU, RICHARD A
7/1/2018: Work is in progress, going well and to be complete prior to the fall semester.
Design Firm: Elevator Consulting Assoc. Contractor: External Contractor Name: Careno Construction
2018‐0117
Taylor Hall Projects in Building 1
Taylor Hall ‐ Rm 102 Create Wall and Door Accesss
2.5‐ IN PROCUREMENT
FCRHECKLER, BARBARA K
6/29/2018: Funding available 7/1. Start date dependent on Milestoneʹs summer schedule; work
may need to wait until September.
Design Firm: Contractor: External Contractor Name: Milestone
2018‐0148
Thompson Hall Projects in Building 1
Thompson Hall ‐ Card Access and Security Camera Cable Pathways
3.1‐ SUBSTANTIAL COMPLETION
FCRHOUDE, DONALD A
6‐25‐18 This project is for the most part complete. The dept has some issues to work oout with
providing an administrator. We are doing punch list.
Design Firm: Contractor: External Contractor Name: Yates
2018‐0246
Utility Distribution Projects in Building 11
Utility Distribution ‐ Library Way Tunnel Design
1.1‐ PLAN/EST
RRKING, KATHLEEN M
4/27/18: PM is waiting on final direction from asset management and utilities
Design Firm: Contractor: Contractor Name:
2017‐0005
Monday, July 02, 2018 Page 25 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Utility Distribution ‐ College Brook Culvert Repair
2‐ IN DESIGN
RRHENRY, PAUL A
6‐26‐18 Exposted site, have to remove electrical duct bank to do work, working with Energy to
incluce some High Voltage work to take atvanatve of moving the switches above ground,
meeting next week.
Design Firm: Tighe & Bond Contractor: External Contractor Name: TBD
2018‐0100
UNH Utility Master Plan
2‐ IN DESIGN
SIKING, KATHLEEN M
4/27/18: Final comments returned to consultants and final report due May 11, followed by
presentations by consultants.
Design Firm: RMF Contractor: Contractor Name:
2017‐0169
Utility Distribution ‐ HHW Line Replacement Service Building to Zais Hall
2‐ IN DESIGN
RRRINES, DANIEL M
6‐26‐28: Met with DFD and EMS: will need to maintain one way access utilizing keyed in steel
plates.
RH White and Charter Bros pricing job.
Design Firm: Contractor: Contractor Name:
2017‐0354
Utility Distribution ‐ Edgewood Water Tank ‐ Decomissio
2.5‐ IN PROCUREMENT
FCRBRICKETT, ALEXANDER J
6/27/2018_PO for demolition issued to Charter Bros. Work to occur 8/1/18.
Design Firm: Contractor: External Contractor Name: Charter Brothers
2010‐0729
Utility Distribution ‐ Reconfigure and Relocation of Colovos SSL0109 and SSL0486
2.5‐ IN PROCUREMENT
RRGEUTHER, MARK E
06‐25‐2018: Temporary road approved by DFD and UNHPD. Temp road scheduled for
construction the end of the week of July 9. Manhole replacement the week of July 16.
Design Firm: Tighe & Bond Contractor: External Contractor Name: T&S Construction
2018‐0183
Utility Distribution ‐ Main Street Tunnel Corrective Repair and Design
3‐ IN CONSTRUCTION
RRRINES, DANIEL M
6‐26‐18: RH White is substantially complete. Waiting on punchlist items to be completed,
including RH White approval of plan for steam shut down to fix the SS Brackets inside the
tunnel.
Design Firm: Simpson Gumpertz & Heger Contractor: External Contractor Name: R.H. White Construction
2018‐0155
Monday, July 02, 2018 Page 26 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Utility Distribution ‐ HV ‐ Circuit 11 Hamilton Smith to Memorial Union Phase II
3‐ IN CONSTRUCTION
SIHOUDE, DONALD A
6‐25‐18 The contractor has a PO. Work is in Progress, I have extended the scope of work to also
install the HV cable between the new HV switch and the H/S Sector cabinet.
Design Firm: Contractor: External Contractor Name:
2018‐0067
Utility Distribution ‐ Horton to PCAC HHW Line Replacements and Pit Repairs
3‐ IN CONSTRUCTION
RRROULEAU, RICHARD A
7/1/2018 Update: Construction is ongoing. All piping between Horton and PCAC pits and all
service piping into Horton and PCAC has been installed, xrayed and hydrostatically and tested.
Trench covers have been reinstalled between Horton and PCAC pits and backfilling is in
progress at the Horton and PCAC service entrance piping. Re‐establishment of landscaping and
hardscaping between Horton and PCAC pits underway. Intent is to have Ramoneʹs open for
business on or before July 8. Piping inside pits has commenced. Phase 2 trench work from
PCAC toward Spaulding has commenced. Unforeseen/hidden conditions are being addressed as
they come to light.
Design Firm: Harriman Associates Contractor: External Contractor Name: Charters Bros.
2017‐0094
Utility Distribution ‐ HHW and Sewer Line Replacement College Road to Kendall and
Nesmith
3‐ IN CONSTRUCTION
RRGEUTHER, MARK E
06‐25‐2018: Work continues. Progress is slow due to numerous unforeseen conditions.
Contractor has hired additional resources.
Design Firm: Harriman/Tighe & Bond Contractor: External Contractor Name: Waterline Industries
2017‐0093
Utility Distribution ‐ Gables Distribution Line Replacements
3.1‐ SUBSTANTIAL COMPLETION
RRKING, KATHLEEN M
4/27/18: Project is substantially complete, waiting on final invoicing.
Design Firm: Harriman Contractor: External Contractor Name: RH White
2017‐0348
Veterinary Diagnostic Lab Projects in Building 1
NHVDL ‐ Relocation
3‐ IN CONSTRUCTION
SIPARSONS, STEPHANIE E
6/21/18: Final details being completed; whiteboard in necropsy, hose reel in necropsy, outlet on
standby power vs normal power. Additional smoke detection will be installed in lab area at
customer request.
Design Firm: Contractor: External Contractor Name: Careno Construction / Norris
2013‐1537
Water Treatment Plant Projects in Building 1
Monday, July 02, 2018 Page 27 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Water Treatment Plant ‐ New Construction
3‐ IN CONSTRUCTION
SIGEUTHER, MARK E
06‐25‐2018: Concrete tank work ongoing. Site work on going. Mock up wall approved
Design Firm: Woodard & Curran Contractor: External Contractor Name: Waterline Industries
2008‐0038
Whittemore Center ‐ Arena Projects in Building 4
Whittemore Center ‐ Arena ‐ Ice System Engineering Evaluation
1.1‐ PLAN/EST
RRBRICKETT, ALEXANDER J
6/27/2018_Meeting on 3/2 indicated that ice system needs replacement. Initial design phase in
progress.
Design Firm: Stevens Engineering Contractor: Contractor Name:
2018‐0235
Whittemore Center ‐ Arena ‐ Engineering Evaluation for Exterior Concrete and Interior
Mechanical Room Slab
3‐ IN CONSTRUCTION
RRRINES, DANIEL M
6‐26‐18: SGH set crack monitors in NW Wall, and preformed survey and analysis of interior
mechanical slab on 6‐25‐18. Data will be analyzed, and futher monitoring visits will be planned.
Design Firm: SGH Contractor: Contractor Name:
2017‐0394
Whittemore Center ‐ Arena ‐ Fire Alarm System Replacement
3‐ IN CONSTRUCTION
FCRPARSONS, STEPHANIE E
6/29/18: Final modifications to glass tower with DFD coordination nearing completion.
Modifications include, removing speaker / strobe (nusence) remove manual smoke evacuation
interface, provide permanent source of heat to the room, provide 6ʹ x 2ʹ table for material storage
and site command use.
Design Firm: SFC Engineering Contractor: External Contractor Name: Careno Construction
2015‐2400
Whittemore Center ‐ Arena ‐ Concessions Stand Electrical Work
3‐ IN CONSTRUCTION
FCRBRICKETT, ALEXANDER J
6/27/2018_Yates has finished electrical work. Telecom work in progress.
Design Firm: Contractor: External Contractor Name: Yates
2018‐0157
Woodside ABC Projects in Building 1
Monday, July 02, 2018 Page 28 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Woodsides Complex ‐ Boiler Replacements and Modifications
3‐ IN CONSTRUCTION
FCRPOLITANO, FRANK
6/26/18_ New boilers are in place, piping has begun in PQR, this unit is 90% complete. 2 other
buildings are expected to be ready for electrical by 6/29.
Design Firm: SMRT Contractor: External Contractor Name: Careno
2017‐0408
Zais Hall Projects in Building 1
Zais Hall ‐ Room 205 Carpet/Flooring Replacement
1.1‐ PLAN/EST
RRHECKLER, BARBARA K
6/29/2018: Will address week of 7/3.
Design Firm: Contractor: Contractor Name:
2018‐0359
Monday, July 02, 2018 Page 29 of 29University of New Hampshire
Brenda Whitmore, Director Facilities Project Management