Council for the Built Environment technical subcommittee
1001 General Services Complex 1369TAMU College Station, TX 77843-1369 Tel. 979.845.8661 http://fcor.tamu.edu/
March 1, 2010 MEMORANDUM To: Dr. Douglas Palmer Chair, Council for the Built Environment Subject: Proposed Major Renovation of Olsen Field RECOMMENDATION
The Council for the Built Environment’s (CBE) technical sub committee (CBE-tsc) provides the following as a report to support the discussion and final recommendation(s) of the CBE regarding the proposed Major Renovation of Olsen Field.
SCOPE
At your direction, the CBE-tsc met this morning to consider the request of the Athletic Department to initiate a project which includes a major renovation of Olsen Field. As described in the attached, February 18, 2010 letter to you from Kevin Hurley, the estimated $16 million project will address most of the fire/life safety and ADA issues identified in the 2005 Life Safety Assessment. The construction will also upgrade the façade of the building; improve seating options (although the seating capacity will be decreased), include a new baseball operations area, provide larger concourses, construct a weight room and larger locker facilities.
CONSTRUCTION TIMING
The renovation is projected to start in early 2011 and last approximately 18 months. The schedule will likely cause some inconvenience to the fans, but the construction will not displace the ability of the team to play baseball in Olsen Field.
ANALYSIS
Facilities The entire Olsen Field facility is assigned to and managed by the Athletic Department. Physical Plant The project management for this project will be provided by the Facilities Planning & Construction office of the Texas A&M University System. The Physical Plant Department will provide support to their efforts as needed.
Security and Safety Environmental Health & Safety is supportive of this project’s addressing the fire/life safety items identified in the 2005 Life Safety Assessment.
Proposed Major Renovation of Olsen Field CBE-tsc Report March 1, 2010 Page 2
Telecommunications and Computing & Information Services All related services will be upgraded as needed during the design and construction of this project.
Project Funding
The funding source for the project will be donor funds. Athletics has asserted that they have sufficient funds as required by the TAMUS rules to proceed with the selection of an Architect to begin the design of the renovation. Finance reports that the 12th Man Foundation confirmed pledges of $12.2M and cash on hand of $5.7M with an additional $2M expected by fiscal year end. The Division of Finance will work with Athletics to develop a pro forma financial statement to support this project prior to the May BOR meeting.
Purchasing
All university rules related to the procurement of services or other materials related to the proposed uses of this facility will be adhered to.
Parking and Campus Access
Transportation Services is in the process of renovating the parking areas adjacent to Olsen Field. The department requests that Athletics work closely with them to coordinate lay-down areas, acceptable parking for contractors, and develop a traffic plan for trucks to avoid damaging recently renovated parking lots.
We are pleased to offer this report for this project and welcome further inquiries related to this analysis. Sincerely, James Massey Chairman, CBE-technical sub committee Director Office of Facilities Coordination Attachments CC: CBE-tsc members
Project Information Requirements for Capital Planning System Member
Name of Project
Description of Project
New Construction/Addition Acquisition Renovation/Rehabilitation Project x
Space RequirementsOffices: 1,900 NASF Justification for space need:Classrooms: ‐ NASFLabs: Wet (Undergraduate) ‐ NASF
Dry ‐ NASFR&D ‐ NASF
Other: (describe below) 36,000 NASF
Total Net Assignable Square Footage: 37,900 NASFTotal E&G Square Footage: ‐ NASFTotal Gross Square Footage: 37,900 GSF
Infrastructure Impacts and Project Site
Parking required? y (Y/N) Utility relocation required? n (Y/N)Number of parking spaces needed tbd Description of utility relocation requirementsDescription of parking requirements
Utility plant expansion required? n (Y/N) Data/Telecom required? y (Y/N)Additional tons of CW/HW needed Description of data/telecom requirementsDescription of utility plant expansion requirements
Other requirements? n (Y/N) Project Site Identified? y (Y/N)Description of other requirements If yes, provide project site information.
Project Planning and Funding
Project Planning amount: FY in which project design will be initiated: 2010
Revenue Financing System (RFS) Debt Source of funds for RFS debt service (if applicable):Permanent University Fund (PUF) DebtCash Gift FundsTotal
Will any services in the facility be contracted with a third party (dining, bookstore, advertising)? y (Y/N)If yes, provide a copy of contract to Treasury Services and estimated NSF for third party operations. NASF1,200
Olsen Field Renovation
The proposed project will address fire/life safety/ADA issues that were brought up in the Life Safety Assessment of 2005. New wider chair back seating will replace the metal seating in the lower level. Field level seats will move the fan closer to the field and provide new dugouts for the teams. The renovation will create wider concourses, larger and additional restrooms and concession stands. The creation of a new baseball operations area will provide much needed offices, weight room, training room and locker room.
The facility can be brought up to code in fire/life safety/ADA. Olsen Field is the only facility in the Big 12 Conference that has not had a renovation to its seating bowl since the inception of the conference. This renovation will allow our team to compete for the best recruits in the country. This will allow our fans to participate in a high quality event with no limitations.
16,000,000$
bathrooms, concession stands, locker room, weight room
Parking will be used during construction for a lay down area but no parking will be permantly lost due to this project.
It is projected the utilities that enter the site will be adequate but analysis will need to be performed to confirm.
16,000,000$
Texas A&M University
At this time sufficent capacity is projected.Additional phones and data will be required for this project in the locker rooms, concessions stands and media areas.
16,000,000$
‐$ ‐$ ‐$
Inside the current footprint (fence line) of Olsen Field
TAMU College Station Project Concept Initiation Form For renovations in excess of $2M, new construction in excess of $1M, change in footprint, or capital projects
I. GENERAL PROJECT INFORMATION
A) Project name: Olsen Field Renovation
B) Type of project: 1) New building 2) Renovation 3) Expansion 4) Deferred Maintenance 5) Other Capital Improvement C) TAMUS System part: 02
D) Department name: Athletics II. PROJECT DESCRIPTION, JUSTIFICATION AND SCOPE
A. Description The proposed project will correct fire/life safety/ADA issues that were brought up in the Life Safety Assessment of
2005. New wider chair back seating will replace the metal seating in the lower level. Field level seats will move the fan closer to the field and provide new dugouts for the teams. The renovation will create wider concourses, large and additional restrooms and concession stands. The creation of a new baseball operations area will provide much needed new offices, weight room, a larger training room and larger locker room.
B. Justification The facility can be brought up to code in fire/life safety/ADA. Olsen Field is the only facility in the Big 12 that has
not had a renovation to its seating bowl since the inception of the Big 12 Conference. This will allow our team to compete for the best recruits in the country. This will allow our fans to participate in a high quality event with no limitations.
C. Scope 1. Total estimated gross square feet 37,900 2. Total estimated cost 16, 000,000 3. Will this project include education and general (E&G) space? No
III. CAPITAL PLANNING A. Is the project compatible with the strategic plan of the requesting division or agency? Yes B. Is this project on a TAMUS capital plan? No C. Source of funds gifts to the 12th Man Foundation via account 02-300090 D. Fiscal year during which the project will be initiated: 2010
IV. LOCATION OF REQUESTED BUILDING SITE : Current Olsen Field location on West Campus (corner of Olsen Drive and George Bush Drive) Initiator's name: Kevin Hurley
Phone number: 979-862-2575 The project described above is endorsed by this division or agency of the Texas A&M University System, and is offered
for consideration as an agenda item of the Campus Facilities Planning Committee: Vice President/Agency Director:
Please submit this signed form to the Vice President for Administration, MS 1247, room 218 Williams Administration Building
Olsen Field Renovation Phasing Plan
Executive Summary
Phase 1 Baseball Operations Building
This phase will include a new locker room, weight room, coach’s offices, study lounge, training room and players lounge. The building will be attached to the new concourse and be located next to the current batting cages but not attached. This building will remain inside the footprint of the Olsen Complex as it is today. With the relocation of the locker room, new dugouts will be constructed which will then allow for additional field seating between the new dugouts behind home plate.
Phase 2 New Lower Concourse
This phase will renovate the lower concourse by enlarging the concourse, adding more restrooms and concessions stands. The lower seating bowl will be renovated to include new seats, sounds system, elevator and bring the press box functions down to this level.
Phase 3 New Front Entry Plaza
This phase will create a new entry where the fan enters the Olsen Field Complex and walks up some stairs to arrive on the concourse behind home plate. This will dress the stadium up and will relocate the ticket windows. This phase will include a new roof and new net behind home plate.
Phase 4 New Right Field Seating Berm
This phase will see the elimination of the right field bleachers. A new grass seating berm will be set in its place. With this phase the ground maintence shop will be relocated to behind the center field wall. An enclosed play area, restroom, concession stands and a Fieldturf practice infield will be components of this phase.
Phase 5 New Left Field Seating Berm
This phase will place a grass seating berm between the current home bull pen and the current cement seating of the lower level on the left field side of Olsen Field.
1. NEW ENTRY PAVILLION
Foundation/slab 3,000 sf 55.00 165,000
Steel structure, 20#/sf/level 75 ton 4,500.00 337,500
Roof area with flashing and deck 3,000 sf 19.50 58,500
Exterior skin, precast 6,500 sf 42.00 273,000Interior skin, precast 1,300 sf 42.00 54,600Interior skin, plaster 5,200 sf 11.50 59,800Interior ceiling 3,000 sf 15.00 45,000Glass area, priced curtain wall 1,600 sf 65.00 104,000Backing for skin, stud 13,000 sf 10.00 130,000Allow for lighting/electrical 6,000 sf 20.00 120,000Roof drainage 3,000 sf 7.50 22,500
Subtotal 1,369,900
2. Ticket window façade improvements 35,000
3 Player entry with storefron 384 sf 150.00 57,600
4. Replace roof with structured standing seam
Roof surface repalcement standing seam 9,600 sf 15.00 144,000Structural support for standing seam 9,600 sf 7.50 72,000
Subtotal 216,000
5. Plaster and cast stone panels 4,368 sf 108.56 474,190
6. Clean and paint stadium exterior 14,500 sf 3.00 43,500
7. Added glass and spandrel glass 2,750 sf 61.07 167,929
8. Entry plazaallowance for additional specalty paving 12 sf 2,000.00 24,000
Subtotal All Line Items 2,388,119Contractor/CMr mark-up - 18% 358,218Contingency - 15% 411,950Total Additional Cost 3,158,287
March 6, 2009Turner & Townsend
Olsen Field Entry Modifications Estimate of Cost
Item/Description Quantity Rate $ Total $
Scope A - Baseball Operations/Expanded Concourse
Baseball Operations
Head Coach Office 256 225.00 57,600
Assistant Coach 1 115 211.50 24,323
Assistant Coach 2 115 211.50 24,323
Assistant Coach 3 115 211.50 24,323
Operations Director Office 115 211.50 24,323
Grad Assistant Office 81 202.50 16,403
Break Area 63 207.00 13,041
Front Desk / Reception 325 234.00 76,050
Coach's Locker Room 222 294.50 65,379
Coach's Shower/Toilet 222 318.25 70,652
Janitor Storage Closet 49 202.50 9,923
Conference Room 260 265.50 69,030
Baseball Operations Storage 49 202.50 9,923
Texas AM Camp Storage 200 202.50 40,500
Data/Electrical Room 50 202.50 10,125
Baseball Operations Net Area 2,237 239.57 535,914
20% Grossing Factor 559 220.50 123,315
Baseball Operations Gross Area 2,796 235.75 659,229
Texas AM Club House
Home Locker Area 1,824 294.50 537,168
Shower/Toilet Room 609 318.25 193,814
Team Meeting/Multipurpose 600 232.75 139,650
Training Room 400 261.25 104,500
Hydrotherapy Area 204 585.00 119,340
Rehabilitation Area 204 385.00 78,540
Trainer's Office 100 211.50 21,150
Trainers' Locker - Women 200 294.50 58,900
Trainer's Locker - Men 200 294.50 58,900
Weight Training Room 2,000 234.00 468,000
Weight Room Office 100 211.50 21,150
Storage 204 202.50 41,310
Date of Estimate: October 30, 2008 - Revised March 18, 2009
Texas A&M University
College Station, Texas
OLSEN FIELD RENOVATION
Preliminary/Program Design Estimate
Prepared by Busby & Associates, Inc., Houston, TX Page 1 of 6
Item/Description Quantity Rate $ Total $
Date of Estimate: October 30, 2008 - Revised March 18, 2009
Texas A&M University
College Station, Texas
OLSEN FIELD RENOVATION
Preliminary/Program Design Estimate
Equipment Storage / Distribution 600 223.25 133,950
Laundry 204 435.00 88,740
Data/Electrical/AV Closet 80 202.50 16,200
Texas AM Club House Net Area 7,529 276.44 2,081,312
20% Grossing Factor 1,882 220.50 415,036
Texas AM Club House Gross Area 9,411 265.25 2,496,348
Visitor Club House
Visitor Locker Area 704 294.50 207,328
Shower/Toilet Room 650 318.25 206,863
Training Room 400 247.50 99,000
Storage 200 202.50 40,500
Data/Electrical/AV Closet 80 202.50 16,200
Visitor Club House Net Area 2,034 280.18 569,891
20% Grossing Factor 509 220.50 112,124
Visitor Club House Gross Area 2,543 268.25 682,015
Fan Amenities
Concession Stands 150sf each (based on 7,000 seats) 2,700 211.50 571,050
1 point of sale per 250 fans, with 10 being temp.
Men's Restroom - Public (see attached) 2,320 318.25 738,340
Women's Restroom - Public (see attached) 4,000 318.25 1,273,000
Family Toilet Room 80 318.25 25,460
Novelty 1,200 211.50 253,800
Security Office 150 220.50 33,075
First Aid 150 247.50 37,125
Janitor/Storage Closet 50 225.00 11,250
Janitor/Storage Closet No. 2 50 202.50 10,125
Fan Amenities Net Area 10,700 276.00 2,953,225
20% Grossing Factor 2,675 220.50 589,838
Fan Amenities Gross Area 13,375 264.90 3,543,063
Stadium Operations
Concession Storage 420 202.50 85,094
Concession Kitchen 954 360.00 343,289
Prepared by Busby & Associates, Inc., Houston, TX Page 2 of 6
Item/Description Quantity Rate $ Total $
Date of Estimate: October 30, 2008 - Revised March 18, 2009
Texas A&M University
College Station, Texas
OLSEN FIELD RENOVATION
Preliminary/Program Design Estimate
Concession Manager's Office 158 211.50 33,343
Ticket Sales / Office 230 229.50 52,754
Mechanical/Electrical/Fire/Telecom 739 202.50 149,709
Umpires Locker/Shower/Toilet 543 318.25 172,859
Storage/Counting 200 202.50 40,500
Stadium Operations Net Area 3,244 270.53 877,549
20% Grossing Factor 811 220.50 178,813
Stadium Operations Gross Area 4,055 260.53 1,056,362
Press / Media Facilities
Press Facilities Upper Level 432 211.50 91,270
Press Facilities Concourse Level 403 211.50 85,334
Press / Media Net Area 835 211.50 176,604
20% Grossing Factor 209 220.50 46,030
Press / Media Gross Area 1,044 213.30 222,634
Concourse and Sitework
Demolish concourse 10,267 5.00 51,335
Concourse, new/rebuilt 10,256 65.00 666,615
Entry structure roof area 0 75.00 0
Walk/plaza type paving, complete 27,762 7.50 208,213
Landscaping & irrigation, allowance 22,410 5.50 123,253
Subtotal Concoures and Sitework 1,049,415
20% Grossing Factor n/a n/a n/a
Total Concoures and Sitework 0 n/a 1,049,415
Subtotal Scope A 9,709,066
Add for Contingency (10%) & Escalation (5%) - 15% 1,456,360
Total Previous Construction Cost: Scope A 11,165,425
Total Fees 24%: Scope A 2,679,702
Previous Total Project Cost: Scope A 13,845,128
Total Additional Cost (See Attached Breakdown) 3,158,287
Total New Fees 24%: Scope A 757,989
Total New Project Cost: Scope A 17,761,403
Prepared by Busby & Associates, Inc., Houston, TX Page 3 of 6
Item/Description Quantity Rate $ Total $
Date of Estimate: October 30, 2008 - Revised March 18, 2009
Texas A&M University
College Station, Texas
OLSEN FIELD RENOVATION
Preliminary/Program Design Estimate
SCOPE B - New Field Club Seating & Dugouts
Dugouts, complete 2,493 45.00 112,174
Construct Stands for Lower Seating 1,931 125.00 241,436
Seating, added Stands 257 200.00 51,416
Subtotal Phase B 405,027
Add for Contingency (10%) & Escalation (5%) - 15% 60,754
Total Construction Cost: Scope B 465,781
Total Fees 24%: Scope B 111,787
Total Project Cost: Scope B 577,568
Scope C - Seat Replacement - Entire Stadium
Seating, Replacement, Lower Stands 1,287 125.00 160,875
Seating, Replacement, Upper Stands 3,368 125.00 421,000
Field Lighting Equipment 340,000 1.00 340,000
Field Lighting Demo & Installation 110,000 1.00 110,000
Subtotal Scope C 1,031,875
Add for Contingency (10%) & Escalation (5%) - 15% 154,781
Total Construction Cost: Scope C 1,186,656
Total Fees 24%: Scope C 284,798
Total Project Cost: Scope C 1,471,454
Scope D - Right Field Foul Area
Seating, Replacement, Lower Stands 1,017 65.00 66,105
Concourse Addition 6,832 22.00 150,306
Construct Stands for Right Field Seating 6,319 65.00 410,736
Storage area vault 1,500 110.00 165,000
Play Set, Tent, Ground Cover 1,200 50.00 60,000
Restroom/Concession 2,159 270.75 584,483
Pitcher's Warm-up Field 1,812 40.00 72,462
Maintenance Facilities 1,318 225.00 296,462
Subtotal Scope D 1,805,554
Add for Contingency (10%) & Escalation (5%) - 15% 270,833
Total Construction Cost: Scope D 2,076,387
Prepared by Busby & Associates, Inc., Houston, TX Page 4 of 6
Item/Description Quantity Rate $ Total $
Date of Estimate: October 30, 2008 - Revised March 18, 2009
Texas A&M University
College Station, Texas
OLSEN FIELD RENOVATION
Preliminary/Program Design Estimate
Total Fees 24%: Scope D 498,333
Total Project Cost: Scope D 2,574,719
Scope E - Left Field Foul Seating Area
Seating, Replacement, Lower Stands 817 65.00 53,105
Concourse Addition 4,658 22.00 102,487
Construct Stands for Right Field Seating 5,293 65.00 344,027
Restroom/Concession 0 285.00 0
Pitcher's Warm-up Field 1,812 40.00 72,462
Maintenance Facilities 0 250.00 0
Subtotal Scope E 572,081
Add for Contingency (10%) & Escalation (5%) - 15% 85,812
Total Construction Cost: Scope E 657,893
Total Fees 24%: Scope E 157,894
Total Project Cost: Scope E 815,788
Scope F - Home Plate Club
Home Plate Club 3,965 261.00 1,034,759
Restroom/Custodian area 816 318.25 259,713
Subtotal Scope F 1,294,472
Add for Contingency (10%) & Escalation (5%) - 15% 194,171
Total Construction Cost: Scope F 1,488,643
Total Fees 24%: Scope F 357,274
Total Project Cost: Scope F 1,845,917
Total Previous Construction Cost: All Phases 17,040,785
Total Previous Fees at 24%: All Phases 4,089,788
Total Previous Project Cost: All Phases 21,130,574
Total Previuos Construction Cost: Phase 1 (Scope A-B) 11,631,206
Total Previous Fees at 24%: Phase 1 (Scope A-B) 2,791,489
Total Previous Project Cost: Phase 1 14,422,695
Total Updated Construction Cost: All Scope 20,199,072
Prepared by Busby & Associates, Inc., Houston, TX Page 5 of 6
Item/Description Quantity Rate $ Total $
Date of Estimate: October 30, 2008 - Revised March 18, 2009
Texas A&M University
College Station, Texas
OLSEN FIELD RENOVATION
Preliminary/Program Design Estimate
Total Updated Fees at 24%: All Scope 4,847,777
Total Updated Project Cost: All Scope 25,046,849
Total Updated Construction Cost: Phase 1 (Scope A-B) 14,789,493
Total Updated Fees at 24%: Phase 1 (Scope A-B) 3,549,478
Total Updated Project Cost: Phase 1 18,338,971
Total Updated Construction Cost: Phase 2 (Scope C-E) 3,920,936
Total Updated Fees at 24%: Phase 2 (Scope C-E) 941,025
Total Updated Project Cost: Phase 2 4,861,961
Total Updated Project Cost: Phase 1 & 2 23,200,932
24% Fee Estimate Provided by Texas AM Facilties Department
Based on Fall 2008 Preliminary Design and Program Study by DLR Group with Texas AM University