Facility Condition Assessment Final Report Region: 11-National Capital Region Campus: Potomac Asset: GSA-ROB
Submitted by: VFA, Inc. Joseph Hanratty 266 Summer St. Boston, MA 02210-1112 800-693-3132 June, 2010
5/28/2010 1
Acknowledgements VFA, Inc. extends our appreciation to GSA. We wish to acknowledge the time and effort put forth by everyone who assisted with this project. Thank you to the entire staff at GSA whom offered guidance and assistance during the project and contributed to the success of the project. The members of the project team went to great lengths to assure that the information they collected was accurate and concise, and of the utmost value to GSA. There are other members who undoubtedly participated in this project, though may not have been mentioned in this acknowledgement. To those, we express our appreciation for your help and input. Report Disclaimer VFA has produced this document under an agreement between VFA and GSA. Other than to Client, VFA disclaims any obligation to any other person with respect to any material presented in this document and no person may rely upon this document without advance and express written consent from VFA and such person's written agreement to be bound by the limitations, qualifications, terms, conditions, and indemnities to VFA set forth in that agreement. VFA specifically states that its review of the property in question is subject to monetary restraints and scope limitations. Given those limitations and conditions, VFA has made what, in its opinion, is a reasonable investigation, limited to visual observations. Design analysis of systems including structural systems has not been performed. VFA has also relied upon interviews and documents with the understanding that independent verification of their factual content is beyond the scope of VFA's work. The materials presented in this document are "to VFA's knowledge" where such phrase means to VFA's actual knowledge of the subject matter after such inquiry as VFA considered reasonable in light of the qualifications and limitations upon the scope of work. Assumptions regarding the overall condition of the properties have been developed based upon inspection of "representative" areas of the facilities. As such, the development of schematic methods and associated costs for the correction of identified deficiencies is based upon the overview inspection and is also limited with respect to completeness. Investigation for the presence of asbestos containing materials (ACM), PCB's, CFC's, radon and other environmentally hazardous materials is not part of this Agreement. In addition, a review and certification that the buildings have been designed to meet current seismic requirements is not part of this review.
t a b l e o f c o n t e n t s
page 1 of 1
Region: 11-National Capital Region Campus: Potomac Asset: GSA-ROB
Section
Executive Summary A • Facilities Condition Assessment • Report Structure
Assessment Methodology B • System List Report
Complex Renewal Management C • Facility Renewal Forecast
Complex Funding Scenarios D • Comparison of Options • Funding/FCI Report
Complex Current Requirement Management E • Asset List Report • Crosstab of Requirements by Category and Priority • Crosstab of Requirements by Category and System Group • Crosstab of Requirements by System Group Priority • Requirement Summary by Category • Requirement Summary by System Group • Requirement Summary by Priority
Asset Detailed Data F The following reports are included:
• Asset Detail • Requirement Detail by Priority • Photographs
Glossary G
e x e c u t i v e s u m m a r y
Page 1 of 4
VFA, Inc. conducted a facility condition assessment of National Capital
Region/Potomac/GSA-ROB. The following facility assessment reporting demonstrates the
VFA method of facilities analysis and the proprietary software systems that support the
analysis. The primary goals of the assessment include:
1. To determine the overall building condition and the condition of the primary systems.
2. Identify the building requirements and needs.
3. Recommend actions for the requirements.
4. Provide cost estimates for the requirement actions.
5. Prioritize the requirements.
6. Establish budgetary requirements for the deferred Maintenance backlogs, facility
renewal, and functional and programmatic improvements.
The facilities analysis includes the following; all based on a detailed on-site assessment of
GSA-ROB by the VFA specialized facilities assessment professionals:
• Current condition analyses – existing facility requirements including deferred
Maintenance, deferred renewal, near-term anticipated renewal, recommended
discretionary improvements, and code non-compliance issues.
• Anticipated capital renewal analyses – projections of ongoing degradation of facilities’
components and costs associated with the renewal or replacement of these
components as they reach the end of their useful lives.
• Capital funding analyses – scenario comparisons showing various funding levels and
the effect of each on the condition of the building; an optimal funding level is
identified.
e x e c u t i v e s u m m a r y
Page 2 of 4
Current conditions analysis –
Asset Name and Current Replacement Value
Approximate Requirement Cost and FCI
Approximate Requirement Cost and RI
GSA-ROB CRV = $182,889,000 (GSA’s STAR value)
$65,852,000 FCI (Priorities 1-3) = 0.36
$65,852,000 RI (Priorities 1-5) = 0.36
The assessment team identified and estimated current requirements with actions totaling
$65,852,000 for GSA-ROB. Summarizing VFA condition findings, the present condition as
evidenced by a Facility Condition Index (FCI) of 0.36 is poor. Refer to the Assessment
Methodology for further discussion of FCI.
On a system by system basis, Interior Construction and Conveyance (38%), Electrical
System (24%) and HVAC System (24%) accounted for 94% of the overall backlog. Analyzing
the requirement data by category shows that 63% of the total $65,852,295 backlog is
attributed to Capacity/Design (18%), Integrity (17%), Appearance (15%) and Recapture
Vacant Space (13%) issues. Of the $65,852,295 backlog, $47,765,026 or 73% of it can be
attributed to near term requirements (priorities 1-3), years 1-5. $18,087,269 can be attributed
to 5+ Years and Does Not Meet Current Codes/Standards (priorities 4-5).
It should be noted that the CRV indicated in the "Current condition analysis-" above, is from
GSA’s STAR system. Calculations performed within VFA.facility and the results displayed in
this report are based on system models in the VFA.facility software application, not the STAR
CRV. These systems are displayed in the “System List Report” which can be found under tab
“B” in this report binder.
Anticipated capital renewal analysis –
VFA estimates average capital renewal requirements, averaged over a 20-year period, GSA-
ROB to be approximately $7,862,518 per year. It is important to note these values represent
current dollar 20-year average costs. The profile of annual spending associated is non-linear
and “spiky” as evidenced by the Facility Renewal Forecast. Based on systems reaching the
end of their expected lifecycles, increased capital expenditures are forecasted to peak in
years 2020, 2022 and 2030.
e x e c u t i v e s u m m a r y
Page 3 of 4
The capital renewal forecasts represent only costs associated with anticipated systems
requiring replacement as they reach the end of their useful lives. Current deferred
Maintenance backlog is not included in the above figure; however, the combination of both
capital renewal need and deferred Maintenance is addressed in the funding scenario
analyses.
Capital funding analyses –
As an example of our capability of producing multiple funding scenarios to model the effects
of various levels of funding on the condition of GSA-ROB, we have selected three models as
defined below.
Three options were modeled for priorities 1 – 3:
1. Typical funding modeled as annual funding at 1/2% of current replacement value;
2. Maintain the current condition level of requirement costs or FCI; and
3. Attain a condition level, FCI=0.05 to be reached in ten years and maintained
thereafter.
Total Aggregate Funding in Net Present Dollars over 20 years
Condition at Year 20 as Percent of Building Replacement Value
Backlog at End of Model Duration (in Net Present Dollars)
Option 1: Level funding @ 1/2% Plant Value
$18,288,922 FCI = 0.36 $75,634,407
Option 2: Maintain Current FCI
$26,340,918 FCI = 0.36 $65,852,295
Option 3: Attain desired condition level over 10 years.
$66,603,468 FCI = 0.05 $9,144,462
e x e c u t i v e s u m m a r y
Page 4 of 4
Report Structure
The report contains the following sections, which illustrate the scope of work performed by
VFA and demonstrate the capabilities of VFA.facility:
Assessment Methodology
Describes the methods employed and defines the categorization and prioritization standards
applied to identify requirements. Also defines Facility Condition Index (FCI).
Complex Renewal Management
Building systems reaching the end of their useful lives require replacement. An important
feature of VFA.facility is the ability to predict the annual facility renewal funding required
maintaining a portfolio of buildings or any subset thereof. This section presents the
methodology used in this analysis and Capital Renewal Forecast for GSA-ROB.
Complex Funding Scenarios
The logic and methodology used during the analysis of the condition data is presented along
with three funding scenarios that have been provided for illustrative purposes. The three
scenarios represent different ends of the funding spectrum and their resultant effects on the
facility over time.
Complex Current Requirement Management
Additional reports summarize the requirement cost by priority, category and the building
system group. Cross-tabular reports presenting requirements sorted by category and priority
and system and priority, and category and system are also included.
Asset Detailed Data
VFA.facility provides a building summary containing a general description of each building,
its construction and condition. At the top of the report, the building FCI is included.
Additionally, general building information and a summary of the building component condition
are included. For full requirement detail, the building report contains detailed descriptions of
each requirement and of associated action methods. These detailed reports also indicate the
action cost detail provided through the use of the program’s estimating module, VFA.
estimator.
a s s e s s m e n t m e t h o d o l o g y
page 1 of 6
Initial Project Setup Prior to the field survey, the VFA project manager obtained all pertinent data, drawings and
information for the building to be assessed. The assessment team met with Mid-Atlantic Pacific
Rim Region/North Los Angeles Street Field Office representatives at the start of the field
assessment to review criteria to be used to evaluate the facility. Discussions were conducted to
ascertain particular problems previously encountered, corrective solutions used and their
effectiveness, and anticipated future projects. Existing building requirements and sensible
improvements were noted. These instructions and checklists are represented below.
Building Survey The survey team consisting of an architect, a mechanical consultant and an electrical consultant
inspected the building or buildings contained in this report. In conjunction with the building
surveys, the team met with the Building Staff responsible for maintenance to get a more in depth
viewpoint of problem areas.
The requirements were classified in several ways. In addition to detailed specific descriptions,
each requirement was assigned to a category, priority, and primary system association. This
parallel differentiation allows for multiple queries of the database, facilitating analysis of the data.
It is possible, for instance, to query the database for all Priority 1 requirements in the HVAC
System, or all Priority 1 and 2 Building Integrity issues in the Exterior Wall Systems.
The criteria used to determine the priorities, categories and primary systems are as follows:
Priorities Priorities are assigned to requirements to indicate severity and a time frame in which corrective
action should take place. The following list is of the default priorities:
Name
1 – Currently Critical (immediate)
2 – Potentially Critical (1yr)
3 – Necessary – Not yet critical (years 2-5)
4 – Recommended (years 6-10)
5 – Does Not Meet Current Codes/Standards (“Grandfathered”)
a s s e s s m e n t m e t h o d o l o g y
page 2 of 6
Requirement Priorities
Priority 1 Currently Critical (immediate) o Require immediate action o Correct a cited safety hazard o Stop accelerated deterioration o Return a facility or equipment to operation
Priority 2 Potentially Critical (year 1)
o If not corrected expeditiously, will become critical within a year. o Potential life safety hazard o Intermittent operations o Rapid deterioration which will lead to loss of facility operation
Priority 3 Necessary - Not yet critical (years 2-5)
o Repairs which provide a rapid return on investment, often including energy efficiency projects
o Associated damage or higher costs if deferred further o Building or site improvements uncompleted due to inadequate funding or other
reasons o Repairs which will preclude predictable deterioration, potential downtime, and / or
higher short-term maintenance costs, or replacement of building components which have exceeded their predicted useful life
Priority 4 Recommended (years 6-10)
o Sensible improvement to existing conditions that is not required for the basic function of the facility
o Overall usability improvement o Long term maintenance cost reduction
Priority 5 Does Not Meet Current Codes / Standards (“Grandfathered”) o No action is required at this time, but substantial work performed in the future
may require correct
Deficiency Categories Top-level parent categories, which group requirement categories, are listed below in bold italics.
Child categories are grouped underneath a parent, and are listed below in italics. You can apply a
parent category or a child category to a requirement.
Code Compliance
• Accessibility: Conditions that violate the American Disabilities Act guidelines.
(Examples: Non-compliant building entrances, plumbing fixtures, and door hardware).
• Building Code: Conditions that violate Building codes (Examples: Any condition that
disregards building, electrical, mechanical, and plumbing codes.)
• Life Safety: Conditions that violate the NFPA 101 Life Safety Code (Example: Any
condition that endangers life in the event of fire, smoke, fumes or panic.)
Operations
a s s e s s m e n t m e t h o d o l o g y
page 3 of 6
• Energy: Conditions that adversely affect energy use (Examples: Single pane
windows, pipe insulation).
• Maintenance: Components or systems that require routine maintenance. (Examples:
Recalibrate thermostats, clean ducts).
• Security: Conditions that compromise the protection of the asset or its occupants
(Examples: Broken locks, lack of lighting).
Environmental
• Air/Water Quality: Conditions that affect the environmental quality of the water or air
(Examples: Insufficient ventilation, lack of chemical treatment, no backflow
protection).
• Asbestos: Visible observance of suspected Asbestos Containing Materials (ACMs).
• Lead: Visible observance of suspected lead-based paint.
• PCB: Visible observance of suspected PCB-containing materials in building
equipment (Example: Transformer).
Functionality
• Mission: Components or systems that do not meet the standards of the organization
(Examples: Non- uniform paint and décor; equipment upgrades to ensure a facility is
operational 24/7.)
• Modernization: Conditions that need to be made modern in appearance or function
(Example: Outdated furniture).
• Plant Adaptation: Components or systems that must change to fit a new or adapted
use (Example: Renovation or restoration of old space).
• Obsolescence: Components or systems that are or are becoming obsolete (Example:
Outdated equipment).
• Capacity: Components or systems that do not have the ability to keep up with
demand load (Example: Heating equipment that cannot adequately cover its intended
area, overcrowding).
Integrity
• Appearance: Problems with the asset’s appearance that are not functional in nature
(Examples: Peeling paint, worn carpet).
• Reliability: Components or systems that cannot be depended upon (Example:
Equipment that functions correctly but sometimes is unpredictable).
• Beyond Rated Life: A component or system that had exceeded its rated life
(Example: A 20 year warranted roof that is 30 years old).
a s s e s s m e n t m e t h o d o l o g y
page 4 of 6
Miscellaneous
• Other: Other deficient items not covered in all other categories (Examples: Space
utilization, Occupational Health and Safety, and OSHA Facilities and Equipment).
Primary Systems (VFA’s Classifications)
Structure
Foundations
Basement Construction
Superstructure
Ramps
Exterior Structure
Exterior Stairs and Fire Escapes
Roof Construction
Exterior Walls
Exterior Soffits
Exterior Windows
Exterior Doors
Roofing
Gutters and Downspouts
Roof Openings
Interior Construction
Interior Construction
Partitions
Interior Windows and Storefronts
Interior Doors
Stairs
Interior Finishes
Wall Finishes
Floor Finishes
Ceiling Finishes
Elevators and Lifts
Escalators and Moving Walks
Other Conveying Systems
Equipment
Furnishings
Hazardous Components Abatement
Special Construction
Plumbing
a s s e s s m e n t m e t h o d o l o g y
page 5 of 6
Plumbing Fixtures
Domestic Water Distribution
Sanitary Waste
Rain Water Drainage
Other Plumbing Systems
Sprinklers
Standpipes
Other Fire Protection Systems
HVAC
Heat Generating Systems
Insulation
Cooling Generating Systems
Distribution Systems
Terminal and Package Units
Controls and Instrumentation
Exhaust & Ventilating Systems
Other HVAC Systems and Equipment
Electrical
Electrical Service and Distribution
Lighting and Branch Wiring
Communications and Security
Fire Alarm Systems
Other Electrical Systems
Emergency Light and Power Systems
Cost Estimating For each requirement, one or more proposed actions were established, and a recommended
action identified. VFA assessors base the recommended action on an “in kind” replacement or the
current technology available utilizing their experiences and good engineering practice. The
corrective work was then estimated using 2009 R.S. Means Estimating Data accessed directly by
VFA.facility. For work not covered by R.S. Means, a lump sum figure was inserted and described
in the text of the requirement.
Building and Other Codes Used The detailed on-site assessment performed by VFA’s specialized facilities assessment
professionals, included a review of all major building systems for Code Compliance. The latest
issue dates of the codes utilized are:
GSA Codes
a s s e s s m e n t m e t h o d o l o g y
page 6 of 6
• Building/Dwelling Code IBC 2003 (State Building Code) • Structural Code IBC 2003 (State Building Code) • Plumbing Code IPC 2003 (State Building Code) • Mechanical Code IMC 2003 (State Building Code) • Electrical Code NEC 2005, NFPA 70 (West Va. State Fire Code) • Fire/Life Safety Code NFPA 2004/2005 Ed., with supplement • Accessibility Code ADAAG (Current)
Facility Condition Index
VFA has automated a standard process for assessing the relative condition of buildings,
facilitating comparison both within and among institutions. For each building, the Facility
Condition Index (FCI) is developed which measures the relative amount of current requirements
in the building. The total value of existing requirements is divided by the current replacement
value of the building; resulting in the FCI. The higher the FCI, the poorer the condition of the
facility. For example, if a building with a replacement value of $1,000,000 has $100,000 of
existing requirements; the FCI is $100,000/$1,000,000 or 0.10. This principle can be expanded to
cover groups of buildings or an entire campus. The FCI standards are:
Excellent 0.00 to 0.05
Good 0.05 to 0.10
Fair 0.10 to 0.15
Poor Greater than 0.15
The FCI is a standard measure used throughout the country; it is recommended by both the
National Association of College Business Officers (NACUBO) and the Association of Higher
Education Facility Officers (APPA).
To determine the current replacement value of the building, VFA.facility uses cost templates
developed for each building construction type or use such as office, laboratory, healthcare, etc.
These building replacement values are derived by VFA from historical and R.S. Means Data.
Reference the following pages for the cost model with a breakdown by building system for the
building or buildings included in this report.
System List Reportby Asset Name
Page 1 of
Region: 11 - National Capital Region Asset Name : GSA-ROB
Service_Center: Potomac Asset Number : DC0031ZZ
Asset Size : 943,493 SF
Asset Replacement Value : 182,889,241
System System Name Lifetime SCI Renewal FY Renewal Cost Replacement Cost
A-Substructure Foundation Wall and
Footings 12-Ft - Full
Basement
75 0.00 2027 124,205 1,987,282
A-Substructure Pile Foundations 75 0.00 2027 62,020 992,320
A-Substructure Structural Slab on
Grade - Heavy
Industrial
75 0.00 2037 1,167,532 18,680,511
B10-Superstructure Multi-Floor
Superstructure - High
Cost
75 0.00 2017 2,633,638 42,138,202
B1014-Ramps Accessible Ramps -
Exterior Concrete
25 0.00 2022 31,986 255,891
B1015-Exterior Stairs and Fire
Escapes
Exterior Stairs -
Entrance - Concrete
50 0.77 2022 34,017 27,214
B2010-Exterior Walls Penthouse CMU
Block Walls (Painted)
75 0.00 2027 21,751 174,005
B2010-Exterior Walls Stucco On CMU and
Concrete Walls
60 0.19 2067 4,273,265 9,767,463
B2010-Exterior Walls Rooftop CMU Screen
Walls
75 0.54 2083 33,640 269,117
B2020-Exterior Windows Aluminum Windows 30 0.00 2029 2,049,744 1,639,795
B2020-Exterior Windows Steel Windows 30 1.59 2040 64,347 51,477
B2030-Exterior Doors Door Assembly -
Storefront - Sliding
30 0.00 2030 23,155 18,524
B2030-Exterior Doors Door Assembly - 6 x
7 Storefront
30 0.00 2030 89,557 71,646
System List Report
by Asset Name
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 8
All costs in USD.
Page 2 of
System System Name Lifetime SCI Renewal FY Renewal Cost Replacement Cost
B2030-Exterior Doors Overhead Doors
(Electrically
Operated)
30 0.00 2034 31,923 25,538
B2030-Exterior Doors Door Assembly -
Average
30 0.08 2030 403,959 323,167
B30-Roofing Single Ply Membrane
- Ballasted
25 1.21 2034 699,683 559,746
B30-Roofing BUR (Built Up
Roofing)
20 1.57 2029 753,780 603,024
B30-Roofing Metal Roofing 65 0.00 2027 52,641 42,113
C1010-Partitions GWB 2HR Rated
Walls
50 0.04 2018 842,589 1,348,142
C1010-Partitions Windows/Storefront
Partitions
50 0.00 2051 8,248 6,598
C1010-Partitions CMU Block Walls -
Facing 2 Sides
50 0.00 2022 5,521,198 8,833,916
C1020-Interior Doors Swinging Doors - 3 x
7 HM - Rated
50 0.11 2058 1,234,375 987,500
C1020-Interior Doors Swinging Doors - 3 x
7 Wd - NR
50 0.48 2059 7,128,796 5,703,037
C1020-Interior Doors Swinging Doors - Pair
- 6 x 7 HM - NR
50 0.00 2018 1,042,284 1,283,600
C1030-Fittings Restroom Accessories 25 0.00 2025 531,520 425,216
C1030-Fittings Toilet Partitions 40 0.00 2041 877,655 702,124
C1035-Identifying Devices Fittings: Signage
(Room Numbering
and Identification)
10 1.31 2018 168,745 134,996
C20-Stairs Stairs 75 0.48 2022 1,069,693 2,852,514
C3010-Wall Finishes Ceramic Tiles 25 0.00 2032 1,157,929 926,343
C3010-Wall Finishes Painted Finish 10 0.90 2021 2,596,001 2,076,801
System List Report
by Asset Name
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 8
All costs in USD.
Page 3 of
System System Name Lifetime SCI Renewal FY Renewal Cost Replacement Cost
C3010-Wall Finishes Wall Covering -
Vinyl
10 0.95 2018 7,533 6,027
C3010-Wall Finishes Raised Wood
Paneling
30 0.00 2030 61,005 75,083
C3010-Wall Finishes Marble Finish 50 0.32 2018 471,627 377,302
C3010-Wall Finishes Epoxy Finish Walls 40 0.04 2049 2,502,324 2,001,859
C3020-Floor Finishes Access Computer
Room Flooring
25 0.07 2025 1,968,526 1,574,821
C3020-Floor Finishes Carpeting - Carpet
Tiles
10 0.74 2020 4,676,852 3,741,482
C3020-Floor Finishes Ceramic Tile - Thin
Set
25 0.00 2014 201,932 161,545
C3020-Floor Finishes Quarry Tile 25 0.00 2014 887,331 709,865
C3020-Floor Finishes Carpeting - Carpet
Broadloom
10 0.50 2020 8,055,641 6,444,513
C3020-Floor Finishes VCT 10 1.29 2019 1,693,586 1,354,868
C3020-Floor Finishes Terrazzo 50 2.57 2060 179,665 143,732
C3020-Floor Finishes Epoxy Painted
Flooring
50 0.29 2059 1,462,760 1,170,208
C3030-Ceiling Finishes GWB Taped and
Finished
30 0.58 2022 216,728 173,382
C3030-Ceiling Finishes ACT System 20 0.81 2032 6,232,222 4,985,778
C3030-Ceiling Finishes Ceiling - Painted
Concrete
30 0.18 2040 1,849,561 1,479,649
D1010-Elevators and Lifts Traction Geared
Freight Elevator #12
35 0.83 2043 593,894 475,116
D1010-Elevators and Lifts Traction Geared
Freight Elevator #7
35 0.00 2042 467,303 373,843
D1010-Elevators and Lifts Traction Geared
Freight Elevator #8
35 0.00 2042 555,645 444,516
System List Report
by Asset Name
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 8
All costs in USD.
Page 4 of
System System Name Lifetime SCI Renewal FY Renewal Cost Replacement Cost
D1010-Elevators and Lifts Traction Gearless
Passenger Elevators
35 1.19 2044 5,193,455 4,154,764
D2010-Plumbing Fixtures Kitchenette Cabinet,
Counter and Sink
30 0.00 2015 82,156 65,725
D2010-Plumbing Fixtures Emergency Eyewash
and Shower Units
30 0.00 2018 8,022 6,418
D2010-Plumbing Fixtures Custodial/Utility
Sinks
30 0.18 2017 463,406 370,725
D2010-Plumbing Fixtures Water Coolers,
Floor-Mounted
20 1.69 2031 35,058 28,047
D2010-Plumbing Fixtures Work and Exam
Stations, Wall Sink
30 0.00 2018 8,145 6,516
D2010-Plumbing Fixtures Water Coolers - Wall
Mount
20 0.00 2020 65,798 52,638
D2010-Plumbing Fixtures Restroom Fixtures 30 2.09 2018 2,782,429 2,225,943
D2020-Domestic Water Distribution Water Dist Complete 30 1.32 2013 1,360,153 1,209,025
D2020-Domestic Water Distribution Pressure Booster
Pump
15 0.00 2021 93,983 83,913
D2020-Domestic Water Distribution Water Heater - Elec 10 0.00 2016 48,239 43,071
D2020-Domestic Water Distribution Water Heater - Steam
- Stor Tank
15 0.00 2016 157,112 140,278
D2030-Sanitary Waste Sanitary Waste
System
50 0.28 2018 1,430,952 1,144,761
D2040-Rain Water Drainage Roof Drainage 50 0.01 2017 2,244,280 1,795,424
D3030-Cooling Generating Systems Chiller - Centrifugal
w/Cooling Tower -
2003
28 0.00 2031 663,842 531,073
D3030-Cooling Generating Systems Chiller - Centrifugal
w/Cooling Tower -
1992
28 0.00 2020 1,718,323 1,374,659
System List Report
by Asset Name
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 8
All costs in USD.
Page 5 of
System System Name Lifetime SCI Renewal FY Renewal Cost Replacement Cost
D3040-Distribution Systems Cabinet Fan Coil AC
System
30 0.00 2015 49,122 39,298
D3040-Distribution Systems Two Pipe Distribution
System
30 0.00 2018 729,317 583,454
D3040-Distribution Systems Return Air Ductwork
and Fan
20 0.01 2017 4,848,465 3,878,772
D3040-Distribution Systems Restroom Exhaust
System w/Roof Fan
20 0.00 2017 229,996 183,997
D3040-Distribution Systems General Building
Exhaust
25 0.00 2013 3,957,561 3,166,049
D3040-Distribution Systems Central AHU, VAV
Syst., w/Distribution
25 4.71 2017 2,160,240 1,728,192
D3040-Distribution Systems Perimeter Heat,
Steam Cast Iron
Radiators
30 0.00 2018 693,692 554,954
D3040-Distribution Systems Heat Exchanger,
Steam to HW, Shell
and Tube
20 0.00 2027 25,928 20,742
D3040-Distribution Systems Kitchen Exhaust
System, Commercial
15 0.00 2022 45,033 36,027
D3040-Distribution Systems Restroom Exhaust
System w/Roof Fan
20 0.00 2013 229,996 183,997
D3040-Distribution Systems Steam Piping and
Condensate Return
30 0.00 2017 1,383,646 1,106,917
D3040-Distribution Systems Return Air Ductwork
and Fan
20 0.00 2015 6,848,456 5,478,765
D3041-Air Distribution Systems Perimeter Duct
System
30 1.07 2018 3,327,964 3,327,964
D3050-Terminal and Package Units Unit Heaters - Steam 25 0.00 2014 23,520 21,000
System List Report
by Asset Name
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 8
All costs in USD.
Page 6 of
System System Name Lifetime SCI Renewal FY Renewal Cost Replacement Cost
D3050-Terminal and Package Units Computer Room
Cooling - DX w/Air
Cooled Remote
Condenser
20 0.00 2018 249,918 199,935
D3050-Terminal and Package Units Window Air
Conditioning Units
10 1.65 2010 8,296 7,901
D3051-Terminal Self-Contained
Units
Split System Units,
Elevator Room AC
Units
15 0.00 2016 27,567 27,567
D3060-Controls and Instrumentation DDC/Pneumatic
System - Hybrid
25 0.00 2015 7,870,201 6,296,161
D40-Fire Protection Fire Extinguishers,
Dry Chem, w/Cabinet
30 0.00 2019 75,677 67,569
D40-Fire Protection Wet Standpipe
System
35 0.00 2013 2,389,444 1,911,555
D40-Fire Protection Wet Sprinkler System
- w/Pump
35 0.62 2013 2,533,033 2,026,426
D5010-Electrical Service and
Distribution
Vault Transformers -
Silicone, Class OA
30 0.09 2020 1,676,994 1,341,595
D5011-High Tension Service and
Dist.
Main Electrical
Service - South Side,
13.8kV
30 1.00 2038 1,934,211 1,547,369
D5012-Low Tension Service and
Dist.
Distribution
Equipment -
Emergency System
Switchboard,
Panelboards and Elev
ATS
30 0.06 2034 1,647,065 1,317,652
D5012-Low Tension Service and
Dist.
Distribution
Equipment - UPS
System Switchboard,
Panelboards and
Feeders
30 0.00 2025 868,570 694,856
System List Report
by Asset Name
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 8
All costs in USD.
Page 7 of
System System Name Lifetime SCI Renewal FY Renewal Cost Replacement Cost
D5012-Low Tension Service and
Dist.
Distribution
Equipment - Network
Protectors, Secondary
Bus and Main
Switchboards
30 0.83 2038 5,127,114 4,101,691
D5012-Low Tension Service and
Dist.
Distribution
Equipment - Normal
System Panelboards
and Feeders
30 0.00 2020 7,285,567 5,828,454
D5012-Low Tension Service and
Dist.
Distribution
Equipment - Normal
System Panelboards
and Feeders
30 0.66 2038 3,740,817 3,937,702
D5021-Branch Wiring Devices Branch Wiring -
Equipment & Devices
30 0.00 2022 6,390,957 5,112,766
D5021-Branch Wiring Devices Branch Wiring -
Equipment & Devices
30 0.73 2038 3,195,478 2,556,383
D5022-Lighting Equipment Lighting Fixtures 20 0.13 2021 12,160,851 9,728,681
D5033-Telephone Systems Telephone System 10 0.09 2019 993,566 2,483,915
D5035-Television Systems Coaxial Connectivity 15 0.00 2015 833,023 666,418
D5037-Fire Alarm Systems Fire Alarm System 10 0.04 2014 3,975,087 5,300,116
D5038-Security and Detection
Systems
Security System -
CCTV
10 0.00 2016 950,672 760,537
D5038-Security and Detection
Systems
Security System -
Card Access System
10 0.04 2013 1,078,435 1,135,195
D5039-Local Area Networks LAN System 15 0.70 2025 1,138,988 2,277,977
D5092-Emergency Light and Power
Systems
Emergency Generator
- 710kW
25 2.91 2033 773,724 703,385
D5092-Emergency Light and Power
Systems
LED Exit Signs -
Average Density
20 0.09 2017 919,716 735,773
D5092-Emergency Light and Power
Systems
UPS System -
160kVA
10 0.00 2014 465,543 372,434
System List Report
by Asset Name
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 8
All costs in USD.
Page 8 of
System System Name Lifetime SCI Renewal FY Renewal Cost Replacement Cost
D5092-Emergency Light and Power
Systems
Incandescent Exit
Signs
20 0.74 2030 229,929 183,943
D5092-Emergency Light and Power
Systems
Emergency Battery
Pack Lights
10 0.96 2020 926,961 741,569
D5092-Emergency Light and Power
Systems
Emergency Battery
Pack Lights
10 0.00 2017 231,740 185,392
E-Equipment and Furnishings Kitchen Cabinets 20 0.00 2019 73,556 58,845
E-Equipment and Furnishings Office Equipment-
Medium
25 0.00 2022 10,167,564 8,134,051
E-Equipment and Furnishings Loading Dock
Equipment - Average
25 0.20 2024 91,061 72,849
E-Equipment and Furnishings Kitchen Equipment 20 0.00 2019 140,197 112,158
E-Equipment and Furnishings Fixed Casework
-Institutional
25 0.00 2022 223,977 179,182
G2020-Parking Lots Parking Lot - Surface
- Bituminous
25 0.01 2022 5,624,035 8,998,456
G2030-Pedestrian Paving Pedestrian Pavement -
Concrete
25 0.06 2020 80,352 128,564
GSA-ROB Total Costs : 193,822,184 242,079,537
Potomac Total Costs : 193,822,184 242,079,537
11 - National Capital Region Total Costs : 193,822,184 242,079,537
System List Report
by Asset Name
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 8
All costs in USD.
f a c i l i t y r e n e w a l m a n a g e m e n t
Page 1 of 2
In addition to management of deficient conditions, VFA.facility provides budgeting and management
tools for facility capital renewal forecasting. Whereas deferred maintenance is concerned with existing
conditions, capital renewal forecasting is concerned with the continuous deterioration of the building.
From an accounting perspective, this is the cause for building depreciation. This section presents the
findings of the capital renewal forecasting for National Capital Region/Potomac/GSA-ROB.
Unlike the theoretical straight-line depreciation familiar to accountants, building deterioration occurs at
a wide variety of rates for various building systems. As such, VFA has developed a methodology for
predicting building deterioration and associated capital renewal funding requirements based on
systematic analyses of the building’s components, estimating renewal costs at the end of each
component’s useful life. In a typical assessment, each building system is modeled with a value
represented as its percent of the total replacement cost of the facility, a lifetime, a percentage of the
system to be replaced at the end of its lifetime and a percent through its lifetime.
Component Lifetime
Component lifetimes represent the anticipated serviceable duration of each building component.
Lifetimes reflect the durability of the type of system present. For example, typical EPDM roofing has a
standard lifetime of 20 years, while slate shingle roofing has a serviceable life of 50 to 100 years
depending on the thickness and construction method used. As such, each component is analyzed
and a life assigned. These figures are based on published standards as modified by VFA to reflect our
professional experience. The lifetimes are further refined to reflect the owner’s experience and
approach to preventative maintenance as well as expected or historic wears on the building.
Percentage Replaced
At the time of renewal, many components are only partially renewed or replaced. For example, while
a roof is generally totally replaced at the end of its life, elevators are not totally replaced, but have
significant residual value. The shaft, piston, doors, etc. generally remain but the cab and electronics
are replaced.
Percent Used
For each component, VFA professionals estimate the percent depletion relative to its lifetime. Field
inspection results are used to determine the percent used, not simply the age of the component.
f a c i l i t y r e n e w a l m a n a g e m e n t
Page 2 of 2
The following graph illustrates the result for GSA-ROB. The annual costs associated with
replacement of systems not currently deficient but anticipated to fail in the future are mapped to the
graph. VFA estimates the average annual capital renewal requirements over a twenty-year period for
the building to be approximately, $7,862,518 (Net Present Value). The values shown in the following
Facility Renewal Forecast Chart are adjusted for inflation. The time frame used was 20 years;
additional analyses can be produced with other time frames. The profile of annual spending is non-
linear with the growth in annual spending peaking in years 2020, 2022 and 2030.
The results of this analysis are used in combination with the data collected on current requirements to
produce the financial models presented and described in the next section, Funding Scenario
Analyses.
Facility Renewal Forecast
Annual
Moving average (5 yr)
Trend based
Average
Facility Renewal Forecast
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved.
All costs in USD.
1
Year Annual Moving average (5 yr) Trend based Average
2010 8,296 7,862,518 2,765 7,061,329
2011 0 8,232,056 3,025,023 7,477,096
2012 0 8,618,963 3,751,300 7,916,347
2013 13,254,710 9,024,055 7,525,670 8,380,371
2014 6,673,394 9,448,186 8,163,835 8,870,526
2015 19,731,563 9,892,251 12,350,964 9,388,242
2016 1,559,126 10,357,188 12,987,997 9,935,030
2017 20,846,766 10,843,976 12,887,641 10,512,477
2018 16,986,338 11,353,644 16,038,255 11,122,257
2019 4,500,265 11,887,265 20,924,729 11,766,134
2020 38,774,006 12,445,967 26,406,955 12,445,967
2021 24,613,003 13,030,929 24,106,402 13,163,713
2022 50,886,346 13,643,383 25,779,103 13,921,434
2023 1,959,301 14,284,623 19,728,179 14,721,302
2024 8,620,136 14,956,001 15,385,607 15,565,606
2025 8,977,312 15,658,933 4,634,407 16,456,754
2026 2,082,926 16,394,904 4,475,989 17,397,286
2027 1,131,520 17,165,465 5,105,092 18,389,875
2028 402,940 17,972,243 10,282,741 19,437,337
2029 13,140,537 18,816,939 12,859,878 20,542,637
2030 38,358,643 19,701,336 17,519,498 21,708,898
Facility Renewal Forecast
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved.
All costs in USD.
2
Region 11 - National Capital Region
Service_Center Potomac
Asset GSA-ROB
Systems All
Years 20
Inflation 4.70%
Cost curve Spiky 0
Fiscal Year Start Date (mm/dd) 1/1
Facility Renewal Forecast
Forecast Parameters
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved.
All costs in USD.All dates are displayed in mm/dd/yyyy format
3
f u n d i n g s c e n a r i o a n a l y s i s
Page 1 of 2
VFA.facility integrates both deferred maintenance and capital renewal projection findings into
comprehensive facility funding analyses. Various strategies can be comparatively analyzed
including various funding levels, various distributions of funding and testing of assumption
parameters. Using this tool, optimal facility investment strategies can be identified.
Three investment scenarios for the National Capital Region/Potomac/GSA-ROB are included
at the end of this section. These models are based on long range planning discussions and
illustrate compelling plant needs. These models do not include debt service as a renewal
investment. The assessment treats the original capital expenditure as a renewal investment.
Adding the debt service counts the single investment twice.
The model integrates the current condition information and the annual renewal projections to
analyze various funding schemes. Building replacement cost is annually adjusted by the inflation
rate identified, in this case 4.7%. If the institution anticipates plant growth, this rate is reflected in
both the replacement cost and the overall FCI, assuming that growth is via new construction with
FCI = 0. Anticipated new requirements are estimated, as the further deterioration of current
requirements not corrected, at the backlog deterioration rate identified as 2%, and the results of
the renewal forecast. The inflation and backlog deterioration rate are based on VFA experience,
client data or published inflation rates in national publications such as the Cost Construction
News. With these factors, various funding schemes can be analyzed and the effect on the
building condition estimated. All figures are adjusted for inflation over the duration of the analysis;
the discount rate used for net present value calculations is the inflation rate as well. Other
discount rates can be used, to reflect the opportunity cost associated with a facility investment.
The investment should be assumed to include major repair costs (other than those for custodial
or routine maintenance needs) and any capital projects that substantially affect the condition of
the plant, such as building or partial building renovations.
The graphs and tables that follow identify funding strategies and show the associated effects on
condition, in terms of the FCI (see Assessment Methodology section for a discussion and
definition of FCI). The Comparison of Options presents key results such as applied funding and
FCI and backlog at end of funding period for the three scenarios. For the graphical presentation,
bars indicate annual dollars invested, as indicated on the left axis, and the lines indicate the
effect of this funding on the FCI, as indicated on the right axis. The spreadsheets have been
projected over 20 years for clarity; further extensions of the model are possible. The following
scenarios are presented for National Capital Region/Potomac/GSA-ROB:
f u n d i n g s c e n a r i o a n a l y s i s
Page 2 of 2
Option One explores the effects of investing 1/2% of current replacement value
(CRV). The present condition is considered poor according to industry standards,
with an overall FCI of 0.36. Over 20 years the condition deteriorated and increased
the FCI is 0.41. Total aggregated net present value of 20 years worth of deferred
maintenance, at this funding level, has resulted in a backlog of work estimated at
$75,634,407, an increase from the current backlog of $65,852,295.
Option Two explores the effects of setting funding levels to maintain the existing
overall FCI. In this scenario, the condition remains stable with an overall FCI of
0.36. Total aggregated net present value of 20 years worth of deferred
maintenance, at this level of funding, has resulted in a backlog that remains at
$65,852,295 given the assumed zero plant growth. The total aggregated net
present value of a 20-year building investment is $26,340,918.
Option Three explores the effects of improving and maintaining the overall FCI to
0.05, which is considered excellent by industry standards. In this scenario, building
improvements are distributed over a multi-year period improving the FCI to an
efficient 0.05 in 10 years, and maintained at this level thereafter. This scenario
implies continued use of the facility during renewal improvements. Total
aggregated net present value of 20 year building investment is $66,603,468. Total
aggregated net present value of 20 years worth of preventative maintenance has
resulted in a backlog of work estimated at $9,144,462. At the end of the 20 year
period, this backlog can be envisioned as a balloon payment of $9,144,462 coming
due to fix the requirements. Combining $9,144,462 and the $66,603,468 invested
over 20 years yields roughly an aggregate investment of $75,747,930 into the
facilities to maintain the facilities in excellent condition.
These options reflect only three of the many possible scenarios. Additional
scenarios can easily be run on the data.
Starting Net Present Value Ending
Funding Option Backlog FCI Applied Funding Ending Backlog Total Funding Requirement Deferred
Maintenance Penalty
FCI
Funding to maintain constant FCI 65,852,295 0.3601 26,340,918 65,852,295 92,193,213 26,340,917 0.3601
0.50% of the Current Replacement
Value
65,852,295 0.3601 18,288,922 75,634,407 93,923,329 28,071,033 0.4136
Funding to reduce FCI to 5% in 10
years
65,852,295 0.3601 66,603,468 9,144,462 75,747,930 9,895,634 0.0500
Pay as you go 65,852,295 0.3601 65,852,296 0 65,852,296 0 0.0000
Comparison Of Options
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved.
All costs in USD.
1
Funding/FCI Report
Funding-Maintain - FCI FCI-Maintain - FCI
Funding-0.50% of the Current Replacement Value FCI-0.50% of the Current Replacement Value
Funding-Target - Funding to reduce FCI to 5% in 10 years FCI-Target - Funding to reduce FCI to 5% in 10 years
Funding/FCI Report
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved.
All costs in USD.
1
Maintain - FCI
Year Replacement Cost Renewal Cost Backlog Deterioration Total New Liability New Backlog Total Net Plant Value Funding
Funding
Reserve FCI
2010 182,889,248 0 0 65,852,295 65,852,295 117,036,953 0 0 0.3601
2011 191,485,052 0 1,378,947 1,378,947 68,947,356 122,537,696 1,378,947 0 0.3601
2012 200,484,859 0 1,443,758 1,443,758 72,187,885 128,296,974 1,443,758 0 0.3601
2013 209,907,658 0 1,511,614 1,511,614 75,580,720 134,326,938 1,511,614 0 0.3601
2014 219,773,328 0 1,582,660 1,582,660 79,133,017 140,640,311 1,582,660 0 0.3601
2015 230,102,686 0 1,657,045 1,657,045 82,852,273 147,250,412 1,657,045 0 0.3601
2016 240,917,523 0 1,734,927 1,734,927 86,746,334 154,171,189 1,734,927 0 0.3601
2017 252,240,659 0 1,816,468 1,816,468 90,823,416 161,417,243 1,816,468 0 0.3601
2018 264,095,983 0 1,901,842 1,901,842 95,092,121 169,003,862 1,901,842 0 0.3601
2019 276,508,507 0 1,991,229 1,991,229 99,561,456 176,947,052 1,991,229 0 0.3601
2020 289,504,421 0 2,084,817 2,084,817 104,240,849 185,263,572 2,084,817 0 0.3601
2021 303,111,144 0 2,182,803 2,182,803 109,140,175 193,970,969 2,182,803 0 0.3601
2022 317,357,383 0 2,285,395 2,285,395 114,269,768 203,087,615 2,285,395 0 0.3601
2023 332,273,196 0 2,392,809 2,392,809 119,640,453 212,632,743 2,392,809 0 0.3601
2024 347,890,053 0 2,505,271 2,505,271 125,263,561 222,626,492 2,505,271 0 0.3601
2025 364,240,903 0 2,623,019 2,623,019 131,150,954 233,089,949 2,623,019 0 0.3601
2026 381,360,244 0 2,746,301 2,746,301 137,315,056 244,045,188 2,746,301 0 0.3601
2027 399,284,194 0 2,875,377 2,875,377 143,768,870 255,515,324 2,875,377 0 0.3601
2028 418,050,572 0 3,010,520 3,010,520 150,526,014 267,524,557 3,010,520 0 0.3601
2029 437,698,970 0 3,152,015 3,152,015 157,600,745 280,098,225 3,152,015 0 0.3601
2030 458,270,844 0 3,300,160 3,300,160 165,007,988 293,262,856 3,300,160 0 0.3601
Funding/FCI Report
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved.
All costs in USD.
2
0.50% of the Current Replacement Value
Year Replacement Cost Renewal Cost Backlog Deterioration Total New Liability New Backlog Total Net Plant Value Funding
Funding
Reserve FCI
2010 182,889,248 0 0 65,852,295 65,852,295 117,036,953 0 0 0.3601
2011 191,485,052 0 1,378,947 1,378,947 69,368,878 122,116,174 957,425 0 0.3623
2012 200,484,859 0 1,452,584 1,452,584 73,079,379 127,405,480 1,002,424 0 0.3645
2013 209,907,658 0 1,530,282 1,530,282 76,994,857 132,912,800 1,049,538 0 0.3668
2014 219,773,328 0 1,612,272 1,612,272 81,127,025 138,646,303 1,098,867 0 0.3691
2015 230,102,686 0 1,698,800 1,698,800 85,488,286 144,614,400 1,150,513 0 0.3715
2016 240,917,523 0 1,790,125 1,790,125 90,091,777 150,825,747 1,204,588 0 0.3740
2017 252,240,659 0 1,886,522 1,886,522 94,951,414 157,289,246 1,261,203 0 0.3764
2018 264,095,983 0 1,988,283 1,988,283 100,081,938 164,014,045 1,320,480 0 0.3790
2019 276,508,507 0 2,095,716 2,095,716 105,498,967 171,009,541 1,382,543 0 0.3815
2020 289,504,421 0 2,209,148 2,209,148 111,219,050 178,285,371 1,447,522 0 0.3842
2021 303,111,144 0 2,328,927 2,328,927 117,259,722 185,851,422 1,515,556 0 0.3869
2022 317,357,383 0 2,455,419 2,455,419 123,639,567 193,717,816 1,586,787 0 0.3896
2023 332,273,196 0 2,589,013 2,589,013 130,378,279 201,894,917 1,661,366 0 0.3924
2024 347,890,053 0 2,730,121 2,730,121 137,496,736 210,393,317 1,739,450 0 0.3952
2025 364,240,903 0 2,879,182 2,879,182 145,017,067 219,223,836 1,821,205 0 0.3981
2026 381,360,244 0 3,036,657 3,036,657 152,962,732 228,397,511 1,906,801 0 0.4011
2027 399,284,194 0 3,203,040 3,203,040 161,358,607 237,925,587 1,996,421 0 0.4041
2028 418,050,572 0 3,378,849 3,378,849 170,231,067 247,819,505 2,090,253 0 0.4072
2029 437,698,970 0 3,564,639 3,564,639 179,608,079 258,090,891 2,188,495 0 0.4103
2030 458,270,844 0 3,760,993 3,760,993 189,519,307 268,751,537 2,291,354 0 0.4136
Funding/FCI Report
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved.
All costs in USD.
3
Target - Funding to reduce FCI to 5% in 10 years
Year Replacement Cost Renewal Cost Backlog Deterioration Total New Liability New Backlog Total Net Plant Value Funding
Funding
Reserve FCI
2010 182,889,248 0 0 65,852,295 65,852,295 117,036,953 0 0 0.3601
2011 191,485,052 0 1,378,947 1,378,947 63,010,046 128,475,006 7,316,257 0 0.3291
2012 200,484,859 0 1,319,430 1,319,430 59,755,157 140,729,702 7,535,795 0 0.2981
2013 209,907,658 0 1,251,273 1,251,273 56,055,119 153,852,539 7,759,807 0 0.2670
2014 219,773,328 0 1,173,794 1,173,794 51,875,277 167,898,051 7,988,229 0 0.2360
2015 230,102,686 0 1,086,268 1,086,268 47,178,704 182,923,982 8,220,982 0 0.2050
2016 240,917,523 0 987,922 987,922 41,926,059 198,991,464 8,457,968 0 0.1740
2017 252,240,659 0 877,932 877,932 36,075,448 216,165,211 8,699,070 0 0.1430
2018 264,095,983 0 755,420 755,420 29,582,264 234,513,719 8,944,152 0 0.1120
2019 276,508,507 0 619,453 619,453 22,399,028 254,109,479 9,193,056 0 0.0810
2020 289,504,421 0 469,036 469,036 14,475,221 275,029,200 9,445,598 0 0.0500
2021 303,111,144 0 303,111 303,111 15,155,557 287,955,587 303,111 0 0.0500
2022 317,357,383 0 317,357 317,357 15,867,869 301,489,514 317,357 0 0.0500
2023 332,273,196 0 332,273 332,273 16,613,660 315,659,536 332,273 0 0.0500
2024 347,890,053 0 347,890 347,890 17,394,503 330,495,550 347,890 0 0.0500
2025 364,240,903 0 364,241 364,241 18,212,045 346,028,858 364,241 0 0.0500
2026 381,360,244 0 381,360 381,360 19,068,012 362,292,232 381,360 0 0.0500
2027 399,284,194 0 399,284 399,284 19,964,210 379,319,985 399,284 0 0.0500
2028 418,050,572 0 418,051 418,051 20,902,529 397,148,043 418,051 0 0.0500
2029 437,698,970 0 437,699 437,699 21,884,948 415,814,021 437,699 0 0.0500
2030 458,270,844 0 458,271 458,271 22,913,542 435,357,301 458,271 0 0.0500
Funding/FCI Report
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved.
All costs in USD.
4
Region 11 - National Capital Region
Service_Center Potomac
Asset GSA-ROB
Systems All
Priority All
Requirement Type All
Years 20
Inflation 4.70%
Backlog Deterioration 2%
Renewal Option No Renewals
Cost curve Spiky 0
Fiscal Year Start Date (mm/dd) 1/1
FCI/RI Setting FCI
Funding/FCI Report
Forecast Parameters
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved.
All costs in USD.All dates are displayed in mm/dd/yyyy format
5
Asset List Reportby Asset Name
Page 1 of
Region: 11 - National Capital Region
Service_Center: Potomac
Asset Type: Building
Number Name Use Age Size Replacement Value Cost/Unit FCI Cost FCI RI Cost RI
DC0031ZZ GSA-ROB OFFICE BUILDING 78 943,493 SF 182,889 0.19 65,852 0.36 65,852 0.36
Total : 943,493 182,889 NA 65,852 0.36 65,852 0.36
Asset List Report
by Asset Name
May 27, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 1
All costs in 000s USD.
Requirement Crosstab Reportby Category and Priority
Page 1 of
Region:
11 - National Capital Region
Service_Center:
Potomac
Asset Name:
GSA-ROB
Category and Priority 1 - Immediate / First Year 2 - Within 1 to 2 Years 3 - Within 3 to 5 Years 4 - 5+ Years 5: Does Not Meet Current
Codes/Standards
Total
Accessibility 0 0 4,653,780 0 1,411,768 6,065,548
Air and Water Quality 0 2,681 0 0 0 2,681
Appearance 2,603,440 2,875,268 4,373,174 254,701 0 10,106,583
Asbestos 98,347 0 0 0 0 98,347
Beyond Useful Life 0 3,810,473 2,370,878 0 0 6,181,351
Building Code 0 1,251,881 0 1,596,197 2,888,961 5,737,039
Capacity/Design 0 216,514 0 8,143,476 3,566,944 11,926,934
Integrity 0 6,945,208 4,433,546 0 0 11,378,754
Life Safety 501,326 2,466,845 0 0 30,786 2,998,957
Maintenance 0 123,710 0 0 0 123,710
Mission 0 339,892 0 50,443 0 390,335
Modernization 0 4,179 0 82,967 0 87,146
Obsolescence 0 8,817,566 0 0 0 8,817,566
Recapture Vacant Space 0 0 0 61,026 0 61,026
Reliability 0 1,784,113 47,342 0 0 1,831,455
Security 0 0 44,863 0 0 44,863
Total 3,203,113 28,638,330 15,923,583 10,188,810 7,898,459 65,852,295
Requirement Crosstab Report
by Category and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 2
All costs in USD.
Page 2 of
1 - Immediate / First Year
2 - Within 1 to 2 Years
3 - Within 3 to 5 Years
4 - 5+ Years
5: Does Not Meet Current Codes/Standards
Accessibility
Air and W
ater Quality
Appearance
Asbestos
Beyond Useful Life
Building Code
Capacity/Design
Integrity
Life Safety
MaintenanceMissi
on
Modernization
Obsolescence
Recapture Vacant Space
Reliability
Security0
2,250,000
4,500,000
6,750,000
9,000,000
Category
Cos
t
Requirement Crosstab Report
by Category and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 2
All costs in USD.
Requirement Crosstab Reportby Category and System Group
Page 1 of
Region:
11 - National Capital Region
Service_Center:
Potomac
Asset Name:
GSA-ROB
Category and System
Group
Structure Exterior Enclosure Interior
Construction and
Conveyance
Plumbing System HVAC System Fire Protection Electrical System Site Equipment and
Furnishings
Not Applicable Total
Accessibility 0 0 1,411,768 4,653,780 0 0 0 0 0 0 6,065,548
Air and Water Quality 0 0 2,681 0 0 0 0 0 0 0 2,681
Appearance 0 0 6,317,356 66,507 0 0 3,722,720 0 0 0 10,106,583
Asbestos 0 0 98,347 0 0 0 0 0 0 0 98,347
Beyond Useful Life 0 107,027 340,546 1,613,190 13,007 0 4,107,581 0 0 0 6,181,351
Building Code 0 0 1,238,329 318,517 0 1,251,881 1,596,197 0 0 1,332,115 5,737,039
Capacity/Design 0 0 0 0 11,710,420 0 216,514 0 0 0 11,926,934
Integrity 72,271 3,496,535 7,809,948 0 0 0 0 0 0 0 11,378,754
Life Safety 20,992 144,428 349,541 0 30,786 0 2,386,345 0 0 66,865 2,998,957
Maintenance 0 0 0 0 0 0 123,710 0 0 0 123,710
Mission 0 0 339,892 0 0 0 0 0 0 50,443 390,335
Modernization 0 0 0 0 0 0 87,146 0 0 0 87,146
Obsolescence 0 0 5,200,280 0 0 0 3,617,286 0 0 0 8,817,566
Recapture Vacant Space 0 0 0 0 0 0 0 0 0 61,026 61,026
Reliability 0 1,416 1,660,830 47,342 0 0 0 107,450 14,417 0 1,831,455
Security 0 0 0 0 0 0 44,863 0 0 0 44,863
Total 93,263 3,749,406 24,769,518 6,699,336 11,754,213 1,251,881 15,902,362 107,450 14,417 1,510,449 65,852,295
Requirement Crosstab Report
by Category and System Group
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 2
All costs in USD.
Page 2 of
Structure
Exterior Enclosure
Interior Construction and Conveyance
Plumbing System
HVAC System
Fire Protection
Electrical System
Site
Equipment and Furnishings
Not Applicable
Accessibility
Air and W
ater Quality
Appearance
Asbestos
Beyond Useful Life
Building Code
Capacity/Design
Integrity
Life Safety
MaintenanceMissi
on
Modernization
Obsolescence
Recapture Vacant Space
Reliability
Security0
2,500,000
5,000,000
7,500,000
10,000,000
12,500,000
Category
Cos
t
Requirement Crosstab Report
by Category and System Group
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 2
All costs in USD.
Requirement Crosstab Reportby System Group and Priority
Page 1 of
Region:
11 - National Capital Region
Service_Center:
Potomac
Asset Name:
GSA-ROB
System Group and
Priority
1 - Immediate / First Year 2 - Within 1 to 2 Years 3 - Within 3 to 5 Years 4 - 5+ Years 5: Does Not Meet Current
Codes/Standards
Total
Electrical System 2,679,858 9,684,485 1,858,855 1,679,164 0 15,902,362
Equipment and Furnishings 0 14,417 0 0 0 14,417
Exterior Enclosure 0 3,667,640 81,766 0 0 3,749,406
Fire Protection 0 1,251,881 0 0 0 1,251,881
HVAC System 0 13,007 0 8,143,476 3,597,730 11,754,213
Interior Construction and
Conveyance
447,888 13,729,392 7,687,440 254,701 2,650,097 24,769,518
Not Applicable 66,865 0 0 111,469 1,332,115 1,510,449
Plumbing System 0 85,297 6,295,522 0 318,517 6,699,336
Site 0 107,450 0 0 0 107,450
Structure 8,502 84,761 0 0 0 93,263
Total 3,203,113 28,638,330 15,923,583 10,188,810 7,898,459 65,852,295
Requirement Crosstab Report
by System Group and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 2
All costs in USD.
Page 2 of
1 - Immediate / First Year
2 - Within 1 to 2 Years
3 - Within 3 to 5 Years
4 - 5+ Years
5: Does Not Meet Current Codes/Standards
Electrical System
Equipment and Furnishings
Exterior Enclosure
Fire Protection
HVAC System
Interior Constru
ction and Conveyance
Not Applicable
Plumbing System Site
Structure0
2,500,000
5,000,000
7,500,000
10,000,000
12,500,000
15,000,000
System Group
Cos
t
Requirement Crosstab Report
by System Group and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 2
All costs in USD.
Requirement SummaryReport
by Asset Name and Category
Page 1 of
Region:
11 - National Capital Region
Service_Center:
Potomac
Asset Name:
GSA-ROB
Category Percentage of Total Cost Estimated Cost
Accessibility 9% 6,065,548
Air and Water Quality 0% 2,681
Appearance 15% 10,106,583
Asbestos 0% 98,347
Beyond Useful Life 9% 6,181,351
Building Code 9% 5,737,039
Capacity/Design 18% 11,926,934
Integrity 17% 11,378,754
Life Safety 5% 2,998,957
Maintenance 0% 123,710
Mission 1% 390,335
Modernization 0% 87,146
Obsolescence 13% 8,817,566
Recapture Vacant Space 0% 61,026
Reliability 3% 1,831,455
Security 0% 44,863
Totals 65,852,295
Requirement Summary Report
by Asset Name and Category
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 2
All costs in USD.
Page 2 of
Access
ibility
Air and W
ater Q
uality
Appearan
ce
Asbest
os
Beyond U
seful L
ife
Building C
ode
Capac
ity/D
esign
Integrit
y
Life Safe
ty
Main
tenan
ce
Miss
ion
Modern
izatio
n
Obsoles
cence
Recap
ture Vac
ant S
pace
Reliab
ility
Securit
y0
2,500,000
5,000,000
7,500,000
10,000,000
12,500,000
15,000,000
Category
Est
imat
ed C
ost
Requirement Summary Report
by Asset Name and Category
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 2
All costs in USD.
Requirement SummaryReport
by Asset Name and System Group
Page 1 of
Region:
11 - National Capital Region
Service_Center:
Potomac
Asset Name:
GSA-ROB
System Group Percentage of Total Cost Estimated Cost
Electrical System 24% 15,902,362
Equipment and Furnishings 0% 14,417
Exterior Enclosure 6% 3,749,406
Fire Protection 2% 1,251,881
HVAC System 18% 11,754,213
Interior Construction and Conveyance 38% 24,769,518
Not Applicable 2% 1,510,449
Plumbing System 10% 6,699,336
Site 0% 107,450
Structure 0% 93,263
Totals 65,852,295
Electri
cal S
ystem
Equipment a
nd Furnishings
Exterior E
nclosu
re
Fire Protec
tion
HVAC System
Interior C
onstructi
on and C
onveyan
ce
Not Applic
able
Plumbing System Site
Structu
re0
7,500,000
15,000,000
22,500,000
30,000,000
37,500,000
System Group
Est
imat
ed C
ost
Requirement Summary Report
by Asset Name and System Group
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 1
All costs in USD.
Requirement SummaryReport
by Asset Name and Priority
Page 1 of
Region:
11 - National Capital Region
Service_Center:
Potomac
Asset Name:
GSA-ROB
Priority Percentage of Total Cost Estimated Cost
1 - Immediate / First Year 5% 3,203,113
2 - Within 1 to 2 Years 43% 28,638,330
3 - Within 3 to 5 Years 24% 15,923,583
4 - 5+ Years 15% 10,188,810
5: Does Not Meet Current Codes/Standards 12% 7,898,459
Totals 65,852,295
1 - Immed
iate /
First Y
ear
2 - With
in 1 to 2 Y
ears
3 - With
in 3 to 5 Y
ears
4 - 5+ Y
ears
5: Does
Not Mee
t Curre
nt Codes/
Standard
s0
7,500,000
15,000,000
22,500,000
30,000,000
37,500,000
Priority
Est
imat
ed C
ost
Requirement Summary Report
by Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 1
All costs in USD.
Asset Detail Reportby Asset Name
Page 1 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
STATISTICS
BER FCI Requirement Cost: 65,852,294 BER FCI: 0.36
Current Replacement Value 182,889,241 Address 1 7TH & D STREETS SW
Size 943,493 SF Address 2 -
Year Constructed 1932 City WASHINGTON
Year Renovated 1950 State/Province/Region DC
Commission Date - Zip/Postal Code 20407-0001
Decommission Date - Architect Wm. T. Partridge, C. Architect
Ownership Govt. Owned Historical Category UNDEFINED
Floors 7 Construction Type BOCA - Type 1B Protected
Type Building Use OFFICE BUILDING
PHOTO
Exterior View
Seventh Street Entrance
ASSET DESCRIPTION
GENERAL SERVICES ADMINISTRATION (REGIONAL OFFICE BUILDING)
The General Services Administration (ROB) Building is located at the northwest intersection of 7th and D Streets, SW in Washington, DC 20407. The
property is bounded by C Street and the A&O railroad tracks on the north, 7th Street and the Reporters Building on the east, D Street and the Robert C.
Weaver Federal Building on the south, and 9th Street on the west.
The property is zoned for federal use. The office building use is permitted by right without special exception. According to Marshall and Swifts
classification it is an Average Class Office Governmental Building. The original building was built in 1934 and occupied only the western half of the
property. In 1936 a mirror image of the building was constructed on the eastern half of the property.
The gross floor area for the seven story building and basement is 942,355 sq. ft. The basement level includes 30,590 sq. ft of parking, 36,000 S.F. for
office related functions, with the rest taken up by mechanical, electrical, equipment rooms and storage. Each of these seven tenant floors has a gross
square footage of approximately 115,000 S.F. The GSA presently leases space to the Department of Homeland Security. A child care center utilizes
approximately 7,438 S.F. of space.
Asset Detail Report
by Asset Name
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 13
All costs in USD.
Page 2 of
PLANNING
Topographic maps show that the combined site slopes from the higher point at D Street and 9th Street side on the southwest, to a lower level at the C
Street and 7th Street side on the northeast.
SITE PLAN
On 7th Street there is controlled vehicular access to the basement garage parking. Access to C and 9th Street surface parking, loading dock is limited by a
private guard.
SITE ACCESS
Vehicular site access is limited to 7th and D Streets, which are two -way public streets. Access to C Street is controlled by a security guard and 9th Street
is accessible only from C Street. Bus service is available on both 7th and D Streets. Pedestrian access to the building is from two entrances on D Street or
7th Street. Both entrances are accessible with a ramp for physically handicapped persons.
Off-street parking on D Street is limited to those holding government permits. There is space for eighty-two (82) underground, indoor numbered spaces
for cars of which there are no designated handicap accessible spaces. There is a place for drop off of handicapped people by the parking area entrance. The
on-site surface parking has 83 spaces located at the North and West sides of the building. Limited public parking is mitigated by the proximity of the
L'Enfant Metro station on D Street, which is across the street from the property site.
BUILDING PLAN
The GSA building rises seven stories above grade, with one basement level, below grade. The building dimensions are approximately 212 linear feet x
486 linear feet. It is a simple massed building, basically rectangular in plan with an extension on the north side that follows the path of the A&O railroad
tracks.
The building was constructed in two halves. The Western half of the building was constructed in 1934, while the Eastern half and (mirror image of the
building) was added in 1936, thereby doubling the size and bringing the existing building footprint boundary to 9th to 7th, C and D Streets. The building
expansion joint runs North-South at the center point of the building. The roof contains penthouses that house HVAC and mechanical units providing
service to both sides of the building.
A typical floor plan has a double loaded perimeter corridor around the border of the rectangle and two smaller corridors running North-South, which
connect with the perimeter corridors. Private offices are located along the exterior and general open space work areas are located at the central portion of
the floor plan.
The basement level includes areas for car parking, mechanical equipment, support spaces, and offices. On the first floor is a child care area which is now
closed. Floors one through seven contain office space, a library, a cafeteria, a credit union, and conference rooms. The penthouses contain HVAC
equipment. Each of these levels also have service and storage rooms.
Vertical circulation within the building is served by 8 stairways, 3 freight and 10 passenger elevators. A small stairway connects to an elevated auditorium
on the first level. The eight stairways are regularly spaced off the exterior corridors. All eight serve the ground through seventh levels.
There are thirteen elevators. Three freight elevators (F7, F8, F12) serve all floors. Ten passenger elevators (P3-5, 9-10, 13-17) serve all floors.
Men's and women's restrooms are grouped along the corridors at the exterior corners and at the center points of the building. Typically, there are six sets
of restrooms per floor. At least one Men's and Women's restroom is UFAS (Uniform Federal Accessibility Standards) compliant per floor. The remainder
of restrooms are generally not UFAS compliant.
CONSTRUCTION
BOCA 603.0 construction classification is Type 1 Protected. Seismic design considerations are not a factor in this geographic region. The construction
elements below are classified on the basis of the Construction Specification Industries/ Construction Standard Code Uniformat. The CSI/CSC Uniformat
is a classification for construction information based on elements and systems. It is intended to classify data associated with performance costs of
completed projects for comparable analyses. The Uniformat organizes and defines basic building elements and systems under eight broad categories-
Asset Detail Report
by Asset Name
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 13
All costs in USD.
Page 3 of
A. Substructure
B. Superstructure
C. Interiors
D. Services
E. Equipment
F. Other Building Construction
G. Building Sitework
H. General
CONSTRUCTION DESCRIPTION
A - SUBSTRUCTURE
A1 - FOUNDATIONS are continuous perimeter wall reinforced footings and isolated spread footings at the columns.
A12 - SPECIAL FOUNDATIONS.
A13 - SLAB ON GRADE is poured concrete slab.
A2 - BASEMENT walls enclosing the garage and various mechanical spaces, are concrete and the walls are painted concrete blocks. The garage basement
floor is concrete. No interior or exterior insulation or exterior waterproofing was observed. Piping in the area runs overhead adjacent to a metal air duct.
B10 - SUPERSTRUCTURE
B11 - FLOOR construction is a two-way concrete floor slab with dropped panels, which are supported by reinforced concrete columns at all floor levels.
Floor levels three through six are floor slabs. Slabs at the 6th and 7th floor levels of the East addition are supported on all four sides by a system of
reinforced concrete beams that span between the concrete columns.
B12 - ROOF framing is of composite steel construction with one-way concrete slabs supported on structural steel beams and columns. No window
cleaning equipment was observed.
B2 - EXTERIOR CLOSURE
B2010 - EXTERIOR WALLS of the original ground floor exterior is a cast-in-place concrete exterior wall. Floors one through seven are concrete facing
over terracotta; in 1984 the building was reclad with a troweled elastomeric cementitious plaster stucco surface applied on a metal lath. In 1999, at the
time of the replacement of existing windows, the exterior walls were cleaned and repointed. A three foot tall, granite-faced planter borders the building on
the D and 7th Street sides.
The parapet walls are an extension of the facades along the exterior wall below, with matching copings. The parapet is unified in height, design, material,
and color. It has a prefinished aluminum coping. There is a purely decorative concrete seal, which is fluted and is located at the center top edge of the D
Street facade of the building.
B2020 - EXTERIOR WINDOWS were largely replaced in May 2000 with double pane insulating glass fixed windows. Windows in the basement and
tops of stairwells were not replaced. All window sills are precast concrete. They conform to the energy conservation standards of the Facilities Standards
for Public Building Services PBS 100.1 3/66
B2030 - EXTERIOR DOORS: The 7th Street entrance and the West D Street entrance doors are aluminum with full glass. The central D Street entrance
are polished plate glass. They have bronze kick plates. A decorative iron grille covers the glass transom.
The entrance door to the underground garage is a rolling overhead door. The loading dock has four rolling steel overhead doors. The 7th Street entrance is
four pairs of polished plate glass with a full story glass transom, also of polished plate glass. These doors have bronze kick plates on both sides of the
doors. The three exterior doors on the (north) C Street side are hollow metal doors. The exterior door on the (west) 9th Street is a pair of hollow metal
doors with wire glass lites. It has a steel sash and wire glass transom above the pair of doors. The transoms are covered by aluminum decorative grille.
Asset Detail Report
by Asset Name
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 13
All costs in USD.
Page 4 of
B3 - ROOFING
B30 - ROOF COVERING in the East and West roofs are of two different constructions, although both roof sections were jointly redone in a 1999
renovation. The East roof has a four ply built-up membrane system, with pea gravel top dressing set in a bituminous flood coat over various surfaces
which include lightweight concrete, gypsum, steel, and wood decks. The West roof is an Inverted Roof Membrane (IRMA) system, having rigid board
insulation over a concrete deck with pebble ballast and sealant. Covering the penthouse skylight openings, the roofing is a single-ply elastomeric system.
Steel ladders and steps, or stairs with platforms provide access to the two roof systems at different levels.
There are several elevator penthouse rooms, equipment rooms, fan rooms, air handling rooms and multiple compressors and condensers, which serve the
building. Numerous roof drains border the perimeter. Precast concrete 2 ft x 2 ft tiles rim the perimeter and serve as walkway access route pavers to the
mechanical equipment. These pavers are set directly over filter fabric and insulation, which is over a polyethylene sheet and reinforcing and asphalt, over
the structural concrete slab. There is a decorative CMU screen wall, which visually separates the mechanical areas from the perimeter of the building.
Attached to this decorative screen are several antennae, satellite dishes, vent pipes, and lighting units. The D Street central visitors entrance portico has a
small roof with three skylights used for weather protection and to call attention to the main visitors entrance design.
C - INTERIOR CONSTRUCTION
C1010 - INTERIOR PARTITIONS of plaster from the original building construction are found on the basement level. Typically more modern renovated
spaces on the upper floors are gypsum board on metal studs which are painted. Shaft and staircase walls are concrete masonry units which are painted.
Interior office partitions are gypsum board on both sides of metal studs and demountable fabric partitions.
C1020 - INTERIOR DOORS are hollow metal doors hung on metal frames with doorknob sets. Typical hollow metal doors have louvers. Some interior
(North and South) corridor doors are flush hollow metal doors. Some fire doors at staircases have glass lites. Most doors are typical 32 inch width except
for few exterior office area doors, which are 36" wide, also with doorknob sets; some hardware is lever handles. Some toilet room doors and some office
areas have electronic openers. Wood doors are used only in newly renovated interior executive offices.
There are four magnetic hold-open devices at the main corridor D Street entrance lobby at the point of the break between the original building and the
newer building. Stairs 3, 4, and 5 exit through the existing corridors, which provide a protected means of egress through the electro-magnetic devices on
the corridor doors.
C1030 - INTERIOR SPECIALTIES. Metal toilet compartments; Room signage; Lockers (in fitness center); Some toilet accessories include grab bars and
mirrors.
C2 - STAIRWAYS
C20 - ENCLOSED STAIRWAYS are painted terra cotta walls. Eight staircases are located at the corners of the building and also along the two East-West
corridors, at the center of the building perimeter. Staircases 2, 3, 4, 5 have nosing that are abrasive non-slip strip. Staircases 1, 6, 7, 8 have steel nosing.
All stairs have painted ball type wall-mounted steel pipe handrails. Stairs No. 1, 2, 7 exit from the basement while the remaining stairs exit at the first
floor. Stairs 3, 4, and 5 exit through the existing corridors.
C30 - INTERIOR FINISHES
C3010 - INTERIOR WALL FINISHES - Offices, corridors, staff rooms, credit union are painted gypsum or plaster walls. Corridors between the entrance
lobbies and the elevator lobbies are marble clad with a Dolomite marble wainscot. Painted gypsum walls are above. Cafeteria and daycare center are paint
and vinyl wall covering. Fitness center, conference rooms, bid reading room and library are wall fabric covering. Computer centers are painted drywall or
exposed brick. Auditorium are acoustical wall panel treatment and vinyl wall covering over a wood wainscot. Elevator lobbies and the three entrance
lobbies are floor to ceiling Dolomite marble panels with faux painted octagonal columns. At the Seventh Street entrance lobby there are eight painted
murals by WPA artist Harold Weston in the early 1930s. These have been historically restored in 1985. Elevators are vinyl wall panels. Restrooms and
(rear work area) kitchen are ceramic tiles.
Cafeteria (front seating area) are vinyl wall coverings and painted gypsum board.
C3020 - INTERIOR FLOOR FINISHES - Executive offices and interior open office areas are carpet tiles. Restrooms are ceramic mosaic tiles. Corridor
areas are vinyl tile, and rubber. Entrances and elevator lobbies on the first floor are terrazzo marble aggregate.
Cafeteria is carpet and multi-colored ceramic tile. Fitness center is carpet, resilient flooring, wood strip. Credit union is carpet. Conference rooms, bid
reading room and library are carpet tiles and carpet broadloom. Computer secured areas are raised access resilient floor tiles at the computer stacks and
Asset Detail Report
by Asset Name
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 13
All costs in USD.
Page 5 of
computer work areas and carpeting in the computer executive office areas. Raised flooring is in the communications and computer systems rooms.
Daycare center is resilient flooring and carpet. Auditorium is carpet tile, with wood tile at the stage area. The stairs have bronze nosing. The
projection/screening room has vinyl floor tile. Operations and maintenance offices and (basement) security offices are resilient flooring.
C3030 - INTERIOR CEILING FINISHES - The 7th Street entrance is the most elaborate and has been preserved. The ceiling rises two stories above the
entrance terrazzo floor and has rectangular coffered spaces, which now have light fixtures. The border edging areas are decorated in the original 1930s art
deco design of stylized sun and mountain designs of the original construction. Typically are 2-ft x 2-ft or 2-ft X 4 ft suspended acoustical panels with
exposed grid. Security protection area is illuminated. 2-ft x 4-ft translucent plastic diffusers in exposed grid. Auditorium is acoustical ceiling tiles.
Cafeteria is 2-ft x 2-ft acoustical panels suspended in an exposed grid.
D SERVICES
D1 - CONVEYING SYSTEMS
D11 - ELEVATORS. In the perimeter corridor there are 10 passenger elevators: 5 (No. 13, 14, 15, 16, 17) have a 45 Hp rating with a 3,500-lb capacity
and 5 (Nos. 3, 4, 5, 9, 10) have a 47 Hp rating with 4,500-lb load capacity. There are 3 passenger/freight elevators: 1 (No. 7) has a 5,000-lb capacity, 1
(No. 8) has a 8,000 capacity and 1 (No. 12) has a 10,000-lb capacity. These all serve basement level to the 7th floor. Elevators 7 & 8 are newly installed
systems. The ten passenger elevator cabs have plastic laminate walls, carpet flooring and fluorescent lights. Freight elevator 12 has plastic laminate walls,
wood floors, and illuminated incandescent lighting. Freight elevators 7 & 8 have plastic laminate walls, diamond plate steel floors and illuminated
fluorescent lighting. All passenger elevators have an accessible hall cab and cab controls centered at 42 in. Each cab has a 5-ft maneuvering radius. The
elevators were renovated in the mid 1990's for controls. Elevators were manufactured, installed, and currently serviced each month by the Trinity Elevator
Company. There are no escalators in the building.
D PLUMBING
Plumbing fixtures consist of porcelain lavatories, water closets and urinals.
D DOMESTIC WATER
Domestic water is supplied by Washington Suburban Sanitary Commission (WSSC) from two galvanized mains in D and 7th Streets. The water meter is
in the first floor garage where there are two booster pumps.
Domestic hot water is supplied by two steam hot water converters. One is 420 gallons. The back up tank is 1230 gallons. There are 50-gallon electric hot
water heaters located in men's rooms and janitor closets on the 2nd, 4th and 6th floors, and in the jogger's room on P-1. A 119-gallon electric hot water
heater located in the kitchen and another 30-gallon electric hot water heater located in the janitor's closet of the kitchen are also provided.
D SANITARY WASTE SYSTEM
Waste and vent piping systems cast iron and galvanized steel pipes drain to the main sewer at 7th and D Streets.
D RAIN WATER DRAINAGE
The rainwater drainage system has cast iron and galvanized steel pipes from the roof drains that discharge into the storm water sewer in 7th and D Streets.
D SPECIAL PLUMBING SYSTEMS
Compressed air is required for water holding tanks to provide necessary pressure for the sprinkler system.
Natural gas is supplied by Washington Gas from the galvanized main in D Street serving the cafeteria. The gas meter is in the first floor garage.
D HVAC
Heat and Cooling Distribution Systems
Asset Detail Report
by Asset Name
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 13
All costs in USD.
Page 6 of
Steam is provided from a central steam plant located off of the building site. High pressure steam enters the building in the basement north mechanical
room and is reduced to medium pressure steam via a three stage pressure reducing station (250psig-60psig-40psig). Medium pressure steam is distributed
to the various mechanical spaces of the building and then further reduced to low pressure (5psi) via a single pressure reducing valve with by-pass. Low
pressure steam at 5psig is supplied to the following equipment: Domestic hot water generator in the steam room; Preheat and reheat coils in air handling
units located in various areas throughout the building.
Six chilled water and steam air handling units in the penthouse provides conditioned air and heat via ductwork tied into the perimeter unit risers. They are
the main air handling units for the building serving floors 5 through 7. Units A through F serve East floors 5 through 7. Unit G serves west floor 7.
The interior of the 7th floor is provided with conditioned air by 4 air handling units with chilled water and steam heating, while the perimeter is supplid by
6 chilled water and steam air handling units. These air handling units are located in mechanical rooms 7916, 7235 and 7063.
The 6th floor is cooled by 6 chilled water air handling units serving the interior space and heated by 9 steam air handling units serving the perimeter. They
are located in mechanical rooms 6252, 6082, 6920, 6680, 6651, 6517.
The 5th floor is provided conditioned air via 4 chilled water air handling units serving the interior space and heated by nine air handling units serving the
perimeter. These units are located in mechanical rooms 5061, 5928, 5021, .
The 4th floor interior space is cooled by 4 chilled water air handling units and the perimeter is heated by 10 steam air handling units. These units are
located in mechanical rooms 4063, 4924, 4005, 4710, 4510, 4638 and 4928.
The 3rd floor is cooled by 3 chilled water air handling units serving the interior space and the perimeter is heated by 7 steam and chilled water air handling
units located in mechanical rooms 3061, 3930, 3710, 3005, 3638, 3510.
The 2nd floor interior space is cooled by 2 chilled water air handling units and the perimeter is heated by 7 steam air handling units located in mechanical
rooms 2700, 2043, 2617, 2508, 2638, 2005 and 2668.
The first floor interior space is cooled by 7 chilled water air handling units and the perimeter is provided heat via 7 steam air handling units. These units
are located in 1704, 1679, 1005, 1509 and 1638.
The basement is cooled by two split systems serving the interior space and the perimeter is heated by 4 steam air handling units one of which is out of
service. There is a dual temperature heat exchanger located in the main chiller room in the basement.
Steam condensate is collected in six condensate pump systems. One float type system and one vacuum type system are located at the end of the main
hallway on the basement level in the southeast corner of the building. These condensate pumps deliver the condensate on the south side of the building to
the main condensate pumps located in the steam room. The vacuum type condensate pump in the steam room returns condensate from the north side of the
building to the main condensate pumps. The condensate from the north side of the building is combined with the condensate from the south side of the
building and pumped back to the central plant.
Three centrifugal chillers (800, 500 and 300 tons) in the basement provide chilled water serving air handling units and terminal devices. Nine cooling
towers (6 BAC, 250 Tons each and 3 Evapco, 500 Tons each) located on the roof serve the chillers. Six chilled water pumps and three secondary pumps
are located adjacent to the chillers. These units are located in G-228 and G-217.
D Ventilation
Special exhaust systems such as ventilation supply air is provided via air handling units and terminal devices located throughout the building. Return air is
through grilles located in hallways next to the air handlers. The perimeter diffusers are secured to drywall plenums above the ceiling. The restrooms are
exhausted by fans in the pipe shaft between men and women rooms.
The basement garage is ventilated and provides make-up air with an exhaust fan.
The kitchen exhaust system was installed in the late 1950s. Outside air is to be drawn through a roof mounted gooseneck and down a vertical riser to the
kitchen. The dish washing area and other miscellaneous areas are exhausted by exhaust fans located in a roof mounted penthouse. The rest of the building
is ventilated by 5 exhaust fans located on the roof.
Asset Detail Report
by Asset Name
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 13
All costs in USD.
Page 7 of
Package Terminal Air Conditioning for the rooftop elevator machine shop is provided conditioned air by split systems. There are nine Larkin glycol dry
coolers on the roof serving various areas of the building. Six provide conditioned air to room 6625. Three serve room 2043 (GSA computer room).
D Controls
Building control systems are pneumatically operated except the 3rd and 4th floor where electronic controls have been installed.
D FIRE PROTECTION SYSTEMS
Sixty percent of the building is protected by a wet sprinkler system served by a non-backflow protected 8" pipe serving a 500 GPM fire pump. Standpipes
are installed in all eight stairwells. The line pressure is maintained by three-9000 gallons fire tanks located on the roof. There are 2-1/2 inch fire hose
valves at each floor level on each standpipe and within several corridors there are 1-1/2 inch fire hose valves. The standpipe system supplies sprinklers
within the stairwells, sprinklers within the computer room, and sprinklers on each floor. There are exterior Siamese connections at 7th and D Streets.
Portable fire extinguishers (class A,B,C) are distributed throughout the building.
D5 - ELECTRICAL SYSTEMS
D51 - SERVICE AND DISTRIBUTION is provided by Potomac Electric Power Company (PEPCO). Service to the GSA Regional Office Building is
with 3 sets of feeders that provide 13,800 volts connected to the line side of the main switch gear located in the main switch gear room on the basement
level of building. The load side of the main switch gear continues the same voltage to a metal enclosed switch gear or substation located in the
switchboard room on the same level. Voltage is then connected in six transformer vaults throughout the basement level.
The north transformer vault is equipped with (2) 500kVA transformers that reduces 13.8kV to 208Y/120 V and then serves a 208 V substation. Also, (1)
1,000kVA transformer is utilized to reduce voltage to 480Y/277 V to serve a 480 V substation by way of exposed bare copper bus bars.
The northeast transformer vault is equipped with (2) 1,500KkVA transformers. These transformers reduce voltage from 13.8kVA to 2.4Y-kVA. This
voltage is connected to a 2,400 V substation that serves as a disconnect for a circulation water pump, a condenser water pump, and a motor to A/C &
refrigeration equipment. Also from this switchboard, a breaker controls power to a 750kVA dry-type transformer, which converts voltage to 480 V for a
chiller unit.
The northwest transformer vault is equipped with (3) 500kVA transformers, which reduces 13.2kV on the primary side to 208Y-120 secondary voltage.
The substation being served by these transformers, consists of (2) 2,000 A main fused-bolted pressure switches that are separately fed by two 2,000 A
busways.
The south transformer vault is equipped with (3) 750kVA mineral oil-filled transformers, 13.8kV to 208Y/120 V. These transformers serve two separate
switch gear, one with a 3,000 A main air circuit breaker fed with bare copper bus bars; the other has a 3,000 A main protector and is fed with a 2,500 A
enclosed busway.
The southeast transformer vault is equipped with (3) 500kVA, 13.8kV/208Y-120 V transformers. These transformers serve one 8,000 A main switchgear,
fed with (3) 2,500-A enclosed busway. Subsequently, three other switchgear are served separately by (3) 2,000 A air circuit breakers from the main
switchgear. Two of the switchgear are individually fed by a 2,000 A enclosed bus way; the third switchgear is fed by a 2,500-ampere enclosed bus way.
The west transformer vault is equipped with (2) 1,000kva, 13.8kv/480Y-277 volt transformers. These transformers serve a switcher that is fed by multiple
feeders of 500MCM copper conductors. The 1600 A/277-480 V switchboard features (1) 1,600 A tie breaker and (3) 1,600 A frame power circuit breakers
that feed normal power to (3) automatic transfer switches (ATS). One transfer switch is fed through a 650 A enclosed circuit breaker that serves an
emergency distribution panel by way of a 500kVA 480-240/120 V transformer. A second transfer switch is fed through a 900 A enclosed circuit breaker
that feeds the UPS for computer power in the building. The third ATS is fed through an 800 A enclosed circuit breaker that serves a distribution panel
serving emergency air conditioning units.
D52 - LIGHTING AND BRANCH WIRING by general power are provided by a number of 208Y/120 V panels from electrical closets and panel clusters
throughout the building.
ELECTRICAL BRANCH WIRING typically, power for the receptacles, system furniture and lighting originate from the same panelboards. Branch
feeders for power and lighting are provided by RHW insulated wiring or #12 armored-clad cable also known as BX.
Asset Detail Report
by Asset Name
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 13
All costs in USD.
Page 8 of
INTERIOR LIGHTING fixtures typically are recessed fluorescent, 2-ft x 2-ft and 2-ft x 4-ft with acrylic reflectors, two T8 U-tubes and four T8 tubes with
electronic ballast respectively. Light sensors are provided for general lighting in common areas. In some utility spaces such as the penthouse, mechanical
rooms, electrical closets and stairways, there are 1-ft x 4-ft surface mounted fluorescent fixtures with either T8 or T12 tubes and electronic ballasts.
Similar type fixtures are use in the parking garage.
Emergency lighting is provided by self-contained emergency battery pack lighting units. Exit signs are either single- or dual-sided with 6 V or 12 V
incandescent tubes or LED lamps.
D53 - COMMUNICATION AND SECURITY SYSTEMS
ALARM AND DETECTION SYSTEMS
Notifier manufactures the fire alarm system. The system is equipped with an AM2020 addressable control panel that has the capacity for up to 1,980
individually identifiable and controllable detection/control points. This type of system helps fire personnel quickly located a fire during its early stages.
The system includes audible tone, voice messaging, and strobe lights. Also, smoke and heat detectors, photoelectric and ionization duct detectors and
manual pull stations can activate these alarms located throughout the building. The control panel is located near the 7th Street entrance, which is
monitored by the security guards. When a trouble or an alarm mode activates the system, security will contact the Federal Protective Service (FPS) who
will then notify the fire department in case of an emergency. The system is designed for a general alarm that notify the entire building instead of a
particular zone when an evacuation is required. The system meets the requirements of NFPA Local Alarm fire systems.
VOICE AND DATA SYSTEMS
Special spaces, such as the various computer rooms are equipped with a card reader device for space access. Also, a card reader is located at the entrance
of the garage parking to the basement level of the building.
Washington Interagency Telecommunications Service (WITS) provides the telecommunication service the building. The primary feeds are five 600 pair
cables. These feeders originate from Verizon’s Central Office Switch at 30 E Street, Southwest Washington, D. C where the building receives it dial tone.
These feeders enter the main telephone closet on the first floor and terminate to a vertical soldered frame on the line side. Each individual pair cable runs
vertically to a stacked riser from the frame to a telephone closet for horizontal distribution to individual offices and workstations.
D54 - SPECIAL ELECTRICAL SYSTEMS
Two diesel-packaged engine generator systems provide emergency power for equipment and special areas of the building. A primary 710-kw generator
provides power to the 2nd floor computer room and associated equipment. The primary generator is equipped with three 1,000 A automatic transfer switch
and a 500-gallon oil tank. The secondary 60-kW generator is abandoned with no loads connected to it. There are two 600 A automatic transfer switches
connected to the secondary generator and a 25-gallon day tank that are no longer used.
Uninterruptible Power Supply (UPS) is provided for the 2nd floor computer room. The UPS is a 377 ampere, 208-volt system that provides 2 hour
back-up time to any equipment connected to the buildings general power in the main computer room.
D55 - ELECTRICAL CONTROLS AND INSTRUMENTATION
An energy management system is available for HVAC equipment. The system provides equipment stop-start and temperature control.
BER Requirements
Requirement Name Prime System Category Priority
Action
Date Cost
Branch Wiring Devices:
Aged Circuits and Devices
D5021-Branch Wiring
Devices Beyond Useful Life 2 - Within 1 to 2 Years 12/10/2009 1,861,422
Ceiling Finishes:
Polychrome Cornice
Painted Over C3030-Ceiling Finishes Appearance 4 - 5+ Years 04/09/2018 100,975
Asset Detail Report
by Asset Name
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 13
All costs in USD.
Page 9 of
Requirement Name Prime System Category Priority
Action
Date Cost
Ceiling Finishes: ACT
Aged/Stained C3030-Ceiling Finishes Integrity 3 - Within 3 to 5 Years 12/10/2010 4,017,277
Ceiling Finishes: Painted
Concrete Aged/Peeling C3030-Ceiling Finishes Beyond Useful Life 2 - Within 1 to 2 Years 12/10/2009 269,749
Distribution Systems:
Aged and Inadequate
Ductwork
D3040-Distribution
Systems Capacity/Design 4 - 5+ Years 12/10/2017 8,143,476
Distribution Systems: Fire
Dampers Inspection Not
Current
D3040-Distribution
Systems Life Safety
5: Does Not Meet
Current
Codes/Standards 12/10/2017 30,786
Distribution Systems:
Perimeter Ductwork Lacks
Outside Air Intake
D3041-Air Distribution
Systems Capacity/Design
5: Does Not Meet
Current
Codes/Standards 12/10/2017 3,566,944
Domestic Water
Distribution: Aged and
Worn Piping
D2020-Domestic Water
Distribution Beyond Useful Life 3 - Within 3 to 5 Years 12/10/2010 1,594,400
Electrical Service and
Distribution: Vault
Transformer Testing Is
Needed
D5010-Electrical
Service and
Distribution Maintenance 2 - Within 1 to 2 Years 12/10/2009 123,710
Elevators and Lifts:
Abandoned Elevators -
Recapture Vacant
Space 4 - 5+ Years 12/10/2017 51,494
Elevators and Lifts:
Freight Elevator Aged and
Obsolete
D1010-Elevators and
Lifts Obsolescence 2 - Within 1 to 2 Years 12/10/2009 393,981
Elevators and Lifts:
Passenger Elevators Aged
and Obsolete
D1010-Elevators and
Lifts Obsolescence 2 - Within 1 to 2 Years 12/10/2009 4,806,299
Elevators: Missing
Original Paneled Elevator
Doors
D1010-Elevators and
Lifts Appearance 4 - 5+ Years 04/09/2018 128,410
Emergency Light and
Power Systems:
Abandoned Generator -
Recapture Vacant
Space 4 - 5+ Years 12/10/2017 9,532
Emergency Light and
Power Systems: Aged and
Insufficient Generator
D5092-Emergency
Light and Power
Systems Life Safety 2 - Within 1 to 2 Years 12/10/2009 2,045,468
Emergency Light and
Power Systems:
Emergency Lighting
Fixtures Aged
D5092-Emergency
Light and Power
Systems Beyond Useful Life 3 - Within 3 to 5 Years 12/10/2010 518,397
Emergency Light and
Power Systems:
Emergency Lighting
Lacking
D5092-Emergency
Light and Power
Systems Life Safety 2 - Within 1 to 2 Years 12/10/2009 194,755
Asset Detail Report
by Asset Name
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 13
All costs in USD.
Page 10 of
Requirement Name Prime System Category Priority
Action
Date Cost
Emergency Light and
Power Systems: Exit
Signage Aged and
Inefficient
D5092-Emergency
Light and Power
Systems Beyond Useful Life 3 - Within 3 to 5 Years 12/10/2010 135,723
Emergency Light and
Power Systems: Exit
Signage Missing
D5092-Emergency
Light and Power
Systems Life Safety 2 - Within 1 to 2 Years 12/10/2009 69,704
Equipment and
Furnishings: Loading Dock
Facing Rusted
E-Equipment and
Furnishings Reliability 2 - Within 1 to 2 Years 12/10/2009 14,417
Exterior Doors: Flush
Metal Doors Rusted and
Worn B2030-Exterior Doors Beyond Useful Life 2 - Within 1 to 2 Years 12/10/2009 25,261
Exterior Stairs: Rooftop
Stairs Not Compliant
B1015-Exterior Stairs
and Fire Escapes Life Safety
1 - Immediate / First
Year 12/10/2008 8,502
Exterior Stairs: Slab
Granite Damaged
B1015-Exterior Stairs
and Fire Escapes Life Safety 2 - Within 1 to 2 Years 12/10/2009 12,490
Exterior Walls: Aged and
Cracked Stucco B2010-Exterior Walls Integrity 2 - Within 1 to 2 Years 12/10/2009 1,875,244
Exterior Walls: Rooftop
Screen Cracked/Weathered B2010-Exterior Walls Life Safety 2 - Within 1 to 2 Years 12/10/2009 144,428
Exterior Windows:
Glazing Seals Failed
B2020-Exterior
Windows Reliability 2 - Within 1 to 2 Years 12/10/2009 1,416
Exterior Windows: Steel
Windows Aged and
Deteriorated
B2020-Exterior
Windows Beyond Useful Life 3 - Within 3 to 5 Years 12/10/2010 81,766
Fire Alarm System: Fire
Alarm Control Panel and
Hardware Aging
D5037-Fire Alarm
Systems Capacity/Design 2 - Within 1 to 2 Years 12/10/2009 216,514
Fire Protection Systems:
Sprinkler Head Guards
Missing D40-Fire Protection Building Code 2 - Within 1 to 2 Years 12/10/2009 4,335
Fire Protection: Incomplete
Fire Sprinkler System
Coverage D40-Fire Protection Building Code 2 - Within 1 to 2 Years 09/18/2010 1,247,546
Floor Finish: Damaged
Terrazzo Finish C3010-Wall Finishes Appearance 4 - 5+ Years 04/09/2018 25,316
Floor Finishes: Access
Flooring Corroded C3020-Floor Finishes Reliability 2 - Within 1 to 2 Years 12/10/2009 12,650
Floor Finishes: Broadloom
Carpet/Aging C3020-Floor Finishes Appearance 3 - Within 3 to 5 Years 12/10/2010 3,195,535
Floor Finishes: Carpet Tile
Worn/Damaged and
Stained. C3020-Floor Finishes Appearance 2 - Within 1 to 2 Years 12/10/2009 2,762,132
Asset Detail Report
by Asset Name
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 13
All costs in USD.
Page 11 of
Requirement Name Prime System Category Priority
Action
Date Cost
Floor Finishes: Epoxy
Paint Worn C3020-Floor Finishes Mission 2 - Within 1 to 2 Years 12/10/2009 339,892
Floor Finishes: Suspected
Vinyl Asbestos Tile C3020-Floor Finishes Asbestos
1 - Immediate / First
Year 12/10/2008 98,347
Floor Finishes: Terrazzo
Aged and Cracked C3020-Floor Finishes Integrity 3 - Within 3 to 5 Years 12/10/2010 368,783
Floor Finishes: Transition
Strips Missing C3020-Floor Finishes Life Safety
1 - Immediate / First
Year 12/10/2008 101,902
Floor Finishes: Vinyl Tile
Aged/Worn/Damaged C3020-Floor Finishes Reliability 2 - Within 1 to 2 Years 12/10/2009 1,648,180
High Tension Service and
Dist: High Voltage
Switchgear/Cabling
Antiquated
D5011-High Tension
Service and Dist. Beyond Useful Life 2 - Within 1 to 2 Years 12/10/2009 1,551,447
Identifying Devices:
Exterior Signage
Weathered
C1035-Identifying
Devices Integrity 2 - Within 1 to 2 Years 12/10/2009 1,851
Identifying Devices:
Signage Aged/Missing
C1035-Identifying
Devices Accessibility
5: Does Not Meet
Current
Codes/Standards 12/10/2017 175,433
Interior Doors: Aged and
Worn Doors C1020-Interior Doors Integrity 2 - Within 1 to 2 Years 12/10/2009 1,508,866
Interior Doors: Egress
Blocked C1020-Interior Doors Life Safety
1 - Immediate / First
Year 12/10/2008 19,773
Interior Doors: Fire Doors
Non-Compliant C1020-Interior Doors Life Safety
1 - Immediate / First
Year 12/10/2008 109,265
Interior Doors: Hardware
not ADA Compliant C1020-Interior Doors Accessibility
5: Does Not Meet
Current
Codes/Standards 12/10/2017 1,236,335
Lighting Equipment: Aged
Wiring and Dirty Bronze
Fixtures
D5022-Lighting
Equipment Modernization 2 - Within 1 to 2 Years 04/09/2010 4,179
Lighting Equipment:
Missing Art Deco Light
Fixtures
D5022-Lighting
Equipment Modernization 4 - 5+ Years 04/09/2018 82,967
Lighting Equipment: Aged
Lighting Fixtures
D5022-Lighting
Equipment Beyond Useful Life 3 - Within 3 to 5 Years 12/10/2010 40,592
Lighting Equipment: Aged
Occupancy Sensor System
D5022-Lighting
Equipment Appearance 3 - Within 3 to 5 Years 12/10/2010 1,119,280
Local Area Networks:
Cabling Improperly
Supported
D5039-Local Area
Networks Building Code 4 - 5+ Years 12/10/2017 685,884
Asset Detail Report
by Asset Name
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 13
All costs in USD.
Page 12 of
Requirement Name Prime System Category Priority
Action
Date Cost
Local Area Networks:
Dedicated Equipment
Space Lacking
D5039-Local Area
Networks Building Code 4 - 5+ Years 12/10/2017 910,313
Low Tension Service and
Dist: Aged and Obsolete
Panel Boards/Feeders
D5012-Low Tension
Service and Dist. Appearance
1 - Immediate / First
Year 12/10/2008 2,603,440
Low Tension Service and
Dist: Aged and Obsolete
Switchboards
D5012-Low Tension
Service and Dist. Obsolescence 2 - Within 1 to 2 Years 12/10/2009 3,395,977
Low Tension Service and
Dist: Non-Compliant Fire
Pump Supply Conductors
D5012-Low Tension
Service and Dist. Life Safety
1 - Immediate / First
Year 12/10/2008 76,418
Obsolete Equipment:
Abandoned - Mission 4 - 5+ Years 12/10/2017 50,443
Other Electrical Systems:
Lightning Protection
System Missing - Life Safety
1 - Immediate / First
Year 12/10/2008 66,865
Parking Lot:
Striping/Markings Worn G2020-Parking Lots Reliability 2 - Within 1 to 2 Years 12/10/2009 99,221
Partitions: GWB Damaged C1010-Partitions Appearance 2 - Within 1 to 2 Years 12/10/2009 46,629
Partitions: GWB Water
Damage C1010-Partitions Air and Water Quality 2 - Within 1 to 2 Years 12/10/2009 2,681
Pedestrian Paving:
Concrete Crack/Spalled.
G2030-Pedestrian
Paving Reliability 2 - Within 1 to 2 Years 12/10/2009 8,229
Plumbing Fixtures: Aged
and Non-Compliant Water
Coolers
D2010-Plumbing
Fixtures Reliability 3 - Within 3 to 5 Years 12/10/2010 47,342
Plumbing Fixtures: Public
Restrooms Antiquated -
Not ADAAG Compliant
D2010-Plumbing
Fixtures Accessibility 3 - Within 3 to 5 Years 12/10/2010 4,653,780
Plumbing Fixtures: Worn
Utility Sinks
D2010-Plumbing
Fixtures Appearance 2 - Within 1 to 2 Years 12/10/2009 66,507
Rain Water Drainage:
Aged Ground Water Sump
Pumps
D2040-Rain Water
Drainage Beyond Useful Life 2 - Within 1 to 2 Years 12/10/2009 18,790
Roofing: BUR (Built Up
Roofing) Aged/Damaged. B30-Roofing Integrity 2 - Within 1 to 2 Years 12/10/2009 943,852
Roofing: Single Ply
Membrane - Ballasted
Aged/Damaged B30-Roofing Integrity 2 - Within 1 to 2 Years 12/10/2009 677,439
Sanitary Waste: Corroded
Floor Drains D2030-Sanitary Waste Building Code
5: Does Not Meet
Current
Codes/Standards 12/10/2017 150,469
Asset Detail Report
by Asset Name
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 13
All costs in USD.
Page 13 of
Requirement Name Prime System Category Priority
Action
Date Cost
Sanitary Waste: Restroom
Floor Drains Not Installed D2030-Sanitary Waste Building Code
5: Does Not Meet
Current
Codes/Standards 12/10/2017 168,048
Security and Detection
Systems: Break Glass
Detectors Lack Adequate
Coverage
D5038-Security and
Detection Systems Security 3 - Within 3 to 5 Years 12/10/2010 44,863
Stairs: Hand Railing Not
Code Compliant C20-Stairs Building Code
5: Does Not Meet
Current
Codes/Standards 12/10/2017 1,238,329
Stairs: Interior Aged/Worn C20-Stairs Life Safety
1 - Immediate / First
Year 12/10/2008 118,601
Stairwell Smoke Proof
Enclosure/ Pressurization
System - Not Installed - Building Code
5: Does Not Meet
Current
Codes/Standards 12/09/2017 1,332,115
Substructure: Concrete
Parking Lot Aged/Worn A-Substructure Integrity 2 - Within 1 to 2 Years 12/10/2009 72,271
Telephone Systems:
Wiring Old and
Abandoned
D5033-Telephone
Systems Obsolescence 2 - Within 1 to 2 Years 12/10/2009 221,309
Terminal and Package
Units: Aged Window Air
Conditioners
D3050-Terminal and
Package Units Beyond Useful Life 2 - Within 1 to 2 Years 12/10/2009 13,007
Wall Finish: Marble Base
Damaged C3010-Wall Finishes Appearance 3 - Within 3 to 5 Years 04/09/2011 4,134
Wall Finish: Marble Panels
Dirty and Grout Cracking C3010-Wall Finishes Appearance 3 - Within 3 to 5 Years 04/09/2011 44,741
Wall Finishes: Acoustic
Tile Aged/Deteriorated C3010-Wall Finishes Integrity 2 - Within 1 to 2 Years 12/10/2009 5,753
Wall Finishes: Marble
Panels Aged/Deteriorated C3010-Wall Finishes Integrity 3 - Within 3 to 5 Years 12/10/2010 47,486
Wall Finishes: Possibly
Historic Paint Peeling C3010-Wall Finishes Appearance 3 - Within 3 to 5 Years 12/10/2010 9,484
Wall Finishes: Worn and
Stained Painted Walls C3010-Wall Finishes Integrity 2 - Within 1 to 2 Years 12/10/2009 1,859,932
Wall Finishes: Worn Paint
on Concrete Walls C3010-Wall Finishes Beyond Useful Life 2 - Within 1 to 2 Years 12/10/2009 70,797
Total 65,852,295
Asset Detail Report
by Asset Name
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 13
All costs in USD.
Requirement Detail ReportBy Asset Name and Priority
Requirement Detail Report
Table of Contents
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. i
11 - National Capital Region 1
Potomac 1
GSA-ROB 1
1 - Immediate / First Year 1
Exterior Stairs: Rooftop Stairs Not Compliant 1
Floor Finishes: Suspected Vinyl Asbestos Tile 3
Floor Finishes: Transition Strips Missing 5
Interior Doors: Egress Blocked 7
Interior Doors: Fire Doors Non-Compliant 9
Low Tension Service and Dist: Aged and Obsolete Panel Boards/Feeders 11
Low Tension Service and Dist: Non-Compliant Fire Pump SupplyConductors
14
Other Electrical Systems: Lightning Protection System Missing 16
Stairs: Interior Aged/Worn 18
2 - Within 1 to 2 Years 20
Branch Wiring Devices: Aged Circuits and Devices 20
Ceiling Finishes: Painted Concrete Aged/Peeling 23
Electrical Service and Distribution: Vault Transformer Testing Is Needed 25
Elevators and Lifts: Freight Elevator Aged and Obsolete 27
Elevators and Lifts: Passenger Elevators Aged and Obsolete 29
Emergency Light and Power Systems: Aged and Insufficient Generator 32
Emergency Light and Power Systems: Emergency Lighting Lacking 35
Emergency Light and Power Systems: Exit Signage Missing 37
Equipment and Furnishings: Loading Dock Facing Rusted 39
Exterior Doors: Flush Metal Doors Rusted and Worn 41
Exterior Stairs: Slab Granite Damaged 43
Exterior Walls: Aged and Cracked Stucco 45
Exterior Walls: Rooftop Screen Cracked/Weathered 48
Exterior Windows: Glazing Seals Failed 50
Fire Alarm System: Fire Alarm Control Panel and Hardware Aging 51
Fire Protection Systems: Sprinkler Head Guards Missing 53
Fire Protection: Incomplete Fire Sprinkler System Coverage 55
Floor Finishes: Access Flooring Corroded 57
Floor Finishes: Carpet Tile Worn/Damaged and Stained. 59
Floor Finishes: Epoxy Paint Worn 61
Floor Finishes: Vinyl Tile Aged/Worn/Damaged 63
High Tension Service and Dist: High Voltage Switchgear/CablingAntiquated
65
Requirement Detail Report
Table of Contents
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. ii
Identifying Devices: Exterior Signage Weathered 68
Interior Doors: Aged and Worn Doors 70
Lighting Equipment: Aged Wiring and Dirty Bronze Fixtures 72
Low Tension Service and Dist: Aged and Obsolete Switchboards 73
Parking Lot: Striping/Markings Worn 77
Partitions: GWB Damaged 79
Partitions: GWB Water Damage 80
Pedestrian Paving: Concrete Crack/Spalled. 82
Plumbing Fixtures: Worn Utility Sinks 84
Rain Water Drainage: Aged Ground Water Sump Pumps 86
Roofing: BUR (Built Up Roofing) Aged/Damaged. 88
Roofing: Single Ply Membrane - Ballasted Aged/Damaged 90
Substructure: Concrete Parking Lot Aged/Worn 92
Telephone Systems: Wiring Old and Abandoned 94
Terminal and Package Units: Aged Window Air Conditioners 96
Wall Finishes: Acoustic Tile Aged/Deteriorated 98
Wall Finishes: Worn Paint on Concrete Walls 100
Wall Finishes: Worn and Stained Painted Walls 102
3 - Within 3 to 5 Years 104
Ceiling Finishes: ACT Aged/Stained 104
Domestic Water Distribution: Aged and Worn Piping 106
Emergency Light and Power Systems: Emergency Lighting Fixtures Aged 109
Emergency Light and Power Systems: Exit Signage Aged and Inefficient 111
Exterior Windows: Steel Windows Aged and Deteriorated 113
Floor Finishes: Broadloom Carpet/Aging 115
Floor Finishes: Terrazzo Aged and Cracked 117
Lighting Equipment: Aged Lighting Fixtures 119
Lighting Equipment: Aged Occupancy Sensor System 121
Plumbing Fixtures: Aged and Non-Compliant Water Coolers 123
Plumbing Fixtures: Public Restrooms Antiquated - Not ADAAG Compliant 125
Security and Detection Systems: Break Glass Detectors Lack AdequateCoverage
129
Wall Finish: Marble Base Damaged 131
Wall Finish: Marble Panels Dirty and Grout Cracking 132
Wall Finishes: Marble Panels Aged/Deteriorated 133
Wall Finishes: Possibly Historic Paint Peeling 135
4 - 5+ Years 136
Ceiling Finishes: Polychrome Cornice Painted Over 136
Requirement Detail Report
Table of Contents
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. iii
Distribution Systems: Aged and Inadequate Ductwork 138
Elevators and Lifts: Abandoned Elevators 140
Elevators: Missing Original Paneled Elevator Doors 142
Emergency Light and Power Systems: Abandoned Generator 143
Floor Finish: Damaged Terrazzo Finish 145
Lighting Equipment: Missing Art Deco Light Fixtures 146
Local Area Networks: Cabling Improperly Supported 147
Local Area Networks: Dedicated Equipment Space Lacking 149
Obsolete Equipment: Abandoned 152
5: Does Not Meet Current Codes/Standards 154
Distribution Systems: Fire Dampers Inspection Not Current 154
Distribution Systems: Perimeter Ductwork Lacks Outside Air Intake 156
Identifying Devices: Signage Aged/Missing 158
Interior Doors: Hardware not ADA Compliant 160
Sanitary Waste: Corroded Floor Drains 162
Sanitary Waste: Restroom Floor Drains Not Installed 163
Stairs: Hand Railing Not Code Compliant 165
Stairwell Smoke Proof Enclosure/ Pressurization System - Not Installed 167
Page 1 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 1 - Immediate / First Year
Requirement Name Exterior Stairs: Rooftop Stairs Not Compliant
Requirement ID REQ-97526
Linked System Exterior Stairs and Fire Escapes Inspection Date 12/10/2007
Prime System Exterior Stairs and Fire Escapes Finish Date -
Category Life Safety Status Open
Inspector Sasse, Rick Actual Cost 0
Action Date 12/10/2008 Estimated Cost 8,502
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The open tread stair to a penthouse door is deteriorated and is a safety hazard. It is not compliant with OSHA 1910.24 because of its small treads,
nonuniform riser heights, and the open tread. Its rungs are bent. The wooden stair providing access to rooftop mechanical equipment is also noncompliant
because it lacks handrails and its riser spacing is uniform.
PHOTOS
Exterior Stairs
Exterior Stairs: Rooftop Stairs Not Compliant
Exterior Stairs
Exterior Stairs: Rooftop Stairs Not Compliant
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 2 of
ACTION DESCRIPTION
Replace the steel stair to the penthouse door at the masonry screen and the wooden stair to the rooftop mechanical equipment.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
U053103009000 Metal decking, steel, assemble and weld decking,
minimum labor/equipment charge
1.00 Job 702.83 703
U055177000020 Stair, shop fabricated, steel, 3'-6" W, incl pipe railing,
stringers, grating treads w/ safety nosing, per riser
10.00 Riser 492.77 4,928
Subtotal: 5,631
Adjustment Factor: 1.5100
Total: 8,502
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 3 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 1 - Immediate / First Year
Requirement Name Floor Finishes: Suspected Vinyl Asbestos Tile
Requirement ID REQ-20886
Linked System Floor Finishes Inspection Date 12/10/2007
Prime System Floor Finishes Finish Date -
Category Asbestos Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2008 Estimated Cost 98,347
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Flooring by many elevators and other areas throughout the building are 9" X 9" tile suspected of containing asbestos. These tiles need to be tested and
remediated if found to contain asbestos.
PHOTOS
Floor Finishes
Floor Finishes: Asbestos Floor Tile Deteriorated - Room 6648
ACTION DESCRIPTION
Test all 9" x 9" tile throughout building for asbestos. If positive, tiles should be replaced with the 12" x 12" VCT. Work to include testing, remediation,
and replacement with new tile.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AC30204101640 Vinyl tile, maximum 4,500.00 S.F. 9.11 40,995
LASBEJ Asbestos/Insulation Workers/Pipe Coverer 80.00 hour 64.12 5,130
LCLABJ Common Building Laborers 40.00 hour 45.47 1,819
LCLAMJ Common Maintenance Laborer 40.00 hour 31.60 1,264
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 4 of
Code Description Quantity Unit Unit Cost Total Cost
LCRPTJ Carpet & Linoleum Layers 80.00 hour 52.34 4,187
U132811205000 Bulk Asbestos Removal, remove VAT from floor by
hand, incl. disp. tools & 4 suits & resp./day/worker
4,500.00 S.F. 1.92 8,640
U132811551000 Asbestos waste Packaging, Handling & Disposal, double
bag and decontaminate
50.00 Ea. 5.93 297
U132811555020 Asbestos waste Packaging, Handling & Disposal, disposal
charges, excl. haul, max
15.00 C.Y. 186.63 2,799
Subtotal: 65,131
Adjustment Factor: 1.5100
Total: 98,347
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 5 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 1 - Immediate / First Year
Requirement Name Floor Finishes: Transition Strips Missing
Requirement ID REQ-6223
Linked System Floor Finishes Inspection Date 12/10/2007
Prime System Floor Finishes Finish Date -
Category Life Safety Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2008 Estimated Cost 101,902
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Lack of transition strips between different flooring finishes creates trip hazards. Condition occurs
between the carpet and resilient tile and raised flooring and concrete.
PHOTOS
Floor Finishes
Floor Finishes: Raised Flooring - Missing Transition Strips - Room 4926
ACTION DESCRIPTION
Provide thresholds at changes of building interior floor finishes.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LCLABJ Common Building Laborers 40.00 hour 45.47 1,819
LCRPTJ Carpet & Linoleum Layers 40.00 hour 52.34 2,094
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
1.00 Ton 121.33 121
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 6 of
Code Description Quantity Unit Unit Cost Total Cost
U022203500700 Selective demolition, rubbish handling, dumpster, 10
C.Y., 4 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
1.00 Week 366.38 366
U096809200117 Flooring transition strip, floor trim brass 12'/each (@vinyl
to hard surface)
1,224.00 Ea. 51.54 63,085
Subtotal: 67,485
Adjustment Factor: 1.5100
Total: 101,902
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 7 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 1 - Immediate / First Year
Requirement Name Interior Doors: Egress Blocked
Requirement ID REQ-10081
Linked System Interior Doors Inspection Date 12/10/2007
Prime System Interior Doors Finish Date -
Category Life Safety Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2008 Estimated Cost 19,773
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The egress at some of the interior office corridors is blocked by tenant use. Many egress doors are blocked by interior demountable partitions, which
restrict emergency egress. Because entire corridor lengths are blocked, required egress distances are not provided. The egress lanes between many interior
offices do not conform to the width requirements.
PHOTOS
Interior Doors
Interior Doors: Blocked - Room 4636
ACTION DESCRIPTION
Remove furniture and appliances which now block egress doors. Removal of interior partitions that do not conform to width requirements. Removal of
office equipment (Xerox snack bars, Christmas displays, fans, heaters, kitchen equipment) which block accessibility passage.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
U018401001300 Moving Equipment, remove and reset, 100' distance, no
obstructions, assembly or leveling unless noted, copy
machine
150.00 Ea. 29.10 4,365
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 8 of
Code Description Quantity Unit Unit Cost Total Cost
U018401001700 Moving Equipment, remove and reset, 100' distance, no
obstructions, assembly or leveling unless noted, desk with
chair
150.00 Ea. 29.10 4,365
U018401002600 Moving Equipment, remove and reset, 100' distance, no
obstructions, assembly or leveling unless noted, file
cabinet
150.00 Ea. 29.10 4,365
Subtotal: 13,095
Adjustment Factor: 1.5100
Total: 19,773
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 9 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 1 - Immediate / First Year
Requirement Name Interior Doors: Fire Doors Non-Compliant
Requirement ID REQ-9055
Linked System Interior Doors Inspection Date 12/10/2007
Prime System Interior Doors Finish Date -
Category Life Safety Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2008 Estimated Cost 109,265
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Stairwell fire doors on all floors are either not fire rated or UL Labels have been painted over. Fire doors do not comply with 2006 IBC Section 715.4.
PHOTOS
Interior Doors
Interior Doors: Fire Doors Not in Compliance - 1st Floor Stairwell #2
ACTION DESCRIPTION
Replace all fire doors at 8 floors leading to 8 staircases in the building.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AC10201167200 Labeled metal door/metal frame, hollow, 3 hr, 18 ga full
panel, 2'-8" x 7'-0", KD frame, 5-3/4"
64.00 Ea. 1,021.10 65,350
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
4.00 Ton 121.33 485
U022203500840 Selective demolition, rubbish handling, dumpster, 40
C.Y., 13 ton capacity, weekly rental, includes one dump
per week, cost to be added to demolition cost.
2.00 Week 1,577.29 3,155
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 10 of
Code Description Quantity Unit Unit Cost Total Cost
U080601100500 Door demolition, interior door, single, 3' x 7' high, 1-3/8"
thick, remove
64.00 Ea. 18.17 1,163
U080601102201 Door demolition, door frames, wood, remove 960.00 L.F. 2.30 2,208
Subtotal: 72,361
Adjustment Factor: 1.5100
Total: 109,265
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 11 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 1 - Immediate / First Year
Requirement Name Low Tension Service and Dist: Aged and Obsolete
Panel Boards/Feeders
Requirement ID REQ-18726
Linked System Low Tension Service and Dist. Inspection Date 12/10/2007
Prime System Low Tension Service and Dist. Finish Date -
Category Appearance Status Open
Inspector Salomonsson Actual Cost 0
Action Date 12/10/2008 Estimated Cost 2,603,440
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
There are existing sub power and lighting distribution panels located on every floor of the building. There is a combination of newer and older panels. The
old panels are well beyond the end of their life expectancy. All have few or no spares. The feeders that feed these panels are also aged and are well beyond
the end of their life expectancy. Observed feeders have fabric based insulation which is frayed and deteriorated. Panel assemblies have missing protective
covers with bus bars exposed, creating a hazard for any personnel working on these panels. This aged equipment cannot be properly maintained since all
replacement parts are obsolete and unavailable.
Aged panel boards with corresponding feeders should be replaced in the very near future.
PHOTOS
Low Tension Service and Distribution
Low Tension Service and Dist: Aged and Obsolete Panel Boards/Feeders -
Electrical Closet 3672.
ACTION DESCRIPTION
A complete change out is recommended of the aged panels and feeders. New panels shall be equipped with 200 percent neutral bus bar and shall have
built in spare circuit breakers. The installation of new panels should fully conform to the NEC for working clearances. Provide temporary power as needed
to facilitate panel replacements. Ensure that proper disposal of antiquated equipment is provided. Intercept, junction and extend existing branch circuitry
to new panels as needed for a complete installation. Replace any branch circuitry found deteriorated or damaged.
ESTIMATE
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 12 of
Code Description Quantity Unit Unit Cost Total Cost
AD50102300280 Feeder installation 600 V, including RGS conduit and
XHHW wire, 200 A
4,400.00 L.F. 50.88 223,872
AD50102300320 Feeder installation 600 V, including RGS conduit and
XHHW wire, 400 A
800.00 L.F. 101.77 81,416
AD50102300400 Feeder installation 600 V, including RGS conduit and
XHHW wire, 800 A
300.00 L.F. 267.96 80,388
AD50102400200 Switchgear installation, incl switchboard, panels & circuit
breaker, 400 A
16.00 Ea. 8,039.43 128,631
AD50102400280 Switchgear installation, incl switchboard, panels & circuit
breaker, 800 A
6.00 Ea. 24,426.49 146,559
LCARPJ Carpenters 320.00 hour 57.49 18,397
LCLABJ Common Building Laborers 320.00 hour 45.47 14,550
LCLNRJ Cleaner 160.00 hour 44.96 7,194
LELECJ Electricians 720.00 hour 64.91 46,735
LHELPJ Helpers Average (5 trades) 720.00 hour 43.43 31,270
LPLASJ Plasterers 320.00 hour 50.62 16,198
LPORDJ Painters, Ordinary 320.00 hour 48.95 15,664
RD50231240010 Replace armored cable 48.00 M.L.F. 5,267.50 252,840
RD50231260010 Replace branch wiring with junction box 48.00 M.L.F. 1,351.17 64,856
U015100500130 Temporary electrical power equipment (pro-rated per job),
underground feed, 3 uses, 400 amp
48.00 Ea. 2,590.39 124,339
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
24.00 Ton 121.33 2,912
U022203500700 Selective demolition, rubbish handling, dumpster, 10
C.Y., 4 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
6.00 Week 366.38 2,198
U022203500910 Selective demolition, rubbish handling, dumpster,
alternate pricing method, delivery, average for all sizes,
cost to be added to demolition cost.
12.00 Ea. 91.00 1,092
U022203500950 Selective demolition, rubbish handling, dumpster,
alternate pricing method, disposal fee per ton, average for
all sizes, cost to be added to demolition cost.
24.00 Ton 91.00 2,184
U078401000110 Firestopping, metallic piping, non insulated, through
walls, 2" dia
256.00 Ea. 40.45 10,355
U078401000120 Firestopping, metallic piping, non insulated, through
walls, 4" dia
48.00 Ea. 51.82 2,487
U078401000150 Firestopping, metallic piping, non insulated, through
floors, 2" dia
160.00 Ea. 21.76 3,482
U078401000160 Firestopping, metallic piping, non insulated, through
floors, 4" dia
24.00 Ea. 27.50 660
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 13 of
Code Description Quantity Unit Unit Cost Total Cost
U160553000120 Conduit, rigid galvanized steel, 1-1/4" to 2" diameter,
electrical demolition, remove conduit to 15' high, incl
fittings & hangers
4,400.00 L.F. 2.84 12,496
U160553000140 Conduit, rigid galvanized steel, 2-1/2" to 3-1/2" diameter,
electrical demolition, remove conduit to 15' high, incl
fittings & hangers
600.00 L.F. 3.76 2,256
U160553001260 Panelboards, 4 wire, 120/208 V, 125 amp, to 20 circuits,
electrical demolition, remove, incl removal of all breakers,
conduit terminations & wire connections
48.00 Ea. 236.66 11,360
U160553001270 Panelboards, 4 wire, 120/208 V, 200 amp, to 42 circuits,
electrical demolition, remove, incl removal of all breakers,
conduit terminations & wire connections
40.00 Ea. 473.33 18,933
U160553001280 Panelboards, 4 wire, 120/208 V, 400 amp, to 42 circuits,
electrical demolition, remove, incl removal of all breakers,
conduit terminations & wire connections
12.00 Ea. 591.66 7,100
U164407202250 Panelboards, 3 phase 4 wire, main circuit breaker,
120/208 V, 225 amp, 42 circuits, NQOD, incl 20 A 1 pole
plug-in breakers
88.00 Ea. 4,473.96 393,708
Subtotal: 1,724,132
Adjustment Factor: 1.5100
Total: 2,603,440
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 14 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 1 - Immediate / First Year
Requirement Name Low Tension Service and Dist: Non-Compliant
Fire Pump Supply Conductors
Requirement ID REQ-18735
Linked System Low Tension Service and Dist. Inspection Date 12/10/2007
Prime System Low Tension Service and Dist. Finish Date -
Category Life Safety Status Open
Inspector Salomonsson Actual Cost 0
Action Date 12/10/2008 Estimated Cost 76,418
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Fire pump supply conductors, observed routed within the facility (refer to corridor outside B33), serving the fire pump located in room B34, are not fire
rated as required by the 2005 NEC, article 695.6B and the 2007 NFPA 20, section 2-15.1. Since the installation of these feeders occurred in approximately
2004, this is brought forth as a direct code violation, which could impact life safety should a fire occur. The existing feeders should be replaced with fire
insulated mineral insulated conductors in the very near future.
PHOTOS
Low Tension Service and Distribution
Low Tension Service and Dist: Non-Compliant Fire Pump Supply Conductors -
Corridor Adjacent Room B33.
ACTION DESCRIPTION
Replace existing fire pump supply conductors, routed within the building with fire rated mineral insulated conductors for code compliance as well as
improving the life safety system for the facility. Provide temporary power as needed to facilitate the replacement.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
U015100500130 Temporary electrical power equipment (pro-rated per job),
underground feed, 3 uses, 400 amp
2.00 Ea. 2,590.39 5,181
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 15 of
Code Description Quantity Unit Unit Cost Total Cost
U160553000260 Conduit, electric metallic tubing (EMT), 3-1/2" to 4"
diameter, electrical demolition, remove conduit to 15'
high, incl fittings & hangers
300.00 L.F. 3.66 1,098
U160553001700 Pull boxes & cabinets, sheet metal, 36" x 36" x 8",
electrical demolition, remove, incl removal of supports
and terminations
4.00 Ea. 73.77 295
U160553001970 Wire, THW-THWN-THHN, 350 kcmil, electrical
demolition, removed from in place conduit, to 15' high
9.00 C.L.F. 63.11 568
U161205001420 Mineral insulated cable, 1 conductor, 600 volt, 350 kcmil 9.00 C.L.F. 3,887.95 34,992
U161205005420 Mineral insulated cable terminations, 1 conductor, 600
volt, 350 kcmil
18.00 Ea. 234.13 4,214
U161205009500 Mineral insulated cable, minimum labor/equipment charge 9.00 Job 142.00 1,278
U161367000610 Pull boxes, sheet metal, type SC, 30" W x 30" H x 8" D,
NEMA 1
6.00 Ea. 496.99 2,982
Subtotal: 50,608
Adjustment Factor: 1.5100
Total: 76,418
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 16 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 1 - Immediate / First Year
Requirement Name Other Electrical Systems: Lightning Protection
System Missing
Requirement ID REQ-18741
Linked System Not Applicable Inspection Date 12/10/2007
Prime System - Finish Date -
Category Life Safety Status Open
Inspector Salomonsson Actual Cost 0
Action Date 12/10/2008 Estimated Cost 66,865
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The facility is not equipped with a lightning protection system. The probability of damaged, caused by lightning, to the facility and occupants is increased
without an engineered lightning protection system.
NFPA 780, Standard for the Installation of Lightning Protection Systems - Appendix H, Risk Assessment Guide, the assessment of risk for this Building is
classified as moderate to severe.
PHOTOS
Other Electrical Systems
Other Electrical Systems: Lightning Protection System Lacking - Roof.
ACTION DESCRIPTION
Furnish and install a fully engineered lightning protection system in accordance with NFPA 780 standard. Provide cabling, grounding and air terminals as
needed on the roof.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
E015906000120C Lifting and hoisting equipment rental; aerial lift truck, 2
pers, 80'
10.00 Ea./day 594.29 5,943
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 17 of
Code Description Quantity Unit Unit Cost Total Cost
LELECJ Electricians 120.00 hour 64.91 7,789
LHELPJ Helpers Average (5 trades) 120.00 hour 43.43 5,212
RB30131050300 Minor membrane repairs - (2% of roof area) built-up
roofing
8.00 Sq. 409.16 3,273
U131010550500 Air terminal and base, copper, 1/2" dia x 12", over 75' h 36.00 Ea. 100.53 3,619
U131010552100 Lightning protection cable, copper, 375 lb per thousand
feet, over 75' h
1,600.00 L.F. 7.84 12,544
U131010553100 Lightning Arrester, 650 V AC to ground 4.00 Ea. 157.40 630
U160608009000 Grounding, minimum labor/equipment charge 4.00 Job 142.00 568
U161209009000 Wire, minimum labor/equipment charge 12.00 Job 142.00 1,704
U161322100540 Rigid galvanized steel conduit, 1" diameter, to 15' high,
incl couplings only
300.00 L.F. 10.00 3,000
Subtotal: 44,282
Adjustment Factor: 1.5100
Total: 66,865
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 18 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 1 - Immediate / First Year
Requirement Name Stairs: Interior Aged/Worn
Requirement ID REQ-9061
Linked System Stairs Inspection Date 12/10/2007
Prime System Stairs Finish Date -
Category Life Safety Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2008 Estimated Cost 118,601
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The stair nosings on staircases No. 2, 3, 4, 5 are resilient non-slip rubber and metal strips that are deteriorated or missing, creating a safety egress hazard
as outlined in NFPA 101 Life Safety Code Handbook A5-2.2.3.3 (tripping hazard)
PHOTOS
Stairs 2
Stairs: Interior Aged/Worn Stairwell 3 Second Floor
Stairs 1
Stairs: Interior Aged/Worn Stairway 3, Third Floor.
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 19 of
ACTION DESCRIPTION
Remove rubber treads, risers and nosings. Replace with new resilient non-slip rubber. Add non-slip flooring at stair landings No. 2 and 5 (170 sq. ft) and
at stair landings No. 3 and 4(150 sq. ft) for basement to seventh floors.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
10.00 Ton 121.33 1,213
U022203500800 Selective demolition, rubbish handling, dumpster, 30
C.Y., 10 ton capacity, weekly rental, includes one dump
per week, cost to be added to demolition cost.
1.00 Week 1,213.30 1,213
U096511000400 Stair Treads & Risers, rubber, molded tread, colors, 12"
w, 5/16" thick
2,816.00 L.F. 21.10 59,418
U096511009000 Stair Treads & Risers, minimum labor/equipment charge 112.00 Job 149.10 16,699
Subtotal: 78,543
Adjustment Factor: 1.5100
Total: 118,601
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 20 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Branch Wiring Devices: Aged Circuits and
Devices
Requirement ID REQ-18720
Linked System Branch Wiring Devices Inspection Date 12/10/2007
Prime System Branch Wiring Devices Finish Date -
Category Beyond Useful Life Status Open
Inspector Salomonsson Actual Cost 0
Action Date 12/10/2009 Estimated Cost 1,861,422
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
On all floors of the building it was noted that branch circuits are beyond the end of their life expectancy. Frayed and cracked insulation pose risk of shock
and fire hazard. Broken cover plates, worn/aged switches and receptacles were observed on all levels.
Assessor's Notes:
Aged receptacles observed at this facility appear to be considerably worn. Worn receptacles typically lack adequate retaining tension for plugs, which may
lead to arcing when loads are loosely plugged-in. For this reason, as well as the observed fabric based antiquated insulation, replacement should be
considered in the very near future.
PHOTOS
Branch Wiring Devices
Branch Wiring Devices: Aged Circuits and Devices - Mechanical Room 5638.
ACTION DESCRIPTION
Replace branch circuit wiring. Provide an engineering study/design to determine quantity of new circuits and receptacles based on occupancy and
equipment loading. Receptacles for computers shall be equipped with surge protection. Receptacles within restrooms, mechanical rooms, roofs, and
kitchens shall be equipped with ground fault circuit interrupter (GFCI) protection. Replace any aged branch wiring and switches serving aged mechanical
systems equipment. Employ adequate disposal methods as needed for a complete installation. All work should be performed in full accordance with the
NEC and NFPA.
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 21 of
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AD50102301240 Branch installation 600 V, including EMT conduit and
THW wire, 20 A
1,600.00 L.F. 6.90 11,040
AD50201250640 Receptacle duplex G.F.I. 20 A with box, plate, 3/4" EMT
& wire
80.00 Ea. 277.30 22,184
AD50201550200 Motor feeder systems, single phase, feed up to 115 V 1
HP or 230 V 2 HP
3,000.00 L.F. 9.39 28,170
AD50201550520 Motor feeder systems, three phase, feed to 200 V 10 HP,
230 V 10 HP, 460 V 30 HP, 575 V 30 HP
1,000.00 L.F. 11.61 11,610
AD50201550600 Motor feeder systems, three phase, feed to 200 V 15 HP,
230 V 15 HP, 460 V 40 HP, 575 V 50 HP
500.00 L.F. 14.01 7,005
AD50201550680 Motor feeder systems, three phase, feed to 200 V 20 HP,
230 V 25 HP, 460 V 50 HP, 575 V 60 HP
250.00 L.F. 18.82 4,705
AD50201650200 Safety switch, 30 A fused, 1 phase, 2 HP 115 V or 3 HP,
230 V
300.00 Ea. 353.18 105,954
AD50201650280 Safety switch, 30 A fused, 3 phase, 5 HP, 200 V or 7 1/2
HP, 230 V
100.00 Ea. 436.54 43,654
AD50201650440 Safety switch, 60 A fused, 3 phase, 15 HP 200 V or 15 HP
230 V
50.00 Ea. 664.51 33,226
AD50201650600 Safety switch, 100 A fused, 3 phase, 20 HP 200 V or 25
HP 230 V
25.00 Ea. 968.82 24,221
LCLNRJ Cleaner 80.00 hour 44.96 3,597
RD50231240010 Replace armored cable 75.00 M.L.F. 5,267.50 395,063
RD50231260010 Replace branch wiring with junction box 100.00 M.L.F. 1,351.17 135,117
RD50231500020 Replace receptacle/plug receptacles and plugs 3,000.00 Ea. 61.13 183,390
RD50232100030 Replace contactor contactors and relays 25.00 Ea. 752.70 18,818
RD50232200020 Replace switch wiring devices, switches 1,200.00 Ea. 59.03 70,836
U013107000140 Field engineer, maximum 6.00 Week 2,093.70 12,562
U015108000360 Temporary Power, lighting, incl. service lamps, wiring
and outlets, max
942.00 CSF Flr 37.11 34,958
U018323601100 Electrical Facilities Maintenance, distribution systems and
equipment, megger test MCC (each stack)
28.00 Ea. 129.83 3,635
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
24.00 Ton 121.33 2,912
U022203500700 Selective demolition, rubbish handling, dumpster, 10
C.Y., 4 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
6.00 Week 366.38 2,198
U160553009000 Electrical demolition, minimum labor/equipment charge 400.00 Job 142.00 56,800
U162106009000 Meter centers and meter sockets, minimum
labor/equipment charge
28.00 Job 189.33 5,301
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 22 of
Code Description Quantity Unit Unit Cost Total Cost
U162908600150 Voltage monitor systems, AC voltage remote, 3 channel,
120, 230, or 480 V
1.00 Ea. 7,137.19 7,137
U162908600160 Voltage monitor systems, AC voltage remote, with
internal modem
1.00 Ea. 7,535.28 7,535
U162908600170 Voltage monitor systems, AC voltage remote,
combination temperature & humidity probe
1.00 Ea. 1,103.28 1,103
Subtotal: 1,232,730
Adjustment Factor: 1.5100
Total: 1,861,422
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 23 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Ceiling Finishes: Painted Concrete Aged/Peeling
Requirement ID REQ-18746
Linked System Ceiling Finishes Inspection Date 12/10/2007
Prime System Ceiling Finishes Finish Date -
Category Beyond Useful Life Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2009 Estimated Cost 269,749
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Ceiling paint in all mechanical and electrical rooms is beyond useful life. Paint is peeling and falling onto equipment.
PHOTOS
Ceiling Finishes
Ceiling Finishes: Paint Aged/Pealing - Mechanical Room #2506
ACTION DESCRIPTION
Clean paint off ceiling and prepare surface to accept epoxy paint. Paint ceilings with epoxy paint and dispose of all refuse to approved landfill. Provide
protection for equipment located in rooms.
Note: Existing paint may contain lead. The presence of lead should be verified and appropriate precautions taken.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LCLABJ Common Building Laborers 120.00 hour 45.47 5,456
LCLNRJ Cleaner 120.00 hour 44.96 5,395
LPORHJ Painters Helper 120.00 hour 39.12 4,694
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 24 of
Code Description Quantity Unit Unit Cost Total Cost
LPSPRJ Painters, Spray 120.00 hour 60.04 7,205
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
4.00 Ton 121.33 485
U022203500700 Selective demolition, rubbish handling, dumpster, 10
C.Y., 4 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
3.00 Week 366.38 1,099
U099109203620 Paints & Coatings, walls & ceilings, interior, masonry or
concrete block, glaze coating, 3 coats, multicolor, spray
75,000.00 S.F. 1.92 144,000
U099909100750 Surface Preparation, interior, walls, wash, masonry, brick
& block, smooth
75,000.00 S.F. 0.13 9,750
U132814409000 Removal of lead-based paint, minimum labor/equipment
charge
4.00 Job 139.12 556
Subtotal: 178,642
Adjustment Factor: 1.5100
Total: 269,749
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 25 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Electrical Service and Distribution: Vault
Transformer Testing Is Needed
Requirement ID REQ-18765
Linked System Electrical Service and Distribution Inspection Date 12/10/2007
Prime System Electrical Service and Distribution Finish Date -
Category Maintenance Status Open
Inspector Salomonsson Actual Cost 0
Action Date 12/10/2009 Estimated Cost 123,710
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Existing silicone filled vault transformers located in vault rooms, basement and ground levels, have no record of any testing since their approximate
installation in 1989/1990. Dielectric strength, liquid levels, penetration of water, integrity of gaskets, by-product gases are some of the necessary
preventative maintenance tests needed to ensure the transformers are operating within manufacturer's recommended parameters. Testing should be
provided in the very near future.
PHOTOS
Electrical Service and Distribution
Electrical Service and Distribution: Vault Transformer Testing Is Needed - Room
B05.
ACTION DESCRIPTION
Obtain the services of a qualified transformer testing agency to thoroughly test each vault transformer serving the facility.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LELECO Electricians 384.00 hour 67.89 26,070
RD50131100010 Repair 500 kva transformer, primary, liquid filled 16.00 Ea. 2,673.51 42,776
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 26 of
Code Description Quantity Unit Unit Cost Total Cost
RD50131100020 Maintenance and inspection primary transformer, liquid
filled
16.00 Ea. 32.46 519
U013107000140 Field engineer, maximum 6.00 Week 2,093.70 12,562
Subtotal: 81,927
Adjustment Factor: 1.5100
Total: 123,710
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 27 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Elevators and Lifts: Freight Elevator Aged and
Obsolete
Requirement ID REQ-20979
Linked System Elevators and Lifts Inspection Date 12/10/2007
Prime System Elevators and Lifts Finish Date -
Category Obsolescence Status Open
Inspector Salomonsson Actual Cost 0
Action Date 12/10/2009 Estimated Cost 393,981
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Existing freight elevator 12, (10,000lbs capacity, 50hp, location - north central, service to all floors (excluding ground level)), is aged well beyond its
useful life of 35 years per 2003 BOMA Standard. The controls for the system appear to be obsolete. Continued re-use through future years will likely
result in more expensive and equipment breakdowns, which may not be readily remediated. Replacement of the existing freight elevator 12 should be
planned for .
PHOTOS
Elevators and Lifts
Elevators and Lifts: Freight Elevator Aged and Obsolete - Roof Freight Elevator
Machine Room.
ACTION DESCRIPTION
Replace freight elevator 12 with new. Provide demolition and disposal services, as needed for a complete replacement. New freight elevator systems
should be fully compliant with the ADA, UFAS and NFPA requirements.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LCLABJ Common Building Laborers 40.00 hour 45.47 1,819
LELEVJ Elevator Constructors 40.00 hour 78.23 3,129
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 28 of
Code Description Quantity Unit Unit Cost Total Cost
LWRCKJ *Wrecking 40.00 hour 50.25 2,010
U022203403000 Selective demolition, gutting, building interior, includes
disposal, excludes dumpster fees, minimum
labor/equipment charge
4.00 Job 500.38 2,002
U022203500725 Selective demolition, rubbish handling, dumpster, 20
C.Y., 8 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
1.00 Week 940.31 940
U022203500910 Selective demolition, rubbish handling, dumpster,
alternate pricing method, delivery, average for all sizes,
cost to be added to demolition cost.
1.00 Ea. 91.00 91
U022203701090 Selective demolition, torch cutting, steel, minimum
labor/equipment charge
4.00 Job 352.31 1,409
U140552000050 Elevator, cab, track and equipment, removal 8.00 Stop 666.98 5,336
U142102000425 Electric traction freight elevators, base unit, standard
finish, 4000 lb, 200 fpm, 4 stop
1.00 Ea. 136,129.26 136,129
U142102000575 Electric traction freight elevators, for 10000 lb capacity,
add
1.00 Ea. 35,750.00 35,750
U142102001000 Electric traction freight elevators, for number of stops
over 4, add
4.00 Stop 9,505.60 38,022
U142802003875 Elevator options, freight, doors, bi-parting 1.00 Ea. 12,993.66 12,994
U142802003925 Elevator options, freight, freight, finishes, steel plate floor 1.00 Ea. 2,722.50 2,723
U142802003950 Elevator options, freight, finishes, 14 gauge, 1/4" x 4' steel
plate walls
1.00 Ea. 2,090.00 2,090
U142802003975 Elevator options, freight, 12 month maintenance contract 1.00 Ea. 3,952.08 3,952
U142802004000 Elevator options, freight, signal devices, hall lanterns 8.00 Ea. 760.75 6,086
U142802004025 Elevator options, freight, signal devices, position
indicators, up to 3
1.00 Ea. 856.91 857
U142802004050 Elevator options, freight, signal devices, position
indicators, per each over 3
5.00 Ea. 723.69 3,618
U142802004250 Elevator options, hospital, intercom service 1.00 Ea. 1,957.15 1,957
Subtotal: 260,914
Adjustment Factor: 1.5100
Total: 393,981
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 29 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Elevators and Lifts: Passenger Elevators Aged and
Obsolete
Requirement ID REQ-7043
Linked System Elevators and Lifts Inspection Date 12/10/2007
Prime System Elevators and Lifts Finish Date -
Category Obsolescence Status Open
Inspector Salomonsson Actual Cost 0
Action Date 12/10/2009 Estimated Cost 4,806,299
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The passenger elevators have exceeded their expected operational life and do not have adequate ADA features as required by Uniform Accessibility
Standards, Elevators 4.10. In addtion, worn system components require continued maintenance to repalce aged components.
PHOTOS
Elevators and Lifts
Elevators and Lifts: Passenger Elevators Aged and Obsolete - Roof Elevator
Machine Room.
ACTION DESCRIPTION
Replace existing passenger elevators with new.
Include the following elevators:
Elevators 9 & 10 location - south central, service to all floors (excluding ground level), gearless electric.
Elevators 3, 4 & 5 location - south west, service to all floors (excluding ground level), gearless electric.
Elevators 13, 14, 15, 16 & 17 location - west, service to all floors (excluding basement and level 1), gearless electric.
Provide demolition and disposal services, as needed for a complete replacement. New passenger elevator systems should be fully compliant with the
ANSI A19.1, ADA, UFAS and NFPA Building Codes.
ESTIMATE
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 30 of
Code Description Quantity Unit Unit Cost Total Cost
LCLABJ Common Building Laborers 400.00 hour 45.47 18,188
LELEVJ Elevator Constructors 400.00 hour 78.23 31,292
LWRCKJ *Wrecking 400.00 hour 50.25 20,100
U022203403000 Selective demolition, gutting, building interior, includes
disposal, excludes dumpster fees, minimum
labor/equipment charge
40.00 Job 500.38 20,015
U022203500725 Selective demolition, rubbish handling, dumpster, 20
C.Y., 8 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
10.00 Week 940.31 9,403
U022203500910 Selective demolition, rubbish handling, dumpster,
alternate pricing method, delivery, average for all sizes,
cost to be added to demolition cost.
10.00 Ea. 91.00 910
U022203701090 Selective demolition, torch cutting, steel, minimum
labor/equipment charge
40.00 Job 352.31 14,092
U140552000050 Elevator, cab, track and equipment, removal 80.00 Stop 666.98 53,358
U142102001625 Electric Traction Passenger Elevators, base unit, standard
finish, 2000 lb, 200 fpm, 4 stop
10.00 Ea. 127,329.26 1,273,293
U142102001725 Electric Traction Passenger Elevators, base unit, standard
finish, for 4000 lb capacity, add
10.00 Ea. 7,810.00 78,100
U142102002025 Electric Traction Passenger Elevators, base unit, standard
finish, for number of stops over 4, add
40.00 Stop 13,548.10 541,924
U142702003400 Passenger Elevator Options, cab finishes (based on 3500
lb cab size), stainless steel doors
10.00 Ea. 3,272.50 32,725
U142702003475 Passenger Elevator Options, cab finishes (based on 3500
lb cab size), quarry tile flooring
10.00 Ea. 907.50 9,075
U142702003550 Passenger Elevator Options, cab finishes (based on 3500
lb cab size), stainless steel walls
10.00 Ea. 5,692.50 56,925
U142802004250 Elevator options, hospital, intercom service 10.00 Ea. 1,957.15 19,572
U142802004725 Elevator options, hospital, cab finishes (based on 3500 lb
cab size), 12 month maintenance contract
10.00 Ea. 3,952.08 39,521
U142802004750 Elevator options, hospital, cab finishes (based on 3500 lb
cab size), signal devices, hall lanterns
80.00 Ea. 760.75 60,860
U142802004775 Elevator options, hospital, cab finishes (based on 3500 lb
cab size), signal devices, position indicators, up to 3
10.00 Ea. 856.91 8,569
U142802004800 Elevator options, hospital, cab finishes (based on 3500 lb
cab size), signal devices, position indicators, per each over
3
50.00 Ea. 723.69 36,185
U142802004850 Elevator options, hospital, cab finishes (based on 3500 lb
cab size), variable voltage, O.H. gearless machine, min
10.00 Ea. 85,887.27 858,873
Subtotal: 3,182,979
Adjustment Factor: 1.5100
Total: 4,806,299
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 31 of
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 32 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Emergency Light and Power Systems: Aged and
Insufficient Generator
Requirement ID REQ-18734
Linked System Emergency Light and Power Systems Inspection Date 12/10/2007
Prime System Emergency Light and Power Systems Finish Date -
Category Life Safety Status Open
Inspector Salomonsson Actual Cost 0
Action Date 12/10/2009 Estimated Cost 2,045,468
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The existing 710 kW emergency generator located in Room B03 provides limited emergency power for this building. The facility is equipped with
emergency shelter rooms, two on each floor, with no connections to the emergency generator back-up power support system. The shelter rooms are
reportedly intended for 24 hours of operation in the event of an emergency. As implied by article 700.1 of the 2005 NEC, these rooms should be
connected to the emergency power system.
The existing generator has exceeded the BOMA life expectancy of 20 years. The associated switchgear/transfer switches have exceeded their BOMA life
expectancy of 25 years. Parts are reportedly obsolete and unavailable for the three transfer switches. The system should be replaced.
PHOTOS
Emergency Light and Power Systems
Emergency Light and Power Systems Aged and Insufficient Generator - Room
B03.
ACTION DESCRIPTION
Replace existing emergency power system, associated switches, and automatic transfer switches, with a new system adequately sized for present and
future connected loads. The new generating system should include twin parallel generators, allowing maintenance for the system should one of the two
generators be off-line. A parallel system is also recommended since the ownership of the facility is intended to last for many years. A parallel operating
system will last considerably longer, since more thorough system maintenance operations will be easier to apply, without power interruption. Dispose of
existing equipment and provide temporary power as needed. Extend new emergency generating system service to existing emergency risers and feeders as
needed for a complete installation. Equipment operators, wrecking, cleaner, common building laborer and painter hours included for any building
modifications as deemed necessary by the design engineer of record. Estimated size of new parallel generating system at 1000kW; exact size will need to
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 33 of
be determined by the design engineer of record.
The action is considerably more expensive than system model due to added redundancy, demolition/building alteration costs, increased distribution
equipment capacity and parallel generation capabilities.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AD50102300240 Feeder installation 600 V, including RGS conduit and
XHHW wire, 100 A
400.00 L.F. 27.10 10,840
AD50102300280 Feeder installation 600 V, including RGS conduit and
XHHW wire, 200 A
400.00 L.F. 50.88 20,352
AD50102300400 Feeder installation 600 V, including RGS conduit and
XHHW wire, 800 A
400.00 L.F. 267.96 107,184
AD50102300440 Feeder installation 600 V, including RGS conduit and
XHHW wire, 1000 A
200.00 L.F. 314.01 62,802
AD50102300520 Feeder installation 600 V, including RGS conduit and
XHHW wire, 1600 A
50.00 L.F. 535.93 26,797
AD50102400280 Switchgear installation, incl switchboard, panels & circuit
breaker, 800 A
4.00 Ea. 24,426.49 97,706
AD50102400320 Switchgear installation, incl switchboard, panels & circuit
breaker, 1200 A
4.00 Ea. 31,532.83 126,131
AD50102400360 Switchgear installation, incl switchboard, panels & circuit
breaker, 1600 A
1.00 Ea. 43,072.79 43,073
AD50902101400 Generator sets, w/battery, charger, muffler and transfer
switch, diesel engine with fuel tank, 1000 kW
1,000.00 kW 256.54 256,540
AD50902101400 Generator sets, w/battery, charger, muffler and transfer
switch, diesel engine with fuel tank, 1000 kW
1,000.00 kW 256.54 256,540
E015904002080C Rental;forklift, in plant, 2 wheel drive, 10 ton, 120 HP,
diesel
15.00 Ea./day 240.54 3,608
LCARPJ Carpenters 240.00 hour 57.49 13,798
LCLABJ Common Building Laborers 240.00 hour 45.47 10,913
LCLNRJ Cleaner 120.00 hour 44.96 5,395
LELECJ Electricians 320.00 hour 64.91 20,771
LEQLTJ Equipment Operators, Light Equipment 240.00 hour 54.47 13,073
LHELPJ Helpers Average (5 trades) 240.00 hour 43.43 10,423
LPORDJ Painters, Ordinary 120.00 hour 48.95 5,874
LWRCKJ *Wrecking 320.00 hour 50.25 16,080
U015100500170 Temporary electrical power equipment (pro-rated per job),
underground feed, 3 uses, 1200 amp
4.00 Ea. 7,024.82 28,099
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
12.00 Ton 121.33 1,456
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 34 of
Code Description Quantity Unit Unit Cost Total Cost
U022203500700 Selective demolition, rubbish handling, dumpster, 10
C.Y., 4 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
3.00 Week 366.38 1,099
U022203500910 Selective demolition, rubbish handling, dumpster,
alternate pricing method, delivery, average for all sizes,
cost to be added to demolition cost.
6.00 Ea. 91.00 546
U022203500950 Selective demolition, rubbish handling, dumpster,
alternate pricing method, disposal fee per ton, average for
all sizes, cost to be added to demolition cost.
12.00 Ton 91.00 1,092
U022203609000 Selective demolition, saw cutting, minimum
labor/equipment charge
80.00 Job 211.84 16,947
U022203701090 Selective demolition, torch cutting, steel, minimum
labor/equipment charge
40.00 Job 352.31 14,092
U160553009000 Electrical demolition, minimum labor/equipment charge 80.00 Job 142.00 11,360
U162702004700 Transformer, dry-type, 3 phase 480 V primary 120/208 V
secondary, 500 kVA
4.00 Ea. 24,931.98 99,728
U164156000900 Automatic transfer switches, enclosed, 3 pole, 480 volt,
800 amp
4.00 Ea. 15,751.23 63,005
U164156001600 Automatic transfer switches, time delay on engine starting 4.00 Ea. 290.04 1,160
U164156001700 Automatic transfer switches, adjustable time delay on
retransfer
4.00 Ea. 290.04 1,160
U164156001800 Automatic transfer switches, shunt trips for customer
connections
4.00 Ea. 517.52 2,070
U164156001900 Automatic transfer switches, maintenance select switch 4.00 Ea. 118.29 473
U164156002100 Automatic transfer switches, pilot light-emergency 4.00 Ea. 118.29 473
U164156002200 Automatic transfer switches, pilot light-normal 4.00 Ea. 118.29 473
U164156002300 Automatic transfer switches, auxiliary contact-closed on
normal
4.00 Ea. 136.49 546
U164156002400 Automatic transfer switches, auxiliary contact-closed on
emergency
4.00 Ea. 136.49 546
U164156002500 Automatic transfer switches, frequency relay 4.00 Ea. 597.14 2,389
Subtotal: 1,354,615
Adjustment Factor: 1.5100
Total: 2,045,468
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 35 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Emergency Light and Power Systems: Emergency
Lighting Lacking
Requirement ID REQ-20977
Linked System Emergency Light and Power Systems Inspection Date 12/10/2007
Prime System Emergency Light and Power Systems Finish Date -
Category Life Safety Status Open
Inspector Salomonsson Actual Cost 0
Action Date 12/10/2009 Estimated Cost 194,755
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The spacing of emergency lighting battery pack fixtures in places of assembly and along corridors does not meet the illumination requirements of the 2006
Life Safety Code, section 7.9.2.1. The installation of additional fixtures along paths of egress for the entire facility is required.
PHOTOS
Emergency Light and Power Systems
Emergency Light and Power Systems: Emergency Lighting Lacking - Level 4
Corridor.
ACTION DESCRIPTION
Furnish and install self contained emergency lighting battery pack fixtures along paths of egress from the facility, as needed for code compliance.
Common building laborer hours are included for any building modifications that may be necessary to facilitate the installation of new fixtures. Assume 80
fixtures to be installed.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AD50102301240 Branch installation 600 V, including EMT conduit and
THW wire, 20 A
4,000.00 L.F. 6.90 27,600
LCLABJ Common Building Laborers 160.00 hour 45.47 7,275
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 36 of
Code Description Quantity Unit Unit Cost Total Cost
LELECJ Electricians 160.00 hour 64.91 10,386
U161322600110 Hole drilling, concrete wall, 8" thick, 1/2" pipe size, to 10'
high
88.00 Ea. 57.62 5,071
U165303200700 Emergency lighting units, nickel cadmium battery
operated, twin sealed beam light, 25 W, 6 V each
80.00 Ea. 830.13 66,410
U165303200780 Emergency lighting units, additional remote mount, sealed
beam, 25 W 6 V
80.00 Ea. 52.55 4,204
U165303200900 Fluorescent lamp pack, self-contained 8.00 Ea. 222.86 1,783
U165303209000 Emergency lighting units, minimum labor/equipment
charge
44.00 Job 142.00 6,248
Subtotal: 128,977
Adjustment Factor: 1.5100
Total: 194,755
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 37 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Emergency Light and Power Systems: Exit
Signage Missing
Requirement ID REQ-20970
Linked System Emergency Light and Power Systems Inspection Date 12/10/2007
Prime System Emergency Light and Power Systems Finish Date -
Category Life Safety Status Open
Inspector Salomonsson Actual Cost 0
Action Date 12/10/2009 Estimated Cost 69,704
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Open office spaces on each level were observed without adequate exit signage as required by the 2006 Life Safety Code, section 7.10. The installation of
additional exit signage should be considered in the very near future with the intent to improve means of egress for building occupants during an
emergency situation. Example locations include: rooms 7719, 6018, 6920, 6602, 6109, level 5 Kitchen, 4636, 3624, 3522, 2670, and 1021.
PHOTOS
Emergency Light and Power Systems
Emergency Light and Power Systems: Exit Signage Lacking - Room 6018.
ACTION DESCRIPTION
Provide exit signage where required by code in open office areas and along paths of egress. Exit signage should be energy efficient with LED type lamps
and integral battery source. Extend emergency branch circuitry to new signs from existing emergency distribution risers. Common building laborer hours
included for modifications to existing ceiling system, as needed for a complete installation. Assume 48 units are required.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AD50102301240 Branch installation 600 V, including EMT conduit and
THW wire, 20 A
3,000.00 L.F. 6.90 20,700
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 38 of
Code Description Quantity Unit Unit Cost Total Cost
LCLAMJ Common Maintenance Laborer 80.00 hour 31.60 2,528
LELECJ Electricians 48.00 hour 64.91 3,116
LHELPJ Helpers Average (5 trades) 48.00 hour 43.43 2,085
U018322900130 Ceiling maintenance, acoustical tile cleaning, clean and
apply acoustical coating
384.00 S.F. 0.60 230
U165303200240 Exit lighting, L.E.D. w/ battery unit, single face, ceiling or
wall mount
24.00 Ea. 286.05 6,865
U165303200260 Exit lighting, L.E.D. w/ battery unit, double face, ceiling
or wall mount
24.00 Ea. 301.23 7,230
U165303209010 Exit lighting, minimum labor/equipment charge 24.00 Job 142.00 3,408
Subtotal: 46,161
Adjustment Factor: 1.5100
Total: 69,704
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 39 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Equipment and Furnishings: Loading Dock Facing
Rusted
Requirement ID REQ-18774
Linked System Equipment and Furnishings Inspection Date 12/10/2007
Prime System Equipment and Furnishings Finish Date -
Category Reliability Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2009 Estimated Cost 14,417
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The metal facing on the loading dock has rusted through.
PHOTOS
Equipment and Furnishings
Equipment and Furnishings: Loading Dock Rusted - Northwest Loading Dock
ACTION DESCRIPTION
Remove and replace 1/4" X 18" x 24' steel facing on northwest corner loading dock platform.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LHELPJ Helpers Average (5 trades) 8.00 hour 43.43 347
LPORDJ Painters, Ordinary 8.00 hour 48.95 392
LSSWKJ Structural Steel Workers 8.00 hour 73.92 591
LSSWLJ Welders, Structural Steel 8.00 hour 73.92 591
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 40 of
Code Description Quantity Unit Unit Cost Total Cost
U050601100380 Selective metals demolition, manufactured or fabricated
specialty item, 121 - 500 lb, remove whole or cut up into
smaller pieces, excl shoring, bracing, cutting, loading,
hauling, dumping
5.00 Ea. 67.41 337
U111614000020 Dock bumpers, rubber blocks, 4 1/2" thick x 10" h x 14"
long
10.00 Ea. 68.90 689
U111614003200 Dock boards, heavy duty, aluminum, 15,000 lb capacity,
60" x 60"
4.00 Ea. 1,650.00 6,600
Subtotal: 9,548
Adjustment Factor: 1.5100
Total: 14,417
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 41 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Exterior Doors: Flush Metal Doors Rusted and
Worn
Requirement ID REQ-18777
Linked System Exterior Doors Inspection Date 12/10/2007
Prime System Exterior Doors Finish Date -
Category Beyond Useful Life Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2009 Estimated Cost 25,261
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The exterior flush-metal service doors on the roof providing access to the mechanical penthouse exhibit moderate wear and surface degradation. The
exterior doors are approaching the end of their life expectancy of 30 years.
PHOTOS
Exterior Doors: 1
Exterior Doors: Metal Aged/Deteriorated - Penthouse
Exterior Doors: 2
Exterior Doors: Metal Aged/Deteriorated - Penthouse
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 42 of
ACTION DESCRIPTION
Replace exterior rooftop penthouse doors as indicated. Replacement assemblies to meet PBS-PQ100.1 construction standards. Coordinate replacement
with roofing replacement Requirement identified separately.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AB20302203950 Door, steel 18 gauge, hollow metal, 1 door with frame,
"A" label, 3'-0" x 7'-0" opening
7.00 Opng. 1,993.33 13,953
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
1.00 Ton 121.33 121
U022203500700 Selective demolition, rubbish handling, dumpster, 10
C.Y., 4 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
1.00 Week 366.38 366
U076506000100 Sheet metal flashing, aluminum, flexible, mill finish,
.032" thick, including up to 4 bends
25.00 S.F. 4.59 115
U076506009950 Sheet metal flashing, minimum labor and equipment
charge
5.00 Job 143.10 716
U079208000052 Caulking and sealants, backer rod, polyethylene, 1/2" dia 210.00 L.F. 0.99 208
U079208003600 Caulking and sealants, polyurethane, bulk, in place, 1 or 2
component, 1/2" x 1/4"
210.00 L.F. 3.28 689
U080601100200 Door demolition, exterior door, single, 3' x 7' high, 1-3/4"
thick, remove
7.00 Ea. 22.71 159
U080601102000 Door demolition, door frames, metal, remove and reset 7.00 Ea. 57.43 402
Subtotal: 16,729
Adjustment Factor: 1.5100
Total: 25,261
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 43 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Exterior Stairs: Slab Granite Damaged
Requirement ID REQ-9059
Linked System Exterior Stairs and Fire Escapes Inspection Date 12/10/2007
Prime System Exterior Stairs and Fire Escapes Finish Date -
Category Life Safety Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2009 Estimated Cost 12,490
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The granite steps at the entrances are chipped, cracked, or damaged creating a potential trip hazard. Damaged steps observed at the center entrance lobby
on D Street are chipped and cracked. At ground level, the third granite riser is damaged. The steps at the western entrance on D Street are chipped and
steps at the 7th street entrance show signs of damage.
PHOTOS
Exterior Stairs
Exterior Stairs and Fire Escapes: Slab Granite Damaged - D Street Entrance
ACTION DESCRIPTION
Repair or replace slab granite tread at D Street entrance and 7th Street entrance.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LSTONJ Stone Masons 80.00 hour 57.44 4,595
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
4.00 Ton 121.33 485
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 44 of
Code Description Quantity Unit Unit Cost Total Cost
U022203500700 Selective demolition, rubbish handling, dumpster, 10
C.Y., 4 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
1.00 Week 366.38 366
U022203609000 Selective demolition, saw cutting, minimum
labor/equipment charge
4.00 Job 211.84 847
U040551105120 Selective demolition, masonry, veneers, granite and
marble, 4" thick
30.00 S.F. 1.92 58
U048503000750 Granite veneer, cut to size, polished, low price, gray, light
gray, 2-1/2" to 4" thick
32.00 S.F. 59.98 1,919
Subtotal: 8,271
Adjustment Factor: 1.5100
Total: 12,490
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 45 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Exterior Walls: Aged and Cracked Stucco
Requirement ID REQ-9058
Linked System Exterior Walls Inspection Date 12/10/2007
Prime System Exterior Walls Finish Date -
Category Integrity Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2009 Estimated Cost 1,875,244
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Stucco applied to the building exterior is unevenly wearing at window heads, sills and at the corners of the building. The expansion control joint between
the original west building and the more modern east building needs repointing. Hairline cracks are observed in the facade. The joints of the window sills
on the east side of the building need to be repointed.
PHOTOS
Exterior Walls 3
Exterior Walls: Stucco - Aged/Cracked North Elevation
Exterior Walls 2
Exterior Walls: Stucco - Aged/Cracked Northeast Corner
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 46 of
Exterior Walls 1
Exterior Walls: Stucco - Aged/Cracked Northeast Corner
ACTION DESCRIPTION
Inspect the exterior stucco wall covering to determine the scope of work and materials required to repair the numerous cracks and spalled sections that
have allowed water to infiltrate the building envelope.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AB20101513700 Stucco, 3 coat, self furring metal lath 3.4 Lb/SY, on
regular CMU, 10" x 8" x 16"
7,000.00 S.F. 12.90 90,300
E015906004800C Rent hoist & tower personnel, electric, 3000 lb, 150' at
300 fpm
120.00 Ea./day 758.22 90,986
LEQHVJ Equipment Operators, Crane or Shovel 640.00 hour 59.35 37,984
LHELPJ Helpers Average (5 trades) 640.00 hour 43.43 27,795
LLATHJ Lathers 640.00 hour 48.81 31,238
LPLAHJ Plasterer Helpers 640.00 hour 45.24 28,954
LPLASJ Plasterers 640.00 hour 50.62 32,397
LPORHJ Painters Helper 320.00 hour 39.12 12,518
LPSPRJ Painters, Spray 320.00 hour 60.04 19,213
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
100.00 Ton 121.33 12,133
U022203500840 Selective demolition, rubbish handling, dumpster, 40
C.Y., 13 ton capacity, weekly rental, includes one dump
per week, cost to be added to demolition cost.
16.00 Week 1,577.29 25,237
U039206002100 Patching concrete, walls, epoxy grout, 1/4" deep,
including chipping, cleaning and epoxy grout
5,000.00 S.F. 16.01 80,050
U090601300300 Walls and partitions demolition, exterior stucco over
netting, 1" thick
315,025.00 S.F. 0.59 185,865
U092202000100 Stucco, 3 coats, on masonry construction, no mesh incl.,
incl. lath
18,781.00 S.Y. 29.75 558,735
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 47 of
Code Description Quantity Unit Unit Cost Total Cost
U092202009000 Stucco, mesh, minimum labor/equipment charge 100.00 Job 84.79 8,479
Subtotal: 1,241,884
Adjustment Factor: 1.5100
Total: 1,875,244
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 48 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Exterior Walls: Rooftop Screen
Cracked/Weathered
Requirement ID REQ-9184
Linked System Exterior Walls Inspection Date 12/10/2007
Prime System Exterior Walls Finish Date -
Category Life Safety Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2009 Estimated Cost 144,428
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The masonry decorative screen at the rooftop has aged to the point of structural fatigue causing the block to sag and crack along with weather-caused
erosion. It is possible with a strong wind storm the wall could fall causing damage to equipment and possibly personnel working on roof.
PHOTOS
Exterior Walls
Exterior Walls: Screen Walls Aged/Weathered - Roof
ACTION DESCRIPTION
Demolish and remove CMU screen wall from roof. Replace with new reinforced decorative screen walls. Remove rubbish from site and transport to dump
site. Provide pedestrian barriers to provide safety barrier on ground.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LBRHEJ Bricklayer Helpers 240.00 hour 45.24 10,858
LBRICJ Bricklayers 240.00 hour 57.03 13,687
LCLABJ Common Building Laborers 120.00 hour 45.47 5,456
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 49 of
Code Description Quantity Unit Unit Cost Total Cost
LCLAMJ Common Maintenance Laborer 120.00 hour 31.60 3,792
U015602500550 Temporary Fencing, wire mesh, on 100mm x 100mm
posts, 8' high
420.00 L.F. 28.81 12,100
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
60.00 Ton 121.33 7,280
U022203500840 Selective demolition, rubbish handling, dumpster, 40
C.Y., 13 ton capacity, weekly rental, includes one dump
per week, cost to be added to demolition cost.
3.00 Week 1,577.29 4,732
U040551100400 Selective demolition, masonry, concrete block walls,
reinforced alternate courses, 6" thick
16,128.00 S.F. 0.63 10,161
U042202101600 Concrete block, hollow, normal weight, 2000 psi, 6" x 8"
x 16", includes material only
18,146.00 Ea. 1.52 27,582
Subtotal: 95,648
Adjustment Factor: 1.5100
Total: 144,428
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 50 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Exterior Windows: Glazing Seals Failed
Requirement ID REQ-20885
Linked System Exterior Windows Inspection Date 12/10/2007
Prime System Exterior Windows Finish Date -
Category Reliability Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2009 Estimated Cost 1,416
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Glazing seals on the aluminum frame windows in Room 7080 have failed allowing condensation between the two panes of glass.
PHOTOS
Exterior Windows
Exterior Windows: Insulated, Leaking - Room 7080
ACTION DESCRIPTION
Remove and replace insulated glazing on one window in Room 7080.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LCARPJ Carpenters 4.00 hour 57.49 230
U085201003000 Windows, aluminum sash, stock, grade C, for double
glazing, add
40.00 S.F. 17.69 708
Subtotal: 938
Adjustment Factor: 1.5100
Total: 1,416
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 51 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Fire Alarm System: Fire Alarm Control Panel and
Hardware Aging
Requirement ID REQ-20982
Linked System Fire Alarm Systems Inspection Date 12/10/2007
Prime System Fire Alarm Systems Finish Date -
Category Capacity/Design Status Open
Inspector Salomonsson Actual Cost 0
Action Date 12/10/2009 Estimated Cost 216,514
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The existing fire alarm control panel, located in control room L-14 is approaching the end of its useful life. The system lacks modern capabilities such as
network access and capacity suitable for a facility of this size (sq ft). The installation of a new fire alarm control panel and associated hardware is
warranted. The GSA presently has a project scheduled for the upgrade of the fire alarm control panel, work item 1197.
PHOTOS
Fire Alarm Systems
Fire Alarm Systems: Aging Fire Alarm Control Panel - Room L-14.
ACTION DESCRIPTION
Replace existing fire alarm control panel and associated hardware for a complete system upgrade. Provide software upgrades as may be necessary to
facilitate system replacement. Connect power source for fire alarm system to the emergency generator.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AD50102301240 Branch installation 600 V, including EMT conduit and
THW wire, 20 A
200.00 L.F. 6.90 1,380
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 52 of
Code Description Quantity Unit Unit Cost Total Cost
AD50201250560 Receptacle duplex 120 V grounded, 20 A with box, plate,
3/4" EMT & wire
2.00 Ea. 249.37 499
U137200654170 Detection Systems, fire alarm control panel, addressable
with voice, up to 400 points, excluding wires & conduits
4.00 Ea. 11,422.54 45,690
U137200654175 Detection Systems, fire alarm control panel, addressable
interface device, excluding wires & conduits
128.00 Ea. 326.04 41,733
U137200654400 Detection Systems, fire alarm control panel, battery &
rack, automatic charger, excluding wires & conduits
1.00 Ea. 613.68 614
U137200654600 Detection Systems, UPS battery charger, signal bell,
excluding wires & conduits
1.00 Ea. 132.43 132
U137200656400 Detection Systems, code transmitter, excluding wires &
conduits
1.00 Ea. 979.86 980
U137200656800 Detection Systems, master box, excluding wires &
conduits
1.00 Ea. 3,972.48 3,972
U137200658200 Detection Systems, annunciator panel, 16 zone lamp,
excluding wires & conduits
8.00 Ea. 882.63 7,061
U137200659410 Radiation monitoring systems, minimum labor/equipment
charge
120.00 Job 138.36 16,603
U161207501950 Fire alarm cable, FEP teflon, 150 volt, to 200 Deg.C, #18,
4 pair
16.00 C.L.F. 404.96 6,479
U161207502100 Fire alarm cable, FEP teflon, 150 volt, to 200 Deg.C, #18,
10 pair
8.00 C.L.F. 752.34 6,019
U161322055000 Electric metallic tubing (EMT), 1/2" diameter, to 15' high,
incl 2 terminations, 2 elbows & 11 beam clamps per 100
LF
1,600.00 L.F. 4.09 6,544
U161322059990 Conduit, to 15' high, minimum labor/equipment charge 40.00 Job 142.00 5,680
Subtotal: 143,387
Adjustment Factor: 1.5100
Total: 216,514
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 53 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Fire Protection Systems: Sprinkler Head Guards
Missing
Requirement ID REQ-7084
Linked System Fire Protection Inspection Date 12/10/2007
Prime System Fire Protection Finish Date -
Category Building Code Status Open
Inspector Puckett Actual Cost 0
Action Date 12/10/2009 Estimated Cost 4,335
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
None of the electrical closets (38) have guards on the sprinkler heads as recommended by NFPA - 13, Chapter 6 - System Components and Hardware.
guards.
PHOTOS
Fire Safety Protection Systems
Fire Protection Systems: Sprinkler Head Guards Missing - Electrical Rooms
ACTION DESCRIPTION
Install sprinkler head guards in 38 electrical rooms. Guards should comply with 2007 NFPA-13, Chapter 6, Section 6.2.8 Guards.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LSPRIJ Sprinkler Installers 40.00 hour 67.05 2,682
U139304006000 Sprinkler System Components, sprinkler head guards,
bright zinc, 1/2" NPT, excludes supply piping
38.00 Ea. 4.97 189
Subtotal: 2,871
Adjustment Factor: 1.5100
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 54 of
Total: 4,335
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 55 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Fire Protection: Incomplete Fire Sprinkler System
Coverage
Requirement ID REQ-97358
Linked System Fire Protection Inspection Date 09/18/2008
Prime System Fire Protection Finish Date -
Category Building Code Status Open
Inspector Puckett Actual Cost 0
Action Date 09/18/2010 Estimated Cost 1,247,546
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The existing wet fire protection system covers approximately 40% of the building, which leaves 60% unprotected. PQ-100 and NFPA 13 require complete
coverage for high rise buildings.
PHOTOS
ACTION DESCRIPTION
Upgrade the existing fire sprinkler system to provide coverage to unprotected areas. Work to include additional piping, standpipes, and fire pump capacity
as required.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AD40104100640 Wet pipe sprinkler systems, steel, light hazard, 1 floor,
50,000 SF
134,622.00 S.F. 2.25 302,900
AD40104100760 Wet pipe sprinkler systems, steel, light hazard, each
additional floor, 50,000 SF
405,378.00 S.F. 1.67 676,981
AD40203101580 Wet standpipe risers, class III, steel, black, sch 40, 6"
diam pipe, 1 floor
12.00 Floor 10,855.82 130,270
AD40203101600 Wet standpipe risers, class III, steel, black, sch 40, 6"
diam pipe, additional floors
2.00 Floor 2,837.62 5,675
AD40204103650 Fire pump, electric, with controller, 5" pump, 100 HP,
1000 GPM
1.00 Ea. 39,673.65 39,674
AD40204103700 Fire pump, electric, for jockey pump system, add 1.00 Ea. 4,419.48 4,419
AD50201452400 Motor installation, three phase, 460 V, 100 HP motor size 1.00 Ea. 8,138.87 8,139
LCARPJ Carpenters 160.00 hour 57.49 9,198
LCARPJ Carpenters 80.00 hour 57.49 4,599
LELECJ Electricians 80.00 hour 64.91 5,193
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 56 of
Code Description Quantity Unit Unit Cost Total Cost
LSKWKJ Skilled Workers Average (35 trades) 160.00 hour 58.70 9,392
LSPRIJ Sprinkler Installers 160.00 hour 67.05 10,728
LSSWKJ Structural Steel Workers 32.00 hour 73.92 2,365
LSSWLJ Welders, Structural Steel 48.00 hour 73.92 3,548
RC30331080040 Refinish acoustical tile ceiling and grid (occupied area) 40.00 M.S.F. 861.60 34,464
Subtotal: 1,247,546
Adjustment Factor: 1.0000
Total: 1,247,546
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 57 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Floor Finishes: Access Flooring Corroded
Requirement ID REQ-20869
Linked System Floor Finishes Inspection Date 12/10/2007
Prime System Floor Finishes Finish Date -
Category Reliability Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2009 Estimated Cost 12,650
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The raised access flooring in Room 2043A is corroded. A condensation line is leaking into the flooring below causing it to rust. The floor panels and
framing need replacing.
PHOTOS
Floor Finishes
Floor Finishes: Access Computer Flooring Corroded - Room 2043.
ACTION DESCRIPTION
Temporarily relocate HVAC equipment. Remove flooring and replace with new panels and framing. Relocate electrical and computer wiring.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LCARPJ Carpenters 40.00 hour 57.49 2,300
LCLABJ Common Building Laborers 40.00 hour 45.47 1,819
LCLNRJ Cleaner 8.00 hour 44.96 360
LELECJ Electricians 24.00 hour 64.91 1,558
LSHEEJ Sheet Metal Workers 24.00 hour 67.42 1,618
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 58 of
Code Description Quantity Unit Unit Cost Total Cost
U100601002750 Specialties demolition, access floor, metal panel system,
includes pedestals, covering
50.00 S.F. 0.91 46
U102751500110 Access floors, computer room application, particle board
or steel floor panels, metal covered, under 6,000 sf
50.00 S.F. 13.56 678
Subtotal: 8,378
Adjustment Factor: 1.5100
Total: 12,650
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 59 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Floor Finishes: Carpet Tile Worn/Damaged and
Stained.
Requirement ID REQ-9063
Linked System Floor Finishes Inspection Date 12/10/2007
Prime System Floor Finishes Finish Date -
Category Appearance Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2009 Estimated Cost 2,762,132
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Carpeting in long term tenant spaces and common areas shows signs of heavy use, with stains and torn sections observed throughout. The carpeting
should be replaced to remove trip hazards and restore aesthetic consistency to the office areas.
PHOTOS
Floor Finishes 2
Floor Finishes: Carpet Tile Worn/Damaged and Stained - Room 2670
ACTION DESCRIPTION
Remove and replace with new carpet tiles of industrial grade 32 oz.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AC30204100080 Carpet tile, nylon, fusion bonded, 18" x 18" or 24" x 24",
35 oz
288,000.00 S.F. 5.92 1,704,960
LCLABJ Common Building Laborers 480.00 hour 45.47 21,826
LCRPTJ Carpet & Linoleum Layers 480.00 hour 52.34 25,123
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 60 of
Code Description Quantity Unit Unit Cost Total Cost
LPORDJ Painters, Ordinary 240.00 hour 48.95 11,748
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
20.00 Ton 121.33 2,427
U022203500840 Selective demolition, rubbish handling, dumpster, 40
C.Y., 13 ton capacity, weekly rental, includes one dump
per week, cost to be added to demolition cost.
20.00 Week 1,577.29 31,546
U096512001660 Cove base, rubber or vinyl, standard colors, corners, 6" h 5,680.00 Ea. 5.42 30,786
U099106501900 Paints & Coatings, interior alkyd, latex, flat, in 5 gallon
lots
30.00 Gal. 27.06 812
Subtotal: 1,829,227
Adjustment Factor: 1.5100
Total: 2,762,132
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 61 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Floor Finishes: Epoxy Paint Worn
Requirement ID REQ-20863
Linked System Floor Finishes Inspection Date 12/10/2007
Prime System Floor Finishes Finish Date -
Category Mission Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2009 Estimated Cost 339,892
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Epoxy painted flooring in the electrical/mechanical rooms has worn and flaked off of concrete floors. This has allowed moisture to leach through the
concrete floors allowing the possibility of mold to form. Concrete floors are in need of cleaning and sealing. Only a couple of mechanical rooms in the
basement have been completed.
PHOTOS
Floor Finishes
Floor Finishes: Epoxy Paint Aged/Worn - Room 4710
ACTION DESCRIPTION
Clean concrete floors in mechanical/electrical rooms. Seal and paint with epoxy paint.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AC30204100930 Concrete topping, paint 120,318.00 S.F. 1.47 176,867
LPORHJ Painters Helper 320.00 hour 39.12 12,518
LPSPRJ Painters, Spray 320.00 hour 60.04 19,213
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 62 of
Code Description Quantity Unit Unit Cost Total Cost
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
1.00 Ton 121.33 121
U022203500700 Selective demolition, rubbish handling, dumpster, 10
C.Y., 4 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
2.00 Week 366.38 733
U099909100750 Surface Preparation, interior, walls, wash, masonry, brick
& block, smooth
120,318.00 S.F. 0.13 15,641
Subtotal: 225,094
Adjustment Factor: 1.5100
Total: 339,892
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 63 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Floor Finishes: Vinyl Tile Aged/Worn/Damaged
Requirement ID REQ-6965
Linked System Floor Finishes Inspection Date 12/10/2007
Prime System Floor Finishes Finish Date -
Category Reliability Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2009 Estimated Cost 1,648,180
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Much of the resilient flooring tile in the public corridors is worn, stained, cracked, or is missing altogether. Some corridors have unsightly gashes where
machinery has carved out sections of the resilient flooring tile. The age of the flooring is unknown but appears to be at the end of life.
PHOTOS
Floor Finishes
Floor Finishes: Vinyl Tile Aged/Worn/Damaged - Mechanical Room Stairwell #6
ACTION DESCRIPTION
Remove and replace resilient flooring, rubber tile and base. Relocate room furnishings during floor replacement and replace after completion. Clean after
completion.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LCLABJ Common Building Laborers 960.00 hour 45.47 43,651
LCRPTJ Carpet & Linoleum Layers 480.00 hour 52.34 25,123
LPORDJ Painters, Ordinary 320.00 hour 48.95 15,664
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 64 of
Code Description Quantity Unit Unit Cost Total Cost
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
64.00 Ton 121.33 7,765
U022203500840 Selective demolition, rubbish handling, dumpster, 40
C.Y., 13 ton capacity, weekly rental, includes one dump
per week, cost to be added to demolition cost.
12.00 Week 1,577.29 18,927
U090601200601 Flooring demolition, composition 92,327.00 S.F. 1.67 154,186
U090601200850 Flooring demolition, vinyl or rubber cove base, straight
section
10,864.00 L.F. 0.33 3,585
U096512001660 Cove base, rubber or vinyl, standard colors, corners, 6" h 1,358.00 Ea. 5.42 7,360
U096581007700 Resilient Flooring, vinyl tile, marbleized or Travertine
pattern, 12" x 12"x 1/8"
92,327.00 S.F. 8.83 815,247
Subtotal: 1,091,510
Adjustment Factor: 1.5100
Total: 1,648,180
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 65 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name High Tension Service and Dist: High Voltage
Switchgear/Cabling Antiquated
Requirement ID REQ-18766
Linked System High Tension Service and Dist. Inspection Date 12/10/2007
Prime System High Tension Service and Dist. Finish Date -
Category Beyond Useful Life Status Open
Inspector Salomonsson Actual Cost 0
Action Date 12/10/2009 Estimated Cost 1,551,447
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The facility has an old and obsolete main high voltage switchgear substation in a dedicated room adjacent to the south transformer vault on the garage
level. The room is the termination of the PEPCO, 13.8V feeders 14637, 14638 & 14639. From the substation, antiquated high voltage cabling is
distributed within the building to a downstream old and obsolete high voltage distribution substation equipped with twelve no load high voltage switches
for further distribution to facility vault transformers (primary side).
PHOTOS
High Tension Service and Distribution
High Tension Service and Dist: High Voltage Switchgear/Cabling Antiquated -
South Primary Service Room Garage Level.
ACTION DESCRIPTION
Replace existing high voltage switchgear and cabling with new. Provide temporary power as needed to facilitate equipment replacement. Coordinate
replacement with Utility Company. Dispose of old equipment/cabling. Equipment Operators, Painters, Wrecking, Carpenter, Cleaner and Common
Building Laborer hours included for any building modifications as deemed necessary by the design engineer of record.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AD50101101000 High voltage cable, neutral & conduit included, copper
350 kcmil, 15 kV
1,500.00 L.F. 117.60 176,400
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 66 of
Code Description Quantity Unit Unit Cost Total Cost
E015902005500C Rent truck flatbed 1axle 3 ton rating 20.00 Ea./day 225.13 4,503
E015904002060C Rental, in plant forklift, 2 wheel drive, 4 ton, 80 HP,
gasoline
20.00 Ea./day 159.06 3,181
E015904002800C Rent electric generator gas engine 250 kW 20.00 Ea./day 597.08 11,942
LCARPJ Carpenters 240.00 hour 57.49 13,798
LCLABJ Common Building Laborers 240.00 hour 45.47 10,913
LCLNRJ Cleaner 240.00 hour 44.96 10,790
LELECJ Electricians 480.00 hour 64.91 31,157
LEQLTJ Equipment Operators, Light Equipment 240.00 hour 54.47 13,073
LHELPJ Helpers Average (5 trades) 480.00 hour 43.43 20,846
LPORDJ Painters, Ordinary 60.00 hour 48.95 2,937
LWRCKJ *Wrecking 240.00 hour 50.25 12,060
U015100500180 Temporary electrical power equipment (pro-rated per job),
underground feed, 3 uses, 2000 amp
4.00 Ea. 8,579.66 34,319
U022203108500 Selective demolition, cutout, remove, minimum
labor/equipment charge
20.00 Job 89.96 1,799
U022203403000 Selective demolition, gutting, building interior, includes
disposal, excludes dumpster fees, minimum
labor/equipment charge
20.00 Job 500.38 10,008
U022203500700 Selective demolition, rubbish handling, dumpster, 10
C.Y., 4 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
4.00 Week 366.38 1,466
U022203500920 Selective demolition, rubbish handling, dumpster,
alternate pricing method, haul, average for all sizes,
includes one dump per week, cost to be added to
demolition cost.
4.00 Ea. 266.93 1,068
U022203609000 Selective demolition, saw cutting, minimum
labor/equipment charge
20.00 Job 211.84 4,237
U022203701090 Selective demolition, torch cutting, steel, minimum
labor/equipment charge
20.00 Job 352.31 7,046
U160553009000 Electrical demolition, minimum labor/equipment charge 20.00 Job 142.00 2,840
U163307600700 Load interrupter switch, 2 position, 400 kVA & above,
13.8 kV, 600 amp w/CLF fuses, NEMA 1
12.00 Ea. 32,273.94 387,287
U163608002100 Substation equipment, power circuit breakers, air, 13 to 26
kV
3.00 Ea. 70,579.17 211,738
U163608004050 Station capacitors, current transformers, 13 to 26 kV 3.00 Ea. 3,613.66 10,841
U163608004100 Station capacitors, potential transformers, 13 to 26 kV 3.00 Ea. 5,092.88 15,279
U163608008050 Lightning arresters, 13 to 26 kV 3.00 Ea. 1,850.04 5,550
U163608008150 Reactors and resistors, 13 to 26 kV 3.00 Ea. 3,811.50 11,435
U163608009120 Conversion equipment, battery chargers 1.00 Ea. 4,410.44 4,410
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 67 of
Code Description Quantity Unit Unit Cost Total Cost
U163608009200 Control batteries 15.00 K.A.H. 435.20 6,528
Subtotal: 1,027,448
Adjustment Factor: 1.5100
Total: 1,551,447
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 68 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Identifying Devices: Exterior Signage Weathered
Requirement ID REQ-6226
Linked System Identifying Devices Inspection Date 12/10/2007
Prime System Identifying Devices Finish Date -
Category Integrity Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2009 Estimated Cost 1,851
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Signage at the 7th Street entrance is poor. Print on remaining exterior signs have faded due to exposure by the elements and are barely legible.
PHOTOS
Identifying Devices
Identifying Devices: Signage Weathered North Side of building.
ACTION DESCRIPTION
Replace enameled metal exterior entrance signs. For consistency of appearance, it is recommended to replace signs at 7th Street, D Street, and 9th Street
entrances.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LCLABJ Common Building Laborers 8.00 hour 45.47 364
U104302001600 Signs, letters, cast aluminum, 14" h x 2-5/16" deep 5.00 Ea. 123.35 617
U104302009000 Signs, minimum labor/equipment charge 2.00 Job 122.54 245
Subtotal: 1,226
Adjustment Factor: 1.5100
Total: 1,851
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 69 of
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 70 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Interior Doors: Aged and Worn Doors
Requirement ID REQ-9111
Linked System Interior Doors Inspection Date 12/10/2007
Prime System Interior Doors Finish Date -
Category Integrity Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2009 Estimated Cost 1,508,866
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The metal doors throughout the building are damaged and worn, with loose louvers, damaged hinges, and damaged hardware that prevents doors from
latching properly. Repairs and replacement are required to ensure reliable operation.
PHOTOS
Interior Doors
Interior Doors: Metal Aged - Room 2029
ACTION DESCRIPTION
Perform a survey of the doors to determine the scope of work, with approximately 25 percent of the doors anticipated to require full replacement. Install
new hollow metal interior doors with lever handles and frames, including ADA accessible hardware are per 2006 IBC, Section 1008 - Doors, Gates, and
Turnstiles; ADAAG Section 14.3
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AC10201143020 Metal door/metal frame, flush,composite, 18 ga full panel,
3'-0" x 6'-8", butt weld frame, 8-3/4"
556.00 Ea. 1,101.14 612,234
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
10.00 Ton 121.33 1,213
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 71 of
Code Description Quantity Unit Unit Cost Total Cost
U022203500840 Selective demolition, rubbish handling, dumpster, 40
C.Y., 13 ton capacity, weekly rental, includes one dump
per week, cost to be added to demolition cost.
10.00 Week 1,577.29 15,773
U080601100500 Door demolition, interior door, single, 3' x 7' high, 1-3/8"
thick, remove
556.00 Ea. 18.17 10,103
U087101502600 Door hardware, school, single, interior, heavy use, incl.
lever and closer
556.00 Door 647.35 359,927
Subtotal: 999,249
Adjustment Factor: 1.5100
Total: 1,508,866
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 72 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Lighting Equipment: Aged Wiring and Dirty
Bronze Fixtures
Requirement ID REQ-22950
Linked System Lighting Equipment Inspection Date 04/09/2008
Prime System Lighting Equipment Finish Date -
Category Modernization Status Open
Inspector Darrah, Lyle Actual Cost 0
Action Date 04/09/2010 Estimated Cost 4,179
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
In the historically significant 7th Street entrance lobby, the existing wall sconces in the mezzanine and the ceiling fixtures in the vestibule have original
wiring that could pose a life safety hazard. Additionally, the fixtures have become dirty over the years and require cleaning.
PHOTOS
ACTION DESCRIPTION
Remove, clean and rewire the existing light fixtures in the mezzanine and vestibules.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LCLNRJ Cleaner 20.00 hour 44.96 899
LELECJ Electricians 20.00 hour 64.91 1,298
U059506506560 Paints and protective coatings, silicone, sprayed 4.00 S.F. 0.49 2
U160907003200 Lighting fixture, maintenance, remove and replace
(reinstall), incl. remove, disconnect wire terminations,
store, reinstall and reconnect wire terminations
4.00 Ea. 142.00 568
Subtotal: 2,767
Adjustment Factor: 1.5100
Total: 4,179
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 73 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Low Tension Service and Dist: Aged and Obsolete
Switchboards
Requirement ID REQ-6938
Linked System Low Tension Service and Dist. Inspection Date 12/10/2007
Prime System Low Tension Service and Dist. Finish Date -
Category Obsolescence Status Open
Inspector Salomonsson Actual Cost 0
Action Date 12/10/2009 Estimated Cost 3,395,977
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
All feeders and switchboards on the secondary side of vault transformers were determined to be either obsolete or aged beyond useful life. Replacement
parts are highly likely to be unavailable and continued re-use through future years will become more costly. This problem occurs in all switch gear rooms
on the basement level.
The switchboards were installed during the original construction. Associated equipment, such as circuit breakers is no longer available. The switchboards
were installed when the building was constructed in 1934/1936. This means that the equipment is at least 64 to 66 years old, which is twice its expected
useful life.
PHOTOS
Low Tension Service and Distribution
Low Tension Service and Dist: Aged and Obsolete Switchboards - Room G202.
ACTION DESCRIPTION
Replace existing main switchboards and associated feeders. Ensure proper disposal of existing equipment is provided. All associated obsolete bus duct
should be replaced. Utilize temporary power as needed for a complete installation. Common building laborer, carpenter, cleaner, wrecking, light
equipment operator and skilled workers average hours included for any building modifications as determined by the design engineer of record. New
switchboards should include spare capacity for future growth and/or renovations. Scope of work includes the following switchboards & associated feeders
typically located in electrical rooms on the ground and basement levels:
West Swbrd - 277/480V, 1600A
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 74 of
Swbrd D - 120/208V, 4000A
Main Swbrd Elec Shop - 120/208V, 4000A
Swbrd EF - 120/208V, 2000A
Swbrd GH - 120/208V, 2000A
Swbrd B1 - 120/208V, 2000A
Swbrd C - 120/208V, 4000A
Swbrd C1 - 480V (delta), 2000A
Swbrd A - 120/208V, 3000A
Swbrd B - 120/208V, 3000A
Chiller Swgr - 1.34/2.4kV, 600A, includes (1) 750kVA dry type transformer, adjacent.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AD50101100800 High voltage cable, neutral & conduit included, copper
250 kcmil, 5 kV
300.00 L.F. 87.99 26,397
AD50102300520 Feeder installation 600 V, including RGS conduit and
XHHW wire, 1600 A
50.00 L.F. 535.93 26,797
AD50102300560 Feeder installation 600 V, including RGS conduit and
XHHW wire, 2000 A
100.00 L.F. 628.02 62,802
AD50102400360 Switchgear installation, incl switchboard, panels & circuit
breaker, 1600 A
1.00 Ea. 43,072.79 43,073
AD50102400400 Switchgear installation, incl switchboard, panels & circuit
breaker, 2000 A
4.00 Ea. 54,577.30 218,309
E015904007290C Rented truck, flatbed, GVW = 20,000 Lbs 30.00 Ea./day 183.19 5,496
LCARPJ Carpenters 400.00 hour 57.49 22,996
LCLABJ Common Building Laborers 400.00 hour 45.47 18,188
LCLNRJ Cleaner 400.00 hour 44.96 17,984
LELECJ Electricians 800.00 hour 64.91 51,928
LEQLTJ Equipment Operators, Light Equipment 400.00 hour 54.47 21,788
LSKWKJ Skilled Workers Average (35 trades) 400.00 hour 58.70 23,480
LWRCKJ *Wrecking 400.00 hour 50.25 20,100
U015100500180 Temporary electrical power equipment (pro-rated per job),
underground feed, 3 uses, 2000 amp
5.00 Ea. 8,579.66 42,898
U022203500700 Selective demolition, rubbish handling, dumpster, 10
C.Y., 4 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
6.00 Week 366.38 2,198
U022203500910 Selective demolition, rubbish handling, dumpster,
alternate pricing method, delivery, average for all sizes,
cost to be added to demolition cost.
12.00 Ea. 91.00 1,092
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 75 of
Code Description Quantity Unit Unit Cost Total Cost
U022203609000 Selective demolition, saw cutting, minimum
labor/equipment charge
40.00 Job 211.84 8,474
U022203701090 Selective demolition, torch cutting, steel, minimum
labor/equipment charge
40.00 Job 352.31 14,092
U162908600150 Voltage monitor systems, AC voltage remote, 3 channel,
120, 230, or 480 V
10.00 Ea. 7,137.19 71,372
U163307600300 Load interrupter switch, 2 position, 300 kVA & below
w/CLF fuses, 4.8 kV, 600 amp, NEMA 1
2.00 Ea. 26,157.55 52,315
U163307601000 Pothead, one 3 conductor or three 1 conductor 2.00 Ea. 3,383.59 6,767
U163307601200 Pothead, key interlocks 2.00 Ea. 821.68 1,643
U164408000900 Switchboards, distribution section, aluminum bus bars, 4
W, 120/208 or 277/480 V, 3000 amp, excl breakers
12.00 Ea. 9,450.09 113,401
U164408000950 Switchboards, distribution section, aluminum bus bars, 4
W, 120/208 or 277/480 V, 4000 amp, excl breakers
18.00 Ea. 13,018.33 234,330
U164408403320 Switchboards, pressure switch, 4 wire, 120/208 V, 3000
amp, incl CT compartment, excl CT's or PT's
2.00 Ea. 45,120.55 90,241
U164408403330 Switchboards, pressure switch, 4 wire, 120/208 V, 4000
amp, incl CT compartment, excl CT's or PT's
3.00 Ea. 57,435.17 172,306
U164408404600 Switchboards, circuit breaker, mold case, 3 pole, 4 wire,
600 amp
12.00 Ea. 11,302.92 135,635
U164408404800 Switchboards, circuit breaker, mold case, 3 pole, 4 wire,
800 amp
12.00 Ea. 13,408.81 160,906
U164408602620 Switchboards, auxiliary pull section 36", add 10.00 Ea. 3,199.96 32,000
U164503203000 Bus duct, copper, indoor, 3 pole 4 wire, feeder, 2000 amp 100.00 L.F. 634.93 63,493
U164503203020 Bus duct, copper, indoor, 3 pole 4 wire, feeder, 3000 amp 100.00 L.F. 1,008.26 100,826
U164503203030 Bus duct, copper, indoor, 3 pole 4 wire, feeder, 4000 amp 150.00 L.F. 1,364.53 204,680
U164503203800 Bus duct, copper, 3 pole 4 wire, elbow, 2000 amp 4.00 Ea. 3,019.64 12,079
U164503203820 Bus duct, copper, 3 pole 4 wire, elbow, 3000 amp 4.00 Ea. 5,190.41 20,762
U164503203830 Bus duct, copper, 3 pole 4 wire, elbow, 4000 amp 6.00 Ea. 6,605.22 39,631
U164503206400 Bus duct, copper, 3 pole 4 wire, switchboard stub, 2000
amp
2.00 Ea. 3,695.84 7,392
U164503206420 Bus duct, copper, 3 pole 4 wire, switchboard stub, 3000
amp
2.00 Ea. 5,174.29 10,349
U164503206430 Bus duct, copper, 3 pole 4 wire, switchboard stub, 4000
amp
3.00 Ea. 6,612.16 19,836
U164503209270 Bus duct, ground bus added to bus duct, 2000 amp 100.00 L.F. 122.36 12,236
U164503209290 Bus duct, ground bus added to bus duct, 3000 amp 100.00 L.F. 177.55 17,755
U164503209300 Bus duct, ground bus added to bus duct, 4000 amp 150.00 L.F. 231.44 34,716
U164503209320 Bus duct, high short circuit bracing, add 350.00 L.F. 17.80 6,230
Subtotal: 2,248,991
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 76 of
Adjustment Factor: 1.5100
Total: 3,395,977
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 77 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Parking Lot: Striping/Markings Worn
Requirement ID REQ-20978
Linked System Parking Lots Inspection Date 12/10/2007
Prime System Parking Lots Finish Date -
Category Reliability Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2009 Estimated Cost 99,221
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The parking garage striping and parking space markings have worn off making it hard to identify the parking spaces. The striping requires painting to
identify the parking spaces.
PHOTOS
Parking Lot
Parking Lot: Worn Striping/Markings Basement
ACTION DESCRIPTION
Remove and repaint parking garage and lot markings. Prior to restriping, it is recommended to repair and seal existing pavement to maintain surface
integrity.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LCEFIJ Cement Finishers 40.00 hour 52.01 2,080
LCLABJ Common Building Laborers 80.00 hour 45.47 3,638
LPORHJ Painters Helper 80.00 hour 39.12 3,130
LPSPRJ Painters, Spray 80.00 hour 60.04 4,803
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 78 of
Code Description Quantity Unit Unit Cost Total Cost
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
1.00 Ton 121.33 121
U022203500700 Selective demolition, rubbish handling, dumpster, 10
C.Y., 4 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
1.00 Week 366.38 366
U027603000020 Painted pavement markings, acrylic waterborne, white or
yellow, 4" wide
7,260.00 L.F. 0.45 3,267
U027605001200 Pavement markings, handicap symbol 8.00 Ea. 37.93 303
U027852500300 Fog seal, sealcoating, petroleum resistant, over 10,000
S.Y.
25,000.00 S.Y. 1.92 48,000
Subtotal: 65,709
Adjustment Factor: 1.5100
Total: 99,221
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 79 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Partitions: GWB Damaged
Requirement ID REQ-10082
Linked System Partitions Inspection Date 12/10/2007
Prime System Partitions Finish Date -
Category Appearance Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2009 Estimated Cost 46,629
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Surfaces of the gypsum board from the second tthrough the seventh levels were observed to be worn and damaged from impacts that require repair and
repainting.
PHOTOS
ACTION DESCRIPTION
Repair or replace gypsum board that is damaged or missing at levels 2 through 7. Remove refuse from building and provide disposal to local dump. Clean
affected areas after completion of project.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LCLABJ Common Building Laborers 40.00 hour 45.47 1,819
LPLAHJ Plasterer Helpers 40.00 hour 45.24 1,810
LPLASJ Plasterers 40.00 hour 50.62 2,025
RC30132140010 Repair 5/8" drywall - (2% of walls) 5,000.00 S.F. 1.83 9,150
RC30132140030 Refinish drywall 5,000.00 S.F. 0.73 3,650
RC30132140050 Office painting, 10' x 12', 10' high walls 42.00 Ea. 259.04 10,880
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
5.00 Ton 121.33 607
U022203500725 Selective demolition, rubbish handling, dumpster, 20
C.Y., 8 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
1.00 Week 940.31 940
Subtotal: 30,880
Adjustment Factor: 1.5100
Total: 46,629
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 80 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Partitions: GWB Water Damage
Requirement ID REQ-20868
Linked System Partitions Inspection Date 12/10/2007
Prime System Partitions Finish Date -
Category Air and Water Quality Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2009 Estimated Cost 2,681
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Failure of existing stucco around windows allows water to seep inside damaging interior drywall in Room 1912 and the 7th Street Guard Office. Mold is
suspected. One occupant in Room 1912 reports respiratory problems possibly caused by mold. An air quality test was performed and results are pending.
Note: Refer to requirement addressing damaged stucco at windows.
PHOTOS
Partitions 1
Partitions: GWB Water Damage - Room 1912
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 81 of
Partitions 2
Partitions: GWB Water Damaged - Room 1912
ACTION DESCRIPTION
Remove and replace drywall in Room 1912 and Guard Office at 7th Street Entrance. Clean and paint area affected after repair is completion.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AC10101280840 Gypsum board, 1 face only,e xterior sheathing, water
resistant, 5/8"
250.00 S.F. 0.97 243
AC10101280880 Add for the following: fiberglass insulation, 3-1/2" 250.00 S.F. 0.98 245
AC10101280960 Add for the following: taping and finishing 250.00 S.F. 0.45 113
AC30102300080 Painting, interior on plaster and drywall, brushwork,
primer & 2 coats
250.00 S.F. 0.97 243
AC30102300140 Painting, interior on plaster and drywall, walls & ceilings,
roller work, primer & 2 coats
250.00 S.F. 0.71 178
LCLABJ Common Building Laborers 8.00 hour 45.47 364
LPORDJ Painters, Ordinary 8.00 hour 48.95 392
Subtotal: 1,775
Adjustment Factor: 1.5100
Total: 2,681
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 82 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Pedestrian Paving: Concrete Crack/Spalled.
Requirement ID REQ-20884
Linked System Pedestrian Paving Inspection Date 12/10/2007
Prime System Pedestrian Paving Finish Date -
Category Reliability Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2009 Estimated Cost 8,229
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Concrete sidewalk at the 7th Street parking garage entrance and the D Street entrance is cracked and is spalling. The cracks if allowed to get worse as time
progresses, will cause a tripping hazard.
PHOTOS
Pedestrian Paving 1
Pedestrian Paving: Concrete Crack/Spalling - 7th Street Parking Garage Entrance.
Pedestrian Paving 2
Pedestrian Paving: Concrete Crack/Spalling - D Street Entrance.
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 83 of
ACTION DESCRIPTION
Cut damaged concrete at 7th Street parking garage and D Street entrance. Remove and replace concrete to match the elevation of the existing concrete.
Provide pedestrian barricades around area during replacement.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LCEFIJ Cement Finishers 16.00 hour 52.01 832
LCLAMJ Common Maintenance Laborer 16.00 hour 31.60 506
RG20331400100 Remove and replace concrete sidewalk, 4' wide 40.00 L.F. 29.78 1,191
U015601000020 Barricades, wood, fixed, 3 rail, 5' high, 3 rail @ 2" x 8" 40.00 L.F. 51.73 2,069
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
4.00 Ton 121.33 485
U022203500700 Selective demolition, rubbish handling, dumpster, 10
C.Y., 4 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
1.00 Week 366.38 366
Subtotal: 5,450
Adjustment Factor: 1.5100
Total: 8,229
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 84 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Plumbing Fixtures: Worn Utility Sinks
Requirement ID REQ-18763
Linked System Plumbing Fixtures Inspection Date 12/10/2007
Prime System Plumbing Fixtures Finish Date -
Category Appearance Status Open
Inspector Puckett Actual Cost 0
Action Date 12/10/2009 Estimated Cost 66,507
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The utility sinks are beyond their rated life, with corroded surfaces and worn valves. Replacement with new installations is required to reliably conduct
custodial maintenance of the building.
PHOTOS
Plumbing Fixtures - Utility Sinks Need Cleaned
-
ACTION DESCRIPTION
Replace the existing utility sinks and clear drain lines as needed. Coordinate with other plumbing requirements as is necesssary.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AD20104404340 Service sink w/trim, PE on CI, corner floor, wall hung
w/rim guard, 24" x 20"
14.00 Ea. 2,767.10 38,739
LPLUHA Plumber Helpers 40.00 hour 42.28 1,691
LPLUMA Plumbers 40.00 hour 54.31 2,172
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 85 of
Code Description Quantity Unit Unit Cost Total Cost
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
1.00 Ton 121.33 121
U022203500700 Selective demolition, rubbish handling, dumpster, 10
C.Y., 4 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
1.00 Week 366.38 366
U150556001300 Fixture, sink, single compartment, selective demolition 14.00 Ea. 68.10 953
Subtotal: 44,044
Adjustment Factor: 1.5100
Total: 66,507
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 86 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Rain Water Drainage: Aged Ground Water Sump
Pumps
Requirement ID REQ-18755
Linked System Rain Water Drainage Inspection Date 12/10/2007
Prime System Rain Water Drainage Finish Date -
Category Beyond Useful Life Status Open
Inspector Puckett Actual Cost 0
Action Date 12/10/2009 Estimated Cost 18,790
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Submersible sump pumps for groundwater disposal in the basement are aged and worn. Replacement is recommended to ensure relaibale service.
PHOTOS
Storm Water Equipment: Aged Ground Water Sump Pumps
Storm Sewer: Ground Water Sump Pumps Aged - Basement
ACTION DESCRIPTION
Replace the unreliable sump pumps with new installations. Coonect to emergency power supply as required and include controls and alarm systems as
well.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AD50201450240 Motor installation, single phase, 115 V, 1 HP motor size 4.00 Ea. 1,588.87 6,355
U150556002198 Pump, sump or submersible, selective demolition 4.00 Ea. 45.40 182
U154408003300 Pump, sewage ejector, system accessories, for alarm horn
and lights, 115 V mercury switch, add
2.00 Ea. 229.76 460
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 87 of
Code Description Quantity Unit Unit Cost Total Cost
U154408003340 Pump, sewage ejector, system accessories, for switch,
magnetic contactor, alarm bell, light, 3 level control, add
2.00 Ea. 704.43 1,409
U154408003380 Pump, sewage ejector, system accessories, for alternator,
mercury switch activated, add
2.00 Ea. 1,162.41 2,325
U154409407560 Pump, submersible sump, automatic, cast iron, 1/2 H.P.,
1-1/4" discharge
4.00 Ea. 357.49 1,430
U154409409000 Pump, submersible sump, minimum labor/equipment
charge
2.00 Job 141.62 283
Subtotal: 12,443
Adjustment Factor: 1.5100
Total: 18,790
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 88 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Roofing: BUR (Built Up Roofing)
Aged/Damaged.
Requirement ID REQ-7263
Linked System Roofing Inspection Date 12/10/2007
Prime System Roofing Finish Date -
Category Integrity Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2009 Estimated Cost 943,852
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The built up roof on the eastern half of the roof was observed to have deteriorated surface with evidence of ponding and water penetration around drains
and general failure of the membrane due to displaced ballast material.
PHOTOS
Roofing
Roofing: Built Up Roofing Aged/Ponding - Northeast Corner
Roofing 2
Roofing: Built Up Roofing penetrations around roof drains.
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 89 of
ACTION DESCRIPTION
Replace built-up roofing throughout east half of roof (~ 60,000 SF) including insulation, ballast and flashing. Replacement the roofing membrane
assembly above Directors Executive Conference Room (~30,000 SF) with insulation and ballast. Provide sloped roof pitch for water run-off. Remove and
dispose of refuse in approved local landfill and clean area.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
RB30131050500 Minor membrane replacement - (25% of roof area)
built-up roofing
300.00 Sq. 688.32 206,496
RB30131050700 Total roof replacement built-up roofing 600.00 Sq. 657.64 394,584
U022203300300 Selective demolition, dump charges, typical urban city,
rubbish only, includes tipping fees only
133.00 Ton 109.20 14,524
U022203500840 Selective demolition, rubbish handling, dumpster, 40
C.Y., 13 ton capacity, weekly rental, includes one dump
per week, cost to be added to demolition cost.
6.00 Week 1,577.29 9,464
Subtotal: 625,067
Adjustment Factor: 1.5100
Total: 943,852
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 90 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Roofing: Single Ply Membrane - Ballasted
Aged/Damaged
Requirement ID REQ-18749
Linked System Roofing Inspection Date 12/10/2007
Prime System Roofing Finish Date -
Category Integrity Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2009 Estimated Cost 677,439
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The western roof has deteriorated due to heat and weather. Membrane has separated around roof penetrations and roof drains allowing water to penetrate
the roof to areas below. Ballast has shifted to expose and deteriorate roof insulation in selected areas.
PHOTOS
Roofing
Roofing: Single Ply Membrane Aged/Weathered - West Roof
ACTION DESCRIPTION
Replace single ply membrane roofing throughout west half of roof (~60,000 SF), including insulation, ballast and flashing. Provide sloped roof pitch for
water run-off. Remove and dispose of refuse in local dump and clean area.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
RB30131250600 Roof replacement thermosetting 600.00 Sq. 626.91 376,146
U022203300300 Selective demolition, dump charges, typical urban city,
rubbish only, includes tipping fees only
133.00 Ton 109.20 14,524
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 91 of
Code Description Quantity Unit Unit Cost Total Cost
U022203500840 Selective demolition, rubbish handling, dumpster, 40
C.Y., 13 ton capacity, weekly rental, includes one dump
per week, cost to be added to demolition cost.
6.00 Week 1,577.29 9,464
U070601102520 Selective demolition, thermal and moisture protection,
roof insulation board, to 2" thick
59,879.00 S.F. 0.43 25,748
U070601105970 Selective demolition, thermal and moisture protection,
waterproofing, over 1/2" thick
59,879.00 S.F. 0.38 22,754
Subtotal: 448,635
Adjustment Factor: 1.5100
Total: 677,439
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 92 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Substructure: Concrete Parking Lot Aged/Worn
Requirement ID REQ-7828
Linked System Substructure Inspection Date 12/10/2007
Prime System Substructure Finish Date -
Category Integrity Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2009 Estimated Cost 72,271
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The concrete floor surface in the basement garage is aged with cracks and spalling. To prevent further damage and water from coming up through the
cracks the concrete parking slab must be repaired.
PHOTOS
Substructure
Substructure: Concrete Parking Lot Aged/Worn - Basement Parking Area
ACTION DESCRIPTION
Clean out, patch and seal selected areas in the interior basement garage concrete slab, where deposits of salts, car discharges and oil have deteriorated the
concrete slab. Accomplish separate striping Requirement in conjunction with surface restoration.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LCEFIJ Cement Finishers 80.00 hour 52.01 4,161
LCLAMJ Common Maintenance Laborer 80.00 hour 31.60 2,528
LHELPJ Helpers Average (5 trades) 80.00 hour 43.43 3,474
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 93 of
Code Description Quantity Unit Unit Cost Total Cost
U018322301010 Patching concrete, floors, small areas, regular grout, 1/4"
thick
8,000.00 S.F. 3.66 29,280
U018322301050 Sealing concrete floor, oil or urethane base, 2 coats, max 8,000.00 S.F. 0.90 7,200
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
4.00 Ton 121.33 485
U022203500700 Selective demolition, rubbish handling, dumpster, 10
C.Y., 4 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
2.00 Week 366.38 733
Subtotal: 47,861
Adjustment Factor: 1.5100
Total: 72,271
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 94 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Telephone Systems: Wiring Old and Abandoned
Requirement ID REQ-18719
Linked System Telephone Systems Inspection Date 12/10/2007
Prime System Telephone Systems Finish Date -
Category Obsolescence Status Open
Inspector Salomonsson Actual Cost 0
Action Date 12/10/2009 Estimated Cost 221,309
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Throughout the entire building are remains of previous telephone systems cabling likely thirty to sixty years old. Facility personnel reported this cabling is
abandoned and no longer utilized. The cabling should be removed with vacated cabinets/conduits sealed to improve architectural partition integrity.
PHOTOS
Telephone Systems
Telephone Systems: Antiquated and Abandoned Wiring - Electrical Closet 3103.
ACTION DESCRIPTION
Disconnect and remove all of the original, abandoned telephone wiring throughout the building. Vacated conduits, cavities and cabinets should be
properly sealed to improved partition integrity. Carpenter and painter allocated for cutting and patching.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LCARPJ Carpenters 240.00 hour 57.49 13,798
LCLNRJ Cleaner 200.00 hour 44.96 8,992
LELECJ Electricians 400.00 hour 64.91 25,964
LPORDJ Painters, Ordinary 60.00 hour 48.95 2,937
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 95 of
Code Description Quantity Unit Unit Cost Total Cost
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
8.00 Ton 121.33 971
U078401000520 Firestopping, multi trade openings, through walls, 6" x
12"
40.00 Ea. 259.58 10,383
U078401000560 Firestopping, multi trade openings, through floors, 6" x
12"
40.00 Ea. 259.58 10,383
U160553001680 Pull boxes & cabinets, sheet metal, 24" x 24" x 6",
electrical demolition, remove, incl removal of supports
and terminations
80.00 Ea. 46.18 3,694
U160553009000 Electrical demolition, minimum labor/equipment charge 240.00 Job 142.00 34,080
U160557000240 Telephone cable, electrical demolition, remove 120,000.00 L.F. 0.20 24,000
U161207509000 Special wires & fittings, minimum labor/equipment
charge
80.00 Job 142.00 11,360
Subtotal: 146,562
Adjustment Factor: 1.5100
Total: 221,309
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 96 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Terminal and Package Units: Aged Window Air
Conditioners
Requirement ID REQ-18751
Linked System Terminal and Package Units Inspection Date 12/10/2007
Prime System Terminal and Package Units Finish Date -
Category Beyond Useful Life Status Open
Inspector Puckett Actual Cost 0
Action Date 12/10/2009 Estimated Cost 13,007
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The window air conditioners that provide supplemental cooling are aged and worn. Replacement is required to ensure comfort conditioning of the spaces
served is maintained.
PHOTOS
Terminal and Package Units
Terminal and Package Units: Window AC Units Aged - Typical
ACTION DESCRIPTION
Replace the window air conditioners with new installations as needed. Recover and recycle refrigerant as per EPA guidelines.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
U022203500700 Selective demolition, rubbish handling, dumpster, 10
C.Y., 4 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
1.00 Week 366.38 366
U150553008400 Window air conditioner, selective demolition 12.00 Ea. 28.84 346
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 97 of
Code Description Quantity Unit Unit Cost Total Cost
U157308004520 Window unit air conditioner, portable, grounded
receptacle required, 15 amp 125 V, 12,000 BTUH
12.00 Ea. 658.44 7,901
Subtotal: 8,614
Adjustment Factor: 1.5100
Total: 13,007
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 98 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Wall Finishes: Acoustic Tile Aged/Deteriorated
Requirement ID REQ-6220
Linked System Wall Finishes Inspection Date 12/10/2007
Prime System Wall Finishes Finish Date -
Category Integrity Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2009 Estimated Cost 5,753
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The sound attenuation acoustic tile placed on the walls of the Xerox printing room has deteriorated due to frequent changes in tenant use.
PHOTOS
Wall Finishes
Wall Finishes: Acoustic Tile Aged/Deteriorated - Room 4660
ACTION DESCRIPTION
Replace the worn tile system with a modern sound absorbing panel. Work to include demolition of the existing system as well as rough in and fit up of
new paneling.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LCARPJ Carpenters 16.00 hour 57.49 920
LCLABJ Common Building Laborers 16.00 hour 45.47 728
RC30132140030 Refinish drywall 800.00 S.F. 0.73 584
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
0.50 Ton 121.33 61
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 99 of
Code Description Quantity Unit Unit Cost Total Cost
U022203500700 Selective demolition, rubbish handling, dumpster, 10
C.Y., 4 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
1.00 Week 366.38 366
U090601304010 Walls and partitions demolition, insulation, rigid, 1" thick 800.00 S.F. 0.17 136
U090601309000 Walls and partitions demolition, minimum
labor/equipment charge
1.00 Job 83.59 84
U098401000300 Sound Absorbing Panels, fiberboard panels, sound
deadening, 1/2" thick
800.00 S.F. 1.04 832
U098401009000 Sound Absorbing Panels, minimum labor/equipment
charge
1.00 Job 99.86 100
Subtotal: 3,810
Adjustment Factor: 1.5100
Total: 5,753
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 100 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Wall Finishes: Worn Paint on Concrete Walls
Requirement ID REQ-20862
Linked System Wall Finishes Inspection Date 12/10/2007
Prime System Wall Finishes Finish Date -
Category Beyond Useful Life Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2009 Estimated Cost 70,797
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The painted wall surfaces in the electrical/mechanical rooms is fading and worn, requiring resurfacing.
PHOTOS
Wall Finishes
Wall Finishes: Epoxy Painted Concrete Aged/Pealing - Room 2506
ACTION DESCRIPTION
Refinish the interior painted wall surfaces. Repair damaged areas of wall where required. Coordinate with other interior finish replacement corrections
identified separately.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LPORHJ Painters Helper 160.00 hour 39.12 6,259
LPSPRJ Painters, Spray 160.00 hour 60.04 9,606
U015408000100 Tarpaulins, polyvinyl coated nylon, 14 oz. to 18 oz., min 2,000.00 S.F. 0.55 1,100
U099109100450 Paints & Coatings, walls, concrete masonry units (CMU),
smooth surface, first coat, latex, spray
54,400.00 S.F. 0.24 13,056
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 101 of
Code Description Quantity Unit Unit Cost Total Cost
U099109100460 Paints & Coatings, walls, concrete masonry units (CMU),
smooth surface, second coat, latex, spray
54,400.00 S.F. 0.18 9,792
U099909100750 Surface Preparation, interior, walls, wash, masonry, brick
& block, smooth
54,400.00 S.F. 0.13 7,072
Subtotal: 46,886
Adjustment Factor: 1.5100
Total: 70,797
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 102 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 2 - Within 1 to 2 Years
Requirement Name Wall Finishes: Worn and Stained Painted Walls
Requirement ID REQ-9062
Linked System Wall Finishes Inspection Date 12/10/2007
Prime System Wall Finishes Finish Date -
Category Integrity Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2009 Estimated Cost 1,859,932
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The painted walls throughout the building are stained and dirty from wear, and should be repainted withint be scheduled within the next two years.
PHOTOS
Wall Finishes
Wall Finishes: Painted Aged/Worn/Stained
ACTION DESCRIPTION
Prepare and paint plaster and gypsum board walls and ceilings throughout building. Provide protection to contents in work areas prior to painting. Clean
work areas when complete.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LCLNRJ Cleaner 240.00 hour 44.96 10,790
LHELPJ Helpers Average (5 trades) 240.00 hour 43.43 10,423
LPORHJ Painters Helper 480.00 hour 39.12 18,778
LPSPRJ Painters, Spray 480.00 hour 60.04 28,819
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 103 of
Code Description Quantity Unit Unit Cost Total Cost
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
4.00 Ton 121.33 485
U022203500700 Selective demolition, rubbish handling, dumpster, 10
C.Y., 4 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
4.00 Week 366.38 1,466
U099109201380 Paints & Coatings, walls & ceilings, interior, concrete,
drywall or plaster, oil base, 3 coats, sand finish, spray
1,507,769.00 S.F. 0.53 799,118
U099909100660 Surface Preparation, interior, walls, sand, drywall,
gypsum, plaster, light
1,507,769.00 S.F. 0.12 180,932
U099909100730 Surface Preparation, interior, walls, wash, drywall,
gypsum, plaster
1,507,769.00 S.F. 0.12 180,932
Subtotal: 1,231,743
Adjustment Factor: 1.5100
Total: 1,859,932
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 104 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 3 - Within 3 to 5 Years
Requirement Name Ceiling Finishes: ACT Aged/Stained
Requirement ID REQ-9160
Linked System Ceiling Finishes Inspection Date 12/10/2007
Prime System Ceiling Finishes Finish Date -
Category Integrity Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2010 Estimated Cost 4,017,277
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
A large portion of the 2X4 or 2X2 acoustic ceiling tiles on floors 1 through 7 are stained, warped, damaged, or are missing. Rather than replace individual
tiles, the tiles should be replaced throughout.
PHOTOS
Ceiling Finishes
Ceiling Finishes: ACT Aged/Stained - Room 3674
ACTION DESCRIPTION
Replace all ceiling tiles on floor levels 1 through 7 and in the 36,000 sq. ft. occupiable areas of the basement level. Replacement of all tiles is
recommended in order to insure consistency of appearance for new installation. Verify ceiling utilization of fire rated tiles.
Replacement should be coordinated with HVAC replacement or light fixture replacement schedule.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LCARPJ Carpenters 160.00 hour 57.49 9,198
LCLABJ Common Building Laborers 160.00 hour 45.47 7,275
LCLNRJ Cleaner 80.00 hour 44.96 3,597
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 105 of
Code Description Quantity Unit Unit Cost Total Cost
LHELPJ Helpers Average (5 trades) 160.00 hour 43.43 6,949
U022203300300 Selective demolition, dump charges, typical urban city,
rubbish only, includes tipping fees only
13.00 Ton 109.20 1,420
U022203500840 Selective demolition, rubbish handling, dumpster, 40
C.Y., 13 ton capacity, weekly rental, includes one dump
per week, cost to be added to demolition cost.
4.00 Week 1,577.29 6,309
U090601101200 Ceiling demolition, suspended ceiling, mineral fiber, 2 x 2
or 2 x 4, remove
763,285.00 S.F. 0.45 343,478
U095109000900 Ceiling Tiles, mineral fiber, fire rated, plain faced, 3/4"
thick
763,285.00 S.F. 2.99 2,282,222
Subtotal: 2,660,448
Adjustment Factor: 1.5100
Total: 4,017,277
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 106 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 3 - Within 3 to 5 Years
Requirement Name Domestic Water Distribution: Aged and Worn
Piping
Requirement ID REQ-6064
Linked System Domestic Water Distribution Inspection Date 12/10/2007
Prime System Domestic Water Distribution Finish Date -
Category Beyond Useful Life Status Open
Inspector Puckett Actual Cost 0
Action Date 12/10/2010 Estimated Cost 1,594,400
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
With the exception of new piping run during renovation, the majority of the domestic water distribution is original galvanized piping that is aged and
worn, with built up mineral deposits that have reduced the free area of the piping and reduced supply to the building. The system should be inspected and
upgraded as needed to ensure adequate water volume and pressure supply to the building.
PHOTOS
Domestic Water Distribution
Domestic Water Distribution: Water Main Aged
ACTION DESCRIPTION
Perform an engineering analysis of the existing piping to determine its condition and scope of work. Replace aged and unreliable sections of piping and
valves as needed, including non-destructive pressure tests to ensure that the system is fully functional.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LCARPI Carpenters 80.00 hour 58.26 4,661
LCLABI Common Building Laborers 80.00 hour 46.25 3,700
LPLUHI Plumber Helpers 240.00 hour 53.60 12,864
LPLUMI Plumbers 240.00 hour 68.63 16,471
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 107 of
Code Description Quantity Unit Unit Cost Total Cost
U022203108500 Selective demolition, cutout, remove, minimum
labor/equipment charge
56.00 Job 89.96 5,038
U022203500840 Selective demolition, rubbish handling, dumpster, 40
C.Y., 13 ton capacity, weekly rental, includes one dump
per week, cost to be added to demolition cost.
2.00 Week 1,577.29 3,155
U083101001600 Doors, specialty, access, fire rated, with lock, stainless
steel, 12" x 12"
24.00 Ea. 378.66 9,088
U083101001650 Doors, specialty, access, fire rated, with lock, stainless
steel, 18" x 18"
32.00 Ea. 536.67 17,173
U150556002000 Pipe, metal pipe, to 1-1/2" diam., selective demolition 2,000.00 L.F. 2.72 5,440
U150556002050 Pipe, metal pipe, 2" to 3-1/2" diam., selective demolition 2,000.00 L.F. 3.63 7,260
U150556002100 Pipe, metal pipe, 4" to 6" diam., selective demolition 2,000.00 L.F. 10.90 21,800
U150556002150 Pipe, metal pipe, 8" to 14" diam., selective demolition 200.00 L.F. 18.16 3,632
U151074201140 Pipe, copper, tubing, solder, 1/2" diameter, type K,
includes coupling & clevis hanger assembly 10' O.C.
1,000.00 L.F. 12.48 12,480
U151074201160 Pipe, copper, tubing, solder, 5/8" diameter, type K,
includes coupling & clevis hanger assembly 10' O.C.
1,000.00 L.F. 14.12 14,120
U151074201180 Pipe, copper, tubing, solder, 3/4" diameter, type K,
includes coupling & clevis hanger assembly 10' O.C.
1,000.00 L.F. 17.43 17,430
U151074201260 Pipe, copper, tubing, solder, 2" diameter, type K, includes
coupling & clevis hanger assembly 10' O.C.
1,000.00 L.F. 47.17 47,170
U151074201300 Pipe, copper, tubing, solder, 3" diameter, type K, includes
coupling & clevis hanger assembly 10' O.C.
1,000.00 L.F. 88.01 88,010
U151074201330 Pipe, copper, tubing, solder, 4" diameter, type K, includes
coupling & clevis hanger assembly 10' O.C.
1,000.00 L.F. 143.51 143,510
U151074201360 Pipe, copper, tubing, solder, 6" diameter, type K, includes
coupling & clevis hanger assembly 10' O.C.
1,000.00 L.F. 419.64 419,640
U151074201380 Pipe, copper, tubing, solder, 8" diameter, type K, includes
coupling & clevis hanger assembly 10' O.C.
200.00 L.F. 721.37 144,274
U151101602920 Valves, bronze, gate, non-rising stem, soldered, 125 psi,
1/2"
24.00 Ea. 56.80 1,363
U151101602940 Valves, bronze, gate, non-rising stem, soldered, 125 psi,
3/4"
24.00 Ea. 66.29 1,591
U151101602980 Valves, bronze, gate, non-rising stem, soldered, 125 psi,
2"
8.00 Ea. 183.73 1,470
U151101603000 Valves, bronze, gate, non-rising stem, soldered, 125 psi,
3"
8.00 Ea. 515.44 4,124
U151102003680 Valves, iron body, gate, OS&Y, flanged, 125 lb., 4" 8.00 Ea. 887.89 7,103
U151102003700 Valves, iron body, gate, OS&Y, flanged, 125 lb., 6" 8.00 Ea. 1,432.50 11,460
U151102003720 Valves, iron body, gate, OS&Y, flanged, 125 lb., 8" 4.00 Ea. 2,260.20 9,041
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 108 of
Code Description Quantity Unit Unit Cost Total Cost
U151401005250 Backflow preventer, reduced pressure principle, iron,
automatic operation, gate valves, flanged, 8" pipe size,
includes valves and four test cocks
2.00 Ea. 9,590.25 19,181
U159557000200 Pipe testing, nondestructive hydraulic pressure test,
isolate, 1 hour hold, 1" to 4" pipe, 1000 - 2000 L.F.
1.00 Ea. 1,250.26 1,250
U159557000360 Pipe testing, nondestructive hydraulic pressure test,
isolate, 1 hour hold, 6" to 10" pipe, 500 - 1000 L.F.
1.00 Ea. 1,887.19 1,887
U159559001000 Balancing, water, pumps, (Subcontractor's quote including
material & labor)
2.00 Ea. 254.40 509
Subtotal: 1,055,894
Adjustment Factor: 1.5100
Total: 1,594,400
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 109 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 3 - Within 3 to 5 Years
Requirement Name Emergency Light and Power Systems: Emergency
Lighting Fixtures Aged
Requirement ID REQ-20976
Linked System Emergency Light and Power Systems Inspection Date 12/10/2007
Prime System Emergency Light and Power Systems Finish Date -
Category Beyond Useful Life Status Open
Inspector Salomonsson Actual Cost 0
Action Date 12/10/2010 Estimated Cost 518,397
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Existing emergency lighting fixtures are nearing the end of their useful lives and should be planned for replacement. Fixtures are typically wall mounted
battery packs located along paths of egress from places of assembly and corridors.
PHOTOS
Emergency Light and Power Systems
Emergency Light and Power Systems: Emergency Lighting Fixtures Aged -
Room 3129.
ACTION DESCRIPTION
Replace existing emergency lighting fixtures with new. Properly dispose all aged emergency lighting fixtures. Replace any branch wiring found damaged
or deteriorated.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
RD50231260010 Replace branch wiring with junction box 8.00 M.L.F. 1,351.17 10,809
RD50932400030 Replace emergency lighting fixture 360.00 Ea. 874.59 314,852
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
2.00 Ton 121.33 243
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 110 of
Code Description Quantity Unit Unit Cost Total Cost
U022203500700 Selective demolition, rubbish handling, dumpster, 10
C.Y., 4 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
1.00 Week 366.38 366
U160555005320 Emergency battery pack lighting unit, electrical
demolition, remove
360.00 Ea. 47.33 17,039
Subtotal: 343,310
Adjustment Factor: 1.5100
Total: 518,397
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 111 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 3 - Within 3 to 5 Years
Requirement Name Emergency Light and Power Systems: Exit
Signage Aged and Inefficient
Requirement ID REQ-20974
Linked System Emergency Light and Power Systems Inspection Date 12/10/2007
Prime System Emergency Light and Power Systems Finish Date -
Category Beyond Useful Life Status Open
Inspector Salomonsson Actual Cost 0
Action Date 12/10/2010 Estimated Cost 135,723
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The facility has undergone numerous renovations over the years with aged exit signage gradually being replaced by more energy efficient LED exit signs.
During the assessment it was determined that approximately twenty percent of existing exit signs, interspersed on all levels, are incandescent type fixtures.
The fixtures are inefficient, aged, and exceed the BOMA life expectancy of 20 years.
PHOTOS
Emergency Light and Power Systems
Emergency Light and Power Systems: Exit Signage Aged and Inefficient - Room
2080.
ACTION DESCRIPTION
Replace existing aged and inefficient exit signage with new. Exit signage should be energy efficient with LED type lamps and integral battery source.
Extend emergency branch circuitry to new signs from existing emergency distribution risers. Common building laborer hours are included for
modifications to existing ceiling system, as needed for a complete installation. Assume that 96 units are required.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AD50102301240 Branch installation 600 V, including EMT conduit and
THW wire, 20 A
6,000.00 L.F. 6.90 41,400
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 112 of
Code Description Quantity Unit Unit Cost Total Cost
LCLAMJ Common Maintenance Laborer 160.00 hour 31.60 5,056
LELECJ Electricians 48.00 hour 64.91 3,116
LHELPJ Helpers Average (5 trades) 48.00 hour 43.43 2,085
U018322900130 Ceiling maintenance, acoustical tile cleaning, clean and
apply acoustical coating
768.00 S.F. 0.60 461
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
1.00 Ton 121.33 121
U022203500700 Selective demolition, rubbish handling, dumpster, 10
C.Y., 4 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
1.00 Week 366.38 366
U160555005310 Exit light, electrical demolition, remove 96.00 Ea. 23.67 2,272
U165303200240 Exit lighting, L.E.D. w/ battery unit, single face, ceiling or
wall mount
48.00 Ea. 286.05 13,730
U165303200260 Exit lighting, L.E.D. w/ battery unit, double face, ceiling
or wall mount
48.00 Ea. 301.23 14,459
U165303209010 Exit lighting, minimum labor/equipment charge 48.00 Job 142.00 6,816
Subtotal: 89,883
Adjustment Factor: 1.5100
Total: 135,723
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 113 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 3 - Within 3 to 5 Years
Requirement Name Exterior Windows: Steel Windows Aged and
Deteriorated
Requirement ID REQ-20918
Linked System Exterior Windows Inspection Date 12/10/2007
Prime System Exterior Windows Finish Date -
Category Beyond Useful Life Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2010 Estimated Cost 81,766
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Steel awning windows on penthouse mechanical and elevator rooms are rusted and no longer operate properly.
PHOTOS
Exterior Windows
Exterior Windows: Steel Aged/Deteriorated - Penthouse West Mechanical Room
ACTION DESCRIPTION
Remove and replace exterior awning windows on mechanical and electrical rooms on the penthouse.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AB20201045550 Windows, steel, horizontal pivoted, insulated glass, 6' x 4' 24.00 Ea. 2,039.08 48,938
LCARPJ Carpenters 24.00 hour 57.49 1,380
LHELPJ Helpers Average (5 trades) 24.00 hour 43.43 1,042
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
2.00 Ton 121.33 243
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 114 of
Code Description Quantity Unit Unit Cost Total Cost
U022203500700 Selective demolition, rubbish handling, dumpster, 10
C.Y., 4 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
1.00 Week 366.38 366
U080601201040 Window demolition, steel, to 50 S.F., remove old mesh 24.00 Ea. 90.85 2,180
Subtotal: 54,149
Adjustment Factor: 1.5100
Total: 81,766
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 115 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 3 - Within 3 to 5 Years
Requirement Name Floor Finishes: Broadloom Carpet/Aging
Requirement ID REQ-18780
Linked System Floor Finishes Inspection Date 12/10/2007
Prime System Floor Finishes Finish Date -
Category Appearance Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2010 Estimated Cost 3,195,535
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Approximately of 60 percent of the carpeting in the tenant spaces varies in condition from fair to good due to age due to the traffic of each space and the
renovations that occurred over the years with the transition of tenants. Carpet replacement will be warranted based on condition or life expectancy as well
as to maintain the visual appeal of the interior spaces.
PHOTOS
Floor Finishes 4
Floor Covering: Broadloom Carpet Aging/Worn - Room 4051B
Floor Finishes 3
Floor Covering: Broadloom Carpet/Aging - Room 2080
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 116 of
ACTION DESCRIPTION
Replace the carpet flooring in approximately 60 percent of the usable square-footage. Coordinate with separate requirement regarding the replacement of
worn carpet in identified tenant locations.
Note: Per GSA, the tenant is responsible for the work identified within this correction. The cost of this work was estimated at $2,658,713 including a cost
correction factor and Cost Factor of 1.51.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AC30204100140 Carpet, tufted, nylon, roll goods, 12' wide, 26 oz 239,440.00 S.F. 7.26 1,738,334
AC30204100220 Carpet, padding, add to above, minimum 239,440.00 S.F. 1.04 249,018
LCLABJ Common Building Laborers 160.00 hour 45.47 7,275
LCRPTJ Carpet & Linoleum Layers 160.00 hour 52.34 8,374
LHELPJ Helpers Average (5 trades) 160.00 hour 43.43 6,949
LPORDJ Painters, Ordinary 80.00 hour 48.95 3,916
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
6.00 Ton 121.33 728
U022203500840 Selective demolition, rubbish handling, dumpster, 40
C.Y., 13 ton capacity, weekly rental, includes one dump
per week, cost to be added to demolition cost.
12.00 Week 1,577.29 18,927
U090601200400 Flooring demolition, carpet, bonded, includes surface
scraping
239,440.00 S.F. 0.33 79,015
U096512001150 Cove base, rubber or vinyl, standard colors, 4" h, .080"
thick
1,300.00 L.F. 2.73 3,549
U099106501900 Paints & Coatings, interior alkyd, latex, flat, in 5 gallon
lots
6.00 Gal. 27.06 162
Subtotal: 2,116,248
Adjustment Factor: 1.5100
Total: 3,195,535
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 117 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 3 - Within 3 to 5 Years
Requirement Name Floor Finishes: Terrazzo Aged and Cracked
Requirement ID REQ-9060
Linked System Floor Finishes Inspection Date 12/10/2007
Prime System Floor Finishes Finish Date -
Category Integrity Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2010 Estimated Cost 368,783
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The terrazzo flooring in the entrance and elevator lobbies and corridors have significant cracking that must be repaired to prevent further propagation.
PHOTOS
Floor Finishes
Floor Finishes: Terrazzo Aged and Cracked - 1st Floor Corridor by East D Street
Entrance
ACTION DESCRIPTION
Repair terrazzo flooring from elevator and entrance lobbies as well as entrance corridor floors as is necessary remove cracked sections, including the
application of protective finishes and polishing of the floors.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AC30204101920 Terrazzo precast, non-slip, maximum 5,460.00 S.F. 36.94 201,692
LMSTZJ Mosaic & Terrazzo Workers 240.00 hour 51.23 12,295
LMTHEJ Mosaic & Terrazzo Helpers 240.00 hour 41.90 10,056
U022203300300 Selective demolition, dump charges, typical urban city,
rubbish only, includes tipping fees only
30.00 Ton 109.20 3,276
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 118 of
Code Description Quantity Unit Unit Cost Total Cost
U022203500840 Selective demolition, rubbish handling, dumpster, 40
C.Y., 13 ton capacity, weekly rental, includes one dump
per week, cost to be added to demolition cost.
3.00 Week 1,577.29 4,732
U090601202640 Flooring demolition, tile, terrazzo, cast in place 5,460.00 S.F. 2.23 12,176
Subtotal: 244,227
Adjustment Factor: 1.5100
Total: 368,783
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 119 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 3 - Within 3 to 5 Years
Requirement Name Lighting Equipment: Aged Lighting Fixtures
Requirement ID REQ-18750
Linked System Lighting Equipment Inspection Date 12/10/2007
Prime System Lighting Equipment Finish Date -
Category Beyond Useful Life Status Open
Inspector Salomonsson Actual Cost 0
Action Date 12/10/2010 Estimated Cost 40,592
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Aged and inefficient lighting fixtures were observed in some mechanical/utility spaces. The fixtures are aged beyond their useful intended life of twenty
years per 2003 BOMA Standard. Example locations include rooms 4710, 4069,2005,1509, utility spaces adjacent to the kitchen on level five, and the
elevator machine room (roof) which formerly served abandoned elevators 1 and 2. The fixtures should be planned for replacement with more energy
efficient fixtures.
PHOTOS
Lighting Equipment
Lighting Equipment: Aged Lighting Fixtures - Utility Space Adjacent to Level 5
Kitchen.
ACTION DESCRIPTION
Replace existing aged and inefficient lighting fixtures with new, example locations listed in requirement description. Dispose aged fixtures and reconnect
branch circuitry as needed for a complete installation. Replace any branch circuitry found damaged during installation.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
RD50231240010 Replace armored cable 1.00 M.L.F. 5,267.50 5,268
RD50232600030 Replace fixture fluorescent lighting fixture, 80 W 72.00 Ea. 206.48 14,867
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 120 of
Code Description Quantity Unit Unit Cost Total Cost
U160553002340 Fluorescent fixtures, interior, strip fixture, 2 lamp, 4' long,
electrical demolition, remove, surface mount, to 15' high,
incl supports & whips
72.00 Ea. 22.72 1,636
U160553009000 Electrical demolition, minimum labor/equipment charge 36.00 Job 142.00 5,112
Subtotal: 26,882
Adjustment Factor: 1.5100
Total: 40,592
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 121 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 3 - Within 3 to 5 Years
Requirement Name Lighting Equipment: Aged Occupancy Sensor
System
Requirement ID REQ-18740
Linked System Lighting Equipment Inspection Date 12/10/2007
Prime System Lighting Equipment Finish Date -
Category Appearance Status Open
Inspector Salomonsson Actual Cost 0
Action Date 12/10/2010 Estimated Cost 1,119,280
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Existing occupancy sensors are aged beyond their intended useful life of ten years. Spare parts are likely unavailable and continued re-use through future
years will become cost prohibitive. Additionally several occupancy sensors were observed with missing housings. Complete system replacement should
be planned for, with a centralized lighting control system.
PHOTOS
Lighting Equipment
Lighting Equipment: Aged Occupancy Sensor System - Level 6 Corridor.
ACTION DESCRIPTION
Remove and dispose aged occupancy sensors. Intercept, junction and extend existing lighting circuitry as needed for interface to new lighting control
system. Replace any branch wiring found damaged or deteriorated. Provide low voltage control stations and electronic relays with PLC based lighting
control panels and switches. Control system should include integral time control feature to automatically turn-off fixtures at a pre-determined daily time
with the intent to save energy.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AD50102301240 Branch installation 600 V, including EMT conduit and
THW wire, 20 A
13,392.00 L.F. 6.90 92,405
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 122 of
Code Description Quantity Unit Unit Cost Total Cost
LELECJ Electricians 240.00 hour 64.91 15,578
RD50231260010 Replace branch wiring with junction box 6.70 M.L.F. 1,351.17 9,053
U160553000310 Armored cable, (BX), #12, 3 wire, average 50' runs,
electrical demolition, remove
11,160.00 L.F. 1.11 12,388
U160553001720 Junction boxes, 4" square & octagon, electrical
demolition, remove, incl removal of supports and
terminations
2,232.00 Ea. 7.10 15,847
U160553009000 Electrical demolition, minimum labor/equipment charge 279.00 Job 142.00 39,618
U161367001400 Pull boxes, hinged, sheet metal, 24" W x 36" H x 8" D,
NEMA 1
31.00 Ea. 519.74 16,112
U161405004200 Low voltage switching, transformer, low voltage
switching, 115 V to 25 V
31.00 Ea. 172.45 5,346
U161405004400 Low voltage switching, master control, 12 circuit, manual 31.00 Ea. 269.39 8,351
U161405004600 Low voltage switching, rectifier, silicon 1,116.00 Ea. 88.85 99,157
U161405005800 Low voltage switching, switchplates, 3 gang, 9 switch,
stainless steel
31.00 Ea. 85.43 2,648
U161405006500 Low voltage switching, frame, low voltage switching, to
hold up to 6 relays
186.00 Ea. 112.16 20,862
U161405007400 Low voltage switching, control wire, 3 conductor 124.00 C.L.F. 157.96 19,587
U161405007600 Low voltage switching, control wire, 19 conductor 31.00 C.L.F. 585.48 18,150
U164108401100 Load management device, 8 loads 140.00 Ea. 2,615.31 366,143
Subtotal: 741,245
Adjustment Factor: 1.5100
Total: 1,119,280
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 123 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 3 - Within 3 to 5 Years
Requirement Name Plumbing Fixtures: Aged and Non-Compliant
Water Coolers
Requirement ID REQ-7367
Linked System Plumbing Fixtures Inspection Date 12/10/2007
Prime System Plumbing Fixtures Finish Date -
Category Reliability Status Open
Inspector Puckett Actual Cost 0
Action Date 12/10/2010 Estimated Cost 47,342
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Water coolers are aged beyond their estimated life expectancy of twenty years showing corrosion and chipped paint. These fixtures do not comply with
current ANSI/NSF 61 requirements for lead content. In addition, this fixture does not comply with ADAAG Sections 4.1.3(10)(a) and 4.15.1 for
provisions for one accessible to wheelchair users in accordance with 4.15 and one accessible to persons who have difficulty bending.
PHOTOS
Plumbing Fixtures
Plumbing Fixtures: Aged and Non-Compliant Water Coolers
ACTION DESCRIPTION
Work to include replacing floor mounted water coolers with dual height water coolers, including wall repairs as required.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AD20108201880 Water cooler, electric, wall hung, dual height, 14.3 GPH 14.00 Ea. 1,787.31 25,022
LELECJ Electricians 8.00 hour 64.91 519
LPLASJ Plasterers 24.00 hour 50.62 1,215
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 124 of
Code Description Quantity Unit Unit Cost Total Cost
LPLUMJ Plumbers 24.00 hour 67.88 1,629
LTILFJ Tile Layers 16.00 hour 51.78 828
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
1.00 Ton 121.33 121
U022203500840 Selective demolition, rubbish handling, dumpster, 40
C.Y., 13 ton capacity, weekly rental, includes one dump
per week, cost to be added to demolition cost.
1.00 Week 1,577.29 1,577
U092101000100 Gypsum Plaster, 80 lb bag, more than 1 ton 4.00 Bag 18.19 73
U093101005400 Ceramic tile, walls, interior, thin set, 4-1/4" x 4-1/4" 50.00 S.F. 6.25 313
U099108000180 Paints & Coatings, trim, exterior, fascia, latex paint, 1 coat
coverage, brushwork, 1" x 12"
50.00 L.F. 0.66 33
U099108000190 Paints & Coatings, trim, exterior, fascia, latex paint, 1 coat
coverage, roller, 1" x 12"
50.00 L.F. 0.43 22
Subtotal: 31,352
Adjustment Factor: 1.5100
Total: 47,342
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 125 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 3 - Within 3 to 5 Years
Requirement Name Plumbing Fixtures: Public Restrooms Antiquated -
Not ADAAG Compliant
Requirement ID REQ-7093
Linked System Plumbing Fixtures Inspection Date 12/10/2007
Prime System Plumbing Fixtures Finish Date -
Category Accessibility Status Open
Inspector Puckett Actual Cost 0
Action Date 12/10/2010 Estimated Cost 4,653,780
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The finishes and fixtures in the majority of the public use restrooms throughout the building are antiquated, worn and do not comply with ADAAG
accessibility requirements.
The existing restroom construction and fixtures do not meet the (2002 amended) ADAAG requirements per sections 4.13, 4.15, 4.16, and 4.18 regarding
compliant door widths, toilets, urinals, lavatory heights and clearances and stall partitions.
PHOTOS
Plumbing Fixtures
Plumbing Fixtures: Aged - Typical
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 126 of
Plumbing Fixtures 1
Plumbing Fixtures: Restroom Aged/Non ADAAG Compliant Men's Room 2039.
Plumbing Fixtures
Plumbing Fixtures: Aged - Typical
Plumbing Fixtures 2
Plumbing Fixtures: Restroom Aged/Non ADAAG Compliant Men's Room 4500
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 127 of
Plumbing Fixtures 3
Plumbing Fixtures: Restroom Aged/Non ADAAG Compliant Women's Restroom
4508
ACTION DESCRIPTION
At the time of plumbing renovation, architectural coordination of all restroom work is required to include fixtures, walls, floors, partitions and
architectural fixtures to be handicap accessible.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AD20101201800 Water closetss, battery mount, wall hung, side by side,
each additional water closet, add
400.00 Ea. 1,802.17 720,868
AD20102201800 Urinals, battery mount, side by side, each additional
urinal, add
128.00 Ea. 1,224.24 156,703
AD20103201800 Lavatories, battery mount, side by side, each additional
lavatory, add
368.00 Ea. 1,376.53 506,563
LCARPJ Carpenters 480.00 hour 57.49 27,595
LCEFIJ Cement Finishers 240.00 hour 52.01 12,482
LCLABJ Common Building Laborers 480.00 hour 45.47 21,826
LELECJ Electricians 400.00 hour 64.91 25,964
LPLUHJ Plumber Helpers 400.00 hour 52.85 21,140
LPLUMJ Plumbers 400.00 hour 67.88 27,152
LPORDJ Painters, Ordinary 400.00 hour 48.95 19,580
LPORHJ Painters Helper 400.00 hour 39.12 15,648
LTILFJ Tile Layers 400.00 hour 51.78 20,712
LTILHJ Tile Layers Helpers 400.00 hour 40.83 16,332
U022203300300 Selective demolition, dump charges, typical urban city,
rubbish only, includes tipping fees only
39.00 Ton 109.20 4,259
U022203500840 Selective demolition, rubbish handling, dumpster, 40
C.Y., 13 ton capacity, weekly rental, includes one dump
per week, cost to be added to demolition cost.
24.00 Week 1,577.29 37,855
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 128 of
Code Description Quantity Unit Unit Cost Total Cost
U087101001450 Door hardware, automatic openers, commercial, electronic
door opener, for single swing door, per opening, incl.
motion sensor, 12V control box, motor
84.00 Opng. 5,174.46 434,655
U087101001750 Door hardware, automatic openers, commercial, for
handicap actuator buttons (2), incl. 12V DC wiring, add
84.00 Pr. 794.74 66,758
U090601303760 Walls and partitions demolition, tile, ceramic, on walls 33,792.00 S.F. 1.11 37,509
U093101001000 Ceramic tile, cove base, thin set, 6" x 4-1/4" h 683.00 L.F. 8.68 5,928
U093101001800 Ceramic bathroom accessories, average 84.00 Ea. 19.39 1,629
U093101003270 Ceramic tile, floors, glazed, thin set, color group 1, 12" x
12"
27,000.00 S.F. 6.80 183,600
U093101005400 Ceramic tile, walls, interior, thin set, 4-1/4" x 4-1/4" 33,792.00 S.F. 6.25 211,200
U101601000200 Partitions, toilet, cubicles, ceiling hung, powder coated
steel
340.00 Ea. 756.57 257,234
U101601000600 Partitions, toilet, cubicles, incl. 52" grab bars, ceiling
hung, for handicap units, add
84.00 Ea. 429.00 36,036
U101801005200 Partitions, toilet, urinal screen, floor mounted, marble 96.00 Ea. 777.82 74,671
U108101000610 Toilet Accessories, dispenser units, towel dispenser &
waste receptacle, 18 gallon capacity
84.00 Ea. 483.51 40,615
U108101001100 Toilet Accessories, grab bars, straight, stainless steel, 36"
long
84.00 Ea. 64.11 5,385
U108101003000 Toilet Accessories, mirror, 18" x 24", with stainless steel
3/4" square frame
346.00 Ea. 84.46 29,223
U108101005000 Toilet Accessories, soap dispenser, stainless steel,
recessed, liquid
168.00 Ea. 203.01 34,106
U108101006200 Toilet Accessories, toilet tissue dispenser, stainless steel,
surface mounted, double roll
340.00 Ea. 46.82 15,919
U150806002945 Insulation, insulated protectors (ADA), for exposed piping
under sinks or lavatories, vinylcoated foam, velcro tabs, p
trap, 1-1/4" or 1-1/2"
84.00 Ea. 37.38 3,140
U150806002965 Insulation, insulated protectors (ADA), for exposed piping
under sinks or lavatories, vinylcoated foam, velcro tabs,
valve and supplycover, 1/2", 3/8", and 7/16" pipe size
84.00 Ea. 36.39 3,057
U150806002975 Insulation, insulated protectors (ADA), for exposed piping
under sinks or lavatories, vinylcoated foam, velcro tabs,
extension draincover, 1-1/4", or 1-1/2" pipe size
84.00 Ea. 38.26 3,214
U150806002985 Insulation, insulated protectors (ADA), for exposed piping
under sinks or lavatories, vinylcoated foam, velcro tabs,
tailpiece offset (wheelchair), 1-1/4" pipe size
84.00 Ea. 40.68 3,417
Subtotal: 3,081,974
Adjustment Factor: 1.5100
Total: 4,653,780
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 129 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 3 - Within 3 to 5 Years
Requirement Name Security and Detection Systems: Break Glass
Detectors Lack Adequate Coverage
Requirement ID REQ-20983
Linked System Security and Detection Systems Inspection Date 12/10/2007
Prime System Security and Detection Systems Finish Date -
Category Security Status Open
Inspector Salomonsson Actual Cost 0
Action Date 12/10/2010 Estimated Cost 44,863
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Perimeter office spaces on the first and ground levels with windows adjacent to the street level do not have adequate coverage of break glass detectors.
The facility is prone to criminal break-ins thorough perimeter windows. The present arrangement does not appear to be fully compliant with GSA
Standard P100 (year 2000), section 8.10.
PHOTOS
Security and Detection Systems
Security and Detection Systems: Break Glass Detectors Lacks Adequate
Coverage - Room 1912.
ACTION DESCRIPTION
Provide additional break glass detectors serving perimeter, scalable windows accessible from levels one and the ground. All devices, existing and new,
should be fully compliant.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AD50201250560 Receptacle duplex 120 V grounded, 20 A with box, plate,
3/4" EMT & wire
2.00 Ea. 249.37 499
LELECJ Electricians 80.00 hour 64.91 5,193
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 130 of
Code Description Quantity Unit Unit Cost Total Cost
U137200652200 Detection Systems, indicating panels, 10 channel, excl.
wires & conduit
2.00 Ea. 1,693.40 3,387
U137200653400 Detection Systems, glass break alarm switch, excl. wires
& conduit
40.00 Ea. 120.33 4,813
U161201209020 Metal clad cable, copper, steel clad, 600 volt, 3 conductor,
#14
4.00 C.L.F. 394.67 1,579
U161202800030 Control cable, copper, THHN wire with PVC jacket, 600
V, 3 wires, #14
20.00 C.L.F. 114.79 2,296
U161322055000 Electric metallic tubing (EMT), 1/2" diameter, to 15' high,
incl 2 terminations, 2 elbows & 11 beam clamps per 100
LF
2,000.00 L.F. 4.09 8,180
U161322055200 Electric metallic tubing (EMT), field bends, 45 Deg. to 90
Deg., 1/2" diameter
200.00 Ea. 6.38 1,276
U161366000150 Outlet boxes, pressed steel, 4" square 80.00 Ea. 31.11 2,489
Subtotal: 29,711
Adjustment Factor: 1.5100
Total: 44,863
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 131 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 3 - Within 3 to 5 Years
Requirement Name Wall Finish: Marble Base Damaged
Requirement ID REQ-22943
Linked System Wall Finishes Inspection Date 04/09/2008
Prime System Wall Finishes Finish Date -
Category Appearance Status Open
Inspector Darrah, Lyle Actual Cost 0
Action Date 04/09/2011 Estimated Cost 4,134
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
In the historically significant 7th Street entrance lobby, the marble base near the passenger and service elevators is damaged from carts. Recommend
repairs.
PHOTOS
ACTION DESCRIPTION
Remove damaged marble base and replace with matching material. Dispose of waste and provide protection as required.
Quarry tile installation costs used for budgetary purposes. The actual material and installation should matching existing marble base.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LMARBJ Marble Setters 18.00 hour 54.43 980
U015408000050 Tarpaulins, cotton duck cloth, 10 oz. to 13.13 oz. per S.Y.,
max
300.00 S.F. 0.61 183
U093301000100 Quarry tile, base, cove, or sanitary, mud set, 1/2" thick, 2"
or 5" high
20.00 L.F. 12.09 242
U096351009000 Marble flooring, minimum equipment/labor charge 5.00 Job 266.67 1,333
Subtotal: 2,738
Adjustment Factor: 1.5100
Total: 4,134
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 132 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 3 - Within 3 to 5 Years
Requirement Name Wall Finish: Marble Panels Dirty and Grout
Cracking
Requirement ID REQ-22942
Linked System Wall Finishes Inspection Date 04/09/2008
Prime System Wall Finishes Finish Date -
Category Appearance Status Open
Inspector Darrah, Lyle Actual Cost 0
Action Date 04/09/2011 Estimated Cost 44,741
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
In the historically significant 7th Street entrance lobby the marble wall finish is dirty and the grout joints are showing signs of age. Recommend surface
cleaning and replacement of the joint material.
PHOTOS
ACTION DESCRIPTION
Remove the existing grout between panels and regrout. Clean all marble panels. Install protection as required to protect adjacent surfaces with extra
precautions around the wall murals.
Regrout cost based on ceramic tile costs as the method and materials are similar in cost and final product. Cleaning hours are based on two cleaners for
one week.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LCLABJ Common Building Laborers 40.00 hour 45.47 1,819
LCLNRJ Cleaner 80.00 hour 44.96 3,597
LMARBJ Marble Setters 40.00 hour 54.43 2,177
U015408000050 Tarpaulins, cotton duck cloth, 10 oz. to 13.13 oz. per S.Y.,
max
5,500.00 S.F. 0.61 3,355
U022203500700 Selective demolition, rubbish handling, dumpster, 10
C.Y., 4 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
1.00 Week 366.38 366
U093101009000 Ceramic tile, regrout tile on wall, 4-1/2" x 4-1/2" or larger 4,424.00 S.F. 4.14 18,315
Subtotal: 29,630
Adjustment Factor: 1.5100
Total: 44,741
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 133 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 3 - Within 3 to 5 Years
Requirement Name Wall Finishes: Marble Panels Aged/Deteriorated
Requirement ID REQ-7895
Linked System Wall Finishes Inspection Date 12/10/2007
Prime System Wall Finishes Finish Date -
Category Integrity Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2010 Estimated Cost 47,486
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The marble panels on the first floor D Street entrances and on the ground level 7th Street entrance and elevator lobbies are in need of repair and
repointing. The marble panels have aged and the mortar joints have eroded.
PHOTOS
Wall Finishes
Wall Finishes: Marble Cracked/Damaged - 7th Street Entrance
Wall Finishes
Wall Finish: Marble Aging - 7th Street Entrance
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 134 of
ACTION DESCRIPTION
Rake out by hand and repoint 100% of all cracked or otherwise deteriorated mortar joints in the marble wall cladding of the elevator and entrance lobbies,
repair or fill all chips. This work is to include all baseboards and pilasters (assumes 50% of all joints). Repointing grout shall be tooled flush and match
the color of the original grout. Treat and seal all areas when complete.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LHELPJ Helpers Average (5 trades) 80.00 hour 43.43 3,474
LMARBJ Marble Setters 80.00 hour 54.43 4,354
LPORDJ Painters, Ordinary 40.00 hour 48.95 1,958
U048505009000 Marble, minimum labor/equipment charge 60.00 Job 361.02 21,661
Subtotal: 31,448
Adjustment Factor: 1.5100
Total: 47,486
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 135 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 3 - Within 3 to 5 Years
Requirement Name Wall Finishes: Possibly Historic Paint Peeling
Requirement ID REQ-20906
Linked System Wall Finishes Inspection Date 12/10/2007
Prime System Wall Finishes Finish Date -
Category Appearance Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2010 Estimated Cost 9,484
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Walls and ceiling in the 7th Street entrance are peeling. Finishes underneath the paint in the entrance area is suspected to be historic. Prior to painting, an
historic study needs to be conducted to check for original finishes.
PHOTOS
Wall Finishes
Wall Finishes: Historic Pealing Paint - 7th Street Entrance
ACTION DESCRIPTION
Conduct historic study to determine the existing paint from origin of building prior to prepare and paint walls and ceiling in the 7th Street entrance.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
U013107000140 Field engineer, maximum 3.00 Week 2,093.70 6,281
Subtotal: 6,281
Adjustment Factor: 1.5100
Total: 9,484
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 136 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 4 - 5+ Years
Requirement Name Ceiling Finishes: Polychrome Cornice Painted
Over
Requirement ID REQ-22944
Linked System Ceiling Finishes Inspection Date 04/09/2008
Prime System Ceiling Finishes Finish Date -
Category Appearance Status Open
Inspector Darrah, Lyle Actual Cost 0
Action Date 04/09/2018 Estimated Cost 100,975
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
In the historically significant 7th Street entrance lobby, the original plaster work at the cornices and cross beams were finished with an ornate polychrome
treatment. Through the life of the building the treatment was not maintained and eventually white washed. To restore the historical fabric of the lobby it is
recommended that a study be conducted to determine the original paint palette and restore the original colors.
PHOTOS
ACTION DESCRIPTION
Conduct a study to determine the original paint palette. The study will involve document research, historical trends during the original construction and
destructive demolition within the lobby and other parts of the building. Upon completion of the study, repair, repaint the ceiling and restore the cornice
and cross beam finishes to the original polychrome finish.
Install protection as required to protect adjacent surfaces with extra precautions around the wall murals.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
E015904000160C Rent aerial lift to 25'high 2000 lb cap scissor type 5.00 Ea./day 67.93 340
LCLABJ Common Building Laborers 40.00 hour 45.47 1,819
LCLNRJ Cleaner 40.00 hour 44.96 1,798
LPLASJ Plasterers 40.00 hour 50.62 2,025
LPORDJ Painters, Ordinary 40.00 hour 48.95 1,958
U013107000140 Field engineer, maximum 2.00 Week 2,093.70 4,187
U015408000050 Tarpaulins, cotton duck cloth, 10 oz. to 13.13 oz. per S.Y.,
max
10,000.00 S.F. 0.61 6,100
U092101000402 Gypsum Plaster, 2 coats, on ceilings, with perlite or
vermiculite, lath excluded
4,500.00 S.F. 3.23 14,535
U099106309220 Paints & Coatings, misc. int., trusses & wood frames,
paint 2 coats, oil base, brushwork
24,260.00 S.F. 0.90 21,834
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 137 of
Code Description Quantity Unit Unit Cost Total Cost
U099109201300 Paints & Coatings, walls & ceilings, interior, concrete,
drywall or plaster, oil base, 3 coats, sand finish,
brushwork
5,500.00 S.F. 1.05 5,775
U099109201340 Paints & Coatings, walls & ceilings, interior, concrete,
drywall or plaster, oil base, 3 coats, sand finish, roller
550.00 S.F. 0.79 435
U099909100770 Surface Preparation, interior, ceiling, wash, light 24,260.00 S.F. 0.25 6,065
Subtotal: 66,871
Adjustment Factor: 1.5100
Total: 100,975
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 138 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 4 - 5+ Years
Requirement Name Distribution Systems: Aged and Inadequate
Ductwork
Requirement ID REQ-6435
Linked System Distribution Systems Inspection Date 12/10/2007
Prime System Distribution Systems Finish Date -
Category Capacity/Design Status Open
Inspector Puckett Actual Cost 0
Action Date 12/10/2017 Estimated Cost 8,143,476
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The ductwork supplying the interior of the building was originally installed in the 1950s and while in fair condition for its age, does not provide adequate
air flow for the change in use of the office space configuration over the years, causing negative pressure in the building and insufficient outside air to be
introduced to the system. The distribution system should be upgraded to meet the requirements of ASHRAE 62.1-2004.
PHOTOS
Distribution System
Distribution System: Aged and Inadequate Ductwork - Typical
ACTION DESCRIPTION
Perform an engineering analysis of the existing ductwork distribution to determine the scope of work and modifications required. Upgrade and reconfigure
the ductwork system as needed to modernized the system to current Building Codes and provide optimum comfort conditioning to the areas served.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LASBEJ Asbestos/Insulation Workers/Pipe Coverer 240.00 hour 64.12 15,389
LCARPJ Carpenters 240.00 hour 57.49 13,798
LSHEEJ Sheet Metal Workers 240.00 hour 67.42 16,181
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 139 of
Code Description Quantity Unit Unit Cost Total Cost
LSKWKI Skilled Workers Average (35 trades) 240.00 hour 59.47 14,273
LSTPIJ Steamfitters or Pipefitters 240.00 hour 68.72 16,493
U013107000140 Field engineer, maximum 8.00 Week 2,093.70 16,750
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
85.00 Ton 121.33 10,313
U022203500840 Selective demolition, rubbish handling, dumpster, 40
C.Y., 13 ton capacity, weekly rental, includes one dump
per week, cost to be added to demolition cost.
7.00 Week 1,577.29 11,041
U022203500940 Selective demolition, rubbish handling, dumpster,
alternate pricing method, rent per month, average for all
sizes, includes one dump per week, cost to be added to
demolition cost.
4.00 Ea. 91.00 364
U150553001570 Ductwork, metal; steel and sst, fabricated, selective
demolition
170,000.00 Lb. 0.97 164,900
U157306009430 Rooftop air conditioner, subassembly for assembly
systems, ductwork, VAV cooling/ton rooftop multizone
and single zone, per ton
1,416.00 Ton 3,611.25 5,113,530
Subtotal: 5,393,030
Adjustment Factor: 1.5100
Total: 8,143,476
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 140 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 4 - 5+ Years
Requirement Name Elevators and Lifts: Abandoned Elevators
Requirement ID REQ-20980
Linked System Not Applicable Inspection Date 12/10/2007
Prime System - Finish Date -
Category Recapture Vacant Space Status Open
Inspector Salomonsson Actual Cost 0
Action Date 12/10/2017 Estimated Cost 51,494
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
There are two antiquated, abandoned passenger elevators ( 1 & 2 ). Remove with the intent to recapture vacated space.
PHOTOS
Elevators and Lifts
Elevators and Lifts: Abandoned Elevators - Roof Elevator Machine Room 1
ACTION DESCRIPTION
Remove abandoned elevators 1 and 2 with the intent to recapture vacated space.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LELECJ Electricians 40.00 hour 64.91 2,596
LELEVJ Elevator Constructors 80.00 hour 78.23 6,258
LSSWKJ Structural Steel Workers 24.00 hour 73.92 1,774
LSSWLJ Welders, Structural Steel 16.00 hour 73.92 1,183
U013107000140 Field engineer, maximum 2.00 Week 2,093.70 4,187
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 141 of
Code Description Quantity Unit Unit Cost Total Cost
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
8.00 Ton 121.33 971
U022203500700 Selective demolition, rubbish handling, dumpster, 10
C.Y., 4 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
2.00 Week 366.38 733
U022203500910 Selective demolition, rubbish handling, dumpster,
alternate pricing method, delivery, average for all sizes,
cost to be added to demolition cost.
1.00 Ea. 91.00 91
U022203701090 Selective demolition, torch cutting, steel, minimum
labor/equipment charge
16.00 Job 352.31 5,637
U140552000050 Elevator, cab, track and equipment, removal 16.00 Stop 666.98 10,672
Subtotal: 34,102
Adjustment Factor: 1.5100
Total: 51,494
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 142 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 4 - 5+ Years
Requirement Name Elevators: Missing Original Paneled Elevator
Doors
Requirement ID REQ-22946
Linked System Elevators and Lifts Inspection Date 04/09/2008
Prime System Elevators and Lifts Finish Date -
Category Appearance Status Open
Inspector Puckett Actual Cost 0
Action Date 04/09/2018 Estimated Cost 128,410
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
In the historically significant 7th Street entrance lobby, the elevator doors are modern in appearance and do not match the original paneled elevator door
design. Recommend replacing the elevator doors and floor indicator panels above the doors with reproductions or complimentary styles of the original
paneled door design.
PHOTOS
ACTION DESCRIPTION
Remove the existing doors and frames and install paneled doors consistent with the original design. Replace the floor indicators above the doors with
reproductions that also reflect the original design intent. Dispose of waste.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
U142802003075 Elevator options, passenger, automatic controls, 5 car
group
1.00 Ea. 58,040.63 58,041
U142802003200 Elevator options, passenger, center opening 2 speed doors 5.50 Ea. 3,471.98 19,096
U142802003725 Elevator options, passenger, cab finishes (based on 3500
lb cab size), signal devices, position indicators, up to 3
5.00 Ea. 856.91 4,285
U142802003750 Elevator options, passenger, cab finishes (based on 3500
lb cab size), signal devices, position indicators, per each
over 3
5.00 Ea. 723.69 3,618
Subtotal: 85,040
Adjustment Factor: 1.5100
Total: 128,410
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 143 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 4 - 5+ Years
Requirement Name Emergency Light and Power Systems: Abandoned
Generator
Requirement ID REQ-20981
Linked System Not Applicable Inspection Date 12/10/2007
Prime System - Finish Date -
Category Recapture Vacant Space Status Open
Inspector Salomonsson Actual Cost 0
Action Date 12/10/2017 Estimated Cost 9,532
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
There is an abandoned diesel emergency generator in Room B03. This generator is rated for 60kW at 120/208V and it formerly served a room on the sixth
floor. System includes complete generator assembly. The generator is approximately twenty to twenty five years old and is nearing the end of its expected
useful life.
PHOTOS
Emergency Light and Power Systems
Emergency Light and Power Systems: Abandoned Generator - Room B03.
ACTION DESCRIPTION
Remove existing abandoned generator from room B03, with the intent to recapture vacated space.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LWRCKJ *Wrecking 24.00 hour 50.25 1,206
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
4.00 Ton 121.33 485
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 144 of
Code Description Quantity Unit Unit Cost Total Cost
U022203500725 Selective demolition, rubbish handling, dumpster, 20
C.Y., 8 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
1.00 Week 940.31 940
U022203701090 Selective demolition, torch cutting, steel, minimum
labor/equipment charge
4.00 Job 352.31 1,409
U160553502080 Generator set, 3 ph 4 wire, 277/480 V, 100 kW, electrical
demolition, remove, incl accessories
1.00 Ea. 2,271.98 2,272
Subtotal: 6,313
Adjustment Factor: 1.5100
Total: 9,532
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 145 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 4 - 5+ Years
Requirement Name Floor Finish: Damaged Terrazzo Finish
Requirement ID REQ-22949
Linked System Wall Finishes Inspection Date 04/09/2008
Prime System Wall Finishes Finish Date -
Category Appearance Status Open
Inspector Darrah, Lyle Actual Cost 0
Action Date 04/09/2018 Estimated Cost 25,316
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
In the historically significant 7th Street entrance lobby, the terrazzo floor finish is damaged in a few areas from the Magnetrons x-ray machines. Upon the
removal or replacement of these machines the floor should be repaired and the entire floor cleaned and resealed. Minor damage such as surface cracks that
do not pose a trip hazard and do not need to be repaired in accordance with the intent of the historical preservation.
PHOTOS
ACTION DESCRIPTION
Upon the removal or replacement of the Magnetrons (x-ray machines) repair holes with colored epoxy or matching terrazzo and aggregate. Clean and seal
entire floor area.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LCLABJ Common Building Laborers 40.00 hour 45.47 1,819
LCLNRJ Cleaner 80.00 hour 44.96 3,597
U018322301050 Sealing concrete floor, oil or urethane base, 2 coats, max 5,461.00 S.F. 0.90 4,915
U094502000500 Tile or Terrazzo Base, scratch and brown coat only 16.00 S.F. 6.06 97
U094502009000 Tile or Terrazzo Base, minimum labor/equipment charge 16.00 Job 396.12 6,338
Subtotal: 16,765
Adjustment Factor: 1.5100
Total: 25,316
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 146 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 4 - 5+ Years
Requirement Name Lighting Equipment: Missing Art Deco Light
Fixtures
Requirement ID REQ-22951
Linked System Lighting Equipment Inspection Date 04/09/2008
Prime System Lighting Equipment Finish Date -
Category Modernization Status Open
Inspector Darrah, Lyle Actual Cost 0
Action Date 04/09/2018 Estimated Cost 82,967
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
In the historically significant 7th Street entrance lobby, the original Art Deco light fixtures have been removed and replaced with indirect light fixtures. To
restore the historical fabric of the lobby the existing light fixtures should be removed and replaced with bronze reproductions of the original Art Deco
fixtures.
PHOTOS
ACTION DESCRIPTION
Remove the existing indirect lamp fixtures and replace with bronze reproductions of the original Art Deco pendant fixtures.
Coordinate work with plaster ceiling and cornice painting. Ceiling patching and repair covered in the painting requirement.
Note: The incandescent lamp selected for the action line item is representative of the cost required for bronze reproductions. Approximately the cost of
each lamp could be broken down into three equal parts: 1/3 of the costs for custom design services of an AE and the lamp fabricator, 1/3 of the lamp costs
for custom lamp holder design and circuitry and the final third for fabrication and delivery. The specific lamp and wattages may vary based on energy
efficiency requirements.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LELECJ Electricians 160.00 hour 64.91 10,386
U022203500700 Selective demolition, rubbish handling, dumpster, 10
C.Y., 4 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
1.00 Week 366.38 366
U160555005000 Ballast, fluorescent fixture, electrical demolition, remove 12.00 Ea. 23.67 284
U165856002240 Incandescent lamp, interior, 1500 watt, PS52 6.00 C 7,318.19 43,909
Subtotal: 54,945
Adjustment Factor: 1.5100
Total: 82,967
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 147 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 4 - 5+ Years
Requirement Name Local Area Networks: Cabling Improperly
Supported
Requirement ID REQ-18743
Linked System Local Area Networks Inspection Date 12/10/2007
Prime System Local Area Networks Finish Date -
Category Building Code Status Open
Inspector Salomonsson Actual Cost 0
Action Date 12/10/2017 Estimated Cost 685,884
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
A sampling above suspended ceilings indicates that telecommunication cables/wires are loosely strung and supported by means not compliant with
NEC-2005 Edition Section 800-6. Cables all over the building were seen taped, tie wrapped and secured by other means to electrical and mechanical
piping. Cables were also seen run on suspended ceiling tiles. Repairs and modifications are warranted.
PHOTOS
Local Area Networks
Local Area Networks: Cabling Improperly Supported - Level 6 Corridor.
ACTION DESCRIPTION
Install cable tray where required for adequate support of telecom wire and cable. Remove and reinstall loosely run and unsupported wiring and cable
through the building. Carpenter and painter allocated for cutting and patching.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LCARPJ Carpenters 160.00 hour 57.49 9,198
LCLNRJ Cleaner 160.00 hour 44.96 7,194
LELECJ Electricians 400.00 hour 64.91 25,964
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 148 of
Code Description Quantity Unit Unit Cost Total Cost
LHELPJ Helpers Average (5 trades) 400.00 hour 43.43 17,372
LPORDJ Painters, Ordinary 80.00 hour 48.95 3,916
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
4.00 Ton 121.33 485
U065104005000 Fiberglass Castings, threaded rod, 3/8" diameter 4,000.00 L.F. 7.06 28,240
U091301009000 Ceiling Suspension System, minimum labor/equipment
charge
120.00 Job 84.55 10,146
U160703203300 Washers, galvanized steel, 3/8" diameter 20.00 C 23.32 466
U160703203800 Channels, steel, 3/4" x 1-1/2" 1,336.00 L.F. 14.78 19,746
U160703204250 Spring nuts, steel channel, long, 3/8" 2,000.00 Ea. 8.77 17,540
U161207509000 Special wires & fittings, minimum labor/equipment
charge
20.00 Job 142.00 2,840
U161311050400 Cable tray, ladder type, galvanized steel, 4" deep, 4" rung
spacing, 18" wide, to 15' elevation, incl fittings &
supports
8,000.00 L.F. 34.84 278,720
U161311052590 Cable tray, ladder type, galvanized steel tray connector 800.00 Ea. 40.50 32,400
Subtotal: 454,228
Adjustment Factor: 1.5100
Total: 685,884
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 149 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 4 - 5+ Years
Requirement Name Local Area Networks: Dedicated Equipment Space
Lacking
Requirement ID REQ-18744
Linked System Local Area Networks Inspection Date 12/10/2007
Prime System Local Area Networks Finish Date -
Category Building Code Status Open
Inspector Salomonsson Actual Cost 0
Action Date 12/10/2017 Estimated Cost 910,313
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Telecommunications equipment is not installed in dedicated closets as required by the BICSI Telecommunication Distribution Method Manual (TDMM)
9th edition Chapter 7 and Facilities Standard P-100, chapter 6.15. The present arrangement with telecom equipment sharing space with electrical
equipment hinders system accessibility, expansion and proper management of cabling. The installation of vertically stacked telecom closets should be
considered.
PHOTOS
Local Area Networks
Local Area Networks: Dedicated Equipment Space Lacking - Electrical Closet
3628.
ACTION DESCRIPTION
Relocate all of the telecommunication equipment located in the stacked electrical rooms to dedicated closets. Advancement of this correction will require
allocation of space in the immediate area of the deficient location. Additional costs are included for modifications to allocated space. Two dedicated
telecommunication rooms per floor (levels 1 thru 7) is recommended. Estimated size for each closet is 6'x8'. Space vacated within existing electrical
closets should be utilized for electrical equipment as may be needed for any future renovations or expansions.
ESTIMATE
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 150 of
Code Description Quantity Unit Unit Cost Total Cost
AC10101022010 Concrere block (CMU) partition, regular weight, hollow,
8" thick, gyp plaster 2 coat, 1 side
4,704.00 S.F. 10.13 47,652
AD50102301440 Branch installation 600 V, including EMT conduit and
THW wire, 100 A
700.00 L.F. 19.76 13,832
AD50201250600 Receptacle duplex G.F.I. 15 A with box, plate, 3/4" EMT
& wire
140.00 Ea. 275.02 38,503
AD50201250680 Toggle switch single pole, 15 A with box, plate, 3/4"
EMT & wire
140.00 Ea. 237.30 33,222
AD50201350520 Miscellaneous power, 3 watts 672.00 S.F. 0.74 497
AD50202100240 Fluorescent fixtures recess mounted in ceiling, 2 watt per
SF, 40 FC, 10 fixtures @40 watt per 1000 SF
672.00 S.F. 4.92 3,306
LCARPJ Carpenters 560.00 hour 57.49 32,194
LCLABJ Common Building Laborers 560.00 hour 45.47 25,463
LCLNRJ Cleaner 280.00 hour 44.96 12,589
LWRCKJ *Wrecking 240.00 hour 50.25 12,060
RD50931500020 Replace computer ground system 6.00 M.L.F. 2,019.09 12,115
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
14.00 Ton 121.33 1,699
U022203500700 Selective demolition, rubbish handling, dumpster, 10
C.Y., 4 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
8.00 Week 366.38 2,931
U065104005000 Fiberglass Castings, threaded rod, 3/8" diameter 840.00 L.F. 7.06 5,930
U081108205440 Frames, hollow metal, steel, knock down, "B" label,
double, 14 ga., up to 5-3/4" deep, 7'-0" h x 8'-0" w, double
14.00 Ea. 322.39 4,513
U082109500890 Doors, wood, fire, particle core, 7 face plies, "B" label, 90
minutes, oak face, 1-3/4" x 3'-0" x 7'-0"
14.00 Ea. 437.41 6,124
U087101502550 Door hardware, school, single, interior, regular use, incl.
handicap lever
14.00 Door 482.57 6,756
U099109200840 Paints & Coatings, walls & ceilings, interior, concrete,
drywall or plaster, oil base, 2 coats, smooth finish, roller
4,704.00 S.F. 0.63 2,964
U137200655240 Detection Systems, smoke detector, addressable type,
excl. wires & conduit
14.00 Ea. 274.84 3,848
U158101000110 Metal Ductwork, fabricated rectangular, 100 to 500 lb.,
aluminum alloy 3003-H14, includes fittings, joints,
supports and allowance for a flexible connection, excludes
insulation
1,400.00 Lb. 20.95 29,330
U158301008520 Fans, wall exhauster, centrifugal, auto damper, direct
drive, 1/8" S.P., 610 CFM, 1/20 H.P.
14.00 Ea. 447.86 6,270
U160703203300 Washers, galvanized steel, 3/8" diameter 3.00 C 23.32 70
U160703203550 Lock washers, galvanized steel, 3/8" diameter 3.00 C 19.62 59
U160703203800 Channels, steel, 3/4" x 1-1/2" 504.00 L.F. 14.78 7,449
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 151 of
Code Description Quantity Unit Unit Cost Total Cost
U160703204250 Spring nuts, steel channel, long, 3/8" 3.00 Ea. 8.77 26
U161201209050 Metal clad cable, copper, steel clad, 600 volt, 3 conductor,
#12
14.00 C.L.F. 429.58 6,014
U161207509000 Special wires & fittings, minimum labor/equipment
charge
140.00 Job 142.00 19,880
U161311050200 Cable tray, ladder type, galvanized steel, 4" deep, 4" rung
spacing, 12" wide, to 15' elevation, incl fittings &
supports
840.00 L.F. 31.29 26,284
U161311051070 Cable tray, ladder type, galvanized steel elbow horiz., 90
Deg., 9" rung spacing, 12" radius, 12" wide
56.00 Ea. 217.15 12,160
U161311051760 Cable tray, ladder type, galvanized steel tee horiz., 90
Deg., 9" rung spacing, 12" radius, 12" wide
56.00 Ea. 398.08 22,292
U162608000160 Uninterruptible power supply, charger, inverter, and alarm
1 phase, 120 V, 1.0 kVA, incl 10 minutes battery
14.00 Ea. 2,871.05 40,195
U164407202050 Panelboards, 3 phase 4 wire, main circuit breaker,
120/208 V, 100 amp, 24 circuits, NQOD, incl 20 A 1 pole
plug-in breakers
14.00 Ea. 2,374.33 33,241
U165802000100 Occupancy sensors infrared, ceiling mounted 14.00 Ea. 199.43 2,792
U167104000150 Fiber optic jumper 168.00 Ea. 63.13 10,606
U167104000300 Fiber optic connector 336.00 Ea. 44.65 15,002
U167104000400 Fiber optics, transceiver (low cost bi-directional) 14.00 Ea. 412.22 5,771
U167104000450 Fiber optics, rack housing, 4 rack spaces, 12 panels (144
fibers)
14.00 Ea. 710.52 9,947
U167104001100 Fiber optics cable, 50 microns, 12 fiber, indoor 3,266.00 L.F. 4.70 15,350
U167107507200 Unshielded twisted pair (UTP) cable, stranded, PVC
jacket, #24, 4 pair, category 5
700.00 C.L.F. 105.60 73,920
Subtotal: 602,856
Adjustment Factor: 1.5100
Total: 910,313
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 152 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 4 - 5+ Years
Requirement Name Obsolete Equipment: Abandoned
Requirement ID REQ-18757
Linked System Not Applicable Inspection Date 12/10/2007
Prime System - Finish Date -
Category Mission Status Open
Inspector Puckett Actual Cost 0
Action Date 12/10/2017 Estimated Cost 50,443
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
There is a substantial amount of abandoned equipment throughout the building, especially on the roof. This equipment needs to be identified and removed
from the building both for safety and operational purposes.
PHOTOS
Abandoned Equipment
Obsolete Equipment: Abandoned - Various Locations
ACTION DESCRIPTION
Remove abandoned equipment.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
E015906002200D Rent crane truck mount, cable 8x4 drive 115 ton, 15'
radius
2.00 Ea./day 2,554.90 5,110
LCLABI Common Building Laborers 120.00 hour 46.25 5,550
LCLABJ Common Building Laborers 240.00 hour 45.47 10,913
LELECJ Electricians 40.00 hour 64.91 2,596
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 153 of
Code Description Quantity Unit Unit Cost Total Cost
LPLUMJ Plumbers 40.00 hour 67.88 2,715
LROFCJ Roofers, Composition 30.00 hour 53.55 1,607
LSKWKJ Skilled Workers Average (35 trades) 30.00 hour 58.70 1,761
U022203500840 Selective demolition, rubbish handling, dumpster, 40
C.Y., 13 ton capacity, weekly rental, includes one dump
per week, cost to be added to demolition cost.
2.00 Week 1,577.29 3,155
Subtotal: 33,406
Adjustment Factor: 1.5100
Total: 50,443
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 154 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 5: Does Not Meet Current
Codes/Standards
Requirement Name Distribution Systems: Fire Dampers Inspection
Not Current
Requirement ID REQ-18756
Linked System Distribution Systems Inspection Date 12/10/2007
Prime System Distribution Systems Finish Date -
Category Life Safety Status Open
Inspector Puckett Actual Cost 0
Action Date 12/10/2017 Estimated Cost 30,786
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The fire dampers in the building do not appear to have been maintained as outlined in NFPA 80 Section 19.5 and 19.5.
PHOTOS
Fire Protection
Distribution Systems: Fire Dampers Beyond Expected Life - Typical
ACTION DESCRIPTION
Locate and test existing fire dampers for condfition and operability as outlined in NFPA 80, replacing fire dampers that are damaged or otherwise
unreliable.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
U158203003180 Duct accessories, fire damper, curtain type, vertical, 16" x
12", U.L. label, 1-1/2 hour rated
40.00 Ea. 51.34 2,054
U158203003320 Duct accessories, fire damper, curtain type, vertical, 24" x
16", U.L. label, 1-1/2 hour rated
60.00 Ea. 88.59 5,315
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 155 of
Code Description Quantity Unit Unit Cost Total Cost
U158203009900 Duct accessories, minimum labor/equipment charge 100.00 Job 130.19 13,019
Subtotal: 20,388
Adjustment Factor: 1.5100
Total: 30,786
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 156 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 5: Does Not Meet Current
Codes/Standards
Requirement Name Distribution Systems: Perimeter Ductwork Lacks
Outside Air Intake
Requirement ID REQ-7195
Linked System Air Distribution Systems Inspection Date 12/10/2007
Prime System Air Distribution Systems Finish Date -
Category Capacity/Design Status Open
Inspector Puckett Actual Cost 0
Action Date 12/10/2017 Estimated Cost 3,566,944
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The ductwork supplying the perimeter of the building was originally installed in the 1950s and does not provide adequate outside air as required by
ASHRAE 62.1-2004.
PHOTOS
Distribution Systems
Distribution Systems: Perimeter Ductwork, Poor Design - Typical
ACTION DESCRIPTION
Perform an engineering analysis of the perimeter ductwork to determine the scope of work and modifications required. Upgrade the distribution ductowrk
serving the perimeter of the building. Work to include demoltion of the existing ducts, remediation of asbestos for concealed duct runs, and installation of
new ductwork to provide adequate air flows
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LASBEJ Asbestos/Insulation Workers/Pipe Coverer 560.00 hour 64.12 35,907
LSHEEI Sheet Metal Workers 560.00 hour 68.19 38,186
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 157 of
Code Description Quantity Unit Unit Cost Total Cost
U013107000140 Field engineer, maximum 8.00 Week 2,093.70 16,750
U132811200400 Bulk Asbestos Removal, duct or AHU insulation, incl.
disp. tools & 4 suits & resp./day/worker
10,000.00 S.F. 5.25 52,500
U150553001000 Air conditioner, ductwork, rigid, 4" x 8", selective
demolition
10,000.00 L.F. 1.82 18,200
U157306009420 Rooftop air conditioner, subassembly for assembly
systems, ductwork per ton for rooftop multizone units
944.00 Ton 2,331.22 2,200,672
Subtotal: 2,362,215
Adjustment Factor: 1.5100
Total: 3,566,944
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 158 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 5: Does Not Meet Current
Codes/Standards
Requirement Name Identifying Devices: Signage Aged/Missing
Requirement ID REQ-7825
Linked System Identifying Devices Inspection Date 12/10/2007
Prime System Identifying Devices Finish Date -
Category Accessibility Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2017 Estimated Cost 175,433
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Interior signage in the building is aged and in some area missing. The room signage is not compliant with 2004 ADAAG 703.2 because it does not contain
Braille characters. There are no signs showing the accessible route for egress. This does not conform with IBC Chapter 1007.
PHOTOS
Identifying Devices
Identifying Devices: Fittings Signage not ADAAG Compliant - Room 1507
ACTION DESCRIPTION
Provide signage throughout building including elevators that complies with IBC Chapter 1007 and ADAAG 4.30.4.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LCARPJ Carpenters 120.00 hour 57.49 6,899
LCLABJ Common Building Laborers 120.00 hour 45.47 5,456
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
1.00 Ton 121.33 121
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 159 of
Code Description Quantity Unit Unit Cost Total Cost
U022203500700 Selective demolition, rubbish handling, dumpster, 10
C.Y., 4 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
1.00 Week 366.38 366
U104402001100 Signs, flexible door sign, adhesive back, w/Braille, 5/8"
letters, 8" x 2"
1,800.00 Ea. 42.37 76,266
U104402001600 Signs, graphic symbols, adhesive back, 8" x 8" 600.00 Ea. 45.12 27,072
Subtotal: 116,181
Adjustment Factor: 1.5100
Total: 175,433
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 160 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 5: Does Not Meet Current
Codes/Standards
Requirement Name Interior Doors: Hardware not ADA Compliant
Requirement ID REQ-8982
Linked System Interior Doors Inspection Date 12/10/2007
Prime System Interior Doors Finish Date -
Category Accessibility Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2017 Estimated Cost 1,236,335
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Typical interior office doors have knob type handles that are not handicap accessible required by UFAS 4.13.9. Door hardware on floors 1 through 7
require lever locksets. Total 2042 locksets.
PHOTOS
Interior Doors
Interior Doors: Hardware Not ADA Compliant - Room 6018
ACTION DESCRIPTION
Replace all doorknob hardware on floors 1 through 7 with lever handle locksets along accessible building routes such as entrance doors, fire doors, stair
doors, and corridor doors to public spaces such as offices, restrooms, conference rooms.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LCARPJ Carpenters 204.00 hour 57.49 11,728
LCLAMJ Common Maintenance Laborer 204.00 hour 31.60 6,446
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
4.00 Ton 121.33 485
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 161 of
Code Description Quantity Unit Unit Cost Total Cost
U022203500700 Selective demolition, rubbish handling, dumpster, 10
C.Y., 4 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
10.00 Week 366.38 3,664
U087104000015 Door hardware, entrance locks, cylinder, grip handle,
deadlocking latch
2,042.00 Ea. 200.53 409,482
U087104000900 Door hardware, entrance locks, for handicapped lever, add 2,042.00 Ea. 189.50 386,959
Subtotal: 818,765
Adjustment Factor: 1.5100
Total: 1,236,335
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 162 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 5: Does Not Meet Current
Codes/Standards
Requirement Name Sanitary Waste: Corroded Floor Drains
Requirement ID REQ-98158
Linked System Sanitary Waste Inspection Date 12/10/2007
Prime System Sanitary Waste Finish Date -
Category Building Code Status Open
Inspector Puckett Actual Cost 0
Action Date 12/10/2017 Estimated Cost 150,469
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
At the time of the assessment, it was observed that many of the floor drains in the mechanical rooms were worn and corroded. Replacement is required to
ensure reliable drainage.
PHOTOS
ACTION DESCRIPTION
Replace the corroded floor drains as required and inspect the piping to determine its condition and free area for drainage. Work to include cutout, rough in,
and fit up to exiting plumbing systems.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AD20908101080 Pipe cast iron, soil, B & S, no hub, 3" diameter 1,400.00 L.F. 26.10 36,540
LPLUHJ Plumber Helpers 160.00 hour 52.85 8,456
LPLUMJ Plumbers 160.00 hour 67.88 10,861
RD20333100030 Replace floor drain w/o bucket 28.00 Ea. 945.94 26,486
U022203108500 Selective demolition, cutout, remove, minimum
labor/equipment charge
56.00 Job 89.96 5,038
U029552109060 Pipe, internal cleaning and inspection, television camera
with video, up to 500 linear feet
14.00 Total 876.25 12,268
Subtotal: 99,648
Adjustment Factor: 1.5100
Total: 150,469
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 163 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 5: Does Not Meet Current
Codes/Standards
Requirement Name Sanitary Waste: Restroom Floor Drains Not
Installed
Requirement ID REQ-7210
Linked System Sanitary Waste Inspection Date 12/10/2007
Prime System Sanitary Waste Finish Date -
Category Building Code Status Open
Inspector Puckett Actual Cost 0
Action Date 12/10/2017 Estimated Cost 168,048
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The multi-fixture restrooms are not equipped with floor drains as required by GSA PBS P100-5.24.
PHOTOS
Sanitary System
Sanitary Waste Equipment: Restroom Floor Drains Missing - Typical
ACTION DESCRIPTION
Install floor drains in the restrooms as required, including hose bibbs to prime the traps. Work to include cutout, rough in, and fit up to exiting plumbing
systems.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AD20908101080 Pipe cast iron, soil, B & S, no hub, 3" diameter 1,400.00 L.F. 26.10 36,540
AD20908101880 Copper tubing, hard temper, solder, type M, 3/4" diameter 700.00 L.F. 11.84 8,288
LPLUHJ Plumber Helpers 160.00 hour 52.85 8,456
LPLUMJ Plumbers 160.00 hour 67.88 10,861
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 164 of
Code Description Quantity Unit Unit Cost Total Cost
RD20333100030 Replace floor drain w/o bucket 28.00 Ea. 945.94 26,486
U022203108500 Selective demolition, cutout, remove, minimum
labor/equipment charge
56.00 Job 89.96 5,038
U154115005100 Hydrant, ground box type, all bronze, moderate climate,
polished face and scoriated cover, set flush, 3/4" I.P.S.
connection
28.00 Ea. 557.90 15,621
Subtotal: 111,290
Adjustment Factor: 1.5100
Total: 168,048
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 165 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 5: Does Not Meet Current
Codes/Standards
Requirement Name Stairs: Hand Railing Not Code Compliant
Requirement ID REQ-20904
Linked System Stairs Inspection Date 12/10/2007
Prime System Stairs Finish Date -
Category Building Code Status Open
Inspector Eichner Actual Cost 0
Action Date 12/10/2017 Estimated Cost 1,238,329
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
Hand railing in all stairwells is lacking the 42" high guard railing to the inside of the stairs as required by 2006 IBC Section 1013.2. The hand railing also
does not extend 1 foot or one tread width past the top or bottom of the stairs as per 2006 IBC, Section 1012.5.
PHOTOS
Stairs 3
Stairs: Hand Railing Not ADAAG or IBC Compliant. Stairwell #1 Third Floor
Stairs 4
Stairs: Hand Railing Not ADAAG or IBC Compliant - Stairwell #1, Third Floor
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 166 of
ACTION DESCRIPTION
Install guard railing in stairwells throughout and hand railing on the wall portion of the stairwells.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
LCARPJ Carpenters 160.00 hour 57.49 9,198
LCEFIJ Cement Finishers 80.00 hour 52.01 4,161
LCLABJ Common Building Laborers 160.00 hour 45.47 7,275
LCLAMJ Common Maintenance Laborer 160.00 hour 31.60 5,056
LPSPRJ Painters, Spray 24.00 hour 60.04 1,441
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
4.00 Ton 121.33 485
U022203500700 Selective demolition, rubbish handling, dumpster, 10
C.Y., 4 ton capacity, weekly rental, includes one dump per
week, cost to be added to demolition cost.
4.00 Week 366.38 1,466
U022204280100 Selective demolition, highway guard rails & barriers,
corrugated steel
7,616.00 L.F. 2.41 18,355
U064306201550 Prefabricated wood stairs, stair handrail with balusters 7,616.00 L.F. 96.66 736,163
U064306209000 Prefabricated wood stairs, minimum labor/equipment
charge
136.00 Job 268.28 36,486
Subtotal: 820,085
Adjustment Factor: 1.5100
Total: 1,238,329
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 167 of
Region: 11 - National Capital Region Asset Name: GSA-ROB
Service_Center: Potomac Asset Number: DC0031ZZ
Priority: 5: Does Not Meet Current
Codes/Standards
Requirement Name Stairwell Smoke Proof Enclosure/ Pressurization
System - Not Installed
Requirement ID REQ-98250
Linked System Not Applicable Inspection Date 12/09/2007
Prime System - Finish Date -
Category Building Code Status Open
Inspector Hultgren Actual Cost 0
Action Date 12/09/2017 Estimated Cost 1,332,115
Impact on FCI - Impact on Energy -
REQUIREMENT DESCRIPTION
The International Building Code requires that all exit stairs serving occupants of a floor level located more than 75 feet above the level of exit discharge,
or located more than 30 feet below the level of exit discharge shall be protected by a smoke proof enclosure as specified in Uniform Building Code
Section 905 -Smoke Control. The existing systems for the two core stairwells are aged, and should be replaced with new equipment to ensure system
reliability.
A smoke proof enclosure requires a vestibule outside the stair on each floor opening into the stair. The vestibule must be ventilated by large openings
directly to the outside or by a mechanical ventilation system. The cost of constructing vestibules would be prohibitive and not practical due to space
limitations and are not included. Additional requirements of Section 1005.3.3.7.1.1-3 include providing a two hour fire resistive duct chase assembly,
floor smoke detectors and electrical services to, but not including, the legally required standby power system.
PHOTOS
ACTION DESCRIPTION
Install stairwell pressurization systems as outlined in NFPA 92A. Conduct engineering survey to design system to meet present Code requirements. The
system would consist of supply fans and 2 hour rated supply duct shafts. Supply air would be introduced into the stairs at every other floor. The duct
shafts would be constructed of shaft wall, for ease of construction, to provide the two hour rating. A relief vent would be provided at the top of the stairs to
relieve excess pressure. Provide feeders from the recommended on site standby system to the fans, smoke detectors at each level outside of the stair to
initiate the pressurization of the stair and required interconnections to the building fire alarm system.
ESTIMATE
Code Description Quantity Unit Unit Cost Total Cost
AD50102300280 Feeder installation 600 V, including RGS conduit and
XHHW wire, 200 A
1,400.00 L.F. 50.88 71,232
AD50201452120 Motor installation, three phase, 460 V,20 HP motor size 8.00 Ea. 2,827.10 22,617
LCEFIJ Cement Finishers 480.00 hour 52.01 24,965
LELECJ Electricians 480.00 hour 64.91 31,157
LSHEEJ Sheet Metal Workers 640.00 hour 67.42 43,149
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 168 of
Code Description Quantity Unit Unit Cost Total Cost
NU 158508005860 Ventilator, relief vent, rectangular, aluminum, galvanized
curb, intake/exhaust, 0.05" S.P., 40,000 CFM, 96" x 120",
includes base and damper
8.00 Ea. 8,857.37 70,859
U013107000140 Field engineer, maximum 8.00 Week 2,093.70 16,750
U022203300100 Selective demolition, dump charges, typical urban city,
building construction materials, includes tipping fees only
34.00 Ton 121.33 4,125
U022203500800 Selective demolition, rubbish handling, dumpster, 30
C.Y., 10 ton capacity, weekly rental, includes one dump
per week, cost to be added to demolition cost.
8.00 Week 1,213.30 9,706
U022203600820 Concrete sawing, concrete walls, rod reinforcing, per inch
of depth
14,800.00 L.F. 10.57 156,436
U090601301020 Walls and partitions demolition, drywall, two layers,
glued and nailed
5,800.00 S.F. 0.37 2,146
U091101002000 Metal stud partition, non-load bearing, galvanized, 10'
high, 1-5/8" wide, 25 gauge, 16" O.C., includes top &
bottom track
5,800.00 S.F. 1.23 7,134
U092608000060 Shaft Wall, cavity type on 25 ga. J track & C-H studs, 24"
O.C., 1" thick coreboard wall liner on shaft side, 2 hour
assembly w/double layer, 5/8" fire rated gypsum board on
room side
5,800.00 S.F. 5.54 32,132
U092608000900 Shaft Wall, for taping & finishing, add per side 5,800.00 S.F. 0.43 2,494
U099109200240 Paints & Coatings, walls & ceilings, interior, concrete,
drywall or plaster, oil base, primer or sealer coat, smooth
finish, roller
5,800.00 S.F. 0.34 1,972
U099109200840 Paints & Coatings, walls & ceilings, interior, concrete,
drywall or plaster, oil base, 2 coats, smooth finish, roller
5,800.00 S.F. 0.63 3,654
U137200654175 Detection Systems, fire alarm control panel, addressable
interface device, excluding wires & conduits
8.00 Ea. 326.04 2,608
U137200655240 Detection Systems, smoke detector, addressable type,
excl. wires & conduit
64.00 Ea. 274.84 17,590
U150553001400 Air conditioner, ductwork, rigid, 18" x 24", selective
demolition
1,000.00 L.F. 5.45 5,450
U150553003000 HVAC, mechanical equipment, light items; unit is weight,
not cooling, selective demolition
4.00 Ton 1,103.05 4,412
U150553009000 HVAC, selective demolition, minimum labor/equipment
charge
8.00 Job 514.76 4,118
U158101000570 Metal Ductwork, fabricated rectangular, galvanized steel,
2000 to 5000 lb., includes fittings, joints, supports and
allowance for a flexible connection, excludes insulation
20,000.00 Lb. 6.35 127,000
U158203008260 Duct accessories, multi-blade dampers, parallel blade, 30"
x 18"
40.00 Ea. 249.29 9,972
U158301004240 Fans, centrifugal, airfoil, double width wheel, belt drive,
capacities at 2000 FPM, 2.5" S.P. for motor size indicated,
27,580 CFM, 20 H.P., excludes motor
8.00 Ea. 9,293.26 74,346
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Page 169 of
Code Description Quantity Unit Unit Cost Total Cost
U158507001460 Register, air supply, ceiling/wall, anodized aluminum,
adjustable curved face bars, one or two way deflection,
30" x 30", includes opposed blade damper
40.00 Ea. 361.18 14,447
U160553009000 Electrical demolition, minimum labor/equipment charge 96.00 Job 142.00 13,632
U161207501850 Fire alarm cable, FEP teflon, 150 volt, to 200 Deg.C, #18,
1 pair
64.00 C.L.F. 169.95 10,877
U161209001000 Wire, copper, stranded, 600 volt, #14, type
THWN-THHN, in raceway
64.00 C.L.F. 55.52 3,553
U161322055000 Electric metallic tubing (EMT), 1/2" diameter, to 15' high,
incl 2 terminations, 2 elbows & 11 beam clamps per 100
LF
6,400.00 L.F. 4.09 26,176
U161366000020 Outlet boxes, pressed steel, 4" octagon 64.00 Ea. 31.91 2,042
U161366000100 Outlet boxes, pressed steel, extension rings, 4" octagon 64.00 Ea. 20.06 1,284
U161366000150 Outlet boxes, pressed steel, 4" square 64.00 Ea. 31.11 1,991
U161366000200 Outlet boxes, pressed steel, extension rings, 4" square 64.00 Ea. 20.11 1,287
U161366000250 Outlet boxes, pressed steel, covers, blank, 4" square 64.00 Ea. 10.47 670
U162206100450 Motors, dripproof, premium efficiency, 1.15 service
factor, 1800 RPM, 230/460 V, 60 Hz, 20 HP
8.00 Ea. 1,412.73 11,302
U162209001150 Variable frequency drives, custom-engineered, 460 volt,
20 HP motor size
8.00 Ea. 7,405.50 59,244
U164407001200 Circuit breakers, ground fault, 14 k A I.C., 1 pole, 277
volt, 15 - 30 amp
40.00 Ea. 118.77 4,751
U164407202600 Panelboards, 3 phase 4 wire, main circuit breaker,
277/480 V, 225 amp, 30 circuits, NEHB, incl 20 A 1 pole
plug-in breakers
8.00 Ea. 5,103.70 40,830
Subtotal: 938,109
Adjustment Factor: 1.4200
Total: 1,332,115
Requirement Detail Report
By Asset Name and Priority
Jun 2, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 169
All costs in USD.
Photographs
Page 1 of
11 - National Capital RegionPotomacGSA-ROB-DC0031ZZ
Obsolete Equipment: Abandoned - Various Locations
Abandoned Equipment
Mechanical
Branch Wiring Devices: Aged Circuits and Devices - Mechanical Room
5638.
Branch Wiring Devices
Electrical
Ceiling Finishes: ACT Aged/Stained - Room 3674
Ceiling Finishes
Architectural
Ceiling Finishes: Paint Aged/Pealing - Mechanical Room #2506
Ceiling Finishes
Architectural
Photographs
11 - National Capital Region : Potomac : GSA-ROB-DC0031ZZ
May 27, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 26
Page 2 of
Distribution System: Aged and Inadequate Ductwork - Typical
Distribution System
Mechanical
Distribution Systems: Perimeter Ductwork, Poor Design - Typical
Distribution Systems
Mechanical
Distribution Systems: Building Exhaust System Aged/Out of NFPA Code
Distribution Systems
Mechanical
Distribution Systems: Restroom Exhaust Aged - Typical
Distribution Systems
Mechanical
Photographs
11 - National Capital Region : Potomac : GSA-ROB-DC0031ZZ
May 27, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 26
Page 3 of
Distribution Systems: Air Handlers Aged - Typical
Distribution Systems
Mechanical
Distribution Systems: Steam Room Equipment Aged - Steam Room
Distribution Systems
Mechanical
Electrical Service and Distribution: Vault Transformer Testing Is Needed -
Room B05.
Electrical Service and Distribution
Electrical
Elevators and Lifts: Abandoned Elevators - Roof Elevator Machine Room
1&2.
Elevators and Lifts
Electrical
Photographs
11 - National Capital Region : Potomac : GSA-ROB-DC0031ZZ
May 27, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 26
Page 4 of
Elevators and Lifts: Passenger Elevators Aged and Obsolete - Roof
Elevator Machine Room.
Elevators and Lifts
Electrical
Elevators and Lifts: Freight Elevator Aged and Obsolete - Roof Freight
Elevator Machine Room.
Elevators and Lifts
Electrical
Emergency Light and Power Systems: Abandoned Generator - Room B03.
Emergency Light and Power Systems
Electrical
Emergency Light and Power Systems: Emergency Lighting Fixtures Aged
- Room 3129.
Emergency Light and Power Systems
Electrical
Photographs
11 - National Capital Region : Potomac : GSA-ROB-DC0031ZZ
May 27, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 26
Page 5 of
Emergency Light and Power Systems: Emergency Lighting Lacking -
Level 4 Corridor.
Emergency Light and Power Systems
Electrical
Emergency Light and Power Systems: Exit Signage Lacking - Room
6018.
Emergency Light and Power Systems
Electrical
Emergency Light and Power Systems: Exit Signage Aged and Inefficient -
Room 2080.
Emergency Light and Power Systems
Electrical
Emergency Light and Power Systems Aged and Insufficient Generator -
Room B03.
Emergency Light and Power Systems
Electrical
Photographs
11 - National Capital Region : Potomac : GSA-ROB-DC0031ZZ
May 27, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 26
Page 6 of
Equipment and Furnishings: Loading Dock Rusted - Northwest Loading
Dock
Equipment and Furnishings
Architectural
Exterior Doors: Metal Aged/Deteriorated - Penthouse
Exterior Doors: 1
Architectural
Exterior Doors: Metal Aged/Deteriorated - Penthouse
Exterior Doors: 2
Architectural
Exterior Stairs: Rooftop Stairs Not Compliant
Exterior Stairs
Architectural
Photographs
11 - National Capital Region : Potomac : GSA-ROB-DC0031ZZ
May 27, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 26
Page 7 of
Exterior Stairs: Rooftop Stairs Not Compliant
Exterior Stairs
Architectural
Exterior Stairs and Fire Escapes: Slab Granite Damaged - D Street
Entrance
Exterior Stairs
Architectural
Seventh Street Entrance
Exterior View
Architectural
Exterior Walls: Stucco Deteriorated -by Room 1912
Exterior Walls
Architectural
Photographs
11 - National Capital Region : Potomac : GSA-ROB-DC0031ZZ
May 27, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 26
Page 8 of
Exterior Walls: Screen Walls Aged/Weathered - Roof
Exterior Walls
Architectural
Exterior Walls: Stucco - Aged/Cracked Northeast Corner
Exterior Walls 1
Architectural
Exterior Walls: Stucco - Aged/Cracked Northeast Corner
Exterior Walls 2
Architectural
Exterior Walls: Stucco - Aged/Cracked North Elevation
Exterior Walls 3
Architectural
Photographs
11 - National Capital Region : Potomac : GSA-ROB-DC0031ZZ
May 27, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 26
Page 9 of
Exterior Windows: Steel Aged/Deteriorated - Penthouse West Mechanical
Room
Exterior Windows
Architectural
Exterior Windows: Insulated, Leaking - Room 7080
Exterior Windows
Architectural
Fire Alarm Systems: Aging Fire Alarm Control Panel - Room L-14.
Fire Alarm Systems
Electrical
Distribution Systems: Fire Dampers Beyond Expected Life - Typical
Fire Protection
Mechanical
Photographs
11 - National Capital Region : Potomac : GSA-ROB-DC0031ZZ
May 27, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 26
Page 10 of
Fire Protection Systems: Sprinkler Head Guards Missing - Electrical
Rooms
Fire Safety Protection Systems
Mechanical
Floor Finishes: Epoxy Paint Aged/Worn - Room 4710
Floor Finishes
Architectural
Floor Finishes: Raised Flooring - Missing Transition Strips - Room 4926
Floor Finishes
Architectural
Floor Finishes: Access Computer Flooring Corroded - Room 2043.
Floor Finishes
Architectural
Photographs
11 - National Capital Region : Potomac : GSA-ROB-DC0031ZZ
May 27, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 26
Page 11 of
Floor Finishes: Terrazzo Aged and Cracked - 1st Floor Corridor by East D
Street Entrance
Floor Finishes
Architectural
Floor Finishes: Vinyl Tile Aged/Worn/Damaged - Mechanical Room
Stairwell #6
Floor Finishes
Architectural
Floor Finishes: Asbestos Floor Tile Deteriorated - Room 6648
Floor Finishes
Architectural
Floor Finishes: Carpet Tile Worn/Damaged and Stained - Room 2670
Floor Finishes 2
Architectural
Photographs
11 - National Capital Region : Potomac : GSA-ROB-DC0031ZZ
May 27, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 26
Page 12 of
Floor Covering: Broadloom Carpet/Aging - Room 2080
Floor Finishes 3
Architectural
Floor Covering: Broadloom Carpet Aging/Worn - Room 4051B
Floor Finishes 4
Architectural
High Tension Service and Dist: High Voltage Switchgear/Cabling
Antiquated - South Primary Service Room Garage Level.
High Tension Service and Distribution
Electrical
Identifying Devices: Fittings Signage not ADAAG Compliant - Room
1507
Identifying Devices
Architectural
Photographs
11 - National Capital Region : Potomac : GSA-ROB-DC0031ZZ
May 27, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 26
Page 13 of
Identifying Devices: Signage Weathered North Side of building.
Identifying Devices
Architectural
Interior Doors: Blocked - Room 4636
Interior Doors
Architectural
Interior Doors: Fire Doors Not in Compliance - 1st Floor Stairwell #2
Interior Doors
Architectural
Interior Doors: Hardware Not ADA Compliant - Room 6018
Interior Doors
Architectural
Photographs
11 - National Capital Region : Potomac : GSA-ROB-DC0031ZZ
May 27, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 26
Page 14 of
Interior Doors: Metal Aged - Room 2029
Interior Doors
Architectural
Lighting Equipment: Aged Lighting Fixtures - Utility Space Adjacent to
Level 5 Kitchen.
Lighting Equipment
Electrical
Lighting Equipment: Aged Occupancy Sensor System - Level 6 Corridor.
Lighting Equipment
Electrical
Local Area Networks: Cabling Improperly Supported - Level 6 Corridor.
Local Area Networks
Electrical
Photographs
11 - National Capital Region : Potomac : GSA-ROB-DC0031ZZ
May 27, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 26
Page 15 of
Local Area Networks: Dedicated Equipment Space Lacking - Electrical
Closet 3628.
Local Area Networks
Electrical
Low Tension Service and Dist: Non-Compliant Fire Pump Supply
Conductors - Corridor Adjacent Room B33.
Low Tension Service and Distribution
Electrical
Low Tension Service and Dist: Aged and Obsolete Switchboards - Room
G202.
Low Tension Service and Distribution
Electrical
Low Tension Service and Dist: Aged and Obsolete Panel Boards/Feeders -
Electrical Closet 3672.
Low Tension Service and Distribution
Electrical
Photographs
11 - National Capital Region : Potomac : GSA-ROB-DC0031ZZ
May 27, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 26
Page 16 of
Other Electrical Systems: Lightning Protection System Lacking - Roof.
Other Electrical Systems
Electrical
Parking Lot: Worn Striping/Markings Basement
Parking Lot
Architectural
Partitions: GWB Water Damage - Room 1912
Partitions 1
Architectural
Partitions: GWB Water Damaged - Room 1912
Partitions 2
Architectural
Photographs
11 - National Capital Region : Potomac : GSA-ROB-DC0031ZZ
May 27, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 26
Page 17 of
Pedestrian Paving: Concrete Crack/Spalling - 7th Street Parking Garage
Entrance.
Pedestrian Paving 1
Architectural
Pedestrian Paving: Concrete Crack/Spalling - D Street Entrance.
Pedestrian Paving 2
Architectural
Plumbing Fixtures: Aged - Typical
Plumbing Fixtures
Mechanical
Plumbing Fixtures - Utility Sinks Need Cleaned
Mechanical
Photographs
11 - National Capital Region : Potomac : GSA-ROB-DC0031ZZ
May 27, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 26
Page 18 of
Plumbing Fixtures: Restroom Aged/Non ADAAG Compliant Men's Room
2039.
Plumbing Fixtures 1
Architectural
Plumbing Fixtures: Restroom Aged/Non ADAAG Compliant Men's Room
4500
Plumbing Fixtures 2
Architectural
Plumbing Fixtures: Restroom Aged/Non ADAAG Compliant Women's
Restroom 4508
Plumbing Fixtures 3
Architectural
Roofing: Built Up Roofing Aged/Ponding - Northeast Corner
Roofing
Architectural
Photographs
11 - National Capital Region : Potomac : GSA-ROB-DC0031ZZ
May 27, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 26
Page 19 of
Roofing: Single Ply Membrane Aged/Weathered - West Roof
Roofing
Architectural
Roofing: Built Up Roofing penetrations around roof drains.
Roofing 2
Architectural
Sanitary Waste System: Floor Drains Corroded - Typical
Sanitary Waste Systems
Mechanical
Security and Detection Systems: Break Glass Detectors Lacks Adequate
Coverage - Room 1912.
Security and Detection Systems
Electrical
Photographs
11 - National Capital Region : Potomac : GSA-ROB-DC0031ZZ
May 27, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 26
Page 20 of
Stairs: Interior Aged/Worn Stairway 3, Third Floor.
Stairs 1
Architectural
Stairs: Interior Aged/Worn Stairwell 3 Second Floor
Stairs 2
Architectural
Stairs: Hand Railing Not ADAAG or IBC Compliant. Stairwell #1 Third
Floor
Stairs 3
Architectural
Stairs: Hand Railing Not ADAAG or IBC Compliant - Stairwell #1, Third
Floor
Stairs 4
Architectural
Photographs
11 - National Capital Region : Potomac : GSA-ROB-DC0031ZZ
May 27, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 26
Page 21 of
Storm Sewer: Ground Water Sump Pumps Aged - Basement
Storm Water Equipment: Aged Ground Water Sump Pumps
Mechanical
Substructure: Concrete Parking Lot Aged/Worn - Basement Parking Area
Substructure
Architectural
Telephone Systems: Antiquated and Abandoned Wiring - Electrical Closet
3103.
Telephone Systems
Electrical
Terminal and Package Units: Computer Room AC Aged
Terminal and Package Units
Mechanical
Photographs
11 - National Capital Region : Potomac : GSA-ROB-DC0031ZZ
May 27, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 26
Page 22 of
Terminal and Package Units: Window AC Units Aged - Typical
Terminal and Package Units
Mechanical
Wall Finish: Marble Aging - 7th Street Entrance
Wall Finishes
Architectural
Wall Finishes: Acoustic Tile Aged/Deteriorated - Room 4660
Wall Finishes
Architectural
Wall Finishes: Historic Pealing Paint - 7th Street Entrance
Wall Finishes
Architectural
Photographs
11 - National Capital Region : Potomac : GSA-ROB-DC0031ZZ
May 27, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 26
Page 23 of
Wall Finishes: Painted Aged/Worn/Stained
Wall Finishes
Architectural
Wall Finishes: Epoxy Painted Concrete Aged/Pealing - Room 2506
Wall Finishes
Architectural
Wall Finishes: Marble Cracked/Damaged - 7th Street Entrance
Wall Finishes
Architectural
Elevation: South, D Street
Photographs
11 - National Capital Region : Potomac : GSA-ROB-DC0031ZZ
May 27, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 26
Page 24 of
Elevation: North, C Street
Elevation: West, 9th Street
Elevation: South D Street
Plumbing Fixtures: Aged and Non-Compliant Water Coolers
Plumbing Fixtures
Mechanical
Photographs
11 - National Capital Region : Potomac : GSA-ROB-DC0031ZZ
May 27, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 26
Page 25 of
Plumbing Fixtures: Uninsulated Sink Piping - Typical
Plumbing Fixtures
Mechanical
Domestic Water Distribution: Water Main Aged
Domestic Water Distribution
Mechanical
Domestic Water Distribution: Booster Pumps Aged
Domestic Water Distribution
Mechanical
Plumbing Fixtures: Aged - Typical
Plumbing Fixtures
Mechanical
Photographs
11 - National Capital Region : Potomac : GSA-ROB-DC0031ZZ
May 27, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 26
Page 26 of
Distribution Systems: Air Handlers Aged - Typical
Distribution Systems
Mechanical
Sanitary Waste Equipment: Restroom Floor Drains Missing - Typical
Sanitary System
Mechanical
Photographs
11 - National Capital Region : Potomac : GSA-ROB-DC0031ZZ
May 27, 2010Copyright © 1998-2010 VFA, Inc. All rights reserved. 26
G l o s s a r y
6/2/2010 1 of 11
Glossary of Terms
________________________________________________________________
% Used
% Used is the portion of a System's life that is used at the time of inspection. This value establishes the System's condition, and is used to calculate the System's next renewal year. For example, a 20-year roof that is 75% used is projected for replacement in 5 years.
% Renew
% Renew is the percentage of a system's replacement cost that is required to return the system to "like new" condition at the end (or over the course) of the system's lifetime.
~ (tilde)
~ (tilde) is a symbol that prefixes a record's name if the record is a duplicate of another record (i.e., it has been copied and pasted) or if the record was created from a template. The ~ can be removed by editing the record's name.
Access Privileges
Access Privileges allow a user to view and work with records. For example, a user can have full access privileges to an Asset record. Access privileges are assigned to a user account by a User Administrator.
Action
An Action is a strategy for correcting a Requirement that includes the scope of work to be done and an itemized estimate of its cost (line items).
Addition
Addition is an Action Type that involves expanding a facility.
Administrator
An Administrator is a user who can create user accounts and assign access privileges to other users. Administrators also may be able to customize their VFA website by configuring drop-down lists, adding or modifying record properties, and enabling/disabling site features.
Adjustment Factor
Adjustment Factor is a number assigned to an itemized list of System or Action costs that signifies additional complexity and/or resources involved in construction. The adjustment factor is multiplied against the line items for the total cost.
Assembly
An Assembly is a group of parts or components that fit together to form a self-contained unit.
Asset
An Asset is a free-standing structure, a portion of a structure, or any part of facility infrastructure that is distinguishable from its surroundings by date of construction, construction type, and/or the Systems that comprise it.
G l o s s a r y
6/2/2010 2 of 11
Asset Exterior
The Asset Exterior is the exterior surface area of an Asset, calculated as follows: (Asset Perimeter) * (number of floors) * 11 ft (floor height).
Asset Footprint
The Asset Footprint is the ground area occupied by an Asset, calculated as follows: (Asset Area) / (Number of Asset Floors).
Asset Perimeter
The Asset Perimeter is the distance around the Asset, calculated as follows: (Asset Footprint)^(.5) * 4.25. (Asset Footprint is the Asset's Area divided by the number of floors.)
New Topic (2)
Asset Replacement Value (RV) is the total amount of expenditure required to construct a replacement facility to the current building codes, design criteria, and materials. The RV for a single Asset can be based on the sum of the System replacement costs, or it can be a custom cost. The RV may include or exclude overhead costs.
Asset Size
Asset size is the total area in a building for all floors to the outer surface of exterior walls. GSF (Gross Square Foot or Gross Square Meters) is the standard figure used in defining construction costs for facilities. Some Asset Types such as piping may be measured in linear feet or meters, and others in volume or numbers ("Each").
Asset Template
An Asset Template is a template for the individual Systems that comprise an Asset.
Asset Type
The Asset Type is the role that the Asset has in the facility. For example, an Asset can be a building, a utility, land, or an outdoor structure. The Asset Type field allows the Asset record to be configured by an Administrator to capture Type-specific information, such as unit of measurement.
Backlog
Backlog is facility maintenance that has been deferred on a planned or unplanned basis.
Backlog Deterioration Rate
Backlog Deterioration Rate is the increase in cost from year to year of deferred maintenance (independent of any inflationary increases in construction costs).
Breadcrumbs
Breadcrumbs is a website navigation tool located beneath the Main Menu that displays the navigation trail of the record or record list that you are currently viewing.
Budget Scenario
A Budget Scenario uses a Ranking Strategy to guide the prioritization of funding for the correction of Requirements. The results of a Budget Scenario ranks the correction of a set of Requirements, and shows the impact of budget levels on the FCI.
Campus
G l o s s a r y
6/2/2010 3 of 11
A Campus is a grouping of Assets that are generally adjacent to one another on a contiguous site and bounded by property lines.
Campus Code
The Campus Code is a unique alphanumeric identifier assigned to each Campus. This identifier can be changed at any time as long as the new identifier remains unique and is not shared by another Campus.
Campus Map Coordinate
A Campus Map Coordinate is an identifier for the location of an Asset on a map or site plan.
Capability
A capability allows a user to access certain site functionality. For example, the Project Planning capability allows a user to access the Projects module. Capabilities are assigned to a user account by a User Administrator.
Capital Improvement
A Capital Improvement is a facility change or addition that is not required for the most basic function. Capital improvements include upgrades and mission-specific adaptations to an Asset's assemblies, finishes, fixtures, equipment, Systems, and/or program. A capital improvement can also allow a facility to comply with existing codes by remedying a grandfathered condition.
City Cost Index (CCI)
The City Cost Index (CCI) is a factor used to adjust RSMeans Construction Data to a specific city. The appropriate CCI is selected from a list compiled by RSMeans that includes all major U.S. and Canadian cities and metro areas.
Commission Date
The Commission Date is the date that an Asset is "active." The Commission Date is a future date; it is used to include Assets that are not yet a part of a portfolio in forecasts.
Component Renewal
Component Renewal is the full or partial replacement of a System as it reaches or exceeds its useful lifetime.
Construction Type
An Asset's Construction Type is a classification based on building structural elements and fire resistance that is specified by the appropriate building code.
Computer Aided Design (CAD)
Computer Aided Design (CAD) is a program for creating and manipulating electronic drawings stored in a computer.
Configurable Property
A Configurable Property is a data field that an Administrator has configured to display on a particular type of record in order to collect additional information. Configurable properties are not explained in the manual.
Cost Curve
A Cost Curve is a characterization of how the System's renewal costs occur over time. Each System is assigned a Cost Curve in order to realistically model how its renewal costs are distributed in forecasts.
G l o s s a r y
6/2/2010 4 of 11
CSV
A CSV ("Comma Separated Value") file can be opened in a variety of spreadsheet and database applications (for example, Microsoft Excel). You can then extract or format the raw data to suit the needs of your organization.
Data Browser
The Data Browser is a website tool that allows users to extract customizable data sets from record fields.
Decommission Date
Decommission Date is the date that an Asset is no longer a part of a portfolio, or that a System is no longer a part of a portfolio. The Decommission Date is used to exclude renewal costs from forecasts when the costs will no longer be incurred.
Demolition
Demolition is an Action Type that involves the dismantling, removal, and disposal of a facility (either partially or in its entirety).
Detail View
Detail View is when you are viewing all of a record's data fields. You can edit a record's fields in Detail View if you have proper access privileges.
Deferred Maintenance
Deferred maintenance is work that is deferred on a planned or unplanned basis. Deferred maintenance includes existing major repairs and replacements; it does not include future maintenance, capital improvements, or grandfathered code issues.
Deferred Maintenance Penalty
Deferred Maintenance Penalty is the additional cost of deferring maintenance over a period of time.
Dimension
A dimension is an Asset or Requirement property that is used to rank Requirements in a Ranking Strategy.
Estimator
The Estimator is the actual person who estimates the cost of an Action. Also see the RSMeans Estimator.
Extended
Extended refers to the total cost of an Action's line items (quantity multiplied by unit price), including the Overhead and Profit for the given trade.
Facility Condition Assessment (FCA)
Facility Condition Assessment (FCA) is a collection of detailed facility data to support a capital renewal and deferred-maintenance program by identifying, estimating, and prioritizing existing deferred maintenance and predicting capital-renewal requirements.
G l o s s a r y
6/2/2010 5 of 11
Facility Condition Index (FCI)
Facility Condition Index. FCI is an industry-standard index that objectively measures the current condition of a facility, allowing comparison both within and among institutions. To determine FCI for any given set of Assets, the total cost of remedying deferred maintenance Requirements is divided by the current replacement value. Generally, the higher the FCI, the poorer the condition of the facility. An Administrator may configure FCI to include and exclude Requirements based on category and recommended action date.
Favorites
Favorites is a tool that provides one-click shortcut access to navigational contexts and reporting criteria. All users can create Favorites for their own use. Some users can share Favorites with all other users on the site.
FCI Category
An FCI Category is a Requirement Category that, when assigned to a Requirement, makes that Requirement's cost eligible for inclusion in the FCI backlog. FCI categories can be configured by an Administrator.
Field
A field is one cell of information in a VFA.facility record, such as the name of an Asset or the size of a Room.
Fiscal Plan
A Fiscal Plan is a financial strategy for the costs associated with multiple Projects.
Fiscal Year
The Fiscal Year refers to an accounting period lasting 365 days (or 366 days) that does not necessarily mirror the calendar year. In VFA.facility, forecasts and FCI calculations are reset at the beginning of each fiscal year. Administrators can specify the beginning date of the fiscal year.
Floor
A floor is contiguous occupiable space within an Asset that shares the same elevation or floor level.
Funding Reserve
The Funding Reserve is excess funding that was allocated for an Asset in a forecast but not needed in that year. The Funding Reserve may not display on your site if the Funding Reserve site setting is disabled by your Administrator.
Funding Scenario
A Funding Scenario is a strategy for expending funds to remedy physical plant requirements, expressed as a statement of how much is to be funded in each future year.
Future Years Included
Future Years Included refer to the FCI setting that determine how many future fiscal years of Requirement costs are included in the FCI. FCI always includes Requirements with Action Dates in the past and current fiscal years.
Green Building Line Items
Green Building Line Items are RSMeans line items that use green building technologies, design concepts, standards, and costs.
G l o s s a r y
6/2/2010 6 of 11
Group Template
A Group Template is a template for multiple Systems that can be grouped together (for example, an HVAC assembly).
Historical Category
The Historical Category indicates the historical significance of an Asset.
Inflation Rate
Inflation Rate is the rate of increase in the costs of goods and services. In VFA.facility, the inflation rate is applied annually. However, the inflation rate should reflect the anticipated long-range increases in future goods and service, not increases in any particular year. The default annual inflation rate is 4.7% unless it is changed.
Infrastructure
Infrastructure refers to the non-architectural elements of a facility (for example, utilities, roadways, or undeveloped land). A piece of infrastructure is entered into VFA.facility as an Asset, with the Asset Type identifying the infrastructure as a non-building Asset.
Inspector
The Inspector is the actual person who observed and investigated a Requirement.
Intersections
An Intersection is a Requirement that is in at least two Projects, or a Project that is in at least two Fiscal Plans.
Inventory
Inventory is any item or piece of equipment in an Asset.
Lifetime
Lifetime is the number of years a System is expected to be useful (its "useful life") before Renewal is required.
Line Item
A Line Item is a single item in an itemized list of costs. Line items can be added using the Estimator, a cost estimation tool based on RSMeans construction costs, or users can create blank, Non-Means items. Line items can be attached to an Action in order to estimate the cost of the Action. Line items are also used to derive unit costs for Asset Systems.
Linked System
A Linked System is the functional System that a Requirement affects. A Requirement can be linked to any System record within the same Asset as a Requirement.
List View
List View is a summary list of records of a particular type. For example, in Room list view, you can view a list of all of the Room records in an asset.
Modernization
Modernization is a type of Action that alters a facility solely to implement new or higher standards or to accommodate new functions.
G l o s s a r y
6/2/2010 7 of 11
Module
A module is a work area within VFA.facility (for example, Assets, Projects or Reports). All of the modules that you can access display as tabs at the top of your screen.
Net Present Value (NPV)
Net Present Value (NPV) is an approach used in capital budgeting that discounts future cash flows to their present values. NPV is calculated by removing the accumulated inflation over the funding period.
OpenShop
OpenShop is a RSMeans Resource setting that specifies labor costs should reflect non-union commercial rates.
OPTotal
OPTotal is, in an Action, the total calculated for each unit in a line, including the Overhead and Profit for the given trade (under the heading "Each").
Overhead
An Overhead is an expense incurred during a project that is in addition to the actual cost of construction. For example, design fees, permits, land acquisition costs, legal fees, and administration costs are considered Overheads. Overheads can be added to a Project, or the Replacement Value of an Asset.
Override Action Date
The Override Action Date is the date by when a Requirement should ideally be corrected. The Override Action Date is entered by a user, and overrides the Recommended Action Date that is automatically assigned to the Requirement. If a Requirement has an Override Action Date, then this is date determines if the Requirement is included in the FCI.
Pay As You Go
Pay As You Go is an "ideal" funding scenario in which every facility need is allocated funding as soon as it occurs, thus preventing the accumulation of backlog and deferred maintenance costs. This funding option appears on the Comparison of Options report, chiefly for comparison to the other options.
Planning Window
Each VFA.facility website has a Planning Window, which is a configurable future number of years during which a Renewal Requirement will automatically be created for a System renewal event. When any System's Renewal Fiscal Year falls within the Planning Window, the Renewal Requirement is created. The Planning Window can be viewed and configured by an Administrator.
Primary Photo
The Primary Photo is the most representative photo of an Asset.
Prime Action
The Prime Action is the planned "course of action" to correct the Requirement. The cost of a Requirement is the Estimated Cost of its Prime Action. Other Actions may be created to record other possible correction strategies.
Prime System
The Prime System is the primary Uniformat II Category that a Requirement affects. You can assign a Prime System to a Requirement on the Requirement record.
G l o s s a r y
6/2/2010 8 of 11
Project
A Project is a combination of Requirements plus any additional "overhead" cost data. Projects allow organizations to explore how to remedy and fund Requirements in the most cost-effective manner. Projects can be placed in fiscal plans in order to accurately track financials and scheduling.
Project Group
A Project Group is a "container" for projects and fiscal plans. Project access privileges are assigned by Group.
Ranking Strategy
A Ranking Strategy is a prioritization of Asset and Requirement properties according to how your organization wants to allocate funds for the correction of Requirements. A Ranking Strategy can be applied to a Budget Scenario in order to set the budgetary priorities.
RSMeans
RSMeans is North America's leading supplier of construction cost information. In VFA.facility, the Estimator uses cost information from RSMeans.
RSMeans Annual Update
The RSMeans Annual Update is the annual adjustment of RSMeans Line Items in order to account for changes in construction costs.
Recommended Action Date
The Recommended Action Date is the date by when a Requirement should ideally be corrected. The date is automatically assigned to a Requirement based on its priority. Requirement Priorities may have a time frame for correction. For example, a Priority 1 Requirement should be corrected within 1 year. Each Priority may add a set number of years (the "Year Offset") to the Inspection Date, resulting in the Recommended Action Date. Requirements may be included or excluded from the FCI based on the Recommended Action Date. Typically, the more severe Priorities have earlier action dates. Priorities may also have a "null" year offset, resulting in no Recommended Action Date and permanent exclusion from FCI. Users can override the Recommended Action Date by assigning an Override Action Date.
Record
A record is a collection of data. It contains all the information for an item, such as a campus or asset.
Region
A region is the first level of division for facility management. Regions are divided into campuses.
Renewal Cost
The renewal cost is the cost of replacing an asset System as it reaches or exceeds the end of its useful life.
Renewal Event
A renewal event is the year when a system is forecast to be renewed. See 'System Renewal.'
Renewal Fiscal Year
The Renewal Fiscal Year is the year that a System is expected to require renewal funding (its renewal cost), either based on its age or based on its observed condition.
G l o s s a r y
6/2/2010 9 of 11
Renewal Forecast
Renewal Forecast is a forecast that models the estimated renewal costs for all asset systems as they approach the end of their useful lives.
Renewal Requirement
A Renewal Requirement is a Requirement record that is automatically generated based on a System Renewal event.
Renovation
Renovation is a type of Action that is extends the service life of a facility as well as keeps it modern and relevant.
Replacement
Replacement is a type of Action that replaces facility equipment or Systems with items of higher or equal quality, but that will not substantially change the function or capacity.
Replacement Value (RV)
Replacement Value (RV). See Asset Replacement Value.
Resource
Resource is the appropriate type of labor for a specific campus. The labor rates for each RSMeans line item are affected by the Resource type selected for the Campus.
Requirement
A Requirement is a facility need or a deficient condition that should be addressed, including deferred maintenance, code issues, functional requirements, and capital improvements. A Requirement can affect an assembly, piece of equipment, or any other System. It is assigned a Category, Priority, and System in order for its costs to be categorized appropriately and time frame for action assigned.
Requirement Category
A Requirement Category is the type of issue that must be addressed for a Requirement. Each Requirement is assigned a category so that the issues affecting a facility can be categorized. The category also may affect if the Requirement's costs are measured in the FCI. For example, Requirement categories that are FCI categories are included in FCI calculation.
Requirement System
The Requirement System is the single construction assembly or mechanical system that contributes to a Requirement.
Requirement Priority
The Requirement Priority is the severity of a Requirement and the time frame during which it should be scheduled for correction (if correction is applicable).
Requirements Index (RI)
The Requirements Index (RI) is a total needs Requirements index. RI includes the costs of all non-closed Requirements, regardless of category and time. To determine RI for any given Asset, the total cost of addressing all Requirements is divided by the current replacement value. The RI may not display on your site if the RI site setting is disabled by your Administrator.
G l o s s a r y
6/2/2010 10 of 11
Repair
Repair is a type of action that restores a facility or a system to a condition so that it may effectively be used for its designated functional purpose.
Repair Resource
Repair Resource is a RSMeans Resource setting that specifies labor costs should reflect union wage rates, crew composition, and overhead and profit. This Resource setting is the same as Standard, except the Overhead and Profit costs are about 10% higher.
Room
A Room is an interior space enclosed or separated by walls.
Size
Size is the measurement of an Asset in the appropriate unit of measurement.
Soft Costs
Soft costs include costs that are necessary to prepare and complete the non-construction needs of a construction project, but not directly associated with construction or equipment costs (for example, design fees, permits, inspections, consultants, environmental studies, and regulatory demands. Soft costs may differ according to your locale.)
Standard
Standard is a RSMeans Resource setting that specifies labor costs should reflect union wage rates, crew composition, and overhead and profit.
System
A System is an assembly, finish, fixture, piece of equipment, or other component that makes up an Asset.
System Condition Index (SCI)
The System Condition Index (SCI) measures the relative condition of the systems within an Asset. SCI uses costs from all requirements that are included in FCI in order to measure the relative health of a system and facilitate comparison within a single Asset. SCI follows the same configuration settings as FCI. Each system in an asset is measured against the total cost of maintenance requirements with a matching System.
System Renewal
System Renewal is the cyclical repair and/or replacement of a System as it reaches or exceeds its useful life. The act of System Renewal is also called a 'Renewal Event.' System Renewal is forecast to occur at the end of a System's lifetime in its Renewal Year, which is based on the System's expected lifetime or its observed condition. The future costs of System Renewal are based on the System Replacement Cost, and take in account the percentage of the System that is renewed (% Renew). System Renewal costs are forecast in the Renewal Forecast (a Funding Module report) as well as various System reports.
New Topic (2)
The System Replacement Cost is the expenditure required to place a System to its optimal condition so that it meets the current acceptable standards of construction and complies with regulations.
G l o s s a r y
6/2/2010 11 of 11
System Template
A System Template is used as the basis for creating new Systems, and contains costs, Lifetimes, descriptions, and general System information. System Templates are managed in the Template Library, which features a vast array of Systems based on BOMA lifetimes and VFA's best practices.
System Template Library
The System Template Library is an extensive repository of standard templates for creating Systems.
Total New Liability
The Total New Liability in the Funding Report is the sum of the year's total Renewal Cost, Backlog Deterioration, and any new Requirements.
Uniformat II Category
A Uniformat II Category is an element of the Uniform Classification System for organizing preliminary construction information into a standardized classification structure. These elements are common to most buildings and usually perform a given function regardless of the design specification, construction method, or materials used. There are four levels of classifications.
User Administrator
A User Administrator can create, modify and delete user accounts, and control user access to data and advanced functionality. The User Administrator must have the User Administration capability.
Unit Cost Basis
A System's Unit Cost Basis is the amount of the system for which the System Cost Estimate is built. For example, if the System Cost Estimate is for 1000 SF of flooring, then the Unit Cost Basis is 1000. The Unit Cost Basis is important to consider when entering the System's Quantity. If you have 5000 SF of flooring and the Unit Cost Basis is 1000 SF, then you should enter a Quantity of 5.
Year Offset
Year Offset is a number of years added to a Requirement's inspection date in order to determine the recommended action date. Each Requirement priority has a Year Offset that should reflect the respective severity of the Requirement. Priorities may also have a "null" year offset that will not assign a recommended action date to the Requirement.