FCC Troubleshooting - Catalyst Losses

Embed Size (px)

Citation preview

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    1/36

    1

    FCC Trouble Shooting

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    2/36

    2

    Determining the Cause of a Problem

    The Fluid Catalytic Cracking (FCC) process has many complex interactions

    between catalyst, hardware, feed, and products.

    This complexity can make it difficult to determine the cause of a problem.

    When a problem arises, the first step must be to define the problem.

    This is done by gathering data on current operation and comparing this

    information with data from a time of normal operation.

    Consider any changes that occurred near the time the problem was first

    observed.

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    3/36

    3

    Some Common Major Problems

    High Catalyst Losses

    Poor Catalyst Circulation

    Poor Product Yields

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    4/36

    4

    A: Definition of ProblemHigh Catalyst Loss Rate

    Are losses from the reactor, regen., or both?

    From one vessel mechanical or operation problem

    From both vessels low system pressure or catalyst

    problem

    Are losses steady or increasing with time?

    Steady losses blocked cyclone dipleg

    Increasing hole or crack in vessel or line

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    5/36

    5

    A: Definition of ProblemHigh Catalyst Loss Rate, cont.

    Is fines fraction (0-40 ) in the eq. cat. decreasing

    or increasing? Decreasing poor fines retention;

    low fines replacement

    Increasing high stream velocity; soft catalyst

    Are the gas velocities in the affected vessel within

    cyclone design ranges? If no unit pushed beyond operating

    envelope

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    6/36

    6

    A: Definition of ProblemHigh Catalyst Loss Rate, cont.

    Additional questions:

    Has there been a change in the particle size of theescaping catalyst?

    When were the high cat. losses first observed?

    Did the change occur suddenly or gradually?

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    7/36

    7

    High Catalyst Losses

    Troubleshooting Check List

    OBSERVED DATA POTENTIAL CAUSES INITIAL ACTION

    Fines increase inequilibrium catalyst;

    high cyclone P

    High velocity stream indense phase (>70 m/s)

    Soft catalyst

    Reduce velocities(replace missing RO,

    close bypass valves,

    reduce stripping steam) Test catalyst attrition

    Loss increases with time Crack in plenum or hole in

    cyclones

    Reduce vessel

    velocity

    Fines decrease inequilibrium catalyst

    Unit shut-down maybe required

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    8/36

    8

    High Catalyst Losses

    Troubleshooting Check List, cont.

    OBSERVED DATA POTENTIAL CAUSES INITIAL ACTION

    Losses are steady at thehigher level

    Fines decrease in

    equilibrium catalyst

    Something has broken,not simply cracked; or

    flooded/plugged dip leg

    Reduce c clone velocit

    Additional Data

    a APS of losses = 25 a 2nd

    sta e c clone roblem

    b APS of losses > 30 b 1st

    or 2nd

    stage cyclone

    roblem or hole in lenum

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    9/36

    9

    High Catalyst LossesTroubleshooting Check List, cont.

    OBSERVED DATA POTENTIAL CAUSES INITIAL ACTION

    Losses from both

    vessels increase after

    the unit operating

    pressure was reduced

    Losses are normal for the

    increased gas volume

    (from reduced pressure)

    Either increase

    operating pressure

    or accept higher

    losses

    Fines in equilibriumcatalyst are decreasing

    Losses at the increased

    level are steady

    Catalyst level in diplegs istoo high, or improper

    dipleg seal

    Increase operatingpressure until

    losses reach an

    acceptable level

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    10/36

    10

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    11/36

    11

    B: Definition of ProblemPoor Catalyst Circulation

    Is problem in spent, regenerated, or both catalyst

    lines? If in one of the lines aeration problem

    If in both catalyst problem

    Is problem increasing with time?

    If yes mechanical problem

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    12/36

    12

    B: Definition of ProblemPoor Catalyst Circulation, cont.

    Has the percentage of fines (0-40) in the eq. cat. changed?

    If decreasing fines coarse fresh catalyst / poor finesretention

    If steady fines poor aeration

    Has the pressure profile changed?

    If yes make adjustments to aeration to minimize

    problem

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    13/36

    13

    Catalyst Circulation

    Troubleshooting Check List

    OBSERVED DATA POTENTIAL CAUSES INITIAL ACTION

    Poor regeneration

    Change in yields

    Poorer stripping

    Coarse catalyst

    Loss of fines

    No catalyst withdrawals

    Lower regen. velocity

    Add more or finercatalyst

    Unsteady standpipe P Hole in standpipe Alter S/P aeration

    High regen. holdup High temps. and stresses Review operatinghistory and standpipedesign

    Uneven regen. temps

    Uneven flue O2or CO Erosion / Corrosion

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    14/36

    14

    Catalyst Circulation

    Troubleshooting Check List, cont.

    OBSERVED DATA POTENTIAL CAUSES INITIAL ACTION

    Unsteady regen. temp. Unsteady reactor temp

    Unsteady press diff.

    control (PDRC)

    Check slide valves

    and controllers

    Catalyst shifts between

    reactor and regen.

    Unsteady regen. press.

    Slide valve operation - poor instrumentation - sticky slide valves

    Adjust aeration in

    cat. transfer lines

    Poor gas compressor

    Unsteady reactor temp. Improper aeration Aeration changes

    Catalyst shifts betweenreactor and regen.

    Transfer line vibration Fluctuating valve P

    Water in aeration medium Water in steam lines Malfunctioning cat. slide

    valve actuators

    Remove water from aeration system Check SV system

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    15/36

    15

    C: Definition of ProblemPoor Product Yields

    Is there a poor weight balance? If yes metering error or exchanger leak

    Are yields steadily deteriorating with time? If yesmechanical problem such as feed

    nozzle erosion

    Are metals on equilibrium catalyst increasing? If yes feed quality or low catalyst

    replacement

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    16/36

    16

    Poor Product Yields

    Troubleshooting Check List

    OBSERVED DATA POTENTIAL CAUSES INITIAL ACTION

    High H2 yield High metals in feed Lower feed metals High coke yield Catalyst contamination Segregate feed

    Higher riser velocities Poor resid catalyst Increase cat. addition Overloaded gas

    compressor

    Feed type change Change to metals

    tolerant catalyst Low catalyst replacement Inject antimony

    Vac. unit op. conditions Increase riser steam

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    17/36

    17

    Poor Product Yields

    Troubleshooting Check List, cont.

    OBSERVED DATA POTENTIAL CAUSES INITIAL ACTION

    High coke yield Poor wei ht balance

    Leak in exchanger train;Hvy. products in feed

    Isolate leaking HXAdjust feed train pressure

    balance Partly open S/U valves Close valves, install blinds

    Low coke yield Poor wei ht balance Unsteady feed

    header pressure

    Leak in exchanger train;

    Lt. products in feed

    Isolate leaking HXAdjust feed train pressure

    balance

    High coke yield High H in coke

    Poor stripping Poor feed vaporization

    Increase steam rate Increase rxtr. temp.

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    18/36

    18

    Poor Product Yields

    Troubleshooting Check List, cont.

    OBSERVED DATA POTENTIAL CAUSES INITIAL ACTION

    Low catalyst activity High regen. temps. Localized high temps.

    Review regen. operation Use combustion promoter

    Hi h Na and V on catal st

    Increase cat. addition Minimize metals into FCCU

    Excessive steam in re en. Torch oil

    Review regen. operation Remove torch oil; install

    blind in line

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    19/36

    19

    Poor Product Yields

    Troubleshooting Check List, cont.

    OBSERVED DATA POTENTIAL CAUSES INITIAL ACTION Poor circulation

    Poor regeneration

    Coarse catalyst

    Loss of fines

    Review regen. ops.

    Use finer catalyst Poor stripping No catalyst withdrawals Increase cat. addition

    Change in riser P Eroded or blocked riser Review riser design

    Riser velocity too high Feed injector vel. too low

    Change PDRC tocontrol circulation

    Check feed injection

    High LCO endpoint; low

    HCO initial boiling point

    Poor LCO/HCO split Adjust pumparound

    duties Inefficient HCO stripper Check steam rates Improper tray loading in

    Main Column

    Review MC operation

    and internals

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    20/36

    20

    Conclusions

    You Cant Fix a Mechanical Problem by Changing Catalysts (thoughmany try)

    BUT

    Proper Catalyst Selection May Allow Longer/ Smoother Operation

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    21/36

    21

    Regenerator Cyclone Operation

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    22/36

    22

    Regenerator Cyclone Operation

    Catalyst loading to cyclones depends on

    operation

    - high velocity, 3.5 fps = 1.1 lbs catalyst

    per ft3 of flue gas

    - low velocity, 2.5 fps = 0.6 lbs/ft3

    - entrainment has an exponential curve

    Catalyst loading is usually higher than

    catalyst circulation.

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    23/36

    23

    FCC Catalyst Entrainment

    0.01

    0.10

    1.00

    10.00

    1.5 2.0 2.5 3.0 3.5 4.0 4.5

    Superficial Velocity @ Bed Outlet, fps

    CatalystEntrainment,lb/c

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    24/36

    24

    Cyclone Design Issues

    Must be very, very efficient - 99.997 % or

    more is a typical target typical loading of reactor cyclones for 30,000

    BPD FCC is ~ 18 tons/min, or 26,000

    tons/day

    99.997 % efficient system means losses of0.8 tons/day from the reactor

    Must be able to withstand erosive conditions

    in order to meet run length targets

    Needs high reliability of support system

    Has to handle wide range of operating

    conditions

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    25/36

    25

    Typical Cyclone Terminology

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    26/36

    26

    Industry Cyclone Design Targets

    DIPLEG FLUX

    100-150 lb/ft-secfor Riser and

    Regen 1st stage

    cyclones

    75 lbs/ ft-sec forUpper and Regen

    2nd Stage

    cyclones

    INLET VELOCITIES

    Riser 55 - 65 ft/sec

    Upper 60 - 75 ft /sec

    Regen 1st Stage 60 - 70 ft /sec

    2nd Stage 70 - 80 ft/sec

    OUTLET VELOCITIES

    Riser 45 - 65 ft /sec

    Upper 175 ft /sec maximum

    Regen 1st Stage 50 - 70 ft /sec

    2nd Stage 175 ft/sec max

    INLET

    OUTLET

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    27/36

    27

    Other Cyclone Parameters

    To improve system efficiency

    Target first stage cyclone L/D ratio to be at least 3.6,

    higher if possible

    Target 2nd stage cyclone L/D for 5.0 when possible

    Check dipleg pressure balance

    Want several feet remaining in the diplegs at all

    operating conditions to avoid upsets/carryover

    Plan on 1 of hexmesh refractory

    AA-22S is industry standard

    For trickle valves, plan on partially shrouded designs

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    28/36

    28

    Likely Maintenance Issues For Cyclones

    Weld Cracks

    Crossover Duct Cracks

    Vortex Termination Catalyst/Vapor Entrainment

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    29/36

    29

    Dipleg Erosion

    Caused by

    vortexbeing

    pushed

    into top of

    dipleg

    EXTREMELY

    common!

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    30/36

    30

    Localized Erosion

    Gouge in refractorythrough to metal

    Caused by shape ofinlet horn

    this case is minor

    Not obvious from

    drawings Very obvious from

    field inspection

    Cause of damage

    may not be apparentUNTIL you are in theunit!

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    31/36

    31

    Reactor Cyclone Coking

    Approximately 1 of

    coke has formed on

    the outlet tubeINSIDE the reactor

    cyclone

    You MUST remove

    this if found duringan inspection

    VERY likely to fall

    off on start up and

    plug the dipleg

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    32/36

    32

    Reactor Cyclone Coking Causes

    Coke formation is usually due to condensation of heavy

    hydrocarbons

    Material condenses in the dead area behind the cyclone inlet horn

    Can be minimized with:

    good feed injection

    increased steam in riser

    making sure unit is hot when feed is initially injected taking feed out before riser outlet temperature is too low

    Fi l C l Th ht

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    33/36

    33

    Final Cyclone Thoughts

    Cyclones are listed as one of the top three reasons why FCCUs end

    runs early

    Many people run higher than design inlet velocities

    This is not unacceptable It does carry inherent risk of ending a run early due to mechanical

    damage

    Erosion to a cyclone is a function of velocity to at least the 3rd

    power, if not higher a 10 % increase in velocity corresponds to at least a 33 % increase in

    erosion

    Units can run for an extended time period with cyclone damage, but

    need to be aware of:

    fluidization effects due to loss of small particles

    potential safety issues

    added headache of catalyst management

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    34/36

    34

    TYPICAL FCCU LAYOUT

    FLUE GAS

    PdRC

    TRC

    REGENERATOR

    REACTOR

    STRIPPER

    LRC

    AIR

    STEAM

    AIR

    STEAM

    OIL FEED

    RECYCLE

    LT. ENDS

    PRODUCTS

    TPA

    MAIN

    COLUMN

    LCOPRODUCT

    HCN

    PRODUCT

    MPA

    BPA

    DCO PRODUCT

    Steam

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    35/36

    35

    TYPICAL AERATION LAYOUT

    STEAM

    AIR

    AIR

    STEAM

    STEAM

    STEAM

    STEAM

    FEED

    STRIPPER

    REGENERATOR

    RISER

  • 7/23/2019 FCC Troubleshooting - Catalyst Losses

    36/36

    36

    TYPICAL 2-STAGE CYCLONE

    PlenumPlenum

    Gas Outlet TubeGas Outlet Tube

    Gas Inlet DuctGas Inlet Duct

    BarrelBarrel

    ConeCone

    DiplegDipleg

    Dust HopperDust Hopper

    Flapper ValveFlapper Valve

    2nd

    Stage1st

    Stage