49
Feasibility study project for the JCM 2016FY“Feasibility study for installing Solar PV system at Mwea Rice Mills in the Republic of Kenya” March, 2017 Ministry of Economy, Trade and Industry (METI) NTT Data Institute of Management Consulting, Inc.

Feasibility study project for the JCM 2016FY · 2018-01-16 · Feasibility study project for the JCM (2016FY) “Feasibility study for installing Solar PV system at Mwea Rice

  • Upload
    others

  • View
    24

  • Download
    0

Embed Size (px)

Citation preview

Feasibility study project for the JCM

(2016FY)

“Feasibility study for installing Solar PV system

at Mwea Rice Mills

in the Republic of Kenya”

March, 2017

Ministry of Economy, Trade and Industry (METI)

NTT Data Institute of Management Consulting, Inc.

Contents

1. Overview of the study ............................................................................. 1

1.1. Background and Objective of the Study ............................................................. 1

1.2. Scope of the Study ................................................................................................ 1

1.3. Outline of “Japanese technology” ....................................................................... 2

2. Technical assessment of solar generating system ................................. 3

2.1. Self-consumption project employing linear control for solar power systems in

Kenya .................................................................................................................... 3

2.1.1 Key points concerning solar power linear control ..................................... 3

2.1.2 Overview of project site ............................................................................... 5

2.1.3 System considerations ................................................................................. 6

3. Solar power potential in irrigation sector ............................................ 15

3.1. Potential assessment of irrigation sector ......................................................... 15

3.1.1 Rice industry .............................................................................................. 15

3.1.2 Irrigation policy ......................................................................................... 15

3.1.3 Strategic Plan of NIB ................................................................................ 16

3.1.4 Specific Plan of NIB .................................................................................. 17

3.2. Summary of potential assessment of Irrigation sector ................................... 17

4. Potential assessment of private sector ................................................ 19

4.1. Market potential for solar power in Kenya ...................................................... 19

4.2. Analyzing the business environment for the solar power market in the private

sector ................................................................................................................... 19

4.2.1 Interview with private sector business operators ................................... 19

4.2.2 Cost performance analysis and economic scale from solar business, as

learned through interviews ......................................................................................... 21

4.2.3 Analyzing self-consumption private IPP businesses in Kenya .............. 21

4.3. Analyzing business risk..................................................................................... 25

4.4. Feasibility of market entry by Japanese enterprises ...................................... 27

4.5. Business feasibility in the products or services market ................................. 28

4.5.1 For the utility-scale market (500 kW – 40 MW) ..................................... 28

4.5.2 For self consumption market (several kW to 500 kW systems) ............. 29

4.6. Power generation business investment feasibility .......................................... 30

4.6.1 Business investment options .................................................................... 30

4.6.2 Interview concerning feasibility of investment by Japanese enterprises

31

4.7. Potential in off grid markets ............................................................................. 32

4.7.1 Essence of hybrid mini-grid ...................................................................... 32

4.7.2 Potential assessment of hybrid mini-grid ................................................ 33

4.8. Conclusion .......................................................................................................... 35

5. Potential of GHG reduction by proposed projects ............................... 38

5.1. Potential assessment of Irrigation sector ........................................................ 38

5.1.1 Proposed Methodology KE_PM002 .......................................................... 38

5.1.2 Reference emission .................................................................................... 38

5.2. Estimation of GHG reduction by proposed projects ........................................ 38

5.2.1 Potential of GHG reduction by proposed projects ................................... 39

6. Issues and opportunities on project development ............................... 40

6.1. Issues involved in launching a business .......................................................... 40

6.1.1 Issues concerning business investment/capitalization ........................... 40

6.1.2 Issues concerning the deployment of equipment, systems, and other

hardware 40

6.2. Specific actions for establishing a business ..................................................... 41

6.2.1 Japanese companies' advantages ............................................................. 41

6.2.2 Carrying out projects through international support ............................. 42

6.2.3 Carrying out projects with investment from Japan ................................ 42

6.3. Best practices in Thailand ................................................................................ 43

7. Utilizing the JCM in the Future .......................................................... 44

7.1. The JCM as a motivating factor for business in Kenya .................................. 44

7.1.1 Paris Agreement and Kenya's INDC........................................................ 44

7.1.2 Improving MRV capability through the use of the JCM ........................ 44

7.1.3 Specific projects going forward ................................................................. 45

8. Conclusion: Strategic engagement about JCM development ............. 46

1

1. Overview of the study

1.1. Background and Objective of the Study

Renewable energy is widely promoted in Kenya to respond the increase of electricity demands.

We will conduct a feasibility study (F/S) for installing Japanese Solar PV system at Mwea rice mill

and calculate the GHG reduction by this project at rice mill. And we will promote the Japanese

Solar PV system based upon the F/S to other sectors in Kenya.

1.2. Scope of the Study

The scope of F/S is to install Solar PV system with 200kW to 500kW capacity at Mwea rice mill

owned and managed by NIB (National Irrigation Board). The solar PV system could reduce GHG

by alternating electricity from national grid or diesel generators. This GHG reduction at rice mill

will contribute to JCM scheme as well. KYOCERA will introduce their PV modules, PCS (Power

conditioners) and electricity control unit to this project.

The specific items of this study is as follows;

① Technical assessment of Solar generating system

② Potential assessment of irrigation sector

③ Potential assessment of private sector

④ Potential of GHG reduction by proposed projects

⑤ Issues and opportunities on project development

⑥ Utilizing the JCM in the Future

⑦ Conclusion: Strategic engagement about JCM development

2

1.3. Outline of “Japanese technology”

Figure 1 Before and After the project

Mwea rice mill uses electricity provided from National grid and standby diesel generators.

Project will install Solar PV system (PV module/ PCS: Power Conditioner) and Controlling system

arranged by KYOCERA. Regarding KYOCERA PV modules, they have over 30 years records of

operation, and third party institutions/organizations verify their reliability. Controlling system can

provide electricity with minimized batteries to reduce the initial cost. And the controlling system can

utilize electricity from National grid / diesel generates at night or on rainy/cloudy days when Solar

PV does not generate enough electricity. Even Controlling system can improve the quality of

electricity.

Before Project (Current)

After project

3

2. Technical assessment of solar generating system

This chapter examines a concrete plan for a follow-up project using the type of solar power system

targeted to be used under the JCM in Kenya.

2.1. Self-consumption project employing linear control for solar power systems in Kenya

2.1.1 Key points concerning solar power linear control

This section discusses the deployment of a solar power linear control at Mwea Rice Mills (MRM)

in Kirinyaga County, Kenya. Linear control is a technology needed to maximize solar power supply

without generating a reverse power flow, and is used when deploying a solar power system at a plant

with unstable power loads.

In general, solar power systems are connected via power conditioners to the national grid, which is

run by a power utility. Power generated by a solar power system is first consumed according to that

consumer's load. The remainder is then sent to the national grid via reverse power flow and is

purchased by a power utility. In other words, maximum power output is achieved at all times,

regardless of the load being used by the consumer.

However, many countries that have fragile power grids or that do not have net metering systems

prohibit power generated by a solar power system from being sent to the national grid. When deploying

solar power systems in such countries, one can deploy solar power systems with output capacities

smaller than the consumer's load, which eliminates any reverse power flow. One can also install a

reverse power relay (RPR) at the point of connection to the power grid. When the RPR detects a

reverse power flow, it shuts down the solar power system. The first method, because it involves

limiting solar power systems' capacity, does a poor job of reducing CO2 emissions and lowering grid

power consumption. The second method involves frequent shutdowns of the solar power system. Thus,

both methods have problems in terms of capacity utilization.

Therefore we propose the “PV Linear Control System”, which allows a solar power system to

operate in accordance with the load used by a consumer without ever shutting down, and does not

involve generating a reverse power flow to the national grid. “PV Linear Control System” allows for

monitoring the power flow at the grid connection point and the output generated by the solar power

system, and controls the output from the system so as to avoid generating a reverse power flow to the

grid.

When a net metering system is implemented in the future, it will be easy to change from the linear

control system to maximum power point tracking by reconfiguring the control system software. This

will make it possible to sell surplus electricity to the grid while still consuming self-generated power.

The figures below show the workings of the two systems.

4

Figure 2 Existing method and PV Linear Control System

5

2.1.2 Overview of project site

The following provides an overview of MRM, the site for this project. Mwea irrigation scheme

plays an important role in the cultivation of the rice milled at MRM. The NIB (National Irrigation

Board) built MRM's facilities and currently maintains and manages them. Since MRM is a subsidiary

of NBI, MRM is, in a broad sense, part of the Mwea irrigation scheme. Mwea irrigation scheme are

an important aspect of NIB planning, and there are plans to expand the irrigation area. Mwea is a major

irrigation scheme for rice cultivation and a model of agricultural success through irrigation.

Figure 3 Location and facilities

Figure 4 MRM facilities

Mill [1]

Mill [1] Mill [2]

Mill [2] Ware houses

Ware houses

6

2.1.3 System considerations

1) Power usage

MRM purchases power from Kenya Power, a power company. We obtained electricity charges for

the 12 month period from September 2015 to August 2016, and looked at annual contract demand

(kVA) and power consumption. Maximum contract demand was 277 kVA (June 2016) and annual

power consumption was 387,367 kWh. The figure below shows contract demand and power

consumption.

Figure 5 Annual contract demand and power consumption

Contract demand was about 260 kVA and no significant monthly fluctuation was seen. Power

consumption was 51,239 kWh in January 2016 — about two times greater than the months preceding

and following. According to an interview with MRM, this is due to the double-shift system instituted

during the peak season (January – April) to accommodate the extended operating times. No other

seasonal power consumption fluctuations occurred. It should be noted that power consumption

gradually rose after dropping in November 2015.

However, the system examined in this feasibility study utilizes a technology that enables real time

tracking control of solar power system output against consumer load fluctuation in increments ranging

from one second to several tens of seconds. Gauging the effectiveness of deploying a solar power

system consequently requires a power usage profile for demand in one-minute increments. We

therefore conducted a site survey at MRM whereby we measured a power usage profile based on one-

minute increments.

The power usage profile for an MRM operating day in October 2016 is shown below.

0

50

100

150

200

250

300

0

10,000

20,000

30,000

40,000

50,000

60,000

2015-Sep

2015-O

ct

2015-N

ov

2015-D

ec

2016-Jan

2016-Feb

2016-M

ar

2016-A

pr

2016-M

ay

2016-Jun

2016-Jul

2016-A

ug

De

ma

nd

[k

VA

]

Po

we

r C

on

su

mp

tio

n [

kW

h]

Power consumption Demand

7

Figure 6 MRM's power usage profile (one-minute increments, October 2016)

The maximum load in the power usage profile for the operating day measured was 277 kW (at 11:23

AM). Plant operating hours are estimated to be from 8 AM to 5 PM, giving a daily load between 60

kW and 150 kW. Night time load is an almost constant 1–3 kW, suggesting a power draw from night

time lighting or other equipment.

To evaluate year-round business sustainability, we must also take into account monthly power usage

fluctuations. Although it is usually desirable to measure power usage profiles on a monthly basis, for

this feasibility study we made a proportional correction based on power usage for each month to the

power usage profile, which involved measuring power consumption on one plant operating day in

October 2016. Actual values obtained from electricity charges for the past 12 months are given for

monthly power consumption. MRM operates on weekdays and Saturdays. Workers are on holiday on

Kenya's national holidays, which fall on January 1, March 25, March 28, May 2, June 1, July 8,

October 20, December 12, and December 26.

The figure below shows power usage profile for May 2016 after correction.

0

25

50

75

100

125

150

175

200

225

250

275

3000:0

0

2:0

0

4:0

0

6:0

0

8:0

0

10:0

0

12:0

0

14:0

0

16:0

0

18:0

0

20:0

0

22:0

0

Lo

ad

Pro

file

[kW

]

8

Figure 7 Power usage profile for May 2016 (after correction)

0

50

100

150

200

250

30005/0

1

05/0

2

05/0

3

05/0

4

05/0

5

05/0

6

05/0

7

05/0

8

05/0

9

05/1

0

05/1

1

05/1

2

05/1

3

05/1

4

05/1

5

05/1

6

05/1

7

05/1

8

05/1

9

05/2

0

05/2

1

05/2

2

05/2

3

05/2

4

05/2

5

05/2

6

05/2

7

05/2

8

05/2

9

05/3

0

05/3

1

Lo

ad

Pro

file

[kW

]

9

2) Site information

MRM uses a large amount of power during the day to operate its rice mills that produce edible rice

from paddy. Some of the MRM site is unused land and could be used to install high-capacity solar

power systems.

The Embu-Nairobi Highway runs close by the site, allowing for relatively easy transport of

equipment and materials by truck.

Figure 8 View of the candidate site for solar power system installation (MRM)

3) System structure

The system being considered for MRM uses 1,152 solar cell modules rated at 270 W, giving a total

of 311.04 kW. The figure below shows a layout of the site.

Figure 9 Site layout (MRM)

80 m x 30 m of the plant site is usable land that would allow for the installation of a solar array that

could generate up to 311.04 kW. The diagrams and estimates provided below assume the deployment

Electric Room

Container Room

Cable Root* Power Line* Control Line

Map Data ⓒ2016 Google

Image ⓒ2016 Landsat / Copernicus

10

of solar panels capable of providing 311.04 kW of output, the scale needed to maximize self

consumption at the site. The unused land could also be utilized for a future solar array expansion. The

"Container Room" in the figure would be a container-like equipment storage facility and would store

power conditioners, AC Connection Board, and interface box. The "Electric Room" is MRM's existing

electric room and would serve for the installation of a PV Switchgear Panel and control box.

The diagram below shows the system block.

Figure 10 System block diagram (MRM)

12 power conditioners rated at 25 kW would be used. The power conditioners' output cables would

collect power via the breaker box and photovoltaic connection boards, and would connect to the bus

bar on the existing switchgear panel. In addition, the photovoltaic control box would collect power

supplied from the grid and output generated by the solar power system, maximize self consumption

at the plant, and instantly compute the maximum generated output for the solar power system such

that there was no reverse power flow to the grid. The computed maximum generated output from the

solar panel system would be sent to the power conditioners via the interface box, and the power

conditioners would control solar power system output according to the command values received

from the PV Control Box. Accomplishing this entire control procedure in just a few seconds allows

for linear control of solar panel system output according to the rice mill's power load.

System Block Diagram

Grid 3φ 3W11kV, 50Hz

Photovoltaic Array24s × 4p 25.92kW

Photovoltaic Array24s × 4p 25.92kW

Pyranometer

Thermometer

: Power Cable

: Signal Cable

: LAN Cable

Photovoltaic Array24s × 4p 25.92kW

Photovoltaic Array24s × 4p 25.92kW

Power ConditionerNo.6 25kW

Power ConditionerNo.7 25kW

Power ConditionerNo.12 25kW

Power ConditionerNo.1 25kW AC

Connection BoardNo.1

ExistingHUB

500A Busbar 500A Busbar

500A Switch

500A Switch

30A Switch

60A Switch

100ASwitch

30ASwitch

15ASwitch

30ASwitch

150ASwitch

150ASwitch

Transformer

630kVA11kV/433V

3φ 4W, 250/433V, 50Hz

Interface Box(With Signal Transducer)

Off

ice

Man

ager

House

White

Ric

e M

ill

Par

boile

dR

ice M

ill

Boile

r R

oom

Genera

tor

Room

Lig

hting

/ O

utlet

Road

Lig

hting

Par

boile

d R

ice M

ill (N

ew

P

anel)

AC Connection

BoardNo.2

DG 72kVA

PVSwitchgear

Panel

PV ControlBox

Switch

PV Site Electrical Room

InternetTotal PV Capacity : 311.04kW(270W x 24s x 48p)

Container Room

11

4) Power generation simulation

The figures below show power generation simulations for a sunny day and cloudy day in May 2016,

after system implementation. Total solar array output of 311.04 kW was used for the trial calculations,

Metronome Ver 7.1 was used for the sunlight database, and JIS C 8907 was referenced as a power

output calculation standard.

Using the ratio of generated output for the solar power system to the load power used, the energy

self-consumption rate was 92% on sunny days and 36% on cloudy days. On sunny days, the solar

power system supplies about 90% of the power used by the plant. Moreover, there is no reverse power

flow (negative numbers) to the national grid. Solar power system output is being adjusted via linear

control according to the plant's power load.

Figure 11 Power generation simulation (sunny day in March)

Figure 12 Power generation simulation (cloudy day in March)

0

50

100

150

200

250

300

0:0

0

2:0

0

4:0

0

6:0

0

8:0

0

10

:00

12

:00

14

:00

16

:00

18

:00

20

:00

22

:00

Po

we

r (

Lo

ad

& P

V) [

kW

]

PV(After Control)

PV(Before Control)

Load

Grid

Energy self-

sufficiency rate = 92%* Load : 1,069 kWh/day* PV : 986 kWh/day* Grid : 83 kWh/day

0

50

100

150

200

250

300

0:0

0

2:0

0

4:0

0

6:0

0

8:0

0

10

:00

12

:00

14

:00

16

:00

18

:00

20

:00

22

:00

Po

we

r (

Lo

ad

& P

V) [

kW

]

PV(After Control)

PV(Before Control)

Load

Grid

Energy self-

sufficiency rate = 36%* Load : 1,069 kWh/day* PV : 382 kWh/day* Grid : 687 kWh/day

12

5) System pricing

In light of the technologies for linearly controlling solar power system output and of the need to

guarantee the system, the main equipment and materials required for the solar power system will be

procured from Japan.

Table 1 shows the total costs for the project in four categories: (1) equipment and material cost, (2)

transport cost, (3) trial run technology cost, and (4) construction cost. VAT will be added to the total

amount.

Table 1 Total project costs (not including MRM or VAT)

No. Equipment or Cost Quantity Price

① Equipment and material cost

$ 614,000

1 Mounting structure 1,152

2 Equipment to be installed 1

3 Power conditioners

(25 kW models) 12

4 AC Connection Board 2

5 PV Switchgear Panel 1

6 Control system 1

7 Measuring device (including a

weather gauge) 1

8 Cables, etc. 1

② Transport cost $ 61,600

③ Trial run technology cost $ 67,000

④ Construction cost $ 310,600

Total $ 1,053,200

6) Projections for utility power consumption reduction and return on investment due to self-

consumption

Deploying this solar power system and maximizing the self-consumption of its output can reduce

power purchased from the national grid. Fig. 13 shows projections for reducing power purchased from

the national grid. Fig. 14 shows projections for years until return on investment and profit loss

assuming that costs related to the power grid and the site's power contract (kW unit price, kWh unit

price, fixed fees, fuel charges, foreign exchange fees, other taxes) will not change from their 2016

levels. Return on investment will be obtained in approximately 25.2 years.

13

Figure 13 Projections for reducing power purchased from the national grid

Figure 14 Years until return on investment and profit/loss

7) Ideal scenario “Maximize the demand of MRM”

As Fig.11 shows, the peak of electricity demands at MRM was at 11am and 16pm. Although

electricity generated by solar power system reach the highest amount around noon, the electricity

demand isn’t high. If MRM operates facilities in accordance with the pattern of solar power generation,

the efficiency of power usage will be improved.

The figure below showed the improved demand at MRM. In this scenario, MRM could use almost

all the electricity generated by solar power system. Return on investment will be improved and

obtained in approximately 14.1 years.

0

10,000

20,000

30,000

40,000

50,000

60,000

20

15

-Se

p

20

15

-Oc

t

20

15

-No

v

20

15

-De

c

20

16

-Jan

20

16

-Fe

b

20

16

-Ma

r

20

16

-Ap

r

20

16

-Ma

y

20

16

-Ju

n

20

16

-Ju

l

20

16

-Au

g

Po

we

r C

on

su

mp

tio

n [

kW

h]

Before

Aftetr

-120,000

-110,000

-100,000

-90,000

-80,000

-70,000

-60,000

-50,000

-40,000

-30,000

-20,000

-10,000

0

10,000

20,000

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

[k K

sh

]

Annual Saving of Electrical Bill

Accumulated Saving Against Initial Cost

Initial Cost

14

Figure 15 Improved power generation simulation (sunny day in March)

0

50

100

150

200

250

3000:0

0

2:0

0

4:0

0

6:0

0

8:0

0

10

:00

12

:00

14

:00

16

:00

18

:00

20

:00

22

:00

Po

we

r (

Lo

ad

& P

V) [

kW

]

PV(After Control)

PV(Before Control)

Grid

Load(After adjustment)

Energy self-sufficiency

rate = 92%* Load : 1,875 kWh/day* PV : 1,723 kWh/day* Grid : 151 kWh/day

15

3. Solar power potential in irrigation sector

3.1. Potential assessment of irrigation sector

3.1.1 Rice industry

Ministry of Agriculture (now Ministry of Agriculture, Livestock and Fisheries) has published

““National Rice Development Strategy (2008 – 2018)” 1 . According to this strategy, the

consumption of rice will reach 517,538,004tons /year. And in order to supply all the rice from

domestic farmers, the production of rice should grow 9.31%/year. This means the rice production

increase three times between 2008 and 2030.

Figure 16 Projections on production and consumption of rice by 2030

3.1.2 Irrigation policy

Ministry of Agriculture, Livestock and Fisheries2 has published “National Irrigation Policy,

2015” 3 (NIP2015). NIP pointed that Kenya has not fully developed the irrigation potential

estimated as 1.342 million ha. The irrigation potential is based on surface and underground water

1 Ministry of Agriculture “National Rice Development Strategy (2008 – 2018)” 2 From 2016, the Ministry of Water and Irrigation is in charge of irrigation

policies. 3 Ministry of Agriculture, Livestock and Fisheries “National Irrigation Policy,

2015”

16

including water harvesting and storage. By end of 2013, approximately 161,840 ha of irrigation

potential had been developed. This is about 12% of the potential leaving more than 80% of Kenya's

irrigation potential undeveloped.

Additional irrigation infrastructure will be developed and existing schemes expanded by the

National Government in collaboration with the County Government, with the aim of attaining the

national target in order to ensure irrigation contributes to the attainment of national targets,

1,341,900 ha by 2030. This ambitious policy means that the irrigation scheme in 2030 is eight times

larger than in 2013.

3.1.3 Strategic Plan of NIB

NIB has published “Strategic Plan 2013-2017” and showed the specific plan of irrigation

development as shown in the following table.

Table 2 Irrigation plan of NIB

Number of

projects

Irrigation area Irrigation area

(2013 – 2017)

Estimated Cost

(Ksh million)

Large scale 28 502,750ha 120,650ha 65,364

Small scale 108 47,000ha NA 31,339

Total 136 549,750ha - 96,703

The table shows that NIB has specific plan to develop 549,750ha. On the other hand, the target

of NIP2015 is 1,341,900 ha by 2030. If NIB accomplish all the project, the irrigation area will be

40% of target showed by NIP2015.

17

3.1.4 Specific Plan of NIB

Figure 17 Irrigation plan by NIB and three prioritized projects

The figure above illustrates the irrigation plan by NIB and three prioritized projects. We

interviewed with NIB and found 1. Galana and Kulalu Ranch project, 2. Expansion of Mwea

irrigation scheme and 3. Expansion of Mwea irrigation scheme are the prioritized projects.

Especially, the electricity demands of Galana and Kulalu Ranch project will be 5MW, and NIB

will install diesel generators to supply electricity. Considering the solar diesel hybrid system, the

potential of solar power system in Galana and Kulalu Ranch project will be around 3MW.

3.2. Summary of potential assessment of Irrigation sector

The table below shows the summary of potential assessment of Irrigation sector. Currently, the

facility which we can install solar power system is only Mwea Rice Mills (MRM). Other mills are

small to install solar power system. The proposed capacity of solar power system at MRM is

311.04kW. According to the “Strategic Plan 2013-2017” of NIB, the irrigation area will be

developed to 3.4 times larger. The potential of milling facility will also 3.4 times larger than MRM.

18

We could assume that the potential of solar power system in irrigation scheme would 1,057kW

(311.04kW x 3.4).

In addition, we could point out that the potential of solar power system at Galana and Kulalu

Ranch would be around 3MW.

Table 3 Summary of potential assessment of Irrigation sector

Policy/Plan Objects Increase

1. Ministry of

Agriculture

National Rice

Development

Strategy (2008 –

2018)

Rice production 7 times

(2008-2030)

2. Ministry of

Agriculture,

Livestock and

Fisheries

“National

Irrigation Policy,

2015

Irrigation area 8 times

(2013-2030)

3. NIB Strategic Plan

2013-2017

Specific irrigation plan 3.4 times

(2013- )

19

4. Potential assessment of private sector

4.1. Market potential for solar power in Kenya

There are two main methods for installing solar power systems: ground installations and rooftop

installations. With the former, sufficient land needs to be acquired for the project size. Ground

installation projects in Kenya hold considerable market potential in Kenya due to the vast space

available. However, using this plan requires negotiating with landowners and having regard for the

preservation of flora and fauna. As discussed further on, ground installations also carry risks that

include having the equipment stolen. Because of these circumstances, this study focuses on the

potential of installing solar power systems on rooftops.

The total potential for solar power system installation in the nonresidential market in Kenya has

been estimated between 900 MW and 1700 MW. As this estimate assumes nonresidential building

area comprises the rooftops of all plants and warehouses, the true capacity is likely to be lower. As

discussed later on, interviews with people in the private sector suggest there are anywhere from

2,000 to 3,000 warehouses in the country, which would place total potential output at somewhere

between 900 MW and 1700 MW.

4.2. Analyzing the business environment for the solar power market in the private sector

4.2.1 Interview with private sector business operators

We interviewed government officials, EPC business operators, project developers, and private

enterprises that have the potential to install solar power systems in the future.

From the interviews, we learned that the most promising market for solar power in the private

sector is the grid-connected self-consumption market for private citizens.

One reason is that Kenya receives abundant sunlight — a prerequisite for solar business — that

will allow for more power generation than would be possible in Japan. Another reason is that the

necessary investment costs for installing solar power systems is 1.0 to 1.5 USD/W, less than half

the cost in Japan. Depending on project period length, this would allow for keeping power

generation costs even lower than the cost per energy unit on grid power. However, grid power is

expensive and felt to be burdensome by many private enterprises. These factors seem to suggest

potential for business in Kenya that involves supplying solar power systems to replace grid power

usage.

Assuming a project period of 12 years, the power cost would be 9 cents/kWh during the project

period, less than half the price of grid power. Given this power cost comparison, the self-

consumption market is eminently feasible. There are business risks, however, and political risk is

estimated to be chief among them. Consequently, projects with overly long payback periods are not

20

likely to get off the ground. Every enterprise interviewed said their payback period was around five

years, which suggests five years or so will be the hurdle for new businesses.

Lastly, all enterprises thought Japan's renewable energy technologies produced high-quality,

albeit costly, products. There is a considerable gap between the current market prices of solar panels

in Japan and the price of solar panels in Kenya as we discovered in the study. Given that solar panels

have come to be viewed as commodities, improving cost competitiveness in order to continue

selling their products will remain a major focus for Japanese manufacturers.

Table 4 Findings from interviews with private enterprises

No Question Category Summary

1

Trends concerning permits

and laws

Half of those we interviewed were skeptical about any

kind of FIT or net metering system being implemented.

Some systems may offer a certain measure of cost

performance.

2 Industrial power pricing

trends

Everyone felt industrial power pricing in Kenya was too

high and wanted lower pricing

3

Cost of investment for solar

power system installation

Solar power systems cost roughly 1.5 to 5.0 USD/W to

install. Recently, cost of some large projects are less than

1.5 USD/W.

4

Environment for locally-

sourced financing

Lending rate regulations stifle private enterprises' ability

to get financing and loans are difficult to get for high-risk

projects. Financing thus remains a challenge. However,

with respect to companies with relatively stable finances,

it is possible to get financing from international

organizations/investors.

5

Business risk in Kenya Political risk (risks involving politics, changes to approval

schemes, etc.) was thought to be the most significant

business risk. Some development-related enterprises said

they had trouble getting land rights.

6

Solar power business

development in Kenya

Most solar power projects are on the scale of 100–200 kW,

and extremely short payback periods (roughly 5 years) are

commonly desired.

7

Evaluation of Japanese

renewable energy

technologies

Although everyone we spoke with lauded Japanese

renewable energy technologies for their high quality, sales

prices were about twice that for locally-sourced panels.

21

4.2.2 Cost performance analysis and economic scale from solar business, as learned

through interviews

Based on the above considerations, we estimated the economic scale of renewable energy

generation business (100% self-consumption model) in Kenya. This was accomplished by

multiplying the potential capacity as already calculated in the potential output analysis by the

economic scale of that capacity (including deployment costs and total maintenance fees during the

project period). The figure below presents these results.

The economy for the deployment of solar power systems solely for self-consumption in Kenya

could be up to 2,667 million USD, and the economy for maintenance around 755 million USD.

Table 5 Economic scale estimates

4.2.3 Analyzing self-consumption private IPP businesses in Kenya

As background context for this business conditions, some private enterprises are beginning to

appear that use renewable energy to offer decreased electricity charges as a business solution. South

Africa-based SolarAfrica is a project developer that uses solar power. The company operates a solar

power energy supply service for Garden City Mall, which was built outside Nairobi in 2015.

Facility overview

Garden City Mall is a large shopping mall along Thika Road, 13 km north of downtown Nairobi.

The mall opened in 2015 with facilities that include everything from restaurants to a consumer

electronics chain store, a supermarket, and clothing stores.

Economic scale calculations

Subject Value Unit Source

Project period 12 years Arbitrarily set

Unit of capacity 1.5 USD/W From interviews

Installed capacity 100 kW Arbitrarily set

Deployment cost 150,000 USD Unit of capacity x installed capacity

Annual maintenance cost 7,500 USD 5% of annual sales

Total maintenance cost 42,453 USD Discounted present value through government bonds

Total 192,453 USD Deployment cost + total maintenance cost

Economic scale for capacity 2 USD/W

Breakdown: Deployment cost 1.5 USD/W

Maintenance cost 0.4 USD/W

Economic scale based on potential

Subject Value Unit Source

Potential installed capacity 1,778 MW Estimate of potential

Economic scale for capacity 1.9 USD/W From above calculation

Economic scale 3,422 M USD Potential capacity x economic scale for capacity

Breakdown: Deployment cost 2,667 M USD

Maintenance cost 755 M USD

22

Figure 18 Aerial view of Garden City Mall

Business scheme

SolarAfrica operates a business that supplies renewable energy to this shopping center. The figure

below details the company's business scheme based on the information we have obtained.

Figure 19 Business scheme

Table 6 Organizations involved in the Garden City Mall Project

Role Organization Notes

Client Garden City Mall Shopping mall owner. Mall funding was

provided by Actis, an investment fund

financing projects in Asia and South

America

General contractor SolarAfrica Co., Ltd. A company that provides solar power

Garden City Mall(ショッピングセンター)

(太陽光発電プロジェクト・オーナー)

BOT契約12年間 設置施工

EPC発注

(EPC事業者)

(Solar power project owner)

(EPC)

EPC contact

12-year BOT contract Building and installation

(Shopping center)

23

self-consumption solutions and

financing functions for enterprises in

Africa

EPC Solar Century Co., Ltd. Designs and builds solar power systems

Project owner SolarAfrica contracts out system construction to Solar Century (which handles

EPC, i.e. engineering procurement, and construction). Solar Century designs and builds solar power

systems for Garden City Mall. After the system is built, Solar Century provides the system to

SolarAfrica. SolarAfrica has formed a 12-year BOT (Build Own Transfer) agreement with Garden

City Mall and will be in charge of system operation for this contract period. Generated output is

sold to Garden City Mall to be used within the mall. When the agreement period ends, power

generation equipment ownership transfers from SolarAfrica to Garden City Mall.

Installed system structure

The following table lays out the structure of the installed system.

Table 7 Garden City Mall project solar power system structure

Subject Details Notes

System structure Solar diesel hybrid system System switching is performed

automatically using a system

controller made by SMA

Installed panels 3,366 255 W output per panel

Panels made by Yingli Green

Energy

Total output (kW) 858 kW

CO2 emission reduction

during operating period

18,750 tons 12-year operating period

The system is characteristic for its usage of multiple small inverters (with about 12 kW in output

each) rather than one or two large inverters (with 500 kW-level output) as is common at mega solar

plants. Recent years have seen usage of this multiple small inverter system design in distributed

systems, even in Japan.

Although more power conditioners increases the need for maintenance manpower, this system is

able to minimize power loss as its power conditioners are capable of shutting off. This type of

system, which utilizes multiple smaller power conditioners, is seen as a practical means of risk

avoidance in environments such as Kenya where there is a lack of a robust network for system

24

maintenance and inspection.

Figure 20 Installed power conditioners

Installation conditions

The following photos show how system equipment is installed. Panels are used to construct the

roofs over carports in covered parking lots. Installing solar panel systems on carports makes

effective use of the plentiful space of covered parking lots while at the same time keeping

temperatures down inside cars parked there.

Figure 21 Solar power plant using carports

25

Figure 22 Mounts for solar panel-equipped carports

System operation monitoring

According to its service agreement, SolarAfrica provides monitoring and maintenance services,

and guarantees performance. SolarAfrica conducts monitoring remotely, with maintenance and

inspections performed using the company's local network of partners.

4.3. Analyzing business risk

This section discusses business risks in Kenya and potential solutions to mitigate them.

Essentially, rather than building a business scheme dependent on feed in tariffs, as is the case in

Japan, it would be advisable to build a business scheme focused on replacing costly grid energy

with low-cost renewable energy and recouping investment in a short timeframe.

Table 8 Renewable energy-related business using Japanese technologies

No Risk Solutions

1

Non-payment risk - Presently, those installing solar power systems for

self consumption should be limited to foreign-

owned enterprises operating in Kenya, state-backed

enterprises with financial stability, and other such

organizations.

- It is also advisable to minimize payback risk from

nonpayment by dramatically shortening the

payback period by such means as reducing the costs

of the systems installed.

26

2

Technical risks - In order to prevent unexpected output drops during

the operating period, enterprises must choose solar

panels that can stably generate power over the long-

term, i.e. nationally certified panels or panels that

conform to proprietary standards.

- Enterprises need to hire engineering companies with

extensive experience building systems in order to

mitigate technical risks throughout the entire system

3

Operation and maintenance

risks

- To minimize system downtime, enterprises also need

to bring on as project partners local O&M

companies with problem-solving ability

4

Foreign exchange risk - In PPA agreements signed with local enterprises, the

U.S. dollar should be used as the currency for the

payment of self-consumption service charges to

project owners by local enterprises.

5

Risk of theft - Systems should be installed on the roofs or rooftops

of the facility, whether a plant, warehouse, or

shopping center. This deters theft by making it

difficult to physically interact with the equipment

6

Political risk - Building a business scheme that is not reliant on the

usage of a feed-in-tariff or net metering system is

ideal

- Enterprises should deploy self-consumption systems

through "private-private agreements" with the aim

of replacing high cost grid power with low-cost

renewable energy as a means to mitigate the risk of

changes to legislation or permit systems.

27

4.4. Feasibility of market entry by Japanese enterprises

We examined the feasibility of solar power market entry in Kenya by Japanese enterprises. The

figure below presents general power generation business schemes for countries to use.

These can be broadly categorized into two methods by which Japanese enterprises can do

business in Kenya. The first involves providing products or services to the Kenyan market. More

specifically, it involves either selling solar panels or designing and building systems and then selling

them — engineering businesses, in other words. The second entails operating a pure investment

business. This means running business more indirectly instead of directly operating a business.

Specific methods for market entry may include contributing to investment funds whose sole focus

is on renewable energy investment, or offering loans through an SPV established to conduct power

generation business locally.

Figure 23 Options for doing business in Kenya's solar power industry

The table below provides additional notes on the role of different enterprises in the above business

schemes.

Table 9 Renewable energy-related business using Japanese technologies

Enterprise Role Notes

Investor Domestic investor Operates renewable energy

generation business in Kenya

Investment fund Obtains funding from investors and runs a

fund

Using an investment fund is not

necessary but may be useful in

certain cases.

SPC A special purpose corporation established

through an investment fund in the business

Are generally established in the

business hub country, after

Investor A

Investor B

Investor X

Investment fundSPC

(business hub

country, etc.)

Commercial

and industrial

sector

enterprises

SPV

Local EPC,

etc.

Investment

Dividends

Financing

Investme

nt

Management

O&M

Investment

Dividends

PPA

or

Lease

Solar power

equipment

1

Conduct business in the products

and services market

Invest in power generation business

28

hub country. consideration of the presence of

investment treaties, etc. between

Japan and the investee country.

SPV An investment vehicle established for each

project by a special purpose company

Uses the appropriate legal

instruments based on the local legal

and taxation systems

Local EPC, etc. Enterprises engaged in engineering,

procurement, and construction of power

generation systems in Kenya

May include conducting O&M

after project start

Solar power

equipment

Power generation equipment owned by an

SPV locally

Supplies generated power to a client

Enterprises in the

commercial or

industrial sectors

Are the purchasers of power and the

enterprises that have solar power systems

installed

Procure power from SPVs through

PPA agreements, etc.

4.5. Business feasibility in the products or services market

4.5.1 For the utility-scale market (500 kW – 40 MW)

With respect to systems for the utility-scale market, enterprises need to reduce EPC costs by

conducting bigger projects. Reducing EPC costs low keeps initial investment low, which in turn

lowers power generation costs throughout the project period. By lowering these costs, enterprises

can make winning bids with cheaper power selling prices when they participate in feed-in tariff

auctions.

Another important requirement regarding solar power systems is ensuring that output does not

drop during the project period. Conservatively speaking, solar power system output generally

declines by about 0.5% yearly. For utility-scale projects with particularly long project periods (over

20 years or so), annual average degradation rate numbers can significantly impact business

profitability. The figure below presents a graph estimating cumulative cash flow in the 20th year for

different annual degradation rates.

29

Figure 24 Cumulative cash flow for different annual degradation rates (at the time of project period

end)

It has been estimated that, when compared to the base case of a 0.5% annual degradation rate, a

rate of 3.0% results in a roughly 30% difference in cumulative cash flow by the end of the project.

With utility-scale projects involving systems with tens of thousands of panels, defective panels

sometimes need to be replaced after they have already been installed. The replacement costs in this

case are enormous, and are extremely damaging to the business's bottom line.

As we can see from the above, in the case of utility-scale projects, while it is important to reduce

initial investment costs, enterprises must also deploy solar panels that can continue to stably provide

a certain level of output as long as they are in use.

4.5.2 For self consumption market (several kW to 500 kW systems)

We now turn to the needs of the self-consumption market and the technical requirements involved.

As mentioned previously, power costs are high in the industrial sector (about 20 Ksh/kWh). Solar

power systems have the potential to serve as non-utility power solutions that lower these high power

costs.

However, they require a reverse power flow to the grid. Kenyan law currently does not allow the

selling of surplus solar power back to the grid. Furthermore, although there are plans to deploy a

net metering system, there has been no clear indication of selling price or when the system will be

instituted. In view of the above, power control technologies that prevent excess solar power from

0.50% 1.00% 2.00% 3.00%

Cu

mu

lative

ca

sh

flo

w (

KsH

)

Mill

ion

Average annual degradation rate (%)

Cumulative cash flow for different annual degradation rates(at the time of project period end)

▲30%

30

going to the grid are likely to become technical requirements in the self-consumption market.

On many of the buildings in the industrial and commercial sectors, which are expected to be the

main markets for this technology, diesel generators are installed as emergency non-utility power

equipment. Enterprises will need to meet power control requirements that include coordinated

control for these diesel generators and solar power systems. In addition to incorporating these power

control technologies into systems, enterprises will have to develop a cost structure that will allow

for keeping total unit price during the project period to below that for grid power.

4.6. Power generation business investment feasibility

Now we would like to look at the potential for investing in power generation business in Kenya,

the second option available to Japanese enterprises looking to enter the Kenyan market. There

appear to be three options for business investment.

4.6.1 Business investment options

The first option is direct investment into trustworthy local EPC pursuits. Another option is

investing in an investment fund or SPC and recouping investment through dividend earnings. The

third option involves establishing an SPC oneself locally, which then runs a power production

business.

Figure 25 Three business investment options

Investor A

Investor B

Investor X

Investment fundSPC

(business hub

country, etc.)

Commercial

and industrial

sectorsSPV

Local EPC,

etc.

Investment

Dividends

Financing

1

2

Investment

Management

O&M

Investment

Dividends

PPA

or

Lease

Solar power

equipment

Power

supply

3

Investment in EPC Company

Investment in IPP Projects

31

The pros and cons of each option are shown below.

Table 10 Business investment option pros and cons

No. Option Pros Cons Challenges

1 Invest in EPC

Do not assume technical

risks (power plant

equipment risk) during the

power generating period.

Assume construction

completion risks, etc.;

earnings following

construction completion are

assured

As more projects

means more revenues

and expenses, the

effects of changes in

the economy and to

approval systems are

received directly

Finding trustworthy EPC

partners and making

investments

2 Invest in funds

Can hedge all business risks

associated with generating

power

Contract out to fund

managers operations such as

project monitoring

Is an investment

business, so business

growth potential is

limited (e.g. new

business created out of

power generation

business)

Finding good funds in

terms of investment

performance in the

renewable energy field

3

Invest in

power

generation

projects

(SPVs)

Can make earnings through

power generation business

based on stake.

Can expect stable CF

throughout the project

period

Will assume all

business risk

concerning the power

equipment, in addition

to all off-take, political,

and other risks

Minimizing business risk

and achieving a good cost

performance balance

4.6.2 Interview concerning feasibility of investment by Japanese enterprises

Based on the results of our studies and analyses so far, we held an exchange of views with

Japanese private-sector IPP enterprises concerning the feasibility of conducting renewable power

generation business in Kenya.

All were in agreement that non-payment risks and off-take risks were salient business risks. Given

the high price of electricity in Kenya, all enterprises were interested in self-consumption as a

solution that uses renewable energy. However, the fact that there is no network of trustworthy

enterprises in the country is a major hurdle to serious consideration of doing business in the market.

32

Many also said they may hesitate to invest in the country because of the existence of a feed-in

tariff system in Japan. The enterprises have renewable energy businesses in both Japan and other

countries, and the IRR in Japan and other countries are 5% and 15%, respectively. Under Japan's

feed-in tariff system, 20 years of revenue from sales of electric power is guaranteed for commercial

solar power systems. However, as previously discussed, power generation business in other

countries involves different risks than those in Japan, including off-take risk and political risk. In

order to invest outside of Japan, these enterprises therefore have to get upper managers on board by

explaining the grounds for and measures to accommodate the 10% IRR gap between Japan and

other countries. When unable to justify the 10% gap, they become unable to get the business going,

no matter how high the IRR may be.

4.7. Potential in off grid markets

4.7.1 Essence of hybrid mini-grid

In the areas where the extension of the national grid is difficult, the mini-grid system using diesel

generators is formed under the electrification policies that contribute to the improvement of living

standards of residents and local industrial development. However, electric power generation

systems that use fossil fuels lead to generation of greenhouse gas. Increases in fuel prices on a long-

term span are also concerned. In response to these issues, this FS proposes the implementation of a

hybrid mini-grid system in combination with a photovoltaic power generation system, which is a

renewable energy system (not including storage battery).

33

4.7.2 Potential assessment of hybrid mini-grid

Figure 26 Distribution of Hybrid-Mini Grids

(Source: Kenya Power)

The Government of Kenya repeated negotiations with various donors. The AFD (French Agency

for Development) decided to provide a low-interest loan of 30 million euros (approximately 4

billion yen) in 2013 for 23 sites in the map shown below. “Number 3, Lodwar” in the table below

is scheduled to expand the solar power generation system with a grant aid from NORAD

(Norwegian Agency for Development Cooperation).

34

Table 11 Hybrid Mini-Grids Plan4

4 AFD(African Solar Designs and Marge) “AFD Feasibility Study for an Off- Grid

Programme in Kenya”, June 2014

DIESEL

CAPACITY

(KW)

SOLAR PV

(KW)

WIND

(KW)

SOLAR PV

(KW)

WIND

(KW)

1 MANDERA 1,600 350 0 200 0

2 WAJIR 3,400 0 0 800 300

3 LODWAR 1,440 60 0 250 0

4 HOLA 800 60 0 100 0

5 MERTI 128 10 0 100 100

6 HABASWEIN 360 30 50 100 0

7 ELWAK 360 50 0 100 0

8 BARAGOI 128 0 0 100 100

9 MFANGANO 520 11 0 100 0

10 RHAMU 184 0 0 50+50 0

11 ELDAS 184 0 0 30+70 0

12 TAKABA 184 0 0 50+50 0

13 LOKICHOGGIO 640 0 0 80+70 0

14 LOKORI 184 0 0 150 0

15 FAZA 360 0 0 100 100

16 KIUNGA 230 0 0 150 0

17 HULUGHO 230 0 0 150 0

18 LAISAMIS 184 0 0 80 0

19 NORTH HORR 184 0 0 100 100

20 LOKITANG 184 0 0 150 0

21 DADAAB 640 0 0 200 0

22 MAIKONA 640 0 0 100 100

23 LOKIRIAMA 0 0 0 150 0

24 BANISA 0 0 0 100 100

12,764 571 50 3,730 900

NUNBER STAION NAME

EXISTING PROPOSED

for AFD

TOTAL

35

Concerning solar power generation systems and wind power generation systems in these 23 sites,

the material and technology to be adopted will be decided through tenders held by REA (Rural

Electrification Authority). For the time being, aggregate 3.5 MW solar power (without 3 Lodwar

site) generation indicated in this plan is the potential of hybrid mini-grids.

In addition to the support from AFD and NORAD, other funding from KfW(Reconstruction

Credit Institute, Germany), GIZ(German Federal Enterprise for International Cooperation)、World

Bank, DFID(Department for International Development, UK) , USAID and Embassy of Spain are

planning to provide supports to hybrid mini-grids. REA has identified over 100 sites and there will

be huge markets of renewable energy in rural electrification by the hybrid mini-grids.

4.8. Conclusion

The table below summarizes the overall direction for rural electrification and getting into IPP

business in Kenya using Japanese renewable technologies. We examined opportunities and

challenges for each market segment with respect to options for doing business (selling systems to

power project enterprises and investing in renewable energy projects using SPC, etc.).

36

Figure 27 Evaluation of business options in Kenya's solar power market

On gridOff grid

50

0kW

to

40

MW

Pro

jec

t

Cap

acity

10

0kW

to

MW

cla

ss

Be

low

10

0kW

10

0kW

To

MW

cla

ss

So

urc

e o

f

Pro

fit

Au

ctio

n s

tyle

FIT

(<K

SH

12/k

Wh)

Alte

rna

ting

“Die

sel G

en

se

t”

(K

SH

50

-

60

/kW

h)

Alte

rna

ting

“Ke

rose

ne”

Se

lf-

co

nsu

mptio

n

by re

pla

cin

g

“Grid

Ele

ctric

ity”

(K

SH

20/k

Wh)

Ne

t Mete

ring

(<K

SH

2.6

/kW

h)

Sta

tus

of M

ark

et

•“A

uctio

n s

tyle

FIT

” will b

e in

trod

uced

in

20

17

.

•F

rom

the

“Au

ctio

n s

tyle

FIT

” in S

ou

th

Afric

a, F

IT m

igh

t be

KS

H4

to 6

/kW

h.

•B

idd

ers

ha

ve

to s

ho

w “c

om

pe

titive

FIT

by d

eve

lop

ing

larg

e s

ca

le p

roje

cts

.

•O

pp

ortu

nitie

s o

f “roo

f top

insta

llatio

n” a

t

co

mm

erc

ial s

ecto

rs a

nd in

du

stria

l secto

rs.

(so

me

sh

op

pin

g m

alls

insta

lled

so

lar)

•T

he

issu

e is

“Se

cu

re th

e in

itial c

ost”.

Le

ase

mo

de

l by P

PA

ag

ree

me

nt m

igh

t

be

a g

oo

d s

olu

tion

.

•H

yb

ridiz

atio

n (S

ola

r + G

en

se

tse

tc) a

nd

co

ntro

lling

syste

m w

ill be

req

uire

d.

•N

et m

ete

ring

po

licy m

igh

t be

a d

rive

of

“roo

f top

insta

llatio

n”

•H

yb

rid s

yste

m (S

ola

r + G

en

se

ts) is

ma

in

op

tion

. Co

ntro

lling

syste

m w

ith “A

nti

reve

rse

cu

rren

t” an

d “M

atc

hin

g w

ith

de

ma

nd

s” w

ill be

req

uire

d.

•P

roje

ct w

ith p

ub

lic s

ecto

rs w

ill attra

ct

“inte

rna

tion

al s

up

po

rt” e.g

. Irriga

tion

,

Ru

ral e

lectrific

atio

n.

•S

ola

r lan

tern

s a

re p

en

etra

ting

into

off-

grid

are

as.

Hard

we

ar / S

ys

tem

●C

om

pe

tition

of “E

PC

pric

e”

“Au

ctio

n s

tyle

FIT

●L

arg

e s

ca

le p

roje

cts

will

ha

ve

ad

va

nta

ge

. Ho

we

ve

r,

securin

g la

nd a

nd O

&M

will b

e c

ha

llen

ge

s.

○N

ee

ds o

f co

ntro

lling s

yste

m

(So

lar+

Ge

nse

t, Ma

tch

ing

with

De

ma

nd

s)

○P

roje

ct w

ith p

ub

lic s

ecto

rs to

ob

tain

“inte

rna

tion

al s

up

po

rt”

an

d s

ecu

re in

itial c

ost.

●C

ost o

f Ja

pa

ne

se

So

lar

pro

du

cts

/syste

m

○N

ee

ds o

f co

ntro

lling

syste

m (S

ola

r+G

en

se

t,

Ma

tch

ing

with

De

ma

nd

s)

○H

igh

effic

ien

cy o

f So

lar to

limite

d p

roje

ct s

ite

○T

ech

nic

al p

rop

osa

l with

se

cu

ring

initia

l co

st w

ill be

acce

pta

ble

●C

ost o

f Ja

pa

ne

se

So

lar

pro

du

cts

/syste

m

×○~◎ ○-

Inve

stm

en

t to b

usin

es

s

○In

vestm

en

t as a

min

or s

ha

re

ho

lde

rs o

f pro

jects

●L

arg

e s

ca

le p

roje

ct in

ord

er to

bid

co

mp

etitiv

e F

IT

●L

oca

l bra

nch

will b

e re

qu

ired

to

de

ve

lop

larg

e p

roje

cts

.

○P

ub

lic fin

an

ce

/ Inte

rna

tion

al

su

pp

ort w

ill de

cre

ase

the

off

take

rs ris

k.

●W

e c

an

’t invest in

Gra

nd p

roje

ct.

○A

ctiv

e m

ark

ets

with

“hig

h

ele

ctric

ity ta

riff”.

○P

roje

ct d

eve

lop

me

nt w

ith

fore

ign

inve

stm

en

t to s

ecu

re

the in

itial c

ost.

●P

artn

er s

hip

with

loca

l EP

C o

r

fore

ign

inve

sto

rs

●O

ff take

rs ris

k, E

PC

risk, O

&M

risk.

△○ ○-

Eva

lua

tion

an

d C

om

me

nts

“O

pp

ortu

nity

” a

nd

“C

ha

llen

ge”

Ou

tline

of S

ola

r PV

bu

sin

es

s in

Ke

nya

Ke

y:○:O

pp

ortu

nity

●:C

ha

llen

ge

Eva

lua

tion

an

d C

om

me

nts

37

Business in the power generation products and services market

Looking first at system sales business, diesel power alternatives in the off-grid market appears to

be the most attractive business option here.

However, the most competitive area appears to be the 500 kW or greater utility-scale market.

Although revenues and expenses can be more easily forecasted in power sales businesses operating

under a feed-in tariff system, keeping power costs low requires controlling total operating expenses

(initial investment + interest + operation and maintenance costs) incurred during the project period.

This effectively means Japanese system sellers negotiating on price with foreign system sellers to

keep initial investment low. According to a report published by IRENA in September 2016, there is

already a nearly 40% price difference between solar panels made in Japan and those made in China.

Given the likelihood of a price war with system sellers dealing in low cost panels under auction

systems, Japanese panel costs will need to come down even further if Japanese renewable energy

technologies are to be deployed in the utility-scale market.

Investment in power generation business

We next examine investment in renewable energy businesses in Kenya. There appear to be

opportunities here in areas that include investing in grid-connected, self-consumption systems

operating under net metering, as well as investing in SPCs offering diesel-alternative solutions for

the off-grid market.

Competition is most fierce, however, in the aforementioned system sales business and utility-

scale market, making such business investment tricky. In Kenya, the successful development of

utility-scale projects, in particular, requires not only planning for the kinds of business risk so far

discussed but also building a network with local EPC enterprises and government officials.

Enterprises that do not have a network or business office with project development functions in

the country will need to expend time and manpower to build them first. This makes utility-scale

projects relatively unattractive for business investment.

There are other possible business opportunities in these two areas, but success will require

forming agreements to effectively avoid off-take risk, in addition to having partners that can

faithfully and properly provide O&M services during the project period.

38

5. Potential of GHG reduction by proposed projects

5.1. Potential assessment of Irrigation sector

5.1.1 Proposed Methodology KE_PM002

In Kenya, a draft mmethodology “KE_PM002 Installation of Solar PV System” was

published under the JCM procedure on 2nd March 2017. The scope of GHG emission

reduction measures is “Displacement of grid electricity and/or captive electricity using fossil

fuel as a power source by installation and operation of the solar PV system(s)”. When we

successfully develop the proposed project under JCM scheme, we will apply this methodology.

5.1.2 Reference emission

KE_PM002 defines the emission factor as 0.533 tCO2/MWh. This emission factor is

lower than 0.5793 tCO2/MWh as the build margin calculated at that time addressed in the report

published by the National Environment Management Authority of Kenya (NEMA 2014).

The back ground of this consideration is that almost all of the electricity generated by “non

renewable and hydro power plants” which emits GHG was sourced from diesel. To ensure net

emission reductions, KE_PM002 uses conservative emission factor. The most efficient diesel

generator in the world has a generation efficiency close to 49%. A power generation efficiency

of 49% translates into an emission factor of 0.533 tCO2/MWh.

5.2. Estimation of GHG reduction by proposed projects

In the case of solar power generation, Project Emission (PE) is 0 (zero). And the amount of

Reference Emissions (RE) is equal to GHG reduction.

[Reference emissions]

REp Reference emissions during period p[tCO2/p]

EG i,y Quantity of electricity generated by project solar PV system i during

period p[MWh/p]

EFRE Reference CO2emission factor [tCO2/MWh]

39

5.2.1 Potential of GHG reduction by proposed projects

The table below shows the potential of GHG reduction by proposed projects in this study.

Table 12 GHG reduction by the proposed projects

Projects

Solar System

Capacity

(kW)

Electrity from

Solar system

(MWh/year)

GHG Reduciotn

(t-CO2/year)

1Mwea Rice Mills

*Under current factory loads311.04 285.2 152.0

2

Mwea Rice Mills

*Under the scenario Factory loads are

maximized

311.04 524.3 279.4

3 Galana and Kulalu Ranch project 3,000.00 5,056.6 2,695.2

4 Future potential at rice mills in Kenya 1,057.00 1,781.6 949.6

5Rural Electrification

(Hybrid Mini Grid)3,500.00 5,899.4 3,144.4

Step 3 6Future potential in Private sector

(roof tops of factries, mall etc)900,000.00 1,516,987.8 808,554.5

Total(2+3+4+5+6) 907,868.04 1,530,249.8 815,623.1

Step 1

Step 2

[Project emissions]

PEp Project emissions during period p [tCO2/p]

[Emissions reductions]

ERp Emission reductions during period p[tCO2/p]

REp Reference emissions during period p[tCO2/p]

PEp Project emissions during period p[tCO2/p]

40

6. Issues and opportunities on project development

Chapter 4 examined the possibilities for solar power business in Kenya and laid out two possible

avenues: 1. deploying equipment, systems, and other hardware, and 2. investing in projects. This

chapter looks at issues Japanese companies may face when getting into the solar power business in

Kenya and lays out a strategy for solving these issues and expanding business opportunities.

6.1. Issues involved in launching a business

6.1.1 Issues concerning business investment/capitalization

Focusing first on the subject of business investment, IPP businesses in Japan and energy or

infrastructure-related businesses that are already doing business overseas are among the companies

with a strong desire to invest in business in Kenya.

There are two risks with the potential to hinder business investment or capitalization in Kenya:

1. the lack of a business network, and 2. off-take risk.

Regarding 1., a comparison to Asian countries makes it clear that fewer Japanese companies are

doing business in Africa. Even companies interested in Africa do not even have agencies in the

region, let alone offices. This situation makes it extremely difficult to get local information, look

for potential partner companies, and then construct and execute a project. Simply put, Africa is still

a long way off for Japanese companies.

With respect to off-take risk, enterprises will need to carefully consider project owners' solvency.

In Kenya, there is a method for mitigating this-offtake risk by shortening the payback period for

initial investment to two or three years. However, there is a limited range of businesses where this

kind of short-term initial investment can be achieved, and it is very difficult to use this model for

solar power and other energy-related business.

6.1.2 Issues concerning the deployment of equipment, systems, and other hardware

Let us next analyze the issues involved in deploying equipment, systems, and other hardware.

We conducted a SWOT analysis (see figure below) focused on the entry of Japanese solar power

equipment manufacturers and EPC businesses into the Kenyan market.

The results point to cost as being the biggest issue with respect to Japanese solar power systems.

In light of this, and because the auction-determined feed-in tariffs to be conducted beginning in

2017 are likely to result in an EPC price war, deploying Japanese solar power systems will

unfortunately be rather difficult.

On the other hand, with respect to the use of self-consumption oriented solar power and solar

power for rural electrification, the linear control discussed here will have an advantage. Lowering

EPC prices is something that must be done, but reliable solar power systems and control systems

41

are areas where Japanese companies enjoy major advantages.

Especially in rural, off-grid areas, costly-to-run diesel generators are a necessity for electrification.

Consequently, it is conceivable that EPC costs under solar panel business will exceed those for

projects using FIT schemes. Because of the nature of off-grid areas, EPC costs are set high due to

the technical requirements, which include the need for hybrid diesel-solar systems. This project

would therefore be a good market entry project for Japanese companies.

6.2. Specific actions for establishing a business

In light of the issues described above, the following discussion focuses on specific actions for

conducting solar power business by Japanese companies in Kenya. Japanese companies should

begin in the public sector in order to demonstrate their technological advantages and, in the process,

build a steadfast EPC structure locally. After building a solid EPC structure, these companies can

ultimately launch private solar power businesses in Kenya with capitalization from Japan.

Figure 28 Future actions for business development

6.2.1 Japanese companies' advantages

Like the linear control and other technologies described in Chapter 3, Japanese companies hold

technical advantages when it comes to solar power systems. After these advantages are leveraged

in the Kenyan market, they need to be effectively advertised. Using solar power equipment with

low degradation rates, for example, can help avoid dramatic losses in cumulative cash flow over the

project's entire lifecycle. Another major benefit is the fact that using linear control brings solar

power equipment uptime to over 90%, whereas existing system uptime is only 25%.

[STEP1]Pilot project

MRM “Solar Pilot project”by LCET and JCM

[STEP2]Project withpublic sectorRenewable energy projectin Public sector with International support

[STEP3]Project with Japanese investmentProject development with investment from Japan.We will develop solar projects not only “Public sector”, but also "Private sector”.

42

It should also be made clear that, especially with projects conducted in the public sector, the

emphasis should be on the long-term durability and reliability of the equipment, as well as the

trustworthiness of the technologies themselves. In the case of business by private enterprises, there

is no need to extend project periods as long as initial investment is paid back and profits are

generated. Consequently, greater emphasis is often placed on EPC cost than on the long-term

reliability of solar power systems. Nevertheless, the goal of public sector projects is not to achieve

a return on investment but to maximize the benefits of solar power through long-term usage of the

equipment. Japanese enterprises need to conduct pilot projects and other efforts in order to show

the public sector the advantages of Japan's solar power systems.

6.2.2 Carrying out projects through international support

When promoting Japanese enterprises' solar power systems to the public sector, the JCM, LCET

Programme, and GCF (Green Carbon Fund) are some of the means available for acquiring

international support.

As discussed in the previous sub-section, the reliability of solar power systems over extended

project periods is highly compatible with the aims of public sector projects. Furthermore, public

sector projects solve development problems in Kenya and are therefore highly likely to receive

international support. Specifically, it may be effective to use international support to provide

renewable energy for irrigation projects in off-grid areas as currently being considered by the NIB,

and to get involved with hybrid/mini-grid projects being conducted by the REA (Rural

Electrification Agency) that have already received support from multiple countries.

Enterprises can also conduct technology transfers and provide EPC advisement and education

when conducting public sector projects with international support. When a country has poor

capabilities in terms of EPC, the involvement of Japanese engineers becomes all the more critical,

causing costs to increase. When carrying out projects, enterprises that are able to improve local EPC

capabilities will be able to specialize in the E (Engineering) of EPC in Japan and lower their EPC

costs. The goal is to localize Japanese-style EPC and build a low-cost, high-quality EPC structure.

6.2.3 Carrying out projects with investment from Japan

If the actions discussed in the previous subsection are taken into consideration, the Kenyan

market should seem attractive to the Japanese investor. International support and collaboration with

the public sector will drive down off-take risk. Moreover, low-cost, high-quality EPC systems can

mitigate project risk. Japanese private sector investment can therefore bring about substantial

opportunities for public sector business.

This would ultimately improve connections between Japanese enterprises and the Kenyan market

and would expand networks. The lack of a good network in the region, a risk for Japanese investors,

43

would also be remedied. It would also better pave the way for business in the private sector, which

holds the greatest possibilities for business.

6.3. Best practices in Thailand

Let us look at Thailand-based SPCG as a model for how it may be possible to start businesses in

Kenya in the future.

SPCG operates a solar power business in Thailand that provides 250 MW of output. The company

is committed to using Kyocera-brand power generation modules for its solar power systems.

Its 250 MW-plus project makes use of feed-in tariffs and the company has received funding as

an IPP. In recent years, it has installed solar panels on, among other places, the roofs of plants and

commercial facilities as part of efforts to further develop the self-consumption oriented project. The

company has entered into agreements with and received extensive investment from Japanese

companies, among other organizations.

In this way, enterprises that utilize Japanese technologies and that have a good handle on EPC

can join with partners capable of expanding their business to grow the solar power market in Kenya.

Lastly, we would like to share the response we received regarding why SPCG's president

continues to use Kyocera-brand solar power modules:

"If your child was sick, you would no doubt do everything in your power to take him to the most

competent hospital. Solar power projects are my children — I will spend the next 10 or 20 years

raising my children. Using high-quality products to ensure the prosperous future, this is a matter of

course for any parents."

Figure 29 Introduction of SPCG by UNFCCC5

5 http://unfccc.int/secretariat/momentum_for_change/items/8693.php

44

7. Utilizing the JCM in the Future

7.1. The JCM as a motivating factor for business in Kenya

7.1.1 Paris Agreement and Kenya's INDC

The Paris Agreement was adopted at COP21 on December 12, 2015. The key point of the

agreement is that "all developed and developing countries establish targets to reduce greenhouse

gases and work towards their achievement".

Before the Paris Agreement was made, Kenya submitted its new climate action plan, an Intended

Nationally Determine Contribution (INDC), on July 31, 2015. In essence, it seeks to "reduce CO2

emissions to 30% below the BAU level in 2030", and states that "it is necessary to have international

support in the form of things such as finance, investment, technology development and transfer, and

capacity building". If Kenya is going to need projects that achieve specific CO2 emission reductions,

action will need to be taken to gain international support for these endeavors.

7.1.2 Improving MRV capability through the use of the JCM

Through this survey, the "importance of promoting a better understanding of the JCM as

preparation for acquiring international support for reducing CO2 emissions" has been repeatedly

explained based on the background described in the previous subsection. After explaining that there

are limits to existing support and development schemes being put forth to resolve issues hindering

development in Kenya, it was explained that international support could be obtained if the concept

of reducing CO2 emissions were raised as a development subjects.

As a strategy for obtaining international support, we proposed building the capabilities of MRV

(Monitoring, Reporting, and Verification), which seeks to reduce CO2 emissions, by conducting

projects under the JCM scheme. The international community is looking for projects aimed at

reducing CO2 emissions not only in Africa but around the world. By showing its MRV capability

through JCM projects, Kenya can gain an advantage over other countries with respect to obtaining

international support.

Kenya and Japan agreed on the development of JMC. Efforts must be made to better motivate the

host country with respect to making broader use of the JCM. Specific actions must of course be

taken, including conducting feasibility studies and pilot projects, organizing JCM projects, and

expanding JCM projects under the leadership of the private sector. But a strong commitment from

both the public and private sectors in Japan are also needed.

45

Figure 30 Project with/without capability of MRV

7.1.3 Specific projects going forward

Kenya has a strategic plan to develop/expand irrigation scheme. For example, the leading

project “Galana and Kulalu Ranch project” will irrigate 1.21 million acres (540,000ha) of land for

agriculture. And electricity demand of “Galana and Kulalu Ranch project” will be 5MW. If Kenya

could show “Capability of MRV”, it might be possible to introduce various renewable energy to

alternate 5MW Diesel generators with international supports. And the project will become a

sustainable model with Adaptation (irrigation) and Mitigation (renewable energy) to climate change.

Figure 31 Installation of renwable energy to irrigation scheme

“Without” Capability of MRV

Development subjects Electrification

Enhance power supply etc

[1] Government of Kenya

[2] International supports*in terms of “basic human needs”

Budget/Support

There is a limitation of conventional

scheme/budget to cover “Development

subjects”.

Kenya is not LDC and it is difficult to

obtain conventional supports.

Development subjects Electrification

Enhance power supply etc

[1] Government of Kenya

[2] International supports*in terms of “basic human needs”

Budget/Support

[3] International supports for

“GHG reduction (Mitigation) “

“Actions against Global warming

(Adaptation)”

“With” Capability of MRV

Irrigation scheme(Adaptation by Kenya)

Renewable energy(Mitigation by international support)

Micro / Small hydro power

Solar power Biomass power

46

8. Conclusion: Strategic engagement about JCM development

The following box shows the “Strategic engagement about JCM development in Kenya”. This

“Strategic engagement” is based upon the discussion in the previous chapters.

1. Irrigation sector

Sustainable agriculture by liking development subjects with GHG reduction

Installation of “Solar power system by linear controlling” to existing/new rice mills

and irrigation schemes

2. Energy sector

With regard to Solar power “Assurance of performance for 20 years based on long

term experience” should be required.

Reliable control system should be introduced off-grid areas where electricity is

supplied by grid power, diesel generators and renewable energy.

Attractive policy to activate the solar power market in Kenya

3. Implementation of JCM

Kenya could enjoy the reliable/durable Japanese low carbon technology

Promoting JCM in order to contribute to the INDC, or to abate its GHG emission by

30% by 2030 with international supports