Sattva Cadenza Planned V/S Achieved For the month of Feb-2015 Date 23.02.2015 Feb-15 Programme MILESTONES TARGET Feb-15 Qty cum balance Units Week-1 (1st to 07th) Week-2 (8th to 15th) Week-3 (16th to 22nd) Week-4 (23rd to end ) Planned Status Planned Status Planned Status Planned Status 450.0 360.0 90.0 Cum 450.0 80% Completed 1.0 Pour-1 Barbending works 85.8 85.8 0.0 MT 85.8 Completed 428.8 Shuttering 56.0 56.0 0.0 Sqm 56.0 Completed 18.7 Concreting 456.0 456.0 0.0 Cum 456.0 Completed Pour-2 Barbending works 159.3 159.3 0.0 MT 159.3 Completed 796.3 Shuttering 104.0 104.0 0.0 Sqm 104.0 Completed 34.7 Concreting 884.0 876.0 8.0 Cum 884.0 876.0 2.0 Isolated footings (45 Nos), as weekly priority list Footings 22 nos (Tower-1 location Grid M,C/P1,P4) Earth work 30.0 30.0 0.0 CUM 30.0 Completed PCC 7.3 7.3 0.0 CUM 7.3 Completed Barbending works 15.8 15.8 0.0 MT 15.8 Completed 90.5 Shuttering 150.7 150.7 0.0 Sqm 150.7 Completed 53.8 Concreting 86.0 86.0 0.0 Cum 86.0 Completed Footings (Tower-1 non tower location C,CA/P1,P5) Earth work 14.0 12.0 2.0 CUM 14.0 12.0 PCC 3.2 1.0 2.2 CUM 3.2 1.0 Barbending works 7.3 2.0 5.3 MT 7.3 2.0 41.5 Shuttering 67.4 35.0 32.4 Sqm 67.4 35.0 24.1 Concreting 38.4 12.0 26.4 Cum 38.4 12.0 Earth work 22.0 0.0 22.0 CUM 22.0 0.0 PCC 4.6 0.0 4.6 CUM 4.6 0.0 Barbending works 11.9 0.0 11.9 MT 11.9 67.9 Shuttering 95.4 0.0 95.4 Sqm 95.4 34.1 Concreting 50.1 0.0 50.1 Cum 50.1 3.0 Foundation (South balance 10 Mts Length) Earth work 8.0 8.0 0.0 Cum 8.0 8.0 Barbending works 3.0 3.0 0.0 MT 3.0 Completed 17.1 Shuttering 10.0 10.0 0.0 Sqm 10.0 Completed 3.6 Concreting 10.8 10.8 0.0 Cum 10.8 Completed R.wall at Lower basement lvl (90 Rmt Length) 20 Mts Completed 38.5 Mts 38.5 Mts Barbending works 14.0 3.5 10.5 MT 2.8 Completed 5.6 W.U.P 5.6 80.0 Shuttering 683.8 136.8 547.1 Sqm 136.8 Completed 273.5 W.U.P 273.5 244.2 Concreting 102.6 20.5 82.1 Cum 20.5 Completed 41.0 41.0 4.0 Columns 1st Shift concreting 30 nos 15 Nos 7 nos 15 Nos Barbending works 6.0 3.0 3.0 MT 3.0 completed 3.0 34.3 Shuttering 150.0 37.5 112.5 Sqm 75.0 50% completed 75.0 53.6 Concreting 20.0 5.0 15.0 Cum 10.0 50% completed 10.0 5.0 2000.0 50.0 1950.0 Cum 500.0 50.0 1500.0 6.0 Tower-4 Lift pit PCC & Concreting Barbending works 24.5 0.0 24.5 MT 12.3 0.0 12.3 140.0 Shuttering 45.0 0.0 45.0 Sqm 15.0 0.0 30.0 16.1 Concreting 140.0 0.0 140.0 Cum 10.0 130.0 7.0 Excavation for Tower-4 Lift work 225.0 225.0 0.0 Cum 225.0 Completed Labours required for the month of Feb-15 1696.3 482.7 Per Day Man Power Required 65.2 21.1 ACTUAL UP TO DATE LABOURS IN FEB 1349.0 468.0 PLANNED V/S ACHIEVED - FEB 2015 PER DAY Avg Labours 71.0 24.6 MAIN EVENTS Planned-Feb Achieved BALANCE UNITS 1.0 Concrete 1787.9 1466.3 321.6 Cum 82.0% 2.0 Shuttering 1362.2 529.9 832.3 Sqm 38.9% 3.0 Steel 327.5 272.3 55.1 MT 83.2% 4.0 Earth work excavation 749.0 635.0 114.0 cum 84.8% 5.0 Back Filling 2000.0 50.0 1950.0 cum 2.5% Achieved Up to date Barbenders in Nos carpenters in Nos Earth work Excavation & surface dressing at Tower1, 2 & 3 location Tower 2 & 3 Raft Footings 12 Nos (Tower 2,3 Non Tower area Grid P9,P19/PA,PF) Tower 1, 2, 3 Retaining wall South side (90 Mts) side at parrelel to acces road+ B/W Tower 3 & 4 joining area Back filling up to footings at Tower-1 (Aprx 3000 cum) Cum % Achieved V/S Plan Feb 2015

Feb'15 Planned vs Achieved 15 Feb 15

Embed Size (px)

DESCRIPTION

1

Citation preview

MONTHLY TARGETPROJET NAME :- Salarpuria Sattva Cadenza PROJECT CODE:-96060MONTHLY PROGRAME FOR THE MONTH OF FEBRUARY 2015Work DescriptionTotal qty in FEB-15Unit Rate Amount1st Week2nd Week3rd Week4th WeekEarth Work excavationOrdinary Soil150.0200.0200.0100.0650.0Cum377245,050.00Hard Rock50.050.050.050200.0Cum1695339,000.00Earth Filling2,000.02,000.0Cum251502,000.00Plum concerete 15.015.025.055.0Cum4939271,645.00PCC45.020.015.085.0165.0Cum5350882,750.00RCC 50.01,300.0140.0135.01,625.0Cum643910,463,375.00shuttering 400.0400.0400.0400.01,362.2Sqm614836,420.89Reinforcement steel82.082.082.082.0328.0MT128894,227,592.00structural steel0.0MT0.0Block work0.00.0100 MM0.00.0150MM0.00.0200MM75.075.0Sqm128296,150.00Internal Plastering0.0Sqm0.0External plastering0.0Sqm0.0Expansion Joint50.050.0Sqm108054,000.0017,917,982.89

MILESTONES & MAN POWERSattva CadenzaPlanned V/S Achieved For the month of Feb-2015Date23.02.2015 Feb-15 ProgrammeMILESTONES TARGETFeb-15 QtyAchieved Up to datecum balanceUnitsWeek-1 (1st to 07th)Week-2 (8th to 15th)Week-3 (16th to 22nd)Week-4 (23rd to end )Barbenders in Noscarpenters in NosPlannedStatusPlannedStatusPlannedStatusPlannedStatusEarth work Excavation & surface dressing at Tower1, 2 & 3 location450.0360.090.0Cum450.080% Completed

1.0Tower 2 & 3 Raft Pour-1Barbending works85.885.80.0MT85.8Completed428.8Shuttering56.056.00.0Sqm56.0Completed18.7Concreting456.0456.00.0Cum456.0CompletedPour-2Barbending works159.3159.30.0MT159.3Completed796.3Shuttering104.0104.00.0Sqm104.0Completed34.7Concreting884.0876.08.0Cum884.0876.0

2.0Isolated footings (45 Nos), as weekly priority list Footings 22 nos (Tower-1 location Grid M,C/P1,P4)Earth work30.030.00.0CUM30.0CompletedPCC7.37.30.0CUM7.3CompletedBarbending works15.815.80.0MT15.8Completed90.5Shuttering150.7150.70.0Sqm150.7Completed53.8Concreting86.086.00.0Cum86.0Completed Footings (Tower-1 non tower location C,CA/P1,P5)Earth work14.012.02.0CUM14.012.0PCC3.21.02.2CUM3.21.0Barbending works7.32.05.3MT7.32.041.5Shuttering67.435.032.4Sqm67.435.024.1Concreting38.412.026.4Cum38.412.0Footings 12 Nos (Tower 2,3 Non Tower area Grid P9,P19/PA,PF)Earth work22.00.022.0CUM22.00.0PCC4.60.04.6CUM4.60.0Barbending works11.90.011.9MT11.967.9Shuttering95.40.095.4Sqm95.434.1Concreting50.10.050.1Cum50.1

3.0Tower 1, 2, 3Retaining wall South side (90 Mts) sideat parrelel to acces road+ B/W Tower 3 & 4 joining areaFoundation (South balance 10 Mts Length)Earth work8.08.00.0Cum8.08.0Barbending works3.03.00.0MT3.0Completed17.1Shuttering10.010.00.0Sqm10.0Completed3.6Concreting10.810.80.0Cum10.8Completed

R.wall at Lower basement lvl (90 Rmt Length)20 MtsCompleted38.5 Mts38.5 MtsBarbending works14.03.510.5MT2.8Completed5.6W.U.P5.680.0Shuttering683.8136.8547.1Sqm136.8Completed273.5W.U.P273.5244.2Concreting102.620.582.1Cum20.5Completed41.041.0

4.0Columns 1st Shift concreting 30 nos15 Nos7 nos15 NosBarbending works6.03.03.0MT3.0completed3.034.3Shuttering150.037.5112.5Sqm75.050% completed75.053.6Concreting20.05.015.0Cum10.050% completed10.05.0Back filling up to footingsat Tower-1 (Aprx 3000 cum)2000.050.01950.0Cum500.050.01500.06.0Tower-4 Lift pit PCC & ConcretingBarbending works24.50.024.5MT12.30.012.3140.0Shuttering45.00.045.0Sqm15.00.030.016.1Concreting140.00.0140.0Cum10.0130.0

7.0Excavation for Tower-4 Lift work225.0225.00.0Cum225.0Completed Labours required for the month of Feb-151696.3482.7Per Day Man Power Required65.221.1ACTUAL UP TO DATE LABOURS IN FEB1349.0468.0PLANNED V/S ACHIEVED - FEB 2015Cum % Achieved V/S Plan Feb 2015PER DAY Avg Labours71.024.6MAIN EVENTSPlanned-FebAchievedBALANCEUNITS1.0Concrete1787.91466.3321.6Cum82.0%2.0Shuttering1362.2529.9832.3Sqm38.9%3.0Steel327.5272.355.1MT83.2%4.0Earth work excavation749.0635.0114.0cum84.8%5.0Back Filling2000.050.01950.0cum2.5%

Retaining wallSattva CadenzaTantative Retaining Wall Quantity In Feb-15

LocationLength in MtswidthHeightConcrete QtyShuttering QtyTower 1, 2 & 3 Lower basement +Upper BasementRW South97.690.33.5102.5745Cum683.83Sqm

Total Concrete for Foundation102.40.4510.8Cum9Sqm

Total Concrete for Retaining wall113.37Cum692.83Sqm

Total Shuttering Qty 692.83Sqm

Sheet2PROJET NAME :- Salarpuria Sattva Cadenza PROJECT CODE:-96060MONTHLY PROGRAME FOR THE MONTH OF FEBRUARY 2015Work DescriptionQTY on FEB-15Target Quantity (Jan+Feb)Unit Rate Amount12345678910111213141516171819202122232425262728Earth Work excavationOrdinary Soil50.050.050.050.050.050.050.050.050.050.050.050.050.050.0700.01,000.0Cum377377,000.00Hard Rock50.050.050.050200.0500.0Cum1695847,500.00Earth Filling400.0600.0600.06006006003,400.03,500.0Cum251878,500.00Plum concerete 30.015.025.070.0160.0Cum4939790,240.00PCC45.05.05.05.05.010.05.05.080.0165.0230.0Cum53501,230,500.00RCC 12.010.010.010.010.010.015.010.0400.0450.0400.015.015.020.020.025.020.020.020.020.0130.020.020.020.025.01,727.02,000.0Cum643912,878,000.00shuttering 50.0140.0140.0140.0140.0140.0140.050.0140.0140.0140.0140.0140.0140.0140.0140.0140.0140.0140.0140.0140.0140.0140.0140.0140.0140.03,460.03,500.0Sqm6142,149,000.00Reinforcement steel5.014.014.014.014.014.014.05.014.014.014.014.014.014.05.014.014.014.014.014.014.05.014.014.014.014.014.014.0356.0450.0MT128895,800,050.00structural steel0.00.0MT0.0Block work0.00.00.0100 MM0.00.00.0150MM0.00.00.0200MM50.025.075.0150.0Sqm1282192,300.00Internal Plastering0.00.0Sqm0.0External plastering0.00.0Sqm0.0Water Bar50.050.050.050.050.050.050.050.05050500.0500.0Rmt600300,000.00Expansion Joint10.010.010101050.050.0Sqm108054,000.00

25,497,090.00

RW estSattva CadenzaTantative Retaining Wall Quantity In over all Project

LocationLength in MtswidthHeightConcrete QtyShuttering QtyTower 1, 2 & 3 Lower basement +Upper BasementRW South97.690.37.1208.0797Cum1387.198SqmWest27.1050.37.157.73365Cum384.891SqmNorth105.7450.37.1225.23685Cum1501.579SqmEast14.3250.47.140.683Cum203.415Sqm27.360.87.1155.4048Cum388.512SqmTower 4 Upper Basement only

North35.8250.23.827.227Cum272.27SqmEast25.240.83.876.7296Cum191.824SqmEast16.440.23.812.4944Cum124.944SqmNorth36.2250.23.827.531Cum275.31Sqm

Tower 5 TO 82920.21.587.6Cum876Sqm

Total in Rmt711.85275

Total Concrete for Foundation711.852752.40.45768.80097Cum640.667475Sqm

Deduct in Raft-602.40.45-64.8Cum-54SqmTotal Concrete for Retaining wall1622.72Cum

Total Shuttering Qty 6192.61Sqm1576.333333333328.9333333333394.0833333333197.041666666765.6805555556

Iso FootingsIsolated footings Casting at Tower 1,2 & 32nd week target 08.02.15 to 14.02.15FOOTINGS NOLBDQTYPCCF13222.50.77.0012.60.594F1412.31.80.6252.595.1250.25CF612.52.60.74.557.140.378F413.32.30.856.459.520.4375F512.51.90.653.095.720.2835F7221.40.52.806.80.352F652.81.80.717.6432.21.5CF512.62.40.6253.906.250.364F1142.51.80.6511.7022.361.08F913.52.50.9258.0911.10.4995F231220.62.404.80.242F1012.51.40.551.934.290.216F313.12.10.7755.058.060.3795F1222.82.10.758.8214.70.692486.00CUM150.665Sqm7.266CUM3rd week target 15.02.15 to 21.02.15F323.12.10.77510.0916.120.759F413.32.30.856.459.520.4375F512.51.90.653.095.720.2835F7121.40.51.403.40.176F212.12.10.6752.985.670.2645F112.62.60.865.818.9440.392F1422.31.80.6255.1810.250.5F1512.11.60.551.854.070.207F17121.50.5251.583.6750.1871138.42CUM67.369Sqm3.2065CUM4th week target 22.02.15 to 28.02.15F1512.11.60.551.854.070.207CF212.11.70.72.505.320.2185F1872.31.90.6519.8838.221.8375F13322.50.710.5018.90.891F1412.31.80.6252.595.1250.25F1912.62.10.754.107.050.322CF313.22.20.755.288.10.408F1621.71.20.41.634.640.266CF4121.60.551.763.960.1981850.09CUM95.385Sqm4.598CUMNo of footings planned53174.50CUM313.42Sqm15.0705CUMHolded to Ramp20

Sheet1

T1LB720sqm144

8.490.3841355.7612201.849.4Tapas MaityFlooring Labour contractor# 438/118/2, Doddatagur, Electronic city post, Bangalore-100Pan No: BMSPM8708AM: 81235 19560Quotation for Tiling work in Toilets at cadenza site contractor & PMC Office.Details: Labour works of toilet Flooring & dadoing including hacking/chipping, Cutting, Grouting, Acid washing complete at 9 toilets in contractor & PMC office of cadenza site at rate of Over all lumpsum amount Rs.18,000/-

Signature

Tapas Maity53.584576.563842571.42857142868648.457625.7142857143

Sheet3WEEKLY PROGRAMME (FEB-20 TO 28) As Per Internal MeetingSTARTFINISHQUANTITYUNITDESCRIPTIONSTARGET UP TO DATE ACHIEVEDTOTAL PLANNEDREMARKS1TOWER-1AFOOTINGS20-Feb-1523-Feb-1552934NOSBRETAINING WALL (SOUTH)20-Feb-1524-Feb-1540040RMTCCOLUMNS20-Feb-1524-Feb-1512315NOSDBackfilling activity23-Feb-1528-Feb-15

2TOWER-2 & 3ASTARTER FOR COLUMNS & RETAINING WALL20-Feb-1521-Feb-1533740NOSBRETAINING WALL (SOUTH)21-Feb-1526-Feb-1530030RMTFor conventional method board preparation under progressCCOLUMNS23-Feb-1528-Feb-1532032NOSDPEDESTRALS & STARTERS (ALL COMPLETE)20-Feb-1528-Feb-1520020NOSELIFT PIT CORE WALL21-Feb-1522-Feb-15

3OTHER ACTIVITYABACK FILLING AT TOWER-123-Feb-1528-Feb-15200002000CUMBTOWER-4 LIFT PIT EXC/DRESSING21-Feb-1522-Feb-15CTOWER-4 LIFT PIT PCC & REINFORCEMENT24-Feb-1526-Feb-15ACTUAL QTYDTOWER-4 LIFT PIT RCC28-Feb-1528-Feb-15ACTUAL QTY

Sheet4MARCH LOOK AHEAD PROGRAMMEDESCRIPTIONSSTARTFINISHQUANTITYUNITDISTRIBUTIONREMARKSTARGET UP TO PREVIOUS PLANNEDTOTAL PLANNEDWEEK11 TO 7thWEEK 28th to 14thWEEK 315th to 21th22nd to 31CARPENTERFITTER1-Jul-862-May-831TOWER-1AFOOTINGS20-Feb-1523-Feb-1552934NOSBRETAINING WALL (SOUTH)20-Feb-1524-Feb-1540040RMTCCOLUMNS20-Feb-1524-Feb-1512315NOSDBackfilling activity23-Feb-1528-Feb-15

2TOWER-2 & 3ASTARTER FOR COLUMNS & RETAINING WALL20-Feb-1521-Feb-1533740NOSBRETAINING WALL (SOUTH)21-Feb-1526-Feb-1530030RMTFor conventional method board preparation under progressCCOLUMNS23-Feb-1528-Feb-1532032NOSDPEDESTRALS & STARTERS (ALL COMPLETE)20-Feb-1528-Feb-1520020NOSELIFT PIT CORE WALL21-Feb-1522-Feb-15

3OTHER ACTIVITYABACK FILLING AT TOWER-123-Feb-1528-Feb-15200002000CUMBTOWER-4 LIFT PIT EXC/DRESSING21-Feb-1522-Feb-15CTOWER-4 LIFT PIT PCC & REINFORCEMENT24-Feb-1526-Feb-15ACTUAL QTYDTOWER-4 LIFT PIT RCC28-Feb-1528-Feb-15ACTUAL QTY23-Feb-1523-Feb-15EVENTS AT TOWER-4-10464-11620RAFT -28.6684931507-31.8356164384EXCAVATION1-Mar-154-Mar-156006060PCC4-Mar-156-Mar-1542.5042.542.5REINFORCEMENT6-Mar-1510-Mar-15110011010100SHUTTERING9-Mar-1511-Mar-159509595RAFT/PEDESTRAL CONCRETING12-Mar-1513-Mar-156900690690

ISOLATED FOOTINGSEXCAVATION4-Mar-1510-Mar-151001010PCC6-Mar-1511-Mar-152022REINFORCEMENT11-Mar-1514-Mar-155055SHUTTERING14-Mar-1516-Mar-155305353CONCRETING14-Mar-1515-Mar-152902929RETAINING WALL Total length 113 RmtEXCAVATION1-Mar-154-Mar-1545.2045.245.2PCC/PLUM CONCRETING4-Mar-157-Mar-151001010REINFORCEMENT7-Mar-159-Mar-155050.54.5SHUTTERINGCONCRETING FOR FOUNDATION & WALL8-Mar-1518-Mar-1580080

COLUMNSREINFORCEMENT14-Mar-1519-Mar-1525025322SHUTTERING16-Mar-1522-Mar-153950395395CONCRETING17-Mar-1523-Mar-15420422121

BACK FILLING QTY- Tower-46500650200450

EVENTS AT TOWER-1, 2 & 3 TOWER-1, 2 & 3 SLABS AT UPPER BASEMENT LEVELSLAB POUR-1 AT TOWER-2 BUILT AREA ONLYSHUTTERING1-Mar-158-Mar-15950950REINFORCEMENT6-Mar-1511-Mar-151717CONCRETING-Pour-113-Mar-1513-Mar-151451458400SLAB POUR-2 AT TOWER-3 BUILT AREA ONLY31000SHUTTERING6-Mar-1513-Mar-15815707456400REINFORCEMENT11-Mar-1516-Mar-15161645800CONCRETING-Pour-118-Mar-1518-Mar-15125125

SLAB POUR-3 AT TOWER-1 BUILT AREA ONLYSHUTTERING11-Mar-1518-Mar-15940470470REINFORCEMENT16-Mar-1521-Mar-151313CONCRETING-Pour-123-Mar-1523-Mar-15135135

columns at upper basement level at tower 2& 3REINFORCEMENT15-Mar-1518-Mar-153003030SHUTTERING17-Mar-1522-Mar-15560056050060CONCRETING18-Mar-1523-Mar-1510401047034

RETAINING WALL NORTH SIDE 90 MTSPCC1-Mar-154-Mar-154.504.5FOUNDATION CONCRETE2-Mar-157-Mar-1540040WALLS REINFORCEMENT7-Mar-1517-Mar-152500250WALLS SHUTTERING10-Mar-1519-Mar-156200620WALLS CONCRETING10-Mar-1519-Mar-1577077

RETAINING WALL WEST SIDE 30 MTS b/w TOWER 3 & 4PCC15-Mar-1518-Mar-15202FOUNDATION CONCRETE16-Mar-1521-Mar-1515015WALLS REINFORCEMENT21-Mar-1531-Mar-15202WALLS SHUTTERING24-Mar-152-Apr-152000200WALLS CONCRETING24-Mar-152-Apr-1580080

RAMP-3 AT LOWER BASEMENT LEVEL 36 RMTFOOTINGS FOR RAMPEXCAVATION FOR RAMP FOOTINGS1-Mar-154-Mar-1513.2013.2CUMPCC4-Mar-157-Mar-152.202.2CUMRCC FOR FOOTINGS & COLUMNS 5-Mar-1513-Mar-1519.47019.47CUMSHUTTERING4-Mar-1513-Mar-151500150SQMREINFORCEMENT6-Mar-1512-Mar-15404MTCONCRETING FOR RAMP15-Mar-1516-Mar-1528028CUM