64
FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. 03190A, 03190B, 03190C, 03190D, 03190E, 03190F, 03191A, 03191B, 03191D, AND 03191E INTERSTATE 84 AND ROUTE 8 FEDERAL AID PROJECT NOS.: 0842(307), 0842(306), AND 0008(134) STATE PROJECT NOS. 0151-0312, 0151-0313, AND 0151-0326 CITY OF WATERBURY ADDENDUM NO. 6 This Addendum addresses the following questions and answers contained on the CT DOT QUESTIONS AND ANSWERS WEBSITE FOR ADVERTISED CONSTRUCTION PROJECTS”: Question and Answer Nos. 7, 49, 51, 52, 53, 54, 55, 58, 64, 66, 68, 70, 71, 73, 77, 78, 80, 81, 83, 84, 86, 87, 88, 89, 91, 94, 95, 96, 99, 100 SPECIAL PROVISIONS NEW SPECIAL PROVISION The following Special Provision is hereby added to the Contract: ITEM NO. 1206011A REMOVAL OF EXISTING OVERHEAD SIGNING REVISED SPECIAL PROVISIONS The following Special Provisions are hereby deleted in their entirety and replaced with the attached like-named Special Provisions: ITEM NO. 0601039A MODIFY BRIDGE PARAPET ITEM NO. 0601044A - BRIDGE PARAPET CAP ITEM NO. 0601107A HIGH EARLY STRENGTH CONCRETE ITEM NO. 0601999A EXODERMIC DECK ITEM NO. 1131016A SMART WORK ZONE MOBILE VIDEO CAMERA/QUEUE SENSOR TRAILER (SVQS) ITEM NO. 1131017A SMART WORK ZONE MOBILE VIDEO CAMERA/QUEUE SENSOR TRAILER(SVQS) SERVICE ITEM NO. 1131018A SMART WORK ZONE VARIABLE MESSAGE SIGN/QUEUE SENSOR TRAILER (SVMQ) ITEM NO. 1131019A SMART WORK ZONE VARIABLE MESSAGE SIGN/QUEUE SENSOR TRAILER (SVMQ) SERVICE ITEM NO. 1131020A SMART WORK ZONE DEPLOYMENT ITEM NO. 1131021A SMART WORK ZONE OPERATIONS ITEM NO. 1131022A SMART WORK ZONE TRAILER RELOCATION PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326 1 ADDENDUM NO. 6

FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

FEBRUARY 6, 2018

REHABILITATION OF BRIDGE NOS. 03190A, 03190B, 03190C, 03190D, 03190E,

03190F, 03191A, 03191B, 03191D, AND 03191E INTERSTATE 84 AND ROUTE 8

FEDERAL AID PROJECT NOS.: 0842(307), 0842(306), AND 0008(134)

STATE PROJECT NOS. 0151-0312, 0151-0313, AND 0151-0326

CITY OF WATERBURY

ADDENDUM NO. 6

This Addendum addresses the following questions and answers contained on the “CT DOT

QUESTIONS AND ANSWERS WEBSITE FOR ADVERTISED CONSTRUCTION

PROJECTS”:

Question and Answer Nos. 7, 49, 51, 52, 53, 54, 55, 58, 64, 66, 68, 70, 71, 73, 77, 78, 80, 81, 83,

84, 86, 87, 88, 89, 91, 94, 95, 96, 99, 100

SPECIAL PROVISIONS

NEW SPECIAL PROVISION

The following Special Provision is hereby added to the Contract:

ITEM NO. 1206011A – REMOVAL OF EXISTING OVERHEAD SIGNING

REVISED SPECIAL PROVISIONS

The following Special Provisions are hereby deleted in their entirety and replaced with the

attached like-named Special Provisions:

ITEM NO. 0601039A – MODIFY BRIDGE PARAPET

ITEM NO. 0601044A - BRIDGE PARAPET CAP

ITEM NO. 0601107A – HIGH EARLY STRENGTH CONCRETE

ITEM NO. 0601999A – EXODERMIC DECK

ITEM NO. 1131016A – SMART WORK ZONE MOBILE VIDEO

CAMERA/QUEUE SENSOR TRAILER (SVQS)

ITEM NO. 1131017A – SMART WORK ZONE MOBILE VIDEO

CAMERA/QUEUE SENSOR TRAILER(SVQS) SERVICE

ITEM NO. 1131018A – SMART WORK ZONE VARIABLE MESSAGE

SIGN/QUEUE SENSOR TRAILER (SVMQ)

ITEM NO. 1131019A – SMART WORK ZONE VARIABLE MESSAGE

SIGN/QUEUE SENSOR TRAILER (SVMQ) SERVICE

ITEM NO. 1131020A – SMART WORK ZONE DEPLOYMENT

ITEM NO. 1131021A – SMART WORK ZONE OPERATIONS

ITEM NO. 1131022A – SMART WORK ZONE TRAILER RELOCATION

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

1 ADDENDUM NO. 6

Page 2: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

ITEM NO. 1131023A – SMART WORK ZONE QUEUE TRAILER/SENSOR

(SQT)

ITEM NO. 1131024A – SMART WORK ZONE QUEUE TRAILER/SENSOR

(SQT) SERVICE

ITEM NO. 1201802A – 4 CHORD TRUSS BRIDGE SIGN STRUCTURE

ITEM NO. 1220027A – CONSTRUCTION SIGNS

CONTRACT ITEMS

NEW CONTRACT ITEM

ITEM NO. DESCRIPTION UNIT QUANTITY

1002203 TRAFFIC CONTROL FOUNDATION-

PEDESTAL-TYPE I

EA 8 EA

REVISED CONTRACT ITEMS

ITEM NO. DESCRIPTION ORIGINAL

QUANTITY

REVISED

QUANTITY

0214100

0821022A

0822002

1807100

COMPACTED GRANULAR FILL

REMOVE AND RESET PRECAST

CONCRETE BARRIER CURB

RELOCATED TEMPORARY

PRECAST CONCRETE BARRIER

CURB

RELOCATION OF (TYPE A)

IMPACT ATTENUATION SYSTEM

590 CY

1,235 LF

6,100 LF

3 EA

830 CY

400 LF

17,790 LF

101 EA

PLANS

NEW PLAN

The following Plan Sheet is hereby added to the Contract:

02.01.02.A6

REVISED PLANS

The following Plan Sheets are hereby deleted and replaced with the like-numbered Plan Sheets:

02.01.01.A6

07.01.09.A6

PROJECT NO. 151-312 04.09.040.A6

04.09.041.A6

04.09.067.A6

04.09.127-1.A6

04.09.133-1.A6

04.09.141.A6

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326 2 ADDENDUM NO. 6

Page 3: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

PROJECT NO. 151-313

04.10.097-1.A6

04.10.099-1.A6

04.10.102.A6

04.10.109.A6

PROJECT NO. 151-326

03.01.12.A6

03.01.26.A6

03.11.095.A6

04.01.006.A6

04.01.007.A6

04.01.080.A6

04.01.116.A6

04.01.128-1.A6

04.02.06.A6

04.02.42.A6

04.02.47.A6

04.02.58.A6

04.02.76.A6

04.03.24.A6

04.03.26.A6

04.04.23.A6

04.04.25.A6

04.08.22.A6

04.08.23.A6

04.11.04.A6

04.11.17.A6

The Bid Proposal Form has been revised to reflect these changes.

The Detailed Estimate Sheets do not reflect these changes.

There will be no change in the number of calendar days due to this Addendum.

The foregoing is hereby made a part of the contract.

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

3 ADDENDUM NO. 6

Page 4: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/29/18

ITEM #1206011A

ITEM #1206011A – REMOVAL OF EXISTING OVERHEAD SIGNING

12.06.01 – Description:

Add the following sentence:

This work shall also include the storage and reinstallation of Overhead Signs, where applicable,

and the removal of Temporary Overhead Signs. This work will occur on the following Sign

Structures:

#20552 – Route 8 Northbound

#20553 – NB Riverside Street approaching Route 8 NB Exit 30 On Ramp

#20558 – Route 8 Northbound approaching Exit 35

#20559 – Route 8 Northbound approaching Exit 35

#20576 – Route 8 Southbound approaching Exit 31

#20577 – Route 8 Southbound approaching Exit 31

12.06.03 – Construction Methods:

Add the following sentences:

When signs are to be reinstalled, the Contractor shall transport, carefully load/unload the signs

and store in a safe, dry place. The signs shall be reinstalled in accordance with Section 12.07.03.

Temporary Overhead Signs upon removal shall be disposed of as described in paragraphs 1 and 2

of this specification.

12.06.04 – Method of Measurement:

Replace this section with the following:

This work will be at the Contract lump sum price, which shall include all signs (including

Temporary Overhead Signs), sign supports and foundations, if applicable, and delineators

designated for removal in the Contract.

The work to transport, load/unload, store and reinstall the overhead signs is included in this

Contract lump sum price.

12.06.05 – Basis of Payment:

Add the following sentence:

The price shall include the reinstallation of overhead signs including the transport, storage and

loading/unloading, which price shall include all hardware, materials, equipment, labor and work

incidental thereto.

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

4 ADDENDUM NO. 6

Page 5: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #0601039A

ITEM #0601039A – MODIFY BRIDGE PARAPET

Description:

Work under this item shall consist of removing and disposing of existing granite face reinforced

concrete safety walk and placing a reinforced concrete sloped face in its place as shown on the

plans, as directed by the Engineer and in accordance with these specifications.

Materials:

1 - Concrete: The concrete shall be a Contractor designed portland cement concrete, air entrained,

with a maximum size coarse aggregate of 3/8 inch and a minimum 28 day compressive strength, f'c,

of 4,400 psi.

The Contractor shall submit to the Engineer a concrete mix design for approval. The Contractor

shall further provide a certificate stating that the mix submitted shall meet the requirements.

Coarse aggregate shall consist of broken stone, having a maximum size of 3/8 inch, conforming to

the requirements of Article M.03.01.

Fine aggregate, Water, Air-Entraining Admixture and Retarder Admixture shall conform to the

requirements of Article M.03.01.

The air-entraining feature may be obtained by the use of either air-entraining portland cement or an

approved air-entraining admixture. The entrained air content shall not be less than 4 % or more than

6 %.

Portland Cement shall conform to the requirements of M.03.01, except that Type III or Type IIIA

portland cement may be used at no additional cost to the State.

The Contractor may submit, for the approval of the Engineer, a water-reducing admixture for the

purpose of increasing workability and reducing the water requirement for the concrete.

When the Engineer has previously approved the use of a high range water reducer in the concrete

mix, the entrained air content shall be not less than 5 %, nor more than 8 %.

The addition to the mix of calcium chloride or an admixture containing calcium chloride will not be

permitted.

2 - Chemical Anchoring Material: The chemical anchoring material shall conform to Article

M.03.07.

3 - Reinforcement: Reinforcing bars shall meet the requirements of ASTM A615, Grade 60 and be

galvanized after fabrication to the requirements of ASTM A767.

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

5 ADDENDUM NO. 6

Page 6: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #0601039A

Construction Methods:

The safety walk shall be removed by the Contractor at the locations and to the limits as shown in the

contract plans. The granite curbing, removed as part of the safety walk, shall be salvaged by the

Contractor for the State. Refer to the specification “Notice to Contractor - Salvage” for salvage

instructions.

The concrete shall be saw cut to delineate the removal limits. Care shall be taken not to damage the

portion of the parapet that is to remain in place. Removal of the concrete shall be accomplished by

pneumatic hammers approved by the Engineer. The weight of the pneumatic hammers shall not

exceed 30 pounds. Pneumatic tools shall not be placed in direct contact with the reinforcing steel.

Existing reinforcing, designated to remain in place, shall be cleaned of loose rust, concrete, and

other foreign matter, and if required, cut and bent as shown on the plans. All debris shall be

disposed of, from the site, by the Contractor.

The holes for the reinforcement shall be located as shown on the plans and clear the existing

reinforcing. A pachometer shall be used to locate existing reinforcing steel. If existing reinforcing

is encountered during the drilling operation, the holes shall be relocated and the uncompleted holes

shall be filled with the chemical anchoring material and finished smooth to the contour of the

surrounding concrete surface.

Hole drilling methods shall not cause spalling, cracking, or other damage to the existing concrete.

The weight of the drill shall not exceed 20 pounds. The hole diameter for the reinforcement shall be

as recommended by the manufacturer of the chemical anchoring material for its diameter. Those

areas damaged by the Contractor shall be repaired by him in a manner suitable to the Engineer and

at no expense to the State.

Prior to placing the chemical anchoring material in the holes, the holes shall be cleaned of all dirt,

moisture, concrete dust and other foreign materials. Fabrication and placement of reinforcing steel

shall conform to the requirements of Article 6.02.03. The reinforcing steel and the chemical

anchoring material shall be installed in the holes in accordance with the chemical anchoring

material manufacturer's recommendations.

Prior to placing the concrete, the surface on which the concrete will be placed shall be intentionally

roughened to a depth of 1/2 inch. Mixing, placing, curing, and finishing of the concrete shall be in

accordance with Article 6.01.03.

Any newly placed concrete having a hollow sound when sounded with a hammer shall be replaced

by the Contractor at his expense by a method acceptable to the Engineer.

The existing faces of parapet shall be protected during the pouring and finishing of the modified

section to prevent concrete staining. Any staining or discoloration of existing concrete caused by

the Contractor shall be cleaned at the Contractors expense by a method acceptable to the Engineer.

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

6 ADDENDUM NO. 6

Page 7: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #0601039A

The Contractor shall take adequate precautions to prevent any materials from entering on to

adjacent traffic lanes and adjoining property or from falling to the area below the structure.

Should any damage occur to the structure, as a result of the Contractor's operations, the Contractor

shall make repairs at his own expense. The repair work shall be approved in advance and shall be

of a quality acceptable to the Engineer.

Method of Measurement:

This work will be measured for payment by the number of linear feet of Modify Bridge Parapet,

completed and accepted.

Basis of Payment:

This work will be paid for at the contract unit price per linear foot, for "Modify Bridge Parapet",

complete in place, which price shall include all materials, equipment, tools and labor incidental

thereto.

Pay Item Pay Unit

Modify Bridge Parapet l.f.

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

7 ADDENDUM NO. 6

Page 8: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #0601044A

ITEM #0601044A – BRIDGE PARAPET CAP

Description:

Work under this item shall consist of removing and disposing of existing steel metal bridge rail,

reconstructing end portions of existing parapets and placing a reinforced concrete cap on top of the

parapets as shown on the plans, as directed by the Engineer and in accordance with these

specifications.

Materials:

1 - Concrete: The concrete shall be a Contractor designed portland cement concrete, air entrained,

with a maximum size coarse aggregate of 3/8 inch and a minimum 28 day compressive strength, f'c,

of 4,400 psi.

The Contractor shall submit to the Engineer a concrete mix design for approval. The Contractor

shall further provide a certificate stating that the mix submitted shall meet the requirements.

Coarse aggregate shall consist of broken stone, having a maximum size of 3/8 inch, conforming to

the requirements of Article M.03.01.

Fine aggregate, Water, Air-Entraining Admixture and Retarder Admixture shall conform to the

requirements of Article M.03.01.

The air-entraining feature may be obtained by the use of either air-entraining portland cement or an

approved air-entraining admixture. The entrained air content shall not be less than 4 % or more than

6 %.

Portland Cement shall conform to the requirements of M.03.01, except that Type III or Type IIIA

portland cement may be used at no additional cost to the State.

The Contractor may submit, for the approval of the Engineer, a water-reducing admixture for the

purpose of increasing workability and reducing the water requirement for the concrete.

When the Engineer has previously approved the use of a high range water reducer in the concrete

mix, the entrained air content shall be not less than 5 %, nor more than 8 %.

The addition to the mix of calcium chloride or an admixture containing calcium chloride will not be

permitted.

2 - Chemical Anchoring Material: The chemical anchoring material shall conform to Article

M.03.07.

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

8 ADDENDUM NO. 6

Page 9: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #0601044A

3 - Reinforcement: Reinforcing bars shall meet the requirements of ASTM A615, Grade 60 and be

galvanized after fabrication to the requirements of ASTM A767.

Construction Methods:

The metal bridge rail elements and posts shall be removed by the Contractor at the locations and as

shown in the contract plans. The bridge rail components specified in the contract plans shall be

salvaged by the Contractor for the State. Refer to the specification “Notice to Contractor - Salvage”

for salvage instructions.

The end portions of the parapets shall be removed to the limits shown on the plans. The concrete

shall be saw cut to delineate the removal limits. Care shall be taken not to damage the portion of the

parapet that is to remain in place. Removal of the concrete shall be accomplished by pneumatic

hammers approved by the Engineer. The weight of the pneumatic hammers shall not exceed 30

pounds. Pneumatic tools shall not be placed in direct contact with the reinforcing steel. Existing

reinforcing, designated to remain in place, shall be cleaned of loose rust, concrete, and other foreign

matter, and if required, cut and bent as shown on the plans. All debris shall be disposed of, from the

site, by the Contractor.

The holes for the reinforcement shall be located as shown on the plans and clear the existing

reinforcing. A pachometer shall be used to locate existing reinforcing steel. If existing reinforcing

is encountered during the drilling operation, the holes shall be relocated and the uncompleted holes

shall be filled with the chemical anchoring material and finished smooth to the contour of the

surrounding concrete surface.

Hole drilling methods shall not cause spalling, cracking, or other damage to the existing concrete.

The weight of the drill shall not exceed 20 pounds. The hole diameter for the reinforcement shall be

as recommended by the manufacturer of the chemical anchoring material for its diameter. Those

areas damaged by the Contractor shall be repaired by him in a manner suitable to the Engineer and

at no expense to the State.

Prior to placing the chemical anchoring material in the holes, the holes shall be cleaned of all dirt,

moisture, concrete dust and other foreign materials. Fabrication and placement of reinforcing steel

shall conform to the requirements of Article 6.02.03. The reinforcing steel and the chemical

anchoring material shall be installed in the holes in accordance with the chemical anchoring

material manufacturer's recommendations.

Prior to placing the concrete, the surface on which the concrete will be placed shall be intentionally

roughened to a depth of 1/2 inch. Mixing, placing, curing, and finishing of the concrete shall be in

accordance with Article 6.01.03.

Any newly placed concrete having a hollow sound when sounded with a hammer shall be replaced

by the Contractor at his expense by a method acceptable to the Engineer.

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

9 ADDENDUM NO. 6

Page 10: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #0601044A

The existing vertical faces of parapet shall be protected during the pouring and finishing of the

modified section to prevent concrete staining. Any staining or discoloration of existing concrete

caused by the Contractor shall be cleaned at the Contractors expense by a method acceptable to the

Engineer.

The Contractor shall take adequate precautions to prevent any materials from entering on to

adjacent traffic lanes and adjoining property or from falling to the area below the structure.

Should any damage occur to the structure as a result of the Contractor's operations, the Contractor

shall make repairs at his own expense. The repair work shall be approved in advance and shall be

of a quality acceptable to the Engineer.

Method of Measurement:

This work will be measured for payment by the number of linear feet of bridge parapet cap,

completed and accepted.

Basis of Payment:

This work will be paid for at the contract unit price per linear foot, for "Bridge Parapet Cap",

complete in place, which price shall include all materials, equipment, tools and labor incidental

thereto.

Pay Item Pay Unit

Bridge Parapet Cap l.f.

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

10 ADDENDUM NO. 6

Page 11: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #0601107A

ITEM #0601107A – HIGH EARLY STRENGTH CONCRETE

Work under this item shall conform to Section 6.01 Concrete for Structures as supplemented and

amended herein to provide for High Early Strength Concrete.

6.01.01-Description: Add the following:

Work under this item shall include placing the HES concrete, constructing form work, field

testing of the material and developing maturity indexes for the concrete mix.

High Early Strength (HES) Concrete shall include concrete used for Exodermic deck panel cast

in field elements, closure pours and parapet construction and other incidental construction as

required.

The HES requirements shall be used for the Items “Localized Replacement of Concrete Deck for

Steel Strengthening” and “Reconstruct Concrete Deck End – Type B”.

6.01.02-Materials: Add the following:

The high early strength concrete shall conform to the requirements of M.03.01 and the following

criteria:

a) The Contractor shall design and submit to the Engineer for approval a high early strength

concrete mix a minimum of 90 days prior to placing any HES concrete. This mix shall be

air-entrained and shall be composed of Portland cement, fine and coarse aggregates,

approved admixtures and additives, water and fiber reinforcing.

Cement: Portland Type III

Cement content: Minimum 658 lb./c.y.

Water Cement Ratio: Maximum 0.4

Course Aggregate: Maximum size is 3/8”

Air Entrainment: 6.0 +/- 1.5%

Slump: Maximum 7 inches (use HRWR)

Concrete temperature: between 65°F and 90°F delivered to work site

Compressive Strength 4,000 psi @ 8 hrs

5,500 psi @ 28 days

Fiber Reinforcing: Minimum 3 lb./c.y.

b) Portland cement to conform to AASHTO M85.

c) Water-cementitious material ratio is by weight, including water in the admixture solution

and based on saturated surface dry condition of aggregates.

d) Admixtures and air entraining agents are to be compatible with the cement.

e) Only use accelerating admixtures which do not contain chlorides.

f) For fiber reinforcing use monofilament or collated fibrillated synthetic fiber in

accordance with ASTM C 1116, 4.1.3 Type II or Type III and note 2. The fiber shall

meet ICC ES AC32, Section 3.1.1 and 3.1.2 requirements. Provide a test report

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

11 ADDENDUM NO. 6

Page 12: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #0601107A

complying with ICC Evaluation services (ICC-ES) AC32 Acceptance Criteria for

Concrete with synthetic fibers from an Independent Certified Laboratory. Provide a

method of adding the fibers to the mix such that the fibers are dispersed during mixing

and no clumps of fibers are present at the end of a mix cycle.

g) A shrinkage reducing admixture shall be added to the concrete mix according to the

manufacturer’s recommendation such that there will be no cracks at 14 days in the

sample tested in AASHTO T334. The shrinkage reducing admixture shall be tested by an

approved testing lab and meet the requirements of ASTM C494-10 Type S, except that in

Table 1 length change shall be measured as: Length Change (percent of control) shall be

a minimum of 35% less than that of the control. Table 1 Length Change (increase over

control) shall not apply. Shrinkage reducing admixtures shall not contain expansive

metallic materials.

A confined shrinkage test as outlined in the AASHTO T334 - Practice for Estimating

the Crack Tendency of Concrete shall be performed by an AASHTO accredited

laboratory. The results of these tests (documenting zero cracks at 14 days) shall be

submitted to the Engineer.

The shrinkage compensating additive shall also allow no separation of the closure pour

concrete area from the parent concrete. This shrinkage-compensating additive shall be

utilized to produce expansion in the high early strength concrete of no more than 3%.

h) The use of lightweight aggregate is not allowed.

Mix Design Requirements:

a) Concrete shall be controlled, mixed, and handled as specified in the pertinent portions of

Section 6.01 Concrete for Structures, Supplemental Specifications and as indicated below:

b) The Contractor shall design and submit for approval the proportions and test results for a

concrete mix which shall attain the minimum final design compressive strength and the

early compressive strength as defined by this specification and consistent with the approved

Quality Control Plan.

c) The concrete mix design shall have a rapid chloride ion permeability of 2000 Coulombs at

not more than 28 days using AASHTO T 277 and the air entrainment as defined under the

material section. Contractor may opt to take multiple tests prior to 28 days which will be

considered accepted once the target value of 2,000 coulombs is reached. Testing shall be in

accordance with AASHTO T 119 and T 152. Multiple samples should be tested using the

intended curing methods in order to establish the required cure times for the mix.

d) Should a change in sources of material be made, a new mix design shall be established and

approved prior to incorporating the new material. When unsatisfactory results or other

conditions make it necessary, the Department will require a new mix design.

e) All tests necessary to demonstrate the adequacy of the concrete mix shall be performed by

the Contractor, witnessed by CTDOT, including, but not limited to: slump, air content,

temperature, initial set and final set (AASHTO T197). Compressive strength tests shall be

determined by the maturity method and field cured cylinders (6” X 12” cylinders) as

described in this specification. Additionally, a confined shrinkage test as outlined in the

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

12 ADDENDUM NO. 6

Page 13: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #0601107A

AASHTO T334 - Practice for Estimating the Crack Tendency of Concrete shall be

performed by an AASHTO accredited laboratory. The results of these tests (documenting

zero cracks at 14 days) shall be submitted to the Engineer.

Demonstration Pour / Test Batch: a) A minimum of 30 days prior to field placement of any HES concrete and after the mix

design has been approved perform a demonstration pour / test batch of the HES concrete.

b) The Department shall be notified at least 14 days prior to the demonstration pour / test

batching and shall be present to witness the testing.

c) The demonstration shall consist of a minimum HES concrete batch of 3 c.y. The HES

concrete demonstration pour may be performed in conjunction with other project related

demonstrations. If performed in conjunction with the other demonstration pours, the entire

use of the material from the 3 c.y. batch is not required.

d) The Contractor will be required to demonstrate proper mix design, batching, placement,

finishing and curing of the high early strength concrete. The trial placement shall simulate

the actual job conditions in all respects including plant conditions, transit equipment, travel

conditions, admixtures, forming, the use of bonding compounds, restraint of adjacent

concrete, placement equipment, and personnel.

e) Use the maturity method in conjunction with cylinder breaks to verify the required strength

in the desired time period.

f) If the demonstration pour is in conjunction with other demonstration pour, the demonstration

pour will not be taken a part or have destructive testing performed for 14 days otherwise a

separate pour from the same batch will be made to check for shrinkage cracking at 14 days.

g) The demonstration pour will be checked for cracking and separation at 14 days.

The trial placement concrete shall not exhibit cracking or separation from the test panel

in excess of 0.016 inches wide

There shall be no more than one transverse crack in excess of 0.010 inches wide in the

pour area or spaced no more than 10 feet apart, whichever is less.

If the trial placement fails these criteria, the Contractor will be required to submit a

corrective action plan on how repairs of these crack sizes will be performed. The

Department may require the Contractor to conduct more trial batches and trial

placements. The costs of trial batches, trial placements and the removal of trial

placement concrete from the job site is incidental to the work and will not be measured

for payment. The requirement for multiple test placements shall not be cause for a time

extension.

The final accepted trial placement testing shall be used to establish the final acceptance

testing protocol for the field placements.

6.01.03-Construction Methods: Construction methods shall conform to the following

requirements:

1. Preparation:

a) Provide a quality control plan and submit it for review. Detail appropriate action points for

all phases of construction, including concrete mixing, curing, sealing, sampling and testing

before opening to traffic.

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

13 ADDENDUM NO. 6

Page 14: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #0601107A

b) Before placing concrete, ensure adequate equipment and trained personnel are available and

sufficient hauling units scheduled to maintain continuity in placement.

c) Before any HES concrete is placed the Contractor will provide the Engineer clear access

to all areas in which concrete is to be in contact with the new HES concrete. During this

time, the Engineer will perform an inspection of the areas to receive concrete. The

engineer will verify that all debris has been removed, the forms are adequately sealed and

the concrete surfaces are wet without ponding.

2. Surface Preparation:

a) Concrete surfaces against which the new HES concrete will be placed shall be saturated by

water. All free water shall be removed from the surface.

b) Forms shall conform to the pertinent requirements of Subarticle 6.01.03-1.

3. Maturity Sensors:

a) Prior to placing HES concrete the Contractor shall install the maturity sensors. Maturity

sensors shall not be in contact with reinforcing steel or formwork. Sensors may be attached

to insulated wire that is tied between the reinforcing bars. Maturity sensors are to be placed

2 to 4 inches from the bottom surface or form with a minimum 2 inch cover above. The

sensors installed shall be of the same type used to establish the maturity index.

b) Location and number of maturity sensors installed shall be in accordance with the following:

For deck closure pours place a minimum of 2 sensors per longitudinal closure pour

and 2 sensors per transvers closure pour. Sensors placed at the intersection of longitudinal

and transvers closure pours may be counted as a sensor for both pours. Place on additional

sensor in each exterior longitudinal closure pour.

For new parapets on Bridge No. 03190B that are constructed with the exodermic

deck replacement spans and the new wingwall parapets, provide a minimum of 3 sensors

at the top and 3 sensors at the bottom equally spaced. Maximum spacing of the sensors

shall be 30 feet.

For new parapets constructed as part of Item #0503988A – Reconstruct Concrete

Deck End – Type B, provide a minimum of 1 sensor at the top and 1 sensor at the bottom.

c) The Engineer may reduce or increase the number of sensors required after the second

weekend closure based on the consistency level of the data collected from the first two

weekend closures.

4. Mixing, Placing, and Finishing:

a) Mixing and placing concrete shall be done in accordance with the applicable portions of

Article 6.01.03. Mixing and placing shall not be executed unless the ambient temperature is

above 40 °F and rising. The concrete mix shall be properly placed to insure complete

contact around all reinforcing steel and against existing concrete at edges and compacted to

a level slightly above the surrounding deck surface. Vibrators of the appropriate size shall

be used for all consolidation of the concrete, regardless of the size of the area, with no hand

tamping or rodding allowed. Concrete may be moved horizontally with the aid of hand

tools, but not with the use of vibrators (excess vibration shall be avoided).

b) Vibrating plates or vibrating screed shall be used on the surface of all patches for strike off

and consolidation. After the concrete has been spread evenly and compacted to a level

slightly above the adjacent concrete surface, the vibrating plate or screed shall be drawn

over the surface at a uniform speed without stopping to finish the surface smooth and even

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

14 ADDENDUM NO. 6

Page 15: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #0601107A

with adjacent concrete. The surface shall be float finished. Finishing operations shall be

completed before initial set takes place.

5. Curing:

a) The concrete curing methods shall be developed by the Contractor as part of the Quality

Control Management Plans (QMP). The curing methods used in the production

placements shall be the same as the curing methods used for the demonstration pour.

6. Testing:

a) All personnel performing tests shall be qualified NETTCP Concrete Technicians and

certified ACI Concrete Laboratory and Concrete Strength Technicians. Anytime the

Contractor moves the testing equipment all equipment shall be recalibrated. This

requirement is intended to minimize the movement of test cylinders.

b) The Contractor shall provide a portable compressive testing machine on site for the purpose

of testing all compressive strength cylinders. All testing shall be in accordance with the

requirements of ASTM C39. Any compressive testing machines used for this test must be

calibrated in accordance with the provisions of Section 5, ASTM C39.

c) Maturity testing shall be used to monitor the strength of the in-place concrete during the

weekend closure. Once maturity testing indicates the required compressive strength has

been achieved to open the structure to traffic, standard concrete cylinder break tests shall

be used to confirm the maturity data. Concrete cylinder testing is to be used to determine

the 28-day compressive strength. The Contractor shall form, cure and test all concrete test

cylinders under supervision of a representative of the Department. The dimensions, type

of cylinder mold, number of cylinders, and method of curing shall be as directed by the

Engineer.

d) The Contractor is required to perform initial set and final set tests (AASHTO T197) in

addition to slump, air content and temperature on concrete from each concrete truck used

in the placing of this High Early Strength Concrete.

e) Field cured cylinders will be made from the first and last concrete trucks.

f) The contractor shall prepare a sufficient number of test cylinders so that if the initial

breaks do not produce the required strength testing can be completed again at a later

period. A minimum of three cylinder breaks providing uniform coverage of the pour area

are to produce acceptable test results.

g) The Engineer shall be allowed to witness the testing and comment on all the tests

performed by the Contractor. The Contractor shall not open the roadway to traffic until

the final strength has been met and when the Engineer has directed that the roadway can

be opened to traffic.

h) Acceptance tests will be performed by the Department on standard cured cylinders at 7

days and 28 days. Cylinder breaks at 7 days and 28 days must be at least 10% above the

approved trial batch results. The Contractor will be notified of any verification tests that

do not meet these requirements and will be required to develop a contingency corrective

action plan incase final strength is not achieved. Concrete will be accepted based on

meeting the 28-day strength requirement.

7. High Early Strength Concrete Crack Inspection:

a) The Contractor shall inspect the finished high early strength concrete surface for cracks.

Inspection of the deck for cracking shall be completed prior to the preparation of the deck

for placement of the membrane waterproofing system.

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

15 ADDENDUM NO. 6

Page 16: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #0601107A

b) The Contractor shall document the location and frequency of cracks on the closure pours

(number of cracks per square foot). Cracks greater than 0.016 inches in width shall be

repaired as required by the membrane waterproofing manufacturer.

Maturity testing: 1. SCOPE

1.1.1 This test method provides a procedure for estimating concrete strength by means of

the maturity method. The maturity method is based on strength gain as a function of

temperature and time.

1.1.2 Maturity test shall be in accordance with ASTM C1074.

1.1.3 The maturity method consists of three steps:

developing strength-maturity relationship

estimating in-place strength

verifying strength-maturity relationship.

1.2.1 This test procedure employs the Nurse-Saul temperature-time factor (TTF) maturity

index, with a datum temperature of -10°C (14°F).

1.2.2 The strength maturity relationship shall be developed and submitted to the Engineer

a minimum of 45 days prior to any HES concrete placement

1.2.3 The values given in parentheses (if provided) are not standard and may not be exact

mathematical conversions. Use each system of units separately. Combining values

from the two systems may result in nonconformance with the standard.

2 APPARATUS

2.2 Commercial maturity-recording devices that automatically compute and display the

maturity in terms of a temperature-time factor are acceptable. Acceptable devices include

thermocouples connected to digital data-loggers, or embedded devices that record and

store the data. All devices must be able to transfer the collected data to a computer for

permanent storage.

2.3 The maturity-recording device shall be able to record the temperature accurately to within

+/- 1°C (2°F).

2.4 The maximum recording intervals shall be every ½ hour for the first 48 hours, and every

hour thereafter.

2.5 If the maturity meter has input capability for datum temperature, be sure to select the

proper value of the datum temperature prior to each use.

2.6 Use the same brand and type of maturity meters in the field as those used to develop and

verify the strength-maturity relationship. Prior to selecting sensors for the maturity testing

the Contractor shall verify that an adequate supply of is available for use on the project.

When using different sensors during a different period of construction a develop new

maturity index curve.

3 PROCEDURE

3.1 Calibration—Verify calibration prior to use on a project and, as a minimum, on an annual

basis by placing a randomly sampled maturity meter in a controlled-temperature water

bath and recording whether the indicated result agrees with the known temperature of the

water bath. The maturity meter temperature recording device must be accurate to within ±

1°C (± 2°F). Verify accuracy at a minimum of three different temperatures, e.g., 5°C,

25°C, and 45°C (41°F, 77°F, and 113°F).

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

16 ADDENDUM NO. 6

Page 17: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #0601107A

3.2 Developing Strength-Maturity Relationship:

3.2.1 For every concrete design being evaluated by the maturity method, prepare a

minimum of 55 cylinders in accordance with AASHTO T23. The minimum size of

each batch should be approximately 3 yd.3(3 m

3) using the same mixture proportions

and constituents of the concrete as those of the job concrete being evaluated.

Note: Cast additional specimens to avoid having to repeat the procedure.

3.2.2 Test each batch of fresh concrete for concrete placement temperature, slump, and air

content in accordance with AASHTO T23.

3.2.3 Embed maturity meters in at least four specimens. Place the meter 50–100 mm (2–4

in.) from any surface. Begin data collection as soon as the meter contacts the fresh

concrete. Data collection must be uninterrupted.

3.2.4 Moist-cure the specimens in a water bath or in a moist room in accordance with

AASHTO T23 and conditions similar to the actual field conditions.

3.2.5 Perform compression tests on sets of cylinders at 2 hour increments from the 2hrs to

24 hours and then at 3, 5, 7, 14, and 28 days in accordance with AASHTO T22. Test

a set at each age and compute the average strength. Evaluate additional test

specimens and test ages at the discretion of the Engineer. A set of cylinders is three

cylinders at the same age.

Note: If a specimen is defective (e.g., not cylindrical, not square, damaged due to

handling), discard the specimen. If an individual cylinder strength is greater than

or less than 10 percent outside the average of a set, consider the specimen

defective and discard. When two of the three specimens are defective, evaluate a

new batch, unless additional acceptable specimens are available.

Note: Test the specimens with the meters last and only if the maximum

dimension of the embedded meter is less than one-third the diameter of cylinder

mold or width of the beam mold.

3.2.6 At each test age, record the individual and average values of maturity and strength

for each batch on a permanent data sheet.

3.2.7 Plot the average strengths as a function of the average maturity values with data

points shown. Using a computer spreadsheet program such as Microsoft Excel,

calculate a logarithmic best-fit curve through the data. Record the equation of the

curve and the R2 value. The resulting curve is the strength-maturity relationship to

be used for estimating the strength of the concrete mixture placed in the field.

Note: When developing the strength-maturity relationship, the spreadsheet

software allows the Engineer to develop the corresponding maturity equation

that defines the strength-maturity relationship and an R2 value to fit the strength-

maturity relationship. The R2 value indicates the reliability of the strength-

maturity relationship. Expected results should produce an R2 value of at least

0.90. When the reliability is less than 0.90, the Engineer should carefully

examine the data for “outliers,” faulty beam breaks, or faulty maturity readings.

The Engineer should use judgment to determine if certain points should be

discarded, or retested, or whether the entire strength-maturity relationship should

be regenerated.

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

17 ADDENDUM NO. 6

Page 18: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #0601107A

3.2.8 The plot of the strength-maturity relationship for each concrete mixture, with data

points, must be circulated and signed by the Contractor or his representative and

reviewed by the Department Materials Testing Lab.

3.3 Estimating In-Place Strength:

3.3.1 A Department inspector must be present at the concrete plant when placing concrete

to be evaluated by the maturity method. While batching of concrete for the project is

taking place the inspector must be at the plant daily and must verify batching

operations using a checklist. As a minimum, the checklist should verify the correct

mix design is being used, the correct aggregate is being used, and the concrete batch

tickets reflect the mix correctly.

Note: Any approved alteration in mix proportions or source or type of any

material in excess of those tolerable by batching variability requires the

development of a new strength-maturity relationship prior to its use. This

includes a change in type, source, or proportion of cement, fly ash, coarse

aggregate, fine aggregate, or admixtures. A change in water-to-cementitious

material ratio greater than 0.05 requires the development of a new strength-

maturity relationship.

3.3.2 As soon as practical after concrete placement, connect and activate the maturity

meter(s).

Note: Do not disable meters until the required maturity values are achieved. Data

collection must be uninterrupted.

3.3.3 Record maturity data on a permanent data sheet and or electronically. If data is

electronically recorded, maintain a backup copy of the data and a field log of the

data collected. The permanent data sheet must show the Required Strength and the

Required TTF for the specified Operation.

3.3.4 When the maturity is at a value that is equal to or greater than the required strength

for that concrete mixture as determined by the strength-maturity relationship, record

the maturity value, and when appropriate, verify the specimen strength in

accordance with Section 3.4.

3.3.5 Clip the wires at the concrete surface.

3.4 Verifying Field Strength-Maturity Relationship:

3.4.1 Make a minimum of one set (three cylinders) in accordance with AASHTO T23 at

the frequency specified in this specification.

3.4.2 Test fresh concrete for concrete placement temperature, slump, and air content in

accordance with AASHTO T23.

3.4.3 Embed one meter in a minimum of three specimens. Place meter(s) 50–100 mm (2–

4 in.) from any surface. Begin data collection as soon as the meter contacts the fresh

concrete. Data collection must be uninterrupted.

3.4.4 Cure the field specimens under the actual field condition of the in-place concrete.

3.4.5 Perform compression strength tests when the specimen achieves the TTF (within

10%) corresponding to the design strength, or when the required TTF of the in-place

concrete is achieved in the field. Test the three specimens in accordance with

AASHTO T22 and computer the average strength of the specimens.

Note: If a specimen is obviously defective (e.g., out of round, not square,

damaged due to handling), discard the specimen. If an individual cylinder

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

18 ADDENDUM NO. 6

Page 19: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #0601107A

strength is greater than 10 percent outside the average of three specimens,

consider the specimen defective and discard. When two of the three specimens

are defective, evaluate a new batch, unless additional acceptable specimens are

available.

Note: Test the specimen(s) with the meter last and only if the maximum

dimension of the embedded meter is less than one-third the diameter of cylinder

mold or width of the beam mold.

3.4.6 Compare the average strength determined from the specimen breaks to the strength

predicted by the strength-maturity relationship. The average strength of the

specimens must be equal or greater than the compressive strength specified for the

structure to be opened to traffic. When three consecutive verification test results fall

between 5% and 10% above or below the predicted strength based on the S-M

Relationship, the condition does not warrant a redo of the S-M Relationship; the

condition, however, requires a mathematical adjustment to the S-M Relationship.

Adjust the curve using the adjustment feature of the Excel spreadsheet program.

When a single verification test exceeds the 10%, a new S-M Relationship curve

must be developed according to specification requirements.

6.01.04-Method of Measurement: Replace the entire Article with the following:

This work will be measured for payment by the actual volume in cubic yards of placed concrete,

complete and accepted. No deduction will be made for the volume of reinforcing steel.

6.01.05-Basis of Payment: Replace the entire Article with the following:

This work will be paid for at the Contract unit price per cubic yard for “High Early Strength

Concrete” complete in place, which price shall include, surface preparation, furnishing and

installing forming material, all equipment, tools, labor, maturity sensors, data collecting equipment,

maturity testing, maturity index development, material testing, demonstration pours and work

incidental thereto.

Pay Item Pay Unit

High Early Strength Concrete c.y.

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

19 ADDENDUM NO. 6

Page 20: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #0601999A

ITEM #0601999A – EXODERMIC DECK

Description: This work shall consist of the furnishing, delivery, and installation of the precast Exodermic

®

deck panels, any miscellaneous metal forms (or other related forming materials), reinforcing

steel, and precast concrete as shown in the contract drawings and in accordance with the

manufacturer’s recommendations. All concrete required for this item shall be precast except for

the closure joints which shall be cast in the field.

General Scope of Work:

Survey existing structure

Develop shop drawings

Fabricate Exodermic deck panels

Remove existing deck and shear connectors (as needed)

Install Exodermic deck panels

Install shear connectors (Separate Pay Item)

Place closure pour concrete (Separate Pay Item)

Construct new parapets (Separate Pay Item)

Place waterproofing membrane and wearing surface overlay (Separate Pay Item)

Materials: The materials for this work shall meet the quality requirements of the relevant portions of the

Standard Specifications unless the same are altered by any specific requirements under any

Special Provision or by notes shown on the contract drawings.

Within 10 days after the contract is awarded, the contractor shall notify the Engineer of the

name, address, telephone number, and contact person of the Exodermic™ deck grid fabricator

and precaster of all deck panels to be manufactured, supplied, and installed. A single fabricator

is to be used for fabrication of all deck panels to be manufactured.

The Exodermic® grid deck system must be purchased from an AISC certified fabricator and

participating BGFMA member, such as the following:

Bailey Bridges, Inc. (256) 845-7575

LB Foster (412) 928-3548

Further information may be obtained from:

BGFMA

Attn: Philip Gase

300 East Cherry Street

North Baltimore, OH 45872

Tel: (419) 257-5495

[email protected]

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

20 ADDENDUM NO. 6

Page 21: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #0601999A

The main bearing bars of the steel grid deck shall be fabricated from WT structural shapes

conforming to AASHTO M270 Grade 50S T2 steel. Distribution bars and miscellaneous plates,

rod and bar steel shall conform to AASHTO M270 Grade 50 T2.

The 20-gage steel sheet metal form pans installed in the grid prior to galvanizing for panel

fabrication shall conform to ASTM A1008 SS Grade 80. Galvanized steel sheet metal forms

installed following grid panel galvanizing shall conform to the latest specification for ASTM

A653 SS Grade 80 with a coating G165 furnished in the gauge specified on the contract

drawings. This is steel sheet metal intended to be used for closure pours and beam pockets.

Welding shall be in conformance with established grid industry practice, including the permitted

use of Gas Metal Arc Welding (MIG). Weld qualification and weld procedures are to be in

accordance with AWS D1.5 or per the relevant portions of the owner’s Standard Specifications

and shall be approved prior to deck panel fabrication.

All fabricated steel is to be galvanized. Galvanized coatings shall conform to ASTM

A123/A123M. Any defects in galvanizing shall be repaired as specified in ASTM A780. Repair

materials containing aluminum shall not be used to restore defective areas.

Reinforcing bars shall meet the requirements of ASTM A615, Grade 60 and be galvanized after

fabrication to the requirements of ASTM A767, Class 1, including supplemental requirements.

Concrete shall be in conformance with Section 6.01 and Section M.03 of Form 817 for Class “F”

concrete and as modified by the following. The maximum coarse aggregate shall not exceed

3/8” in size. Include fiber reinforcing in the mix design at a minimum of 3 lbs/c.y. Maximum

slump which may include a HRWR shall not be greater than 6 inches. Submit a mix design for

approval to the Engineer prior to any casting of the concrete for the Exodermic deck panels.

Upon acceptance of the mix design a panel mock up and test pour will be completed.

Lightweight concrete is not permitted.

Fiber reinforcing: use monofilament or collated fibrillated synthetic fiber in accordance with

ASTM C 1116, 4.1.3 Type III and note 2. The fiber shall meet ICC ES AC32, Section 3.1.1 and

3.1.2 requirements. Provide a test report complying with ICC Evaluation services (ICC-ES)

AC32 Acceptance Criteria for Concrete with synthetic fibers from an Independent Certified

Laboratory. Provide a method of adding the fibers to the mix such that the fibers are dispersed

during mixing and no clumps of fibers are present at the end of a mix cycle.

Unless specified otherwise, leveling bolts, nuts, and washers shall conform to the specifications

of ASTM A307, ASTM A563 and ASTM F844 respectively. Leveling bolts need not be

galvanized if minimum top cover over the bolts of 2.5 inches is provided.

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

21 ADDENDUM NO. 6

Page 22: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #0601999A

Construction Methods:

The panel layout shown on the Contract plans is suggested. The Contractor in coordination with

the fabricator shall develop the final horizontal and vertical layout of the panels and detail it on

the shop drawings. The Contractor is to survey the existing structure to determine controlling

geometry. The survey will be compared against the proposed geometry and the shop drawings

developed. At a minimum, the survey shall document the deck joints, existing vertical profile,

existing vertical clearances and location of the existing steel framing. Any discrepancies in the

survey with the existing plans or contract plans shall be brought to the attention of the Engineer

prior to the submission of the shop drawings. Final layout of the panels shall be controlled by

the following:

Top of new concrete at expansion joints shall match the top of existing concrete for the adjacent

span at the joint.

The final vertical profile shall be within 1 inch of the existing profile. However, the minimum

vertical clearance from the top of the roadway to any element above shall not be decreased below

16’-6”. If the vertical profile used on the shop drawing deviates from the proposed vertical

profile the revised profile is to be shown on the shop drawings.

The proposed cross slopes are to be maintained as shown on the contract drawings.

Mock-up Panel

a) Prior to full scale panel fabrication, a test module shall be constructed to demonstrate that

the final product can be constructed as required. The minimum module size shall be 8 feet

by 8 feet. The module will contain the steel grid with portions of precast concrete

containing reinforcing, a beam pocket and a transvers panel joint with reinforcing lap slice.

After the prefabricated portion of the module is constructed, a demonstration of the beam

pocket and transverse joint closure pour will be performed. The following items will be

demonstrated with the test module:

In field fit up of prefabricated panels in the field.

In field leveling and adjustability of prefabricated panel.

Form up of transverse panel joints.

How the reinforcing lap splices will be made in the field at the transverse joints.

Forming and sealing of the beam pockets.

Installation of shear studs in the beam pockets.

Placement of the closure pour concrete to meet the required compressive strength in the

allotted time.

b) After the test module has been constructed and the closure pour concrete reaches the

required compressive strength, the Engineer will direct the test module to be taken apart and

inspected. The Contractor shall submit a deconstruction procedure of the test module to the

Engineer for approval. The deconstructed test module will be reviewed for proper cover of

concrete, bonding of concrete to member and reinforcing and bonding of the closure pour

concrete to the precast concrete. The performance of the test module is to be documented

with field notes and photographs and submitted to the Engineer. Following the

demonstration, a meeting is to be held to evaluate and discuss any issues or lessons learned

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

22 ADDENDUM NO. 6

Page 23: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #0601999A

from the test module. At a minimum, the meeting will be attended by the Engineer,

Contractor and Fabricator. The Engineer will attend the placement of the closure pour

concrete for the test module and be given a minimum of two weeks’ notice prior to it

occurring.

Steel Grid Deck

a) The steel grid deck shall be fabricated to the dimensions and properties as shown on the

plans, shop drawings, and in accordance with the relevant portions of the Standard

Specifications. The use of tertiary or supplemental bars to develop composite action

between the concrete deck and steel grid shall not be allowed. Weld sizes shall be in

conformance with established grid industry practice unless otherwise indicated on the

contract plans. It shall be the contractor’s responsibility to field verify all dimensions to

make necessary changes prior to fabrication. Due consideration shall be given to the

placement of leveling devices to provide adequate clearance for their field adjustment from

above using a socket wrench and for adequate clearance for field placement of headed shear

studs. After the attachment of edge bars, leveling devices, vertical form pans, and other

components as described in the plans and specifications, the grid deck shall be galvanized.

b) After galvanizing the fabricated steel grid shall be inspected for warping and distortion from

the galvanization process. Any geometry differences from the shop drawings outside of the

dimensional tolerance shall be corrected if possible. Panels that cannot be corrected shall be

replaced at no additional cost to the Department. All procedures to make geometry

corrections shall be submitted to the Engineer for approval prior to starting correction

procedures. Procedure for corrections need to consider if the galvanized coating will be

damaged and how to address damage to the coating. Replacement of the panel will be at the

discretion of the Engineer.

c) The dimensional tolerances for each steel grid panel shall be in accordance with the most

recent version of BGFMA TS-01, “Fabrication Tolerances for Grid Decks”, published by

the Bridge Grid Flooring Manufacturers Association. Note the calculated tolerances are in

inches for items d, e, and f with the length or width entered as feet.

d) Sheet metal forms shall be installed in such a manner as to minimize leakage of closure pour

concrete.

e) Lifting locations and lifting procedures shall be included on the shop drawing submission.

Care shall be taken to avoid twisting of the panels or bending of the panels in the weak

(perpendicular to main bar) direction. Use of multiple pick points is recommended. Steel

grid panels must be properly blocked with wood (with due regard to built-in panel camber)

during transportation and storage to avoid distortion or other damage. Lifting devices should

be designed to support loading caused by the fully assembled panel (including steel grid,

reinforcing and concrete) with a minimum safety factor of 1.5.

Precast Concrete

a) An approved concrete mix design shall be used for casting the panels. Rebar layout shall

consider the location of the leveling bolts providing sufficient clearance for adjustment in

the field using a socket wrench. Main (top) rebar, which runs in the same direction as the

main bearing bars of the steel grid, shall be placed a minimum of 1” from the web of the

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

23 ADDENDUM NO. 6

Page 24: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #0601999A

main bearing bars. Minimum cover between rebar and exposed surfaces of precast concrete

shall be 1” unless otherwise shown on the plans.

b) Match casting is to be used in placing the precast concrete and reinforcing to ensure that

there are no reinforcing conflicts and that geometry between panels match. The contractor

may submit to the Engineer for approval an alternative way to ensure there are no

reinforcing conflicts.

c) The top surface of the concrete shall be given a textured finish as designated by the Engineer

and as accepted by the Department.

d) The casting bed and forms shall have provisions for straightening and holding the steel grid

panels flat and square prior to placing concrete. The steel grid panels shall be checked for

conformity with the required dimensions as to cross slope, and must be supported to prevent

displacement during precasting operations to obtain the proper concrete thickness.

e) Precast panels shall not be removed from the forms or moved until the concrete has reached

the greater of 3500 psi or 75% of the concrete design compressive strength.

f) Precast panels shall be properly cured until the concrete reaches its 28-day design strength.

The precast panels may be steam cured or cured by standard methods for a concrete deck in

accordance with the standard specification.

g) The dimensional tolerances of a completed precast panel in any direction shall be ±1/4 inch.

h) After curing, all form release material and any other forming materials adhering to the

vertical faces of concrete shall be removed. Precast concrete vertical faces shall be

sandblasted, with care taken to avoid damage to the galvanized coatings. If the galvanize

coating of the reinforcing is damaged it is to be repaired at no cost to the owner.

i) A rigid lifting frame should be used whenever the precast panels are moved. Lifting

locations must be positioned to limit stresses in the panel. Proposed handling methods must

limit the actual concrete tensile stresses to 50% of the concrete modulus of rupture based

upon the proposed support locations and expected dynamic loading during handling,

storage, and transportation of the panels. Care shall be taken to avoid twisting of the panels

or bending of the panels in the weak (perpendicular to the main bar) direction.

j) The completed panels shall be marked with their proper identification label on top of the

panel and all four edges. Panels shall be stored and shipped right side up, and protected

from exposure to the weather. Wood lagging shall be used (with due regard to built-in panel

camber) to prevent damage to the steel, concrete, sheet metal, or galvanized coating. At a

minimum, lagging shall be placed immediately adjacent to the proposed lifting locations and

at the ends of the panel. Preferably, blocking should be placed at all stringer (floor beam)

block-outs and at the ends of the panel. Blocking between stacked panels must be in vertical

alignment across the panel width. Stack no more than four precast panels high.

Field Installation

a) Installation of the Exodermic deck panels will only be allowed during the period between

May 1st and October 14

th. The Engineer may adjust these limits on a case by case basis.

Due consideration should be given to the potential of deicing materials being introduced to

the Exodermic deck panel before an overlay and deck joints can be installed. Introduction of

deicer can be in the form of direct application or secondary transfer.

b) For each area to have the deck replaced by Exodermic decking an installation plan shall be

developed and submitted for approval. Individual areas are Span 10, Spans 14 thru 16 and

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

24 ADDENDUM NO. 6

Page 25: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #0601999A

Span 21 as indicated on the contract drawings. The plan is to include a constructions

schedule that is in 15minute increments for the weekend closures work. Include at a

minimum a list of tasks to be completed during the weekend closure and a list of responsible

parties for each task. Provide an estimate of the minimum number of personnel involved in

the deck replacements throughout the weekend closures at 4hr intervals.

c) Prior to each weekend closure a pre-closure meet will be held. The meeting will be held

between 5 and 10 days prior to each weekend closure. In each meeting the construction

schedule and task for the closure will be reviewed along staffing levels, contingency plans,

equipment and materials. For the first weekend closure a detailed walk through of the

schedule and tasks will be performed along with methods of construction. The first

weekend closure meeting shall be attended be the Engineer, construction inspectors, a

representative from the Departments traffic management center, Contractor’s

superintendent, Contractor personnel overseeing tasks, representatives from specialty

services, State and local Police representative. Attendees of future pre-closure meeting are

to be determined by the Engineer.

d) Advanced saw cutting of the existing concrete deck as indicated on the contract drawing

will be allowed under the following conditions. The period and conditions of work is to be

in accordance with the Maintenance and Protection of Traffic specification. The Contractor

will provide calculations to the Engineer demonstrating that cutting the deck will not affect

the safety of traffic. Saw cuts shall only be in the transverse direction across the deck. Only

saw cut portions of the deck required for the deck replacement that will occur during the

immediate weekend closure. Work can only be performed two nights in advance of the

weekend closure (Wednesday & Thursday). Extreme care is to be taken to avoid damaging

the existing structure which is to remain, including the steel members.

e) For removal of the existing deck submit a removal plan to the Engineer for approval. The

plan is to include at a minimum, the following:

Limits of deck removal.

Locations of saw cuts.

Locations of equipment.

Show minimum vertical clearances and clearances of equipment to the existing structure.

Maximum weights of pieces that are going to be lifted by equipment.

Type of equipment and weight of equipment to be placed on the bridge (excavators,

cranes, transfer vehicles).

Maximum loading from equipment used to lift material on the structure.

Provide an analysis that demonstrates that the existing structure will not be overstressed

by equipment used for the deck removal.

Provide details on containment system to prevent debris from entering the waterway or

storm water system.

Provide a plan as to how the existing structure will not be damage from removal

operations (example: saw cutting, jack hammers).

Extreme care is to be taken to avoid damaging the existing steel members by saw cutting. It

is recommended that the Contractor verify the thickness of the existing deck and account for

any changes in member sizes.

f) The method of installation for lifting and moving the panels is at the discretion of the

Contractor. Cranes, custom-made gantry, rigging from the structure above are allowed.

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

25 ADDENDUM NO. 6

Page 26: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #0601999A

Submit to the Engineer for approval a plan for lifting and moving the panels at each

location. At a minimum, the plan should include the following:

Lifting stress on the panels. The stress in the precast concrete shall not exceed 50% the

modulus of rupture for the concrete.

Information on the rigging to be used for lifting including maximum working loads.

Weights of panels to be lifted with a given rigging configuration.

Capacity of equipment to be used for lifting.

Locations of lifting equipment and delivery/ transfer equipment.

Sequence of panels to be installed.

Maximum loading placed by lifting equipment on the existing structure.

Provide an analysis that demonstrates that the existing structure will not be overstressed

by equipment used for the deck removal.

If custom gantry or equipment are used provide documentation or certification of the

maximum working load capacity and stability.

If rigging is attached to the structure above provide an analysis indicating that the above

structure can still carry active traffic while lifting of the operations are occurring and the

capacity of the rigging. Use a safety factor of two times the panel and rigging weight for the

analysis. If the rigging is to be left in place during times other than the weekend closures,

the minimum vertical clearance is to be 17 feet to any part of the rigging. Additionally, a

backup support system shall be use so that in the event of any attachment point fails no part

of the rigging is to fall below the 17 foot limit. The rigging will be inspected every 8 hours

for failure of attachment points or change in position. The Engineer may change the

frequency of these inspections. No welding to the existing structure is allowed for installing

rigging. Any hole drilled or cut into the structure must be repaired to the Engineers

satisfaction and at no cost to the Department. The rigging is to be painted in a high visibility

manner and have reflective stickers applied to them.

g) Installation and installation tolerances shall be in accordance with this specification and the

most recent version of BGFMA TS-03, “Installation Tolerances and Guidelines for Grid

Reinforced Concrete Bridge Decks,” published by the Bridge Grid Flooring Manufacturers

Association.

h) Panels will be delivered to the job site free from any defects and bearing the proper

identifying marks. The panels will be checked by the Engineer for defects and identification.

Repair or replace the grid panels or metal forms damaged during shipment and storage, to

the satisfaction of the Engineer. The panels may be rejected if the panels cannot be repaired

to the Engineer’s satisfaction.

i) Prior to deck panel installation, blast clean the top surfaces of beam flanges and the surfaces

of concrete that will be in contact with closure pour concrete according to the relevant

portions of the Standard Specifications.

j) The panels shall be placed on the structure with careful consideration given to the alignment

of each adjacent panel. Measure from fixed points to avoid cumulative error. Lifting panels

from the leveling devices, rebar, or distribution bars is prohibited.

k) Adjustment to proper elevation shall be made using of the built-in leveling bolts as

specified, or shims or other means.

l) After panels have been adjusted to their proper elevation, and all haunch and miscellaneous

forms have been installed, the contractor shall install the welded headed shear studs to the

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

26 ADDENDUM NO. 6

Page 27: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #0601999A

steel stringers, girders, and/or floor beams as detailed on the contract drawings through the

openings provided in the deck panels. Alternatively, with careful layout and the Engineer’s

permission, studs may be installed prior to placing deck panels. A separate welding

generator shall be used to furnish power to each stud gun to assure acceptable welds.

m) After all studs have been installed, the Contractor shall clean the top surface of all flanges

before any concrete is placed, including breaking the ceramic ferrules around the welded

studs.

n) At haunches and areas of full-depth concrete, the contractor shall seal the openings in the

main bars using duct tape or other similar material prior to concrete placement. Seal the

openings from the haunch or full-depth side.

o) High Early Strength (HES) concrete for field closure pours shall be paid for, placed,

finished, and cured in accordance with the HES concrete specification [and the relevant

portions of the owner’s Standard Specifications]. A pencil vibrator shall be used in the

haunch and transverse panel connection areas to assure good consolidation.

p) Construct new parapets on the Exodermic panels after they have been installed. Reinforcing

for the parapets may be placed while panels are being installed and closure pour concrete is

being placed. However reinforcing bars will not be allowed to stockpiled on the panels nor

equipment for moving the reinforcing allowed on the panels until the closure pour concrete

has reached a strength of 2,500 PSI. HES concrete for the parapets may be placed once the

closure pour concrete has reached a compressive strength of 3,000 PSI. Parapet HES

concrete shall be placed, finished, and cured in accordance with the HES concrete

specification [and relevant portions of the owner’s Standard Specifications].

q) The structure may be opened to traffic, without the use of a temporary concrete barrier, once

the HES joint closure concrete has reached a compressive strength of 4,000 PSI and the

parapet HES concrete has reached a compressive strength of 4,000 PSI. The structure may

be opened to traffic, with the use of a temporary concrete barrier placed in front of the

parapet, once the HES joint closure concrete has reached a compressive strength of 4,000

PSI and the parapet HES concrete has reached a compressive strength of 2,500 PSI. The

temporary barrier does not need to be anchored to the bridge deck. The temporary barrier

shall have the appropriate transition sections and impact attenuation at the ends. If used,

payment for the temporary barrier, transitions, and impact attenuation shall be under the

appropriate items. If the parapet is damaged from an impact on the temporary barrier, the

Contractor is to repair and restore the parapet before removing the temporary barrier.

r) A bituminous overlay and waterproofing membrane is to be placed over the Exodermic deck

panels that is in accordance with the project’s special provisions. For all installed

exodermic deck panels, no more than 14 days shall elapse between the final stage weekend

closure to place the panels and the complete placement of the overlay covering the

Exodermic panels.

s) Install the deck joints after the bituminous overlays has been placed. The joint type and

installation are to be in accordance with the contract drawings and associate specification.

Payment for the deck joint be paid for under the appropriate item.

Submittals:

a) Survey Report: A copy of the survey report used to develop the shop drawings is to be

submitted to the Engineer with the shop drawing. As indicated in the Exodermic Deck

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

27 ADDENDUM NO. 6

Page 28: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #0601999A

Panel section any discrepancies in geometry from the survey and contract drawings needs

to be resolved prior to the shop drawing submission. Submit a draft survey report to the

Engineer a minimum of one week prior to discussing the discrepancies for resolution.

Include a description of the discrepancies that will need to be resolved.

b) Shop Drawings: Shop drawings requested under the Exodermic Deck Panel section shall

be in accordance with Form 817 section 1.05 and modified by the following. Shop

drawings shall be submitted a minimum of 60 days prior to the start of any fabrication of

the Exodermic deck panels begins. Shop drawings submission for the fabrication of the

Exodermic deck panels and any subsequent follow-up submission must stand as a

complete and comprehensive package. The submission package should not rely on

references to prior submissions. All changes in subsequent submissions are to be clearly

indicated. If the reviewer finds any changes between submissions that are not indicated,

the reviewer may stop the review at that point and return the submission to the Contractor

for revisions. Additionally, the reviewer may stop a review and return it to the

Contractor if responses to comments are not provided. The Department and reviewer will

not be held responsible for delays to the project due to submissions that were returned for

changes to plans not being indicated or non-responses to comments. In lieu of hardcopy

submissions the Contract may make submissions by PDF. The PDF’s must be

electronically generated and not scans of hardcopies.

c) Concrete Mix Design: The concrete mix design for the concrete used to precast the

Exodermic deck panels shall be submitted a minimum of 45 days prior to any placement

of concrete.

d) Demonstration Test Module Report: The demonstration test module report shall be

submitted a minimum of 60 days prior to the installation of any Exodermic deck panels.

e) Deck Removal Plan: A separate existing deck removal plan may be submitted for each

deck replacement area. With the areas defined as, Span 10, Spans 14 thru 16 and, Span

21. The removal plan shall be submitted a minimum of 60 days prior to the applicable

weekend closure.

f) Saw Cutting of Existing Decking Procedure: As part of the deck removal plan submit a

saw cutting procedure. The procedure shall discuss how damaging of the existing

structure and steel is to be prevented and how the structure will be inspected for damage.

g) Installation Plan: A separate Exodermic deck panel installation plan may be submitted for

each deck replacement area. With the areas defined as, Span 10, Spans 14 thru 16 and,

Span 21. The installation plan shall be submitted a minimum of 60 days prior to the

applicable weekend closure.

h) Rigging & Lifting Plan: A separate rigging & lifting plan may be submitted for each deck

replacement area. With the areas defined as, Span 10, Spans 14 thru 16 and, Span 21.

The rigging & lifting plan shall be submitted a minimum of 60 days prior to the

applicable weekend closure when using cranes and gantry equipment. If rigging or lifting

from the above structure is proposed the plan shall be submitted a minimum of 90 days

prior to the applicable weekend closure.

i) Rigging Analysis: As part of the rigging and lifting plan submit calculations supporting

the rigging and lifting plan.

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

28 ADDENDUM NO. 6

Page 29: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #0601999A

j) Custom Gantry: If a custom gantry or equipment is to be used for lifting and moving the

Exodermic panels submit documentation of the equipment’s capacity a minimum of 60

days prior to the applicable weekend closure that the equipment is going to be used for.

k) Geometry Correction & Repair plan: If in the event that the Exodermic deck panels will

require geometry corrections or damage repaired prior to installation a plan and

procedure for making corrections or repairs will be submitted. The reviewer will be

given 14 days for the first review and 7 days for each subsequent review if the plan and

procedure are submitted at the time of the event. The Department or Reviewer are not to

be held responsible for delays due to time required to review the plan and procedure. The

plans and procedure may be submitted prior to the fabrication of the Exodermic deck

panels, with the review being allotted 60 days to complete.

Method of Measurement:

Precast Exodermic® panels shall be measured as the total gross square footage of the deck panels

installed and inspected in accordance with the plans and specifications. Measurements shall be

taken as the area encompassed by the outside deck edges and the centerline of deck joints taken

at the top surface of the deck slab. No deduction shall be made for joints, block-outs, or

openings.

Basis of Payment:

The unit bid price shall include the cost of furnishing all labor, materials, and equipment

necessary to complete the work, including the furnishing and installation of all deck panels,

which also includes the cost of transportation, storage, and protection from damage to the deck

panels. Items for replacing the existing deck with Exodermic deck panels include the following:

Exodermic Deck Panels:

fabricated steel (included)

concrete (included)

reinforcing (included)

Demonstration test module (included)

Closure Pour Concrete:

Sheet metal for forms (included)

Reinforcing (included)

Miscellaneous materials for sealing block outs (included)

HES Concrete (separate pay item)

Parapets:

Reinforcing, not cast with panel (separate pay item)

HES Concrete (separate pay item)

Formwork (incidental to HES concrete)

Temporary barrier (separate pay item)

Overlay:

Waterproofing membrane (separate pay item)

Bituminous pavement (separate pay item)

Expansion joints (separate pay item)

Miscellaneous:

Removal of the existing deck (separate pay item)

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

29 ADDENDUM NO. 6

Page 30: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #0601999A

Shear Studs (separate pay item)

Shop Drawing (incidental to the associated item)

Survey (included)

Submissions (incidental to the associated item)

Meeting (incidental to the associated item)

Transporting and Installation (included)

Any cranes, gantries, rigging, load distributing materails and custom equipment shall be included

in the cost of the Exodermic Deck.

Pay Item Pay Unit

Exodermic Deck s.f.

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

30 ADDENDUM NO. 6

Page 31: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #1131016

THROUGH #1131024

ITEM #1131016A – SMART WORK ZONE MOBILE VIDEO

CAMERA/QUEUE SENSOR TRAILER (SVQS)

ITEM #1131017A – SMART WORK ZONE MOBILE VIDEO

CAMERA/QUEUE SENSOR TRAILER (SVQS) SERVICE

ITEM #1131018A – SMART WORK ZONE VARIABLE MESSAGE

SIGN/QUEUE SENSOR TRAILER (SVMQ)

ITEM #1131019A – SMART WORK ZONE VARIABLE MESSAGE

SIGN/QUEUE SENSOR TRAILER (SVMQ) SERVICE

ITEM #1131020A – SMART WORK ZONE DEPLOYMENT

ITEM #1131021A – SMART WORK ZONE OPERATIONS

ITEM #1131022A – SMART WORK ZONE TRAILER RELOCATION

ITEM #1131023A – SMART WORK ZONE QUEUE TRAILER/SENSOR

(SQT)

ITEM #1131024A – SMART WORK ZONE QUEUE TRAILER/SENSOR

(SQT) SERVICE

Description: This work shall consist of furnishing, installing, operating, servicing, maintaining,

relocating and removing an automated Smart Work Zone (SWZ) of the complete system for the

duration of the Project.

These items shall include vehicle trailers, sensors, cameras, variable message signs, cloud hosted

third party traffic speed data, processed rock for leveling trailers, website, communications

equipment, relocation, service and maintenance. Included in the operational responsibilities is

the assumption of all trailer license plates, communication costs such as FCC licensing, cellular

telephone, wireless data networks, satellite and internet subscription charges, solar system

support, battery charging and maintenance. In addition to these requirements, the Contractor

shall assume all responsibility for any damaged equipment included in the system due to crashes,

vandalism, adverse weather, etc. that may occur during system deployment and operation.

This system shall monitor the areas in advance of the project work zone and project’s work zone

area. The SWZ shall provide Connecticut Department of Transportation (CTDOT) operators

control of the cameras to disseminate real-time information to the traveling public and other

stakeholders. The system shall be completely operational 14 days prior to the start of roadwork

PROJECT NOS. 0151-0312,0151-0313, & 0151-0326

31

ADDENDUM NO. 6

Page 32: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #1131016

THROUGH #1131024

to allow for traffic data accumulation by the system. The SWZ shall consist of an automated

system using trailer-mounted microwave sensors that transmit vehicle speed and related data

through cellular communications to a Contractor-hosted central computer system. The camera

shall be used to verify traffic conditions within the viewable area of the camera. The central

computer system shall send automated and operator manual commands to variable message signs

through cellular communications to display travel time, delay and stopped traffic information.

The speed data, video images, and variable message sign content shall be hosted on a Contractor-

supplied website.

The SWZ shall be capable of detecting the presence of queued traffic in the segments identified

on the plans and reporting via the queue warning Smart Work Zone Variable Message

Sign/Queue Sensor Trailer (SVMQ). The distance from the SVMQ to the detected back of

queue shall be reported within 1/2 mile accuracy on the system, but reported on the SVMQ at 1

mile accuracy rounded up to the nearest mile. This “real-time” queue location information shall

be calculated and displayed on the applicable SVMQ to the nearest minute.

The SWZ shall have the capability to notify the construction field office, Contractor or others, as

determined by the Engineer, of travel times and when the speed through the work zone decreases

below 30 mph. The system shall be capable of transferring real-time data in a file format

compatible with Oracle®. “Motion” video feeds updated once per 1 second shall be available for

the CTDOT to display on the Contractor-provided website. In addition, any number of CTDOT

or Contractor employees shall be notified via email or text message for these speed changes.

Contact information will be furnished by the Engineer at the start of the SMZ deployment.

All the required components of the SWZ shall be fully operational within 45 days of notice to

deploy from the Engineer. If not fully operational within said 45 days, a payment reduction of

5% for each day the entire system is not operating will apply, as determined by the Engineer.

Once operations begin, the SWZ shall perform with no major malfunctions throughout the

Contract, unless the Engineer requests the system or portions of the system be removed.

Malfunctions include, but are not limited to, the inability of the equipment to provide accurate

real-time video feeds, delay, or travel time information, inability to withstand the construction

roadside environment or normal weather conditions. The Engineer reserves the right to

terminate this item at any time if it is determined the SWZ is not performing in accordance with

this specification.

Construction Methods:

Submittals:

1. At least 20 days prior to beginning installation, the Contractor shall submit to the Engineer for

review and approval, in consultation with the CTDOT’s Subject Matter Expert, evidence that the

proposed supplier has successfully completed at least 5 SWZ projects similar in concept and

scope to the proposed system in the past 5 years. The proposed supplier shall also provide the

credentials of a qualified technician who shall install and operate the system. Include names,

addresses, and telephone numbers of the similar project’s owner’s representatives for

verification.

PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

32

ADDENDUM NO. 6

Page 33: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #1131016

THROUGH #1131024

2. Also, at least 20 days prior to beginning installation, submit brochures and cut sheets on all

units of the SWZ, with details of how and which communications systems shall be used, and the

technical specifications for the website.

3. The Contractor shall demonstrate to the Engineer an operating SWZ.

4. At least 14 days prior to installation, the Contractor shall propose the actual device layout to

the CTDOT for review and approval.

5. Prior to public viewing, the website map showing device locations and other interactive

elements shall be submitted for the Engineer’s review.

6. The Engineer reserves the right to add or remove locations as needed.

Equipment:

1. The SWZ shall consist of the following equipment.

a) Thirteen (13) SVQS with camera with pan-tilt-zoom (PTZ). The computer hardware and

software must meet the manufacturer’s requirements to operate and monitor the system.

The camera response time to web commands for PTZ shall be reviewed and approved

by the Engineer. The PTZ response time shall follow the operator’s manual commands

to move the camera to the desired position.

b) Four (4) SQT shall provide real time speed, volumes, occupancy and other necessary data

to the SWZ to activate messaging on the variable message signs and provide historical

data.

c) Eight (8) SVMQ shall display real-time travel time messaging and back of queue warning

to the traveling public.

d) Communication equipment including wireless data networks, base stations, cell phone

data interfaces, Ethernet network interfaces, and internet interfaces.

e) Customized Webpage integrated with the SWZ to include traveling public and Project

staff accessibility; SWZ website shall be allowed to “link” to the CTDOT’s website

f) Software package customized for this particular Project’s needs

2. The following shall be provided for each SQT, SVMQ and SVQS with PTZ:

a) Approximate locations of variable message signs and traffic sensors shown on the figures

below may be adjusted to ensure sightlines and safety are adequate

b) Clean stone or processed rock to provide a level area for trailers and provide for

sufficient height for sensors to operate correctly.

c) Individually mounted on trailer units with solar power.

d) Equipped with digital wireless cellular modems as required.

e) Linked to the Contractor’s central computer server.

f) Maintained as needed to remain operational, including cleaning and inspecting

components, snow and ice removal from solar panels and keeping batteries charged.

g) Extra set of programming instructions stored in the units for emergency use.

3. The SVQS, SQT, and SVMQ shall collect and process traffic data as programmed within the

software provided with the sensors. This data shall be transmitted over a digital cellular network

to access and store the respective data remotely. The remote monitoring and data collection shall

be placed in areas where wireless communication is available. The SVQS, SQT, SVMQ shall

PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

33

ADDENDUM NO. 6

Page 34: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #1131016

THROUGH #1131024

use both solar power and deep cycle batteries to provide a self-contained completely autonomous

system.

The SVQS mobile camera(s) shall provide a mobile, self-contained, all-weather, trailer-mounted

equipment platform. The mobile camera system shall use wireless communication. The mobile

camera shall provide a rapidly-deployable real-time video system viewable from a remote

location. The mobile camera shall be capable as a stand-alone camera system.

a) Trailer and power requirements:

i. 2-wheel industrial grade trailer with stabilizer legs

ii. Available as a mobile unit or permanent mount

iii. Adjustable solar array for maximum exposure to sun

iv. Removable trailer tongue

v. Battery bank sized for 30-day autonomy

b) SVQS requirements:

i. Microwave detection (Wavetronix Smart Sensor HD or approved equal) with

Dual Radar that reliably detects up to 22 lanes of traffic, auto configuration

ii. Provide data including speed, volume and occupancy

iii. Digital cellular communications

iv. Dome camera with day/night adjustable pan/tilt/zoom IP addressable

v. Mobile camera system shall provide camera operating software to use

camera manufacturer’s operating system.

vi. Minimum 30 ft extendable mast with 360 degree lockable rotation

vii. Capable of providing streaming or snapshot video

viii. Electric hoists for rapid deployment

c) SQT requirements:

i. Microwave detection reliably detects up to 22 lanes of traffic

ii. Data provided includes speed, volume and occupancy

iii. Available as a mobile unit or permanent mount

iv. Digital cellular communications

4. The SVMQ shall be configured with the following variable message sign requirements or

approved equal:

a) Trailer and power requirements:

i. 2-wheeled trailer structurally adequate to serve as both a carrier and an operating

platform

ii. Meets Federal Regulations for safety and travel

iii. Color of trailer paint shall be safety orange or as approved by the Engineer

iv. Bank of batteries capable of being recharged automatically by a group of solar

panels located at the highest point on the unit

v. Variable message signs shall be designed with sufficient energy backup to operate

for a period of 30 days (minimum) at 75°F without sun exposure

vi. Solar panel generator array shall recharge the battery bank at a rate of 2 1/2 hours

peak sun per 24 hour period of usage

vii. Solar panel array sized to replace the power used in typical daily operation with

less than 4 hours of sun

PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

34

ADDENDUM NO. 6

Page 35: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #1131016

THROUGH #1131024

viii. Deep cycle, lead acid 12 volt batteries wired in parallel, housed in a lockable

heavy duty steel weatherproof battery box

ix. Batteries recharged by a solar panel array producing 110 watts of power minimum

x. Built-in battery charger with minimum 25 ampere per hour rating

xi. Solar charge current meter and battery charger current meter visible

xii. Protective housing painted with manufacturer’s standard colors

b) Variable Message Sign/Queue Sensor requirements:

i. Sign panel of welded aluminum alloy construction, assembled to prevent

dissimilar metal action from occurring

ii. Length of sign panel 128 inches or less

iii. Front face of sign covered with clear UV-inhibited polycarbonate to prevent

fading

iv. Message center:

1) 3 separate lines, center justified

2) Each line up to 8 characters, equally spaced a minimum of 3 inches apart

3) Each character 18 inches high by 12 inches wide

4) Each character configured with 35 LED lamp pixels in a 5 x 7 element

arrangement

5) Message color 590 nanometers (yellow-orange)

i. Remote sign operation via central computer

ii. Messages to be displayed shall have capability to be timed to changes at various

times of day and days of week

iii. Trailer-mounted variable message board consisting of optically enhanced LED

lamp matrix panels powered by a bank of batteries in order to convey bright,

distinctive messages to the traveling public

iv. Sign capable of displaying up to 8 pages in a multiple page message, with

variable timing in 1/10 second increments under computer control

v. Sign shall completely change all lines of message copy in not more than 100

milliseconds

vi. Sign clearly visible and legible from a distance of 800 feet under both day and

night conditions, with a photocell automatically adjusting its light source for

variable light level conditions

vii. Sign panel supported on a telescoping upright member with hydraulic lift to

permit raising the sign for operation and lowering the sign for transport

viii. Telescoping upright able to rotate 360 degrees and shall lock into position

ix. Telescoping distance of nominally 5 feet to allow bottom of sign to be at least 7

feet above the ground

x. Sign panel shall pivot to the longitudinal axis of the trailer for transport, to reduce

aerodynamic drag

xi. Static sign attached identifying the message board is for the Project; coordinate

sign content and appearance with the Engineer

xii. Microwave detection (Wavetronix Smart Sensor HD or approved equal) with dual

radar that reliably detects up to 22 lanes of traffic, auto configuration

xiii. Data provided from sensor to include speed, volume and occupancy

xiv. Available as a mobile unit or permanent mount

PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

35

ADDENDUM NO. 6

Page 36: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #1131016

THROUGH #1131024

c) Variable Message Sign on-board dedicated computer requirements:

i. Solid state design, removable, including a keyboard through which user originated

messages may be entered for display or storage

ii. LCD display screen upon which messages can be reviewed before display on the

message sign

iii. Storage of a minimum of 100 preprogrammed messages for display when called

upon by an operator through the keyboard and a minimum of 100 users

originated multiple page messages.

iv. Password coding or key entry.

v. Control programming to present sequenced messages under operator control

through keyboard entry.

vi. Control for moving arrow displays.

vii. Calendar program to automatically start and stop the display of sequences at

predetermined times.

viii. Character board and battery diagnostics.

ix. Computer housing: weather resistant, shock resistant lockable control box with a

light for night operation.

x. Power control unit housed in a lockable, steel, weatherproof battery box

containing 2 current meters (to show amperage generated with battery charger

and amperage from solar panels to battery bank).

xi. Power control unit to incorporate a PV regulator with thermal compensation for

variances in ambient temperature, to regulate the charge rate to the battery bank.

xii. Control circuitry connected to variable message sign’s photocell that detects

ambient light conditions and reduces lamp intensity at night to reduce glare.

d) Variable Message Sign - other requirements:

i. Variable message sign operation using cellular telephone and cellular telephone

service (trailer must be located within cellular telephone coverage), allowing

operator remote control of the on-board computer

ii. A Queue Trailer/Sensor may be located next to designated SVMQ to collect data

iii. The message sign shall provide for remote sign operation via central computer

base station or Website allowing operators to manually override the automated

messaging in order to display a message at any time. The operator shall be able

to cancel this override and initiate the systems automated messaging feature.

iv. Any request to change messages on the Variable Message Signs shall be approved

by the CTDOT.

Deployment and Operation:

The decision to deploy or remove individual devices or the entire SWZ will be made by the

Engineer. Once the decision is made to deploy the system, the Engineer will coordinate with the

Contractor for the duration of system deployment.

1. The SWZ shall be installed as shown in the approved layout. The locations may require

repositioning as directed by the Engineer and as the project continues. The system shall be

maintained and operated for the duration of the Project or as directed by the Engineer. The

Contractor shall service the SWZ on a 6 month regular interval for the duration of the Project or

as directed by the Engineer. Additionally, the Contractor shall clean the Camera dome bubbles at

PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

36

ADDENDUM NO. 6

Page 37: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #1131016

THROUGH #1131024

least once per month during the winter months between December and March for the duration of

the project as directed by the Engineer. The service shall include cleaning the sign panel,

removing snow/ice and debris from the solar panels as needed or as directed by the Engineer.

The Contractor shall follow the manufacturer’s requirements for cleaning the SVQS. The cost of

the service shall be included in the items (Item Nos. 1131017A, 1131019A, and 1131024A) for

each unit.

2. The Contractor shall prepare the locations to receive the equipment in accordance with the

equipment manufacturer’s requirements. Each location shall include clean stone or processed

rock provided and installed by the Contractor to level the surface area. Some location may

require the trailers to be lifted over the safety barrier and placed on the level processed rock.

3. The Contractor shall install each of the system components in accordance with the

manufacturer’s recommendations, in compliance with all industry standards and codes such that

each system is fully operational and can be operated and controlled from the Construction Field

Office or remotely, as approved by the Engineer.

4. The Contractor shall coordinate the work with others as designated by the Engineer to

complete installation and integration of all equipment for all system types.

5. System Calibration and Configuration: The SWZ shall provide the following:

a) Software shall be configured for notification to appropriate personnel at the Highway

Operations Center, the Construction Field Office and the Contractor by email each time a

malfunction has occurred in the system. A malfunction record shall also be made in the

database. The software shall be configured so that any number of approved personnel

can be notified. The email shall display an error message for the device or devices

affected. Through the Contractor, the SWZ Webpage Integrator shall be responsible for

this notification procedure.

b) Software shall be configured to provide current operational and location status (such as

current traffic data and messages, communications system, signs, and sensors as well as

latitude/longitude of all deployed devices) via the Internet to a dedicated Website

established for the purpose of monitoring the corridor and the SWZ equipment.

c) Software shall be configured to assess any type of malfunction that has occurred. This

assessment includes communications disruption between any device in the system

configuration, variable message board malfunctioning, speed sensor malfunction, loss of

power, low battery, etc. This malfunction information shall be sent via email in text

format to the Highway Operations Center, Engineer, or Contractor, as designated by the

Engineer, for each occurrence.

d) To support incident management, the SWZ software shall be configured to allow Project

staff to manually override motorist information messages for a user-specified duration;

after which, automatic operation will resume with display of messages appropriate to the

prevailing traffic conditions. All overriding messages shall have the message content and

the username logged into the database.

6. SWZ Website shall have the following:

a) Password protected link for approved personnel to access the operational characteristics

of the system, allowing manual override of errant messages.

b) The website shall display current traffic conditions and real time speed at upstream

locations to the nearest minute. The “real time” traffic delay information displayed on

PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

37

ADDENDUM NO. 6

Page 38: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #1131016

THROUGH #1131024

the SVMQ’s shall be updated every 1 minute minimum with the website delay

information updated simultaneously.

c) The website shall allow the scheduling of messages by the operator on a sign or group of

signs, to turn on and to turn off messages at times set in the future.

d) Placement of all devices shall be shown on the dedicated website using latitude/longitude

coordinates. The placement of these devices on the website shall be approved by the

Engineer prior to release of the website.

e) The website shall display camera images at least five (5) frames per second. Cameras

images shall be displayed by a user selectable menu. Cameras can be selected one (1) at a

time or all cameras images simultaneously using another page or “video wall.” Camera

images can be displayed by “hovering” over and selecting the camera icon.

f) Via the internet and the dedicated website, the website shall provide a full color map

using Google Maps or equivalent depicting the Project area with locations of traffic

sensors and SVMQ’s. Using an administrator defined color-coding scheme, the map

reflects the current average speed at each traffic sensor and displays the entire

information message being shown by each SVMQ either on the map or on the side bar of

the website. The Contractor shall use the third-party traffic speed data to “fill” in the

speed data display on the website between sensors. The contractor shall use the sensors

for maximum distance of one-half (1/2) mile on the map. The map shall be automatically

refreshed a minimum of once every minute to display any changes to traffic sensor(s)

and/or SVMQ’s. A legend of all icons and a short description of each shall be placed on

the website.

g) The SWZ website shall be capable of providing and displaying the travel delay cost data

(monetary values) in a graph and/or chart format and allow users to run reports against

the data by hour, day and month intervals through the browser. This feature shall not be

accessible by the public. The SWZ website shall have report output formats that include

at minimum PDF, rich text format, and Microsoft Excel formats. See requirement 10.

Part o. h) The SWZ Website shall provide a map with current traffic conditions by way of a colored

layer over the road. The layer on the map shall display a different color for the different

traffic speeds by use of colored bars over the existing road, with a legend explaining the

meaning of each color. The color descriptions are as follows: i. less than 10 mph = black

ii. less than 30 mph = red

iii. less than 40 mph = orange

iv. less than 50 mph = yellow

v. 50 mph and over = green

7. Smart Work Zone Operations

a) System Communications shall meet the following requirements:

i. The Contractor shall perform the required configuration of the SWZ’s

communications system during system initialization.

ii. Communications between the server and any individual SVMQ or SVQS shall be

independent through the full range of deployed locations and shall not rely upon

communications with any other SVMQ or SVQS sensor.

PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

38

ADDENDUM NO. 6

Page 39: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #1131016

THROUGH #1131024

iii. The SWZ communications system shall incorporate an error detection/ correction

mechanism to insure the integrity of all traffic conditions data and motorist

information messages.

b) In addition to meeting manufacturer’s specifications, the Contractor shall program the

SWZ to ensure that the following General Operational requirements are met:

i. The SWZ traffic sensors shall be such that the accuracy is not degraded by

inclement weather and visibility conditions including precipitation, fog,

darkness, excessive dust and road debris. The sensors shall be capable of

acquiring traffic data for a minimum of 22 lanes of traffic on a lane-by-lane

basis.

ii. The SWZ shall operate continuously (24 hours, 7 days a week) when deployed on

the Project. It shall always be collecting and storing data.

iii. All traffic data and motorist information messages displayed by the SWZ shall be

archived in the database with time and date stamps.

iv. The SWZ shall be capable of acquiring traffic volume and speed data, developing

travel times, and selecting motorist information messages automatically without

operator intervention after system initialization.

v. The SWZ shall automatically select default and advisory messages based on

traffic conditions at a single traffic sensor point or at multiple traffic sensor

points in combination.

vi. Administrative users shall be able to create and save a library of messages with up

to 20 different default or automatic advisory messages for each SVMQ.

vii. System operator control functions shall be password protected.

viii. To support incident management, the SWZ shall allow the Engineer and Project

staff with password privileges to manually override motorist information

messages for a user-specified duration, after which automatic operation shall

resume with display of messages appropriate to the prevailing traffic conditions.

ix. The SWZ shall be capable of providing current operational status (such as current

traffic data and messages, communications system, signs and sensors, video

feeds) via the dedicated Project website.

x. For remote sign operation, the website shall allow password-protected access for

Project staff to manually override automated messaging in order to display a

message at any time. The staff shall be able to send a pre-programmed or

custom message to a selected sign or group of signs. The staff shall be able to

cancel this manual override and initiate any and all of the system’s automated

messaging features at any time.

xi. The default and advisory message content shall be programmable from the

website as well as the field laptops.

xii. The dedicated Project website shall provide a full color map depicting the Project

area with locations of SVQS sensors and SVMQ’s. The graphical

representation of each device location is based on latitude/longitude

coordinates. The map shall show the current traffic conditions at each SQT and

display the entire SVMQ message at each location.

xiii. The website shall have a link to the CTDOT’s website and the website shall allow

the CTDOT’s website to link to it.

PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

39

ADDENDUM NO. 6

Page 40: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #1131016

THROUGH #1131024

xiv. The system shall autonomously restart in case of power failure in any part of the

system.

xv. Each SVMQ shall be capable of displaying 8 characters on each of 3 rows.

Standard messages shall be as defined in “Smart Work Zone Management

System Motorist Information Messages” section below.

xvi. Cameras must be capable of operating on both solar and AC power. Should the

visibility of the traffic cameras be degraded by inclement weather including

snow, precipitation, excessive dust or road debris, the Contractor shall clean the

camera housing to restore proper viewing.

8. Training and Support required:

a) Ensure that the SWZ is furnished, installed and maintained by personnel who are

experienced in this type of work. Deploying firm personnel must have a minimum of 5

similar deployments.

b) Training shall be provided to Project staff on their authorized use and operation of the

physical field hardware, software and website of the SWZ.

c) The Contractor shall supply training and documentation to enable the Engineer to add

additional signs or traffic sensors to the system. The Contractor shall provide the

communications for any of these additional signs or traffic sensors.

9. System Operational Performance:

a) To ensure a prompt response to incidents involving the integrity of the SWZ devices, the

Contractor shall be required to make all necessary corrections to the components of the

system within 24 hours of notification by the CTDOT.

b) If all corrections are made within this 24-hour period and the system is brought back on-

line, no pay reduction (as outlined in the Method of Measurement section) will occur.

c) If the 24-hour timeframe expires and the components of the system are not fully restored

to proper working order, no payment will be made from the time of initial notification

until the system is brought back on-line. If the system is restored within 10 days, a pro-

rated monthly payment reduction will be determined as outlined in the Method of

Measurement section.

d) If the components of the SWZ are down for more than 10 total days in a month, whether

they are consecutive or cumulative, and then NO payment will be made for that month.

Components are the SWZ variable message signs, SWZ Mobile Camera with PTZ,

Communications Equipment, and SWZ Queue Sensors, computer hardware and software

required to place the real time information on the signs, and the project’s Website. The

CTDOT reserves the right to remove the SWZ components if it determines the system is

not performing in accordance with this specification, and no additional payment shall be

made.

10. Data Acquisition requirements:

a) Each SVQS sensor shall communicate with the field computers and the website to

activate the appropriate SVMQ whenever the prevailing traffic speed slows to below 15

mph (or other designated speed as determined by the Engineer). Once activated, pre-

programmed messages shall be automatically displayed on the SVMQ. The message

content shall be as directed by the Engineer.

PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

40

ADDENDUM NO. 6

Page 41: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #1131016

THROUGH #1131024

b) The SWZ shall be capable of calculating and having “real time” delay information

displayed on the SVMQ’s. This “real time” delay shall be calculated and displayed on

the SVMQ’s to the nearest minute.

c) The website delay information shall be updated simultaneously with the traffic speed

information displayed on the Variable Message Signs.

d) To allow for motorist information messages of high specificity, the SWZ shall acquire

quantitative traffic data using an accurate speed measurement technique that includes the

capability of detecting stopped traffic and counting traffic volume.

e) The SWZ system’s traffic sensors shall be of a type whose accuracy is not degraded by

inclement weather or low visibility conditions including precipitation, fog, darkness,

excessive dust, and road debris.

f) The SWZ shall be capable of acquiring traffic data from up to 22 lanes of traffic in

multiple directions, for example: 11 northbound and 11 southbound.

g) The Contractor shall provide redundancy for data archiving and exchange. The

Contractor shall provide Content Delivery Network (CDN) to aggregate video data

streams from any PTZ camera to a centralized location to reduce bandwidth consumption

from each individual PTZ camera head to end users and allow for separate controllable/

configurable streams for public and operator use.

h) The CDN shall be capable of allowing the Project staff to start and stop public feeds from

the SWZ website while not interfering with the private feeds being displayed on the

website.

i) All traffic data acquired by the SWZ including, but not limited to, calculated data fields

shall be archived in a log file with time and date stamps for the duration of the Project.

During the Project, requests for archived data may be made through the Engineer to the

SWZ contractor. The Contractor shall provide this data to the Engineer within 5 days

upon receipt of the original request.

j) At the end of the Project, the SWZ Contractor shall provide the CTDOT comprehensive

Project archive data with the exception of video. This logged information shall be in a

format compatible with CTDOT requirements. The Contractor shall coordinate with the

Engineer for requirements.

k) The SWZ shall provide device outage alerts via email to the Engineer for outages greater

than 15 minutes. The alerts shall be used to generate a monthly summary spreadsheet

displaying outages greater than 24 hours, submitted to the Engineer. The email addresses

for recipients of outage alerts shall be provided by the Engineer. Any pay reductions as

per the pro-rated schedule will be calculated from the monthly outage summaries, as

described in the Method of Measurement section.

l) The system shall be capable of transferring for each camera device a video data format

acceptable to the CTDOT.

m) The Contractor shall provide notification of data format changes to the CTDOT before

they take place.

n) Unique device identifiers shall be coordinated at the beginning of the Project and shall

not change once the SWZ contractor has initially defined them, unless otherwise

approved by the Engineer.

o) The SWZ shall be capable of calculating travel delay cost (monetary value) information

for passenger cars and trucks from the beginning of the Project to the end of the Project.

PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

41

ADDENDUM NO. 6

Page 42: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #1131016

THROUGH #1131024

The SWZ system shall maintain a database of current and historical travel delay cost

data. The SWZ travel delay cost information shall be provided in dollars per hours

($/hr.) of travel time. The SWZ travel time delay cost information shall follow the

Chapter 2 (Sections 2.2.1 – 2.2.2.3) of the Work Zone Road Users Costs Manual

(FHWA-HOP-12-005). The Contractor shall provide the calculations and formulas for

the travel delay costs to the Engineer for review and approval prior to the SWZ system

implementation. The Contractor shall provide examples of the charts and tables for the

travel delay costs to the Engineer for review and approval prior to the SWZ system

implementation. The scale of the travel delay costs charts and tables shall be consistent

with the data accumulated by the SWZ throughout the Project period.

11. SWZ Motorist Information Message requirements:

a) The SVMQ shall be capable of providing speed, delay, length of traffic queue, travel

time, stopped vehicles, and lane closure message advisories to motorists.

b) Records of all motorist information messages and travel times displayed by the SWZ

shall be submitted to the Engineer in a format compatible with CTDOT requirements.

c) The SWZ must have capacity to preset up to 20 different default or automatic advisory

messages for each SVMQ.

d) Message Sets:

i. The upstream SVMQs within 1 1/2 miles of the work zone shall display either the

following message or an alternate message approved by the Engineer:

ROAD WORK AHEAD

XX MIN THRU WORKZONE

ii. SVMQs located within the work zone will display different messages as per their

location. Either the following sample message or an alternate message

approved by the Engineer will be displayed:

TO EXIT XX

X MILES

X - X MIN

iii. Queue warning SVMQ’s located prior to any construction activity that negatively

impacts traffic flows shall display the following message or an alternate

message approved by the Engineer:

STOPPED TRAFFIC XX MILES

BE PREPARED TO STOP

- or -

SLOW TRAFFIC XX MILES

USE CAUTION

e) The sequences above are a minimum requirement and can be adjusted by the Engineer at

his or her discretion.

f) The SWZ shall acquire traffic flow data and use an accurate speed calculation technique

that includes the capability of detecting stopped traffic, counting traffic volume and lane

occupancy.

g) The wireless cellular communications system(s) used for the Project must be reliable,

dependable, and capable of functioning at all times regardless of weather, locations and

cell phone usage. The Contractor shall be responsible for all communications costs,

PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

42

ADDENDUM NO. 6

Page 43: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #1131016

THROUGH #1131024

utilities, and satellite or cellular phone services needed to provide the dependable

functioning SWZ.

Approximate Location of SWZ:

Figures 1-4 and Tables 1-4 are provided as a guide. Actual locations of the SWZ equipment

shall be determined in the field. The Engineer will review and approve final locations of the

equipment.

PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

43

ADDENDUM NO. 6

Page 44: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #1131016

THROUGH #1131024

FIGURE 1: Rte 8 Northern Section

N

PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

44

ADDENDUM NO. 6

Page 45: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #1131016

THROUGH #1131024

FIGURE 2: Rte 8 Southern Section

N

PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

45

ADDENDUM NO. 6

Page 46: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #1131016

THROUGH #1131024

FIGURE 3: I-84 Western Section

N

PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

46

ADDENDUM NO. 6

Page 47: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #1131016

THROUGH #1131024

FIGURE 4: I-84 Eastern Section

N

PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

47

ADDENDUM NO. 6

Page 48: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #1131016

THROUGH #1131024

Tables: Approximate Location of SWZ Implementation for the Project Site. All locations shall

be confirmed with the Engineer.

Table 1 – Rte 8 Northern Section

Route Direction Town Location Type of

Equipment

Rte 8 Southbound Waterbury Rte 8 at

Huntingdon Ave

On Ramp shoulder

behind guide-rails

(Near Huntingdon

Ave Playground)

SVMQ-1

Rte 8 Southbound Waterbury Rte 8 after “ I-84

Hartford Danbury

1 Mile” Roadway

Sign (near scrap

yard)

SQT-1

Rte 73 Southbound Waterbury Rte 73 Shoulder

West of 108

Edwin Ave

SVMQ-2

Rte 73 Southbound Waterbury Rte 73 Median

West of 49 Edwin

Ave

SVQS-1

Rte 8 Southbound Waterbury Rte 73 On-Ramp

shoulder to Rte 8

(behind Brass City

Hyundai)

SVQS-2

Rte 8 Southbound Waterbury Rte 8 shoulder

East of 151

Watertown Ave

SQT-2

Rte 8 Northbound Waterbury Rte 8 at Riverside

St On-Ramp

(Watertown Ave

Overpass)

SVQS-3

Rte 8 Northbound Waterbury Rte 8 at Riverside

St On-Ramp

behind concrete

barrier (after

Freight Street

Overpass)

SVMQ-3

PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

48

ADDENDUM NO. 6

Page 49: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #1131016

THROUGH #1131024

Table 2 - Rte 8 Southern Section

Route Direction Town Location Type of

Equipment

Rte 8 Northbound Waterbury TBD in field SVQS-6 (Phase

2)

Riverside

St

Northbound Waterbury Riverside St

shoulder behind

guiderails after

Summit Street

Intersection

SVQS-4 (4

months)

Rte 8 Northbound Waterbury Rte 8 Gore Area

on S Riverside St

On-Ramp

SVQS-5

Rte 8 Northbound Waterbury Rte 8 Exit 30

Gore

SQT-4

Rte 8 Northbound Waterbury Rte 8 shoulder

behind guiderails

West of 300 S

Leonard St

SVMQ-4

Table 3 - I-84 Western Section

Route Direction Town Location Type of

Equipment

I-84 Eastbound Waterbury I-84 Median West

of 86 Country

Club Rd

SVMQ-5

I-84 Eastbound Waterbury I-84 Shoulder

behind guide-rails

before “Exit 18

Chase Pkway 1

Mile” Overhead

Bridge Sign

SVQS-7

I-84 Eastbound Waterbury I-84 Shoulder

behind guide-rails

before “Exit 18

Chase Pkway 1/2

Mile” Roadway

Sign Sign

SVMQ-6

I-84 Eastbound Waterbury I-84 Shoulder

behind guide-rails

south of Chase

Pkway Park and

Ride Lot

SVQS-8

I-84 Eastbound Waterbury I-84 On-Ramp SQT-4

PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

49

ADDENDUM NO. 6

Page 50: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #1131016

THROUGH #1131024

Gore Area near

462 Chase Pkway

I-84 Eastbound Waterbury I-84 Exit 20 Split

Gore Area

SVQS-9

Rte 8

from I-

84

Eastbound Waterbury Rte 8 South and

Sunny Side and

River Side Split

Gore Area

SVQS-10

Table 4 - I-84 Eastern Section

Route Direction Town Location Type of

Equipment

I-84 Westbound Waterbury I-84 Gore Area

after Exit 21

SVQS-11

Union

Street

to I-84

Westbound Waterbury Union Street On-

Ramp to I-84

(Before

“FATHER

MICHAEL J.

McGIVNEY

MONUMENT

EXIT 21”

roadway sign

SVQS-12

I-84 Westbound Waterbury I-84 West of 522

Hamilton Street

(near Park and

Ride Lot)

SVMQ-7

I-84 Westbound Waterbury I-84 Before Exit

23

SVMQ-7 (Phase

2)

I-84 Westbound Waterbury I-84 South of 262

Plank Rd

SVQS-13 (Phase

2)

I-84 Westbound Waterbury I-84 South of 2698

E. Main St

SVMQ-8 (Phase

2)

Trailer Relocation Operations:

1. The Contractor shall relocate the SWZ trailers as agreed between the Contractor and the

Engineer.

2. The Contractor shall reconfigure the SWZ equipment including the SVQS sensor and the

camera with PTZ shall to monitor travel lanes at the relocation site. The Contractor shall confirm

the reconfigured settings with the Engineer.

3. The Contractor shall update the website with the relocation sites of the SWZ. The Website

shall show the new location of the SWZs upon completion of the update. The update shall occur

within 2 weekdays of the relocation.

Method of Measurement:

PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

50

ADDENDUM NO. 6

Page 51: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #1131016

THROUGH #1131024

1. The SWZ Deployment will be measured as a Contract lump sum item.

2. The SVMQ, SVQS, and SQT items will be measured based on uninterrupted operation of

all trailer, sensors, cameras with pan-tilt-zoom, variable message signs, solar panels,

batteries. SVMQ, SVQS, and SQT will be measured for payment on a per unit basis for

each month that the piece of equipment is in use, and as follows:

a) Measurement will begin from the date each unit is fully operational, as determined

by the Engineer, to the date it is released back to the Contractor.

b) The Engineer will compute periods of less than 1 month at the rate of 1/30 of a

month for each day of use.

3. The SVMQ, SVQS, and SQT service items will be measured for payment by the month

or fraction of a month as follows:

a) Includes monthly operations, monthly cellular service communications,

maintenance, charging batteries, cleaning solar panels, camera dome bubble,

repair, programming, and integration.

b) The following pro-rated reduction of the monthly payment will be computed if the

monthly summary spreadsheet of outages greater than 24 hours indicates

interruption of service has occurred:

1 day = 5% pay reduction 6 days = 30% pay reduction

2 days = 7% pay reduction 7 days = 35% pay reduction

3 days = 10% pay reduction 8 days = 40% pay reduction

4 days = 20% pay reduction 9 days = 50% pay reduction

5 days = 25% pay reduction 10 days = 75% pay reduction

c) If the components of the SWZ are down for more than 10 total days in a month,

whether they are consecutive or cumulative, and then NO payment will be made

for that month.

4. The SWZ Operations item will be measure items will be measured for payment by the

month for web site operations.

5. The SWZ Trailer Relocation item will be measured for payment each time a SQT, SVQS,

or SVMQ is relocated from an existing location to another location, as approved or

directed by the Engineer.

Basis of Payment:

1. Payment for accepted SWZ installation will be at the Contract lump sum price for “Smart

Work Zone Deployment” which shall include submittals, component delivery, and

system set up, all materials, equipment, tools, travel and labor incidental thereto. The

Contractor shall comply with the requirements stated in the System Performance section

herein.

2. Payment for accepted trailer-mounted components will be at the Contract unit price per

month or a fraction of the month for each “Smart Work Zone Queue Trailer/Sensor

(SQT),” “Smart Work Zone Mobile Video Camera/Queue Sensor Trailer (SVQS)” and

“Smart Work Zone Variable Message Sign/Queue Sensor Trailer (SVMQ)” which price

shall include queue trailer and sensor, camera/queue sensors and trailers, variable

message signs, sensors and trailers, cloud hosted third party traffic speed data, processed

rock, temporary license plates, solar panels, batteries, removal, travel, and all materials,

equipment, tools and labor incidental thereto.

PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

51

ADDENDUM NO. 6

Page 52: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 01/30/18

ITEM #1131016

THROUGH #1131024

3. Payment for accepted SQT Service, SVMQ Service, and SVQS Service items shall

include all operational and service costs directly related to the furnishing and installing

individual trailers and trailer-mounted equipment including, but not limited to, cellular

communications, programming, service, maintenance, cleaning, repair, and all materials,

equipment, tools, and labor incidental thereto.

4. Payment for uninterrupted SWZ operations as specified will be at the Contract unit price

per month for “Smart Work Zone Operations” which price shall include all operations

and maintenance costs not directly related to the individual trailers and trailer mounted

equipment including, but not limited to, website operations, data collection and travel

delay cost calculations, programming, system integration, maintenance, repair, and all

materials, equipment, tools and labor Cost for hosting a web site incidental thereto.

5. Payment for approved relocation of SQT, SVQS and SVMQ units will be at the Contract

unit price for each “Smart Work Zone Trailer Relocation” which price shall include

processed rock, website revisions, and all materials, equipment, tools and labor incidental

thereto.

The pay unit is each that will be paid on a monthly basis for each of the Smart Work Zone

Variable Message Sign/Queue Sensor Trailer (SVMQ) and the Smart Work Zone Video

Camera/Queue Sensor Trailer (SVQS). The Engineer may remove or add SWZ items by unit at

the Engineer’s discretion. The contractor will be notified thirty (30) days in advance by the

Engineer. The payment shall be adjusted based on the actual number of SWZ units installed or

removed including corresponding operations items.

Pay Item Pay Unit

Smart Work Zone Video Camera/Queue Sensor Trailer (SVQS) ea.

Smart Work Zone Video Camera/Queue Sensor Trailer (SVQS)

Service mo.

Smart Work Zone Variable Message Sign/Queue Sensor

Trailer (SVMQ) ea.

Smart Work Zone Variable Message Sign/Queue Sensor

Trailer (SVMQ) Service mo.

Smart Work Zone Deployment l.s.

Smart Work Zone Operations mo.

Smart Work Zone Trailer Relocation ea.

Smart Work Zone Queue Trailer/Sensor (SQT) ea.

Smart Work Zone Queue Trailer/Sensor (SQT) Service mo.

PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

52

ADDENDUM NO. 6

Page 53: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev Date 01/31/18

ITEM #1201802A

ITEM #1201802A – 4 CHORD TRUSS BRIDGE SIGN STRUCTURE

Description:

Work under this item shall consist of providing field survey, furnishing, fabricating, surface

preparation, galvanizing, transporting and erecting a tubular truss sign support structure at the

location shown on the plans or as directed by the Engineer. The tubular truss sign support shall

include the posts, mast, sign panel support beams, sign stops, base plates, splice plates, filler

plates, gusset plates, blocking plates continuous bar, field splice assemblies, conduit couplers,

handhole assemblies, splice bolts, U-bolts, nuts, washers, all incidental work related to the

tubular truss sign support structure, anchor bolt modifications/replacement and work related to

the reconstruction of concrete parapets and concrete foundations. New anchor bolts at base

plates shall be included in this item. Work under this item shall also include the design of the

sign panel support members and the members’ connections to the truss chord and sign panels.

This item shall not include the anchor bolt assemblies called for to be reused that connect the

overhead sign support to the existing structure or sign panels. The new Overhead Sign Structure

brackets to the bottom of the base plate for Bridge No. 03190A are not included in this item, and

shall be paid for separately by Item #0603061A – Structural Steel (Site No. 1).

Materials: The materials for this work shall conform to the following:

Structural tubing shall conform to the requirements of ASTM A53, Grade B, Type E or S, A252

Grade 3, Type E or S, A106, Grade C Type S only, API 5L, Grade B, Type E or S, A500,

Grade C, or API 5LX, Grade X42, Type E or S (or greater), galvanized with minimum yield

strength of 46,000 psi.

Steel plates shall conform to the requirements of AASHTO M270, Grade 50, galvanized.

High strength bolts shall conform to ASTM A325, Type 1. Nuts shall conform to either ASTM

A563, Grade DH or ASTM A194, Grade 2H. Flat hardened washers shall conform to ASTM

F436. U-bolts shall conform to ASTM A449.

All nuts for high-strength bolted connections including nuts for anchor bolts shall be “prevailing

torque-reusable type” locking nuts.

Compressible washer type direct tension indicates (load indicating washers) shall conform to the

requirements of ASTM F959, Type 325, and shall be galvanized in conformance with ASTM

B695, Class 50.

All stainless steel nuts, bolts, cap screws, plates and washers shall be nickel-stainless steel

conforming to AISI 300 series.

Stainless steel plates shall conform to requirements of ASTM A240, Type 304.

PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

53

ADDENDUM NO. 6

Page 54: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev Date 01/31/18

ITEM #1201802A

Bonded bushings, couplings and square head plugs shall conform to the requirements of ASTM

A307.

Hot-dip galvanizing of the tubular members and steel plates shall conform to the requirements of

ASTM A123.

Mechanically galvanizing of the high strength bolts, U-bolts, nuts and washers shall conform to

the requirements of ASTM B695, Class 50.

Hot-dip galvanizing of the high strength bolts, U-bolts, nuts and washers shall conform to the

requirements of ASTM A153.

Zinc-rich field primer for touch-up shall conform to the requirements of Federal Specification

TT-P-641-Type I and ASTM A780. The use of aerosol spray cans shall not be permitted.

Neoprene gasket material for the access openings shall conform to ASTM D1056, Grade 2A2 or

2A3. Other grades of neoprene approved by the Engineer may be used.

Certified Test Reports and Materials Certificates will be required in accordance with Article

1.06.07 for the hot-dip galvanizing.

Add in note 1.A./B. from M.18.01 regarding ASA Flanges for truss chord splices: Flanges for

inner and outer truss chord splices shall be 150 pounds (68 kilograms) ASA Flanges, lap joint

type, and shall conform to the requirements of ASTM A181, Grade II.

Welding design and fabrication for steel tubular bridge sign support shall conform with the latest

edition of AWS Structural Welding Code D1.1-Steel and the applicable provisions.

Concrete for foundation shall be Class “A” concrete. Concrete for parapets shall be Class “F”

concrete. Work and materials shall conform to Section 6.01. The reinforcement used shall be

galvanized and conform to Section M.06.

Construction Methods:

Sign panel support members and connections shall be designed and furnished per the design

criteria and requirements of the Item “4 Chord Truss Cantilever Sign Structure.”

The Contractor shall submit shop drawings for approval, in accordance with Article 1.05.02.

These drawings shall include, but not be limited to the following:

1. The support location and elevation, the span length, and anchor bolt locations.

2. The lengths of each member (post heights and arm lengths) and complete details of the

tubular sign support, including dimensions of all components, camber and materials

designations.

PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

54

ADDENDUM NO. 6

Page 55: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev Date 01/31/18

ITEM #1201802A

3. Location of sign panels relative to the roadway travel paths.

4. Roadway minimum clearances from sign support structures and sign panels.

The Contractor shall be responsible for all measurements and the final fit of all members.

After the truss members have been completely fabricated, including cambering, but prior to

galvanizing, all connections and splices shall be trial fitted and bolted in the fabricator's shop.

The fabricated members may be rejected by the Engineer if the mating surfaces of the plates

have a gap which is greater than the filler plate tolerance shown on the plans. Bolts used for the

trial shop fit-up shall not be reused in the final field assembly.

The horizontal member on the sign support and/or cantilever sign support structure shall be

checked for proper residual camber prior to it being galvanized. Horizontal members with

splices shall be bolted together with temporary bolts for checking camber. With the horizontal

member supported at its ends, the residual camber shall be measured at mid-span and the

member shall be rejected if the camber does not fall within the following limits:

Minimum Residual Camber Span/1000

Maximum Residual Camber Span/500

Steel surface defects such as fins, slivers, tears, delaminations, burrs, sharp edges and other

defects shall be ground down with use of a power disc grinder or other tools approved by the

Engineer, to afford as close to a continuous surface characteristic as possible. Defects that in the

opinion of the inspection personnel, are so large or deep that grinding may not rectify the defect,

shall be referred to the Engineer for resolution.

After the posts and the horizontal members have been fabricated, welds ground smooth, flux and

splatter removed, they shall be hot-dip galvanized in accordance with ASTM A123, as

applicable.

Each lot of steel so treated shall bear a label clearly showing the name of the galvanizer, the

ASTM specification used for the galvanizing, and complete instructions for touch-up/repair of

damaged material. Fabrications and materials shall be packed with sufficient dunnage and

padding to protect finished surfaces.

Mating surfaces of the splice and connection plates, just prior to assembly, shall be wire brushed

to mark and score the zinc surface without appreciably removing any material.

Prior to assembly, the top and bottom surface of the base plate shall be planed, or else the plate

shall be hot straightened. The post shall be faced at the bottom end.

Assembly of bolted connections and splices shall conform to the applicable requirements of

Article 6.03.03-4 (f). Anchoring nuts shall be installed “snug tight” and then tightened

additionally in accordance with High Strength Bolted Connections Turn-of-Nut Installation

Method, modified as follow: Nut rotation from the snug tight condition shall be 1/4 turn.

PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

55

ADDENDUM NO. 6

Page 56: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev Date 01/31/18

ITEM #1201802A

The posts shall be securely bolted to their bases and shall be plumb or slightly back from the

roadway upon completion of erection and after application of dead load.

The Contractor shall prevent distortion of the sign support members or changes in span lengths

between anchorage plates during sign support erection operations.

All damaged areas of the galvanizing shall be properly prepared and touched up. Damaged zinc

shall be touched-up in accordance with ASTM A780. Spray aerosol cans of zinc-rich primer will

not be permitted.

All unused 1" diameter couplings shall be capped with a galvanized malleable iron cap.

Bridge parapets may contain electrical conduit (rigid metal or PVC) and wiring. The Contractor

shall assume the presence of electrical conduit and wiring within the parapets. New conduit

couplers, new conduit and conduit expansion devices shall be installed in parapets which are

reconstructed as part of the sign support foundation and are incidental to the truss bridge sign

structure. Replacement of electrical wire is not covered under this item.

Method of Measurement:

This work will be measured for payment by the actual number of bridge sign structures, installed

and accepted in place.

Basis of Payment:

This work will be paid for at the Contract unit price each for "4 Chord Truss Bridge Sign

Structure", complete in place, which price shall include the field survey, furnishing, fabricating,

surface preparation, galvanizing, transporting and erecting a tubular bridge sign support, and all

materials, equipment, labor, tools, and work incidental thereto. Design of sign panel support

members and the associated connections are included in this item. Foundation reconstruction,

parapet reconstruction, and replacement of conduit within the parapet to be reconstructed are

incidental to this item.

Pay Item Pay Unit

4 Chord Truss Bridge Sign Structure ea.

PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

56

ADDENDUM NO. 6

Page 57: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

Rev. Date 11/02/17

ITEM #1220027A

ITEM #1220027A – CONSTRUCTION SIGNS

12.20.01 – Description is revised as follows:

Under this item the Contractor shall furnish, install and remove construction signs with

retroreflective sheeting and their required portable supports or metal sign posts that meet the

requirements of NCHRP Report 350 (TL‑ 3) or MASH for Category 2 Devices. The

construction signs and their required portable supports or metal sign posts shall comply with the

signing requirements stated in the item “Maintenance and Protection of Traffic,” as shown on

the plans or as directed by the Engineer. The Contractor shall furnish a sufficient number of

signs to provide the signing patterns for all operations which are being undertaken concurrently.

Construction Signs is supplemented with the sign details that follow.

Pay Item Pay Unit

Construction Signs s.f.

PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

57

ADDENDUM NO. 6

Page 58: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

*

*

TE

MP

_008N

_151_28.6

0_S

TG

1-3

12"

See S

ign

See S

ign

See S

ign

See S

ign

0" /

2"

ST

AG

E 1

-3

Nic

ho

ls D

riv

e B

rid

ge.

Concrete

at

Prote

ct

Sig

n B

ehin

d

CO

NS

TR

UC

TIO

N S

IGN

S

IT

EM

: 1220027

64

.0 S

q.F

t.

LE

TT

ER

PO

SIT

ION

S (

X)

SIG

N D

ET

AIL

TY

PE

:

TY

PE

:

CO

LO

R:

CO

LO

R:

BA

CK

GR

OU

ND

LE

GE

ND

/BO

RD

ER

SIG

N N

UM

BE

R

TO

TA

L (

Sq

.fT

.)

SY

MB

OL

XY

WID

HT

LE

NG

TH

SE

RIE

S/S

IZE

RO

T

SIG

N P

AN

EL

CO

RN

ER

RA

DIU

S

CR

OW

N

1:6

0

BD

R I

NS

ET

/WID

TH

RE

V'D

/

PL

OT

TE

D :9

/6/2

01

7

Gro

und

En

gin

eer

: J.

Massin

/

Desig

ned

by

: J

. M

assin

i

Pro

ject

No

. 1

51

-32

6

Lo

cati

on

: W

ate

rbu

ry R

ou

te 8

N.B

. :

28

.60

Sig

n S

upport

No. N

/A

Mo

un

ted

:

Mate

rial

: D

ete

rmin

ed b

y t

he C

ontr

acto

r &

accepta

ble

to T

he E

ngin

eer.

Dim

en

sio

ns a

re i

n I

nch

es.

4'-

6"

2'-0"

7.5

"

9"E

7.5

"

11

.5"

31

"1

1.5

"

9.0

Sq.F

t.

73

.0 S

q.F

t.L

eg

en

d :

Wh

ite T

yp

e I

VB

ack

gro

un

d :

Gre

en

Ty

pe I

V

(0

" I

nset/

.75

" W

)L

egend/B

ord

er:

Bla

ck T

ype P

lain

Backgro

und:

Yell

ow

Type I

V

9.9

H

12

.7

a

12

.7

r

7.7

t

8.9

f

7.7

o

11

.9

r

7.8

d

7.9

8.8

77

.3

EM

2000

12/9

10

D

12

.2

a

12

.7

n

12

.7

b

11

.6

u

12

.7

r

7.6

y

10

.26.2

79

.8

EM

2000

12/9

29

.1

1

3.4

7.5

M 9

I

3.3

L

6.9

E

5.6

31

.23

5.7

E 2

000

11

.3,7

.5

6.2

"8

3.6

"6

.2"

8'-

0"

8.2

"

24

"

46

.9"

11

.3"E

5.6

"

37

.7"

12

"E

M

10

.2"

12

"E

M

9.1

"

7.5

"E

7.5

"

8'-0"

M1_1

6.2

63

.824

24

0

A

Rev. Date 11/2/17

ITEM #1220027APROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

58

ADDENDUM NO. 6

Page 59: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

8.4

"7

9.8

"7

.8"

8'-

0"

7.8

"

24

"

5.8

"

12

"E

M

7"

12

"E

M

11

.3"

7.5

"E

8.6

"8'-0"

PO

RT

ER

ST

. B

RID

GE

CO

NC

RE

TE

AT

INS

TA

LL

ING

BE

HIN

D

PR

OT

EC

T S

IGN

BY

ST

AG

E 1

CO

NS

TR

UC

TIO

N S

IGN

S

IT

EM

: 1

22

00

27

*

LE

TT

ER

PO

SIT

ION

S (

X)

SIG

N D

ET

AIL

TY

PE

:

TY

PE

:

CO

LO

R:

CO

LO

R:

BA

CK

GR

OU

ND

LE

GE

ND

/BO

RD

ER

SIG

N N

UM

BE

R

TO

TA

L (

Sq

.fT

.)

SY

MB

OL

XY

WID

HT

LE

NG

TH

SE

RIE

S/S

IZE

RO

T

SIG

N P

AN

EL

CO

RN

ER

RA

DIU

S

EX

IT C

RO

WN

1:6

0

BD

R I

NS

ET

/WID

TH

RE

V'D

/

PL

OT

TE

D :9

/6/2

01

7

Engin

eer

: J. M

assin

i /

Desig

ned b

y :

J. M

assin

i /

Checked b

y :

L. C

onro

y

Pro

ject

No

. 1

51

-32

6

Locati

on :

Hart

ford

R

oute

8 N

.B. M

ileage :

29.3

7

Sig

n S

upport

No. N

/A

Mounte

d :

Gro

und

Mate

rial

: S

ee S

pec.

Dim

en

sio

ns a

re i

n I

nch

es.

*

TE

MP

_0

08

N_

15

1_

29

.37

_S

TG

1

64

.0 S

q.F

t.

12"

Whit

e/W

hit

e

Ty

pe I

V

Green

Ty

pe I

V

N/A

64

.0 S

q.F

t.

0" /

2"

9.7

H

12

.7

a

12

.7

r

7.7

t

8.9

f

7.7

o

11

.9

r

7.8

d

7.9

97

7.3

EM

20

00

12/9

8.4

D

12

.2

a

12

.7

n

12

.7

b

11

.6

u

12

.7

r

7.6

y

10

.27.8

79

.8

EM

20

00

12/9

19

.4

K

7.4

E

7.1

E

7.1

P

6.1

7.5

L

6.9

E

7.1

F

6.2

T

5.6

15

.56

1.1

E 2

000

7.5

M1_1

36

.56

4.2

24

24

0

A

Rev. Date 11/2/17

ITEM #1220027APROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

59

ADDENDUM NO. 6

Page 60: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

panelStyle:80-9920 FOR 151-326.ssipanelName:namepanelQuantity:1panelStation:nonepanelMaterial:0legendMaterial:0panelMounting:1panelWidthLock:1panelHeightLock:1marginAlign:9panelRoundCorners:1constructPanelMode:0constructPanels:36|24

|18panelSizes:panelStandard:1levels:GSCOLORFILL|GSBWFILL|GSOUTLINEversion:2widthRounding:6heightRounding:6panelShape:0panelBorderRadius:12.

000chevronTipRadius:12.0

00chevronShoulderRadiu

s:12.000

80

-99

20

(D

WN

TW

N M

ET

RO

NT

H)

0.3

75

" /

0.6

25

"

1.5

"

Pla

in

Bla

ck/B

lack

Orange

2.4

"25.4

"2.4

"

2'-

6"

3.5

"

4"C

1.2

"0.5

"1.3

"

4"C

3.6

"

1'-6"

CO

NS

TR

UC

TIO

N S

IGN

S

IT

EM

: 1220027

LE

TT

ER

PO

SIT

ION

S (

X)

SIG

N D

ET

AIL

TY

PE

: S

ee S

pec.

TY

PE

:

CO

LO

R:

CO

LO

R:

BA

CK

GR

OU

ND

LE

GE

ND

/BO

RD

ER

SIG

N N

UM

BE

R

TO

TA

L (

Sq

.fT

.)

SY

MB

OL

XY

WID

HT

LE

NG

TH

SE

RIE

S/S

IZE

RO

T

SIG

N P

AN

EL

CO

RN

ER

RA

DIU

S

EX

IT C

RO

WN

BD

R I

NS

ET

/WID

TH

RE

V'D

/

PL

OT

TE

D :9

/6/2

01

7

Gro

un

dM

ounte

d :

Pro

ject

No

. 0

15

1-0

32

6

Engin

eer :

J. M

assin

i D

esig

ned B

y:

J. M

assin

i

Lo

cati

on

: W

ate

rb

ury

R

ou

te 8

N.B

. E

XIT

32

Deto

ur t

o E

xit

30

Sig

n S

up

po

rt

No

. N

/A

Mate

ria

l :

See S

pec.

Dim

ensio

n a

re i

n I

nches

3.8

Sq.F

t.

3.8

Sq.F

t.

3.3

D 3

O

2.8

W 3.6

N

2.8

T

2.5

O

2.8

W 3.6

N

2.3

3.5

23

.4

C 2

000

4

2.4

M

3.5

E

2.4

T

2.6

R

2.8

O

2.4

4

N

2.8

T

2.6

H

2.3

2.4

25

.4

C 2

00

0

4

A

Rev. Date 11/2/17

ITEM #1220027APROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

60

ADDENDUM NO. 6

Page 61: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

panelStyle:regula

tory.ssipanelStat

ion:nonepanelHeig

htLock:1panelRoun

dCorners:0

constructPanelMode

:0construct

Panels:36|24|18

panelSizes:MIN.:18x

18,STD.:24x24,SPC

L.:30x30levels:GSCO

LORFILL|GSBWFILL|G

SOUTLINEpanelBord

erRadius:12.000

chevronTipRadius:

12.000chevronSh

oulderRadius:12.000

4.3

"5

2.9

"1

4.8

"

6'-

0"

5.9

"

7"E

4.5

"

5"E

1.7

"1"

2.2

"

5"E

6.3

"

6"E

3.4

"

34

.8"

8"

5.2

"4'-0"

1:2

0

4.3

E

6.2

X

7.5

I

2.4

T

5.3

7

3

6.7

2

5.7

27

40

.7

E 2

000

7

4.3

D 5

O

4.9

W 6.2

N

4.9

T

4.5

O

4.9

W 6.2

N

4.1

27

.14

0.6

E 2

000

5

4.4

M 6

E

4.3

T

4.6

R

4.9

O

4.2

5

N

5.2

O

5.3

R

4.6

T

4.6

H

4.1

14

.85

2.8

E 2

000

5

4.4

D

6.2

E

5.2

T

5.3

O

6.4

U

6.4

R

4.9

33

.23

4.4

E 2

000

6

AR

_T

ype A

45

.65.2

81

2.6

30

0

80-9929 (

Ex 3

2 D

eto

ur E

xit

Rm

p)

24.0

0 S

q.F

t.

.5" /

1"

6"

SE

E S

PE

C

SE

E S

IGN

SE

E S

PE

C

SE

E S

IGN

LE

GE

ND

/BO

RD

ER

: B

LA

CK

PL

AIN

BA

CK

GR

OU

ND

: O

RA

NG

E R

ET

RO

RE

FL

EC

TIV

E

RE

TR

OR

EF

LE

CT

IVE

)

(18"X

18" B

LU

E/W

HIT

E

HO

SP

ITA

L

CO

NS

TR

UC

TIO

N S

IGN

S

IT

EM

: 1

22

00

27

LE

TT

ER

PO

SIT

ION

S (

X)

SIG

N D

ET

AIL

TY

PE

:

TY

PE

:

CO

LO

R:

CO

LO

R:

BA

CK

GR

OU

ND

LE

GE

ND

/BO

RD

ER

SIG

N N

UM

BE

R

TO

TA

L (

Sq

.fT

.)

SY

MB

OL

XY

WID

HT

LE

NG

TH

SE

RIE

S/S

IZE

RO

T

SIG

N P

AN

EL

CO

RN

ER

RA

DIU

S

EX

IT C

RO

WN

BD

R I

NS

ET

/WID

TH

RE

V'D

/

PL

OT

TE

D :9

/6/2

01

7

Gro

un

dM

ounte

d :

Pro

ject

No

. 0

15

1-0

32

6

Engin

eer :

J. M

assin

i D

esig

ned B

y:

J. M

assin

i

Locati

on :

Wate

rbury

R

oute

8 N

.B. E

XIT

30 R

AM

P

Sig

n S

upport

No. N

/A

Mate

ria

l :

See S

pec.

Dim

ensio

n a

re i

n I

nches

24.0

0 S

q.F

t.

A

Rev. Date 11/2/17

ITEM #1220027APROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

61

ADDENDUM NO. 6

Page 62: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

ST

AG

E 1

panelStyle:guide_fwy_minor.ssipanelName:namepanelQuantity:1panelStation:nonepanelMaterial:0legendMaterial:0panelMounting:0panelWidthLock:1panelHeightLock:1marginAlign:9panelRoundCorners:1constructPanelMode:0constructPanels:36|24|18panelSizes:panelStandard:2levels:GSCOLORFILL|GSBWFILL|GSOUTLINEversion:2widthRounding:6heightRounding:6panelShape:0panelBorderRadius:12.000chevronTipRadius:12.000chevronShoulderRadius:12.000

45

.5 S

q.F

t.

10"

Wh

ite/W

hit

e

IVGreen

IV

0" /

1.2

5"

25

.3

E

7.1

X

8.6

I

2.8

T 6

8

3

7.8

1

2.5

9.9

42

.8

E 2

00

0

8

39

.3

E 61.1

A

6.8

S

5.5

T

4.5

14

.82

3.9

E 2

00

0

8,6

13

.3

H

8.5

a

8.5

r

5.1

t

5.9

f

5.1

o

7.9

r

5.2

d

5.3

13

.25

1.5

EM

20

00

8/6

12

.3

N

6.4

E

5.3

X

5.9

T

4.5

6

R

6.1

I

2.5

G

6.2

H

5.9

T

4.5

12

.45

3.3

E 2

00

0

6

M1

_1

13

.23

4.6

18

18

0

TE

MP

_E

XIT

_3

1_

NE

XT

_R

IGH

T_

ST

G1

12

.3"

55

.8"

9.9

"

6'-

6"

31

.3"

18

.1"

34

.6"

8.6

"

8"E

6.2

"

0.8

"

7.7

"

8"E

16"

8"E

M

8"

6"E

6.7

"

33

.3"

6"E

44

.7"

7'-0"

CO

NS

TR

UC

TIO

N S

IGN

S

IT

EM

: 1220027

LE

TT

ER

PO

SIT

ION

S (

X)

SIG

N D

ET

AIL

TY

PE

:

TY

PE

:

CO

LO

R:

CO

LO

R:

BA

CK

GR

OU

ND

LE

GE

ND

/BO

RD

ER

SIG

N N

UM

BE

R

TO

TA

L (

Sq

.fT

.)

SY

MB

OL

XY

WID

HT

LE

NG

TH

SE

RIE

S/S

IZE

RO

T

SIG

N P

AN

EL

CO

RN

ER

RA

DIU

S

EX

IT C

RO

WN

1:4

0

BD

R I

NS

ET

/WID

TH

RE

V'D

/

PL

OT

TE

D :9

/6/2

01

7

En

gin

eer

: J.

Massin

i /

Desig

ned

by

: J

. M

assin

i

Pro

ject

No. 151-3

26

Locati

on :

Wate

rbury

Route

8 N

.B. S

tage 1

sta

tion 2

80+

00

Sig

n S

upport

No. N

/A

Mounte

d :

Gro

und

Mate

rial

: S

ee S

pec.

Dim

en

sio

ns a

re i

n I

nch

es.

A

Rev. Date 11/2/17

ITEM #1220027APROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

62

ADDENDUM NO. 6

Page 63: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

4.8

"9

8.7

"4

.5"

9'-

0"

26

.3"

8"C 4"

1.5

" 3.8

"

8"C

11

.4"

9"D 6"

6.0

5"

9"D

38

.9"

18

"

6.0

5"

6'-6"

LE

TT

ER

PO

SIT

ION

S (

X)

SIG

N D

ET

AIL

TY

PE

:

TY

PE

:

CO

LO

R:

CO

LO

R:

BA

CK

GR

OU

ND

LE

GE

ND

/BO

RD

ER

SIG

N N

UM

BE

R

TO

TA

L (

Sq

.fT

.)

SY

MB

OL

XY

WID

HT

LE

NG

TH

SE

RIE

S/S

IZE

RO

T

SIG

N P

AN

EL

CO

RN

ER

RA

DIU

S

EX

IT C

RO

WN

1:6

0

BD

R I

NS

ET

/WID

TH

RE

V'D

/

PL

OT

TE

D :9

/6/2

01

7

Gro

und

En

gin

eer

: J.

Massin

/

Desig

ned

by

: J

. M

assin

i /

Ch

eck

ed

by

: L

. C

on

roy

Pro

ject

No

. 1

51

-32

6

Locati

on :

Wate

rbury

Route

8 N

.B. 1

500 F

T &

1/2

Mil

e B

efo

re E

xit

32

Sig

n S

upport

No. N

/A

Mo

un

ted

:

Mate

rial

: S

ee S

pec.

Dim

en

sio

ns a

re i

n I

nch

es.

TE

MP

_E

XIT

_3

2_

CL

OS

ED

_S

TG

1-3

58

.5 S

q.F

t.

10"

Bla

ck

Pla

in

Orange

Refle

cti

ve

N/A

58

.5 S

q.F

t.

0" /

1.5

"

5.5

E

6.5

X

7.6

I

2.8

T

5.6

9

3

7.9

2

6.1

9

C

8.1

L

6.7

O

7.7

S

7.7

E

7.1

D

6.1

4.5

98

D 2

00

0

9

20

.6

D

5.9

O

5.7

W 7.2

N

5.6

T 5

O

5.7

W 7.2

N

4.5

40

.64

6.8

C 2

00

0

8

12

.7

M 7

E

4.8

T

5.2

R

5.7

O

4.7

8

N

6.1

O

6.3

R

5.2

T

5.2

H

4.5

32

.66

2.7

C 2

00

0

8

4.8

U

7.7

S

7.6

E

5.6

9

E

6.5

X

7.6

I

2.8

T

5.6

9

3

7.9

0

6.4

27

.57

5.7

D 2

00

0

9

84

.36

18

18

0H

osp

ital

ST

AG

ES

1-3

*CO

NS

TR

UC

TIO

N S

IGN

S

IT

EM

: 1220027

GU

IDE

RA

IL

DE

FL

EC

TIO

N O

F

INS

TA

LL

ING

BE

HIN

D

PR

OT

EC

T S

IGN

S B

Y

*

Bla

ck

- P

lain

Legend\B

ord

er

:B

ack

gro

un

d :

Ora

ng

e

Legend :

Whit

e T

ype I

VB

ack

gro

un

d :

BL

UE

Ty

pe I

V

A

Rev. Date 11/2/17

ITEM #1220027A

30

1/30/18

PROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

63

ADDENDUM NO. 6

Page 64: FEBRUARY 6, 2018 REHABILITATION OF BRIDGE NOS. …february 6, 2018 rehabilitation of bridge nos. 03190a, 03190b, 03190c, 03190d, 03190e, 03190f, 03191a, 03191b, 03191d, and 03191e

9.0

Sq.F

t.

1.5

"

Bla

ck

/Bla

ck

Refle

cti

ve

0.4

7" /

0.6

3"

3.6

D

5.3

E

4.3

T

4.4

O

5.4

U

5.4

R

4.1

3.6

28.8

EM

2000

5

80-9

933(D

ET

OU

R 8

4 F

OR

151-3

26)

LE

TT

ER

PO

SIT

ION

S (

X)

SIG

N D

ET

AIL

TY

PE

:

TY

PE

:

CO

LO

R:

CO

LO

R:

BA

CK

GR

OU

ND

LE

GE

ND

/BO

RD

ER

SIG

N N

UM

BE

R

TO

TA

L (

Sq

.fT

.)

SY

MB

OL

XY

WID

HT

LE

NG

TH

SE

RIE

S/S

IZE

RO

T

SIG

N P

AN

EL

CO

RN

ER

RA

DIU

S

EX

IT C

RO

WN

1:2

0

BD

R I

NS

ET

/WID

TH

RE

V'D

/

PL

OT

TE

D :9

/6/2

01

7

Gro

und -

Constr

ucti

on S

ign

En

gin

eer

: J.

Massin

i /

Desig

ned

by

: J

. M

assin

i

/ C

heck

ed

by

:

Pro

ject

No. 151-3

26

Lo

cati

on

: W

ate

rbu

ry -

fo

r T

em

po

rar

U-T

urn

Sig

n S

upport

No. N

/A

Mo

un

ted

:

Mate

rial

: dete

rmin

ed b

y C

ontr

acto

r &

accepta

ble

to t

he E

ngin

eer

Dim

en

sio

ns a

re i

n I

nch

es.

TE

MP

OR

AR

Y U

-TU

RN

4.1

"2

8.8

"3

.1"

3'-

0"

4.2

"

18"

4.6

"

5"E

M

4.2

"

3'-0"

M1_1

91

3.8

18

18

0

Pla

in

Oran

ge

INT

ER

ST

AT

E S

HIE

LD

WH

ITE

BD

R/T

EX

TR

ED

/BL

UE

BA

CK

GR

OU

ND

CO

NS

TR

UC

TIO

N S

IGN

S

IT

EM

: 1

22

00

27

A

Rev. Date 11/2/17

ITEM #1220027APROJECT NOS. 0151-0312, 0151-0313, & 0151-0326

64

ADDENDUM NO. 6