Fermilab User Facility US-CMS User Facility and Regional Center at Fermilab Matthias Kasemann FNAL

Fermilab User Facility US-CMS User Facility and Regional Center at Fermilab Matthias Kasemann FNAL

Embed Size (px)

Citation preview

Page 1: Fermilab User Facility US-CMS User Facility and Regional Center at Fermilab Matthias Kasemann FNAL

Fermilab

User Facility

US-CMS User Facilityand Regional Center

at Fermilab

Matthias Kasemann

FNAL

Page 2: Fermilab User Facility US-CMS User Facility and Regional Center at Fermilab Matthias Kasemann FNAL

April 13, 1999 US-CMS User facility Matthias

Kasemann, FNAL2

Fermilab

User Facility

Outline

User Facility Goals + Schedule + Organization

US-CMS Regional Center at Fermilab Hardware and Networking Data required Support Functions

Size of Regional Center Cost and Personnel Profile Summary

Page 3: Fermilab User Facility US-CMS User Facility and Regional Center at Fermilab Matthias Kasemann FNAL

April 13, 1999 US-CMS User facility Matthias

Kasemann, FNAL3

Fermilab

User Facility

User Facility: Goals

Scope and Size: support US-CMS collaboration (20% of full CMS).

Provide enabling infrastructure of software and computing to allow US physicists to fully participate in physics program of CMS.

Support the development and data analysis activities of US-CMS: acquire, develop, install, integrate, commission and operate

hardware and software.

This will include a major ‘Tier1’ regional computing center at Fermilab to support US physicists working on CMS.

Page 4: Fermilab User Facility US-CMS User Facility and Regional Center at Fermilab Matthias Kasemann FNAL

April 13, 1999 US-CMS User facility Matthias

Kasemann, FNAL4

Fermilab

User Facility

US_CMS RC1 at FNALSchedule + Organization

1999 - 2003: R&D Phase 2003 - 2005: Implementation Phase 2006 onwards: Operations Phase

All Phases of the US-CMS RC1 will be managed and operated within the FNAL Computing Division.

FNAL-CD is collecting very qualified experience from Tevatron RunII preparations and operations.This will put us in a unique position to support collaborations of

4-500 CMS scientists doing pp physics.

Page 5: Fermilab User Facility US-CMS User Facility and Regional Center at Fermilab Matthias Kasemann FNAL

April 13, 1999 US-CMS User facility Matthias

Kasemann, FNAL5

Fermilab

User Facility

Run II Parameters for DØ: Trigger rate 50 Hz (LHC / 2) Raw data event size 250 kB (LHC / 4) Data collection 6 x 108 evts/ yr. (LHC / 1.6) Summary event size 150 kB (LHC x 1.5) Physics sum’ry evt size 10 kB (LHC) Total dataset size 300 TB/yr. (LHC / 3)

Bottom line: Computing project ~ O (Run I x 20)

~ O (LHC / 2-3)

This will be accomplished with resources available in 2000.

Fermilab Run II Computing and Software

Page 6: Fermilab User Facility US-CMS User Facility and Regional Center at Fermilab Matthias Kasemann FNAL

April 13, 1999 US-CMS User facility Matthias

Kasemann, FNAL6

Fermilab

User Facility

US-CMS Regional Center at FNAL

Hardware and Networking

Implement the main US-CMS regional center at Fermilab include substantial CPU for analysis, reprocessing and simulation data storage data access facilities.

Networks and networking will play a key role in this distributed computing model: Deliver data to other US-CMS institutions through high-speed

networks. High bandwidth network connection to CERN.

Technology and policy in this area is in a state of flux. We have to track technology and participate in prototyping work.

Page 7: Fermilab User Facility US-CMS User Facility and Regional Center at Fermilab Matthias Kasemann FNAL

April 13, 1999 US-CMS User facility Matthias

Kasemann, FNAL7

Fermilab

User Facility

Data required at US-CMS RC1

Event data available at regional center: event samples for testing and code development,

a collection of very interesting events

the full set of the Analysis Object data (AOD)

about 10% of the raw and reconstructed data (ESD)

all available event meta data

Non-event data: detector databases for calibration, monitoring, geometry,

cabling

data related databases: production log, run conditions, trigger setups

Page 8: Fermilab User Facility US-CMS User Facility and Regional Center at Fermilab Matthias Kasemann FNAL

April 13, 1999 US-CMS User facility Matthias

Kasemann, FNAL8

Fermilab

User Facility

Include user support personnel training, documentation, code distribution, ...

Personnel to manage licenses and license acquisition. Contract for needed services. Responsibility and personnel to develop or acquire any

software that is required to carry out its production and operation activities.

Provide support for many development activities during the detector construction period before data taking begins.

Provide ongoing support during operations phase of the experiment.

US-CMS Regional Center at FNAL

Support Functions

Page 9: Fermilab User Facility US-CMS User Facility and Regional Center at Fermilab Matthias Kasemann FNAL

April 13, 1999 US-CMS User facility Matthias

Kasemann, FNAL9

Fermilab

User Facility

R&D Phase activities

Participate in R&D to prove the concept of LHC regional centers: MONARC testbed Object database testbeds Prototype regional center by 2002 Networking testbeds

In R&D phase and beyond: Provide CMS user support:

documentation code management and distribution training user help desk

Page 10: Fermilab User Facility US-CMS User Facility and Regional Center at Fermilab Matthias Kasemann FNAL

April 13, 1999 US-CMS User facility Matthias

Kasemann, FNAL10

Fermilab

User Facility

Size of the Tier 1 Regional Center

The base for these estimates is a set of figures for CMS offline computing at CERN that was made available by CMS in mid-1998.

CPU (1 TIPS = 106 MIPS 25k SpecInt95) in 2005: 3.6 TIPS 2006 on: 1.2 TIPS new + 1.2 TIPS replacement

Disk storage in 2005:108 TB 2006 on: 40 TB new + 27 TB replacement

Serial storage in 2005:1 robot + 0.4 PB 2006 on: 0.2 PB new + robot every 3 years

Page 11: Fermilab User Facility US-CMS User Facility and Regional Center at Fermilab Matthias Kasemann FNAL

April 13, 1999 US-CMS User facility Matthias

Kasemann, FNAL11

Fermilab

User Facility

Hardware cost estimation

Costs de-escalated according to technology-cost development expectations.

Actual costs for CPU and disk are based on our Run II experience: CPU: $3.5M/TIPS in 2003 (extrapolated from 1999) disk: $26.90/GB in 2003 (extrapolated from 1999)

The cost reflect the use of expensive SMP machines for analysis in Run II.

Cost for serial storage also based on Run II $1.1M per robot plus $0.5M/PB for media

Page 12: Fermilab User Facility US-CMS User Facility and Regional Center at Fermilab Matthias Kasemann FNAL

April 13, 1999 US-CMS User facility Matthias

Kasemann, FNAL12

Fermilab

User Facility

Regional Center ScheduleImplementation and

Operation phase

To distribute cost over 2003, 2004 and 2005 and profit from price/performance evolution we plan to acquire 10% of disk and CPU in 2003, 30% in 2004, 60% in 2005.

Integrated capacity installed per year: 2003 2004 2005 2006 CMS

operation CPU: 0.4 1.44 3.6 4.8 TIPS disk: 11 43 108 148 GB tape: 0.03 0.05 0.4 0.6 PB robots: 1 0.33 robots

Page 13: Fermilab User Facility US-CMS User Facility and Regional Center at Fermilab Matthias Kasemann FNAL

April 13, 1999 US-CMS User facility Matthias

Kasemann, FNAL13

Fermilab

User Facility

Cost and Personnel Profile

U S-CMS T ier 1 Regional Center @ FNALHardw are Costs

1999 2000 2001 2002 2003 2004 2005 total to 2005 2006 onwarddisk 0.05 0.03 0.02 0.01 0.27 0.57 0.75 1.70 0.41tape 0.00 0.00 0.00 0.00 1.12 0.01 0.18 1.31 0.47cpu 0.00 0.00 0.00 0.00 1.41 2.74 3.50 7.66 1.85Annual $M 0.05 0.03 0.02 0.01 2.80 3.32 4.44 2.73Cumulative 0.05 0.08 0.10 0.11 2.91 6.23 10.66 10.66Netw ork ing and L ic ens ing Costs

network 0.01 0.01 0.00 0.00 0.56 0.66 0.89 2.13 1.09s/w licenses 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.70 0.1Total 13.50 3.92

Personnel Costs

FTE's 3.00 7.00 10.00 15.00 25.00 35.00 35.00 35Annual $M 0.10 0.3 0.7 1 1.5 2.5 3.5 3.5 3.5Cumulative 0.30 1.00 2.00 3.50 6.00 9.50 13.00

Tota l Cost

$M 26.50 7.42

Page 14: Fermilab User Facility US-CMS User Facility and Regional Center at Fermilab Matthias Kasemann FNAL

April 13, 1999 US-CMS User facility Matthias

Kasemann, FNAL14

Fermilab

User Facility

Cost Summary

Total costs through 2005: hardware: $10.6 M networking in US: $2.1 M licenses: $0.1 M / year

Operating phase 2006 onward: $3.9 M hardware + 35 people

Note: This hardware costs are based on what it is costing to serve

400-500 people in CDF and DØ under the assumption of exponential price/performance evolutions ($9.1M for CDF or D0).

Numbers are conservative (SMP-CPU,…)

Page 15: Fermilab User Facility US-CMS User Facility and Regional Center at Fermilab Matthias Kasemann FNAL

April 13, 1999 US-CMS User facility Matthias

Kasemann, FNAL15

Fermilab

User Facility

US-CMS User FacilitySummary

The User Facility has to provide US-CMS scientists with a competitive infrastructure to fully participate in the science program of CMS.

FNAL with the experience of Tevatron experiments is well suited to host the US-CMS major ‘Tier 1’ Regional Center.

Setup and support of the Regional Center will happen during 2003 - 2005. Initial hardware cost estimations (w.o. networking) are $10.6M + 35 FTE’s (by 2005).

Operations cost estimates are $2.7M/year for hardware (w.o. networking) and about 35 people.

Networking cost will be substantial.