Fermilab
User Facility
US-CMS User Facilityand Regional Center
at Fermilab
Matthias Kasemann
FNAL
April 13, 1999 US-CMS User facility Matthias
Kasemann, FNAL2
Fermilab
User Facility
Outline
User Facility Goals + Schedule + Organization
US-CMS Regional Center at Fermilab Hardware and Networking Data required Support Functions
Size of Regional Center Cost and Personnel Profile Summary
April 13, 1999 US-CMS User facility Matthias
Kasemann, FNAL3
Fermilab
User Facility
User Facility: Goals
Scope and Size: support US-CMS collaboration (20% of full CMS).
Provide enabling infrastructure of software and computing to allow US physicists to fully participate in physics program of CMS.
Support the development and data analysis activities of US-CMS: acquire, develop, install, integrate, commission and operate
hardware and software.
This will include a major ‘Tier1’ regional computing center at Fermilab to support US physicists working on CMS.
April 13, 1999 US-CMS User facility Matthias
Kasemann, FNAL4
Fermilab
User Facility
US_CMS RC1 at FNALSchedule + Organization
1999 - 2003: R&D Phase 2003 - 2005: Implementation Phase 2006 onwards: Operations Phase
All Phases of the US-CMS RC1 will be managed and operated within the FNAL Computing Division.
FNAL-CD is collecting very qualified experience from Tevatron RunII preparations and operations.This will put us in a unique position to support collaborations of
4-500 CMS scientists doing pp physics.
April 13, 1999 US-CMS User facility Matthias
Kasemann, FNAL5
Fermilab
User Facility
Run II Parameters for DØ: Trigger rate 50 Hz (LHC / 2) Raw data event size 250 kB (LHC / 4) Data collection 6 x 108 evts/ yr. (LHC / 1.6) Summary event size 150 kB (LHC x 1.5) Physics sum’ry evt size 10 kB (LHC) Total dataset size 300 TB/yr. (LHC / 3)
Bottom line: Computing project ~ O (Run I x 20)
~ O (LHC / 2-3)
This will be accomplished with resources available in 2000.
Fermilab Run II Computing and Software
April 13, 1999 US-CMS User facility Matthias
Kasemann, FNAL6
Fermilab
User Facility
US-CMS Regional Center at FNAL
Hardware and Networking
Implement the main US-CMS regional center at Fermilab include substantial CPU for analysis, reprocessing and simulation data storage data access facilities.
Networks and networking will play a key role in this distributed computing model: Deliver data to other US-CMS institutions through high-speed
networks. High bandwidth network connection to CERN.
Technology and policy in this area is in a state of flux. We have to track technology and participate in prototyping work.
April 13, 1999 US-CMS User facility Matthias
Kasemann, FNAL7
Fermilab
User Facility
Data required at US-CMS RC1
Event data available at regional center: event samples for testing and code development,
a collection of very interesting events
the full set of the Analysis Object data (AOD)
about 10% of the raw and reconstructed data (ESD)
all available event meta data
Non-event data: detector databases for calibration, monitoring, geometry,
cabling
data related databases: production log, run conditions, trigger setups
April 13, 1999 US-CMS User facility Matthias
Kasemann, FNAL8
Fermilab
User Facility
Include user support personnel training, documentation, code distribution, ...
Personnel to manage licenses and license acquisition. Contract for needed services. Responsibility and personnel to develop or acquire any
software that is required to carry out its production and operation activities.
Provide support for many development activities during the detector construction period before data taking begins.
Provide ongoing support during operations phase of the experiment.
US-CMS Regional Center at FNAL
Support Functions
April 13, 1999 US-CMS User facility Matthias
Kasemann, FNAL9
Fermilab
User Facility
R&D Phase activities
Participate in R&D to prove the concept of LHC regional centers: MONARC testbed Object database testbeds Prototype regional center by 2002 Networking testbeds
In R&D phase and beyond: Provide CMS user support:
documentation code management and distribution training user help desk
April 13, 1999 US-CMS User facility Matthias
Kasemann, FNAL10
Fermilab
User Facility
Size of the Tier 1 Regional Center
The base for these estimates is a set of figures for CMS offline computing at CERN that was made available by CMS in mid-1998.
CPU (1 TIPS = 106 MIPS 25k SpecInt95) in 2005: 3.6 TIPS 2006 on: 1.2 TIPS new + 1.2 TIPS replacement
Disk storage in 2005:108 TB 2006 on: 40 TB new + 27 TB replacement
Serial storage in 2005:1 robot + 0.4 PB 2006 on: 0.2 PB new + robot every 3 years
April 13, 1999 US-CMS User facility Matthias
Kasemann, FNAL11
Fermilab
User Facility
Hardware cost estimation
Costs de-escalated according to technology-cost development expectations.
Actual costs for CPU and disk are based on our Run II experience: CPU: $3.5M/TIPS in 2003 (extrapolated from 1999) disk: $26.90/GB in 2003 (extrapolated from 1999)
The cost reflect the use of expensive SMP machines for analysis in Run II.
Cost for serial storage also based on Run II $1.1M per robot plus $0.5M/PB for media
April 13, 1999 US-CMS User facility Matthias
Kasemann, FNAL12
Fermilab
User Facility
Regional Center ScheduleImplementation and
Operation phase
To distribute cost over 2003, 2004 and 2005 and profit from price/performance evolution we plan to acquire 10% of disk and CPU in 2003, 30% in 2004, 60% in 2005.
Integrated capacity installed per year: 2003 2004 2005 2006 CMS
operation CPU: 0.4 1.44 3.6 4.8 TIPS disk: 11 43 108 148 GB tape: 0.03 0.05 0.4 0.6 PB robots: 1 0.33 robots
April 13, 1999 US-CMS User facility Matthias
Kasemann, FNAL13
Fermilab
User Facility
Cost and Personnel Profile
U S-CMS T ier 1 Regional Center @ FNALHardw are Costs
1999 2000 2001 2002 2003 2004 2005 total to 2005 2006 onwarddisk 0.05 0.03 0.02 0.01 0.27 0.57 0.75 1.70 0.41tape 0.00 0.00 0.00 0.00 1.12 0.01 0.18 1.31 0.47cpu 0.00 0.00 0.00 0.00 1.41 2.74 3.50 7.66 1.85Annual $M 0.05 0.03 0.02 0.01 2.80 3.32 4.44 2.73Cumulative 0.05 0.08 0.10 0.11 2.91 6.23 10.66 10.66Netw ork ing and L ic ens ing Costs
network 0.01 0.01 0.00 0.00 0.56 0.66 0.89 2.13 1.09s/w licenses 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.70 0.1Total 13.50 3.92
Personnel Costs
FTE's 3.00 7.00 10.00 15.00 25.00 35.00 35.00 35Annual $M 0.10 0.3 0.7 1 1.5 2.5 3.5 3.5 3.5Cumulative 0.30 1.00 2.00 3.50 6.00 9.50 13.00
Tota l Cost
$M 26.50 7.42
April 13, 1999 US-CMS User facility Matthias
Kasemann, FNAL14
Fermilab
User Facility
Cost Summary
Total costs through 2005: hardware: $10.6 M networking in US: $2.1 M licenses: $0.1 M / year
Operating phase 2006 onward: $3.9 M hardware + 35 people
Note: This hardware costs are based on what it is costing to serve
400-500 people in CDF and DØ under the assumption of exponential price/performance evolutions ($9.1M for CDF or D0).
Numbers are conservative (SMP-CPU,…)
April 13, 1999 US-CMS User facility Matthias
Kasemann, FNAL15
Fermilab
User Facility
US-CMS User FacilitySummary
The User Facility has to provide US-CMS scientists with a competitive infrastructure to fully participate in the science program of CMS.
FNAL with the experience of Tevatron experiments is well suited to host the US-CMS major ‘Tier 1’ Regional Center.
Setup and support of the Regional Center will happen during 2003 - 2005. Initial hardware cost estimations (w.o. networking) are $10.6M + 35 FTE’s (by 2005).
Operations cost estimates are $2.7M/year for hardware (w.o. networking) and about 35 people.
Networking cost will be substantial.